You are on page 1of 353

Project Dwg. No: G101-25-1700.

01-MM51

Main Turbine
MECHANICAL MAINTENANCE MANUAL
PT PAITON ENERGY
PAITON EXPANSION PROJECT

Main Turbine Maintenance


Manual No. MM-M05.01
Revision 001

Note
This mechanical maintenance manual is intended to provide the Paiton Expansion Project
mechanical maintenance personnel with the basic understanding required to perform preventive,
routine, corrective and overhaul maintenance activities on the subject equipment.

No part of this document may be reproduced for use by parties other than Mitsubishi Heavy
Industries, Ltd. and Paiton Expansion Project.

Main Turbine
Maintenance

Be sure to read this manual.

Contents

Safety

General

Specifications

Preventive Maintenance

Disassembly and Reassembly

Corrective Maintenance

Recommended Lubrication

Appendixes

Contents

Contents
Revision Record i
Important Informationii
Warranty v
Limitation of Liabilityvii
Copyrightix
Personnel to whom the Manual is Directed x
Contact Addressxi
Abbreviations xii
List of Vendor Manuals xiii
Arrangement of the System Maintenance Manualxiv

Chapter1

Safety ____________________________

1.1

Feature of Main Turbine Safety 1-1

1.2

Warnings Description 1-2


1.2.1

Definitions of Serious Injury, Minor Injury, Serious


Damage to Property, and Minor Damage to Property 1-3

1.2.2

Symbol 1-4

1.2.3

Hazard Warning Label 1-5

1.2.4

Hazard Area 1-7

1.3

Risk Assessment Standard 1-8

1.4

Safety Measures

1-10

1.4.1

Work Permit System (Lockout/Tagout) 1-10

1.4.2

General Cautions on Personnel in Working Area 1-11

1.4.2.1 Caution against Rotating Equipment 1-11


1.4.2.2 Cautions against High Voltage Section 1-11
1.4.2.3 Cautions against High Temperature Sections 1-12
1.4.2.4 Cautions for Steam Leak in the Plant 1-13
1.4.2.5 Cautions against Oil Leak in the Plant 1-13
1.4.2.6 Cautions against Chemicals 1-14
1.4.2.7 Cautions against Combustible Materials/Storage Areas 1-14
Rev.001

1.4.2.8 Cautions against Lack of Oxygen 1-15


1.4.2.9 Cautions against Lifting Heavy Object 1-16
1.4.2.10 Caution against Sharp Objects 1-16

MM-M05.01

1.4.2.11 Cautions using Fork Lift 1-16

Main Turbine
Mitsubishi

Contents

Chapter1

Safety (Continued from previous page)


1.4.2.12 Cautions using Crane 1-17
1.4.2.13 Disposal 1-18

1.5

Emergency Measure 1-19


1.5.1

Evacuation on Emergency Case 1-19

1.5.1.1 Evacuation Route 1-19


1.5.1.2 Evacuation of disabled persons who cannot move by
themselves 1-19
1.5.1.3 Evacuation from Power House 1-20
1.5.2

Fire Accident 1-21

1.5.3

Earthquake 1-22

1.5.4

Explosion Accident 1-22

1.6

Qualification and Training 1-23

Chapter2

General ___________________________

2.1

Purpose 2-1

2.2

References 2-1

2.3

Overview of the Main Turbine 2-2

2.4

Components 2-8
2.4.1

Turbine Casings 2-9

2.4.2

Rotors 2-12

2.4.3

Blading 2-16

2.4.4

Rotor Seals 2-23

2.4.5

Gland Seals 2-24

2.4.6

Turbine Bearings 2-25

2.4.7

Rotor Couplings 2-33

2.4.8

Steam Admission Valves 2-34

2.4.9

Turning Gear 2-35

2.4.10 Rotor Grounding Device 2-36


2.4.11 Breakable Diaphragm 2-36
2.4.12 Turbine Enclosure 2-37

Specifications _____________________

MM-M05.01

Rev.001

Chapter3

Main Turbine
Mitsubishi

Contents

Chapter4

Preventive Maintenance _____________

4.1

Prerequisites 4-1

4.2

4.3

4.1.1

Scheduling 4-1

4.1.2

Departmental Interface/Notification 4-2

4.1.3

Isolation of Equipment 4-2

4.1.4

Safety Precautions 4-2

4.1.5

Visual Inspection 4-3

Routine Maintenance 4-4


4.2.1

Preparation 4-4

4.2.2

Inspection and Maintenance 4-5

Outage Maintenance 4-13


4.3.1

Preparation 4-13

4.3.2

Inspection and Maintenance 4-13

Disassembly and Reassembly ________

5.1

HP-IP Turbine Disassembly and Reassembly 5-1

5.2

LP1 Turbine Disassembly and Reassembly 5-54

5.3

LP2 Turbine Disassembly and Reassembly 5-94

Chapter6

Corrective Maintenance _____________

6.1

Prerequisites 6-1

6.2

Preparation 6-2

6.3

Troubleshooting 6-2

Chapter7

Recommended Lubrication __________

MM-M05.01

Rev.001

Chapter5

Main Turbine
Mitsubishi

Contents

Appendixes
Torque Chart A-1

Appendix B

Recommended Spare Parts B-1

Appendix C

Special Tools C-1

Appendix D

Coupling Alignment D-1

Appendix E

Applicable Vendor Drawings E-1

Appendix F

Bolt Tightening Details F-1

Appendix G

Top and Bottom Blade Radial Clearance Check


Procedure G-1

Appendix H

Lifting Methods H-1

Appendix I

Tightening Large Bolts and Studs with Heating Elements I-1

MM-M05.01

Rev.001

Appendix A

Main Turbine
Mitsubishi

Contents

Figure1-1

Types of Hazard Warning Labels 1-6

Figure 1-2

Mapping for Hazard Areas 1-9

Figure 2-1

Main and Reheat Steam Flow Diagram 2-4

Figure 2-2

Isometric View of Main Turbine 2-5

Figure 2-3

Sectional View of Main Turbine 2-6

Figure 2-4

Turbine and Generator Outline 2-7

Figure 2-5

Cutaway View of HP-IP Turbine 2-38

Figure 2-6

Sectional View of HP-IP Turbine 2-39

Figure 2-7

Cutaway View of LP1 Turbine 2-40

Figure 2-8

Sectional View of LP1 Turbine 2-41

Figure 2-9

Cutaway View of LP2 Turbine 2-42

Figure 2-10

Sectional View of LP2 Turbine 2-43

Figure 2-11

Turbine Casing Anchoring Details 2-44

Figure 2-12

Turbine Casing Centering and Tie Beams Arrangement 2-45

Figure 2-13

HP Pedestal Arrangement 2-46

Figure 2-14

IP to LP Turbines Cross-over Pipe Arrangement 2-47

Figure 2-15

HP-IP Rotor Assembly 2-48

Figure 2-16

LP1 Rotor Assembly 2-49

Figure 2-17

LP2 Rotor Assembly 2-50

Figure 2-18

Mechanical Overspeed Test (MOST) Device 2-51

Figure 2-19

HP Turbine Impulse Blading Rateau Stage 2-52

Figure 2-20

HP Turbine Reaction Blading 2-53

Figure 2-21

IP Turbine Reaction Blading 2-54

Figure 2-22

LP1/LP2 Turbine Reaction Blading 2-55

Figure 2-23

HP Turbine Blading-Seal Arrangement 2-56

Figure 2-24

IP Turbine Blading-Seal Arrangement 2-57

Figure 2-25

LP1/LP2 Turbine Blading-Seal Arrangement 2-58

Figure 2-26

Typical Turbine Shaft Gland Sealing Arrangement 2-59

Rev.001

Figure 2-27

Sectional View of Main Bearing Nos. 1 and 2 2-60

Figure 2-28

Sectional View of Main Bearing Nos. 3, 4 and 5 2-61

MM-M05.01

List Of Figures

Figure 2-29

Sectional View of Main Bearing No. 6 2-62

Main Turbine
Mitsubishi

Contents

MM-M05.01

Rev.001

List Of Figures (continued from previous page )

Main Turbine
Mitsubishi

Figure 2-30

Thrust Bearing Assembly 2-63

Figure 2-31

HP-IP to LP1 Rotor Coupling 2-64

Figure 2-32

LP1 to LP2 Rotor Coupling 2-65

Figure 2-33

LP2 to Generator Rotor Coupling 2-66

Figure 2-34

Main Stop Valve and Governing Valve Assembly 2-67

Figure 2-35

Interceptor Valve and Reheat Stop Valve Assembly 2-68

Figure 2-36

Main Turbine Turning Gear 2-69

Figure 2-37

Rotor Grounding Device 2-70

Figure 2-38

Breakable Diaphragm 2-71

Figure 2-39

Arrangement of Turbine Enclosure 2-72

Figure 5-1

HP-IP Turbine Inlet Steam Piping 5-44

Figure 5-2

HP-IP Turbine Shell Clearance 5-45

Figure 5-3

HP Turbine Shaft Gland Design Clearances 5-46

Figure 5-4

IP Turbine Shaft Gland Design Clearances 5-47

Figure 5-5

No.1 and No.2 Dummy Rings Design Clearances 5-48

Figure 5-6

HP Turbine Rotor and Cylinder Design Clearances 5-49

Figure 5-7

IP Turbine Rotor and Cylinder Design Clearances 5-50

Figure 5-8

HP-IP Turbine Blade and Gland Seals Radial


Clearances 5-51

Figure 5-9

Support Arrangement for the HP-IP Turbine Parts 5-52

Figure 5-10

HP- IP Turbine Rotor Guide Pillar Location 5-53

Figure 5-11

LP1 Turbine Shell Clearances 5-84

Figure 5-12

LP1 Turbine Gov End Shaft Gland Design


Clearances 5-85

Figure 5-13

LP1 Turbine Gen End Shaft Gland Design Clearances 5-86

Figure 5-14

LP1 Turbine Gov End Rotor and Cylinder Design


Clearances 5-87

Figure 5-15

LP1 Turbine Gen End Rotor and Cylinder Design


Clearances 5-88

Figure 5-16

LP1 Turbine - Blade and Gland Seals Radial Clearance


Table 5-89

Figure 5-17

LP1 Rotor Guide Pillar and Inner Casing Guide Bolt


Locations 5-90

Figure 5-18

Exhaust Flow Guide Lifting Arrangement 5-91

Contents

List Of Figures (continued from previous page )


Support Arrangement for the LP/LP2 Turbine Parts 5-92

Figure 5-20

LP2 Turbine Shell Clearances 5-123

Figure 5-21

LP2 Turbine Gov End Shaft Gland Design


Clearances 5-124

Figure 5-22

LP2 Turbine Gen End Shaft Gland Design


Clearances 5-125

Figure 5-23

LP2 Turbine Gov End Rotor and Cylinder Design


Clearances 5-126

Figure 5-24

LP2 Turbine Gen End Rotor and Cylinder Design


Clearances 5-128

Figure 5-25

LP2 Turbine - Blade and Gland Seals Radial Clearance


Table 5-128

Figure 5-26

LP2 Rotor Guide Pillar and Inner Casing Guide Bolt


Locations 5-129

Figure E-1

Turbine Sectional Assembly E-2

Figure E-2

Steam Turbine and Generator Overhaul Plan E-3

Figure F-1

Cylinder Bolting Arrangement F-2

Figure F-2

HP-IP Turbine Cylinder Bolting ArrangementF-3

Figure F-3

LP1, LP2 Turbine Cylinder Bolting ArrangementF-4

Figure F-4

HP-IP Turbine Cylinder Bolting ArrangementF-5

Figure F-5

LP1/ LP2 Turbine Cylinder Bolting ArrangementF-6

Figure H-1

HP IP and LP Turbines Lifting Gear Assemblies H-2

Figure I-1

Bolt Stretch Measurement I-7

MM-M05.01

Rev.001

Figure 5-19

Main Turbine
Mitsubishi

Contents

List of Tables
Main Risk Assessment Standard as per MIL STD822 1-8

Table 3-1

Main Turbine 3-1

Table 4-1

Routine Maintenance Checklist 4-8

Table 4-2

Standard Inspection Periods 4-23

Table 4-3

Outage Maintenance Check List 4-24

Table 6-1

Troubleshooting Main Turbine 6-3

Table A-1

Stretch for Alloy Steel Bolts A-1

Table A-2

Alloy Steel Bolt Tightening TorqueA-1

Table B-1

Recommended List of Strategic Spare Parts B-1

Table B-2

Recommended List of Strategic Spare


Parts (Offshore)B-4

Table B-3

Recommended Spare Parts List for One Year


Operation (Offshore) B-13

Table C-1

Main Turbine Special Tools C-1

Table I-1

Details of Bolts and Bolts Heaters I-6

MM-M05.01

Rev.001

Table 1-1

Main Turbine
Mitsubishi

Revision Record
Page Number
General

Description of Revision
Revision record added and all

Revision Issue
Date

Date Revised

Pages
Inserted

2012/03/26

2012/03/26

2012/03/26

2012/03/26

2012/03/26

2012/03/26

pages modified to revision 001


Drawing Review Sheet (DRS)
added.
Page 2-2

Chapter 2 Section 2.3 para 1


steam air heater removed.

Page 2-52

Chapter 2 Figure 2-19


revised.

Page 3-1

Chapter 3 Table 3-1 LP2


critical speed revised.

Page 4-6

Chapter 4 Sub-section 4.2.2


para. 5 revised.

Page 4-10

Chapter 4 Table 4-1 Item 6

MM-M05.01

Rev.001

remarks revised.

Main Turbine
Mitsubishi

Important Information
Purpose of the Plant Usage
This plant is designed to generate electric power of 815 MW by the steam turbine
generator.
The plant is only used for the electric power generation purpose that supports stable
and reliable electric power supply to the power grid and supplying steam for auxiliary
equipment in the power station.

General
1.

To satisfy the purpose mentioned above the following points must be strictly
observed,
a)

The operation, maintenance and inspection of Equipment must be


performed by the persons who have basic technical knowledge and have
been trained concerning the hazard of the Equipment and the avoidance
of the hazard.

b)

The operators and maintainers must read and understand these manuals
before starting the operation, maintenance or inspection.
It is often experienced that serious damage to the equipment or personnel
have occurred by the unexpected action of operators or maintainers who
do not fully understand the equipment.

c)

The modification or change of operational specification must be performed


under MHI supervision or as per the written acceptances of MHI.
The modification or change of specification causes not only a decline in
performance but also a decline in safety for operation of the equipment.
The Customer is requested to contact MHI regarding any modification or
proposed changes before the work commences.

MM-M05.01

Rev.001

The address for MHI to be contacted is shown in this chapter.


2.

The operation and maintenance must be performed according to the applicable


laws and regulations at the location of the power station.

3.

Disposal from the power station must be treated to satisfy the local regulations.

4.

The copyright of software, drawings and other documents provided by MHI at


all times, is still reserved by MHI.

Main Turbine
Mitsubishi

ii

Use or copying of the whole or part of any information provided by MHI for
any purpose other than operation and maintenance of this plant without
written consent is strictly prohibited.

Important General Notice for Safety


1.

The operator and maintainer must have knowledge about the equipment to
maintain good operating condition and to avoid danger when using the
equipment and systems.

2.

The protection measures must satisfy all of the operational functions.

3.

The safety activity must be planned systematically as a Safety and Health


management system and operate continuously.
Safety and Health management system must include the following points,
a) Instruction for use and the maintenance of the personal protective
equipment issued to operators and maintainers
b) The establishment of a work management organization to make clear the
operation directives and work procedures
c) Implementation of training for operator and maintainer

4.

The Customer must train the operators and maintainers to act positively and
to prevent the occurrence of an accident by using their knowledge of the
power plant.

5.

The Customer must make the operators and maintainers understand that the
most important purpose of safety control is to protect all personnel from
accidents and also to maintain operation of the plant without troubles.

6.

To prevent accidents involving personnel and equipment, it is necessary to


observe the notices of this manual and to keep the correct operation
according to the description provided in this manual.
If the notices are not observed, the following dangers could occur to the
operator, and to the maintainer.

7.

Risk of a fatal accident

b)

Danger to lose his health and fitness

c)

Danger of damage to the equipment

MHI can not forecast all possible dangers existing in the plant such as danger
due to human error and/or dangers caused by the operating environment.
As this manual and the alert label cannot cover all of the dangers, the
operators and maintainers have to pay their full attention to all general safety
notices.

Rev.001
MM-M05.01

a)

Main Turbine
Mitsubishi

iii

8.

MHI can not be responsible for damages and injury caused by neglecting the
notices in this manual, and other necessary general notices.

Instruction of this Manual


This manual is provided for people familiar with the use of English. If some
person not familiar with English is going to operate the plant, the Customer
must train him specially.

2.

The warning labels are to be expressed in the English language.

3.

This manual contains optional matters.

4.

Some figures in this manual include internal parts of the equipment which
may not be obvious, when looking at the completed equipment drawing.

5.

MHI may change the content of this manual without notice.

6.

This manual is intended for the use by the operators and maintainers and it
must be accessible to them at all times.

7.

If the Customer needs more detailed information, please contact MHI local
office or MHIs official agent.

MM-M05.01

Rev.001

1.

Main Turbine
Mitsubishi

iv

Warranty

The provisions set forth in this section are in addition to all liability and warranty
disclaimers and limitations set forth in the Contract, whether arising under law
or from course of performance, course of dealing, or usage of trade.

Nothing in these provisions shall constitute or be deemed to constitute any


additional liability undertaking or warranty, express or implied, with respect to
the Plant. All capitalized terms used, but not defined in this Warranty
Limitations section shall have the respective meanings ascribed to them in the
Contract.

The Contract Warranties are subject to the construction, installation and


Customering works having been performed in full compliance with the
requirements stated in (a) the Contract, (b) all manuals provided by MHI,
including this manual, (c) all applicable rules, regulations and laws prevailing in
the location where the Plant has been installed and will operate, and (d) any
other instructions, if any, provided by MHI (collectively, Rules and
Requirements). The Contract Warranties will NOT cover any accidents, partial
or total failure of the Plant, losses or damages to personnel or property
(including, without limitation, the Plants components, parts, systems and other
equipment), or any other liability (collectively, Accidents and Damages) in the
case of any breach of the stated Rules and Requirements.

For the detailed terms and conditions of the warranty concerning the Works
and Project, refer to the Contract.

In addition to the foregoing, the Contract Warranties will NOT cover any of the
following Accidents and Damages:
Accidents and Damages caused by any deviation from the Rules and
Requirements;

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

Accidents and Damages caused by the modification or re-installation of the


Plant after the original installation, or caused by operation of the Plant for a
purpose other than that for which it is designed;

Accidents and Damages caused by natural disasters or accidents during


transfer or related handling;

Accidents and Damages occurring after the term of the warranty has expired;

Accidents and Damages due to faulty operation or operation not in accordance


with the Rules and Requirements;

Accidents and Damages due to inappropriate maintenance or servicing


performed by the Customer, its personnel or any other party.

Accidents and Damages caused by any components, parts, systems or other


equipment other than those delivered by MHI;

Accidents and Damages caused by unidentifiable reasons including loss of the


damaged parts which is necessary to pinpoint a cause of the failure;

Accidents and Damages caused by referring to inadequate, or incorrect


references, data or information provided by the Customer;

Accidents and Damages or rust/corrosion due to inadequate handling and/or


storage by the Customer; or

Accidents and Damages due to handling, storage and/ or use of the Plant
under severe conditions or in an environment that does not meet the design
specification conditions.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

vi

Limitation of Liability
General

Nothing in this Limitation of Liability section or manual shall constitute or be


deemed to constitute any additional liability undertaking or warranty, express
or implied, with respect to the Plant. All capitalized terms used, but not defined
in this Limitation of Liability section shall have the respective meanings
ascribed to them in the Contract.

The contents of this manual are subject to change without prior notice and
without any obligation or liability to MHI.

Use and Disposal

Use of the Plant must be limited to the use specified by MHI, including without
limitation, use of the Plant in accordance with the Contract, this manual, all
Safety Manuals, all applicable laws and regulations, and any other instructions,
if any, provided by MHI. The Plant components, parts, systems and other
equipment (collectively, Equipment) must be appropriately disposed of in
accordance with the Contract, this manual, all Safety Manuals, all applicable
laws and regulations, and any other instructions, if any, provided by MHI.

For Documents and Safety Training

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

The Customers personnel must read, understand and abide by all documents
provided by MHI, including without limitation, the operation and maintenance
manuals, safety manuals, and instruction manuals (collectively, Safety
Manuals) and must have received all required and/or necessary safety
training prior to the start of their work. Persons who have not received such
safety training are not permitted to work on the installed Plant. This initial
training, however, is merely the minimum requirements prior to allowing any
personnel to work on the installed Plant. The Customer must, on a continual
and regular schedule, give up-to-date training to its personnel on safety
requirements, provide testing or other methods to confirm their understanding
of the safety training, and confirm that they have the physical and mental
capability to perform their respective roles. The Customers obligation for
safety training and personnel supervision is an ongoing obligation and must be
continuously performed and kept current throughout the operation of the Plant.
Accidents, partial or total failure of the Plant, damage to personnel or property,
loss, injuries, and other liability (collectively, Liability) caused by inadequate
safety training or the Customers personnels failure to abide by the documents
provided by MHI are expressly excluded from the coverage of any warranty
provided by MHI and are the sole and exclusive responsibility of the Customer.

vii

MHI will NOT be liable for any Liability caused by modification or changes
made in Plant-related documents (including any Safety Manual) by anyone
other than MHI.

For Damage to the Plant


Accidents may occur by use of Equipment that is acquired from anyone other
than MHI or anyone not appointed by MHI to modify or repair this Plant. The
Customer shall not be permitted to modify or repair the Plant or change
Equipment of the Plant without MHIs prior written approval, under any
circumstance.

MHI will NOT be liable for any Liability resulting from any abuse, misuse,
misapplication of the Equipment supplied by MHI.

MHI will NOT be liable for any Liability caused by an act by the Customer in
violation of the Contract, this manual, any applicable law or regulation, or any
Safety Manual or any other instruction provided by MHI, including without
limitation, a change of the installation environment or the removal and
installation of any Equipment in a location different to that originally selected by
MHI.

MHI will NOT be liable for any Liability caused by a defect, imperfection, or fault,
in material or Equipment that was used during a repair, even when such repair
was performed by or under an instruction given by MHI.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

viii

Copyright
COPYRIGHT 2009, MITSUBISHI HEAVY INDUSTRIES, LTD. ALL RIGHTS
RESERVED. ANY REPRODUCTION IS EXPRESSLY PROHIBITED.
All of the content contained in this manual is protected by Japanese,
International and/or United States copyright laws.

All copyright, trade secrets, and other proprietary and intellectual property
rights in the documents provided by Mitsubishi Heavy Industries, Ltd.(MHI)
(including safety-and-instruction manuals) are at all times owned and reserved
by MHI. Subject to your compliance with the restrictions set forth below, MHI
grants to you a limited, non-exclusive license in the copyright for the sole
purpose of allowing you to use, operate, maintain and inspect the Plant.

Use, copying, other reproduction of the whole or part of the documents


provided by MHI (including safety-and-instruction manuals) for any purpose
other than the purpose described above without MHIs prior written consent is
strictly prohibited.

The act of rewriting, translating, modifying, revising, creating electronic copies,


uploading, selling, sublicensing, or otherwise disclosing the whole or part of the
manuals is strictly prohibited.

Except as specifically set forth above, no right, title or license to the documents
provided by MHI, whether arising from contract, implication, estoppel or
otherwise, is being granted or otherwise transferred.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

ix

Personnel to whom the


Manual is Directed
This Manual was prepared for all personnel who will participate in the operation and
maintenance of the plant, and the other related mechanical plant and equipment
installed.
In this Manual, MHI classifies personnel into the following two classes based on
their ability, experience and their attitude to the safety of personnel, and the plant
installed.
Only the personnel recognized by the Customer as trained personnel are allowed to
perform the operation and maintenance specified in the manuals.
Maintainers and Operators are required to have read and understood the contents
of the safety, operation, and maintenance manuals and sufficiently understand the
work procedures before actually starting their tasks.

Operator

Operators following the instructions of their supervisor or the Shift Charge Engineer
are permitted to handle materials to be used in the operation of the plant.
Operators are allowed to turn on the power supply, startup equipment, open up or
remove covers or panels on receipt of an instruction or authorization from their
superior.
Operators are permitted access to emergency stop devices following instructions
given by their superior when dangerous or hazardous situations are recognized.

Maintainer

MM-M05.01

Rev.001

Maintainers are permitted to perform maintenance on the plant. They will also
perform troubleshooting routine and periodical inspections of the installed
equipment. The maintainer will also work under the supervision of MHIs
supervisors during on-the-job training and annual maintenance and overhaul work if
MHIs supervisors are requested to witness periodical inspections, etc.
Maintainers MUST have attended the training programme initially provided by MHI
and subsequently by the Customer, and they must have obtained the necessary
knowledge and maintenance skills to understand the characteristics of their tasks
before actually starting their work.
Main Turbine
Mitsubishi

Contact Address
For any question or any clarification required, please do not hesitate to contact MHI
through the following address (es).

For Support before Operation:


MITSUBISHI HEAVY INDUSTRIES, Ltd.
Nagasaki Shipyard & Machinery Works

MM-M05.01

Rev.001

1-1, Akunoura Machi, Nagasaki 850-91

Main Turbine
Mitsubishi

xi

Abbreviations
Abb.

Expanded Form

Abb.

Expanded Form

CCCW

Closed Cycle Cooling Water

MOP

Main Oil Pump

DTI

Dial Test Indicator

MOST

Mechanical Overspeed Trip

Gen End

Generator End

MOT

Main Oil Tank

Gov End

Governor End

MSDS

Material Safety Data Sheet

HP

High Pressure

OJT

On Job Training

HP-IP

High Pressure Intermediate

P&ID

Process and Instrumentation

(HIP)

Pressure

I&C

Instrumentation and Control

PPE

Personal Protective Equipment

IP

Intermediate Pressure

PTW

Permit to Work

LP

Low Pressure

MM-M05.01

Rev.001

Diagram

Main Turbine
Mitsubishi

xii

List of Vendor Manuals

MM-M05.01

Rev.001

NIL

Main Turbine
Mitsubishi

xiii

Arrangement of the System


Maintenance Manual
This manual is arranged as follows.
Chapter 1
Describes health and safety issues during maintenance, disassembly and reassembly
of the Main Turbine.

Chapter 2
Describes the construction, purpose, and function of the Main Turbine and the
associated parts.

Chapter 3
Describes the Main Turbine parts, using the relevant Data Sheets.

Chapter 4
Describes the Preventive, Routine, and Outage Maintenance.

Chapter 5
Describes the disassembly and reassembly procedures, necessary to obtain access
to internal parts for inspection and repair during Main Turbine overhaul.

Chapter 6
Describes the corrective maintenance procedures to be followed to investigate,
identify and remedy defects occurring during operation.

MM-M05.01

Rev.001

Chapter 7

Includes Torque Chart, Spare Parts, Special Tools and Vendor Drawings/Documents

Main Turbine
Mitsubishi

xiv

Chapter 1

Safety

C h a p t er

1 S af et y
1.1

Feature of Main Turbine Safety


The main turbine is the equipment that rotates at high speeds using high
pressure and high temperature steam from the boiler. The steam turbine when
in service is subject to the various pressure and temperature variations. These
variations occur due to fluctuation in generator load or due to disturbance in
boiler firing.
As the steam turbine is operated at a very high pressure and at a highly
superheated steam temperature, the components of the turbine and the
connected steam pipes have high stress during operation. The turbine is also a
large structure and unequal temperature distribution in several parts is
unavoidable. Thus the turbine components have high variable stress and risk of
flange/pipe leakages and blade failures. Leaked steam from the turbine parts
can cause extensive damage in the vicinity of the turbine, and to persons
working in the area.
As the steam leaked from such failures cannot be seen, all persons in the
turbine area must have their attention tuned to noise caused by steam leakages.
Oil lines supplying control and the lubricating oils to the main turbine are located
around the main turbine. Any oil leakage in the vicinity of the turbine could lead
to a fire which could damage the nearby components. All personnel should pay
strict attention and report any oil leakage to the Shift Charge Engineer for his
action.
The Turbine generator located adjacent to the main turbine operates with highly
combustible hydrogen gas for cooling. Any hydrogen gas leakage when
contacting any ignition source could lead to a fire and/or explosion and could
cause severe damage to the turbine-generator components and to the operating
personnel.

MM-M05.01

Rev.001

All operators and maintainers must be aware of the danger and keep
themselves safe, following the recommendations written in this manual.

Main Turbine
Mitsubishi

1-1

Chapter 1

1.2

Safety

Warnings Description
Safety of personnel working in the power plant is the most important matter and
all kinds of consideration to avoid dangerous conditions are studied and applied
to the design of the power plant. However, certain risks are unavoidable due to
the nature of the plant.
This manual classifies the severity and hazard level of such risks by two
categories, DANGER and CAUTIONS. Read and understand the
indications thoroughly before operation or maintenance of the plant.
The contents of wordings, DANGER and CAUTION are described as follows;
Kinds

Meaning of Warnings
DANGER indicates an imminently hazardous situation
during use of the Main Turbine, which, if not avoided,
could result in death or serious injury, or serious
damage to the property or environment.
CAUTION indicates a potentially hazardous situation

CAUTION

during use of the Main Turbine, which, if not avoided,


may result in minor injury, or minor damage to the
property or environment.

This manual also uses the following indicators in addition to the hazard level
indications described so far.

Kinds

Meaning of Warnings
IMPORTANT describes the particular information or
items that personnel must know during operation and

IMPORTANT

maintenance of the Main Turbine, and that, if not heeded,


may result in an accident of an in-assessable hazard
level.
NOTICE describes useful information and tips for
operation and maintenance of the Main Turbine.

MM-M05.01

Rev.001

Notice

Main Turbine
Mitsubishi

1-2

Chapter 1

Safety

1.2.1 Definitions of Serious Injury, Minor Injury,


Serious Damage to Property, and Minor Damage to
Property
Serious Injury
This term describes injuries, which leave after effects such as loss of
eye sight, permanent disability, bone fracture or breakage, gas
inhalation, asphyxiation, electric shock, hospitalization or prolonged
hospital visits for treatment.

Minor Injury
This term describes injuries, which do not require hospitalization or
prolonged attention at a hospital (injuries other than the serious
injuries described above).

Serious Damage to Property


This term describes damages, which require a suspension of
productive activity for one day or more due to restoration of the
damaged property.

Minor Damage to Property

MM-M05.01

Rev.001

This term describes damage, which does not require any suspension
of productive activity due to restoration of the damaged property.

Main Turbine
Mitsubishi

1-3

Chapter 1

Safety

1.2.2 Symbol
In this manual, the following symbols are added for easy understanding
of the contents of warnings and are found next to DANGER,
CAUTION and indications.
These symbols are in compliance with ISO 3684.

Symbol

Description
This symbol indicates the possible presence of high voltage, and
warns of a hazard which may result in system shock, burn or
death by electric shock if safety precautions are neglected or the
system is handled incorrectly.
This symbol indicates a movable section that is inside a safety
cover or is exposed.
Movable parts may inflict laceration or bone fracture to body parts
such as a hand by pinching the hand and/or clothing.
This symbol indicates the presence of parts the surface of which
could be hot, and may cause a burn if handled incorrectly.
This symbol indicates that care should be taken where you place
your feet when moving around the area.
Risk of injury by tripping is present near this symbol due to
factors such as a location with an unstable surface, or
obstructions such as scaffolding, temporary pipe lines, or other
protrusions.
This symbol indicates the possible presence of gas(es) harmful or
asphyxiant to personnel.
Be sure to ventilate fully before work commences.
This symbol indicates caution against the handling of a heavy
object or working in an abnormal position.
Do not work in an abnormal posture which may damage your back
or waist.
This symbol indicates prohibited items or actions during the

MM-M05.01

Rev.001

operation and maintenance of the Main Turbine.

Main Turbine
Mitsubishi

1-4

Chapter 1

1.2.2

Safety

Symbols (Continued )

Symbol

Description
This symbol indicates that personnel must not touch since the
surface is hot.
Do NOT enter any area where this symbol is displayed.

This symbol indicates that the entry of personnel is prohibited.


Do NOT enter any area where this symbol is displayed.

This symbol indicates that physical contact is prohibited.


Do NOT touch or enter a location or enclosure where this symbol
is displayed.
This symbol indicates that the stated items or actions in the
warning notices relative to operation and maintenance of the Main
Turbine are mandatory.
This symbol indicates a movable section that is inside a safety
cover or exposed.
Do NOT touch any equipment where this symbol is displayed.

1.2.3 Hazard Warning Label


Hazard warning labels are applied where potential hazards are present
during operation and maintenance activities.
Hazard warning labels will be in appropriate sizes and colors that will
catch the eye and the attention of personnel. They also have symbols
that show the hazard types, in addition to the descriptions of warning
contents.

IMPORTANT
Personnel are requested to confirm the location of, and to read, and
thoroughly understand the contents of all hazard warning labels
applied to the Main Turbine. If any of the hazard warning labels peel
Rev.001

off/wear out or become unreadable, install a new label in the original

MM-M05.01

location without delay.

Main Turbine
Mitsubishi

1-5

Chapter 1

WARNING

Safety

DO NOT COME
NEAR TO SHAFT
EXPOSED ZONE
WHEN IN
OPERATION

PINCH POINT

STEEP
DROP

DO NOT
ENTER

DO NOT
TOUCH

DO NOT
TOUCH

MM-M05.01

Rev.001

TB0001_A

FIGURE 1-1
Main Turbine
Mitsubishi

TYPES OF HAZARD WARNING LABEL

1-6

Chapter 1

Safety

1.2.4 Hazard Area

IMPORTANT
Only trained maintainers and operators are allowed to enter the
maintenance work area. Entry to the area by personnel untrained
could cause not only injury but also serious damage to the Main

MM-M05.01

Rev.001

Turbine.

Main Turbine
Mitsubishi

1-7

Chapter 1

1.3

Safety

Risk Assessment Standard


As prepared by the Design Section as per MIL STD822D.
TABLE 1-1

RISK ASSESSMENT STANDARD


Detailed Description of Impact on each Object

Category

Safety

Catastrophic

- Unit shutdown (unit cannot be


operated)
- More than 4 days for repairing

- Death

II

Critical

- Unit shutdown (can not be operated)


- Within 3 days for repairing

- Serious Injury

- Same as the above

III

Marginal

- Unit shutdown (can not be operated)


- Can be repaired by Customer

- Minor Injury
(with
hospitalization)

VI

Negligible

- Same as the above


- High temperature surface
- High elevation or unstable
- Not harmful and high
pressure & temperature
leakage
-Mechanical protected

- Minor Injury
(without
hospitalization)

RISK ASSESSMENT STANDARD (CONTINUED)

Definition

Description

Category

Detailed

(A)

Frequent

Repeating occurrence

1 time / 1 or 2 months

(B)

Probable

Known to occur, or, it has happened

1 time / 1 year

(C)

Occasional

Could occur

1 time / 5 years

(D)

Remote

Not likely to occur

1 time / 10 years

(E)

Improbable

Practically Impossible

1 or 2 times / total life

TABLE 1-1
Hazard
Categories
Frequency
of Occurrence

Rev.001

Environment
- Harmful gas or oil leakage
- High pressure and
temperature material leakage
such as steam, water, air and
gas, oil etc.
- Low oxygen

TABLE 1-1

MM-M05.01

Health

RISK ASSESSMENT STANDARD (CONTINUED)


I

II

III

VI

Catastrophic

Critical

Marginal

Negligible

(A)

Frequent

13

(B)

Probable

16

(C)

Occasional

11

18

(D)

Remote

10

14

19

(E)

Improbable

12

15

17

20

Main Turbine
Mitsubishi

1-8

Chapter 1

10
5
3
2

10
5
3
2

10
5
3
2

10
5
3
2

7
4
3

4
3 9
2 8
1 7

7
4
3

Safety

7
4
3
7
4
3

4
3

STAIR WAY

2
3
5
10

3
7
8

3
4
7

STAIR WAY

2
3
5
10

2
3
5
10

2
3
5
10

3
4
7

3
4
7

1 7
2 8
3 9
4

3
4
7
NOTES
WARNING LABELS SHOUD BE IN ARABIC.

GEN. SIDE

MM-M05.01

Rev.001

YELLOW

AVOID INJURY
WATCH YOUR STEP

MPTD-3-0314

YELLOW

FALL
WATCH YOUR STEP

YELLOW

RISK OF A ROTATING
A HAND

YELLOW

RISK OF A GEAR
PINCHING A HAND

GOV. SIDE

(*1)

YELLOW

RISK OF A CHAIN
PINCHING A HAND

YELLOW

PINCH POINT
KEEP HANDS AWAY

YELLOW

YELLOW

DO NOT TOUCH
HOT SURFACE

YELLOW

YELLOW

DISCONNECT
AUTOMATIC START.
ELECTRICAL POWER
KEEP HANDS CLEAR.
BEFORE SERVICING

RED

DO NOT SMOKE
IN THIS AREA.

10

RED

OPERATING PERIOD

(*1) THE MOST SUITABLE ONE WILL BE ADOPTED TO EACH PLACE.

FIGURE 1-2
Main Turbine
Mitsubishi

YELLOW

MAPPING FOR HAZARDOUS AREA

1-9

Chapter 1

1.4

Safety

Safety Measures
1.4.1 Work Permit System (Lockout/ Tagout)
Work permit system is applied when equipment is shutdown for
maintenance work, to complete the maintenance work under a safe
condition. The outline of the work permit system is as follows:

(2)

The Shift Charge Engineer passes the work permit form to the
operator to study and decide the isolation method from the line in
operation on the mechanical and electrical view point and then
report to the Shift Charge Engineer with the comments on the
hazard conditions for the work.

(3)

The Shift Charge Engineer gives work permit number and


prepares necessary tags to show the work permit number and
the situation of isolation by valves and power supply. He will then
instruct the operators to set the isolation condition following the
work permit form.

(4)

The operators will open the breaker and set the valves to the
specified condition, they will also drain and vent the equipment to
be worked on, and the breaker and the valves are to be locked.
The operators return the work permit to the Shift Charge
Engineer.

(5)

The Shift Charge Engineer checks the isolation and will issue the
signed work permit to the Maintenance Engineer, or his
representative.

(6)

The Maintenance Engineer orders the start of the maintenance


work to the personnel nominated.

(7)

The Maintenance Engineer or his representative will then return


the signed work permit to the Shift Charge Engineer after making
sure the maintenance work is completed.

(8)

The Shift Charge Engineer will then send operators to release the
locks and return to the original situation.

(9)

The operators check the situation and report that the system is
now back to the normal condition when signing off the work
permit.

Rev.001

The Maintenance Engineer applies for the work permit clearly


indicating the content of the maintenance work that he wants to
do, and submits it to the Shift Charge Engineer.

(10) The Shift Charge Engineer makes sure that the work under the
permit is completed and files details in the log book.

MM-M05.01

(1)

The work permit system is to clarify responsibility for the works on each
step and to ensure that the work is performed safely.
Main Turbine
Mitsubishi

1-10

Chapter 1

Safety

1.4.2 General Cautions on Personnel in Working Area


1.4.2.1

Cautions against Rotating Equipment


All couplings on rotating machines are covered by the
coupling cover but whole parts of the shaft are not fully
covered. It is recommended that the following warning is
observed strictly.

Do not approach or operate the equipment where


protective covers have been removed. Get additional
supervisor assistance.

Make sure that the breaker for the motor is opened when
you are required to remove the cover.

Care must be taken of the exposed rotating parts,


especially in the area between the casing and the coupling

All shafting, coupling and other rotating parts must be


guarded in order to prevent accidental contact.

1.4.2.2

Cautions against Electrical Equipment

MM-M05.01

Rev.001

The electrical equipment covered under this section


includes all the concerned plant equipment and the
maintenance tools like grinders, lamps, welding equipment
etc. Though live parts of the plant or maintenance tools
are insulated, be sure to observe the following cautions.
Failure to observe them may cause fatal accidents,
personal injuries and damage to the electrical equipment.

Main Turbine
Mitsubishi

Always, confirm that power supply is disconnected at the


up-stream side of power supply system and it is locked
according to the Work Permit.

Do not remove or open panels or doors labeled with high


voltage live part warning label not included in the Work
Permit.

Ensure the proper earthing is provided for all electrically


operated tools and equipment used for maintenance works.

In case of usage of lamps for internal inspection, ensure


that a low voltage system (24volts) is available.

Make sure that no materials or Parts remain in the Panels or


terminal box before closing them finally.

1-11

Chapter 1

1.4.2.3

Safety

Cautions against High Temperature Sections


Various equipment and pipelines contain high temperature
fluid and they are insulated on their surface. There are
however some pipe lines which are not insulated, and as
their temperature is very high and you could get burned,
please observe the following caution to avoid burn injury.

CAUTION
Suitable Personal Protective clothing is always available
and should always be worn, including gloves to avoid
direct contact to hot spots in the plant.

Level gauges of pressure vessels including connecting


pipes are not insulated to cool down the steam to drain.

Sampling piping is not insulated to cool down the steam to


a suitable temperature for the analyzer except at the places
located close to the work place.

All exhaust pipes of the safety valves and the exhaust pipe
of the boiler flush pipe are not insulated.

Always wear gloves.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

1-12

Chapter 1

1.4.2.4

Safety

Cautions for Steam Leak in the Plant


The steam leak especially from high temperature steam
may cause serious injury to the personnel and it must be
repaired at an early stage of the leakage. The following
pre-cautions must be followed to find leakage at an early
stage.

Water drips may occur at the insulated parts such as the


connected part of the lagging. The leaking point can be found
by removing insulation partially using great care.

As you approach the leakage the water will change to visible


steam. It is now too dangerous to remove the insulation.

Leakage of the superheated steam only makes whistling


noise without generating white steam. It is very dangerous to
approach the noise area.

Contact the Charge Engineer to obtain a Permit to Work to


ensure plant isolation before repairing the damage.

Be well aware of the steam. The steam could leak from the
water system containing water at 100C or higher even if it is
a low pressure type water system.

High temperature drain or steam could leak from the flush


pipe during start-up.

If not avoided, the steam or vapor can enter the inside of your
working wear through the small gap between the body and
the clothing.

1.4.2.5 Caution against Oil Leak in the Plant

MM-M05.01

Rev.001

CAUTION

Main Turbine
Mitsubishi

Oil leakage is very dangerous. It is a potential fire hazard.

Any oil spillage must be reported to the Shift Charge


Engineer.

Oil leaks make the area slippery and people are advised to
move around these areas carefully.

1-13

Chapter 1

1.4.2.6

Safety

Cautions against Chemicals


Pay attention to the items listed below to prevent any
accident related to the chemicals in the plant.

IMPORTANT
Precaution against chemicals:

Operate chemical injection systems by strictly following the


instruction of the chemist. The operator must use suitable
protective tools.

Disposal:

Observe the rules and regulation of the installation site.

Material Safety Data Sheet (hereafter MSDS):

Always understand the content of the applicable MSDS


before using, and observe the notified instructions when
handling the chemical.

Emergency response:

Solution against emergency must be thoroughly instructed


to all personnel involved so that the fullest measures can be
taken against any situation.

1.4.2.7

Cautions against Combustible Materials/


Storage Areas

IMPORTANT
Storage containers must be clearly marked to indicate the
content.

Bunding must be provided for bulk tanks.

Suitable fire protection must be provided for each area.

Do not store bulk combustible materials on the site.

Small quantities of combustible materials must be stored in


fire resistant cupboards.

Combustible materials must be segregated from other


equipment.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

1-14

Chapter 1

1.4.2.7

Safety

Cautions against Combustible Materials /


Storage Areas (Continued)

IMPORTANT

Leakage of gasoline has the risk of fire. Maximum storage


quantity of gasoline outside of the dispensing pump is five
liters.

Emergency response:

Personnel directly involved in combustible materials MUST


be properly trained and thoroughly instructed. Other
personnel in the vicinity must be aware of the dangers and
take precautions in all situations.

1.4.2.8

Cautions against Lack of Oxygen

Check that the oxygen content in the equipment vessel or in


the confined space is between 18~22% before entering, and
ensure sufficient ventilation.

Continue monitoring oxygen and ventilation during


inspection.

It is recommended that you do not enter the equipment,


vessel or confined space alone but if the situation demands
that you must enter, take the necessary preventive safety
measure provided, breathing system etc, and find a partner
who will wait for your return at the point of entry, keeping in
verbal contact throughout.

Make complete arrangements for rescue.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

1-15

Chapter 1

1.4.2.9

Safety

Cautions against Lifting Heavy Object


Be careful during the removal/installation of any
equipment during maintenance.

CAUTION

Do NOT attempt to move or lift equipment in an abnormal


posture. ALWAYS install/remove equipment, using a forklift
or a crane. A normal lift without mechanical aid should be
shared between two or more persons.

Failure to observe the above may cause injury due to


dropped equipment, back or waist injury or damage to the
equipment.

1.4.2.10 Cautions against Sharp Objects

CAUTION

Use leather gloves when handling parts with sharp edges.

1.4.2.11 Cautions using Fork Lift

MM-M05.01

Rev.001

CAUTION

Main Turbine
Mitsubishi

Do NOT permit anyone to stand below any item being lifted


under any circumstance.

Failure to observe this may cause fatal accidents.

When using a forklift, ALWAYS lift the objects parallel to


the ground while considering the center of gravity.

Otherwise, lifted objects may fall and serious damage


could occur.

A forklift is often used to transfer small machines. Check


fork insertion position for the forklift prior to use. Be
careful, as marks which indicate the fork insertion
positions are sometimes hidden by wraps or packing
materials.

1-16

Chapter 1

Safety

1.4.2.12 Cautions using Crane

CAUTION

A crane is often used to transfer heavy parts. Check for any


possible risks which could occur during hoisting and
transportation before operating the crane.

Check of the equipment:

Check the crane, the crane hook and all related items
before use. Use wire ropes which can withstand the weight
of the parts multiplied by a safety factor.

Inspect the shackles, eyebolts, jigs and wire ropes


provided for the hoisting work prior to the actual hoisting.

Perform periodical inspection (dye penetrant test) of


hoisting tools at least once a year.

Rigging / Slinging work:

Only authorized personnel can perform slinging work and


operation of the crane.

Work area:

Before hoisting, secure a working area around the part to


be lifted and prohibit the entry of unrelated personnel.

Hoisting method:

Hoist the part parallel to the ground while paying attention


to the center of gravity.

Do NOT permit any person to stand under the part being


lifted.

Pay attention to and ensure that all persons are clear of the
equipment being lifted.

Hoisting point:

Do NOT hoist any parts from a position other than the


specified hoisting points.

Unpacking:

Rev.001

Do NOT unpack any part until it is located in the


designated location.

Protection of machine:
Avoid any impact to the unpacked parts.

MM-M05.01

Main Turbine
Mitsubishi

1-17

Chapter 1

Safety

1.4.2.13 Disposal
a)

Water disposal including oily drain


The water is disposed to the plant drain system. The water must
be carefully disposed according to materials contained in the
water. The water drain system is separated into three categories
that are rain water, chemical water and oily water.
The waste waters are treated and then discharged to the public
drain system.

b)

Chemical disposal
Chemicals must be handled following the instruction of the MSDS
and disposed to the chemical drain system.

c)

Solid disposal made by maintenance work.

MM-M05.01

Rev.001

For disposal from the site, observe the local legal regulations.

Main Turbine
Mitsubishi

1-18

Chapter 1

1.5

Safety

Emergency Measure
1.5.1 Evacuation on Emergency Case
1.5.1.1

Evacuation Route
Following items are considered on design and installation
of emergency evacuation.

IMPORTANT

Each building installed in the plant is provided with at least two


exits. A clear indication of the exits can be seen from anywhere
in the building as the exit sign is illuminated using the
emergency power supply.

Evacuation routes are indicated on each floor of the building,


directing personnel to the exits.

Keep the evacuation routes completely free from materials and


tools.

1.5.1.2

Evacuation of Disabled Persons Who Cannot


Move by Themselves
The following are necessary items, prepared for emergency
evacuation:

IMPORTANT
It is recommended to keep a stretcher available for
emergencies at the places selected as being secure at the
safety meeting.

If you find this kind of accident, inform the rescue team, and
attempt to bring the collapsed person to the first aid station.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

1-19

Chapter 1

1.5.1.3

Safety

Evacuation from Power House


Following are guidance for the evacuation from the power
house.

IMPORTANT

An evacuation place for personnel to gather in after


evacuation from the power house in an emergency must be
predetermined and explained beforehand in the emergency
training.

Evacuation directive must be given by the responsible


person such as Shift Charge Engineer, and all personnel
must be alerted in the power house repeatedly with an
available broadcast facility.

All people working in the power house must stop their work
immediately and leave the power house to the gathering
place.

When evacuated to the evacuation place, make sure


that there is no one missing.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

1-20

Chapter 1

Safety

1.5.2 Fire Accident

IMPORTANT
Clearly show the location of fire alarm push button and fire
extinguisher to make everybody take the first step at fire
protection.

Inform everyone concerned that a fire has now started if


you discover a fire.

Start fire fighting using the fire extinguisher located near


the fire site.

The operators must check the plant is ready for trip, and
wait for order from the responsible person.

The operator and other personnel must transfer the fire


fighting to the fire fighting team when they arrive at the fire
site and the operators must wait for instruction from the
Shift Charge Engineer. All other personnel must
immediately start evacuation.

If unit trip is decided, the operator must trip the plant


manually.

The operators must evacuate from the power house


according to the instruction of the responsible person
immediately after shutdown of the unit.

If the fire is extinguished successfully, the operators


should return to the power house as required by the Shift
Charge Engineer and start inspection of the equipment for
restart of the unit.

Based on the inspection, the responsible person should


decide whether to operate the unit again or shutdown for
repairing.

After the inspection or repair, and then checking the


equipment and/or system, start up the unit again.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

1-21

Chapter 1

Safety

1.5.3 Earthquake
In the case of an earthquake, the shift charge engineer or operator
must judge whether the unit trip is necessary according to the intensity
of the earthquake, and immediately trip the unit manually. If the unit is
tripped, all equipment must be carefully checked on its operation status
and tripped if abnormal phenomena are found.
In the local area, mechanical and/or thermal shocks may be given to
the equipment, piping, instruments and electrical panels. Be sure to
observe the following when completing the inspection.

Check that the lubricating oil pump is running. Bearings of


the equipment will be damaged if lubricating oil is not
supplied.

Check the piping and equipment for steam and water


leakage. The steam or high temperature water leakage may
cause serious injury to the personnel and it must be
repaired at an early stage of the leakage.

Check the pulverizers and/or coal silos for signs of a fire. If


a coal fire does start, make sure that the CO 2 fire fighting
system is properly operated.

Check the position of the boiler seismic stopper. Since the


boiler seismic stopper must be anchored at the original
position, the boiler cannot be re-started if the slippage is
found. If the stopper is not at the original position, please
contact MHI.

CAUTION

Check the piping and equipment for the breaking and the
dropping of insulation. Since the exposure of the hot
surface may cause burn injury, it must be repaired by a
worker fully dressed in Personal Protective Equipment.

1.5.4 Explosion Accident

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

Do not use a fire in a hazardous area where the combustibles


(hydrogen gas, oxygen gas, coal, fuel oil, etc.) are stored or
handled. Use of a fire in a hazardous area could cause
serious injury to personnel and serious damage to
equipment due to an explosion.

1-22

Chapter 1

1.6

Safety

Qualification and Training


The system must be operated only by authorized operators & maintenance
supervisors.
The customer shall authorize all operators and maintainers, who are involved in
the operation and maintenance of this plant, either by the training course given
by Mitsubishi, or by customers own personnel assessment.
Operator and maintainer training course (both classroom training and On the
Job Training (OJT)) will be provided by Mitsubishi before the handing over of
this plant. The customer must train and assess new operators and maintainers
who join after the turn-over according to his own procedure and standard,
(Mitsubishi training course may still be available if required).
As a minimum, operator and maintainer must satisfy the following:
Operator and Maintainer can read and fully understand the description of
this manual.

Operator and Maintainer can understand the related P & ID, logic diagram.

Operator and Maintainer know the location of the system equipment


including pipe routes, valves and the various instruments.

Operator and Maintainer have fundamental knowledge of the function of


each equipment.

Operator can operate the equipment and the system manually at local
stations.

Operator can operate the system remotely using DCS system.

Operator can respond suitably for any kind of alarm.

Operator knows location of emergency exit on power house and is available


to provide first aid treatment.

Operator knows emergency communication system operation.

Operator and Maintainer, following the Charge Engineers instruction are


aware of the isolation method for mechanical, electrical and instrumental
equipment being prepared for safe maintenance while the unit is in
operation.

Maintainer must also be able to handle the maintenance tools provided by


the owner and those supplied by the manufacturer.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

1-23

Chapter-2

General

C h a p t er

2 General
2.1

Purpose
The purpose of this maintenance manual is to provide specific information to the
Paiton Expansion Project maintenance personnel regarding the maintenance of
the main turbine. Although this document will convey a good knowledge and
direction regarding maintenance of the main turbine, it is recommended that in
the event of a problem not covered in the document the person responsible
should seek assistance or instruction from the turbine manufacturer.

MM-M05.01

Rev.001

2.2

References
a)

Steam Turbine Sectional Assembly


MHI Dwg No : T3059AAAA001
Project Dwg No: P101-50-3-TB-TGO003.

b)

Turbine and Generator Outline


MHI Dwg No: T3059AAAA003-1
Customer Dwg No: P101-50-3-TB-TGO001.

c)

Turbine and Generator Outline


MHI Dwg No: T3059AAAA003-2
Customer Dwg No: P101-50-3-TB-TGO002.

d)

Control and Lubrication Oil System Diagram


MHI Dwg No: T3059AAAA210-1
Project Dwg No: P101-51-3-TB-LTO001.

e)

Control and Lubrication Oil System Diagram


MHI Dwg No: T3059AAAA210-2
Project Dwg No: P101-51-3-TB-LTO002.

f)

Control and Lubrication Oil System Diagram


MHI Dwg No: T3059AAAA210-3
Project Dwg No: P101-51-3-TB-LTO003.

g)

Gland Steam and Drain Piping Diagram (1/4)


MHI Dwg No: T3059AAAA210-2
Project Dwg No: P101-51-3-TB-TLO001.

h)

Gland Steam and Drain Piping Diagram (2/4)


MHI Dwg No: T3059AAAA230-2
Project Dwg No: P101-51-3-TB-TLO002.

Main Turbine
Mitsubishi

2-1

Chapter-2

2.3

i)

Gland Steam and Drain Piping Diagram (3/4)


MHI Dwg No: T3059AAAA210-3
Project Dwg No: P101-51-3-TB-TLO003.

j)

Gland Steam and Drain Piping Diagram (4/4)


MHI Dwg No: T3059AAAA210-4
Project Dwg No: P101-51-3-TB-TLO004.

General

Overview of the Main Turbine


Refer to Figures 2-1 to 2-4.
The functions of the main turbine are to accomplish the conversion of thermal
energy contained in the driving steam to the mechanical energy required to drive
the generator and to provide extraction steam to the regenerative feed water
heaters and the deaerator.
The main turbine receives superheated steam at 24.5 MPa(a) and 538C and
reheated steam at 4.7 MPa(a) and 566C from the boiler, rotates clockwise
(when viewed from governor end) at a speed of 3000 rpm and generates 815
MW of electricity through a generator coupled to the turbine rotor.
The turbine-generator unit is installed on concrete foundations at FL+13000 in
the turbine building.
The unit is a three-cylinder tandem compound, quadruple exhaust, condensing
reheat turbine, designed for high operating efficiency and maximum reliability.
Figure 2-2 shows the isometric view of the turbine unit and Figure 2-3 shows the
longitudinal section through the vertical centerline of the HP-IP combined
element (HP-IP) turbine (ie. the high pressure and the intermediate pressure
turbines are arranged in one cylinder), and the No.1 and No.2 low pressure (LP)
turbines. Figure 2-4 shows the turbine and the generator outline. (It may be
noted that the LP1 and LP2 turbines are designated as LP-3A and LP-3B
turbines respectively).

MM-M05.01

Rev.001

The HP turbine has a combination of impulse (Rateau) and reaction type blading.
The main steam enters the HP turbine through two steam chests each of which
includes one main stop valve (MSV) and two governing valves (GV), and are
located, one on each side of the HP turbine. The GV outlets are connected to the
HP element of the HP-IP casing through four inlet pipes, each connected to the
steam chest of the No.1 dummy ring by a slip joint. Two of these inlet steam
pipes are connected to the upper casing and the other two to the lower casing.
As the steam passes through the HP turbine blading towards the exhaust
openings through which the steam is directed to the reheater, steam is extracted
from the intermediate stage to No.8 HP feed water heater and from the HP
turbine exhaust (cold reheat) line to No.7 HP feed water heater.

Main Turbine
Mitsubishi

2-2

Chapter-2

General

In the reheater the HP turbine exhaust steam temperature is increased and the
reheated steam is returned to the IP element of the HP-IP turbine at 566C
through two sets of RSV/ICV assemblies, each set consisting of one reheat stop
valve (RSV) and two interceptor valve (ICV). These assemblies are installed in
front of the HP pedestal, one set on each side of the turbine casing. Two of the
four ICV outlets are connected to the IP element of the HP-IP upper casing and
two to the lower casing. As the steam passes through the IP turbine blading,
towards the exhaust opening in the outer casing cover, steam is extracted from
an intermediate stage and directed into the No.6 HP feed water heater for
heating the feed water. Steam from the exhaust of the IP turbine is extracted and
directed to the deaerator to heat and remove air and non-condensable gases
from the feed water.
The IP turbine exhaust opening is connected through a crossover pipe to an inlet
opening in each of the LP turbines to supply drive steam for the LP turbines. Cold
spring of 50 mm is provided on the cross-over pipe between the IP and LP1
turbines and 70 mm between LP1 and LP2 turbines. Two expansion joints
installed on the crossover pipe together with the cold spring jointly accommodate
the thermal expansion. The LP turbines are of the double flow type with steam
entering at the center of the blade path and flowing toward an exhaust opening at
each end. Thence the steam flows downward into the main condenser. The LP
turbine blading is of the reaction type with 35.4-inch (900 mm) last row blades.
Openings are provided in the lower half LP1 and LP2 casings through which
steam is extracted to the four low pressure feed water heaters.

MM-M05.01

Rev.001

Steam exhausts from both ends of each LP turbine at a near total vacuum and at
a relatively low temperature. It exhausts directly into the main condenser, where
it is condensed and the condensate is collected in the condenser hot well.

Main Turbine
Mitsubishi

2-3

Chapter 2

General

S A FE TY VA LV E
S IL E N C E R

T O S A M P L IN G R A C K
(H T R )

M A IN S T E A M P IP E 3 A
S IL E N C E R
(S L 3 B )

ESCAPE
P IP E

M A IN S T E A M P IP E 3 B
PS

3R Y SH
OUTLET HEADER

PS

PS

T O T /B V A L V E
W A R M IN G

T O H P T U R B IN E
B Y -P A S S V A L V E

M
ZT

3RY SH
IN L E T H E A D E R

S IL E N C E R
(S L 3 A )

3RY
SUPERHEATER

3R Y
SUPERHEATER

3RY SH
O UTLET HEADER

M
ZT

3RY SH
IN L E T H E A D E R

S IL E N C E R
(S L 3 B )

T O S A M P L IN G R A C K

E S C A P E P IP E
TO CONDENSER

T O T U R B IN E F L A S H P IP E

H O T R E H E A T P IP E 3 A

E S C A P E P IP E

H O T R E H E A T P IP E 3 B

2RY RH
O UTLET HEADER
2RY RH
IN L E T H E A D E R

E S C A P E P IP E

ESCAPE
P IP E

GV
2RY
2RY
REHEATER REHEATER

1RY
1RY
REHEATER REHEATER

RSV 3B

R S V 3A

GV

IC V

IC V

T O T U R B IN E
F L A S H P IP E

H P /IP T U R B IN E
TO CONDENSER

1RY RH
O UTLET H EADER

2R Y RH
IN L E T H E A D E R

C O L D R E H E A T P IP E

TO HP NO. 7
FEED W ATER H EATER

LS

LS

Rev.001

TO S O O T B LO W ER
T O A U X IL IA R Y
STEAM SYSTEM

T O B O IL E R F L A S H P IP E

MM-M05.01

M SV 3A

2RY RH
O UTLET HEADER
ESCAPE ESCAPE ESCAPE
P IP E
P IP E
P IP E
2R Y RH
IN L E T H E A D E R

E S C A P E P IP E

1R Y RH
O UTLET HEADER
1RY RH
IN L E T H E A D E R

M SV 3B

F R O M N IT R O G E N G A S S E A L S Y S T E M

TO CONDENSER

T O T U R B IN E F L A S H P IP E

M P T D -3 -0 2 0 0

FIGURE 2-1
Main Turbine
Mitsubishi

MAIN STEAM AND REHEAT FLOW DIAGRAM

2-4

Chapter 2

General

MM-M05.01

Rev.001

IP TURBINE EXHAUST

HP-IP TURBINE EXHAUST

MPTD-3-0201

FIGURE 2-2
Main Turbine
Mitsubishi

ISOMETRIC VIEW OF MAIN TURBINE

2-5

Chapter 2

GEN. SIDE

General

VIBRATION PICK UP

VIBRATION PICK UP

C
L OF MAIN OIL PUMP

C
L OF THRUST BRG.

