Professional Documents
Culture Documents
This analysis based report is done for the readers of my previous report 1MW
Utility Scale SPV Power Plant, mainly for the readers from South region of
INDIA as they are asking repeatedly about the probability and feasibilitytechnical & Financial-of a SPV power plant in their region. At the same time
its not possible for me to design a report for each and every state from
South India, so I took Chennai city. Also the previous report was not so
detail, was very basic and meant to the readers who want to get an
overview on how a utility scale power plant works. Now, in this report, I
discuss about in depth. From panels selection to CB sizing all are presented
in very detail. Hope, this time you get a strong knowledge on designing and
estimation of 1MW solar PV power plant. Unlike the previous report, the
financial aspect discussed at the end of the paper. In this paper, the
financial assessment has done in very detail and considering the current
scenario of SPV market including the cost of solar PV modules, inverters
cost, cable, transformer etc.
prices
and
the
funding,
interest
rate..
Disclaimer
The presented data here are NOT TAKEN from any copyright materials and
not showing under my name. The meteo data collected from NASA website
and NREL database which is free over the internet. Designing of PV system
is totally based on the practical experience of the author.
Page
1
www.renewpowerzo
ne.in
Page
2
Site consideration: this design has been done by considering the PV modules &
array will be
0
ground-mounted and the site-elevation angle taken 3 .
Cost Estimation: 1MW Solar PV power plant cost estimation has done
considering the current PV market scenario (Sept-Dec 2013), so after few
months the cost may vary according the market.
CAD design & layout: I have not uploaded/attached the CAD design. If
anybody interested in setting up the plant then only contact at the given email ids to get the design file.
Transmission & wheeling losses: Here, in this report, while doing the
technical assessment, the distance from nearest substation to the 1MW
solar PV power plant taken within 1.5 KM and so the wheeling losses
considered as 3% of total power transmission. And in the financial
assessment, no wheeling charges have been considered.
Design Criteria: While designing & estimating the technical components
& solutions, all the required/applicable standard design codes have been
considered. Mainly the IEC (International Electrotechnical Commission)
Codes, IS codes from BIS have been considered thoroughly.
Contents
1) Introduction
2) Project details
3) Location metrological details
4) Determination of optimum tilt angle
5) Solar power plant overview
6) Module selection & sizing
7) Inverter selection & sizing
8) Transformer selection
9) Other protective devices including switch gear details
10)
selection
11)
details
12)
analysis & simulation
13)
project
14)
maintenance structure of the plant
15)
calculation, estimation of NCF, Payback period
16)
selection of various components
4
5
6
7
8
9
11
12
13
Cable sizing &
14
Civil works
16
Performance
17
Timeline of the
21
Operation &
22
Financial
23
Guide on
27
PROJECT AT A GLANCE
1.
2.
Regd. Office.
:
: SRIKAKULAM DIST
3. Works.
SRIKAKULAM Dist.
4.
Line of Activity.
5.
Sector.
Large Scale
6.
Constitution.
Private Limited
7.
Lacs)
PROJECT COST
8. Promoters Contribution.
9. Debt/Equity.
10. Installed Capacity.
AMOUNT
MEANS OF FINANCE
709.00 Capital:
80.00 Bridge loan from
Bank(10% on project)
8.0 Term loan from NRI
0
805.00
TOTAL
: 10.00%
4:1
: 1 MW
A
M
O
U
N
T
80.50
80.50
644.00
805.00
The above said project is in the process of setting up a 1 MW Solar PV project in the prestigious Solar
Project at Srikakulam Dist.
