Professional Documents
Culture Documents
01-MM51
Main Turbine
MECHANICAL MAINTENANCE MANUAL
PT PAITON ENERGY
PAITON EXPANSION PROJECT
Note
This mechanical maintenance manual is intended to provide the Paiton Expansion Project
mechanical maintenance personnel with the basic understanding required to perform preventive,
routine, corrective and overhaul maintenance activities on the subject equipment.
No part of this document may be reproduced for use by parties other than Mitsubishi Heavy
Industries, Ltd. and Paiton Expansion Project.
Main Turbine
Maintenance
Contents
Safety
General
Specifications
Preventive Maintenance
Corrective Maintenance
Recommended Lubrication
Appendixes
Contents
Contents
Revision Record i
Important Informationii
Warranty v
Limitation of Liabilityvii
Copyrightix
Personnel to whom the Manual is Directed x
Contact Addressxi
Abbreviations xii
List of Vendor Manuals xiii
Arrangement of the System Maintenance Manualxiv
Chapter1
Safety ____________________________
1.1
1.2
1.2.2
Symbol 1-4
1.2.3
1.2.4
1.3
1.4
Safety Measures
1-10
1.4.1
1.4.2
MM-M05.01
Main Turbine
Mitsubishi
Contents
Chapter1
1.5
1.5.3
Earthquake 1-22
1.5.4
1.6
Chapter2
General ___________________________
2.1
Purpose 2-1
2.2
References 2-1
2.3
2.4
Components 2-8
2.4.1
2.4.2
Rotors 2-12
2.4.3
Blading 2-16
2.4.4
2.4.5
2.4.6
2.4.7
2.4.8
2.4.9
Specifications _____________________
MM-M05.01
Rev.001
Chapter3
Main Turbine
Mitsubishi
Contents
Chapter4
4.1
Prerequisites 4-1
4.2
4.3
4.1.1
Scheduling 4-1
4.1.2
4.1.3
4.1.4
4.1.5
Preparation 4-4
4.2.2
Preparation 4-13
4.3.2
5.1
5.2
5.3
Chapter6
6.1
Prerequisites 6-1
6.2
Preparation 6-2
6.3
Troubleshooting 6-2
Chapter7
MM-M05.01
Rev.001
Chapter5
Main Turbine
Mitsubishi
Contents
Appendixes
Torque Chart A-1
Appendix B
Appendix C
Appendix D
Appendix E
Appendix F
Appendix G
Appendix H
Appendix I
MM-M05.01
Rev.001
Appendix A
Main Turbine
Mitsubishi
Contents
Figure1-1
Figure 1-2
Figure 2-1
Figure 2-2
Figure 2-3
Figure 2-4
Figure 2-5
Figure 2-6
Figure 2-7
Figure 2-8
Figure 2-9
Figure 2-10
Figure 2-11
Figure 2-12
Figure 2-13
Figure 2-14
Figure 2-15
Figure 2-16
Figure 2-17
Figure 2-18
Figure 2-19
Figure 2-20
Figure 2-21
Figure 2-22
Figure 2-23
Figure 2-24
Figure 2-25
Figure 2-26
Rev.001
Figure 2-27
Figure 2-28
MM-M05.01
List Of Figures
Figure 2-29
Main Turbine
Mitsubishi
Contents
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Figure 2-30
Figure 2-31
Figure 2-32
Figure 2-33
Figure 2-34
Figure 2-35
Figure 2-36
Figure 2-37
Figure 2-38
Figure 2-39
Figure 5-1
Figure 5-2
Figure 5-3
Figure 5-4
Figure 5-5
Figure 5-6
Figure 5-7
Figure 5-8
Figure 5-9
Figure 5-10
Figure 5-11
Figure 5-12
Figure 5-13
Figure 5-14
Figure 5-15
Figure 5-16
Figure 5-17
Figure 5-18
Contents
Figure 5-20
Figure 5-21
Figure 5-22
Figure 5-23
Figure 5-24
Figure 5-25
Figure 5-26
Figure E-1
Figure E-2
Figure F-1
Figure F-2
Figure F-3
Figure F-4
Figure F-5
Figure H-1
Figure I-1
MM-M05.01
Rev.001
Figure 5-19
Main Turbine
Mitsubishi
Contents
List of Tables
Main Risk Assessment Standard as per MIL STD822 1-8
Table 3-1
Table 4-1
Table 4-2
Table 4-3
Table 6-1
Table A-1
Table A-2
Table B-1
Table B-2
Table B-3
Table C-1
Table I-1
MM-M05.01
Rev.001
Table 1-1
Main Turbine
Mitsubishi
Revision Record
Page Number
General
Description of Revision
Revision record added and all
Revision Issue
Date
Date Revised
Pages
Inserted
2012/03/26
2012/03/26
2012/03/26
2012/03/26
2012/03/26
2012/03/26
Page 2-52
Page 3-1
Page 4-6
Page 4-10
MM-M05.01
Rev.001
remarks revised.
Main Turbine
Mitsubishi
Important Information
Purpose of the Plant Usage
This plant is designed to generate electric power of 815 MW by the steam turbine
generator.
The plant is only used for the electric power generation purpose that supports stable
and reliable electric power supply to the power grid and supplying steam for auxiliary
equipment in the power station.
General
1.
To satisfy the purpose mentioned above the following points must be strictly
observed,
a)
b)
The operators and maintainers must read and understand these manuals
before starting the operation, maintenance or inspection.
It is often experienced that serious damage to the equipment or personnel
have occurred by the unexpected action of operators or maintainers who
do not fully understand the equipment.
c)
MM-M05.01
Rev.001
3.
Disposal from the power station must be treated to satisfy the local regulations.
4.
Main Turbine
Mitsubishi
ii
Use or copying of the whole or part of any information provided by MHI for
any purpose other than operation and maintenance of this plant without
written consent is strictly prohibited.
The operator and maintainer must have knowledge about the equipment to
maintain good operating condition and to avoid danger when using the
equipment and systems.
2.
3.
4.
The Customer must train the operators and maintainers to act positively and
to prevent the occurrence of an accident by using their knowledge of the
power plant.
5.
The Customer must make the operators and maintainers understand that the
most important purpose of safety control is to protect all personnel from
accidents and also to maintain operation of the plant without troubles.
6.
7.
b)
c)
MHI can not forecast all possible dangers existing in the plant such as danger
due to human error and/or dangers caused by the operating environment.
As this manual and the alert label cannot cover all of the dangers, the
operators and maintainers have to pay their full attention to all general safety
notices.
Rev.001
MM-M05.01
a)
Main Turbine
Mitsubishi
iii
8.
MHI can not be responsible for damages and injury caused by neglecting the
notices in this manual, and other necessary general notices.
2.
3.
4.
Some figures in this manual include internal parts of the equipment which
may not be obvious, when looking at the completed equipment drawing.
5.
6.
This manual is intended for the use by the operators and maintainers and it
must be accessible to them at all times.
7.
If the Customer needs more detailed information, please contact MHI local
office or MHIs official agent.
MM-M05.01
Rev.001
1.
Main Turbine
Mitsubishi
iv
Warranty
The provisions set forth in this section are in addition to all liability and warranty
disclaimers and limitations set forth in the Contract, whether arising under law
or from course of performance, course of dealing, or usage of trade.
For the detailed terms and conditions of the warranty concerning the Works
and Project, refer to the Contract.
In addition to the foregoing, the Contract Warranties will NOT cover any of the
following Accidents and Damages:
Accidents and Damages caused by any deviation from the Rules and
Requirements;
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Accidents and Damages occurring after the term of the warranty has expired;
Accidents and Damages due to handling, storage and/ or use of the Plant
under severe conditions or in an environment that does not meet the design
specification conditions.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
vi
Limitation of Liability
General
The contents of this manual are subject to change without prior notice and
without any obligation or liability to MHI.
Use of the Plant must be limited to the use specified by MHI, including without
limitation, use of the Plant in accordance with the Contract, this manual, all
Safety Manuals, all applicable laws and regulations, and any other instructions,
if any, provided by MHI. The Plant components, parts, systems and other
equipment (collectively, Equipment) must be appropriately disposed of in
accordance with the Contract, this manual, all Safety Manuals, all applicable
laws and regulations, and any other instructions, if any, provided by MHI.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
The Customers personnel must read, understand and abide by all documents
provided by MHI, including without limitation, the operation and maintenance
manuals, safety manuals, and instruction manuals (collectively, Safety
Manuals) and must have received all required and/or necessary safety
training prior to the start of their work. Persons who have not received such
safety training are not permitted to work on the installed Plant. This initial
training, however, is merely the minimum requirements prior to allowing any
personnel to work on the installed Plant. The Customer must, on a continual
and regular schedule, give up-to-date training to its personnel on safety
requirements, provide testing or other methods to confirm their understanding
of the safety training, and confirm that they have the physical and mental
capability to perform their respective roles. The Customers obligation for
safety training and personnel supervision is an ongoing obligation and must be
continuously performed and kept current throughout the operation of the Plant.
Accidents, partial or total failure of the Plant, damage to personnel or property,
loss, injuries, and other liability (collectively, Liability) caused by inadequate
safety training or the Customers personnels failure to abide by the documents
provided by MHI are expressly excluded from the coverage of any warranty
provided by MHI and are the sole and exclusive responsibility of the Customer.
vii
MHI will NOT be liable for any Liability caused by modification or changes
made in Plant-related documents (including any Safety Manual) by anyone
other than MHI.
MHI will NOT be liable for any Liability resulting from any abuse, misuse,
misapplication of the Equipment supplied by MHI.
MHI will NOT be liable for any Liability caused by an act by the Customer in
violation of the Contract, this manual, any applicable law or regulation, or any
Safety Manual or any other instruction provided by MHI, including without
limitation, a change of the installation environment or the removal and
installation of any Equipment in a location different to that originally selected by
MHI.
MHI will NOT be liable for any Liability caused by a defect, imperfection, or fault,
in material or Equipment that was used during a repair, even when such repair
was performed by or under an instruction given by MHI.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
viii
Copyright
COPYRIGHT 2009, MITSUBISHI HEAVY INDUSTRIES, LTD. ALL RIGHTS
RESERVED. ANY REPRODUCTION IS EXPRESSLY PROHIBITED.
All of the content contained in this manual is protected by Japanese,
International and/or United States copyright laws.
All copyright, trade secrets, and other proprietary and intellectual property
rights in the documents provided by Mitsubishi Heavy Industries, Ltd.(MHI)
(including safety-and-instruction manuals) are at all times owned and reserved
by MHI. Subject to your compliance with the restrictions set forth below, MHI
grants to you a limited, non-exclusive license in the copyright for the sole
purpose of allowing you to use, operate, maintain and inspect the Plant.
Except as specifically set forth above, no right, title or license to the documents
provided by MHI, whether arising from contract, implication, estoppel or
otherwise, is being granted or otherwise transferred.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
ix
Operator
Operators following the instructions of their supervisor or the Shift Charge Engineer
are permitted to handle materials to be used in the operation of the plant.
Operators are allowed to turn on the power supply, startup equipment, open up or
remove covers or panels on receipt of an instruction or authorization from their
superior.
Operators are permitted access to emergency stop devices following instructions
given by their superior when dangerous or hazardous situations are recognized.
Maintainer
MM-M05.01
Rev.001
Maintainers are permitted to perform maintenance on the plant. They will also
perform troubleshooting routine and periodical inspections of the installed
equipment. The maintainer will also work under the supervision of MHIs
supervisors during on-the-job training and annual maintenance and overhaul work if
MHIs supervisors are requested to witness periodical inspections, etc.
Maintainers MUST have attended the training programme initially provided by MHI
and subsequently by the Customer, and they must have obtained the necessary
knowledge and maintenance skills to understand the characteristics of their tasks
before actually starting their work.
Main Turbine
Mitsubishi
Contact Address
For any question or any clarification required, please do not hesitate to contact MHI
through the following address (es).
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
xi
Abbreviations
Abb.
Expanded Form
Abb.
Expanded Form
CCCW
MOP
DTI
MOST
Gen End
Generator End
MOT
Gov End
Governor End
MSDS
HP
High Pressure
OJT
On Job Training
HP-IP
P&ID
(HIP)
Pressure
I&C
PPE
IP
Intermediate Pressure
PTW
Permit to Work
LP
Low Pressure
MM-M05.01
Rev.001
Diagram
Main Turbine
Mitsubishi
xii
MM-M05.01
Rev.001
NIL
Main Turbine
Mitsubishi
xiii
Chapter 2
Describes the construction, purpose, and function of the Main Turbine and the
associated parts.
Chapter 3
Describes the Main Turbine parts, using the relevant Data Sheets.
Chapter 4
Describes the Preventive, Routine, and Outage Maintenance.
Chapter 5
Describes the disassembly and reassembly procedures, necessary to obtain access
to internal parts for inspection and repair during Main Turbine overhaul.
Chapter 6
Describes the corrective maintenance procedures to be followed to investigate,
identify and remedy defects occurring during operation.
MM-M05.01
Rev.001
Chapter 7
Includes Torque Chart, Spare Parts, Special Tools and Vendor Drawings/Documents
Main Turbine
Mitsubishi
xiv
Chapter 1
Safety
C h a p t er
1 S af et y
1.1
MM-M05.01
Rev.001
All operators and maintainers must be aware of the danger and keep
themselves safe, following the recommendations written in this manual.
Main Turbine
Mitsubishi
1-1
Chapter 1
1.2
Safety
Warnings Description
Safety of personnel working in the power plant is the most important matter and
all kinds of consideration to avoid dangerous conditions are studied and applied
to the design of the power plant. However, certain risks are unavoidable due to
the nature of the plant.
This manual classifies the severity and hazard level of such risks by two
categories, DANGER and CAUTIONS. Read and understand the
indications thoroughly before operation or maintenance of the plant.
The contents of wordings, DANGER and CAUTION are described as follows;
Kinds
Meaning of Warnings
DANGER indicates an imminently hazardous situation
during use of the Main Turbine, which, if not avoided,
could result in death or serious injury, or serious
damage to the property or environment.
CAUTION indicates a potentially hazardous situation
CAUTION
This manual also uses the following indicators in addition to the hazard level
indications described so far.
Kinds
Meaning of Warnings
IMPORTANT describes the particular information or
items that personnel must know during operation and
IMPORTANT
MM-M05.01
Rev.001
Notice
Main Turbine
Mitsubishi
1-2
Chapter 1
Safety
Minor Injury
This term describes injuries, which do not require hospitalization or
prolonged attention at a hospital (injuries other than the serious
injuries described above).
MM-M05.01
Rev.001
This term describes damage, which does not require any suspension
of productive activity due to restoration of the damaged property.
Main Turbine
Mitsubishi
1-3
Chapter 1
Safety
1.2.2 Symbol
In this manual, the following symbols are added for easy understanding
of the contents of warnings and are found next to DANGER,
CAUTION and indications.
These symbols are in compliance with ISO 3684.
Symbol
Description
This symbol indicates the possible presence of high voltage, and
warns of a hazard which may result in system shock, burn or
death by electric shock if safety precautions are neglected or the
system is handled incorrectly.
This symbol indicates a movable section that is inside a safety
cover or is exposed.
Movable parts may inflict laceration or bone fracture to body parts
such as a hand by pinching the hand and/or clothing.
This symbol indicates the presence of parts the surface of which
could be hot, and may cause a burn if handled incorrectly.
This symbol indicates that care should be taken where you place
your feet when moving around the area.
Risk of injury by tripping is present near this symbol due to
factors such as a location with an unstable surface, or
obstructions such as scaffolding, temporary pipe lines, or other
protrusions.
This symbol indicates the possible presence of gas(es) harmful or
asphyxiant to personnel.
Be sure to ventilate fully before work commences.
This symbol indicates caution against the handling of a heavy
object or working in an abnormal position.
Do not work in an abnormal posture which may damage your back
or waist.
This symbol indicates prohibited items or actions during the
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
1-4
Chapter 1
1.2.2
Safety
Symbols (Continued )
Symbol
Description
This symbol indicates that personnel must not touch since the
surface is hot.
Do NOT enter any area where this symbol is displayed.
IMPORTANT
Personnel are requested to confirm the location of, and to read, and
thoroughly understand the contents of all hazard warning labels
applied to the Main Turbine. If any of the hazard warning labels peel
Rev.001
MM-M05.01
Main Turbine
Mitsubishi
1-5
Chapter 1
WARNING
Safety
DO NOT COME
NEAR TO SHAFT
EXPOSED ZONE
WHEN IN
OPERATION
PINCH POINT
STEEP
DROP
DO NOT
ENTER
DO NOT
TOUCH
DO NOT
TOUCH
MM-M05.01
Rev.001
TB0001_A
FIGURE 1-1
Main Turbine
Mitsubishi
1-6
Chapter 1
Safety
IMPORTANT
Only trained maintainers and operators are allowed to enter the
maintenance work area. Entry to the area by personnel untrained
could cause not only injury but also serious damage to the Main
MM-M05.01
Rev.001
Turbine.
Main Turbine
Mitsubishi
1-7
Chapter 1
1.3
Safety
Category
Safety
Catastrophic
- Death
II
Critical
- Serious Injury
III
Marginal
- Minor Injury
(with
hospitalization)
VI
Negligible
- Minor Injury
(without
hospitalization)
Definition
Description
Category
Detailed
(A)
Frequent
Repeating occurrence
1 time / 1 or 2 months
(B)
Probable
1 time / 1 year
(C)
Occasional
Could occur
1 time / 5 years
(D)
Remote
1 time / 10 years
(E)
Improbable
Practically Impossible
TABLE 1-1
Hazard
Categories
Frequency
of Occurrence
Rev.001
Environment
- Harmful gas or oil leakage
- High pressure and
temperature material leakage
such as steam, water, air and
gas, oil etc.
- Low oxygen
TABLE 1-1
MM-M05.01
Health
II
III
VI
Catastrophic
Critical
Marginal
Negligible
(A)
Frequent
13
(B)
Probable
16
(C)
Occasional
11
18
(D)
Remote
10
14
19
(E)
Improbable
12
15
17
20
Main Turbine
Mitsubishi
1-8
Chapter 1
10
5
3
2
10
5
3
2
10
5
3
2
10
5
3
2
7
4
3
4
3 9
2 8
1 7
7
4
3
Safety
7
4
3
7
4
3
4
3
STAIR WAY
2
3
5
10
3
7
8
3
4
7
STAIR WAY
2
3
5
10
2
3
5
10
2
3
5
10
3
4
7
3
4
7
1 7
2 8
3 9
4
3
4
7
NOTES
WARNING LABELS SHOUD BE IN ARABIC.
GEN. SIDE
MM-M05.01
Rev.001
YELLOW
AVOID INJURY
WATCH YOUR STEP
MPTD-3-0314
YELLOW
FALL
WATCH YOUR STEP
YELLOW
RISK OF A ROTATING
A HAND
YELLOW
RISK OF A GEAR
PINCHING A HAND
GOV. SIDE
(*1)
YELLOW
RISK OF A CHAIN
PINCHING A HAND
YELLOW
PINCH POINT
KEEP HANDS AWAY
YELLOW
YELLOW
DO NOT TOUCH
HOT SURFACE
YELLOW
YELLOW
DISCONNECT
AUTOMATIC START.
