Professional Documents
Culture Documents
MOJKOVAC SUBSTATION
AND
TRANSMISSION LINE CONNECTOR IMPROVEMENT
(WB-T-2)
Project Description
The project will consist of reinforcement of the existing connector line from the Mojkovac substation to the main transmission
line by adding another line along the same route. The connector line will remain at 220 kV and will be about 2.5 km in length. An
additional transformer bay will also be constructed adjacent to the site of the existing Mojkovac substation and will utilize about 20003000 m2 of land.
Mojkovac substation is situated on the site of a lead and zinc mine and ore processing facility that was abandoned about twenty
years ago. The adjacent land site contains several old empty buildings that have been in disuse since the time the mining operation had
ceased. The entire facility is about one kilometer from downtown Mojkovac, and the mine tailings pond that has caused some concern of
water pollution to local residents is about 0.5 kilometers from the substation site. All local drinking water is derived from surface waters
flowing from the nearby mountains. The connector line route is sparsely populated and very hilly with limited farming activities. The Site
consists mostly of meadowland and some trees.
Some of the abandoned buildings will be demolished to provide space for the additional transformer bay.
A. MITIGATION PLAN
Phase
Construction
Issue
Mitigating
Measure
Dusty areas
(demolition site,
transformer bay
site) will be
sprayed with
water, particularly
during hot, windy
weather
Noise
Work will be
conducted
weekdays from
8:00 AM-6:00 PM
If additional times
are needed, local
residents will be
informed at least
one week in
advance
Machinery engine
Combustion
emissions
engine vehicles
must have official
valid emission
certifications
Cost of
Mitigation
(If Substantial)
Responsibility*
Start Date
End Date
Construction
contractor
Building
demolition
activities begin
Transformer
bay
construction
is complete
Minor
Construction
contractor
Construction
activities at
substation and
connection line
begin
Construction
activities at
substation
and
connection
line end
Minor
Construction
contractor
Construction
activities at
substation and
connection line
begin
Construction
activities at
substation
and
connection
line end
Minor
Minor
Building demolition
waste materials
Removed by truck
(covered and or
watered) to local
official municipal
disposal site
Right-of-way (ROW)
Clearance
land clearance
performed by
manual and/or
mechanical
means-no
pesticide use
Polychlorinated
biphenyls (PCBs)
Wood will be
sold locally,
vegetative scrap
trucked to local
official municipal
disposal site
Steep slopes will
have minimal
clearance of
vegetation and
replanted as a
priority
Any electric
equipment
purchased for the
project are
prohibited from
containing PCBs
Minor
Construction
contractor
Building
demolition
activities begin
Construction
contractor
ROW
clearance
begins
Building
demolition
activities end
and site is
cleared
ROW
clearance
ends
Minor
Construction
contractor
ROW
clearance
begins
ROW
clearance
ends
Minor
Construction
contractor
Prior to
purchase of
electrical
equipment
After last
piece of
electrical
equipment is
purchased
Minor
Minor
Access road
construction
Minor
Construction
contractor
Disruption of local
traffic patterns
Alternative traffic
routes will be
designated,
detailed traffic
signs located
strategically to
avoid confusion
Tower heights will
be designed and
built to
International
Electric
Commission (IEC)
standards to assure
ground level
electric and
magnetic fields
meet standards:
E 5kV/m
Minor
Construction
contractor
Minor
Construction
contractor
Electric and
magnetic field
strength at ground
level
Operation
Construction
activities at
connection line
begin
Construction
activities at
substation and
connection line
begin
Construction
activities at
connection
line end
Construction
activities at
substation
and
connection
line end
During tower
design
After tower is
constructed
B 100T
Items indicated to be the responsibility of the contractor shall be specified in the bid documents
Phase
What
parameter is
to be
monitored?
Construction
Worker
health
B. MONITORING PLAN
When
Monitoring
is the
Cost
Where
How
is the
parameter to
be monitored?
is the
parameter to
be monitored/
type of
monitoring
equipment?
At
construction
site
Dust levels
Responsibility
Start Date
End Date
Building
demolition
activities
begin
Transformer
bay
construction is
complete
Construction
activities at
substation
and
connection
line begin
Construction
activities at
substation
and
connection
line begin
Construction
activities at
substation and
connection line
end
parameter
to be
monitoredfrequency of
measuremen
t or
continuous?