C
L OF NO.1 BRG.

PHASE DETECTOR
PICK UP

PEDESTAL

VIBRATION PICK UP

DIFFERENTIAL
EXPANSION PICK UP
NO.6 BEARING
PEDESTAL
ROTOR GROUNDING
DEVICE

C
L OF MAIN STEAM INLET

VIBRATION
PICK UP

C
L OF REHEAT STEAM INLET

VIBRATION
PICK UP

C
L OF IP EXHAUST

C
L

C
L OF NO.2 BRG.

OF NO.3 BRG.

C
L OF LP1 TURBINE

C
L OF NO.4 BRG.

C
L OF NO.5 BRG.

C
L OF NO.6 BRG.

C
L OF LP2 TURBINE

GOV. SIDE

DIFFERENTIAL

VIBRATION
PICK UP

NOS.4&5 BEARING
PEDESTAL

HP PEDESTAL
ZERO SPEED
& SPEED PICK UP
ECCENTRICITY
PICK UP
ROTOR POSITION
PICK UP
ROTATION

OPERATING FLOOR

NO.3 EXTRACTION

NO.2 EXTRACTION
NO.3 EXTRACTION

NO.1 EXTRACTION
NO.2 EXTRACTION
NO.4 EXTRACTION

NO.1 EXTRACTION
NO.2 EXTRACTION
NO.4 EXTRACTION

GLAND STEAM INLET


GLAND STEAM OUTET

NO.2 EXTRACTION

NO.1 EXTRACTION

GLAND STEAM INLET


GLAND STEAM OUTET

NO.1 EXTRACTION

GLAND STEAM INLET


GLAND STEAM OUTET

GLAND STEAM INLET


GLAND STEAM OUTET

NO.7 EXTRACTION
NO.8 EXTRACTION
MAIN STEAM INLET
NO.5 EXTRACTION

REHEAT STEAM INLET


NO.6 EXTRACTION

MM-M05.01

Rev.001

MPTD-3-0202

FIGURE 2-3
Main Turbine
Mitsubishi

SECTIONAL VIEW OF MAIN TURBINE

2-6

Chapter 2

General

ICV
LP2 TURBINE

LP1 TURBINE
MSV/GV ASSEMBLY
RSV

EXCITER

GENERATOR
C
L

OF RSV&ICV

HP PEDESTAL

C
L

MS. INLET
C
L ON CYLINDER

C
L

RSV

No.1 BRG.

ICV

C
L

No.7 BRG.
C
L

GENERATOR
C
L

C
L

No.8 BRG.

ICV

EXCITER

OF RSV&ICV

GOV. SIDE

C
L

MSV
C
L

No.2 BRG.
C
L

No.3 BRG.
C
L

LP-1 TURBINE
C
L& CONDENSER

No.4 BRG.
C
L

No.5 BRG.
C
L

C
L

GEN. SIDE

LP-2 TURBINE
C
L& CONDENSER

No.6 BRG.

C
L

HP PEDESTAL

RSV

ROTATION

OPERATING FLOOR

HP PEDESTAL

NO.7 EXTRACTION
NO.1 EXTRACTION
NO.2 EXTRACTION

Rev.001

NO.3 EXTRACTION

NO.1 EXTRACTION
NO.2 EXTRACTION
NO.3 EXTRACTION

NO.1 EXTRACTION
NO.2 EXTRACTION
NO.4 EXTRACTION

NO.8 EXTRACTION

NO.1 EXTRACTION
NO.2 EXTRACTION

MAIN STEAM INLET

NO.4 EXTRACTION

REHEAT STEAM INLET

NO.5 EXTRACTION
NO.6 EXTRACTION

MM-M05.01

MAIN STEAM INLET PIPE


HOT REHEAT STEAM INLET PIPE
MPTD-3-0203

FIGURE 2-4
Main Turbine
Mitsubishi

TURBINE AND GENERATOR OUTLINE


2-7

Chapter-2

2.4

General

Components
The complete turbine is described as a tandem compound, 3-cylinder, quadruple
exhaust, extracting, condensing, reheat turbine. The three cylinders contain a
HP-lP combined element and two LP turbines viz. LP1 and LP2. The above three
cylinders combined form the main turbine unit. The combined HP-IP, LP1 and
LP2 turbine rotor shafts connect all turbine sections, and these connect to the
generator shaft to provide a compound rotor. All turbine rotor shafts are
connected by bolted flanged solid couplings. When the turbine operates, the
compound rotor rotates simultaneously within the three turbine cylinders and the
generator.
The entire turbine unit is mounted on a concrete foundation. The complete
rotating element of the turbine is supported by six journal bearings, one at each
end of the three rotors. The journal bearings are mounted in individual pedestals
located at the ends of each turbine. The bearing pedestals rest on metal base
plates on the concrete foundation. The base plates allow the bearing pedestals
and cylinders to slide axially along the length of the rotor to permit thermal
expansion during turbine operation. Differential expansion pick-ups are located
between the HP Turbine and the LP1 Turbine and at the rear of the LP2 turbine
to monitor relative thermal expansion between turbine cylinder sections and the
rotor during operation. A thrust bearing installed within the HP pedestal between
No.1 bearing and the shaft driven main oil pump (MOP) locates the turbine rotor
axially and absorbs the axial thrust. All turbine bearings receive oil for lubrication
and cooling from the main turbine lubricating oil system.

MM-M05.01

Rev.001

The main components of the turbine are:

turbine casings

rotors

blading

rotor seals

gland seals

bearings

rotor couplings

steam admission valves

turning gear

rotor grounding device

breakable diaphragm

turbine enclosure.

Main Turbine
Mitsubishi

2-8

Chapter-2

General

2.4.1 Turbine Casings


The structural shape of the turbine casings and their method of support
are carefully designed to obtain free and symmetrical movement
resulting from thermal changes and thereby reduce the possibility of
distortion to a minimum.

HP-IP Casing
Refer to Figures 2-5 and 2-6.
The HP-IP turbine consists of an outer casing which accommodates the
HP-IP turbine parts viz. turbine rotor, inner casing, IP blade ring, No.1
and No.2 dummy rings, HP and IP stationary blade rings, turbine
blading, etc.
The outer casing of the combined HP-IP turbine is an alloy steel casting
split in the horizontal center plane to form a base (1) and a cover (2).
The inner casing (3) is also made of alloy steel casting split in the center
plane to form a base and cover. The inner casing is supported in the
outer casing at the horizontal joint and located by dowels (24) and
matching tongue and groove fits so as to maintain the correct position
with regard to the turbine axis while allowing the components to expand
and contract freely in response to temperature changes.
The No.1 dummy ring (5) is supported within the inner casing (3) at the
horizontal joint. At the HP turbine end of the No.1 dummy ring, a nozzle
block (25) is installed which contains several nozzles (26) arranged in a
circle. These nozzles are arranged such that they direct the incoming
main steam to the Rateau stage blades at high velocity. At the IP turbine
end of the No.1 dummy ring, it is provided with an extension ring which
contains sealing rings with seal strips to minimize leakage of steam from
the Rateau stage inlet to the IP turbine inlet. The No.1 dummy ring also
carries the 1st ~ 3rd stage HP stationary blade diaphragms.
The four main steam inlets are connected to the No.1 dummy ring (5)
through nozzles cast integral with the HP end of the HP-IP outer casing
(1, 2) on either side (RS and LS) of the turbine axis. Likewise, the four
reheat steam inlets are connected to nozzles cast integral with the IP
end of the HP-IP outer casing (1, 2), two on the cover and two on the
base.

MM-M05.01

Rev.001

The No.1 and No.2 HP stationary blade rings (6, 7), which carry the 4th ~
9th stage stationary blade diaphragms of the HP turbine, are supported
in the inner casing (3) at the horizontal joint. The HP stationary blade
rings are located axially in the inner casing (3) by matching tongue and
groove fits and supported at the horizontal by liners and support keys.

Main Turbine
Mitsubishi

2-9

Chapter-2

General

The No.1 ~ No.4 IP stationary blade rings (8, 9, 10 and 11), which
together carry the entire stationary blade diaphragms of the IP turbine,
are supported in the IP blade ring (4) at the horizontal joint. The four IP
stationary blade rings are located in the IP blade ring (4) by matching
tongue and groove fits and supported at the horizontal joint by support
keys and liners, similar to the HP stationary blade rings.
The No.2 dummy ring (13) and the thermal shield (19) are supported in
the outer casing by support keys and liners at the horizontal joint and
located by dowel pins at the top and bottom.
The combined HP-IP turbine casing is supported by four arms (or lugs)
which are cast integrally at the top of the base section, thus locating the
point of support as closely as possible to the horizontal center line. The
HP-IP outer casing is supported on the HP pedestal (14) at the governor
end (Gov End) and on the LP1 turbine outer casing at the generator end
(Gen End) as shown in Figure 2-5. For this purpose horizontal
machined surfaces are prepared on the HP pedestal and on the LP1
outer casing base.
The HP-IP outer casing base at the Gov End is supported on the HP
pedestal where the casing arms are located on transverse keys,
installed between the arms and the pedestal, on which the arms are free
to slide transversely. At the Gen End, the arms are supported on the top
surface of the LP1 outer casing base adjacent to the No.2&3 bearing
pedestal.
Refer to Figure 2-13 for details of HP pedestal. The HP pedestal is free
to slide axially on its base plate (21), but it is held against transverse
movement by two axial keys (17) placed on the longitudinal centerline
between the pedestal and the base plate. Any tendency of the pedestal
to tilt or lift is limited by side gibs, which are fitted with ample clearance
to allow free movement axially. Any tendency of the HP-IP outer casing
to rise off the HP pedestal is limited by a stud bolt (7) through each arm.
These stud bolts are fitted with ample clearance under the nut (29) and
around the bolt to allow free movement of the outer casing arms in
response to temperature changes.
The arms of the HP-IP outer casing at the Gen End are free to slide on
the No.2&3 bearing pedestal base. The tendency of the HP-IP casing to
rise off the bearing pedestal is limited and clearance for free expansion
movement is provided by similar arrangements provided on the HP
pedestal at the Gov End.

MM-M05.01

Rev.001

At each end of the HP-IP turbine between the outer casing and the
pedestals, centering beams are installed to maintain the correct axial
and transverse positions of the outer casing. Refer to Figure 2-12 for
details of centering beams.

Main Turbine
Mitsubishi

2-10

Chapter-2

General

The HP-IP turbine outer casing base and cover have integrally cast
nozzles for the entry and exit of main steam and reheat steam. The
outer casing base has nozzles for the extraction of steam to the high
pressure feed water heaters and other purposes. The HP-IP turbine
outer casing also has nozzles for HP and LP balancing pipes which
transfer leakage steam from the No.1 dummy ring seals to the HP
turbine exhaust and the No.2 dummy ring (13) seals to the IP turbine
exhaust respectively.

LP Casing
Refer to Figures 2-7 to 2-10. The constructional features of the LP1 and
LP2 turbine casings are similar.
The LP1/LP2 casing mainly consists of an outer casing (1, 2) and an
inner casing (3). The outer casing and the inner casing are split at the
horizontal center line to form a base and a cover. A steam chamber (4),
an inner flow guide ring (5) and two exhaust flow guide rings (6) are
installed in the LP casing; these components are also split in the
horizontal center plane to form a base and a cover.
The inner casing (3) is supported on the outer casing base at the
horizontal joint and located by a dowel pin (19) secured to the outer
casing base at the bottom.
The steam chamber (4) is supported on the inner casing horizontal joint
and located by a dowel (20) and two radial pins (22) at the bottom end.
The inner flow guide ring (5) is supported on the steam chamber
horizontal joint and located by dowel pin (21) welded to the inner flow
guide ring.
The LP blade rings (7) are supported on the steam chamber (4), one on
each end of the inner flow guide ring, and located by dowel pin (21) and
radial pins (23).
The first and second stage stationary blade diaphragms on each
flow-path of the turbine are secured to the LP blade rings (7) and the
third to fifth stage stationary blade diaphragms to the inner casing (3).
The last two stage stationary blade diaphragms are located and
secured to the inner casing.

MM-M05.01

Rev.001

The cross-over pipe from the IP turbine exhaust is connected to the LP1
and LP2 inner casings using flanged joints via flanged nozzles welded
on the top of the inner casings. Refer to Figure 2-14 for details of
cross-over piping connection and sealing arrangements. Expansion
joints together with cold spring settings (50 mm and 70 mm) provided on
the cross-over pipe accommodate the casing differential expansion.
The joints between the LP1 and LP2 inner casings and the outer
casings are sealed by a top seal ring arrangement as shown in Detail F
to prevent ingress of atmospheric air into the turbine.
Main Turbine
Mitsubishi

2-11

Chapter-2

General

The inner flow guide ring (5) located within the steam chamber (4) at the
vertical axis of each LP turbine guides the inlet steam to each flow-path.
The exhaust flow guide rings (6) secured to the ends of the inner casing
(3) guide the LP turbine outlet steam to the exhaust ports and to the
main condenser. To provide rigidity within the LP outer casing a series
of reinforcing bars and piping are installed.
Each LP1/LP2 turbine is supported by a continuous foot or skirt which is
made integral with and extends around the outer casing base. This foot
rests on seating plates which are bolted and grouted to the turbine
foundation.
Four transverse anchor blocks, provided one on each end of the LP1
and LP2 turbines, locate the LP1 and LP2 turbine casings in the turbine
axis. The transverse anchor blocks are secured to the turbine
foundations and locate the axial centerlines of the LP1 and LP2 turbine
casings in the turbine axis. With respect to the transverse anchor blocks,
the LP1 and LP2 turbine casings expand laterally (outwards) in opposite
directions. Refer to Figure 2-11 for LP turbine anchoring details.
Two axial anchor blocks, provided one on each side of the LP1 outer
casing, locate the entire turbine unit in the axial direction. They are
installed near the Gen End of LP1 turbine at a distance of 3275 mm from
the transverse centerline of LP1 turbine. Maintaining the axial anchor
blocks as fixed points, the LP1 and LP2 turbine casings expand axially
in opposite directions towards the HP pedestal and the generator. All
four casings (HP-IP, LP1, LP2 and generator casings) move axially with
respect to these axial anchor blocks.
In addition to the above anchor blocks, two tie beams are installed
between the LP1 and LP2 turbine outer casings, one on each side of the
turbine axis, to maintain the correct axial and transverse positions of the
outer casings. Refer to Figure 2-12 for details of tie beams.
Each LP turbine outer casing base has nozzles for the extraction of
steam for the low pressure feed water heaters and other purposes. The
LP1 turbine is provided with nozzles for No.1, No.2 and No.4 extractions
and the LP2 turbine is provided with nozzles for No.1, No.2 and No.3
extractions.
Two breakable diaphragms are provided on top of each outer casing
cover, one at each end of the LP1 and LP2 turbines, to protect the LP
turbine from high pressure damage.

MM-M05.01

Rev.001

2.4.2 Rotors
Refer to Figures 2-15 to 2-18.
The turbine rotor essentially consists of HP-IP, LP1 and LP2 rotors,
installed within their respective turbine casings.
Main Turbine
Mitsubishi

2-12

Chapter-2

General

Rigid type couplings connect the HP-IP rotor to the Gov End of LP1
rotor, Gen End of LP1 rotor to the Gov End of LP2 rotor and Gen End of
the LP2 rotor to the generator rotor. All coupling flanges are cast integral
with their respective turbine rotors. The main rotating element thus
formed (consisting of the HP-IP turbine rotor, LP1 and LP2 turbine
rotors and the generator rotor) is carried in eight journal bearings. The
rotating element thus formed is located axially by a thrust bearing
installed within the HP pedestal.

HP-IP Rotor
Refer to Figure 2-15.
The HP-IP turbine rotor is machined from a solid CrMoV alloy steel
forging. The rotor is finish machined and after being completely bladed,
is given an accurate dynamic balance test. The HP turbine rotating
blades (2), IP turbine rotating blades (3) and Rateau stage blades (4)
are secured to the HP-IP rotor.
The HP-IP rotor is provided with a series of balancing holes (7)
circumferentially at three locations, one near the centre of the rotor near
the IP turbine 1st stage and one at each end near the Gov End and Gen
End inner gland casings. The centrally located balancing holes are
normally used at the factory balancing and the holes at each end are
used in the event of site balancing being necessary. The HP-IP casing
is provided with necessary openings to provide access for the
installation of balancing weights in the event of HP-IP rotor site
balancing.
The Gen End of the HP-IP rotor is flanged to enable coupling. This
coupling flange is also provided with balancing holes on the
circumference to enable site balancing.
On the IP side of the main steam inlet, sealing rings are installed in the
No.1 dummy ring around stepped surfaces on the rotor to reduce steam
leakage from the inlet of HP turbine Rateau stage into the inlet of the IP
turbine. The No.2 dummy ring is installed at the Gov End of the rotor
within the HP-IP outer casing to minimize steam leakage from the HP
turbine exhaust into the Gov End gland casing.
At the Gov End of the HP-IP rotor, an extension stub shaft (5) is
provided to support the turbine main oil pump (MOP) impeller (6) and to
contain the mechanical overspeed trip (MOST) device. The extension
stub shaft is also provided with an integrally machined thrust collar (10)
to locate the combined turbine rotor axially.

MM-M05.01

Rev.001

The HP-IP rotor is provided with stepped surfaces (8) in the vicinity of
the HP and IP stationary blade diaphragms, sealing rings of No.1
dummy ring and No.2 dummy ring to provide efficient sealing and to
minimize steam leakage from the high pressure zone to the low
pressure zone.
Main Turbine
Mitsubishi

2-13

Chapter-2

General

The HP-IP rotor is also provided with stepped machined surfaces at


both ends, where the rotor shaft penetrates the casing, to provide
effective gland sealing.
The HP-IP rotor is provided with steps near the bearing journals to
facilitate rotor vibration measurement. The HP-IP extension shaft has
provisions for the measurement of rotor phase angle, rotor eccentricity,
rotor position and turbine speed.

LP Rotors
Refer to Figures 2-16 and 2-17.
The constructional features of the LP1 and LP2 rotors are similar. Each
LP rotor is machined from a solid NiCrMoV alloy steel forging. The rotor
is finish machined and after being completely bladed, is given an
accurate dynamic balance test. The rotating blades of each LP turbine
are secured to the respective LP rotors.
The LP rotor is provided with a series of balancing holes (4)
circumferentially at three locations, one in the LP turbine vertical axis
and one at each end near the Gov End and the Gen End gland casings.
The central balancing holes are normally used to perform dynamic
balancing in the factory and the holes at the ends are used in the event
of any site balancing. The LP1 and LP2 turbine outer casings are
provided with necessary flanged openings to provide access for the
installation of balancing plugs in the event of rotor site balancing.
Each LP rotor is provided with plain machined surfaces at both ends
where the rotor shaft penetrates the casing, and also in the vicinity of
the stationary blade diaphragms to provide effective gland sealing.
The LP1 rotor is provided with stepped surfaces near Nos. 3 and 4
bearing journals for the measurement of LP1 rotor vibration. The LP2
rotor is provided with stepped surfaces in the vicinity of Nos. 5 and 6
bearing journals for the measurement of the LP2 rotor vibration and
slant surfaces bear the Gen End coupling flange for the measurement of
turbine rotor differential expansion.

Mechanical Overspeed Trip (MOST) Device


Refer to Figure 2-18.

MM-M05.01

Rev.001

The turbine rotor is provided with an automatic mechanical overspeed


trip device to protect the turbine from overspeeding without control and
the subsequent damage to turbine components.
The function of the MOST device is to initiate a protection Stop
command to the turbine by stopping the flow of steam into the turbine if
the speed increases above 110% of the rated speed (i.e. 3300 rpm).

Main Turbine
Mitsubishi

2-14

Chapter-2

General

The MOST device comprises a overspeed trip weight (8), a balance


block (1) and a spring (4) fitted into the turbine rotor. The overspeed trip
weight is held in position by the spring (4). The compression of this
spring can be adjusted by rotating the spring retainer (2). The variation
of the spring compression changes the speed set point at which the trip
weight would actuate the overspeed trip trigger. The spring retainer (2)
can be locked after adjustment using a set pin (3), spring (5) and screw
(7).
The MOST device is screwed onto the end of the turbine rotor extension
stub shaft outboard of the thrust collar and held in position by a thread
cut opposite to the direction of rotation of the turbine. The trip weight is
carried in a transverse aperture in the extension stub shaft with its
center of gravity offset from the axis of rotation such that centrifugal
force exerts an outward force on the weight at all times.
Under normal operating conditions, the compressive force exerted on
this overspeed trip weight (8) by the spring (4) is greater than the
centrifugal force. However, if the turbine speed is increased to between
109% (3270 rpm) and 111% (3330 rpm) of the rated speed the
centrifugal force overcomes the spring tension and the weight moves to
a position where it protrudes through the aperture. In this position, the
weight strikes a trip trigger lever assembly, which rotates on a fulcrum
pin and is attached to the trip relay.
When the weight strikes the trip trigger, the trip relay is mechanically
moved to the tripped position, breaking the drain port seal and allowing
the auto stop oil pressure to rapidly decay which results in a turbine trip.
The weight remains in the extended position until the turbine speed has
reduced down to about 104% (3120 rpm) of the rated speed. Once
tripped the trip relay is not automatically reset when the turbine speed
returns to normal. The operator is required to initiate the Reset
command or reset the trip relay locally.
A true overspeed test is carried out on the turbine annually and also
after any major maintenance outage. The actual operating speed at
which the weight operates is confirmed.
The MOST device is provided with a facility to check that the MOST
weight is free to move without tripping the turbine. A test valve, when
opened directs the HP oil jet into a passage machined in the end of the
overspeed trip device. This allows oil pressure to be built up under the
overspeed weight, which assists in overcoming the spring tension.
When sufficient oil pressure is built up, the weight is operated and
moved to the tripped position contacting the trip trigger lever assembly.

MM-M05.01

Rev.001

The oil injection test is normally carried out on a monthly basis with
options for remote testing through a solenoid valve or locally through a
manually operated valve. During the above test, the turbine is
prevented from tripping by the operation of the lock out solenoid valve
for the remote test or by the operation of hand test lever for local test.
Main Turbine
Mitsubishi

2-15

Chapter-2

General

2.4.3 Blading
The blade path includes a Rateau stage operating with partial
admission control, followed by reaction stages in the HP, IP, LP1 and
LP2 turbines. The exact blade arrangement and the number of stages
or rows are given in Section 3, Specifications. Throughout the blade
path the rotating and the stationary parts are separated by relatively
large axial clearances. The much smaller radial clearances necessary
to control steam leakage are maintained by thin seal strips. These strips
are made of an alloy steel with excellent wearing qualities so that should
contact occur under normal conditions, the strips will rub away.

a)

Impulse Blading Rateau Stage HP Turbine


Refer to Figure 2-19.
The drawing shows an arrangement of the impulse blading in the
steam inlet of the HP turbine. The arrangement of the impulse
element consists of one row of impulse blades secured to the
HP-IP rotor. Nozzles (12) secured to nozzle block (11) installed at
the outlet of the No.1 dummy ring (3) direct the incoming steam
with high velocity towards the impulse blades to have a smooth
entry.
The No.1 dummy ring is divided into two halves and the nozzle
chamber in each half of the No.1 dummy ring is provided with 31
nozzles. The outlets from the four GVs are separately connected
to the nozzle chamber by slip joints consisting of seal rings (6) and
a seal ring retainer (7).
The outlets from #1 and #2 GVs are connected to the HP-IP
casing cover, which directs the steam to the upper half nozzle
chamber. Similarly the outlets from #3 and #4 GVs are connected
to the casing base, which directs the steam to the lower half
nozzle chamber.
The rotating blades are of an integral shroud type construction,
with a shroud machined integrally in each blade. The rotating
blades are secured to the rotor by means of serrated roots and are
installed in grooves cut across the surface of the rotor and
machined to conform to the shape of the blade roots.

MM-M05.01

Rev.001

A half round groove is machined circumferentially on the outer


surface of the rotor and each blade has a hole drilled in its base in
line with the groove in the rotor. Hence, as each blade is inserted
in its groove and properly located, a retaining pin is inserted in this
hole, thus locking the blade to the rotor. As the blades are inserted,
one after another, the flank face on each blade locks in the
retaining pin of the previously inserted blade. The last blade
entered is specially pinned with two lock screws.
Main Turbine
Mitsubishi

2-16

Chapter-2

General

The blades are shaped to form their own shroud thus forming a
closed passage for the steam flow. In order to reduce vibrational
stresses, these blades are bound together in groups by additional
shrouds (15) and tenons (16) on the end of the blades and
secured by riveting over the tenons.
The shanks are accurately machined to fit closely to one another
to give the correct spacing for the steam passage. To ensure that
steam leakage around the blades may be held to a minimum, seal
strips (17) are provided as shown in Fig 2-19.

b)

Reaction Blading HP Turbine


Refer to Figure 2-20.
The drawing shows an arrangement of the reaction blading in the
HP turbine. This arrangement permits small radial blade
clearances to be maintained during Unit operation.
The rotating blades are of an integral shroud type construction,
with a shroud machined integrally in each blade. The rotating
blades are secured to the rotor by Tee-root fastening and are
held against the top of the grooves by caulking strips, caulked in
place at the bottom as shown in Detail D. The last blade inserted
in specially pinned with two lock screws as shown in Sections A-A,
B-B and C-C.
The stationary blades are machined from bar stock with an offset
root and an integral shroud. The individual blades are then welded
together on the base and shroud to form a stationary blade
diaphragm which is split at the horizontal joint.
The stationary blade diaphragms are secured to the No.1 dummy
ring and the two HP stationary blade rings (No.1 and No.2 HP
stationary blade rings). The 1st to 3rd stage stationary blade
diaphragms are secured to the No.1 dummy ring, 4th to 7th stage
diaphragms to the No.2 HP stationary blade ring and 8th to 9th
stage diaphragms to the No.1 HP stationary blade ring.

MM-M05.01

Rev.001

The No.1 dummy ring and the two HP stationary blade rings are
machined with straight-sided grooves to hold the stationary blade
diaphragms in their correct locations. Each stationary blade ring
groove is sized to match the stationary blade diaphragm width
required at each row. A slot is machined in each HP stationary
blade ring groove to accommodate a metal packing strip used to
secure the stationary blade diaphragm in the HP stationary blade
ring as indicated in Detail E. The packing strip, caulked in at
installation, seals the stationary blade diaphragm groove.

Main Turbine
Mitsubishi

2-17

Chapter-2

General

At installation of the stationary blade diaphragms, a slot and a


tapped hole are added to the upper and lower half diaphragms for
installation of a setscrew in the horizontal joint area as indicated in
Detail E. The setscrew prevents the stationary blade diaphragm
from rotation during operation. The set screw also keeps the
diaphragm assembly from falling out when the HP stationary
blade rings are removed for maintenance.
The No.1 and No.2 HP stationary blade rings are made in two
halves, split at the horizontal joint. The lower half HP stationary
blade rings are secured to the HP-IP inner casing using keys and
liners to prevent them from rotation and the upper half HP
stationary blade rings are secured the lower halves by horizontal
joint bolts. Refer to Detail Z and Section J-J for details of HP
stationary blade ring support.
Each rotating/stationary blade shroud forms a close radial
clearance with thin flat seal strips, as shown in Fig 2-23, to ensure
that steam leakage around the blades may be held to a minimum.
The seal strips are removable and can be renewed if the
clearance between them and the corresponding blade shrouds
become excessive.

c)

Reaction Blading IP Turbine


Refer to Figure 2-21.
The figure shows an arrangement of the reaction blading in the IP
turbine. This arrangement permits small radial blade clearances
to be maintained during Unit operation.
The rotating blades are of an integral shroud type construction,
with a shroud machined integrally in each blade. The rotating
blades are secured to the rotor by means of serrated roots and are
installed in grooves cut across the surface of the rotor and
machined to conform to the shape of the blade roots.
A half round groove is machined circumferentially on the outer
surface of the rotor and each blade has a hole drilled in its base in
line with the groove in the rotor. Hence, as each blade is inserted
in its groove and properly located, a retaining pin is inserted in this
hole, thus locking the blade to the rotor as indicated in Section
B-B.

MM-M05.01

Rev.001

As the blades are inserted, one after another, the flank face on
each blade locks in the retaining pin of the previously inserted
blade. The last blade entered is specially pinned with two lock
screws.

Main Turbine
Mitsubishi

2-18

Chapter-2

General

The stationary blades are machined from bar stock with an offset
root and an integral shroud. The individual blades are then welded
together on the base and shroud to form a stationary blade
diaphragm which is split at the horizontal joint.
The stationary blade diaphragms are secured to the four IP
stationary blade rings (No.1, No.2, No.3 and No.4 IP stationary
blade rings) as indicated in Detail C. All IP stationary blade rings
have machined, straight-sided grooves to hold the stationary
blade diaphragms in their correct locations. Each stationary blade
ring groove is sized to match the stationary blade diaphragm width
required at each row. A slot is machined in each IP stationary
blade ring groove to accommodate a metal packing strip which
secures the stationary blade diaphragm in the IP stationary blade
ring. The packing strip, caulked in at installation, seals the
stationary blade diaphragm groove.
At installation of the stationary blades, a slot and a tapped hole
are added to the upper and lower half stationary blade
diaphragms for installation of a setscrew in the horizontal joint
area. Refer to Detail C for details. The setscrew prevents the
stationary blade diaphragm from rotation during operation. The
set screw also keeps the stationary blade diaphragm from falling
out when the IP stationary blade ring is removed for maintenance.
All IP stationary blade rings are made in two halves, split at the
horizontal joint. The lower half IP stationary blade rings are
secured to the IP blade ring using keys and liners, similar to the
HP stationary blade rings, to prevent them from rotation and the
upper half blade rings are secured the lower halves by horizontal
joint bolts.
Each rotating/stationary blade shroud forms a close radial
clearance with thin flat seal strips, as shown in Fig 2-24, to ensure
that steam leakage around the blades may be held to a minimum.
The seal strips around the rotating blades are secured in slots
machined in the IP stationary blade rings.
The stationary blade diaphragms are provided with spring-backed
seal rings onto which the seal strips are secured to provide
effective sealing with the rotor. These seal rings are installed in
segments and each segment is backed by a separate spring.

MM-M05.01

Rev.001

The seal strips are removable and can be renewed if the


clearance between them and the corresponding blade shrouds
become excessive.

Main Turbine
Mitsubishi

2-19

Chapter-2

d)

General

Reaction Blading LP1/LP2 Turbine


Refer to Figure 2-22.
The figure shows an arrangement of the double-flow LP reaction
blading in seven stages, with sealing details by means of which
small radial running clearances are maintained. The blading
arrangement for LP1 and LP2 turbines is similar.
Each reaction stage consists of a separate row of rotating and
stationary blades. The rotating blades are secured to the turbine
rotor and the stationary blades are secured by the LP blade rings,
and LP inner casing.
The stationary blade diaphragms are located in front of the
respective rotating blade rows and direct the downstream driving
steam to the next stage rotating blades.

Rotating Blades
Each LP rotor is fitted with seven rows of right-hand (RH) blading
on the Gen End and seven rows of left-hand (LH) blading on the
Gov End blade paths. Both sets of blading are the same but to the
opposite hand.
Since the steam flows in opposite directions through the blade
path in a double-flow unit, the rotating blades in the Gen End
blade path are RH blades, and those in the Gov End blade path
are LH blades. This permits the steam leaving the trailing edge of
either the Gen End or Gov End rotating blade row to travel in the
same rotating direction.
The rotating blades have serrated roots and are installed in
grooves cut across the surface of the rotor and machined to
conform to the shape of the blade root.
At the first through the fourth stages, the rotating blades are
installed similar to those in the IP turbine. A half-round groove is
machined circumferentially on the outer surface of the rotor and
each blade has a hole drilled at its base in line with the groove in
the rotor. Hence, as each blade is inserted in its groove and
properly located, a retaining pin is inserted in this hole thus locking

MM-M05.01

Rev.001

the blade to the rotor. As the blades are inserted one after another,
the free face of each blade is fixed by the retaining pin, which is
used to lock the previously inserted blade to the rotor. The last
blade entered is specially pinned by two set screws.

Main Turbine
Mitsubishi

2-20

Chapter-2

General

For the installation of the last three stage blades refer to View X-X,
Section A-A and View C-C in Figure 2-22. In the last three stages,
the rotating blades are fixed by driving a caulking strip into the
bottom of the blade root and the blade axial positions are fixed by
the insertion of a locking piece in a circumferential groove at each
end of the blade groove.
The rotating blades are of an integral shroud type construction,
with a shroud machined integrally in each blade.
As the rotating blades in the last row are relatively larger blades,
the blades have stubs provided mid-length on the individual
blades which when the rotor is turning at high-speed act to
prevent blade distortion and possible vibration.
The rotating blades in the last row operate in a zone where the
steam has high moisture content, which may cause blade erosion.
To minimize blade erosion due to moisture, a portion of each
blade is fitted with a stellite strip along the leading edge. Stellite, a
binary alloy of cobalt and chromium base, is very hard and is
highly resistant to erosion.
As shown in Figure 2-22, a flow guide is provided at each end of
the inner casing to maintain a smooth flow of steam from the last
stage rotating blades into the exhaust chamber.
The rotating blade shrouds in the first to the fourth stages form
close radial clearances with thin flat seal strips, as shown in
Figure 2-25, to ensure that steam leakage around the blades is
held to a minimum. The seal strips are removable and can be
renewed if the clearance between them and the corresponding
blade shrouds become excessive.
The fifth and the sixth stage rotating blade shrouds are provided
with spring-backed sealing rings secured to the inner casing to
minimize steam leakage. The last stage rotating blade shrouds
are also provided with spring-backed sealing rings and are
secured to the exhaust flow guide rings.

Stationary Blades

MM-M05.01

Rev.001

Each LP turbine is fitted with seven rows of right-hand stationary


blading on the Gen End and seven rows of left-hand blading on
the Gov End blade paths. Both sets of blading are the same but to
the opposite hand. The stationary blades direct the steam into the
rotating blades on the rotor.
Similar to the rotating blades, the RH and LH blade combination
permits the steam leaving the stationary blade diaphragms at the
Gen End or Gov End to travel in the same rotating direction.
Main Turbine
Mitsubishi

2-21

Chapter-2

General

The stationary blade diaphragms are held in their locations by the


inner casing and the blade rings. Matching grooves, machined in
the blade rings and the inner casing, hold the first to fifth stage
stationary blade diaphragms in their locations. The sixth and
seventh stage stationary blade diaphragms are held by tongues
(projections) provided on the inner casing.
Grooves in the blade rings and the inner casing are machined to
match the stationary blade diaphragm at each stage.
For the first to fifth stages, slots are machined in the grooves for
installing metal packing/caulking strips that are used to secure the
stationary blade diaphragms in the respective grooves. The
packing strip/caulking strip is caulked in at installation and also
serves to seal the grooves.
The tongues (projections) on the inner casing structure match the
grooves on the sixth and seventh stage stationary blade
diaphragms to prevent axial movement during operation. A radial
clearance of 5 mm is provided in the tongue and groove fit to
accommodate relative thermal expansion between the stationary
blade ring and the inner casing.
Each stationary blade diaphragm is composed of an inner and
outer ring with airfoil sections between rings. The inner and the
outer rings are separated into two halves at the horizontal
centerline.
Each stationary blade diaphragm is provided with a slot and
tapped hole for installation of set screws in the horizontal joint
area. The set screws keep the diaphragm from rotation during
operation. The set screws also keep the diaphragm assembly
from falling out when the upper half inner casing is removed for
maintenance.
The stationary blade diaphragms in the second to the fifth stages
are provided with thin flat seal strips secured to the stationary
blade diaphragm/rotor, as shown in Figure 2-25, to form close
radial clearances and ensure that steam leakage around the
blades is held to a minimum.

MM-M05.01

Rev.001

The stationary blade diaphragms in the first, sixth and seventh


stages are provided with spring-backed seal rings as shown in
Figure 2-25. These seal rings are installed in segments and each
segment is backed by a separate spring. The seal strips can be
removed and renewed if the clearance becomes excessive.
The seal rings in the sixth and seventh stage diaphragms are
provided with thin integral sealing tips.

Main Turbine
Mitsubishi

2-22

Chapter-2

General

2.4.4 Rotor Seals


Refer to Figures 2-23 to 2-25.
Leakage of steam through the gap between rotating and stationary
turbine components in the HP-IP, LP1 and LP2 turbines is reduced by
providing thin metallic strips.
The seal strips, secured to the turbine rotor or the stationary
components, provide very small running clearances thereby diverting
more steam through the turbine blades to improve turbine efficiency.
Each seal, made of 180-degree segment thin metal strips, is of a
tapered section inserted in a machined groove and held in position by a
soft steel locking strip which is caulked into the groove.
The seal strips are made of such material with good wearing properties
and permits close running clearances. This prevents serious damage to
the rotor during any accidental rubbing.
Leakage of steam, between the rotating and stationary turbine
components in certain locations in the IP and LP turbines, No.1 dummy
ring and No.2 dummy ring, is reduced by providing spring-backed
labyrinth type seals.
The labyrinth seals are a major item in maintaining the efficiency of the
turbine by keeping the steam flow within the blade path. The labyrinth
seal ring is assembled using groups of seal segments and springs that
are fitted into special, machined grooves. The seal supporting grooves
have a slot to hold the spring and base of the seal segment. The seal is
always installed such that the steam force will hold the seal against the
retaining groove and form an axial seal.
Slots of the supporting groove are large enough to permit the seal to
move within the groove. The backing spring holds the seal radially
against the supporting groove and allows a minimum running clearance
between the rotor and seal ring.
The spring-backed seal construction provides extra seal clearance in
case the rotor becomes distorted due to some abnormal operating
condition.
Each seal ring can be compressed and can spring back at each rotor
revolution. This prevents serious damage to the seal ring and heavy
rubbing on the rotor.

MM-M05.01

Rev.001

The seal rings are removable and can be renewed if the clearance
becomes excessive.

Main Turbine
Mitsubishi

2-23

Chapter-2

General

2.4.5 Gland Seals


Refer to Figure 2-26.
Because of the high differential pressure between the inside of the
turbine casing and the outside atmosphere, gland seals are provided at
each end of the HP-IP, LP1 and LP2 turbines.
For the HP-IP turbine, the seals prevent steam inside the turbine from
leaking out into the atmosphere. The last stages of the LP1 and LP2
turbines operate under a vacuum; the gland seals on the LP turbines
therefore prevent the ingress of air into the LP turbines and the
condensers.
The gland seals are of the labyrinth type. The gland seals are supplied
with sealing steam from the Gland Steam System.
There are minor differences between the HP-IP and LP turbine gland
sealing arrangements and the details of these gland sealing
arrangements are described in the mechanical maintenance manual
M05.03, Gland Steam System and GSC Fan.
The description below is of a typical gland sealing arrangement installed
at the Gen End of the HP-IP turbine.
The shaft gland seals are of the labyrinth type, consisting of a number of
seal strips to minimize the steam leakage.
Each gland seal ring is made in four or eight segments with a T-root
which fits into a corresponding groove in the gland case.
Rotation of these rings is prevented by anti-rotation pins which fit in slots
cut in each of the upper half seal ring segments at the horizontal joint.
Each gland seal ring segment is backed by a strap type spring secured
by a screw with ample clearance under the head to permit movement of
the spring. The retaining screws are locked at assembly by prick
punching.
The segments are numbered at each joint for identification. When
reassembling, after the rings have been dismantled, it is important that
these rings be reassembled in their original locations.

MM-M05.01

Rev.001

A steam pressure supply slot is provided in each segment, except the


glands facing the atmosphere in the outer gland case, to make the seal
rings seat radially by having a steam force that is greater on the external
side than on the internal side.
These seal rings should always be inserted with these slots facing the
steam flow as indicated. The seal strips inserted in these rings are made
of such material that permits close running clearances.
Main Turbine
Mitsubishi

2-24

Chapter-2

General

Sealing steam is admitted to or removed from a positive pressure


chamber for the HP and IP turbines through a connection in the lower
half of the outer gland case. For the HP and IP turbine glands, sealing
steam flows towards the glands from the gland steam header at low
loads and the flow reverses at higher loads. For the LP1 and LP2
turbines, the gland steam flow is always from the gland steam header to
the glands.
The leakage steam is evacuated from a negative pressure chamber
through a connection in the upper half of the outer gland case, to the
gland steam condenser. The gland steam condenser maintains a partial
vacuum in the negative pressure chamber which prevents steam
leakage past this chamber to atmosphere.
A pressure of approximately 0.2 barg is automatically maintained in this
chamber, under all operating conditions by the gland steam pressure
controller.

2.4.6 Turbine Bearings


The turbine bearings are briefly described in this section. Full details,
including dismantling, overhaul, reassembly and adjustment
procedures, are provided in the mechanical maintenance manual No.
M05.04, Turbine Bearings and Thrust Bearing.
The turbine bearings are numbered from the Gov End of the turbine,
thus the HP-IP rotor is supported at the Gov End by No.1 bearing and at
the Gen End by No.2 bearing. Similarly, LP1 rotor is supported by Nos.
3 and 4 bearings and LP2 rotor by Nos. 5 and 6 bearings. The resultant
thrust of the entire rotor assembly is absorbed by a single thrust bearing
located in the HP pedestal. All the bearings are of the forced lubrication
type.

a)

Bearing Nos. 1 and 2


Refer to Figure 2-27.
Nos. 1 and 2 bearings are of the self-aligning, tilting pad type
bearing with four white metal lined steel pads.
The bearing pads (3) are located in a bearing carrier ring, which is
split in the horizontal plane and each half of the carrier ring
supports two pads. The two halves of the carrier ring (1, 2) are
secured together using four horizontal joint bolts (9) and spring
washers (10).The upper half of the carrier ring (2) is located on the
lower half (1) by two dowel pins (8) at the horizontal joint.

MM-M05.01

Rev.001

Each bearing pad is supported in the carrier ring and is definitely


located by a pivot (4) installed into recesses on the inner surface
of the carrier ring. Inner liners (5), provided between the pivot and
the bearing pad, fit into recesses provided in the center of each
pad. The inner liners pivot on the pivots permitting self-alignment
of the bearing pads with the journal.
Main Turbine
Mitsubishi

2-25

Chapter-2

General

The circumferential movement of the bearing pad is restricted by


two pad stoppers (11), located at each end of the pad and are
secured to the carrier ring with the split rings (27). The axial
movement of the pads is restricted by end covers (15) fitted at
each end of the carrier ring.
Each upper bearing pad is provided with two compression springs
(22) near the trailing edge and inserted between the pad and the
carrier ring. These springs apply force to the trailing edge of the
pads continuously. This ensures that the trailing edge clearance is
closed and the leading edge clearance is opened, which is the
normal configuration. This arrangement prevents movement or
chattering of the unloaded upper pads.
The assembled bearing is positioned in the respective bearing
pedestal by four outer liners (6) set into the upper and lower
halves of the carrier ring at 45 to the vertical and horizontal
centerlines. The outer surfaces of the outer liners are spherical, to
match the mating surface of the bearing housing comprising a
bearing seat (28) welded to the pedestal base and a bearing keep
(29). (The bearing keep for No.2 bearing is integral with the
pedestal cover).
The four supporting outer liners are machined to a radius slightly
more than that of the bearing housing to provide an interference fit
of 0.08 mm, thus supporting the carrier ring in the bearing
pedestal. Each outer liner is installed in a recess on the outer
surface of the carrier ring, located by two dowel pins (18) and
secured by four hexagonal socket head bolts (19).
The lower half carrier ring (1) is provided with a fifth key (7)
(adjacent to No.3 bearing pad) at an angle of 25 to the vertical
centerline to admit lubricating oil to the bearing. This key is
installed with a clearance of 0 to 0.1 mm.
Spacers (21) and shims (20) of varying thicknesses are provided
between each outer liner and the carrier ring. Shims of variable
thicknesses (0.05, 0.1 and 0.2 mm) are supplied with each
bearing for adjustment during coupling alignment. By adjusting
the thickness of the shims between locations, the bearings and
therefore the rotor can be moved vertically and horizontally
relative to the pedestal and the turbine casing to locate the rotor
accurately within the casing.

MM-M05.01

Rev.001

The bearing pads, inner liners, pivots, supporting outer liners at


45 and shims at each location are numbered 1 to 4. The bearing
carrier rings are also match marked 1 to 4, to ensure that the
bearing components are assembled in their correct positions
following an inspection.

Main Turbine
Mitsubishi

2-26

Chapter-2

General

A stopper pin (14) fitted in the lower half bearing carrier ring fits
into a notch in the pedestal base just below the horizontal joint
(between Nos. 1 & 4 bearing pads), thus preventing rotation of the
bearing during operation.
Each bearing pad is provided with two temporary bolts (23) which
clamp each end of the pad to the bearing carrier ring. The purpose
of these bolts is to hold the pads in place during transportation and
installation. They are removed and the holes plugged with plugs
(24) during final assembly.
The bearing assembly is lubricated by lubricating oil from the main
turbine lubricating oil system. Lubricating oil reaches the bearing
through a passage in the pedestal base, and enters the lower half
carrier ring through a hole in the center of the outer liner (7).
Passages within the carrier ring direct the oil to the pad stoppers
(11) through matching holes. The pad stoppers, provided with
internal passages, spray the lubricating oil onto the journal
surface through oil distributors (13). The oil distributor is made of a
header with fine holes to distribute the oil uniformly onto the
journal surface. The end covers (15), fitted to the ends of the
carrier ring with a small clearance with the rotor, prevent
excessive oil leakage from the bearing. Oil is drained into the
pedestal through the clearance between the end covers and the
rotor.
The bottom bearing pads (Pad Nos. 3 and 4) have provisions for
the installation of thermocouples to measure the bearing
temperature just beneath the Babbitt lining.

b)

Bearing Nos. 3, 4 and 5


Refer to Figure 2-28.
The Nos. 3, 4 and 5 bearings are white metal lined cast steel
bearings. They are spherically seated, to provide a measure of
self-alignment, and can be adjusted for radial position within the
bearing housings.
Each bearing is made in two halves, lower and upper, bolted
together by hexagonal socket head bolts (6) at the horizontal joint.
The hexagonal socket head bolts are prevented from loosening by
interlocking them with lock bolts (7) fixed on the upper half shell
(2) using lock wire (8).
Two dowel pins (5) provided at the horizontal joint locate the
upper half shell (2) to the lower half shell (1).

MM-M05.01

Rev.001

Each bearing is positioned in the bearing pedestal by three keys


(3) set into grooves provided on the outer surface of the upper and
lower half shells. Two of these keys are assembled on the lower
half shell at an angle of 45 to the horizontal and vertical
Main Turbine
Mitsubishi

2-27

Chapter-2

General

centerlines, while the third one is located at the top of the upper
half shell on the vertical centerline.
Each key (3) is located in their respective groove on the outer
surface of the bearing shell using a dowel pin (10) and secured by
two key fixing bolts (9). The keys are provided with threaded holes
for jacking during removal.
The outer surfaces of the keys are spherical to match the mating
surface of the bearing housing comprising the bearing seat (13) in
the pedestal base and the bearing keep (14). (The bearing keeps
for the Nos. 3, 4 and 5 bearings are integral with the respective
pedestal covers). The keys are machined to a radius slightly less
than that of the bearing housing to provide a clearance fit of 0.3 to
0.4 mm.
Liners (12) and shims (11) are provided between each key and
the bearing shell. Shims of variable thicknesses (0.05, 0.1, 0.2
and 0.3 mm) are supplied with each bearing for adjustment during
coupling alignment. By adjusting the thickness of the liners and
shims between locations, the bearings and therefore the rotor can
be moved relative to the bearing housing and the turbine casing.
The support keys and the liners are numbered 1 to 3 and the
bearing shells are match marked to ensure that the bearing
components are assembled in their correct positions following an
inspection.
A stopper pin (4) fitted in the lower half shell fits into a notch in the
pedestal base just below the horizontal joint, thus preventing
rotation of the bearing during operation.
The lower half bearing shell is provided with a jacking oil
arrangement as shown in detail D to supply jacking oil and lift the
heavier LP rotors at low turbine speeds.
The bearing is lubricated by lubricating oil from the main turbine
lubricating oil system. Lubricating oil is supplied to the bearing
through an aperture drilled in the pedestal base, which is aligned
with an opening in the center of the right side bottom key (Key
No.2). Passages within the bearing shell direct the oil to the
bearing surface in the top half of the bearing as shown in the
drawing.

MM-M05.01

Rev.001

The bearing is provided with relieved sections, which have large


clearances along both sides around the horizontal joint. The
relieved sections do not extend to the ends of the bearing but stop
at an annular drainage groove close to each end.
The effect of these features is to create a constant supply (pool) of
oil for lubrication. Oil is drawn into the smaller gap that exists
between the lower half bearing surface and the journal by the

Main Turbine
Mitsubishi

2-28

Chapter-2

General

rotation of the shaft. This is a desirable characteristic for the


bearings supporting the heavier LP turbine rotor.
Oil exits from the ends of the bearing into the pedestal through
holes at the bottom of the annular groove.
As a fail safe measure, all three bearing keys have an oil hole.
However, components should always be match marked to ensure
that the bearing components are assembled in the correct/original
positions following an inspection.

c)

Bearing No.6
Refer to Figure 2-29.
The No.6 bearing is of the white metal lined, self-aligning, tilting
pad type. It is spherically seated to provide a measure of
self-alignment and can be adjusted for radial position within the
bearing pedestal.
The bearing is a two-pad type journal bearing consisting of a cast
steel shell, split into two halves (1 and 2). The lower half of the
shell (1) is provided with two tilting pad assemblies. The upper half
of the shell is of the sleeve type bearing and is not provided with
any tilting pad.
The two halves of the bearing shell are bolted together by four
hexagonal head cap screws (5) at the horizontal joint. Two dowel
pins (6) provided at the horizontal joint locate the upper half shell
(2) on the lower half shell (1).
The bearing shell is positioned in the bearing pedestal by three
keys (3) set into the upper and lower halves of the shell. Two of
these keys are assembled on the lower half shell at an angle of
45 to the horizontal and vertical centerlines. The third key is
located at the top of the upper half shell on the vertical centerline.
All three bearing keys are of similar design, with an oil hole
through the center. These keys and the bearing shell are clearly
numbered (1, 2 and 3) and the keys should always be assembled
in the same way in accordance with the marks.

MM-M05.01

Rev.001

As a fail safe measure, all three bearing keys are provided with an
oil hole. However, components should always be match marked
to ensure that the bearing components are assembled in the
correct/original positions following an inspection.
The outer surfaces of the keys (3) are spherical to match the
mating surfaces of the bearing seat (26) and the bearing keep (27).
The bearing seat (26) is integral with the No.6 bearing pedestal
base and the bearing keep (27) is integral with the pedestal cover.
Main Turbine
Mitsubishi

2-29

Chapter-2

General

The seating surface of the keys on the bearing pedestal is


machined to a radius slightly less than that of the bearing pedestal
to provide a clearance fit of 0.3 to 0.4 mm.
Liners (8) / shims (37) are provided between each key and the
bearing shell. By adjusting the thickness of these liners between
locations, the bearings can be moved relative to the pedestal. The
movement of the bearing enables the movement of the rotor
relative to the turbine casing.
A stopper pin (4) fitted in the lower half bearing shell (1) fits into a
notch in the bearing seat (26) just below the horizontal joint. This
stopper pin prevents rotation of the bearing during operation.
Two bearing pad assemblies are located on the lower half shell at
an angle of 45 to the horizontal and vertical centerlines. Each
assembly consists of a bearing pad (16) and a pad support (11).
The bearing pad is secured to the pad support by four pad fixing
bolts (23). The bottom surface of the pad support is provided with
a projection having a spherical surface. The pad support and
hence the pad pivots on this spherical surface permitting
self-alignment of the pads with the journal. Diaphragms (9) are
provided on either end of the pad supports to locate and to limit
the tilt of bearing pads during operation.
Each bearing pad is provided with four temporary bolts (21) which
clamp each end of the pad support (11 to the lower half bearing
shell. The purpose of these temporary bolts is to hold the bearing
pads in place during transportation and installation. They are
removed and the holes plugged with plugs (34) during final
assembly.
Each pad support in the lower half shell is provided with drilled
passages for admitting jacking oil to lift the LP-2 turbine rotor.
Jacking oil is admitted into the pad support through a check valve
assembly (17) fitted at the end of the bearing. Matching holes are
provided in the pads (16) and the pad supports (11) to admit
jacking oil to the rotor journal. Jacking oil to these bearings is
supplied from the discharge of the jacking oil pump.

MM-M05.01

Rev.001

The bearing shell is provided with an oil seal assembly at both


ends to prevent excessive leakage. Each oil seal assembly
consists of an oil seal ring (15) and an oil seal ring retainer (12 and
13). The oil seal ring is located within a slot (groove) machined on
the inner surface of the oil seal ring retainer. The inner surface of
the oil seal ring is lined with Babbitt to provide bearing surface.
A stopper pin (20), inserted through the upper half oil seal ring
retainer (12) along the vertical centerline, engages a slot
machined in the upper half oil seal ring (15) and prevents rotation
of the oil seal ring during operation.
Main Turbine
Mitsubishi

2-30

Chapter-2

General

Oil leaking through the oil seal ring is collected and drained to the
bearing pedestal through passages machined in the oil seal rings.
The oil seal ring retainers are also provided with passages at the
bottom end for this purpose.
The bearing is lubricated by lubricating oil from the main turbine
lubricating oil system. Lubricating oil is supplied to the bearing
through a hole in the bearing seat, which is aligned with the oil
hole in the center of key No.2 on the lower half shell.
As shown in the illustration, from this key the oil is led through
drilled internal passages to a relieved section in the upper half
bearing shell. The relieved sections have large clearances along
both sides around the horizontal joint. The relieved sections do
not extend to the ends of the bearing but stop at an annular
drainage groove close to each end.
The effect of these features is to create a constant supply (pool) of
oil for lubrication. Oil is then drawn into the smaller gap that exists
between the lower half bearing surface and the journal by the
rotation of the shaft. This is a desirable characteristic for the
bearings supporting the heavier LP turbine rotors.

d)

Thrust Bearing
Refer to Figure 2-30.
The thrust bearing is designed to resist thrust in either direction,
although the overall turbine design is for the thrust to act towards
the Gen End. The thrust bearing therefore limits the potential
turbine axial movement within the thrust clearance, and provides
protection for the turbine internal components.
The thrust bearing is a white metal faced multiple pad bearing,
with a lever mounting system to allow the pads to tilt and thereby
share the load evenly. A thrust collar (24), machined integrally
with the HP-IP rotor extension stub shaft (27), transmits thrust
from the turbine rotor to the turbine structure via the thrust bearing
assembly.

MM-M05.01

Rev.001

The thrust bearing is provided with eight pads (4, 15, 17, 18) on
each side of the thrust collar (25). The pads are numbered #1-1 to
#1-8 on the Gen End and #2-1 to #2-8 on the Gov End. The pads
#1-1 (20), #1-5 (17), #2-1 (22) and #2-5 (18), which are adjacent
to the carrier ring split line, are secured to the carrier ring using
parallel pins (19) and are called anti-fall pads. These anti-fall pads
prevent other pads from falling when the upper half carrier ring is
lifted. The anti-fall pads #1-1 and #2-1 and pads #1-4 and #2-4 are
provided with thermocouples for temperature measurement. Each
pad is provided with white metal coating on the bearing side.
Main Turbine
Mitsubishi

2-31

Chapter-2

General

The thrust pads are supported on a lever arrangement consisting


of upper levers (6) and lower levers (7). The thrust pads are
supported on the upper levers (6) through pivots (5) and pillars (8).
The upper levers (6) are interlocked with the adjacent lower levers
(7) as indicated in Section C-C.
The pivots (5) are held in grooves cut on the non-bearing side of
the pads. Pad stops (2), installed in the carrier ring (1) and held in
grooves at the sides of the pads as indicated in Section C-C,
maintain the pitch between the pads. O-rings (3 and 9) installed
on the pillars (8) and pad stops (2) prevent internal oil leakage.
The pads, pivots, pillars and levers are contained in the carrier
ring (1), which is split into halves. The thrust bearing components
at each side are retained by a spacer (16), which is secured to the
carrier ring (1) by socket head cap screws (12). The spacer
provides support to the lower levers (7) which in turn support other
components.
The levers, by virtue of their rocking motion, allow the pads to take
a position with their centers of loading all in the same plane.
Consequently, each pad takes an equal share of the load. This
construction eliminates the need to have all the pads exactly of
the same thickness and also compensates for small irregularities
in either the thrust collar or the thrust bearing case.
The carrier rings (1) are contained in a thrust bearing case (26),
which is also made in halves. The carrier rings are prevented from
rotation by anti-rotation pins (13) fitted between the thrust bearing
case and the carrier rings.
The upper and lower halves of the bearing case are provided with
extended arms at the horizontal joint. The two halves of the
bearing case are located at the extended arm by two dowel pins
and bolted together by hexagonal socket head screws. The thrust
bearing case is supported at the bottom by two supports provided
from the base of the HP pedestal.
The thrust bearing assembly is located and secured to the HP
pedestal base by a thrust bearing locating mechanism on either
side of the thrust bearing case.

MM-M05.01

Rev.001

The thrust bearing is lubricated by lube oil from the main turbine
lubricating oil system. Lubricating oil is supplied through two oil
inlets, one for each side of the bearing, on the upper half bearing
case and drained into the HP pedestal through an aperture in the
lower half bearing case.

Main Turbine
Mitsubishi

2-32

Chapter-2

General

2.4.7 Rotor Couplings


Refer to Figures 2-31 to 2-33.
The turbine couplings (HP-IP~LP1, LP1~LP2 and LP2~generator) are
of the flanged rigid type. The coupling flanges at the end of these rotors
are manufactured integral with the rotors from solid forgings. The
coupling flange of the generator rotor is provided with a nut cover which
is shrink-fit onto the coupling flange.
When all couplings are connected, a single rigid rotating element is
formed, consisting of the HP-IP, LP1, LP2 turbine rotors and the
generator rotor. This rotating element is supported in eight journal
bearings located in the turbine bearing pedestals and located axially by
a single thrust bearing installed within the HP pedestal.
In all cases, the two halves of the coupling and the respective spacer
ring are bolted together and secured with reamer bolts.
The HP-IP~LP1 and the LP1~LP2 couplings are provided each with a
40 mm thick spacer ring and the LP2~generator coupling is provided
with a 125 mm thick spacer gear ring.
The spacer rings and the spacer gear ring are machined to form a spigot
fit with each coupling. To remove a spacer ring or the spacer gear ring,
one or both of the rotors must be moved axially to obtain sufficient
clearance for the spacer to clear the spigots. Jacking screw holes are
provided on the coupling flanges for this purpose.
The spacer gear ring between the LP2 and the generator rotor coupling
has spur gear teeth around the periphery. The spacer gear is provided
with teeth to engage the output gear of the turning gear drive with the
turbine rotor.
The spacer rings at the HP-IP~LP1 and LP1~LP2 couplings are
provided with eyebolt holes for handling during maintenance; the
toothed spacer gear at the LP2~generator coupling does not have any
eyebolt hole.
The coupling flanges of the HP-IP, LP1 and LP2 rotors are provided with
balance plug holes around the periphery. This is to facilitate balancing
of the turbine rotating element. Balancing plugs are installed in some of
these holes, if necessary, during dynamic balancing. A description of
the balancing process is outside the scope of this document.