ELECTRICAL POWER
KEEP HANDS CLEAR.
BEFORE SERVICING
RED
DO NOT SMOKE
IN THIS AREA.
10
RED
OPERATING PERIOD
FIGURE 1-2
Main Turbine
Mitsubishi
YELLOW
1-9
Chapter 1
1.4
Safety
Safety Measures
1.4.1 Work Permit System (Lockout/ Tagout)
Work permit system is applied when equipment is shutdown for
maintenance work, to complete the maintenance work under a safe
condition. The outline of the work permit system is as follows:
(2)
The Shift Charge Engineer passes the work permit form to the
operator to study and decide the isolation method from the line in
operation on the mechanical and electrical view point and then
report to the Shift Charge Engineer with the comments on the
hazard conditions for the work.
(3)
(4)
The operators will open the breaker and set the valves to the
specified condition, they will also drain and vent the equipment to
be worked on, and the breaker and the valves are to be locked.
The operators return the work permit to the Shift Charge
Engineer.
(5)
The Shift Charge Engineer checks the isolation and will issue the
signed work permit to the Maintenance Engineer, or his
representative.
(6)
(7)
(8)
The Shift Charge Engineer will then send operators to release the
locks and return to the original situation.
(9)
The operators check the situation and report that the system is
now back to the normal condition when signing off the work
permit.
Rev.001
(10) The Shift Charge Engineer makes sure that the work under the
permit is completed and files details in the log book.
MM-M05.01
(1)
The work permit system is to clarify responsibility for the works on each
step and to ensure that the work is performed safely.
Main Turbine
Mitsubishi
1-10
Chapter 1
Safety
Make sure that the breaker for the motor is opened when
you are required to remove the cover.
1.4.2.2
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
1-11
Chapter 1
1.4.2.3
Safety
CAUTION
Suitable Personal Protective clothing is always available
and should always be worn, including gloves to avoid
direct contact to hot spots in the plant.
All exhaust pipes of the safety valves and the exhaust pipe
of the boiler flush pipe are not insulated.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
1-12
Chapter 1
1.4.2.4
Safety
Be well aware of the steam. The steam could leak from the
water system containing water at 100C or higher even if it is
a low pressure type water system.
If not avoided, the steam or vapor can enter the inside of your
working wear through the small gap between the body and
the clothing.
MM-M05.01
Rev.001
CAUTION
Main Turbine
Mitsubishi
Oil leaks make the area slippery and people are advised to
move around these areas carefully.
1-13
Chapter 1
1.4.2.6
Safety
IMPORTANT
Precaution against chemicals:
Disposal:
Emergency response:
1.4.2.7
IMPORTANT
Storage containers must be clearly marked to indicate the
content.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
1-14
Chapter 1
1.4.2.7
Safety
IMPORTANT
Emergency response:
1.4.2.8
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
1-15
Chapter 1
1.4.2.9
Safety
CAUTION
CAUTION
MM-M05.01
Rev.001
CAUTION
Main Turbine
Mitsubishi
1-16
Chapter 1
Safety
CAUTION
Check the crane, the crane hook and all related items
before use. Use wire ropes which can withstand the weight
of the parts multiplied by a safety factor.
Work area:
Hoisting method:
Pay attention to and ensure that all persons are clear of the
equipment being lifted.
Hoisting point:
Unpacking:
Rev.001
Protection of machine:
Avoid any impact to the unpacked parts.
MM-M05.01
Main Turbine
Mitsubishi
1-17
Chapter 1
Safety
1.4.2.13 Disposal
a)
b)
Chemical disposal
Chemicals must be handled following the instruction of the MSDS
and disposed to the chemical drain system.
c)
MM-M05.01
Rev.001
For disposal from the site, observe the local legal regulations.
Main Turbine
Mitsubishi
1-18
Chapter 1
1.5
Safety
Emergency Measure
1.5.1 Evacuation on Emergency Case
1.5.1.1
Evacuation Route
Following items are considered on design and installation
of emergency evacuation.
IMPORTANT
1.5.1.2
IMPORTANT
It is recommended to keep a stretcher available for
emergencies at the places selected as being secure at the
safety meeting.
If you find this kind of accident, inform the rescue team, and
attempt to bring the collapsed person to the first aid station.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
1-19
Chapter 1
1.5.1.3
Safety
IMPORTANT
All people working in the power house must stop their work
immediately and leave the power house to the gathering
place.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
1-20
Chapter 1
Safety
IMPORTANT
Clearly show the location of fire alarm push button and fire
extinguisher to make everybody take the first step at fire
protection.
The operators must check the plant is ready for trip, and
wait for order from the responsible person.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
1-21
Chapter 1
Safety
1.5.3 Earthquake
In the case of an earthquake, the shift charge engineer or operator
must judge whether the unit trip is necessary according to the intensity
of the earthquake, and immediately trip the unit manually. If the unit is
tripped, all equipment must be carefully checked on its operation status
and tripped if abnormal phenomena are found.
In the local area, mechanical and/or thermal shocks may be given to
the equipment, piping, instruments and electrical panels. Be sure to
observe the following when completing the inspection.
CAUTION
Check the piping and equipment for the breaking and the
dropping of insulation. Since the exposure of the hot
surface may cause burn injury, it must be repaired by a
worker fully dressed in Personal Protective Equipment.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
1-22
Chapter 1
1.6
Safety
Operator and Maintainer can understand the related P & ID, logic diagram.
Operator can operate the equipment and the system manually at local
stations.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
1-23
Chapter-2
General
C h a p t er
2 General
2.1
Purpose
The purpose of this maintenance manual is to provide specific information to the
Paiton Expansion Project maintenance personnel regarding the maintenance of
the main turbine. Although this document will convey a good knowledge and
direction regarding maintenance of the main turbine, it is recommended that in
the event of a problem not covered in the document the person responsible
should seek assistance or instruction from the turbine manufacturer.
MM-M05.01
Rev.001
2.2
References
a)
b)
c)
d)
e)
f)
g)
h)
Main Turbine
Mitsubishi
2-1
Chapter-2
2.3
i)
j)
General
MM-M05.01
Rev.001
The HP turbine has a combination of impulse (Rateau) and reaction type blading.
The main steam enters the HP turbine through two steam chests each of which
includes one main stop valve (MSV) and two governing valves (GV), and are
located, one on each side of the HP turbine. The GV outlets are connected to the
HP element of the HP-IP casing through four inlet pipes, each connected to the
steam chest of the No.1 dummy ring by a slip joint. Two of these inlet steam
pipes are connected to the upper casing and the other two to the lower casing.
As the steam passes through the HP turbine blading towards the exhaust
openings through which the steam is directed to the reheater, steam is extracted
from the intermediate stage to No.8 HP feed water heater and from the HP
turbine exhaust (cold reheat) line to No.7 HP feed water heater.
Main Turbine
Mitsubishi
2-2
Chapter-2
General
In the reheater the HP turbine exhaust steam temperature is increased and the
reheated steam is returned to the IP element of the HP-IP turbine at 566C
through two sets of RSV/ICV assemblies, each set consisting of one reheat stop
valve (RSV) and two interceptor valve (ICV). These assemblies are installed in
front of the HP pedestal, one set on each side of the turbine casing. Two of the
four ICV outlets are connected to the IP element of the HP-IP upper casing and
two to the lower casing. As the steam passes through the IP turbine blading,
towards the exhaust opening in the outer casing cover, steam is extracted from
an intermediate stage and directed into the No.6 HP feed water heater for
heating the feed water. Steam from the exhaust of the IP turbine is extracted and
directed to the deaerator to heat and remove air and non-condensable gases
from the feed water.
The IP turbine exhaust opening is connected through a crossover pipe to an inlet
opening in each of the LP turbines to supply drive steam for the LP turbines. Cold
spring of 50 mm is provided on the cross-over pipe between the IP and LP1
turbines and 70 mm between LP1 and LP2 turbines. Two expansion joints
installed on the crossover pipe together with the cold spring jointly accommodate
the thermal expansion. The LP turbines are of the double flow type with steam
entering at the center of the blade path and flowing toward an exhaust opening at
each end. Thence the steam flows downward into the main condenser. The LP
turbine blading is of the reaction type with 35.4-inch (900 mm) last row blades.
Openings are provided in the lower half LP1 and LP2 casings through which
steam is extracted to the four low pressure feed water heaters.
MM-M05.01
Rev.001
Steam exhausts from both ends of each LP turbine at a near total vacuum and at
a relatively low temperature. It exhausts directly into the main condenser, where
it is condensed and the condensate is collected in the condenser hot well.
Main Turbine
Mitsubishi
2-3
Chapter 2
General
S A FE TY VA LV E
S IL E N C E R
T O S A M P L IN G R A C K
(H T R )
M A IN S T E A M P IP E 3 A
S IL E N C E R
(S L 3 B )
ESCAPE
P IP E
M A IN S T E A M P IP E 3 B
PS
3R Y SH
OUTLET HEADER
PS
PS
T O T /B V A L V E
W A R M IN G
T O H P T U R B IN E
B Y -P A S S V A L V E
M
ZT
3RY SH
IN L E T H E A D E R
S IL E N C E R
(S L 3 A )
3RY
SUPERHEATER
3R Y
SUPERHEATER
3RY SH
O UTLET HEADER
M
ZT
3RY SH
IN L E T H E A D E R
S IL E N C E R
(S L 3 B )
T O S A M P L IN G R A C K
E S C A P E P IP E
TO CONDENSER
T O T U R B IN E F L A S H P IP E
H O T R E H E A T P IP E 3 A
E S C A P E P IP E
H O T R E H E A T P IP E 3 B
2RY RH
O UTLET HEADER
2RY RH
IN L E T H E A D E R
E S C A P E P IP E
ESCAPE
P IP E
GV
2RY
2RY
REHEATER REHEATER
1RY
1RY
REHEATER REHEATER
RSV 3B
R S V 3A
GV
IC V
IC V
T O T U R B IN E
F L A S H P IP E
H P /IP T U R B IN E
TO CONDENSER
1RY RH
O UTLET H EADER
2R Y RH
IN L E T H E A D E R
C O L D R E H E A T P IP E
TO HP NO. 7
FEED W ATER H EATER
LS
LS
Rev.001
TO S O O T B LO W ER
T O A U X IL IA R Y
STEAM SYSTEM
T O B O IL E R F L A S H P IP E
MM-M05.01
M SV 3A
2RY RH
O UTLET HEADER
ESCAPE ESCAPE ESCAPE
P IP E
P IP E
P IP E
2R Y RH
IN L E T H E A D E R
E S C A P E P IP E
1R Y RH
O UTLET HEADER
1RY RH
IN L E T H E A D E R
M SV 3B
F R O M N IT R O G E N G A S S E A L S Y S T E M
TO CONDENSER
T O T U R B IN E F L A S H P IP E
M P T D -3 -0 2 0 0
FIGURE 2-1
Main Turbine
Mitsubishi
2-4
Chapter 2
General
MM-M05.01
Rev.001
IP TURBINE EXHAUST
MPTD-3-0201
FIGURE 2-2
Main Turbine
Mitsubishi
2-5
Chapter 2
GEN. SIDE
General
VIBRATION PICK UP
VIBRATION PICK UP
C
L OF MAIN OIL PUMP
C
L OF THRUST BRG.
C
L OF NO.1 BRG.
PHASE DETECTOR
PICK UP
PEDESTAL
VIBRATION PICK UP
DIFFERENTIAL
EXPANSION PICK UP
NO.6 BEARING
PEDESTAL
ROTOR GROUNDING
DEVICE
C
L OF MAIN STEAM INLET
VIBRATION
PICK UP
C
L OF REHEAT STEAM INLET
VIBRATION
PICK UP
C
L OF IP EXHAUST
C
L
C
L OF NO.2 BRG.
OF NO.3 BRG.
C
L OF LP1 TURBINE
C
L OF NO.4 BRG.
C
L OF NO.5 BRG.
C
L OF NO.6 BRG.
C
L OF LP2 TURBINE
GOV. SIDE
DIFFERENTIAL
VIBRATION
PICK UP
NOS.4&5 BEARING
PEDESTAL
HP PEDESTAL
ZERO SPEED
& SPEED PICK UP
ECCENTRICITY
PICK UP
ROTOR POSITION
PICK UP
ROTATION
OPERATING FLOOR
NO.3 EXTRACTION
NO.2 EXTRACTION
NO.3 EXTRACTION
NO.1 EXTRACTION
NO.2 EXTRACTION
NO.4 EXTRACTION
NO.1 EXTRACTION
NO.2 EXTRACTION
NO.4 EXTRACTION
NO.2 EXTRACTION
NO.1 EXTRACTION
NO.1 EXTRACTION
NO.7 EXTRACTION
NO.8 EXTRACTION
MAIN STEAM INLET
NO.5 EXTRACTION
MM-M05.01
Rev.001
MPTD-3-0202
FIGURE 2-3
Main Turbine
Mitsubishi
2-6
Chapter 2
General
ICV
LP2 TURBINE
LP1 TURBINE
MSV/GV ASSEMBLY
RSV
EXCITER
GENERATOR
C
L
OF RSV&ICV
HP PEDESTAL
C
L
MS. INLET
C
L ON CYLINDER
C
L
RSV
No.1 BRG.
ICV
C
L
No.7 BRG.
C
L
GENERATOR
C
L
C
L
No.8 BRG.
ICV
EXCITER
OF RSV&ICV
GOV. SIDE
C
L
MSV
C
L
No.2 BRG.
C
L
No.3 BRG.
C
L
LP-1 TURBINE
C
L& CONDENSER
No.4 BRG.
C
L
No.5 BRG.
C
L
C
L
GEN. SIDE
LP-2 TURBINE
C
L& CONDENSER
No.6 BRG.
C
L
HP PEDESTAL
RSV
ROTATION
OPERATING FLOOR
HP PEDESTAL
NO.7 EXTRACTION
NO.1 EXTRACTION
NO.2 EXTRACTION
Rev.001
NO.3 EXTRACTION
NO.1 EXTRACTION
NO.2 EXTRACTION
NO.3 EXTRACTION
NO.1 EXTRACTION
NO.2 EXTRACTION
NO.4 EXTRACTION
NO.8 EXTRACTION
NO.1 EXTRACTION
NO.2 EXTRACTION
NO.4 EXTRACTION
NO.5 EXTRACTION
NO.6 EXTRACTION
MM-M05.01
FIGURE 2-4
Main Turbine
Mitsubishi
Chapter-2
2.4
General
Components
The complete turbine is described as a tandem compound, 3-cylinder, quadruple
exhaust, extracting, condensing, reheat turbine. The three cylinders contain a
HP-lP combined element and two LP turbines viz. LP1 and LP2. The above three
cylinders combined form the main turbine unit. The combined HP-IP, LP1 and
LP2 turbine rotor shafts connect all turbine sections, and these connect to the
generator shaft to provide a compound rotor. All turbine rotor shafts are
connected by bolted flanged solid couplings. When the turbine operates, the
compound rotor rotates simultaneously within the three turbine cylinders and the
generator.
The entire turbine unit is mounted on a concrete foundation. The complete
rotating element of the turbine is supported by six journal bearings, one at each
end of the three rotors. The journal bearings are mounted in individual pedestals
located at the ends of each turbine. The bearing pedestals rest on metal base
plates on the concrete foundation. The base plates allow the bearing pedestals
and cylinders to slide axially along the length of the rotor to permit thermal
expansion during turbine operation. Differential expansion pick-ups are located
between the HP Turbine and the LP1 Turbine and at the rear of the LP2 turbine
to monitor relative thermal expansion between turbine cylinder sections and the
rotor during operation. A thrust bearing installed within the HP pedestal between
No.1 bearing and the shaft driven main oil pump (MOP) locates the turbine rotor
axially and absorbs the axial thrust. All turbine bearings receive oil for lubrication
and cooling from the main turbine lubricating oil system.
MM-M05.01
Rev.001
turbine casings
rotors
blading
rotor seals
gland seals
bearings
rotor couplings
turning gear
breakable diaphragm
turbine enclosure.
Main Turbine
Mitsubishi
2-8
Chapter-2
General
HP-IP Casing
Refer to Figures 2-5 and 2-6.
The HP-IP turbine consists of an outer casing which accommodates the
HP-IP turbine parts viz. turbine rotor, inner casing, IP blade ring, No.1
and No.2 dummy rings, HP and IP stationary blade rings, turbine
blading, etc.
The outer casing of the combined HP-IP turbine is an alloy steel casting
split in the horizontal center plane to form a base (1) and a cover (2).
The inner casing (3) is also made of alloy steel casting split in the center
plane to form a base and cover. The inner casing is supported in the
outer casing at the horizontal joint and located by dowels (24) and
matching tongue and groove fits so as to maintain the correct position
with regard to the turbine axis while allowing the components to expand
and contract freely in response to temperature changes.
The No.1 dummy ring (5) is supported within the inner casing (3) at the
horizontal joint. At the HP turbine end of the No.1 dummy ring, a nozzle
block (25) is installed which contains several nozzles (26) arranged in a
circle. These nozzles are arranged such that they direct the incoming
main steam to the Rateau stage blades at high velocity. At the IP turbine
end of the No.1 dummy ring, it is provided with an extension ring which
contains sealing rings with seal strips to minimize leakage of steam from
the Rateau stage inlet to the IP turbine inlet. The No.1 dummy ring also
carries the 1st ~ 3rd stage HP stationary blade diaphragms.
The four main steam inlets are connected to the No.1 dummy ring (5)
through nozzles cast integral with the HP end of the HP-IP outer casing
(1, 2) on either side (RS and LS) of the turbine axis. Likewise, the four
reheat steam inlets are connected to nozzles cast integral with the IP
end of the HP-IP outer casing (1, 2), two on the cover and two on the
base.
MM-M05.01
Rev.001
The No.1 and No.2 HP stationary blade rings (6, 7), which carry the 4th ~
9th stage stationary blade diaphragms of the HP turbine, are supported
in the inner casing (3) at the horizontal joint. The HP stationary blade
rings are located axially in the inner casing (3) by matching tongue and
groove fits and supported at the horizontal by liners and support keys.
Main Turbine
Mitsubishi
2-9
Chapter-2
General
The No.1 ~ No.4 IP stationary blade rings (8, 9, 10 and 11), which
together carry the entire stationary blade diaphragms of the IP turbine,
are supported in the IP blade ring (4) at the horizontal joint. The four IP
stationary blade rings are located in the IP blade ring (4) by matching
tongue and groove fits and supported at the horizontal joint by support
keys and liners, similar to the HP stationary blade rings.
The No.2 dummy ring (13) and the thermal shield (19) are supported in
the outer casing by support keys and liners at the horizontal joint and
located by dowel pins at the top and bottom.
