ID

Task Name
1

Duration

Investigation Topic

Start

25 days

Mon 02/02/15

Get a topic

1 day

Tue 03/02/15

Discuss with supervisor

1 day

Tue 03/02/15

Research

10 days

Wed 04/02/15

Proposal Draft

5 days

Tue 17/02/15

Submit Proposal Draft

1 day

Mon 23/02/15

Edit Proposal

2 days

Mon 23/02/15

Submit Final Proposal

1 day

Mon 02/02/15

Feedback from Supervisor

5 days

Mon 02/03/15

10 days

Wed 25/02/15

10
11

Literature Study

Laser Additive Manufacturing5 days

Project: Project1
Date: Fri 27/02/15

1st Quarter
Jan
Feb

Mar

2nd Quarter
Apr
May

Wed 25/02/15

Task

Manual Summary

Split

Start-only

Milestone

Finish-only

Summary

External Tasks

Project Summary

External Milestone

Inactive Task

Deadline

Inactive Milestone

Path Predecessor Milestone Task

Inactive Summary

Path Predecessor Summary Task

Manual Task

Path Predecessor Normal Task

Duration-only

Progress

Manual Summary Rollup

Manual Progress

Page 1

Jun

3rd Quarter
Jul
Aug

Sep

4th Quarter
Oct
Nov

Dec

ID

Task Name

Duration

Start

12

Titanium

2 days

Wed 04/03/15

13

Titanium Alloys

1 day

Fri 06/03/15

14

Titanium Diboride

1 day

Sat 07/02/15

15

Water Jet cutting

1 day

Sun 08/03/15

Experimental Design

9 days

Tue 10/03/15

17

Develop sample preparation2 days

Tue 10/03/15

18

Develop Testing Procedures 5 days

Thu 12/03/15

19

Develop Experimental
2 days
Matrix
Submit Preliminary Report 1 day
Draft
Edit Preliminary Report
1 day

Thu 19/03/15

Submit final preliminary


report

Mon 23/03/15

16

20
21
22

Project: Project1
Date: Fri 27/02/15

1 day

1st Quarter
Jan
Feb

Mar

2nd Quarter
Apr
May

Fri 20/03/15
Sat 21/03/15

Task

Manual Summary

Split

Start-only

Milestone

Finish-only

Summary

External Tasks

Project Summary

External Milestone

Inactive Task

Deadline

Inactive Milestone

Path Predecessor Milestone Task

Inactive Summary

Path Predecessor Summary Task

Manual Task

Path Predecessor Normal Task

Duration-only

Progress

Manual Summary Rollup

Manual Progress

Page 2

Jun

3rd Quarter
Jul
Aug

Sep

4th Quarter
Oct
Nov

Dec

ID

Task Name
23

Duration

Experimental Procedure

Start

47 days

Tue 24/03/15

24

Prepare Sample

4 days

Tue 24/03/15

25

Analyse Powder - SEM

5 days

Mon 30/03/15

26

Water Jet cutting

5 days

Mon 06/04/15

27

Microstructure

5 days

Mon 13/04/15

28

Wear And Corrosion Testing 15 days

Mon 20/04/15

29

Hardness

5 days

Mon 11/05/15

30

Simulation

8 days

Mon 18/05/15

31

Presentation 1

4 days

Tue 05/05/15

32

Prepare Slides

2 days

Tue 05/05/15

33

Prepare Speech

2 days

Thu 07/05/15

Project: Project1
Date: Fri 27/02/15

1st Quarter
Jan
Feb

Mar

2nd Quarter
Apr
May

Task

Manual Summary

Split

Start-only

Milestone

Finish-only

Summary

External Tasks

Project Summary

External Milestone

Inactive Task

Deadline

Inactive Milestone

Path Predecessor Milestone Task

Inactive Summary

Path Predecessor Summary Task

Manual Task

Path Predecessor Normal Task

Duration-only

Progress

Manual Summary Rollup

Manual Progress

Page 3

Jun

3rd Quarter
Jul
Aug

Sep

4th Quarter
Oct
Nov

Dec

ID

Task Name
34

Duration

Second Preliminary Report

Start

65 days

Mon 01/06/15

35

Results

30 days

Mon 01/06/15

36

Discussion

15 days

Sat 11/07/15

37

Conclusion

15 days

Thu 30/07/15

38

Submit Draft

1 day

Thu 20/08/15

39

Edit Draft

5 days

Fri 21/08/15

40

Submit final

1 day

Fri 28/08/15

41

Presentation 2

5 days

Mon 31/08/15

42

Prepare Slides

3 days

Mon 31/08/15

43

Prepare Speech

2 days

Thu 03/09/15

44

Final Dissertation

22 days

Sat 05/09/15

Project: Project1
Date: Fri 27/02/15

1st Quarter
Jan
Feb

Mar

2nd Quarter
Apr
May

Task

Manual Summary

Split

Start-only

Milestone

Finish-only

Summary

External Tasks

Project Summary

External Milestone

Inactive Task

Deadline

Inactive Milestone

Path Predecessor Milestone Task

Inactive Summary

Path Predecessor Summary Task

Manual Task

Path Predecessor Normal Task

Duration-only

Progress

Manual Summary Rollup

Manual Progress

Page 4

Jun

3rd Quarter
Jul
Aug

Sep

4th Quarter
Oct
Nov

Dec

ID

Task Name

Duration

Start

45

Final Dissertation

10 days

Sat 05/09/15

46

Submit Draft

3 days

Thu 17/09/15

47

Edit

8 days

Tue 22/09/15

48

Submit Final

1 day

Mon 05/10/15

6 days

Mon 05/10/15

49

Poster

50

Prepare Poster

5 days

Mon 05/10/15

51

Submit Poster

1 day

Mon 12/10/15

Project: Project1
Date: Fri 27/02/15

1st Quarter
Jan
Feb

Mar

2nd Quarter
Apr
May

Task

Manual Summary

Split

Start-only

Milestone

Finish-only

Summary

External Tasks

Project Summary

External Milestone

Inactive Task

Deadline

Inactive Milestone

Path Predecessor Milestone Task

Inactive Summary

Path Predecessor Summary Task

Manual Task

Path Predecessor Normal Task

Duration-only

Progress

Manual Summary Rollup

Manual Progress

Page 5

Jun

3rd Quarter
Jul
Aug

Sep

4th Quarter
Oct
Nov

Dec

You might also like