Professional Documents
Culture Documents
Work Order No
& Title
JOBCARD ID NO
X X X
- P - 0 0 1
- A
GENERAL
JOB DESCRIPTION
WORK CATEGORY
SYS NO
DISCIPLINE
SCHEDULE
SISO
Onshore
Offshore
Prefabrication
Hook-Up
OPS MODE
SIPROD
SIPCOM
Pre Shutdown
WORK
PHASE
XXX
SYS DESC
N/A
Hook-Up
Demolition
PIPING
LOCATION
CD
Commissioning
Decommissioning
Early Start
Late Start
Actual Start
Plan Duration
Early Finish
Late Finish
Actual Finish
Actual Duration
Shutdown
Post Shutdown
Percent
Weight
PERMIT TO WORK
Standart PPE
Body Harness
Cold Work
Lifting
Hearing Protection
Chemical Protection
Hot Work
Radiation
Work Vest
Breathing Apparatus
_____________________
Electrical
QUALITY
TEST
REQUIREMENT
VI
UT
Hydrotest
Cable Tests
Calibration
RT
MPI
Reinstatement
RV Pop Test
Loopcheck
Others
MANPOWER RESOURCES
TASK
NO
TASK DESCRIPTION
WORK VOLUME
TRADE
PLAN MHRS
Unit
Total
Unit
Total
RG
PAX
3.00
0.50
1.50
RG
PCS
25.00
1.10
27.50
RG
LOT
0.75
27.50
20.63
HOUSEKEEPING
RG
PAX
3.00
0.5
1.50
Contractor
Personnel
RS
PF
PWL
SF
SWL
FW
MW
IT
IF
ELE
BP
RG
51.125
Third Party
Personnel
NDT
PT
BT
IS
CC
VR
WH
L&R-001
Job Constraints /
Hold Points
Page 1 of 18
Item No
Unit
Utility Requirements
Qty
Description
Utility Air
Instrument Air
MESC No
Qty
Potable Water
Description
Power
VAC
Others __________
Description
Type
Unit
Service / Firewater
Unit
MATERIALS
Item No
Item No
Rev
NOTES
JOBCARD
APPROVAL
Name
Designation
CONTRACTOR
Prepared By
Muhd Hasril Rahaman
Piping Engineer
Reviewed By
Agreed By
PCSB
Approved by
Project Manager
HUC Engineer
Signature
Date
L&R-001
Page 2 of 18
JOBCARD
APPROVAL
Name
Designation
CONTRACTOR
PCSB
Presented By
Verified By
Confirmed By
Accepted By
Foreman / Supervisor
Construction Superintendent
Discipline Inspector
HUC Engineer
Signature
Date
L&R-001
Page 3 of 18
SISO
SIPROD
SIPCOM
Pre Shutdown
Shutdown
Post Shutdown
ACT
MHRS
L&R-001
Page 4 of 18
Description
Others ___________
Qty
S = Commissioning Spares
Drawing / Document Title
PCSB
Approved by
HUC Engineer
L&R-001
Page 5 of 18
PCSB
Accepted By
HUC Engineer
L&R-001
Page 6 of 18
Work Order No
& Title
JOBCARD ID NO
X X X
- P - 0 0 2
- A
GENERAL
JOB DESCRIPTION
WORK CATEGORY
SYS NO
DISCIPLINE
SCHEDULE
SISO
Onshore
Offshore
Prefabrication
Hook-Up
OPS MODE
SIPROD
SIPCOM
Pre Shutdown
WORK
PHASE
XXX
SYS DESC
N/A
Hook-Up
Demolition
PIPING
LOCATION
CD
Commissioning
Decommissioning
Early Start
Late Start
Actual Start
Plan Duration
Early Finish
Late Finish
Actual Finish
Actual Duration
Shutdown
Post Shutdown
Percent
Weight
PERMIT TO WORK
Standart PPE
Body Harness
Cold Work
Lifting
Hearing Protection
Chemical Protection
Hot Work
Radiation
Work Vest
Breathing Apparatus
_____________________
Electrical
QUALITY
TEST
REQUIREMENT
VI
UT
Hydrotest
Cable Tests
Calibration
RT
MPI
Reinstatement
RV Pop Test
Loopcheck
Others
MANPOWER RESOURCES
TASK
NO
TASK DESCRIPTION
WORK VOLUME
TRADE
PLAN MHRS
Unit
Total
Unit
Total
RG
PAX
4.00
0.50
2.00
RG
NOS
14.00
1.60
22.40
RG
PAX
22.40
0.75
16.80
HOUSEKEEPING
RG
PAX
4.00
0.5
2.00
Contractor
Personnel
RS
PF
PWL
SF
SWL
FW
MW
IT
IF
ELE
BP
RG
43.2
Third Party