The combined HP-IP turbine casing is supported by four arms (or lugs)
which are cast integrally at the top of the base section, thus locating the
point of support as closely as possible to the horizontal center line. The
HP-IP outer casing is supported on the HP pedestal (14) at the governor
end (Gov End) and on the LP1 turbine outer casing at the generator end
(Gen End) as shown in Figure 2-5. For this purpose horizontal
machined surfaces are prepared on the HP pedestal and on the LP1
outer casing base.
The HP-IP outer casing base at the Gov End is supported on the HP
pedestal where the casing arms are located on transverse keys,
installed between the arms and the pedestal, on which the arms are free
to slide transversely. At the Gen End, the arms are supported on the top
surface of the LP1 outer casing base adjacent to the No.2&3 bearing
pedestal.
Refer to Figure 2-13 for details of HP pedestal. The HP pedestal is free
to slide axially on its base plate (21), but it is held against transverse
movement by two axial keys (17) placed on the longitudinal centerline
between the pedestal and the base plate. Any tendency of the pedestal
to tilt or lift is limited by side gibs, which are fitted with ample clearance
to allow free movement axially. Any tendency of the HP-IP outer casing
to rise off the HP pedestal is limited by a stud bolt (7) through each arm.
These stud bolts are fitted with ample clearance under the nut (29) and
around the bolt to allow free movement of the outer casing arms in
response to temperature changes.
The arms of the HP-IP outer casing at the Gen End are free to slide on
the No.2&3 bearing pedestal base. The tendency of the HP-IP casing to
rise off the bearing pedestal is limited and clearance for free expansion
movement is provided by similar arrangements provided on the HP
pedestal at the Gov End.
MM-M05.01
Rev.001
At each end of the HP-IP turbine between the outer casing and the
pedestals, centering beams are installed to maintain the correct axial
and transverse positions of the outer casing. Refer to Figure 2-12 for
details of centering beams.
Main Turbine
Mitsubishi
2-10
Chapter-2
General
The HP-IP turbine outer casing base and cover have integrally cast
nozzles for the entry and exit of main steam and reheat steam. The
outer casing base has nozzles for the extraction of steam to the high
pressure feed water heaters and other purposes. The HP-IP turbine
outer casing also has nozzles for HP and LP balancing pipes which
transfer leakage steam from the No.1 dummy ring seals to the HP
turbine exhaust and the No.2 dummy ring (13) seals to the IP turbine
exhaust respectively.
LP Casing
Refer to Figures 2-7 to 2-10. The constructional features of the LP1 and
LP2 turbine casings are similar.
The LP1/LP2 casing mainly consists of an outer casing (1, 2) and an
inner casing (3). The outer casing and the inner casing are split at the
horizontal center line to form a base and a cover. A steam chamber (4),
an inner flow guide ring (5) and two exhaust flow guide rings (6) are
installed in the LP casing; these components are also split in the
horizontal center plane to form a base and a cover.
The inner casing (3) is supported on the outer casing base at the
horizontal joint and located by a dowel pin (19) secured to the outer
casing base at the bottom.
The steam chamber (4) is supported on the inner casing horizontal joint
and located by a dowel (20) and two radial pins (22) at the bottom end.
The inner flow guide ring (5) is supported on the steam chamber
horizontal joint and located by dowel pin (21) welded to the inner flow
guide ring.
The LP blade rings (7) are supported on the steam chamber (4), one on
each end of the inner flow guide ring, and located by dowel pin (21) and
radial pins (23).
The first and second stage stationary blade diaphragms on each
flow-path of the turbine are secured to the LP blade rings (7) and the
third to fifth stage stationary blade diaphragms to the inner casing (3).
The last two stage stationary blade diaphragms are located and
secured to the inner casing.
MM-M05.01
Rev.001
The cross-over pipe from the IP turbine exhaust is connected to the LP1
and LP2 inner casings using flanged joints via flanged nozzles welded
on the top of the inner casings. Refer to Figure 2-14 for details of
cross-over piping connection and sealing arrangements. Expansion
joints together with cold spring settings (50 mm and 70 mm) provided on
the cross-over pipe accommodate the casing differential expansion.
The joints between the LP1 and LP2 inner casings and the outer
casings are sealed by a top seal ring arrangement as shown in Detail F
to prevent ingress of atmospheric air into the turbine.
Main Turbine
Mitsubishi
2-11
Chapter-2
General
The inner flow guide ring (5) located within the steam chamber (4) at the
vertical axis of each LP turbine guides the inlet steam to each flow-path.
The exhaust flow guide rings (6) secured to the ends of the inner casing
(3) guide the LP turbine outlet steam to the exhaust ports and to the
main condenser. To provide rigidity within the LP outer casing a series
of reinforcing bars and piping are installed.
Each LP1/LP2 turbine is supported by a continuous foot or skirt which is
made integral with and extends around the outer casing base. This foot
rests on seating plates which are bolted and grouted to the turbine
foundation.
Four transverse anchor blocks, provided one on each end of the LP1
and LP2 turbines, locate the LP1 and LP2 turbine casings in the turbine
axis. The transverse anchor blocks are secured to the turbine
foundations and locate the axial centerlines of the LP1 and LP2 turbine
casings in the turbine axis. With respect to the transverse anchor blocks,
the LP1 and LP2 turbine casings expand laterally (outwards) in opposite
directions. Refer to Figure 2-11 for LP turbine anchoring details.
Two axial anchor blocks, provided one on each side of the LP1 outer
casing, locate the entire turbine unit in the axial direction. They are
installed near the Gen End of LP1 turbine at a distance of 3275 mm from
the transverse centerline of LP1 turbine. Maintaining the axial anchor
blocks as fixed points, the LP1 and LP2 turbine casings expand axially
in opposite directions towards the HP pedestal and the generator. All
four casings (HP-IP, LP1, LP2 and generator casings) move axially with
respect to these axial anchor blocks.
In addition to the above anchor blocks, two tie beams are installed
between the LP1 and LP2 turbine outer casings, one on each side of the
turbine axis, to maintain the correct axial and transverse positions of the
outer casings. Refer to Figure 2-12 for details of tie beams.
Each LP turbine outer casing base has nozzles for the extraction of
steam for the low pressure feed water heaters and other purposes. The
LP1 turbine is provided with nozzles for No.1, No.2 and No.4 extractions
and the LP2 turbine is provided with nozzles for No.1, No.2 and No.3
extractions.
Two breakable diaphragms are provided on top of each outer casing
cover, one at each end of the LP1 and LP2 turbines, to protect the LP
turbine from high pressure damage.
MM-M05.01
Rev.001
2.4.2 Rotors
Refer to Figures 2-15 to 2-18.
The turbine rotor essentially consists of HP-IP, LP1 and LP2 rotors,
installed within their respective turbine casings.
Main Turbine
Mitsubishi
2-12
Chapter-2
General
Rigid type couplings connect the HP-IP rotor to the Gov End of LP1
rotor, Gen End of LP1 rotor to the Gov End of LP2 rotor and Gen End of
the LP2 rotor to the generator rotor. All coupling flanges are cast integral
with their respective turbine rotors. The main rotating element thus
formed (consisting of the HP-IP turbine rotor, LP1 and LP2 turbine
rotors and the generator rotor) is carried in eight journal bearings. The
rotating element thus formed is located axially by a thrust bearing
installed within the HP pedestal.
HP-IP Rotor
Refer to Figure 2-15.
The HP-IP turbine rotor is machined from a solid CrMoV alloy steel
forging. The rotor is finish machined and after being completely bladed,
is given an accurate dynamic balance test. The HP turbine rotating
blades (2), IP turbine rotating blades (3) and Rateau stage blades (4)
are secured to the HP-IP rotor.
The HP-IP rotor is provided with a series of balancing holes (7)
circumferentially at three locations, one near the centre of the rotor near
the IP turbine 1st stage and one at each end near the Gov End and Gen
End inner gland casings. The centrally located balancing holes are
normally used at the factory balancing and the holes at each end are
used in the event of site balancing being necessary. The HP-IP casing
is provided with necessary openings to provide access for the
installation of balancing weights in the event of HP-IP rotor site
balancing.
The Gen End of the HP-IP rotor is flanged to enable coupling. This
coupling flange is also provided with balancing holes on the
circumference to enable site balancing.
On the IP side of the main steam inlet, sealing rings are installed in the
No.1 dummy ring around stepped surfaces on the rotor to reduce steam
leakage from the inlet of HP turbine Rateau stage into the inlet of the IP
turbine. The No.2 dummy ring is installed at the Gov End of the rotor
within the HP-IP outer casing to minimize steam leakage from the HP
turbine exhaust into the Gov End gland casing.
At the Gov End of the HP-IP rotor, an extension stub shaft (5) is
provided to support the turbine main oil pump (MOP) impeller (6) and to
contain the mechanical overspeed trip (MOST) device. The extension
stub shaft is also provided with an integrally machined thrust collar (10)
to locate the combined turbine rotor axially.
MM-M05.01
Rev.001
The HP-IP rotor is provided with stepped surfaces (8) in the vicinity of
the HP and IP stationary blade diaphragms, sealing rings of No.1
dummy ring and No.2 dummy ring to provide efficient sealing and to
minimize steam leakage from the high pressure zone to the low
pressure zone.
Main Turbine
Mitsubishi
2-13
Chapter-2
General
LP Rotors
Refer to Figures 2-16 and 2-17.
The constructional features of the LP1 and LP2 rotors are similar. Each
LP rotor is machined from a solid NiCrMoV alloy steel forging. The rotor
is finish machined and after being completely bladed, is given an
accurate dynamic balance test. The rotating blades of each LP turbine
are secured to the respective LP rotors.
The LP rotor is provided with a series of balancing holes (4)
circumferentially at three locations, one in the LP turbine vertical axis
and one at each end near the Gov End and the Gen End gland casings.
The central balancing holes are normally used to perform dynamic
balancing in the factory and the holes at the ends are used in the event
of any site balancing. The LP1 and LP2 turbine outer casings are
provided with necessary flanged openings to provide access for the
installation of balancing plugs in the event of rotor site balancing.
Each LP rotor is provided with plain machined surfaces at both ends
where the rotor shaft penetrates the casing, and also in the vicinity of
the stationary blade diaphragms to provide effective gland sealing.
The LP1 rotor is provided with stepped surfaces near Nos. 3 and 4
bearing journals for the measurement of LP1 rotor vibration. The LP2
rotor is provided with stepped surfaces in the vicinity of Nos. 5 and 6
bearing journals for the measurement of the LP2 rotor vibration and
slant surfaces bear the Gen End coupling flange for the measurement of
turbine rotor differential expansion.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
2-14
Chapter-2
General
MM-M05.01
Rev.001
The oil injection test is normally carried out on a monthly basis with
options for remote testing through a solenoid valve or locally through a
manually operated valve. During the above test, the turbine is
prevented from tripping by the operation of the lock out solenoid valve
for the remote test or by the operation of hand test lever for local test.
Main Turbine
Mitsubishi
2-15
Chapter-2
General
2.4.3 Blading
The blade path includes a Rateau stage operating with partial
admission control, followed by reaction stages in the HP, IP, LP1 and
LP2 turbines. The exact blade arrangement and the number of stages
or rows are given in Section 3, Specifications. Throughout the blade
path the rotating and the stationary parts are separated by relatively
large axial clearances. The much smaller radial clearances necessary
to control steam leakage are maintained by thin seal strips. These strips
are made of an alloy steel with excellent wearing qualities so that should
contact occur under normal conditions, the strips will rub away.
a)
MM-M05.01
Rev.001
2-16
Chapter-2
General
The blades are shaped to form their own shroud thus forming a
closed passage for the steam flow. In order to reduce vibrational
stresses, these blades are bound together in groups by additional
shrouds (15) and tenons (16) on the end of the blades and
secured by riveting over the tenons.
The shanks are accurately machined to fit closely to one another
to give the correct spacing for the steam passage. To ensure that
steam leakage around the blades may be held to a minimum, seal
strips (17) are provided as shown in Fig 2-19.
b)
MM-M05.01
Rev.001
The No.1 dummy ring and the two HP stationary blade rings are
machined with straight-sided grooves to hold the stationary blade
diaphragms in their correct locations. Each stationary blade ring
groove is sized to match the stationary blade diaphragm width
required at each row. A slot is machined in each HP stationary
blade ring groove to accommodate a metal packing strip used to
secure the stationary blade diaphragm in the HP stationary blade
ring as indicated in Detail E. The packing strip, caulked in at
installation, seals the stationary blade diaphragm groove.
Main Turbine
Mitsubishi
2-17
Chapter-2
General
c)
MM-M05.01
Rev.001
As the blades are inserted, one after another, the flank face on
each blade locks in the retaining pin of the previously inserted
blade. The last blade entered is specially pinned with two lock
screws.
Main Turbine
Mitsubishi
2-18
Chapter-2
General
The stationary blades are machined from bar stock with an offset
root and an integral shroud. The individual blades are then welded
together on the base and shroud to form a stationary blade
diaphragm which is split at the horizontal joint.
The stationary blade diaphragms are secured to the four IP
stationary blade rings (No.1, No.2, No.3 and No.4 IP stationary
blade rings) as indicated in Detail C. All IP stationary blade rings
have machined, straight-sided grooves to hold the stationary
blade diaphragms in their correct locations. Each stationary blade
ring groove is sized to match the stationary blade diaphragm width
required at each row. A slot is machined in each IP stationary
blade ring groove to accommodate a metal packing strip which
secures the stationary blade diaphragm in the IP stationary blade
ring. The packing strip, caulked in at installation, seals the
stationary blade diaphragm groove.
At installation of the stationary blades, a slot and a tapped hole
are added to the upper and lower half stationary blade
diaphragms for installation of a setscrew in the horizontal joint
area. Refer to Detail C for details. The setscrew prevents the
stationary blade diaphragm from rotation during operation. The
set screw also keeps the stationary blade diaphragm from falling
out when the IP stationary blade ring is removed for maintenance.
All IP stationary blade rings are made in two halves, split at the
horizontal joint. The lower half IP stationary blade rings are
secured to the IP blade ring using keys and liners, similar to the
HP stationary blade rings, to prevent them from rotation and the
upper half blade rings are secured the lower halves by horizontal
joint bolts.
Each rotating/stationary blade shroud forms a close radial
clearance with thin flat seal strips, as shown in Fig 2-24, to ensure
that steam leakage around the blades may be held to a minimum.
The seal strips around the rotating blades are secured in slots
machined in the IP stationary blade rings.
The stationary blade diaphragms are provided with spring-backed
seal rings onto which the seal strips are secured to provide
effective sealing with the rotor. These seal rings are installed in
segments and each segment is backed by a separate spring.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
2-19
Chapter-2
d)
General
Rotating Blades
Each LP rotor is fitted with seven rows of right-hand (RH) blading
on the Gen End and seven rows of left-hand (LH) blading on the
Gov End blade paths. Both sets of blading are the same but to the
opposite hand.
Since the steam flows in opposite directions through the blade
path in a double-flow unit, the rotating blades in the Gen End
blade path are RH blades, and those in the Gov End blade path
are LH blades. This permits the steam leaving the trailing edge of
either the Gen End or Gov End rotating blade row to travel in the
same rotating direction.
The rotating blades have serrated roots and are installed in
grooves cut across the surface of the rotor and machined to
conform to the shape of the blade root.
At the first through the fourth stages, the rotating blades are
installed similar to those in the IP turbine. A half-round groove is
machined circumferentially on the outer surface of the rotor and
each blade has a hole drilled at its base in line with the groove in
the rotor. Hence, as each blade is inserted in its groove and
properly located, a retaining pin is inserted in this hole thus locking
MM-M05.01
Rev.001
the blade to the rotor. As the blades are inserted one after another,
the free face of each blade is fixed by the retaining pin, which is
used to lock the previously inserted blade to the rotor. The last
blade entered is specially pinned by two set screws.
Main Turbine
Mitsubishi
2-20
Chapter-2
General
For the installation of the last three stage blades refer to View X-X,
Section A-A and View C-C in Figure 2-22. In the last three stages,
the rotating blades are fixed by driving a caulking strip into the
bottom of the blade root and the blade axial positions are fixed by
the insertion of a locking piece in a circumferential groove at each
end of the blade groove.
The rotating blades are of an integral shroud type construction,
with a shroud machined integrally in each blade.
As the rotating blades in the last row are relatively larger blades,
the blades have stubs provided mid-length on the individual
blades which when the rotor is turning at high-speed act to
prevent blade distortion and possible vibration.
The rotating blades in the last row operate in a zone where the
steam has high moisture content, which may cause blade erosion.
To minimize blade erosion due to moisture, a portion of each
blade is fitted with a stellite strip along the leading edge. Stellite, a
binary alloy of cobalt and chromium base, is very hard and is
highly resistant to erosion.
As shown in Figure 2-22, a flow guide is provided at each end of
the inner casing to maintain a smooth flow of steam from the last
stage rotating blades into the exhaust chamber.
The rotating blade shrouds in the first to the fourth stages form
close radial clearances with thin flat seal strips, as shown in
Figure 2-25, to ensure that steam leakage around the blades is
held to a minimum. The seal strips are removable and can be
renewed if the clearance between them and the corresponding
blade shrouds become excessive.
The fifth and the sixth stage rotating blade shrouds are provided
with spring-backed sealing rings secured to the inner casing to
minimize steam leakage. The last stage rotating blade shrouds
are also provided with spring-backed sealing rings and are
secured to the exhaust flow guide rings.
Stationary Blades
MM-M05.01
Rev.001
2-21
Chapter-2
General
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
2-22
Chapter-2
General
MM-M05.01
Rev.001
The seal rings are removable and can be renewed if the clearance
becomes excessive.
Main Turbine
Mitsubishi
2-23
Chapter-2
General
MM-M05.01
Rev.001
2-24
Chapter-2
General
a)
MM-M05.01
Rev.001
2-25
Chapter-2
General
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
2-26
Chapter-2
General
A stopper pin (14) fitted in the lower half bearing carrier ring fits
into a notch in the pedestal base just below the horizontal joint
(between Nos. 1 & 4 bearing pads), thus preventing rotation of the
bearing during operation.
Each bearing pad is provided with two temporary bolts (23) which
clamp each end of the pad to the bearing carrier ring. The purpose
of these bolts is to hold the pads in place during transportation and
installation. They are removed and the holes plugged with plugs
(24) during final assembly.
The bearing assembly is lubricated by lubricating oil from the main
turbine lubricating oil system. Lubricating oil reaches the bearing
through a passage in the pedestal base, and enters the lower half
carrier ring through a hole in the center of the outer liner (7).
Passages within the carrier ring direct the oil to the pad stoppers
(11) through matching holes. The pad stoppers, provided with
internal passages, spray the lubricating oil onto the journal
surface through oil distributors (13). The oil distributor is made of a
header with fine holes to distribute the oil uniformly onto the
journal surface. The end covers (15), fitted to the ends of the
carrier ring with a small clearance with the rotor, prevent
excessive oil leakage from the bearing. Oil is drained into the
pedestal through the clearance between the end covers and the
rotor.