MM-M05.01

Rev.001

All couplings are provided with coupling guards for the safety of the
nearby equipment and the working personnel, in the event of any
unforeseen coupling failure or loosening of coupling bolts occurs.

Main Turbine
Mitsubishi

2-33

Chapter-2

General

The coupling guards are fabricated steel components. They are made in
two halves split at the horizontal joint, the upper half and the lower half.
The lower half is mounted on the respective lower half bearing pedestal
and the upper half coupling guard is supported by the lower half
coupling guard at the horizontal joint.
All couplings are provided with a supply of lubricating oil from the main
turbine bearing lubrication system. The oil is sprayed on the outer
surface of the coupling guards to dissipate any heat generated on these
couplings/coupling guards during operation. The heated oil is returned
to the main oil tank through the drain guard pipe.

2.4.8 Steam Admission Valves


Refer to Figures 2-34 and 2-35.
The total steam requirement for the main turbine unit is controlled by
two sets of main stop valve (MSV) and governing valve (GV)
assemblies and two sets of reheat stop valve (RSV) and interceptor
valve (ICV) assemblies.
Steam admission to the HP turbine is controlled by the MSV/GV
assemblies. The MSVs and GVs are constructed in common
assemblies referred to as steam chests, which are located on either
side of the HP turbine. Each steam chest consists of a single MSV
(throttle valve) and two GVs. The GV in each steam chest admits steam
to the HP turbine nozzle chamber in the No.1 dummy ring through
separate steam leads. During normal loaded operation of the turbine,
the GVs are operated in parallel to control the total flow of steam to the
turbine.
The RSV/ICV assemblies control the steam flow to the IP turbine. The
RSVs and the ICVs are constructed in two common assemblies which
are located on either side of the HP turbine adjacent to the HP pedestal.
Each RSV/ICV assembly consists of a RSV and two ICVs. The RSVs
and the ICVs control the flow of hot reheat steam to the four steam inlets
of the IP turbine.
The function, inspection, and maintenance of these valves are
described in detail in the mechanical maintenance manual M05.02,
Steam Admission Valves.
There are no valves to control the flow of steam to the LP1 and LP2
turbines. Steam exhausting from the IP turbine is directly routed to the
LP1 and LP2 turbines through the crossover pipe.

MM-M05.01

Rev.001

Control of the turbine valves (and therefore turbine operation) is by the


Distributed Control System (DCS) and the Main Turbine Digital
Electro-hydraulic (DEH) Control System. Details of these control
systems are provided in the respective Instrument & Control (I&C)
maintenance manual.
Main Turbine
Mitsubishi

2-34

Chapter-2

General

2.4.9 Turning Gear


Refer to Figure 2-36.
The function of the turning gear is to rotate the turbine rotor at a low
speed (about 3 rpm) when the main turbine is shutdown and cooling,
and also before turbine startup. The turning protects the turbine rotors
from distortion (bending or warping). Rotor distortion may cause high
rotor eccentricity and high bearing vibration during startup.
The turning gear is installed between the LP2 turbine and the generator
and is driven by an AC motor (1). Spray oil lubricates the turning gear
when the main turbine is turning. The lube oil branched from the No.6
bearing oil supply line is sprayed onto the meshing teeth of the spacer
gear (8) and final pinion gear (7) through an associated solenoid valve.
The solenoid valve has a bypass line which has a normally closed
manual valve. (The valve is manually opened if the solenoid valve is not
available). The thrust bearing of the worm (9) is also lubricated by oil
branched from the No.6 bearing oil supply line. The worm (9), worm
wheel (5) and intermediate gear (6) run in an oil sump formed in the
turning gear housing. An overflow flow hole in the turning gear housing
(13) maintains the level in the sump.
The shafts of the worm wheel, intermediate gear and final output gear
are supported separately on two DU bushings. The DU bushings are
made of Teflon impregnated porous bronze, which do not require any
lubrication.
A clutch plate assembly (4) which supports the final pinion gear (7) is
connected to a pneumatic operated air cylinder (14) through an
operating lever (2).
A turning gear panel (18) mounted on the turning gear housing contains
the pneumatic operated air cylinder (14), operating lever (2), solenoid
valve (19) and limit switches (15, 16, 17) for trouble free remote
operation of the turning gear.
The solenoid valve (19) supplies compressed instrument air to the
pneumatic air cylinder (14) during Engage and Disengage operations.
The limit switches (15, 16) indicate the Engage and Disengage
positions of the air cylinder. A bar (21) secured to the operating lever
operates the limit switch levers at the Engage and Disengage
positions. Another limit switch (17) installed near the cylinder support
bracket provides indication for positive gear contact between the final
pinion gear (7) and the spacer gear (8).

MM-M05.01

Rev.001

A 6 pole, 380 V, 50 Hz, 1000 rpm, 22 kW motor (1) bolted to the turning
gear housing drives the turning gear.
A ratchet spanner (10) supplied as a special tool is used to rotate the
turbine rotor manually when the turning gear motor is damaged or
during a total power supply failure.
Main Turbine
Mitsubishi

2-35

Chapter-2

General

Mechanical maintenance manual M05.07 provides full details, and the


maintenance procedures for the turning gear.

2.4.10 Rotor Grounding Device


Refer to Figure 2-37.
Steam turbines, running at high speeds risk a build up of static electricity
on the turbine rotors, and as there is no clear route to ground, a rotor
grounding device is installed to dissipate the static electric charge.
If this low resistance device were not provided, the electrostatic charge
would probably be discharged to ground through the bearings and the
pedestals. Apart from the obvious, but small, safety risk (possible
electrical discharge in the presence of a flammable liquid or vapor),
such discharges could cause surface burning and damage to the
bearing surfaces.
Two sets of rotor grounding devices are located between the LP2
turbine and the generator, one in the vertical axis and the other at an
inclination of 60.
Each rotor grounding device consists of a 6 mm thick copper braid (9)
backed by a 0.7 mm thick plate spring (8). The braid and the plate spring
are sandwiched between three support plates (7) and bolted to a
bracket (6), which is mounted on the Gen End oil retaining ring at the
No.6 bearing pedestal.
The free end of the copper braid is held in constant contact with the
generator rotor by the spring force and the other end is connected,
through an earthing cable, to an earth terminal block (14) mounted on
the Gen End of the LP turbine base. Another earthing cable discharges
the electrostatic charge from the earth terminal block (14) to the power
plant earthing network.

2.4.11 Breakable Diaphragm


Refer to Figure 2-38.
Two breakable diaphragms are mounted on the top of each LP turbine
outer casing to provide automatic emergency relief should the internal
pressure rise beyond the maximum safe value for which the cylinder is
designed.

MM-M05.01

Rev.001

Each breakable diaphragm assembly consists of a diaphragm (4) made


of thin lead sheet supported against the external atmospheric pressure
by a round thin diaphragm pressure disc (3). The diaphragm pressure
disc (3) is located loosely in a slot in the LP outer casing and the
diaphragm (4) is clamped between the LP casing (1) and the guard (2)
using bolts (5).

Main Turbine
Mitsubishi

2-36

Chapter-2

General

If the exhaust pressure rises above the predetermined point, the


diaphragm pressure disc is forced outward causing the lead diaphragm
to be sheared off between the inner edge of the guard and the edge of
the diaphragm pressure disc.
Rupturing of this diaphragm relieves the pressure in the turbine exhaust.
The turbine casing directs the rush of steam upward and the guard (2)
prevents scattering of the diaphragm (4) and the disc (3).
This diaphragm is used in conjunction with an automatic low vacuum
trip, which shuts the turbine down, when the exhaust pressure rises to a
predetermined point, usually about 430 mm of Hg. The expected
pressure at which the lead diaphragm ruptures is usually 0.36 barg.

2.4.12 Turbine Enclosure


Refer to Figure 2-39.
The turbine is provided with an indoor type enclosure, around the
HP-IP turbine cylinder, MSV/GV assemblies, RSV/ICV assemblies, the
HP and Nos. 2&3 bearing pedestals, etc. Enclosure is also provided
around the foot of the LP turbine bottom casing.
The purpose of the turbine enclosure is to reduce noise level from the
turbine and to reduce thermal radiation from the HP-IP turbine hot
components.
The turbine enclosure consists of several panels, which are bolted
together to enclose the turbine from all sides. The panels are filled with
acoustic material to reduce the noise level outside the enclosure.
The top side of the enclosure is not covered and left open to provide
natural ventilation.
The sides of the enclosure are provided with lockable, hinged doors on
all sides to facilitate inspection of the turbine during normal operation.
The doors are to be normally kept closed to prevent entry of unqualified
persons.

MM-M05.01

Rev.001

The enclosure is of the removable type and it can be removed for


carrying out any major maintenance activity.

Main Turbine
Mitsubishi

2-37

Chapter 2

General

INNER CASING
NO.1 DUMMY RING
OUTER CASING COVER
THRUST BEARING
No.2 HP STATIONARY
BLADE RING
No.1 HP STATIONARY
BLADE RING
MOP
No.2 DUMMY RING

No. 1 BEARING

No.1 IP STATIONARY
BLADE RING
No.2 IP STATIONARY
BLADE RING

Rev.001

No.3 IP STATIONARY
BLADE RING
No.4 IP STATIONARY
BLADE RING

MM-M05.01

No. 2 BEARING
MPTD-3-0204

HP-IP ~ LP1 COUPLING

FIGURE 2-5
Main Turbine
Mitsubishi

CUT AWAY VIEW OF HP-IP TURBINE


2-38

Chapter 2

11

4
17

IP EXHAUST

MAIN STEAM
INLET
REHEAT STEAM
INLET

10

21

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22

3
6

25
8

19

23

22

GEN.SIDE

GOV. SIDE

16

23

18

24
25
26

15

General

OUTER CASING BASE


OUTER CASING COVER
INNER CASING
IP BLADE RING
No.1 DUMMY RING

MOST DEVICE
No.2 DUMMY RING
HP PEDESTAL
MOP
NO. 1 BEARING
NO. 2 BEARING
THRUST BEARING
THERMAL SHIELD
HP-IP ROTOR
HP BALANCING PIPE
LP BALANCING PIPE
NOS. 2&3 BEARING
PEDESTAL
DOWEL
NOZZLE BLOCK
NOZZLES

14
12

OPERATING FLOOR

HP EXHAUST

MM-M05.01

Rev.001

26

20

MPTD-3-0205

REHEAT STEAM
INLET

24

MAIN STEAM
INLET

13
24

1
FIGURE 2-6

Main Turbine
Mitsubishi

SECTIONAL VIEW OF HP-IP TURBINE


2-39

Chapter 2

General

INNER CASING

MM-M05.01

Rev.001

NO.4 BEARING

MPTD-3-0206

FIGURE 2-7
Main Turbine
Mitsubishi

CUTAWAY VIEW OF LP1 TURBINE


2-40

Chapter 2

15

23

10

11

STEAM
INLET

12

18

14

MM-M05.01

Rev.001

GENERATOR
END

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23

General

OUTER CASING BASE


OUTER CASING COVER
INNER CASING
STEAM CHAMBER
INNER FLOW GUIDE
EXHAUST FLOW GUIDE
LP BLADE RING
LP1 ROTOR
ROTATING BLADES
STATIONARY BLADES
No. 3 BEARING
No. 4 BEARING
SHAFT GLAND
No. 2 BEARING
BREAKABLE DIAPHRAGM
GLAND STEAM INLET
GLAND STEAM OUTLET
VIBRATION PICKUP
DOWEL
DOWEL
DOWEL
RADIAL PIN
RADIAL PIN

GOVERNOR
END

17

16

13

21

20

19

22

13

16

17

MPTD-3-0207

FIGURE 2-8
Main Turbine
Mitsubishi

SECTIONAL VIEW OF LP1 TURBINE


2-41

Chapter 2

General

NO. 5 BEARING

MM-M05.01

Rev.001

NO.6 BEARING

MPTD-3-0208

FIGURE 2-9
Main Turbine
Mitsubishi

CUTAWAY VIEW OF LP2 TURBINE


2-42

Chapter 2

15

23

14

10

11

STEAM
INLET

12

18

18
23

22

Rev.001
MM-M05.01

17

Main Turbine
Mitsubishi

OUTER CASING BASE


OUTER CASING COVER
INNER CASING
STEAM CHAMBER
INNER FLOW GUIDE
EXHAUST FLOW GUIDE
LP BLADE RING
LP2 ROTOR
ROTATING BLADES
STATIONARY BLADES
No. 5 BEARING
No. 6 BEARING
SHAFT GLAND
STEAM INLET NOZZLE
BREAKABLE DIAPHRAGM
GLAND STEAM INLET
GLAND STEAM OUTLET
VIBRATION PICKUP
DOWEL
DOWEL
DOWEL
ROTOR GROUNDING DEVICE

GOVERNOR
END

GENERATOR
END

MPTD-3-0209

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23

General

16

13

21

20

19

22

13

16

17

FIGURE 2-10

SECTIONAL VIEW OF LP2 TURBINE

2-43

Chapter 2

LP-1 TURBINE CASING

No.1 BRG.
C
L

MS. INLET
C
LON CYLINDER

No.2 BRG.
C
L

No.3 BRG.
C
L

LP-1 TURBINE
C
L& CONDENSER

No.4 BRG.
C
L

No.5 BRG.
C
L

No.6 BRG.
C
L

No.7 BRG.
C
L

No.8 BRG.
C
L

LP-2 TURBINE
C
L& CONDENSER

GOV. SIDE

GENERATOR
C
L

GEN. SIDE

General

SEATING PLATE
FOR LP-1 TURBINE

LP-1 TURBINE CASING

C
L

RSV

2-ANCHOR PLATE

C
L

MSV&GV
C
L

RSV

e
EYE BOLT

VIEW "J"

LP-2 TURBINE

CLEARANCE
0.02~ 0.04
( EACH SIDE)

T/G UNIT
C
L

LP-1 TURBINE

"J"

SPOT WELDING
LP-1 TURBINE CASING

RSV

OPERATING FLOOR

C
L

MSV&GV
C
L

C
L

RSV

SEATING PLATE
FOR LP-1 TURBINE

LP-1 TURBINE CASING

TRANSVERS ANCHOR BLOCK


SEE DETAIL "A"

TRANSVERS ANCHOR BLOCK


SEE DETAIL "B"

TRANSVERS ANCHOR BLOCK


SEE DETAIL "C"

2-AXIAL ANCHOR BLOCK


SEE DETAIL "E"

TRANSVERS ANCHOR BLOCK


SEE DETAIL "D"

DETAIL "E"
(AXIAL)

BOLT

EYE BOLT

0.02~ 0.04

CLEARANCE

0.02~ 0.04

EYE BOLT

EYE BOLT

EYE BOLT

(EACH SIDE)

CLEARANCE

0.02~ 0.04

(EACH SIDE)

0.02~ 0.04

CLEARANCE

CLEARANCE

0.02~ 0.04

(EACH SIDE)

CLEARANCE

EYE BOLT

(EACH SIDE)

LP-2 TURBINE CASING


(EACH SIDE)

CLEARANCE
0.02~ 0.04
iEACH SIDE j

SEATING PLATE
FOR EXCITER

GENERATOR CASING
EYE BOLT

GENERATOR CASING

VIEW "F"

VIEW "H"
VIEW "G"

SEATING PLATE
FOR EXCITER

SEATING PLATE
FOR LP-2 TURBINE

SEATING PLATE
FOR GENERATOR

"F"

BOLT

SEATING PLATE
FOR LP-2 TURBINE

"G"

GROUT

GROUT

GROUT

GROUT

BOLT

OPERATING FLOOR

BOLT

GROUT

GROUT

GROUT
SEATING PLATE
FOR LP-1 TURBINE

c
c

Rev.001

"I"

OPERATING FLOOR

MM-M05.01

LP-1 TURBINE
CASING

"H"

GROUT

VIEW "I"
LP-2 TURBINE
CASING

LP-2 TURBINE
CASING

OPERATING FLOOR

GROUT

LP-1 TURBINE
CASING

DETAIL "A"

DETAIL "B"

DETAIL "C"

DETAIL "D"

(GENERATOR)

(GEN~LP2)

(LP2~LP1)

(LP1~HP-IP)

MPTD-3-0210

FIGURE 2-11
Main Turbine
Mitsubishi

TURBINE CASING ANCHORING DETAILS


2-44

Chapter 2
GEN. SIDE

General

C
L OF MAIN OIL PUMP
PHASE DETECTOR
PICK UP

"A"
NO.6 BEARING
PEDESTAL

C
L OF THRUST BRG.

C
L OF NO.1 BRG.

C
L OF MAIN STEAM INLET

C
L OF REHEAT STEAM INLET

C
L OF IP EXHAUST

C
L

C
L OF NO.2 BRG.

OF NO.3 BRG.

C
L OF LP1 TURBINE

C
L OF NO.4 BRG.

C
L OF NO.5 BRG.

C
L OF NO.6 BRG.

C
L OF LP2 TURBINE

GOV. SIDE

HP PEDESTAL
ZERO SPEED
& SPEED PICK UP

NOS.4&5 BEARING
PEDESTAL

ECCENTRICITY
PICK UP

NOS.2&3 BEARING
PEDESTAL

ROTOR POSITION
PICK UP
ROTATION

OPERATING FLOOR

LP2 OUTER CASING

CENTERING BEAM

LP1 OUTER CASING


STUD BOLT

LOCATING PIN

CENTERING BEAM
WASHER
BOLT

BUSHING

NUT

SPHERICAL
WASHER

REAMER
STUD BOLT

NOS.2&3 BEARING
PEDESTAL

HP PEDESTAL

SPHERICAL WASHER

STUD BOLT

SPACER
BOLT

TIE BEAM

LP2 OUTER
CASING

REAMER
STUD BOLT

HP-IP OUTER CASING


SPHERICAL
WASHER
BOLT

WASHER

SPACER

BUSHING

NUT
BUSHING

LP1 OUTER CASING

NUT

SPACER

LOCATING PIN

HP-IP OUTER CASING

DETAIL "B"
"B"

MPTD-3-0211

MM-M05.01

Rev.001

VIEW "A"

FIGURE 2-12
Main Turbine
Mitsubishi

TURBINE CASING CENTERING AND TIE BEAMS ARRANGEMENT


2-45

Chapter 2

General

5
11

13
14
3

1
4

18
12

"G"

28

27

10
29

10
29

12

H
9

24

13

B
10

F
VIEW A

SECTION B-B

10

VIEW C
VIEW E

E
4

27

26

27

13

13
14

14

C
18

18

25

18

23
22

17

21

VIEW D

19

LOCATING PIN

20

SET SCREW

21

BASE PLATE

22

GREASE PIPE

23

CENTERING BEAM

24

OIL STRAINER

25

PLUG

26

NAMEPLATE

27

INSPECTION COVER

28

BOLT

29

NUT

16 15

VIEW F

SECTION X-X
20
27

28

1
8

Rev.001

19

MM-M05.01

SECTION H-H
DETAIL "G"
FIGURE 2-13
Main Turbine
Mitsubishi

HP PEDESTAL ARRANGEMENT
2-46

General

MM-M05.01

Rev.001

Chapter 2

FIGURE 2-14
Main Turbine
Mitsubishi

IP TO LP TURBINES CROSS-OVER PIPE ARRANGEMENT


2-47

Chapter 2

General

8
GEN. SIDE

GOV. SIDE

3
4

10
6

1 2 3
8

4 5 6 7

8 9

1
2
3
4
5
6
7
8

MM-M05.01

Rev.001

9
10

VIEW A

VIEW B

HP-IP ROTOR
HPT ROTATING BLADES
IPT ROTATING BLADES
RATEAU STAGE BLADE
STUB EXTENSION SHAFT
MOP IMPELLER
BALANCING HOLE
STEPPED SURFACES
FOR ROTOR GLAND SEALS
SERRATED BLADE ROOT
THRUST COLLAR

MPTD-3-0214

FIGURE 2-15
Main Turbine
Mitsubishi

HP-IP ROTOR ASSEMBLY


2-48

Chapter 2

General

GEN. SIDE

GOV. SIDE

A
4

1
2
3
4
5
6

LP1 ROTOR
ROTATING BLADE
SERRATED BLADE ROOT
BALANCING HOLE
STUB
STELLITE STRIP

MM-M05.01

Rev.001

93

VIEW A

VIEW B

MPTD-3-0215

FIGURE 2-16
Main Turbine
Mitsubishi

LP1 ROTOR ASSEMBLY


2-49

Chapter 2

General

GEN. SIDE

GOV. SIDE

A
4

1
2
3
4
5
6

LP2 ROTOR
ROTATING BLADE
SERRATED BLADE ROOT
BALANCING HOLE
STUB
STELLITE STRIP

MM-M05.01

Rev.001

93

MPTD-3-0216

VIEW A

VIEW B
FIGURE 2-17

Main Turbine
Mitsubishi

LP2 ROTOR ASSEMBLY


2-50

Chapter-2

General

5
8
7
2

1
2
3
4
5
6
7
8

SECTION A-A

BALANCE BLOCK
SPRING RETAINER
SET PIN
SPRING
SPRING
SET SCREW
MACHINE SCREW
OVERSPEED TRIP WEIGHT

MM-M05.01

Rev.001

MPTD-4-0217

FIGURE 2-18
Main Turbine
Mitsubishi

MECHANICAL OVERSPEED TEST (MOST) DEVICE

2-51

Chapter 2

General

11
7

15
6

14
4

12

13

3
10
5

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Rev.001

MAIN STEAM NOZZLE


HP INNER CASING
NOZZLE BLOCK
RATEAU STAGE BLADE
ROTOR
SEAL RINGS
SEAL RING RETAINER
SEALING RINGS
DOWEL
GLAND SEAL RING
NOZZLE HOLDER
NOZZLE
BLADE ROOT
SHROUD
SEAL STRIP

MM-M05.01

MPTD-3-0218

FIGURE 2-19
Main Turbine
Mitsubishi

HP TURBINE IMPULSE BLADING RATEAU STAGE


2-52

Chapter 2

General

GOV. SIDE

GEN. SIDE

PACKING STRIP

STEAM
IN

No.1 DUMMY RING

No.1 HP STATIONARY BLADE RING

NOZZLE

ROTATING BLADE SHROUD

NOZZLE BLOCK

SEAL STRIP

No.2 HP STATIONARY
BLADE RING

STATIONARY BLADE BASE


ROTATING BLADE

SET SCREW
AT HORIZONTAL JOINT
(IC TO 9C)

"E"

STEAM
OUT

ROTATING BLADE
HP-IP ROTOR

A
2C

1C

1S

2S

3S

4S

7C

6C

5C

4C

3C

5S

6S

9C

8C

7S

8S

9S

LOCK SCREW
STATIONARY BLADE

LOCK SCREW

A-A

SECTION C-C

STATIONARY BLADE SHROUD

AT HORIZONTAL JOINT

No.1 DUMMY RING

ROOT

LOCK SCREW

LAST BLADE

GROOVE

C
SECTION B-B

STATIONARY BLADE BASE

MM-M05.01

Rev.001

CAULKING STRIP

DETAIL "E"

DETAIL "D"

MPTD-3-0219

FIGURE 2-20
Main Turbine
Mitsubishi

HP TURBINE REACTION BLADING


2-53

Chapter 2
GEN. SIDE

General

GOV. SIDE

ROTATING BLADE

IP BLADE RING
SET SCREW
AT HORIZONTAL JOINT
(IC TO 8C)

SEAL STRIP
ROTATING BLADE SHROUD
PACKING STRIP
RETAINING PIN

No.1 IP STATIONARY BLADE RING


STATIONARY BLADE BASE

LAST BLADE

A
STEAM
OUT
8S

8C

7S

STEAM
IN
7C

6S

6C

5S

5C

4S

4C

3S

3C

2S

2C

1S

1C

LOCK SCREW
NO.1 DUMMY RING

SECTION B-B

SEAL STRIP
ROTOR BALANCING
PLUG HOLE

STATIONARY BLADE SHROUD


ROTATING BLADE

SET SCREW
AT HORIZONTAL JOINT

MM-M05.01

Rev.001

SERRATED ROOT

DETAIL "C"

A-A

MPTD-3-0220

FIGURE 2-21
Main Turbine
Mitsubishi

IP TURBINE REACTION BLADING

2-54

Chapter 2

GEN. SIDE

General

GOV. SIDE

ROTATING BLADE
STATIONARY BLADE BASE
STEAM CHAMBER
INNER CASING

ROTATING BLADE

PACKING STRIP

INNER FLOW GUIDE

LOCKING STRIP

5R

STATIONARY BLADE

LP BLADE RING

ROTATING BLADE SHROUD


LP ROTOR

SEAL STRIP

STEAM
IN

FLOW GUIDE

STELLITE STRIP
STUB

7R

7C

7C

7R

LOCKING PIECE

LOCKING PIECE
6R

VIEW X-X

6C

6C
5R

5C

4R

4C 3R 3C

2R 2C 1R 1C

4C
1C 1R 2C 2R 3C3R

4R

5C

6R

5R

LOCKING PIECE

LP ROTOR

C
CAULKING PIECE

SHAFT GLAND

VIEW A-A
SERRATED

BALANCING PLUG HOLE

ROTATING BLADE ROOT

BALANCING PLUG HOLE


HORIZONTAL JOINT SET SCREW

STATIONARY BLADE SHROUD

VIEW C-C

MPTD-3-0221

MM-M05.01

Rev.001

CAULKING PIECE

FIGURE 2-22
Main Turbine
Mitsubishi

LP1/LP2 TURBINE REACTION BLADING

2-55

Chapter 2

No.2 HP STATIONARY
BLADE RING

No.1 HP STATIONARY
BLADE RING

LOCKING STRIP

STAGES 1S~3S

General

LOCKING STRIP

STAGES 4S~7S

STAGES 8S~9S

STATIONARY
BLADE DIAPHRAGM

LOCKING STRIP

SEAL STRIP
SEAL STRIP

SEAL STRIP

LOCKING STRIP

STAGES 4C~7C

STAGES 8C~9C

MM-M05.01

Rev.001

STAGES 1C~3C

LOCKING STRIP

MPTD-3-0222
FIGURE 2-23
Main Turbine
Mitsubishi

HP TURBINE BLADING SEAL ARRANGEMENT

2-56

Chapter 2

General

LOCKING STRIP

SEAL STRIP
ROTATING BLADE

STAGES 1S~8S

STAGES 4C~8C

STAGES 2C~3C

MPTD-3-0223

MM-M05.01

Rev.001

STAGES 1C

FIGURE 2-24
Main Turbine
Mitsubishi

IP TURBINE BLADING SEAL ARRANGEMENT

2-57

Chapter 2

General

INNER CASING

LOCKING STRIP
SEAL STRIP

SEAL STRIP

STAGE 7R(LH, RH)

STAGE 6R(LH, RH)

STAGE 5R(LH, RH)

STAGE 4R(LH, RH)

STAGE 3R(LH, RH)

STAGE 1R & 2R(LH, RH)

SEAL RING

STATIONARY
BLADE SHROUD

SEAL STRIP
SEAL STRIP

LOCKING STRIP

LOCKING STRIP

LP ROTOR

STAGE 5C(LH, RH)


STAGE 2C, 3C& 4C(LH, RH)

STAGE 6C(LH, RH)

MPTD-3-0224

MM-M05.01

Rev.001

STAGE 7C(LH, RH)

STAGE 1C(LH, RH)

FIGURE 2-25
Main Turbine
Mitsubishi

LP1/LP2 TURBINE BLADING SEAL ARRANGEMENT

2-58

Chapter 2
GEN. SIDE

GOV. SIDE

27

10

D R
N SE
LA N
G DE
TO O N
C

19

10

13

27

19

T
C OG
O
N LA
D N
EN D
SE
R

General

14

24

15

"E"
D

C-C

"H"

19

10

HORIZ. JOINT

28

C
p

24

28

FROM GLAND STEAM


SUPPLY HEADER

FROM GLAND STEAM


SUPPLY HEADER

12
11

20

D-D

1
7

"F"
3

HORIZ. JOINT

5
9

A
18

A-A

G-G
1

25

26

20

23
8
1

7
5

Rev.001

PRESSURE
SUPPLY SLOT

20

21

22

27
16

MM-M05.01

28

22
21

HORIZ. JOINT

17
20

B-B

13

DETAIL "H"
DETAIL "F"

DETAIL "E"

24

MPTD-3-0225

FIGURE 2-26
Main Turbine
Mitsubishi

TYPICAL TURBINE SHAFT GLAND SEALING ARRANGEMENT


2-59

Chapter 2

11

12

25

25

11

19

6
22

12
C

2
18

20 21

13

ROTATION

General

ROTATION

10
23
14
1
5

26

14

26

14

24

26
B

4
3

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28

CARRIER RING (LOWER HALF)


CARRIER RING (UPPER HALF)
BEARING PAD
PIVOT
INNER LINER
OUTER LINER
OUTER LINER (OIL INLET)
DOWEL PIN
HORIZONTAL JOINT BOLT
SPRING WASHER
PAD STOPPER
PLUG
OIL DISTRIBUTOR
STOPPER PIN
END COVER
END COVER SCREW
LOCK WIRE
PARALLEL PIN
HEX. SOCKET HEAD BOLT
SHIM
SPACER
SPRING
TEMPORARY BOLT
PLUG
SPLIT RING
THERMOCOUPLE OPENING
THERMOCOUPLE LEAD SUPPORT
THERMOCOUPLE LEAD SUPPORT

MPTD-3-0226

MM-M05.01

Rev.001

21
7
20 19

17 16

15

VIEW A

15

18

OIL SUPPLY HOLE

SECTION B-B
28

27

SECTION C-C
26

26

DETAIL E
2

DETAIL H
15

28

DETAIL G

28

12 11

24

26

27

26

3
22

SECTION D-D
27

No.3 PAD

No.4 PAD

VIEW G
FIGURE 2-27

Main Turbine
Mitsubishi

VIEW F

SECTIONAL VIEW OF BEARING NOS. 1 & 2

2-60

Chapter 2

General

B
4

8
7
21

15

10

A
9
F
4

19
F

6
VIEW E

SECTION C-C

E
B

11

14

23

12

16

25

21

26

24

22

4
17

1
C

SECTION F-F

18
DETAIL D

25

24

17

12

17
E
3
21

Rev.001

20
13

E
B

MM-M05.01

SECTION A-A

11

2
11
12

23

SECTION B-B

19

20
SECTION E-E

FIGURE 2-28
Main Turbine
Mitsubishi

21

SECTIONAL VIEW OF BEARING NOS. 3, 4 & 5

2-61

Chapter 2

General

33

5
19
18

34

DETAIL H
17
30

28

10

24

25

29

31
32

13

VIEW F

DETAIL E

27

GEN. END

37

10

GOV. END

12
25

1
1

14
20
24

15

5
6

29

15

27
ROTATION

28

4
22

LUBE OIL
OUTLET

35
16

36

R
O
TA

2G

O
V

2G

O
V

TI
O
N

23
G
O
V
G
O
V

36

11

MM-M05.01

Rev.001

21

26
9

22

LU
BE

13
O

IL

13

E
IN

LE
T

37

VIEW G

26

SECTION A-A
MPTD-3-0228

Main Turbine
Mitsubishi

SECTION B-B
FIGURE 2-29

SECTIONAL VIEW OF BEARING NO. 6

2-62

24

X
"E"

25

OIL
IN

OIL
IN

Chapter 2

General

10

22

20

"E"

26

13
2

#2-2

#2-1

#1-1
27

ROTATION

#2-5

#1-8

#2-7

#1-3
G
IN INE
AR L
BE PLIT
S

#2-4

ROTATION

#2-8
SP BEA
L I T RI
LINNG
E

#2-3

#1-2

#1-7

#2-6

#1-6

#1-4

D
D

#1-5

5
1

23
16

11

21
2

5
19

12

15

B-B

19

17

A-A

OIL
OUT

18

X-X
15

8
2

4
5

MM-M05.01

Rev.001

22 23

VIEW "E"

20 21

20 21 22 23

D-D

C-C

11

MPTD-3-0229

FIGURE 2-30
Main Turbine
Mitsubishi

THRUST BEARING ASSEMBLY

2-63

Chapter 2

GEN. SIDE

General

GOV. SIDE

11
10

16
17

ROTATION

PEDESTAL BASE

HP-IP ROTOR

LP1 ROTOR

NO.2 BEARING

NO.3 BEARING

SPACER

COUPLING BOLT & NUT

COUPLING GUARD

COUPLING COOLING
OIL SPRAY LINE

10

HP-IP OUTER CASING

11

LP1 OUTER CASING

12

LP1 GLAND STEAM


EXHAUST PIPE

13

BASE PLATE

14
15
16

OIL RETAINING RING

17

THERMAL SHIELD

18

INSPECTION COVER

19

19

MM-M05.01

Rev.001

MPTD-3-0231

FIGURE 2-31
Main Turbine
Mitsubishi

HP-IP TO LP1 COUPLING

2-64

Chapter 2

General

10

11

PEDESTAL BASE

LP1 ROTOR

LP2 ROTOR

NO.4 BEARING

NO.5 BEARING

SPACER

COUPLING BOLT & NUT

COUPLING GUARD

COUPLING COOLING
OIL SPRAY LINE

10

LP1 OUTER CASING

11

LP2 OUTER CASING

12

LP1 GLAND STEAM


EXHAUST PIPE

13

LP2 GLAND STEAM


EXHAUST PIPE

14

PEDESTAL COVER

15

PEDESTAL COVER

16

BASE PLATE

17

INSPECTION COVER

18

TRANSVERSE ANCHOR BOLT

19

OIL RETAINING RING

13
12

MM-M05.01

Rev.001

MPTD-3-0232

FIGURE 2-32
Main Turbine
Mitsubishi

LP1 TO LP2 COUPLING

2-65

Chapter 2

General

PEDESTAL BASE

LP2 ROTOR

GENERATOR ROTOR

NO.6 BEARING

SPACER GEAR

COUPLING BOLT & NUT

COUPLING GUARD

COUPLING COOLING
OIL SPRAY LINE

ROTOR GROUNDING DEVICE

10

LP2 OUTER CASING

11

LP2 GLAND STEAM


EXHAUST PIPE

12

NUT COVER

13

BASE PLATE

14
15

PEDESTAL COVER (COUPLING)

16
OIL RETAINING RING

18

INSPECTION COVER

11

Rev.001
MM-M05.01

17

MPTD-3-0233

FIGURE 2-33
Main Turbine
Mitsubishi

LP2 TO GENERATOR COUPLING

2-66

General

MM-M05.01

Rev.001

Chapter 2

FIGURE 2-34
Main Turbine
Mitsubishi

MAIN STOP VALVE AND GOVERNING VALVE ASSEMBLY

2-67

Chapter 2

General

SPRING HOUSING

BONNET

REHEAT STOP VALVE

SUPPORT
INTERCEPTOR VALVE

STEM LEAKOFF
SPRING HOUSING

STEAM OUTLET
( TO IP TURBINE )

Rev.001

RSV ACTUATOR

MM-M05.01

MPTD-3-0235

FIGURE 2-35
Main Turbine
Mitsubishi

INTERCEPTOR VALVE AND REHEAT STOP VALVE ASSEMBLY

2-68

General

MM-M05.01

Rev.001

Chapter 2

FIGURE 2-36
Main Turbine
Mitsubishi

MAIN TURBINE TURNING GEAR

2-69

Chapter 2
2
GEN. SIDE

General

13

GOV. SIDE

6
TO EARTH TERMINAL

11

A
9

7
4

6
1

13
8

TO EARTH
TERMINAL

B
10 11 12

ROTATION

10
9

60

GENERATOR ROTOR
NO.4 BEARING PEDESTAL COVER
PEDESTAL END COVER
OIL BAFFLE
LP CASING BASE PLATE
BRACKET
SUPPORT
SPRING
BRUSH
BOLT
U NUT
WASHER
FITTING BOLT
EARTH TERMINAL
LP CASING

12

C
L OF TURBINE

C
L OF TURBINE

VIEW A

GEN. SIDE

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

11

12

GOV. SIDE

11

FROM GROUNDING
DEVICE

7
C
L OF TURBINE

15

14

10 12

15

14

EARTH NET

SECTION B-B

SECTION D-D

MM-M05.01

Rev.001

ARRANGEMENT OF EARTH TERMINAL

MPTD-3-0237

Main Turbine
Mitsubishi

FIGURE 2-37

ROTOR GROUNDING DEVICE

2-70

Chapter-2

General

MM-M05.01

Rev.001

A-A

LP OUTER CASING

GUARD

DIAPHRAGM PRESSURE DISC

DIAPHRAGM

BOLT

MPTD-4-0238

FIGURE 2-38
Main Turbine
Mitsubishi

BREAKABLE DIAPHRAGM
2-71

Chapter 2

DOOR

STAIR WAY

TERMINAL BOX &


PRESS. SWITCH BOX

General

TERMINAL BOX &


PRESS. SWITCH BOX

TERMINAL BOX

TURBINE
ENCLOSURE

TURBINE
ENCLOSURE

DOOR

TERMINAL BOX &


PRESS. SWITCH BOX

DOOR

DOOR
STAIR WAY

STAIR WAY

"B"

DOOR

VIEW "A"

TERMINAL BOX

TURBINE
ENCLOSURE

VIEW "C"

TERMINAL BOX &


PRESS. SWITCH BOX

"A"
GEN. SIDE

GOV. SIDE

TURBINE ENCLOSURE

"C"

"D"

ROTATION

OPERATING FLOOR

VIEW "B"
TURBINE ENCLOSURE

DOOR

DOOR
SOUNDPROOF
INSULATION

TURBINE ENCLOSURE

TURBINE ENCLOSURE

SOUNDPROOF
INSULATION

WELD

DOOR FOR TRIP LEVER

WELD

OPERATING FLOOR

OPERATING FLOOR

OPERATING FLOOR

Rev.001
MM-M05.01

TEST DOOR

VIEW "D"

GUIDE BOLT
FITTING BOLT

DOOR

DOOR

CHANNEL

E-E

CHANNEL

F-F

G-G

MPTD-3-0239

FIGURE 2-39
Main Turbine
Mitsubishi

ARRANGEMENT OF TURBINE ENCLOSURE

2-72

Chapter-3

Specifications

C h a p t er

3 Specifications
TABLE 3-1

MAIN TURBINE

Subject

Specifications

Equipment number
HP-IP Turbine

03MAA31AE1

LP1 Turbine

03MAC11AE1

LP2 Turbine

03MAC11AE2

Quantity
Turbine

Steam
Conditions

Blading

1
Model

Tandem Compound Quadruple Exhaust


Condensing Reheat

Type

TC4F-35.4

Speed

3000 rpm

Direction of Rotation

Clockwise (viewed from Gov End)

Rated Output

865 900 kW

Inlet Pressure

24.5 MPa(a)

@ MSV inlet

Inlet Temperature

538C

@ MSV inlet

Hot reheat Pressure

4.7 MPa(a)

@ RSV inlet

Hot reheat Temperature

566C

@ RSV inlet

Exhaust Pressure

0.0079 MPa(a)

@ Condenser top

No. of Extractions

HP turbine

1 x 1 Row of Rateau
1 x 9 Rows of Reaction

IP turbine

1 x 8 Rows of Reaction

LP1/LP2 turbine

2 x 7 Rows of Reaction

Last row LP turbine

Critical speed

Blade Height

900 mm (35.4 inches)

Tip diameter

3537.6 mm

HP-IP
LP1

1700~1750 rpm
st

1150~1550 rpm

nd

2400~2650 rpm

st

1300~1500 rpm

nd

2400~2550 rpm

1
2

LP2

1
2

MM-M05.01

Rev.001

Main valves

Main Turbine
Mitsubishi

MSV

Horizontal plug

GV

Vertical plug

RSV

Horizontal swing check

ICV

Vertical plug

3-1

Chapter-3

Specifications

Continued

TABLE 3-1

MAIN TURBINE

Subject

MM-M05.01

Rev.001

Weights

Main Turbine
Mitsubishi

Specifications

HP-IP Rotor

42.65 ton

HP-IP Outer Casing Cover (including inlet


sleeve, main steam inlet pipe, balance pipes,
insulation, lifting tool)

65.0 ton

HP-IP Inner Casing Cover

9.24 ton

HP-IP Inner Casing Base

10.25 ton

No.1 HP Stationary Blade Ring with stationary


blades (lower + upper)

1.19 ton

No.2 HP Stationary Blade Ring with stationary


blades (lower + upper)

1.71 ton

IP Blade Ring Cover

6.71 ton

IP Blade Ring Base

5.32 ton

No.1 IP Stationary Blade Ring with stationary


blades (lower + upper)

2.44 ton

No.2 IP Stationary Blade Ring with stationary


blades (lower + upper)

3.59 ton

No.3 IP Stationary Blade Ring with stationary


blades (lower + upper)

1.72 ton

No.4 IP Stationary Blade Ring with stationary


blades (lower + upper)

2.98 ton

No.1 Dummy Ring (lower + upper)

11.25 ton

No.2 Dummy Ring (lower + upper)

1.19 ton

HP Pedestal

6.55 ton

LP1 Rotor

61.46 ton

LP2 Rotor

60.86 ton

LP1/LP2 Outer Casing Cover (including flow


guide ring, breakable diaphragm, lifting tool)

38.4 ton

LP1/LP2 Inner Casing Cover

19.51 ton

LP1/LP2 Inner Casing Base

18.54 ton

LP1/LP2 Steam Chamber (Upper half)

3.73 ton

LP1/LP2 Steam Chamber (Lower half)

3.96 ton

LP1/LP2 Blade Ring (upper + lower)

2.38 ton

LP1/LP2 Flow Guide (upper + lower)

3.67 ton

Breakable Diaphragm Assembly

0.5 ton

MSV/GV Set

35.6 ton

RSV/ICV Set

29.8 ton

HP-IP Rotor Lifting Tool

4.9 ton

LP Rotor Lifting Tool

4.9 ton

3-2

Chapter 4

Preventive Maintenance

C h a p t er

4 Preventive Maintenance
Preventive maintenance is carried out to avoid or minimize the possibility of failure or
deterioration of equipment performance. This requires a constant effort from
maintenance staff to ensure that the Unit is available on demand.
There are two categories of preventive maintenance, Routine Maintenance and Annual
Outage Maintenance. Routine maintenance helps to reduce the possibility of outage
and hence the downtime of machinery. Annual outage maintenance is required to
maintain the internal components of the installed equipment.
Though vendor/manufacturers recommendations provide a good basis for the
provision of a preventive maintenance schedule, the frequency and other details should
be updated from time to time based on the practical experience and actual field
feedback gathered through inspection and normal operation of the equipment/plant.
Consideration of these site related specific issues will make the preventive
maintenance more effective.

4.1

Prerequisites
The necessary prerequisites for the preventive maintenance of the main turbine
are as follows:

4.1.1 Scheduling

MM-M05.01

Rev.001

Scheduling is the first activity in the preparation of a preventive


maintenance program, the schedule is to include planning to attend all
operating equipment on a fixed regular basis. Initially, schedules will be
prepared based on vendor/manufacturers generic instructions, the
schedules will, however, be updated (frequency, nature of inspection,
etc.) as site-specific data becomes available. Preventive maintenance
is to be co-ordinated with other concerned departments. In the case of
a major scheduled outage, maintenance personnel and other
concerned departments should jointly produce a plan of activities, well
in advance, to decide the inspection activities and other logistics (such
as the availability and supply of required equipment, spare parts, and
tools, etc.). The schedule should clearly identify the critical path.
Priority is to be assigned to specific tasks that also involve parallel
activities to reduce the equipment downtime and to complete the work
within the scheduled time.

Main Turbine
Mitsubishi

4-1

Chapter 4

Preventive Maintenance

4.1.2 Departmental Interface/Notification


Departmental communication is essential and interfacing between
departments is to be maintained to avoid any lack of communication
that may arise and adversely affect routine or annual outage
maintenance work. Prior to commencing preventive maintenance all
concerned persons (shift supervisor, operators, etc.) are to be made
aware of the schedule and the nature of the activities that are to take
place. If it becomes clear that there is a problem or a conflict of
interests in the schedule (e.g. the maintenance schedule interferes with
another groups work), this is to be resolved by mutual agreement
between the parties involved.

4.1.3 Isolation of Equipment


It is important that isolations are agreed and valid clearances and work
permits are obtained before any maintenance work is performed. The
isolation boundaries of the particular equipment to be taken under
maintenance are to be clearly identified.
In the case of an electrical isolation the power supply shall be
disconnected and/or the fuses removed. In the case of mechanical
isolation, the valves or other mechanical means of isolation, at the
isolation boundaries are to be closed / if possible locked closed and a
Do not operate Tag to be installed. The system within the isolation
boundaries is to be depressurized.

4.1.4 Safety Precautions


Before the commencement of any maintenance work, the person in
charge of the work site is to perform a risk assessment and method
statement for the safe execution of the job scope activities, described
within the work permit. Risk assessment includes identifying,
recognizing and understanding the potential hazards associated with
the work. The method statement is to illustrate the safe working
practices in accordance with the safety manual and the manufacturers
instruction manual to prevent personal injury and/or equipment
damage.

MM-M05.01

Rev.001

Prior to the commencement of actual work, the person carrying out the
work is to make a safety check based on the above method statement
and also use his own judgment to ensure that the equipment and the
prevailing working conditions are safe. During maintenance work,
every employee should follow the safe working procedures detailed in
the method statement.

Main Turbine
Mitsubishi

4-2

Chapter 4

Preventive Maintenance

4.1.5 Visual Inspection


Due to its construction, and its function, frequent visual inspections of
the main turbine can produce evidence of defects before they occur.
Daily patrols of the main turbine and associated equipment by a
conscientious operator or a maintainer can quite often enable early
action to be taken to rectify a situation which, if not observed and
corrected, could result in a serious failure and a subsequent forced
outage.
Daily patrols are therefore recommended during which time the
operator or the maintainer should make himself familiar with all
pressures, temperatures and levels as recorded on the installed
instruments, and be familiar with the sounds of the equipment in
operation.

MM-M05.01

Rev.001

Any deviation from normal, with regard to pressure, temperatures,


noise or vibration levels should alert the operator or the maintainer, to
the necessity of reporting the situation to the Shift Charge Engineer.

Main Turbine
Mitsubishi

4-3

Chapter 4

4.2

Preventive Maintenance

Routine Maintenance
The purpose of routine maintenance is the implementation of the preventive
maintenance program on a day-to-day basis through a planned and correctly
executed inspection. The routine maintenance activities are very important in
that if they are properly carried out, they will enhance equipment reliability. As a
result, good routine maintenance activities may help in cost reduction in the long
run through minimization of equipment downtime.
Cleaning is an important and necessary maintenance activity to prevent the
ingress of foreign material. (Summarized major routine activities are shown in
Table 4-1).

4.2.1 Preparation
a)

Parts, Tools and Equipment


It is important to prepare the necessary parts, tools and
equipment before commencing actual work. Routine
maintenance generally requires a standard mechanical toolkit,
consumables, cleaning materials, etc. Any shortages of these
items will affect the maintenance activity and may delay the
schedule. Personal Protective Equipment (PPE) is necessary for
maintenance staff at all times.
Upon completion of work, all tools and equipment should be
serviced and stored correctly to ensure availability for further use.

b)

Documentation

MM-M05.01

Rev.001

Documentation is an important part of any maintenance duty. All


findings should be noted on a comprehensive log sheet, reporting
all aspects of the equipment observed during the routine
inspection. The data recorded in these documents may become
most useful in determining the root cause of equipment failure
found during annual outage/corrective maintenance work. Any
abnormalities, if observed, are to be immediately communicated
to the concerned department/personnel for rectification and are
to be detailed in the report.

Main Turbine
Mitsubishi

4-4

Chapter 4

Preventive Maintenance

4.2.2 Inspection and Maintenance

Take care near rotating machinery. Hands and clothing can be


drawn into machinery. Always make sure that all guards are in
place before starting any rotating machinery.

Beware of any noise inside the turbine enclosure and near the
steam admission valves. There can be invisible superheat
steam leakage which can cause burn injuries.

Extreme care must be taken while inspecting a hot steam


turbine. Hands and clothing can be burned by contact with the
steam turbine parts.

CAUTION
Wear ear protection when near a running machine.

CAUTION
Take utmost care while performing inspection near the main oil
tank, oil lines and oil pumps. Oil-soaked floor will be extremely
slippery and susceptible for injuries.

Rev.001

A daily check should be carried out to check for abnormal noises and
vibration, and to note any trend deterioration. These values should be
correlated with those for the operational parameters, as this may help to
identify the source of a potential problem.

MM-M05.01

The sliding surfaces around and under the turbine bearing pedestals
should be maintained in good condition. Regular lubrication is required
to ensure that the pedestals and turbine casings can move freely when
the turbine expands or contracts.

Main Turbine
Mitsubishi

4-5

Chapter 4

Preventive Maintenance

Replenish anti-seize compound to the sliding surfaces under the turbine


casing supports and the HP pedestal as required.
The routine maintenance checks on the turbine protection devices are
operational functions and should be carried out on a regular basis to
check the integrity of the devices.
The condition of the turbine turning gear should be monitored diligently,
and trended. It has a major role in maintaining the integrity of the turbine,
and it is important that unscheduled outages are avoided.
The turbine steam admission valves should be checked daily for
abnormal noise or vibration, and for steam leakage from the valve stem
or body to bonnet joint.
A valve stem freedom test should be performed weekly with the turbine
at 35~60% or 72 ~ 75% load on the following valves:

Main stop valves

Governing valves

Reheat stop valves

Interceptor valves

Extraction check valves.

The following protective device function tests should be performed on


load each month to check alarm and trip values:

Overspeed protection test

Lubricating oil pressure low trip test.

A thrust wear trip test should be carried out once or twice a year
off-load either on turning gear or at complete rest.
A turbine solenoid trip test should be performed once or twice a year,
off-load on turning gear or at complete rest.

Auxiliary oil pump

Turning oil pump

Emergency oil pump.

MM-M05.01

Rev.001

An oil pump auto start test should be performed monthly to check the
setting value of the following pumps:

Main Turbine
Mitsubishi

4-6

Chapter 4

Preventive Maintenance

Weekly lube oil system checks:

Oil level in the main oil tank and oil purifier

Oil leakage from the oil piping and main oil tank

Vacuum inside the main oil tank

Condition of vapor extractor fan

Lube oil temperature control valve functioning

Differential pressure across oil filters

Return oil strainer cleanliness.

Weekly E/H System check:

Oil level in the E/H oil tank

Differential pressure across filters

E/H oil temperature control valve functioning.

Each month carry out the following analyses:


E/H oil (millipore and chemical)

Lube oil, sampling from the main oil tank bottom and the oil
purifier/conditioner outlet.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

4-7

Chapter 4 Preventive Maintenance

TABLE 4-1
No.
1

Description
Casing and Rotor

Major Check Item

ROUTINE MAINTENANCE CHECKLIST

Check Method

Check Reference

Action to be Taken
(if beyond acceptable
limit)

Remarks

Abnormal sound, noise


and vibrations

Audible, visual and


installed instruments

All to be normal

Report to supervisor

Turbine supervisory
instruments

Installed instruments

All to be within normal values

Report to supervisor

Vibration (on shaft)

Installed instruments

(Alarm)
(Trip)

Report to supervisor

Double amplitude

Differential expansion

Installed instruments

Limits:
Abnormal High Trip (Rotor
long):
> +20 mm

Report to supervisor

Differential expansion
readings measured near No. 8
bearing. Manual Trip
Recommended.

125 m
250 m

Recommended
Maintenance
Frequency

Daily

High Alarm: > +18 mm

Governing valve position

Installed instruments

Commensurate with load

Report to supervisor

Eccentricity

Installed instruments

Normal < 50 m
Alarm > 75 m

Report to supervisor

Rotor position

Installed instruments

Limit:

Report to supervisor

Steam pressure and


temperature at each
turbine inlet

Installed instruments

Steam leakage from all


sections

Visual, audible

Alarm:

> 0.9 mm

Alarm:

> 1.0 mm

Commensurate with load

During turbine rolling (0-600


rpm)

During every
turbine rolling

Daily

Report to supervisor
Daily

No leakage

Report to supervisor

Pay special attention to casing


flange and each gland

Daily

MM-M05.01

Rev.001

Low Alarm: < 1.5 mm

Main Turbine
Mitsubishi

4-8

Chapter 4 Preventive Maintenance

Continued from previous page


TABLE 4-1

No.
1

Description
Casing and Rotor
(Continued.)

Major Check Item


Turbine exhaust
temperature

Check Method
Installed instruments

Pedestal center keys


and base plate

Check lubrication

Bearing

Bearing supply oil pressure Installed instruments

Bearing metal temperature

MM-M05.01

Main Turbine
Mitsubishi

Installed instruments

Check Reference
Limits:

Action to be Taken
(if beyond acceptable limit)
Report to supervisor

Remarks

Alarm: > 80C

Exhaust hood spray control


valve set to open at 70C.

Trip : > 120C

Manual Trip Recommended.

Lubricant to be evident

Apply lubricant as required

To be within normal limits

Report to supervisor
Replace over lube oil
strainers

Limits (Alarm):
Thrust bearing : > 99C
Journal bearing: > 107C

No leakage

Recommended
Maintenance
Frequency

Daily

Every 3 to 6
months
Daily

Check lube oil flow and


temperature
Shutdown turbine and
inspect bearings and check
alignment

Oil leakage from oil


retaining rings and
pedestals

Visual

Bearing drain oil flow


through the sight glass

Visual

Flow normal

Check and adjust oil


pressure

Visual and installed


instruments

Normal operation

Report to supervisor

Gland steam supply


pressure

Installed instruments

Between 0.02 to 0.03 MPa

Adjust control values

Leakage in the vacuum


side of the gland
condenser

Flame or smoke test

Gland Steam System Operation of gland steam


controller and valves

Rev.001

Visual

ROUTINE MAINTENANCE CHECKLIST

Clean the area


Adjust main oil tank vacuum
Daily

Low Alarm: < 0.02 MPa


No leakage

Tighten leaking joints

4-9

Chapter 4 Preventive Maintenance

Continued from previous page


TABLE 4-1

No.
4

Description
Gland Steam System
(cont.)

Major Check Item

ROUTINE MAINTENANCE CHECKLIST

Check Method

Check Reference

Action to be Taken
(if beyond acceptable limit)

Remarks

Recommended
Maintenance
Frequency

Operation of drain traps

Visual

Proper operation of traps Repair or replace defective


trap and clean the strainer

LP turbine gland steam


temperature

Installed
instruments

Temperature between
120C and 180C

Adjust temperature control at


150C

Daily

No oil leakage

Visual

No leakage

Identify and rectify source of


oil leakage

Daily

Turning gear lever position

Visual

Correct Engage /
Disengage position

Report to supervisor

Freedom of all valve stems

Movement should be
free

Report to supervisor

Governing valve

Stem freedom
test

Reheat stop valve

Visual

No sticking

Visual

Movement should be
free

Turning gear

Main stop valve

Interceptor valve

Condition of valve during


operation

Report to supervisor

Weekly

Daily
To be carried out at
following load range
35~60% or 72~75% load
Pay special attention to
valve sticking

Weekly

Daily

No sticking
Valve closing during turbine
tripping

Visual

No sticking

Report to supervisor

Steam leakage from valve


stem and bonnet

Visual and
audible

No leakage

Report to supervisor

Abnormal noise and vibration

Visual and
audible

No abnormality

Report to supervisor

Installed
instruments

At every turbine
trip

MM-M05.01

Rev.001

Daily

Main Turbine
Mitsubishi

4-10

Chapter 4 Preventive Maintenance

Continued from previous page


TABLE 4-1
No.
7

Description

Major Check Item

ROUTINE MAINTENANCE CHECKLIST

Check Method
Visual

Check Reference
No sticking

Extraction non-return
valve

Valve stem freedom test

Protective Devices

Lubricating oil pressure low


trip

Follow prescribed
procedures

Alarm: < 0.075 MPa


Trip : < 0.05 MPa

Operations would normally


supervise this procedure

Vacuum low trip

Follow prescribed
procedures

Alarm: - 84.6 kPa


Trip : - 73.3 kPa

Operations would normally


supervise this procedure

MOST, EOST

MOST: 110 1% speed

Operations would normally


supervise this procedure

Report to supervisor

Tank oil level

Visual

Add or remove oil as


High Alarm: NOL >+150mm required
Low Alarm : NOL >150mm

Oil leakage from the oil


piping, oil cooler and around
the oil reservoir

Visual

No leakage

Advise supervisor then


attempt to tighten leaking
joints

Vacuum within the oil tank

Installed
instruments

Between -10 to -15 mmwc

Adjust damper and increase


vacuum

Rev.001

Monthly

No abnormality

Changeover to standby fan


and advise supervisor

Daily

Daily

Daily

MM-M05.01

Audible, visual
and touch

Vacuum Unloader
operates at < 81.3 kPa and
released at > 85.4 kPa

At NOL

Check for open man hole


door and air leakage
Abnormal sound, noise,
vibration and temperature of
vapor extraction fan bearing

Recommended
Maintenance
Frequency
Weekly

EOST: 111% speed


Main oil tank
Lube oil cooler
Lube oil piping

Remarks

Installed
instruments

Overspeed trip test

Action to be Taken
(if beyond acceptable limit)

Main Turbine
Mitsubishi

4-11

Chapter 4 Preventive Maintenance

Continued from previous page


TABLE 4-1
No.
9

Description
Main oil tank
Lube oil cooler
Lube oil piping
(Continued)

Major Check Item


Lube oil properties

ROUTINE MAINTENANCE CHECKLIST

Check Method
Sample analysis
in laboratory

Lube oil temperature (after oil Installed


cooler)
instruments

Check Reference
Acceptable condition

Visual

Remarks

High Alarm:
At Normal operation:> 50C
> 40C

Satisfactory control

Recommended
Maintenance
Frequency

Operate oil purifier


Replace oil during next
available shutdown

At Turning :
Oil temperature control valve

Action to be Taken
(if beyond acceptable
limit)

Daily

Check for high bearing oil


drain temperature and/or
performance of oil cooler

Daily

Make necessary
adjustment

Monthly

Advise supervisor
Visual

No leakage

Advise supervisor, then


attempt to tighten leaking
joint

Lube oil filter

Installed
instruments

Differential pressure High


Alarm: >0.015 MPa

Clean the filter

Control oil filter

Installed
instruments

Differential pressure High


Alarm: >0.69 MPa

Clean the filter

Check and clean the main oil


tank return strainer

Visual

No debris

Remove any accumulated


debris

Auto start test of oil pumps

Under operators
supervision using
Test Block

Set point
AOP: < 0.75 MPa
TOP: < 0.075 MPa
EOP: < 0.065 MPa

Reset and recheck

Daily

Daily
Daily
At shutdown
EOP set point should be
slightly lower than low
lube oil pressure trip set
point

Monthly

MM-M05.01

Rev.001

Leakage from the oil cooler

Main Turbine
Mitsubishi

4-12

Chapter 4 Preventive Maintenance

4.3

Outage Maintenance
The purpose of routine outage maintenance is the implementation of a
preventive maintenance program on a yearly basis according to a planned and
correctly executed maintenance work program accompanying necessary
inspections. Such outage maintenance activities are very important because
such maintenance will extend the service life and improve the reliability of the
steam turbine, if properly performed.
Major activities related to annual outage maintenance are as follows:
(Summarized major activities for annual outage maintenance are also shown in
Table 4-3).

