Professional Documents
Culture Documents
(First Edition)
AWWA Standard
Installation of Steel
Water Pipe4 In.
(100 mm) and Larger
SM
Advocacy
Communications
Conferences
Education and Training
Science and Technology
Sections
AWWA Standard
This document is an American Water Works Association (AWWA) standard. It is not a specification. AWWA standards
describe minimum requirements and do not contain all of the engineering and administrative information normally
contained in specifications. The AWWA standards usually contain options that must be evaluated by the user of the
standard. Until each optional feature is specified by the user, the product or service is not fully defined. AWWA publication
of a standard does not constitute endorsement of any product or product type, nor does AWWA test, certify, or approve
any product. The use of AWWA standards is entirely voluntary. AWWA standards are intended to represent a consensus
of the water supply industry that the product described will provide satisfactory service. When AWWA revises or withdraws
this standard, an official notice of action will be placed on the first page of the classified advertising section of Journal
AWWA.The action becomes effective on the first day of the month following the month of Journal AWWA publication of the
official notice.
ii
Copyright 2007 American Water Works Association. All Rights Reserved.
Committee Personnel
The Steel Water Pipe-Manufacturers Technical Advisory Committee (SWPMTAC)
Task Force for Development and Maintenance of AWWA C604, which developed this
standard, had the following personnel at the time:
Nash Williams, Chair
H.H. Bardakjian, Ameron Concrete & Steel Pipe,
Rancho Cucamonga, Calif.
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
iii
Copyright 2007 American Water Works Association. All Rights Reserved.
(AWWA)
(AWWA)
(AWWA)
The Standards Committee on Steel Pipe, which reviewed and approved this standard,
had the following personnel at the time of approval:
George J. Tupac, Chair
John H. Bambei Jr., Vice-Chair
Dennis Dechant, Secretary
General Interest Members
E. Bakall, Consulting Engineer, Tustin, Calif.
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
* Alternate
Liaison, nonvoting
iv
Copyright 2007 American Water Works Association. All Rights Reserved.
(AWWA)
Producer Members
H.H. Bardakjian, Ameron Concrete & Steel Pipe,
Rancho Cucamonga, Calif.
(AWWA)
(AWWA)
(MSS)
(AWWA)
(AWWA)
B.D. Keil, Continental Pipe Manufacturing Company, Pleasant Grove, Utah (SPFA)
J.L. Luka, American SpiralWeld Pipe Company, Columbia, S.C.
(AWWA)
(AWWA)
(AWWA)
User Members
G.A. Andersen, New York City Bureau of Water Supply, Corona, N.Y.
(AWWA)
(AWWA)
(USBR)
(AWWA)
(AWWA)
(AWWA)
(AWWA)
G.P. Stine, San Diego County Water Authority, San Diego, Calif.
(AWWA)
(AWWA)
* Alternate
v
Copyright 2007 American Water Works Association. All Rights Reserved.
vi
Copyright 2007 American Water Works Association. All Rights Reserved.
Contents
All AWWA standards follow the general format indicated subsequently. Some variations from this format
may be found in a particular standard.
SEC.
PAGE
SEC.
PAGE
Foreword
Installation
Introduction........................................ix
3.1
I.A
3.2
I.B
Discussion...........................................ix
3.3
I.C
Acceptance ..........................................ix
3.4
II
Special Issues.......................................xi
3.5
II.A
Application .........................................xi
3.6
Thrust Restraint.................................27
III
3.7
Backfilling..........................................27
III.A
3.8
Flushing .............................................30
III.B
Modification to Standard...................xii
IV
Comments .........................................xii
4.1
Disinfection.......................................32
6.1
Casing Pipe........................................32
6.2
Standard
1
General
1.1
Scope ...................................................1
1.2
Purpose ................................................2
1.3
References ............................................2
Subaqueous Crossings
1.4
Definitions...........................................3
7.1
1.5
Preconstruction Planning.....................6
1.6
Permeation...........................................7
Figures
and Storage
2.1
Inspection ............................................7
2.2
vii
Copyright 2007 American Water Works Association. All Rights Reserved.
SEC.
PAGE
SEC.
viii
Copyright 2007 American Water Works Association. All Rights Reserved.
PAGE
Foreword
This foreword is for information only and is not a part of AWWA C604.
I. Introduction.
I.A. History of Standard. This standard pertains to the in-ground installation
of steel pipelines for use in the distribution and transmission of water, air, and other
products in water system facilities. It has been prepared by the AWWA Standards
Committee on Steel Pipe, initially formed as Committee A7A in 1939. At that time,
the Steel Water Pipe Manufacturers Technical Advisory Committee was organized as
a subsidiary group to function as a source of technical information for the parent
committee. Committee A7A and its successors, Committee 8310D and the AWWA
Standards Committee on Steel Pipe have assumed responsibility for all AWWA
standards and manuals pertaining to steel pipe, fittings, linings and coatings, field
installations, and related items.
In 1996 the AWWA Standards Council directed the Standards Committee on
Steel Pipe to develop a standard for the installation of steel pipelines and their
appurtenances used in water treatment or conveying facilities. This standard,
AWWA C604, is the first steel pipe installation standard developed by AWWA.
I.B. Discussion. AWWA C604 includes all types of steel pipe 4 in. (100 mm)
in diameter and larger typically used in the water industry, regardless of pipe
manufacturing source. With adequate quality assurance, pipe manufactured in a
fabricators shop or in a steel-pipe mill is suitable for water utility service. Pipe
produced in a fabricators shop or pipe mill for installation in accordance with
AWWA C604 shall meet the stringent design, quality control, and testing
requirements of AWWA Manual M11 and AWWA C200. Shop and mill-fabricated
pipe made from materials and in accordance with the quality control measures
stipulated in AWWA Manual M11 and AWWA C200 will ensure fabricated pipe of
high quality.
I.C. Acceptance. In May 1985, the US Environmental Protection Agency
(USEPA) entered into a cooperative agreement with a consortium led by NSF
International (NSF) to develop voluntary third-party consensus standards and a
certification program for all direct and indirect drinking water additives. Other
members of the original consortium included the American Water Works Association
Research Foundation (AwwaRF) and the Conference of State Health and Environ-
ix
Copyright 2007 American Water Works Association. All Rights Reserved.
