You are on page 1of 312

Project Dwg. No: P101-25-1701.

03-W017

Forced Draft Fan


MECHANICAL MAINTENANCE MANUAL
PT PAITON ENERGY
PAITON EXPANSION PROJECT

Forced Draft Fan Maintenance


Manual No. MM-M02.01
Revision 003

Note
This mechanical maintenance manual is intended to provide the Paiton Expansion Project
mechanical maintenance personnel with the basic understanding required to perform preventive,
routine, corrective and overhaul maintenance activities on the subject equipment.

No part of this document may be reproduced for use by parties other than Mitsubishi Heavy
Industries, Ltd. and Paiton Expansion Project.

Forced
Draft
Fans

Be sure to read this manual.


Contents
Safety

General

Specifications

Preventive Maintenance

Disassembly and Reassembly

Corrective Maintenance

Recommended Lubrication

Appendixes

Contents

Contents
Revision Record i
Important Informationii
Warranty v
Limitation of Liabilityvii
Copyright viii
Personnel to whom the Manual is Directed ix
Contact Address x
Abbreviations xi
List of Vendor Manuals xiv
Arrangement of the System Maintenance Manualxv

Chapter1

Safety ____________________________

1.1

Feature of Forced Draft Fan Safety 1-1

1.2

Warnings Description 1-2


1.2.1

Definitions of Serious Injury, Minor Injury, Serious


Damage to Property, and Minor Damage to Property 1-3

1.2.2

Symbol 1-4

1.2.3

Hazard Warning Label 1-5

1.2.4

Hazard Area 1-7

1.3

Risk Assessment Standard 1-8

1.4

Safety Measures 1-10


1.4.1

Work Permit System (Lockout/Tagout) 1-10

1.4.2

General Cautions on Personnel in Working Area 1-11

1.4.2.1 Cautions against Rotating Equipment 1-11


1.4.2.2 Cautions against High Voltage Section 1-11
1.4.2.3 Cautions against High Temperature Sections 1-12
1.4.2.4 Cautions for Steam Leak in the Plant 1-13
1.4.2.5 Cautions against Oil/Coal Leak in the Plant 1-13
1.4.2.6 Cautions against Chemicals 1-14
1.4.2.7 Cautions against Combustible Materials/Storage Areas 1-14
1.4.2.8 Cautions against Lack of Oxygen 1-15
Rev.003

1.4.2.10Cautions against Sharp Objects 1-16

MM-M02.01

1.4.2.9 Cautions against Lifting Heavy Object 1-16

1.4.2.12Cautions using Crane 1-17

1.4.2.11Cautions using Fork Lift 1-16


1.4.2.13Disposal 1-18
Forced Draft Fan
Mitsubishi

Contents

Chapter1
1.5

Safety (Continued from previous page)


Emergency Measure 1-19
1.5.1

Evacuation in an Emergency 1-19

1.5.1.1 Evacuation Route 1-19


1.5.1.2 Evacuation of Disabled persons who cannot move
by themselves 1-19
1.5.1.3 Evacuation from Power House 1-20

Rev.003

Fire Accident 1-21

1.5.3

Earthquake 1-22

1.5.4

Explosion Accident 1-22

1.6

Qualification and Training 1-23

Chapter2

General ___________________________

2.1

Purpose 2-1

2.2

References 2-1

2.3

Overview of the FDF 2-2

2.4

Components 2-7
2.4.1

Casing 2-7

2.4.2

Rotor 2-9

2.4.3

Moving Blade Regulating Mechanism 2-10

2.4.4

Main Bearing Assembly 2-11

2.4.5

Control/Lubricating Oil System 2-11

2.4.6

Coupling 2-12

Chapter3

Specifications _____________________

Chapter4

Preventive Maintenance _____________

4.1

Prerequisites 4-1

4.2

MM-M02.01

1.5.2

4.3

Forced Draft Fan


Mitsubishi

4.1.1

Scheduling 4-1

4.1.2

Departmental Interface/Notification 4-2

4.1.3

Isolation of Equipment 4-2

4.1.4

Safety Precautions 4-2

Routine Maintenance 4-3


4.2.1

Preparation 4-3

4.2.2

Inspection and Maintenance 4-4

Annual Outage Maintenance 4-10


4.3.1

Preparation 4-10

4.3.2

Inspection and Maintenance 4-11

Contents

Disassembly and Reassembly ________

5.1

FDF Disassembly and Reassembly 5-1

5.2

Rotor Disassembly and Reassembly 5-18

5.3

Bearing Disassembly and Reassembly 5-27

5.4

Moving Blade Regulating Mechanism Linkage


Disassembly and Reassembly 5-33

5.5

Coupling Disassembly and Reassembly 5-38

Chapter6

Corrective Maintenance _____________

6.1

Prerequisites 6-1

6.2

Preparation 6-2

6.3

Troubleshooting 6-2

Chapter7

Recommended Lubrication __________

MM-M02.01

Rev.003

Chapter5

Forced Draft Fan


Mitsubishi

Contents

Appendixes
Appendix A

Torque Chart A-1

Appendix B

Spare Parts B-1

Appendix C

Special Tools C-1

Appendix D

Coupling Alignment D-1

Appendix E

Applicable Vendor Drawings E-1

Appendix F

MV Packing Insertion F-1

Appendix G

Applicable Vendor Manuals G-1

Appendix H

Part List H-1

Appendix I

Moving Blade Paint Data Sheet I-1

MM-M02.01

Rev.003

List of Figures
Figure1-1

Types of Hazard Warning Label 1-6

Figure 1-2

FDF Mapping for Hazard Areas 1-9

Figure 2-1

Air & Flue Gas P & I D 2-3

Figure 2-2

FD Fan Outline 2-4

Figure 2-3

FD Fan Sectional View 2-5

Figure 2-4

FD Fan Cutaway View 2-6

Figure 2-5

FDF Casing Assembly 2-13

Figure 2-6

Rotor Assembly 2-14

Figure 2-7

Moving Blade Regulating Mechanism Assembly 2-15

Figure 2-8-1

Linkage Mechanism Assembly 2-16

Figure 2-8-2

Blade Sticking Detector 2-17

Figure 2-9

Bearing Box Assembly 2-18

Figure 2-10

FDF Lube and Control Oil P & I D 2-19

Figure 2-11

Intermediate Shaft and Coupling Assembly 2-20

Figure 3-1

Performance Curve 3-4

Figure 4-1

FDF Clearance Details 4-18

Figure 5-1A

Overhaul Plan for FDF 1/2 5-15

Figure 5-1B

Overhaul Plan for FDF 2/2 5-16

Figure 5-2

Supporting Procedure for FDF Rotor 5-17

Figure 5-3

MB Hydraulic Mechanism Exploded View 5-24

Forced Draft Fan


Mitsubishi

Contents

List of Figures
MB Mechanism Exploded View 5-25

Figure 5-5

Supporting Procedure for Rotor Disassembly


& Reassembly 5-26

Figure 5-6

Bearing Box Exploded View 5-31

Figure 5-7

Supporting Procedure for Bearing Removal 5-32

Figure 5-8

MB Regulating Linkage Mechanism Exploded View 5-37

Figure 5-9

Centering Tool Assembly for Intermediate Shaft 5-41

Figure E-1

Forced Draft Fan Outline Drawing E-2

Figure E-2

Forced Draft Fan Sectional Drawing E-3

Figure E-3

FDF Lubricant & Control Oil Unit P & ID E-4

Figure E-4

FDF-A Lubricant & Control Oil System Unit


Assembly 1/2E-5

Figure E-5

FDF-A Lubricant & Control Oil Unit


Assembly 2/2E-6

Figure E-6

FDF-B Lubricant & Control Oil Unit


Assembly 1/2E-7

Figure E-7

FDF-B Lubricant & Control Oil Unit


Assembly 2/2E-8

Figure F-1

MV Packing Insertion F-2

Figure F-2

MV Packing Material & DimensionF-3

MM-M02.01

Rev.003

Figure 5-4

Forced Draft Fan


Mitsubishi

Contents

List of Tables
Risk Assessment Standard 1-8

Table 3-1

Forced Draft Fan 3-1

Table 3-2

Forced Draft Fan-Motor 3-2

Table 3-3

FDF Control Oil Unit 3-3

Table 4-1

Routine Maintenance Checklist 4-7

Table 4-2

Annual Outage Maintenance Checklist 4-14

Table 6-1

Troubleshooting Forced Draft Fan 6-3

Table 7-1

FD Fan Recommended Lubrication 7-1

Table A-1

Torque Chart A-1

Table B-1

Recommended List of Strategic Spare Parts


(Off-Shore) B-2

Table C-1

FD Fan Special Tools C-2

Table H-1

Part List (1 of 8) H-2

Table H-2

Part List (2 of 8) H-5

Table H-3

Part List (3 of 8) H-8

Table H-4

Part List (4 of 8)H-11

Table H-5

Part List (5 of 8) H-15

Table H-6

Part List (6 of 8) H-18

Table H-7

Part List (7 of 8) H-21

Table H-8

Part List (8 of 8) H-24

Table I-1

Moving Blade Paint Data Sheet (1 of 2) I-2

Table I-2

Moving Blade Paint Data Sheet (2 of 2) I-3

MM-M02.01

Rev.003

Table 1-1

Forced Draft Fan


Mitsubishi

Revision Record
Revision Issue
Date

Date Revised

Pages
Inserted

2-11, 2-13,
2-18

Revised in accordance with design


progress.

26. May. 2011

26. May. 2011

2-14 ~ 2-16

Revised in accordance with


Drawing review sheet

26. May. 2011

26. May. 2011

2-17

Added drawing of blade sticking


detector in accordance with
drawing review sheet
(PE-MHIN-PEHO-T-11025)

26. May. 2011

26. May. 2011

3-4

Added performance curve in


accordance with drawing review
sheet (PE-MHIN-PEHO-T-11025)

26. May. 2011

26. May. 2011

4-18,
4-14~4-18

Revised in accordance with design


progress.

26. May. 2011

26. May. 2011

5-28

Corrected an error.

26. May. 2011

26. May. 2011

Appendix B

Revised updated status

26. May. 2011

26. May. 2011

F-3

Revised in accordance with


drawing review sheet
(PE-MHIN-PEHO-T-11025)

26. May. 2011

26. May. 2011

Appendix-H

Added the part list.

26. May. 2011

26. May. 2011

4-14
G-19~G-21
G-28, G-29

Added the comments in


accordance with drawing review
sheet (PE-MHIN-PEHO-T-13681)

27.Feb. 2012

27.Feb. 2012

3-1, 4-5, 4-14,


4-18, 6-3

Added the comments in


accordance with design progress.

27.Feb. 2012

27.Feb. 2012

E-4

Revised the updated status.

27.Feb. 2012

27.Feb. 2012

2-5
Appendix I

Added the comments in


accordance with drawing review
sheet (PE-MHIN-PEHO-T-13681)

27.Feb. 2012

27.Feb. 2012

4-8, G-16

Revised in accordance with design


progress.

27.Feb. 2012

27.Feb. 2012

G-120~G-128

Added Line Filter manual in


accordance with design progress.

27.Feb. 2012

27.Feb. 2012

Rev.003

Description of Revision

5-9, 5-13

Added the comments in


accordance with NCR
(MBK-N-NCR-0047).

23. March.2012

23. March.2012

MM-M02.01

Page Number

E-4

Revised updated status.

23. March.2012

23. March.2012

Forced Draft Fan


Mitsubishi

Important Information
Purpose of the Plant Usage
This plant is designed to generate electric power of 815 MW by the steam turbine
generator.
The plant is used for the electric power generation purpose that supports stable and
reliable electric power supply to the power grid and supplying steam for auxiliary
equipment in the power station.

General
1.

To satisfy the purpose mentioned above, the following points must be strictly
observed.
a)

The operation, maintenance and inspection of the Forced Draft Fan


must be performed by the persons who have basic technical knowledge
and have been trained concerning the hazard of the Forced Draft Fan
and the avoidance of the hazard.

b)

The operators and maintainers must read and understand these


manuals before starting the operation, maintenance or inspection.
It is often experienced that serious damages to the equipment or
personnel have occurred by the unexpected action of operators or
maintainers who do not understand well about the equipment.

c)

The modification or change of operational specification must be


performed under MHI supervision or as per the written acceptances of
MHI.
The modification or change of specification causes not only a decline in
performance but also a decline in safety for operation of the equipment.
The customer is requested to discuss with MHI about any planned
modification or changes before the work actually starts.

MM-M02.01

Rev.003

The address for MHI to be contacted is shown in this chapter.


2.

The operation and maintenance must be performed according to the


applicable laws and regulations at the location of the power station.

3.

Disposal from the power station must be treated to satisfy the local
regulations.

4.

The copyright of software, drawings and other documents provided by MHI


at all times, is still reserved by MHI.

Forced Draft Fan


Mitsubishi

ii

5.

Use or copying of the whole or part of any information provided by MHI for
any purpose other than operation and maintenance of this plant without
written consent is strictly prohibited.

Important General Notice for Safety


1.

The operator and maintainer must have knowledge about the equipment to
maintain good operating condition and to avoid danger when using the
equipment and systems.

2.

The protection measures must satisfy all of the operational functions.

3.

The safety activity must be planned systematically as a Safety and Health


management system and operate continuously.
The Safety and Health management system must include the following
points,
a) Instruction for the use and the maintenance of the personal protective
equipment issued to operators and maintainers
b) The establishment of a work management organization to make clear
the operation directives and work procedures
c) Implementation of training for operator and maintainer

4.

The customer must train the operators and maintainers to act actively and to
prevent the occurrence of an accident by using their knowledge of the power
plant.

5.

The customer must make the operators and maintainers understand that the
most important purpose of safety control is to protect all personnel from
accidents and also to maintain operation of the plant without troubles.

6.

To prevent accidents involving personnel and equipment, it is necessary to


observe the notices of this manual and to keep the correct operation
according to the description provided in this manual.
If the notices are not observed, the following dangers could occur to the
operators or to the maintainers.

Rev.003

7.

a)

Risk of a fatal accident

b)

Danger to lose his health and fitness

c)

Danger of damage to the equipment

MHI can not forecast all possible dangers existing in the plant such as
danger due to human error and/or dangers caused by the operating
environment.

MM-M02.01

As this manual and the alert label cannot cover all of the dangers, the
operators and maintainers have to pay their full attention to all general safety
notices.

Forced Draft Fan


Mitsubishi

iii

8.

MHI can not be responsible for damages and injury caused by neglecting the
notices in this manual, and other necessary general notices.

Instruction of this Manual


This manual is provided for people familiar with the use of English. If some
person not familiar with English is going to operate the plant, the Customer
must train him specially.

2.

The warning labels are to be expressed in the English language.

3.

This manual contains optional matters.

4.

Some figures in this manual include internal parts of the equipment which
may not be obvious, when looking at the completed equipment drawing.

5.

MHI may change the content of this manual without notice.

6.

This manual is intended for the use by the operators and maintainers and it
must be accessible to them at all times.

7.

If the Customer needs more detailed information, please contact MHI local
office or MHIs official agent.

MM-M02.01

Rev.003

1.

Forced Draft Fan


Mitsubishi

iv

Warranty

The provisions set forth in this section are in addition to all liability and
warranty disclaimers and limitations set forth in the Contract, whether arising
under law or from course of performance, course of dealing, or usage of trade.

Nothing in these provisions shall constitute or be deemed to constitute any


additional liability undertaking or warranty, express or implied, with respect to
the Plant. All capitalized terms used, but not defined in this Warranty
Limitations section shall have the respective meanings ascribed to them in the
Contract.

The Contract Warranties are subject to the construction, installation and


Commissioning works having been performed in full compliance with the
requirements stated in (a) the Contract, (b) all manuals provided by MHI,
including this manual, (c) all applicable rules, regulations and laws prevailing
in the location where the Plant has been installed and will operate, and (d) any
other instructions, if any, provided by MHI (collectively, Rules and
Requirements). The Contract Warranties will NOT cover any accidents,
partial or total failure of the Plant, losses or damages to personnel or property
(including, without limitation, the Plants components, parts, systems and
other equipment), or any other liability (collectively, Accidents and Damages)
in the case of any breach of the stated Rules and Requirements.

For the detailed terms and conditions of the warranty concerning the Works
and Project, refer to the Contract.

In addition to the foregoing, the Contract Warranties will NOT cover any of the
following Accidents and Damages:
Accidents and Damages caused by any deviation from the Rules and
Requirements;

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

Accidents and Damages caused by the modification or re-installation of the


Plant after the original installation, or caused by operation of the Plant for a
purpose other than that for which it is designed;

Accidents and Damages caused by natural disasters or accidents during


transfer or related handling;

Accidents and Damages occurring after the term of the warranty has expired;

Accidents and Damages due to faulty operation or operation not in


accordance with the Rules and Requirements;

Accidents and Damages due to inappropriate maintenance or servicing


performed by the Customer, its personnel or any other party.

Accidents and Damages caused by any components, parts, systems or other


equipment other than those delivered by MHI;

Accidents and Damages caused by unidentifiable reasons including loss of


the damaged parts which is necessary to pinpoint a cause of the failure;

Accidents and Damages caused by referring to inadequate, or incorrect


references, data or information provided by the Customer;

Accidents and Damages or rust/corrosion due to inadequate handling and/or


storage by the Customer; or

Accidents and Damages due to handling, storage and/ or use of the Plant
under severe conditions or in an environment that does not meet the design
specification conditions.

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

vi

Limitation of Liability
Use and Disposal

Nothing in this Limitation of Liability section or manual shall constitute or be


deemed to constitute any additional liability undertaking or warranty, express
or implied, with respect to the Plant. All capitalized terms used, but not defined
in this Limitation of Liability section shall have the respective meanings
ascribed to them in the Contract.

The contents of this manual are subject to change without prior notice and
without any obligation or liability to MHI.

For Documents and Safety Training

Use of the Plant must be limited to the use specified by MHI, including without
limitation, use of the Plant in accordance with the Contract, this manual, all
Safety Manuals, all applicable laws and regulations, and any other instructions,
if any, provided by MHI. The Plant components, parts, systems and other
equipment (collectively, Equipment) must be appropriately disposed of in
accordance with the Contract, this manual, all Safety Manuals, all applicable
laws and regulations, and any other instructions, if any, provided by MHI.

For Damage to the Plant

MM-M02.01

Rev.003

The Customers personnel must read, understand and abide by all documents
provided by MHI, including without limitation, the operation and maintenance
manuals, safety manuals, and instruction manuals (collectively, Safety
Manuals) and must have received all required and/or necessary safety
training prior to the start of their work. Persons who have not received such
safety training are not permitted to work on the installed Plant. This initial
training, however, is merely the minimum requirements prior to allowing any
personnel to work on the installed Plant. The Customer must, on a continual
and regular schedule, give up-to-date training to its personnel on safety
requirements, provide testing or other methods to confirm their understanding
of the safety training, and confirm that they have the physical and mental
capability to perform their respective roles. The Customers obligation for
safety training and personnel supervision is an ongoing obligation and must
be continuously performed and kept current throughout the operation of the
Plant. Accidents, partial or total failure of the Plant, damage to personnel or
property, loss, injuries, and other liability (collectively, Liability) caused by
inadequate safety training or the Customers personnels failure to abide by
the documents provided by MHI are expressly excluded from the coverage of
any warranty provided by MHI and are the sole and exclusive responsibility of
the Customer.

Forced Draft Fan


Mitsubishi

vii

MHI will NOT be liable for any Liability caused by modification or changes
made in Plant-related documents (including any Safety Manual) by anyone
other than MHI.

For Damage to the Plant


Accidents may occur by use of Equipment that is acquired from anyone other
than MHI or anyone not appointed by MHI to modify or repair this Plant. The
Customer shall not be permitted to modify or repair the Plant or change
Equipment of the Plant without MHIs prior written approval, under any
circumstance.

MHI will NOT be liable for any Liability resulting from any abuse, misuse,
misapplication of the Equipment supplied by MHI.

MHI will NOT be liable for any Liability caused by an act by the Customer in
violation of the Contract, this manual, any applicable law or regulation, or any
Safety Manual or any other instruction provided by MHI, including without
limitation, a change of the installation environment or the removal and
installation of any Equipment in a location different to that originally selected
by MHI.

MHI will NOT be liable for any Liability caused by a defect, imperfection, or
fault, in material or Equipment that was used during a repair, even when such
a repair was performed by or under an instruction given by MHI.

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

viii

Copyright
COPYRIGHT 2009, MITSUBISHI HEAVY INDUSTRIES, LTD. ALL RIGHTS RESERVED.
ANY REPRODUCTION IS EXPRESSLY PROHIBITED.
All of the content contained in this manual is protected by Japanese, International
and/or United States copyright laws.

All copyright, trade secrets, and other proprietary and intellectual property rights in
the documents provided by Mitsubishi Heavy Industries, Ltd. (MHI) (including
safety-and-instruction manuals) are at all times owned and reserved by MHI. Subject
to your compliance with the restrictions set forth below, MHI grants to you a limited,
non-exclusive license in the copyright for the sole purpose of allowing you to use,
operate, maintain and inspect the Plant.

Use, copying, other reproduction of the whole or part of the documents provided by
MHI (including safety-and-instruction manuals) for any purpose other than the
purpose described above without MHIs prior written consent is strictly prohibited.

The act of rewriting, translating, modifying, revising, creating electronic copies,


uploading, selling, sublicensing, or otherwise disclosing the whole or part of the
manuals is strictly prohibited.

Except as specifically set forth above, no right, title or license to the documents
provided by MHI, whether arising from contract, implication, and estoppel or
otherwise, is being granted or otherwise transferred.

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

ix

Personnel to whom the


Manual is directed
This Manual was prepared for all personnel who will participate in the operation
and maintenance of the plant, and other related mechanical plant and equipment
installed.
In this Manual, MHI classifies personnel into the following two classes based on
their ability, experience and their attitude to the safety of personnel, and the plant
installed.
Only the personnel recognized by the Customer as trained personnel are allowed
to perform the operation and maintenance specified in the manuals.
Maintainers and Operators are required to have read and understood the contents
of the safety, operation, and maintenance manuals and sufficiently understand the
work procedures before actually starting their tasks.

Operator

Operators following the instructions of their supervisor or the Shift Charge


Engineer are permitted to handle materials to be used in the operation of the plant.
Operators are allowed to turn on the power supply, startup equipment, open up or
remove covers or panels on receipt of an instruction or authorization from their
superior.
Operators are permitted access to emergency stop devices following instructions
given by their superior when dangerous or hazardous situations are recognized.

Maintainer

MM-M02.01

Rev.003

Maintainers are permitted to perform maintenance on the plant. They will also
perform troubleshooting routine and periodical inspections of the installed
equipment. The maintainer will also work under the supervision of MHIs
supervisors during on-the-job training and annual maintenance and overhaul work
if MHIs supervisors are requested to witness periodical inspections, etc.
Maintainers MUST have attended the training programme initially provided by MHI
and subsequently by the Customer, and they must have obtained the necessary
knowledge and maintenance skills to understand the characteristics of their tasks
before actually starting their work.

Forced Draft Fan


Mitsubishi

Contact Address
For any question or any clarification required, please do not hesitate to contact MHI
through the following address (es).

For Support before Operation:


MITSUBISHI HEAVY INDUSTRIES, Ltd.
Nagasaki Shipyard & Machinery Works

MM-M02.01

Rev.003

1-1, Akunoura Machi, Nagasaki 850-063

Forced Draft Fan


Mitsubishi

xi

Abbreviations
Abb.

Expanded Form

Abb.

Expanded Form

American Society for Testing and


Materials

FDF

Forced Draft Fan

BMCR

Boiler Maximum Continuous


Rating

MB

Moving Blade

CCW

Counter-Clock Wise

NDE

Non-Drive End

CCCW

Closed Circuit Cooling Water

NOL

Normal Oil Level

DE

Drive End

PPE

Personal Protective Equipment

DP

Differential Pressure

DTI

Dial Test Indicator

MM-M02.01

Rev.003

ASTM

Forced Draft Fan


Mitsubishi

xii

List of Vendor Manuals


Description

Manufacturer

Handling Manual of Lubrication Oil


Unit for FD Fan

Daikin Hydraulic Engineering Co. Ltd.


Japan

Handling Manual of Pleated Type


Accumulator

Nippon Accumulator Co., Ltd.


Japan

MM-M02.01

Rev.003

Item No.

Forced Draft Fan


Mitsubishi

xiii

Arrangement of the System


Maintenance Manual
This manual is arranged as follows.

Chapter 1
Explains health and safety issues during installation, operation, maintenance,
disassembly and reassembly of the FDF.

Chapter 2
Describes the construction, purpose, and function of the FDF and the associated
parts.

Chapter 3
Describes the FDF parts, using the relevant Data Sheets.

Chapter 4
Describes the Preventive, Routine, and Outage Maintenance.

Chapter 5
Describes the disassembly and reassembly procedures, necessary to obtain access
to internal parts for inspection and repair during FDF overhaul.

Chapter 6
Describes the corrective maintenance procedures to be followed to investigate,
identify and remedy defects occurring during operation.

