Professional Documents
Culture Documents
observations:
- You could have computed EOQ and Reorder-Point and used it. Some of the teams did that,
but others did not. A few teams thought it was not possible to use the EOQ formula as the
problem did not explicitly specify an inventory holding cost, but you could have substituted
another figure for holding costs (which was given). For safety-stock, you would have to
compute demand variability from historical demand pattern.
- Many of the teams were not able to figure out the impact of lot-size on queue and throughput.
Smaller lot sizes do reduce WIP, but due to increased number of setups, there could be an
adverse effect on effective capacity of the resource.
The bottom line is: the theory learned in class can be (and should be) applied in practice, but
unlike text-book problems and exam questions, the relevant data may not be presented to you
on a platter.
Introduction
About Littlefield
Littlefield simulation was about running a real-time factory, making decisions on shop floor and
understanding and living with the consequences of the decisions made.
Process
The factory was working on Make to Order Model. The entire process takes place in batches.
When the order from the customer was received, raw material was moved from Inventory to
station one. Station one assembled the raw material into final product. The final product was then
moved to station two. Station two conducted tests on the final product and sent it out for delivery
if the product was properly calibrated or else the final product was directed to station three.
Station three tunes the product and directs it to station two, where the process is repeated and the
product is dispatched if calibrated correctly. There were queues in front of each station where the
WIP was kept if the machine was loaded.
Decision Variable
The decision variables were as follows:-
Objective
The objective was to maximize the profitability of the company by changing decision variables.
average revenue above $750, the company will be better off. Hence A1 started accepting contract
two from day 120, i.e. a commitment to deliver within one day.
Mistake 1: Reduction of Batch Size
A1 was not able to realize the full revenue under contract two. In order the get full revenue, A1
reduced the batch size to six (i.e. lot order of 10) [DAY 120].
The premise for the action was that the machine utilization will improve as number of batches
will increase and the batch size will reduce. Even if the order was not entirely executed, partial
order will be delivered on time; overall lead time should decrease. As a result full revenue on
partial order will be realized. Unfortunately, the effect observed after the lag time was different.
By reducing the batch size, the queue at station one started building up. Within 10 days of the
change the queue touched 5000 batches. Although the batch size was increased to 30 [Day 125]
and later 60 [Day 128] the queue was not disappearing. Due to this, the lead time increased
exponentially. Lead time reached all-time high of 12 days as an effect of mistake one.
Hence the machine was not bought. Since the reorder cost was $1000, the order quantity was
increased to 250*60 = 150,000 kits, which was to be reduced to 65*60 = 3900 kits.
Unfortunately this exit strategy was not executed on day 386.
There is a lag between the decision taken and the effect to be followed
Working capital has a huge importance in an institution; lack of working capital can lead
to bankruptcy
One should always remain calm and patient while making decision
Second and third mistake could have been avoided by being calm and patient
Note: The
anomalies
observed
after day 120 in all the graphs are the result of the first mistake, which were further reinforced by
the subsequent mistakes.