Location:
Village
Distric
t
State
Latitud
e
Longit
ude
Solar
Project
plots
Srikakulam
Andhra Pradesh
xxx
Sailent Features:
Project capacity
Earmarked Land
Technology
Solar Irradiation (GHI)
CUF
Performance Ratio
Annual Energy Generation
Rating of Photovoltaic Modules
No. of Modules required
Quantity of Water required to wash modules per day
1 MW
5 Acres
Crystalline Silicon / Thin
Film Modules
5.7 kWh/m2/Day
20%
80%
1.76 BU
250 Watt
400, 000
80000 Ltrs
Wash Cycle
Size of Invertors
No of Invertors
Evacuation
Power evacuation upto 500 MW
Power evacuation beyond 500 MW
15 days
500 KW
200
11/66 kV Line
220 kV Substation
400 k V Substation
adoption, but perhaps the biggest factor has been need. India, "as a growing economy
with a surging middle class, is now facing a severe electricity deficit that often runs
between 10% and 13% of daily need". India is planning to install the World's largest Solar
Power Plant with 4,000 MW Capacity near Sambhar Lake inRajasthan.
There are various factors that we need to consider before investing into a solar power
plant. A lot of enthusiasm has been seen among people about the use of Solar Energy as a
substitute of conventional sources of energy. However, currently, with the power subsidies
in India, solar works economical only in those areas that are using diesel generators as a
primary source of electricity. The entire payback is made in 23 years. Solar system for
petrol pumps is a leading example of such an application. IOCL is leading the race for
solarization of petrol pumps with aggressive targets. Solar applications for petrol pumps
by RelyOn Solar has been installed in more than 150 IOCL petrol pumps across India and
now other oil companies are also looking to solarize their ROs. Solar installations for
commercial buildings, where the electricity rates are higher, are also proving to be a game
changer for the owners of IT companies.
On 16 May 2011, Indias first 5 MW of installed capacity solar power project was registered
under the Clean Development Mechanism. The project is in Sivagangai
Village,Sivaganga district, Tamil Nadu.
Current status
Installed solar PV
Year
2010
161
2011
461
2012
1,205
2013
2,319
2014
2,632
2015
3,744
With about 300 clear, sunny days in a year, India's theoretical solar power reception, on
only its land area, is about 5,000 trillionkilowatt-hours (kWh) per year (or 5 EWh/yr). The
daily average solar energy incident over India varies from 4 to 7 kWh/m 2 with about
1,5002,000 sunshine hours per year (depending upon location), which is far more than
current total energy consumption. For example, assuming the efficiency of PV modules
were as low as 10%, this would still be a thousand times greater than the domestic
electricity demand projected for 2015.
The amount of solar energy produced in India in 2007 was less than 1% of the total energy
demand. The grid-connected solar power as of December 2010 was merely 10 MW
Government-funded solar energy in India only accounted for approximately 6.4 MW-yrs of
power as of 2005. However, India is ranked number one in terms of solar energy
production per watt installed, with an insolation of 1,700 to 1,900 kilowatt hours per
kilowatt peak (kWh/KWp). 25.1 MW was added in 2010 and 468.3 MW in 2011. By end
March 2015, the installed grid connected solar power capacity is 3,744 MW, and India
expects to install an additional 10,000 MW by 2017, and a total of 100,000 MW by 2022.