Rev.003

Describes the lubricants and its frequency and quantity of applications.

MM-M02.01

Chapter 7

Includes Torque Chart, Spare Parts, Special Tools and Vendor Drawings/ Documents

Forced Draft Fan


Mitsubishi

xiv

Chapter 1

Safety

C h a p t er

1 S af et y
1.1

Feature of Forced Draft Fan Safety


The function of the Forced Draft Fan is to supply combustion air to the steam
generator. Hence this is very critical equipment for uninterrupted power
generation.
The FDF is an axial fan with a rotor (moving) blade pitch control mechanism for
controlling the air flow and is fitted with aluminum blades. Absolute care must be
taken during maintenance of these fans and also cleanliness of the fan internal
is very important. If not, the fan blades will be damaged by the foreign particles
and will lead to the reduction of boiler load or stoppage of generation due to non
availability of the fan.
Like any other critical rotating equipment, this fan also has many clearances
with close tolerance. Utmost care is to be taken to maintain these values as per
this manual. Incorrect clearances can either lead to the damage of the fan or
hamper the performance of the equipment.
For the proper functioning of the bearings and also for the control of the blade
pitch, the FDF is provided with an oil system. Any oil leak and foreign particles in
the system is not only dangerous to the equipment but it also can cause the
area around the fan to be slippery leading to the fall of operating personnel. Oil
leakage and foreign particles also can lead to a fire.
Considering the above fact, a constant monitoring of the fan and its oil unit is
necessary.
During normal conditions, all the standard safety precautions are to be followed.

MM-M02.01

Rev.003

During outage maintenance, proper safety procedures are to be followed by the


operating personnel who will purge all systems before issuing a Permit to Work
to the Maintenance Staff.

Forced Draft Fan


Mitsubishi

1-1

Chapter 1

1.2

Safety

Warnings Description
Safety of personnel working in the power plant is the most important matter. And
all kinds of consideration to avoid dangerous conditions are studied and applied
to the design of the power plant. However, certain risks are unavoidable due to
the nature of the plant.
This manual classifies the severity and hazard level of such risks by two
categories, DANGER and CAUTION. Read and understand the indications
thoroughly before operation or maintenance of the plant.
The contents of wordings, DANGER and CAUTION are described as follows;
Kinds

Meaning of Warnings
DANGER indicates an imminently hazardous situation
during use of the Forced Draft Fan, which, if not avoided,
could result in death or serious injury, or serious
damage to the property or environment.
CAUTION indicates a potentially hazardous situation

CAUTION

during use of the Forced Draft Fan, which, if not avoided,


may result in minor injury or minor damage to the
property or environment.

This manual also uses the following indicators in addition to the hazard level
indications described so far.

Kinds

Meaning of Warnings
IMPORTANT describes the particular information or
items that personnel must know during operation and

IMPORTANT

maintenance of the Forced Draft Fan, and that, if not


heeded, may result in an accident of an in-assessable
hazard level.
NOTICE describes useful information and tips for
operation and maintenance of the Forced Draft Fan.

MM-M02.01

Rev.003

Notice

Forced Draft Fan


Mitsubishi

1-2

Chapter 1

Safety

1.2.1 Definitions of Serious Injury, Minor Injury,


Serious Damage to Property, and Minor Damage to
Property
Serious Injury
This term describes injuries, which leave after effects such as loss of
eye sight, permanent disability, bone fracture or breakage, gas
inhalation, asphyxiation, electric shock, hospitalization or prolonged
hospital visits for treatment.

Minor Injury
This term describes injuries, which do not require hospitalization or
prolonged attention at a hospital (injuries other than the serious
injuries described above).

Serious Damage to Property


This term describes damages, which require a suspension of
productive activity for one day or more due to restoration of the
damaged property.

Minor Damage to Property

MM-M02.01

Rev.003

This term describes damage, which does not require any suspension
of productive activity due to restoration of the damaged property.

Forced Draft Fan


Mitsubishi

1-3

Chapter 1

Safety

1.2.2 Symbol
In this manual, the following symbols are added for easy understanding
of the contents of warnings and are found next to DANGER,
CAUTION and other indications.
These symbols are in compliance with ISO 3684.
Symbol

Description
This symbol indicates the possible presence of high voltage, and
warns of a hazard which may result in system shock, burn or
death by electric shock if safety precautions are neglected or the
system is handled incorrectly.
This symbol indicates a movable section that is inside a safety
cover or is exposed.
Movable parts may inflict laceration or bone fracture to body parts
such as a hand by pinching the hand and/or clothing.
This symbol indicates the presence of parts the surface of which
could be hot, and may cause a burn if handled incorrectly.
This symbol indicates that care should be taken where you place
your feet when moving around the area.
Risk of injury by tripping is present near this symbol due to
factors such as a location with an unstable surface, or
obstructions such as scaffolding, temporary pipe lines, or other
protrusions.
This symbol indicates the possible presence of gas (es) harmful
or asphyxiant to personnel.
Be sure to ventilate fully before work commences.
This symbol indicates caution against the handling of a heavy
object or working in an abnormal position.
Do not work in an abnormal posture which may damage your back
or waist.
This symbol indicates prohibited items or actions during the

MM-M02.01

Rev.003

operation and maintenance of the Forced Draft Fan.

Forced Draft Fan


Mitsubishi

1-4

Chapter 1

1.2.2

Safety

Symbols (Continued from previous page)

Symbol

Description
This symbol indicates that personnel must not touch since the
surface is hot.
Do NOT enter any area where this symbol is displayed.

This symbol indicates that the entry of personnel is prohibited.


Do NOT enter any area where this symbol is displayed.

This symbol indicates that physical contact is prohibited.


Do NOT touch or enter a location or enclosure where this symbol
is displayed.
This symbol indicates that the stated items or actions in the
warning notices relative to operation and maintenance of the
Forced Draft Fan are mandatory.
This symbol indicates a movable section that is inside a safety
cover or exposed.
Do NOT touch any equipment where this symbol is displayed.

1.2.3 Hazard Warning Label


Hazard warning labels are applied where potential hazards are present
during operation and maintenance activities.
Hazard warning labels will be in appropriate sizes and colors that will
catch the eye and the attention of personnel. They also have symbols
that show the hazard types, in addition to the descriptions of warning
contents.

IMPORTANT
Personnel are requested to confirm the location of, and to read, and
thoroughly understand the contents of all hazard warning labels
applied to this Forced Draft Fan. If any of the hazard warning labels
Rev.003

peel off/wear out or become unreadable, install a new label in the

MM-M02.01

original location without delay.

Forced Draft Fan


Mitsubishi

1-5

Chapter 1

WARNING

Safety

DO NOT COME
NEAR TO SHAFT
EXPOSED ZONE
WHEN IN
OPERATION

PINCH POINT

STEEP
DROP

DO NOT
ENTER

DO NOT
TOUCH

DO NOT
TOUCH

MM-M02.01

Rev.003

TB0001_A

FIGURE 1-1
Forced Draft Fan
Mitsubishi

TYPES OF HAZARD WARNING LABELS

1-6

Chapter 1

1.2.4

Safety

Hazard Area

IMPORTANT
Only trained maintainers or operators are allowed to enter the
maintenance work area. Entry to the area by personnel untrained
could cause not only injury but also serious damage to the Forced

MM-M02.01

Rev.003

Draft Fan.

Forced Draft Fan


Mitsubishi

1-7

Chapter 1

1.3

Safety

Risk Assessment Standard


As prepared by the Design Section as per MIL STD822D.
TABLE 1-1

RISK ASSESSMENT STANDARD


Detailed Description of Impact on each Object

Category

Safety

Catastrophic

II

Critical

III

Marginal

VI

Negligible

- Unit shutdown (unit cannot be


operated)
- More than 4 days for repairing
- Unit shutdown (can not be
operated)
- Within 3 days for repairing
- Unit shutdown (can not be
operated)
- Can be repaired by Customer

TABLE 1-1

- Death

- Harmful gas, coal or oil leakage


- High pressure and temperature
material leakage such as steam,
water, air and gas, oil, coal etc.
- Low oxygen

- Serious Injury

- Same as the above

- Minor Injury
(with
hospitalization)
- Minor Injury
(without
hospitalization)

- Same as the above


- High temperature surface
- High elevation or unstable
- Not harmful and high pressure
& temperature leakage
-Mechanical protected

Description

Category

Detailed

(A)

Frequent

Repeating occurrence

1 time / 1 or 2 months

(B)

Probable

Known to occur, or, it has happened

1 time / 1 year

(C)

Occasional

Could occur

1 time / 5 years

(D)

Remote

Not likely to occur

1 time / 10 years

(E)

Improbable

Practically Impossible

1 or 2 times / total life

TABLE 1-1
Hazard
Categories
Frequency
of Occurrence

Rev.003

Environment

RISK ASSESSMENT STANDARD (CONTINUED)

Definition

MM-M02.01

Health

RISK ASSESSMENT STANDARD (CONTINUED)


I

II

III

VI

Catastrophic

Critical

Marginal

Negligible

(A)

Frequent

13

(B)

Probable

16

(C)

Occasional

11

18

(D)

Remote

10

14

19

(E)

Improbable

12

15

17

20

Forced Draft Fan


Mitsubishi

1-8

Chapter 1

Safety

DANGER ZONE
(Contains the high temperature
& high pressure medium such
as steam, water, air and gas,
coal, oil etc)

MM-M02.01

Rev.003

WORKING FLOOR

MPTD-3-0536

Forced Draft Fan


Mitsubishi

FIGURE 1-2

FDF MAPPING FOR HAZARDOUS AREAS


1-9

Chapter 1

1.4

Safety

Safety Measures
1.4.1 Work Permit System (Lockout / Tagout)
Work permit system is applied when equipment is shutdown for
maintenance work, to complete the maintenance work under a safe
condition. The outline of the work permit system is as follows:
(1)

The Maintenance Engineer applies for the work permit clearly


indicating the content of the maintenance work that he wants to
do, and submits it to the Shift Charge Engineer.

(2)

The Shift Charge Engineer passes the work permit form to the
operator to study and decide the isolation method from the line in
operation on the mechanical and electrical view point and then
report to the Shift Charge Engineer with his comments on the
hazard conditions for the work.

(3)

The Shift Charge Engineer gives work permit number and


prepares necessary tags to show the work permit number and
the situation of isolation by valves and power supply. He will then
instruct the operators to set the isolation condition following the
work permit form.

(4)

The operators will open the breaker and set the valves to the
specified condition, they will drain and vent the equipment to be
worked on, and the breaker and the valves are then locked. The
operators return the work permit to the Shift Charge Engineer.

(5)

The Shift Charge Engineer checks the isolation and will issue the
signed work permit to the Maintenance Engineer, or his
representative.

(6)

The Maintenance Engineer orders the start of the maintenance


work to the personnel nominated.

(7)

The Maintenance Engineer or his representative will then return


the signed work permit to the Shift Charge Engineer after making
sure the maintenance work is completed.

(8)

The Shift Charge Engineer will then send operators to release the
locks and return to the original situation.

(9)

The operators check the situation and report that the system is
now back to the normal condition when signing off the work
permit.

Rev.003

(10) The Shift Charge Engineer makes sure that the work under the
permit is completed and files details in the log book.

MM-M02.01

The work permit system is to clarify responsibility for the works on each
step and to ensure that the work is performed safely.

Forced Draft Fan


Mitsubishi

1-10

Chapter 1

Safety

1.4.2 General Cautions on Personnel in Working Area


1.4.2.1

Cautions against Rotating Equipment


All couplings on rotating machines are covered by the
coupling cover but whole parts of the shaft are not fully
covered. It is recommended that the following warning is
observed strictly.

Do not approach or operate the equipment where protective


covers have been removed. Get additional supervisor
assistance.

Make sure that the breaker for the motor is opened when you
are required to remove the cover.

Care must be taken of the exposed rotating parts especially


in the area between the casing , the coupling and moving
blades.

All shafting, coupling and other rotating parts must be


guarded in order to prevent accidental contact.

1.4.2.2

Cautions against Electrical Equipment

MM-M02.01

Rev.003

The electrical equipment covered under this section


includes all the concerned plant equipment and the
maintenance tools like grinders, lamps, welding equipment
etc. though live parts of the plant equipment or
maintenance tools are insulated; be sure to observe the
following cautions. Failure to observe them may cause
fatal accidents, personal injuries and damage to the
electrical equipment.

Forced Draft Fan


Mitsubishi

Always, confirm that power supply is disconnected at the


up-stream side of power supply system and it is locked
according to the Work Permit.

Do not remove or open panels or doors labeled with high


voltage live part warning label not included in the Work
Permit.

Ensure the proper earthing is provided for all electrically


operated tools and equipment used for maintenance works.

When using lamps for internal inspection, ensure that a low


voltage system (24volts) is available.

Make sure that no materials or Parts remain in the Panel or


terminal box before closing them finally.

1-11

Chapter 1

1.4.2.3

Safety

Cautions against High Temperature Sections


Various equipment and pipelines contain high temperature
steam or water in the plant, and most are insulated on their
surface.
There are also several hot spots in the wide area of the
Plant where some specified equipment and pipe lines are
not insulated, and as the temperature is quite high, you
could get burned.
Please observe the following cautions to avoid burn injury.

CAUTION
Wear suitable working wear including gloves, to avoid direct
contact to hot spots in the plant.

Clinkers in the boiler bottom are often very hot inside even
though they look cool on the outer surface.

Always wear gloves in this situation.

Level gauges of pressure vessels including connecting pipes


are not insulated to cool down the steam to drain.

Sampling piping is not insulated to cool down the steam to a


suitable temperature for the analyzer except in the places
located close to the working area for personnel.

All exhaust pipes of the safety valves and the exhaust pipe of
the boiler flush pipe are not insulated.

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

1-12

Chapter 1

1.4.2.4

Safety

Cautions for Steam Leak in the Plant


The steam leak especially from high temperature steam
may cause serious injury to the personnel and it must be
repaired at an early stage of the leakage. The following
pre-cautions must be followed to find leakage at an early
stage.

Water drips may occur at the insulated parts such as the


connected parts of the lagging. The leaking point can be
found by removing insulation partially using great care.

As you approach the leakage, the water will change to visible


steam. It is now too dangerous to remove the insulation.

Leakage of the superheated steam only makes whistling


noise without generating white steam. It is very dangerous to
approach the noise area.

Contact the Charge Engineer to obtain a Permit to Work


before repairing the damage.

Be well aware of the steam. The steam could leak from the
water system containing water at 100C or higher even if it is
a low pressure type water system.

High temperature drain or steam could leak from the flush


pipe during start-up.

If not avoided, the steam or vapor can enter the inside of your
working wear through the small gap between the body and
the clothing.

1.4.2.5 Caution against Oil / Coal Leak in the Plant

Oil / Coal leakage is very dangerous. It is a potential fire


hazard.

Rev.003

Any oil spillage must be reported to the Shift Charge


Engineer.

MM-M02.01

CAUTION

Oil leaks make the area slippery and people are advised to
move around these areas carefully.

Forced Draft Fan


Mitsubishi

1-13

Chapter 1

1.4.2.6

Safety

Cautions against Chemicals


Pay attention to the items listed below to prevent any
accident related to the chemicals in the plant.

IMPORTANT
Precaution against chemicals:

Operate chemical injection systems by strictly following the


instruction of the chemist. The operator must use suitable
protective tools.

Disposal:

Observe the rules and regulation of the installation site.

Material safety data sheet (hereafter MSDS):

Always understand the content of applicable MSDS in


advance, and observe the notified instructions when
handling.

Emergency response:

Solution against emergency must be thoroughly instructed to


all personnel involved so that the fullest measures can be
taken against any situation.

1.4.2.7

Cautions against Combustible Materials/


Storage Areas

MM-M02.01

Rev.003

IMPORTANT

Forced Draft Fan


Mitsubishi

Storage containers must be clearly marked to indicate the


content.

Bunding must be provided for bulk tanks.

Suitable fire protection must be provided for each area.

Do not store bulk combustible materials on the site.

Small quantities of combustible materials must be stored in


fire resistant cupboards.

Combustible materials must be segregated from other


equipment.

1-14

Chapter 1

1.4.2.7

Safety

Cautions against Combustible Materials /


Storage Areas (Continued)

IMPORTANT

Leakage of gasoline has the risk of fire. Maximum storage


quantity of gasoline outside of the dispensing pump is five
liters.

Emergency response:

Personnel directly involved in combustible materials MUST be


properly trained and thoroughly instructed. Other personnel
in the vicinity must be aware of the dangers and take
precautions in all situations.

1.4.2.8

Cautions against Lack of Oxygen

Check that the oxygen content in the equipment vessel or in


the confined space is between 18~22% before entering, and
ensure sufficient ventilation.

Continue monitoring oxygen and ventilation during


inspection.

It is recommended that you do not enter the equipment,


vessel or confined space alone but if the situation demands
that you must enter, take the necessary preventive safety
measure provided, breathing system etc, and find a partner
who will wait for your return at the point of entry, keeping in
verbal contact throughout.

Make complete arrangements for rescue.

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

1-15

Chapter 1

1.4.2.9

Safety

Cautions against Lifting Heavy Object


Be careful during the removal/installation of any
equipment during maintenance.

CAUTION
Do NOT attempt to move or lift equipment in an abnormal

posture. ALWAYS install/remove equipment, using a forklift or


a crane. A normal lift without mechanical aid should be
handled by using two or more persons.
Failure to observe the above may cause injury due to dropped

equipment, back or waist injury or damage to the equipment.

1.4.2.10 Caution against Sharp Objects

CAUTION
Use leather gloves when handling parts with sharp edges.

1.4.2.11 Cautions using Fork Lift

CAUTION
Do NOT permit anyone to stand below any item being lifted

under any circumstance.


Failure to observe this may cause fatal accidents.
When using a forklift, ALWAYS lift the objects parallel to the

ground while considering the center of gravity.


Otherwise, lifted objects may fall and serious damage could

occur.
A forklift is often used to transfer small machines. Check fork

MM-M02.01

Rev.003

insertion position for the forklift prior to use. Be careful, as


marks which indicate the fork insertion positions are
sometimes hidden by wraps or packing materials.

Forced Draft Fan


Mitsubishi

1-16

Chapter 1

Safety

1.4.2.12 Cautions using Crane

CAUTION
A crane is often used to transfer heavy parts. Check for any
possible risks which could occur during hoisting and
transportation before operating the crane.
Check of the equipment:
Check the crane, the crane hook and all related items before

use. Use wire ropes which can withstand the weight of the parts
multiplied by a safety factor.
Inspect the shackles, eyebolts, jigs and wire ropes provided for

the hoisting work prior to the actual hoisting.


Perform periodical inspection (dye penetrant test) of hoisting

tools at least once a year.


Rigging / Slinging work:
Only authorized personnel can perform slinging work and

operation of the crane.


Work area:
Before hoisting, secure a working area around the part to be

lifted and prohibit the entry of unrelated personnel.

Hoisting method:
Hoist the part parallel to the ground while paying attention to

the center of gravity.


Do NOT permit any person to stand under the part being lifted.
Pay attention to and ensure that all persons are clear of the

equipment being lifted.


Hoisting point:
Do NOT hoist any parts from a position other than the specified

hoisting points.
Unpacking:
Do NOT unpack any part until it is located in the designated

location.
Rev.003

Protection of machine:

MM-M02.01

Avoid any impact to the unpacked parts.

Forced Draft Fan


Mitsubishi

1-17

Chapter 1

1.4.2.13
a)

Safety

Disposal
Water disposal including oily drain
The water is disposed to the plant drain system. The water
must be carefully disposed according to the materials
contained in the water. The water drain system is
separated into three categories that are rain water,
chemical water and oily water.
The waste waters are treated and then discharged into the
public drain system.

b)

Chemical disposal
Chemicals must be handled following the instruction of the
MSDS and disposed to the chemical drain system.

c)

Solid disposal made by maintenance work

MM-M02.01

Rev.003

For disposal from the site, observe the local legal


regulations.

Forced Draft Fan


Mitsubishi

1-18

Chapter 1

1.5

Safety

Emergency Measure
1.5.1 Evacuation on Emergency Case
1.5.1.1

Evacuation Route
Following items are considered on design and installation
of emergency evacuation.

IMPORTANT
Each building installed in the plant is provided with at least two

exits. A clear indication of the exits can be seen from anywhere


in the building as the exit sign is illuminated using the
emergency power supply.
Evacuation routes are indicated on each floor of the building,

directing personnel to the exits.


Keep the evacuation routes completely free from materials and

tools.

1.5.1.2

Evacuation of Disabled Persons Who Cannot


Move by Themselves
The following are necessary items, prepared for emergency
evacuation.

IMPORTANT
It is recommended to keep a stretcher available for

emergencies at the places selected as being secure at the


safety meeting.
If you find this kind of accident, inform the rescue team, and

MM-M02.01

Rev.003

attempt to bring the collapsed person to the first aid station.

Forced Draft Fan


Mitsubishi

1-19

Chapter 1

1.5.1.3

Safety

Evacuation from Power House


Following are guidance for the evacuation from the power
house.

IMPORTANT
An evacuation place for personnel to gather in after evacuation

from the power house in an emergency must be predetermined


and explained beforehand in the emergency training.
Evacuation directive must be given by the responsible person

such as Shift Charge Engineer, and all personnel must be


alerted in the power house repeatedly with an available
broadcast facility.
All people working in the power house must stop their work

immediately and leave the power house to the gathering place.


When evacuated to the evacuation place, make sure

MM-M02.01

Rev.003

that there is no one missing.

Forced Draft Fan


Mitsubishi

1-20

Chapter 1

Safety

1.5.2 Fire Accident

IMPORTANT
Clearly show the location of fire alarm push button and fire

extinguisher to make everybody take the first step at fire


protection.
Inform everyone concerned that a fire has now started if you

discover a fire.
Start fire fighting using the fire extinguisher located near the

fire site.
The operators must check the plant is ready for trip, and wait

for order from the responsible person.


The operator and other personnel must transfer the fire fighting

to the fire fighting team when they arrive at the fire site and the
operators must wait for instruction from the Shift Charge
Engineer. All other personnel must immediately start
evacuation.
If unit trip is decided, the operator must trip the plant manually.
The operators must evacuate from the power house according

to the instruction of the responsible person immediately after


shutdown of the unit.
If the fire is extinguished successfully, the operators should

return to the power house as required by the Shift Charge


Engineer and start inspection of the equipment for restart of the
unit.
Based on the inspection, the responsible person should decide

whether to operate the unit again or shutdown for repairing.


After the inspection or repair, and then checking the equipment

MM-M02.01

Rev.003

and/or system, start up the unit again.

Forced Draft Fan


Mitsubishi

1-21

Chapter 1

Safety

1.5.3 Earthquake
In the case of an earthquake, the shift charge engineer or operator
must judge whether the unit trip is necessary according to the intensity
of the earthquake, and immediately trip the unit manually. If the unit is
tripped, all equipment must be carefully checked on its operation status
and tripped if abnormal phenomena are found.
In the local area, mechanical and/or thermal shocks may be given to
the equipment, piping, instruments and electrical panels. Be sure to
observe the following when completing the inspection.

Check that the lubricating oil pump is running. Bearings of the

equipment will be damaged if lubricating oil is not supplied.


Check the piping and equipment for steam and water leakage. The

steam or high temperature water leakage may cause serious


injury to the personnel and it must be repaired at an early stage of
the leakage.
Check the pulverizers and /or coal silos for signs of a fire. If a coal

fire does start, make sure that CO2 fire fighting system is properly
operated.
Check the position of boiler seismic stopper. Since the boiler

seismic stopper must be anchored at the original position, boiler


cannot be re-started if the slippage is found. If the stopper is not
at the original position, please contact MHI.

CAUTION
Check the piping and equipment for breaking and the dropping of

insulation. Since the exposure of hot surface may cause burn


injury, it must be repaired by a maintainer fully dressed in his
personnel protective equipment.

1.5.4 Explosion Accident

Rev.003

Do not use a fire in a hazardous area where the combustibles

MM-M02.01

(hydrogen gas, oxygen gas, coal, fuel oil, etc.) are stored or
handled. Use of a fire in a hazardous area could cause serious
injury to personnel and serious damage to equipment due to an
explosion.

Forced Draft Fan


Mitsubishi

1-22

Chapter 1

1.6

Safety

Qualification and Training


The system must be operated only by authorized operators & maintenance
supervisors.
The customer shall authorize all operators and maintainers, who are involved in
the operation and maintenance of this plant, either by the training course given
by Mitsubishi, or by the customers own personnel assessment.
Operator and maintainer training course (both classroom training and On Job
Training (OJT)) will be provided by Mitsubishi before the handing over of this
plant. The customer must train and assess new operators and maintainers who
join after the turn-over according to his own procedure and standard, (Mitsubishi
training course may still be available if required).

Operator and Maintainer can read and fully understand the description of
this manual.

Operator and Maintainer can understand the related P & ID, logic diagram.

Operator and Maintainer know the location of the system equipment


including pipe routes, valves and instruments.

Operator and Maintainer have fundamental knowledge of the function of


each equipment.

Operator can operate the equipment and the system manually at local
stations.