The bottom bearing pads (Pad Nos. 3 and 4) have provisions for
the installation of thermocouples to measure the bearing
temperature just beneath the Babbitt lining.
b)
MM-M05.01
Rev.001
2-27
Chapter-2
General
centerlines, while the third one is located at the top of the upper
half shell on the vertical centerline.
Each key (3) is located in their respective groove on the outer
surface of the bearing shell using a dowel pin (10) and secured by
two key fixing bolts (9). The keys are provided with threaded holes
for jacking during removal.
The outer surfaces of the keys are spherical to match the mating
surface of the bearing housing comprising the bearing seat (13) in
the pedestal base and the bearing keep (14). (The bearing keeps
for the Nos. 3, 4 and 5 bearings are integral with the respective
pedestal covers). The keys are machined to a radius slightly less
than that of the bearing housing to provide a clearance fit of 0.3 to
0.4 mm.
Liners (12) and shims (11) are provided between each key and
the bearing shell. Shims of variable thicknesses (0.05, 0.1, 0.2
and 0.3 mm) are supplied with each bearing for adjustment during
coupling alignment. By adjusting the thickness of the liners and
shims between locations, the bearings and therefore the rotor can
be moved relative to the bearing housing and the turbine casing.
The support keys and the liners are numbered 1 to 3 and the
bearing shells are match marked to ensure that the bearing
components are assembled in their correct positions following an
inspection.
A stopper pin (4) fitted in the lower half shell fits into a notch in the
pedestal base just below the horizontal joint, thus preventing
rotation of the bearing during operation.
The lower half bearing shell is provided with a jacking oil
arrangement as shown in detail D to supply jacking oil and lift the
heavier LP rotors at low turbine speeds.
The bearing is lubricated by lubricating oil from the main turbine
lubricating oil system. Lubricating oil is supplied to the bearing
through an aperture drilled in the pedestal base, which is aligned
with an opening in the center of the right side bottom key (Key
No.2). Passages within the bearing shell direct the oil to the
bearing surface in the top half of the bearing as shown in the
drawing.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
2-28
Chapter-2
General
c)
Bearing No.6
Refer to Figure 2-29.
The No.6 bearing is of the white metal lined, self-aligning, tilting
pad type. It is spherically seated to provide a measure of
self-alignment and can be adjusted for radial position within the
bearing pedestal.
The bearing is a two-pad type journal bearing consisting of a cast
steel shell, split into two halves (1 and 2). The lower half of the
shell (1) is provided with two tilting pad assemblies. The upper half
of the shell is of the sleeve type bearing and is not provided with
any tilting pad.
The two halves of the bearing shell are bolted together by four
hexagonal head cap screws (5) at the horizontal joint. Two dowel
pins (6) provided at the horizontal joint locate the upper half shell
(2) on the lower half shell (1).
The bearing shell is positioned in the bearing pedestal by three
keys (3) set into the upper and lower halves of the shell. Two of
these keys are assembled on the lower half shell at an angle of
45 to the horizontal and vertical centerlines. The third key is
located at the top of the upper half shell on the vertical centerline.
All three bearing keys are of similar design, with an oil hole
through the center. These keys and the bearing shell are clearly
numbered (1, 2 and 3) and the keys should always be assembled
in the same way in accordance with the marks.
MM-M05.01
Rev.001
As a fail safe measure, all three bearing keys are provided with an
oil hole. However, components should always be match marked
to ensure that the bearing components are assembled in the
correct/original positions following an inspection.
The outer surfaces of the keys (3) are spherical to match the
mating surfaces of the bearing seat (26) and the bearing keep (27).
The bearing seat (26) is integral with the No.6 bearing pedestal
base and the bearing keep (27) is integral with the pedestal cover.
Main Turbine
Mitsubishi
2-29
Chapter-2
General
MM-M05.01
Rev.001
2-30
Chapter-2
General
Oil leaking through the oil seal ring is collected and drained to the
bearing pedestal through passages machined in the oil seal rings.
The oil seal ring retainers are also provided with passages at the
bottom end for this purpose.
The bearing is lubricated by lubricating oil from the main turbine
lubricating oil system. Lubricating oil is supplied to the bearing
through a hole in the bearing seat, which is aligned with the oil
hole in the center of key No.2 on the lower half shell.
As shown in the illustration, from this key the oil is led through
drilled internal passages to a relieved section in the upper half
bearing shell. The relieved sections have large clearances along
both sides around the horizontal joint. The relieved sections do
not extend to the ends of the bearing but stop at an annular
drainage groove close to each end.
The effect of these features is to create a constant supply (pool) of
oil for lubrication. Oil is then drawn into the smaller gap that exists
between the lower half bearing surface and the journal by the
rotation of the shaft. This is a desirable characteristic for the
bearings supporting the heavier LP turbine rotors.
d)
Thrust Bearing
Refer to Figure 2-30.
The thrust bearing is designed to resist thrust in either direction,
although the overall turbine design is for the thrust to act towards
the Gen End. The thrust bearing therefore limits the potential
turbine axial movement within the thrust clearance, and provides
protection for the turbine internal components.
The thrust bearing is a white metal faced multiple pad bearing,
with a lever mounting system to allow the pads to tilt and thereby
share the load evenly. A thrust collar (24), machined integrally
with the HP-IP rotor extension stub shaft (27), transmits thrust
from the turbine rotor to the turbine structure via the thrust bearing
assembly.
MM-M05.01
Rev.001
The thrust bearing is provided with eight pads (4, 15, 17, 18) on
each side of the thrust collar (25). The pads are numbered #1-1 to
#1-8 on the Gen End and #2-1 to #2-8 on the Gov End. The pads
#1-1 (20), #1-5 (17), #2-1 (22) and #2-5 (18), which are adjacent
to the carrier ring split line, are secured to the carrier ring using
parallel pins (19) and are called anti-fall pads. These anti-fall pads
prevent other pads from falling when the upper half carrier ring is
lifted. The anti-fall pads #1-1 and #2-1 and pads #1-4 and #2-4 are
provided with thermocouples for temperature measurement. Each
pad is provided with white metal coating on the bearing side.
Main Turbine
Mitsubishi
2-31
Chapter-2
General
MM-M05.01
Rev.001
The thrust bearing is lubricated by lube oil from the main turbine
lubricating oil system. Lubricating oil is supplied through two oil
inlets, one for each side of the bearing, on the upper half bearing
case and drained into the HP pedestal through an aperture in the
lower half bearing case.
Main Turbine
Mitsubishi
2-32
Chapter-2
General
MM-M05.01
Rev.001
All couplings are provided with coupling guards for the safety of the
nearby equipment and the working personnel, in the event of any
unforeseen coupling failure or loosening of coupling bolts occurs.
Main Turbine
Mitsubishi
2-33
Chapter-2
General
The coupling guards are fabricated steel components. They are made in
two halves split at the horizontal joint, the upper half and the lower half.
The lower half is mounted on the respective lower half bearing pedestal
and the upper half coupling guard is supported by the lower half
coupling guard at the horizontal joint.
All couplings are provided with a supply of lubricating oil from the main
turbine bearing lubrication system. The oil is sprayed on the outer
surface of the coupling guards to dissipate any heat generated on these
couplings/coupling guards during operation. The heated oil is returned
to the main oil tank through the drain guard pipe.
MM-M05.01
Rev.001
2-34
Chapter-2
General
MM-M05.01
Rev.001
A 6 pole, 380 V, 50 Hz, 1000 rpm, 22 kW motor (1) bolted to the turning
gear housing drives the turning gear.
A ratchet spanner (10) supplied as a special tool is used to rotate the
turbine rotor manually when the turning gear motor is damaged or
during a total power supply failure.
Main Turbine
Mitsubishi
2-35
Chapter-2
General
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
2-36
Chapter-2
General
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
2-37
Chapter 2
General
INNER CASING
NO.1 DUMMY RING
OUTER CASING COVER
THRUST BEARING
No.2 HP STATIONARY
BLADE RING
No.1 HP STATIONARY
BLADE RING
MOP
No.2 DUMMY RING
No. 1 BEARING
No.1 IP STATIONARY
BLADE RING
No.2 IP STATIONARY
BLADE RING
Rev.001
No.3 IP STATIONARY
BLADE RING
No.4 IP STATIONARY
BLADE RING
MM-M05.01
No. 2 BEARING
MPTD-3-0204
FIGURE 2-5
Main Turbine
Mitsubishi
Chapter 2
11
4
17
IP EXHAUST
MAIN STEAM
INLET
REHEAT STEAM
INLET
10
21
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
3
6
25
8
19
23
22
GEN.SIDE
GOV. SIDE
16
23
18
24
25
26
15
General
MOST DEVICE
No.2 DUMMY RING
HP PEDESTAL
MOP
NO. 1 BEARING
NO. 2 BEARING
THRUST BEARING
THERMAL SHIELD
HP-IP ROTOR
HP BALANCING PIPE
LP BALANCING PIPE
NOS. 2&3 BEARING
PEDESTAL
DOWEL
NOZZLE BLOCK
NOZZLES
14
12
OPERATING FLOOR
HP EXHAUST
MM-M05.01
Rev.001
26
20
MPTD-3-0205
REHEAT STEAM
INLET
24
MAIN STEAM
INLET
13
24
1
FIGURE 2-6
Main Turbine
Mitsubishi
Chapter 2
General
INNER CASING
MM-M05.01
Rev.001
NO.4 BEARING
MPTD-3-0206
FIGURE 2-7
Main Turbine
Mitsubishi
Chapter 2
15
23
10
11
STEAM
INLET
12
18
14
MM-M05.01
Rev.001
GENERATOR
END
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
General
GOVERNOR
END
17
16
13
21
20
19
22
13
16
17
MPTD-3-0207
FIGURE 2-8
Main Turbine
Mitsubishi
Chapter 2
General
NO. 5 BEARING
MM-M05.01
Rev.001
NO.6 BEARING
MPTD-3-0208
FIGURE 2-9
Main Turbine
Mitsubishi
Chapter 2
15
23
14
10
11
STEAM
INLET
12
18
18
23
22
Rev.001
MM-M05.01
17
Main Turbine
Mitsubishi
GOVERNOR
END
GENERATOR
END
MPTD-3-0209
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
General
16
13
21
20
19
22
13
16
17
FIGURE 2-10
2-43
Chapter 2
No.1 BRG.
C
L
MS. INLET
C
LON CYLINDER
No.2 BRG.
C
L
No.3 BRG.
C
L
LP-1 TURBINE
C
L& CONDENSER
No.4 BRG.
C
L
No.5 BRG.
C
L
No.6 BRG.
C
L
No.7 BRG.
C
L
No.8 BRG.
C
L
LP-2 TURBINE
C
L& CONDENSER
GOV. SIDE
GENERATOR
C
L
GEN. SIDE
General
SEATING PLATE
FOR LP-1 TURBINE
C
L
RSV
2-ANCHOR PLATE
C
L
MSV&GV
C
L
RSV
e
EYE BOLT
VIEW "J"
LP-2 TURBINE
CLEARANCE
0.02~ 0.04
( EACH SIDE)
T/G UNIT
C
L
LP-1 TURBINE
"J"
SPOT WELDING
LP-1 TURBINE CASING
RSV
OPERATING FLOOR
C
L
MSV&GV
C
L
C
L
RSV
SEATING PLATE
FOR LP-1 TURBINE
DETAIL "E"
(AXIAL)
BOLT
EYE BOLT
0.02~ 0.04
CLEARANCE
0.02~ 0.04
EYE BOLT
EYE BOLT
EYE BOLT
(EACH SIDE)
CLEARANCE
0.02~ 0.04
(EACH SIDE)
0.02~ 0.04
CLEARANCE
CLEARANCE
0.02~ 0.04
(EACH SIDE)
CLEARANCE
EYE BOLT
(EACH SIDE)
CLEARANCE
0.02~ 0.04
iEACH SIDE j
SEATING PLATE
FOR EXCITER
GENERATOR CASING
EYE BOLT
GENERATOR CASING
VIEW "F"
VIEW "H"
VIEW "G"
SEATING PLATE
FOR EXCITER
SEATING PLATE
FOR LP-2 TURBINE
SEATING PLATE
FOR GENERATOR
"F"
BOLT
SEATING PLATE
FOR LP-2 TURBINE
"G"
GROUT
GROUT
GROUT
GROUT
BOLT
OPERATING FLOOR
BOLT
GROUT
GROUT
GROUT
SEATING PLATE
FOR LP-1 TURBINE
c
c
Rev.001
"I"
OPERATING FLOOR
MM-M05.01
LP-1 TURBINE
CASING
"H"
GROUT
VIEW "I"
LP-2 TURBINE
CASING
LP-2 TURBINE
CASING
OPERATING FLOOR
GROUT
LP-1 TURBINE
CASING
DETAIL "A"
DETAIL "B"
DETAIL "C"
DETAIL "D"
(GENERATOR)
(GEN~LP2)
(LP2~LP1)
(LP1~HP-IP)
MPTD-3-0210
FIGURE 2-11
Main Turbine
Mitsubishi
Chapter 2
GEN. SIDE
General
C
L OF MAIN OIL PUMP
PHASE DETECTOR
PICK UP
"A"
NO.6 BEARING
PEDESTAL
C
L OF THRUST BRG.
C
L OF NO.1 BRG.
C
L OF MAIN STEAM INLET
C
L OF REHEAT STEAM INLET
C
L OF IP EXHAUST
C
L
C
L OF NO.2 BRG.
OF NO.3 BRG.
C
L OF LP1 TURBINE
C
L OF NO.4 BRG.
C
L OF NO.5 BRG.
C
L OF NO.6 BRG.