India's largest photovoltaic (PV) power plants
Name of Plant
DC
Peak
Power
(MW)
GWh
/year[1
8]
Capac
ity
factor
Notes
DonBosco,Kurla, Omega
Natural Polarity (ONP) Mumbai- 0.1
Maharashtra
Commissioned
December 2014
221
Commissioned April
2012
151
Commissioned
February 2014
125
Commissioned March
2013
50
Commissioned 2014
50
Commissioned March,
2014
50
Commissioned March
2013
Name of Plant
DC
Peak
Power
(MW)
48
Commissioned 2014
40
Commissioned January
2012
40
Commissioned in April
2012
30
Commissioned October
2011
25
Commissioned 25
January 2012
20
Commissioned 2014
15
Commissioned 2014
10
Commissioned 2011
10
Commissioned 2014
GWh
/year[1
8]
Capac
ity
factor
Notes
Name of Plant
DC
Peak
Power
(MW)
10
Commissioned 2011
10
Commissioned June
2011, 63 acres, using
36,000 Suntech Power
panels.[31]
10
Commissioned
November 2011
10
Commissioned
December 2011
Commissioned 2012
Commissioned 2011
Commissioned 2011
Completed in January
2012
Completed December
2010
GWh
/year[1
8]
Capac
ity
factor
Notes
Name of Plant
DC
Peak
Power
(MW)
Commissioned October
2011
Commissioned 2011
Commissioned 2011
Commissioned 2011
Commissioned 2011
Commissioned 26
September 2011
Itnal Photovoltaic
Plant, Belgaum, Karnataka
Tata
Power - Mulshi, Maharashtra
Commissioned April
2011
August 2014
GWh
/year[1
8]
Capac
ity
factor
Notes
DC
Peak
Power
(MW)
Name of Plant
GWh
/year[1
8]
Capac
ity
factor
Notes
December 2009
August 2009
Commissioned January
2012
1.5
Commissioned 2013
M G M Minerals - Odisha
Commissioned 2010
Commissioned 2011
Commissioned 2011
Commissioned March
2012
21 January 2011
[32][43]
Name of Plant
DC
Peak
Power
(MW)
GWh
/year[1
8]
Capac
ity
factor
Notes
Gujarat
2010
Commissioned
February 2012
Completed in
December 2011
Commissioned 1
August 2011
Urja Global
Limited - Jharkhand, Delhi
Commissioned 1
August 2012
April 2010
Commissioned January
2012
0.8
Commissioned 15
Name of Plant
DC
Peak
Power
(MW)
GWh
/year[1
8]
Capac
ity
factor
Notes
- Narnaul, Haryana
State
MWp
Andhra Pradesh
127.85
4.00
Chhattisgarh
4.0
0.30
Delhi
2.5
0.19
Gujarat
654.8
49.90
Haryana
7.8
0.59
Jharkhand
4.0
0.30
Karnataka
9.0
0.69
Madhya Pradesh
132.0
9.15
Maharashtra
20.0
1.38
Ref
State
MWp
Odisha
13.0
0.99
Punjab
9.0
0.69
Rajasthan
510.25
38.89
Tamil Nadu
15.0
1.14
Telangana
1.0
0.08
Uttar Pradesh
12.0
0.91
Uttarakhand
5.0
0.38
West Bengal
2.0
0.15
Total
1442.10
100
Ref
[59]
[17][60]
With a view to make Gandhinagar a solar city, the State government has launched a rooftop solar power generation scheme. Under this scheme, the State plans to generate five
megawatt of solar power by putting solar panels on about 50 state government buildings
and on 500 private buildings. The State has also a plan to emulate this project
in Rajkot,Surat, Bhavnagar and Vadodara in 2012-13.
The State plans to generate solar power by putting solar panels on the Narmada canal
branches. As a part of this scheme, the State has already commissioned a one megawatt
solar plant on a branch of the Narmada Canal near Chandrasan area of Anand taluka. This
also helps by stopping 90,000 liter water/year of the Narmada river from evaporating.
Solar PV water pumping systems are used for irrigation and drinking water. The majority of
the pumps are fitted with a 2003,000 watt motor that are powered with 1,800 Wp PV
array which can deliver about 140,000 litres (37,000 US gal) of water per day from a total
head of 10 metres (33 ft). By 30 September 2006, a total of 7,068 solar PV water pumping
systems had been installed, and by March 2012, 7,771 had been installed.
Solar driers are used to dry harvests before storage.
Solar water heaters
Bangalore has the largest deployment of roof top solar water heaters in India. These
heaters generate an energy equivalent of 200 MW.
Bangalore is also the first city in the country to put in place an incentive mechanism by
providing a rebate of 50 (79 US) on monthly electricity bills for residents using roof-top
thermal systems. These systems are now mandatory for all new structures.
Pune has also recently made installation of solar water heaters in new buildings
mandatory.
Price history of silicon PV cells since 1977. The great thing about solar power is that it is a
technology and not a fuel. It is unlimited and the more it is deployed the cheaper it would
be. While the more limited fossil fuels are used, the more expensive they become.