Operator can operate the system remotely using the DCS system.

Operator can respond suitably for any kind of alarm.

Operator knows the location of emergency exit on the power house and is
available to provide first aid treatment.

Operator knows emergency communication system operation.

Operator and Maintainer, following the Charge Engineers instruction are


aware of the isolation method for mechanical, electrical and instrumental
equipment being prepared for safe maintenance while the unit is in
operation.

Maintainer must also be able to handle the maintenance tools provided by


the owner and those supplied by the manufacturer.

MM-M02.01

Rev.003

As a minimum, operator and maintainer must satisfy the following:

Forced Draft Fan


Mitsubishi

1-23

Chapter 2

General

C h a p t er

2 General
2.1

Purpose
The purpose of this maintenance manual is to provide specific information to the
PAITON III Power Plant maintenance personnel regarding the maintenance of
the FD Fans. Although this document will convey a good knowledge and
direction regarding maintenance of the FD Fans, it is recommended that in the
event of a problem not covered in the document the person responsible should
seek assistance or instruction from the manufacturer.

References
a)

Air & Flue Gas System Flow Diagram


MHI Dwg No. 0C058-97000-2161-1A
Project Dwg No. P101-51-3-00-10-B049

b)

Forced Draft Fan Lubricant And Control Oil System P& ID


MHI Dwg No. N29-10M-7091
Project Dwg No. P101-51-3-BB-BG-W004

c)

Forced Draft Fan Particular Study


MHI Dwg No. 0C058-97000-2161-1A
Project Dwg No. P101-18-1701.03-B007

d)

Forced Draft Fan Outline Drawing


MHI Dwg No. 0C058 - N29-10P-2385
Project Dwg No. P101-50-3-BB-BG-W001

e)

Forced Draft Fan Sectional Drawing


MHI Dwg No. 0C058-N29-10M-7092
Project Dwg No. P101-50-3-BB-BG-W007

f)

Overhaul Plan For Forced Draft Fan


MHI Dwg No. 0C058-P97000-3371
Project Dwg No. G101-57-3-05-00-E029

MM-M02.01 Rev.003

2.2

Forced Draft Fan


Mitsubishi

2-1

Chapter 2

2.3

General

Overview of the FDF


Refer to Figures 2-1, 2-2, 2-3, 2-4 and 2-10.
The Forced Draft Fan (FDF) is an essential equipment / auxiliary for the supply
of combustion air to the steam generator.
Each unit of Paiton Power Project is equipped with two FD fans. Each fan
supplies 50% of the combustion air required at the Boiler Maximum Continuous
Rating (BMCR) condition.
The fan design parameters are based on air temperature of 25.5C and an air
density of 1.1665 kg/m at the fan inlet. The fan supplies combustion air to the
boiler at a static pressure of 480 mmH2O (Gauge) as shown in Figure 2-1 and
Figure 2-2.
The FDF is a single stage axial fan with rotor moving blade pitch control. It is
driven by a single speed 13.2 kV motor at a rated speed of 980 rpm. Looking
from the motor NDE side, the direction of rotation of the fan is CW.
The fan suction casing is bolted to the air inlet structure above the fan and is
supported by a steel framework. The inlet structure consists of sections bolted
together at the flanges. The top section is the air intake section and it is provided
with a wire netting of stainless steel to prevent the ingress of foreign material.
The suction silencer suction section along with the acoustic insulation on inside
of the casing is designed to reduce the air intake noise to 85 dB (A) at 1 m
distance from the equipment. The lower section is curved to direct the air into
the impeller casing.
The fans are located outside of the Generation Building at ground level. The fan
and the motor are suitably supported on the four reinforced concrete
foundations as shown in the Figure 2-2.
A hydraulic mechanism regulates the pitch of the moving blades on the rotor
which rotates at the design speed as shown in Figure 2-3.

MM-M02.01 Rev.003

Refer to Figure 2-10. An oil unit supplies the necessary high pressure control oil
required to change the pitch of the moving blades during fan operation. Oil
obtained from a connection before the control oil filter, is used at a reduced
pressure, to lubricate the fan bearings. Cooling water from the Closed Circuit
Cooling Water (CCCW) System is used to cool the lubricating oil flowing through
the cooler.

Forced Draft Fan


Mitsubishi

2-2

General

MM-M02.01

Rev.003

Chapter 2

FIGURE 2-1
Forced Draft Fan
Mitsubishi

AIR & FLUE GAS P & I D

2-3

LOCAL PANEL

Chapter 2

General

OIL UNIT
ACCUMULATOR

BLADE DRIVE UNIT


E
TRURTH N
NO

N
PLANT
NORTH

CW

FDF 3A

CL OF BOILER

CW

A-A

FLOW

FLOW

FDF 3B

FLOW

SUCTION SILENCER

SUCTION SILENCER

FLOW

KEY PLAN

FAN SPECIFICATION
FAN TYPE
MOTOR

A
FAN

FLOW

FAN FLOW RATE

Rev.003

m /min/FAN

FAN INLET TOTAL PRESS.

-50

mmH2O(Gauge)

FAN OUTLET STATIC PRESS.

480

mmH2O(Gauge)

FLUID TEMP. AT FAN INLET

25.5

FAN SPEED

980

FLUID DENSITY
RATED MOTOR OUTPUT

MM-M02.01

AXIAL FAN
21000

1.1665
2500

C
rpm

kg/m3
kW

MANHOLE

MPTD-3-0002

FIGURE 2-2
Forced Draft Fan
Mitsubishi

FD FAN OUTLINE

2-4

Chapter 2

ITEM

50
54

52

51

CL OF M/B

1
2

FLOW

MOTOR SIDE

12

33 31

MOVING BLADE

ROTOR

TEFLON RING

CRANK ARM

CRANK ARM

SERVO CYLINDER

SERVO CYLINDER COVER

SLIDING PIECE FOR CRANK ARM

SLIDING PIECE FOR CRANK ARM (WITH PIN)

10

SIDE RING OF ACTUATOR DISK


NUT FOR MOVING BLADE SHAFT

12

MOVING BLADE SUPPORT BEARING

19 18

13

INTERMEDIATE SHAFT

14

COUPLING SPACER

15

PISTON

16

PISTON RING

17

NUT FOR PISTON

18

MV-PACKING

19

PLATE FOR MV-PACKING

20

SLEEVE

21

COUPLING

22

NUT

23

BEARING BOX

24

RADIAL BEARING

25

THRUST BEARING

26

BEARING BOX COVER

27

SPHERICAL KEY

28

SLEEVE FOR BRG.

29

PILOT SLEEVE

30

PILOT VALVE

31

COVER

32

OIL COVER FOR PILOT LEAK

33

CONTROL OIL INNER PIPINGS

50

SUCTION CASING

51

IMPELLER CASING

52

REAR CASING

53

DIFFUSER

54

BAND FOR CASING

27

23

14

21 22
13

ROTATION

11

17 15 16
9

DESCRIPTION

11
10
30 32 29 7

CL OF SUCTION

53

26 28

26
24 25

MM-M02.01

Rev.003

20

General

MPTD-3-0025

FIGURE 2-3
Forced Draft Fan
Mitsubishi

FD FAN SECTIONAL VIEW

2-5

General

MM-M02.01

Rev.003

Chapter 2

FIGURE 2-4
Forced Draft Fan
Mitsubishi

FD FAN CUTAWAY VIEW

2-6

Chapter 2

2.4

General

Components
Each FDF consists of the following components:

Casing

Rotor assembly

Moving blade regulating mechanism

Main bearing assembly

Coupling

Control/lubricating oil system

2.4.1

Casing
Refer to Figure 2-5.
The fan casing consists of the following sections:

suction silencer casing

impeller casing

rear casing

diffuser casing

The suction silencer consists of an expansion joint, sound deadening


part, wire netting part and roof are bolted and seal welded. The suction
silencer components are bolted and seal welded. Sound proofing
insulation is provided on the internal surface of the suction casing. A
blind drain pipe is provided for bottom of suction casing. For
maintenance purpose a manhole is provided at the bottom of the
suction casing lower part.
The fan drive shaft penetrates the suction casing to connect with the
electric drive motor installed outside the fan casing. The suction casing
shape changes from rectangular to circular, in the direction of the flow.
The impeller, rear and diffuser casing sections are provided with inner
casings concentric to the horizontal axis of the fan and are supported
on the outer casings with support plates. A band for casing is provided
around the flanged joint of the rear casing and the diffuser.

MM-M02.01 Rev.003

Sound proofing insulation is provided for each outer casings. For the
suction casing sound proofing insulation is done internally. Ladder is
provided on both the impeller and rear outer casing for outage
maintenance.
The casing shape is specially designed to provide a streamline flow of
air to the moving blades.
Forced Draft Fan
Mitsubishi

2-7

Chapter 2

General

All the flanged joints of the casing are provided with Neoprene rubber
as a gasket. The casing shape is specially designed to provide a
streamline flow of air to the moving blades. From the rectangular inlet
connection, the air flows horizontally over the rotating blades.
Air from the atmosphere is drawn through the wire netting into the
suction casing through a silencer. It is directed towards the moving
blades via a 90-degree bend. The air flows through the annular space
between the inner casings and the outer casings.
The diffuser is connected to the discharge duct through an expansion
joint.
Oil line is routed through the inner casing bottom side to the oil unit.
Instrument tapping points are provided on the suction casing to
facilitate the measurement of static pressure.

Impeller casing

The impeller casing houses of the following:

rotor assembly

bearing assembly

The circular impeller casing gradually reduces in diameter in the


direction of the flow. A tubular inner casing, installed within the impeller
casing, houses the bearing assembly. The moving blades occupy the
annular space between the tubular inner casing and the impeller outer
casing. The impeller casing is horizontally split to ease maintenance
activities.
The annular inner circumferential surface of the impeller casing outer
side which along the circumference of the tip circle of the moving
blades is machined surface.
The upper half of the impeller casing is bolted to the lower half for easy
removal during maintenance.

Rear casing

MM-M02.01 Rev.003

The rear casing is of uniform diameter and is located between the


impeller casing at the upstream side and the diffuser at the
downstream side. The impeller casing and the rear casing are axially
split, enabling maintenance access to the rotor wheel and the
components of the moving blade regulating mechanism.
The rear casing facilitates the routing of the moving blades operating
shaft. The control oil supply and return lines to the moving blade
operating mechanism are also routed through the rear casing.
Forced Draft Fan
Mitsubishi

2-8

Chapter 2

General

The rear casing is provided with an inner casing to protect the moving
blade regulating mechanism components from damage. The rear inner
casing is supported by the stationary blades around the circumference.
A manhole is provided on the inner casing for inspection and
maintenance of the moving blade regulating mechanism.

Diffusser

The diffuser is installed downstream of the rear casing and is


connected to the discharge duct through an expansion joint. The
diffuser section gradually increases in cross-sectional area, recovering
the kinetic energy imparted by the moving blade.
The diffuser is provided with an inner casing and is supported by plate
at two locations. A manhole door is provided on the diffuser inner
casing for the entry of personnel from the discharge duct and to
carryout any inspection and maintenance of the moving blade
regulating mechanism.

2.4.2 Rotor
Refer to Figure 2-6.
The rotor is a forged component welded to a solid shaft. The rotor is
supported on the shaft at one point within the bearing box by
anti-friction bearings. The motor side and fan side of the bearing box
covers are provided with labyrinth seals to prevent oil leaks.
The DE side of the shaft is fitted with a sleeve for facilitating installation
of bearings on the shaft. The coupling half is keyed and shrink fitted to
the rotor shaft end at the DE side and locked with a nut.
The rotor is comprised of moving blades, the blade shafts and blade
regulating mechanism. The blade shafts are supported by the moving
blade support bearing and nuts. The moving blade support bearings
are of the sealed type.
The piston applied as blade pitch regulating servo cylinder piston is
located on the rotor boss. The piston is fixed by means of a sleeve and
parallel pin on one side and a nut on the other side. The servo cylinder
moves axially over the piston while both parts are rotating. The axial
movement of the servo cylinder is converted into rotary movement of
the blades by a crank arm connecting the moving blade shaft.
MM-M02.01 Rev.003

The moving blades, made of forged aluminum, are of light weight. The
moving blades have a laminar flow blade profile, high efficiency and a
good performance characteristic.
Provision is made on the rotor for the addition of weights required for
the dynamic balancing of the fan.
Forced Draft Fan
Mitsubishi

2-9

Chapter 2

General

2.4.3 Moving Blade Regulating Mechanism


Refer to Figures 2-7 and 2-8-1, 2-8-2.
The moving blade regulating mechanism regulates the blade pitch
even while the fan operates at the rated speed. The moving blade
regulating mechanism consists of the fixed piston mounted on the boss
of the rotor shaft, the movable servo cylinder and the pilot valve.
The servo cylinder and the piston rotate at the same speed as the rotor
and cylinder alone is free to move axially. The cylinder cover secured to
the servo cylinder has the necessary holes for the supply and return of
the control oil which moves the cylinder.
The pilot valve can move axially only and is located inside a sleeve
secured to the inside of a servo cylinder. This pilot valve moves in and
out to allow the flow of control oil as necessary to operate the moving
blades.
Control inner pipe (flexible hoses) on the pilot valve head enable the
flow of supply and return, control oil and leakage oil through the drain
cover.
A pneumatically operated control drive located outside of the fan casing
enables the operation of the pilot valve through a linkage mechanism.
The linkage mechanism is so arranged that a 90 rotation of the control
drive unit link rotates the moving blades through an angle of 40 to
+14. A moving blade sticking detector is provided on the linkage
between the control drive unit outside of the fan casing to detect any
excessive load for operation of the blades.

MM-M02.01 Rev.003

The servo cylinder is a compact modular design and it is easy to


overhaul. The ratio of input to output is one, yielding a good response
characteristic.

Forced Draft Fan


Mitsubishi

2-10

Chapter 2

General

2.4.4 Main Bearing Assembly


Refer to Figure 2-9.
The bearing box is supported on the inner casing of the impeller casing.
The rotor can be overhung with one bearing box. The bearing box
contains an antifriction cylindrical roller bearing at the fan end and two
ball bearings at the motor end. The cylindrical roller bearing absorbs
the radial load and the ball bearings absorb the thrust load generated
by the fan work.
End covers fitted on either side of the bearing box are provided with oil
baffles or labyrinth seals to prevent lubricating oil leakage along the
shaft from the bearing box.
Lubricating oil is supplied to the bearing box through an oil supply line
and distributed to bearings through internal holes on the bearing. An oil
bath is provided in the bearing box by means of suitable protrusions in
the lower half bearing box to match roller or ball of bearings. The
lubricating oil for the bearings is supplied from a forced lubricating oil
system, an external oil unit.

2.4.5 Control / Lubricating Oil System


Refer to Figures 2-10.
The control/lubricating oil system consists of:

one 400 liter capacity oil tank

2 x 100% control oil pump, one in operations, one in standby

control oil pump suction strainer

control oil pump discharge strainers

lube oil duplex strainers

lubricating oil cooler

one return oil strainer

an accumulator (control oil)

MM-M02.01 Rev.003

The oil pumps mounted on the top of the reservoir draw oil from the
reservoir through two dedicated individual suction strainers. The oil is
then filtered by two 100% capacity oil filters and supplied as control oil
at about 5.39~5.88 MPa for the blade regulating mechanism. An oil
accumulator (pre-charge N2 pressure at 1.4MPa) installed on the
control oil supply line absorbs minor pressure fluctuations.

Forced Draft Fan


Mitsubishi

2-11

Chapter 2

General

Pressure reducing valves reduce the pressure of the control oil to about
0.15~0.18 MPa and supply lubricating oil to the fan bearings. The
return control oil from the blade regulating mechanism is also directed
to the lubricating oil supply line. The oil cooler receives cooling water
from the CCCW System to cool the lubricating oil before admitting it to
the bearing box.
The oil reservoir is provided with a return oil filter to collect debris in the
return oil.
For further details, please refer to the Vendors manual, Appendix F.

2.4.6 Coupling
Refer to Figure 2-11.
The fan rotor is coupled to the drive motor with a rigid coupling.

MM-M02.01 Rev.003

The coupling consists of one intermediate shaft, two hubs (motor side
and fan side), a spacer (motor side), reamer bolts and nuts.

Forced Draft Fan


Mitsubishi

2-12

General

MM-M02.01

Rev.003

Chapter 2

FIGURE 2-5
Forced Draft Fan
Mitsubishi

FDF CASING ASSEMBLY

2-13

General

MM-M02.01

Rev.003

Chapter 2

FIGURE 2-6
Forced Draft Fan
Mitsubishi

ROTOR ASSEMBLY

2-14

General

MM-M02.01

Rev.003

Chapter 2

FIGURE 2-7
Forced Draft Fan
Mitsubishi

MOVING BLADE REGULATING MECHANISM ASSEMBLY


2-15

General

MM-M02.01

Rev.003

Chapter 2

FIGURE 2-8-1
Forced Draft Fan
Mitsubishi

LINKAGE MECHANISM ASSEMBLY

2-16

General

MM-M02.01

Rev.003

Chapter 2

FIGURE 2-8-2
Forced Draft Fan
Mitsubishi

BLADE STICKING DETECTOR

2-17

MOTOR SIDE

Chapter 2

ITEM

29

16 17
F

34

33

28

33 34

31

MOTOR SIDE

23

18
10
19

32

28

DET.G
E-E

22

C
L OF BEARING

36

T
GAS

37

VEN

35

OIL SUPPLY
OF BEARING

D-D

B
9
MOTOR SIDE

37

26

F-F

41 42

39

26

30
5

ROTATION

D
SEAT FOR
VIBROMETER

T
RO
N
IO
AT

25

OIL LEVEL

OIL LEVEL

2
E

40

E
38

37

DESCRIPTION
BEARING BOX (UPPER)

BEARING BOX (LOWER)

STOPPER

PLATE FOR BEARING KEEP

ADJUSTING RING (UPPER)

ADJUSTING RING (LOWER)

STOPPER BOLT

PIPE FOR RETURN OIL

ECCENTRIC BUSH

10

O-RING

11
12

SEAL PACKING
ADJUSTING LINER

13

ADJUSTING LINER

14

ADJUSTING LINER

15

ADJUSTING LINER

16

BOLT

17

WASHER

18

SPECIAL BOLT

19

FLAT BAR

20

BOLT

21

WASHER

22

90 ELBOW

23

TAPER PIN

24

SEAT FOR THERMOMETER

General

25

PARALLEL PIN

26

BEARING KEEP

27

OIL BATH DRAIN PLUG

28

THRUST BEARING

29

RADIAL BEARING

30

SLEEVE

31

O-RING

32

O-RING

33

BEARING INNER SPACER

34

BEARING OUTER SPACER

35

BOLT

36

PARALLEL PIN

37

SPHERICAL KEY

38

OIL BAFFLE ASS'Y (COUPLING SIDE)

39

OIL BAFFLE ASS'Y (ROTOR SIDE)

40

SHAFT

41

BOLT

42

WASHER

MM-M02.01

Rev.003

B-B

C
C-C

12 13 14 15

B
11
A-A

OIL RETURN
OF BEARING

20 21
27

24

27

MPTD-3-0037

FIGURE 2-9
Forced Draft Fan
Mitsubishi

BEARING BOX ASSEMBLY

2-18

Chapter-2

FT

FT

FT

PT

TE

2~4

General

FDF SUCTION
SILENCER

TI
TE
25A

10A

65A

15A

15A
20A
15A
15A
20A

25A

PI
40A

40A

DPI
PT
FT
XE
PS

LUBRICATING OIL RETURN

BLADE STICKING DETECTOR

20A

PILOT
LEAK OIL

20A

ZS
2

OIL SEAL
LEAK OIL

ZS

U-SEAL

LS
LI

U-SEAL
CONTROL OIL LEAK OIL

20A

20A

25A

40A

25A

PS
1

FOR MAINTENANCE

PS
6
PS
5
PS
4
65A

PS
2

LOCAL PANEL

20A

PS
3

LUBRICATING OIL SUPPLY

A-1

FOR MAINTENANCE

25A

ZS
1

CONTROL OIL SUPPLY

DU-1

CONTROL OIL RETURN

40A

F-4

PI
2

PI
1

F-6

PI
4
03HLB01AC1
C-1

WATER DRAIN

P
AIR BREATHER

TI
1

M
P 03HLB01AP202
P-2

(03HLB01AP204)

LS
1

PI
5

TI
3

OIL SUPPLY PLUG

F-1
LI
1

T-1
03HLB01BB101
(03HLB01BB102)
F-3

50A

50A

40A

MM-M02.01

Rev.003

OIL UNIT

SET POINT

5.39 ~ 5.88 MPa

0.15 ~ 0.18 MPa

RANGE
0~15MPa
0~15MPa
0~15MPa
0~1.0MPa
0~1.0MPa
0~0.4MPa

SYMBOL
PI-1
PI-2
PI-3
PI-4
PI-5
PI-6

03HLB01CP211
(03HLB01CP221)
03HLB01CP212
(03HLB01CP222)
03HLB01CP213
(03HLB01CP223)
03HLB01CP214
(03HLB01CP224)
03HLB01CP215
(03HLB01CP225)
03HLB01CP216
(03HLB01CP226)

CONTROL OIL PRESS. NORMAL INTERLOCK

03HLB01CT311
(03HLB01CT321)
03HLB01CT312
(03HLB01CT322)
03HLB01CT313
(03HLB01CT323)
03HLB01CT314
(03HLB01CT324)

FDF LUBRICATING OIL COOLER INLET


FDF LUBRICATING OIL COOLER OUTLET
COOLING WATER INLET
OIL TANK

03HLB01CT011
(03HLB01CT021)
03HLB01CT001
(03HLB01CT051)
03HLB01CT002
(03HLB01CT052)
03HLB01CT003
(03HLB01CT0530

BEARING OIL TEMPERATURE HIGH ALARM


FDF 3A/3B SUCTION AIR TEMP.-A
FDF 3A/3B SUCTION AIR TEMP.-B
FDF 3A/3B SUCTION AIR TEMP.-C

03HLB01CY011
(03HLB01CY021)

BEARING VIBRATION HIGH ALARM

03HLB01CG211
(03HLB01CG221)
03HLB01CG212
(03HLB01CG222)

BLADE ANGLE 0% POSITION INTERLOCK


BLADE STICKING ALARM

FULL CLOSE ON

ZS-1
ZS-2

03HLB01CG211
(03HLB01CG221)
03HLB01CG212
(03HLB01CG222)

OIL TANK LEVEL LOW ALARM

MIN. OIL LEVEL LOWER


THAN 50mm (122 ) ON

LS-1

03HLB01CL311
(03HLB01CL321)

OIL TANK LEVEL

MAX. OIL LEVEL 400


MIN. OIL LEVEL 170

LI-1

03HLB01CF101
(03HLB01CF151)
03HLB01CF102
(03HLB01CF152)
03HLB01CF103
(03HLB01CF153)

FDF 3A/3B AIR FLOW-A


FDF 3A/3B AIR FLOW-B
FDF 3A/3B AIR FLOW-C

03HLB01CP101
(03HLB01CP151)

FDF 3A/3B SUCTION PRESS.

CONTROL OIL PRESS. LOW TRIP


LUBRICATING OIL PRESS. NORMAL INTERLOCK
LUBRICATING OIL PRESS. LOW TRIP

0~10MPa
P>
= 4.90 MPa ON
0~10MPa
P<
= 4.41 MPa ON
< 1.96 MPa ON
0~10MPa
P=
> 0.13 MPa ON 0.02~0.2MPa
P=
< 0.12 MPa ON 0.02~0.2MPa
P=
< 0.08 MPa ON 0.02~0.2MPa
P=

PS-1
PS-2
PS-3
PS-4
PS-5
PS-6

0~100 C
0~100 C
0~100 C
0~100 C

TI-1
TI-2
TI-3
TI-4

T>
= 70 C ON

0~150 C

TE-1
TE-2
TE-3
TE-4

V>
l ON
= 105um

0~300um(P-P)
l

XE-1

EQUIPMENTS LIST
SYMBOL

TI
4

F-2

03HLB01CP311
(03HLB01CP321)
03HLB01CP312
(03HLB01CP322)
03HLB01CP313
(03HLB01CP323)
03HLB01CP314
(03HLB01CP324)
03HLB01CP315
(03HLB01CP325)
03HLB01CP316
(03HLB01CP326)

DESCRIPTION
FDF CONTROL OIL PUMP 3 A1/B1 OUTLET
FDF CONTROL OIL PUMP 3 A2/B2 OUTLET
CONTROL OIL SUPPLY PRESS.
FDF LUBRICATING OIL COOLER INLET
FDF LUBRICATING OIL COOLER OUTLET
LUBRICATING OIL SUPPLY PRESS.

