You are on page 1of 45

Carbon Capture and Storage (CCS):

Costs and Project Financing

RECS
June 9, 2015

Howard Herzog / MIT Energy Initiative

Topics
Types of cost estimates
Bottom-up
Top-down

Definitions of key metrics


Comparing costs across technologies
Estimates of CCS costs
Financing CCS Projects
BECCS
Howard Herzog / MIT Energy Initiative

Simplified View for the Use of


CCS Cost Estimates
Cost Estimates
CCS (and others)
Technology
Assessments

Policy
Assessments

R&D Priorities
Capital Investments
Marketing

Legislation
Regulation
Advocacy

Howard Herzog / MIT Energy Initiative

Bottom-up Cost Estimates


Limited number of public comprehensive,
independent engineering studies
Quite a few derivative studies

Howard Herzog / MIT Energy Initiative

Top-down Cost Estimates


Bottom-up estimates embedded
Usually need to translate estimates from
bottom-up studies
Multiple technologies each technology
may be from different sources no
guarantee they are on consistent basis

Howard Herzog / MIT Energy Initiative

Top-Down Cost Estimate


IPCC Special Report on CCS

Howard Herzog / MIT Energy Initiative

Levelized Cost of Electricity


Standard method used by utility industry
Costs are levelized throughout the plants
lifetime
It is calculated at the busbar (generating cost
only, excludes transmission and distribution)
The levelized cost is a breakeven cost (i.e.,
NPV=0) required to cover capital charges (debt
and equity) and operational charges (including
fuel costs)
Not a good metric to compare dispatchable to
non-dispatchable electricity sources
Howard Herzog / MIT Energy Initiative

Cost of Electricity (COE)

Graphic courtesy of
Ed Rubin

Howard Herzog / MIT Energy Initiative

Capture Cost vs. Avoided Cost


CO2 avoided can be looked at as net
amount of CO2 captured
CO2 avoided < CO2 captured

Cost = $/ton CO2

Avoided cost > Captured cost


For mitigation purposes (CCS), avoided cost is
used
For utilization purposes (CCUS), capture cost is
the better metric
Howard Herzog / MIT Energy Initiative

CO2 Captured vs. CO2 Avoided


a) Reference Plant (No Capture)

CO2 to
atmosphere

2884 x 10 6

7210

Btu/hr

Btu/kWh

Energy Penalty
(400-314)/400
21.5%

270 tonnes/hr
(0.674 kg/kWh)

400 MW

b) Capture Plant

CO2 to
atmosphere

2884 x 106

9173

Btu/hr

Btu/kWh

28 tonnes/hr
(0.088 kg/kWh)

314 MW

CO2
captured

242 tonnes/hr
(0.769 kg/kWh)

Howard Herzog / MIT Energy Initiative

CO2 Captured vs. CO2 Avoided


Emitted
Captured

Reference
Plant

CO2 avoided
CO2 captured

Capture
Plant

0.2

0.4

0.6

0.8

CO2 produced (kg/kWh)

Howard Herzog / MIT Energy Initiative

Tons Capture vs. Tons Avoided


Define
X = Emissions from reference plant
f = capture rate
Ep = Energy Penalty

Amount captured = f * X/(1- Ep)


Amount avoided = X - X/(1- Ep) * (1-f)
Tons captured / Tons avoided = 1/(1- Ep/f)
Howard Herzog / MIT Energy Initiative

Tons Capture vs. Tons Avoided

Howard Herzog / MIT Energy Initiative

Mitigation (Avoided) Costs


Mitigation Cost = $/tCO2 avoided
For power plants
($/MWhcap $/MWhref) / (tCO2/MWhcap tCO2/MWhref)

For other industries (i.e., FT Diesel)


($/bblcap - $/bblref) / (tCO2/bblcap - tCO2/bblref)

Requires specifying a reference plant this


can lead to widely varying results

Howard Herzog / MIT Energy Initiative

Mitigation Costs
COE (mills/kWh)

70
60
50
40
30

PC ($32 /tonne CO2 avoided)

20
10
0
0

0.2

0.4

0.6

CO2 Emissions (kg/kWh)

Howard Herzog / MIT Energy Initiative

0.8

Mitigation Costs
COE (mills/kWh)

70
60
50
40
30
IGCC ($18/tonne CO2 avoided)
PC ($32 /tonne CO2 avoided)
NGCC ($41 /tonne CO2 avoided)

20
10
0
0

0.2

0.4

0.6

CO2 Emissions (kg/kWh)

Howard Herzog / MIT Energy Initiative

0.8

Mitigation Costs
COE (mills/kWh)

