You are on page 1of 2

PROPOSED TWO-STOREY JAIME HILARIO INTEGRATED SCHOOL - LA

SALLE
DIVISION
1 - GENERAL REQUIREMENTS
SECTION
01 71 23 - FIELD ENGINEERING
May 2013

Project :
Location :

Proposed Two-Storey Jaime Hilario Integrated School - La Salle


Banawang, Bagac, Bataan

DIVISION

SECTION 01 71 23

GENERAL REQUIREMENTS
-

Field Engineering

1.01 SERVICES OF LICENSED SURVEYOR


A.

Contractor shall pay for services of a licensed surveyor who shall fully and
completely layout all work required by the Contract.

B.

The Contractor shall furnish certifications from a licensed surveyor that all
portions of the work are located in accordance with Contract Requirements
and at elevations required thereby.

C.

The licensed surveyor shall


1.

Identify and locate existing control points, boundary lines, property lines,
corner stakes indicated on the drawings before starting work. Promptly
notify Project Representative of any discrepancies within twenty-four (24)
hours of discovery of same.

2.

Promptly verify and certify to lines and levels of any portion of subdivision
of work at any time it may be deemed necessary by the Project
Representative. Any deviation from the Drawings shall be certified to the
Project Representative within 24 hours of discovery of same.

3.

Locate and protect control points before starting work and preserve all
permanent reference points during construction.
a.
b.
c.

Make no changes or re-locations without prior written notice to Project


Representative.
Report to Architect when any reference point is lost or destroyed, or
requires relocation because of necessary changes in grades or other
reasons.
Replace project control points which may be lost or destroyed based
on original survey control.

Field Engineering
01 71 23
of 2

Page

PROPOSED TWO-STOREY JAIME HILARIO INTEGRATED SCHOOL - LA


SALLE
DIVISION
1 - GENERAL REQUIREMENTS
SECTION
01 71 23 - FIELD ENGINEERING
May 2013
4.

Establish a minimum of two permanent benchmarks on site, referenced to


data established by survey control points.
Record locations, with
horizontal and vertical data, on project record documents.

5.

Establish lines and levels.


similar appropriate means:

6.

Locate and layout, by instrumen tation and

a.

Site improvements:
- Pavements
- Stakes for grading, fill and topsoil placement.
- Utility slopes and invert elevations.

b.

Grid or axis for structures.

c.

Building foundation, column locations and floor levels.

d.

Controlling lines and levels required for mechanical and electrical


trades.

Periodically verify layouts.

1.02 STATUS OF SURVEYOR


The Surveyor selected for the purpose shall be subject to the Project
Representatives approval. He shall not be a regular employee of the Contractor,
nor shall he have any interest in the Contract. He shall not be employed by the
Contractor in laying out any work, it being intended that surveyors certification
shall present an independent and disinterested verification of such layout.
1.03 FINAL CERTIFICATION
Final certification shall be submitted upon completion of work, or upon completion
of any section of work, if required by the Project Representative, and before final
payment is made. Any exception or deviations from the Drawings shall be noted
on final certificate, and there shall be included any map, plot, note, and the like
necessary in the opinion of Architect to constitute a full and complete report.
End of Section 01 71 23