TI
2

OIL DRAIN

03HLB01AP201
(03HLB01AP203)

P-1

20A

PI
6

F-5

65A

25A

PI
3

40A

25A

25A

THERMOMETER
(LOCAL)
THERMOCOUPLE
PRESSURE GAUGE
(LOCAL)
DIFFERENTIAL PRESSURE GAUGE
PRESSURE TRANSMITTER
DIFFERENTIAL PRESSURE TRANSMITTER
VIBRATION METER
PRESS. SWITCH
LIMIT SWITCH
LEVEL SWITCH
LEVEL GAUGE
GLOBE VALVE
GLOBE VALVE (NORMALLY CLOSED)
REGULATING VALVE
SAFETY VALVE
3-WAY VALVE
STOP CHECK VALVE
BUTTERFLY VALVE
NEEDLE VALVE
REDUCER
SIGHT FLOW
STRAINER
OIL COOLER
ORIFICE
ACCUMULATOR
CHECK DAMPER
FLANGE
EXPANSION JOINT
FLEXIBLE HOSE
CAP
OIL LINE
DRAIN LINE
COOLING WATER LINE
AIR LINE
CAPILLARY
ELECTRIC SIGNAL
AIR SIGNAL

PRESSURE GAUGE

MOTOR

INSTRUMENTS LIST

PRESSURE SWITCH

FDF

EXPLANATION OF SYMBOL
DESCRIPTION
INSTRUMENT(FIELD MOUNTED)
LOCAL PANEL MOUNTED INSTRUMENT

THERMOMETER

SYMBOL

THERMO
COUPLE

03HLB01AN101
(03HLB01AN102)

LEVEL LEVEL LIMIT


GAUGE SWITCH SWITCH

15A

TE
1

15A

03HLB01BS101
(03HLB01BS102)

XE
1

P-1
P-2
F-1
F-2
F-3
F-4
F-5
F-6
C-1
A-1
T-1
DU-1

DESCRIPTION
FDF CONTROL OIL PUMP 3 A1/B1
FDF CONTROL OIL PUMP 3 A2/B2
RETURN OIL STRAINER

LUBRICATING OIL DOUPLEX STRAINER


FDF LUBRICATING OIL COOLER
ACCUMULATOR
OIL TANK
DRIVE UNIT
FORCED DRAFT FAN
FDF MOTOR

REMARKS
7.85 MPax 34.5 /min
AC 416 V x 50 Hz
7.5 kW x 6P

100 mesh
150 mesh
150 mesh
20u
l
20u
l
200 mesh
3 TON/Hr
60
400
Torque 102 N-m
21000 m3/minx480 mmH2O
2500kW x 6P

COOLING WATER

FIGURE 2-10

FDF LUBE AND CONTROL OIL P & I D

MPTD-3-0026

Forced Draft Fan


Mitsubishi

2-19

Chapter 2

ITEM
1
2
3
4
5
6
7

General

DESCRIPTION
MOTOR COUPLING
SPACER
REAMER BOLTS
REAMER BOLTS
NUT
WIRE
INTERMEDIATE SHAFT

A-A

FAN SIDE

MOTOR SIDE

PUT MATCH MARKS

PUT MATCH MARKS

MM-M02.01 Rev.003

MPTD-4-0036

FIGURE 2-11

Forced Draft Fan


Mitsubishi

INTERMEDIATE SHAFT AND COUPLING ASSEMBLY

2-20

Chapter 3

Specifications

C h a p t er

3 Specifications
TABLE 3-1

FORCED DRAFT FAN

Subject

Specifications

Equipment number

03HLB01AN101
03HLB01AN102

Quantity

Two (2)

Fan

Coupling
Bearing

Manufacturer

MHI

Model

ML-H1-R132/270

Type

Axial Fan, Variable Blade Control

Manufacturer

MHI

Type

Rigid Coupling

Manufacturer

J TEKT

Type

Anti-friction bearing (MHI special type)


Bearing No.

Major material

MM-M02.01

Rev.003

Weight
(approximately)

Forced Draft Fan


Mitsubishi

Basic load rating (kN)


Dynamic

Static

NJ338AF3C3
+DP30-1

987

1260

7338B/1DAD
T/30-1

1170

4220

Casing

Rolled Steel for General Structure

Moving Blade

Forged Aluminum

Rotor Shaft

Carbon Steel for Machine Structural Use

Bearing (Box/Body)

Cast steel

Coupling

Cast steel

Silencer

33.0 t (including expansion joint)

Rotor assembly

3.0 t

Suction Casing

17.0 t (including insulation)

Impeller Casing
Upper Half

2.0 t (included insulation)

Impeller Casing
Lower Half

3.0 t (without insulation)

Rear Casing
Upper Half

1.3t (included insulation)

Rear Casing
Lower Half

1.4 t (without insulation)

Diffuser

7.6 t (without insulation)

3-1

Chapter 3

Specifications

Continued form previous page

TABLE 3-1

FORCED DRAFT FAN

Subject

Specifications

Design Rotating Speed

980 rpm

Blade

14

Performance Characteristics
Direction of Rotation

Clockwise (Viewed from motor side)

Capacity (each fan)

21,000 m3/min

Inlet pressure

-50 mmH2O

Outlet static pressure

480 mmH2O

Fluid

Air

Fluid temperature at inlet

25.5 C

Fluid density (design)

1.1665 kg/m3

TABLE 3-2

FORCED DRAFT FAN - MOTOR

Subject

Specifications

Manufacturer

Hyundai Heavy Industries Co. Ltd.

Type

HRP3 637-68E

Rated Output

2,500 kW

Rated Voltage

13,200 V

Rated Current

133.1 A

Frequency

50 Hz

Poles

Coupling

Direct

Rating

Continuous

Insulation Class

Maximum Ambient Temperature

40 C

Bearing

Split sleeve

Type

14,500 kg

MM-M02.01

Rev.003

Total Weight (approximately)

Forced Draft Fan


Mitsubishi

3-2

Chapter 3

TABLE 3-3

Specifications

FDF CONTROL OIL UNIT

Subject

Oil Specification

Specifications

ISO VG 32

Electric Power

Power

AC 380V, 7.5kW, 1,000rpm

Control Oil Pump

Type

Vane Pump

Quantity

Two (2) sets (1 Normal ; the other for


stand-by)

Capacity

34.5L/min

Working Pressure

7.85 MPa

Type

Totally Enclosed Fan Cooled Type

Quantity

Two (2) sets

Oil Tank

Total Volume

400 l

Oil Cooler

Type

Shell and Tube

Quantity

One (1) set

Water quantity

3.0 Ton/H

Oil Pump Motor

150 mesh

Return Oil Strainer

100 mesh

Lub. Oil Pump Discharge duplex


strainer

200 mesh

Control Oil Pump Discharge Strainer

20

Accumulator

60 l

MM-M02.01

Rev.003

Suction Strainer Control oil system

Forced Draft Fan


Mitsubishi

3-3

Specifications

MM-M02.01

Rev.003

Chapter 3

FIGURE 3-1

Forced Draft Fan


Mitsubishi

PEFORMANCE CURVE

3-4

Chapter 4 Preventive Maintenance

eu

C h a p t er

4 Preventive Maintenance
Preventive maintenance is carried out to avoid or minimize the possibility of failure or
deterioration of equipment performance. This requires a constant effort from
maintenance staff to ensure that the Unit is available on demand.
There are two categories of preventive maintenance, Routine Maintenance and Annual
Outage Maintenance. Routine maintenance helps to reduce the possibility of outage
and hence the downtime of machinery. Annual outage maintenance is required to
maintain the internal components of the installed equipment.
Though vendor/manufacturers recommendations provide a good basis for the
provision of a preventive maintenance schedule, the frequency and other details should
be updated from time to time based on practical experience and actual feedback
gathered through inspection and normal operation of the equipment/plant.
Consideration of these site related specific issues will make the preventive
maintenance more effective.

4.1

Prerequisites
The necessary prerequisites for the preventive maintenance of the FDF are as
follows:

4.1.1 Scheduling
Scheduling is the first activity in the preparation of a preventive
maintenance program. The schedule is to include planning to attend all
operating equipment on a fixed regular basis.
Initially, schedules will be prepared based on vendor/manufacturers
generic instructions, the schedules will, however, be updated
(frequency, nature of inspection, etc.) as site specific data becomes
available.

Rev.003

Preventive maintenance is to be coordinated with other concerned


departments. In the case of a major scheduled outage, maintenance
personnel and other concerned departments should jointly produce a
plan of activities, well in advance, to decide the inspection activities and
other logistics (such as the availability and supply of required
equipment, spare parts, and tools, etc.).

MM-M02.01

The schedule should clearly identify the critical path. Priority is to be


assigned to specific tasks that also involve parallel activities to reduce
the equipment downtime and to complete the work within the
scheduled time.
Forced Draft Fan
Mitsubishi

4-1

Chapter 4 Preventive Maintenance

4.1.2 Departmental Interface/Notification


Departmental communication is essential and interfacing between
departments is to be maintained to avoid any lack of communication
that may arise and adversely affect routine or annual outage
maintenance work.
Prior to commencing preventive maintenance all concerned persons
(shift supervisor, operators, etc.) are to be made aware of the schedule
and the nature of the activities that are to take place.
If it becomes clear that there is a problem or a conflict of interests in the
schedule (e.g. the maintenance schedule interferes with another
groups work, inter departmental works, sub contractors work etc.), this
is to be resolved by mutual agreement between the parties involved.

4.1.3 Isolation of Equipment


It is important that isolations are agreed and valid clearances and work
permits are obtained before any maintenance work is performed. The
isolation boundaries of the particular equipment to be taken under
maintenance are to be clearly identified.
In the case of an electrical isolation the power supply shall be
disconnected and/or the fuses removed. In the case of a mechanical
isolation, the valves or other mechanical means of isolation, at the
isolation boundaries are to be closed and if possible locked closed. The
system within the isolation boundaries is to be vented and
depressurized.

4.1.4 Safety Precautions


Before the commencement of any maintenance work, the person in
charge of the work site is to perform a risk assessment and method
statement for the safe execution of the job scope activities, described
within the work permit.
Risk assessment includes identifying, recognizing and understanding
the potential hazards associated with the work. The method statement
is to illustrate the safe working practices in accordance with the safety
manual and the manufacturers instruction manual to prevent personal
injury and/or equipment damage.

Rev.003

Prior to the commencement of actual work, the person carrying out the
work is to make a safety check based on the above method statement
and also use his own judgment to ensure that the equipment and the
prevailing working conditions are safe.

MM-M02.01

During maintenance work, every employee should follow the safe


working procedures detailed in the method statement.
Forced Draft Fan
Mitsubishi

4-2

Chapter 4 Preventive Maintenance

4.2

Routine Maintenance
The purpose of routine maintenance is the implementation of the preventive
maintenance program on a day-to-day basis through a planned and correctly
executed inspection.
The routine maintenance activities are very important in that if they are properly
carried out, they will enhance equipment reliability. As a result, good routine
maintenance activities may help in cost reduction in the long run through the
minimization of equipment downtime.
Cleaning is an important and necessary maintenance activity to prevent the
ingress of foreign material. Other major points are as follows: (Summarized
major routine activities are also shown in Table 4-1).

4.2.1 Preparation
a)

Spare parts, Tools and Equipment


It is important to prepare the necessary parts, tools and
equipment before commencing actual work. Routine
maintenance generally requires a standard mechanical toolkit,
consumables, cleaning materials, etc.
Any shortages of these items will affect the maintenance activity
and may delay the schedule. Personal Protective Equipment
(PPE) is necessary for maintenance staff at all times.
Maintenance work area must be barricaded showing the
necessary warning signs.
Upon completion of work, all tools and equipment should be
serviced and stored correctly to ensure availability for further use.

b)

Documentation
Documentation is an important part of any maintenance duty. All
findings should be noted on a comprehensive log sheet, reporting
all aspects of the equipment observed during the routine
inspection.
The data recorded in these documents will be useful in
determining the root cause of equipment failure found during
annual outage/corrective maintenance work.

MM-M02.01

Rev.003

Any abnormalities, if observed, are to be immediately


communicated to the concerned department/personnel for
rectification and are to be detailed in the report and the value
recorded every time.

Forced Draft Fan


Mitsubishi

4-3

Chapter 4 Preventive Maintenance

4.2.2 Inspection and Maintenance

Take care near rotating machinery, hands, feet, and clothing


can be drawn into machinery. Always check that all guards
are in place before starting any rotating machinery.

No open flames or other source of ignition permitted in fan


area.

Dont come closer around the suction silencer inlet less than
2 m.

CAUTION

Dont open the manhole when fan is running.

Check that instruction is clear when fan is running.

Dont climb on casing when fan is running.

a)

Rotor Assembly
The rotor assembly, consisting of the rotor, the moving blades
and the rotor shaft, etc. is to be monitored for vibration. Vibration
may be generated by several factors. Possible causes of
vibration are an imbalance of the rotor resulting from erosion or
damage to the rotor by foreign materials, or by dust adhering to
the impeller blades.
Another possible cause of vibration could be shaft misalignment.
If the vibration is observed to have increased, but is still within the
limit of 105 m without any other abnormality noticed, the
equipment may continue to be operated under close supervision.
If vibration alarm announced, look over the vibration and incase
of vibration increasing, stop the fan immediately. As well as
vibration, another area that deserves attention is the identification
of any abnormal noise. Any abnormal noise generated should be
investigated to identify the source. If the noise comes from the
flange joints, e.g. high noise created by air leakage from the
packing, operation may be continued, as it has no direct impact
on possible fan failure or operation.

MM-M02.01

Rev.003

However, if any abnormality is observed at the coupling, the


equipment is to be shutdown immediately for rectification of the
problem.

Forced Draft Fan


Mitsubishi

4-4

Chapter 4 Preventive Maintenance

b)

Bearings
Bearing problems generally result from lubricating oil starvation
and/or excessive vibration. Emphasis is to be given to check the
equipment operating parameters, (e.g. oil supply, oil temperature,
bearing temperature and oil tank levels).
The temperature of the returning lubrication oil from the bearing
is alarm value of 70C. Correct oil flow is to be verified through
the lubricating oil return line oil flow indicator.
Lack of cooling water flow, fouling of oil cooler tubes, presence of
dirt in the lubricating oil, deteriorated bearings may also lead to
an increase in bearing operating temperature.
Entering foreign materials leads to bearing damage. Using
un-recommend oil leads to a poor bearing performance.

c)

Moving Blade Regulating Mechanism


The moving blade regulating mechanism is to be monitored for
smooth operation. Visual inspection of the linkage mechanism is
to be carried out for looseness of pins and links.
Operational availability of blade sticking detector is to be ensured.
If there is any sign of linkage mechanism sticking, the cause
should be eliminated at the earliest opportunity depending upon
the severity of the problem. See Chapter 6 Corrective
maintenance for reference.

CAUTION
Dont come closer to drive unit and moving blade sticking
detector.

d)

Fan Casing
The fan casing is to be checked for leakage. Erosion, abrasion or
cracking may occur in the casing during fan operation. In the
event of air leakage through any part of the casing, external patch
welding work may be undertaken as a temporary measure and
the event should be recorded for inclusion in the annual overhaul
program.

Rev.003

e)

Control/Lubricating Oil System

MM-M02.01

The oil pump is to be monitored for smooth operation, seal


leakage and vibration. Any apparent problem is to be immediately
resolved.

Forced Draft Fan


Mitsubishi

4-5

Chapter 4 Preventive Maintenance

The condition of the control oil / lube oil filter is to be monitored.


When there is a high differential pressure across a filter the stand
by filter should be placed in service and the defective filter,
should be cleaned or replaced immediately to be an effective
standby.
It is most important to follow the lubricating oil requirements such
as, the frequency of replacement of the lubricating oil as per the
manufacturers instruction or based on the analysis result
received from the laboratory.
Regular visual inspection of the oil condition is recommended,
(e.g. if the color of the oil becomes green/white, it signifies that
water ingress has taken place. Alternately, if the oil gradually
becomes dark, it implies that either overheating or debris/dirt
mixing has taken place).
The tank oil level is to be monitored at frequent intervals. The
system is to be observed for any oil leakage if a gradual decrease
in oil level is noticed.
The oil flow through the return line flow indicator is to be
monitored regularly. If there is an abnormal decrease or increase
in return oil flow, the cause is to be investigated and rectified.
If oil leakage is found, inspect the oil level gauge every time. And
repair them after reducing oil pressure, if it is possible to stop the
fan.

CAUTION

If oil leakage is found, take care not to come close the


leakage point because workers can get oil in the eyes.

Dont go up on the piping not to damage the piping.


The temperature of oil in the tank should be observed on a
routine basis. The temperature should be below 70C.
For further details, please refer to the vendors manual in
Appendix F.

f)

Coupling

MM-M02.01

Rev.003

The fan coupling is to be monitored for any abnormal noise.


Noise would be heard from the coupling if there is any looseness
of the coupling bolts or coupling. Noise is also generated if the
coupling misalignment is beyond permissible limits or if the
coupling rubs the coupling guard.

Forced Draft Fan


Mitsubishi

4-6

Chapter 4 Preventive Maintenance

TABLE 4-1

No.

Description

Main Bearing

ROUTINE MAINTENANCE CHECKLIST

Major Check Item

Check Method

Check Reference

Vibration

Permanent
instruments

Less than 105 m

Temperature

Permanent
instruments

Not exceeding 70C

Action to be Taken
(if beyond acceptable limit)

Remarks

Recommended
Maintenance
Frequency

Shut down and check for bearing damage and the


rotor assembly for unbalance.
Check and clean the moving blades for any
deposits.
Check and adjust alignment.

Daily

Check for any foreign materials in the lubricating oil


Rotate the rotor assembly by hand and observe for
any rubbing noise.
Replace bearings if the vibration is not decreased
after field balancing.
2

Moving Blade
Regulating
Mechanism

MM-M02.01

Rev.003

Coupling

Casing

Forced Draft Fan


Mitsubishi

Abnormal noise

Audible

No abnormal noise.

Check and replace coupling bolts, etc., if damaged


and then re-check alignment.

Rubbing contact
with the coupling
guard

Visual and
audible

No contact between
the coupling and
coupling guard.

Adjust coupling guard clearance.

Control oil pump


discharge strainer

Visual

Not Clogged

Replace the clogged filter.

Smooth operation

Permanent
instrument

No alarm

Visual and
audible

No apparent air
leakage

Check for any air


leakage

Beware of rotating part


during maintenance

Daily

Daily

Permanent
instruments
Rectify defective regulating mechanism and linkage
mechanism after shut-down if FDF cannot be
controlled.
Tighten bolts or patch weld after shutdown.

Daily

Daily

4-7

Chapter 4 Preventive Maintenance

Continued from previous page


TABLE 4-1

No.

Description

Lubricating oil
system

Major Check Item Check Method

Oil pressure

Permanent
instrument

ROUTINE MAINTENANCE CHECKLIST

Check Reference

Lube oil supply is 0.15


to 0.18 MPa.

Action to be Taken
(if beyond acceptable limit)

Remarks

Recommended
Maintenance
Frequency

Check the lube oil pump discharge pressure and by For more details, Please refer
sight glass.
to Vendors Manual.
Check the oil flow into the bearing, pressure control
valve.
Check oil temperature.
Check Oil flow.

MM-M02.01

Rev.003

Check the operation of the stand by pump.


Oil pump bearing
temperature

Touch/ Portable No appreciable


thermometer
temperature rise

Check the cause of temperature rise.

Oil pump shaft oil


leak

Visual

No leak

Replace oil seal

Oil pump shaft


rotating condition

Visual
Audible

No abnormal noise
No abnormal trembling

Investigate and take action to normalize the


condition such as exchange of bearings.

Oil strainer

Permanent
instrument

Not clogged
Color indicator on the
top of the strainer is not
red (replacement) , but
green (normal)

Change over the stand by control oil pump line and


replace the clogged up strainer. (Control oil pump
discharge strainer)

(Control oil discharge


strainer)

Forced Draft Fan


Mitsubishi

Daily

Change over the stand-by strainer and clean the


blocked filter in maintenance filter (lubricating oil
duplex strainer).

4-8

Chapter 4 Preventive Maintenance

Continued from previous page


TABLE 4-1

No.

Description

Lubricating oil
system (Cont)

Major Check Item Check Method

Oil strainer

Permanent
instrument

ROUTINE MAINTENANCE CHECKLIST

Check Reference

Diff. press. Less than


0.1 MPa
(Lubricating oil duplex
strainer)

Level gauge

Oil tank
Oil temperature

Rev.003

Oil cooler water


flow

Action to be Taken
(if beyond acceptable limit)

Recommended
Maintenance
Frequency

Change over the stand by control oil pump line and


replace the clogged up strainer. (Control oil pump
discharge strainer)
Change over the stand-by strainer and clean the
blocked filter in maintenance filter (lubricating oil
duplex strainer).

Visual

No leak

Exchange of O-ring
Further tightening

Permanent
instrument

Normal Oil Level

Investigate and top up the oil level.

Permanent
instruments

Not to exceed 70C.

Investigate and take action to reduce the


temperature

Visual,

Rated flow

Investigate and normalize the flow.

Daily

Repair of any leakage of water into the system.

Further details, please refer to


Daily
Vendors manual.

Permanent
Instrument
Visual

Remarks

No leak of water or oil

Further tightening

MM-M02.01

Exchange of packing.
Visual,
Permanent
Instrument

Forced Draft Fan


Mitsubishi

Oil temp. of oil cooler


outlet is not to exceed
70C.

Cooling water check


Disassembly & clean up of cooler.

4-9

Chapter 4

4.3

Preventive Maintenance

Annual Outage Maintenance


The purpose of annual outage maintenance is the implementation of a
preventive maintenance program on a yearly basis through a planned and
correctly executed maintenance work program accompanying necessary
inspections. The annual outage maintenance activities are very important in the
sense that if properly undertaken these enhance the life and reliability of
equipment.
Major activities related to annual outage maintenance are as follows:
(Summarized major activities for annual outage maintenance are also shown in
Table 4-2).

4.3.1 Preparation
a)

Parts, Tools and Equipment


Refer to Subsection 4.2.1 a) Spare Parts, Tools and Equipment.
In addition, it will be necessary to identify and request the
provision of any spare part requirements.
Annual outage will, in certain cases, require the use of material
handling equipment.
Unused spare parts are to be returned for correct storage and
used spare parts are to be replenished.

b)

Documentation
Refer to Subsection 4.2.1 b), Documentation.
Records are to be maintained to record information regarding the
spares and consumables used. These records will be used for
future reference and spare parts replenishment.

MM-M02.01

Rev.003

On completion of annual outage maintenance work, the


equipment is to be monitored for correct operation and
maintenance data logging. This will help to determine the correct
intervals of preventive maintenance activities to ensure optimum
plant availability. The correct recording of findings during
inspection will build a valuable document for future reference.

Forced Draft Fan


Mitsubishi

4-10

Chapter 4

Preventive Maintenance

4.3.2 Inspection and Maintenance


a)

Rotor Assembly
The rotor assembly is to be checked for erosion, and for the
adhesion of dust that could have occurred during normal
operation of the equipment, either of which could induce severe
rotor imbalance resulting in excessive vibration of the rotating
assembly, and could cause serious equipment damage.
The occurrence of wear and cracking is to be further checked
through a non-destructive testing procedure (e.g. dye penetrant
test, etc.).
The rotor clearances with the respective stationary parts are to
be checked against the tolerances as indicated in Figure 4-1,
FDF Clearance Details. After thorough inspection, if any part is
found to be worn beyond the acceptable limits as specified in the
annual outage maintenance check list table (Table 4-2), the
respective part is to be replaced.
The moving blades are to be operated for full opening and closing
positions to ensure that all moving blades move in unison. The
support bearing of any sticking blade is to be inspected and
replaced if found defective.
The grooves /bosses on the rotor shaft corresponding to the
bearing box oil baffle assemblies on both motor side and fan side
are to be inspected for damage or wear. Minor damage can be
corrected with an oilstone.

b)

Bearings
Replace the fan bearings if they surpass the recommended
replacement period or if they show indications of wear during
operation.
Operation with damaged bearings can have serious
consequences in that it may induce excessive vibration and
bearing temperature problems that may cause subsequent
damage to the shaft.

Rev.003

To maintain the bearings in good condition the lubricating oil in


the tank is to be analyzed for oil properties in a laboratory at
frequent intervals and replaced in its entirety when there is
deterioration in oil quality.

MM-M02.01

Prior to disassembly, the bearing box is to be inspected for any


trace of oil leakage through the shaft. After disassembly, check
the clearance between the oil baffle assemblies and the rotor
shaft.
Forced Draft Fan
Mitsubishi

4-11

Chapter 4

Preventive Maintenance

Any damage to the grooves of the rotor shaft and the


corresponding oil baffle assembly on the bearing box end covers
is also to be checked.
Check the tightness of the bearing box fixing bolts. A loose
bearing box may induce vibration which could damage the fan
internals.

c)

Moving Blade Regulating Mechanism


Prior to dismantling, the moving blade regulating mechanism is to
be inspected for any trace of oil leakage from the hydraulic
cylinder and pilot valve head that might have occurred during
normal operation.
The inner surface of the hydraulic cylinder and the outer surface
of the piston are to be checked for any damage, pitting or scratch.
Minor damage can be polished with an oilstone under MHI
supervision. The piston rings and the hydraulic cylinder packings
are to be inspected for damage and replaced with new if found
defective.
The flexible oil hoses connecting the pilot valve are to be
inspected for ageing, damage or cracks. Defective hoses are to
be replaced with new.
Correct tightening of the bolts and nuts for the linkage assembly
and the greasing of the various moving parts is to be performed.
On completion of the maintenance work the linkage assembly is
to be checked for smooth operation with the power cylinder. The
90 movement of the power cylinder lever is to be adjusted for the
moving blade operation range of 40 to + 14.

d)

Casing
The fan casing is to be inspected internally to check for erosion,
wear and cracks, and any previously reported defects are to be
investigated and repaired by patch-welding.
However, if wear or erosion occurs repeatedly in any particular
area, the welding of a wear plate in position should be considered
as a solution to the problem. Checks for corrosion are to be
performed at this time.