Personnel
NDT
PT
BT
IS
CC
VR
WH
L&R-002
Job Constraints /
Hold Points
Page 7 of 18
Item No
Unit
Utility Requirements
Qty
Description
Utility Air
Instrument Air
MESC No
Qty
Potable Water
Description
Power
VAC
Others __________
Description
Type
Unit
Service / Firewater
Unit
MATERIALS
Item No
Item No
Rev
NOTES
JOBCARD
APPROVAL
Name
Designation
CONTRACTOR
Prepared By
Muhd Hasril Rahaman
Piping Engineer
Reviewed By
Agreed By
PCSB
Approved by
Project Manager
HUC Engineer
Signature
Date
L&R-002
Page 8 of 18
JOBCARD
APPROVAL
Name
Designation
CONTRACTOR
PCSB
Presented By
Verified By
Confirmed By
Accepted By
Foreman / Supervisor
Construction Superintendent
Discipline Inspector
HUC Engineer
Signature
Date
L&R-002
Page 9 of 18
SISO
SIPROD
SIPCOM
Pre Shutdown
Shutdown
Post Shutdown
ACT
MHRS
L&R-002
Page 10 of 18
Description
Others ___________
Qty
S = Commissioning Spares
Drawing / Document Title
PCSB
Approved by
HUC Engineer
L&R-002
Page 11 of 18
PCSB
Accepted By
HUC Engineer
L&R-002
Page 12 of 18
Work Order No
& Title
JOBCARD ID NO
X X X
- P - 0 0 2
- A
GENERAL
JOB DESCRIPTION
WORK CATEGORY
Lift-up & move gaskets & stud bolts (SD) to laydown area
SYS NO
DISCIPLINE
SCHEDULE
SISO
Onshore
Offshore
Prefabrication
Hook-Up
OPS MODE
SIPROD
SIPCOM
Pre Shutdown
WORK
PHASE
XXX
SYS DESC
N/A
Hook-Up
Demolition
PIPING
LOCATION
CD
Commissioning
Decommissioning
Early Start
Late Start
Actual Start
Plan Duration
Early Finish
Late Finish
Actual Finish
Actual Duration
Shutdown
Post Shutdown
Percent
Weight
PERMIT TO WORK
Standart PPE
Body Harness
Cold Work
Lifting
Hearing Protection
Chemical Protection
Hot Work
Radiation
Work Vest
Breathing Apparatus
_____________________
Electrical
QUALITY
TEST
REQUIREMENT
VI
UT
Hydrotest
Cable Tests
Calibration
RT
MPI
Reinstatement
RV Pop Test
Loopcheck
Others
MANPOWER RESOURCES
TASK
NO
TASK DESCRIPTION
WORK VOLUME
TRADE
PLAN MHRS
Unit
Total
Unit
Total
RG
PAX
2.00
0.50
1.00
RG
LOT
2.00
1.60
3.20
RG
PAX
3.20
0.75
2.40
HOUSEKEEPING
RG
PAX
2.00
0.5
1.00
Contractor
Personnel
RS
PF
PWL
SF
SWL
FW
MW
IT
IF
ELE
BP
RG
7.6
Third Party
Personnel
NDT
PT
BT
IS
CC
VR
WH
L&R-003
Job Constraints /
Hold Points
Page 13 of 18
Item No
Unit
Utility Requirements
Qty
Description
Utility Air
Instrument Air
MESC No
Qty
Potable Water
Description
Power
VAC
Others __________
Description
Type
Unit
Service / Firewater
Unit
MATERIALS
Item No
Item No
Rev
NOTES
JOBCARD
APPROVAL
Name
Designation
CONTRACTOR
Prepared By
Muhd Hasril Rahaman
Piping Engineer
Reviewed By
Agreed By
PCSB
Approved by
Project Manager
HUC Engineer
Signature
Date
L&R-003
Page 14 of 18
JOBCARD
APPROVAL
Name
Designation
CONTRACTOR
PCSB
Presented By
Verified By
Confirmed By
Accepted By
Foreman / Supervisor
Construction Superintendent
Discipline Inspector
HUC Engineer
Signature
Date
L&R-003
Page 15 of 18
SISO
SIPROD
SIPCOM
Pre Shutdown
Shutdown
Post Shutdown
ACT
MHRS
L&R-003
Page 16 of 18
Description
Others ___________
Qty
S = Commissioning Spares
Drawing / Document Title
PCSB
Approved by
HUC Engineer
L&R-003
Page 17 of 18
PCSB
Accepted By
HUC Engineer
L&R-003
Page 18 of 18