CHECKLIST FOR PIPING ISOMETRICS

INPUT REQUIRED
1.
2.
3.
4.
5.

P&ID of those pipe lines


Line list
Piping layout
Piping material specification
Construction piping isometrics supports marked layout also

PIPING ISOMETRIC DRAWINGS CHECKLIST


1. Fix the north positions
2. The isometrics drawn to not to scale
3. Mention the dimensions parallel to the pipe line (aligned dimensions)
4. Mention the elevation and centre line of the pipe
5. Mention the pipe line tag numbers
6. Reference position ( like column, beam, wall, equipments with coordination as
needed)
7. Bill of materials reference (part) numbers for each components
8. Mention the piping branch connection & continuation
9. Mention the pump nozzle, vessel nozzle connection
10. Mentions the equipment No., nozzle No., flange connection elevation (FOF,EOF)
11. If one pipe line drawn in more than one sheet means must be mentioned the sheet
reference numbers and continuation reference numbers
12. Mention the continuation line in dotted that bill of materials doesnt include in
isometrics that components must include in continuation isometric sheet (refer
flow directions)
13. Flow direction
14. Insulation, insulation thickness
15. Pipe tracing (electrical /steam tracing) to be denoted
16. the BOM sheet use to be serial no, components quantities, dimension size,
materials weight material specification (like materials, dimension, ASME B
36.10 Pipe dimension standards , ASTM A 106 Gr B this is chemical composition
standards)
17. Autocad / Esapro follow the different layers for pipe line, dimension, tag, and
letters.
18. Stress Iso shall be includes design temperature, design pr, operating temp.,
operating pr, hydro pr, materials.
19. Stress Iso shall be excluded BOM.
20. Drawn the slope as per P&ID and piping layouts
21. incase of reference taken from adjacent pipe line means that adjacent pipe line
tag should appear completely.
22. (a) for stainless steel pipe supports trunions special class
(b) all other spec. pipe supports trunions are as per line class
23. Pipe supports should not be provided with in the spool piece removable area
24. P&ID numbers in the isometrics should be from origin P&ID numbers

25.
26.
27.
28.

29.
30.
31.

32.
33.
34.
35.
36.
37.
38.
39.

40.
41.
42.
43.
44.

45.
46.

Note on safety valve outlet line going to atmosphere (End to be chamber 45


downwards )
for wafer type butter fly valve/wafer type check valve, special (extra) length
through bolts to be used
For commissioning Temp, strainers not to be included in the MTO list (i.e Temp,
presu, strainer supplied by commissioning contractor)
anubar type flow transmitter in the isometrics as per instrumentation
recommendation only hole to be provided on the pipe and orientation has to be
mentioned
revisions comes in the isometrics properly clouded the particular portion & put
revision symbol
Process vent/ drains, Hydro test vent & drains for modeling Lucite standards to be
followed
IFC issue back drafting level after updating of all comments designer to take iso
print out and through the isos , all previous items are properly appearing in the
isometrics drawing
(a) Pipe supports to be moved through MDS only. Not by using move commands
(b) dont use out spec. comments
branch connection to be checked with the branch table
For all valves normally (by default) reduced bore ball valves are used. if full bore
ball valve are mentioned in P&ID
for ductile & malliable iron double flanged type butterfly valves flat face flanges
to be used
wherever mono flange used for INST. Tapping extra bolt length to be used as per
INST. Recommendation
wherever extended spindle valves in the isometrics, spindle length to be indicate
in the isometrics
wherever chain operated valves isometrics chain length to be indicated in
isometrics
standards colors codes for checking isometrics;
Yellow for correction
Red for addition
Blue for deleted items
Green for information
the MTO column fabrication/ erection split-up to be properly checked
comments from stress /supports/inst/ MTO to be properly checked
for line size 1 & < 1 field supports to suit at site ( notes has to be
indicate )
valves special notes : LO-LC lock open/lock closed to be marked in iso
for small bore particular piping add note : contractor and FW construction shall
verify route and modify as necessary to suit site condition ( refer doc)
fluid codes: WCS /WCR , RF, WD, WP,AI,AS,AN,GN,AM
note for actuated valve size 1 and below as actuated valves are heavy,
adequate supports shall be placed either side off the valves close vicinity
safety valves inlet line extra bolt length has to provide