MM-M02.01

Rev.003

Any corrosion encountered is to be removed and the resultant


bare metal treated. Any accumulation of debris is to be collected
and removed.

Forced Draft Fan


Mitsubishi

4-12

Chapter 4

e)

Preventive Maintenance

Control / Lubricating Oil System


The oil pump components such as casing, gears, bearings, oil
seals, fasteners, etc. are to be inspected for any damage and the
defective components replaced with new.
The control oil filters are to be inspected for any deformation or
damage. If there is any damage to filters, they must be replaced.
The accumulator bladder is to be inspected for ageing, cracks or
rupture. A defective bladder is to be replaced with new. The
pre-charge pressure of the oil accumulator is to be checked and
pressure readjusted using nitrogen gas. A falling pre-charge
pressure is to be investigated and the defective components
replaced.
The lubricating oil cooler is to be inspected for tube damage or
blockage. Hydraulic testing of the cooler is to be conducted and
any leaking tube is to be plugged. Replace the tube bundle set
with a new one if the cooler performance deteriorates after
plugging several tubes.
For further details, please refer to the vendors manual in
Appendix F.

f)

Coupling

MM-M02.01

Rev.003

Coupling alignment checks are to be conducted carefully both


before dismantling and after reassembly, (refer to Appendix D).
Check the coupling bolts, hubs and spacer for damage or wear.
Defective components are to be replaced with new. Check and
confirm the security of the hubs on the respective shafts.

Forced Draft Fan


Mitsubishi

4-13

Chapter 4 Preventive Maintenance

TABLE 4-2
No.
1

Description
Rotor
1
(inc. shaft* )

Moving
Blades

Major Check
Item

Check
Method

Check
Reference

ANNUAL OUTAGE MAINTENANCE CHECK LIST


Action to be Taken
(if beyond
acceptable limit)

Remarks

Wear, cracks

Visual

No appreciable
wear
No crack

Replace the rotor


Every rotor overhaul
assembly
(4 years)
Repair and rebalance *1 every bearing
overhaul (every 8
years) (if have
spares), 4 years (if
have not spares)

Inner casing
and seal
clearances

Measurement

Clearances are
within specified
criteria (Refer to
Figure 4-1)

Adjust clearance by
adjusting of bearing
box position (using by
shim plate, etc)

Outer casing
clearances

Measurement

Clearances are
within specified
criteria (Refer to
Fig 4-1)

Adjust clearance

Wear, crack

Visual*1,
Measurement
*2
PT check*2

Wear less than


10%

Replace the blades

Inspection Date

Inspector

Results

Every casing overhaul


(4 years)
Adjusting clearance
carried after checking
of correct rotor
assembling.

Blades are to be
replaced as a set.
*1. Every inner
inspection (2 years)
*2. Every rotor
overhaul (4 years)

No crack

Moving Blade Replacement


Bearing

Visual

Not loose (in


caulked
condition)

Tighten the blade


fixing bolts and caulk

N/A

N/A

Replace

Every rotor overhaul


(every four years)

MM-M02.01

Rev.003

Axial
movement

Forced Draft Fan


Mitsubishi

4-14

Chapter 4 Preventive Maintenance

(Continued from previous page)

TABLE 4-2
No.
3

Coupling

Major Check
Item

Check
Method

Check
Reference

Action to be Taken
(if beyond
acceptable limit)

Visual

No defective
parts

Alignment

Measurement

Refer to Appendix Realign within


D
specified criteria

Every coupling
overhaul (4 years)

Rubbing with
the coupling
guard

Visual and
Audible

No contact
between the
coupling and
coupling guard

Adjust the coupling


guard position

Every coupling
overhaul (4 years)

Main Bearing

N/A

N/A

N/A

Replace

Clearance check is
carried out when
replace the bearing.
Recommended to
replace bearing every
8 years (if have
spares), 4 years (if
have not spares)

Bearing box

Seal clearance Measurement


measurement

Clearance are
within specified
criteria (Refer to
Figure 4-1)

Replace

Every rotor overhaul


(every 4 years)

Casing

Wear, Cracks

Visual,
Measurement

No appreciable
wear

Repair the casing

Casing to blade
clearance should not
exceed tolerance
limits

Debris

Visual

No debris

Remove debris and


clean the fan casing
inside

Every inner
inspections (2 years)

Inspection Date

Inspector

Results

Every coupling
overhaul (4 years)

MM-M02.01

Replace or repair

Remarks

Deformation,
crack and
damage

Rev.003

Description

ANNUAL OUTAGE MAINTENANCE CHECK LIST

Forced Draft Fan


Mitsubishi

4-15

Chapter 4 Preventive Maintenance

(Continued from previous page)

TABLE 4-2
No.

Major Check
Item

Check
Method

Moving Blade Pilot valve and Measurement


Regulating
sleeve
Mechanism
clearances

Check
Reference

Action to be Taken
(if beyond acceptable
limit)

Remarks

Clearances are Replace the pilot valve


within specified and sleeve
criteria (Refer to
Figure 4-1)

Recommended to
replace Cylinder, Pilot
valve & Sleeve every
8 years. (if have spare
parts, 6 years if have
not spares)

Wear of servo Measurement


cylinder,
sleeve

Clearance are
Replace
within specified
criteria (Refer to
Figure 4-1)

Every rotor overhaul


(4 years)

Oil leakage

Visual

No oil leakage

Replace the O-rings


and MV-packing

Every inner inspection


(2 years)

Moving blade
operation

Visual

Smooth
operation

Replace defective
components

Moving blade
adjustment

Visual,
Measurement

Adjust blades
position from
-40 to +14

Adjust connecting rod


length

Corresponding
control drive range is
0 to 100 (0 to 90)
Every rotor overhaul
(4 years)

Replacement N/A
of consumable
parts

N/A

Replace

Every rotor overhaul


(4 years)
Refer to Appendix H.

Replacement N/A
of consumable
parts (oil hose)

N/A

Replace

Every inner inspection


(2 years)
Refer to Appendix H.

Inspection Date

Inspector

Results

MM-M02.01

Rev.003

Description

ANNUAL OUTAGE MAINTENANCE CHECK LIST

Forced Draft Fan


Mitsubishi

4-16

Chapter 4 Preventive Maintenance

(Continued from previous page

TABLE 4-2
No.

Description

Major Check
Item
Grease up

Linkage
mechanism

Check
Method

Check
Reference

ANNUAL OUTAGE MAINTENANCE CHECK LIST


Action to be Taken
(if beyond acceptable
limit)

N/A

N/A

N/A

Every year

Replacement
of consumable N/A
parts

N/A

Replace

Every casing overhaul (4


years)
Refer to Appendix H

No appreciable
Repair the silencer
wear

Silencer

Wear crack

Visual

Control/
Lubricating
Oil System

Oil condition*1

Visual

Replace oil
every annual
outage
maintenance.

N/A

Wear or
damage of oil
pump
3
components*

Visual

No wear or
damage

Replace defective
components

Damage of
control oil
filters*2

Visual

No damage

Replace filter

Accumulator
2
bladder*

Visual
Pressure
gauge

No ageing,
cracks or
damage

Replace bladder

Oil cooler
3
leakage*

Visual
Hydraulic test

No leak

Plug the leaking parts


(packing and O-rings)

Oil cooler
protecting
2
zincs*

Measurement

Their length is
below 1/4
1/3 of the
original length
or not

Replace new one

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

Remarks

Inspection Date

Inspector

Results

Drop of silencer wall


leads to rotor damage.
Every inner inspection (2
years)
For further details, please
refer to Vendors manual.
*1 Interval is every 1
year.
*2 Interval is every 2
years.
*3 Interval Is every 4
years.

4-17

Preventive Maintenance

MM-M02.01

Rev.003

Chapter 4

FIGURE 4-1
Forced Draft Fan
Mitsubishi

FDF CLEARANCE DETAILS

4-18

Chapter 5

Disassembly and Reassembly

C h a p t er

5 Disassembly and Reassembly


Disassembly and reassembly are the activities to be conducted when internal parts of
the equipment are required to be accessed. An important part of the activities is the
preparatory work. This should identify the manpower, spare parts and tools that may be
required during the maintenance work. A shortfall of any of these may affect the
schedule and the operational status of the plant.
The major parts of the FDF are the casing, blade pitch control mechanism, bearing and
the blade assembly. Except for the bearing replacement all other disassembly and
reassembly of the FDF parts can be done in site. The rotor removal to a lay down area
is necessary when the bearings are to be replaced as this work is possible only with
shaft in vertical position. The following sections describe the details of disassembly and
reassembly of various parts.
The major steps associated with disassembly and assembly are as follows:

Note
MHI recommends that disassembly and reassembly of FDF is carried out
under MHI supervision only.

5.1

FDF Disassembly and Reassembly


a)

Preparation

MM-M02.01

Rev.003

If FDF disassembly becomes necessary, all associated equipment is to be


mechanically and electrically isolated and an authorized clearance and
work permit shall be in place at the location prior to the commencement of
work. The following points are also to be considered when preparing for
disassembly and assembly:

Forced Draft Fan


Mitsubishi

Have all necessary drawings (assembly drawings, sectional drawings,


spare part details, etc.) and documents (log sheets, field record book,
etc.) ready prior to start of work.

Prepare the necessary handling facilities (e.g. cranes, chain blocks


jacks and supports, etc.) to remove and store the various parts of the
equipment.

Co-ordinate with the I&C Department to remove all the attached


instrumentation such as vibration pick ups, thermocouples and
impulse piping before starting disassembly work.

Move the moving blades to fully closed position before stopping the oil
pumps.

5-1

Chapter 5

Disassembly and Reassembly

Ensure that the electrical breaker must be switched off & locked at
both locations & the key must be retained by the Charge Engineer.

Special tools are listed in Appendix C.

b)

Disassembly

CAUTION
When separating joints and flanges use jacking bolts and
wooden mallets. Never apply force with hammers, chisels or
screwdrivers.
All data is to be recorded during disassembly. During disassembly, make
match marks on adjoining parts for easy identification during reassembly.
The disassembly procedure is described as follows:

Upper Casing Removal:


Refer to Figure 2-5.

Check O content inside before entering the fan compartment.


O content should always be >20%.

CAUTION
Use the safety belt when entering inside the casing through
the manhole.
Take precaution against falling.

MM-M02.01

Rev.003

When working inside of the fan, a colleague should be


stationed at the entry point to provide assistance when
required.

Forced Draft Fan


Mitsubishi

Move the moving blades to a fully close position before starting


disassembly of the FDF. Take care not to be close to moving blade
when direction is changing.

Remove the insulation of the flange section of upper halves of the


impeller casing (17) and rear casing (19).

Remove the band for casing (26) provided between rear and diffuser
(upper part only) casings.

5-2

Chapter 5

Disassembly and Reassembly

Remove vertical joint bolts (8) between suction casing (28) and
impeller casing (17) (upper part only).

Remove the horizontal flange bolts and nuts (9, 2&12, 1&11)
connecting upper and lower half of the rear casing (19) (outer side)
and impeller casing (17) (outer side).

Enter the discharge duct through a duct manhole.

Enter the diffuser inner from the manhole diffuser inner casing (29).

Remove the manhole cover for rear casings (22). Please note that
the two halves of the rear inner casing do not have a bolted joint and
have only metal to metal contact.

Enter the suction casing through the suction casing manhole (30).

10 Remove the bolt (16) connection with the impeller inner casing and
intermediate shaft cover. Slide the impeller shaft cover (23) towards
the motor side.
11 Remove the horizontal joint of the impeller inner casing.
12 Thus both the rear and impeller casings can be lifted together. If to be
removed separately, remove the vertical joint bolts and nuts between
the outer impeller casing and the rear casing also.
13 Lift the outer casing along with the connected inner casing.

CAUTION
Rigging and transportation of equipment must be carried out
by authorized persons. Care is to be taken while equipment
weight and center of gravity is to be considered.

CAUTION
Ensure that the moving blades are in the fully closed position.
Removal of rear casing inner casing with moving blades in the
open position leads to damage of the moving blades.

Special care is to be taken when lifting the casing to


prevent damage to the moving blades.

Special care is to be taken when moving blade operates.

MM-M02.01

Rev.003

CAUTION

Forced Draft Fan


Mitsubishi

5-3

Chapter 5

Disassembly and Reassembly

Take care not to drop the part to be lifted while rigging. If the
part drops on equipment the part as well as the equipment will
get damaged.

Dont stand or walk under a lifted object. If the object falls, it


could lead to a fatal or a severe injury.

CAUTION
While rigging, never stand or sit on the object to be lifted.

CAUTION
Rise the upper casing more than 1.8m above from the moving
blade to avoid contact.
14 Clean the inside of the fan casing before disassembly, to prevent the
entry of any foreign material into the bearing box and the servo
cylinder.

Oil Lines Removal:


Refer to Figure 2-3.

CAUTION
Remove the oil connections only after depressurizing the system
to atmospheric pressure.

Rev.003

15 Remove the connecting pin (5 of Figure 2-8) and disconnect the pilot
valve (30) of Figure 2-3 from the control drive linkage (For details of
linkage assembly refer to Figure 2-8).

MM-M02.01

16 Remove the control oil inner pipings (flexible hoses) (33) from the pilot
valve (30) of control oil supply, control oil return, pilot leak and oil leak
line.
17 Cover the openings of oil lines immediately with cloth to prevent the
entry of dust.
Forced Draft Fan
Mitsubishi

5-4

Chapter 5

Disassembly and Reassembly

Pilot Valve Removal:


Refer to Figures 2-7 and 5-3.
18 Remove the oil cover for pilot leak (40) from the pilot valve by
withdrawing machine screw (37) and washer (32).
19 Remove the bolts and washer (24 & 31) of cover (10).
20 Slowly withdraw the pilot valve (1) together with the joint (14), the
bearing (6), the scroll (5) and the cover (10).
21 Provide temporary covers for the opening of the servo cylinder cover
(39).

Note
If pilot valve disassembly is to be done follow the steps
below, pilot valve disassemble is carried out at the clean
place (work shop etc.) carefully.
Refer to Figures 2-7 and 5-3.
The pilot valve (1) dismantling is done in the following steps:
(i)

Remove the retaining rings (27) on either side of the


scroll (5). Slide the pilot valve (1) with the scroll (5) and
bearing (6).

(ii)

Remove the retaining ring (28) and the bearing (6) from
the scroll (5).

(iii)

Remove the set screw (35) and then the scroll. Remove
the spring pin (34) from the pilot valve shaft.

(iv)

Remove the cover (10) with oil seal (7) and floating ring
(9) from the pilot valve (1).

(v)

Remove the retaining rings (8 & 29) on either side of


cover.

(vi)

Remove the floating ring (9) and oil seal (7) and O ring
(56).

(vii) Remove the bolts (25) and spring washer (33). Discard the
packing (15).

Rev.003

Note :

MM-M02.01

Pilot parts shall be kept in the oil bath after disassembly.

Forced Draft Fan


Mitsubishi

5-5

Chapter 5

Disassembly and Reassembly

Coupling Removal:
Refer to Figure 2-5, 2-11, 5-2 and 5-9.
22 Remove the drive side coupling cover assembly (24 of Figure 2-5).
23 Fix the supporting tools with the impeller inner casing and suction
casing to support the intermediate shaft as shown in Figure 5-9.
24 Install the support bar (turn buckle, washer, plate) to the rotor not to
fall the rotor from the casing and be damage as shown in Figure 5.2.
25 Remove and secure the wire ( 6 of Figure 2-11).
26 Remove the reamer bolts (3 of Figure 2-11) and nuts (5 of Figure
2-11) on the rotor side of the coupling to decouple the fan from the
intermediate shaft.
27 If motor removal is necessary for annual outage maintenance,
remove the bolts (4 of Figure 2-11) and nuts (5 of Figure 2-11) on the
motor side of the coupling to decouple motor from the intermediate
shaft.

Note
As per the design, the intermediate shaft cover can slide
inside the suction inner casing. This arrangement will
provide sufficient space for fixing the intermediate shaft
centering special tool at the fan side impeller inner casing
bottom half. Similarly on the motor side of the intermediate
shaft sufficient space is available for fixing the centering
tool on the suction inner casing bottom half after removal of
coupling cover.

Rotor Assembly & Bearing Removal:


Refer to Figure 2-9.
28 Disconnect and remove the lubricating oil supply pipe from the
bearing box upper, and cover the openings immediately with clean
clothes to prevent the entry of foreign material.
29 Drain the oil from the bearing box by removing the oil bath drain plug
(27) and reinstall the plug in position.
30 Remove the temperature measuring instrument and vibration pickups
from the bearing box assembly.
Rev.003

31 Install eye bolts in the threaded holes provided on the bearing box
and the rotor.

MM-M02.01

32 Connect the appropriate lifting gear to the lugs provided on the


bearing box and the rotor wheel.

Forced Draft Fan


Mitsubishi

5-6

Chapter 5

Disassembly and Reassembly

33 Remove the bolts (16 and 35), Remove the taper pins (23) in position
and parallel pin (36).
34 Remove the bearing box upper half (1) and oil baffle assembly (38 &
39) upper half.
35 Adjust the slings to facilitate the vertical lifting of the combined rotor
and the bearing assembly.
36 After removing the rotor and bearing assembly, cover the lower half of
the bearing box by a sheet and plate.

Note
To prevent the plate from moving, secure using a wire.

Note
Please note that the bearing box is assembled in two halves.
The removal of the bearing box lower half may be judiciously
decided. If the bearing box removal is necessary, the taper
pins need not be removed from its position on the lower half.
Please note that the taper pins are spot welded to the
eccentric bush (9) which is inserted and caulked to the base.
The rotor is normally removed by removing the upper half of
the bearing box as described in this section.

CAUTION
Special care is to be taken when lifting the rotor assembly with
blades to prevent damage to the moving blades and the bearing
box.

CAUTION

Dont sit or stand on a rotor being removed.

Dont go near a rotor being lifted.

MM-M02.01

Rev.003

37 Slowly lift up the rotor assembly with the bearing and transport it to
the lay down area.

Forced Draft Fan


Mitsubishi

5-7

Chapter 5

c)

Disassembly and Reassembly

Reassembly
The reassembly procedure is carried out in the reverse sequence to that
for disassembling. Install all parts in the same positions they were
removed from, referring to the match marks and checking that the
clearances are maintained as specified in Figure 4-1. All contact surfaces
are to be cleaned before starting reassembly and all gaskets are to be
replaced.

Note
Before the installing of the rotor assembly, oil flushing is
finished.

If disassembly of rotor has been performed, ensure that the rotor is


reassembled and ready for installation as per section 5.2.

If disassembly of the bearing box has been performed, ensure that


the bearing is reassembled and ready for installation as per section
5.3.

Visually inspect the fan casings to ensure that they are clean and free
of foreign material before rotor installation.

Lift the rotor assembly slightly to ensure that the load is correctly
balanced.

Take care not to drop the lifted object while rigging. If the
lifting part falls, it will damage the stationary equipment.

Never stand under an object being lifted. This could cause a


fatal or a severe injury.

CAUTION

Rev.003

CAUTION

MM-M02.01

Ensure that the moving blades are in the fully closed position.

Special care is to be taken when lowering the casing to


prevent damage to the moving blades, and bearings.

Forced Draft Fan


Mitsubishi

5-8

Chapter 5

Disassembly and Reassembly

Refer to Figures 2-9.


5

Transport the rotor assembly with the bearing, blades and servo
cylinder to the fan casing.

Using a suitable lifting device lower the assembly slowly into the
casing.

Take care of the proper seating of the bearing on its assigned support.

Install the support bar (turn buckle, washer, plate) to the rotor, not to
fall the rotor from the casing as shown in Figure 5-2.

Remove the lifting equipment.

CAUTION
Dont sit or stand on a rotor being removed.

10 Install the upper half of bearing box and oil baffle assembly (38&39).

Note
Install the bolt (35) and parallel pin (36) before installing
bearing box cover to bearing box. If you dont keep this
assembling process, it leads to oil leakage.

11 Check the bearing clearances between the shaft and bearing box
cover (radial & axial) with those specified in Figure 4-1.
12 Accordingly, fix the spherical keys (37) with shims (45) Figure 5-6 to
the bearing keep (26), for adjusting the clearances specified in Figure
4-1.
13 Fix the bearing body stopper (3).
14 Measure and check the tolerances between the bearing box and the
spherical key which is top side specified in Figure 4-1.
15 Install the bearing box taper pins (23) and parallel pin (36) in its
original place on the upper half of bearing box and install bolts (16 &
35).
16 Tighten the fixing bolts (16&17) to the required torque.

Rev.003

17 Replace the consumable parts (packing etc.) and install all the
bearing box oil supply lines.

MM-M02.01

18 Install the vibration monitors and the temperature measuring elements


on to the bearing box.
19 Reassemble the coupling as per section 5.5 and remove the rotor
support bar and coupling support.
Forced Draft Fan
Mitsubishi

5-9

Chapter 5

Disassembly and Reassembly

CAUTION
Be careful not to place your finger between the upper and the
lower casings during reassembly.

CAUTION
Ensure the moving blade full close position before the
installing the casing.

20 Measure the radial clearance of the impeller with the outer casings the
impeller and the rear inner casing.
21 Adjust the inner casings to achieve the clearance as indicated in
Figure 4-1.

CAUTION
Not enough adjusting of clearance leads to contact of rotation
parts and stationary parts.
After completing maintenance in the oil lines of the bearing
box/oil unit, do complete oil flushing using eye protection.

Note
If pilot valve disassembly is done, it is reassembled as
follows, pilot valve reassemble is carried out at the clean
place (work shop, etc.) carefully.
Refer to Figures 2-7 and 5-3.
The pilot valve (1) reassembly is done in the following steps:
(i) Reassemble the pilot valve with the bearing (6), scroll (5),
cover (10) in the reverse order to disassembly. Note before
reassembly replaced the consumable parts ( oil seal (7),
floating ring (9), bearing (6), O ring and retaining ring.)

Rev.003

(ii) Install the cover (10) with oil seal (7) and floating ring (9)
to the pilot valve (1)

MM-M02.01

(iii) Install the scroll (5) with the spring pin (34) and the set
screw (35). Note before the installing the scroll, set the
retaining ring (27) of joint side (14).

Forced Draft Fan


Mitsubishi

5-10

Chapter 5

Disassembly and Reassembly

(iv) Install the retaining rings (27) on the either side of the
scroll (5).
(v) Install the retaining rings (28) and the bearing (6).
(vi) Provide packing (15) onto the pilot valve head, install the
joint (14) and secure it with spring washers (33) and bolts
(25).
Refer to Figure 20-7 and 5-3
22 Remove the temporary cover provided for the opening of the servo
cylinder cover (39).

CAUTION
Installing the pilot to the rotor should be carried out in the
casing.
23 Smear lubricating oil over the pilot valve assembly and slowly insert
the pilot valve assembly on the servo cylinder cover (39).
24 Tighten the bolts (24) with washers (31).
25 Install the oil cover for pilot leak (40) and secure it with spring washer
(32) and screw (37).
26 Connect the control oil inner piping (Figure 2-3 (33)) to the pilot valve
(1) to the control oil supply, control oil return, pilot leak, oil leak line.

Oil Lines Reassembly and Fan Normalization:


Refer to Figure 2-8.

CAUTION
Wear the eye protection in oil line assembly working.

Special care is to be taken with oil hose, do not bend.

Rev.003

27 Start the oil pump, operate the moving blades


28 Check for the correct lubricating oil flow.

MM-M02.01

29 Check and confirm that the system is free from any control and
lubricating oil leakage.

Forced Draft Fan


Mitsubishi

5-11

Chapter 5

Disassembly and Reassembly

30 Ensure the moving blade stroke from 0% to 100% (from - 40 to +


14) as per the procedure described below.
(i)

Start the oil pump and check that the oil pressure is between 1.0
and 1.5 MPa.

(ii) Locate the reference moving blade manually at the - 40 position


stamped on the rotor.
(iii) Move slowly the pilot valve by manual to the +14 position, and
ensure the moving blade stroking smoothly.
(iv) Return the pilot valve by manual to the - 40 position stamped on
the rotor.

Note
Ensuring of moving blade stroking may carried out before
rotor installing (after rotor reassembly) by using N2 gas.

