BE calculation guide

SAP BE Using controlling module


For Calculation of BE in SAP, Based on future Price, we need to follow the following steps:

Upload Raw materials future price.


Upload Plan cost.
Upload Plan Activity
Calculate plan activity rates
Run cost estimates (up to analysis stage)

1. Upload Future raw material prices (Via Upload program), which appears in Material Master data
Planned Price 2 see fig 01, because priority is set for valuation variant in costing variant ZPC1 see
fig 02

Fig. 01

Fig. 02

BE calculation guide
2. Upload Plan cost to all Work centers (Production Cost Centers 2020Split for Beltexco Ltd)
using LSMW, and use Plan Version 08

3. Upload Plan Activity for all Work centers (Production Cost Centers) using LSMW upload
program, and use Plan Version 08.
4. Calculate Plan Price for Activity using T Code KSPI and check the price in KSBT report

BE calculation guide
KSBT Report:

5. Create Cost Estimate using CK40N, using Costing ZPC1 and Costing Version other than 08and

BE calculation guide
Select proper range of date for which BE is required, and complete the only up to Analysis stage to get
the results.

BE calculation guide

UPLOAD Procedure and programs (Material Prices, KP06 and KP26)


Material Price Upload
Future Price of Raw Material is uploaded considering following steps.
1. Identify list of materials which need to valuated at Future price/ Market Price in coordination
with procurement dept.
2. Arrange all data in Upload template and complete the file in excel and convert to Notepad.
3. Use LSMW with upload program PSL_PLAN_PRICE1.

01) Procurement dept. will provide list of Raw materials whose price are evaluated at future/market
value for the month or quarter for which the BE is being provided.
02) Upload template:

Upload template contain following fields


Material number (Use only)
Check box (Use only)
Plant (Use only)
Future Planned Price 1
Future Planned Price 2 (Use only)
Future Planned Price 3
Date from Which Future Planned Price 1 Is Valid
Date from Which Future Planned Price 2 Is Valid (Use only)
Date from Which Future Planned Price 3 Is Valid

Then copy the data from excel upload template into Notepad document and remove space from bottom
of the document remove space from the bottom of notepad and maintain space on the top of file

Then upload file is ready for uploading.

BE calculation guide
03) Upload Procedure

Use T code LSMW to upload with program PSL_PLAN_PRICE1

Write the program into all field Project, Subproject and object and then press execute button the
following screen appears, go to item # 7 Specify Files and execute.

After execution the following screen pops up and first press


double click on selected row to give path to upload file

to bring the data into change mode

BE calculation guide

And the complete all steps


Assign files, Read Data, Display Read Data, Convert Data, display converted data, Create batch input
session

BE calculation guide

And finally Run Batch input session and press

And press

And for verification check materials master data for planned prices.

BE calculation guide

Uploading Planning Activity KP26


Steps

Prepare planning activity file in excel and then convert to Notepad for upload
Use LSMW bearing Project Midas_fico, Subproject zfi_co Object KP26PRD
Check upload results in report S_ALR_87013611.

BE calculation guide

Uploading Planning cost KP06


Steps

Prepare planning activity file in excel and then convert to Notepad for upload
Use LSMW bearing Project MIDAS SL 3 , Subproject FICO, Object KP061
Check upload results in report S_ALR_87013611.