C
L OF LP2 TURBINE
GOV. SIDE
HP PEDESTAL
ZERO SPEED
& SPEED PICK UP
NOS.4&5 BEARING
PEDESTAL
ECCENTRICITY
PICK UP
NOS.2&3 BEARING
PEDESTAL
ROTOR POSITION
PICK UP
ROTATION
OPERATING FLOOR
CENTERING BEAM
LOCATING PIN
CENTERING BEAM
WASHER
BOLT
BUSHING
NUT
SPHERICAL
WASHER
REAMER
STUD BOLT
NOS.2&3 BEARING
PEDESTAL
HP PEDESTAL
SPHERICAL WASHER
STUD BOLT
SPACER
BOLT
TIE BEAM
LP2 OUTER
CASING
REAMER
STUD BOLT
WASHER
SPACER
BUSHING
NUT
BUSHING
NUT
SPACER
LOCATING PIN
DETAIL "B"
"B"
MPTD-3-0211
MM-M05.01
Rev.001
VIEW "A"
FIGURE 2-12
Main Turbine
Mitsubishi
Chapter 2
General
5
11
13
14
3
1
4
18
12
"G"
28
27
10
29
10
29
12
H
9
24
13
B
10
F
VIEW A
SECTION B-B
10
VIEW C
VIEW E
E
4
27
26
27
13
13
14
14
C
18
18
25
18
23
22
17
21
VIEW D
19
LOCATING PIN
20
SET SCREW
21
BASE PLATE
22
GREASE PIPE
23
CENTERING BEAM
24
OIL STRAINER
25
PLUG
26
NAMEPLATE
27
INSPECTION COVER
28
BOLT
29
NUT
16 15
VIEW F
SECTION X-X
20
27
28
1
8
Rev.001
19
MM-M05.01
SECTION H-H
DETAIL "G"
FIGURE 2-13
Main Turbine
Mitsubishi
HP PEDESTAL ARRANGEMENT
2-46
General
MM-M05.01
Rev.001
Chapter 2
FIGURE 2-14
Main Turbine
Mitsubishi
Chapter 2
General
8
GEN. SIDE
GOV. SIDE
3
4
10
6
1 2 3
8
4 5 6 7
8 9
1
2
3
4
5
6
7
8
MM-M05.01
Rev.001
9
10
VIEW A
VIEW B
HP-IP ROTOR
HPT ROTATING BLADES
IPT ROTATING BLADES
RATEAU STAGE BLADE
STUB EXTENSION SHAFT
MOP IMPELLER
BALANCING HOLE
STEPPED SURFACES
FOR ROTOR GLAND SEALS
SERRATED BLADE ROOT
THRUST COLLAR
MPTD-3-0214
FIGURE 2-15
Main Turbine
Mitsubishi
Chapter 2
General
GEN. SIDE
GOV. SIDE
A
4
1
2
3
4
5
6
LP1 ROTOR
ROTATING BLADE
SERRATED BLADE ROOT
BALANCING HOLE
STUB
STELLITE STRIP
MM-M05.01
Rev.001
93
VIEW A
VIEW B
MPTD-3-0215
FIGURE 2-16
Main Turbine
Mitsubishi
Chapter 2
General
GEN. SIDE
GOV. SIDE
A
4
1
2
3
4
5
6
LP2 ROTOR
ROTATING BLADE
SERRATED BLADE ROOT
BALANCING HOLE
STUB
STELLITE STRIP
MM-M05.01
Rev.001
93
MPTD-3-0216
VIEW A
VIEW B
FIGURE 2-17
Main Turbine
Mitsubishi
Chapter-2
General
5
8
7
2
1
2
3
4
5
6
7
8
SECTION A-A
BALANCE BLOCK
SPRING RETAINER
SET PIN
SPRING
SPRING
SET SCREW
MACHINE SCREW
OVERSPEED TRIP WEIGHT
MM-M05.01
Rev.001
MPTD-4-0217
FIGURE 2-18
Main Turbine
Mitsubishi
2-51
Chapter 2
General
11
7
15
6
14
4
12
13
3
10
5
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Rev.001
MM-M05.01
MPTD-3-0218
FIGURE 2-19
Main Turbine
Mitsubishi
Chapter 2
General
GOV. SIDE
GEN. SIDE
PACKING STRIP
STEAM
IN
NOZZLE
NOZZLE BLOCK
SEAL STRIP
No.2 HP STATIONARY
BLADE RING
SET SCREW
AT HORIZONTAL JOINT
(IC TO 9C)
"E"
STEAM
OUT
ROTATING BLADE
HP-IP ROTOR
A
2C
1C
1S
2S
3S
4S
7C
6C
5C
4C
3C
5S
6S
9C
8C
7S
8S
9S
LOCK SCREW
STATIONARY BLADE
LOCK SCREW
A-A
SECTION C-C
AT HORIZONTAL JOINT
ROOT
LOCK SCREW
LAST BLADE
GROOVE
C
SECTION B-B
MM-M05.01
Rev.001
CAULKING STRIP
DETAIL "E"
DETAIL "D"
MPTD-3-0219
FIGURE 2-20
Main Turbine
Mitsubishi
Chapter 2
GEN. SIDE
General
GOV. SIDE
ROTATING BLADE
IP BLADE RING
SET SCREW
AT HORIZONTAL JOINT
(IC TO 8C)
SEAL STRIP
ROTATING BLADE SHROUD
PACKING STRIP
RETAINING PIN
LAST BLADE
A
STEAM
OUT
8S
8C
7S
STEAM
IN
7C
6S
6C
5S
5C
4S
4C
3S
3C
2S
2C
1S
1C
LOCK SCREW
NO.1 DUMMY RING
SECTION B-B
SEAL STRIP
ROTOR BALANCING
PLUG HOLE
SET SCREW
AT HORIZONTAL JOINT
MM-M05.01
Rev.001
SERRATED ROOT
DETAIL "C"
A-A
MPTD-3-0220
FIGURE 2-21
Main Turbine
Mitsubishi
2-54
Chapter 2
GEN. SIDE
General
GOV. SIDE
ROTATING BLADE
STATIONARY BLADE BASE
STEAM CHAMBER
INNER CASING
ROTATING BLADE
PACKING STRIP
LOCKING STRIP
5R
STATIONARY BLADE
LP BLADE RING
SEAL STRIP
STEAM
IN
FLOW GUIDE
STELLITE STRIP
STUB
7R
7C
7C
7R
LOCKING PIECE
LOCKING PIECE
6R
VIEW X-X
6C
6C
5R
5C
4R
4C 3R 3C
2R 2C 1R 1C
4C
1C 1R 2C 2R 3C3R
4R
5C
6R
5R
LOCKING PIECE
LP ROTOR
C
CAULKING PIECE
SHAFT GLAND
VIEW A-A
SERRATED
VIEW C-C
MPTD-3-0221
MM-M05.01
Rev.001
CAULKING PIECE
FIGURE 2-22
Main Turbine
Mitsubishi
2-55
Chapter 2
No.2 HP STATIONARY
BLADE RING
No.1 HP STATIONARY
BLADE RING
LOCKING STRIP
STAGES 1S~3S
General
LOCKING STRIP
STAGES 4S~7S
STAGES 8S~9S
STATIONARY
BLADE DIAPHRAGM
LOCKING STRIP
SEAL STRIP
SEAL STRIP
SEAL STRIP
LOCKING STRIP
STAGES 4C~7C
STAGES 8C~9C
MM-M05.01
Rev.001
STAGES 1C~3C
LOCKING STRIP
MPTD-3-0222
FIGURE 2-23
Main Turbine
Mitsubishi
2-56
Chapter 2
General
LOCKING STRIP
SEAL STRIP
ROTATING BLADE
STAGES 1S~8S
STAGES 4C~8C
STAGES 2C~3C
MPTD-3-0223
MM-M05.01
Rev.001
STAGES 1C
FIGURE 2-24
Main Turbine
Mitsubishi
2-57
Chapter 2
General
INNER CASING
LOCKING STRIP
SEAL STRIP
SEAL STRIP
SEAL RING
STATIONARY
BLADE SHROUD
SEAL STRIP
SEAL STRIP
LOCKING STRIP
LOCKING STRIP
LP ROTOR
MPTD-3-0224
MM-M05.01
Rev.001
FIGURE 2-25
Main Turbine
Mitsubishi
2-58
Chapter 2
GEN. SIDE
GOV. SIDE
27
10
D R
N SE
LA N
G DE
TO O N
C
19
10
13
27
19
T
C OG
O
N LA
D N
EN D
SE
R
General
14
24
15
"E"
D
C-C
"H"
19
10
HORIZ. JOINT
28
C
p
24
28
12
11
20
D-D
1
7
"F"
3
HORIZ. JOINT
5
9
A
18
A-A
G-G
1
25
26
20
23
8
1
7
5
Rev.001
PRESSURE
SUPPLY SLOT
20
21
22
27
16
MM-M05.01
28
22
21
HORIZ. JOINT
17
20
B-B
13
DETAIL "H"
DETAIL "F"
DETAIL "E"
24
MPTD-3-0225
FIGURE 2-26
Main Turbine
Mitsubishi
Chapter 2
11
12
25
25
11
19
6
22
12
C
2
18
20 21
13
ROTATION
General
ROTATION
10
23
14
1
5
26
14
26
14
24
26
B
4
3
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
MPTD-3-0226
MM-M05.01
Rev.001
21
7
20 19
17 16
15
VIEW A
15
18
SECTION B-B
28
27
SECTION C-C
26
26
DETAIL E
2
DETAIL H
15
28
DETAIL G
28
12 11
24
26
27
26
3
22
SECTION D-D
27
No.3 PAD
No.4 PAD
VIEW G
FIGURE 2-27
Main Turbine
Mitsubishi
VIEW F
2-60
Chapter 2
General
B
4
8
7
21
15
10
A
9
F
4
19
F
6
VIEW E
SECTION C-C
E
B
11
14
23
12
16
25
21
26
24
22
4
17
1
C
SECTION F-F
18
DETAIL D
25
24
17
12
17
E
3
21
Rev.001
20
13
E
B
MM-M05.01
SECTION A-A
11
2
11
12
23
SECTION B-B
19
20
SECTION E-E
FIGURE 2-28
Main Turbine
Mitsubishi
21
2-61
Chapter 2
General
33
5
19
18
34
DETAIL H
17
30
28
10
24
25
29
31
32
13
VIEW F
DETAIL E
27
GEN. END
37
10
GOV. END
12
25
1
1
14
20
24
15
5
6
29
15
27
ROTATION
28
4
22
LUBE OIL
OUTLET
35
16
36
R
O
TA
2G
O
V
2G
O
V
TI
O
N
23
G
O
V
G
O
V
36
11
MM-M05.01
Rev.001
21
26
9
22
LU
BE
13
O
IL
13
E
IN
LE
T
37
VIEW G
26
SECTION A-A
MPTD-3-0228
Main Turbine
Mitsubishi
SECTION B-B
FIGURE 2-29
2-62
24
X
"E"
25
OIL
IN
OIL
IN
Chapter 2
General
10
22
20
"E"
26
13
2
#2-2
#2-1
#1-1
27
ROTATION
#2-5
#1-8
#2-7
#1-3
G
IN INE
AR L
BE PLIT
S
#2-4
ROTATION
#2-8
SP BEA
L I T RI
LINNG
E
#2-3
#1-2
#1-7
#2-6
#1-6
#1-4
D
D
#1-5
5
1
23
16
11
21
2
5
19
12
15
B-B
19
17
A-A
OIL
OUT
18
X-X
15
8
2
4
5
MM-M05.01
Rev.001
22 23
VIEW "E"
20 21
20 21 22 23
D-D
C-C
11
MPTD-3-0229
FIGURE 2-30
Main Turbine
Mitsubishi
2-63
Chapter 2
GEN. SIDE
General
GOV. SIDE
11
10
16
17
ROTATION
PEDESTAL BASE
HP-IP ROTOR
LP1 ROTOR
NO.2 BEARING
NO.3 BEARING
SPACER
COUPLING GUARD
COUPLING COOLING
OIL SPRAY LINE
10
11
12
13
BASE PLATE
14
15
16
17
THERMAL SHIELD
18
INSPECTION COVER
19
19
MM-M05.01
Rev.001
MPTD-3-0231
FIGURE 2-31
Main Turbine
Mitsubishi
2-64
Chapter 2
General
10
11
PEDESTAL BASE
LP1 ROTOR
LP2 ROTOR
NO.4 BEARING
NO.5 BEARING
SPACER
COUPLING GUARD
COUPLING COOLING
OIL SPRAY LINE
10
11
12
13
14
PEDESTAL COVER
15
PEDESTAL COVER
16
BASE PLATE
17
INSPECTION COVER
18
19
13
12
MM-M05.01
Rev.001
MPTD-3-0232
FIGURE 2-32
Main Turbine
Mitsubishi
2-65
Chapter 2
General
PEDESTAL BASE
LP2 ROTOR
GENERATOR ROTOR
NO.6 BEARING
SPACER GEAR
COUPLING GUARD
COUPLING COOLING
OIL SPRAY LINE
10
11
12
NUT COVER
13
BASE PLATE
14
15
16
OIL RETAINING RING
18
INSPECTION COVER
11
Rev.001
MM-M05.01
17
MPTD-3-0233
FIGURE 2-33
Main Turbine
Mitsubishi
2-66
General
MM-M05.01
Rev.001
Chapter 2
FIGURE 2-34
Main Turbine
Mitsubishi
2-67
Chapter 2
General
SPRING HOUSING
BONNET
SUPPORT
INTERCEPTOR VALVE
STEM LEAKOFF
SPRING HOUSING
STEAM OUTLET
( TO IP TURBINE )
Rev.001
RSV ACTUATOR
MM-M05.01
MPTD-3-0235
FIGURE 2-35
Main Turbine
Mitsubishi
2-68
General
MM-M05.01
Rev.001
Chapter 2
FIGURE 2-36
Main Turbine
Mitsubishi
2-69
Chapter 2
2
GEN. SIDE
General
13
GOV. SIDE
6
TO EARTH TERMINAL
11
A
9
7
4
6
1
13
8
TO EARTH
TERMINAL
B
10 11 12
ROTATION
10
9
60
GENERATOR ROTOR
NO.4 BEARING PEDESTAL COVER
PEDESTAL END COVER
OIL BAFFLE
LP CASING BASE PLATE
BRACKET
SUPPORT
SPRING
BRUSH
BOLT
U NUT
WASHER
FITTING BOLT
EARTH TERMINAL
LP CASING
12
C
L OF TURBINE
C
L OF TURBINE
VIEW A
GEN. SIDE
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
11
12
GOV. SIDE
11
FROM GROUNDING
DEVICE
7
C
L OF TURBINE
15
14
10 12
15
14
EARTH NET
SECTION B-B
SECTION D-D
MM-M05.01
Rev.001
MPTD-3-0237
Main Turbine
Mitsubishi
FIGURE 2-37
2-70
Chapter-2
General
MM-M05.01
Rev.001
A-A
LP OUTER CASING
GUARD
DIAPHRAGM
BOLT
MPTD-4-0238
FIGURE 2-38
Main Turbine
Mitsubishi
BREAKABLE DIAPHRAGM
2-71
Chapter 2
DOOR
STAIR WAY
General
TERMINAL BOX
TURBINE
ENCLOSURE
TURBINE
ENCLOSURE
DOOR
DOOR
DOOR
STAIR WAY
STAIR WAY
"B"
DOOR
VIEW "A"
TERMINAL BOX
TURBINE
ENCLOSURE
VIEW "C"
"A"
GEN. SIDE
GOV. SIDE
TURBINE ENCLOSURE
"C"
"D"
ROTATION
OPERATING FLOOR
VIEW "B"
TURBINE ENCLOSURE
DOOR
DOOR
SOUNDPROOF
INSULATION
TURBINE ENCLOSURE
TURBINE ENCLOSURE
SOUNDPROOF
INSULATION
WELD
WELD
OPERATING FLOOR
OPERATING FLOOR
OPERATING FLOOR
Rev.001
MM-M05.01
TEST DOOR
VIEW "D"
GUIDE BOLT
FITTING BOLT
DOOR
DOOR
CHANNEL
E-E
CHANNEL
F-F
G-G
MPTD-3-0239
FIGURE 2-39
Main Turbine
Mitsubishi
2-72
Chapter-3
Specifications
C h a p t er
3 Specifications
TABLE 3-1
MAIN TURBINE
Subject
Specifications
Equipment number
HP-IP Turbine
03MAA31AE1
LP1 Turbine
03MAC11AE1
LP2 Turbine
03MAC11AE2
Quantity
Turbine
Steam
Conditions
Blading
1
Model
Type
TC4F-35.4
Speed
3000 rpm
Direction of Rotation
Rated Output
865 900 kW
Inlet Pressure
24.5 MPa(a)
@ MSV inlet
Inlet Temperature
538C
@ MSV inlet
4.7 MPa(a)
@ RSV inlet
566C
@ RSV inlet
Exhaust Pressure
0.0079 MPa(a)
@ Condenser top
No. of Extractions
HP turbine
1 x 1 Row of Rateau
1 x 9 Rows of Reaction
IP turbine
1 x 8 Rows of Reaction
LP1/LP2 turbine
2 x 7 Rows of Reaction
Critical speed
Blade Height
Tip diameter
3537.6 mm
HP-IP
LP1
1700~1750 rpm
st
1150~1550 rpm
nd
2400~2650 rpm
st
1300~1500 rpm
nd
2400~2550 rpm
1
2
LP2
1
2
MM-M05.01
Rev.001
Main valves
Main Turbine
Mitsubishi
MSV
Horizontal plug
GV
Vertical plug
RSV
ICV
Vertical plug
3-1
Chapter-3
Specifications
Continued
TABLE 3-1
MAIN TURBINE
Subject
MM-M05.01
Rev.001
Weights
Main Turbine
Mitsubishi
Specifications
HP-IP Rotor
42.65 ton
65.0 ton
9.24 ton
10.25 ton
1.19 ton
1.71 ton
6.71 ton
5.32 ton
2.44 ton
3.59 ton
1.72 ton
2.98 ton
11.25 ton
1.19 ton
HP Pedestal
6.55 ton
LP1 Rotor
61.46 ton
LP2 Rotor
60.86 ton
38.4 ton
19.51 ton
18.54 ton
3.73 ton
3.96 ton
2.38 ton
3.67 ton
0.5 ton
MSV/GV Set
35.6 ton
RSV/ICV Set
29.8 ton
4.9 ton
4.9 ton
3-2
Chapter 4
Preventive Maintenance
C h a p t er
4 Preventive Maintenance
Preventive maintenance is carried out to avoid or minimize the possibility of failure or
deterioration of equipment performance. This requires a constant effort from
maintenance staff to ensure that the Unit is available on demand.
There are two categories of preventive maintenance, Routine Maintenance and Annual
Outage Maintenance. Routine maintenance helps to reduce the possibility of outage
and hence the downtime of machinery. Annual outage maintenance is required to
maintain the internal components of the installed equipment.
Though vendor/manufacturers recommendations provide a good basis for the
provision of a preventive maintenance schedule, the frequency and other details should
be updated from time to time based on the practical experience and actual field
feedback gathered through inspection and normal operation of the equipment/plant.
Consideration of these site related specific issues will make the preventive
maintenance more effective.
4.1
Prerequisites
The necessary prerequisites for the preventive maintenance of the main turbine
are as follows:
4.1.1 Scheduling
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
4-1
Chapter 4
Preventive Maintenance
MM-M05.01
Rev.001
Prior to the commencement of actual work, the person carrying out the
work is to make a safety check based on the above method statement
and also use his own judgment to ensure that the equipment and the
prevailing working conditions are safe. During maintenance work,
every employee should follow the safe working procedures detailed in
the method statement.
Main Turbine
Mitsubishi
4-2
Chapter 4
Preventive Maintenance
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
4-3
Chapter 4
4.2
Preventive Maintenance
Routine Maintenance
The purpose of routine maintenance is the implementation of the preventive
maintenance program on a day-to-day basis through a planned and correctly
executed inspection. The routine maintenance activities are very important in
that if they are properly carried out, they will enhance equipment reliability. As a
result, good routine maintenance activities may help in cost reduction in the long
run through minimization of equipment downtime.
Cleaning is an important and necessary maintenance activity to prevent the
ingress of foreign material. (Summarized major routine activities are shown in
Table 4-1).
4.2.1 Preparation
a)
b)
Documentation
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
4-4
Chapter 4
Preventive Maintenance
Beware of any noise inside the turbine enclosure and near the
steam admission valves. There can be invisible superheat
steam leakage which can cause burn injuries.
CAUTION
Wear ear protection when near a running machine.
CAUTION
Take utmost care while performing inspection near the main oil
tank, oil lines and oil pumps. Oil-soaked floor will be extremely
slippery and susceptible for injuries.
Rev.001
A daily check should be carried out to check for abnormal noises and
vibration, and to note any trend deterioration. These values should be
correlated with those for the operational parameters, as this may help to
identify the source of a potential problem.
MM-M05.01
The sliding surfaces around and under the turbine bearing pedestals
should be maintained in good condition. Regular lubrication is required
to ensure that the pedestals and turbine casings can move freely when
the turbine expands or contracts.
Main Turbine
Mitsubishi
4-5
Chapter 4
Preventive Maintenance
Governing valves
Interceptor valves
A thrust wear trip test should be carried out once or twice a year
off-load either on turning gear or at complete rest.
A turbine solenoid trip test should be performed once or twice a year,
off-load on turning gear or at complete rest.
MM-M05.01
Rev.001
An oil pump auto start test should be performed monthly to check the
setting value of the following pumps:
Main Turbine
Mitsubishi
4-6
Chapter 4
Preventive Maintenance
Oil leakage from the oil piping and main oil tank
Lube oil, sampling from the main oil tank bottom and the oil
purifier/conditioner outlet.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
4-7
TABLE 4-1
No.
1
Description
Casing and Rotor
Check Method
Check Reference
Action to be Taken
(if beyond acceptable
limit)
Remarks
All to be normal
Report to supervisor
Turbine supervisory
instruments
Installed instruments
Report to supervisor
Installed instruments
(Alarm)
(Trip)
Report to supervisor
Double amplitude
Differential expansion
Installed instruments
Limits:
Abnormal High Trip (Rotor
long):
> +20 mm
Report to supervisor
Differential expansion
readings measured near No. 8
bearing. Manual Trip
Recommended.
125 m
250 m
Recommended
Maintenance
Frequency
Daily
Installed instruments
Report to supervisor
Eccentricity
Installed instruments
Normal < 50 m
Alarm > 75 m
Report to supervisor
Rotor position
Installed instruments
Limit:
Report to supervisor
Installed instruments
Visual, audible
Alarm:
> 0.9 mm
Alarm:
> 1.0 mm
During every
turbine rolling
Daily
Report to supervisor
Daily
No leakage
Report to supervisor
Daily
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
4-8
No.
1
Description
Casing and Rotor
(Continued.)
Check Method
Installed instruments
Check lubrication
Bearing
MM-M05.01
Main Turbine
Mitsubishi
Installed instruments
Check Reference
Limits:
Action to be Taken
(if beyond acceptable limit)
Report to supervisor
Remarks
Lubricant to be evident
Report to supervisor
Replace over lube oil
strainers
Limits (Alarm):
Thrust bearing : > 99C
Journal bearing: > 107C
No leakage
Recommended
Maintenance
Frequency
Daily
Every 3 to 6
months
Daily
Visual
Visual
Flow normal
Normal operation
Report to supervisor
Installed instruments
Rev.001
Visual
4-9
No.
4
Description
Gland Steam System
(cont.)