CAUTION
Before the moving blade operates, check that the support bar
(refer figure 5-2) is removed from the rotor.
Be careful when adjusting the moving blade. It could result in
the breaking of the equipment.
Special care is to be taken when the moving blade operate.
(Like pinching in the moving blade)

31 After ensuring the moving blade stroke, readjust that control oil
pressure is between 5.39 MPa and 5.88 MPa.
32 Connect the linkage mechanism to the pilot valve joint (14).
33 Adjust and calibrate the moving blade stroke from 0% to 100% (from 40 to + 14) as per the procedure described below.
(i)

Start the oil pump and check that the oil pressure is between 1.0
5.39 MPa and 5.88 MPa..

MM-M02.01

Rev.003

(ii) Operate the control drive locally from 0% to 100% and ensure
that the moving blade pitch indicator is moved form fully closed
positions to fully open positions and stamped on the rotor is
moved from - 40 to + 14. Adjust the linkage mechanism if
required.

Forced Draft Fan


Mitsubishi

5-12

Chapter 5

Disassembly and Reassembly

(iii) Operate the control drive from the DCS from 0% to 100% to
confirm that the moving blade pitch angle is in requirement with
the DCS indication. Adjust the linkage mechanism if required.
(iv) Record the angle of stamped on the rotor and moving blade pitch
indicator on side of outer casing for every 20% DCS demand.

CAUTION
Be careful when adjusting the moving blade. It could result in
the breaking of the equipment.
Special care is to be taken when the moving blade operate.
(Like pinching in the moving blade)

Refer to Figure 2-5.


34 Install the upper halves of the impeller casing (17) and rear casings
(19) by using a special tool (guide tool).

Note
Check no oil leakage from the bearing box etc. before installing the
upper halves of casings.

35 Measure the impeller axial clearance at the upper half of the rear and
impeller inner casings.
36 Measure the radial clearance between the blades and the rear inner
casing in the open position as indicated in Figure 4-1.
37 Grind the rear inner casing to achieve a clearance within the tolerance,
if required.

CAUTION
Dont operate the moving blade while installing the casing.

Do not machine the moving blades to achieve the required


clearance.
38 Adjust the inner casings to achieve clearance as indicated in Figure
4-1.
Rev.003

CAUTION

MM-M02.01

Not enough adjusting of clearance leads to contact of rotation


parts and stationary parts.

Forced Draft Fan


Mitsubishi

5-13

Chapter 5

Disassembly and Reassembly

39 Install the joint bolts (1 & 11, 2 & 12, 9, 10 & 13) as required for the
casings (horizontal and vertical) and tighten them after achieving the
required tolerances.
40 Slide the intermediate shaft cover (23) to the rotor side and install the
bolts (16) and spring washer (14).
41 Install the drive side coupling cover assy (24).
42 Install the band for casing (26) provided over the rear upper casing.

CAUTION
Before entering through a manhole inside the casing,
establish a temporary platform/grating.
43 Replace or renew the insulation around the casing joints.

CAUTION
Keep a sufficient distance while fixing the upper and lower
casing. If you are trapped between the casings, it could result
in a fatal or a serious injury.
44 After a final inspection inside the casings, close all the manhole (22,
29 and 30 of Figure 2-5).

CAUTION
Before closing the manholes/access doors to the FDF, an
inspection must be carried out to ensure that no material has
been left inside. If some thing remains in the fan, it could lead
to serious fan damage.
Before you close the manhole, check that all persons have
left.

MM-M02.01

Rev.003

45 Return the fan into service.

Forced Draft Fan


Mitsubishi

5-14

Chapter-5

Disassembly and Reassembly

L
10400

610 1890

E
TRU TH N
R
NO

2860

690825
600

3000

PLANT
NORTH

3B

2100

700

700

11001000

NOTES :

11001000

600

1300

BOILER FRONT

1. THIS DRAWING SHOWS THE DISASSEMBLY PROCEDURE.


PLEASE REFER TO EACH EQUIPMENT O&M FOR DETAIL.

1200

FLOOR(FL+7500)

MOTORIZED
GEARED
TROLLEY
CHAIN BLOCK
20ton

MONORAIL

L
10400
5900

690 3810

2. OVERHAUL BY THIS DRAWING MAKES FAN(A) AND


FAN(B) SYMMETRICAL TO BOILER CENTER.

8200

4500

min.
1380

10400

3040

2860

A2

1550

A3

1A
BCP

FL+9400
MSL+14400

UPPER
CASING
18ton

2870

A1

FL+3600
MSL+8600

OIL UNIT

A4

4. PARTS WEIGHT
UPPER CASING
ROTOR
AIR HOUSING
MOTOR

12400

CARRIER
(SUPPLIED BY
OWNER)
10000

8800

18800
15t TRUCK
(SUPPLIED BY
OWNER)

UPPER CASING
18ton

CARRIER
(SUPPLIED BY
OWNER)

3B

SUBMERSIBLE SCRUBBER CONVEYOR

SECTION A-A

97000-3015 : GENERAL ARRANGEMENT


(SIDE VIEW)

A3 A4
D3 D4

10000

OVERHAUL OF UPPER CASING


A5

MOTOR
13.2ton
A1 A2

FORCED DRAFT
FAN 3A

3470 1860

3810

3040

FLAME DETECTOR & FURNACE


TV CAMERA COOLING AIR FAN(AC)

LOCAL
PANEL

SILENCER

OIL UNIT

MOTORIZED
HOIST
15ton

FLAME DETECTOR & FURNACE


TV CAMERA COOLING AIR FAN(DC)

LOCAL
PANEL

8800

OIL UNIT

FORCED DRAFT
FAN 3B

C2

UPPER CASING
18ton
A1

3470

1860

B1 B2
4500

B3 B4

8200

SECTION B-B
600

C3

7A

1000

C4

MONORAIL FOR MOTOR


BOS FL+9400(I-450x175)

5900

10400

10000

ROTOR
5ton

AIR HOUSING
1.3ton

A2

FL+3600
MSL+8600

18800

R8000

MOTORIZED
GEARED
TROLLEY
CHAIN BLOCK
20ton

MAX.
4420

1500

min.
1380

5A

FL+9400
MSL+14400

min
1650

3000

3000

FURNACE

3000

C1

Rev.003

2860

B
R8000

8800

690

18800

D1 D2

BOILER

MM-M02.01

: 3.3ton
: 3ton
: 1.3ton
: 13.2ton

5. REFERENCE DWG. No.


97000-3011 : GENERAL ARRANGEMENT
1FL(FL+0)
-

5A

3B

600

3. OVERHAUL PROCEDURE
UPPER CASING (REF. TO SECTION A-A,B-B)
1) LIFT UP THE UPPER CASING FROM THE
POSITION A1 TO A2 WITH MOTORIZED
GEARED TROLLEY.
2) MOVE THE UPPER CASING FROM THE
POSITION A2 TO A3 AND TURN IT.
3) PUT DOWN THE UPPER CASING ON THE
CARRIER FROM THE POSITION A3 TO A4 .
4) MOVE THE UPPER CASING FROM THE
POSITION A5 TO TEMPORARY STORAGE AREA.

690

10t TRUCK
(SUPPLIED BY
825 OWNER)
3810
3040

2860

OVERHAUL OF UPPER CASING

MONORAIL FOR ROTOR


BOS FL+9400(I-450x175)

PLAN
MPTD-3-0040-1

Forced Draft Fan


Mitsubishi

FIGURE 5-1A

OVERHAUL PLAN FOR FDF 1/2

5-15

Chapter-5
690

3810

3040

Disassembly and Reassembly

2860

NOTES :
MOTORIZED
GEARED
TROLLEY
CHAIN BLOCK
20ton

1800
B1

B4

MOTORIZED
HOIST
15ton
FL+3600
MSL+8600

3. OVERHAUL PROCEDURE
ROTOR (REF. TO SECTION A-A)
1) LIFT UP THE ROTOR FROM THE POSITION
POSITION B1 TO B2 WITH MOTORIZED
GEARED TROLLEY.
2) MOVE THE ROTOR FROM THE POSITION
B2 TO B3 .
3) PUT DOWN THE ROTOR ON THE TRUCK FROM
THE POSITION B3 TO B4 .

min.
1380

MOTORIZED
GEARED
TROLLEY
CHAIN BLOCK
20ton

A2
UPPER CASING
18ton

MAX.
4420

B2

B3

FL+9400
MSL+14400

min
1650

FL+9400
MSL+14400

2620

ROTOR
5ton

TEMPORARY
RACK
(SUPPLIED BY
OWNER)

2. OVERHAUL BY THIS DRAWING MAKES FAN(A) AND


FAN(B) SYMMETRICAL TO BOILER CENTER.

min.
1380

MONORAIL

1. THIS DRAWING SHOWS THE DISASSEMBLY PROCEDURE.


PLEASE REFER TO EACH EQUIPMENT O&M FOR DETAIL.

SILENCER

A1

FL+3600
MSL+8600

AIR HOUSING (REF. TO SECTION C-C)


1) LIFT UP THE AIR HOUSING FROM THE
POSITION C1 TO C2 WITH MOTORIZED HOIST.
2) MOVE THE AIR HOUSING FROM THE
POSITION C2 TO C3 AND TURN IT.
3) PUT DOWN THE AIR HOUSING ON THE
TRUCK FROM THE POSITION C3 TO C4 .

OIL UNIT

3470

10t TRUCK
(SUPPLIED BY
OWNER)
10000

8800

1860

4500

5900

18800

10400

3B

5A

8200

MOTOR (REF. TO SECTION B-B,C-C)


1) LIFT UP THE MOTOR FROM THE POSITION
POSITION D1 TO D2 WITH MOTORIZED HOIST.
2) MOVE THE MOTOR FROM THE POSITION
D2 TO D3 .
3) PUT DOWN THE MOTOR ON THE TRUCK FROM
THE POSITION D3 TO D4 .

SECTION A-A

SECTION B-B

OVERHAUL OF ROTOR

OVERHAUL OF UPPER CASING

4. PARTS WEIGHT
UPPER CASING
ROTOR
AIR HOUSING
MOTOR
MONORAIL
MOTORIZED
HOIST
15ton

MOTORIZED
HOIST
15ton

SILENCER

: 3.3ton
: 3ton
: 1.3ton
: 13.2ton

5. REFERENCE DWG. No.


97000-3011 : GENERAL ARRANGEMENT
1FL(FL+0)
-

SILENCER

97000-3015 : GENERAL ARRANGEMENT


(SIDE VIEW)
min.
1650
MOTOR
13.2ton
D3

C1

D2

1000

950

3200

C2

C3

AIR
HOUSING
1.3ton

FL+9400
MSL+14400

FL+3600
MSL+8600

D1

C4

MONORAIL

3150

min.
1650

FL+9400
MSL+14400

FL+3600
MSL+8600

D4

10t TRUCK
(SUPPLIED BY
OWNER)
10000

15t TRUCK
(SUPPLIED BY
OWNER)

8800

18800

8800

18800

5A

3B

10000

5A

3B
SECTION C-C

OVERHAUL OF AIR HOUSING

OVERHAUL OF MOTOR

MM-M02.01

Rev.003

SECTION C-C

MPTD-3-0040-2

Forced Draft Fan


Mitsubishi

FIGURE 5-1B

OVERHAUL PLAN FOR FDF 2/2

5-16

Chapter-5

ITEM
1
2
3

Disassembly and Reassembly

DESCRIPTION
SUPPORT BAR
TAPERED WASHER
CENTERING TOOL ASSY

NOTE:
TAKE CARE OF SETTING DIRECTION OF TAPERED WASHER

CL OF M/B

3
2

MM-M02.01

Rev.003

A-A

MPTD-3-1195

FIGURE 5-2
Forced Draft Fan
Mitsubishi

SUPPORTING PROCEDURE OF FDF ROTOR

5-17

Chapter 5

5.2

Disassembly and Reassembly

Rotor Disassembly and Reassembly


a)

Preparation
If the removal of the moving blades and the hydraulic cylinder in FDF rotor
becomes necessary, all associated equipment is to be mechanically and
electrically isolated and an authorized work permit and valid isolation
certificate shall be in place prior to the commencement of the work. The
outer casings are to be removed and FDF rotor is disassembled as per
section along with blades, bearing and hydraulic cylinder as per section
5.1. The following points are also to be considered while preparing for
disassembly and reassembly of FDF rotor:

Have all necessary drawings and documents (log sheets, field record
book, etc.) ready prior to the start of work.

Prepare the necessary handling facilities (e.g. cranes, chain blocks


jacks and supports, etc.) to remove and store the various parts of the
equipment.

Special tools are listed in Appendix C.

CAUTION
Wear safety glasses to protect your eyes during the inspection /
maintenance.

CAUTION
Always use the Personnel Protective Equipment (PPE) during
maintenance.

Note
Ensure that the rotor is set on the maintenance stand. See Figure
5-5.

b)

Disassembly

Rev.003

All data is to be recorded during the disassembly of each part. During


disassembly, make match marks on the adjoining parts for reference
during the reassembly. The disassembly procedure is described as
follows after the disassembly of the FD fan as described under the section
5.1.

MM-M02.01

Disassembly of Moving Blades and Hydraulic Cylinder:


Refer to Figures 2-6, and 5-4.
1
Forced Draft Fan
Mitsubishi

Match mark the blades with their installed locations.

5-18

Chapter 5

Disassembly and Reassembly

Note
Figure 5-4 shows the exploded view of the rotor consisting of
blades, crank arm and sliding piece for crank arm.

Remove the set screw (22) and the U-nut (23) and then unscrew the
nut for blade support (4) by using a special tool (spanner) for nut for
M/B and place it down inside the rotor.

Lightly tap and remove the moving blade support bearing (36) and
place it inside the rotor wheel above the nut for blade support (4).

Slowly pull the moving blade (1) with the Teflon ring (15).

Refer to Figures 2-7 and 5-3


5

Remove the bolts (26) and then remove the servo cylinder cover
assembly (39) with pilot sleeve (2).

Remove the bolts (22) and washer (30), and pull up the pilot sleeve
(2) with blade (4) and cover (3).

Note
The pilot sleeve shall be kept in the oil bath together with pilot
valve.

The sleeve (2) dismantling is done in the following steps:


(i)

Remove the cover (3) by unscrewing the bolts (23).

(ii) Remove the blade (4) by unscrewing the screw (36). Remove the
washer (32).
8

Discard the O-rings (16~21).

Remove the set screws (48) and then unscrew the nut for piston (43)
(using special tool) from the fan shaft.

10 Remove the piston (42) with the help of special tools (draw out tool,
guide bar & nut). Dismantle the piston rings (46) from the piston.
Refer to Figures 2-6 & 5-4.
11 Remove the fixing bolts (20) and the side ring of actuator disk (6) from
the rotor (8).

Rev.003

12 Remove the crank arm (2) as an assembly outwards from the rotor (8)
after removing the retaining ring (28).

MM-M02.01

13 Remove the bush (17) from the rotor (8).

Forced Draft Fan


Mitsubishi

5-19

Chapter 5

Disassembly and Reassembly

14 Remove the sliding piece with its bush inside (37) from crank arm (2)
after releasing the retaining ring (29). The exceptional one number
sliding piece for crank arm (with pin) (38) and its bushes (18) are also
removed easily after removing the retaining ring (28).
Refer to Figure 2-7 and 5-3
15 Withdraw the servo cylinder (52) axially. Unscrew the set screw (55)
and then remove the bush (54) from the cylinder assembly.
16 Remove the hexagon socket head bolt (49) and then the plate for MV
packing (41). Discard the packing (45).
17 Remove the parallel pin (50) and then pull out the sleeve (44). Discard
the O-ring (51). (if replace the sleeve)

Note
In the case of disassembly and replacement of the sleeve (44) for
its wearing, apply heat to its.

c)

Reassembly
The reassembly procedure is carried out in the reverse sequence to that
of disassembly. Install all parts in the same positions they were removed
from, referring to the match marks and checking that the clearances are
maintained as specified in Figure 4-1, FDF Clearance Details. All removed
gaskets and O-rings are to be discarded and replaced with new ones.

Reassembly of Moving Blades and Servo Cylinder:


Refer to Figures 2-7, and 5-3.
1

Insert the O-ring (51) and then the sleeve (44) onto the fan shaft and
secure it with the parallel pin (50).

Insert the bush (54) inside the servo cylinder (52) and fix it to the
cylinder with the set screw (55)..

Insert the servo cylinder assembly (52) onto the sleeve (44).

Apply grease to the lip of the MV-packing (45), then insert the
MV-packing into the slot ensuring that the lip is facing towards the
piston by using special tools (guide ring, tightening plate, inset ring,
guide bar & nut).

Note
Rev.003

Be sure to assemble the MV-Packing in the direction indicated


in the drawing. If assembled in reverse direction, it may cause oil

MM-M02.01

leakage. Additional details on MV-packing insertion are provided


in Appendix F.

Forced Draft Fan


Mitsubishi

5-20

Chapter 5

Disassembly and Reassembly

Note
Use the MV-packing insert tool supplied as a special tool for the
installation of MV-packing.

Note
Ensure that the plate for MV packing (41) does not protrude from
the servo cylinder face.

Install and gradually tighten the plate for MV packing (41) to the servo
cylinder (52) by bolts (49).

Install the retaining ring (47) after final tightening of the plate for MV
packing (41).

Refer to Figures 2-6 and 5-4.

Note
Control match marks of moving blades and rotor. Apply specified
torque on each bolt using torque wrench. Apply lubricant to the
threads and seating surfaces when tightening the bolts.

CAUTION
Do not use lubricants containing Molybdenum Base such as
Molycoat.
If a moving blade is sticking after re-assembly, confirm the
clearance and check for any crack.
7

Install bush for crank arm (17) on the rotor (8). The seam of this bush
is to be located at 45 towards motor side and with respect to the
direction of rotation of the rotor.

Install all the 13 numbers of the crank arms (2) onto the inner side
holes in the rotor (8). Lock the crank arms with the retaining ring (28).

Install all the 13 numbers of sliding pieces for crank arm (37) and
secure them in the position with the crank arm (2) by retaining ring
(29). The oil less bush for sliding piece (41) is to be located on center
line and 180 opposite to the direction of rotation of rotor.

MM-M02.01

Rev.003

10 Install the crank arm (3) on the rotor (8). Lock the crank arms for
blade shaft with the retaining ring (28). Install sliding piece for crank
arm (with pin) (38) in the hole of the servo cylinder (35).

Forced Draft Fan


Mitsubishi

5-21

Chapter 5

Disassembly and Reassembly

Note
Install the moving blade such that the leading edge of the moving
blade is toward the suction casing and the trailing edge toward the
rear casing.

Refer to Figures 2-6 and 5-4.


11 Install the Teflon ring (15) onto the top of the holes in the outer
periphery in the rotor (8).
12 Insert the moving blade with (1) through the holes in the outer
periphery of rotor (8) into the involute spline hole of the crank arm
(2/3).

Note
Moving blade weight measurement should be carried out. Decide
the blade arrangement by calculating the balancing by blade
weights. Allowable unbalance is to be adjusted during a balancing
procedure by additional weights.

13 While inserting the blade in the rotor (8), install the moving blade
support bearing (36) along with the nut for moving blade shaft (4)
through the bottom side of the outer periphery holes in the rotor (8)
before locating the moving blade bottom into the spline hole of crank
arm (2/3) .
14 Ensure the position of the moving blades shaft end on the spline hole
in the crank arm (3).
15 Secure the moving blade support bearing (36) with the nut for moving
blade shaft (4) by using a special tool (spanner).

CAUTION
Do not machine the moving blades to achieve the required
clearance.

16 While tightening the nut for moving blade shaft (4), ensure that
moving blades are free to rotate by hand.

Rev.003

17 Follow the same procedure to install the remaining moving blades.


Refer to Figures 2-7 and 5-3.

MM-M02.01

18 Replace the piston rings (46) on the piston, if they were removed
during disassembly, then insert the piston (42) through the rotor shaft
by using the special tool and locate it butting to the sleeve (44).

Forced Draft Fan


Mitsubishi

5-22

Chapter 5

Disassembly and Reassembly

19 Install the nut for piston (43) and secure it by using special tool
(spanner) and set screws (48).
Refer to Figures 2-6 and 5-4.
20 Install the side ring of actuator disk (6) such that the hole matches the
pin of the sliding piece with pin (38).
21 Tighten the bolts (20) to the specified torque as per Appendix A.
Refer to Figures 2-7 and 5-3.
22 Install the sleeve (57) onto the inside surface of the servo cylinder
cover (39) if removed during disassembly and secure it by set screw
(58).
23 Reassemble the pilot sleeve (2) with blade (4) and the cover (3) after
replacing the defective parts and the O-ring (17).
24 Install new O-rings (18 & 19) in their respective slots in the sleeve (57)
and install the sleeve assembly onto the servo cylinder cover (39) and
secure it with bolts and washers (22&30).
25 Install and tighten the set screw (22) and the U-nut (23) to the
required torque as per Appendix A.
26 Install the servo cylinder cover (39) on to the servo cylinder (52) with
bolts (26).
27 Check the 0% position of moving blade angle and cylinder position.
28 Verify that the blade root clearance is within the specified tolerance.
Adjust the axial clearance of the moving blade, if necessary.
29 Ensure that the balance weights (32) are in their original locations on
the rotor wheel and the screws (33) are not loose.

Note
Ensure the moving blade stroke by using N2 gas etc, if possible.
After ensuring the moving blade stroking, pilot valve shall be kept

MM-M02.01

Rev.003

in the oil bath till installing the rotor to the casing.

Forced Draft Fan


Mitsubishi

5-23

Chapter-5

Disassembly and Reassembly

ITEM

PILOT VALVE
PILOT SLEEVE
COVER

SCROLL

7
8

OIL SEAL
RETAINING RING
FLOATING RING
COVER
PLUG

10

13

18
19
20

O RING
O RING
BOLT

24
25
27
28
29
31

RETAINING RING
WASHER
SPRING WASHER

33
SET SCREW
36
PARALLEL PIN
CYLINDER COVER
DRAIN COVER

43
45

MM-M02.01

Rev.003

54
55

FIGURE 5-3
Forced Draft Fan
Mitsubishi

MB HYDRAULIC MECHANISM - EXPLODED VIEW

5-24

Chapter-5

Disassembly and Reassembly

MM-M02.01

Rev.003

FIGURE 5-4
Forced Draft Fan
Mitsubishi

MB MECHANISM EXPLODED VIEW

5-25

Chapter 5

Disassembly and Reassembly

APPROX. 72kg

APPROX. 20kg

2
1
CL OF M/B

MAINTENANCE STAND

MM-M02.01

Rev.003

MPTD-4-1194

FIGURE 5-5 SUPPORTING PROCEDURE FOR ROTOR DISASSEMBLY & REASSEMBLY

Forced Draft Fan


Mitsubishi

5-26

Chapter 5

5.3

Disassembly and Reassembly

Bearing Disassembly and Reassembly


a)

Preparation
If bearing disassembly becomes necessary, all associated equipment is to
be mechanically and electrically isolated and an authorized work permit
and valid isolation certificate is to be in place prior to the commencement
of work. The outer casings are to be removed and rotor is shifted to lay
down area. Please refer to section 5.1 for the details. The following points
are also to be considered when preparing for disassembly and
reassembly:

Have all necessary drawings and documents (log sheets, field record
book, etc.) ready prior to the start of work.

Prepare the necessary handling facilities (e.g. cranes, chain blocks


jacks and supports, etc.) to remove and store the various parts of the
equipment.

Remove all instrumentation such as vibration pick ups and


thermometers before starting the disassembly work.

Prepare a suitable fixture to support the rotor assembly vertically


when carrying out the disassembly and reassembly of the bearings.

Special tools are listed in Appendix C.

CAUTION
Be careful not to put your finger in between the upper and the
lower halves during reassembly.

CAUTION
Always ensure that the wire slings, shackles, eyebolts and lifting
gear are certified to the Safe Working Load (SWL).

CAUTION

MM-M02.01

Rev.003

Do not stand under a lifted object. This could lead to a fatal / or a


severe injury.

Forced Draft Fan


Mitsubishi

5-27

Chapter 5

b)

Disassembly and Reassembly

Disassembly
The disassembly of the bearing box shall be carried out after the removal
of the moving blades to prevent any damage to the blades during handling.
If the servo cylinder does not require any disassembly, take due care to
position the pilot valve clear off the ground while supporting the rotor
assembly vertically.
All data is to be recorded during the disassembly of each part. During
disassembly, make match marks on the adjoining parts for reference
during reassembly. The disassembly procedure is described as follows:

Note
Protect the openings on the rotor with proper covers to prevent the
entry of dust.

CAUTION
Rigging and transportation of equipment must be carried out by
authorized persons. Care is to be taken where equipment weight
and center of gravity is to be considered.

CAUTION
After the maintenance of oil lines of the bearing box/oil unit,
ensure that oil flushing of the lines is carried out to remove any
entrapped foreign matters.
1

Support the rotor assembly vertically (Refer Figure 5-7).

CAUTION
Special care is to be taken to prevent the outer race of radial
bearing and the bush from falling.
Refer to Figure 2-6.
2

Remove the set screw (24) and nut (14).

Remove the driving coupling half. (Need with burner)

Rev.003

CAUTION

MM-M02.01

If remove the driving coupling half, apply with burner (propane


gas)

Forced Draft Fan


Mitsubishi

5-28

Chapter 5

Disassembly and Reassembly

Remove the sleeve for bearing (13).