4.3.1 Preparation
a)

Parts, Tools and Equipment


Refer to Subsection 4.2.1 a), Parts, Tools and Equipment.
It is necessary to identify the spare parts required.
Annual outage will, in certain cases, require the use of material
handling equipment.
Return unused spare parts for correct storage, and re-order used
spare parts.

b)

Documentation
Refer to Subsection 4.2.1 b), Documentation.
Records are to be maintained to record information on spares
and consumables used. These records will be used for future
reference and spare parts replenishment.
On completion of annual outage maintenance work, the steam
turbine is monitored for correct operation and maintenance data
logging. This will help to determine the correct intervals of
preventive maintenance activities to ensure optimum plant
availability. The correct recording of the findings during
inspection will provide a valuable document for future reference.

4.3.2 Inspection and Maintenance

MM-M05.01

Rev.001

The first overhaul inspection provides an opportunity to detect initial


failures or abnormalities at their early stage and permits the
implementation of countermeasures to prevent their further progress. It
also provides information to decide the frequency of inspections,
routine and preventive maintenance, and overhauls.
It is therefore recommended that the first overhaul is within one year
after the start of commercial operation.
Main Turbine
Mitsubishi

4-13

Chapter 4 Preventive Maintenance

After the first overhaul, perform the overhaul as shown in Table 4.2
which shows the standard intervals of inspections for respective parts
and equipment, and how they are classified.
However, it is recommended that the maintenance program is arranged
so that all equipment can be inspected at least once within 4 years.
The major activities involved in the outage maintenance are detailed
below. Assembly and reassembly of the various parts is detailed in
Chapter 5.

Preparation
1

Shutdown the turbine and when it has come to rest start the
jacking oil pump and the turning gear. Continue operation of the
lubricating oil pumps. When the highest first stage metal
temperature is below 170C, the turning gear can be stopped.
However, dependent on the work content and the intended
duration of the outage, the actual stoppage of the turning gear,
lubricating oil pump, seal oil pump, etc. is a joint operational and
maintenance department decision.

Remove lagging and thermal insulation to provide access to the


turbine casing horizontal joints. Start removing insulation
materials from the low temperature zones.

CAUTION
Wear proper goggles and face masks when working on the
insulation. Insulation material is harmful to the respiratory
system.

Inspection of HP-IP and LP Turbines


Note
Equipment to be inspected is detailed in this section. For

MM-M05.01

Rev.001

disassembly and re-assembly refer to Chapter 5.

Main Turbine
Mitsubishi

Remove the IP to LP turbines crossover pipe and visually check


for deformation and cracking within the pipe and the expansion
joints. Check for erosion on the inside surfaces.

Remove the LP1 and LP2 rotor Gov End and Gen End upper half
gland casings. Inspect the gland seal rings and seal strips for
damage or erosion.

4-14

Chapter 4 Preventive Maintenance

Visually check for deformation and leakage erosion of the


horizontal joint flanges.

Check the welded portion of the internal stays and ribs and
perform a dye penetrant test on the welded joints.

Check for erosion on the inside surface of the upper and


lower outer casings.

Disassemble the LP1 and LP2 inner casing covers and visually
check for deformation and leakage from the horizontal joint
flanges. Remove any scale from the stationary blades and
perform a dye penetrant test to check for cracks. Any
countermeasure for damage should be decided by the inspection
results.

Following the requirement of the mechanical maintenance manual


M-05.02, Steam Admission Valves, remove the main steam inlet
pipework to the HP turbine.

Disconnect the flanges at the hot reheat steam inlet piping to the
IP turbine.

Remove the HP-IP rotor Gov End and Gen End upper half outer
gland casings and inspect the gland seal ring segments and seal
strips for wear or damage.

Disassemble the HP-IP outer casing cover and perform the


following checks:

Visually check for deformation and leakage erosion of the


horizontal flange.

Check the outside and inside surfaces of the removed cover


and perform a dye penetrant or magnetic particle test on the
cover internal surfaces.

Check for cracks on pipe nozzles on the outer casing and on


the welded sections of the main steam inlet pipes using dye
penetrant and ultrasonic test procedures.

Test the bolts used in high temperature locations (above 350C),


in the HP-IP casing, main valves, blade rings, dummy rings, etc.
for deterioration, using ultrasonic and dye penetrant tests.

10

Remove the HP-IP rotor inner gland upper casings from both ends
and inspect the gland seal ring segments and seal strips for wear
or damage.

Rev.001
MM-M05.01

Main Turbine
Mitsubishi

Remove the LP1 and LP2 turbine outer casing covers and
perform the following checks:

4-15

MM-M05.01

Rev.001

Chapter 4 Preventive Maintenance

Main Turbine
Mitsubishi

11

Disassemble the upper halves of the inner casing, IP blade ring,


No.1 dummy ring, No.2 dummy ring, thermal shield, HP stationary
blade rings and IP stationary blade rings. Check for deformation
and leakage erosion on the inner casing cover, IP blade ring,
dummy rings, stationary blade rings, thermal shield and horizontal
joints, and perform a dye penetrant test.

12

Visually check for cracking and erosion of the nozzle block and
the nozzles. Perform a dye penetrant test. Check for deterioration
of bolts using ultrasonic and dye penetrant tests. Visually check
for, and measure any wear and deformation on the slip-joint seal
rings and the retaining rings.

13

Remove the upper halves of all turbine bearing pedestals.

14

Remove the coupling cooling oil lines, coupling guards and


coupling bolts from the HP-IP ~ LP1, LP1 ~ LP2 and LP2 ~
generator couplings and perform the following checks:

Remove the toothed spacer from the LP2 ~ generator


coupling and inspect turning gear engaging teeth for any
damage or wear.

Visually inspect the coupling faces and spacer rebates for


burrs, fretting or other surface defects.

Check all coupling alignments and keep a record for


reassembly.

Measure the diameter of the coupling bolts. The design


clearance between the bolt and the reamed hole is 0.06 mm.
If the clearance exceeds 0.10 mm, replace the bolts.

Check visually for any damage to the bolt thread and replace
if damaged.

Perform non-destructive examination (NDE) on the coupling


surfaces, coupling spacers and the coupling bolts and nuts.

15

Disassemble and remove the upper halves of all turbine journal


bearings. Perform a dye penetrant test to check for damage to the
journal bearings. Measure and record oil clearance for all journal
bearings as per the procedure described in the mechanical
maintenance manual M05.04, Turbine Bearings and Thrust
Bearing.

16

Remove the MOP cover to check the impeller and casing seal
rings. Perform a dye penetrant test to check for damage to the
MOP impeller. Inspect the seal rings and wear rings for any
damage or wear.

4-16

Chapter 4 Preventive Maintenance

17

Dismantle the upper half of the thrust bearing case, carrier rings,
liners, etc. Remove and inspect all thrust pads and other internal
components for damage or wear. Check the thrust collar for any
crack, dent, scratch or damage.

18

Remove the upper halves of the steam chamber, LP blade ring


and inner flow guide ring for the LP1 and LP2 turbines and inspect
them for damage or wear.

19

Measure and record rotor deflection for the HP-IP, LP1 and LP2
rotors.

20

Remove the LP1 and LP2 rotors and perform the following
checks:

MM-M05.01

Rev.001

21

Main Turbine
Mitsubishi

Perform a magnetic particle test.

Check for any damage or crack in the shroud, tenons and


blades including the stub of the last row of blades. Perform
dye penetrant and ultrasonic tests.

Visually check for erosion of the stellite shields on the last row
blades and perform a dye penetrant test.

Check for and remove any scale deposits.

Visually check the coupling faces and spigots for any


damage.

Remove the HP-IP rotor and perform the following checks:

Perform a magnetic particle test.

Check for damage and cracking in the shroud, tenons and


blades and carry out dye penetrant and ultrasonic tests.

Check for and remove any deposits of scale.

Visually check the coupling faces and spigots for any


damage.

22

Inspect the turning gear and check the contact between the gears
of the turning gear drive.

23

Remove all lower half inner and outer turbine gland casings and
check the gland seal rings, seal strips, springs, etc. for any wear
or damage.

24

Disassemble and inspect the HP-IP turbine lower half casings


including:

No.1 dummy ring

No.2 dummy ring

4-17

Chapter 4 Preventive Maintenance

25

26

No.1 and No.2 HP stationary blade rings

No.1 ~ No.4 IP stationary blade rings

Thermal shield

Inner casing and IP blade ring (before removal, cut and


separate the impulse chamber drain and pressure sensing
pipes, located outside the outer casing)

Disassemble and inspect the LP1 and LP2 lower half casings
including:

Inner casings

Steam chambers

Blade rings

Inner and exhaust flow guide rings.

Visually check for deformation and damage, and using dye


penetrant test, check for crack, erosion and deterioration of the
inner casing bolts in a similar manner to that used to check the
outer casing bolts.

Inspection of Lubrication and Control Oil System


1

Inspect the tank internally

Check the condition of oil filters

Check all pipe work and pipe supports

Check the tank internal surfaces, clean and repair as


necessary.

Disassemble the oil cooler end frames and the plates. Check the
plates for any damage and scale deposit and repair or clean as
necessary. Inspect and replace any damaged gaskets.

On the electro-hydraulic control system (MT-DEH), servo valves


and on all hydraulic cylinders visually check for:

Rev.001
MM-M05.01

Main Turbine
Mitsubishi

Drain oil from the main oil tank and perform the following checks:

Dump valve

Servo valve

Accumulator

Blockage of the orifice

Looseness and free movement of linkage of hydraulic


cylinders.

Remove and check for any blockage in the E/H oil filters.

Check the emergency trip oil line for any blockage of the orifice.

4-18

Chapter 4 Preventive Maintenance

Disassemble and check the E/H oil cooler tubes for blockage and
cleanliness.

Disassemble and check the E/H oil pump relief valves for any
internal damage and seat contact.

The details of the lubrication and control oil systems are fully explained
in the Turbine Control and Lubrication Oil System operation manual,
OPM - 08 and the respective equipment vendor manuals.

Turbine Reassembly
Note
All parts are to be thoroughly cleaned before reassembly.

Assemble and replace all lower half bearings and confirm that the
contact area between the bearing spherical keys and the housing
exceeds 75% of the total area.

Reassemble the following LP1 and LP2 turbine lower half


sections:

Gland casing

Inner casing

Steam chamber

Blade ring

Inner and exhaust flow guide rings.

Note
Straighten and adjust or replace any seal strip if found
worn or damaged.

When replacing the LP rotors, with reference to the clearance


tables, set the radial and axial clearances and then set the turbine
differential expansion pick-ups.

Note
The LP1 and LP2 rotors should be positioned in their
respective K positions before rotor radial and axial

Rev.001

clearances are measured.

Note

MM-M05.01

The procedure for measuring the turbine gland


clearances is detailed in the mechanical maintenance
manual, M05.03, Gland Steam Condenser System and
GSC Exhaust Fan.

Main Turbine
Mitsubishi

4-19

Chapter 4 Preventive Maintenance

Reassemble the following HP-IP turbine lower internal sections:

Inner casing

Thermal shield

IP blade ring

No.1 dummy ring

No.2 dummy ring

No.1 and No.2 HP stationary blade rings

No.1 ~ No.4 IP stationary blade rings

Inner and outer gland casings.

Note
Straighten and adjust or replace any seal strip if found
worn or damaged.

Note
Re-weld the impulse chamber drain and pressure
sensing pipes cut during disassembly.

When replacing the HP-IP rotor, with reference to the clearance


tables set the radial and axial clearances and then set the shaft
position pick-up.

Note
The HP-IP rotor is to be positioned in the K position
before rotor radial and axial clearances are measured.

Before replacing the upper half sections of the inner casing, steam
chamber and inner flow guide ring for the LP1 and LP2 turbines,
measure the top and bottom clearances between the LP rotor and
the blades and other internal parts (refer to clearance drawings).
Check that there are no foreign materials inside of the casing.

Assemble the upper half sections for the LP1 and LP2 turbines
including:

Rev.001

MM-M05.01

Main Turbine
Mitsubishi

Inner casing

Steam chamber

Blade ring.

Check the top and bottom clearances between the HP-IP turbine
parts and the rotor blade seals etc. (refer to the clearance table).
Check that no foreign materials remain inside the casing.

4-20

Chapter 4 Preventive Maintenance

Assemble the upper half sections for the HP-IP turbine including:

Inner casing

IP blade ring

No.1 dummy ring

No.2 dummy ring

No.1 and No.2 HP stationary blade rings

No.1 ~ No.4 IP stationary blade rings

Thermal shield

Inner gland casing.

10

Check all bolt holes and bolts and the horizontal joint flange faces.
Reassemble the HP-IP, LP1 and LP2 outer casing covers,
including the outer gland seals. Perform non-destructive testing
(NDT) at any suspect areas.

11

Set the thrust bearing ensuring that the clearance between the
thrust collar and the thrust bearing is within the design value of
0.250.38 mm, but try to obtain a clearance of 0.31 mm.

Note
Thrust bearing should be set with the HP-IP rotor at the
K position.

Replace the upper halves of the turbine bearings. Check the oil
clearance in each bearing, as per the procedure indicated in the
mechanical maintenance manual, M-05.04, Turbine Bearings and
Thrust Bearing.

13

Assemble the MOP upper half casing. Ensure that the oil seal ring
and wear ring clearances in the MOP are within design values.
For details of clearance, refer to the mechanical maintenance
manual M05.06, Turbine Main Oil Pump.

14

Align the LP2 ~ generator, LP1 ~ LP2 and LP1 ~ HP-IP couplings
as per the procedure described in the mechanical maintenance
manual M05.05, Turbine Couplings and Alignment.

15

Connect the couplings between the HP-IP to LP1, LP1 to LP2 and
LP2 to generator rotors. Ensure that the coupling bolts and nuts
are installed according to their match marks. Tighten the bolts
according to the procedure and values specified in the mechanical
maintenance manual, M05.05, Turbine Couplings and Alignment.
Replace the coupling guards and the coupling cooling oil lines.

16

Replace the turning gear and check the drive gear backlash. For
details, refer to the mechanical maintenance manual M05.07,
Main Turbine Turning Gear.

MM-M05.01

Rev.001

12

Main Turbine
Mitsubishi

4-21

Chapter 4 Preventive Maintenance

17

Install and calibrate all turbine vibration pick-ups and other


instrumentation pick-ups removed during disassembly.

18

Reassemble the bearing keep for No.1 bearing and all pedestal
covers. Ensure that the clearance/interference between pedestal
covers and spherical seat of the bearings, and the clearance of
the pedestal oil retaining rings are within design. Refer to the
clearance tables in the mechanical maintenance manual M05.04,
Turbine Bearings and Thrust Bearing.

19

Install the IP to LP1/LP2 turbine crossover pipe including the


expansion joints. Set the crossover pipe cold spring values to 50
mm between IP and LP1 turbines and 70 mm between LP1 and
LP2 turbines.

20

Install new gaskets and connect the main steam and reheat steam
pipes with the HP and IP turbine inlet pipes which were
disconnected during disassembly.

Reassembly of Lubrication and Control Oil Systems


1

Reassemble the oil cooler and ensure that all bolts are tightened
properly.

Fill the main oil tank to the normal working level (NWL).

Install a temporary strainer at the inlet to each turbine bearing and


perform flushing of the lube oil system. Check for leakage of oil
and cooling water. Inspect the temporary strainers at frequent
intervals and continue flushing until debris is no longer collected
on the strainers.

Note
The oil purifier should be kept in service during oil
flushing. For details of the oil purifier, refer to the oil
purifier vendor manual.

Adjust the control oil system. Refer to control oil pressure setting
instruction for oil pressure setting, servo-valve adjustment,
pressure switch and limit switch settings, and interlock settings.

Return Unit to Service


Arrange with Operations department to start the turning gear and
check for any rubbing or contact within the turbine. Perform a
turning gear interlock test and check the turning gear amperage.

Adjust and test the turbine protective devices and perform a Unit
interlock test. (Refer to the control oil pressure setting instructions
and the interlock sequence diagram).

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

4-22

Chapter 4 Preventive Maintenance

Re-install the removed thermal insulation. Check for damage and


replace or repair as required. Check security of fastenings.

CAUTION
Wear proper goggles and face masks when working on the
insulation. Insulation material is harmful to the respiratory
system.
4

Arrange with Operations department to run the turbine up to


normal running speed and check the following items:

Control oil pressure setting

Test protective devices

Turbine overspeed trip test

Vibration measurement.

Take readings during initial operation (pressures, temperatures,


etc.) and record.

TABLE 4-2
Class
C

STANDARD INSPECTION PERIODS

Intervals
1 year
(Routine maintenance)

Parts and Equipment Inspected


Condenser
Oil conditioner
Instruments and control valves
Filters of E/H oil system

2 years
(Minor overhaul)

Bearings and turning gear


Shaft alignment
Steam admission valves
Protective devices
Lube oil pumps and lube oil systems
Water pumps and heat exchangers
Miscellaneous for E/H oil system

4 years
(Major overhaul)

Turbine proper
E/H oil system
Piping

MM-M05.01

Rev.001

8 to 10 years
Diagnostic investigation for
aging deterioration

Turbine rotors
Turbine casings
Steam admission valves

Main Turbine
Mitsubishi

4-23

Chapter 4 Preventive Maintenance

TABLE 4-3
No

Description

Steam
Turbine

Valves

Major Check
Item

OUTAGE MAINTENANCE CHECK LIST


Action to be taken

Remark

Interval

Turbine casing

Inspection of inner surface


Deformation check

Turbine rotor

Inspection of blades
Inspection of clearance

Blade ring

Check the condition of each


part

Every 4 years

Dummy ring,
gland

Check the condition of each


part

Every 4 years

Bolts for high


temperature
zone

Deterioration check

Every 4 years

Bearing

Inspection of thrust and


journal bearings

Every 2 years

Turning gear

General inspection

Every 2 years

Overhaul inspection

Every 4 years

Alignment

Coupling alignment check

Every 2 years

MSV

Inspection of valve
components

Every 2 years

E/H oil Pump

Overhaul

Every 4 years

Suction
strainer

Clean and re-use

Every year

GV

Every 4 years
Investigate state of
deterioration

Every 4 years

RSV
ICV
3

E/H Oil
System

Line filter
Return filter

Replace elements

If the return oil pressure


is over 0.29 MPa,
replace elements

Every year

Earth filter

Replace elements

If neutralization value
cannot be kept under
0.3 mg KOH/g, replace
elements

Every 6
months

MM-M05.01

Rev.001

Back up filter

Main Turbine
Mitsubishi

Micro
separator

Clean and re-use

Every year

Polishing filter

Replace elements

Differential
pressure
switch

Replace

Every 4 years

Unloading
valve

Inspect, clean and replace if


necessary

Every 4 years

Check valve

Inspect, clean and replace if


necessary

Every 4 years

Relief valve

Inspect, clean and replace if


necessary

Every 4 years

If differential pressure is
over 0.34 MPa, replace
elements

4-24

Chapter 4 Preventive Maintenance

Continued from previous page

TABLE 4-3
No
3

Description

Major Check
Item

OUTAGE MAINTENANCE CHECK LIST


Action to be taken

Remark

Interval

E/H Oil
System
(Contd)

Oil coolers

Inspect, clean and replace if


necessary

Every 4 years

Stop valve

Inspect, clean and replace if


necessary

Every 4 years

E/H oil
accumulator

Accumulator

Replace piston ring and


sealing parts

Every 4 years

Stop valve

Replace sealing parts

Every 4 years

Hydraulic
cylinder

Replace piston ring and


sealing parts

Every 4 years

Servo valve

Performance test (replace


parts as required by the
result of test)

Every 2 years

Replace filter and sealing


parts

Every 4 years

Filter

Clean and re-use

Every year

Solenoid valve

Replace

Every 4 years

Dump valve

Replace sealing parts

Every 4 years

Solenoid valve

Replace

Every 4 years

Check valve

Replace sealing parts

Every 4 years

Pumps

Disassembly and inspection

Every 2 years

Relief valve

Disassembly and inspection

Every 2 years

Oil tank

Inspection of inner parts

Every 2 years

Oil cooler

Cleaning of cooling plate


surface

Every 2 years

Disassembly and inspection

Every 4 years

Oil conditioner

Cleaning and inspection

Every 1 year

Control valves

Inspection and adjustment

Every 1 year

Instrument

Inspection and adjustment

Every 1 year

Actuator

Stop valve
Check valve
6

Solenoid
block
Lubricating
oil system

Instruments

Piping

Piping

Condition of paint and lining


Deformation of piping

Every 4 years

10

Insulation

Insulation

Inspection and replacement

Every 4 years

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

4-25

Chapter 5

Disassembly and Reassembly

C h a p t er

5 Disassembly and Reassembly


Disassembly and reassembly are the activities to be conducted when internal parts of
the steam turbine are required to be accessed. An important part of the activities is the
preparatory work. This should identify the manpower, spares and tools that may be
required during the maintenance work. A shortfall of any of these may affect the
schedule and the operational status of the plant. The major steps of disassembly and
reassembly are as follows.

5.1

HP-IP Turbine Disassembly and Reassembly


a)

Preparation
If HP-IP turbine disassembly becomes necessary, all associated
equipment must be mechanically and electrically isolated and an
authorized clearance and work permit must be in place prior to the start of
work. The following points must also to be considered when preparing for
disassembly and reassembly:

Have all necessary drawings (assembly drawings, sectional drawings,


part details, etc.) and documents (log sheets, field record book, etc.)
ready prior to start of work.

Prepare the necessary handling facilities (crane facilities, temporary


supports etc.) to remove and store the various parts of the steam
turbine.

Take care to protect the turbine operating floor during steam turbine
overhaul. Place the steam turbine components and other materials
on a protective sheet such as aluminium, plywood or gasket spread
on the turbine floor for this purpose.

Co-ordinate with the Instrument and Control (I&C) Department to


remove all the attached instrumentation before starting disassembly
work.

Rev.001

Special tools are listed in Appendix C.

MM-M05.01

Do not stand below the lifted turbine parts. There can be


danger of an accident due to components falling down.

Main Turbine
Mitsubishi

5-1

Chapter 5

Disassembly and Reassembly

CAUTION
Spigot joints between the turbine stationary components
(such as outer and inner casings, blade rings, etc.) could bind
due to scale formation during operation under the high
temperature environment.

CAUTION
The binding mentioned above may require additional jacking
or crane load which could exceed the dead weight of the
concerned components as the components are separated or
lifted apart. This could cause surface damage such as seizure,
galling or scoring. Take due care and initiate any special
measures necessary when separating or lifting equipment, and
binding is apparent or suspected.

CAUTION
Personnel working inside the turbine should not carry any
loose items in the pockets and should take special care not to
drop tools or debris into the turbine.

CAUTION
Any surface irregularity or damage caused by the reasons
described above must be ground off smoothly, or
reconditioned by build-up welding and facing to reinstate the
original surface finish and clearance if any between mating
parts.

CAUTION

MM-M05.01

Rev.001

Wear proper goggles and face masks when working on the


insulation. Insulation material is harmful to the respiratory
system.

Main Turbine
Mitsubishi

5-2

Chapter 5

b)

Disassembly and Reassembly

Disassembly
Refer to Figures 5-1 and E-2.

Note
Place the removed turbine components on the turbine operating
floor on protection sheets such as aluminium sheet, plywood or
gasket as per the overhaul plan shown in Appendix E. The
removed components may be placed as per the guide line
locations indicated in Figure E-2 or any other locations
convenient to the maintenance personnel.

During normal operation, before the Unit is shutdown for overhaul,


perform a thorough external visual inspection of the entire turbine unit
to detect any obvious deficiencies. These are to be rectified during
the turbine overhaul.

Remove the turbine enclosure around the HP-IP turbine. Refer to


Figure 2-39 for details of enclosure disassembly details.

Remove the fire extinguishing piping around the HP-IP turbine before
starting disassembly.

Prepare an area for the abrasive blasting of the turbine components.

Label and identify all components as they are disassembled. Tag and
bag all hardware and fasteners with the associated component and
store in the designated area.

Prepare a lay-down area for the turbine components including an


area for the turbine rotor cradle.

Remove insulation from the horizontal joint of the outer casing, the
gland casing area, main steam and hot reheat inlet flanges and the IP
turbine exhaust flange.

Remove the covers (upper half gland casings) from the HP-IP turbine
outer glands and remove the gland seal ring segments as described
in the mechanical maintenance manual M05.03, Gland Steam
Condenser System and GSC Exhaust Fan.

Remove the bolts and nuts from the main steam and reheat steam
inlet flanges to the HP-IP turbine. Refer to Figure 5-1 for details of
main steam and reheat steam piping flange locations.

MM-M05.01

Rev.001

10 Refer to Figure 2-14. Remove the fasteners securing the cross-over


pipe to the LP1 and LP2 turbine inlet flanges and the IP turbine
exhaust flange, and then remove the crossover pipe. Remove the
fasteners securing the top seal rings to the LP1/LP2 outer casing as
shown in detail F and then remove the top seal rings between the
LP1 and LP2 outer and inner casings.
Main Turbine
Mitsubishi

5-3

Chapter 5

Disassembly and Reassembly

Removal of HP-IP Outer Casing Cover


Refer to Figure 2-6.
1

Have electricians remove the thermocouple lead wires.

With reference to the Bolt Arrangement data in Appendix F, label all


bolts and nuts securing the HP-IP outer casing cover to the outer
casing base with their number and indicate right side (RS) or left side
(LS).

Bolt heaters are electrical devices capable of causing personal


injury or death if improperly used.

Note
Refer to the Bolt Heating Data in Appendix F to identify the bolts
and to determine the required heater type and size. The bolts
and/or studs on each side of the turbine have the same number
but are designated RS or LS. For the purposes of this procedure
only the bolt and/or stud number will be given. Remove the same
numbered bolt and/or stud from both sides of the turbine
simultaneously. The same procedure is to be followed when bolt
tightening during reassembly.

CAUTION
Take care not to touch the hot part. Contact with hot parts
could cause burns or other injury.

Using four bolt heaters (two on each side), heat the bolts in
accordance with Bolt Heater Instruction of Appendix I, avoid heating
adjacent bolts, and remove bolts from both the left and right sides of
the casing in the following sequence:
(i)

2 toward 10, 12 toward 22 and 24 toward 40

(ii) Reamer bolts 1, 11, 23 and 41.


4

Remove the nuts as follows:

Rev.001

(i)

Install a safety hoist ring or an eye bolt and copper washer into
the nut to be removed.

MM-M05.01

(ii) Connect suitable lifting gear to the safety hoist ring and remove
the nut.

Main Turbine
Mitsubishi

5-4

Chapter 5

Disassembly and Reassembly

Note
Provide supports for the bolts with both top and bottom nuts,
while removing the top nuts.

Install hydraulic jacks on the flat surfaces provided on the outer


casing near the lifting lugs in preparation for separating the outer
casing cover and the base. Lubricate and install jack screws in the
locations provided.

Note
During operation of the turbine, oxides and deposits
accumulate between the mating surfaces of the casings. The
forces required to separate these surfaces may be noticeably
greater than those required to suspend the weight of the outer
casing cover.

Install the outer casing cover lifting gear as shown in Appendix H.

Gradually operate the hydraulic jacks uniformly rotate the jack screws
to raise and separate the outer casing cover from the casing base.

CAUTION
Visually follow the motion of the outer casing cover while the
crane is hoisting. Do not overload the wire rope slings.

Tension the wire rope sling with the crane hook located over the
center of gravity of the outer casing cover.

Make a trial lift and adjust the lift so that the cover horizontal joint is
parallel to the base horizontal joint.

10 Evenly raise the outer casing cover in small increments until the cover
is clear of the stud bolts.
11 Lift the outer casing cover clear of the inner casing and transport it to
the lay-down area.

Note
Ensure that the openings left by the removal of the outer
casing cover are covered to prevent the entry of foreign

Rev.001

12 Protect the horizontal joint of the outer casing cover.

MM-M05.01

materials into the turbine.

14 Disconnect and remove the lifting gear.

13 Lower the outer casing cover onto wooden blocks.

Main Turbine
Mitsubishi

5-5

Chapter 5

Disassembly and Reassembly

15 Remove the Gov End and Gen End inner gland casing upper halves
in accordance with the mechanical maintenance manual M05.03,
Gland Steam Condenser System and GSC Exhaust Fan.

Removal of Inner Casing Cover


1

Referring to Figure F-1, label all inner casing cover bolts and nuts
with their numbers provided in Appendix F and indicate RS (Right
Side) or LS (Left Side).

Bolt heaters are electrical devices capable of causing personal


injury or death if improperly used.

Note
Refer to the Bolt Heating Data in Appendix F to identify the
bolts and determine the required heater type and size

Using four bolt heaters (two on each side), heat the bolts in
accordance with Bolt Heater Instruction in Appendix I, avoiding
heating adjacent bolts, and remove bolts from both the RS and LS of
the casing in the following sequence:
(i)

52 toward 55 and 57 toward 61

(ii) Reamer bolts 51, 56 and 62.


3

Remove the nuts as follows:


(i)

Install safety hoist ring and copper washer into the nut to be
removed.

Inspect and clean the jack screw threads.

Lubricate and install the jack screws in the locations provided.

Install the inner casing cover lifting gear.

Using the jack screws provided raise the inner casing cover, approx.
10 mm.

Rev.001

Make a trial lift and adjust the turn buckle or the chain block to obtain
a level lift.

MM-M05.01

(ii) Connect suitable lifting gear to the hoist ring and remove the
nuts.

Raise the inner casing cover in small increments until the cover is
clear of the stud bolts.

Main Turbine
Mitsubishi

5-6

Chapter 5

Disassembly and Reassembly

10 Lift the inner casing cover clear of the No.1 dummy ring and transport
it to the lay-down area.

Note
Ensure that the openings exposed by removal of the inner
casing cover are protected.

11 Lower the inner casing cover onto wooden blocks.


12 Disconnect and remove the lifting gear.
13 Remove the retainer and then the seal rings from the bore of inner
casing if inspection or replacement of the slip-joint seal rings is
essential.

Removal of Thermal Shield Upper Half


1

Loosen and remove nuts from the studs at the horizontal joint of the
thermal shield at both the RS and LS.

Lubricate and install the jack screws in the locations provided.

Remove the dowels.

Install eye bolts on the upper half thermal shield and connect the
lifting gear.

Using the jack screws provided raise the upper half thermal shield,
approx. 10 mm.

Rig and remove the thermal shield and transport it to the lay-down
area.

Removal of IP Blade Ring Upper Half


1

Referring to Figure F-1, label all upper half IP blade ring bolts and
nuts with their numbers provided in Appendix F and indicate RS
(Right Side) or LS (Left Side).

Bolt heaters are electrical devices capable of causing personal


injury or death if improperly used.

Rev.001

Note
Refer to the Bolt Heating Data in Appendix F to identify the

MM-M05.01

bolts and determine the required heater type and size

Main Turbine
Mitsubishi

5-7

Chapter 5

Disassembly and Reassembly

Using four bolt heaters (two on each side), heat the bolts in
accordance with Bolt Heater Instruction in Appendix I, avoiding
heating adjacent bolts, and remove bolts from both the RS and LS of
the casing in the following sequence:
(i)

73 toward 75 and 77 toward 80

(ii) Reamer bolt 76.


3

Remove the nuts as follows:


(i)

Install safety hoist ring and copper washer into the nut to be
removed.

(ii) Connect suitable lifting gear to the hoist ring and remove the
nuts.
4

Loosen and remove the nuts from bolts 72, 81, 82, 83 and reamer
bolts 71 and 84 at both the RS and LS.

Note
Reamer bolts 71 and 84 and bolts 72, 81, 82, 83 do not have
provision for a bolt heater.

Inspect and clean the jack screw threads.

Lubricate and install the jack screws in the locations provided.

Install suitable lifting gear to the upper half IP blade ring.

Using the jack screws provided raise the upper half IP blade ring,
approx. 10 mm.

Make a trial lift and adjust the turn buckle or the chain block to obtain
a level lift.

10 Raise the upper half IP blade ring in small increments until it is clear
of the stud bolts.
11 Lift the upper half IP blade ring clear of the turbine and transport it to
the lay-down area.

Note
Ensure that the openings exposed by removal of the upper

Rev.001

half IP blade ring are protected.

12 Lower the upper half IP blade ring onto wooden blocks.

MM-M05.01

13 Disconnect and remove the lifting gear.

Main Turbine
Mitsubishi

5-8

Chapter 5

Disassembly and Reassembly

Removal of HP Stationary Blade Ring Upper Halves


1

Label all bolts and nuts which secure the No.1 HP stationary blade
ring upper half to the lower half with the numbers provided in Appendix
F and indicate RS or LS.

Loosen and remove the joint bolts at both the RS and LS.

Install eye bolts in the upper half stationary blade ring.

Rig the No.1 HP stationary blade ring upper half and make a trial lift.

Adjust the chain blocks or turn buckle, whichever is being used, to


achieve a level lift.

CAUTION
Carefully and evenly lift the stationary blade ring to prevent
damage to the stationary and rotating blading.

Lift the stationary blade ring clear of the rotor blades and transport it
to the lay-down area.

Disconnect and remove the lifting gear.

Following a similar procedure remove the No.2 HP stationary blade


ring upper half.

Removal of IP Stationary Blade Ring Upper Halves


1

Label all No.1 IP stationary blade ring bolts and nuts with their
number and indicate RS or LS.

Loosen and remove the joint bolts at both the RS and LS.

Install eye bolts and lifting gear.

Rig the No.1 IP stationary blade ring upper half and make a trial lift.

Adjust the chain blocks to evenly lift the stationary blade ring upper
half.

CAUTION
Rev.001

Carefully and evenly lift the stationary blade ring to prevent


damage to the stationary and rotating blading.

MM-M05.01

Main Turbine
Mitsubishi

Lift the stationary blade ring clear of the rotor blades and transport it
to the lay-down area.

5-9

Chapter 5

Disassembly and Reassembly

Disconnect and remove the lifting gear.

Following a similar procedure remove the No.2, No.3 and No.4 IP


stationary blade ring upper halves.

Removal of No.1 Dummy Ring Upper Half


1

Referring to Figure F-1, label all No.1 dummy ring bolts and nuts with
their numbers provided in Appendix F and indicate RS (Right Side) or
LS (Left Side).

Bolt heaters are electrical devices capable of causing personal


injury or death if improperly used.

Note
Refer to the Bolt Heating Data in Appendix F to identify the
bolts and determine the required heater type and size

Using four bolt heaters (two on each side), heat the bolts in
accordance with Bolt Heater Instruction in Appendix I, avoiding
heating adjacent bolts, and remove bolts from both the RS and LS of
the casing in the following sequence:
(i)

92 toward 101

(ii) Reamer bolts 91 and 102.


3

Remove the nuts as follows:


(i)

Install safety hoist ring and copper washer into the nut to be
removed.

(ii) Connect suitable lifting gear to the hoist ring and remove the
nuts.
4

Loosen and remove the nuts from bolts 103 and 104 and reamer bolt
105 at both the RS and LS.

Note
Reamer bolt 105 and bolts 103 and 104 do not have provision

MM-M05.01

Rev.001

for a bolt heater.

Main Turbine
Mitsubishi

Inspect and clean the jack screw threads.

Lubricate and install the jack screws in the locations provided.

Install the lifting gear for the No.1 dummy ring upper half.

5-10

Chapter 5

Disassembly and Reassembly

Using the jack screws provided raise the No.1 dummy ring upper half,
approx. 10 mm.

Make a trial lift and adjust the turn buckle or the chain block to obtain
a level lift.

10 Raise the No.1 dummy ring upper half in small increments until it is
clear of the stud bolts.
11 Lift the No.1 dummy ring upper half clear of the blades and transport
it to the lay-down area.

CAUTION
Carefully and evenly lift the No.1 dummy ring to prevent
damage to the stationary and rotating blading.

Note
Ensure that the openings exposed by removal of the No.1
dummy ring upper half are protected.

12 Lower the No.1 dummy ring upper half onto wooden blocks.
13 Disconnect and remove the lifting gear.

Removal of No.2 Dummy Ring Upper Half


1

Label the No.2 dummy ring bolts and nuts with their number and
indicate RS or LS.

Note
Refer to Bolt Arrangement Data in Appendix F to identify the

Using bolt heaters heat the bolt 112 in accordance with Bolt Heater
Instruction in Appendix I, avoiding heating adjacent bolts, and remove
the nuts from bolts from both the RS and LS.

Remove nut from the reamer bolt 111 from the No.2 dummy ring.

Install eye bolts on the upper half No.2 dummy ring.

Rig and remove the No.2 dummy ring and transport it to the lay-down
area.

Remove the lifting gear.

MM-M05.01

Rev.001

bolts.

Main Turbine
Mitsubishi

5-11

Chapter 5

Disassembly and Reassembly

Setting the HP-IP Rotor in the K Position


Refer to Figure 5-6.
Position the rotor axially such that clearance K is RS: 12.00 mm, LS:
12.0+1.5/0.5 mm before taking any of the following measurements.

Note
Clearance K must be set correctly as all other turbine clearances
are based on this measurement.

Measurement of HP and IP Gland Clearances


Refer to Figures 5-3 and 5-4.
Measure and record the radial clearance between the gland seals and the
HP-IP rotor at the RS and LS of the turbine casing for the Gov End and
Gen End rotor gland seals.

Note
Details of measurement of the gland seal clearances are
described in the mechanical maintenance manual M 05.03,
Gland Steam Condenser System and GSC Exhaust Fan.

Measurement of No.1 and No.2 Dummy Ring Seal Clearances


Refer to Figure 5-5.
Measure and record the radial clearance between the seals installed in
the No.1 and No.2 dummy rings with the HP-IP rotor at the RS and LS.
Measurement of HP Turbine Rotating and Stationary Blade Clearances
Refer to Figure 5-6.
1

Measure and record the radial clearance between the seal strip
(located in the nozzle block) and the shroud for the Rateau stage
blades.

Measure and record the following axial clearances at the RS and LS:

Rev.001

(i)

Clearance A between the base of the first stage stationary blade


outlet and the shroud of the first stage rotating blade inlet.

(ii) Repeat Step (i) above for the second through ninth stages.

MM-M05.01

(iii) Clearance B between the end of the first stage stationary blade
outlet and the base of the first stage rotating blade inlet.

Main Turbine
Mitsubishi

5-12

Chapter 5

Disassembly and Reassembly

(iv) Repeat Step (iii) above for the second through ninth stages.
(v) Clearance E between the shroud of the first stage rotating blade
outlet and the base of the second stage stationary blade inlet.
(vi) Repeat Step (v) above for the second, fourth through sixth and
eighth stages.
(vii) Clearance F between the base of the first stage rotating blade
outlet and the end of the second stationary blade inlet.
(viii) Repeat Step (vii) above for the second through eighth stages.
3

Measure and record the following radial clearances at the RS and LS:
(i)

Seal clearance between the seal strips (installed in the No.1


dummy ring and No.1 & No.2 HP stationary blade rings) and the
rotating blade shroud, for the first through ninth stages.

(ii) Seal clearance for the seal strips (installed in the HP stationary
blade diaphragms and rotor), for the first through ninth stages.

Note
The procedure for checking top and bottom blade radial
clearances is provided in Appendix G.

Note
If seal strip clearances exceed 200% of the design
clearances, the seal strips may have to be changed.

Measurement of IP Turbine Rotating and Stationary Blade Clearances


Refer to Figure 5-7.
1

Measure and record the following axial clearances at the RS and LS:
(i)

Measure and record the clearance A between the base of the


first stage stationary blade outlet and the shroud of the first stage
rotating blade inlet.

(ii) Repeat Step (i) above for the second through eighth stages.

Rev.001

(iii) Measure and record the clearance B between the end of the first
stage stationary blade outlet and the base of the first stage
rotating blade inlet.
(iv) Repeat Step (iii) above for the second through eighth stages.

MM-M05.01

(v) Measure and record the clearance E between shroud of the first
stage rotating blade outlet and the base of the second stage
stationary blade inlet.
Main Turbine
Mitsubishi

5-13

Chapter 5

Disassembly and Reassembly

(vi) Repeat Step (v) above for the second, fourth, fifth and seventh
stages.
(vii) Measure and record the clearance F between the base of the
first stage rotating blade outlet and the end of the second
stationary blade inlet.
(viii) Repeat Step (vii) above for the second through seventh stages.
2

Measure and record the axial distance FF from the edge of the No.1
dummy ring to the base of the first stage rotating blade inlet at the RS
and LS.

Measure and record the following radial clearances at the RS and LS:
(i)

Seal clearance between the seal strips (installed in the No.1 to


No.4 IP stationary blade rings) and rotating blade shrouds at the
RS and LS, for the first through eighth stages.

(ii) Seal clearance between the seal strips (secured to the first stage
stationary blade diaphragm) and the No.1 dummy ring at the RS
and LS.
(ii) Seal clearance between the seal strips (secured to the IP
stationary blade diaphragms) and rotor at the RS and LS, for the
second through eighth stages.

Note
If seal strip clearances exceed 200% of the design
clearances, the seal strips may have to be changed.

Note
The procedure for checking top and bottom blade radial
clearances is provided in Appendix G.

Removal of HP-IP Rotor


Refer to Figure 5-10.
1

Ensure that the HP-IP rotor support stand is assembled in the


lay-down area.

Note
Rev.001

Before attempting to remove the rotor, remove other


equipment such as instrumentation pick-ups and bearing

MM-M05.01

pedestal covers to obtain access to the bearings and the


couplings.

Main Turbine
Mitsubishi

5-14

Chapter 5

Disassembly and Reassembly

Remove covers from the HP pedestal and the No.2&3 bearing


pedestal.

Arrange for all instruments to be removed, checked and calibrated if


necessary.

Remove the cover of MOP located in the HP pedestal.

Remove the coupling oil spray lines, the upper half of the coupling
guard from the HP-IP ~ LP1 coupling. Remove the coupling bolts and
the coupling spacer in accordance with the mechanical maintenance
manual M05.05, Turbine Couplings and Alignment.

Remove the upper halves of No.1 and No.2 bearings in accordance


with the mechanical maintenance manual M 05.04, Turbine
Bearings and Thrust Bearing.

Disassemble the thrust bearing in accordance with mechanical


maintenance manual M 05.04.

Spread the dovetail ends of the outer gland casing gaskets to permit
rotor removal.

Install the rotor lifting guide pillars supplied as special tools on the
HP-IP outer casing base.

10 Confirm that there is sufficient clearance between the HP-IP and LP1
coupling flanges for the removal of the HP-IP rotor.
11 Install the HP-IP rotor lifting gear as shown in Appendix H.
12 Adjust the slings to lift the rotor evenly.
13 Using the turn buckle, level the lifting beam.
14 Lift the HP-IP rotor clear of the bearings to check the rotor level, and
again check that there is sufficient axial clearance for the rotor
removal.

CAUTION
Slow and careful removal of the HP-IP rotor must be
performed to avoid damage.

15 Lift the rotor in small increments and ensure that binding does not
occur.
Rev.001

16 Lift the rotor clear of the HP-IP casing base.

Note

MM-M05.01

Ensure that the rotor journals are protected prior to setting the
rotor in the support stand.

Main Turbine
Mitsubishi

5-15

Chapter 5

Disassembly and Reassembly

17 Transport the rotor to the lay-down area and set in the support stand.
18 Remove the lower halves of No.1 and No.2 bearings.
19 Remove the lower halves of the inner and outer gland casings at the
Gov End and Gen End.

Removal of No.1 Dummy Ring Lower Half


1

Install eye bolts in the lower half No.1 dummy ring.

Connect suitable lifting gear to the lower half No.1 dummy ring.

Remove the upper liners secured to the inner casing base at the
horizontal joint which lock the lower half No.1 dummy ring with inner
casing base. Refer to Section G-G in Figure 5-9 for details.

Make a trial lift and adjust the chain blocks to evenly lift the lower half
No.1 dummy ring.

Rig and remove the No.1 dummy ring and transport it to the lay-down
area.

Remove the lifting gear.

Remove the supports and liners secured to the lower half No.1
dummy ring and inner casing base if inspection or replacement is
essential.

Rev.001

Removal of No.2 Dummy Ring Lower Half


1

Install eye bolts on the lower half No.2 dummy ring.

Connect suitable lifting gear to the lower half No.2 dummy ring.

Remove the upper liners secured to the outer casing base at the
horizontal joint which lock the lower half No.2 dummy ring with outer
casing base. Refer to Section D-D in Figure 5-9 for details.

Rig and remove the No.2 dummy ring and transport it to the lay-down
area.

Remove the lifting gear.

Remove the supports secured to the lower half No.2 dummy ring and
the lower liners secured to the outer casing base if inspection or
replacement is essential.

Removal of HP Stationary Blade Ring Lower Halves

MM-M05.01

Main Turbine
Mitsubishi

Install eye bolts in the lower half No.1 HP stationary blade ring and
tighten.

5-16

Chapter 5

Disassembly and Reassembly

Connect suitable lifting gear to the lower half No.1 HP stationary


blade ring.

Remove the upper liners secured to the HP-IP inner casing base
which lock the lower half No.1 HP stationary blade ring with inner
casing base. Refer to Detail Z in Figure 5-9 for details.

Rig and lift the stationary blade ring clear of the inner casing and
transport it to the lay-down area.

Disconnect and remove the lifting gear.

Remove the supports secured to the lower half No.1 HP stationary


blade ring and the lower liners secured to the inner casing base if
inspection or replacement is essential.

Following a similar procedure, remove the lower half No.2 HP


stationary blade ring.

Removal of IP Stationary Blade Ring Lower Halves


1

Install eye bolts into the IP No.1 stationary blade ring lower half and
tighten.

Connect suitable lifting gear to the lower half No.1 IP stationary blade
ring.

Remove the upper liners secured to the IP blade ring base which lock
the lower half No.1 IP stationary blade ring with IP blade ring base
(similar to HP stationary blade ring).

Rig and lift the No.1 IP stationary blade ring clear of the IP blade ring
and transport it to the lay-down area.

Disconnect and remove the lifting gear.

Remove the supports secured to the lower half No.1 IP stationary


blade ring and the lower liners secured to the IP blade ring base if
inspection or replacement is essential.

Following a similar procedure, remove the lower halves of No.2, No.3


and No.4 IP stationary blade rings.

MM-M05.01

Rev.001

Removal of IP Blade Ring Lower Half

Main Turbine
Mitsubishi

Install eye bolts into the lower half IP blade ring.

Connect suitable lifting gear to the lower half IP blade ring.

Remove the hexagonal socket head bolts at the horizontal joint which
secure the lower half IP blade ring to the HP-IP outer casing base.

5-17

Chapter 5

Disassembly and Reassembly

Make a trial lift and adjust the turnbuckle to achieve an even lift.

Slowly raise the lifting gear until the lower half IP blade ring is clear of
the outer casing base.

Transport the lower half IP blade ring to the lay-down area.

Remove the lifting gear.

Remove the upper liners secured to the lower half IP blade ring and
the lower liners secured to the outer casing base if inspection or
replacement is essential. Refer to Detail X in Figure 5-9 for details.

After removal of the lower half IP blade ring, ensure that the openings
in the outer casing base are covered.

Removal of Thermal Shield Lower Half


1

Install eye bolts on the lower half thermal shield.

Connect suitable lifting gear to the lower half thermal shield.

Rig and remove the lower half thermal shield and transport it to the
lay-down area.

Remove the lifting gear.

Remove the liners secured to the lower half thermal shield and to the
outer casing base, if required. Refer to Section B-B in Figure 5-9.

Rev.001

Removal of Inner Casing Base


1

Cut and remove the impulse chamber drain line, and the pressure
sensing piping, outside the HP-IP outer casing base.

Install eye bolts into the inner casing base.

Connect suitable lifting gear to the inner casing base.

Remove the hexagonal socket head bolts which secure the inner
casing base to the outer casing base at the horizontal joint.

Make a trial lift and adjust the turnbuckle to achieve an even lift.

Slowly raise the lifting gear until the inner casing base is clear of the
outer casing base.

Transport the inner casing base to the lay-down area.

Remove the lifting gear.

After removal of the inner casing base, ensure that the openings in
the outer casing base are covered.

MM-M05.01

10 Remove the liners secured to the inner casing base and the outer
casing base, if required. Refer to Detail Y in Figure 5-9 for details.

Main Turbine
Mitsubishi

5-18

Chapter 5

c)

Disassembly and Reassembly

Cleaning and Inspection


Inspection of HP-IP Outer Casing
1

Manually clean the horizontal joint flanges and bolts.

Visually inspect the following areas for erosion, wear, steam cuts,
cracks, or other damage:
(i)

Cover (horizontal joint)

(ii) Base (horizontal joint)


(iii) Outer casing to inner casing, IP blade ring, No.2 dummy ring and
thermal shield fits
(iv) Steam penetrations
(v) Seal rings on No.8 extraction nozzle.

Note
Any discrepancies found must be corrected by stoning
or honing.

Perform NDT on the following areas:


(i)

Cover (horizontal joint)

(ii) Base (horizontal joint)


(iii) Joint bolts
(iv) Steam penetrations.
4

Visually inspect the threaded portions of the joint bolts for


deformation, galling, binding, or unusual wear.

Inspection of HP-IP Inner Casing


1

Clean all areas of the inner casing by abrasive blasting.

Note
Ensure the horizontal flange areas are protected prior to blast

Rev.001

cleaning.

Manually clean the horizontal joint flanges.

Visually inspect the following components for erosion, wear, steam


cuts, cracks, or other damage:
(i)

Cover (horizontal joint)

MM-M05.01

(ii) Base (horizontal joint)


(iii) Outer casing to inner casing fits
Main Turbine
Mitsubishi

5-19

Chapter 5

Disassembly and Reassembly

(iv) No.1 and No.2 HP stationary blade rings to inner casing fits
(v) Inner casing to No.8 extraction nozzle fit and seal rings
(vi) Steam penetrations
(vii) Pressure seal rings and seal retaining rings of slip joints.

Note
Any discrepancies found must be corrected by stoning or
honing.

Perform NDT on the following areas:


(i)

Cover (horizontal joint)

(ii) Base (horizontal joint)


(iii) Joint bolts
(iv) Steam penetrations.
5

Visually inspect the threaded portions of the joint bolts for


deformation, galling, binding, or unusual wear.

Inspection of IP Blade Ring


1

Clean all areas of the blade ring by abrasive blasting.

Note
Ensure the horizontal flange areas are protected prior to blast
cleaning.

Manually clean the horizontal joint flanges.

Visually inspect the following components for erosion, wear, steam


cuts, cracks, or other damage:
(i)

Upper half (horizontal joint)

(ii) Lower half (horizontal joint)


(iii) IP blade ring to outer casing fits
(iv) No.1 ~ No.4 IP stationary blade rings to IP blade ring fits.

Note
Any discrepancies found must be corrected by stoning or

Rev.001

honing.

Perform NDT on the following areas:

MM-M05.01

(i)

Upper half (horizontal joint)

(ii) Lower half (horizontal joint)

Main Turbine
Mitsubishi

5-20

Chapter 5

Disassembly and Reassembly

(iii) Joint bolts


(iv) Remainder of IP blade ring.
5

Visually inspect the threaded portions of the joint bolts for


deformation, galling, binding, or unusual wear.

Inspection of HP and IP Stationary Blade Rings


1

Inspect all seal strips for rubs or other signs of contact.

Note
Change seal strip(s) if they are damaged.

Clean all areas of the stationary blade rings by abrasive blasting.

Note
Ensure the horizontal flange areas are protected prior to blast
cleaning.

Manually clean the horizontal joint flanges and bolts.

Visually inspect the following areas for erosion, wear, steam cuts,
cracks, or other damage:
(i)

Upper half (horizontal joint)

(ii) Lower half (horizontal joint)


(iii) HP-IP inner casing to No.1 and No.2 HP stationary blade ring fits
(iv) IP blade ring to No.1~ No.4 IP stationary blade ring fits.

Note
Any discrepancies found must be corrected by stoning
or honing.

Visually inspect the HP stationary blades to HP stationary blade ring


joints and packing strips for looseness and wear.

Visually inspect the IP stationary blades to IP stationary blade ring


joints and packing strips for looseness and wear.

Perform NDT on the following areas:


(i)

Upper half (horizontal joint)

Rev.001

(ii) Lower half (horizontal joint)


(iii) Joint bolts

MM-M05.01

(iv) Stationary blades


(v) Steam penetrations.
Main Turbine
Mitsubishi

5-21

Chapter 5

Disassembly and Reassembly

Visually inspect the threaded portions of the joint bolts for


deformation, galling, binding, or unusual wear.

Inspection of No.1 Dummy Ring


1

Inspect all seal strips for rubs or other signs of contact.

Note
Change seal strip(s) if they are damaged.

Clean the No.1 dummy ring by abrasive blasting.

Note
Ensure the horizontal flange areas are protected prior to blast
cleaning.

Manually clean the No.1 dummy ring.

Visually inspect the following components for erosion, wear, steam


cuts, cracks, or other damage:
(i)

Nozzle block and nozzles

(ii) Nozzle chamber internal steam passage


(iii) Pressure seal rings and retaining rings
(iv) No.1 dummy ring to inner casing fits.

Note
Any discrepancies found must be corrected by stoning or
honing.

Visually inspect the 1st ~ 3rd stages HP stationary blades to No.1


dummy ring joints and packing strips for looseness and wear.

Perform NDT on the following areas:


(i)

Upper half (horizontal joint)

(ii) Lower half (horizontal joint)


(iii) Joint bolts
(iv) HP stationary blades
(v) Remainder of No.1 dummy ring.
Visually inspect the threaded portions of the horizontal joint bolts for
deformation, galling, binding, or unusual wear.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

5-22

Chapter 5

Disassembly and Reassembly

Inspection of No.2 Dummy Ring


1

Inspect all seal strips for rubs or other signs of contact.

Note
Replace seal strip(s) if they are damaged.

Abrasive blast clean all areas of the dummy ring.

Note
Ensure the horizontal flange areas are protected prior to blast
cleaning.

Hand clean the horizontal joint flanges.

Visually inspect the following components for erosion, wear, steam


cuts, cracks, or other damage:
(i)

Upper half (horizontal joint)

(ii) Lower half (horizontal joint)


(iii) Dummy ring to outer casing fits.

Note
Any discrepancies found must be corrected by stoning or
honing.

Perform NDT on the following areas:


(i)

Upper half (horizontal joint)

(ii) Lower half (horizontal joint)


(iii) Joint bolts
(iv) Remainder of No.2 dummy ring.
6

Visually inspect the threaded portions of the joint bolts for


deformation, galling, binding, or unusual wear.

Inspection of Thermal Shield


1

Inspect all seal rings for rubs or other signs of contact.

Note

MM-M05.01

Rev.001

Repair or replace seal ring(s) if they are damaged.

Main Turbine
Mitsubishi

5-23

Chapter 5

Disassembly and Reassembly

Clean all areas of the thermal shield by abrasive blasting.

Note
Ensure the horizontal flange areas are protected prior to blast
cleaning.

Manually clean the horizontal joint flanges.

Visually inspect the following components for erosion, wear, steam


cuts, cracks, or other damage:
(i)

Upper half (horizontal joint)

(ii) Lower half (horizontal joint)


(iii) Thermal shield to outer casing fits
(iv) Piston rings on the LP balancing steam nozzle.

Note
Any discrepancies found must be corrected by stoning or
honing.

Perform NDT on the following areas:


(i)

Upper half (horizontal joint)

(ii) Lower half (horizontal joint)


(iii) Joint bolts
(iv) Remainder of thermal shield.
6

Visually inspect the threaded portions of the joint bolts for


deformation, galling, binding, or unusual wear.

Inspection of HP-IP Rotor


1

Inspect all seal strips for rubs or other signs of contact.

Note

Rev.001

Change seal strip(s) if they are damaged.

Visually inspect the fit of the rotor balancing plugs.

Abrasive blast clean the rotor including the blading and shrouds.

Note
Ensure the rotor journal areas are protected prior to blast

MM-M05.01

cleaning.

Main Turbine
Mitsubishi

5-24

Chapter 5

Disassembly and Reassembly

Visually inspect the rotor gland areas for erosion, wear, steam cuts,
cracks, or other damage.

Visually inspect the rotor journal areas and thrust collar for scratches,
dents, pitting or other damage.

Visually inspect the following areas for pitting, deposits or impact


damage and also check that the blade trailing edges are straight and
uniform:
(i)

Reaction blading

(ii) Root of blading


(iii) Shrouds
(iv) Rateau blading.

Note
Any discrepancies found must be corrected by stoning,
honing, or component replacement.

Perform NDT on the following areas:


(i)

Reaction and impulse blading

(ii) Blading shrouds


(iii) Blading roots
(iv) Tenons
(v) Shaft surfaces
(vi) Rotor gland areas
(vii) Rotor journal areas and thrust collar.

d)

Reassembly
The reassembly procedure is carried out in the reverse sequence to that
for disassembly. Install all parts in the same positions they were removed
from, referring to the match marks and checking that the clearances are
maintained as specified.
Ensure that all components are free from burrs and bruises, blending
away the defects using fine files, carborundum stones and emery cloth.

MM-M05.01

Rev.001

All contact surfaces are to be cleaned before starting reassembly. The


reassembly procedure is described below:

Main Turbine
Mitsubishi

5-25

Chapter 5

Disassembly and Reassembly

CAUTION
Prior to installation of the turbine components, thoroughly
inspect the internals for foreign materials. Ensure that the
utmost standards of cleanliness are applied at all times.

Installation of Inner Casing Base


Refer to Figure 2-6.

Note
Lubricate all bolts and studs with Molykote.

Clean the mating areas of the inner casing base and the outer casing
base and support liners.

Ensure that the seal rings and the retaining rings are correctly
installed in the inner casing base and cover, if removed during
disassembly.

Ensure that the seal rings are correctly installed in the slots on the
No.8 extraction nozzle, if removed during disassembly.

Secure the liners to the inner casing base and the outer casing base
if removed during disassembly. Refer to Figure 5-9 for details.

Connect suitable lifting gear to the inner casing base.

Make a trial lift and adjust the turn buckle to achieve a level lift.

Lubricate all mating areas of the seal rings and liners.

Move the inner casing base from the lay-down area and position it
above the outer casing base.

Attach a tag line to each end of the inner casing base to control any
rotation.

10 Slowly and carefully lower the inner casing base until it rests on the
liners bolted to the outer casing base.
11 Remove the lifting gear.

MM-M05.01

Rev.001

12 Reconnect and re-weld the impulse chamber drain and pressure


sensing piping which were cut during disassembly.

Main Turbine
Mitsubishi

5-26

Chapter 5

Disassembly and Reassembly

Installation of Thermal Shield Lower Half


1

Clean and lubricate the dowel and mating areas on the thermal shield
lower half and support liners.

Replace all seal rings and piston rings in the thermal shield in their
original locations, if removed during disassembly.

Secure the liners to the outer casing base and to the lower half
thermal shield if removed during disassembly. Refer to Figure 5-9 for
details.

Connect suitable lifting gear.

Make a trial lift and adjust to achieve a level lift.

Transport the thermal shield lower half from the lay-down area and
align it with the HP-IP outer casing base.

Lower the thermal shield slowly and evenly into the dowel pin
secured in the outer casing until the weight is on the liners and the
horizontal joint is even with that of the outer casing base. Take care
while lowering the thermal shield to prevent any damage to the seal
rings.

Remove the lifting gear.

Installation of IP Blade Ring Lower Half


Refer to Figure 2-6.

Note

MM-M05.01

Rev.001

Lubricate all bolts and studs with Molykote.

Main Turbine
Mitsubishi

Clean the mating areas of the lower half IP blade ring and the HP-IP
outer casing base and support liners.

Ensure that the liners are correctly installed in the outer casing base
horizontal joint. Refer to Figure 5-9 for details.

Ensure that the seal rings are correctly installed in the slots on the
No.6 extraction nozzle, if removed during disassembly.

Connect suitable lifting gear to the lower half IP blade ring.

Make a trial lift and adjust the turn buckle to achieve a level lift.

Lubricate all mating areas of the lower half IP blade ring.