Check Method
Check Reference
Action to be Taken
(if beyond acceptable limit)
Remarks
Recommended
Maintenance
Frequency
Visual
Installed
instruments
Temperature between
120C and 180C
Daily
No oil leakage
Visual
No leakage
Daily
Visual
Correct Engage /
Disengage position
Report to supervisor
Movement should be
free
Report to supervisor
Governing valve
Stem freedom
test
Visual
No sticking
Visual
Movement should be
free
Turning gear
Interceptor valve
Report to supervisor
Weekly
Daily
To be carried out at
following load range
35~60% or 72~75% load
Pay special attention to
valve sticking
Weekly
Daily
No sticking
Valve closing during turbine
tripping
Visual
No sticking
Report to supervisor
Visual and
audible
No leakage
Report to supervisor
Visual and
audible
No abnormality
Report to supervisor
Installed
instruments
At every turbine
trip
MM-M05.01
Rev.001
Daily
Main Turbine
Mitsubishi
4-10
Description
Check Method
Visual
Check Reference
No sticking
Extraction non-return
valve
Protective Devices
Follow prescribed
procedures
Follow prescribed
procedures
MOST, EOST
Report to supervisor
Visual
Visual
No leakage
Installed
instruments
Rev.001
Monthly
No abnormality
Daily
Daily
Daily
MM-M05.01
Audible, visual
and touch
Vacuum Unloader
operates at < 81.3 kPa and
released at > 85.4 kPa
At NOL
Recommended
Maintenance
Frequency
Weekly
Remarks
Installed
instruments
Action to be Taken
(if beyond acceptable limit)
Main Turbine
Mitsubishi
4-11
Description
Main oil tank
Lube oil cooler
Lube oil piping
(Continued)
Check Method
Sample analysis
in laboratory
Check Reference
Acceptable condition
Visual
Remarks
High Alarm:
At Normal operation:> 50C
> 40C
Satisfactory control
Recommended
Maintenance
Frequency
At Turning :
Oil temperature control valve
Action to be Taken
(if beyond acceptable
limit)
Daily
Daily
Make necessary
adjustment
Monthly
Advise supervisor
Visual
No leakage
Installed
instruments
Installed
instruments
Visual
No debris
Under operators
supervision using
Test Block
Set point
AOP: < 0.75 MPa
TOP: < 0.075 MPa
EOP: < 0.065 MPa
Daily
Daily
Daily
At shutdown
EOP set point should be
slightly lower than low
lube oil pressure trip set
point
Monthly
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
4-12
4.3
Outage Maintenance
The purpose of routine outage maintenance is the implementation of a
preventive maintenance program on a yearly basis according to a planned and
correctly executed maintenance work program accompanying necessary
inspections. Such outage maintenance activities are very important because
such maintenance will extend the service life and improve the reliability of the
steam turbine, if properly performed.
Major activities related to annual outage maintenance are as follows:
(Summarized major activities for annual outage maintenance are also shown in
Table 4-3).
4.3.1 Preparation
a)
b)
Documentation
Refer to Subsection 4.2.1 b), Documentation.
Records are to be maintained to record information on spares
and consumables used. These records will be used for future
reference and spare parts replenishment.
On completion of annual outage maintenance work, the steam
turbine is monitored for correct operation and maintenance data
logging. This will help to determine the correct intervals of
preventive maintenance activities to ensure optimum plant
availability. The correct recording of the findings during
inspection will provide a valuable document for future reference.
MM-M05.01
Rev.001
4-13
After the first overhaul, perform the overhaul as shown in Table 4.2
which shows the standard intervals of inspections for respective parts
and equipment, and how they are classified.
However, it is recommended that the maintenance program is arranged
so that all equipment can be inspected at least once within 4 years.
The major activities involved in the outage maintenance are detailed
below. Assembly and reassembly of the various parts is detailed in
Chapter 5.
Preparation
1
Shutdown the turbine and when it has come to rest start the
jacking oil pump and the turning gear. Continue operation of the
lubricating oil pumps. When the highest first stage metal
temperature is below 170C, the turning gear can be stopped.
However, dependent on the work content and the intended
duration of the outage, the actual stoppage of the turning gear,
lubricating oil pump, seal oil pump, etc. is a joint operational and
maintenance department decision.
CAUTION
Wear proper goggles and face masks when working on the
insulation. Insulation material is harmful to the respiratory
system.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Remove the LP1 and LP2 rotor Gov End and Gen End upper half
gland casings. Inspect the gland seal rings and seal strips for
damage or erosion.
4-14
Check the welded portion of the internal stays and ribs and
perform a dye penetrant test on the welded joints.
Disassemble the LP1 and LP2 inner casing covers and visually
check for deformation and leakage from the horizontal joint
flanges. Remove any scale from the stationary blades and
perform a dye penetrant test to check for cracks. Any
countermeasure for damage should be decided by the inspection
results.
Disconnect the flanges at the hot reheat steam inlet piping to the
IP turbine.
Remove the HP-IP rotor Gov End and Gen End upper half outer
gland casings and inspect the gland seal ring segments and seal
strips for wear or damage.
10
Remove the HP-IP rotor inner gland upper casings from both ends
and inspect the gland seal ring segments and seal strips for wear
or damage.
Rev.001
MM-M05.01
Main Turbine
Mitsubishi
Remove the LP1 and LP2 turbine outer casing covers and
perform the following checks:
4-15
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
11
12
Visually check for cracking and erosion of the nozzle block and
the nozzles. Perform a dye penetrant test. Check for deterioration
of bolts using ultrasonic and dye penetrant tests. Visually check
for, and measure any wear and deformation on the slip-joint seal
rings and the retaining rings.
13
14
Check visually for any damage to the bolt thread and replace
if damaged.
15
16
Remove the MOP cover to check the impeller and casing seal
rings. Perform a dye penetrant test to check for damage to the
MOP impeller. Inspect the seal rings and wear rings for any
damage or wear.
4-16
17
Dismantle the upper half of the thrust bearing case, carrier rings,
liners, etc. Remove and inspect all thrust pads and other internal
components for damage or wear. Check the thrust collar for any
crack, dent, scratch or damage.
18
19
Measure and record rotor deflection for the HP-IP, LP1 and LP2
rotors.
20
Remove the LP1 and LP2 rotors and perform the following
checks:
MM-M05.01
Rev.001
21
Main Turbine
Mitsubishi
Visually check for erosion of the stellite shields on the last row
blades and perform a dye penetrant test.
22
Inspect the turning gear and check the contact between the gears
of the turning gear drive.
23
Remove all lower half inner and outer turbine gland casings and
check the gland seal rings, seal strips, springs, etc. for any wear
or damage.
24
4-17
25
26
Thermal shield
Disassemble and inspect the LP1 and LP2 lower half casings
including:
Inner casings
Steam chambers
Blade rings
Disassemble the oil cooler end frames and the plates. Check the
plates for any damage and scale deposit and repair or clean as
necessary. Inspect and replace any damaged gaskets.
Rev.001
MM-M05.01
Main Turbine
Mitsubishi
Drain oil from the main oil tank and perform the following checks:
Dump valve
Servo valve
Accumulator
Remove and check for any blockage in the E/H oil filters.
Check the emergency trip oil line for any blockage of the orifice.
4-18
Disassemble and check the E/H oil cooler tubes for blockage and
cleanliness.
Disassemble and check the E/H oil pump relief valves for any
internal damage and seat contact.
The details of the lubrication and control oil systems are fully explained
in the Turbine Control and Lubrication Oil System operation manual,
OPM - 08 and the respective equipment vendor manuals.
Turbine Reassembly
Note
All parts are to be thoroughly cleaned before reassembly.
Assemble and replace all lower half bearings and confirm that the
contact area between the bearing spherical keys and the housing
exceeds 75% of the total area.
Gland casing
Inner casing
Steam chamber
Blade ring
Note
Straighten and adjust or replace any seal strip if found
worn or damaged.
Note
The LP1 and LP2 rotors should be positioned in their
respective K positions before rotor radial and axial
Rev.001
Note
MM-M05.01
Main Turbine
Mitsubishi
4-19
Inner casing
Thermal shield
IP blade ring
Note
Straighten and adjust or replace any seal strip if found
worn or damaged.
Note
Re-weld the impulse chamber drain and pressure
sensing pipes cut during disassembly.
Note
The HP-IP rotor is to be positioned in the K position
before rotor radial and axial clearances are measured.
Before replacing the upper half sections of the inner casing, steam
chamber and inner flow guide ring for the LP1 and LP2 turbines,
measure the top and bottom clearances between the LP rotor and
the blades and other internal parts (refer to clearance drawings).
Check that there are no foreign materials inside of the casing.
Assemble the upper half sections for the LP1 and LP2 turbines
including:
Rev.001
MM-M05.01
Main Turbine
Mitsubishi
Inner casing
Steam chamber
Blade ring.
Check the top and bottom clearances between the HP-IP turbine
parts and the rotor blade seals etc. (refer to the clearance table).
Check that no foreign materials remain inside the casing.
4-20
Assemble the upper half sections for the HP-IP turbine including:
Inner casing
IP blade ring
Thermal shield
10
Check all bolt holes and bolts and the horizontal joint flange faces.
Reassemble the HP-IP, LP1 and LP2 outer casing covers,
including the outer gland seals. Perform non-destructive testing
(NDT) at any suspect areas.
11
Set the thrust bearing ensuring that the clearance between the
thrust collar and the thrust bearing is within the design value of
0.250.38 mm, but try to obtain a clearance of 0.31 mm.
Note
Thrust bearing should be set with the HP-IP rotor at the
K position.
Replace the upper halves of the turbine bearings. Check the oil
clearance in each bearing, as per the procedure indicated in the
mechanical maintenance manual, M-05.04, Turbine Bearings and
Thrust Bearing.
13
Assemble the MOP upper half casing. Ensure that the oil seal ring
and wear ring clearances in the MOP are within design values.
For details of clearance, refer to the mechanical maintenance
manual M05.06, Turbine Main Oil Pump.
14
Align the LP2 ~ generator, LP1 ~ LP2 and LP1 ~ HP-IP couplings
as per the procedure described in the mechanical maintenance
manual M05.05, Turbine Couplings and Alignment.
15
Connect the couplings between the HP-IP to LP1, LP1 to LP2 and
LP2 to generator rotors. Ensure that the coupling bolts and nuts
are installed according to their match marks. Tighten the bolts
according to the procedure and values specified in the mechanical
maintenance manual, M05.05, Turbine Couplings and Alignment.
Replace the coupling guards and the coupling cooling oil lines.
16
Replace the turning gear and check the drive gear backlash. For
details, refer to the mechanical maintenance manual M05.07,
Main Turbine Turning Gear.
MM-M05.01
Rev.001
12
Main Turbine
Mitsubishi
4-21
17
18
Reassemble the bearing keep for No.1 bearing and all pedestal
covers. Ensure that the clearance/interference between pedestal
covers and spherical seat of the bearings, and the clearance of
the pedestal oil retaining rings are within design. Refer to the
clearance tables in the mechanical maintenance manual M05.04,
Turbine Bearings and Thrust Bearing.
19
20
Install new gaskets and connect the main steam and reheat steam
pipes with the HP and IP turbine inlet pipes which were
disconnected during disassembly.
Reassemble the oil cooler and ensure that all bolts are tightened
properly.
Fill the main oil tank to the normal working level (NWL).
Note
The oil purifier should be kept in service during oil
flushing. For details of the oil purifier, refer to the oil
purifier vendor manual.
Adjust the control oil system. Refer to control oil pressure setting
instruction for oil pressure setting, servo-valve adjustment,
pressure switch and limit switch settings, and interlock settings.
Adjust and test the turbine protective devices and perform a Unit
interlock test. (Refer to the control oil pressure setting instructions
and the interlock sequence diagram).
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
4-22
CAUTION
Wear proper goggles and face masks when working on the
insulation. Insulation material is harmful to the respiratory
system.
4
Vibration measurement.
TABLE 4-2
Class
C
Intervals
1 year
(Routine maintenance)
2 years
(Minor overhaul)
4 years
(Major overhaul)
Turbine proper
E/H oil system
Piping
MM-M05.01
Rev.001
8 to 10 years
Diagnostic investigation for
aging deterioration
Turbine rotors
Turbine casings
Steam admission valves
Main Turbine
Mitsubishi
4-23
TABLE 4-3
No
Description
Steam
Turbine
Valves
Major Check
Item
Remark
Interval
Turbine casing
Turbine rotor
Inspection of blades
Inspection of clearance
Blade ring
Every 4 years
Dummy ring,
gland
Every 4 years
Deterioration check
Every 4 years
Bearing
Every 2 years
Turning gear
General inspection
Every 2 years
Overhaul inspection
Every 4 years
Alignment
Every 2 years
MSV
Inspection of valve
components
Every 2 years
Overhaul
Every 4 years
Suction
strainer
Every year
GV
Every 4 years
Investigate state of
deterioration
Every 4 years
RSV
ICV
3
E/H Oil
System
Line filter
Return filter
Replace elements
Every year
Earth filter
Replace elements
If neutralization value
cannot be kept under
0.3 mg KOH/g, replace
elements
Every 6
months
MM-M05.01
Rev.001
Back up filter
Main Turbine
Mitsubishi
Micro
separator
Every year
Polishing filter
Replace elements
Differential
pressure
switch
Replace
Every 4 years
Unloading
valve
Every 4 years
Check valve
Every 4 years
Relief valve
Every 4 years
If differential pressure is
over 0.34 MPa, replace
elements
4-24
TABLE 4-3
No
3
Description
Major Check
Item
Remark
Interval
E/H Oil
System
(Contd)
Oil coolers
Every 4 years
Stop valve
Every 4 years
E/H oil
accumulator
Accumulator
Every 4 years
Stop valve
Every 4 years
Hydraulic
cylinder
Every 4 years
Servo valve
Every 2 years
Every 4 years
Filter
Every year
Solenoid valve
Replace
Every 4 years
Dump valve
Every 4 years
Solenoid valve
Replace
Every 4 years
Check valve
Every 4 years
Pumps
Every 2 years
Relief valve
Every 2 years
Oil tank
Every 2 years
Oil cooler
Every 2 years
Every 4 years
Oil conditioner
Every 1 year
Control valves
Every 1 year
Instrument
Every 1 year
Actuator
Stop valve
Check valve
6
Solenoid
block
Lubricating
oil system
Instruments
Piping
Piping
Every 4 years
10
Insulation
Insulation
Every 4 years
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
4-25
Chapter 5
C h a p t er
5.1
Preparation
If HP-IP turbine disassembly becomes necessary, all associated
equipment must be mechanically and electrically isolated and an
authorized clearance and work permit must be in place prior to the start of
work. The following points must also to be considered when preparing for
disassembly and reassembly:
Take care to protect the turbine operating floor during steam turbine
overhaul. Place the steam turbine components and other materials
on a protective sheet such as aluminium, plywood or gasket spread
on the turbine floor for this purpose.
Rev.001
MM-M05.01
Main Turbine
Mitsubishi
5-1
Chapter 5
CAUTION
Spigot joints between the turbine stationary components
(such as outer and inner casings, blade rings, etc.) could bind
due to scale formation during operation under the high
temperature environment.
CAUTION
The binding mentioned above may require additional jacking
or crane load which could exceed the dead weight of the
concerned components as the components are separated or
lifted apart. This could cause surface damage such as seizure,
galling or scoring. Take due care and initiate any special
measures necessary when separating or lifting equipment, and
binding is apparent or suspected.
CAUTION
Personnel working inside the turbine should not carry any
loose items in the pockets and should take special care not to
drop tools or debris into the turbine.
CAUTION
Any surface irregularity or damage caused by the reasons
described above must be ground off smoothly, or
reconditioned by build-up welding and facing to reinstate the
original surface finish and clearance if any between mating
parts.
CAUTION
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-2
Chapter 5
b)
Disassembly
Refer to Figures 5-1 and E-2.
Note
Place the removed turbine components on the turbine operating
floor on protection sheets such as aluminium sheet, plywood or
gasket as per the overhaul plan shown in Appendix E. The
removed components may be placed as per the guide line
locations indicated in Figure E-2 or any other locations
convenient to the maintenance personnel.
Remove the fire extinguishing piping around the HP-IP turbine before
starting disassembly.
Label and identify all components as they are disassembled. Tag and
bag all hardware and fasteners with the associated component and
store in the designated area.
Remove insulation from the horizontal joint of the outer casing, the
gland casing area, main steam and hot reheat inlet flanges and the IP
turbine exhaust flange.
Remove the covers (upper half gland casings) from the HP-IP turbine
outer glands and remove the gland seal ring segments as described
in the mechanical maintenance manual M05.03, Gland Steam
Condenser System and GSC Exhaust Fan.
Remove the bolts and nuts from the main steam and reheat steam
inlet flanges to the HP-IP turbine. Refer to Figure 5-1 for details of
main steam and reheat steam piping flange locations.
MM-M05.01
Rev.001
5-3
Chapter 5
Note
Refer to the Bolt Heating Data in Appendix F to identify the bolts
and to determine the required heater type and size. The bolts
and/or studs on each side of the turbine have the same number
but are designated RS or LS. For the purposes of this procedure
only the bolt and/or stud number will be given. Remove the same
numbered bolt and/or stud from both sides of the turbine
simultaneously. The same procedure is to be followed when bolt
tightening during reassembly.
CAUTION
Take care not to touch the hot part. Contact with hot parts
could cause burns or other injury.
Using four bolt heaters (two on each side), heat the bolts in
accordance with Bolt Heater Instruction of Appendix I, avoid heating
adjacent bolts, and remove bolts from both the left and right sides of
the casing in the following sequence:
(i)
Rev.001
(i)
Install a safety hoist ring or an eye bolt and copper washer into
the nut to be removed.
MM-M05.01
(ii) Connect suitable lifting gear to the safety hoist ring and remove
the nut.
Main Turbine
Mitsubishi
5-4
Chapter 5
Note
Provide supports for the bolts with both top and bottom nuts,
while removing the top nuts.
Note
During operation of the turbine, oxides and deposits
accumulate between the mating surfaces of the casings. The
forces required to separate these surfaces may be noticeably
greater than those required to suspend the weight of the outer
casing cover.
Gradually operate the hydraulic jacks uniformly rotate the jack screws
to raise and separate the outer casing cover from the casing base.
CAUTION
Visually follow the motion of the outer casing cover while the
crane is hoisting. Do not overload the wire rope slings.
Tension the wire rope sling with the crane hook located over the
center of gravity of the outer casing cover.
Make a trial lift and adjust the lift so that the cover horizontal joint is
parallel to the base horizontal joint.
10 Evenly raise the outer casing cover in small increments until the cover
is clear of the stud bolts.
11 Lift the outer casing cover clear of the inner casing and transport it to
the lay-down area.
Note
Ensure that the openings left by the removal of the outer
casing cover are covered to prevent the entry of foreign
Rev.001
MM-M05.01
Main Turbine
Mitsubishi
5-5
Chapter 5
15 Remove the Gov End and Gen End inner gland casing upper halves
in accordance with the mechanical maintenance manual M05.03,
Gland Steam Condenser System and GSC Exhaust Fan.
Referring to Figure F-1, label all inner casing cover bolts and nuts
with their numbers provided in Appendix F and indicate RS (Right
Side) or LS (Left Side).
Note
Refer to the Bolt Heating Data in Appendix F to identify the
bolts and determine the required heater type and size
Using four bolt heaters (two on each side), heat the bolts in
accordance with Bolt Heater Instruction in Appendix I, avoiding
heating adjacent bolts, and remove bolts from both the RS and LS of
the casing in the following sequence:
(i)
Install safety hoist ring and copper washer into the nut to be
removed.
Using the jack screws provided raise the inner casing cover, approx.
10 mm.
Rev.001
Make a trial lift and adjust the turn buckle or the chain block to obtain
a level lift.
MM-M05.01
(ii) Connect suitable lifting gear to the hoist ring and remove the
nuts.
Raise the inner casing cover in small increments until the cover is
clear of the stud bolts.