70
60
50
40
30
IGCC ($18 to $77/tonne CO2 avoided)
PC ($32 to $128 /tonne CO2 avoided)
NGCC ($41 /tonne CO2 avoided)

20
10
0
0

0.2

0.4

0.6

CO2 Emissions (kg/kWh)

Howard Herzog / MIT Energy Initiative

0.8

CCS in a Mitigation Portfolio


Many users of CCS costs are also interested
in costs of other CO2 mitigation
technologies
An important use of CCS costs are to
compare them to the cost of other CO2
mitigation technologies

Howard Herzog / MIT Energy Initiative

Total Costs and Comparison to


Other Technologies
Mitigation costs are usually represented as $/tC or $/
tCO2
In theory,

Comparable to carbon price resulting from a carbon tax or a capand-trade system


Allows cost comparison across different technologies

However,
Even though same units, bases for the calculation can vary wildly
Most times they do not incorporate variability and uncertainty
Bias a concern - most people doing the cost estimates have a
vested interest in seeing their technology being successful

CO2 vs. C

100 t C = 370 t CO2


$100/t C = $27 t CO2
Howard Herzog / MIT Energy Initiative

McKinsey& Company
December 2007

Howard Herzog / MIT Energy Initiative

CCS Cost Components


Capture
Separation
Compression

Sequestration
Transport
Injection

Howard Herzog / MIT Energy Initiative

Elements of Capital Cost

From Toward a Common


Method
Howard Herzog / MIT Energy Initiative

Capital Cost Trends

PCCI Power Capital Costs Index (excluding nuclear) (IHS-CERA, 2014)


CEPCI Chemical Engineering Plant Cost Index (CE, 2014)
CPI US Consumer Price Index (BLS, 2015)
Howard Herzog / MIT Energy Initiative

Fuel Cost Trends for US Power Plants

Graphic courtesy of
Ed Rubin

Howard Herzog / MIT Energy Initiative

Elements of Storage Costs

Wide range in costs (factor of 10) result from:


Geology (depth, porosity, permeability, lithologic complexity)
Access (surface constraints, proximity to existing O&G locations)
Category: (land vs OS, oilfield, gasfield, depleted?, age?, available infrastructure?)

Lowest cost category may be least available (large onshore O&G field)
Confidence level needed for final investment decision
Major cost BEFORE Investment decision is exploration (seismic + drilling)
Major cost AFTER decision is well construction
Could be spread across operating lifetime for large storage site
Monitoring costs are relatively small

Main cost items to consider:

Characterization costs (seismic, appraisal wells), success rate


Size of reservoir compared to volume of CO2 to be stored
Number of wells injectivity, redundancy, monitoring, maintenance!
Intensity of MMV (seismic + wells)
Offshore structure surface or seabed
Cost of ownership, liability
Contingency

Howard Herzog / MIT Energy Initiative

2015 Cost Update


(J. Davison, H. Herzog, E. Rubin)
Compiled data from recent CCS cost studies in the
U.S. and Europe for new power plants with:
Post-combustion CO2 capture (SCPC and NGCC)
Pre-combustion CO2 capture (IGCC)
Oxy-combustion CO2 capture (SCPC)

Adjusted all costs to constant 2013 US dollars


Compared current cost estimates to SRCCS values

Howard Herzog / MIT Energy Initiative

Notes on Costs
Output high purity supercritical CO2
There is much variability in the cost
Process Variability plant location, coal type,
criteria emission levels, process integration, etc.
Economic Variability fuel costs, cost of capital,
material and labor costs, capacity factor, etc.

Transport Cost: 0 7 USD/tCO2


Geologic Storage Cost: 1 - 12 USD/tCO2
EOR Credit: 15 40 USD/tCO2
Howard Herzog / MIT Energy Initiative

Capture plus Geologic Storage


(Constant 2013 USD)
Fuel type

Coal

NG

Capture route

Post-combustion

Post-combustion

Total capital requirement reference plant (USD/kW)

2300 3000 (2600)

800 1400 (1050)

Total capital requirement capture plant (USD/kW)

4100 5300 (4600)

1400 2600 (2050)

58 91 (75)

76 121 (96)

61 - 79

42 - 83

LCOE capture plant (USD/MWh)

95 150

63 - 122

% increase LCOE

50 - 100

30 - 70

Energy penalty (%)

17 - 31

11.5 - 15

Cost of CO2 avoided (USD/tCO2)

50 - 100

60 - 140

% increase capital cost


LCOE reference plant (USD/MWh)