Transport the lower half IP blade ring from the lay-down area and
position it above the outer casing base.

5-27

Chapter 5

Disassembly and Reassembly

Attach a tag line to each end of the lower half IP blade ring to control
any rotation.

Slowly and carefully lower the lower half IP blade ring until it is
supported on the liners bolted to the outer casing base.

10 Remove the lifting gear.

Installation of IP Stationary Blade Ring Lower Halves


1

Clean the mating areas of the lower half No.1 IP stationary blade ring
and the IP blade ring base and the support liners and keys.

Secure the lower liners to the IP blade ring base and the supports to
the lower half No.1 IP stationary blade ring, if removed during
disassembly. Refer to Figure 5-9 for details.

Install eye bolts in the lower half No.1 IP stationary blade ring and
tighten.

Connect suitable lifting gear.

Make a trial lift and adjust the chain blocks to obtain a level lift.

Transport the lower half No.1 IP stationary blade ring from the
lay-down area and align it over the IP blade ring base.

Lower the No.1 IP stationary blade ring slowly and evenly into the IP
blade ring until the supports rest on the lower liners. Ensure that the
horizontal joint of the IP stationary blade ring is even with the
horizontal joint of the IP blade ring base and the weight is on the
liners.

Install and secure the upper liners to the lower half IP blade ring.

Remove the lifting gear.

10 Following a similar procedure as described above, install the lower


halves of No.2, No.3 and No.4 IP stationary blade rings.

Installation of HP Stationary Blade Ring Lower Halves


Clean the mating areas of the lower half No.1 HP stationary blade
ring and the HP-IP inner casing base and the supporting liners and
supports.

Secure the lower liners to the inner casing base and the supports to
the lower half No.1 HP stationary blade ring, if removed during
disassembly. Refer to Figure 5-9 for details.

Install eye bolts in the lower half No.1 HP stationary blade ring and
tighten.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

5-28

Chapter 5

Disassembly and Reassembly

Connect suitable lifting gear.

Make a trial lift and adjust the chain blocks to obtain a level lift.

Transport the lower half No.1 HP stationary blade ring from the
lay-down area and align it over the inner casing base.

Lower the No.1 HP stationary blade ring slowly and evenly into the
inner casing until the supports rest on the lower liners. Ensure that
the horizontal joint of the HP stationary blade ring is even with the
horizontal joint of the inner casing base and the weight is on the lower
liners.

Install and secure the upper liners to the inner casing base.

Remove the lifting gear.

10 Following a similar procedure as described above, install the lower


half No.2 HP stationary blade ring.

Rev.001

Installation of No.1 Dummy Ring Lower Half


1

Clean and lubricate all mating areas on the No.1 dummy ring lower
half.

Secure the lower liners to the inner casing base and the supports to
the lower half No.1 dummy ring, if removed during disassembly.
Refer to Figure 5-9 for details.

Replace all seal rings in the No.1 dummy ring in their original
locations if removed during disassembly and secure them with the
seal ring retainer.

Install eye bolts and tighten.

Connect suitable lifting gear.

Make a trial lift and adjust to achieve a level lift.

Transport the No.1 dummy ring from the lay-down area and align it
above the inner casing base.

Lower the No.1 dummy ring slowly and evenly into the inner casing
until the supports rest on the lower liners. Ensure that the horizontal
joint of the No.1 dummy ring is even with the horizontal joint of the
inner casing base and the weight is on the lower liners.

Install and secure the upper liners to the inner casing base.

MM-M05.01

10 Remove the lifting gear.

Main Turbine
Mitsubishi

5-29

Chapter 5

Disassembly and Reassembly

Installation of No.2 Dummy Ring Lower Half


1

Clean and lubricate all mating areas on the No.2 dummy ring lower
half.

Secure the lower liners to the outer casing base and the supports to
the lower half No.2 dummy ring, if removed during disassembly.
Refer to Figure 5-9 for details.

Replace all seal rings in the No.1 dummy ring if removed during
disassembly.

Install eye bolts and tighten.

Connect suitable lifting gear.

Make a trial lift and adjust to achieve a level lift.

Transport the No.2 dummy ring from the lay-down area and align it
above the outer casing base.

Lower the No.2 dummy ring slowly and evenly into the outer casing
until the supports rest on the lower liners. Ensure that the horizontal
joint of the No.2 dummy ring is even with the horizontal joint of the
outer casing base and the weight is on the lower liners.

Install and secure the upper liners to the outer casing base.

10 Remove the lifting gear.

Installation of HP-IP Rotor


Refer to Figure 5-10.
1

Install the lower halves of the No.1 and No.2 turbine bearings and the
thrust bearing.

Visually inspect the HP-IP turbine base to make sure that it is clean
and free of foreign objects before rotor installation.

Install the rotor guide pillars on the outer casing base.

Note
These may not have been removed.

Rev.001

Install the lifting gear to the HP-IP rotor as shown in Appendix H.

Note

MM-M05.01

If the top and bottom radial blade clearances have to or must


be checked perform this activity at this time. Refer to the
procedure in Appendix G.

Main Turbine
Mitsubishi

5-30

Chapter 5

Disassembly and Reassembly

Make a trial lift.

Adjust the slings from the center of the lifting beam to achieve a level
lift, adjusting the turnbuckle as required.

Transport the rotor to the HP-IP turbine base and align it with the rotor
guides.

Remove any remaining protective coverings and lubricate the rotor


journal areas.

Place a machinist level on the rotor shaft to confirm a level lift.

CAUTION
Care must be taken when installing the rotor to ensure that the
blading and journal areas are not damaged. The turbine rotor
is a sensitive component with numerous tight axial and radial
clearances which must remain intact for correct operation.
Damaging the rotor can cause serious delays in turbine
assembly if additional repairs are necessary.
10 Lower the rotor slowly into the rotor guide pillars while constantly
watching the rotor level.
11 Stop lowering at any change in rotor inclination to determine and
eliminate the cause.
12 Slowly lower the rotor until it is supported in No.1 & No.2 bearings.
13 Raise the rotor slowly again and apply lubricating oil on the bearing
surfaces.
14 Lower the rotor slowly until it is supported in the bearings.
15 Remove the rotor guide pillars and block the rotor to restrict axial
movement.
16 Rotate the rotor slowly as per the procedure indicated in the
mechanical maintenance manual M-05.05, Turbine Couplings and
Alignment, and make sure that the rotor turns freely without rubbing.

CAUTION

MM-M05.01

Rev.001

The rotor must always be rotated in the normal direction of


rotation. If any binding or noise is felt or heard while rotating
the rotor, stop, determine and correct the cause of the noise
and/or binding.

Main Turbine
Mitsubishi

5-31

Chapter 5

Disassembly and Reassembly

Setting of HP-IP Rotor in the K Position


Refer to Figure 5-6.
Position the rotor axially such that clearance K is RS: 12.00.0 mm, LS:
12.0+1.5/0.5 mm before taking any of the following measurements.

Note
Clearance K must be set correctly as all other turbine clearances
are based on this measurement.

Measurement of HP-IP Gland Clearances


Refer to Figures 5-3 to 5-4.
Measure and record the radial clearance between the inner and outer
gland seals and the HP-IP rotor at the RS and LS for the Gov End and
Gen End rotor gland seals.

Note
Details of measurement of the gland seal clearances are
described in the mechanical maintenance manual M 05.03,
Gland Steam Condenser System and GSC Exhaust Fan.

Measurement of No.1 and No.2 Dummy Ring Seal Clearances


Refer to Figure 5-5.
Measure and record the radial clearance between the seals installed in
the No.1 and the No.2 dummy rings and the HP-IP rotor at the RS and LS.
Measurement of HP Turbine Rotating and Stationary Blade Clearances
Refer to Figure 5-6.
1

Measure and record the radial clearance between the seal strip
(located in the nozzle holder) and the shroud for the Rateau stage
blades.

Measure and record the following axial clearances at the RS and LS:

Rev.001

(i)

Clearance A between the base of the first stage stationary blade


outlet and the shroud of the first stage rotating blade inlet.

MM-M05.01

(ii) Repeat Step (i) above for the second through ninth stages.
(iii) Clearance B between the end of the first stage stationary blade
outlet and the base of the first stage rotating blade inlet.
Main Turbine
Mitsubishi

5-32

Chapter 5

Disassembly and Reassembly

(iv) Repeat Step (iii) above for the second through ninth stages.
(v) Clearance E between the shroud of the first stage rotating blade
outlet and the base of the second stage stationary blade inlet.
(vi) Repeat Step (v) above for the second, fourth through sixth and
eighth stages.
(vii) Clearance F between the base of the first stage rotating blade
outlet and the end of the second stationary blade inlet.
(viii) Repeat Step (vii) above for the second through eighth stages.
3

Measure and record the following radial clearances at the RS and LS:
(i)

Seal clearance between the seal strips (installed in the No.1


dummy ring and No.1 & No.2 HP stationary blade rings) and the
rotating blade shroud, for the first through ninth stages.

(ii) Seal clearance for the seal strips (installed in the stationary blade
diaphragms and rotor), for the first through ninth stages.

Note
The procedure for checking top and bottom blade radial
clearances is provided in Appendix G.

Note
If seal strip clearances exceed 200% of the design
clearances, the seal strips may have to be changed.

Measurement of IP Turbine Rotating and Stationary Blade Clearances


Refer to Figure 5-7.
1

Measure and record the following axial clearances at the RS and LS:
(i)

Measure and record the clearance A between the base of the


first stage stationary blade outlet and the shroud of the first stage
rotating blade inlet.

(ii) Repeat Step (i) above for the second through eighth stages.

Rev.001

(iii) Measure and record the clearance B between the end of the first
stage stationary blade outlet and the base of the first stage
rotating blade inlet.
(iv) Repeat Step (iii) above for the second through eighth stages.

MM-M05.01

(v) Measure and record the clearance E between shroud of the first
stage rotating blade outlet and the base of the second stage
stationary blade inlet.
Main Turbine
Mitsubishi

5-33

Chapter 5

Disassembly and Reassembly

(vi) Repeat Step (v) above for the second, fourth, fifth and seventh
stages.
(vii) Measure and record the clearance F between the base of the
first stage rotating blade outlet and the end of the second
stationary blade inlet.
(viii) Repeat Step (vii) above for the second through seventh stages.
2

Measure and record the axial distance FF from the edge of the No.1
dummy ring to the base of the first stage rotating blade inlet at the RS
and LS.

Measure and record the following radial clearances at the RS and LS:
(i)

Seal clearance between the seal strips (installed in the No.1 to


No.4 IP stationary blade rings) and rotating blade shrouds at the
RS and LS, for the first through eighth stages.

(ii) Seal clearance between the seal strips (secured to the first stage
stationary blade diaphragm) and the No.1 dummy ring at the RS
and LS.
(iii) Seal clearance between the seal strips (secured to the stationary
blade diaphragms) and rotor at the RS and LS, for the second
through eighth stages.

Note
If seal strip clearances exceed 200% of the design
clearances, the seal strips may have to be changed.

Note
The procedure for checking top and bottom blade radial
clearances is provided in Appendix G.

MM-M05.01

Rev.001

Alignment and Coupling

Main Turbine
Mitsubishi

Have the electricians install the rotor position, eccentricity and phase
detector pick-ups.

Install the thrust bearing and confirm that the thrust axial clearance
and the No.1 and No.2 bearing oil clearances are within the
acceptance criteria in accordance with mechanical maintenance
manual M 05.04, Turbine Bearings and Thrust Bearing.

Perform coupling alignment between the HP-IP and LP1 rotors and
make sure that the coupling alignment is within tolerance. For details,
refer to the mechanical maintenance manual M 05.05, Turbine
Couplings and Alignment.

5-34

Chapter 5

Disassembly and Reassembly

Install the upper halves of the No.1 and No.2 journal bearings.

Install the HP-IP to LP1 coupling spacer and the coupling bolts in
accordance with mechanical maintenance manual M 05.05, Turbine
Couplings and Alignment.

Install the upper half coupling guard and connect the coupling cooling
oil line for the HP-IP to LP1 coupling.

Have the electricians install the speed and vibration pick-ups.

Install the inner gland casing upper halves in accordance with


mechanical maintenance manual M05.03, Gland Steam Condenser
System and GSC Exhaust Fan.

Note
The above items 5, 6 and 7 assume that only the HP-IP turbine
has been subjected to overhaul. In the event that LP turbines
are also to be overhauled connection of the HP-IP to LP1
coupling will be performed after their reassembly.

Installation of HP and IP Stationary Blade Ring Upper Halves


Install eye bolts in the No.2 HP stationary blade ring upper half.

Connect suitable lifting gear and make a trial lift.

Adjust the chain block to evenly lift the No.2 HP stationary blade ring
upper half.

Move the No.2 HP stationary blade ring upper half from the lay-down
area to the turbine casing.

Align the upper half stationary blade ring with the lower half stationary
blade ring.

Clean the No.2 HP stationary blade ring upper and lower halves
horizontal joint and coat the upper half joint with triple boiled linseed
oil or special compound for flange surface.

Clean stud threads and coat with Molykote.

Lower the No.2 stationary blade ring upper half slowly and evenly
over the joint studs until the horizontal joint is closed.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

5-35

Chapter 5

Disassembly and Reassembly

CAUTION
Care must be taken when installing the upper half stationary
blade ring to ensure that the turbine blading are not damaged.
The blading are installed with tight axial clearances which
must remain intact for correct operation. Damages to the
blading can cause serious delays in turbine assembly if
additional repairs are necessary.
9

Remove the lifting gear.

10 Coat the horizontal joint washers with Molykote and install on studs.
11 Tighten the horizontal joint bolts at both the RS and LS.
12 Following similar procedure described above install the upper half
No.1 HP stationary blade ring and No.1 ~ No.4 IP stationary blade
rings.
13 Rotate the HP-IP rotor to ensure freedom of rotor movement.

Replace the seal rings in the No.1 dummy ring upper half, if removed
during disassembly.

Install eye bolts in the No.1 dummy ring upper half.

Connect suitable lifting gear and make a trial lift.

Adjust the chain block to evenly lift the dummy ring upper half.

Move the dummy ring upper half from the lay-down area to the
turbine casing.

Align the dummy ring upper half over the dummy ring lower half.

Clean the dummy ring upper and lower halves horizontal joint and
coat the upper half joint with triple boiled linseed oil or special
compound for flange surface.

Clean the stud threads and fit groove areas and coat them with
Molykote.

Lower the dummy ring upper half slowly and evenly over the joint
studs until the horizontal joint is closed.

MM-M05.01

Rev.001

Installation of No.1 dummy ring Upper Half

Main Turbine
Mitsubishi

5-36

Chapter 5

Disassembly and Reassembly

CAUTION
Care must be taken when installing the upper half dummy ring
to ensure that the turbine blading are not damaged. The
blading are installed with tight axial clearances which must
remain intact for correct operation. Damages to the blading
can cause serious delays in turbine assembly if additional
repairs are necessary.
10 Remove the lifting gear.
11 Coat the horizontal joint washers with Molykote and install them on
the studs.

Bolt heaters are electrical devices capable of causing personal


injury or death if improperly used.

Note
Refer to the Bolt Heating Data in Appendix F to identify the
bolts and determine the required heater type and size. Heat
the bolts in accordance with Bolt Heater Instruction in
Appendix I.

Note
Tighten the nuts without bolt heaters to the torque specified in
Appendix F.

12 Install the nuts 91 to 105 in the following sequence:


(i)

Heat and tighten reamer bolts 91 and 102

(ii) Torque tighten reamer bolt 105


(iii) Torque tighten bolts 103 and 104
(iv) Heat and tighten bolts 101 toward 92.

MM-M05.01

Rev.001

13 Rotate the HP-IP rotor to ensure freedom of rotor movement.

Main Turbine
Mitsubishi

5-37

Chapter 5

Disassembly and Reassembly

Installation of No.2 Dummy Ring Upper Half


1

Replace seal rings in the No.2 dummy ring, if removed during


disassembly.

Install eye bolts in the No.2 dummy ring upper half.

Connect suitable lifting gear and make a trial lift.

Adjust the chain block to evenly lift the dummy ring upper half.

Move the dummy ring upper half from the lay-down area to the
turbine casing.

Align the dummy ring upper half over the dummy ring lower half.

Clean the dummy ring upper and lower halves horizontal joint and
coat the upper half joint with triple boiled linseed oil or special
compound for flange surface.

Clean stud threads and coat with Molykote.

Lower the dummy ring upper half slowly and evenly over the joint
studs until the horizontal joint is closed.

10 Remove the lifting gear.


11 Coat the horizontal joint washers with Molykote and install on studs.
12 Tighten the nuts on reamer bolt 111 at both the RS and LS to the
torque value specified in Appendix F.
13 Heat and tighten the nuts on bolt 112 at both the RS and LS to the
value specified in Appendix F.

Installation of IP Blade Ring Upper Half


Install eye bolts in the IP blade ring upper half.

Connect the lifting gear and make a trial lift.

Adjust the chain blocks to evenly lift the IP blade ring upper half.

Transport the IP blade ring from the lay-down area and align it with
the lower half IP blade ring.

Clean the horizontal joint flanges of the upper and lower halves IP
blade ring and coat the upper half joint with triple boiled linseed oil or
special compound for flange surface.

Clean stud threads, dowels and groove areas and coat with Molykote.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

5-38

Chapter 5

Disassembly and Reassembly

Lower the IP blade ring upper half slowly and evenly over the joint
studs until the horizontal joint is closed.

Remove the lifting gear.

Coat the horizontal joint washers with Molykote and install on studs.

Bolt heaters are electrical devices capable of causing personal


injury or death if improperly used.

Note
Refer to the Bolt Heating Data in Appendix F to identify the
bolts and determine the required heater type and size. Heat
the bolts in accordance with Bolt Heater Instruction in
Appendix I.

Note
Tighten the nuts without bolt heaters to the torque specified in
Appendix F.

10 Install the nuts on the bolts 71 to 84 in the following sequence:


(i)

Heat and tighten reamer bolt 76

(ii) Torque tighten reamer bolts 71 and 84


(iii) Torque tighten bolts 72, 81, 82 and 83
(iv) Heat and tighten bolts 80 77 and 75 73.
11 Rotate the HP-IP rotor to ensure freedom of rotor movement and
rubbing.

MM-M05.01

Rev.001

Installation of Inner Casing Cover

Main Turbine
Mitsubishi

Visually inspect the HP-IP turbine base for foreign material prior to
installing the inner casing cover, and record the result.

Replace the seal rings and retaining rings in the inner casing cover, if
removed during disassembly.

Install eyebolts and connect suitable lifting gear to the inner casing
cover.

Make a trial lift and adjust to obtain a level lift.

5-39

Chapter 5

Disassembly and Reassembly

Transport the inner casing cover and position it above the inner
casing base joint bolts.

Align the horizontal joint bolt holes with the studs.

Lubricate the joint bolts and dowels with Molykote.

Apply a coat of triple boiled linseed oil or special compound to the


inner casing cover horizontal joint.

Adjust the turnbuckles of the lifting gear so that the cover horizontal
joint is parallel to the base horizontal joint.

10 Slowly lower and align the cover with the studs.


11 Continue lowering the cover until the horizontal joint is closed.
12 Remove the lifting gear.

Bolt heaters are electrical devices capable of causing personal


injury or death if improperly used.

13 Heat the bolts 51 to 62 and tighten the nuts in a diametrically opposite


pattern to the torque value specified in Appendix F in the following
sequence:
(i)

Reamer bolts 51, 56 and 62

(ii) Bolts 61 57 and 55 52.


14 Slowly rotate the HP-IP rotor to ensure that it turns freely without
rubbing.

Replace the seal rings and piston rings in the thermal shield, if
removed during disassembly.

Replace and secure the upper liners to the upper half thermal shield.

Install eye bolts in the thermal shield upper half.

Connect suitable lifting gear and make a trial lift.

Adjust the chain blocks to obtain a level lift.

Transport the thermal shield upper half from the lay-down area to the
turbine casing and align it with the lower half.

MM-M05.01

Rev.001

Installation of Thermal Shield Upper Half

Main Turbine
Mitsubishi

5-40

Chapter 5

Disassembly and Reassembly

Clean and coat the upper half horizontal joint with triple boiled linseed
oil or special compound for flange surface.

Clean bolt threads, bushing and groove areas and coat with
Molykote.

Lower the upper half thermal shield slowly and evenly until the
horizontal joint is closed. While lowering ensure that the LP leakage
steam nozzle slides smoothly into the No.1 dummy ring and the seal
rings slide smoothly along the IP blade ring and inner casing cover.

10 Remove the lifting gear.


11 Install the dowel pins and tighten the horizontal joint bolts.

Installation of HP-IP Outer Casing Cover


1

Perform a visual inspection of the turbine to ensure that no foreign


material is present before installation of the outer casing cover.

Connect the HP-IP outer casing cover lifting gear in accordance with
Appendix H.

Make a trial lift and adjust to obtain a level lift.

Transport the outer casing cover from the lay-down area and align it
to the outer casing base.

Lubricate the joint bolts, dowels, steam inlet nozzle sleeves and other
mating areas with Molykote.

Lubricate the outer casing cover horizontal joint flange with triple
boiled linseed oil or special compound for flange surface.

Slowly lower the outer casing cover and make sure that the main
steam inlet sleeves in the outer casing cover are aligned with the
inner casing cover.

Lubricate the jack screws with Molykote.

Install the jack screws in the outer casing cover when the cover
reaches to 50 mm above the horizontal joint. Turn the jack screws in
the outer casing cover until they protrude 10 mm below the horizontal
joint.

Rev.001

10 Lower the outer casing cover further until the jack screws rest on the
horizontal joint of the outer casing base.

MM-M05.01

11 Continue lowering the outer cover by backing off all the jack screws
equally 1/2 turn at a time.

Main Turbine
Mitsubishi

5-41

Chapter 5

Disassembly and Reassembly

Note
Follow the downward motion of the outer casing with the
lifting device to ensure that the load is transferred to the jack
screws.

12 Continue to lower the outer cover until the horizontal joint is closed.

Note
Check the contact between the flanges using a feeler gauge.

13 Remove the lifting gear.


14 Place the respective washers over the open bolt holes in the outer
casing cover flange.
15 Fit the nuts to the stud bolts.
16 Install the bolts into the flange by lifting the bolts with safety hoist
rings using suitable lifting gear and lowering the bolts through the
washers and flanges.
17 Install washers and nuts on bolt bottom threads and cold tighten nuts
to seat the washers in accordance with the Bolt Arrangement Data in
Appendix F.

Note
Tighten, in a diametrically opposite pattern, the HP-IP outer
casing bolts in the following order.

(i)

Reamer bolts 11 and 23

(ii) Reamer bolts 1 and 41


(iii) Bolts 22 12, 10 2 and 24 40.

Bolt heaters are electrical devices capable of causing personal


injury or death if improperly used.

MM-M05.01

Rev.001

18 Heat and stretch the bolts 1 41 and tighten the nuts in the sequence
indicated above in accordance with Appendix I.

Main Turbine
Mitsubishi

5-42

Chapter 5

Disassembly and Reassembly

Return to Service
Return to Service
Refer to Figure 5-1.
Install and secure the MOP cover to the pump base.

Reconnect the main steam and reheat steam inlets by installing new
gaskets in the inlet flanges.

Install the top seal rings and reconnect the IP to LP1/LP2 crossover
pipe.

Have the electricians connect thermocouple lead wires to the outer


casing cover.

Install the outer gland casing upper halves and secure them to the
HP-IP outer casing cover.

Thoroughly inspect and clean the bearing pedestals internally and


externally, then install the HP pedestal and No.2&3 bearing pedestal
covers.

All instrumentation removed for the turbine overhaul must now be


changed and checked to ensure satisfactory operation.

All removed insulation must be replaced.

Reinstall the removed fire extinguishing piping and the turbine


enclosure.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

5-43

Chapter 5

Disassembly and Reassembly


GOV. SIDE

GEN. SIDE

ICV
MAIN STEAM
INLET PIPE

MAIN STOP VALVE

ICV

HP-IP TURBINE

GV BODY

STEAM FLOW

RSV

"C"

DETAIL "I"

"F"

"I"

OPERATING FLOOR

OPERATING FLOOR

HP-IP TURBINE
RSV

HP-IP TURBINE
MAIN STEAM INLET PIPE
HOT REHEAT STEAM
INLET PIPE

D-D

G-G

MAIN STEAM INLET PIPE


HOT REHEAT STEAM INLET PIPE

A-A

"E"

E -E

MAIN STEAM INLET PIPE

"A"
"H"
ICV
MAIN STOP VALVE

MAIN STEAM
INLET SLEEVE

GV BODY

"B"

HP-IP TURBINE

ICV
RSV

RSV

HP-IP TURBINE

HP-IP TURBINE

CL OF TURBINE
OPERATING FLOOR

OPERATING FLOOR

HP-IP TURBINE

MAIN STEAM
INLET SLEEVE

MM-M05.01

Rev.001

HOT REHEAT STEAM INLET PIPE


MAIN STEAM INLET PIPE

VIEW "B"
VIEW "C"

HOT REHEAT STEAM INLET PIPE

VIEW "H"

VIEW "F"

MPTD-3-0240

FIGURE 5-1
Main Turbine
Mitsubishi

HP-IP TURBINE INLET STEAM PIPING

5-44

Chapter 5

IP BLADE RING

Disassembly and Reassembly

OUTER CASING

5
4

OUTER CASING

No.2 DUMMY RING


INNER CASING

IP BLADE RING
No.3 IP STATIONARY
BLADE RING

No.4 IP STATIONARY
BLADE RING

OUTER CASING

No.1 DUMMY RING

0.20 +- 0.05
20 +- 2

GLAND CASING

HIP ROTOR
GLAND CASING
OUTER CASING

GEN. SIDE

GOV. SIDE
IP BLADE RING

5
4

INNER CASING
No.1 DUMMY RING

MM-M05.01

Rev.001

No.2 IP STATIONARY
BLADE RING

No.1 IP STATIONARY
BLADE RING

4
5

1.5

1.5

NOZZLE BLOCK

No.2 HP STATIONARY
BLADE RING

No.1 HP STATIONARY
BLADE RING

MPTD-3-0241

FIGURE 5-2
Main Turbine
Mitsubishi

HP-IP TURBINE SHELL CLEARANCE

5-45

Chapter 5

Disassembly and Reassembly

0.5+-0.1

HIP ROTOR

OUTER CASING

GOV. SIDE

CL OF HIP ROTOR

GLAND CASING

GLAND CASING

0.5+- 0.1

0.5+- 0.1

HIP ROTOR

HIP ROTOR

MM-M05.01

Rev.001

SEAL STRIP

SEAL STRIP

NOTE: REFER TO FIGURE 5-8 FOR RADIAL SEAL CLEARANCES (X)

MPTD-4-0242

FIGURE 5-3
Main Turbine
Mitsubishi

HP TURBINE SHAFT GLAND DESIGN CLEARANCES


5-46

Chapter 5

Disassembly and Reassembly

OUTER CASING

GEN. SIDE

CL OF HIP ROTOR

MM-M05.01

Rev.001

NOTE: REFER TO FIGURE 5-8 FOR GLAND SEAL RADIAL CLEARANCES (X)

MPTD-4-0243

FIGURE 5-4
Main Turbine
Mitsubishi

IP TURBINE SHAFT GLAND DESIGN CLEARANCES

5-47

Chapter 5
INNER CASING

0.5+-0.1
0.13~0.2

SEAL RING

No.1 DUMMY RING

0.0~0.1

0.5+-0.1

1.6

SEAL RING

Disassembly and Reassembly

No.1 DUMMY RING

SEAL STRIP

SEAL STRIP

HIP ROTOR

SEAL STRIP

No.1 DUMMY RING


HIP ROTOR

C
L OF HIP ROTOR

GEN. SIDE
No.1 DUMMY RING

0.5+-0.1

0.5+-0.1

0.5+-0.1

0.5+-0.1

0.5+-0.1

0.5+-0.1
No.2 DUMMY RING

MM-M05.01

Rev.001

HIP ROTOR

SEAL RING

x
x

0.5+-0.1

0.5+-0.1

GOV. SIDE

SEAL STRIP
SEAL RING

MPTD-3-0244

HIP ROTOR

NOTE: REFER TO FIGURE 5-8 FOR SEAL RADIAL CLEARANCES (X)

FIGURE 5-5
Main Turbine
Mitsubishi

SEAL STRIP

NO.1 & NO.2 DUMMY RINGS DESIGN CLEARANCES

5-48

Disassembly and Reassembly

SEAL STRIP

5C

4C

9C

8C

SEAL STRIP

ROTATING
BLADE

7C

6C

3C

2C

1C

Chapter 5

ROTATING
BLADE

ROTATING
BLADE

SEAL STRIP
RATEAU
STAGE BLADE

ROW No.

12.5+1.5
-0.5
E

3C

4C

1R

2R

3R

+1.5
-0.5

5C

6C

7C

A
B

8C

9C

A
B

LOCATION

4R

5R

6R

8R

7R

9R

GEN. SIDE

GOV. SIDE

SEAL STRIP

ROTATING
BLADE

ROTATING
BLADE

SEAL STRIP

2R

3R

4R

5R

6R

7R

MM-M05.01

Rev.001

1R

SEAL STRIP

NOTE: REFER TO FIGURE 5-8 FOR SEAL RADIAL CLEARANCES (X)


MPTD-3-0245

FIGURE 5-6
Main Turbine
Mitsubishi

1
2
3
4
NO.2 HP STATIONARY 5
BLADE RING
6
7
NO.1 HP STATIONARY 8
BLADE RING
9
NO.1 DUMMY RING

ROTOR BLADES
INLET
OUTLET
A
B
E
F
11.9 12.7 7.3 8.1
11.9 12.7 7.3 8.1
11.9 12.7
38.1
11.9 12.7 7.3 8.1
11.9 12.7 7.3 8.1
11.9 12.7 13.6 14.4
56.2
11.9 12.7
11.9 12.7 7.3 8.1
_
11.9 12.7

12

1C

2C

HIP ROTOR

Right Side Left Side

12+-0.0

8R

9R
ROTATING
BLADE

HP TURBINE - ROTOR & CASING DESIGN CLEARANCES

5-49

Disassembly and Reassembly

3C

4C

5C

Chapter 5

2C

1C

6C
SEAL STRIP

SEAL STRIP

ROTATING
BLADE

SEAL STRIP

ROTATING
BLADE

ROTATING
BLADE

E
8C

8R

6C

7R

4C

5R

3C

2C

A
B

6R

8C
7C

5C

4R

3R

LOCATION

2R

1R

1C

IP No.1 STATIONARY
BLADE RING

IP No.2 STATIONARY
BLADE RING

ROTATING
BLADE

SEAL STRIP

IP No.3 STATIONARY
BLADE RING
IP No.4 STATIONARY
BLADE RING

GEN. SIDE

1
2
3
4
5

ROTOR BLADES
INLET
OUTLET
A
B
E
F
24 11.5 23.6 17.1
27.3 8.5
47.1
27.3 8.5 29.9 17.1
21.0 8.5 23.6 17.1
32.8 8.5
47

6 21.0

8.5

60.1

7 21.0 8.5 23.6 17.1


8 33.6 10.1

GOV. SIDE

4R

3R
2R

5R

7R

8R

ROW No.

7C

1R

6R
x

SEAL STRIP

SEAL STRIP

HIP ROTOR

MM-M05.01

Rev.001

HIP ROTOR
SEAL STRIP

SEAL STRIP

HIP ROTOR

HIP ROTOR

MPTD-3-0246

FIGURE 5-7
Main Turbine
Mitsubishi

IP TURBINE - ROTOR & CASING DESIGN CLEARANCES

5-50

Chapter 5

Disassembly and Reassembly

RADIAL SEAL CLEARANCE TABLE (COLD SET/DESIGN


VERTICAL DIRECTION
AFT. ASS'Y
CASING DEFLEC.

NOMINAL CLEA.
LOCATION

LENGTH

SEAL RING (1)


SEAL RING (2)
SEAL RING (1)
SEAL RING (2)
SEAL RING (1)
SEAL RING (2)
SEAL RING (3)
HP 9 R
HP 9 C
HP 8 R
HP 8 C
HP 7 R
HP 7 C
HP 6 R
HP 6 C
HP 5 R
HP 5 C
HP 4 R
HP 4 C
HP 3 R
HP 3 C
HP 2 R
HP 2 C
HP 1 R
HP 1 C

460.75
578.75
676.75
761.75
866.50
943.50
1013.50
1353.30
1408.15
1455.65
1503.55
1601.70
1656.65
1712.95
1764.65
1814.75
1866.45
1916.55
1968.25
2048.35
2100.05
2150.15
2201.85
2251.95
2303.65
2466.50
2928.75
3001.75
3083.75
3156.75
3229.75
3385.75
3847.10
3972.30
4067.40
4171.20
4302.60
4406.40
4500.95
4591.35
4679.55
4785.15
4917.55
5007.90
5139.15
5229.50
5317.75
5429.95
5632.87
5732.87
5843.87
5965.37
866.50
943.50
3001.75

0.65
0.65
0.60
0.60
1.40
1.20
0.70
0.85
0.65
0.90
0.65
0.90
0.65
0.90
0.65
0.90
0.65
0.90
0.65
0.80
0.65
0.80
0.65
0.80
0.65
1.00
0.85
1.55
0.85
0.85
0.85
0.95
0.40
0.80
0.60
0.80
0.60
0.95
0.60
1.05
0.60
1.10
0.60
1.05
0.60
1.05
0.60
1.10
0.60
0.60
0.60
0.60
0.40
0.40
0.55

0.65
0.65
0.60
0.60
1.40
1.20
0.70
0.85
0.65
0.90
0.65
0.90
0.65
0.90
0.65
0.90
0.65
0.90
0.65
0.80
0.65
0.80
0.65
0.80
0.65
1.00
0.85
1.55
0.85
0.85
0.85
0.95
0.40
0.80
0.60
0.80
0.60
0.95
0.60
1.05
0.60
1.10
0.60
1.05
0.60
1.05
0.60
1.10
0.60
0.60
0.60
0.60
0.40
0.40
0.55

0.02
0.01
-0.01
-0.01
-0.02
-0.03
-0.04
-0.07
-0.07
-0.08
-0.08
-0.09
-0.09
-0.10
-0.10
-0.10
-0.11
-0.11
-0.11
-0.12
-0.12
-0.12
-0.12
-0.13
-0.13
-0.13
-0.14
-0.14
-0.14
-0.14
-0.14
-0.14
-0.13
-0.12
-0.12
-0.11
-0.11
-0.10
-0.10
-0.09
-0.09
-0.08
-0.07
-0.07
-0.06
-0.05
-0.05
-0.04
-0.02
-0.01
0.01
0.03
0.02
-0.03
-0.14

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

ELEMENT

OUTER GLAND
(GOV. END)
INNER GLAND
(GEN. END)
NO.2 DUMMY
RING
HP8~9C
DIAPHRAGM

HP4~7C
DIAPHRAGM

NO.1
DUMMY RING

HP NOZZLE

SEAL RING (1)


SEAL RING (2)
SEAL RING (3)
NO.1
DUMMY RING SEAL RING (4)
SEAL RING (5)
SEAL RING (6)
IP 1 C
IP 1 R
IP1 ~ 2C
DIAPHRAGM
IP 2 C
IP 2 R
IP 3 C
IP 3 R
IP3 ~ 5C
IP 4 C
DIAPHRAGM
IP 4 R
IP 5 C
IP 5 R
IP6C
IP 6 C
DIAPHRAGM
IP 6 R
IP 7 C
IP 7 R
IP7 ~ 8C
DIAPHRAGM
IP 8 C
IP 8 R
SEAL RING (2)
INNER GLAND
(GEN. END)
SEAL RING (1)
SEAL RING (2)
OUTER GLAND
(GEN. END)
SEAL RING (1)
ACC SEAL 1
NO.2
DUMMY RING
ACC SEAL 2
NO.1 DUMMY RING ACC SEAL 2

AFT. BOTTOM ASS'Y

HORIZONTAL DIRECTION
AFT. ASS'Y
CASING DEFLEC.

NOMINAL CLEA.
23

24

NOTE:
1. RADIAL CLEARANCES AT ASSEMBLY OF HIP TURBINE
IS AS SHOWN IN THIS DRAWING IN CASE THAT SETTING
OF EACH PART AND DEFLECTION OF THE ROTOR IS
TAKEN INTO ACCOUNT.

10

11

2. THE BASIS OF RADIAL CLEARANCE SETTING


IN THIS DRAWING IS SETTING BORE.

10 11

+0.15
-0.05

+0.10
-0.05

+0.15
-0.05
+0.10
-0.05

21

22

0.65
0.65
0.60
0.60
0.70
0.70
0.70
0.65
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.60
0.65
0.60
0.65
0.60
0.65
1.00
0.85
0.85
0.85
0.85
0.85
0.95
0.40
0.60
0.60
0.60
0.60
0.75
0.60
0.85
0.60
0.90
0.60
0.85
0.60
0.85
0.60
0.90
0.60
0.60
0.60
0.60
0.70
0.70
0.85

0.65
0.65
0.60
0.60
0.70
0.70
0.70
0.65
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.60
0.65
0.60
0.65
0.60
0.65
1.00
0.85
0.85
0.85
0.85
0.85
0.95
0.40
0.60
0.60
0.60
0.60
0.75
0.60
0.85
0.60
0.90
0.60
0.85
0.60
0.85
0.60
0.90
0.60
0.60
0.60
0.60
0.70
0.70
0.85

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

Y
-

+
+

RIGHT SIDE CLEARANCE

Rev.001

ROTATION

MM-M05.01

26

27

28

0.65
0.65
0.60
0.60
0.70
0.70
0.70
0.65
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.60
0.65
0.60
0.65
0.60
0.65
1.00
0.85
0.85
0.85
0.85
0.85
0.95
0.40
0.60
0.60
0.60
0.60
0.75
0.60
0.85
0.60
0.90
0.60
0.85
0.60
0.85
0.60
0.90
0.60
0.60
0.60
0.60
0.70
0.70
0.85

0.65
0.65
0.60
0.60
0.70
0.70
0.70
0.65
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.60
0.65
0.60
0.65
0.60
0.65
1.00
0.85
0.85
0.85
0.85
0.85
0.95
0.40
0.60
0.60
0.60
0.60
0.75
0.60
0.85
0.60
0.90
0.60
0.85
0.60
0.85
0.60
0.90
0.60
0.60
0.60
0.60
0.70
0.70
0.85

3. CLEARANCE AT ASSEMBLY OF HIP TURBINE IS CALCULATED


BY THE FOLLOWING EQUATIONS.
HOWEVER, SIGNS OF MOVEMENT AND DEFLECTION ARE
TO BE AS SHOWN BELOW.

TOP CLEARANCE

* RIGHT AND LEFT SIDE CLEARANCES ARE SHOWN


IN CASE THAT THE VIEW IS FROM GOVERNOR
SIDE TO GENERATOR SIDE.

LEFT SIDE CLEARANCE

25

AFT. BOTTOM ASS'Y

29
30
29 30
ROTOR AFT. ASY AFT. ASY CASING CASING AT SET. AT SET.
FROM
AFT. ASY AFT. ASY CASING CASING AT SET. AT SET. TOLERANCE
NOMINAL NOMINAL ELEMENT ROTOR
NOMINAL NOMINAL ELEMENT ROTOR
TOLERANCE
No.1 BRG. TOP
SETTING SETTING RIGHT
LEFT
DEFLEC. DEFLEC. RIGHT
BOTTOM SETTING DEFLEC. SETTING TOP
LEFT
BOTTOM
RIGHT
LEFT
BOTTOM DEFLEC. DEFLEC. TOP
LEFT
CLEARA. CLEARA.
CLEARA. CLEARA.
CLEARA. CLEARA.
CLEARA. CLEARA. RIGHT
BOTTOM CLEARA. CLEARA.
CLEARA. CLEARA. TOP
6

+0.15
-0.05

+0.10
-0.05

+0.15
-0.05
+0.10
-0.05

a) AFTER COMPLETION OF ASSEMBLY:


6 = 1 + 3 - 4
TOP CLEARANCE
BOTTOM CLEARANCE 7 = 1 + 2 - 6
RIGHT SIDE CLEARANCE 25 = 21 + 23 LEFT SIDE CLEARANCE 26 = 21 + 22 -

- 5
24
25

b) AT MEASUREMENT WITH LEAD WIRE:


10 = 6 - 8
TOP CLEARANCE
11 = 7 + 9
BOTTOM CLEARANCE
RIGHT SIDE CLEARANCE 29 = 25 - 27
LEFT SIDE CLEARANCE 30 = 26 + 28

BOTTOM CLEARANCE

MPTD-3-0247

FIGURE 5-8
Main Turbine
Mitsubishi

HP-IP TURBINE BLADE & GLAND SEALS RADIAL CLEARANCE TABLE

5-51

Chapter 5

10

10

Disassembly and Reassembly

10

15

13
8

G
I
2

8
1

A-A

B-B

1
7

12

12

3
"X"

C
B

13

13

14

14
6

10
3

2
10

15
10

11

15

DETAIL "X"

IP BLADE RING SUPPORT

"Y"

DETAIL "Y"
INNER CASING SUPPORT

15

16

C-C

20

15

THERMAL SHIELD SUPPORT

18

17
17
3

16

3
15

15

DETAIL "Z"
14

18

17

17

MM-M05.01

Rev.001

17

16
17

18

2
6

19

15

20

"Z"

4
NO.1 DUMMY RING SUPPORT

HP STATIONARY BLADE RING SUPPORT

NO.2 DUMMY RING SUPPORT


MPTD-3-0230

FIGURE 5-9
Main Turbine
Mitsubishi

SUPPORT DETAILS FOR THE HP-IP TURBINE PARTS AT HORIZONTAL JOINT

5-52

Disassembly and Reassembly

MPTD-4-0249
MPTD-4-0248

MM-M05.01

Rev.001

Chapter 5

FIGURE 5-10
Main Turbine
Mitsubishi

HP-IP ROTOR GUIDE PILLAR LOCATION

5-53

Chapter 5

5.2

Disassembly and Reassembly

LP1 Turbine Disassembly and Reassembly


a)

Preparation
If LP1 turbine disassembly becomes necessary, all associated equipment
must be mechanically and electrically isolated and an authorized
clearance and work permit must be in place prior to the commencement of
work. The following points must also to be considered when preparing for
disassembly and reassembly:

Have all necessary drawings (assembly drawings, sectional drawings,


part details, etc.) and documents (log sheets, field record book, etc.)
ready prior to start of work.

Prepare the necessary handling facilities (crane facilities, temporary


supports etc.) to remove and store the various parts of the steam
turbine.

Co-ordinate with the Instrument and Control (I&C) Department to


remove all the attached instruments before starting disassembly
work.

Special tools are listed in Appendix C.

Do not stand below the lifted turbine parts. There can be


danger of an accident due to components falling down.

CAUTION
Spigot joints between the turbine stationary components
(such as outer and inner casings, blade rings, etc.) could bind
due to scale formation during operation under the high
temperature environment.

CAUTION

MM-M05.01

Rev.001

The binding mentioned above may require additional jacking


or crane load which could exceed the dead weight of the
concerned components as the components are separated or
lifted apart. This could cause surface damage such as seizure,
galling or scoring. Take due care and initiate any special
measures necessary when separating or lifting the steam
turbine and binding is apparent or suspected.

Main Turbine
Mitsubishi

5-54

Chapter 5

Disassembly and Reassembly

CAUTION
Personnel working inside the turbine should not carry any
loose items in the pockets and should take special care not to
drop tools or debris into the turbine.

CAUTION
Any surface irregularity or damage caused by the reasons
described above, must be ground off smoothly, or
reconditioned by build-up welding and facing to reinstate the
original surface finish and clearance if any between mating
parts.

CAUTION
Wear proper goggles and face masks when working on the
insulation. Insulation material is harmful to the respiratory
system.

b)

Disassembly
Refer to Figures 2-8 and E-2.

Preparation for Disassembly


1

During normal operation, before the Unit is shut down for overhaul,
perform a thorough external visual inspection of the entire turbine unit
to detect any obvious deficiencies. These are to be rectified during
the turbine overhaul.

Prepare an area for the abrasive blasting of the turbine components.

Note
Label and identify all components as they are disassembled.
Tag and bag all hardware and fasteners with the associated

MM-M05.01

Rev.001

components and store in the designated area.

Main Turbine
Mitsubishi

Prepare a lay-down area for the turbine components including the


turbine rotor cradles.

Remove the insulation from the IP turbine exhaust to LP1 and LP2
turbines steam inlet flanges.

5-55

Chapter 5

Disassembly and Reassembly

Refer to Figure 2-14. Remove the nuts from the flange joints and then
remove the crossover piping connecting the IP exhaust to the LP1
and LP2 turbines inlet. Remove the top seal ring from between the
LP1 inner and outer casings.

Removal of LP1 Outer Casing Cover


1

Have the electricians remove the thermocouple lead wires.

Label all LP1 outer casing cover bolts and nuts.

Loosen the flange bolts on all LP1 outer casing manhole covers.

Install eye bolts in the manhole covers.

Install lifting gear to the eye bolts.

Support the weight of the manhole covers using the lifting gear.

Remove the bolts and the manhole covers.

Transport the manhole covers to the lay-down area.

Remove the Gov End and Gen End shaft upper half gland casings
and remove the seal rings from the gland casings into storage.

Note
The following steps 10~15, to disassemble the Gov End and
Gen End exhaust flow guides are performed inside the outer
casing. Refer to Figure 5-18.

10 Disconnect the exhaust hood spray nozzle piping secured to the


exhaust flow guide by disconnecting the pipe unions.
11 Connect the lifting gear to the exhaust flow guide upper half.
12 Install chain blocks between the exhaust flow guide upper half and
the eye plate.
13 Remove all flange bolts from the exhaust flow guide upper half except
for four bolts adjacent to the jack screws.

Rev.001

14 Adjust the lifting gear to support the weight of exhaust flow guide
upper half, and alternately tighten the jack screws and loosen the
adjacent bolts until the locating eccentric pins have been pulled free
from the inner casing.

MM-M05.01

15 Remove the jackscrews from the flange, lift the exhaust flow guide
upper half, and fasten it securely to the inside of the outer casing
cover.
16 Remove the horizontal joint bolts from the LP1 outer casing base.
Main Turbine
Mitsubishi

5-56

Chapter 5

Disassembly and Reassembly

17 Install jack screws in the outer casing cover horizontal joint flange and
manually tighten to contact the outer casing base horizontal joint
face.
18 Turn the jack screws half a turn at a time to open the horizontal joint,
maintaining equal loading on the jack screws and equal gap at the
horizontal joint opening.

Note
During operation of the turbine, oxides and deposits
accumulate between the mating surfaces of the casings. The
forces required to separate these surfaces may be noticeably
greater than those required to suspend the weight of the outer
casing cover.

19 Install the lifting gear to the LP1 outer casing cover in accordance
with Appendix H.
20 Tension the wire ropes and position the hook over the center of
gravity, make a trial lift and adjust the lifting equipment until an even
lift is achieved.

CAUTION
Follow the upward motion of the LP1 outer casing with the
crane attached to the lifting device. Do not overload the lifting
cables.
21 Attach a tag line to each end of the LP1 outer casing cover to control
any rotation of the casing during the lift.
22 Evenly raise the LP1 outer casing cover in small increments until it
stands clear of the bolts.
23 Lift the LP1 outer casing cover clear of the turbine and transport it to
the lay-down area.
24 Set wooden supports on the floor to support the outer casing cover.
25 Protect the horizontal joints of the LP1 outer casing cover.
26 Lower the LP1 outer casing cover onto the wooden supports.
27 Disconnect and remove the lifting gear.

Rev.001

Note
Ensure that the openings in the lower half turbine exposed by
the removal of the outer casing cover are protected. It is

MM-M05.01

recommended that a material exclusion area be established


around the turbine to prevent entry of foreign material into the
turbine.

Main Turbine
Mitsubishi

5-57

Chapter 5

Disassembly and Reassembly

Removal of LP1 Inner Casing Cover

CAUTION
When working in or over the condenser plenum, take special
care not to drop tools or debris into the condenser tube area.
Damage to the condenser tubes could result in condenser tube
leakage.
1

Match mark and remove the access cover plates to expose the
internal horizontal joint bolts.

Note
Refer to Appendix F to identify the horizontal joint bolts, and
to determine the required bolt heater type and size. Remove
the bolts from both LS and RS of the LP1 inner casing starting
at the transverse centerline of both LS and RS, working
outwards toward each end. Remove the bolts parallel to the
transverse axis starting at the extreme end and working
towards the turbine longitudinal axis.

Mark nuts with their respective number and indicate RS or LS.

Bolt heaters are electrical devices capable of causing personal


injury or death if improperly used.

Using four bolt heaters (two on each side), heat the bolts 213 224 in
accordance with Bolt Heater Instruction in Appendix I, avoiding
heating adjacent bolts, and loosen the nuts from both the RS and LS
of the casing in the following sequence:
(i)

213 toward 217 and 219 toward 224

(ii) Reamer bolt 218.

Note
Rev.001

To avoid heating the casing flange excessively, frequently


loosen the nuts. As soon as the nuts are loosened and the bolt

MM-M05.01

heaters have cooled sufficiently, remove the bolt heaters.

Main Turbine
Mitsubishi

5-58

Chapter 5

Disassembly and Reassembly

Remove the nuts as follows:


(i)

Install safety hoist ring and copper washer into the nut to be
removed.

(ii) Connect suitable lifting gear to the safety hoist ring and remove
the nuts.
5

Loosen and remove the nuts from bolts 201 212 and 225 272 in
the following sequence:

Note
Bolts 201 212 and 225 272 do not have provision for a bolt
heater.

(i)

Bolts 202 212, 225 235

(ii) Bolts 237 241, 243 251, 253 263, 265 271
(iii) Reamer bolts 201 and 236
(iv) Reamer bolts 242, 252, 264 and 272.
6

Inspect and clean the jackscrew threads.

Lubricate and install jackscrews into the inner casing cover horizontal
joint flange and hand tighten until contact is made with the inner
casing base horizontal joint flange.

Note
During the operation of the turbine, oxides and the deposits
accumulate between the mating surfaces of the casings. The
forces required to separate these surfaces may be noticeably
greater than those required to suspend the weight of the inner
casing cover.

Install the inner casing guide bolts (supplied as Special Tools) on the
inner casing base as indicated in Figure 5-17.

Turn the jack screws half a turn at a time to open the horizontal joint
and maintain an equal gap at the horizontal joint openings.

10 Install the appropriate lifting gear to the inner casing cover.

CAUTION

MM-M05.01

Rev.001

Follow the upward motion of the inner casing cover with the
crane attached to the lifting device. Do not overload the lifting
cables.

Main Turbine
Mitsubishi

5-59

Chapter 5

Disassembly and Reassembly

11 Continue turning the jack screws, ensuring equal distance at all


points, until the inner casing cover is raised approximately 10 mm.
12 With the hook over the center of gravity, tension the wire ropes.
13 Make a trial lift to make sure that the cover horizontal joint is parallel
to the base horizontal joint.
14 Attach tag lines to each end of the inner casing cover to control any
rotation of the cover during the lift.
15 Evenly raise the inner casing cover in small increments until the cover
is clear of the stud bolts.
16 Transport the inner casing cover to the lay-down area.

Note
Ensure that the openings left by the removal of the inner
casing cover are protected.

17 Protect the horizontal joint of the inner casing cover.


18 Lower the inner casing cover onto wooden blocks.
19 Disconnect and remove the lifting gear.

Removal of LP1 Steam Chamber Cover

CAUTION
When working in or over the condenser plenum, take special
care not to drop tools or debris into the condenser tube area.
Damage to the condenser tubes could result in tube leakage.
1

Match mark and remove the access cover plates to expose the
internal horizontal joint bolts.

Note
Refer to Appendix F to identify the bolts and determine the

Rev.001

required torque values.

Mark nuts with their respective number and indicate RS or LS.

Loosen and remove the nuts and washers from bolts 301 318 in the
following sequence:

MM-M05.01

(i)

Bolts 302 308 and 311 317

(ii) Reamer bolts 301, 309, 310 and 318.


Main Turbine
Mitsubishi

5-60

Chapter 5

Disassembly and Reassembly

Note
Bolts 301 318 do not have provision for a bolt heater.

Lubricate and install jackscrews in the steam chamber cover


horizontal joint flange, and hand tighten until contact is made with the
steam chamber base horizontal joint flange.

Note
During the operation of the turbine, oxides and the deposits
accumulate between the mating surfaces of the steam
chamber. The forces required to separate these surfaces may
be noticeably greater than those the required to suspend the
weight of the steam chamber cover.

Turn the jack screws half a turn at a time to open the horizontal joint
and maintain an equal gap at the horizontal joint openings.

Install eyebolts and connect suitable lifting gear to the steam


chamber cover.

CAUTION
Follow the upward motion of the steam chamber cover while
the crane is hoisting. Do not overload the wire rope slings.

Continue turning the jack screws, measuring for equal distance at all
points until the steam chamber cover is raised approximately 10 mm.

With the hook over the center of gravity, tension the wire ropes.

Make a trial lift to confirm that the cover horizontal joint is parallel to
the base horizontal joint.

10 Attach tag lines to each end of the steam chamber cover to control
any rotation of the steam chamber during the lift.
11 Evenly raise the steam chamber cover in small increments until the
cover is clear of the bolts.
12 Transport the steam chamber cover to the lay-down area.

Note

Rev.001

Ensure that the openings left in the LP1 casing are covered.

13 Protect the horizontal joint of the steam chamber cover.

MM-M05.01

14 Lower the steam chamber cover onto wooden blocks.


15 Disconnect and remove the lifting gear.
Main Turbine
Mitsubishi

5-61

Chapter 5

Disassembly and Reassembly

Removal of LP1 Blade Ring Upper Halves


1

Label the Gov End LP1 blade ring bolts and nuts with their respective
numbers and indicate RS or LS.

Loosen and remove the nuts and washers from bolts 401 403 in the
following sequence:
(i)

Bolts 402 and 403

(ii) Reamer bolt 401.


3

Install eye bolts into the LP1 blade ring upper half and tighten.

Lubricate and install jackscrews in the LP1 blade ring upper half
horizontal joint flange, and hand tighten until contact is made with the
lower half flange.

Note
During the operation of the turbine, oxides and the deposits
accumulate between the mating surfaces of the blade ring.
The forces required to separate these surfaces may be
noticeably greater than those the required to suspend the
weight of the upper half blade ring.

Turn the jack screws half a turn at a time to open the horizontal joint
and maintain an equal gap at the horizontal joint openings.

Connect suitable lifting gear to the blade ring upper half and make a
trial lift.

Adjust the chain blocks to evenly lift the blade ring upper half.

Set support blocks on the floor.

CAUTION
Carefully lift the upper half blade rings from the turbine
casings to avoid contact between the stationary and rotating
blades.

Rev.001

Lift the blade ring clear of the lower half joint bolts and transport it to
the lay-down area.

10 Disconnect and remove the lifting gear.

MM-M05.01

11 Using a similar procedure, remove the Gen End LP1 blade ring upper
half after removing the horizontal joint nut from bolts 404 406.

Main Turbine
Mitsubishi

5-62

Chapter 5

Disassembly and Reassembly

Removal of LP1 Inner Flow Guide Ring Upper Half


1

Remove the nuts and washers from the horizontal joint studs which
secure the LP1 inner flow guide ring upper half to the lower half.

Install eye bolts into the LP1 inner flow guide ring upper half and
tighten.

Lubricate and install jackscrews in the upper half inner flow guide ring
and hand tighten until contact is made with the lower half flange.

Turn the jack screws half a turn at a time to open the horizontal joint
and maintain an equal gap at the horizontal joint openings.

Connect suitable lifting gear to the upper half flow guide ring and
make a trial lift.

Adjust the chain blocks to evenly lift the upper half inner flow guide
ring.

Set support blocks on the floor.

Lift the upper half inner flow guide ring clear of the lower half joint
bolts and transport it to the lay-down area.

Disconnect and remove the lifting gear.

Setting LP1 Rotor in the K Position


Refer to Figure 5-14.
Position the rotor axially in the K position (Right Side: 24.5 0.0 mm; Left
Side: 24.5+1.5/-0.5 mm).

Note
As all axial clearances are based on the correct setting of the
rotor in the K position, the target tolerance is 0 mm.

Measurement of LP1 Shaft Gland Clearances


Refer to Figures 5-12 and 5-13.

MM-M05.01

Rev.001

Measure and record the clearances between the LP1 Gov End and Gen
End shaft glands and the surface of the rotor at the RS and LS as
described in the mechanical maintenance manual M 05.03, Gland
Steam Condenser System and GSC Exhaust Fan.

Main Turbine
Mitsubishi

5-63

Chapter 5

Disassembly and Reassembly

Measurement of LP1 Rotor and Casing Clearances


Refer to Figures 5-14 and 5-15.

Note
Measure and record the following clearances at the RS and LS.

Measure and record the axial clearance (A) between the base of the
Gov End first stage stationary blade outlet and the shroud of the first
stage rotating blade inlet.

Note
Clearance A for the Gov End first stage is clearance K.

Repeat Step 1 above for the second through seventh stages.

Measure and record the clearance B between the end of the first
stage stationary blade outlet and the base of the first stage rotating
blade inlet.

Repeat Step 3 above for the second through seventh stages.

Measure and record the clearance E between shroud of the first


stage rotating blade outlet and the base of the second stage
stationary blade inlet.

Repeat Step 5 above for the second through fourth stages.

Measure and record the clearance F between the base of the first
stage rotating blade outlet and the end of the second stage stationary
blade inlet.

Repeat Step 7 above for the second through sixth stages.

Measure and record the rotating and stationary blading seal strip
radial clearances.

Note
If the seal strip clearances exceed 200% of the design
clearances, seal strip replacement should be considered.

MM-M05.01

Rev.001

10 Repeat the above procedure to measure the LP1 Gen End rotor and
casing clearances.

Main Turbine
Mitsubishi

5-64

Chapter 5

Disassembly and Reassembly

Removal of LP1 Rotor


Refer to Figure 5-17.
1

Ensure that the LP rotor support stand is assembled in the lay-down


area.

Note
Before attempting to remove the rotor, it is necessary to
remove other equipment to eliminate interference or provide
clearance.

Have the electricians remove the vibration pick-ups.

Remove the covers from No.2&3 and No.4&5 bearing pedestals,


coupling cooling oil lines, upper half of the coupling guards, coupling
bolts and coupling spacers from the HP-IP~LP1 and LP1~LP2
couplings in accordance with the mechanical maintenance manual
M 05.05, Turbine Couplings and Alignment.

Remove the upper halves of No.3 and No.4 bearings in accordance


with mechanical maintenance manual M 05.04, Turbine Bearings
and Thrust Bearing.

Install the LP rotor guide pillars (supplied as Special Tools) at the Gov
End and Gen End of the outer casing base, as shown in Figure 5-17.

Confirm that there is clearance between the HP-IP and LP1 coupling
flange faces.

Confirm that there is clearance between the LP1 and LP2 coupling
flange faces.

Install the LP rotor lifting gear to the LP1 rotor as shown in Appendix
H.

Adjust the wire rope slings from the center of the lifting beam to lift the
rotor evenly.

10 Using the turn buckle, level the rotor with a machinist spirit level.
11 Lift the LP1 rotor high enough to make sure that there is sufficient
axial clearance for the rotor removal.

MM-M05.01

Rev.001

12 Tie a tag line to each end of the LP1 rotor to allow control of the rotor
during the lift.

Main Turbine
Mitsubishi

5-65

Chapter 5

Disassembly and Reassembly

CAUTION
Slow and careful removal of the LP rotor must be performed to
ensure that damage does not occur to the rotor or casing
blades.
13

Lift the LP1 rotor in small increments and ensure that no binding
occurs.

14

Lift the LP1 rotor clear of the turbine.

15
16

Transport the LP1 rotor to the lay-down area.


Lubricate the rotor support stand saddles and set the LP1 rotor in
the support stand.

Note
Ensure that the rotor journals are protected prior to setting the
rotor in the support stand.