Main Turbine
Mitsubishi
5-6
Chapter 5
10 Lift the inner casing cover clear of the No.1 dummy ring and transport
it to the lay-down area.
Note
Ensure that the openings exposed by removal of the inner
casing cover are protected.
Loosen and remove nuts from the studs at the horizontal joint of the
thermal shield at both the RS and LS.
Install eye bolts on the upper half thermal shield and connect the
lifting gear.
Using the jack screws provided raise the upper half thermal shield,
approx. 10 mm.
Rig and remove the thermal shield and transport it to the lay-down
area.
Referring to Figure F-1, label all upper half IP blade ring bolts and
nuts with their numbers provided in Appendix F and indicate RS
(Right Side) or LS (Left Side).
Rev.001
Note
Refer to the Bolt Heating Data in Appendix F to identify the
MM-M05.01
Main Turbine
Mitsubishi
5-7
Chapter 5
Using four bolt heaters (two on each side), heat the bolts in
accordance with Bolt Heater Instruction in Appendix I, avoiding
heating adjacent bolts, and remove bolts from both the RS and LS of
the casing in the following sequence:
(i)
Install safety hoist ring and copper washer into the nut to be
removed.
(ii) Connect suitable lifting gear to the hoist ring and remove the
nuts.
4
Loosen and remove the nuts from bolts 72, 81, 82, 83 and reamer
bolts 71 and 84 at both the RS and LS.
Note
Reamer bolts 71 and 84 and bolts 72, 81, 82, 83 do not have
provision for a bolt heater.
Using the jack screws provided raise the upper half IP blade ring,
approx. 10 mm.
Make a trial lift and adjust the turn buckle or the chain block to obtain
a level lift.
10 Raise the upper half IP blade ring in small increments until it is clear
of the stud bolts.
11 Lift the upper half IP blade ring clear of the turbine and transport it to
the lay-down area.
Note
Ensure that the openings exposed by removal of the upper
Rev.001
MM-M05.01
Main Turbine
Mitsubishi
5-8
Chapter 5
Label all bolts and nuts which secure the No.1 HP stationary blade
ring upper half to the lower half with the numbers provided in Appendix
F and indicate RS or LS.
Loosen and remove the joint bolts at both the RS and LS.
Rig the No.1 HP stationary blade ring upper half and make a trial lift.
CAUTION
Carefully and evenly lift the stationary blade ring to prevent
damage to the stationary and rotating blading.
Lift the stationary blade ring clear of the rotor blades and transport it
to the lay-down area.
Label all No.1 IP stationary blade ring bolts and nuts with their
number and indicate RS or LS.
Loosen and remove the joint bolts at both the RS and LS.
Rig the No.1 IP stationary blade ring upper half and make a trial lift.
Adjust the chain blocks to evenly lift the stationary blade ring upper
half.
CAUTION
Rev.001
MM-M05.01
Main Turbine
Mitsubishi
Lift the stationary blade ring clear of the rotor blades and transport it
to the lay-down area.
5-9
Chapter 5
Referring to Figure F-1, label all No.1 dummy ring bolts and nuts with
their numbers provided in Appendix F and indicate RS (Right Side) or
LS (Left Side).
Note
Refer to the Bolt Heating Data in Appendix F to identify the
bolts and determine the required heater type and size
Using four bolt heaters (two on each side), heat the bolts in
accordance with Bolt Heater Instruction in Appendix I, avoiding
heating adjacent bolts, and remove bolts from both the RS and LS of
the casing in the following sequence:
(i)
92 toward 101
Install safety hoist ring and copper washer into the nut to be
removed.
(ii) Connect suitable lifting gear to the hoist ring and remove the
nuts.
4
Loosen and remove the nuts from bolts 103 and 104 and reamer bolt
105 at both the RS and LS.
Note
Reamer bolt 105 and bolts 103 and 104 do not have provision
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Install the lifting gear for the No.1 dummy ring upper half.
5-10
Chapter 5
Using the jack screws provided raise the No.1 dummy ring upper half,
approx. 10 mm.
Make a trial lift and adjust the turn buckle or the chain block to obtain
a level lift.
10 Raise the No.1 dummy ring upper half in small increments until it is
clear of the stud bolts.
11 Lift the No.1 dummy ring upper half clear of the blades and transport
it to the lay-down area.
CAUTION
Carefully and evenly lift the No.1 dummy ring to prevent
damage to the stationary and rotating blading.
Note
Ensure that the openings exposed by removal of the No.1
dummy ring upper half are protected.
12 Lower the No.1 dummy ring upper half onto wooden blocks.
13 Disconnect and remove the lifting gear.
Label the No.2 dummy ring bolts and nuts with their number and
indicate RS or LS.
Note
Refer to Bolt Arrangement Data in Appendix F to identify the
Using bolt heaters heat the bolt 112 in accordance with Bolt Heater
Instruction in Appendix I, avoiding heating adjacent bolts, and remove
the nuts from bolts from both the RS and LS.
Remove nut from the reamer bolt 111 from the No.2 dummy ring.
Rig and remove the No.2 dummy ring and transport it to the lay-down
area.
MM-M05.01
Rev.001
bolts.
Main Turbine
Mitsubishi
5-11
Chapter 5
Note
Clearance K must be set correctly as all other turbine clearances
are based on this measurement.
Note
Details of measurement of the gland seal clearances are
described in the mechanical maintenance manual M 05.03,
Gland Steam Condenser System and GSC Exhaust Fan.
Measure and record the radial clearance between the seal strip
(located in the nozzle block) and the shroud for the Rateau stage
blades.
Measure and record the following axial clearances at the RS and LS:
Rev.001
(i)
(ii) Repeat Step (i) above for the second through ninth stages.
MM-M05.01
(iii) Clearance B between the end of the first stage stationary blade
outlet and the base of the first stage rotating blade inlet.
Main Turbine
Mitsubishi
5-12
Chapter 5
(iv) Repeat Step (iii) above for the second through ninth stages.
(v) Clearance E between the shroud of the first stage rotating blade
outlet and the base of the second stage stationary blade inlet.
(vi) Repeat Step (v) above for the second, fourth through sixth and
eighth stages.
(vii) Clearance F between the base of the first stage rotating blade
outlet and the end of the second stationary blade inlet.
(viii) Repeat Step (vii) above for the second through eighth stages.
3
Measure and record the following radial clearances at the RS and LS:
(i)
(ii) Seal clearance for the seal strips (installed in the HP stationary
blade diaphragms and rotor), for the first through ninth stages.
Note
The procedure for checking top and bottom blade radial
clearances is provided in Appendix G.
Note
If seal strip clearances exceed 200% of the design
clearances, the seal strips may have to be changed.
Measure and record the following axial clearances at the RS and LS:
(i)
(ii) Repeat Step (i) above for the second through eighth stages.
Rev.001
(iii) Measure and record the clearance B between the end of the first
stage stationary blade outlet and the base of the first stage
rotating blade inlet.
(iv) Repeat Step (iii) above for the second through eighth stages.
MM-M05.01
(v) Measure and record the clearance E between shroud of the first
stage rotating blade outlet and the base of the second stage
stationary blade inlet.
Main Turbine
Mitsubishi
5-13
Chapter 5
(vi) Repeat Step (v) above for the second, fourth, fifth and seventh
stages.
(vii) Measure and record the clearance F between the base of the
first stage rotating blade outlet and the end of the second
stationary blade inlet.
(viii) Repeat Step (vii) above for the second through seventh stages.
2
Measure and record the axial distance FF from the edge of the No.1
dummy ring to the base of the first stage rotating blade inlet at the RS
and LS.
Measure and record the following radial clearances at the RS and LS:
(i)
(ii) Seal clearance between the seal strips (secured to the first stage
stationary blade diaphragm) and the No.1 dummy ring at the RS
and LS.
(ii) Seal clearance between the seal strips (secured to the IP
stationary blade diaphragms) and rotor at the RS and LS, for the
second through eighth stages.
Note
If seal strip clearances exceed 200% of the design
clearances, the seal strips may have to be changed.
Note
The procedure for checking top and bottom blade radial
clearances is provided in Appendix G.
Note
Rev.001
MM-M05.01
Main Turbine
Mitsubishi
5-14
Chapter 5
Remove the coupling oil spray lines, the upper half of the coupling
guard from the HP-IP ~ LP1 coupling. Remove the coupling bolts and
the coupling spacer in accordance with the mechanical maintenance
manual M05.05, Turbine Couplings and Alignment.
Spread the dovetail ends of the outer gland casing gaskets to permit
rotor removal.
Install the rotor lifting guide pillars supplied as special tools on the
HP-IP outer casing base.
10 Confirm that there is sufficient clearance between the HP-IP and LP1
coupling flanges for the removal of the HP-IP rotor.
11 Install the HP-IP rotor lifting gear as shown in Appendix H.
12 Adjust the slings to lift the rotor evenly.
13 Using the turn buckle, level the lifting beam.
14 Lift the HP-IP rotor clear of the bearings to check the rotor level, and
again check that there is sufficient axial clearance for the rotor
removal.
CAUTION
Slow and careful removal of the HP-IP rotor must be
performed to avoid damage.
15 Lift the rotor in small increments and ensure that binding does not
occur.
Rev.001
Note
MM-M05.01
Ensure that the rotor journals are protected prior to setting the
rotor in the support stand.
Main Turbine
Mitsubishi
5-15
Chapter 5
17 Transport the rotor to the lay-down area and set in the support stand.
18 Remove the lower halves of No.1 and No.2 bearings.
19 Remove the lower halves of the inner and outer gland casings at the
Gov End and Gen End.
Connect suitable lifting gear to the lower half No.1 dummy ring.
Remove the upper liners secured to the inner casing base at the
horizontal joint which lock the lower half No.1 dummy ring with inner
casing base. Refer to Section G-G in Figure 5-9 for details.
Make a trial lift and adjust the chain blocks to evenly lift the lower half
No.1 dummy ring.
Rig and remove the No.1 dummy ring and transport it to the lay-down
area.
Remove the supports and liners secured to the lower half No.1
dummy ring and inner casing base if inspection or replacement is
essential.
Rev.001
Connect suitable lifting gear to the lower half No.2 dummy ring.
Remove the upper liners secured to the outer casing base at the
horizontal joint which lock the lower half No.2 dummy ring with outer
casing base. Refer to Section D-D in Figure 5-9 for details.
Rig and remove the No.2 dummy ring and transport it to the lay-down
area.
Remove the supports secured to the lower half No.2 dummy ring and
the lower liners secured to the outer casing base if inspection or
replacement is essential.
MM-M05.01
Main Turbine
Mitsubishi
Install eye bolts in the lower half No.1 HP stationary blade ring and
tighten.
5-16
Chapter 5
Remove the upper liners secured to the HP-IP inner casing base
which lock the lower half No.1 HP stationary blade ring with inner
casing base. Refer to Detail Z in Figure 5-9 for details.
Rig and lift the stationary blade ring clear of the inner casing and
transport it to the lay-down area.
Install eye bolts into the IP No.1 stationary blade ring lower half and
tighten.
Connect suitable lifting gear to the lower half No.1 IP stationary blade
ring.
Remove the upper liners secured to the IP blade ring base which lock
the lower half No.1 IP stationary blade ring with IP blade ring base
(similar to HP stationary blade ring).
Rig and lift the No.1 IP stationary blade ring clear of the IP blade ring
and transport it to the lay-down area.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Remove the hexagonal socket head bolts at the horizontal joint which
secure the lower half IP blade ring to the HP-IP outer casing base.
5-17
Chapter 5
Make a trial lift and adjust the turnbuckle to achieve an even lift.
Slowly raise the lifting gear until the lower half IP blade ring is clear of
the outer casing base.
Remove the upper liners secured to the lower half IP blade ring and
the lower liners secured to the outer casing base if inspection or
replacement is essential. Refer to Detail X in Figure 5-9 for details.
After removal of the lower half IP blade ring, ensure that the openings
in the outer casing base are covered.
Rig and remove the lower half thermal shield and transport it to the
lay-down area.
Remove the liners secured to the lower half thermal shield and to the
outer casing base, if required. Refer to Section B-B in Figure 5-9.
Rev.001
Cut and remove the impulse chamber drain line, and the pressure
sensing piping, outside the HP-IP outer casing base.
Remove the hexagonal socket head bolts which secure the inner
casing base to the outer casing base at the horizontal joint.
Make a trial lift and adjust the turnbuckle to achieve an even lift.
Slowly raise the lifting gear until the inner casing base is clear of the
outer casing base.
After removal of the inner casing base, ensure that the openings in
the outer casing base are covered.
MM-M05.01
10 Remove the liners secured to the inner casing base and the outer
casing base, if required. Refer to Detail Y in Figure 5-9 for details.
Main Turbine
Mitsubishi
5-18
Chapter 5
c)
Visually inspect the following areas for erosion, wear, steam cuts,
cracks, or other damage:
(i)
Note
Any discrepancies found must be corrected by stoning
or honing.
Note
Ensure the horizontal flange areas are protected prior to blast
Rev.001
cleaning.
MM-M05.01
5-19
Chapter 5
(iv) No.1 and No.2 HP stationary blade rings to inner casing fits
(v) Inner casing to No.8 extraction nozzle fit and seal rings
(vi) Steam penetrations
(vii) Pressure seal rings and seal retaining rings of slip joints.
Note
Any discrepancies found must be corrected by stoning or
honing.
Note
Ensure the horizontal flange areas are protected prior to blast
cleaning.
Note
Any discrepancies found must be corrected by stoning or
Rev.001
honing.
MM-M05.01
(i)
Main Turbine
Mitsubishi
5-20
Chapter 5
Note
Change seal strip(s) if they are damaged.
Note
Ensure the horizontal flange areas are protected prior to blast
cleaning.
Visually inspect the following areas for erosion, wear, steam cuts,
cracks, or other damage:
(i)
Note
Any discrepancies found must be corrected by stoning
or honing.
Rev.001
MM-M05.01
5-21
Chapter 5
Note
Change seal strip(s) if they are damaged.
Note
Ensure the horizontal flange areas are protected prior to blast
cleaning.
Note
Any discrepancies found must be corrected by stoning or
honing.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-22
Chapter 5
Note
Replace seal strip(s) if they are damaged.
Note
Ensure the horizontal flange areas are protected prior to blast
cleaning.
Note
Any discrepancies found must be corrected by stoning or
honing.
Note
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-23
Chapter 5
Note
Ensure the horizontal flange areas are protected prior to blast
cleaning.
Note
Any discrepancies found must be corrected by stoning or
honing.
Note
Rev.001
Abrasive blast clean the rotor including the blading and shrouds.
Note
Ensure the rotor journal areas are protected prior to blast
MM-M05.01
cleaning.
Main Turbine
Mitsubishi
5-24
Chapter 5
Visually inspect the rotor gland areas for erosion, wear, steam cuts,
cracks, or other damage.
Visually inspect the rotor journal areas and thrust collar for scratches,
dents, pitting or other damage.
Reaction blading
Note
Any discrepancies found must be corrected by stoning,
honing, or component replacement.
d)
Reassembly
The reassembly procedure is carried out in the reverse sequence to that
for disassembly. Install all parts in the same positions they were removed
from, referring to the match marks and checking that the clearances are
maintained as specified.
Ensure that all components are free from burrs and bruises, blending
away the defects using fine files, carborundum stones and emery cloth.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-25
Chapter 5
CAUTION
Prior to installation of the turbine components, thoroughly
inspect the internals for foreign materials. Ensure that the
utmost standards of cleanliness are applied at all times.
Note
Lubricate all bolts and studs with Molykote.
Clean the mating areas of the inner casing base and the outer casing
base and support liners.
Ensure that the seal rings and the retaining rings are correctly
installed in the inner casing base and cover, if removed during
disassembly.
Ensure that the seal rings are correctly installed in the slots on the
No.8 extraction nozzle, if removed during disassembly.
Secure the liners to the inner casing base and the outer casing base
if removed during disassembly. Refer to Figure 5-9 for details.
Make a trial lift and adjust the turn buckle to achieve a level lift.
Move the inner casing base from the lay-down area and position it
above the outer casing base.
Attach a tag line to each end of the inner casing base to control any
rotation.
10 Slowly and carefully lower the inner casing base until it rests on the
liners bolted to the outer casing base.
11 Remove the lifting gear.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-26
Chapter 5
Clean and lubricate the dowel and mating areas on the thermal shield
lower half and support liners.
Replace all seal rings and piston rings in the thermal shield in their
original locations, if removed during disassembly.
Secure the liners to the outer casing base and to the lower half
thermal shield if removed during disassembly. Refer to Figure 5-9 for
details.
Transport the thermal shield lower half from the lay-down area and
align it with the HP-IP outer casing base.
Lower the thermal shield slowly and evenly into the dowel pin
secured in the outer casing until the weight is on the liners and the
horizontal joint is even with that of the outer casing base. Take care
while lowering the thermal shield to prevent any damage to the seal
rings.
Note
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Clean the mating areas of the lower half IP blade ring and the HP-IP
outer casing base and support liners.
Ensure that the liners are correctly installed in the outer casing base
horizontal joint. Refer to Figure 5-9 for details.
Ensure that the seal rings are correctly installed in the slots on the
No.6 extraction nozzle, if removed during disassembly.
Make a trial lift and adjust the turn buckle to achieve a level lift.
Transport the lower half IP blade ring from the lay-down area and
position it above the outer casing base.
5-27
Chapter 5
Attach a tag line to each end of the lower half IP blade ring to control
any rotation.
Slowly and carefully lower the lower half IP blade ring until it is
supported on the liners bolted to the outer casing base.
Clean the mating areas of the lower half No.1 IP stationary blade ring
and the IP blade ring base and the support liners and keys.
Secure the lower liners to the IP blade ring base and the supports to
the lower half No.1 IP stationary blade ring, if removed during
disassembly. Refer to Figure 5-9 for details.
Install eye bolts in the lower half No.1 IP stationary blade ring and
tighten.
Make a trial lift and adjust the chain blocks to obtain a level lift.
Transport the lower half No.1 IP stationary blade ring from the
lay-down area and align it over the IP blade ring base.
Lower the No.1 IP stationary blade ring slowly and evenly into the IP
blade ring until the supports rest on the lower liners. Ensure that the
horizontal joint of the IP stationary blade ring is even with the
horizontal joint of the IP blade ring base and the weight is on the
liners.
Install and secure the upper liners to the lower half IP blade ring.
Secure the lower liners to the inner casing base and the supports to
the lower half No.1 HP stationary blade ring, if removed during
disassembly. Refer to Figure 5-9 for details.
Install eye bolts in the lower half No.1 HP stationary blade ring and
tighten.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-28
Chapter 5
Make a trial lift and adjust the chain blocks to obtain a level lift.
Transport the lower half No.1 HP stationary blade ring from the
lay-down area and align it over the inner casing base.
Lower the No.1 HP stationary blade ring slowly and evenly into the
inner casing until the supports rest on the lower liners. Ensure that
the horizontal joint of the HP stationary blade ring is even with the
horizontal joint of the inner casing base and the weight is on the lower
liners.