Howard Herzog / MIT Energy Initiative

Capture plus EOR


(Constant 2013 USD)
Fuel type

Coal

NG

Capture route

Post-combustion

Post-combustion

Total capital requirement reference plant (USD/kW)

2300 3000 (2600)

800 1400 (1050)

Total capital requirement capture plant (USD/kW)

4100 5300 (4600)

1400 2600 (2050)

58 91 (75)

76 121 (96)

LCOE reference plant (USD/MWh)

61 - 79

42 - 83

LCOE capture plant (USD/MWh)

61 - 121

48 - 112

% increase LCOE

0 - 60

10 - 60

Energy penalty (%)

17 - 31

11.5 - 15

Cost of CO2 avoided (USD/tCO2)

0 - 60

10 - 110

% increase capital cost

Howard Herzog / MIT Energy Initiative

The high parasitic energy load is a


significant factor in costs
Power
Capture
Capital
Power
Plant Technology Investment Output
PostSCPC
+38%
-21%
Combustion

$/kW
+75%

$/kW = 1.38/ (1-.21) = 1.75


Howard Herzog / MIT Energy Initiative

Demonstration Project Costs vs. Cost Studies


(FOAK from GCCSI 2011 update)
4

RESULTS AND COMPARATIVE SENSITIVITY ANALYSIS (CONTINUED)


Figure
4-1Installed
costs
550MW
net generation
CO2 capture
facility (FOAK)
Figure 4.1
Installed Costs
for for
550MW
Net Generation
and COand
Facility (FOAK)
2 Capture
Capital costs (US$/kW)

1,000

2,000

3,000

4,000

5,000

PC supercritical
Supercritical 2

RETROFIT

COST (in $/
kW)

Peterhead
(hydrogen from
natural gas)

2840

Antelope Valley
(coal-fired)

2392

AEP Mountaineer
(coal-fired)

2843

Longannet
(supercritical)

5835

Plant Barry

4375

Average

3657

GCCSI Estimate

Ultra-supercritical
Oxy-combustion supercritical
Oxy-combustion ultra-supercritical
Oxy-combustion ITM supercritical

~2000 + T&S

IGCC
NGCC

Region: United States

Without capture
With capture

Levelised cost of electricity


COAL-FIRED

COST (in $/

IGCC

Capital costs presented above, along with transportation and storage capital costs (based on
kW)
matching the captured CO2 flows), were used as inputs to the economic assessments. The
LCOEs for FOAK and NOAK plants are presented in tabular form in Table 4-1 and graphically in
Goldenbergwerk
Janschwalde
8065
Figure 4-2.
and cost of CO2
The cost parameters calculated from the LCOEs, the cost of CO
2 avoidedGasification
Sweeny
Kingsnorth
8330
captured (including transportation and storage), in the economic assessment are provided for
(supercritical)
FOAK and NOAK units in Table 4-2 and shown graphically forZeroGen
FOAK units in Figure 4-3.
avoided
and
captured
have
decreased
slightly since the 2009 report.
The
costs
of
LCOE
and
CO
2
Average
8189
This is likely to be a reflection of the revised fuel costs for thisTaylorville
update.
GCCSI Estimate
~4500 +T&S
Average

Howard Herzog / MIT Energy Initiative

GCCSI Estimate

COST (in $/
kW)
9091
6003
10616
5814
7881
~4600 + T&S

Major Demonstration Projects


Phase 1 Pioneer Projects (little/no govt
money)
Natural Gas Processing (4) Sleipner (Statoil),
In Salah (BP), Snovit (Statoil), Gorgon
(Chevron)
Synfuels - Weyborn (Dakota Gasification),
EOR driven
Major Pilots - Schwarze Pumpe (Vattenfall),
capture, no storage
Howard Herzog / MIT Energy Initiative

Sleipner (North Sea, Norway)

Howard Herzog / MIT Energy Initiative

Major Demonstration Projects


Phase 2 CCS RD&D Programs
Power Plants
Operating Boundary Dam (Canada)
Under Constuction Kemper (US), Petra Nova (US)
Planning TCEP (US), HECA (US), White Rose (UK),
Peterhead (UK)

Industrial Facilities
Operating - Air Products (US, Methane Reformer), ADM (US,
Ethanol)
Under Construction Quest (Canada, Methane Reformer),
Alberta Trunk Line (Canada, pipeline between refinery and
fertilizer plants to EOR)