*Persons outside the United States should contact the appropriate authority having jurisdiction.
NSF International, 789 North Dixboro Road, Ann Arbor, MI 48105.
American National Standards Institute, 25 West 43rd Street, Fourth Floor, New York, NY 10036.
Both publications available from National Academy of Sciences, 500 Fifth Street, NW,
Washington, DC 20001.
x
Copyright 2007 American Water Works Association. All Rights Reserved.
xi
Copyright 2007 American Water Works Association. All Rights Reserved.
5. Surface restoration.
6. Special handling requirements.
III.B. Modification to Standard. Any modification to the provisions, definitions, or terminology in this standard must be provided in the purchasers
specifications.
IV. Major Revisions. This is the first edition of this standard.
V. Comments. If you have any comments or questions about this standard,
please call the AWWA Volunteer & Technical Support Group at 303.794.7711, FAX
303.795.7603, write to the group at 6666 W. Quincy Avenue, Denver, CO 802353098, or e-mail at standards@awwa.org.
xii
Copyright 2007 American Water Works Association. All Rights Reserved.
AWWA C604-06
(First Edition)
AWWA Standard
GENERAL
Scope
This standard provides the field installation guidelines for buried steel water
pipe, 4 in. (100 mm)* and larger, and their appurtenances.
The information contained in this standard is intended to be used as a guide to
assist in the installation of steel water pipe. Whenever the methods contained herein
conflict with those of the contract documents and/or the purchaser, the contract
documents and/or purchaser should be followed.
1.1.1 Conditions which may require additional considerations. In s t a l l a t i o n s
that require special attention, techniques, and materials are not covered. Some of
these installations are
1. Piping through rigid walls.
*Metric conversions given in this standard are direct conversions of US customary units and are not
those specified in the International Organization for Standardization (ISO) standards.
1
Copyright 2007 American Water Works Association. All Rights Reserved.
2 AWWA C604-06
2.
3.
4.
5.
6.
7.
8.
9.
10.
Sec. 1.2
Purpose
This standard is intended to cover typical pipeline construction practices that
are deemed adequate for the satisfactory installation of steel water pipe and
appurtenances. Individual project requirements can vary substantially and should
always be thoroughly reviewed prior to bidding or construction startup. For this
reason, some practices discussed in this standard may not be suitable for all project
conditions, and, in some cases specialized installation techniques may be required
that are beyond the scope of this standard.
Sec. 1.3
References
This standard references the following documents. In their latest editions, the
referenced documents form a part of this standard to the extent specified herein. In
any case of conflict, the requirements of this standard shall prevail.
AASHTO T99*Moisture Density Relations of Soils Using a 5.5-lb (2.5-kg)
Rammer and a 12-in. (305-mm) Drop.
ANSI/AWWA C500Metal-Seated Gate Valves for Water Supply Service.
ANSI/AWWA C509Resilient-Seated Gate Valves for Water Supply Service.
ANSI/AWWA C651Disinfecting Water Mains.
AWWA Manual M3, Safety Practices for Water Utilities, AWWA, Denver, Colo.
(1990).
The reader is referred to the following standards for additional information on
the use or limitations of specific products.
*American Association of State Highway and Transportation Officials, 444 North Capitol Street N.W.,
Suite 249, Washington, DC 20001-1512.
Sec. 1.4
Definitions
In this standard, the following definitions shall apply:
1.4.1 Bevel: The angle formed between the prepared edge of a pipe end and
a plane perpendicular to the longitudinal axis of the pipe. Bevels are generally used
for butt welding of pipe ends.
*Occupational Safety and Health Administration, Code of Federal Regulations; available from
Government Printing Office, 720 N. Main, Pueblo, CO 81003.
American Welding Society, 550 N.W. LeJeune Road, Miami, FL 33126-5699.
4 AWWA C604-06
inch for steel sheet or 490 lb per cubic foot for steel plate shall be used when
calculating weight per foot.
1.4.14 Pipe bedding: The material immediately under the pipeline and by
which the pipeline is supported. This material is usually of a specific description and
may simply be the reuse of the originally excavated material.
1.4.15 Plain-end pipe: Pipe that is not threaded, belled, or otherwise given a
special end configuration.
1.4.16 Plans: Drawings normally prepared by an engineer employed or
retained by the purchaser system-operator entity showing the location and details for
the construction of the pipeline and appurtenances.
1.4.17 Plasma-arc cutting: An arc-cutting process that severs metal by
melting a localized area with a constricted arc and removing the molten material with
a high-velocity jet of hot, ionized gas blown at high speed from the constricting
orifice.
1.4.18 Purchaser: The person, company, or organization that purchases any
materials or work to be performed.
1.4.19 Random lengths: Pipe lengths as produced in a pipe mill, to which no
special treatment is given to make the lengths uniform.
1.4.20 Root: That portion of a joint to be welded where the members
approach closest to each other. In cross section, the root of a joint may be a point, a
line, or an area.
1.4.21 Seamless pipe: Pipe without welds or filler metal, made from solid
ingots, blooms, billets, or round bars that have been hot pierced and then brought to
the desired size by hot rolling, hot drawing, or a combination of both.
1.4.22 Select material: The native soil free of rocks, foreign or organic
materials, and frozen earth.
1.4.23 Special section: Any piece of pipe other than a normal full-length
straight section. This includes but is not limited to elbows, personnel access sections,
short pieces, reducers, adapter sections with special ends, and other nonstandard
sections.
1.4.24 Specifications: Detailed procedures and requirements initiated by the
purchaser or designee, outlining methods of design, manufacture, standards of
acceptability, methods of installation, or any other criteria the purchaser deems
necessary for the procurement of the product required. Installation specifications may
6 AWWA C604-06
Sec. 1.5
Preconstruction Planning
The installation of steel pipelines usually involves multiple suppliers and
subcontractors that have varying preparation requirements. For this reason a
preconstruction meeting is strongly recommended to schedule the critical path
aspects of all involved parties. In particular, pipe and valve materials are usually
manufactured to fit specific locations of the project and often require an extended
lead time for the purchase of raw material, drawing preparation, and drawing
approvals that must precede construction activities. Any preconstruction planning
meeting initiated by the purchaser should include all essential suppliers and
subcontractors. During the meeting a schedule should be prepared that is agreeable
to all parties and provides float for operations subject to potential delays. All parties
elaborate on their respective preparations, such as procurement of materials,
preparation of drawings, and submittals. The constructor shall be required to provide
the starting location and direction of construction. Care should be taken when
preparing the construction schedule as later changes in construction plans may affect
shop drawings, laying schedules, delivery dates, and other parties. Detailed shop
drawings must be approved by the constructor and purchaser prior to pipe
production.