17 Remove the lower halves of No.3 and No.4 bearings.

Removal of LP1 Inner Flow Guide Ring Lower Half


1

Remove the set screws and then remove the nuts from the inner flow
guide ring fixing studs which secure the lower half inner flow guide
ring to the lower half steam chamber. Refer to Figure 5-19 for details.

Install eye bolts in the inner flow guide ring lower half.

Install suitable lifting gear and make a trial lift.

Adjust the chain blocks to evenly lift the inner flow guide ring.

Set support blocks on the floor.

Lift the inner flow guide ring clear of steam chamber.

Transport the inner flow guide ring to the lay-down area and set it on
wooden blocks.

Disconnect and remove the lifting gear.

MM-M05.01

Rev.001

Removal of LP1 Blade Ring Lower Halves

Main Turbine
Mitsubishi

Install eye bolts in the lower half LP1 blade ring at the Gov End.

Install suitable lifting gear and make a trial lift.

Adjust the chain blocks to evenly lift the blade ring.

5-66

Chapter 5

Disassembly and Reassembly

Set support blocks on the floor.

Lift the lower half blade ring clear of the steam chamber base.

Transport the blade ring to the lay-down area and set it on wooden
blocks.

Disconnect and remove the lifting gear.

Following a similar procedure, remove the lower half LP1 blade ring
at the Gen End.

Removal of LP1 Steam Chamber Base


1

Remove the hexagonal socket head bolts which secure the steam
chamber base to the inner casing base.

Install eye bolts in the steam chamber base.

Install suitable lifting gear and make a trial lift.

Adjust the chain blocks to evenly lift the steam chamber base.

Set support blocks on the floor.

Lift the steam chamber base clear of the inner casing base.

Transport the steam chamber base to the lay-down area and set it on
wooden blocks.

Disconnect and remove the lifting gear.

Removal of LP1 Inner Casing Base


Remove the nuts from the stud bolts which secure the inner casing
base to the outer casing base.

Install suitable lifting gear and make a trial lift.

Adjust the chain blocks to evenly lift the inner casing.

Set support blocks on the floor.

Transport the inner casing base to the lay-down area and set it on
wooden blocks.

Disconnect and remove the lifting gear.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

5-67

Chapter 5

c)

Disassembly and Reassembly

Cleaning and Inspection


LP1 Outer Casing
1

Manually clean the following areas and the associated bolts and nuts:
(i)

Horizontal joint flanges

(ii) Manhole flanges


(iii) Breakable diaphragm areas.
2

Visually inspect the following areas for erosion, wear, steam cuts,
cracks, or other damage:
(i)

Cover (horizontal joint)

(ii) Base (horizontal joint)


(iii) Outer casing to inner casing fits
(iv) Crossover pipe flange and top seal ring
(v) Manholes
(vi) Breakable diaphragm seating surfaces.

Note
Any discrepancies found should be corrected by stoning or
honing.

Perform NDT on the following areas:


(i) Cover (horizontal joint)
(ii) Base (horizontal joint)
(iii) Joint bolts
(iv) Steam penetrations.

Visually inspect the threaded portions of the joint bolts for


deformation, galling, binding, or excessive wear.

LP1 Inner Casing


1

Inspect all seal strips for rubs or other signs of damage.

Rev.001

Note

MM-M05.01

Replace seal strips if damaged.

Main Turbine
Mitsubishi

Hand clean the horizontal joint flanges and seals.

Visually inspect the following areas for erosion, wear, steam cuts,
cracks, or other damage:

5-68

Chapter 5

(i)

Disassembly and Reassembly

Cover (horizontal joint)

(ii) Base (horizontal joint)


(iii) Stationary blade diaphragms
(iv) Inner casing to outer casing and steam chamber fits
(v) Steam penetrations.

Note
Any discrepancies found should be corrected by stoning or
honing.

Perform NDT on the following areas:


(i)

Cover (horizontal joint)

(ii) Base (horizontal joint)


(iii) Stationary blades
(iv) Remainder of the stationary blade diaphragms
(v) Joint bolts
(vi) Steam penetrations.
5

Visually inspect the threaded portions of the joint bolts for


deformation, galling, binding or excessive wear.

Visually inspect the stationary blade diaphragms to inner casing fits


and the packing strips for looseness and wear.

Visually inspect the inner casing drains for blockage.

LP1 Steam Chamber


1

Hand clean the horizontal joint flanges.

Visually inspect the following areas for erosion, wear, steam cuts,
cracks, or other damage:
(i)

Cover (horizontal joint)

(ii) Base (horizontal joint)

Rev.001

(iii) Steam chamber to inner casing, LP blade ring and inner flow
guide fits

MM-M05.01

(iv) Steam penetrations.

Main Turbine
Mitsubishi

5-69

Chapter 5

Disassembly and Reassembly

Note
Any discrepancies found should be corrected by stoning or
honing.

Perform NDT on the following areas:


(i)

Cover (horizontal joint)

(ii) Base (horizontal joint)


(iii) Remainder of the steam chamber
(iv) Joint bolts
(v) Steam penetrations.
4

Visually inspect the threaded portions of the joint bolts for


deformation, galling, binding or excessive wear.

LP1 Blade Rings


Perform all measurements for the Gov End and Gen End blade rings.
1

Inspect all seal strips for rubs or other signs of damage.

Note
Replace seal strips if damaged.

Hand clean the horizontal joint flanges and seals.

Visually inspect the following components for erosion, wear, steam


cuts, cracks, or other damage:
(i)

Upper half (horizontal joint)

(ii) Lower half (horizontal joint)


(iii) Stationary blades
(iv) LP1 blade ring to steam chamber fits.

Note
Any discrepancies found should be corrected by stoning or
honing.

Perform NDT on the following areas:

Rev.001

(i)

Upper half (horizontal flanges)

MM-M05.01

(ii) Lower half (horizontal flanges)


(iii) Joint bolts

Main Turbine
Mitsubishi

5-70

Chapter 5

Disassembly and Reassembly

(iv) Stationary blades


(v) Remainder of the blade ring.
5

Visually inspect the stationary blade diaphragms to LP1 blade ring fits
and packing strips for looseness and wear.

Visually inspect the threaded portions of the joint bolts for


deformation, galling, binding or excessive wear.

LP1 Inner Flow Guide Ring


1

Inspect all seal rings for rubs or other signs of damage.

Note
Replace seal rings if damaged.

Manually clean the horizontal joint flanges and seal rings.

Visually inspect the following components for erosion, wear, steam


cuts, cracks, or other damage:
(i)

Upper half horizontal flange joint

(ii) Lower half horizontal flange joint


(iii) Inner flow guide ring to steam chamber fits.

Note
Any discrepancies found should be corrected by stoning or
honing.

Perform NDT on the following areas:


(i)

Upper half horizontal flange

(ii) Lower half horizontal flange


(iii) Joint bolts
(iv) Remainder of the inner flow guide ring.
5

Visually inspect the threaded portion of the joint bolts for deformation,
galling, binding or excessive wear.

LP1 Rotor
Rev.001

Inspect all seal strips for rubs or other signs of damage.

MM-M05.01

Note
Replace seal strips if damaged.

Main Turbine
Mitsubishi

5-71

Chapter 5

Disassembly and Reassembly

Visually inspect the tightness of the rotor balancing plugs.

Visually inspect the following components/areas for erosion, wear,


steam cuts, cracks, or other damage:
(i)

Retaining pin

(ii) Rotor gland areas


(iii) Flow guide ring areas
(iv) Stub dampers.
4

Visually inspect the following areas for pitting, deposits, impact


damage, and that the trailing edges are straight and uniform:
(i)

Rotating blades

(ii) Shrouds
(iii) Erosion protection shields.

Note
Any discrepancies found should be corrected by stoning,
honing or component replacement.

Perform NDT on the following:


(i)

Rotating blades

(ii) Blading shroud


(iii) Tenons
(iv) Stubs
(v) Shaft surfaces
(vi) Rotor gland areas
(vii) Rotor journal areas.

d)

Reassembly

Rev.001

The reassembly procedure is carried out in the reverse sequence to that


for disassembly. Install all parts in the same positions they were removed
from, referring to the match marks and checking that the clearances are
maintained as specified.

MM-M05.01

Ensure that all components are free from burrs and bruises, blending
away the defects using fine files, carborundum stones and emery cloth.
All contact surfaces are to be cleaned before starting reassembly. The
reassembly procedure is described below:
Main Turbine
Mitsubishi

5-72

Chapter 5

Disassembly and Reassembly

CAUTION
Prior to the installation of turbine components, thoroughly
inspect the internals for foreign materials. Ensure that the
utmost standards of cleanliness are applied at all times.

Installation of LP1 Inner Casing Base


1

Clean the inner casing base to outer casing and steam chamber
horizontal joint fit areas.

Clean and lubricate the dowel and mating areas on the inner casing
base.

Ensure that the liners are secured correctly to the inner casing base.
Refer to Figure 5-19 for details.

Connect suitable lifting gear.

Make a trial lift and adjust to evenly lift the inner casing base.

Transport the inner casing base from the lay-down area to the LP1
turbine base and align it over the outer casing base.

Lower the inner casing slowly and evenly into the outer casing base
ensuring that the dowel engages the inner casing smoothly. Continue
to lower the inner casing until the horizontal joint is even with that of
the outer casing and the weight is on the outer casing base.

Replace and tighten the nuts onto the stud bolts and secure the inner
casing base to the outer casing base.

Install the dowel pins in the inner casing which locate the steam
chamber in the inner casing.

10 Remove the lifting gear.


11 Install the LP1 shaft gland casing lower halves.

MM-M05.01

Rev.001

Installation of LP1 Steam Chamber Base

Main Turbine
Mitsubishi

Clean the steam chamber base to inner casing, LP1 blade ring and
inner flow guide ring horizontal joint fit areas.

Clean and lubricate the dowel and mating areas on the steam
chamber base.

Ensure that the liners are secured correctly to the steam chamber
base. Refer to Figure 5-19 for details.

5-73

Chapter 5

Disassembly and Reassembly

Install eye bolts in the steam chamber base and tighten.

Connect suitable lifting gear.

Make a trial lift and adjust to evenly lift the steam chamber base.

Transport the steam chamber base from the lay-down area to the LP1
turbine and align it over the inner casing base.

Lower the steam chamber base slowly and evenly into the inner
casing base ensuring that the dowel engages the steam chamber
smoothly. Continue to lower the steam chamber base until the
horizontal joint is even with that of the inner casing and the weight is
on the inner casing base.

Replace and tighten the hexagonal socket head bolts and secure the
steam chamber base to the inner casing base.

10 Remove the lifting gear.

Rev.001

Installation of LP1 Blade Ring Lower Halves


1

Clean the Gov End LP1 blade ring to steam chamber horizontal joint
fit areas.

Clean and lubricate the dowel and mating areas on the lower half LP1
blade ring.

Install the dowel pins in the blade rings which locate the LP1 blade
rings in the steam chamber.

Install eye bolts in the lower half blade ring and tighten.

Connect suitable lifting gear.

Make a trial lift and adjust to evenly lift the lower half blade ring.

Transport the lower half blade ring from the lay-down area to the LP1
turbine and align it over the steam chamber base.

Lower the lower half blade ring into the steam chamber base
ensuring that the dowel enters the steam chamber smoothly and the
horizontal joint is even with that of the steam chamber base.

Ensure that the lower liners are installed on the steam chamber base.
Replace the aligning plates on the lower half blade ring, if removed
during disassembly, and secure them with the hexagonal socket
head bolts. Refer to Figure 5-19 for details.

MM-M05.01

10 Remove the lifting gear.


11 Following a similar procedure install the Gen End lower half LP1
blade ring.
Main Turbine
Mitsubishi

5-74

Chapter 5

Disassembly and Reassembly

Installation of LP1 Inner Flow Guide Ring Lower Half


1

Clean the lower half inner flow guide ring to steam chamber
horizontal joint fit areas.

Clean and lubricate the dowel and mating areas of the lower half
inner flow guide ring.

Install eye bolts on the inner flow guide ring and tighten.

Connect suitable lifting gear.

Make a trial lift and adjust to evenly lift the inner flow guide ring.

Transport the inner flow guide ring lower half from the lay-down area
to the LP1 turbine and align it over the steam chamber.

Lower the inner flow guide ring slowly and evenly into the steam
chamber base and place it on the liners secured to the steam
chamber base until the horizontal joint is even with the horizontal joint
of the steam chamber and the weight is on the liners.

Remove the lifting gear.

Replace the aligning plates if removed during disassembly and


secure them with hexagonal socket head cap screws. Refer to Figure
5-19 for details.

10 Lubricate the lower half inner flow guide ring fixing studs and install
the washers and nuts.
11 Tighten the nuts and install the set screws.

Installation of LP1 Rotor


Refer to Figure 5- 17.
1

Install the lower halves of No.3 and No.4 bearings in their original
locations.

Visually inspect the LP1 casing base to make sure it is clean and free
of foreign objects before rotor installation.

Install the Gen End and Gov End rotor guide pillars.

Note

MM-M05.01

Rev.001

Rotor guide pillars may not have been removed.

Main Turbine
Mitsubishi

Install the LP rotor lifting gear to the LP1 rotor in accordance with
Appendix H.

Make a trial lift.

5-75

Chapter 5

Disassembly and Reassembly

Adjust the slings from the center of the lifting beam to lift the rotor
evenly and adjust the turnbuckles to make a level lift.

Move the LP1 rotor to the LP1 turbine and align it over the rotor guide
pillars.

Attach tag lines to each end of the rotor to control rotation of the rotor
during installation.

Remove the protective coverings and lubricate the rotor journal


areas.

10 Place a machinist spirit level on the rotor shaft to check the level of
the rotor.

CAUTION
Take care when installing the rotor to ensure that the blading
and the journal areas are not damaged. Clearances between
the fixed and moving blades are limited, as required for
efficient operation. Damage to blading, bearings or rotor
journals can cause serious delays in assembly of the steam
turbine if additional repairs are required.
11 Lower the rotor slowly into the rotor guide pillars while constantly
watching the rotor level.
12 Stop lowering at any change in rotor inclination to determine and
eliminate the cause.
13 Slowly lower the rotor until it is supported by No.3 and No.4 bearings.
14 Check the bearing to journal contact using blue marking on the
journal surface.
15 Lift the rotor slowly, remove the blue marking and smear lubricating
oil on the bearing surfaces.
16 Lower the rotor slowly again until it is supported in the bearings.
17 Remove the rotor guide pillars and block the LP1 rotor to prevent
axial movement.

CAUTION

Rev.001

The rotor must always be rotated in the normal direction. If any


binding or noise is felt or heard while rotating the rotor, stop,
determine and remove the cause of the noise and/or binding.

MM-M05.01

18 Rotate the LP1 rotor slowly to ensure that the rotor turns freely
without rubbing.

Main Turbine
Mitsubishi

5-76

Chapter 5

Disassembly and Reassembly

Setting of LP1 Rotor in the K Position


Refer to Figure 5-14.
Position the LP1 rotor axially in the K position (Right Side: 24.5 0.0 mm;
Left Side: 24.5+1.5/-0.5 mm).

Note
As all axial clearances are based on the correct setting of the
rotor in the K position, the target tolerance is 0 mm.

Measurement of LP1 Shaft Gland Clearances


Refer to Figures 5-12 and 5-13.
Measure and record the clearance between the LP1 Gov End and Gen
End shaft glands and the surface of the rotor as described in mechanical
maintenance manual M05.03, Gland Steam Condenser System and
GSC Exhaust Fan.

Measurement of LP1 Rotor and Casing Clearances


Refer to Figures 5-14 and 5-15.

Note
If LP1 turbine blade top and bottom clearances must be checked,
refer to Appendix G for the procedure.

Note
Measure and record the following clearances at the RS and LS.

Measure and record the axial clearance (A) between the base of the
Gov End first stage stationary blade outlet and the shroud of the first
stage rotating blade inlet.

Note

MM-M05.01

Rev.001

Clearance A for the Gov End first stage is clearance K.

Main Turbine
Mitsubishi

Repeat Step 1 above for the second through seventh stages.

Measure and record the clearance B between the end of the first
stage stationary blade outlet and the base of the first stage rotating
blade inlet.

Repeat Step 3 above for the second through seventh stages.

Measure and record the clearance E between shroud of the first


stage rotating blade outlet and the base of the second stage
stationary blade inlet.

5-77

Chapter 5

Disassembly and Reassembly

Repeat Step 5 above for the second through fourth stages.

Measure and record the clearance F between the base of the first
stage rotating blade outlet and the end of the second stage stationary
blade inlet.

Repeat Step 7 above for the second through sixth stages.

Measure and record the rotating and stationary blading seal strip
radial clearances.

Note
If the seal strip clearances exceed 200% of the design
clearances, seal strip replacement should be considered.

10 Repeat the above procedure to measure the LP1 Gen End rotor and
casing clearances.

Alignment and Coupling


1

Confirm that the oil clearances for No.3 and No.4 bearings are within
the acceptance criteria in accordance with mechanical maintenance
manual M05.04, Turbine Bearings and Thrust Bearing.

Confirm that the coupling alignment is within tolerance. Refer to the


mechanical maintenance manual M05.05.

Install the upper halves of the No.3 and No.4 main bearings.

Install the coupling spacers for the HP-IP ~ LP1 and LP1 ~ LP2
couplings and the coupling bolts into the respective couplings in
accordance with mechanical maintenance manual M05.05.

Replace the coupling guards and restore the coupling cooling oil
connections.

Install the upper half of the coupling guards and the cooling oil lines
for the HP-IP ~ LP1 and LP1 ~ LP2 couplings.

Install the shaft gland seal ring upper halves in accordance with
mechanical maintenance manual M05.03.

Have the electrician install the removed vibration pick-ups.

MM-M05.01

Rev.001

Installation of LP1 Inner Flow Guide Ring Upper Half

Main Turbine
Mitsubishi

Install eye bolts on the inner flow guide ring upper half.

Rig and transport the inner flow guide ring upper half over the LP1
rotor.

Apply a thin coat of triple boiled linseed oil to the horizontal joint
flanges or a special compound for flange surface.

5-78

Chapter 5

Disassembly and Reassembly

Lubricate the joint bolts with Molykote.

Lower the inner flow guide ring upper half slowly and evenly over the
joint studs until the horizontal joint is closed.

Remove the lifting gear.

Install the nuts and tighten.

Installation of LP1 Blade Ring Upper Halves


1

Install the safety hoist eye bolts on the Gov End LP1 blade ring upper
half.

Rig and transport the upper half blade ring over the LP1 turbine.

Apply a thin coat of triple boiled linseed oil or a special compound for
flange surface to the horizontal joint flanges and to the aligning plate
and liner surfaces.

Lubricate the joint bolts with Molykote.

Lower the upper half blade ring slowly and evenly over the lower half
blade ring until the horizontal joint is closed and the weight is on the
aligning plates.

CAUTION
Care must be taken when installing the upper half blade ring to
ensure that the turbine blading are not damaged. The blading
are installed with tight axial clearances which must remain
intact for correct operation. Damages to the blading can cause
serious delays in turbine assembly if additional repairs are
necessary.
6

Remove the lifting gear.

Torque tighten the nuts on studs 401 403 in accordance with


Appendix F in the following sequence:
(i)

Reamer bolt 401

Rev.001

(ii) Bolts 402 and 403.


8

Following a similar procedure, install the Gen End LP1 blade ring
upper half by torque-tightening the nuts on the reamer bolt 404 and
on the bolts 405 and 406.

Rotate the LP1 rotor to ensure freedom of rotor movement.

MM-M05.01

Installation of LP1 Steam Chamber Cover


1
Main Turbine
Mitsubishi

Visually inspect the LP1 turbine for foreign material prior to installing
the steam chamber cover.
5-79

Chapter 5

Disassembly and Reassembly

CAUTION
When working in or over the condenser plenum, take special
care not to drop tools or debris into the condenser tube area.
Damage to the condenser tubes could result in tube leakage.
2

Install the safety hoist eye bolts on the steam chamber cover.

Rig and transport the steam chamber cover over the LP1 turbine.

Ensure that the upper liners are secured to the steam chamber cover.
Refer to Figure 5-19 for details.

Install the dowels in the upper half LP1 blade rings.

Apply a thin coat of triple boiled linseed oil or a special compound for
flange surface to the horizontal joint flanges and to the liner surfaces.

Lubricate the joint bolts with Molykote.

Lower the steam chamber cover slowly and evenly over the dowels
and the horizontal joint studs until the horizontal joint is closed.

Remove the lifting gear.

10 Torque tighten the nuts on studs 301 318 in accordance with


Appendix F in the following sequence:
(i)

Reamer bolts 301, 309, 310 and 318

(ii) Bolts 317 toward 311 and 308 toward 302.

Installation of LP1 Inner Casing Cover


1

Visually inspect the LP1 casing for foreign material prior to installing
the inner casing cover.

CAUTION

MM-M05.01

Rev.001

When working in or over the condenser plenum, take special


care not to drop tools or debris into the condenser tube area.
Damage to the condenser tubes could result in tube leakage.

Main Turbine
Mitsubishi

Install the inner casing guide bolts in the locations indicated in Figure
5-18.

Install the appropriate lifting gear to the inner casing cover.

Make a trial lift and adjust the chain blocks or turn buckle, to provide a
level lift.

5-80

Chapter 5

Disassembly and Reassembly

Transport the inner casing cover and position it above the inner
casing base.

Ensure that the liners are secured to the inner casing cover. Refer to
Figure 5-19 for details.

Install the dowels in the inner casing cover.

Align the inner casing cover with the inner casing guide bolts.

Lubricate the joint bolts and dowels with Molykote.

10 Apply a coat of triple boiled linseed oil or a special compound for the
flange surface of the inner casing horizontal joint and to the liner
surfaces.
11 Check that the inner casing cover horizontal joint is parallel to the
base horizontal joint.
12 Slowly lower and align the inner casing cover with the studs and
dowels.
13 Continue lowering the cover until the horizontal joint is closed.
14 Remove the lifting gear and the inner casing guide bolts.
15 Install the nuts and washers onto the studs and hand tighten.

Bolt heaters are electrical devices capable of causing personal


injury or death if improperly used.

Note
Refer to the Bolt Heating Data in Appendix F to identify the
bolts and determine the required heater type and size. Heat
the bolts in accordance with Bolt Heater Instruction in
Appendix I.

Note
Tighten the nuts without bolt heaters to the torque specified in

Rev.001

Appendix F.

Note

MM-M05.01

Install the bolts from both the LS and RS of the LP casing


starting at the transverse centerline, working outwards toward
each end.

Main Turbine
Mitsubishi

5-81

Chapter 5

Disassembly and Reassembly

16 Install the nuts on the bolts 201 to 272 in the following sequence:
(i)

Heat and tighten reamer bolt 218

(ii) Torque tighten reamer bolts 201, 236, 242, 252, 264 and 272
(iii) Heat and tighten bolts 217 213 and 219 224
(iv) Torque tighten bolts 212 202 and 225 235
(v) Torque tighten bolts 241 237, 251 243, 263 255 and 271
267.
17 Install the access cover plates.
18 Slowly rotate the LP1 rotor to ensure that it turns freely.
19 Install the LP1 shaft gland casing upper halves.

Installation of LP1 Outer Casing Cover


1

Perform a visual inspection of the LP1 turbine to ensure that no


foreign material is present before installation of the LP1 outer casing
cover.

Install the lifting equipment to the LP1 outer casing cover in


accordance with Appendix H.

Make a trial lift and adjust as necessary to obtain a level lift.

Transport the outer casing cover over the outer casing base and align
it to the outer casing base.

Attach tag lines to each end of the outer casing cover to control the
rotation of the cover during installation.

Lubricate the horizontal joint bolts with Molykote.

Lubricate the outer casing cover horizontal flange with triple boiled
linseed oil or special compound for flange surface.

Slowly lower the outer casing cover, ensuring that the outer cover is
aligned with the outer casing base.

Lubricate the jack screws with Molykote and install them in the outer
casing cover.

10 Turn the jack screws in the outer casing cover until they protrude 10
mm below the horizontal joint.
Rev.001

11 Lower the outer casing cover slowly until the jack screws rest on the
horizontal joint of the outer casing base.

MM-M05.01

12 Continue lowering the outer casing cover by slackening the jack


screws equally half a turn at a time.

Main Turbine
Mitsubishi

5-82

Chapter 5

Disassembly and Reassembly

Note
Follow the downward motion of the outer casing cover with
the crane to ensure that the load is transferred to the jack
screws.

13 Continue to lower the outer casing cover until the horizontal joint is
closed.
14 Remove the lifting gear.
15 Place the washers over the open bolt holes in the outer casing cover
flange.
16 Install the nuts on top of the bolts and tighten.
17 Tighten the outer casing horizontal joint flange bolts in a diametrically
opposite pattern in the following order:
(i)

Reamer bolts.

(ii) Joint bolts starting at the gland bores working outward toward the
corners (transverse direction).
(iii) Joint bolts starting at the transverse centerline towards the
corners (longitudinal direction).
18 Replace the top seal ring between the outer casing cover and the
inner casing cover.

Note
The following items 19 to 22 are performed inside the LP outer
casing cover. Refer to Figure 5-18.

19 Install the lifting gear, and evenly lower the LP exhaust flow guides
into place aligning the eccentric pins as they are lowered.
20 Install and securely tighten the flange bolts into the Gov End and the
Gen End exhaust flow guide upper halves.
21 Remove the lifting gear and jack screws.
22 Install the spray nozzle piping to the exhaust flow guides.
23 Install the lifting gear on the manhole covers.
Rev.001

24 Rig and transport the manhole covers into position.

MM-M05.01

25 Install a new gasket on the manhole cover and lower into place.
26 Remove the eye bolts.
27 Install the cover flange bolts and tighten.
Main Turbine
Mitsubishi

5-83

Chapter 5

Disassembly and Reassembly

Return to Service
Have the electricians connect thermocouple lead wires to the outer
casing cover.

Replace the bearing pedestal covers.

Install the IP to LP1/LP2 crossover pipe.

Replace the insulation and metal cladding removed from the turbine.

Confirm that all instruments removed for the overhaul have been
installed and are available.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

5-84

Chapter 5

0.3~0.5

0.3~0.5

0.2+-0.05

0.2+-0.05
STEAM
CHAMBER

STEAM
CHAMBER

STEAM CHAMBER

STEAM CHAMBER

LP1 BLADE RING

LP1 BLADE RING

0.2+-0.05

0.2+-0.05
INNER CASING

INNER CASING

E
E

A
B

STATIONARY BLADE

6R

7R

5C

A
B
4R

5R

4C

A
B

3C

3R

A 2C 1C A
B B
2R

7C

4C

E
E

1R

A 1C

A
B

2C A 3C A

B
1R

B
2R

3R

4R

5R

GEN. SIDE

E
5C

7C

6C

STATIONARY BLADE

6R

7R

F
RIGHT SIDE
LEFT SIDE

LP1 ROTOR

Rev.001

INNER CASING

1
2
3
4
5
6
7

1
2
3
4
5
6
7

BLADE AXIAL CLEARANCE


(TOLERANCE +1.5
-0.5 )
ROTOR BLADES
INLET
OUTLET

13.5
13.5
13.5
13.5
35.5
32.6
46.1

14.3
14.3
14.3
14.3
13.7
16.1
16.1

24.5
50.6
24.5
37.6

25.3
51.4
25.3
37.6
27.1
27.1

BLADE AXIAL CLEARANCE


(TOLERANCE +1.5
-0.5 )
ROTOR BLADES
INLET
OUTLET

24.5
24.5
24.5
46.5
43.6
57.1

25.3
25.3
25.3
25.3
24.7
27.1
27.1

13.5
39.6
13.5
26.6

14.3
40.4
14.3
26.6
16.1
16.1
-

LP1 ROTOR
INNER FLOW
GUIDE

6C

MM-M05.01

24.5 +1.5
-0.5

0.2+-0.05

0.2 +-0.05

16.1 +1.5
-0.5

INNER FLOW
GUIDE

27.1 +1.5
-0.5

STATIONARY BLADE

6C

INNER CASING
STATIONARY BLADE

NOTE: REFER TO FIGURE 5-16 FOR BLADE SEAL RADIAL CLEARANCES


FIGURE 5-11

Main Turbine
Mitsubishi

K=24.5 +- 0.0

GOV. SIDE

6C

ROW No.

7C

ROW No.

7C

MPTD-3-0249

Disassembly and Reassembly

LP1 TURBINE SHELL CLEARANCE

5-85

Chapter 5

Disassembly and Reassembly

SEAL RING

SEAL RING

GLAND
CASING

0.5+-0.1

GLAND
CASING

0.5+-0.1

X
SEAL STRIP

SEAL STRIP

OUTER CASING
COVER

CL OF LP1 ROTOR

GLAND
CASING

0.5+-0.1

SEAL STRIP

GLAND
CASING

LP1 ROTOR

0.5+-0.1

SEAL STRIP

LP1 ROTOR

MM-M05.01

Rev.001

NOTE: REFER TO FIGURE 5-16 FOR BLADE SEAL RADIAL CLEARANCES (X)

MPTD-4-0250

FIGURE 5-12
Main Turbine
Mitsubishi

LP1 TURBINE GOV END SHAFT GLAND DESIGN CLEARANCES

5-86

Chapter 5

Disassembly and Reassembly

SEAL RING

SEAL RING

GLAND
CASING

0.5+-0.1

GLAND
CASING

0.5+-0.1

X
SEAL STRIP

SEAL STRIP

OUTER CASING
COVER

C
L OF LP1 ROTOR

GLAND
CASING

LP1 ROTOR

SEAL STRIP

GLAND
CASING

0.5+-0.1

0.5+- 0.1

LP1 ROTOR

SEAL STRIP

MM-M05.01

Rev.001

NOTE: REFER TO FIGURE 5-16 FOR BLADE SEAL RADIAL CLEARANCES (X)

MPTD-4-0251

FIGURE 5-13
Main Turbine
Mitsubishi

LP1 TURBINE GEN END SHAFT GLAND DESIGN CLEARANCES

5-87

Chapter 5

Disassembly and Reassembly

0.3 0.1
STATIONARY BLADE
+-

ROTATING BLADE

INNER CASING
ROTATING BLADE

INNER CASING

6R

0.3 0.1

SEAL STRIP

5R

4R

EXHAUST
FLOW GUIDE

7C

3R
7R

ROTATING BLADE
LP1 BLADE RING

ROTATING
BLADE

6C

SEAL STRIP

5C

1R

4C

2R

1C

2C

0.3 0.1

3C

STATIONARY
BLADE

LP1 ROTOR

0.0

1R

2R

3R

4R

5R

7C
6R

7R

ROTATING BLADE

7.5

1C

LP1 ROTOR

27.1

0.3 0.1
STATIONARY
BLADE

6C
4C

5C

LP1 ROTOR

3C

2C

STATIONARY BLADE

MM-M05.01

Rev.001

3
SEAL STRIP
MPTD-3-0252

LP1 ROTOR

SEAL STRIP

NOTE: REFER TO FIGURE 5-16 FOR BLADE SEAL RADIAL CLEARANCES (X)

FIGURE 5-14
Main Turbine
Mitsubishi

LP1 TURBINE GOV. END-ROTOR & CASING DESIGN CLEARANCES

5-88

Chapter 5

Disassembly and Reassembly

0.3 0.1
STATIONARY BLADE
+-

ROTATING BLADE

INNER CASING
ROTATING BLADE

6R

INNER CASING

0.3 0.1

5R

SEAL STRIP

EXHAUST
FLOW GUIDE

4R

7C

3R
7R

ROTATING BLADE

ROTATING
BLADE

LP1 BLADE RING

6C

SEAL STRIP

5C

STATIONARY
BLADE

3C

2C

4C

0.3 0.1

1C

2R

1R

LP1 ROTOR
6R

7R

5R

4R

3R

ROTATING BLADE

2R 1R

3.5

0.0

7C

1C

LP1 ROTOR

16.1

0.3 0.1

0.5

0.5

STATIONARY
BLADE

4C

5C

6C

3C

2C

Rev.001

LP1 ROTOR

STATIONARY BLADE

MM-M05.01

MPTD-3-0253

SEAL STRIP

LP1 ROTOR

SEAL STRIP

NOTE: REFER TO FIGURE 5-16 FOR BLADE SEAL RADIAL CLEARANCES (X)

FIGURE 5-15
Main Turbine
Mitsubishi

LP1 TURBINE GEN. END-ROTOR & CASING DESIGN CLEARANCES

5-89

Chapter 5

Disassembly and Reassembly

RADIAL SEAL CLEARANCE TABLE (COLD SET/DESIGN


VERTICAL DIRECTION
AFT. ASS'Y
CASING DEFLEC.

NOMINAL CLEA.
ELEMENT

OUTER GLAND
(GOV. END)

LOCATION

LENGTH

AIR SEAL (1)


SEAL RING (2)
SEAL RING (3)
SEAL RING (4)
LP7R (GOV.)

407.75
481.25
555.75
629.75

1.20
1.20
1.20
1.20

0.95
0.90
0.90
0.90

0.25
0.25
0.25
0.25

-0.01
-0.02
-0.03
-0.04

0.00
0.00
0.00
0.00

1.46
1.47
1.48
1.49

0.69
0.63
0.62
0.61

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

1.46
1.47
1.48
1.49

0.69
0.63
0.62
0.61

974.85

10.00

10.00

0.25

-0.06

0.00

10.31

9.69

0.00

0.00

10.31

9.69

1433.10
1536.50
1641.40
1816.50
1911.90
1990.20
2050.05
2104.40
2154.70
2232.00
2282.30
2333.50
2379.80
2725.20
2771.50
2822.70
2873.00
2950.30
3000.60
3054.95
3114.80
3193.10
3288.50
3463.60
3568.50
3671.90

2.67
4.00
1.65
2.00
1.50
1.60
1.50
1.30
1.10
1.30
1.10
1.30
1.10
1.10
1.30
1.10
1.30
1.10
1.30
1.50
1.60
1.50
2.00
1.65
4.00
2.67

2.67
4.00
1.65
2.00
1.50
1.60
1.50
1.30
1.10
1.30
1.10
1.30
1.10
1.10
1.30
1.10
1.30
1.10
1.30
1.50
1.60
1.50
2.00
1.65
4.00
2.67

0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25

-0.08
-0.09
-0.09
-0.10
-0.10
-0.11
-0.11
-0.11
-0.11
-0.11
-0.12
-0.12
-0.12
-0.12
-0.12
-0.12
-0.11
-0.11
-0.11
-0.11
-0.11
-0.10
-0.10
-0.09
-0.09
-0.08

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

3.00
4.34
1.99
2.35
1.85
1.96
1.86
1.66
1.46
1.66
1.47
1.67
1.47
1.47
1.67
1.47
1.66
1.46
1.66
1.86
1.96
1.85
2.35
1.99
4.34
3.00

2.34
3.66
1.31
1.65
1.15
1.24
1.14
0.94
0.74
0.94
0.73
0.93
0.73
0.73
0.93
0.73
0.94
0.74
0.94
1.14
1.24
1.15
1.65
1.31
3.66
2.34

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

3.00
4.34
1.99
2.35
1.85
1.96
1.86
1.66
1.46
1.66
1.47
1.67
1.47
1.47
1.67
1.47
1.66
1.46
1.66
1.86
1.96
1.85
2.35
1.99
4.34
3.00

4130.15

10.00

10.00

0.25

-0.06

0.00

10.31

9.69

0.00

0.00

4475.25
4549.25
4623.75
4697.25

1.20
1.20
1.20
1.20

0.90
0.90
0.90
0.95

0.25
0.25
0.25
0.25

-0.03
-0.03
-0.02
-0.01

0.00
0.00
0.00
0.00

1.48
1.48
1.47
1.46

0.62
0.62
0.63
0.69

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

LP7C (GOV.)
LP6R (GOV.)
LP6C (GOV.)
LP5R (GOV.)
LP5C (GOV.)
LP4R (GOV.)
LP4C (GOV.)
LP3R (GOV.)
LP3C (GOV.)
LP2R (GOV.)
LP1 BLADE RING
LP2C (GOV.)
(GOV. END)
LP1R (GOV.)
STEAM FLOW
GUIDE INLET
LP1R (GEN.)
LP1 BLADE RING
LP2C (GEN.)
(GEN. END)
LP2R (GEN.)
LP3C (GEN.)
LP3R (GEN.)
LP4C (GEN.)
LP4R (GEN.)
LP5C (GEN.)
LP5R (GEN.)
LP6C (GEN.)
LP6R (GEN.)
LP7C (GEN.)
LP7R (GEN.)
OUTER GLAND
(GEN END)

AFT. BOTTOM ASS'Y

SEAL RING (4)


SEAL RING (3)
SEAL RING (2)
AIR SEAL (1)

HORIZONTAL DIRECTION
AFT. ASS'Y
CASING DEFLEC.

NOMINAL CLEA.
23

24

0.75
0.50
0.50
0.50

0.00
0.00
0.00
0.00

10.00

10.00

+0.10
-0.05

2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67

9.69

+0.50
-0.00

0.62
0.62
0.63
0.69

+0.15
-0.05

AFT. BOTTOM ASS'Y

29
30
6
7
8
9
10
11
10 11
29 30
ROTOR AFT. ASY AFT. ASY CASING CASING AT SET. AT SET.
FROM
AFT. ASY AFT. ASY CASING CASING AT SET. AT SET. TOLERANCE
NOMINAL NOMINAL ELEMENT ROTOR
NOMINAL NOMINAL ELEMENT ROTOR
TOLERANCE
No.3 BRG. TOP
SETTING
DEFLEC.
SETTING
SETTING
SETTING
RIGHT
LEFT
DEFLEC.
DEFLEC.
BOTTOM
RIGHT
LEFT
BOTTOM
LEFT
RIGHT
TOP
BOTTOM DEFLEC. DEFLEC. TOP
CLEARA. CLEARA.
LEFT
CLEARA. CLEARA.
CLEARA. CLEARA.
CLEARA. CLEARA. RIGHT
BOTTOM CLEARA. CLEARA.
CLEARA. CLEARA. TOP

NOTE:
1. RADIAL CLEARANCES AT ASSEMBLY OF LP-1 TURBINE
IS AS SHOWN IN THIS DRAWING IN CASE THAT SETTING
OF EACH PART AND DEFLECTION OF THE ROTOR IS
TAKEN INTO ACCOUNT.

2. THE BASIS OF RADIAL CLEARANCE SETTING


IN THIS DRAWING IS OIL RING BORE.

25

26

27

28

0.00
0.00
0.00
0.00

0.75
0.50
0.50
0.50

0.75
0.50
0.50
0.50

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.75
0.50
0.50
0.50

0.75
0.50
0.50
0.50

+0.15
-0.15

0.00

0.00

10.00

10.00

0.00

0.00

10.00

10.00

+0.50
-0.00

2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67

2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67

2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67

+0.10
-0.05

10.00

10.00

0.00

0.00

10.00

10.00

0.00

0.00

10.00

10.00

+0.50
-0.00

0.50
0.50
0.50
0.75

0.50
0.50
0.50
0.75

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.50
0.50
0.50
0.75

0.50
0.50
0.50
0.75

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.50
0.50
0.50
0.75

0.50
0.50
0.50
0.75

+0.15
-0.05

21

22

+0.15
-0.05

0.75
0.50
0.50
0.50

+0.50
-0.00

2.34
3.66
1.31
1.65
1.15
1.24
1.14
0.94
0.74
0.94
0.73
0.93
0.73
0.73
0.93
0.73
0.94
0.74
0.94
1.14
1.24
1.15
1.65
1.31
3.66
2.34

10.31
1.48
1.48
1.47
1.46

3. CLEARANCE AT ASSEMBLY OF LP-1 TURBINE IS CALCULATED


BY THE FOLLOWING EQUATIONS.
HOWEVER, SIGNS OF MOVEMENT AND DEFLECTION ARE
TO BE AS SHOWN BELOW.

TOP CLEARANCE

+
+

RIGHT SIDE CLEARANCE


ROTATION

* RIGHT AND LEFT SIDE CLEARANCES ARE SHOWN


IN CASE THAT THE VIEW IS FROM GOVERNOR
SIDE TO GENERATOR SIDE.

LEFT SIDE CLEARANCE

a) AFTER COMPLETION OF ASSEMBLY:


6 = 1 + 3 - 4
TOP CLEARANCE
BOTTOM CLEARANCE 7 = 1 + 2 - 6
RIGHT SIDE CLEARANCE 25 = 21 + 23 LEFT SIDE CLEARANCE 26 = 21 + 22 -

- 5
24
25

b) AT MEASUREMENT WITH LEAD WIRE:


10 = 6 - 8
TOP CLEARANCE
11 = 7 + 9
BOTTOM CLEARANCE
RIGHT SIDE CLEARANCE 29 = 25 - 27
LEFT SIDE CLEARANCE 30 = 26 + 28

BOTTOM CLEARANCE

Rev.001

MM-M05.01

MPTD-3-0254

FIGURE 5-16
Main Turbine
Mitsubishi

LP1 TURBINE- BLADE & GLAND SEALS RADIAL CLEARANCE TABLE

5-90

Disassembly and Reassembly

MM-M05.01

Rev.001

Chapter 5

FIGURE 5-17

LP1 ROTOR GUIDE PILLAR AND INNER CASING GUIDE BOLT


LOCATIONS

Main Turbine
Mitsubishi

5-91

Chapter 5

Disassembly and Reassembly

3
A

HORIZONTAL JOINT

2
A

B-B

B-B
8

DETAIL "D"

MM-M05.01

Rev.001

DETAIL "C"

FIGURE 5-18

Main Turbine
Mitsubishi

EXHAUST FLOW GUIDE LIFTING ARRANGEMENT

5-92

Chapter 5

Disassembly and Reassembly

16
4
20

8
7

21

E
6

B
6

7
8

20
HORIZONTAL JOINT

21
2

18

16

21

A-A

OUTER CASING COVER


OUTER CASING BASE
INNER CASING COVER
INNER CASING BASE
ADJUSTING LINER
STUD BOLT
NUT
BOLT
ADJUSTING LINER
TONGUE WASHER
BOLT
ADJUSTING LINER
STEAM CHAMBER COVER
STEAM CHAMBER BASE
UPPER LINER
LOWER LINER
TAPER BOLT

FLOW GUIDE
20 INNER
(LOWER HALF)

E-E

B-B

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19

ALIGNING PLATE

INNER FLOW GUIDE RING SUPPORT


INNER CASINGSUPPORT
19

13

8
16

12

15

18
14

19

15
17

17

17
3

12

16

14

HORIZONTAL JOINT

"X"

18

11
11

13

H-H

18
Rev.001

18

F-F

20

16

13

DETAIL "X"

16

G-G
STEAM CHAMBER SUPPORT

MM-M05.01

MPTD-3-0626

FIGURE 5-19
Main Turbine
Mitsubishi

SUPPORT DETAILS FOR THE LP1/LP2 TURBINE PARTS AT HORIZONTAL JOINT

5-93

Chapter 5

5.3

Disassembly and Reassembly

LP2 Turbine Disassembly and Reassembly


a)

Preparation
If LP2 turbine disassembly becomes necessary, all associated equipment
must be mechanically and electrically isolated and an authorized
clearance and work permit must be in place prior to the commencement of
work. The following points must also to be considered when preparing for
disassembly and reassembly:

Have all necessary drawings (assembly drawings, sectional drawings,


part details, etc.) and documents (log sheets, field record book, etc.)
ready prior to start of work.

Prepare the necessary handling facilities (crane facilities, temporary


supports etc.) to remove and store the various parts of the steam
turbine.

Co-ordinate with the Instrument and Control (I&C) Department to


remove all the attached instruments before starting disassembly
work.

Special tools are listed in Appendix C.

Do not stand below the lifted turbine parts. There can be


danger of an accident due to components falling down.

CAUTION
Spigot joints between the turbine stationary components
(such as outer and inner casings, blade rings, etc.) could bind
due to scale formation during operation under the high
temperature environment.

CAUTION

MM-M05.01

Rev.001

The binding mentioned above may require additional jacking


or crane load which could exceed the dead weight of the
concerned components as the components are separated or
lifted apart. This could cause surface damage such as seizure,
galling or scoring. Take due care and initiate any special
measures necessary when separating or lifting the steam
turbine and binding is apparent or suspected.

Main Turbine
Mitsubishi

5-94

Chapter 5

Disassembly and Reassembly

CAUTION
Personnel working inside the turbine should not carry any
loose items in their pockets and should take special care not
to drop tools or debris into the turbine.

CAUTION
Any surface irregularity or damage caused by the reasons
described above, must be ground off smoothly, or
reconditioned by build-up welding and facing to reinstate the
original surface finish and clearance if any between mating
parts.

CAUTION
Wear proper goggles and face masks when working on the
insulation. Insulation material is harmful to the respiratory
system.

b)

Disassembly
Refer to Figures 2-10 and E-2.

Preparation for Disassembly


1

During normal operation, before the Unit is shut down for overhaul,
perform a thorough external visual inspection of the entire turbine unit
to detect any obvious deficiencies. These are to be rectified during
the turbine overhaul.

Prepare an area for the abrasive blasting of the turbine components.

Note
Label and identify all components as they are disassembled.
Tag and bag all hardware and fasteners with the associated

MM-M05.01

Rev.001

components and store in the designated area.

Main Turbine
Mitsubishi

Prepare a lay-down area for the turbine components including the


turbine rotor cradles.

Remove the insulation from the IP turbine exhaust to LP1 and LP2
turbines steam inlet flanges.

5-95

Chapter 5

Disassembly and Reassembly

Refer to Figure 2-14. Remove the nuts from the flange joints and then
remove the crossover piping connecting the IP exhaust to the LP1
and LP2 turbines inlet. Remove the top seal ring from between the
LP2 inner and outer casings.

Removal of LP2 Outer Casing Cover


1

Have the electricians remove the thermocouple lead wires.

Label all LP2 outer casing cover bolts and nuts.

Loosen the flange bolts on all LP2 outer casing manhole covers.

Install eye bolts in the manhole covers.

Install lifting gear to the eye bolts.

Support the weight of the manhole covers using the lifting gear.

Remove the bolts and the manhole covers.

Transport the manhole covers to the lay-down area.

Remove the Gov End and Gen End shaft upper half gland casings
and remove the seal rings from the gland casings into storage.

Note
The following steps 10~15, to disassemble the Gov End and
Gen End exhaust flow guides are performed inside the outer
casing. Refer to Figure 5-18.

10 Disconnect the exhaust hood spray nozzle piping secured to the


exhaust flow guide by disconnecting the pipe unions.
11 Connect the lifting gear to the exhaust flow guide upper half.
12 Install chain blocks between the exhaust flow guide upper half and
the eye plate.
13 Remove all flange bolts from the exhaust flow guide upper half except
for four bolts adjacent to the jack screws.

Rev.001

14 Adjust the lifting gear to support the weight of exhaust flow guide
upper half, and alternately tighten the jack screws and loosen the
adjacent bolts until the locating eccentric pins have been pulled free
from the inner casing.

MM-M05.01

15 Remove the jackscrews from the flange, lift the exhaust flow guide
upper half, and fasten it securely to the inside of the outer casing
cover.
16 Remove the horizontal joint bolts from the LP2 outer casing base.
Main Turbine
Mitsubishi

5-96

Chapter 5

Disassembly and Reassembly

17 Install jack screws in the outer casing cover horizontal joint flange and
manually tighten to contact the outer casing base horizontal joint
face.
18 Turn the jack screws half a turn at a time to open the horizontal joint,
maintaining equal loading on the jack screws and equal gap at the
horizontal joint opening.

Note
During operation of the turbine, oxides and deposits
accumulate between the mating surfaces of the casings. The
forces required to separate these surfaces may be noticeably
greater than those required to suspend the weight of the outer
casing cover.

19 Install the lifting gear to the LP2 outer casing cover in accordance
with Appendix H.
20 Tension the wire ropes and position the hook over the center of
gravity, make a trial lift and adjust the lifting equipment until an even
lift is achieved.

CAUTION
Follow the upward motion of the LP2 outer casing with the
crane attached to the lifting device. Do not overload the lifting
cables.

21 Attach a tag line to each end of the LP2 outer casing cover to control
any rotation of the casing during the lift.
22 Evenly raise the LP2 outer casing cover in small increments until it
stands clear of the bolts.
23 Lift the LP2 outer casing cover clear of the turbine and transport it to
the lay-down area.
24 Set wooden supports on the floor to support the outer casing cover.
25 Protect the horizontal joints of the LP2 outer casing cover.
26 Lower the LP2 outer casing cover onto the wooden supports.
27 Disconnect and remove the lifting gear.

Rev.001

Note
Ensure that the openings in the lower half turbine exposed by
the removal of the outer casing cover are protected. It is

MM-M05.01

recommended that a material exclusion area be established


around the turbine to prevent entry of foreign material into the
turbine.

Main Turbine
Mitsubishi

5-97

Chapter 5

Disassembly and Reassembly

Removal of LP2 Inner Casing Cover

CAUTION
When working in or over the condenser plenum, take special
care not to drop tools or debris into the condenser tube area.
Damage to the condenser tubes could result in condenser tube
leakage.

Match mark and remove the access cover plates to expose the
internal horizontal joint bolts.

Note
Refer to Appendix F to identify the horizontal joint bolts, and
to determine the required bolt heater type and size. Remove
the bolts from both LS and RS of the LP2 inner casing starting
at the transverse centerline of both LS and RS, working
outwards toward each end. Remove the bolts parallel to the
transverse axis starting at the extreme end and working
towards the turbine longitudinal axis.

Mark nuts with their respective number and indicate RS or LS.

Bolt heaters are electrical devices capable of causing personal


injury or death if improperly used.

Using four bolt heaters (two on each side), heat the bolts 513 524 in
accordance with Bolt Heater Instruction in Appendix I, avoiding
heating adjacent bolts, and loosen the nuts from both the RS and LS
of the casing in the following sequence:
(i)

513 toward 517 and 519 toward 524

(ii) Reamer bolt 518.

Note
Rev.001

To avoid heating the casing flange excessively, frequently


loosen the nuts. As soon as the nuts are loosened and the bolt

MM-M05.01

heaters have cooled sufficiently, remove the bolt heaters.

Main Turbine
Mitsubishi

5-98

Chapter 5

Disassembly and Reassembly

Remove the nuts as follows:


(i)

Install safety hoist ring and copper washer into the nut to be
removed.

(ii) Connect suitable lifting gear to the safety hoist ring and remove
the nuts.
5

Loosen and remove the nuts from bolts 501 512 and 525 572 in
the following sequence:

Note
Bolts 501 512 and 525 572 do not have provision for a bolt
heater.

(i)

Bolts 502 512, 525 535

(ii) Bolts 537 541, 543 551, 555 563, 567 571
(iii) Reamer bolts 501 and 536
(iv) Reamer bolts 542, 552, 564 and 572.
6

Inspect and clean the jackscrew threads.

Lubricate and install jackscrews into the inner casing cover horizontal
joint flange and hand tighten until contact is made with the inner
casing base horizontal joint flange.

Note
During the operation of the turbine, oxides and the deposits
accumulate between the mating surfaces of the casings. The
forces required to separate these surfaces may be noticeably
greater than those required to suspend the weight of the inner
casing cover.

Install the inner casing guide bolts (supplied as Special Tools) on the
inner casing base as indicated in Figure 5-17.

Turn the jack screws half a turn at a time to open the horizontal joint
and maintain an equal gap at the horizontal joint openings.

10 Install the appropriate lifting gear to the inner casing cover.

CAUTION

MM-M05.01

Rev.001

Follow the upward motion of the inner casing cover with the
crane attached to the lifting device. Do not overload the lifting
cables.

Main Turbine
Mitsubishi

5-99

Chapter 5

Disassembly and Reassembly

11 Continue turning the jack screws, ensuring equal distance at all


points, until the inner casing cover is raised approximately 10 mm.
12 With the hook over the center of gravity, tension the wire ropes.
13 Make a trial lift to make sure that the cover horizontal joint is parallel
to the base horizontal joint.
14 Attach tag lines to each end of the inner casing cover to control any
rotation of the cover during the lift.
15 Evenly raise the inner casing cover in small increments until the cover
is clear of the stud bolts.
16 Transport the inner casing cover to the lay-down area.

Note
Ensure that the openings left by the removal of the inner
casing cover are protected.

17 Protect the horizontal joint of the inner casing cover.


18 Lower the inner casing cover onto wooden blocks.
19 Disconnect and remove the lifting gear.

Removal of LP2 Steam Chamber Cover

CAUTION
When working in or over the condenser plenum, take special
care not to drop tools or debris into the condenser tube area.
Damage to the condenser tubes could result in tube leakage.

Match mark and remove the access cover plates to expose the
internal horizontal joint bolts.

Note
Refer to Appendix F to identify the bolts and determine the
required torque values.

Rev.001

Loosen and remove the nuts and washers from bolts 601 618 in the
following sequence:
(i)

Bolts 602 608 and 611 617

MM-M05.01

(ii) Reamer bolts 601, 609, 610 and 618.

Main Turbine
Mitsubishi

5-100

Chapter 5

Disassembly and Reassembly

Note
Bolts 601 618 do not have provision for a bolt heater.

Lubricate and install jackscrews in the steam chamber cover


horizontal joint flange, and hand tighten until contact is made with the
steam chamber base horizontal joint flange.

Note
During the operation of the turbine, oxides and the deposits
accumulate between the mating surfaces of the steam
chamber. The forces required to separate these surfaces may
be noticeably greater than those the required to suspend the
weight of the steam chamber cover.

Turn the jack screws half a turn at a time to open the horizontal joint
and maintain an equal gap at the horizontal joint openings.

Install eyebolts and connect suitable lifting gear to the steam


chamber cover.

CAUTION
Follow the upward motion of the steam chamber cover while
the crane is hoisting. Do not overload the wire rope slings.

Continue turning the jack screws, measuring for equal distance at all
points until the steam chamber cover is raised approximately 10 mm.

With the hook over the center of gravity, tension the wire ropes.

Make a trial lift to confirm that the cover horizontal joint is parallel to
the base horizontal joint.

Attach tag lines to each end of the steam chamber cover to control
any rotation of the steam chamber during the lift.

10 Evenly raise the steam chamber cover in small increments until the
cover is clear of the bolts.
11 Transport the steam chamber cover to the lay-down area.

Note
Rev.001

Ensure that the openings left in the LP2 casing are covered.

MM-M05.01

12 Protect the horizontal joint of the steam chamber cover.


13 Lower the steam chamber cover onto wooden blocks.
14 Disconnect and remove the lifting gear.
Main Turbine
Mitsubishi

5-101

Chapter 5

Disassembly and Reassembly

Removal of LP2 Blade Ring Upper Halves


1

Label the Gov End LP2 blade ring bolts and nuts with their respective
numbers and indicate RS or LS.

Loosen and remove the nuts and washers from bolts 701 704 in the
following sequence:
(i)

Bolts 702 and 703

(ii) Reamer bolts 701 and 704.


3

Install eye bolts into the LP2 blade ring upper half and tighten.

Lubricate and install jackscrews in the LP2 blade ring upper half
horizontal joint flange, and hand tighten until contact is made with the
lower half flange.

Note
During the operation of the turbine, oxides and the deposits
accumulate between the mating surfaces of the blade ring.
The forces required to separate these surfaces may be
noticeably greater than those the required to suspend the
weight of the upper half blade ring.

Turn the jack screws half a turn at a time to open the horizontal joint
and maintain an equal gap at the horizontal joint openings.

Connect suitable lifting gear to the blade ring upper half and make a
trial lift.

Adjust the chain blocks to evenly lift the blade ring upper half.

Set support blocks on the floor.

CAUTION
Carefully lift the upper half blade rings from the turbine
casings to avoid contact between the stationary and rotating
blades.

Rev.001

Lift the blade ring clear of the lower half joint bolts and transport it to
the lay-down area.

10 Disconnect and remove the lifting gear.

MM-M05.01

11 Using a similar procedure, remove the Gen End LP2 blade ring upper
half after removing the horizontal joint nut from bolts 705 708.

Main Turbine
Mitsubishi

5-102

Chapter 5

Disassembly and Reassembly

Removal of LP2 Inner Flow Guide Ring Upper Half


1

Remove the nuts and washers from the horizontal joint studs which
secure the LP2 inner flow guide ring upper half to the lower half.

Install eye bolts into the LP2 inner flow guide ring upper half and
tighten.

Lubricate and install jackscrews in the upper half inner flow guide ring
and hand tighten until contact is made with the lower half flange.

Turn the jack screws half a turn at a time to open the horizontal joint
and maintain an equal gap at the horizontal joint openings.

Connect suitable lifting gear to the upper half flow guide ring and
make a trial lift.

Adjust the chain blocks to evenly lift the upper half inner flow guide
ring.

Set support blocks on the floor.

Lift the upper half inner flow guide ring clear of the lower half joint
bolts and transport it to the lay-down area.

Disconnect and remove the lifting gear.

Setting LP2 Rotor in the K Position


Refer to Figure 5-23.
Position the rotor axially in the K position (Right Side: 29.0 0.0 mm; Left
Side: 29.0+1.5/-0.5 mm).

Note
As all axial clearances are based on the correct setting of the
rotor in the K position, the target tolerance is 0 mm.

Measurement of LP1 Shaft Gland Clearances


Refer to Figures 5-21 and 5-22.

MM-M05.01

Rev.001

Measure and record the clearances between the LP2 Gov End and Gen
End shaft glands and the surface of the rotor at the RS and LS as
described in the mechanical maintenance manual M 05.03, Gland
Steam Condenser System and GSC Exhaust Fan.

Main Turbine
Mitsubishi

5-103

Chapter 5

Disassembly and Reassembly

Measurement of LP2 Rotor and Casing Clearances


Refer to Figures 5-23 and 5-24.

Note
Measure and record the following clearances at the RS and LS.

Measure and record the axial clearance (A) between the base of the
Gov End first stage stationary blade outlet and the shroud of the first
stage rotating blade inlet.

Note
Clearance A for the Gov End first stage is clearance K.

Repeat Step 1 above for the second through seventh stages.

Measure and record the clearance B between the end of the first
stage stationary blade outlet and the base of the first stage rotating
blade inlet.

Repeat Step 3 above for the second through seventh stages.

Measure and record the clearance E between shroud of the first


stage rotating blade outlet and the base of the second stage
stationary blade inlet.

Repeat Step 5 above for the second through fourth stages.

Measure and record the clearance F between the base of the first
stage rotating blade outlet and the end of the second stage stationary
blade inlet.

Repeat Step 7 above for the second through sixth stages.

Measure and record the rotating and stationary blading seal strip
radial clearances.

Note
If the seal strip clearances exceed 200% of the design
clearances, seal strip replacement should be considered.

MM-M05.01

Rev.001

10 Repeat the above procedure to measure the LP2 Gen End rotor and
casing clearances.

Main Turbine
Mitsubishi

5-104

Chapter 5

Disassembly and Reassembly

Removal of LP2 Rotor


Refer to Figure 5-26.
1

Ensure that the LP rotor support stand is assembled in the lay-down


area.

Note
Before attempting to remove the rotor, it is necessary to
remove other equipment to eliminate interference or provide
clearance.

Have the electricians remove the vibration and differential expansion


pick-ups.

Remove the covers from No.4&5 and No.6 bearing pedestals,


coupling cooling oil lines, upper half of the coupling guards, coupling
bolts and coupling spacer/spacer gear from the LP1~LP2 coupling
and LP2~generator couplings in accordance with the mechanical
maintenance manual M 05.05, Turbine Couplings and Alignment.

Remove the upper halves of No.5 and No.6 bearings in accordance


with mechanical maintenance manual M 05.04, Turbine Bearings
and Thrust Bearing.

Install the LP rotor guide pillars (supplied as Special Tools) at the Gov
End and Gen End of the outer casing base, as shown in Figure 5-17.

Confirm that there is clearance between the LP1 and LP2 coupling
flange faces.

Confirm that there is clearance between the LP2 and generator


coupling flange faces.

Install the LP rotor lifting gear to the LP2 rotor as shown in Appendix
H.