Refer to Figure 2-9.


5

Match mark the plate for bearing keep (4) with the bearing keep (26)
and remove the 90o elbow (22) with the connecting pipe from the
plate.

Loosen and remove the bolts (20) and washers (21) securing the
plate for bearing keep (4) with bearing body. Carefully hold the plate
to avoid its fall. Also the adjusting ring bottom half (6) may fall from its
position along with the plate for bearing keep. Carefully remove the
adjusting ring bottom half.

Remove the upper half of the adjusting ring (5) from the outer race of
the radial bearing by removing the stopper bolt (7).

Slide the plate for the bearing keep (4) down the shaft. This plate can
be removed only after removal of the bearings.

Using a puller if required to remove the bearing keep (26) with its
spherical keys (37) and shims from the bearing assembly. Remove
the O-rings (10) from inside the bearing keep.

10 Remove both the thrust ball bearings (28) and the outer spacers (34)
with O-rings (32). Discard the O-rings. Use puller and heat as
required.
11 The inner spacers (33) for the above bearings are secured.
12 Remove the radial bearing (29) at the fan side. Use puller and heat as
required.
13 The plate for bearing keep (4) can be withdrawn now from the shaft
(40).

c)

Reassembly
The reassembly procedure is carried out in the reverse sequence to that
for disassembly. Install all parts in the same positions they were removed
from, referring to the match marks and checking that the clearances are
maintained as specified in Figure 4-1, Clearance Drawing for FDF. The
used gaskets and O-rings are to be discarded and replaced with new
ones.

Rev.003

Refer to Figures 2-9 and 5-6.


Clean the bearing seating surfaces on the rotor. Minor surface
corrections shall be carried out using an oilstone.

MM-M02.01

Forced Draft Fan


Mitsubishi

5-29

Chapter 5

Disassembly and Reassembly

Note
The reassembly of the bearings and the coupling hub on the
rotor are to be carried out in the vertical position.

Insert the plate for bearing keep (4) on to the shaft (40).

Install the fan side radial bearing (with rollers and outer race) onto the
inner race.

Heat the inner race of the radial bearing (29) in an oil bath to about
100C until the inner race diameter increases by 0.1 mm.

Transfer the inner race of radial bearing (29) from the oil bath or oven
and install it on the rotor so that the inner race abuts the step provided
on the rotor.

A weight or pressure should be applied to the inner race to ensure it


remains in contact with the step on the rotor as it cools.

Include the bearing inner spacer (33) and outer spacer (34)on to the
radial bearing.

Insert the O-rings (32) on to the spacer outer.

Follow the heating procedure explained in Step 4.

10 Heat the thrust bearing (28) and insert it onto the rotor so that it abuts
firmly onto the inner spacer and then on to the roller bearing.
11 After the ball bearing has cooled to ambient temperature, insert the
next set of inner spacer (33) into the outer spacer (34).
12 Insert O-rings (32) on to the outer spacer.
13 Follow the same heating procedure to install the motor side thrust ball
bearing (28).
14 Fix the upper adjusting ring (5) on to the outer race of the radial
bearing (29).

Note
Adjustable rings must be adjusted so as to maintain 0-0.05mm
axial clearance between the bearing box, bearing box cover
and adjusting ring. Bearing must be closely fitted to the
bearing box.

15 Place a new O-ring (31) on the bearing keep (26).


Rev.003

16 Insert the bearing keep (26) onto the set of bearings.

MM-M02.01

17 Locate the plate for bearing keep (4) in its position matching the
marks provided during disassembly. Along with the plate locate the
lower adjusting ring (6) also.

Forced Draft Fan


Mitsubishi

5-30

Chapter-5

Disassembly and Reassembly

35

29

44

43

32

Rev.003

MM-M02.01

MPTD-3-0473

FIGURE 5-6
Forced Draft Fan
Mitsubishi

BEARING BOX - EXPLODED VIEW

5-31

Chapter 5

Disassembly and Reassembly


NUT

COUPLING

KEY

SLEEVE OF BEARING

O RING

THRUST BEARING (DE)


BEARING INNER SPACER

O RING
O RING

THRUST BEARING
BEARING OUTER SPACER

O RING
O RING
RADIAL BEARING (NDE)

SET SCREW

ROTOR

MM-M02.01

Rev.003

ROTOR STAND

MPTD-4-0554

FIGURE 5-7 SUPPORTNG PROCEDURE FOR BEARING REMOVAL


Forced Draft Fan
Mitsubishi

5-32

Chapter 5

5.4

Disassembly and Reassembly

Moving Blade Regulating Mechanism Linkage Disassembly


and Reassembly
a)

Preparation
Movable blade regulating mechanism linkage is not normally included in
overhaul maintenance but if it should ever be necessary, the procedure is
as follows. All associated equipment is to be mechanically and electrically
isolated and an authorized work permit and valid isolation certificate shall
be in place prior to the commencement of work. The outer casings are to
be removed. Please refer to section 5.1 for the details. The following
points are also to be considered while preparing for disassembly and
reassembly:

Have all necessary drawings and documents (log sheets, field record
book, etc.) ready prior to the start of work.

Prepare the necessary handling facilities (e.g. chain blocks, slings,


etc.) to remove and store the various parts of the equipment.

Special tools are listed in Appendix C.

Dont replace parts in a running unit. Also, when replacing a


new component, be careful the replacement does not fall on the
impeller wheel assembly.

Prepare a temporary platform / grating to work on the defective


cylinder during maintenance.

Dont move the drive unit. Special care is to be taken when


replacing the parts.

b)

Disassembly

MM-M02.01

Rev.003

All data is to be recorded during the disassembly of each part. During


disassembly, make match marks on the adjoining parts for reference
during the reassembly. The disassembly procedure is described as
follows:
Refer to Figures 2-8 and 5-8.
Forced Draft Fan
Mitsubishi

5-33

Chapter 5

Disassembly and Reassembly

Remove the split pins (19), pins (5) and nuts (11), thus disconnecting
the linkage assembly both from the pilot valve end and the control
drive unit. Remove the spherical bearings (6) and lever (1). While
removing the pin from the lever, take care not to drop the spherical
bearing (6) or the lever (1).

Note
If control drive unit is to be removed from the foundation during
disassembly, loosen the bolts on the stand on the control drive .
For disassembly and reassembly of the control drive, please refer
to the respective I&C vendor manual.

Remove the bolt (36), the bush (39) and the U nut and split pin
(37&38) thus disconnecting the power cylinder unit from the linkage
mechanism. While removing the connections on the lever (31) arrest
the detective cylinder assembly so that it does not fall of and cause
damage or injury to persons.

Remove the taper pin (21&22), U-nuts (24&25) and set screws
(18&26).

Remove the levers (30&31) from the operating shaft (28) and remove
the piece (4).

Remove the spring pin (23) and the pointer (29).

Remove the dust cover (32).

Remove the bolts (9), washers (12) and nuts (13); loosen set screws
(34) on both ends.

Remove the sleeve (33). Remove the ball bearing units (7&8) secured
to the operating shaft support (42).

Remove the taper pin (20), bolts (10) and nuts (11).

10 Remove the stand for scale plate (2) together with scale plate (3) from
the operating shaft support (42).
11 Withdraw the operating shaft (28) axially from outside the rear casing
(40).

c)

Reassembly

MM-M02.01

Rev.003

The reassembly procedure is carried out in the reverse sequence to that


for disassembly. Install all parts in the same positions they were removed
from, referring to the match marks and checking that the clearances are
maintained as specified.

Forced Draft Fan


Mitsubishi

5-34

Chapter 5

Disassembly and Reassembly

Refer to Figures 2-8 and 5-8.


1

Clean the operating shaft (28) and insert it through the operating shaft
support (42) from outside rear casing.

Locate the shaft in the same position as it occupied before


disassembly.

Locate the scale plate stand (2) on the operating shaft support (42)
flange with taper pin (20).

Secure the scale plate stand (2) by bolts (10) and washers (15).

Pack the ball bearing units (7&8) at both ends with lubricating grease
and insert it through the operating shaft (28).

Install the sleeve (33) with set screw (34) on both ends of the shaft
inside the bearings.

Secure the ball bearing units (7&8) to the operating shaft support (42)
flange with bolts (9), washers (12), (13).

Install the dust protective cover (32).

Install the scale pointer (29) and secure it to the operating shaft by the
spring pin (23).

10 Insert the piece (4) then insert the lever (30) onto the operating shaft
(28) from inside the rear inner casing (41).
11 Install the taper pin (21) and the U-nut (24).
12 Set the lever (30) in line with the pilot valve axis.
13 Install and tighten the set screws (18) after finalizing the lever
position.
14 Install the spherical bearings (6) into the apertures provided on the
lever (1),
15 Install the lever (1) and secure it with pins (5) and nuts (11) on both
ends of the lever.
16 Insert the split pins (19).
17 Insert the lever (31) onto the operating shaft (28) from outside the rear
housing.
Rev.003

18 Install the taper pin (22) and the U-nut (25).

MM-M02.01

19 Set the lever (31) in line with the actuator lever axis.
20 Install and tighten the set screw (26) after finalizing the lever position.

Forced Draft Fan


Mitsubishi

5-35

Chapter 5

Disassembly and Reassembly

21 Connect the lever (31) to the actuator linkage assembly by installing


the bolt (36), nut (37) and split pin (38).
22 Ensure the direction of detective cylinder assembly (27) as shown in
the Figure 5-8 before connecting the lever (31).
23 Start the control oil pump and check the blade operation from 0% to
100% by manually operating the actuator carefully.
24 Carryout any minor adjustments by altering the length of the lever (31)
and/or the blade sticking detector linkage assembly to achieve the full
range of blade operation.
25 Loosen the spring pin (23) and adjust the pointer (29) to match the
blade position of 0% to 100%.

MM-M02.01

Rev.003

26 Tighten the spring pin after final adjustment.

Forced Draft Fan


Mitsubishi

5-36

Chapter-5

Disassembly and Reassembly

ITEM

10

13

16
17

38

20

MM-M02.01

Rev.003

27

FIGURE 5-8
Forced Draft Fan
Mitsubishi

MB REGULATING LINKAGE MECHANISM EXPLODED VIEW


5-37

Chapter 5

5.5

Disassembly and Reassembly

Coupling Disassembly and Reassembly


a)

Preparation
If FDF coupling disassembly becomes necessary, all associated
equipment is to be mechanically and electrically isolated and an
authorized work permit and valid isolation certificate is to be in place prior
to the commencement of work. The outer casings are to be removed.
Please refer to section 5.1 for the details. The following points are also to
be considered when preparing for disassembly and reassembly:

b)

Have all necessary drawings and documents (log sheets, field record
book, etc.) ready prior to the start of the work.

Prepare the necessary handling facilities (e.g. chain blocks, slings,


etc.) to remove and store the various parts of the equipment.

Disassembly
All data is to be recorded during the disassembly of each part. During
disassembly, make match marks on the adjoining parts for reference
during reassembly. The disassembly procedure is described as follows:
1

Thoroughly clean the surrounding area and the suction casing before
commencement of the work.

Refer to Figure 2-5 and proceed as follows


2

Remove the coupling cover (24) provided outside of the suction


casing at the drive end.

Enter through the suction inner casing manhole (30) and slide the
intermediate shaft cover (23) from the suction inner casing side (28).

Refer to Figure 2-11 and proceed as follows;


4

Support the intermediate shaft (7 of Figure 2-11) suitably using the


supporting tools on both ends as shown in Figure 5-9.

Note
As per the design, the intermediate shaft cover can slide
inside the suction inner casing. This arrangement will provide
sufficient space for fixing the intermediate shaft supporting
special tool at the fan side. Further, the suction inner casing is
supported by the suction casing. After removing the coupling
Rev.003

cover the second supporting tool can be fixed on the other


end of the intermediate shaft towards the motor side.

MM-M02.01

24 Remove the coupling reamer bolts (4) and nuts (5) from the coupling
flange at the motor side securing the motor coupling (1) and the
coupling spacer (2).
Forced Draft Fan
Mitsubishi

5-38

Chapter 5

Disassembly and Reassembly

Note
Leave one coupling reamer bolt and nut in position (preferably at
the bottom hole) to prevent the spacer from falling during
removal. Loosen this bolt and nut to provide a gap for the removal
of the element and the washers.

c)

Gently tap and rotate the spacer (2) with respect to the remaining
coupling bolt.

Support the coupling spacer (2) suitably and remove the last coupling
bolt (3) and nut (5) from the coupling between the coupling spacer (2)
and the intermediate shaft (7).

Remove all the reamer bolts and nuts from the fan rotor coupling
flange.

If further disassembly is required, i.e. removal of coupling hub, use


the special tool to withdraw the hub from the shaft.

Reassembly

MM-M02.01

Rev.003

The reassembly procedure is carried out in the reverse sequence to that


for disassembly. Install all parts in the same positions they were removed
from, referring to the match marks and checking that the clearances are
maintained as specified. Refer to Figures 2-11 and 4-1.

Forced Draft Fan


Mitsubishi

Ensure that intermediate shaft (7 of Figure2-11) is supported by


supporting tool.

Check the shaft and the internal surface of the hub and remove any
scratches or blemishes on the surface.

Check the shaft key and the key ways to ensure that the surfaces are
smooth.

Insert the key into the shaft key way and then into the hub key way to
confirm the fit.

Measure the outside diameter of the shaft and the bore of the hub,
and record these values.

Clean the shaft and the hub. Insert the key into shaft key way. Heat
the hub in an oil bath to approximately 100C and fit the hub onto the
shaft.

Fix the reamer bolts (3&4 of Figure 2-11) on the fan side coupling.
Verify run out by rotation of the fan shaft. After the verification tighten
the coupling bolts and nuts to the specified torque.

Remove the intermediate shaft supporting tool on the fan side.

5-39

Chapter 5

Disassembly and Reassembly

Check the intermediate shaft level by placing a spirit level on the fan
side of the intermediate shaft machined surface.

10 Check that the intermediate shaft to motor shaft coupling alignment is


within the specified criteria (refer to Appendix D).
11 Make preparations for fixing the coupling reamer bolts (3 & 4 of Figure
2-11) with spacer (2 of Figure 2-11) on the motor side. Tighten the
coupling bolts and nuts to the specified torque.
12 Remove the intermediate shaft supporting tool on motor sides.
13 Install the intermediate shaft cover on the fan side and the coupling
cover on the motor side.

MM-M02.01

Rev.003

14 Remove the tools and tackles from inside the suction casing.

Forced Draft Fan


Mitsubishi

5-40

Chapter 5

Disassembly and Reassembly

IMPELLER CASING(INNER)
INTERMDIATE
SHAFT COVER

SLIDE

MOTOR SIDE
INTERMEDIATE SHAFT

CL OF FAN
50
20

180
(

2
B

10

B-B

6
A-A

ITEM
1
2
3
4
5
6
7
8
9
10

DESCRIPTION
JOINT
ADJUSTABLE BOLT
PIN
BEARING
RETAINING RING
BOLT,NUT
BOLT
SUPPORTING PLATE
SUPPORTING PLATE
SUPPORTING PLATE

MM-M02.01

Rev.003

MPTD-4-0556

FIGURE 5-9
Forced Draft Fan
Mitsubishi

CENTERING TOOL ASSEMBLY FOR INTERMEDIATE SHAFT

5-41

Chapter-6

Corrective Maintenance

C h a p t er

6 Corrective Maintenance
Corrective maintenance is the repair or replacement work undertaken for sudden failure of
any part or component of the equipment. Though a well planned preventive maintenance
program tries to minimize the probability of occurrence of sudden failure of equipment,
provision for attending these unscheduled maintenance requirements is to be made.
Corrective maintenance work is to be given priority depending on the seriousness of the
problem faced and the impact on plant operations. The schedule for repair of any
equipment should be carefully planned to keep outage time to a minimum.
During such repair or replacement work, an inspection is to be carefully conducted to
determine why the equipment or component has failed. Good corrective maintenance
requires, not only the quick restoration of the failed equipment back into service but also
demands every effort to identify and record the root cause of the failure. The inspection
results can be of significant help in exploring the exact reason for the failure. The findings,
along with possible rectification proposals, are to be used as a feedback to update the
preventive maintenance procedures.

6.1

Prerequisites
The necessary prerequisites for the corrective maintenance of the FDF are as
follows:

a)

Scheduling
Unlike preventive maintenance, scheduling activity only starts after failure of
the equipment. Depending on the severity of the problem, the importance of
the service provided by the failed equipment and availability of manpower to
attend to the problem, a contingency schedule is to be prepared to solve the
problem at the earliest opportunity. The schedule should clearly indicate the
critical path activity and assign the priority for different parallel activities.
Finally, once the schedule is agreed, strict adherence to it is to be maintained
to ensure timely completion of the maintenance activity.

b)

Departmental Interface/Notification
Refer to Section 4.1.2, Departmental Interface/Notification.

Isolation of Equipment
Refer to Section 4.1.3, Isolation of Equipment.

d)

MM-M02.01

Rev.003

c)

Safety Precautions
Refer to Section 4.1.4, Safety Precautions.

Forced Draft Fan


Mitsubishi

6-1

Chapter-6

6.2

Corrective Maintenance

Preparation
a)

Parts, Tools and Equipment


Refer to Subsection 4.2.1 a), Parts, Tools and Equipment.

b)

Documentation
Refer to Subsection 4.2.1 b), Documentation.

6.3

Troubleshooting

MM-M02.01

Rev.003

This section provides information about carrying out troubleshooting and servicing
for the FDF, pertaining to mechanical maintenance staff. Tables of Faults, Possible
Causes and Remedies have been provided to assist in troubleshooting by qualified
users. If any new kind of problem is encountered which is not listed in the following
table, contact the manufacturer for assistance.

Forced Draft Fan


Mitsubishi

6-2

Chapter-6

TABLE 6-1
Fault
Vibration

Corrective Maintenance

TROUBLESHOOTING FORCED DRAFT FAN


Possible Cause

Remedy

Lubricating oil supply flow/pressure low

Check oil flow in sight glass/adjust


pressure control valve setting

Bearing damaged

Replace bearings

Unbalance of rotor wheel and rotor shaft


due to attached foreign material or
misalignment

Perform field balancing

Bearing fixing bolts loose

Tighten the fixing bolts

Coupling deformation

Replace the damaged coupling


components and realign the fan and
motor

Inadequate lube oil flow

Check oil flow/pressure

Excessive oil temperature

Check and adjust cooling water supply


Clean the oil cooler

Ingress of debris

Check and rectify the cause for debris


ingress

Suction starvation of the lube oil pump

Changeover to the standby pump. Check


the suction filter

Foreign material inside the fan


casing/duct

Check and remove as necessary


material

Air leakage from the shaft seal or casing


flanged joints or cracks developed in
casing/ducting

Check for wear/cracking and repair


Check and replace gasket, if necessary

Contact of rotating parts with stationary


parts

Stop the fan and carry out internal


inspection to check the clearances

Damage of hydraulic cylinder parts

Repair or replace the damaged parts.


(Take record of difference in routine or
annual outage maintenance.)

Seizure of moving blade support bearing

Replace support bearing

Misalignment of linkage/levers

Correct & adjust the alignment

Failure of oil pump

Repair or replace

Malfunction of relief valve

Readjust or replace relief valve

Strainer plugged

Clean or replace strainer

Excessive pilot valve clearance

Replace pilot valve to have proper


clearance

Control/lubricating oil
pressure high

Malfunction of relief valve

Readjust or replace relief valve

Control/lubricating oil
leakage

O-ring failure in pilot valve

Replace O-rings

Excessive lube oil flow

Check and adjust oil flow

Excessive labyrinth seal clearance

Adjust seal clearance

Bearing temperature
high

Abnormal noise

Moving blade sticking

MM-M02.01

Rev.003

Control/lubricating oil
pressure low

Forced Draft Fan


Mitsubishi

6-3

Chapter-7

Recommended Lubrication

C h a p t er

7 R ec om m e nde d L ubr i cat i on


FD FAN RECOMMENDED LUBRICATION

MM-M02.01

Rev.003

TABLE 7-1

Forced Draft Fan


Mitsubishi

7-1

Appendix A

A p p en d i x

A Torque Chart
TABLE A-1
Description

TORQUE CHART

Bolt size

Quantity

Torque

Remarks

Bolt (for operating plate)

M16

16

147 N-m

Bolt (for cylinder cover assembly)

M16

12

147 N-m

Set screws and U nut (nut for M/B


shaft)

M10

14

21 N-m

Note: Perform the following steps in sequence:


Apply lubricants to the threads and seating surfaces when tightening bolts.

Do not use lubricant containing molybdenum when tightening bolts.

Tighten bolts in sequence art 120o intervals.

In the first stage, evenly tighten with 30% of the specified torque.

In the second stage, evenly tighten with 70% of the specified torque.

In the third stage, tighten with the specified torque.

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

A-1

Appendix B

A p p en d i x

MM-M02.01

Rev.003

B Spare Parts

Forced Draft Fan


Mitsubishi

B-1

Appendix B

RECOMMENDED LIST OF STRATEGIC SPARE PARTS (OFF SHORE, ONE YEAR)

MM-M02.01

Rev.003

TABLE B-1

Forced Draft Fan


Mitsubishi

B-2

Appendix B

RECOMMENDED LIST OF STRATEGIC SPARE PARTS (OFF SHORE, STRATEGIC)

MM-M02.01

Rev.003

TABLE B-2

Forced Draft Fan


Mitsubishi

B-3

Appendix C

A p p en d i x

MM-M02.01

Rev.003

C Special Tools

Forced Draft Fan


Mitsubishi

C-1

Appendix C

TABLE C-1
Eqt. ID *
(Note 1)

PJ No.

RG

RG

RG

RG

03HLB01AN1

03HLB01AN1

03HLB01AN1

03HLB01AN1

Tool ID

1-1

1-2

1-3

1-4

Special Tool Name/


Description

SUPPORTING TOOL

SUPPORTING TOOL

SUPPORTING TOOL

JOINT BAR
ASSEMBLY

Name of Eqt. for


which special
tools used

FDF

FDF

FDF

FDF

Suppliers
ID No. (Note 2)

B07100-0002001-001

B07100-0002001-002

B07100-0002001-003

B07100-0002001-004

FDF SPECIAL TOOL LIST (1 OF 7)


Total Qty.
Supplied for
Plant

2 SET

2 SET

2 SET

10 SET

Purpose

FOR
INTERMEDIATE
SHAFT

FOR
INTERMEDIATE
SHAFT

FOR
INTERMEDIATE
SHAFT

FOR
SUPPORTING
TOOL

Ref. Instruction /
Doc/DwgsNote # 3

N29-10M-7093

N29-10M-7093

N29-10M-7093

N29-10M-7093

Outline View &


Dimensions (Note # 4)

Weight

Remarks

11.5 kg

ASSEMBLING PARTS
- ADJUSTING BOLTS:
M30 (2PC)
SPECIAL TOOLS SHALL BE
USED UNDER MHI
SUPERVISION

5.3 kg

ASSEMBLING PARTS
- ADJUSTING BOLTS:
M30 (1PC)
SPECIAL TOOLS SHALL BE
USED UNDER MHI
SUPERVISION

27.8 kg

ASSEMBLING PARTS
- ADJUSTING BOLTS:
M30 (2PC)
SPECIAL TOOLS SHALL BE
USED UNDER MHI
SUPERVISION

1.13 kg

ASSEMBLING PARTS
- PIN : 5 PCS
- BEARING: NAST 15R
(5 PC)
- RETAINING RING:15
(5PC)
SPECIAL TOOLS SHALL BE
USED UNDER MHI
SUPERVISION

RG

03HLB01AN1

1-5

BOLT NUT M16x45

FDF

B07100-0002001-005

12 SET

FOR
SUPPORTING
TOOL

N29-10M-7093

0.141 kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

03HLB01AN1

1-6

BOLT M12x55

FDF

B07100-0002001-006

FOR
SUPPORTING
TOOL

N29-10M-7093

0.068 kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

C-2

Appendix C

TABLE C-1
Eqt. ID *
(Note 1)

PJ No.

RG

RG

03HLB01AN1

03HLB01AN1

Tool ID

3-1

Special Tool Name/


Description

SPANNER

INSERT PIECE

Name of Eqt. for


which special
tools used

Suppliers
ID No. (Note 2)

FDF

B07100-0002002-001

FDF

B07100-0002003-001

FDF SPECIAL TOOL LIST (2 OF 7)


Total Qty.
Supplied for
Plant

Purpose

1 SET

FOR M/B
FASTENING
NUT

FOR MOVING
BLADE ARM
BUSH

FOR MOVING
BLADE ARM
BUSH

Ref. Instruction /
Doc/DwgsNote # 3

Outline View &


Dimensions (Note # 4)

Weight

Remarks

1.1 kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

1.06 kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

0.48 kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

N29-10M-7093

RG

03HLB01AN1

3-2

PLATE

FDF

RG

10

03HLB01AN1

3-3

BOLT

FDF

B07100-0002003-003

FOR MOVING
BLADE ARM
BUSH

0.10 kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

11

03HLB01AN1

3-4

WIRE BAND

FDF

B07100-0002003-004

2 SET

FOR MOVING
BLADE ARM
BUSH

0.05 kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

12

03HLB01AN1

4-1

GUIDE RING

FDF

B07100-0002004-001

FOR MV
PACKING

N29-10M-7093

2.7 kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

MM-M02.01

Rev.003

B07100-0002003-002

Forced Draft Fan


Mitsubishi

C-3

Appendix C

TABLE C-1
Eqt. ID *
(Note 1)

PJ No.