Sec. 1.6
Permeation
The selection of materials is critical for water service and distribution piping in
locations where the pipe is likely to be exposed to significant concentrations of
pollutants composed of low-molecular-weight petroleum products, organic solvents,
or their vapors. Documented research has shown that pipe materials such as
polyethylene, polybutylene, polyvinyl chloride, and asbestos cement, as well as
elastomers, such as those used in jointing gaskets and packing glands, may be subject
to permeation. If a water pipe must pass through such a contaminated area or an area
subject to contamination, consult with the manufacturer regarding permeation of
pipe joints coatings, and so on, before selecting materials for use in that area.
Inspection
2.1.1 Pipe inspection at the plant. All materials shall be subject to inspection
and acceptance at the manufacturers plant. Acceptance criteria shall be based on
criteria agreed to by the purchaser and constructor in accordance with the contract
documents.
2.1.2 Inspection on delivery. All pipe and appurtenances are subject to
inspection at the point of delivery. Material found to be defective because of
manufacture or damage in shipment shall be rejected or recorded on the bill of
lading. There shall be agreement regarding any necessary repairs. These repairs shall
be made and the purchaser shall monitor the repairs prior to installation.
Sec. 2.2
8 AWWA C604-06
SECTION 3:
Sec. 3.1
INSTALLATION
Sec. 3.2
Trench Construction
The trench shall be excavated to the required alignment, depth, and width
specified or shown on the contract documents and shall be in conformance with all
federal, state or provincial, and local regulations for the protection of workers.
3.2.1 Trench preparation. Trench preparation shall proceed in advance of the
pipe installation. The amount of open trench length allowed is limited by the
amount of nonbackfilled pipe according to Sec. 3.3, the contract documents, and any
safety considerations (such as traffic, slope, etc.).
3.2.1.1 Discharges from trench dewatering pumps shall be directed away from
the trench, in order not to affect trench stability, and shall be in accordance with
federal, state, and local point discharge requirements.
3.2.1.2 Excavated material shall be placed in a manner that will not obstruct
the work, endanger workers or the public, or obstruct sidewalks, driveways,
roadways, and other structures. If obstruction of such structures becomes necessary,
10 AWWA C604-06
the constructor shall plan for alternate means to accommodate the public. Placement
of excavated material shall be done in compliance with federal, state or provincial,
and local regulations.
3.2.2 Pavement removal. Removal of pavement and road surfaces shall be a
part of the trench excavation. The amount removed shall depend on the width of
trench required for installation of the pipe, including safety requirements and the
dimensions of the area into which valves, specials, manways, or other structures will
be installed. Methods such as sawing, drilling, or chipping shall be used to ensure the
breakage of pavement along straight lines.
3.2.3 Width. The width of the trench at the top of the pipe shall be as
dictated by the contract documents or as necessitated by safety requirements. In any
case, the trench width shall provide ample clearance to permit the pipe to be installed
and joined properly and to allow the backfill to be placed in accordance with the
contract documents. Trenches shall be of such extra width, when required, to permit
the placement of sheeting, bracing, and appurtenances as required by the safety
requirements of the agency having jurisdiction. In addition, the trench width at the
bottom of the pipe will be governed by the space required for compaction/
consolidation equipment, but never less than the outside diameter of pipe plus 20 in.
(500 mm) (see Figure 5).
3.2.4 Depth. The trench shall be excavated to the specified grade. The
trench bottom shall provide uniform support for the full length of the pipe barrel,
except that a slight depression may be provided to facilitate the removal of pipe slings
or other lifting tackle without damaging the pipe coating. Pipe bedding and backfill
material shall be installed so as to avoid abrasion or other damage to the coating on
the pipe.
3.2.5 Bell holes. Holes for the bells shall be provided at each joint. Holes
shall be adequately sized for completing any external coatings, but shall be no larger
than necessary to allow joint assembly. If the pipe joints are welded or coupled, the
bell holes shall provide adequate clearance for welding or assembly and subsequent
external coatings. A 24-in. (600-mm) clearance below or on the sides of the pipe is
usually adequate for this purpose.
3.2.6 Rock conditions. If excavation of rock is necessary, all rock shall be
removed to provide a clearance below and on each side of all pipe, valves, and
fittings. The minimum clearance shall be 6 in. (150 mm) for pipe with an outside
diameter (OD) up to 24 in. (600 mm) and 10 in. (250 mm) for pipe with an OD
greater than 24 in. (600 mm). When the excavation is completed, a layer of
appropriate backfill material (see Sec. 3.7) shall be placed on the bottom of the
trench to the previously mentioned depths, graded, and tamped. These clearances
and bedding procedures shall also be observed for pieces of concrete or masonry and
other debris or subterranean structures, such as masonry walls, piers, or foundations
that may be encountered during excavation.
3.2.7 Previous excavations. Should the trench pass over a sewer or other
previous excavation, the trench shall be sufficiently compacted to provide support
equal to that of the native soil or conform to other regulatory requirements in a
manner that will prevent damage to the existing installation.
3.2.8 Blasting. Blasting for excavation shall be permitted only after securing
approval(s) and establishing the hours of blasting as required by the contract
documents. The blasting procedure, including protection of existing utilities,
persons, and property, shall be in strict accordance with federal, state or provincial,
and local regulations.
3.2.9 Protection of property. Trees, shrubs, fences, and all other property and
surface structures and underground shall be protected during construction unless
their removal is shown in the contract documents.
3.2.9.1 Temporary support, adequate protection, and maintenance of all
underground and surface structures, drains, sewers, and other obstructions encountered in the progress of the work shall be provided in accordance with the contract
documents or applicable regulations.