Adjust the wire rope slings from the center of the lifting beam to lift the
rotor evenly.

10 Using the turn buckle, level the rotor with a machinist spirit level.
11 Lift the LP2 rotor high enough to make sure that there is sufficient
axial clearance for the rotor removal.

MM-M05.01

Rev.001

12 Tie a tag line to each end of the LP2 rotor to allow control of the rotor
during the lift.

Main Turbine
Mitsubishi

5-105

Chapter 5

Disassembly and Reassembly

CAUTION
Slow and careful removal of the LP rotor must be performed to
ensure that damage does not occur to the rotor or casing
blades.

13

Lift the LP2 rotor in small increments and ensure that no binding
occurs.

14

Lift the LP2 rotor clear of the turbine.

15
16

Transport the LP2 rotor to the lay-down area.


Lubricate the rotor support stand saddles and set the LP2 rotor in
the support stand.

Note
Ensure that the rotor journals are protected prior to setting the
rotor in the support stand.

18 Remove the lower halves of No.5 and No.6 bearings.

Removal of LP2 Inner Flow Guide Ring Lower Half


1

Remove the set screws and then remove the nuts from the inner flow
guide ring fixing studs which secure the lower half inner flow guide
ring to the lower half steam chamber. Refer to Figure 5-19 for details.

Install eye bolts in the inner flow guide ring lower half.

Install suitable lifting gear and make a trial lift.

Adjust the chain blocks to evenly lift the inner flow guide ring.

Set support blocks on the floor.

Lift the inner flow guide ring clear of steam chamber.

Transport the inner flow guide ring to the lay-down area and set it on
wooden blocks.

Disconnect and remove the lifting gear.

MM-M05.01

Rev.001

Removal of LP2 Blade Ring Lower Halves

Main Turbine
Mitsubishi

Install eye bolts in the lower half LP2 blade ring at the Gov End.

Install suitable lifting gear and make a trial lift.

5-106

Chapter 5

Disassembly and Reassembly

Adjust the chain blocks to evenly lift the blade ring.

Set support blocks on the floor.

Lift the lower half blade ring clear of the steam chamber base.

Transport the blade ring to the lay-down area and set it on wooden
blocks.

Disconnect and remove the lifting gear.

Following a similar procedure, remove the lower half LP2 blade ring
at the Gen End.

Removal of LP2 Steam Chamber Base


1

Remove the hexagonal socket head bolts which secure the steam
chamber base to the inner casing base.

Install eye bolts in the steam chamber base.

Install suitable lifting gear and make a trial lift.

Adjust the chain blocks to evenly lift the steam chamber base.

Set support blocks on the floor.

Lift the steam chamber base clear of the inner casing base.

Transport the steam chamber base to the lay-down area and set it on
wooden blocks.

Disconnect and remove the lifting gear.

Removal of LP2 Inner Casing Base


Remove the nuts from the stud bolts which secure the inner casing
base to the outer casing base.

Install suitable lifting gear and make a trial lift.

Adjust the chain blocks to evenly lift the inner casing.

Set support blocks on the floor.

Transport the inner casing base to the lay-down area and set it on
wooden blocks.

Disconnect and remove the lifting gear.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

5-107

Chapter 5

c)

Disassembly and Reassembly

Cleaning and Inspection


LP2 Outer Casing
1

Manually clean the following areas and the associated bolts and nuts:
(i)

Horizontal joint flanges

(ii) Manhole flanges


(iii) Breakable diaphragm areas.
2

Visually inspect the following areas for erosion, wear, steam cuts,
cracks, or other damage:
(i)

Cover (horizontal joint)

(ii) Base (horizontal joint)


(iii) Outer casing to inner casing fits
(iv) Crossover pipe flange and top seal ring
(v) Manholes
(vi) Breakable diaphragm seating surfaces.

Note
Any discrepancies found should be corrected by stoning or
honing.

Perform NDT on the following areas:


(i) Cover (horizontal joint)
(ii) Base (horizontal joint)
(iii) Joint bolts
(iv) Steam penetrations.

Visually inspect the threaded portions of the joint bolts for


deformation, galling, binding, or excessive wear.

LP2 Inner Casing


1

Inspect all seal strips for rubs or other signs of damage.

Rev.001

Note

MM-M05.01

Replace seal strips if damaged.

Main Turbine
Mitsubishi

Hand clean the horizontal joint flanges and seals.

Visually inspect the following areas for erosion, wear, steam cuts,
cracks, or other damage:

5-108

Chapter 5

(i)

Disassembly and Reassembly

Cover (horizontal joint)

(ii) Base (horizontal joint)


(iii) Stationary blade diaphragms
(iv) Inner casing to outer casing and steam chamber fits
(v) Steam penetrations.

Note
Any discrepancies found should be corrected by stoning or
honing.

Perform NDT on the following areas:


(i)

Cover (horizontal joint)

(ii) Base (horizontal joint)


(iii) Stationary blades
(iv) Remainder of the stationary blade diaphragms
(v) Joint bolts
(vi) Steam penetrations.
5

Visually inspect the threaded portions of the joint bolts for


deformation, galling, binding or excessive wear.

Visually inspect the stationary blade diaphragms to inner casing fits


and the packing strips for looseness and wear.

Visually inspect the inner casing drains for blockage.

LP2 Steam Chamber


1

Hand clean the horizontal joint flanges and bolts.

Visually inspect the following areas for erosion, wear, steam cuts,
cracks, or other damage:
(i)

Cover (horizontal joint)

(ii) Base (horizontal joint)

Rev.001

(iii) Steam chamber to inner casing, LP blade ring and inner flow
guide fits

MM-M05.01

(iv) Steam penetrations.

Main Turbine
Mitsubishi

5-109

Chapter 5

Disassembly and Reassembly

Note
Any discrepancies found should be corrected by stoning or
honing.

Perform NDT on the following areas:


(i)

Cover (horizontal joint)

(ii) Base (horizontal joint)


(iii) Remainder of the steam chamber
(iv) Joint bolts
(v) Steam penetrations.
4

Visually inspect the threaded portions of the joint bolts for


deformation, galling, binding or excessive wear.

LP2 Blade Rings


Perform all measurements for the Gov End and Gen End blade rings.
1

Inspect all seal strips for rubs or other signs of damage.

Note
Replace seal strips if damaged.

Hand clean the horizontal joint flanges and seals.

Visually inspect the following components for erosion, wear, steam


cuts, cracks, or other damage:
(i)

Upper half (horizontal joint)

(ii) Lower half (horizontal joint)


(iii) Stationary blades
(iv) LP2 blade ring to steam chamber fits.

Note
Any discrepancies found should be corrected by stoning or
honing.

Perform NDT on the following areas:

Rev.001

(i)

Upper half (horizontal flanges)

MM-M05.01

(ii) Lower half (horizontal flanges)


(iii) Joint bolts

Main Turbine
Mitsubishi

5-110

Chapter 5

Disassembly and Reassembly

(iv) Stationary blades


(v) Remainder of the blade ring.
5

Visually inspect the stationary blade diaphragms to LP2 blade ring fits
and packing strips for looseness and wear.

Visually inspect the threaded portions of the joint bolts for


deformation, galling, binding or excessive wear.

LP2 Inner Flow Guide Ring


1

Inspect all seal rings for rubs or other signs of damage.

Note
Replace seal rings if damaged.

Manually clean the horizontal joint flanges and seal rings.

Visually inspect the following components for erosion, wear, steam


cuts, cracks, or other damage:
(i)

Upper half horizontal flange joint

(ii) Lower half horizontal flange joint


(iii) Inner flow guide ring to steam chamber fits.

Note
Any discrepancies found should be corrected by stoning or
honing.

Perform NDT on the following areas:


(i)

Upper half horizontal flange

(ii) Lower half horizontal flange


(iii) Joint bolts
(iv) Remainder of the inner flow guide ring.
5

Visually inspect the threaded portion of the joint bolts for deformation,
galling, binding or excessive wear.

LP2 Rotor
Rev.001

Inspect all seal strips for rubs or other signs of damage.

MM-M05.01

Note
Replace seal strips if damaged.

Main Turbine
Mitsubishi

5-111

Chapter 5

Disassembly and Reassembly

Visually inspect the tightness of the rotor balancing plugs.

Visually inspect the following components/areas for erosion, wear,


steam cuts, cracks, or other damage:
(i)

Retaining pin

(ii) Rotor gland areas


(iii) Flow guide ring areas
(iv) Stub dampers.
4

Visually inspect the following areas for pitting, deposits, impact


damage, and that the trailing edges are straight and uniform:
(i)

Rotating blades

(ii) Shrouds
(iv) Erosion protection shields.

Note
Any discrepancies found should be corrected by stoning,
honing or component replacement.

Perform NDT on the following:


(i)

Rotating blades

(ii) Blading shroud


(iii) Tenons
(iv) Stubs
(v) Shaft surfaces
(vi) Rotor gland areas
(vii) Rotor journal areas.

d)

Reassembly

Rev.001

The reassembly procedure is carried out in the reverse sequence to that


for disassembly. Install all parts in the same positions they were removed
from, referring to the match marks and checking that the clearances are
maintained as specified.

MM-M05.01

Ensure that all components are free from burrs and bruises, blending
away the defects using fine files, carborundum stones and emery cloth.
All contact surfaces are to be cleaned before starting reassembly. The
reassembly procedure is described below:
Main Turbine
Mitsubishi

5-112

Chapter 5

Disassembly and Reassembly

CAUTION
Prior to the installation of turbine components, thoroughly
inspect the internals for foreign materials. Ensure that the
utmost standards of cleanliness are applied at all times.

Installation of LP2 Inner Casing Base


1

Clean the inner casing base to outer casing and steam chamber
horizontal joint fit areas.

Clean and lubricate the dowel and mating areas on the inner casing
base.

Ensure that the liners are secured correctly to the inner casing base.
Refer to Figure 5-19 for details.

Connect suitable lifting gear.

Make a trial lift and adjust to evenly lift the inner casing base.

Transport the inner casing base from the lay-down area to the LP2
turbine base and align it over the outer casing base.

Lower the inner casing slowly and evenly into the outer casing base
ensuring that the dowel engages the inner casing smoothly. Continue
to lower the inner casing until the horizontal joint is even with that of
the outer casing and the weight is on the outer casing base.

Replace and tighten the nuts onto the stud bolts and secure the inner
casing base to the outer casing base.

Install the dowel pins in the inner casing which locate the steam
chamber in the inner casing.

10 Remove the lifting gear.


11 Install the LP2 shaft gland casing lower halves.

MM-M05.01

Rev.001

Installation of LP2 Steam Chamber Base

Main Turbine
Mitsubishi

Clean the steam chamber base to inner casing, LP2 blade ring and
inner flow guide ring horizontal joint fit areas.

Clean and lubricate the dowel and mating areas on the steam
chamber base.

Ensure that the liners are secured correctly to the steam chamber
base. Refer to Figure 5-19 for details.

5-113

Chapter 5

Disassembly and Reassembly

Install eye bolts in the steam chamber base and tighten.

Connect suitable lifting gear.

Make a trial lift and adjust to evenly lift the steam chamber base.

Transport the steam chamber base from the lay-down area to the LP2
turbine and align it over the inner casing base.

Lower the steam chamber base slowly and evenly into the inner
casing base ensuring that the dowel engages the steam chamber
smoothly. Continue to lower the steam chamber base until the
horizontal joint is even with that of the inner casing and the weight is
on the inner casing base.

Replace and tighten the hexagonal socket head bolts and secure the
steam chamber base to the inner casing base.

10 Remove the lifting gear.

Rev.001

Installation of LP2 Blade Ring Lower Halves


1

Clean the Gov End LP2 blade ring to steam chamber horizontal joint
fit areas.

Clean and lubricate the dowel and mating areas on the lower half LP2
blade ring.

Install the dowel pins in the LP2 blade rings which locate the blade
rings in the steam chamber base.

Install eye bolts in the lower half blade ring and tighten.

Connect suitable lifting gear.

Make a trial lift and adjust to evenly lift the lower half blade ring.

Transport the lower half blade ring from the lay-down area to the LP2
turbine and align it over the steam chamber base.

Lower the lower half blade ring into the steam chamber base
ensuring that the dowel enters the steam chamber smoothly and the
horizontal joint is even with that of the steam chamber base.

Ensure that the lower liners are installed on the steam chamber base.
Replace the aligning plates on the lower half blade ring, if removed
during disassembly, and secure them with the hexagonal socket
head bolts. Refer to Figure 5-19 for details.

MM-M05.01

10 Remove the lifting gear.


11 Following a similar procedure install the Gen End lower half LP2
blade ring.
Main Turbine
Mitsubishi

5-114

Chapter 5

Disassembly and Reassembly

Installation of LP2 Inner Flow Guide Ring Lower Half


1

Clean the lower half inner flow guide ring to steam chamber
horizontal joint fit areas.

Clean and lubricate the dowel and mating areas of the lower half
inner flow guide ring.

Install eye bolts on the inner flow guide ring and tighten.

Connect suitable lifting gear.

Make a trial lift and adjust to evenly lift the inner flow guide ring.

Transport the inner flow guide ring lower half from the lay-down area
to the LP2 turbine and align it over the steam chamber.

Lower the inner flow guide ring slowly and evenly into the steam
chamber base and place it on the liners secured to the steam
chamber base until the horizontal joint is even with the horizontal joint
of the steam chamber and the weight is on the liners.

Remove the lifting gear.

Replace the aligning plates if removed during disassembly and


secure them with hexagonal socket head cap screws. Refer to Figure
5-19 for details.

10 Lubricate the lower half inner flow guide ring fixing studs and install
the washers and nuts.
11 Tighten the nuts and install the set screws.

Installation of LP2 Rotor


Refer to Figure 5- 26.
1

Install the lower halves of No.5 and No.6 bearings in their original
locations.

Visually inspect the LP2 casing base to make sure it is clean and free
of foreign objects before rotor installation.

Install the Gen End and Gov End rotor guide pillars.

Note

MM-M05.01

Rev.001

Rotor guide pillars may not have been removed.

Main Turbine
Mitsubishi

Install the LP rotor lifting gear to the LP2 rotor in accordance with
Appendix H.

Make a trial lift.

5-115

Chapter 5

Disassembly and Reassembly

Adjust the slings from the center of the lifting beam to lift the rotor
evenly and adjust the turnbuckles to make a level lift.

Move the LP2 rotor to the LP2 turbine and align it over the rotor guide
pillars.

Attach tag lines to each end of the rotor to control rotation of the rotor
during installation.

Remove the protective coverings and lubricate the rotor journal


areas.

10 Place a machinist spirit level on the rotor shaft to check the level of
the rotor.

CAUTION
Take care when installing the rotor to ensure that the blading
and the journal areas are not damaged. Clearances between
the fixed and moving blades are limited, as required for
efficient operation. Damage to blading, bearings or rotor
journals can cause serious delays in assembly of the steam
turbine if additional repairs are required.

11 Lower the rotor slowly into the rotor guide pillars while constantly
watching the rotor level.
12 Stop lowering at any change in rotor inclination to determine and
eliminate the cause.
13 Slowly lower the rotor until it is supported by No.5 and No.6 bearings.
14 Check the bearing to journal contact using blue marking on the
journal surface.
15 Lift the rotor slowly, remove the blue marking and smear lubricating
oil on the bearing surfaces.
16 Lower the rotor slowly again until it is supported in the bearings.
17 Remove the rotor guide pillars and block the LP2 rotor to prevent
axial movement.

CAUTION

Rev.001

The rotor must always be rotated in the normal direction. If any


binding or noise is felt or heard while rotating the rotor, stop,
determine and remove the cause of the noise and/or binding.

MM-M05.01

18 Rotate the LP2 rotor slowly to ensure that the rotor turns freely
without rubbing.

Main Turbine
Mitsubishi

5-116

Chapter 5

Disassembly and Reassembly

Setting of LP2 Rotor in the K Position


Refer to Figure 5-23.
Position the LP2 rotor axially in the K position (Right Side: 29.0 0.0 mm;
Left Side: 29.0+1.5/-0.5 mm).

Note
As all axial clearances are based on the correct setting of the
rotor in the K position, the target tolerance is 0 mm.

Measurement of LP2 Shaft Gland Clearances


Refer to Figures 5-21 and 5-22.
Measure and record the clearance between the LP2 Gov End and Gen
End shaft glands and the surface of the rotor as described in mechanical
maintenance manual M05.03, Gland Steam Condenser System and
GSC Exhaust Fan.

Measurement of LP2 Rotor and Casing Clearances


Refer to Figures 5-23 and 5-24.

Note
If LP2 turbine blade top and bottom clearances must be checked,
refer to Appendix G for the procedure.

Note
Measure and record the following clearances at the RS and LS.

Measure and record the axial clearance (A) between the base of the
Gov End first stage stationary blade outlet and the shroud of the first
stage rotating blade inlet.

Note

MM-M05.01

Rev.001

Clearance A for the Gov End first stage is clearance K.

Main Turbine
Mitsubishi

Repeat Step 1 above for the second through seventh stages.

Measure and record the clearance B between the end of the first
stage stationary blade outlet and the base of the first stage rotating
blade inlet.

Repeat Step 3 above for the second through seventh stages.

Measure and record the clearance E between shroud of the first


stage rotating blade outlet and the base of the second stage
stationary blade inlet.

5-117

Chapter 5

Disassembly and Reassembly

Repeat Step 5 above for the second through fourth stages.

Measure and record the clearance F between the base of the first
stage rotating blade outlet and the end of the second stage stationary
blade inlet.

Repeat Step 7 above for the second through sixth stages.

Measure and record the rotating and stationary blading seal strip
radial clearances.

Note
If the seal strip clearances exceed 200% of the design
clearances, seal strip replacement should be considered.

10 Repeat the above procedure to measure the LP2 Gen End rotor and
casing clearances.

Alignment and Coupling


1

Confirm that the oil clearances for No.5 and No.6 bearings are within
the acceptance criteria in accordance with mechanical maintenance
manual M05.04, Turbine Bearings and Thrust Bearing.

Confirm that the coupling alignment is within tolerance. Refer to the


mechanical maintenance manual M05.05.

Install the upper halves of the No.5 and No.6 main bearings.

Install the coupling spacer/ spacer gear for the LP1~LP2 and
LP2~generator couplings and the coupling bolts into the respective
couplings in accordance with mechanical maintenance manual
M05.05.

Replace the coupling guards and restore the coupling cooling oil
connections.

Install the upper half of the coupling guards and the cooling oil lines
for the LP1~LP2 and LP2~generator couplings.

Install the shaft gland seal ring upper halves in accordance with
mechanical maintenance manual M05.03.

Have the electrician install the removed vibration and differential


expansion pick-ups.

MM-M05.01

Rev.001

Installation of LP2 Inner Flow Guide Ring Upper Half

Main Turbine
Mitsubishi

Install eye bolts on the inner flow guide ring upper half.

Rig and transport the inner flow guide ring upper half over the LP2
rotor.

5-118

Chapter 5

Disassembly and Reassembly

Apply a thin coat of triple boiled linseed oil to the horizontal joint
flanges or a special compound for flange surface.

Lubricate the joint bolts with Molykote.

Lower the inner flow guide ring upper half slowly and evenly over the
joint studs until the horizontal joint is closed.

Remove the lifting gear.

Install the nuts and tighten.

Installation of LP2 Blade Ring Upper Halves


1

Install the safety hoist eye bolts on the Gov End LP2 blade ring upper
half.

Rig and transport the upper half blade ring over the LP2 turbine.

Apply a thin coat of triple boiled linseed oil or a special compound for
flange surface to the horizontal joint flanges and to the aligning plate
and liner surfaces.

Lubricate the joint bolts with Molykote.

Lower the upper half blade ring slowly and evenly over the lower half
blade ring until the horizontal joint is closed and the weight is on the
aligning plates.

CAUTION
Care must be taken when installing the upper half blade ring to
ensure that the turbine blading are not damaged. The blading
are installed with tight axial clearances which must remain
intact for correct operation. Damages to the blading can cause
serious delays in turbine assembly if additional repairs are
necessary.

Remove the lifting gear.

Torque tighten the nuts on studs 701 704 in accordance with


Appendix F in the following sequence:
(i)

Reamer bolts 701 and 704

(ii) Bolts 702 and 703.


Following a similar procedure, install the Gen End LP1 blade ring
upper half by torque-tightening the nuts on the reamer bolts 705 and
708 and on the bolts 706 and 707.

Rotate the LP2 rotor to ensure freedom of rotor movement.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

5-119

Chapter 5

Disassembly and Reassembly

Installation of LP2 Steam Chamber Cover


1

Visually inspect the LP2 turbine for foreign material prior to installing
the steam chamber cover.

CAUTION
When working in or over the condenser plenum, take special
care not to drop tools or debris into the condenser tube area.
Damage to the condenser tubes could result in tube leakage.

Install the safety hoist eye bolts on the steam chamber cover.

Rig and transport the steam chamber cover over the LP2 turbine.

Ensure that the upper liners are secured to the steam chamber cover.
Refer to Figure 5-19 for details.

Install the dowels in the upper half LP2 blade rings.

Apply a thin coat of triple boiled linseed oil or a special compound for
flange surface to the horizontal joint flanges and to the liner surfaces.

Lubricate the joint bolts with Molykote.

Lower the steam chamber cover slowly and evenly over the dowels
and the horizontal joint studs until the horizontal joint is closed.

Remove the lifting gear.

10 Torque tighten the nuts on studs 601 618 in accordance with


Appendix F in the following sequence:
(i)

Reamer bolts 601, 609, 610 and 618

(ii) Bolts 617 toward 611 and 608 toward 602.

Installation of LP2 Inner Casing Cover


1

Visually inspect the LP2 turbine for foreign material prior to installing
the inner casing cover.

CAUTION

Rev.001

When working in or over the condenser plenum, take special


care not to drop tools or debris into the condenser tube area.
Damage to the condenser tubes could result in tube leakage.

MM-M05.01

2
3
Main Turbine
Mitsubishi

Install the inner casing guide bolts in the locations indicated in Figure
5-26.
Install the appropriate lifting gear to the inner casing cover.

5-120

Chapter 5

Disassembly and Reassembly

Make a trial lift and adjust the chain blocks or turn buckle, to provide a
level lift.

Transport the inner casing cover and position it above the inner
casing base.

Ensure that the liners are secured to the inner casing cover. Refer to
Figure 5-19 for details.

Install the dowels in the inner casing cover.

Align the inner casing cover with the inner casing guide bolts.

Lubricate the joint bolts and dowels with Molykote.

10 Apply a coat of triple boiled linseed oil or a special compound for the
flange surface of the inner casing horizontal joint and to the liner
surfaces.
11 Check that the inner casing cover horizontal joint is parallel to the
base horizontal joint.
12 Slowly lower and align the inner casing cover with the studs and
dowels.
13 Continue lowering the cover until the horizontal joint is closed.
14 Remove the lifting gear and the inner casing guide bolts.
15 Install the nuts and washers onto the studs and hand tighten.

Bolt heaters are electrical devices capable of causing personal


injury or death if improperly used.

Note
Refer to the Bolt Heating Data in Appendix F to identify the
bolts and determine the required heater type and size. Heat
the bolts in accordance with Bolt Heater Instruction in
Appendix I.

Note
Rev.001

Tighten the nuts without bolt heaters to the torque specified in

MM-M05.01

Appendix F.

Main Turbine
Mitsubishi

5-121

Chapter 5

Disassembly and Reassembly

Note
Install the bolts from both the LS and RS of the LP casing
starting at the transverse centerline, working outwards toward
each end.

16 Install the nuts on the bolts 501 to 572 in the following sequence:
(i)

Heat and tighten reamer bolt 518

(ii) Torque tighten reamer bolts 501, 536, 542, 552, 564 and 572
(iii) Heat and tighten bolts 517 513 and 519 524
(iv) Torque tighten bolts 512 502 and 525 535
(v) Torque tighten bolts 541 537, 551 543, 563 555 and 571
567.
17 Install the access cover plates.
18 Slowly rotate the LP2 rotor to ensure that it turns freely.
19 Install the LP2 shaft gland casing upper halves.

Perform a visual inspection of the LP2 turbine to ensure that no


foreign material is present before installation of the LP2 outer casing
cover.

Install the lifting equipment to the LP2 outer casing cover in


accordance with Appendix H.

Make a trial lift and adjust as necessary to obtain a level lift.

Transport the outer casing cover over the outer casing base and align
it to the outer casing base.

Attach tag lines to each end of the outer casing cover to control the
rotation of the cover during installation.

Lubricate the horizontal joint bolts with Molykote.

Lubricate the outer casing cover horizontal flange with triple boiled
linseed oil or special compound for flange surface.

Rev.001

Slowly lower the outer casing cover, ensuring that the outer cover is
aligned with the outer casing base.

MM-M05.01

Installation of LP2 Outer Casing Cover

Lubricate the jack screws with Molykote and install them in the outer
casing cover.

Main Turbine
Mitsubishi

5-122

Chapter 5

Disassembly and Reassembly

10 Turn the jack screws in the outer casing cover until they protrude 10
mm below the horizontal joint.
11 Lower the outer casing cover slowly until the jack screws rest on the
horizontal joint of the outer casing base.
12 Continue lowering the outer casing cover by slackening the jack
screws equally half a turn at a time.

Note
Follow the downward motion of the outer casing cover with
the crane to ensure that the load is transferred to the jack
screws.

13 Continue to lower the outer casing cover until the horizontal joint is
closed.
14 Remove the lifting gear.
15 Place the washers over the open bolt holes in the outer casing cover
flange.
16 Install the nuts on top of the bolts and tighten.
17 Tighten the outer casing horizontal joint flange bolts in a diametrically
opposite pattern in the following order:
(i)

Reamer bolts.

(ii) Joint bolts starting at the gland bores working outward toward the
corners (transverse direction).
(iii) Joint bolts starting at the transverse centerline towards the
corners (longitudinal direction).
18 Replace the top seal ring between the outer casing cover and the
inner casing cover.

Note
The following items 19 to 22 are performed inside the LP outer
casing cover. Refer to Figure 5-18.

19 Install the lifting gear, and evenly lower the LP exhaust flow guides
into place aligning the eccentric pins as they are lowered.

Rev.001

20 Install and securely tighten the flange bolts into the Gov End and the
Gen End exhaust flow guide upper halves.

MM-M05.01

21 Remove the lifting gear and jack screws.


22 Install the spray nozzle piping to the exhaust flow guides.

Main Turbine
Mitsubishi

5-123

Chapter 5

Disassembly and Reassembly

23 Install the lifting gear on the manhole covers.


24 Rig and transport the manhole covers into position.
25 Install a new gasket on the manhole cover and lower into place.
26 Remove the eye bolts.
27 Install the cover flange bolts and tighten.

Return to Service
Have the electricians connect thermocouple lead wires to the outer
casing cover.

Replace the bearing pedestal covers.

Install the IP to LP1/LP2 crossover pipe.

Replace the insulation and metal cladding removed from the turbine.

Confirm that all instruments removed for the overhaul have been
installed and are available.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

5-124

Chapter 5

0.3~0.5

0.3~0.5

0.2+-0.05

0.2+-0.05
STEAM
CHAMBER

STEAM
CHAMBER

STEAM CHAMBER

STEAM CHAMBER

LP2 BLADE RING

LP2 BLADE RING

0.2+-0.05

0.2+- 0.05
INNER CASING

INNER CASING

A
B

STATIONARY BLADE

6R

7R

A
B

A
B

4R

5R

3C

3R

A 2C 1C A
B B
2R

1R

5C

E
E

4C

A 1C

A
B

2C A3C A

B
1R

B
2R

B
3R

F
F

5R

4R

7C

4C

GEN. SIDE

5C

7C

6C

STATIONARY BLADE

6R

7R

F
RIGHT SIDE

K=29.0 +- 0.0

LEFT SIDE

29.0 +1.5
-0.5

0.2+-0.05

0.2 +-0.05

LP2 ROTOR

6C
Rev.001
MM-M05.01

11.6 +1.5
-0.5

INNER FLOW
GUIDE

31.6 +1.5
-0.5

STATIONARY BLADE

1
2
3
4
5
6
7

ROTOR BLADES
INLET
OUTLET

9.0
9.0
9.0
9.0
31
28.1
46.1

9.8
9.8
9.8
9.8
9.2
11.6
11.6

29
29
29
68.2

29.8
29.8
29.8
68.2
31.6
31.6

BLADE AXIAL CLEARANCE


(TOLERANCE +1.5
-0.5 )
ROTOR BLADES
INLET
OUTLET

29.0
29.0
29.0
51
48.1
61.6

29.8
29.8
29.8
29.8
29.2
31.6
31.6

9.0
9.0
9.0
48.2

9.8
9.8
9.8
48.2
11.6
11.6
-

6C

INNER CASING
STATIONARY BLADE

NOTE: REFER TO FIGURE 5-25 FOR BLADE SEAL RADIAL CLEARANCES


FIGURE 5-20

Main Turbine
Mitsubishi

1
2
3
4
5
6
7

BLADE AXIAL CLEARANCE


(TOLERANCE +1.5
-0.5 )

LP2 ROTOR
INNER FLOW
GUIDE

INNER CASING

GOV. SIDE

6C

ROW No.

7C

ROW No.

7C

MPTD-3-0257

Disassembly and Reassembly

LP2 TURBINE SHELL CLEARANCE

5-125

Chapter 5

Disassembly and Reassembly

SEAL RING

SEAL RING

GLAND
CASING

0.5+-0.1

GLAND
CASING

0.5+-0.1

X
SEAL STRIP

SEAL STRIP

OUTER CASING
COVER

CL OF LP2 ROTOR

GLAND
CASING

0.5+-0.1

SEAL STRIP

GLAND
CASING

LP2 ROTOR

0.5+-0.1

SEAL STRIP

LP2 ROTOR

MM-M05.01

Rev.001

NOTE: REFER TO FIGURE 5-25 FOR BLADE SEAL RADIAL CLEARANCES (X)

MPTD-4-0258

FIGURE 5-21
Main Turbine
Mitsubishi

LP2 TURBINE GOV END SHAFT GLAND DESIGN CLEARANCES

5-126

Chapter 5

Disassembly and Reassembly

SEAL RING

SEAL RING

GLAND
CASING

0.5+-0.1

GLAND
CASING

0.5+-0.1

X
SEAL STRIP

SEAL STRIP

OUTER CASING
COVER

C
L OF LP2 ROTOR

GLAND
CASING

LP2 ROTOR

SEAL STRIP

GLAND
CASING

0.5+- 0.1

0.5+- 0.1

LP2 ROTOR

SEAL STRIP

MM-M05.01

Rev.001

NOTE: REFER TO FIGURE 5-25 FOR BLADE SEAL RADIAL CLEARANCES (X)

MPTD-4-0259

FIGURE 5-22
Main Turbine
Mitsubishi

LP2 TURBINE GEN END SHAFT GLAND DESIGN CLEARANCES

5-127

Chapter 5

Disassembly and Reassembly

0.3 0.1
STATIONARY BLADE
+-

ROTATING BLADE

INNER CASING
LP2 BLADE RING

ROTATING BLADE

6R

0.3 0.1

SEAL STRIP

5R

4R

EXHAUST
FLOW GUIDE

7C

3R
7R

ROTATING BLADE
LP2 BLADE RING

ROTATING
BLADE

6C

SEAL STRIP

5C

1R

4C

2R

1C

0.3 0.1

3C

2C

STATIONARY
BLADE

LP2 ROTOR

0.0

2R

3R

4R

7C

5R

6R

7R

1R

ROTATING BLADE

12

1C

LP2 ROTOR

31.6

0.3 0.1
STATIONARY
BLADE

4C

6C

5C

LP2 ROTOR

MM-M05.01

Rev.001

3C

2C

STATIONARY BLADE

7.5
SEAL STRIP
MPTD-3-0260

LP2 ROTOR

SEAL STRIP

NOTE: REFER TO FIGURE 5-25 FOR BLADE SEAL RADIAL CLEARANCES (X)

FIGURE 5-23
Main Turbine
Mitsubishi

LP2 TURBINE GOV. END ROTOR & CASING DESIGN CLEARANCE

5-128

Chapter 5

Disassembly and Reassembly

0.3 0.1
STATIONARY BLADE
+-

ROTATING BLADE

INNER CASING
ROTATING BLADE

6R

LP2 BLADE RING

0.3 0.1

SEAL STRIP

5R

EXHAUST
FLOW GUIDE

4R

7C

3R
7R

ROTATING BLADE

ROTATING
BLADE

LP2 BLADE RING

6C

SEAL STRIP

5C

STATIONARY
BLADE

3C

2C

4C

0.3 0.1

1C

2R

1R

LP2 ROTOR
6R

7R

4R

5R

3R

2R

ROTATING BLADE

1R

0.0

7C

1C

LP2 ROTOR

11.6

0.3 0.1
STATIONARY
BLADE

4C

5C

6C

3C

2C

LP2 ROTOR

STATIONARY BLADE

MM-M05.01

Rev.001

7.5
SEAL STRIP
M PTD-3-0261

LP2 ROTOR

SEAL STRIP

NOTE: REFER TO FIGURE 5-25 FOR BLADE SEAL RADIAL CLEARANCES (X)

FIGURE 5-24
Main Turbine
Mitsubishi

LP2 TURBINE GEN. END ROTOR & CASING DESIGN CLEARANCE

5-129

Chapter 5

Disassembly and Reassembly

RADIAL SEAL CLEARANCE TABLE (COLD SET/DESIGN


VERTICAL DIRECTION
AFT. ASS'Y
CASING DEFLEC.

NOMINAL CLEA.
ELEMENT

OUTER GLAND
(GOV. END)

LOCATION

LENGTH

AIR SEAL (1)


SEAL RING (2)
SEAL RING (3)
SEAL RING (4)
LP7R (GOV.)

407.75
481.25
555.75
629.75

1.20
1.20
1.20
1.20

0.95
0.90
0.90
0.90

0.25
0.25
0.25
0.25

-0.01
-0.02
-0.03
-0.04

974.85

10.00

10.00

0.25

1433.10
1536.50
1641.40
1816.50
1911.90
2016.30
2076.15
2130.50
2180.80
2232.00
2282.30
2333.50
2379.80
2725.20
2771.50
2822.70
2873.00
2924.20
2974.50
3028.85
3088.70
3193.90
3288.50
3463.60
3568.50
3671.90

2.67
4.00
1.65
2.00
1.50
1.60
1.50
1.30
1.10
1.30
1.10
1.30
1.10
1.10
1.30
1.10
1.30
1.10
1.30
1.50
1.60
1.50
2.00
1.65
4.00
2.67

2.67
4.00
1.65
2.00
1.50
1.60
1.50
1.30
1.10
1.30
1.10
1.30
1.10
1.10
1.30
1.10
1.30
1.10
1.30
1.50
1.60
1.50
2.00
1.65
4.00
2.67

4130.15

10.00

4475.25
4549.25
4623.75
4697.25

1.20
1.20
1.20
1.20

LP7C (GOV.)
LP6R (GOV.)
INNER CASING
LP6C (GOV.)
(GOV. END)
LP5R (GOV.)
LP5C (GOV.)
LP4R (GOV.)
LP4C (GOV.)
LP2 BLADE RING LP3R (GOV.)
LP3C (GOV.)
(GOV. END)
LP2R (GOV.)
LP2C (GOV.)
LP1R (GOV.)
STEAM FLOW
GUIDE INLET
LP1R (GEN.)
LP2C (GEN.)
LP2 BLADE RING LP2R (GEN.)
LP3C (GEN.)
(GEN. END)
LP3R (GEN.)
LP4C (GEN.)
LP4R (GEN.)
LP5C (GEN.)
LP5R (GEN.)
INNER CASING
LP6C (GEN.)
(GOV. END)
LP6R (GEN.)
LP7C (GEN.)
LP7R (GEN.)
OUTER GLAND
(GEN END)

SEAL RING (4)


SEAL RING (3)
SEAL RING (2)
AIR SEAL (1)

AFT. BOTTOM ASS'Y

HORIZONTAL DIRECTION
AFT. ASS'Y
CASING DEFLEC.

NOMINAL CLEA.
23

24

0.75
0.50
0.50
0.50

0.00
0.00
0.00
0.00

10.00

10.00

+0.10
-0.05

2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67

9.68

+0.50
-0.00

0.61
0.61
0.62
0.68

+0.15
-0.05

26

27

28

29
30
29 30
ROTOR AFT. ASY AFT. ASY CASING CASING AT SET. AT SET.
FROM
AFT. ASY AFT. ASY CASING CASING AT SET. AT SET. TOLERANCE
NOMINAL NOMINAL ELEMENT ROTOR
NOMINAL NOMINAL ELEMENT ROTOR
TOLERANCE
No.5 BRG. TOP
SETTING SETTING RIGHT
LEFT
DEFLEC. DEFLEC. RIGHT
BOTTOM SETTING DEFLEC. SETTING TOP
LEFT
BOTTOM
RIGHT
LEFT
BOTTOM DEFLEC. DEFLEC. TOP
LEFT
CLEARA. CLEARA.
CLEARA. CLEARA.
CLEARA. CLEARA.
CLEARA. CLEARA. RIGHT
BOTTOM CLEARA. CLEARA.
CLEARA. CLEARA. TOP

0.00
0.00
0.00
0.00

0.75
0.50
0.50
0.50

0.75
0.50
0.50
0.50

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.75
0.50
0.50
0.50

0.75
0.50
0.50
0.50

+0.15
-0.15

0.00

0.00

10.00

10.00

0.00

0.00

10.00

10.00

+0.50
-0.00

2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67

2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67

2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67

+0.10
-0.05

10.00

10.00

0.00

0.00

10.00

10.00

0.00

0.00

10.00

10.00

+0.50
-0.00

0.50
0.50
0.50
0.75

0.50
0.50
0.50
0.75

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.50
0.50
0.50
0.75

0.50
0.50
0.50
0.75

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.50
0.50
0.50
0.75

0.50
0.50
0.50
0.75

+0.15
-0.05

10

11

10 11

21

22

0.00
0.00
0.00
0.00

1.46
1.47
1.48
1.49

0.69
0.63
0.62
0.61

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

1.46
1.47
1.48
1.49

0.69
0.63
0.62
0.61

+0.15
-0.05

0.75
0.50
0.50
0.50

-0.06

0.00

10.31

9.69

0.00

0.00

10.31

9.69

+0.50
-0.00

0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25

-0.09
-0.10
-0.10
-0.11
-0.12
-0.12
-0.12
-0.12
-0.12
-0.13
-0.13
-0.13
-0.13
-0.13
-0.13
-0.13
-0.13
-0.13
-0.12
-0.12
-0.12
-0.12
-0.11
-0.11
-0.10
-0.10

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

3.01
4.35
2.00
2.36
1.87
1.97
1.87
1.67
1.47
1.68
1.48
1.68
1.48
1.48
1.68
1.48
1.68
1.48
1.67
1.87
1.97
1.87
2.36
2.01
4.35
3.02

2.33
3.65
1.30
1.64
1.13
1.23
1.13
0.93
0.73
0.92
0.72
0.92
0.72
0.72
0.92
0.72
0.92
0.72
0.93
1.13
1.23
1.13
1.64
1.29
3.65
2.32

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

3.01
4.35
2.00
2.36
1.87
1.97
1.87
1.67
1.47
1.68
1.48
1.68
1.48
1.48
1.68
1.48
1.68
1.48
1.67
1.87
1.97
1.87
2.36
2.01
4.35
3.02

2.33
3.65
1.30
1.64
1.13
1.23
1.13
0.93
0.73
0.92
0.72
0.92
0.72
0.72
0.92
0.72
0.92
0.72
0.93
1.13
1.23
1.13
1.64
1.29
3.65
2.32

10.00

0.25

-0.07

0.00

10.32

9.68

0.00

0.00

10.32

0.90
0.90
0.90
0.95

0.25
0.25
0.25
0.25

-0.04
-0.04
-0.03
-0.02

0.00
0.00
0.00
0.00

1.49
1.49
1.48
1.47

0.61
0.61
0.62
0.68

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

1.49
1.49
1.48
1.47

NOTE:
1. RADIAL CLEARANCES AT ASSEMBLY OF LP-2 TURBINE
IS AS SHOWN IN THIS DRAWING IN CASE THAT SETTING
OF EACH PART AND DEFLECTION OF THE ROTOR IS
TAKEN INTO ACCOUNT.

2. THE BASIS OF RADIAL CLEARANCE SETTING


IN THIS DRAWING IS OIL RING BORE.

3. CLEARANCE AT ASSEMBLY OF LP-2 TURBINE IS CALCULATED


BY THE FOLLOWING EQUATIONS.
HOWEVER, SIGNS OF MOVEMENT AND DEFLECTION ARE
TO BE AS SHOWN BELOW.

TOP CLEARANCE

+
+

RIGHT SIDE CLEARANCE


ROTATION

a) AFTER COMPLETION OF ASSEMBLY:


6 = 1 + 3 - 4
TOP CLEARANCE
BOTTOM CLEARANCE 7 = 1 + 2 - 6
RIGHT SIDE CLEARANCE 25 = 21 + 23 LEFT SIDE CLEARANCE 26 = 21 + 22 -

- 5
24
25

b) AT MEASUREMENT WITH LEAD WIRE:


10 = 6 - 8
TOP CLEARANCE
11 = 7 + 9
BOTTOM CLEARANCE
RIGHT SIDE CLEARANCE 29 = 25 - 27
LEFT SIDE CLEARANCE 30 = 26 + 28

BOTTOM CLEARANCE

Rev.001

* RIGHT AND LEFT SIDE CLEARANCES ARE SHOWN


IN CASE THAT THE VIEW IS FROM GOVERNOR
SIDE TO GENERATOR SIDE.

LEFT SIDE CLEARANCE

MM-M05.01

AFT. BOTTOM ASS'Y

25

MPTD-3-0262

FIGURE 5-25
Main Turbine
Mitsubishi

LP2 TURBINE BLADE & GLAND SEALS RADIAL CLEARANCE TABLE

5-130

Disassembly and Reassembly

MM-M05.01

Rev.001

Chapter 5

FIGURE 5-26

LP2 ROTOR GUIDE PILLAR AND INNER CASING GUIDE BOLT


LOCATIONS

Main Turbine
Mitsubishi

5-131

Chapter 6

Corrective Maintenance

C h a p t er

6 Corrective Maintenance
Corrective maintenance means the repair or replacement work to be performed in case of
sudden failure of any part or component of the steam turbine. Though a well-planned
preventive maintenance program is able to reduce the probability of sudden failure of the
steam turbine, unscheduled corrective maintenance is still necessary. Corrective
maintenance is given priority depending on the seriousness of the problem faced and
impact on the plant operation. The schedule for repair of any equipment must be carefully
planned to keep outage time at the minimum.
During such repair or replacement work, inspection must be performed carefully to
determine why the equipment has failed. Good corrective maintenance not only requires
quick restoration of the failed equipment back into service but also demands every effort to
identify and record the cause of the failure. The inspection results will help to find the cause
of the failure. The findings along with possible rectification proposals are to be used as a
feedback to update the preventive maintenance procedures.

6.1

Prerequisites
The prerequisites for the corrective maintenance of the main turbine are as follows:

a)

Scheduling
Unlike preventive maintenance, the scheduling of the corrective maintenance
can be started only after a failure occurred. Depending on the severity of the
problem, the importance of the service provided by the failed equipment and
the availability of manpower to be assigned to the problem, a corrective
maintenance schedule must be prepared to solve the problem at the earliest
opportunity. The schedule should clearly indicate the critical path and the
priority for different parallel activities. Once the schedule is decided, be sure
to observe the schedule so that the maintenance should be completed timely.

b)

Departmental Interface/Notification
Refer to Section 4.1.2, Departmental Interface / Notification.

c)

Isolation of Equipment

d)

Safety Precautions
Refer to Section 4.1.4, Safety Precautions

MM-M05.01

Rev.001

Refer to Section 4.1.3, Isolation of Equipment

Main Turbine
Mitsubishi

6-1

Chapter 6

6.2

Corrective Maintenance

Preparation
a)

Parts, Tools and Equipment


Refer to Subsection 4.2.1 a), Parts, Tools and Equipment.

b)

Documentation
Refer to Subsection 4.2.1 b), Documentation.

6.3

Troubleshooting

MM-M05.01

Rev.001

This section provides information about troubleshooting and servicing for the main
turbine, pertaining to the mechanical maintainer. Tables of faults, possible causes
and remedies have been provided to assist in troubleshooting by qualified
personnel. If any new problem which is not listed in the following table occurs
contact the manufacturer for assistance.

Main Turbine
Mitsubishi

6-2

Chapter 6

TABLE 6-1
Fault
External leakage of steam
from rotor gland

Corrective Maintenance

TROUBLESHOOTING MAIN TURBINE


Possible Cause

Remedy

Gland steam pressure (flow) increased due to:

gland seal clearance excessive

gland steam condenser (GSC) vacuum


low

Replace seal ring


Raise GSC vacuum

External leakage of steam


from casing flange

Rapid fall in steam temperature

Proper steam temperature


control/unloading rate

Erosion of turbine
components and horizontal
flange joint

Continuous leakage of steam through narrow


gap

Re-weld the eroded surface


and grind/machine the
welded surface

External leakage of steam


from steam piping flange

Flange bolts tightening insufficient

Tighten the flange bolts

External leakage of lube oil


from bearing pedestal

Low vacuum in pedestal or main oil tank

Increase loading of vapor


extractor fan
Check and close any open
man hole/inspection door

Excessive oil seal clearance

Introduce seal air temporarily


Adjust or replace oil seals
during shutdown

Abnormal noise in rotor


turning gear

Excessive bearing clearance


Excessive backlash of gears
Abnormal gear engagement

Routine overhaul
Replace damaged parts

Abnormal noise in pedestal


base slide mechanism
(during start-stop/load
replace)

Insufficient lubrication/deteriorated grease

Replenish lubricant

Malfunction of rotor
grounding device

Grounding circuit interrupted by nonconductive


glazed product deposited on rotor surface

Clean or replace copper


braids during shutdown

Electrostatic erosion of
bearings

Electrostatic discharge causes melting, pitting


and pockmarks on bearing face

Check and clean or replace


copper braids of rotor
grounding device during
shutdown

Magnetization of rotor and


casing

Magnetized by electrostatic charge

Check and clean or replace


copper braids of rotor
grounding device during
shutdown

Rotor vibration

Blade failure
Rotor unbalance

Replace blades
Perform balancing of rotor

Mass unbalance due to


bearing misalignment

Bearing alignment disturbed during operation

Check and correct bearing


seating surface
Perform rotor realignment

Loosening of bearing carrier/shell, support


keys, liners, etc.

Check and rectify the cause


for looseness of bearings
Perform rotor realignment

Uneven settling of foundation

Provide additional shims


below bearing pedestals and
perform rotor realignment

MM-M05.01

Rev.001

Sinking of foundation

Main Turbine
Mitsubishi

6-3

Chapter 6

Corrective Maintenance

Continued from previous page.


TABLE 6-1
Fault
Internal rubbing/contact
between rotor and stationary
parts

Rev.001

Possible Cause

Remedy

Damaged bearings

Rectify or replace damaged


bearings

Damaged shaft gland seals

Rectify or replace damaged


gland seals

Dust accumulation on oil retaining ring seals

Proper housekeeping and


clean seals during overhaul

Excessive casing deformation

Machine the excessively


deformed casing and set the
clearances within limits

Turbine rolling with very low steam


temperature

Roll turbine with proper


steam temperature

Failure of controls to shutdown the turbine on


FW heaters high level

Rectify failure of Water


Induction Protection controls

Control stage nozzle erosion

Eroded by solid particles (pipe internal surface


metal oxidized during outage and wiped off
and carried over by high velocity main steam)

Protect pipe internals with


inert gas during long-term
outage
Perform free blowing after
major overhaul

LP turbine blade and stellite


shield strips erosion

Operation with low steam temperature

Operate with correct steam


temperature

Eroded by impingement of water droplet


formed in the wet steam region

Operate with correct steam


temperature and replace
eroded stellite strips

Blockage of casing drain

Clear drain blockage

Gradual rise in internal


steam pressure on nozzles
and blades

Scale deposition on blades

Remove scale during


overhauling
Perform washing operation

Gradual rise in thrust loading


on thrust bearing

Thrust unbalance due to change in pressure


because of scale deposit on blades

Remove scale during


overhauling
Perform washing operation

High water content in the oil

Gland steam leakage into the bearing pedestal

Replace damaged gland seal


rings
Raise gland steam condenser
vacuum

Too high vacuum inside the main oil tank

Throttle vapor extraction fan


suction damper

Entry of rainwater into main oil tank through


vapor extraction fan exhaust line

Prevent ingress of rainwater

Internal leakage of oil cooler

Rectify cooler leakage

Solid particle in lube oil filter

Entry of foreign matter in lube oil


Machining wear
Cavitation erosion

Identify source of
foreign .particle and rectify

External leakage of lube oil


from oil piping

Failure of piping joints


Failure of pipe weld

Replace failed joint gasket.


Rectify defective weld

Water induction

MM-M05.01

TROUBLESHOOTING MAIN TURBINE

Main Turbine
Mitsubishi

6-4

Chapter 6

Corrective Maintenance

Continued from previous page.


TABLE 6-1

TROUBLESHOOTING MAIN TURBINE

Fault

Fault

Fault

Oil leakage from O-rings of oil


seals

Age deterioration

Routine renewal

Fluctuation in auto-stop oil


press

Loose/faulty spring for HP relief valve

Routine inspection

Dust adhering to seat or small clearance


location

Clearance adjustment

Malfunction of relief valve(s)

Rectify and/or adjust relief valve

Sticking due to dirt lodged in small


clearance areas

Control dust/cleanliness

Faulty/loose connecting pin

Repair or replace pin

Air trapped in HP oil

Vent the HP oil system

Blocked filters

Clean or replace filter elements

Malfunction of relief valve(s)

Rectify and/or adjust oil pressure


adjusting valve

Defective oil ejector

Rectify oil ejector

Air trapped in bearing lube oil system

Vent the lube oil system

Malfunction of bearing oil pressure


adjusting valve

Rectify and/or adjust oil pressure


adjusting valve

Scale deposited on stem-bush clearance

Remove scale by overhauling

Blocked filter

Replace filter element

Stem is bent

Replace stem

Dump valve will not open

Dump valve seat is leaking

Disassemble and check dump


valve

Dump valve HP fluid supply is


restricted

Filter is clogged, or stop valve is closed

Clean the oil filter

Steam admission valve will


not close

Servo-valve is clogged or inactive

Check or replace servo-valve

LVDT is faulty

Check or replace LVDT

Closing spring is faulty or stuck

Check by overhauling

Hysteresis increased

LVDT feedback is faulty

Loose connection or interference,


check visually

Oil pump motor over current


(AOP/TOP/EOP)

Low pump discharge pressure

Adjust oil pressure to rated value

Excessive noise and vibration


of oil pump (AOP/TOP/EOP)

Pump misalignment

Realign the pump and motor


Overhaul the oil pump

Fluctuation in HP oil pressure


and/or speed responsive

Abnormal E/H oil pressure

Fluctuation in bearing oil


press

Steam admission valve


movement is sluggish/stuck

Reduced pump discharge


flow (AOP/TOP/EOP)

Impeller wear ring clearance increased


Blocked suction filter

Replace wear ring


Clean chocked filter

Reduced pump discharge


flow (MOP)

Impeller wear ring clearance increased


Defective oil ejector

Replace wear ring


Rectify oil ejector

MM-M05.01

Rev.001

Internal rubbing or contact

Main Turbine
Mitsubishi

6-5

Chapter-7

Recommended Lubrication

Recommended
7 L u b r ic a t io n

C h a p t er

MM-M05.01

Rev.001

The major requirement of the main turbine lubrication is to lubricate the turbine journal and thrust
bearings and the sliding surfaces of the turbine casings at certain locations. Details of the
lubrication for the turbine casing sliding surfaces are provided in this chapter. For details of the
turbine journal and thrust bearings lubrication, refer to the mechanical maintenance manual
M 05.08, Turbine Main Oil Tank and Auxiliary Pumps.

Main Turbine
Mitsubishi

7-1

Recommended Lubrication

MM-M05.01

Rev.001

Chapter-7

Main Turbine
Mitsubishi

7-2

Recommended Lubrication

MM-M05.01

Rev.001

Chapter-7

Main Turbine
Mitsubishi

7-3

Appendix A

A p p en d i x

A Torque Chart
TABLE A-1
Bolt
Size
(mm)

STRETCH FOR ALLOY STEEL BOLTS


Torque (kg-m)

Alloy Steel (SCM 435 / 440)

Carbon Steel (S35C /


S45C)

Carbon Steel (SS400)

0.82

0.90

0.74

0.51

0.56

0.46

0.43

0.47

0.39

2.0

2.2

1.8

1.2

1.3

1.1

1.0

1.1

0.9

10

3.9

4.3

3.5

2.5

2.8

2.2

2.1

2.3

1.9

12

6.8

7.5

6.1

4.2

4.6

3.8

3.6

4.0

3.2

14

11

12

10

6.7

7.4

6.0

5.7

6.3

5.1

16

16

18

14

10

11

9.0

8.6

9.5

7.7

18

22

24

20

14

15

13

12

13

11

20

32

35

29

20

22

18

17

19

15

22

42

46

38

26

29

23

22

24

20

24

54

59

49

34

37

31

29

32

26

27

79

87

71

50

55

45

42

46

38

30

108

119

97

67

74

60

57

63

51

33

145

160

130

91

100

82

77

85

69

36

188

207

169

117

129

105

100

110

90

39

242

266

218

151

166

136

129

142

116

42

300

330

270

188

207

169

160

176

144

45

375

412

338

234

257

211

199

219

179

48

453

498

408

283

311

255

241

265

217

52

583

641

525

365

402

328

310

341

279

56

722

794

650

451

496

406

383

421

345

60

892

981

803

557

613

501

474

521

427

64

1073

1180

966

671

738

604

570

627

513

68

1292

1421

1163

807

888

726

686

755

617

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

A-1

Appendix A

TABLE A-2

ALLOY STEEL BOLT TIGHTENING TORQUE

Bolt Diameter

Torque (kg-m)

Inch

mm

SCM435
(SAE4135/AISI4137)

W-10705BU
(AISI616 Type 22)

W-15106FD
(AISI690)

1/2

(12.7)

5.4

6.2

8.1

5/8

(15.9)

10.9

12.5

16.3

3/4

(19.1)

18.2

20.8

27.0

7/8

(22.2)

29.1

33.4

43.4

(25.4)

44.5

50.8

66.0

1-1/8

(28.6)

64.5

73.7

95.8

1-1/4

(31.8)

90.7

103.7

134.8

1-3/8

(34.9)

123.4

141.0

183.3

1-1/2

(38.1)

145.3

166.0

215.8

1-5/8

(41.3)

199.5

228.0

296.4

1-3/4

(44.5)

272.1

311.0

404.3

1-7/8

(47.6)

363.1

415.0

539.5

(50.8)

399.0

456.0

592.8

Example
SCM435

Bolt Diameter

1 inch

Required Torque

145.3 kg-m

Wrench Handle Length

1.5 m

Required Force is 145.3/1.5

96.9 kg

MM-M05.01

Rev.001

Bolt Material

Main Turbine
Mitsubishi

A-2

Appendix B

Recommended
B Spare Parts

MM-M05.01

Rev.001

A p p en d i x

Main Turbine
Mitsubishi

B-1

Appendix B

TABLE B-1
Supplier
Name

Eqt. ID No.

RECOMMENDED LIST OF STRATEGIC SPARE PARTS


Parts Description

Eqt.
Description

Qty

03MAA31AE101

Outer casing bolt

Steam Turbine

1 set

MHI

03MAA31AE101

Outer casing nut

Steam Turbine

1 set

MHI

03MAA31AE101

Outer casing washer

Steam Turbine

1 set

MHI

03MAA31AE101

Blade ring bolt

Steam Turbine

1 set

MHI

03MAA31AE101

Blade ring nut

Steam Turbine

1 set

MHI

03MAA31AE101

Dummy ring bolt

Steam Turbine

1 set

MHI

03MAA31AE101

Dummy ring nut

Steam Turbine

1 set

MHI

03MAA31AE101

Dummy ring seal ring

Steam Turbine

MHI

03MAA31AE101

Stack ring of main steam inlet

Steam Turbine

MHI

03MAA31AE101

Piston ring of No.6 & 8 Extraction

Steam Turbine

MHI

03MAA31AE101

Piston ring of cooling steam inlet

Steam Turbine

MHI

03MAA31AE101

Earth brush (copper braid)

Steam Turbine

MHI

03MAA31AE101

IP2C seal ring assembly

Steam Turbine

MHI

03MAA31AE101

IP3C seal ring assembly

Steam Turbine

MHI

03MAA31AE101

IP4C seal ring assembly

Steam Turbine

MHI

03MAA31AE101

IP5C seal ring assembly

Steam Turbine

MHI

03MAA31AE101

IP6C seal ring assembly

Steam Turbine

MHI

03MAA31AE101

IP7C seal ring assembly

Steam Turbine

MHI

03MAA31AE101

IP8C seal ring assembly

Steam Turbine

MHI

03MAA31AE101

LP 5R seal ring assy. (RH/LH)

Steam Turbine

MHI

03MAA31AE101

LP 6R seal ring assy. (RH/LH)

Steam Turbine

MHI

03MAA31AE101

LP 7R seal ring assy. (RH/LH)

Steam Turbine

MHI

03MAA31AE101

LP 6C seal ring assy. (RH/LH)

Steam Turbine

MHI

03MAA31AE101

LP 7C seal ring assy. (RH/LH)

Steam Turbine

MHI

03MAA31AE101

LP 5R moving blade assy. (RH/LH)

Steam Turbine

MHI

03MAA31AE101

LP 6R moving blade assy. (RH/LH)

Steam Turbine

MHI

03MAA31AE101

LP 7R moving blade assy. (RH/LH)

Steam Turbine

MM-M05.01

Rev.001

MHI

Main Turbine
Mitsubishi

B-2

Appendix B

Continued from previous page.


TABLE B-1
Supplier
Name

RECOMMENDED LIST OF STRATEGIC SPARE PARTS

Eqt. ID
No.

Parts Description

Eqt.
Description

Qty

03MAA31AE101

HIP/LP3A coupling part reamer bolt

Steam Turbine

MHI

03MAA31AE101

HIP/LP3A coupling part nut

Steam Turbine

MHI

03MAA31AE101

LP3A/LP3B coupling part reamer bolt

Steam Turbine

MHI

03MAA31AE101

LP3A/LP3B coupling part nut

Steam Turbine

MHI

03MAA31AE101

LP3B/Gen coupling part reamer bolt

Steam Turbine

MHI

03MAA31AE101

LP3B/Gen coupling part nut

Steam Turbine

MM-M05.01

Rev.001

MHI

Main Turbine
Mitsubishi

B-3

Appendix B

TABLE B-2

RECOMMENDED LISTS OF STRATEGIC SPARE PARTS (OFF SHORE)

MM-M05.01

Rev.001

ON HAND QTY.
STRATEGIC
SPARE PARTS

LEAD
TIME
(PO TO
FOB) Wk

STEAM TURBINE

62

NO. 2 JOURNAL
BEARING

STEAM TURBINE

62

03MAA31AE101

NO.3,4,5 JOURNAL
BEARING METAL

STEAM TURBINE

62

MHI

03MAA31AE101

NO. 6 JOURNAL
BEARING

STEAM TURBINE

62

MHI

03MAA31AE101

THRUST BEARING

STEAM TURBINE

62

MHI

03MAA31AE101

OUTER CASING
BOLT

STEAM TURBINE

1 SET

47

MHI

03MAA31AE101

OUTER CASING
NUT

STEAM TURBINE

1 SET

47

MHI

03MAA31AE101

OUTER CASING
WASHER

STEAM TURBINE

1 SET

47

MHI

03MAA31AE101

BLADE RING BOLT

STEAM TURBINE

1 SET

47

MHI

03MAA31AE101

BLADE RING NUT

STEAM TURBINE

1 SET

47

MHI

03MAA31AE101

DUMMY RING BOLT

STEAM TURBINE

1 SET

47

MHI

03MAA31AE101

DUMMY RING NUT

STEAM TURBINE

1 SET

47

MHI

03MAA31AE101

GLAND SEAL RING

STEAM TURBINE

37

MHI

03MAA31AE101

DUMMY RING SEAL


RING

STEAM TURBINE

37

SUPPLIER
NAME

EQT .