Land is a scarce resource in India and per capita land availability is low. Dedication of land
area for exclusive installation of solar arrays might have to compete with other necessities
that require land. The amount of land required for utility-scale solar power plants
currently approximately 1 km2 (250 acres) for every 2060 MW generated could pose a
strain on India's available land resource. The architecture more suitable for most of India
would be a highly distributed set of individual rooftop power generation systems, all
connected via a local grid. However, erecting such an infrastructure, which does not enjoy
the economies of scale possible in mass, utility-scale, solar panel deployment, needs the
market price of solar technology deployment to substantially decline, so that it attracts
the individual and average family size household consumer. That might be possible in the
future, because PV is projected to continue its current cost reductions for the next decades
and be able to compete with fossil fuel. Government can provide subsidies for the
production of PV panels, in which there will be reduction in the market price and this can
lead to more usage of solar power in India. In the past three years, solar-generation costs
here have dropped from around 18 (29 US) a kWh to about 7 (11 US) a kWh, whereas
power from imported coal and domestically-produced natural gas currently costs around
4.5 (7.1 US) a kWh and it is increasing with time. Experts believe that ultra mega solar
power plants like the upcoming worlds largest 4,000 MW UMPP in Rajasthan, would be
able to produce power for around 5 (7.9 US) a kWh.
Some noted think-tanks recommend that India should adopt a policy of developing solar
power as a dominant component of the renewable energy mix, since being adensely
populated region in the sunny tropical belt, the subcontinent has the ideal combination of
both high solar insolation and therefore a big potential consumer base density. In one of
the analysed scenarios, India can make renewable resources such as solar the backbone
of its economy by 2050, reining in its long-term carbon emissions without compromising
its economic growth potential.
Government support
Total
Capacit
y
2010
161
2011
461
300
2012
1,205
744
2013
2,319
1,114
Yearly
Installation
March-2014
2,632
313
March-2015
3,744
1112
India is densely populated and has high solar insolation, an ideal combination for using
solar power in India. India is already a leader in wind power generation. In the solar
energy sector, some large projects have been proposed, and a 35,000 km2 area of the
Thar Desert has been set aside for solar power projects, sufficient to generate 700 GW to
2,100 GW. Also India's Ministry of New and Renewable Energy has released the JNNSM
Phase 2 Draft Policy, by which the Government aims to install 10GW of Solar Power and of
this 10 GW target, 4 GW would fall under the central scheme and the remaining 6 GW
under various State specific schemes.
The Electricity Act, 2003, paves way for an innovative approach to solve our countrys
power problems. It has paved the way for a competitive environment; open access to
existing transmission and distribution network to transmit electricity across regions; delicensing of generation, captive power and dedicated transmission lines; licensing of
distribution and supply companies and the restructuring of State Electricity Boards.
The Ministry of Power has mandated to promote cogeneration and renewable sources for
Power generation under Nodal agencies and hence it will play a major role in
mainstreaming renewable energy sector. The advantage or renewable resources includes
their capacity to produce energy without producing carbon-based warming and polluting
agents into the atmosphere. The financial cost of its applications is not always cheap but
if the environmental costs of using fossil are accounted for, renewable energy wins handsdown. There are also indirect savings on health and its costs as there are no harmful
emissions.
In the above backdrop, YOUR COMPANY NAME has decided to set up a 1/1000 MW/KW
Solar Power Plant. This Detailed Project Report (DPR) brings out all technical details and
overall costs justifying the selection of the project. The total power generation is
envisaged to be 1050KW from Solar Photovoltaic Cell. It is a very important document
that is required for Environmental Impact Assessment (EIA) studies, fixation of tariff,
finalizing Power Purchase Agreement (PPA) and also for submission to Financial Institutions
for obtaining project funding. The total project cost is expected to be RS. 709.00 Lakhs
and the average cost of generation is expected to be Rs. 7.5/kWh (ASSUMED).
rd
For this project, poly-crystalline technology based 3 generation Solar PV modules will be
used. Along with this, highly efficient, photon-tested string inverters going to be
integrated to the system. These technologies are the best in the industry. So, Its clear
that our project is not compromising with the quality of the materials and or the
components which obviously led this project to success.