3.2.10 Unsuitable subgrade material. When the subgrade is found to include
ashes, cinders, refuse, organic material, or other unsuitable material, such material
shall be removed at least to 6 in. (150 mm) below the bottom of the pipe or to the
depth required by the contract documents. The removed material shall be replaced
with clean, stable backfill material. The bedding shall be compacted and graded so
that the pipe may be installed in accordance with Sec. 3.3.
3.2.11 Unstable subgrade. When the bottom of the trench or the subgrade
consists of material that is unstable to such a degree that it cannot be removed, a
foundation for the pipe and/or appurtenance shall be constructed in accordance with
the contract documents.
12 AWWA C604-06
Sec. 3.3
Pipe Installation
Proper implements, tools, and facilities shall be provided and used for the safe
and convenient performance of the work. All pipe, fittings, and valves shall be
lowered carefully into the trench by means of a backhoe or crane, using nylon slings,
guide ropes, or other suitable tools or equipment, in such a manner as to prevent
damage to the pipe, protective coatings, and linings. Pipe shall not be dropped or
dumped into the trench. The trench shall be dewatered prior to installation of the
pipe and maintained until the pipeline is substantially covered as necessary to prevent
pipe from floating.
The length of pipe that may be installed prior to backfilling shall not exceed
1,000 ft (330 m) or a length approved by the purchaser. Backfilling for this purpose
is described as material covering the top of the pipe. If the constructor chooses to
backfill between pipe joints, the exposed portion of the joint area will be
accumulated toward the limit.
3.3.1 Examination of material. All pipe, fittings, coatings and appurtenances
shall be examined carefully for damage and other defects immediately before
installation. Defective materials shall be marked and held for final disposition as
required by the contract documents.
3.3.2 Pipe ends. All deleterious materials shall be removed from the ends of
each pipe. For bell- and spigot-pipe, the outside of the spigot end and the inside of
the bell shall be wiped clean and dry so that it is free from dirt, sand, grit, and other
foreign matter before the pipe is installed.
3.3.3 Pipe cleanliness. Foreign material shall be prevented from entering the
pipe while it is being placed in the trench. No debris, tools, clothing, or other
materials shall be allowed to accumulate during construction and shall be promptly
removed as work progresses.
3.3.4 Direction of bells. It is common practice to lay welded pipe joints with
the spigot facing the direction in which work is progressing; however, this practice is
not mandatory. For gasketed pipe, common practice is to lay the pipe joints with the
bell facing the direction in which work is progressing to prevent debris from being
scooped into the bell. The direction of the bells is not functionally related to the
direction of flow within the system.
3.3.5 Pipe end caps. When pipe laying is not in progress, the open ends of
pipe may be required to be closed by a plug or other means as specified. If utilized,
the end caps shall remain in place until the trench work proceeds. Care must be
taken to prevent pipe flotation should the trench fill with water.
Sec. 3.4
14 AWWA C604-06
Figure 2
16 AWWA C604-06
continuous. Do not use a stabbing motion, as the feeler gauge can pass through the
gap between the shoulder of the spigot and the inside of the bell and possibly damage
the gasket. The only purpose of the feeler gauge test is to determine whether the
gasket has rolled out of the groove during installation; it is not performed to
determine the amount of clearance between the spigot and the bell.
3.4.1.3 Repair of rubber gasket joints. If the gasket has disengaged, the joint
shall be pulled apart, and the gasket shall be removed and checked for any damage.
Reinstall the gasket, or if damaged, install a new gasket following the procedure in
Section 3.4.1.1. Alternatively, if a pipe segment cannot be removed, insert a rolled
steel round bar into the flare of the bell and seal weld the round bar to the bell and
spigot.
3.4.2 Pipe placement for welded lap joints. Mark the outside of the pipe at the
quarter points for the full stab depth. This dimension will be provided with the
length of the joint detailed in the drawings and will typically range from 2 in. (50
mm) to 3 in. (75 mm). Lift the pipe using a two-point lifting method. On steep
slopes, it may be advisable to use the slings as chokers. Lower the pipe segment, bell
end first, at an approximate 5 to 10 degree angle relative to the previously laid pipe
segment. This will allow the bell edge to overlap the spigot (of the previously laid
pipe) to the proper stab depth mark. On large-diameter pipe, tack weld the joint
edge to provide a hinge that will guide the remainder of the bell insertion as the pipe
is lowered (see Figure 3). The tack welds may remain as part of the permanent weld
if the welder is properly qualified and the weldment meets the requirements of ANSI/
AWWA C206 and the contract documents. Thermal stresses should not be allowed
to accumulate due to the tack weld. Under certain circumstances, some constructors
may choose to insert the spigot straight into the bell by methods described in
Sec. 3.4.1.1. As each length of pipe is placed in the trench, the joint shall be
assembled and checked for stab depth, and the pipe shall be brought to correct line
and grade. After the joint is fully engaged, deflect the joint, if required, within the
prescribed limits in Sec. 3.4.3 or the contract documents. Proceed with the welding
of the joint in accordance with ANSI/AWWA C206 followed by any required testing.
Upon successful weld testing, apply any required linings or coatings. The pipe shall
be secured in place with approved backfill material.
3.4.3 Joint deflection. When it is necessary to deflect gasketed or welded pipe
from a straight line in either the horizontal or vertical plane, the amount of joint
deflection shall not exceed a 1 in. (25 mm) pull, measured at the joint or in
18 AWWA C604-06
S
L
R
S
L
R
=
=
=
=
R=
deflection angle
joint deflection offset
laying length
radius of curve
L
2tan 2
1. Inspect the gasket seating surfaces. Look for tool marks, scratches, or
pitting by corrosion, and make sure that the gasket seating surface is proper for the
type of gasket being used.
2. Inspect the gasket. Look for possible defects or damage in the gasket.
3. Lubricate all thread contact areas and nut facings. This step is very
important.
4. Loosely install the fasteners on the lower half of the flange. Insert the
gasket between the flange facings to allow the bolts to center the gasket on the
assembly. Install the remaining bolts and nuts and tighten them to a hand-tight or
snug condition.
5. Torque the bolts up to a maximum of 30 percent of the final torque value
required, following the sequence recommended in AWWA M11. Number the bolts
so that torquing requirements can be followed.
6. Repeat step 5, increasing the torque to 50 to 60 percent of the final torque
value required.
7. Continue with the sequence of retorquing all fasteners to the specified
torque value.