MHI

03MAA31AE101

NO. 1 JOURNAL
BEARING

MHI

03MAA31AE101

MHI

Main Turbine
Mitsubishi

PARTS
ID

PARTS DESCRIPTION

SUB-ASSEMBLY/
EQT DESCRIPTION

MAN.
PARTS NO.

MAN.
DWG. NO.

EQT. SUPPLIER
PARTS NO.

SPARE
PARTS 1 YR

B-4

REMARKS

Appendix B

Continued from previous page.


TABLE B-2

RECOMMENDED LISTS OF STRATEGIC SPARE PARTS (OFF SHORE)

MM-M05.01

Rev.001

ON HAND QTY.
STRATEGIC
SPARE PARTS

LEAD
TIME
(PO TO
FOB) Wk

STEAM TURBINE

47

PISTON RING NO. 6


& 8 EXTRACTION

STEAM TURBINE

62

03MAA31AE101

PISTON RING OF
COOLING STEAM
INLET

STEAM TURBINE

62

MHI

03MAA31AE101

EARTH BRUSH
(COPPER BRAID)

STEAM TURBINE

17

MHI

03MAA31AE101

OIL SEAL RING

MAIN OIL PUMP

22

MHI

03MAA31AE101

IP2C SEAL RING


ASSEMBLY

MAIN OIL PUMP

50

MHI

03MAA31AE101

IP3C SEAL RING


ASSEMBLY

MAIN OIL PUMP

50

MHI

03MAA31AE101

IP4C SEAL RING


ASSEMBLY

MAIN OIL PUMP

50

MHI

03MAA31AE101

IP5C SEAL RING


ASSEMBLY

MAIN OIL PUMP

50

MHI

03MAA31AE101

IP6C SEAL RING


ASSEMBLY

MAIN OIL PUMP

50

MHI

03MAA31AE101

IP7C SEAL RING


ASSEMBLY

MAIN OIL PUMP

50

MHI

03MAA31AE101

IP8C SEAL RING


ASSEMBLY

MAIN OIL PUMP

50

SUPPLIER
NAME

EQT .

MHI

03MAA31AE101

SLACK RING OF
MAIN STEAM INLET

MHI

03MAA31AE101

MHI

Main Turbine
Mitsubishi

PARTS
ID

PARTS DESCRIPTION

SUB-ASSEMBLY/
EQT DESCRIPTION

MAN.
PARTS NO.

MAN.
DWG. NO.

EQT. SUPPLIER
PARTS NO.

SPARE
PARTS 1 YR

B-5

REMARKS

Appendix B

Continued from previous page.


TABLE B-2

RECOMMENDED LISTS OF STRATEGIC SPARE PARTS (OFF SHORE)

MM-M05.01

Rev.001

ON HAND QTY.
STRATEGIC
SPARE PARTS

LEAD
TIME
(PO TO
FOB) Wk

MAIN OIL PUMP

50

LP6R SEAL RING


ASSY (RH/LH)

MAIN OIL PUMP

50

03MAA31AE101

LP7R SEAL RING


ASSY (RH/LH)

MAIN OIL PUMP

50

MHI

03MAA31AE101

LP6C SEAL RING


ASSY (RH/LH)

MAIN OIL PUMP

50

MHI

03MAA31AE101

LP7C SEAL RING


ASSY (RH/LH)

MAIN OIL PUMP

50

MHI

03MAA31AE101

LP5R MOVING BLADE


ASSY(RH/LH)

MAIN OIL PUMP

74

MHI

03MAA31AE101

LP6R MOVING BLADE


ASSY (RH/LH)

MAIN OIL PUMP

74

MHI

03MAA31AE101

LP7R MOVING BLADE


ASSY (RH/LH)

MAIN OIL PUMP

74

MHI

03MAA31AE101

HIP/LP 3A COUPLING
PART REAMER BOLT

MAIN OIL PUMP

50

MHI

03MAA31AE101

HIP/LP 3A COUPLING
PART NUT

MAIN OIL PUMP

50

MHI

03MAA31AE101

LP3A/3B COUPLING
PART REAMER BOLT

MAIN OIL PUMP

50

MHI

03MAA31AE101

LP3A/3B COUPLING
PART NUT

MAIN OIL PUMP

50

SUPPLIER
NAME

EQT .

MHI

03MAA31AE101

LP 5R SEAL RING
ASSY (RH/LH)

MHI

03MAA31AE101

MHI

Main Turbine
Mitsubishi

PART
ID

PARTS DESCRIPTION

SUB-ASSEMBLY/
EQT DESCRIPTION

MAN.
PARTS NO.

MAN.
DWG. NO.

EQT. SUPPLIER
PARTS NO.

SPARE
PARTS 1 YR

B-6

REMARKS

Appendix B

Continued from previous page.


TABLE B-2

RECOMMENDED LISTS OF STRATEGIC SPARE PARTS (OFF SHORE)

MM-M05.01

Rev.001

INITIAL QUANTITY

ON HAND QTY.
STRATEGIC
SPARE PARTS

LEAD
TIME
(PO TO
FOB) Wk

MAIN OIL PUMP

50

LP3B/GEN COUPLING
PART NUT

MAIN OIL PUMP

50

BUSHING

MAIN STOP VALVE

38

03MAA02AA1

BONNET GASKET

MAIN STOP VALVE

18

MHI

03MAA02AA1

MAIN VALVE

MAIN STOP VALVE

40

MHI

03MAA02AA1

VALVE STEM

MAIN STOP VALVE

30

MHI

03MAA02AA1

PLUG

MAIN STOP VALVE

18

MHI

03MAA02AA1

PILOT VALVE

MAIN STOP VALVE

22

MHI

03MAA02AA1

VALVE NUT

MAIN STOP VALVE

26

MHI

03MAA02AA1

SPRING SUPPORT

MAIN STOP VALVE

10

26

MHI

03MAA02AA1

SPRING

MAIN STOP VALVE

15

26

MHI

03MAA02AA1

10

BUSHING

MAIN STOP VALVE

16

38

MHI

03MAA02AA1

11

BUSHING

MAIN STOP VALVE

17

38

MHI

03MAA02AA1

12

HEX.SOCKET HEAT
BOLT

MAIN STOP VALVE

19

12

22

MHI

03MAA02AA1

13

SPRING GUIDE ROD

MAIN STOP VALVE

20

30

MHI

03MAA02AA1

14

PIN

MAIN STOP VALVE

21

18

MHI

03MAA02AA1

15

LINER

MAIN STOP VALVE

22

58

SUPPLIER
NAME

EQT .

MHI

03MAA31AE101

LP3B/GEN COUPLING
PART REAMER BOLT

MHI

03MAA31AE101

MHI

03MAA02AA1

MHI

Main Turbine
Mitsubishi

PART
ID

PARTS DESCRIPTION

SUB-ASSEMBLY/
EQT DESCRIPTION

MAN.
PARTS NO.

PER EACH
QTY.

TOTAL
PLANT

SPARE
PARTS 1 YR

B-7

REMARKS

Appendix B

Continued from previous page.


TABLE B-2

RECOMMENDED LISTS OF STRATEGIC SPARE PARTS (OFF SHORE)


INITIAL QUANTITY

MM-M05.01

Rev.001

SUPPLIER
NAME

EQT .

PART
ID

PARTS DESCRIPTION

SUB-ASSEMBLY/
EQT DESCRIPTION

MAN.
PARTS NO.

PER EACH
QTY.

TOTAL
PLANT

ON HAND QTY.
SPARE
PARTS 1 YR

STRATEGIC
SPARE PARTS

LEAD
TIME
(PO TO
FOB) Wk

MHI

03MAA02AA1

16

STUD BOLT

MAIN STOP VALVE

23

16

42

MHI

03MAA02AA1

17

CUP NUT

MAIN STOP VALVE

24

16

22

MHI

03MAA02AA1

18

SPHERICAL WASHER

MAIN STOP VALVE

25

16

26

MHI

03MAA02AA1

19

SPHERICAL WASHER

MAIN STOP VALVE

26

16

26

MHI

03MAA02AA1

20

STUD BOLT

MAIN STOP VALVE

27

18

36

42

MHI

03MAA02AA1

21

CUP NUT

MAIN STOP VALVE

28

18

36

36

MHI

03MAA02AA1

22

SPHERICAL WASHER

MAIN STOP VALVE

29

18

36

26

MHI

03MAA02AA1

23

SPHERICAL WASHER

MAIN STOP VALVE

30

18

36

26

MHI

03MAA02AA1

24

PLUG

MAIN STOP VALVE

31

18

36

18

MHI

03MAA02AA1

25

PLUG

MAIN STOP VALVE

32

18

36

18

MHI

03MAA02AA1

26

BUSHING

MAIN STOP VALVE

71

38

MHI

03MAA02AA1

27

VALVE SEAT

MAIN STOP VALVE

38

MHI

03MAA03AA1

STUD BOLT

GOVERNING VALVE

12

48

12

42

MHI

03MAA03AA1

CAP NUT

GOVERNING VALVE

12

48

12

38

MHI

03MAA03AA1

SPHERICAL WASHER

GOVERNING VALVE

12

48

12

20

MHI

03MAA03AA1

SPHERICAL WASHER

GOVERNING VALVE

12

48

12

26

MHI

03MAA03AA1

BONNET GASKET

GOVERNING VALVE

13

18

MHI

03MAA03AA1

VALVE

GOVERNING VALVE

14

22

MHI

03MAA03AA1

VALVE NUT

GOVERNING VALVE

15

30

Main Turbine
Mitsubishi

B-8

REMARKS

Appendix B

Continued from previous page.


TABLE B-2

RECOMMENDED LISTS OF STRATEGIC SPARE PARTS (OFF SHORE)


INITIAL QUANTITY

MM-M05.01

Rev.001

SUPPLIER
NAME

EQT .

PART
ID

PARTS DESCRIPTION

SUB-ASSEMBLY/
EQT DESCRIPTION

MAN.
PARTS NO.

PER EACH
QTY.

TOTAL
PLANT

ON HAND QTY.
SPARE
PARTS 1 YR

STRATEGIC
SPARE PARTS

LEAD
TIME
(PO TO
FOB) Wk

MHI

03MAA03AA1

PIN

GOVERNING VALVE

16

16

42

MHI

03MAA03AA1

VALVE STEM

GOVERNING VALVE

17

30

MHI

03MAA03AA1

10

BUSHING

GOVERNING VALVE

18

38

MHI

03MAA03AA1

11

BUSHING

GOVERNING VALVE

19

30

MHI

03MAA03AA1

12

HEX. SOCKET HEAD


BOLT

GOVERNING VALVE

20

24

22

MHI

03MAA03AA1

13

STUD BOLT

GOVERNING VALVE

29

36

42

MHI

03MAA03AA1

14

NUT

GOVERNING VALVE

30

36

22

MHI

03MAA03AA1

15

SPHERICAL WASHER

GOVERNING VALVE

31

36

26

MHI

03MAA03AA1

16

SPHERICAL WASHER

GOVERNING VALVE

32

36

26

MHI

03MAA03AA1

17

HEX. SOCKET HEAD


BOLT

GOVERNING VALVE

38

16

22

MHI

03MAA03AA1

18

PIN

GOVERNING VALVE

39

18

MHI

03MAA03AA1

19

PIN

GOVERNING VALVE

43

18

MHI

03MAB02AA1

VALVE

REHEAT VALVE

42

MHI

03MAB02AA1

VALVE STEM

REHEAT VALVE

50

MHI

03MAB02AA1

BUSHING

REHEAT VALVE

38

MHI

03MAB02AA1

BUSHING

REHEAT VALVE

26

MHI

03MAB02AA1

BUSHING

REHEAT VALVE

38

MHI

03MAB02AA1

BUSHING

REHEAT VALVE

10

38

Main Turbine
Mitsubishi

B-9

REMARKS

Appendix B

Continued from previous page.


TABLE B-2

RECOMMENDED LISTS OF STRATEGIC SPARE PARTS (OFF SHORE)


INITIAL QUANTITY

MM-M05.01

Rev.001

SUPPLIER
NAME

EQT .

PART
ID

PARTS DESCRIPTION

SUB-ASSEMBLY/
EQT DESCRIPTION

MAN.
PARTS NO.

PER EACH
QTY.

TOTAL
PLANT

ON HAND QTY.
SPARE
PARTS 1 YR

STRATEGIC
SPARE PARTS

LEAD
TIME
(PO TO
FOB) Wk

MHI

03MAB02AA1

SHOULDER RING

REHEAT VALVE

20

26

MHI

03MAB02AA1

RETAINING RING

REHEAT VALVE

21

50

MHI

03MAB02AA1

KEY

REHEAT VALVE

28

18

MHI

03MAB02AA1

10

BONNET GASKET

REHEAT VALVE

34

18

MHI

03MAB02AA1

11

SIDE COVER GASKET

REHEAT VALVE

35

18

MHI

03MAB02AA1

12

NUT

REHEAT VALVE

36

22

MHI

03MAB02AA1

13

PIN

REHEAT VALVE

37

18

MHI

03MAB02AA1

14

STUD BOLT

REHEAT VALVE

39

24

48

12

42

MHI

03MAB02AA1

15

STUD BOLT

REHEAT VALVE

40

12

24

42

MHI

03MAB02AA1

16

CAP NUT

REHEAT VALVE

41

24

48

12

38

MHI

03MAB02AA1

17

NUT

REHEAT VALVE

42

24

48

12

38

MHI

03MAB02AA1

18

STUD BOLT

REHEAT VALVE

43

12

24

42

MHI

03MAB02AA1

19

SPHERICAL WASHER

REHEAT VALVE

44

24

48

12

26

MHI

03MAB02AA1

20

SPHERICAL WASHER

REHEAT VALVE

45

24

48

12

26

MHI

03MAB02AA1

21

SPHERICAL WASHER

REHEAT VALVE

46

24

48

12

26

MHI

03MAB02AA1

22

SPHERICAL WASHER

REHEAT VALVE

47

24

48

12

26

MHI

03MAB02AA1

23

DISC SPRING

REHEAT VALVE

55

16

26

MHI

03MAB02AA1

24

HEX. SOCKET HEAD


BOLT

REHEAT VALVE

58

12

24

18

Main Turbine
Mitsubishi

B-10

REMARKS

Appendix B

Continued from previous page.


TABLE B-2

RECOMMENDED LISTS OF STRATEGIC SPARE PARTS (OFF SHORE)


INITIAL QUANTITY

MM-M05.01

Rev.001

SUPPLIER
NAME

EQT .

PART
ID

PARTS DESCRIPTION

SUB-ASSEMBLY/
EQT DESCRIPTION

MAN.
PARTS NO.

PER EACH
QTY.

TOTAL
PLANT

ON HAND QTY.
SPARE
PARTS 1 YR

STRATEGIC
SPARE PARTS

LEAD
TIME
(PO TO
FOB) Wk

MHI

03MAB02AA1

25

SPRING

REHEAT VALVE

66

26

MHI

03MAB02AA1

26

BEARING

REHEAT VALVE

73

26

MHI

03MAB02AA1

27

PLUG

REHEAT VALVE

74

18

MHI

03MAB02AA1

28

PLUG

REHEAT VALVE

76

36

72

18

18

MHI

03MAB02AA1

29

PLUG

REHEAT VALVE

77

12

24

18

MHI

03MAB02AA1

30

HEX. SOCKET HEAD


BOLT

REHEAT VALVE

78

42

MHI

03MAB03AA1

VALVE STEM

INTERCEPTOR V/V

50

MHI

03MAB03AA1

BUSHING

INTERCEPTOR V/V

38

MHI

03MAB03AA1

BUSHING

INTERCEPTOR V/V

38

MHI

03MAB03AA1

RETAINER

INTERCEPTOR V/V

30

MHI

03MAB03AA1

HEX. SOCKET HEAD


BOLT

INTERCEPTOR V/V

38

42

MHI

03MAB03AA1

PRESSURE SEAL
RING

INTERCEPTOR V/V

42

MHI

03MAB03AA1

STUD BOLT

INTERCEPTOR V/V

17

32

42

MHI

03MAB03AA1

STUD BOLT

INTERCEPTOR V/V

18

28

112

28

42

MHI

03MAB03AA1

NUT

INTERCEPTOR V/V

19

28

112

28

42

MHI

03MAB03AA1

10

SPHERICAL WASHER

INTERCEPTOR V/V

20

28

112

28

26

MHI

03MAB03AA1

11

SPHERICAL WASHER

INTERCEPTOR V/V

21

28

112

28

26

Main Turbine
Mitsubishi

B-11

REMARKS

Appendix B

Continued from previous page.


TABLE B-2

RECOMMENDED LISTS OF STRATEGIC SPARE PARTS (OFF SHORE)


INITIAL QUANTITY

MM-M05.01

Rev.001

SUPPLIER
NAME

EQT .

PART
ID

PARTS DESCRIPTION

SUB-ASSEMBLY/
EQT DESCRIPTION

MAN.
PARTS NO.

PER EACH
QTY.

TOTAL
PLANT

ON HAND QTY.
SPARE
PARTS 1 YR

STRATEGIC
SPARE PARTS

LEAD
TIME
(PO TO
FOB) Wk

MHI

03MAB03AA1

12

SPHERICAL WASHER

INTERCEPTOR V/V

22

32

26

MHI

03MAB03AA1

13

SPHERICAL WASHER

INTERCEPTOR V/V

23

32

26

MHI

03MAB03AA1

14

LINER

INTERCEPTOR V/V

26

18

MHI

03MAB03AA1

15

SCREW

INTERCEPTOR V/V

29

18

MHI

03MAB03AA1

16

SCREW

INTERCEPTOR V/V

30

18

MHI

03MAB03AA1

17

NUT

INTERCEPTOR V/V

36

32

38

MHI

03MAB03AA1

18

MAIN VALVE
SUBASSEMBLY

INTERCEPTOR V/V

42

MHI

03MAB03AE1

101

BOLT

MAIN STEAM INLET


PIPING

32

32

42

MHI

03MAB03AE1

102

CAP NUT

MAIN STEAM INLET


PIPING

64

64

16

22

MHI

03MAB03AE1

103

SPHERICAL WASHER

MAIN STEAM INLET


PIPING

32

32

26

MHI

03MAB03AE1

104

SPHERICAL WASHER

MAIN STEAM INLET


PIPING

32

32

26

MHI

03MAB03AE1

105

WASHER

MAIN STEAM INLET


PIPING

32

32

26

MHI

03MAB03AE1

106

FLANGE GASKET

MAIN STEAM INLET


PIPING

18

MHI

03MAB03AE1

107

PLUG

MAIN STEAM INLET


PIPING

64

64

16

18

MHI

03MAB03AE1

108

PLUG

MAIN STEAM INLET


PIPING

32

32

16

MHI

03MAB03AE1

109

BOLT

HR STEAM INLET
PIPING

40

40

10

42

Main Turbine
Mitsubishi

B-12

REMARKS

Appendix B

Continued from previous page.


TABLE B-2

RECOMMENDED LISTS OF STRATEGIC SPARE PARTS (OFF SHORE)


INITIAL QUANTITY

MM-M05.01

Rev.001

SUPPLIER
NAME

EQT .

PART
ID

PARTS DESCRIPTION

SUB-ASSEMBLY/
EQT DESCRIPTION

MAN.
PARTS NO.

PER EACH
QTY.

TOTAL
PLANT

ON HAND QTY.
SPARE
PARTS 1 YR

STRATEGIC
SPARE PARTS

LEAD
TIME
(PO TO
FOB) Wk

MHI

03MAB031AE1

110

CAP NUT

HR STEAM INLET
PIPING

80

80

20

38

MHI

03MAB031AE1

111

SPHERICAL WASHER

HR STEAM INLET
PIPING

40

40

10

26

MHI

03MAB031AE1

112

SPHERICAL WASHER

HR STEAM INLET
PIPING

40

40

10

26

MHI

03MAB031AE1

113

WASHERS

HR STEAM INLET
PIPING

40

40

10

26

MHI

03MAB031AE1

114

FLANGE GASKET

HR STEAM INLET
PIPING

18

MHI

03MAB031AE1

115

PLUG

HR STEAM INLET
PIPING

80

80

20

18

MHI

03MAB031AE1

116

PLUG

HR STEAM INLET
PIPING

40

40

10

18

MHI

03LB001AA500

MHI

03LB001AA501

MHI

03LB002AA500

MHI

03LB003AA500

PACKING AND
GASKET SET FOR
NONRETURN VALVE

EXTRACTION
NON-RETURN
VALVE

26

MHI

03LB004AA500

MHI

03LBS03AA500

MHI

03LBS04AA500

MHI

03MAA02AE101
MSV ACTUATOR

EHC OIL SYSTEM

62

MHI

03MAA02AE102

Main Turbine
Mitsubishi

B-13

REMARKS

Appendix B

Continued from previous page.


TABLE B-2

RECOMMENDED LISTS OF STRATEGIC SPARE PARTS (OFF SHORE)

MM-M05.01

Rev.001

INITIAL QUANTITY

ON HAND QTY.
STRATEGIC
SPARE PARTS

LEAD
TIME
(PO TO
FOB) Wk

62

62

ICV ACTUATOR

32

TRIP SOLENOID
VALVE

32

03MAY03AA502

EMERGENCY PISTON
VALVE

62

MHI

03MAY03AA502

1/4 STOP VALVE

12

12

32

MHI

03MAY03AA502

3/8 CHECK VALVE

32

32

32

MHI

03MAY03AA502

SERVO VALVE

10

10

32

MHI

03MAY03AA502

OPC SOLENOID
VALVE

32

MHI

03MAY03AA502

O-RING (AS568-8)

16

16

SUPPLIER
NAME

EQT .

MHI

03MAA03AE101

MHI

03MAA03AE102

MHI

03MAA03AE103

MHI

03MAA03AE104

MHI

03MAB02AE101

MHI

03MAB02AE102

MHI

03MAB03AE101

MHI

03MAB03AE102

MHI

03MAB03AE103

MHI

03MAB03AE104

MHI

03MAB04AA101

MHI

03MAB04AA102

MHI

Main Turbine
Mitsubishi

PART
ID

PARTS DESCRIPTION

SUB-ASSEMBLY/
EQT DESCRIPTION

MAN.
PARTS NO.

PER EACH
QTY.

TOTAL
PLANT

GV ACTUATOR

RSV ACTUATOR

SPARE
PARTS 1 YR

B-14

REMARKS

Appendix B

Continued from previous page.


TABLE B-2

RECOMMENDED LISTS OF STRATEGIC SPARE PARTS (OFF SHORE)

MM-M05.01

Rev.001

INITIAL QUANTITY

ON HAND QTY.
STRATEGIC
SPARE PARTS

LEAD
TIME
(PO TO
FOB) Wk

32

O-RING (AS568-8)

03MAY03AA502

O-RING (AS568-12)

MHI

03MAY03AA502

FILTER ELEMENT

12

12

12

22

MHI

03MAY03AA502

BACK UP RING

12

12

12

22

MHI

03MAY03AA502

O-RING (AS568-214)

12

12

12

MHI

03MAY03AA502

O-RING (G60)

12

12

12

MHI

03MAY03AA502

O-RING (P16)

36

36

36

MHI

03MAV03AP101

OIL SEAL

18

MHI

03MAV03AP101

V-RING

18

MHI

03MAV03AP101

O-RING

18

MHI

03MAV03AP101

COUPLING RING

18

MHI

03MAV04AP101

OIL SEAL

MHI

03MAV04AP101

V-RING

18

MHI

03MAV04AP101

O-RING

18

MHI

03MAV04AP101

COUPLING RING

18

SUPPLIER
NAME

EQT .

MHI

03MAY03AA502

MHI

PART
ID

PARTS DESCRIPTION

SUB-ASSEMBLY/
EQT DESCRIPTION

MAN.
PARTS NO.

PER EACH
QTY.

TOTAL
PLANT

O-RING (AS568-12)

03MAY03AA502

RSV TEST SOLENOID


VALVE

MHI

03MAY03AA502

MHI

Main Turbine
Mitsubishi

AOP

TOP

SPARE
PARTS 1 YR

18

B-15

REMARKS

Appendix B

Continued from previous page.


TABLE B-2

RECOMMENDED LISTS OF STRATEGIC SPARE PARTS (OFF SHORE)


INITIAL QUANTITY

MHI

03MAV05AP101

OIL SEAL

MHI

03MAV05AP101

V-RING

18

MHI

03MAV05AP101

O-RING

18

MHI

03MAV05AP101

COUPLING RING

18

MHI

03MAV01BB101

OIL FILTER

03MAV07AN101

OIL SEAL RING VAPOR


EXTRACTOR

MAN.
PARTS NO.

PER EACH
QTY.

TOTAL
PLANT

SPARE
PARTS 1 YR

STRATEGIC
SPARE PARTS

18

EOP

MAIN OIL TANK

18

18

MM-M05.01

Rev.001

PARTS DESCRIPTION

SUB-ASSEMBLY/
EQT DESCRIPTION

LEAD
TIME
(PO TO
FOB) Wk

EQT .

MHI

PART
ID

ON HAND QTY.

SUPPLIER
NAME

Main Turbine
Mitsubishi

B-16

REMARKS

Appendix B

TABLE B-3

RECOMMENDED LISTS OF STRATEGIC SPARE PARTS LIST FOR ONE YEAR OPERATION (OFF SHORE)

MM-M05.01

Rev.001

INITIAL QUANTITY
SUPPLIER
NAME

PART
ID

EQT .

MHI

03MAA31AE101

RELIEF DIAPHRAGM

MHI

03MAA31AE101

MHI

PARTS DESCRIPTION

SUB-ASSEMBLY/
EQT DESCRIPTION

MAN.
PARTS NO.

PER EACH
QTY.

TOTAL
PLANT

ON HAND QTY.
SPARE
PARTS 1 YR

STRATEGIC
SPARE PARTS

LEAD
TIME
(PO TO
FOB) Wk

4 pcs

15

GASKETS FOR HP,IP


PEDESTAL

1 set

15

03MAA31AE101

GASKETS FOR LP
PEDESTAL

1 set

15

MHI

03MAA31AE101

GASKET FOR
CROSSOVER

1set

30

MHI

03MAA02AA101,
102,103,104

MSV GASKET

8 pcs

16

MHI

03MAA02AA101,
102,103,104

GV GASKET

4 pcs

16

MHI

03MAA02AA101,
102,103,104

RSV COVER GASKET

6 pcs

16

MHI

03MAB02AA101,
102,103,104

RSV SIDE COVER


GASKET

6 pcs

16

MHI

03MAB02AA101,
102,103,104

RSV SIDE COVER


GASKET

6 pcs

16

MHI

03MAB03AA101,
102,103,104

ICV GASKET

8 sets

16

MHI

03MAA31AE101

GASKET FOR PIPE


FLANGE

MAIN STEAM INLET


PIPE

2 sets

16

MHI

03MAA31AE101

GASKET FOR PIPE


FLANGE

HOT REHEAT INLET


PIPE

2 sets

16

MHI

03MAV03AP101

BEARING & PACKING

AUX. OIL PUMP

1 set

MHI

03MAV04AP101

BEARING & PACKING

TURNING OIL PUMP

1 set

MHI

03MAV05AP101

BEARING & PACKING

EMER. OIL PUMP

1 set

Main Turbine
Mitsubishi

STEAM TURBINE

MAIN VALVES

B-17

REMARKS

Appendix B

Continued from previous page.


TABLE B-3

RECOMMENDED LISTS OF STRATEGIC SPARE PARTS LIST FOR ONE YEAR OPERATION (OFF SHORE)
INITIAL QUANTITY
MAN.
PARTS NO.

LEAD
TIME
(PO TO
FOB) Wk

EQT .

MHI

03MAV01BB101

GASKET FOR MANHOLE


COVER

MAIN OIL TANK

MHI

03MAV07AN101

OIL SEAL RING FOR


VAPOR EXTRACTOR

MAIN OIL TANK


VAPOR
EXTRACTOR

1 set

MHI

03MAV01AT101,
102

FILTER CARTRIDGE

OIL FILTER

1 set

MHI

03MAV21AT201

FILTER CARTRIDGE

OIL PURIFIER

1 set

MHI

03MAV07AT101

FILTER CARTRIDGE

OIL MIST
SEPARATOR

1 set

MHI

03MAY04AT504

BACK UP FILTER
ELEMENT

EH OIL UNIT

4pcs

MHI

03MAY05AT502

POLISHING FILTER
ELEMENT

2pcs

MHI

03MAY02AT503,
504

LINE FILTER ELEMENT

4pcss

MHI

03MAY04AT501,
502

RETURN FILTER
ELEMENT

4pcs

MHI

03MAY04AT504

EARTH FILTER
ELEMENT

16pcs

PARTS DESCRIPTION

SUB-ASSEMBLY/
EQT DESCRIPTION

PER EACH
QTY.

TOTAL
PLANT

SPARE
PARTS 1 YR

STRATEGIC
SPARE PARTS

MM-M05.01

Rev.001

PART
ID

ON HAND QTY.

SUPPLIER
NAME

Main Turbine
Mitsubishi

B-18

REMARKS

Appendix C

A p p en d i x

MM-M05.01

Rev.001

C Special Tools

Main Turbine
Mitsubishi

C-1

Appendix C

TABLE C-1
Eqt. ID
*(Note 1)

Tool
ID

Special Tool Name/


Description

Name of Equipment for


which special tools
used

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

RF

BEAM FOR
LIFTING GEAR

STEAM TURBINE

3741

RF

SADDLE FOR
LIFTING GEAR

STEAM TURBINE

256

RF

CHAIN BLOCK
FOR LIFTING
GEAR

STEAM TURBINE

245

RF

CHAIN BLOCK
FOR LIFTING
GEAR

STEAM TURBINE

85

RF

SHACKLE FOR
LIFTING GEAR

STEAM TURBINE

MM-M05.01

Rev.001

PJ No.

MAIN TURBINE SPECIAL TOOL LIST

Main Turbine
Mitsubishi

Size

RS25

100

225

21

RS80

180

445

132

RS16

80

205

10

Remarks

C-2

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

RF

Tool
ID

Special Tool Name/


Description

SHACKLE FOR
LIFTING GEAR

MAIN TURBINE SPECIAL TOOL LIST

Name of Equipment for


which special tools
used

Suppliers
ID No.
(Note 2)

RF

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

Remarks

STEAM TURBINE

WIRE ROPE FOR


LIFTING GEAR

Total Qty.
Supplied
for Plant

STEAM TURBINE

Size

RS32

220

380

48

56

12710

146

44

7140

62

44

4770

42

44

4830

42

36

13330

65

36

5680

30

48

5320

62

48

5410

63

C-3

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

RF

Special Tool Name/


Description

WIRE ROPE FOR


LIFTING GEAR

Name of Equipment for


which special tools
used

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

STEAM TURBINE

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

32

2200

44

2900

21

60

3900

55

RF

GUIDE PILLAR
FOR HP ROTOR
(GEN. SIDE)

STEAM TURBINE

31

RF

10

GUIDE PILLAR
FOR HP ROTOR
(GOV. SIDE)

STEAM TURBINE

31

Remarks

MM-M05.01

Rev.001

Tool
ID

MAIN TURBINE SPECIAL TOOL LIST

Main Turbine
Mitsubishi

C-4

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

Tool
ID

Special Tool Name/


Description

MAIN TURBINE SPECIAL TOOL LIST

Name of Equipment for


which special tools
used

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

RF

11

GUIDE PILLAR
FOR LP ROTOR

STEAM TURBINE

164

RF

12

GUIDE PILLAR
FOR LP INNER
CASING

STEAM TURBINE

46

RF

13

OVERHAUL TOOL
FOR NO. 1
BEARING

STEAM TURBINE

123

MM-M05.01

Rev.001

Remarks

Main Turbine
Mitsubishi

C-5

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

Tool
ID

Special Tool Name/


Description

MAIN TURBINE SPECIAL TOOL LIST

Name of Equipment for


which special tools
used

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

RF

14

OVERHAUL TOOL
FOR NO. 2
BEARING

STEAM TURBINE

134

RF

15

OVERHAUL TOOL
FOR NO. 3
BEARING

STEAM TURBINE

223

RF

16

OVERHAUL TOOL
FOR NO. 4
BEARING

STEAM TURBINE

230

MM-M05.01

Rev.001

Remarks

Main Turbine
Mitsubishi

C-6

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

Tool
ID

Special Tool Name/


Description

MAIN TURBINE SPECIAL TOOL LIST

Name of Equipment for


which special tools
used

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

RF

17

OVERHAUL TOOL
FOR NO. 5
BEARING

STEAM TURBINE

230

RF

18

OVERHAUL TOOL
FOR NO. 6
BEARING

STEAM TURBINE

310

RF

19

MICROMETER
FOR THRUST END

STEAM TURBINE

0.1

RF

20

DIAL GAUGE &


ROD FOR ROTOR
ALIGNMENT

STEAM TURBINE

0.1

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

Remarks

C-7

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

RF

21

22

MM-M05.01

Rev.001

RF

Main Turbine
Mitsubishi

Tool
ID

Special Tool Name/


Description

OVERHAUL TOOL
FOR LP OUTER
GLAND

BOLT HEATER

Name of Equipment for


which special tools
used

STEAM TURBINE

STEAM TURBINE

MAIN TURBINE SPECIAL TOOL LIST


Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

Remarks

393

Type

26

1560

Straight

18

26

1310

Straight

26

1160

Straight

23

1490

Straight

23

1100

Straight

20

1140

Straight

18

850

Straight

18

530

Straight

26

1210

Flexible

26

1040

Flexible

C-8

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

RF

22
(cont)

Special Tool Name/


Description

BOLT HEATER

Name of Equipment for


which special tools
used

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

26

770

Flexible

24

960

Flexible

24

790

Flexible

20

950

Flexible

20

720

Flexible

17.5

770

Flexible

15

670

Flexible

15

610

Flexible

RF

23

CABLE FOR BOLT


HEATER

STEAM TURBINE

10

RF

24

DISTRIBUTION
PANEL FOR BOLT
HEATER

STEAM TURBINE

45

25

SLEEVE FOR
BOLT STRETCH
MEASURING
DEVICE

STEAM TURBINE

RF

Main Turbine
Mitsubishi

Remarks

STEAM TURBINE

MM-M05.01

Rev.001

Too
l ID

MAIN TURBINE SPECIAL TOOL LIST

26

195

0.9

31.5

200

37

210

1.3

C-9

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

RF

26

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

Tool
ID

Special Tool Name/


Description

ROD FOR BOLT


STRETCH
MEASURING
DEVICE

Name of Equipment for


which special tools
used

STEAM TURBINE

MAIN TURBINE SPECIAL TOOL LIST


Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

15.8

450

15.8

405

04

15.8

470

0.5

15.8

495

0.5

15.8

510

0.5

15.8

535

0.5

15.8

465

0.5

18.8

410

0.4

18.8

435

0.5

18.8

490

0.5

18.8

505

0.5

18.8

625

0.6

18.8

760

0.7

18.8

805

0.7

21.8

1030

1.1

21.8

1100

1.2

21.8

505

0.7

21.8

585

0.7

21.8

785

0.9

21.8

810

0.9

24.3

810

0.9

24.3

525

0.7

Remarks

0.4

C-10

Appendix C

Continued from previous page.


TABLE C-1
PJ No.

RF

26
(Cont)

Too
l ID

Special Tool Name/


Description

ROD FOR BOLT


STRETCH
MEASURING
DEVICE

Name of Equipment for


which special tools
used

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

24.3

650

0.8

24.3

860

24.3

1025

1.1

24.3

1050

1.1

24.3

1440

1.4

27.8

1095

1.7

27.8

630

1.1

27.8

905

1.5

27.8

1015

1.6

27.8

1075

1.7

27.8

1125

1.8

27.8

1185

1.8

27.8

1275

27.8

1470

2.2

27.8

1485

2.2

27.8

1525

2.3

Remarks

STEAM TURBINE

MM-M05.01

Rev.001

Eqt. ID
*(Note 1)

MAIN TURBINE SPECIAL TOOL LIST

Main Turbine
Mitsubishi

C-11

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

Tool
ID

Special Tool Name/


Description

Name of Equipment for


which special tools
used

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

RF

27

DIAL GAUGE FOR


BOLT STRETCH
MEASURING
DEVICE

RF

28

RATCHET FOR
TURNING GEAR

STEAM TURBINE

RF

29

GREASE GUN

STEAM TURBINE

RF

30

WRENCH FOR
ROTOR BALANCE
PLUG

STEAM TURBINE

MM-M05.01

Rev.001

PJ No.

MAIN TURBINE SPECIAL TOOL LIST

Main Turbine
Mitsubishi

STEAM TURBINE

1.7

Remarks

21.7

2000

10.1

21.7

1200

6.5

21.7

500

3.3

13.8

400

1.5

C-12

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

Tool
ID

Special Tool Name/


Description

MAIN TURBINE SPECIAL TOOL LIST

Name of Equipment for


which special tools
used

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

A
T

RF

31

32

MM-M05.01

Rev.001

RF

Main Turbine
Mitsubishi

SPECIAL EYE
BOLT

SINGLE ENDED
SPANNER

STEAM TURBINE

STEAM TURBINE

Weight

M12

82

0.3

M20

105

0.6

M24

140

M40

160

2.7

M36

180

3.8

M42

200

5.4

90

Remarks

0.1

95

0.1

10

110

0.1

13

135

0.1

17

165

0.1

19

180

0.1

C-13

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

RF

32
(CONT)

Special Tool
Name/ Description

SINGLE ENDED
SPANNER

Name of Equipment for


which special tools
used

STEAM TURBINE

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

22

205

0.2

24

220

0.2

27

245

0.3

30

270

0.4

32

285

0.4

36

320

0.5

41

360

0.7

46

400

50

430

1.2

55

470

1.7

65

550

2.3

70

590

3.3

75

630

Remarks

MM-M05.01

Rev.001

Tool
ID

MAIN TURBINE SPECIAL TOOL LIST

Main Turbine
Mitsubishi

C-14

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

Tool
ID

Special Tool Name/


Description

MAIN TURBINE SPECIAL TOOL LIST

Name of Equipment for


which special tools
used

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

RF

33

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

DOUBLE
HEXAGONAL
SHOCK SPANNER

STEAM TURBINE

Weight

Remarks

41

223

0.8

46

237

0.9

50

250

1.1

55

270

1.6

60

308

2.5

65

308

2.5

75

345

3.5

80

365

4.2

85

365

4.2

95

392

4.5

105

420

7.5

110

443

8.8

54

270

1.5

63

308

2.1

71

345

3.4

77

345

3.9

C-15

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

RF

34

Special Tool Name/


Description

RING SPANNER

Name of Equipment for


which special tools
used

STEAM TURBINE

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

19

166

0.2

22

187

0.2

24

231

0.3

27

231

0.5

30

265

0.4

32

265

0.4

36

292

0.7

46

365

1.7

55

441

2.7

65

508

4.2

75

584

6.1

Remarks

MM-M05.01

Rev.001

Tool
ID

MAIN TURBINE SPECIAL TOOL LIST

Main Turbine
Mitsubishi

C-16

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

35

Special Tool Name/


Description

HEXAGONAL
WRENCH KEY

Name of Equipment for


which special tools
used

STEAM TURBINE

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

63

0.1

70

0.1

80

0.1

90

0.1

100

0.1

112

10

0.1

125

12

0.2

140

14

0.3

160

17

0.4

180

19

0.6

200

22

0.8

250

27

2.1

315

32

3.1

355

36

4.0

Remarks

MM-M05.01

Rev.001

RF

Tool
ID

MAIN TURBINE SPECIAL TOOL LIST

Main Turbine
Mitsubishi

C-17

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

RF

36

37

Special Tool Name/


Description

SCREW DRIVER

SCREW DRIVER

Name of Equipment for


which special tools
used

Suppliers
ID No.
(Note 2)

Total
Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

Remarks

STEAM TURBINE

215

100

28

0.2

280

150

32

0.3

STEAM TURBINE

360

200

37

0.1

395

250

37

10

0.2

MM-M05.01

Rev.001

RF

Tool
ID

MAIN TURBINE SPECIAL TOOL LIST

Main Turbine
Mitsubishi

C-18

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

RF

RF

38

39

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

Tool
ID

Special Tool Name/


Description

EYE BOLT

DRAWING BOLT

MAIN TURBINE SPECIAL TOOL LIST

Name of Equipment for


which special tools
used

STEAM TURBINE

STEAM TURBINE

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

M10

41

59.3

0.1

M12

50

73

0.2

M16

60

87

0.3

M20

72

101

0.4

M24

90

128

0.8

M30

110

155

1.5

M36

133

186.5

2.8

M42

151

215.5

4.3

M48

170

240

M6

38

150

0.1

M8

38

200

0.1

M
10

13

51

200

0.3

M
12

13

56

200

0.3

Remarks

C-19

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

RF

RF

41

Special Tool Name/


Description

PLUG WRENCH
A TYPE

SPECIAL
WRENCH
HANDLE

Name of Equipment for


which special tools
used

STEAM TURBINE

STEAM TURBINE

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

70

17

0.2

75

19

0.1

95

26

0.6

110

32

1.1

150

41

2.4

165

46

3.2

80

50

4.5

Remarks

0.1

MM-M05.01

Rev.001

40

Tool
ID

MAIN TURBINE SPECIAL TOOL LIST

Main Turbine
Mitsubishi

C-20

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

Rev.001

RF

RF

RF

42

43

44

Tool
ID

Special Tool Name/


Description

BOX SPANNER

BOX SPANNER

MONKEY
WRENCH

MAIN TURBINE SPECIAL TOOL LIST

Name of Equipment for


which special tools
used

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

STEAM TURBINE

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

750

46

46

6.9

750

54

54

7.1

400

46

46

3.8

400

54

54

380

120

46

3.6

470

130

54

4.8

Remarks

STEAM TURBINE

STEAM TURBINE

MM-M05.01

Main Turbine
Mitsubishi

310

0.7

385

1.3

C-21

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

RF

45

Special Tool Name/


Description

JACKING BOLT

Name of Equipment for


which special tools
used

STEAM TURBINE

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

W2

360

5.9

W1.1/2

560

5.6

W1.1/2

460

4.6

M10

80

0.1

M12

300

0.3

M20

140

0.4

M24

400

1.6

M36

500

4.5

M24

300

1.2

M24

560

2.1

M24

130

0.6

M24

120

0.5

M12

140

0.2

12

M30

140

Remarks

MM-M05.01

Rev.001

Tool
ID

MAIN TURBINE SPECIAL TOOL LIST

Main Turbine
Mitsubishi

C-22

Appendix C

Continued from previous page.


TABLE C-1
Eqt. ID
*(Note 1)

PJ No.

RF

45
(Cont.)

46

Special Tool
Name/ Description

JACKING BOLT

TURN BUCKLE
FOR LP
TURBINE FLOW
GUIDE

Name of Equipment for


which special tools
used

STEAM TURBINE

Suppliers
ID No.
(Note 2)

Total Qty.
Supplied
for Plant

Purpose

Ref. Instruction /
Doc/DwgsNote # 3

Outline view &


Dimensions (Note # 4)

Weight

M12

140

0.1

M36

240

2.6

M48

220

4.5

M24

250

1.0

M16

100

0.2

M24

500

2.0

M30

400

2.4

M20

110

0.3

M24

360

1.4

M16

140

0.3

M12

180

0.2

Remarks

STEAM TURBINE

950

700

50

23.6

1740

700

50

29.6

MM-M05.01

Rev.001

RF

Tool
ID

MAIN TURBINE SPECIAL TOOL LIST

Main Turbine
Mitsubishi

C-23

Appendix D

A p p en d i x

D Coupling Alignment

MM-M05.01

Rev.001

Specific procedures for the alignment of the main turbine rotor couplings are provided in
Maintenance Manual M-05.05, Turbine Couplings and Alignment.

Main Turbine
Mitsubishi

D-1

Appendix E

A p p en d i x

MM-M05.01

Rev.001

E Applicable Vendor Drawings

Main Turbine
Mitsubishi

E-1

MM-M05.01

Rev.001

Appendix E

MPTD-3-0692

Main Turbine
Mitsubishi

FIGURE E-1

TURBINE SECTIONAL ASSEMBLY


E-2

MM-M05.01

Rev.001

Appendix E

MPTD-3-0590

Main Turbine
Mitsubishi

FIGURE E-2

LOCATION PLAN OF OVERHAUL FOR TURBINE


E-3

Appendix F

A p p en d i x

F Bolt Tightening Details


BOLT TIGHTENING DETAILS
BOLT TIGHTENING DETAILS
The figures attached provide maintenance personnel with the details necessary to proceed
with the bolt stretching required to securely tighten the horizontal joint bolting of the HP-IP,
LP1 and LP2 turbine casings.
Figure F-1 shows the section of each bolt or stud installed, Figures F-2 and F-3 show details
of the bolt heating data and torque values and Figures F-4 and F-5 show details of the
turbine casing bolting arrangement.
The drawing of each turbine casing consists of three sections A, B and C.
A

Shows the horizontal surface of the right side of the relevant turbine cylinder with the
related inner casings, blade rings, nozzle boxes, etc. clearly indicated.
The number located adjacent to the bolt holes is the mark number of the installed stud,
stud bolt, reamer (or fitting) bolt.

Shows the stud or bolt mark numbers, and the alphabetical letters in the adjacent
column indicate the relevant stud or bolt section.
Example (refer to Figure F-1).
Bolt mark no. 1 = A = Reamer (fitting) stud
Bolt mark no. 11 = E = Reamer bolt
Bolt mark no. 2 = B = Stud bolt
Provides the information such as the bolt diameter, bolt free length, nut first torque,
nut turn angle, arc length from zero angle and the amount of bolt stretch or tightening
torque. The type and size of the required bolt heater is also indicated.

MM-M05.01

Rev.001

Main Turbine
Mitsubishi

F-1

MM-M05.01

Rev.001

Appendix F

MPTD-3-0526

Main Turbine
Mitsubishi

FIGURE F-1

CYLINDER BOLTING ARRANGEMENT


F-2

MM-M05.01

Rev.001

Appendix F

MPTD-3-0527

Main Turbine
Mitsubishi

FIGURE F-2

HP-IP TURBINE CYLINDER BOLTING ARRANGEMENT


F-3

MM-M05.01

Rev.001

Appendix F

MPTD-3-0528

Main Turbine
Mitsubishi

FIGURE F-3

LP1/LP2 TURBINE CYLINDER BOLTING ARRANGEMENT


F-4

MM-M05.01

Rev.001

Appendix F

MPTD-3-0529

Main Turbine
Mitsubishi

FIGURE F-4

HP-IP TURBINE CYLINDER BOLTING ARRANGEMENT


F-5

MM-M05.01

Rev.001

Appendix F

MPTD-3-0530

Main Turbine
Mitsubishi

FIGURE F-5

LP1/LP2 TURBINE CYLINDER BOLTING ARRANGEMENT


F-6

Appendix G

Top and Bottom Blade Radial


G Cl e a r a n c e C h e c k P r o c e d u r e

A p p en d i x

TURBINE BLADE RADIAL CLEARANCES


HP-IP Turbine
The measurement of the turbine blade radial clearances at the right side and the left side of
the casings can be made using feeler gauges or a taper gauge, when the upper half of the
stationary blade rings have been removed.
However, as it is on some occasion necessary to measure the radial clearances at the top
and at the bottom of the cylinder the following procedure is recommended:
1

Place a length of 1.5 mm lead wire around the shroud of the bottom center blade in
the lower half stationary blade rings, and around the shroud of the center blade in the
upper half stationary blade rings, gently shaping the lead wire to the contour of the
shroud and the seal strips.

Place a similar length of lead wire around the top center and bottom center blades on
each row of rotating blade shrouds, again gently shaping the lead wire to the contour
of the blade shroud surface.

Note
Selection of lead wire should be such that the diameter of the wire is
higher than the clearance to be measured.
3

Secure the lead wires in their positions using tape or any other suitable method.

When the lead wires have been securely positioned, lift the rotor according to the
procedure described in Appendix H and lower it into the turbine cylinder.

Stop lowering the rotor before the journals seat in the bearings, and set the rotor in the
K position. K position is indicated in the turbine clearance drawings provided in
Chapter 5.

Note

MM-M05.01

Rev.001

Do not rotate the rotor.


6

Clean all horizontal joint surfaces using a smooth file to remove any burrs, then using
suitable lifting equipment lower the upper half stationary blade rings into position.

Install and tighten the horizontal joint bolts, then measure the horizontal joint gap with
feeler gauges and confirm that the joints are completely closed.

Loosen and remove the horizontal joint bolts.

Main Turbine
Mitsubishi

G-1

Appendix G

Using the jacking bolts provided raise each upper half stationary blade ring by about 5
mm.

10

Attach the lifting equipment to each upper half stationary blade ring, remove the blade
rings in sequence, then using the rotor lifting beam and following the prescribed
procedure raise and remove the rotor.

11

Carefully remove the lead wires from both the stationary and the rotating blades
taking care not to misplace the wires on removal.

12

To prevent the loss of, or damage to, the lead wires, they should be affixed to a piece
of cardboard in the sequence in which they were removed. Each should be clearly
marked with the location from which they were removed, stating cylinder identification,
top or bottom, row and whether stationary or rotating blade.

13

When all lead wires have been removed, measure the indentations in the lead wire
using an appropriate wire gauge, micrometer, or similar measuring device, and record
the clearances for inclusion in the final blade clearance charts.

LP1/LP2 Turbine

MM-M05.01

Rev.001

Following a similar procedure, the top and bottom radial seal clearances in the LP1 and LP2
turbines can be measured by fixing suitable size lead wires and lifting the inner casing and
LP blade rings.

Main Turbine
Mitsubishi

G-2

Appendix H

A p p en d i x

H Lifting Methods
The attached drawing shows the recommended lifting method for the turbine rotor and the
casings.
When lifting the heavy turbine parts, it is of utmost importance that the lifted object level
shall be maintained and without rotational or swaying movement during the period of the
lift.
It is therefore necessary to ascertain the center of gravity of the object to be lifted at the
commencement of erection work and to determine the relative axial position between the
object and the lifting gear elements for convenience in application thereafter.
This can be achieved at the commencement of the turbine installation on site, by marking
on the lifting beam the position of the beam clamps required to obtain a level lift of each
casing or rotor.
Lifting slings shall be adjusted to the correct length by the turn buckle. Insert a suitable
material between the sling and the contact surface of the object to be lifted, for protection.
When removing the turbine casing covers, separate the horizontal flanges clearly using
the jacking bolts provided before application of lifting gear and crane. For the LP1/LP2
turbine inner cylinder, the covers shall be lifted (or installed) vertically through "casing
guide bolts" which are round bar rods installed temporarily at the corners of the inner
casing horizontal flange.
When removing (or installing) the turbine rotor, out of or into the casing base, the "rotor
guide pillars" provided are to be installed at the outer casing horizontal joint, one at each
end of the rotor, to prevent rotor swing.
Frequent inspection of all lifting equipment is essential.

MM-M05.01

Rev.001

Avoid the use of slings in which there is a kink, dent, or some other harmful flaw.

Main Turbine
Mitsubishi

H-1

MM-M05.01

Rev.001

Appendix H

MPTD-3-0693

Main Turbine
Mitsubishi

FIGURE H-1

HP-IP AND LP TURBINES LIFTING GEAR ASSEMBLY


H-2

Appendix I

A p p en d i x

I
1

Tightening Large Bolts and


Studs with Heating Elements

TIGHTENING PROCEDURE LARGE BOLTS AND STUDS WITH HEATING ELEMENTS


1

Determine the required stretch.

Lubricate threads and face of the bolt and nut with anti-seize compound.

CAUTION
Excessive grease may enter the bolt heating hole and carbonize during
heating, creating the possibility of an electrical short.

Note
Where cap nuts are used, excessive lubricant may squeeze through the thread,
run over the top of the bolt and enter the heating hole. It is recommended that
the nut be run down through the lubricated bolt and the excessive lubricant
removed from the cap nut and the top of the bolt.

Note

MM-M05.01

Rev.001

A blackened heating element is an indication that an excessive lubricant was


used. Any blackened element should be heated before insertion into the bolt
hole until the lubricant is burnt. Burned lubricant should be brushed from the
element when it has cooled.

Run the nut onto the bolt or stud threads to ensure free fitting.

Clean the bottom of the bolt heating hole with compressed air followed by a swab, the
swab end being smeared with a little clean grease.

Measure the stud or bolt length, with the nut loose using the adapter and the extension
rod.

Tighten all nuts with a 90 kg pull on a wrench handle length of 12 centimeter per one
centimeter of bolt diameter.
Repeat until all the nuts are pulled up uniformly over the entire joint.

Main Turbine
Mitsubishi

I-1

Appendix I

Example:
Bolt Diameter:

2.5 inch

Wrench handle length:

120 cm

Required torque:

6658 kg-cm (90 x 12 x 2.5 x 2.54)

Required force:

57 kg (6658/120)

Obtain the required nut turn from the chart, in Appendix F, and chalk mark reference
points on the nuts and adjacent flange. For a through bolt, the holding nut on the
opposite end and the flange should also be marked to observe if the bolt turns during
tightening.

Heat the stud or bolt and turn the nuts until the reference points coincide.

After the stud or bolt has cooled to the same temperature as before heating, clean
bottom of the hole and measure to see if the required stretch, within tolerance of 10%
has been obtained.

Example of Dimensions for Stretching Large Studs


Stud material

10705BU

Diameter of stud (8 threads per 25.4 mm)

3 inches (76.2 mm)

Free Length (Thickness of flange from joint face to spot


face 240 mm (including packing thickness) plus washer
thickness, plus stud diameter 76.2 mm)

330 mm

Stretch to be obtained by heating (330 x 0.0015)

0.5

Micrometer measurement, nut loose

19.5 mm

Stretch to be obtained by heating

0.5 mm

Amount of turn on nut (From Table in Appendix F)

104 degrees

Micrometer measurement, after cooling

19 mm

Stretch (19.5 19)

0.5 mm

MM-M05.01

Rev.001

For Bolt Heating details refer to Appendix F.

Main Turbine
Mitsubishi

I-2

Appendix I

ALLOY STEEL BOLT TIGHTENING


Alloy steel bolts and studs in the high pressure and/or high temperature flanges, should be
tightened sufficiently to produce a definite amount of stretch as outlined in these
instructions.

Amount of Stretch
The amount of stretch for alloy steel bolts or studs should be as shown in the following table.
Bolt Material

Required Initial Stress


(kg/mm2)

Amount of Stretch per mm of Bolt


Free Length (mm)

28

0.0013

32

0.0015

42

0.00195

JIS-SCM435
Equivalent material
SAE 4135 or AISI 4137
W-10705BU
Equivalent material
AISI 616 Type 22
W-15106FD
Equivalent material
AISI 690,
Refractaloy 26, M8B

The free length of stud is the thickness of the flange from joint face to spot facing, plus one
stud diameter plus washer thickness, if washers are used. The free length of a bolt
extending through both flanges is the thickness of both flanges between spot facings, plus
one bolt diameter, plus thickness of both washers, if washers are used.

Lubrication
The threads of bolts and studs and the bearing faces of nuts should be well lubricated with a
good anti-seize compound to reduce friction and to avoid thread seizure at high
temperature service. We recommend a compound of molybdenum disulphide.

Stretching
The larger size bolts and studs are provided with holes in the center for stretching by means
of electric heating elements. Never use gas flame directly on the bolt or stud because of
possible damage to the material.

MM-M05.01

Rev.001

The smaller bolts and studs must be stretched by wrenching. It is preferable to tighten these
with a steady pull by using an extension wrench.
Tighten all nuts with a 90 kg pull on a wrench handle length of 12 cm for each centimeter of
bolt diameter. Repeat until all the nuts are pulled up uniformly over the entire joint. Then
obtain the required nut turn from the chart provided in Appendix F, and chalk mark
reference points on the nuts and adjacent flange. Turn the nuts until the reference points
coincide.

Main Turbine
Mitsubishi

I-3

Appendix I

The above procedure is expected to give a total stretch which corresponds to the required
initial stress. The permissible tolerance on the measured stretch is 10%.

Measuring Stretch
The only positive way to determine the stretch of a bolt or a stud is by micrometer
measurement. Bolts and studs 50 mm diameter and above have a center hole into which a
rod, adapter and depth micrometer can be inserted as per Figure I-1.
The stretch of studs without holes can usually be measured by means of special adapters,
slipped over the nut and a depth micrometer.
The stretch of through bolts with standard hex nuts but without holes can be measured over
the bolt ends using an ordinary outside micrometer.

Bolts and Studs Impossible to Measure


Where it is not possible to measure the stretch, apply a force as per the table in Appendix F,
at the end of the wrench. This method, which is not very accurate because of friction
variations, is calculated to produce approximately the required initial stress for alloy steel
bolts. The threads must be clean and well lubricated.

ELECTRIC BOLT HEATER


The purpose of the electric bolt heater is to elongate bolts by heating so that they may be
tightened to the required amount without resorting to heavy wrenching or hammering.
The heater is of the insertion type consisting of a heating element in a stainless steel
sheath.

Note
With ordinary care it should have a long life. Even if the heater is bent, the
usefulness of the heater is not impaired as long as actual contact does not
occur between the heating element and the sheath.

The heater may be used on either alternating or direct current circuits, with the usual
protection of fuses or circuit breakers, and with wiring adequate to carry the required current.
However, when used in a direct current circuit, the connector when provided should not be
used as an interrupting device. An additional interrupting device should be provided.

MM-M05.01

Rev.001

It is desirable, but not imperative, that neither side of the circuit be grounded. Absence of a
ground would reduce the likelihood of a short circuit on a heater. It is recommended that
heaters be used until they actually fail in service.
However, when being used, if the required bolt elongation is not obtained in seven minutes
per inch of bolt diameter the cause should be investigated to avoid unnecessary burning out
of the heater.

Main Turbine
Mitsubishi

I-4

Appendix I

No attempt should be made to protect any part of the heater surface by wrapping it with
asbestos or other insulating material since this would cause hot spots and would certainly
result in burning out of the heating coil.
The heater should never be handled with the current on, and care should be exercised in
handling it while hot to avoid burns.

MM-M05.01

Rev.001

The lead wires, while flexible, are heavy and rigid enough to use in handling the heater and
securing it in place when necessary to use the heater in a upside down position.

Main Turbine
Mitsubishi

I-5

Appendix I

TABLE I-1

DETAILS OF BOLTS AND BOLT HEATERS

Capacity
(kW)

Voltage (V)

Hole (mm)

Remarks

4.5

400

26

1050

28

STRAIGHT

5.5

400

23

1450

25

STRAIGHT

4.0

400

23

1100

25

STRAIGHT

4.5

400

20

1350

22

STRAIGHT

2.5

400

20

800

22

STRAIGHT

1.6

400

20

600

22

STRAIGHT

4.5

400

19

1350

20

STRAIGHT

3.5

400

18

1150

19

STRAIGHT

2.2

400

18

800

19

STRAIGHT

10

1.7

400

18

650

19

STRAIGHT

11

1.4

400

18

550

19

STRAIGHT

12

1.4

400

15.3

650

16

STRAIGHT

13

1.1

400

15.3

550

16

STRAIGHT

14

1.0

400

15.3

480

16

STRAIGHT

15

2.7

400

20

950

22

FLEXIBLE

16

1.5

400

17.5

700

19

FLEXIBLE

MM-M05.01

Rev.001

Marks

Main Turbine
Mitsubishi

I-6

Appendix I
MICROMETER

MEASUREMENT
AFTER HEATING
MEASURING
ROD

MEASUREMENT
BEFORE HEATING

Rev.001

MEASURING
SLEEVE

MM-M05.01

MGL-4-4959

FIGURE I-1
Main Turbine
Mitsubishi

BOLT STRETCH MEASUREMENT

I-7

You might also like