Professional Documents
Culture Documents
Abstract
Due to rapid growth in urbanization there is tremendous pressure on industry to
deliver faster construction. In such situation, Pre-cast construction technology becomes a
popular choice. This technology has already addressed several issues like quality, durability and
safety during construction.
This paper presents Need of Precast concrete construction, Its Advantages and
disadvantages. Different joint connections (Beam-Beam, Beam-slab and column-column
connections) and tests conducted to know behaviour and strength of joints in multistory
buildings.
Page
CHAPTER 1
INTRODUCTION
There is a large shortage of housing for many millions in India and the increase in the
cost of construction is a big problem in overcoming this shortage. It is necessary to
develop a large variety of low cost options for different regions of India such that housing
becomes affordable for an ordinary citizen. The major cost increase in house built with
conventional technology is due to two factors viz.[1]
To reduce material consumption and to reduce labour component many cost reducing
system and techniques are required. The cost reduction in precast is very essential as it
forms a major part of the construction cost.
In pre-cast, substantial cost reduction is possible by:
In addition, it is also necessary to reduce the cost of other structural components like
walls, foundation, floor, lintels etc. A study on such options will be useful for reducing
cost of construction.
Page
Page
Page
(a)
(b)
Fig 1.2 : (a) Erection of Gypsum reinforced concrete wall panels construction
in IITM-2013, (b) Precast concrete structure at GVP college of Engg,
Vishakhapatnam during ICICPC-2013 conference.
Page
CHAPTER 2
CONNECTIONS
The structural integrity of precast concrete buildings depends mainly on the
connections between the precast structural components. A sequence of particular
construction causes joints in a structure. Connection can be between old and fresh
concrete and can be between two parts of a structure. Construction joints must be so
positioned that the strength of a completed member is not affected. The most suitable
place for a construction joint in a simple structure is where a bending moment is zero or a
shear force is maximum. A construction joint may be at the junction of a rib and slab of a
T-beam or a smaller beam at a short distance from the junction of intersecting beams.
Joints can also be possible where columns at different floors are to be integrated with slab
or beam construction.
In the completed building the structural connections will form an essential part of
the structural system. The structural response will depend on the behaviour and the
characteristics of the connections. The structural layout, the arrangement of stabilizing
units, the design of the structural system and the design and detailing of the connections
must be made consistently and with awareness of the intended structural behaviour. To
achieve a satisfactory design the designer should understand how the connections
influence the flow of forces through a structure under vertical and horizontal loads. The
main purpose of the structural connections is therefore to transfer forces between the
precast elements in order to enable the intended structural interaction when the system is
loaded. Precast concrete building structures are composed of some basic types of
structural systems. These systems can be combined in different ways to obtain an
appropriate and effective structural concept that fulfils the needs of specific buildings.
The most common systems are:
1. Beam to beam connection
2. Beam to column connection
3. Column to column connection
4. Column beam floor connection
5. Floor and roof system
DEPT OF CIVIL ENGINNERING, MSRIT BANGALORE
Page
Fig 2 : Different type of connections column to footing, column to column and column to
beam.
Page
Page
Fig.
2.2:
Beam
to
column connection
Page
Page
Page
Page
a floor system will not resist loads separately from each other, but a degree of
interaction between adjacent elements is desired. To obtain a transverse distribution
of load effects in case of concentrated loads and prevent uneven vertical
displacements at the longitudinal joints, the floor connections must be designed to
develop shear key action that ensures the interaction between adjacent elements. In
composite floor plate floors precast concrete floor plates are used as formwork for the
cast in-situ part and remain integrated in the composite floor section. Composite
action depends on the shear transfer in the horizontal joint between the precast plate
and the cast in-situ concrete part. There is no requirement for design of longitudinal
joint between the plates as the topping is continuous over the precast joint lines.
Page
The use of bolts is a simple way to establish a safe connection, but it generally
puts strict requirements on the tolerances. The bolts can be threaded rods or regular bolts.
Grouting at the site will to some extent depend upon the weather to be successful.