NOTE: For insulating flanges, refer to the manufacturers recommendations.
3.4.5 Transition couplings. Transition couplings may be required for joining
different types of pipe. Such transition devices are typically available. When ordering,
the actual outside diameter of the pipe ends shall be given.
3.4.6 Tapping sleeves. Tapping sleeves are a means of making branch
connections to existing pipelines. The procedures for proper installation of tapping
sleeves shall follow the manufacturers recommendations.
3.4.7 Sleeve couplings. Sleeve couplings are used on pipelines of all diameters. The typical installation sequence for bolted, sleeve-type couplings is provided in
ANSI/AWWA C219.
3.4.8 Split-sleeve coupling. Split-sleeve couplings are used on pipelines of all
diameters. Follow the manufacturers recommendations for their installation.
3.4.9 Welded joints. The need for welded joints will vary by project and will
be dictated in the contract documents. Several types are common, including lap,
butt, and butt-strap welded joints.
Welding shall meet the requirements of ANSI/AWWA C206 and the contract
documents for the project. Shielded metal arc welding (SMAW), or stick welding, is
the most common method used. Semiautomatic and automated welding processes
20 AWWA C604-06
are practical when a large number of welded joints are required. These processes are
described in ANSI/AWWA C206.
In accordance with ANSI/AWWA C206, joint welding procedures, welders and
welding operators shall be qualified under tests prescribed by the American Welding
Society (AWS) D1.1 Structural Welding CodeSteel. Several common joint welding
procedures outlined in AWS D1.1 are already considered prequalified.
Preheating is required prior to welding when the steel temperature is less than
32F (0C). For most mild steel applications where the steel wall thickness is less than
3/4 in. (19 mm) and using conventional welding processes, preheating is required if
the metal temperature of the steel is less than 32F (0C) as measured at any point
within 3 in. (75 mm) from the weld bead or 4 times the pipe wall thickness,
whichever is greater. The specific preheating requirements will vary depending on the
welding process, steel specification, steel thickness, and metal temperature and should
be determined by using the AWS D1.1 preheat tables or Annex equations.
The pipe shall be left bare a sufficient distance back from the ends to prevent
the heat produced during welding from damaging the protective coatings and to
prevent the coating from contaminating the in-process weld. In addition, a protective
cover shall be draped over the pipe near the vicinity of welding if further protection
is required. Field welding in the interior of steel pipe is ordinarily limited to 36-in.
(900-mm) or larger pipe, to provide for access and egress. When personnel are
working inside, ventilation shall be provided in strict accordance with federal, state or
provincial, and local regulations.
Wire brushing is usually sufficient to remove any dirt or light rust to prepare the
surface for welding. Small tack welds can be used to hold the pipe in position for
welding, provided the tacks are sound and meet the requirements of AWWA C206.
The number of weld passes needed to complete the joint is a function of the steel
wall thickness, the type of joint, and the type of welding.
3.4.9.1 Welded lap joints. Welded lap joints are frequently used when an
economical method of joint restraint is necessary or for diameters greater than can be
manufactured for a gasketed joint. There are several welding configurations for the
lap joint. The lap weld can be required on either the inside or outside of the pipe
joint. Sometimes a lighter seal weld will be required along with the lap weld to allow
for air testing. Less frequently, contract documents will require a full fillet weld both
inside and out. The nominal engagement of a lap-welded joint is 2 to 3 in. (50 to
75 mm) deep with a minimum required final overlap between the bell and the spigot
of 1 in. (25 mm) or 3 times the thickness of the belled pipe, whichever is greater. The
allowable pullout is 1 in. (25 mm), but in all cases the 1 in. (25 mm) minimum
required overlap must be maintained. No part of any field weld shall be closer than
1 in. (25 mm) to the nearest point of tangency to a bell radius. The allowable angle
of deflection is provided in AWWA Manual M11.
3.4.9.2 Welded butt joint. Welded butt joints are sometimes specified for
special design conditions. Butt joints are usually single-V-groove ends and include a
backup ring. The backup ring will be located on the pipe interior for smaller
diameter pipe and on the exterior or interior for larger pipe (over 36 in. [900 mm] in
diameter). Field joints shall be assembled so that seams in adjacent pipes are offset
from each other by at least five times the thickness of the thicker of the pipes being
joined. Single-V-groove butt joints may be welded from the outside of the pipe, or
from the inside of the pipe if the diameter is large enough. The backing rings may be
left in place after welding. Line-up clamps can assist in the pipe installation. The
installation procedure of field-welded butt joints is basically identical to the above
except that when the two ends have touched, caution should be exercised to ensure
that the proper root opening is achieved and the pipe is firmly secured in position
prior to installing subsequent pipe segments.
3.4.9.3 Welded butt-strap joints. Where welded butt-strap joints are used,
the butt straps shall have a minimum plate thickness equal to the thinnest member
being joined and shall be fabricated from material having equivalent chemical and
physical properties. In accordance with the ANSI/AWWA C206, the strap shall have
a minimum width of 4 in. (100 mm) or the width necessary to obtain a minimum
lap between pipe ends and the butt strap.
For butt-strap joints, the seams of adjacent pipe sections may be in alignment
provided that the butt-strap seams are offset from the pipe seams by at least five times
the thickness of the thicker member involved in the joint. The butt strap may be
welded on the pipe exterior, interior, or both.
3.4.9.4 Welded joint testing. Joint testing is generally performed by air
testing of double fillet welds, magnetic particle or dye penetrant testing of single fillet
welds, and magnetic particle testing of butt-welded joints. Limited use of vacuum
look box testing has been utilized as an alternate method for fillet welds and butt
welds. Limited use of radiographic testing and ultrasonic testing has been utilized as
alternate methods of testing butt joints. Radiographic testing is not recommended for
use on the joint types covered in this standard. The test method shall be specified in
22 AWWA C604-06
the contract documents. These test methods and repair of defective welds are further
described in ANSI/AWWA C206.
3.4.10 Pipe cutting. Prior to cutting, pipe shall be checked to ensure it is
within the necessary tolerance for proper assembly with the adjoining pipe. If the
adjoining pipes are not within the needed longitudinal tolerance, either replace the
segment or use an alternate field joint such as a butt strap. Cutting pipe for insertion
of valves, fittings, or closure pieces shall be done in conformance with all safety
requirements. Cutting may be performed by abrasive saw, oxygen-acetylene torch,
plasma arc, air-arc, or other suitable means. The resulting cut end will require
corrective preparation prior to assembly with the adjoining pipe. Cut ends and rough
edges shall be ground smooth.