Client details
Country
India
Location
SRIKAKULAM DIST
Contact id
ABC@XYZ.COM
Contact Person
company
ABCXYZ
Purpose
Power generation
& distribution to State
utility grid
Project Details
10.5, 78.5
(assumed)
28.
5
27.
2
72.5%
25.
5
5.19
2
KWh/m /day
100.1 kPA
Ma
x
29.
6
abc
2.7 m/s
Aver
age
28.
8
10m
Mi
n
26.
4
Type of
installation
Estimated
array
peak
power
Shading
consideration
Grid voltage
Phase
connection
Grid
frequency
Available/require
d area
Safety level
Site Location/Layout
Groundmounted
1100KWp
Shade-free
11KV
3-phase
50Hz
20000
2
m (apprx)
IP65
Solar Irradiation
KWh/m2/day
7
6
5
Solar Irradiation
4
3
2
1
0
31
30
29
28
27
26
25
24
23
Air temperature
earth temperature
Feb
26
Mar
13
Apr
0
Ma
11
Jun
14
Jul
12
Au
5
Sep
6
Oct
19
No
29
Dec
35
Spring/Autumn
Summer
80 angle
56 angle
104 angle
On the 21st December, the sun will rise 87 east of due south and set 87 west of due south.
On the 21st March/21st September, the sun will rise 91 east of due south and set 91 west of due sou
On the 21st June, the sun will rise 95 east of due south and set 95 west of due south.
10
5.04
5.98
6.51
5.76
5.78
5.28
4.99
5.09
5.33
4.67
4.27
4.5
5.26
25
5.35
6.16
6.41
5.39
5.65
5.22
4.9
4.9
5.14
4.69
4.44
4.78
5.25
12
5.41
6.16
6.52
5.85
5.78
5.29
4.99
5.1
5.34
4.71
4.45
4.84
5.36
* Here, 12 angle at AM1.5 has been chosen as fixed south faced model for the project
1082KWp
206
Series
20KW MPPT based 3 phase string
Inverter
MPPT & Transformer Less
53
4/1
Modular Components
Components
Specification
Max Peak
Power=250Wp
Voc= 36V ;Vmp=
29V Isc= 9.25A ;
Non-Modular Components
Solar PV
modules
Components
Inverters
Transformer
SCADA/Moni
toring
System
Circuit Breaker
DC Disconnect
Switch Gear
Distribution
Panel
Isolator
Cables
Electrical
Specification
20KW, 3Phase &MPPT;
Vmax= 800V
1250KVA
Integrated with
Remote Monitoring
system to
web
based
Inverter
Busbar=
46A 3p;
busbar/Panel box to
transformer=
1600A
1000V,20Amps
Quanti
ty
4326
Make
Quanti
ty
53
Make
1
1
53
1
206
Rated voltage=12KV;
Rated main
busbar
current(Max)=1
250A;
SC
NAwithstand capacity
Vmax= 12KV;
Max cont.
2
DC Side= 10 mm
AC Side=LT:
2
16mm & HT:
2
185mm
250Wp
VOC
37.20V
VMPP
30.10V
ISC
8.87A
IMPP
8.30A
15%
Module
Efficiency/modu
le
areaTolerance
Power
2%
Technology
Si-Poly
No. of cells
60 cells in series
-0.07 0.01
Temp.
