Professional Documents
Culture Documents
1.0
Safety Specifications
1.1
General
1.2
1.3
01002 / Page 1 of 50
1.5
1.7
01002 / Page 4 of 50
1.9
Risk Management
1.9.1 The contractor shall conduct a risk assessment in relation to the
safety and health risks posed to any person who may be
affected by his undertaking prior to the commencement of work
in accordance to the Workplace Safety & Health (Risk
Management) Regulations.
1.9.2 The contractor shall take all reasonably practicable steps to
eliminate any foreseeable risk to any person who may be
affected by his undertaking.
1.9.3 The contractor shall maintain a record of risk assessments
conducted, including any control measures taken or to be taken
and any safe work procedures.
1.9.4 The contractor shall ensure that his employees are informed of
the nature of the risk involved, the measures implemented to
control the risk and applicable safe work procedures. Whenever
the assessment of a risk is revised, or where control measures
or safe work procedures are changed, employer shall inform
employees of such changes.
1.9.5 The contractor shall incorporate the time frame required for risk
assessment to be developed into the master/monthly work
program and shall ensure that his employees are informed of
the nature of the risk involved, the measures implemented to
control the risk and applicable safe work procedures prior to
commencement of work.
1.9.5 The contractor shall review and if necessary revise the risk
assessment at least once every year and forthwith if, there is an
occurrence of any injury or illness as a result of exposure to a
hazard, or there has been a significant change in work practices
or procedures.
01002 / Page 5 of 50
01002 / Page 13 of 50
01002 / Page 14 of 50
01002 / Page 16 of 50
01002 / Page 18 of 50
b) Noise Management
The contractor shall as far as practicable, ensure that all
processes, machines and equipment used, do not cause workers
01002 / Page 19 of 50
c) First-Aid
All workplaces as specified within the class or description in the
first schedule of the Workplace Safety & Health Act shall establish
and implement a first-aid programme to provide emergency
treatment to victims of accidents, chemical poisoning or excessive
exposure to toxic substances.
The programme shall include: i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
First-aid facilities;
First-aid boxes;
First-aid room, where there are 500 or more workers at site;
Training and re-training of first-aiders;
First-aid treatment procedures;
First aid for exposure to toxic or corrosive substances
Standard procedures;
Special procedures, e.g. for poisoning
Maintenance of first-aid facilities.
01002 / Page 20 of 50
01002 / Page 21 of 50
Main-Contractor
and
Safety
2.7
Safety Training
2.7.1 Safety Orientation Course
The Contractor shall employ workmen who possess valid Safety
Orientation Course Certificates to work on the site. The
Contractor shall ensure that his workmen attend a prescribed
safety refresher course at regular interval.
01002 / Page 25 of 50
Safety Audit
The Contractor shall appoint an independent Malaysian regulative body
approved external safety auditor where the contract sum awarded is
equal or exceed $10 mil to audit the Safety Management System of the
Site at least once every six (6) months using Construction Safety Audit
Scoring System (ConSASS), with the first audit conducted within one
(1) month from the date of the Letter of Acceptance. In addition, the
Contractor shall carry out internal safety audits to verify whether safety
activities comply with the Safety Management System requirements.
If deemed necessary, the CA shall be entitled to engage an
independent external auditor to audit the Contractors Safety
Management System and the Contractor shall provide all necessary
attendance and information to the auditor. The contractor shall bear the
cost of engaging the external auditor.
The Contractor shall periodically review and evaluate the efficiency of
the Safety Management System in place.
The audit and possible corrective actions shall be carried out in
accordance with the documented procedures.
01002 / Page 28 of 50
Inspection
The Client may appoint in writing one or more Safety Inspectors who
shall be authorized without prior notice to the Contractor, to enter the
Site at all reasonable times to conduct inspections and examinations
for the purpose of ensuring compliance with the safety requirements
described in the Safety Specifications. However, the Contractor shall
be notified of the arrival of Safety Inspector at the Site and any
inspection carried out by the Safety Inspector shall be witnessed by the
Contractors Project Manager and Workplace Safety & Health Officer/
Safety Coordinator.
The frequency of safety inspection shall depend on the nature of the
construction activities, the hazards present, internal and external
feedback received and the performance of the Contractor.
4.0
4.1
Suspend Work
The CA may suspend the progress of works or any part of them if
necessary for the safety of the works or if he is of the opinion that the
working environment or procedure is unsafe for the works to continue.
In such event, the Contractor shall not be entitled to any claims for
compensation or extension of time for Completion.
01002 / Page 30 of 50
5.1
5.2
5.3
7.0
01002 / Page 33 of 50
S/N Infringements
1
2
3
4
01002 / Page 34 of 50
_________________________________
_______________________________
_________________________________
(Name of Company / Company Stamp) (Date)
As defined under the Workplace Safety and Health Act
01002 / Page 35 of 50
The role and responsibility of every individual in the work area on fire safety,
emergency and rescue;
General work area precautions, fire prevention, detection, protection and
warning alarm systems;
Fire-fighting & rescue equipment including types of fire extinguishers;
Fire safety measures for site accommodation;
Escape and communication;
Fire brigade access, facilities and coordination;
Fire drills and training including the use of fire-fighting apparatus;
Material storage including flammable liquids, gases and waste control regime;
The Contractor shall ensure that all procedures, precautionary measures and
safety standards stipulated in the Plan are communicated, implemented and
complied with by all workers including sub-contractors and other interfacing
contractors on Site.
The Contractor shall review and ensure the adequacy of the Plan as the work
progress.