Generally the requirements on tolerances are not severe. When the result from a casting
operation is successful, a very sound connection is established. It also provides fire and
corrosion protection for the steel details.
Mix proportions, aggregate size and casting procedures will vary with the size,
location and orientation of the operation. Patches permanently exposed will often not be
acceptable. Anchoring the grout to relatively large steel surfaces is a problem that is often
overlooked. Large elements such as steel haunches can be wrapped with mesh or wire.
For recessed plates and similar elements headed studs or wiggled refractory anchors can
be welded to plate to provide anchorage for the grout. Gluing with epoxy or polyester is
very dependent upon weather conditions to be successful, especially temperature. Also
the workmanship is of great importance to secure a satisfactory result, like the mixing of
the ingredients and the preparatory cleaning and drying of the contact surfaces. Some
types of glued connections also put some requirements on tolerances. Most types of glue
loose most of their strength when heated to about 80 0C.
Welded connections will in most cases fit without any problems, but the quality of
the weld is totally dependent upon the skill of the welder. When welding outdoors the
welder must have extensive knowledge about what kind of electrodes to use under
different weather conditions on different material qualities, and of treatment of the
electrodes and materials prior to welding. Also the actual work may be difficult and
laborious to perform; like when fixing a small plate with only ladder access, with heavy
cables and no place to put the clamp. The heat generated when welding may also damage
the quality of the concrete close to the weld. Welded connections will in many cases have
to be fire protected.
Page
CHAPTER 3
Tests carried out:Beam-column connection:Types of Connections
FIG 3
Page
RESULTS
Various observations were made from the experimental investigations and are presented
in the following sections. The parameters considered for the present study are Ultimate
Load and Moment Carrying Capacity.
Table 1 Comparison of Experimental Yield and Ultimate Loads of the Specimens
Sl.no
1
2
specimen
Experimental
Yield
load(kn)
Upward
Downward
direction direction
8.8
9.40
6.5
8.62
ML
PC-TR
Experimental
load(kn)
Upward
direction
11.29
7.62
ultimate
Downward
direction
11.75
10.77
specimen
1
2
ML
PC-TR
Slab 1
Slab 2
Slab 3
Slab thickness(mm)
Reinforcement
fc'
50
6@250m
m c/c
39.02
50
6@165m
m c/c
37.06
63
6@200m
m c/c
38.38
fcu
44.82
43.93
43.33
28-day
strength(mpa
)
Page
Page
CHAPTER 4
Discussions and Observations
The construction of precast elements is easy simple and economical. The main
advantage of precast construction is time saving. This type of construction is lighter in
weight and provides better sound and thermal insulation to the buildings. It also ensures
rapid construction and eliminates the use of shuttering which are essentially required to
support slabs and beams in the conventional type of construction.
There is a general concern regarding the seismic performance of precast
construction. It is noticed that large panel construction performs better than frame system.
However, in areas of high seismic risk, structures must be designed to respond safely to
the dynamic forces imparted into the structure. Innovations in joint design are improving
the connection systems in precast concrete structures and making them increasingly
suitable for use in such areas. Connections should be carefully designed where the impact
or dynamic forces are much higher.
It is concluded that special Code provisions are required for seismic performance
of connections in precast concrete construction. More experimental studies are required
for a full scale precast concrete structure to understand the strength, deformation,
ductility, dissipation and damage of the structure. [3]
Page
REFERENCES
1. Mathur, G.C. (1993), Low Cost Housing in Developing Countries, Oxford & IBH
Publishing Co. Pvt. Ltd., New Delhi.
2. Behaviour of precast beam-column tie-rod Connection ,R. Vidjeapriya1 and K.P.
Jaya2
3. Seismic Safety of Joints in Precast Buildings A State-of-theart Literature Review
Ravikanth Chittiprolu & Ramancharla Pradeep Kumar Earthquake Engineering
Research Centre, IIIT Hyderabad.
4. Saddam m, Ahmedi, Umarani Gunasekaran, A Parametric Study of R.C Slab in
Beam-Column Connection Under Cyclic Loading.
5. Code of practice for precast concrete construction (2003).
Page