Co-Eff. Of Pmax
o
(%/ C)
Temp. Co-Eff. Of Voc
-0.43 0.05
0.065 0.05
15A
0
(-10 to 60) C
5500PA
2500PA
-0.34 0.05
15A
249.8.2W
37.2V
30.1V
8.87A
8.31A
15.54%
0
-0.43%/ C
200.6 W
36.8 V
30.2 V
6.64A
7.10A
15.32%
0
-0.43%/ C
@ 400 W/m
100.00
35.8V
30.1V
3.55A
3.33A
15.27%
0
-0.44%/ C
At Avg. Ambient
1100 KWp
1082KWp
250Wp
4326
1100KWp
1100KWp
263Wp
4326
206
21
206
21
Series
609V
8.87A/8.3A
Parallel
780V/635V
1830A/1710A
Series
630V
9.51A/8.82A
Parallel
750V/620V
1960A/1816A
www.renewpowerzo
ne.in
Page
10
INPUT (DC)
Max. Power
Max absolute Input Voltage
Start Voltage
Nominal MPP voltage range
Max Input Current per string
Nos. of Independent MPP
inputs/strings per MPP inputs
23KW
1000V
350V
490V-800V
41.5A
1/6
OUTPUT (AC)
20000W
20000VA
20W
3/N/PE;230/460V
50Hz
3x29A
1
3/3
98.7%
Protection Details
DC Disconnect
DC Surge Arrester
Protection Class
Total harmonic distortion
Operating Temperature range
Noise Emission
Self Consumption
Cooling option
Protection type
Remote Monitoring System
User Interference &
Communication
Electrically Isolated relay output
Status Display
Inverter to inverter
communication
Anti-islanding
protection
Inverter connection details
Available
Available
I (as per IEC 62103)
53
4
Parallel
Parallel into Cu busbar
Provided
<1.8%
-25 -60 C
<35dB
<25W
Forced Air-cooled
IP65 (as per En 60529)
With RS-485/Ethernet
Available
Available
Available
Available
Transformer Sizing
Design Criteria
Transformer type
Cooling type
Rated KVA
High Voltage rating
Low Voltage Rating
Nominal impedance
Impedance tolerance
Nominal secondary amps
Max SC withstand current
HV connection
LV connection
Operating frequency
Tap changer
IS-2026 / IEC-60076
Power transformer, core type with oil0
immersed ; 65 C winding temp rise
ONAN(Oil Natural Air Natural)
1250KVA
11000V
460V
4.7%
7.5%
1250A
20KA/3s
DELTA
Wye
50Hz
5% of full load capacity
Protective devices
components
Specification
Quantity
DC Disconnects
206
Switch gear
Circuit breakers
(MCCB)
(NOT required if Inverter
has inbuilt protection)
busbar/Panel box to
transformer= A 3p;
53
1
IS-9921/IEC129
50hz 3%
11KV
Max system
voltage
12KV
Max continuous
current
Rated SC current
for 3s
2500A
40KA
Rated peak
withstand
currentmicro
(KA sec
1.2/50
lighting withstand
Volts (KV peak)
Rated 1 minute
power
frequency
withstand
No.
of poles
63.5KA
Min creepage
distance
320mm
To earth
and
isolating
poles
Across the
isolating
distances
170
195
To earth
and
isolating
Across the
isolating
distances
75
85
www.renewpowerzo
ne.in
Page
12
Cable Sizing
DC Side Cables (strings to inverter)
Design criteria
Cable material
Single cable length per string to
inverter
Cross
section per string
Voltage drop
Relative power loss reference to
power temp.