RG

Tool ID

Special Tool Name/


Description

Name of Eqt. for


which special
tools used

Suppliers
ID No. (Note 2)

13

03HLB01AN1

4-2

TIGHTENING PLATE

FDF

B07100-0002004-002

FDF SPECIAL TOOL LIST (3 OF 7)


Total Qty.
Supplied for
Plant

Purpose

FOR MV
PACKING

Ref. Instruction /
Doc/DwgsNote # 3

Outline View &


Dimensions (Note # 4)

Weight

Remarks

N29-10M-7093

2.4kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

14

03HLB01AN1

4-3

INSERT RING

FDF

B07100-0002004-003

FOR MV
PACKING

N29-10M-7093

3.4kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

15

03HLB01AN1

4-4

GUIDE BAR & NUT


M10

FDF

B07100-0002004-004

3 SET

FOR MV
PACKING

N29-10M-7093

3.65 kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

16

03HLB01AN1

SPANNER

FDF

B07100-0002005-001

1 SET

FOR NUT OF
PISTON

N29-10M-7093

3.0 kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

17

03HLB01AN1

6-1

DRAW OUT TOOL

FDF

B07100-0002006-001

1 SET

FOR PISTON

N29-10M-7093

3.8 kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

6-2

GUIDE BAR &


NUTM16

FDF

B07100-0002006-002

0.26 kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

18

03HLB01AN1

2 SET

FOR PISTON

N29-10M-7093

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

C-4

Appendix C

TABLE C-1
Eqt. ID *
(Note 1)

PJ No.

RG

Tool ID

Special Tool Name/


Description

Name of Eqt. for


which special
tools used

Suppliers
ID No. (Note 2)

13

03HLB01AN1

4-2

TIGHTENING PLATE

FDF

B07100-0002004-002

FDF SPECIAL TOOL LIST (4 OF 7)


Total Qty.
Supplied for
Plant

Purpose

FOR MV
PACKING

Ref. Instruction /
Doc/DwgsNote # 3

Outline View &


Dimensions (Note # 4)

Weight

Remarks

N29-10M-7093

2.4kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

14

03HLB01AN1

4-3

INSERT RING

FDF

B07100-0002004-003

FOR MV
PACKING

N29-10M-7093

3.4kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

15

03HLB01AN1

4-4

GUIDE BAR & NUT


M10

FDF

B07100-0002004-004

3 SET

FOR MV
PACKING

N29-10M-7093

3.65kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

16

03HLB01AN1

SPANNER

FDF

B07100-0002005-005

1 SET

FOR NUT OF
PISTON

N29-10M-7093

3.0kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

17

03HLB01AN1

6-1

DRAW OUT TOOL

FDF

B07100-0002006-001

1 SET

FOR PISTON

N29-10M-7093

3.8kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

6-2

GUIDE BAR &


NUTM16

FDF

B07100-0002006-002

0.26kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

18

03HLB01AN1

2 SET

FOR PISTON

N29-10M-7093

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

C-5

Appendix C

TABLE C-1
Eqt. ID *
(Note 1)

PJ No.

RG

Tool ID

Special Tool Name/


Description

FDF SPECIAL TOOL LIST (5 OF 7)

Name of Eqt. for


which special
tools used

Suppliers
ID No. (Note 2)

FOR BOLT

19

03HLB01AN1

SOCKET WRENCH

FDF

B07100-0002007-001

Total Qty.
Supplied for
Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline View &


Dimensions (Note # 4)

Weight

Remarks

N29-10M-7093

1.74kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

20

03HLB01AN1

8-1

SPECIAL EYE BOLT

FDF

B07100-0002008-001

FOR ROTOR

2.8kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

21

03HLB01AN1

8-2

SPECIAL EYE BOLT

FDF

B07100-0002008-002

FOR ROTOR

1.2kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

22

03HLB01AN1

9-1

GUIDE TOOL

FDF

B07100-0002009-001

FOR CASING

2.59kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

23

03HLB01AN1

9-2

NUT M20

FDF

B07100-0002009-002

12

FOR CASING

0.059kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

5500 QLE-N

MM-M02.01

Rev.003

RG

24

03HLB01AN1

10

TORQUE WRENCH

FDF

B07100-0002010-001

1 SET

FOR BOLT

5.2 Kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

MPD-4-0579

Forced Draft Fan


Mitsubishi

C-6

Appendix C

TABLE C-1
Eqt. ID *
(Note 1)

PJ No.

RG

Tool ID

Special Tool Name/


Description

25

03HLB01AN1

11

MAINTENANCE
STAND

Name of Eqt. for


which special
tools used

Suppliers
ID No. (Note 2)

FDF SPECIAL TOOL LIST (6 OF 7)


Total Qty.
Supplied for
Plant

Purpose

FDF

B07100-0002011-001

1 SET

FOR ROTOR
ASSEMBLY

Ref. Instruction /
Doc/DwgsNote # 3

Outline View &


Dimensions (Note # 4)

Weight

Remarks

N29-10M-7093

353kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

RG

26

03HLB01AN1

12-1

TURN BUCKLE

FDF

B07100-0002012-001

6 SET

ROTOR
SUPPORT

N29-10M-7093

3.75kg

RG

27

03HLB01AN1

12-2

PLATE

FDF

B07100-0002012-002

ROTOR
SUPPORT

N29-10M-7093

0.06kg

ROTOR
SUPPORT

N29-10M-7093

0.15kg

ROTOR
SUPPORT

0.48kg

RG

28

03HLB01AN1

12-3

WASHER

FDF

B07100-0002012-003

RG

29

03HLB01AN1

13-1

GAS CHARGING
3-WAY VALVE
(M3-G02)

FDF

B07100-0002013-001

MHI INTERNAL REMARKS.


THESE TOOLS ARE
SUPPLIED WITH CASING
ASSEMBLY. AFTER FDF
INSTALLATION. THESE
TOOLS MUST BE STORED
WITH OTHER SPECIAL
TOOLS IN THE TOOL BOX,
TO USE THESE TOOLS IN
ASSEMBLING AND
DISASSEMBLING OF THE
OVERHAUL.
SPECIAL TOOLS SHALL BE
USED UNDER MHI
SUPERVISION.

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

STORE IN THE TOOL BOX


FOR ACCUMULATOR.
RG

30

03HLB01AN1

13-2

HOSE (H210-L02)

FDF

B07100-0002013-002

FOR
ACCUMULATOR

0.64kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

C-7

Appendix C

TABLE C-1
Eqt. ID *
(Note 1)

PJ No.

RG

31

03HLB01AN1

Tool ID

13-3

Special Tool Name/


Description

PRESSURE GAUGE

Name of Eqt. for


which special
tools used

FDF

Suppliers
ID No. (Note 2)

B07100-0002013-003

FDF SPECIAL TOOL LIST (7 OF 7)


Total Qty.
Supplied for
Plant

Purpose

FOR
ACCUMULATOR

Ref. Instruction /
Doc/DwgsNote # 3

Outline View &


Dimensions (Note # 4)

Weight

Remarks

STORE IN THE TOOL BOX


FOR ACCUMULATOR.
-

0.18kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

STORE IN THE TOOL BOX


FOR ACCUMULATOR.

RG

32

03HLB01AN1

13-4

ADAPTOR (AD-23)

FDF

B07100-0002013-004

FOR
ACCUMULATOR

0.18kg

RG

33

03HLB01AN1

13-5

CAP NUT WRENCH


(TWH81)

FDF

B07100-0002013-005

FOR
ACCUMULATOR

1.4kg

SPECIAL TOOLS SHALL BE


USED UNDER MHI
SUPERVISION

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

C-8

Appendix D

A p p en d i x

D Coupling Alignment
The following basic alignment procedure is suitable for most motor to driven machine couplings,
however, for certain types of coupling reference should be made to the manufacturers
instructions.
Peripheral Alignment
(Using a Dial Test Indicator (DTI)).
Match mark the coupling halves.

With both match marks at the top:


Check DTI reading at zero.

Turn both shafts 90, check DTI reading at 90.

Turn both shafts a further 90, check DTI reading at 180.

Turn both shafts a further 90, check DTI reading at 270.

Turn both shafts to zero, recheck DTI reading at zero.

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

D-1

Appendix D

Axial Alignment
An inside micrometer or a tapered gap gauge can be used dependent upon the size of the gap
between the coupling faces. This example uses an inside micrometer.
Ensure both match marks at the top:
1

With shafts stationary, measure a, b, c, d.

Turn both shafts 180 (match marks at the bottom).

With shafts stationary, measure c, d, a, b.

From the readings obtained, adjustments can be made to the liners (shims) installed under the
feet of the driving/driven equipment. Allowable tolerances are as follows:
Flexible Couplings

Rigid Couplings

Peripheral

0.05 mm

Peripheral

0.05 mm

Axial

0.05 mm

Axial

0.05 mm

However, the Flexible Coupling supplier, Daido Precision Industries Ltd, have mentioned the
following specific installation acceptance criteria:

MM-M02.01

Rev.003

Form Flex Coupling

Forced Draft Fan


Mitsubishi

Maximum End Float:

3.1 mm (0.10)

Maximum Lateral Misalignment:

31.8 mm (0.50)

D-2

Appendix E

A p p en d i x

MM-M02.01

Rev.003

E Applicable Vendor Drawings

Forced Draft Fans


Mitsubishi

E-1

MM-M02.01

Rev.003

Appendix E

MPTD-3-0474

Forced Draft Fan


Mitsubishi

FIGURE E-1

FORCED DRAFT FAN OUTLINE DRAWING

E-2

MM-M02.01

Rev.003

Appendix E

MPTD-3-0475

Forced Draft Fans


Mitsubishi

FIGURE E-2

FORCED DRAFT FAN SECTIONAL DRAWING

E-3

MM-M02.01

Rev.003

Appendix E

MPTD-3-0477

Forced Draft Fan


Mitsubishi

FIGURE E-3

FDF LUBRICANT & CONTROL OIL SYSTEM P & ID

E-4

MM-M02.01

Rev.003

Appendix E

MPTD-3-0477

Forced Draft Fan


Mitsubishi

FIGURE E-4

FDF-A LUBRICANT & CONTROL OIL UNIT ASSEMBLY - 1/2

E-5

MM-M02.01

Rev.003

Appendix E

MPTD-3-1198

Forced Draft Fan


Mitsubishi

FIGURE E-5

FDF-A LUBRICANT & CONTROL OIL UNIT ASSEMBLY - 2/2

E-6

MM-M02.01

Rev.003

Appendix E

MPTD-3-1199

Forced Draft Fan


Mitsubishi

FIGURE E-6

FDF-B LUBRICANT & CONTROL OIL UNIT ASSEMBLY - 1/2

E-7

MM-M02.01

Rev.003

Appendix E

MPTD-3-1200

Forced Draft Fan


Mitsubishi

FIGURE E-7

FDF-B LUBRICANT & CONTROL OIL UNIT ASSEMBLY - 2/2

E-8

Appendix F

A p p en d i x

MM-M02.01

Rev.003

F MV PACKING INSERTION

Forced Draft Fan


Mitsubishi

F-1

Appendix F
BOLT
HYDRAULIC CYLINDER
RETAINING RING

1
TO REPLACE THE MV PACKING,
REMOVE THE BOLT, THE RETAINING
RING AND THE STOPPER PLATE.
REMOVE THE OLD PACKING.
MV PACKING
STOPPER PLATE FOR MV PACKING

INSERT THE GUIDE BARS AND


THE GUIDE CYLINDER.

INSERT THE INNER ADAPTER,


INSERT THE MV PACKING,
INSERT THE RUBBER PACKING,
LOCATE THE INSERT RING.

GUIDE BAR

GUIDE BAR

GUIDE CYLINDER

INSERT RING
RUBBER PACKING

INNER ADAPTER

MV PACKING

LOCATE THE TEMPORARY


STOPPER PLATE EVENLY TIGHTEN
THE NUTS. GENTLY PUSH THE
INSERT RING AND THE PACKING
RINGS INTO THE HYDRAULIC
CYLINDER.

WHEN PACKINGS ARE INSERTED


REMOVE THE TEMPORARY
STOPPER PLATE, THE GUIDE BAR
AND THE INSERT RING, INSERT THE
OUTER ADAPTER, THE ORIGINAL
STOPPER PLATE, THE RETAINING
RING, AND THE BOLTS, TIGHTEN
THE BOLTS.
BOLT

STOPPER PLATE

HYDRAULIC CYLINDER
RETAINING RING

STOPPER PLATE

MM-M02.01

Rev.003

RUBBER PACKING

OUTER ADAPTER

NOTE:
SPECIAL TOOLS FOR THIS PROCEDURE ITEM
ARE IN SPECIAL TOOLS LIST, APPENDIX C.

RUBBER PACKING

INNER ADAPTER
MV PACKING

MPTD-4-1196

FIGURE F-1
Forced Draft Fan
Mitsubishi

MV PACKING INSERTION

F-2

MM-M02.01

Rev.003

Appendix F

FIGURE F-2

Forced Draft Fan


Mitsubishi

MV PACKING MATERIAL & DIMENSION

F-3

Appendix G

A p p en d i x

G APPLICABLE VENDOR MANUALS


Description

Manufacturer

Handling Manual of Lubrication Oil


Unit for FD Fan

Daikin Hydraulic Engineering Co. Ltd.


Japan

Handling Manual of Pleated Type


Accumulator

Nippon Accumulator Co., Ltd.


Japan

MM-M02.01

Rev.003

Item No.

Forced Draft Fan


Mitsubishi

G-1

Appendix G

APPENDIX G-1

HANDLING MANUAL
OF
LUBRICATION OIL UNIT FOR FD FAN

Rev.003

VENDOR:
DAIKIN HYDRAULIC ENGINEERING CO., LTD.

MM-M02.01

JAPAN

Forced Draft Fan


Mitsubishi

G-2

Appendix G

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

G-3

Appendix G

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

G-4

Appendix G

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

G-5

Appendix G

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

G-6

Appendix G

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

G-7

Appendix G

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

G-8

Appendix G

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

G-9

Appendix G

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

G-10

Appendix G

MM-M02.01

Rev.003

Forced Draft Fan


Mitsubishi

G-11

Appendix G

MM-M02.01

Rev.003

10

Forced Draft Fan


Mitsubishi

G-12

Appendix G

MM-M02.01

Rev.003

11

Forced Draft Fan


Mitsubishi

G-13

Appendix G

MM-M02.01

Rev.003

12

Forced Draft Fan


Mitsubishi

G-14

Appendix G

MM-M02.01

Rev.003

13

Forced Draft Fan


Mitsubishi

G-15

Appendix G

MM-M02.01

Rev.003

14

Forced Draft Fan


Mitsubishi

G-16

Appendix G

MM-M02.01

Rev.003

15

Forced Draft Fan


Mitsubishi

G-17

Appendix G

MM-M02.01

Rev.003

16

Forced Draft Fan


Mitsubishi

G-18

Appendix G

MM-M02.01

Rev.003

17

Forced Draft Fan


Mitsubishi

G-19

Appendix G

MM-M02.01

Rev.003

18

Forced Draft Fan


Mitsubishi

G-20

Appendix G

MM-M02.01

Rev.003

19

Forced Draft Fan


Mitsubishi

G-21

Appendix G

MM-M02.01

Rev.003

20

Forced Draft Fan


Mitsubishi

G-22

Appendix G

MM-M02.01

Rev.003

21

Forced Draft Fan


Mitsubishi

G-23

Appendix G

MM-M02.01

Rev.003

22

Forced Draft Fan


Mitsubishi

G-24

Appendix G

MM-M02.01

Rev.003

23

Forced Draft Fan


Mitsubishi

G-25

Appendix G

MM-M02.01

Rev.003

24

Forced Draft Fan


Mitsubishi

G-26

Appendix G

MM-M02.01

Rev.003

25

Forced Draft Fan


Mitsubishi

G-27

Appendix G

MM-M02.01

Rev.003

26

Forced Draft Fan


Mitsubishi

G-28

Appendix G

MM-M02.01

Rev.003

27

Forced Draft Fan


Mitsubishi

G-29

Appendix G

MM-M02.01

Rev.003

28

Forced Draft Fan


Mitsubishi

G-30

Appendix G

MM-M02.01

Rev.003

29

Forced Draft Fan


Mitsubishi

G-31

Appendix G

MM-M02.01

Rev.003

30

Forced Draft Fan


Mitsubishi

G-32

Appendix G

MM-M02.01

Rev.003

31

Forced Draft Fan


Mitsubishi

G-33

Appendix G

MM-M02.01

Rev.003

32

Forced Draft Fan


Mitsubishi

G-34

Appendix G

MM-M02.01

Rev.003

33

Forced Draft Fan


Mitsubishi

G-35

Appendix G

MM-M02.01

Rev.003

34

Forced Draft Fan


Mitsubishi

G-36

Appendix G

MM-M02.01

Rev.003

35

Forced Draft Fan


Mitsubishi

G-37

Appendix G

MM-M02.01

Rev.003

36

Forced Draft Fan


Mitsubishi

G-38

Appendix G

MM-M02.01

Rev.003

37

Forced Draft Fan


Mitsubishi

G-39

Appendix G

MM-M02.01

Rev.003

38

Forced Draft Fan


Mitsubishi

G-40

Appendix G

MM-M02.01

Rev.003

39

Forced Draft Fan


Mitsubishi

G-41

Appendix G

MM-M02.01

Rev.003

40

Forced Draft Fan


Mitsubishi

G-42

Appendix G

MM-M02.01

Rev.003

41

Forced Draft Fan


Mitsubishi

G-43

Appendix G

MM-M02.01

Rev.003

42

Forced Draft Fan


Mitsubishi

G-44

Appendix G

MM-M02.01

Rev.003

43

Forced Draft Fan


Mitsubishi

G-45

Appendix G

MM-M02.01

Rev.003

44

Forced Draft Fan


Mitsubishi

G-46

Appendix G

MM-M02.01

Rev.003

45

Forced Draft Fan


Mitsubishi

G-47

Appendix G

MM-M02.01

Rev.003

46

Forced Draft Fan


Mitsubishi

G-48

Appendix G

MM-M02.01

Rev.003

47

Forced Draft Fan


Mitsubishi

G-49

Appendix G

MM-M02.01

Rev.003

48

Forced Draft Fan


Mitsubishi

G-50

Appendix G

MM-M02.01

Rev.003

49

Forced Draft Fan


Mitsubishi

G-51

Appendix G

MM-M02.01

Rev.003

50

Forced Draft Fan


Mitsubishi

G-52

Appendix G

MM-M02.01

Rev.003

51

Forced Draft Fan


Mitsubishi

G-53

Appendix G

MM-M02.01

Rev.003

52

Forced Draft Fan


Mitsubishi

G-54

Appendix G

MM-M02.01

Rev.003

53

Forced Draft Fan


Mitsubishi

G-55

Appendix G

MM-M02.01

Rev.003

54

Forced Draft Fan


Mitsubishi

G-56

Appendix G

MM-M02.01

Rev.003

55

Forced Draft Fan


Mitsubishi

G-57

Appendix G

MM-M02.01

Rev.003

56

Forced Draft Fan


Mitsubishi

G-58

Appendix G

MM-M02.01

Rev.003

57

Forced Draft Fan


Mitsubishi

G-59

Appendix G

MM-M02.01

Rev.003

58

Forced Draft Fan


Mitsubishi

G-60

Appendix G

MM-M02.01

Rev.003

59

Forced Draft Fan


Mitsubishi

G-61

Appendix G

MM-M02.01

Rev.003

60

Forced Draft Fan


Mitsubishi

G-62

Appendix G

MM-M02.01

Rev.003

61

Forced Draft Fan


Mitsubishi

G-63

Appendix G

MM-M02.01

Rev.003

62

Forced Draft Fan


Mitsubishi

G-64

Appendix G

MM-M02.01

Rev.003

63

Forced Draft Fan


Mitsubishi

G-65

Appendix G

MM-M02.01

Rev.003

64

Forced Draft Fan


Mitsubishi

G-66

Appendix G

MM-M02.01

Rev.003

65

Forced Draft Fan


Mitsubishi

G-67

Appendix G

MM-M02.01

Rev.003

66

Forced Draft Fan


Mitsubishi

G-68

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-69

Appendix G

MM-M02.01

Rev.003

68

Forced Draft Fan


Mitsubishi

G-70

Appendix G

MM-M02.01

Rev.003

69

Forced Draft Fan


Mitsubishi

G-71

Appendix G

MM-M02.01

Rev.003

70

Forced Draft Fan


Mitsubishi

G-72

Appendix G

MM-M02.01

Rev.003

71

Forced Draft Fan


Mitsubishi

G-73

Appendix G

MM-M02.01

Rev.003

72

Forced Draft Fan


Mitsubishi

G-74

Appendix G

MM-M02.01

Rev.003

73

Forced Draft Fan


Mitsubishi

G-75

Appendix G

MM-M02.01

Rev.003

74

Forced Draft Fan


Mitsubishi

G-76

Appendix G

MM-M02.01

Rev.003

75

Forced Draft Fan


Mitsubishi

G-77

Appendix G

MM-M02.01

Rev.003

76

Forced Draft Fan


Mitsubishi

G-78

Appendix G

MM-M02.01

Rev.003

77

Forced Draft Fan


Mitsubishi

G-79

Appendix G

MM-M02.01

Rev.003

78

Forced Draft Fan


Mitsubishi

G-80

Appendix G

MM-M02.01

Rev.003

79

Forced Draft Fan


Mitsubishi

G-81

Appendix G

MM-M02.01

Rev.003

80

Forced Draft Fan


Mitsubishi

G-82

Appendix G

MM-M02.01

Rev.003

81

Forced Draft Fan


Mitsubishi

G-83

Appendix G

MM-M02.01

Rev.003

82

Forced Draft Fan


Mitsubishi

G-84

Appendix G

MM-M02.01

Rev.003

83

Forced Draft Fan


Mitsubishi

G-85

Appendix G

MM-M02.01

Rev.003

84

Forced Draft Fan


Mitsubishi

G-86

Appendix G

MM-M02.01

Rev.003

85

Forced Draft Fan


Mitsubishi

G-87

Appendix G

MM-M02.01

Rev.003

86

Forced Draft Fan


Mitsubishi

G-88

Appendix G

MM-M02.01

Rev.003

87

Forced Draft Fan


Mitsubishi

G-89

Appendix G

MM-M02.01

Rev.003

88

Forced Draft Fan


Mitsubishi

G-90

Appendix G

MM-M02.01

Rev.003

89

Forced Draft Fan


Mitsubishi

G-91

Appendix G

MM-M02.01

Rev.003

90

Forced Draft Fan


Mitsubishi

G-92

Appendix G

MM-M02.01

Rev.003

91

Forced Draft Fan


Mitsubishi

G-93

Appendix G

MM-M02.01

Rev.003

92

Forced Draft Fan


Mitsubishi

G-94

Appendix G

APPENDIX G-2

HANDLING MANUAL
OF

Rev.003

PLEATED BLADDER TYPE ACCUMULATOR

MM-M02.01

VENDOR:
NIPPON ACCUMULATOR CO., LTD.

Forced Draft Fan


Mitsubishi

G-95

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-96

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-97

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-98

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-99

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-100

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-101

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-102

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-103

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-104

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-105

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-106

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-107

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-108

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-109

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-110

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-111

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-112

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-113

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-114

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-115

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-116

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-117

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-118

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-119

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-120

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-121

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-122

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-123

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-124

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-125

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-126

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-127

MM-M02.01

Rev.003

Appendix G

Forced Draft Fan


Mitsubishi

G-128

Appendix H

A p p en d i x

MM-M02.01

Rev.003

H PART LIST

Forced Draft Fan


Mitsubishi

H-1

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-2

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-3

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-4

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-5

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-6

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-7

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-8

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-9

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-10

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-11

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-12

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-13

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-14

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-15

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-16

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-17

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-18

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-19

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-20

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-21

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-22

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-23

MM-M02.01

Rev.003

Appendix H

Forced Draft Fan


Mitsubishi

H-24

Appendix I

A p p en d i x

MM-M02.01

Rev.003

Moving Blade
Paint Data Sheet

Forced Draft Fan


Mitsubishi

I-1

MM-M02.01

Rev.003

Appendix I

TABLE I-1
Forced Draft Fan
Mitsubishi

MOVING BLADE PAINT DATA SHEET (1 of 2)

I-2

MM-M02.01

Rev.003

Appendix I

TABLE I-2
Forced Draft Fan
Mitsubishi

MOVING BLADE PAINT DATA SHEET (2 of 2)

I-3

You might also like