The Contractor shall conduct weekly checks on fire-fighting equipment and
test all alarms and detection devices installed on the site.
01002 / Page 36 of 50
3.1
Environmental Control
Under the Sewerage And Drainage Act, Cap. 294 pertaining to the control of
erosion and sediment, the Contractor shall be responsible for preventing silt
from being washed into public drains by implementing effective Earth Control
Measures (ECM) for the construction site to meet the requirements under the
latest Sewerage and Drainage Act Cap 294. (Information on ECM
requirements can be found in the Code of Practice on Surface Water
Drainage and the website.
The Contractor shall note that the ECM are for the containment and treatment
of silty discharges due to the impact of rainwater. ECM are not meant for the
treatment of wastewater due to construction activities (such as slurry from
tunnelling, pipe-jacking and bore-piling works) which shall be treated to
comply with the requirements under Environmental Pollution Control Act
(Chapter 94A).
Before construction works commence on site, the Contractor shall engage a
QECP to plan and design the ECM, and he shall install the ECM according to
the QECP's design. The ECM plan and design shall be submitted 1 week
after the award of the contract. During the course of the construction works,
the Contractor together with his QECP shall review the ECM proposal
regularly to meet the changing needs of the construction activities. The
Contractor shall improve the ECM as advised by his QECP. The planning and
design of the ECM shall meet the minimum requirements stipulated and in
accordance to the Code of Practice on Surface Water Drainage.
The Contractor shall maintain the ECM for the whole duration of the Contract
period to ensure that it is effective at all times. Proper records detailing the
maintenance works, supported by dated photographs, shall be kept by the
Contractor and submitted to CA for verification.
The Contractor shall submit the ECM proposal duly endorsed by his QECP,
for review by the CA prior to submission to Director, Drainage (Public Utilities
Board) for records.
01002 / Page 38 of 50
Site Administration
Site Hoarding
Project Signage and Warning Signs
Approvals Required from the Project Manager
Security
Site Safety
Protection of Hospital/Public Property and Minimal Inconvenience to the
Adjacent Hospital Community
8. Housekeeping
9. Decorum
10. Pollution Control
11. Defect Liability
12. As-Built Drawings / Warranties Submission
1. SITE ADMINISTRATION
1.1
1.2
1.3
The Contractor shall provide its own power supply from portable low
noise genset (less than 2 years of service and 30dBA at 5m away from
genset). The contractor shall not tap power from the existing source
unless otherwise approved by the employer. The installation must be
01002 / Page 40 of 50
The Contractor shall provide and maintain own temporary water supply
and distribution system. The temporary water supply shall be tapped
from the PUB mains and installation shall comply with the requirements
of Public Utilities Board.
1.5
1.6
The Contractor shall submit a site layout clearly indicating the facilities,
site office, emergency assembly area, workers resting, storage area,
free P.P.E zone, designated chemical storage area, etc. to the
Employer and Consultant for approval within 2 weeks upon award of
Contract.
1.7
1.8
1.9
1.10
The Contractor shall mark out all new works (eg. drywall, door, fitment,
etc) on site and seek Consultant / site staff's confirmation before
commencement of work.
1.11
The Contractor shall highlight all existing damaged pipes, cables and
structures to Consultant and CA for follow up action.
1.12
1.13
The Consultant will issue a set of standard forms for the administration
of the contractors works.
1.14
The
Contractor
shall
submit
copies of shop
drawing,
materials/equipment and samples to Consultant for comments when
required to do so.
1.16
1.17
1.18 The Contractor shall ensure all workers, site staff, sub-contractors,
suppliers engaged by the him shall not behave unruly to local people.
For non-compliance the persons involved would be barred from
entering the site.
2. SITE HOARDING
2.1
Project Title :
Project Ref No. :
Developer/Owner : Tel No:
Architect : Tel No:
Professional Engineer : Tel No:
Information & Call Centre HOTLINE: Tel No:
Builder : Tel No:
Expected Date of Completion :
FOR ENQUIRIES OR FEEDBACK, PLEASE CALL THE ABOVE
TELEPHONE / HOTLINE NO. AND QUOTE THE PROJECT
REFERENCE NUMBER
01002 / Page 42 of 50
01002 / Page 45 of 50
01002 / Page 46 of 50
01002 / Page 47 of 50
01002 / Page 48 of 50
7am
7pm
- 7pm
7am
50
55
10.6 The noise shall be measured at 1 m from outside the affected premises
or at the boundary of the construction site if the affected premises are 50m
away from the boundary of the construction site.
10.7 Contractor is to report any Asbestos or hazardous materials found on
THE EMPLOYERS site to Consultant immediately. The Contractor is to
apply permit from the relevant Authority (if applicable) for handling of
Asbestos or hazardous materials. All toxic industrial waste disposals to be
carried out by NEA approved toxic waste contractor.
10.8 Contractor are not allowed to discharge any trade effluent, silt into any
sewerage or drainage. For those Contractors engaging in earthworks, ECM
shall be designed by PUB approved QECP and submitted to CA / PUB
drainage dept for silt discharge control on site.
10.9 Contractor to seek THE EMPLOYERS approval for the proposed
location(s) to house diesel generator on site.
01002 / Page 49 of 50
12.1.2
12.1.3
12.1.4
12.1.5
12.1.6
12.2
12.2.1
12.2.2
12.3 All as-built drawings shall be accompanied with a detailed drawing list,
indicating the project title/reference, type of service, drawing title and drawing
number.
- END 01002 / Page 50 of 50