Major Pilots Mongstad (Norway), capture, no storage


Howard Herzog / MIT Energy Initiative

Major Demonstration Projects


Role of EOR
Phase 2 CCS RD&D Programs
Power Plants
Operating Boundary Dam (Canada)
Under Constuction Kemper (US), Petra Nova (US)
Planning TCEP (US), HECA (US), White Rose (UK),
Peterhead (UK)

Industrial Facilities
Operating - Air Products (US, Methane Reformer), ADM
(US, Ethanol)
Under Construction Quest (Canada, Methane
Reformer), Alberta Trunk Line (Canada, pipeline
between refinery and fertilizer plants to EOR)
Howard Herzog / MIT Energy Initiative

Boundary Dam
Worldss first CCS Power Plant

Howard Herzog / MIT Energy Initiative

BOUNDARY DAM
140

120

CCS Capital Costs

100

Non-CCS Capital Costs

80

Fuel Costs
O&M Costs

60
40

Subsidies and Revenues

20

Net Costs
Null

0
BD Initial Federal
CO2
BD Final Base Load
CoE
Subsidy Revenues
CoE
NGCC

Source: Adapted from SaskPower

37

Levelized Cost of Electricity [$/MWh]

160

4 Reasons BD can compete with


NGCC:
1. Federal Subsidy
2. EOR (sulfuric acid and fly ash)
3. Low lignite costs compared to NG
4. Lower capital costs due to retrofit

Paying for CCS Projects


Markets

Carbon markets
Electricity markets
EOR
Others (e.g., polygeneration)

Government
Cost-sharing, Tax credits, etc.
Rationale
Encourage early action (before markets develop)
Help defray first-mover costs

Industry
Cost of doing business
RD&D Expense
Regulatory Compliance

Howard Herzog / MIT Energy Initiative

Paying for CCS Projects


Boundary Dam
Markets

Carbon markets
Electricity markets
EOR
Others (e.g., polygeneration)

Government
Cost-sharing, Tax credits, etc.
Rationale
Encourage early action (before markets develop)
Help defray first-mover costs

Industry
Cost of doing business
RD&D Expense
Regulatory Compliance

Howard Herzog / MIT Energy Initiative

Incentivizing CCS
US
Comprehensive Climate Policy
New Source Performance Standards
Clean Power Plan

CCS-Specific Mechanisms
Stimulus Money ($3.4 billion) expiring
Investment Tax Credit
Tax Credit for CO2 stored

Howard Herzog / MIT Energy Initiative

IPCC Working Group 3


Summary for Policy Makers
April, 2014
CCS mentioned 35 times
Key points:
CCS reduces costs of meeting key stabilization
targets (i.e., 450 and 550 ppm)
Strong call by IPCC for negative emissions by
BECCS (bio-CCS)
Without CCS, certain targets cannot be met
(due in part to CCS role in negative emissions)
Howard Herzog / MIT Energy Initiative

BECCS Ampere Study


450 ppm case

Howard Herzog / MIT Energy Initiative

BECCS
Without CCS, there will be no BECCS
Cost of BECCS > CCS
At high enough C price, may reverse

Issues with storage are identical

Why did IPCC highlight BECCS


Without negative emissions, 450 ppm (2 degree
C) scenarios are hard to justify
BECCS is basically an accounting trick to keep
the 2 degree C aspirations alive
Howard Herzog / MIT Energy Initiative

Contact Information
Howard Herzog
Senior Research Engineer
Massachusetts Institute of Technology (MIT)
Energy Initiative
Room E19-370L
Cambridge, MA 02139
Phone: 617-253-0688
E-mail: hjherzog@mit.edu
Web Site: sequestration.mit.edu

Howard Herzog / MIT Energy Initiative

Bibliography
Toward a Common Method of Cost Estimation For CO2 Capture and
Storage at Fossil Fuel Power Plants: A White Paper, prepared by the
CCS Costing Methods Task Force: Ed Rubin (Carnegie Mellon
University), George Booras (EPRI), John Davison (IEAGHG), Clas
Ekstrom (Vattenfall), Mike Matuszewski (USDOE/ NETL), Sean
McCoy (IEA), and Chris Short (GCCSI)
http://www.epri.com/abstracts/Pages/ProductAbstract.aspx?
ProductId=000000003002000176

John Davison, Howard Herzog, Edward Rubin, The Cost of CO2


Capture and Storage, International Journal of Greenhouse Gas
Control (2015).
In press

Clark, V. "An analysis of how climate policies and the threat of


stranded fossil fuel assets incentivize CCS deployment," M.I.T.
Masters Thesis, May (2015).
http://sequestration.mit.edu/pdf/2015_VictoriaClark_Thesis.pdf
Howard Herzog / MIT Energy Initiative

You might also like