Max DC
withstand
Normal
condition
0
90 C
2KA/1sec
Stranded
PVC
IEC-60502
Al
25 ft
2
L1
L2
L3
185mm
1.37V
1.37V
1.37V
0.57%
11KV(UE), heavy duty
26KA @1s
XLPE
www.renewpowerzo
ne.in
Page
13
Line Losses
Total cable
Cable cross
section
Power loss @
nominal
operation
Relative power
loss @ nominal
operation
DC Side
AC Side
Total
8120 ft
2
4 mm
35 KW
3070 ft
2
16 mm +185
2
mm
5 KW
11180 ft
2
2
4 mm +16 mm
+185
2
mm
40KW
0.07%
0.76%
0.83%
Main busbar
Busbar insulation
Al alloy
E91 E
gradeinsulated
Fully
Busbar length
Earthing bus materials
Auxilury
busbar
Copper
Main
Aux
3.5mt
0.75mt x 52
GS (IEEE std. 80/IEC-604391)
IEEE Standard-80
Grounding System
Earth grid
resistance
Placing of
earth
electrode
Less than 10
ohm
Earth Pit
www.renewpowerzo
ne.in
Page
14
CIVIL WORKS
Live Loads estimation of control room + admin
building
(as per IS 875:1987)
parameter
details
Remarks
2
Roof load
1750 kg/ m
Ground floor
Control
18000kg/
load
Office
5000kg/
2
Piping
50 kg/ m
2
Electrical +
26 kg/ m
Seismic
loaddrainage
Roof
As per IS-456
As per IS-456
IS-456
As per IS-456
As per IS-456
As per IS-456
Roof drain
6
heads
Construction
details
Interwall
Cement :
1:6
Interwall
230mm
thickness
Parapet walls
Cement :
1:4
thickness
115mm
Steel
work
5 acres
www.renewpowerzo
ne.in
Page
18
www.renewpowerzo
ne.in
Page
19
Design
Land
acquisit
ion
Power Purchase Agreement(PPA) with private power purchaser need to be finalized at a feasible rate.
Required time is 15 working days
PPA
DPR
Preparation of Detailed Project Report including technical feasibility of the project prepared.
Time required 6 working days.
Arrangement of finance/fund for the project from nationalized or private financing agency with
significant interest rate and equity share will be finalized.
Required time for this stage is 1 month.
finance
After finalizing PPA and arrangement of fund for the project, procurement work starts including
preparation & finalizing of vendor selection, BOM, BOQ, order placing, follow-ups of delivery to
site/warehouse.
procurem Estimated time for this step is 1 month.
ent
After the processing of procurement, first civil construction at the site starts for PV mounting structure
set-up and
control-room, administrative building. Finishing the civil works, PV installation & all electrical
constru
construction works including the Grid Evacuation will be processed.
n Estimated time for this whole work is 2 months.
ctio
commis
sio
ing
www.renewpowerzo
ne.in
Page
20
Commissioning of
the plant by
authorized govt.
body or certified
3rd party will be
done followed by
Completion of
project
execution.
required time for this
step is 6 working days.
www.renewpowerzo
ne.in
Page
21
operation
manager
Plant manager
maintenance
Engineer (Mech)
Maintenance
engineer(E&IE)
Technician1
Technician2
skilled labour1
skilled labour2
control room
technician
Skilled labour1
Supply chain
executive
skilled labour2
Accounts
executive
Components/services
6.
7.
8.
9.
SCADA/RMS
Project execution &
Construction works
Grid evacuation
Solar PV modules
Solar inverters
Transformer
Protective devices
Wires/Cables
Total
cost
(in
45,100,000
11,660,000
2,940,000
1,200,000
1,000,000
1,000,000
2,000,000
4,000,000
1,000,000
(assumed)
10.
1,000,000
Remarks
41rs/Watt peak
11rs/Watt peak
From international
From international
vendor
Considering
IEC
codes & ISO
certified
Assumed because of
having no sufficient
data
Subject
to change
as per rules
70,900,000 INR
Total expenses over the year for plant O&M and staffing = 2,000,000
This expense is considered for regular maintenance cleaning of PV array,
checking the status of inverter, cable-fault checking, emergency
maintenance & replacement of components and annual salaries of O&M
team of the plant.
Loan Interest rate is @12% over 70% of total project cost which shall be
completed within next 7 years (the rest 30% as equity shares).