3.4.11 Expansion joints. Provisions shall be made for the expansion and
contraction of exposed lines. Where individual pipe lengths are anchored and sleevetype couplings are used for field joints, the joints must allow enough movement so
that expansion and contraction is not cumulative over an excessive length. Thermal
expansion is usually accommodated for trench-laid welded pipelines to avoid the
accumulation of expansion and contraction during installation. These joints usually
include a lengthened bell which is welded only after all adjacent pipe has been welded
and buried.
3.4.12 Bonding of joints. When required by the contract documents, the
bonding of nonwelded joints shall be utilized to make the line electrically continuous
to allow for monitoring of possible corrosion along the pipeline. Bonding jumpers
(or optional s or z bars) will have to be welded in the field, joining the spigot and
the bell. The weld should be kept close to the ends of the pipe to allow joint end
coatings to cover the bonding jumpers.
3.4.13 Protective coatings at field joints. Generally, pipe lengths are coated
and lined, excluding only the pipe ends that are completed in the field. After field
assembly, the exterior and interior joint ends shall be completed with coatings that
are compatible with the original coating system of the pipe and in conformance with
the applicable AWWA standards. The type of pipe coating and end coating shall be
determined by the contract documents. Various pipe end coatings and linings are
available, which are further described in ANSI/AWWA C203, ANSI/AWWA C205,
ANSI/AWWA C209, ANSI/AWWA C210, ANSI/AWWA C216, ANSI/
AWWA C217, and ANSI/AWWA C222. For application and repair of these
materials, follow the appropriate AWWA standard and the manufacturers recom-
mendations. Three commonly used materials for pipe end field coatings are heatshrink sleeves (ANSI/AWWA C216), tape coating (ANSI/AWWA C209), and mortar
coating (ANSI/AWWA C205). Field joint and repair applications for these two
materials are briefly described by this standard.
3.4.13.1 Tape wrapping field joints. Generally, pipe lengths are coated,
excluding only the pipe ends that are completed in the field. The tape is provided in
various widths for various needs, but is generally 6 to12 in. (150 to 300 mm) wide.
Taping can be completed at any temperature as long as the roll body temperature
of the tape is maintained above 70F (21C). The procedure for proper tape
wrapping of field joints is fully described in AWWA C209 and is summarized as
follows:
1. Make sure the joint to be taped is complete, the gasket is checked, the
weld is inspected and the metal is cool to a temperature below 130F (54C).
2. Clean the area to be taped with a rag to make sure all moisture has been
removed.
3. Prime all around the joint, including several inches on both sides beyond
the area where the actual joint tape will be applied. Place filler material at all pipe
joints and at irregularities to create a smooth surface. (Lap welds, where the exterior
is a full thickness weld, and butt welds do not require filler material.)
4. Start in a downhill direction of the pipe and wrap two complete layers
around the pipe until overlapping the starting point by a minimum of 4 in. (100
mm). Cut the tape so as not to damage the field coating. The start and stop spots do
not need to be much farther than 10 to 15 from off the top centerline.
5. Make sure the tape around the joint is wrinkle-free and stretched taut. It
is preferable to keep the welded bonding jumper close to the pipe ends and wrap the
whole area with the tape as the joint is wrapped.
6. Make sure that partial rolls of tape go around at least one complete wrap.
7. Inspect the completed wrap using a holiday detector.
3.4.13.2 Taped pipe repairs. Many taped pipelines include a 3-layer system.
The first layer that actually bonds to the pipe is typically a black tape. The second
layer is a higher-density tape to give durable protection during handling. The third
layer is a tape that provides good protection to the inner layers of tape. In most cases
this outer layer is white. The three layers are generally supplied in three different
colors so that in the event of damage, the colors will assist in determining the extent
24 AWWA C604-06
of damage to the total tape system. The procedure for properly taped pipe repairs is
fully described in ANSI/AWWA C209 and is summarized as follows:
1. Minor wrinkles, scuffs, or any tears located on the edge of the tape that
do not go past the overlap area are generally acceptable. These conditions listed still
give the tape a full film thickness, and it is not practical to remove the high-density
machine-applied tape and replace it with a softer patch-type material.
2. If a tear occurs in only the outer layer, repair the damaged area with one
layer of tape with a minimum overlap of 4 in. (100 mm) onto the existing coating
system.
3. If the damaged coating area shows evidence of going further into the
coating system, use the repair method outlined below.
a. Cut away the damaged tape at an angle tangent to the surface of the pipe
so that the tape system is not cut or damaged any further.
b. Wipe clean the area to be taped and make sure it is dry and free from dirt.
c. Prime the area to be repaired and let the primer dry to a tackiness before
applying the repair tape.
d. Cut the tape to such a size that it extends beyond the damaged area for a
minimum of 4 in. (100 mm) in all directions around the area to be repaired. Apply
the tape starting at the center and working toward the edge, making sure to smooth
out all wrinkles. Make sure the primed area extends past the tape edges.
e. Only one layer of repair tape is required on damages that affect the outer
layer of tape. If a second layer of tape is required to complete the patch, place the
second layer of patch material over the first with a minimum of 1 in. (25 mm)
overlap in all directions of the bottom patch. It will always require two pieces of tape
to accomplish this overlap process.
f. Perform a holiday test on the repair area.
3.4.13.3 Heat-shrink sleeves on field joints. Heat-shrink sleeves are used to
protect field joints from moisture and oxidation. The procedure for proper
application of heat-shrink sleeves is fully described in ANSI/AWWA C216 and is
summarized as follows:
1. Clean the area of the heat-shrink sleeve to remove all moisture, soil, and
foreign materials. Place filler material at all pipe joints and at irregularities to create a
smooth surface. (Lap welds, where the exterior is a full thickness weld, and butt welds
do not require filler material.)