What is the
cost of
equipment or
contractor
charges to
perform
monitoring
Visual:
Worker
wearing
equipment
Weekly:
random
times
Minor
Construction
Contractor
Dust visible
Weekly,
more
frequently
during dry,
windy
weather
Weekly or
if there are
local
complaints
Minor
Construction
Contractor
Minor
Construction
Contractor
Equipment
first comes
to project
site
Minor
Construction
Contractor
Noise
At
construction
site
dB meter
Machinery
engine
emissions
At
construction
site
Visual:
Examine
engine
exhaust
certification
Construction
activities at
substation and
connection line
end
Building
demolition
waste
materials
transport and
disposal
Right-of-way
(ROW) land
clearance
At
construction
site
At disposal
site
ROW
Visual:
Trucks
covered or
watered
Material
properly
deposited
Visual:
Manual or
Mechanical
methods used
Wood
properly
disposed
Visual:
Proper
procedures
followed
ROW erosion
control
ROW
(particularly
at steep
slopes)
PCBs
At delivery
site
Visual:
Review
equipment
invoice
Access road
construction
Equipment
and material
delivery
routes
Visual:
Existing
roads used
Weekly:
random
times
Minor
Construction
Contractor
Minor
Construction
Contractor
Weekly
Minor
Construction
Contractor
ROW
clearance
begins
ROW clearance
ends
Weekly
Minor
Construction
Contractor
ROW clearance
begins
Monthly,
and during
or after
heavy
rainfall
Before
equipment
delivery is
accepted
Minor
Construction
Contractor
ROW
clearance
begins
ROW
clearance
begins
Minor
Construction
Contractor
Weekly
Minor
Construction
Contractor
Prior to
accepting
delivery of
electrical
equipment
Construction
activities at
connection
line begin
Weekly
Building
demolition
activities
begin
Transformer
bay
construction is
complete
ROW clearance
ends
Construction
activities at
connection line
end
Operate
Disruption of
local traffic
patterns
Roads at or
near
construction
site
Visual:
Alternate
routes clearly
indicated
Monthly
Minor
Construction
contractor
Electric and
magnetic
field strength
at ground
level
Lowest cable
point under
connector
line, and
edge of
ROW
Electrometer
Once
Minor
Construction
contractor
Construction
activities at
substation
and
connection
line begin
When line is
energized
Construction
activities at
substation and
connection line
end
When line is
energized
C. INSTITUTIONAL ARRANGEMENTS
The Project will be implemented, in each of its phases, in compliance with applicable
Montenegrin Environmental Low and Construction Low. At the same time, EPCG
accepts the obligation to follow rules of World Bank and arrange conduction of EMP in
following way:
Construction contractor will be obliged to collect environmental data, and to
inform EPCG about data relevant for conduction of EMP.
The representative of EPCG from the Transmission Functional Entity who is in
charge of EMP will be in the role of supervisor at site, to review and analyze
environmental data.
There is a quality system office in charge of system quality and environmental
safeguarding which will prepare reports monthly or more frequently if required.
If problems emerge, this office recommends measures for solving the problem.
The Manager of the Transmission Functional Entity and the Head of PMU shall
receive monthly reports and decide about implementing recommendations (such
as with-holding of payments to contractor, repeated tests, dismissing contractor,
etc.).
Public consultation on EMP took place on March 16, 2006 in the premises of the
Electricity Distribution Unit of Mojkovac, from 12:20 to 14:30 hours. In addition to the
participants who signed the Participation List (Attachment 4) the public consultation
session was attended by representatives of press and electronic media and the head of
local government, the Mayor of Mojkovac.
Introductory presentation of the EMP was given by Messrs. Branislav Medojevic,
Director of ED Mojkovac, Dusan Vukasovic, Chief Engineer of the Project, the EPCG
Transmission Functional Entity and Ph.D. Veselin Ilic, and was followed by a discussion
as recorded in the Minutes of the Public Consultation (Atachment 5).
The public consultation session and the expectations from the Project were reported in
the press, daily Pobjeda and Vijesti (Attachment 6) and broadcasted on the
government TV channel 1 RTCG 1 in two evening news programmes on Friday, March
17 and morning news on March 18, 2006.
The above EMP, Enviromental Management Plan for Mojkovac Substation and
Transmission Line Connector Improvement (WB-T-2), together with all its
attachments is officially disclosed to public, following the order no. 10-00-4739 dated
March 31, 2006 passed by Executive Director of EPCG, at the EPCG web site
www.epcg.cg.yu as of March 31, 2006.
Attachment 1
Attachment 2
(Translation)
Attachment 3
Attachment 4
Attachment 5
(Translation)
MINUTES
of the Public Consultation held at ED Mojkovac offices in Mojkovac
on March 16, 2006 at 12.20 AM
The topic of the Consultation was Environmental Management Plan proposal for
implementation of 220/110/35 kV Mojkovac SS Extension and 220 kV Transmission
Line Construction Project.
Attendees:
Other attendees:
Project-holder Representatives
1. Duan Vukasovi
2. Vera urovi
3. Dr.Veselin Ili
1. Mayor of Mojkovac
2. Radio Mojkovac Representatives
3. Vijesti reporters
4. NGO Planinar Representatives
5. Citizens
Mr. Branislav Medojevi, manager of ED Mojkovac, opened the discussion and greeted
those present, and afterwards Mr. Duan Vukasovi informed everyone about the
objective and importance of the project 220/110/35 kV Mojkovac SS Extension and 220
kV Transmission Line Construction. After Mr. Vukasovi discussion, Dr. Veselin Ili
advised those present on the proposal of Environmental Management Plan for
implementation of 220/110/35 kV Mojkovac SS Extension and 220 kV Transmission
Line Construction Project.
Following the introductory part the discussion was open, and citizens and representatives
of NGO mountain climbing club "Dambas" Mojkovac took part in it.
-
No one made the environment more beautiful by putting the poles, and we should
take care of number of poles, but if we were aware of our gain and our loss, he
would support the project. Concerning harmful effects on the environment, he
thinks there is no major impact and he would always decide to support to the
project.
Mr. Mini Milisav, citizen representative, asked whether anyone thought to apply
underground solution for OHL? There is a plan to build a cable railway on that
site, and the line would obstruct it.
Mr. Duan Vukasovi replied to the questions asked and said that there was no
consideration of this issue because the price was considerably higher, but that this
issue, together with all remarks from this discussion, would be considered while
designing the OHL.
Attachment 6