Estimated time period
Total Loan amount
Interest rate
EMI
Monthly interest
total Interest paid
7 years
49,630,000
12%
876,110
285,270
23,962,830
10 years
49,630,000
12%
712,050
298,460
35,815,600
Installme
nts
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
EMI
0
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
Monthly
principle
0
379,80
5
383,60
3
387,43
9
391,31
4
395,22
7
399,17
9
403,17
1
407,20
3
411,27
5
415,38
7
419,54
1
423,73
7
427,97
4
432,25
4
436,57
6
440,94
2
445,35
1
449,80
5
454,30
3
458,84
6
463,43
4
468,06
9
472,74
9
477,47
7
482,25
2
487,07
4
491,94
5
496,86
4
501,83
3
506,85
1
511,92
0
517,03
9
522,21
0
527,43
2
532,70
6
538,03
3
543,41
3
548,84
7
554,33
6
Monthly
Interest
0
496,30
0
492,50
2
488,66
6
484,79
2
480,87
8
476,92
6
472,93
4
468,90
3
464,83
1
460,71
8
456,56
4
452,36
9
448,13
1
443,85
1
439,52
9
435,16
3
430,75
4
426,30
0
421,80
2
417,25
9
412,67
1
408,03
6
403,35
6
398,62
8
393,85
3
389,03
1
384,16
0
379,24
1
374,27
2
369,25
4
364,18
5
359,06
6
353,89
6
348,67
4
343,39
9
338,07
2
332,69
2
327,25
8
321,76
9
4
1
4
2
4
3
4
4
5
4
6
4
7
4
8
4
9
5
0
5
1
5
2
5
3
5
4
5
5
6
5
7
5
8
5
9
6
0
6
1
6
2
6
3
6
4
6
5
6
6
7
6
8
6
9
7
0
7
1
7
2
7
3
7
4
7
5
7
6
7
7
8
7
9
8
0
8
1
8
2
8
3
8
4
8
5
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
876,10
5
559,87
9
565,47
8
571,13
3
576,84
4
582,61
3
588,43
9
594,32
3
600,26
6
606,26
9
612,33
2
618,45
5
624,64
0
630,88
6
637,19
5
643,56
7
650,00
2
656,50
2
663,06
8
669,69
8
676,39
5
683,15
9
689,99
1
696,89
1
703,86
0
710,89
8
718,00
7
725,18
7
732,43
9
739,76
3
747,16
1
754,63
3
762,17
9
769,80
1
777,49
9
785,27
4
793,12
7
801,05
8
809,06
8
817,15
9
825,33
1
833,58
4
841,92
0
850,33
9
858,84
2
867,43
1
316,22
6
310,62
7
304,97
2
299,26
1
293,49
2
287,66
6
281,78
2
275,83
9
269,83
6
263,77
3
257,65
0
251,46
6
245,21
9
238,91
0
232,53
8
226,10
3
219,60
3
213,03
8
206,40
7
199,71
0
192,94
6
186,11
4
179,21
4
172,24
6
165,20
7
158,09
8
150,91
8
143,66
6
136,34
2
128,94
4
121,47
2
113,92
6
106,30
498,60
6
90,83
1
82,97
9
75,04
7
67,03
7
58,94
6
50,77
4
42,52
1
34,18
5
25,76
6
17,26
3
8,674
www.renewpowerzo
ne.in
Page
24
www.renewpowerzo
ne.in
Page
25
Inverter
Transformer
Switch gear
DC Disconnect
Circuit breaker
SCADA/RMS
Cables
Isolator
1
.
2
.
3
.4
.
5
.
6
.1
.
2
.
3
.4
.
5
.
6
.1
.2
.
3
.
4
.1
.
2
.
1
1
.2
.
1
1
.
2
.
3
.4
.
1
.
2
.
3
.
Vikram Solar
Waaree Energies
Sova Power
Canadian Solar
Trina Solar
First Solar
Power One
SMA
Smart Power
REFusol
Delta
Schneider Electric
ABB
Schneider Electric
Ascott transformer
Voltech
Schneider Electric
Megawin
Schneider Electric
Megawin
ABB
Draker
Havells
Finolex cables
RR Kabels
Anchors
ABB
Schneider Electric
Megawin
THANK YOU