2. Preheat the area according to the manufacturers requirements.
Sec. 3.5
Fitting Installation
3.5.1 Examination of material. Prior to installation, valves shall be inspected
for direction of opening, number of turns to open, freedom of operation, tightness of
pressure-containing bolting and test plugs, cleanliness of valve ports and especially
seating surfaces, handling damage, and cracks. Defective valves shall be marked and
held for final disposition as required by the contract documents. All bolts and nuts,
with the exception of seat-adjusting bolts or screws in butterfly valves, shall be
checked for specified tightness. Seat-adjusting bolts in butterfly valves shall only be
adjusted when recommended by the manufacturer.
3.5.2 Placement. Valves, fittings, plugs, and caps shall be set and joined to
the pipe in the manner specified in Sec. 3.3 for cleaning and laying and Sec. 3.4 for
26 AWWA C604-06
joining pipe, except that 12-in. (300-mm) and larger valves shall be provided with
special support, such as treated timbers, crushed stone, concrete pads, or a sufficiently
tamped trench bottom, so that the pipe will not be required to support the weight of
the valve. Valves installed aboveground or in plant piping systems shall be supported
to prevent bending of the valve end connections as a result of pipe loading. Valves
shall be installed in the closed position; however, valves should be reopened after
installation to provide access, allow ventilation, and ensure proper operation.
3.5.2.1 In no case shall valves be used to bring misaligned pipe into alignment
during installation. Pipe shall be supported in such a manner as to prevent stress on
the valve.
3.5.2.2 Thrust resulting from closure of valves shall be carefully considered
during testing of the piping system and vaults.
3.5.2.3 Mains shall be drained through drainage branches or blowoffs.
Drainage branches, blowoffs, and appurtenances shall be provided with control valves
and shall be located and installed as shown on the contract documents. Discharges
shall be directed away from the pipe alignment, in order not to affect the trench
stability, and shall be in accordance with federal, state, and local point discharge
requirements.
3.5.2.4 Air release and vacuum vents shall be installed in accordance with the
contract documents at the high points in the line and in areas of potential negative
pressure. The location, number, and size of these air release and vacuum vents should
be provided in the contract documents. The air release and vacuum vents shall be
protected in locations where freezing temperatures are encountered.
3.5.3 Valve vaults. Valve vaults are designed to prevent any settlement that
may damage the valve and prevent its proper operation. Installation of the pipe and
valve in the vault shall be such that the operating nut shall be readily accessible for
operation through the opening in the valve vault, which shall be set flush with the
surface of the finished pavement or such other level as may be specified.
Valves and fittings shall be coated with a compatible coating according to the
coating manufacturers recommendations and the applicable AWWA standard.
Additional information regarding installation of gate valves can be found in the
appendixes of ANSI/AWWA C500 and ANSI/AWWA C509.
3.5.4 Plugs and caps. Before putting the installed pipe and appurtenances
under test pressure, consider all dead ends and the methods available to restrain the
dead ends, blowoff valves, and so on, against the force generated by the test pressure.
Sec. 3.6
Thrust Restraint
The need for thrust restraint is a design consideration that is not covered by this
standard. Such restraint is commonly provided by welded joints, thrust collars,
mechanical harnesses, or concrete thrust blocks. Installation of mechanical joints,
mechanical harnesses, fittings, and welded joints are described in Sec. 3.3 and
Sec. 3.4. Such restraint is commonly used when pipe pressure class can cause
excessive movement, when miter joints exceed 5, within vaults, and when the
known restraint mechanism, such as soil, is not adequate to ensure pipeline integrity
under operational and transient pressure loads. For design of thrust restraint, see
AWWA Manual M11.
NOTE: Restraining mechanisms shall be prepared and coated with a compatible
coating according to the coating manufacturers recommendations and the applicable
AWWA standard.
Sec. 3.7
Backfilling
The excavated pipe trench will usually also have to accommodate a specified
thickness of select graded foundation bedding material (see Figure 5). The
foundation bedding material shall be evenly spread in the bottom of the trench to
support the pipe along its entire length with the exception of a few feet near the joint
areas. Backfill shall be accomplished in accordance with the specified laying
conditions described in Sec. 3.3. Backfilling operations shall be maintained to avoid
having an excessive amount of exposed installed pipe.
3.7.1 Pipe zone backfill and foundation material. All pipe zone backfill and
foundation material shall be free from cinders, ashes, refuse, vegetable or organic
material, boulders, rocks or stones 3 in. (150 mm) in diameter and larger, frozen soil,
or other unsuitable materials described by the contract documents.
3.7.1.1 From 12 in. (300 mm) above the top of the pipe to grade, material
containing stones up to 8 in. (200 mm) in their greatest dimension may be used
unless otherwise specified.
3.7.1.2 When the type of backfill material is not indicated or is not specified,
the excavated material may be used provided that such material consists of loam, clay,
sand, gravel, or other suitable materials.
3.7.1.3 Pipe zone backfill shall be densified around the pipe in accordance
with Figure 5. The maximum dry density of cohesive soil shall be between 85 and
95 percent based on ASTM D698 or AASHTO T99 unless otherwise specified (see
28 AWWA C604-06
Figure 5). For free-draining soils, the relative density shall be at least 70 percent as
determined by ASTM D4253 and ASTM D4254 unless otherwise specified.
Regardless of the method of densification used, materials shall be brought up at
substantially the same rate on both sides of the pipe. When installing pipe 36 in.
(900 mm) and larger, use a probe rod method to confirm that the backfill is properly
consolidated within the pipe lower quadrant (between the pipe spring line and invert
elevation). Take care to ensure that the pipe is not floated or displaced before
backfilling is complete.
3.7.1.4 Cohesive soils shall be compacted with mechanical equipment or hand
tamping. Care shall be taken not to damage coatings during compaction. Proper
equipment and care in placement will ensure the required compaction under the
lower quadrant of the pipe. Pipe zone backfill for pipe up to 48 in. (1,200 mm) in
diameter shall be placed in layers of not more than 6 in. (150 mm) in thickness or
25 percent of the pipe diameter, whichever is greater. Pipe zone backfill for pipe
larger than 48 in. (1,200 mm) in diameter shall be placed in layers not exceeding
24 in. (600 mm) in thickness and subject to meeting the compaction requirements.
3.7.1.5 Free-draining soils may be densified by tamping with water-using
devices, or through methods such as water jets, immersion-type vibrators, or
flooding. These soils are usually placed in a minimum of two layers, with the first
layer placed loose to the spring line of the pipe. The thickness of the layers shall not
exceed the penetrating depth of the vibrators if consolidation is performed by jetting
and internal vibration.
3.7.1.6 Pipe zone bedding and backfill may be class C1, C2, or C3 (95, 90,
or 85 percent dry density or 70 percent relative density as expressed in Sec. 3.7.1.3)
or as specified in the contract documents. Pipe zone backfill shall be densified around
the pipe to the specified height over the top of the pipe. Regardless of the method of
densification used, backfill material shall be brought up at substantially the same rate
on both sides of the pipe. Care shall be taken not to float or displace the pipe before
backfilling is complete.
Trench backfill above the pipe zone shall not be placed until the compaction of
the pipe zone backfill and foundation are satisfactorily complete. To prevent damage
to the pipe, sufficient compacted backfill shall be placed over the pipe before allowing
any type of vehicle over it.
30 AWWA C604-06
passing a No. 4 sieve (4.75 mm) and not more than 5 percent passing a No. 200 sieve
(0.75 mm); (b) gravel is a reasonably uniform combination, containing no boulders
or stones larger than 3 in. (75 mm) and not containing excessive amounts of clay and
loam; (c) crushed rock is material with 100 percent passing a 3/4-in. (19 mm) sieve
and no more than 25 percent passing a No. 100 sieve.
The maximum backfill aggregate size for cementmortar coated pipe shall be 3-in.
(75 mm) minus. The maximum aggregate size for flexible coated pipe shall be 3/4-in.
(19 mm) minus.
3.7.2 Compaction. When special backfill compaction procedures are
required, they shall be accomplished in accordance with contract documents or
applicable federal, state or provincial, and local regulations.
3.7.3 Partial backfilling during testing. Newly installed pipelines are normally tested after backfilling. When unusual conditions require that pressure and
leakage testing be accomplished before completion of backfilling, or with pipe joints
accessible for examination, sufficient backfill material shall be placed over the pipe
barrel between the joints to prevent movement, and due consideration shall be given
to restraining thrust forces during testing. In particular, restrained-joint systems,
which derive their stability from the interaction of the pipe and soil, shall be
backfilled as necessary prior to testing.
Sec. 3.8
Flushing
Foreign material left in pipelines during installation can result in valve or
hydrant seat leakage during pressure tests. Every effort shall be made to keep lines
clean during installation. Thorough flushing is recommended prior to a pressure test;
flushing shall be accomplished by partially opening and closing valves several times
under expected line pressure, with flow velocities adequate to flush foreign material
out of the valves.
NOTE: Discharge shall be directed away from the pipe alignment so that
trench stability is not affected and shall be in accordance with federal, state, and local
point discharge requirements.
SECTION 4:
The main objective of a field hydrostatic pressure test (hydro test) is to check
the watertightness of joints, as each length of pipe is shop tested per contract
documents. The hydro test can be performed after backfilling is complete and at a
purchaser-specified pressure above the design working pressure of the line. Where
possible, bolted flexible joints should be left uncovered until the hydro test is
complete.
The line shall be filled slowly to prevent water hammer. The line shall be vented
and care shall be taken to ensure that all air in the line escapes during the filling
operation. Upon completion of filling with water, the line shall be pressurized to the
required test pressure and maintained for a minimum of 2 hr.
WARNING: The testing methods described in this section are specific for
water-pressure testing. These procedures shall not be applied for air-pressure testing because
of the serious safety hazards involved.
Sec. 4.1
32 AWWA C604-06
The allowable leakage rate for all pipelines in this standard shall not exceed 10 gal
per in. diameter per 24 hr per mi of pipe as measured by the makeup water required,
or shall not exceed the leakage rate specified in the contract documents.
NOTE: The air removal and test procedure above will expel most but not all air
from the pipeline. This section assumes some air will remain in the pipeline during
testing and provides for this condition.
4.1.5 Valve leakage. When testing against closed valves, an additional leakage
per closed valve of 0.0078 gal/hr/in. (1.2 mL/hr/mm) of nominal valve size shall be
allowed. Testing against existing valves is not recommended. When testing against
existing valves is necessary, some leakage can be expected and should not be the sole
basis for rejection.
4.1.6 Acceptance of installation. Acceptance shall be determined on the basis
of allowable leakage. If any test of laid pipe discloses leakage greater than that
specified, repairs or replacements shall be accomplished in accordance with the
contract documents.
4.1.6.1 All visible leaks shall be repaired regardless of the amount of leakage.
SECTION 5:
DISINFECTION
SECTION 6:
Sec. 6.1
Casing Pipe
When casing pipe is specified for highways or railroad crossings, the project
shall be completed in accordance with applicable federal, state or provincial, and local
regulations. In the case of railroad crossings, the project shall also comply with
regulations established by the railroad.
Sec. 6.2
Carrier Pipe
The casing pipe and other pipe appurtenances shall be a minimum of 8 in. (200
mm) larger than the outside diameter of the steel pipe bells to prevent damage during
installation and to prevent pipe-to-casing contact. Carrier pipe may be pushed or
pulled through the completed casing pipe. Spacers and/or insulator skids shall be
placed around the carrier pipe to ensure approximate centering within the casing pipe
and to prevent damage during installation or flotation. Care shall be exercised to
avoid metal-to-metal contact.
SECTION 7:
Sec. 7.1
SUBAQUEOUS CROSSINGS
Subaqueous Installations
When it is necessary to cross a body of water, the preferable practice is to
dewater the area and proceed according to the conventional pipeline construction
practices described in this standard. In the event the specification allows subaqueous
construction, the constructor is strongly advised to utilize an engineered system
specifically developed for the pipe, crossing depth, intended cover, and means
planned for such a crossing. The use of a restrained-type joint (welded or mechanical)
is recommended. However, the additional details necessary for subaqueous construction are not covered in this standard.
AWWA is the authoritative resource for knowledge, information and advocacy to improve the quality and supply
of water in North America and beyond. AWWA is the largest organization of water professionals in the world.
AWWA advances public health, safety and welfare by uniting the efforts of the full spectrum of the water community.
Through our collective strength we become better stewards of water for the greatest good of the
people and the environment.
1P-3.6M-43604-12/07-JP