Install and secure the upper liners to the inner casing base.
Rev.001
Clean and lubricate all mating areas on the No.1 dummy ring lower
half.
Secure the lower liners to the inner casing base and the supports to
the lower half No.1 dummy ring, if removed during disassembly.
Refer to Figure 5-9 for details.
Replace all seal rings in the No.1 dummy ring in their original
locations if removed during disassembly and secure them with the
seal ring retainer.
Transport the No.1 dummy ring from the lay-down area and align it
above the inner casing base.
Lower the No.1 dummy ring slowly and evenly into the inner casing
until the supports rest on the lower liners. Ensure that the horizontal
joint of the No.1 dummy ring is even with the horizontal joint of the
inner casing base and the weight is on the lower liners.
Install and secure the upper liners to the inner casing base.
MM-M05.01
Main Turbine
Mitsubishi
5-29
Chapter 5
Clean and lubricate all mating areas on the No.2 dummy ring lower
half.
Secure the lower liners to the outer casing base and the supports to
the lower half No.2 dummy ring, if removed during disassembly.
Refer to Figure 5-9 for details.
Replace all seal rings in the No.1 dummy ring if removed during
disassembly.
Transport the No.2 dummy ring from the lay-down area and align it
above the outer casing base.
Lower the No.2 dummy ring slowly and evenly into the outer casing
until the supports rest on the lower liners. Ensure that the horizontal
joint of the No.2 dummy ring is even with the horizontal joint of the
outer casing base and the weight is on the lower liners.
Install and secure the upper liners to the outer casing base.
Install the lower halves of the No.1 and No.2 turbine bearings and the
thrust bearing.
Visually inspect the HP-IP turbine base to make sure that it is clean
and free of foreign objects before rotor installation.
Note
These may not have been removed.
Rev.001
Note
MM-M05.01
Main Turbine
Mitsubishi
5-30
Chapter 5
Adjust the slings from the center of the lifting beam to achieve a level
lift, adjusting the turnbuckle as required.
Transport the rotor to the HP-IP turbine base and align it with the rotor
guides.
CAUTION
Care must be taken when installing the rotor to ensure that the
blading and journal areas are not damaged. The turbine rotor
is a sensitive component with numerous tight axial and radial
clearances which must remain intact for correct operation.
Damaging the rotor can cause serious delays in turbine
assembly if additional repairs are necessary.
10 Lower the rotor slowly into the rotor guide pillars while constantly
watching the rotor level.
11 Stop lowering at any change in rotor inclination to determine and
eliminate the cause.
12 Slowly lower the rotor until it is supported in No.1 & No.2 bearings.
13 Raise the rotor slowly again and apply lubricating oil on the bearing
surfaces.
14 Lower the rotor slowly until it is supported in the bearings.
15 Remove the rotor guide pillars and block the rotor to restrict axial
movement.
16 Rotate the rotor slowly as per the procedure indicated in the
mechanical maintenance manual M-05.05, Turbine Couplings and
Alignment, and make sure that the rotor turns freely without rubbing.
CAUTION
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-31
Chapter 5
Note
Clearance K must be set correctly as all other turbine clearances
are based on this measurement.
Note
Details of measurement of the gland seal clearances are
described in the mechanical maintenance manual M 05.03,
Gland Steam Condenser System and GSC Exhaust Fan.
Measure and record the radial clearance between the seal strip
(located in the nozzle holder) and the shroud for the Rateau stage
blades.
Measure and record the following axial clearances at the RS and LS:
Rev.001
(i)
MM-M05.01
(ii) Repeat Step (i) above for the second through ninth stages.
(iii) Clearance B between the end of the first stage stationary blade
outlet and the base of the first stage rotating blade inlet.
Main Turbine
Mitsubishi
5-32
Chapter 5
(iv) Repeat Step (iii) above for the second through ninth stages.
(v) Clearance E between the shroud of the first stage rotating blade
outlet and the base of the second stage stationary blade inlet.
(vi) Repeat Step (v) above for the second, fourth through sixth and
eighth stages.
(vii) Clearance F between the base of the first stage rotating blade
outlet and the end of the second stationary blade inlet.
(viii) Repeat Step (vii) above for the second through eighth stages.
3
Measure and record the following radial clearances at the RS and LS:
(i)
(ii) Seal clearance for the seal strips (installed in the stationary blade
diaphragms and rotor), for the first through ninth stages.
Note
The procedure for checking top and bottom blade radial
clearances is provided in Appendix G.
Note
If seal strip clearances exceed 200% of the design
clearances, the seal strips may have to be changed.
Measure and record the following axial clearances at the RS and LS:
(i)
(ii) Repeat Step (i) above for the second through eighth stages.
Rev.001
(iii) Measure and record the clearance B between the end of the first
stage stationary blade outlet and the base of the first stage
rotating blade inlet.
(iv) Repeat Step (iii) above for the second through eighth stages.
MM-M05.01
(v) Measure and record the clearance E between shroud of the first
stage rotating blade outlet and the base of the second stage
stationary blade inlet.
Main Turbine
Mitsubishi
5-33
Chapter 5
(vi) Repeat Step (v) above for the second, fourth, fifth and seventh
stages.
(vii) Measure and record the clearance F between the base of the
first stage rotating blade outlet and the end of the second
stationary blade inlet.
(viii) Repeat Step (vii) above for the second through seventh stages.
2
Measure and record the axial distance FF from the edge of the No.1
dummy ring to the base of the first stage rotating blade inlet at the RS
and LS.
Measure and record the following radial clearances at the RS and LS:
(i)
(ii) Seal clearance between the seal strips (secured to the first stage
stationary blade diaphragm) and the No.1 dummy ring at the RS
and LS.
(iii) Seal clearance between the seal strips (secured to the stationary
blade diaphragms) and rotor at the RS and LS, for the second
through eighth stages.
Note
If seal strip clearances exceed 200% of the design
clearances, the seal strips may have to be changed.
Note
The procedure for checking top and bottom blade radial
clearances is provided in Appendix G.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Have the electricians install the rotor position, eccentricity and phase
detector pick-ups.
Install the thrust bearing and confirm that the thrust axial clearance
and the No.1 and No.2 bearing oil clearances are within the
acceptance criteria in accordance with mechanical maintenance
manual M 05.04, Turbine Bearings and Thrust Bearing.
Perform coupling alignment between the HP-IP and LP1 rotors and
make sure that the coupling alignment is within tolerance. For details,
refer to the mechanical maintenance manual M 05.05, Turbine
Couplings and Alignment.
5-34
Chapter 5
Install the upper halves of the No.1 and No.2 journal bearings.
Install the HP-IP to LP1 coupling spacer and the coupling bolts in
accordance with mechanical maintenance manual M 05.05, Turbine
Couplings and Alignment.
Install the upper half coupling guard and connect the coupling cooling
oil line for the HP-IP to LP1 coupling.
Note
The above items 5, 6 and 7 assume that only the HP-IP turbine
has been subjected to overhaul. In the event that LP turbines
are also to be overhauled connection of the HP-IP to LP1
coupling will be performed after their reassembly.
Adjust the chain block to evenly lift the No.2 HP stationary blade ring
upper half.
Move the No.2 HP stationary blade ring upper half from the lay-down
area to the turbine casing.
Align the upper half stationary blade ring with the lower half stationary
blade ring.
Clean the No.2 HP stationary blade ring upper and lower halves
horizontal joint and coat the upper half joint with triple boiled linseed
oil or special compound for flange surface.
Lower the No.2 stationary blade ring upper half slowly and evenly
over the joint studs until the horizontal joint is closed.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-35
Chapter 5
CAUTION
Care must be taken when installing the upper half stationary
blade ring to ensure that the turbine blading are not damaged.
The blading are installed with tight axial clearances which
must remain intact for correct operation. Damages to the
blading can cause serious delays in turbine assembly if
additional repairs are necessary.
9
10 Coat the horizontal joint washers with Molykote and install on studs.
11 Tighten the horizontal joint bolts at both the RS and LS.
12 Following similar procedure described above install the upper half
No.1 HP stationary blade ring and No.1 ~ No.4 IP stationary blade
rings.
13 Rotate the HP-IP rotor to ensure freedom of rotor movement.
Replace the seal rings in the No.1 dummy ring upper half, if removed
during disassembly.
Adjust the chain block to evenly lift the dummy ring upper half.
Move the dummy ring upper half from the lay-down area to the
turbine casing.
Align the dummy ring upper half over the dummy ring lower half.
Clean the dummy ring upper and lower halves horizontal joint and
coat the upper half joint with triple boiled linseed oil or special
compound for flange surface.
Clean the stud threads and fit groove areas and coat them with
Molykote.
Lower the dummy ring upper half slowly and evenly over the joint
studs until the horizontal joint is closed.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-36
Chapter 5
CAUTION
Care must be taken when installing the upper half dummy ring
to ensure that the turbine blading are not damaged. The
blading are installed with tight axial clearances which must
remain intact for correct operation. Damages to the blading
can cause serious delays in turbine assembly if additional
repairs are necessary.
10 Remove the lifting gear.
11 Coat the horizontal joint washers with Molykote and install them on
the studs.
Note
Refer to the Bolt Heating Data in Appendix F to identify the
bolts and determine the required heater type and size. Heat
the bolts in accordance with Bolt Heater Instruction in
Appendix I.
Note
Tighten the nuts without bolt heaters to the torque specified in
Appendix F.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-37
Chapter 5
Adjust the chain block to evenly lift the dummy ring upper half.
Move the dummy ring upper half from the lay-down area to the
turbine casing.
Align the dummy ring upper half over the dummy ring lower half.
Clean the dummy ring upper and lower halves horizontal joint and
coat the upper half joint with triple boiled linseed oil or special
compound for flange surface.
Lower the dummy ring upper half slowly and evenly over the joint
studs until the horizontal joint is closed.
Adjust the chain blocks to evenly lift the IP blade ring upper half.
Transport the IP blade ring from the lay-down area and align it with
the lower half IP blade ring.
Clean the horizontal joint flanges of the upper and lower halves IP
blade ring and coat the upper half joint with triple boiled linseed oil or
special compound for flange surface.
Clean stud threads, dowels and groove areas and coat with Molykote.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-38
Chapter 5
Lower the IP blade ring upper half slowly and evenly over the joint
studs until the horizontal joint is closed.
Coat the horizontal joint washers with Molykote and install on studs.
Note
Refer to the Bolt Heating Data in Appendix F to identify the
bolts and determine the required heater type and size. Heat
the bolts in accordance with Bolt Heater Instruction in
Appendix I.
Note
Tighten the nuts without bolt heaters to the torque specified in
Appendix F.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Visually inspect the HP-IP turbine base for foreign material prior to
installing the inner casing cover, and record the result.
Replace the seal rings and retaining rings in the inner casing cover, if
removed during disassembly.
Install eyebolts and connect suitable lifting gear to the inner casing
cover.
5-39
Chapter 5
Transport the inner casing cover and position it above the inner
casing base joint bolts.
Adjust the turnbuckles of the lifting gear so that the cover horizontal
joint is parallel to the base horizontal joint.
Replace the seal rings and piston rings in the thermal shield, if
removed during disassembly.
Replace and secure the upper liners to the upper half thermal shield.
Transport the thermal shield upper half from the lay-down area to the
turbine casing and align it with the lower half.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-40
Chapter 5
Clean and coat the upper half horizontal joint with triple boiled linseed
oil or special compound for flange surface.
Clean bolt threads, bushing and groove areas and coat with
Molykote.
Lower the upper half thermal shield slowly and evenly until the
horizontal joint is closed. While lowering ensure that the LP leakage
steam nozzle slides smoothly into the No.1 dummy ring and the seal
rings slide smoothly along the IP blade ring and inner casing cover.
Connect the HP-IP outer casing cover lifting gear in accordance with
Appendix H.
Transport the outer casing cover from the lay-down area and align it
to the outer casing base.
Lubricate the joint bolts, dowels, steam inlet nozzle sleeves and other
mating areas with Molykote.
Lubricate the outer casing cover horizontal joint flange with triple
boiled linseed oil or special compound for flange surface.
Slowly lower the outer casing cover and make sure that the main
steam inlet sleeves in the outer casing cover are aligned with the
inner casing cover.
Install the jack screws in the outer casing cover when the cover
reaches to 50 mm above the horizontal joint. Turn the jack screws in
the outer casing cover until they protrude 10 mm below the horizontal
joint.
Rev.001
10 Lower the outer casing cover further until the jack screws rest on the
horizontal joint of the outer casing base.
MM-M05.01
11 Continue lowering the outer cover by backing off all the jack screws
equally 1/2 turn at a time.
Main Turbine
Mitsubishi
5-41
Chapter 5
Note
Follow the downward motion of the outer casing with the
lifting device to ensure that the load is transferred to the jack
screws.
12 Continue to lower the outer cover until the horizontal joint is closed.
Note
Check the contact between the flanges using a feeler gauge.
Note
Tighten, in a diametrically opposite pattern, the HP-IP outer
casing bolts in the following order.
(i)
MM-M05.01
Rev.001
18 Heat and stretch the bolts 1 41 and tighten the nuts in the sequence
indicated above in accordance with Appendix I.
Main Turbine
Mitsubishi
5-42
Chapter 5
Return to Service
Return to Service
Refer to Figure 5-1.
Install and secure the MOP cover to the pump base.
Reconnect the main steam and reheat steam inlets by installing new
gaskets in the inlet flanges.
Install the top seal rings and reconnect the IP to LP1/LP2 crossover
pipe.
Install the outer gland casing upper halves and secure them to the
HP-IP outer casing cover.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-43
Chapter 5
GEN. SIDE
ICV
MAIN STEAM
INLET PIPE
ICV
HP-IP TURBINE
GV BODY
STEAM FLOW
RSV
"C"
DETAIL "I"
"F"
"I"
OPERATING FLOOR
OPERATING FLOOR
HP-IP TURBINE
RSV
HP-IP TURBINE
MAIN STEAM INLET PIPE
HOT REHEAT STEAM
INLET PIPE
D-D
G-G
A-A
"E"
E -E
"A"
"H"
ICV
MAIN STOP VALVE
MAIN STEAM
INLET SLEEVE
GV BODY
"B"
HP-IP TURBINE
ICV
RSV
RSV
HP-IP TURBINE
HP-IP TURBINE
CL OF TURBINE
OPERATING FLOOR
OPERATING FLOOR
HP-IP TURBINE
MAIN STEAM
INLET SLEEVE
MM-M05.01
Rev.001
VIEW "B"
VIEW "C"
VIEW "H"
VIEW "F"
MPTD-3-0240
FIGURE 5-1
Main Turbine
Mitsubishi
5-44
Chapter 5
IP BLADE RING
OUTER CASING
5
4
OUTER CASING
IP BLADE RING
No.3 IP STATIONARY
BLADE RING
No.4 IP STATIONARY
BLADE RING
OUTER CASING
0.20 +- 0.05
20 +- 2
GLAND CASING
HIP ROTOR
GLAND CASING
OUTER CASING
GEN. SIDE
GOV. SIDE
IP BLADE RING
5
4
INNER CASING
No.1 DUMMY RING
MM-M05.01
Rev.001
No.2 IP STATIONARY
BLADE RING
No.1 IP STATIONARY
BLADE RING
4
5
1.5
1.5
NOZZLE BLOCK
No.2 HP STATIONARY
BLADE RING
No.1 HP STATIONARY
BLADE RING
MPTD-3-0241
FIGURE 5-2
Main Turbine
Mitsubishi
5-45
Chapter 5
0.5+-0.1
HIP ROTOR
OUTER CASING
GOV. SIDE
CL OF HIP ROTOR
GLAND CASING
GLAND CASING
0.5+- 0.1
0.5+- 0.1
HIP ROTOR
HIP ROTOR
MM-M05.01
Rev.001
SEAL STRIP
SEAL STRIP
MPTD-4-0242
FIGURE 5-3
Main Turbine
Mitsubishi
Chapter 5
OUTER CASING
GEN. SIDE
CL OF HIP ROTOR
MM-M05.01
Rev.001
NOTE: REFER TO FIGURE 5-8 FOR GLAND SEAL RADIAL CLEARANCES (X)
MPTD-4-0243
FIGURE 5-4
Main Turbine
Mitsubishi
5-47
Chapter 5
INNER CASING
0.5+-0.1
0.13~0.2
SEAL RING
0.0~0.1
0.5+-0.1
1.6
SEAL RING
SEAL STRIP
SEAL STRIP
HIP ROTOR
SEAL STRIP
C
L OF HIP ROTOR
GEN. SIDE
No.1 DUMMY RING
0.5+-0.1
0.5+-0.1
0.5+-0.1
0.5+-0.1
0.5+-0.1
0.5+-0.1
No.2 DUMMY RING
MM-M05.01
Rev.001
HIP ROTOR
SEAL RING
x
x
0.5+-0.1
0.5+-0.1
GOV. SIDE
SEAL STRIP
SEAL RING
MPTD-3-0244
HIP ROTOR
FIGURE 5-5
Main Turbine
Mitsubishi
SEAL STRIP
5-48
SEAL STRIP
5C
4C
9C
8C
SEAL STRIP
ROTATING
BLADE
7C
6C
3C
2C
1C
Chapter 5
ROTATING
BLADE
ROTATING
BLADE
SEAL STRIP
RATEAU
STAGE BLADE
ROW No.
12.5+1.5
-0.5
E
3C
4C
1R
2R
3R
+1.5
-0.5
5C
6C
7C
A
B
8C
9C
A
B
LOCATION
4R
5R
6R
8R
7R
9R
GEN. SIDE
GOV. SIDE
SEAL STRIP
ROTATING
BLADE
ROTATING
BLADE
SEAL STRIP
2R
3R
4R
5R
6R
7R
MM-M05.01
Rev.001
1R
SEAL STRIP
FIGURE 5-6
Main Turbine
Mitsubishi
1
2
3
4
NO.2 HP STATIONARY 5
BLADE RING
6
7
NO.1 HP STATIONARY 8
BLADE RING
9
NO.1 DUMMY RING
ROTOR BLADES
INLET
OUTLET
A
B
E
F
11.9 12.7 7.3 8.1
11.9 12.7 7.3 8.1
11.9 12.7
38.1
11.9 12.7 7.3 8.1
11.9 12.7 7.3 8.1
11.9 12.7 13.6 14.4
56.2
11.9 12.7
11.9 12.7 7.3 8.1
_
11.9 12.7
12
1C
2C
HIP ROTOR
12+-0.0
8R
9R
ROTATING
BLADE
5-49
3C
4C
5C
Chapter 5
2C
1C
6C
SEAL STRIP
SEAL STRIP
ROTATING
BLADE
SEAL STRIP
ROTATING
BLADE
ROTATING
BLADE
E
8C
8R
6C
7R
4C
5R
3C
2C
A
B
6R
8C
7C
5C
4R
3R
LOCATION
2R
1R
1C
IP No.1 STATIONARY
BLADE RING
IP No.2 STATIONARY
BLADE RING
ROTATING
BLADE
SEAL STRIP
IP No.3 STATIONARY
BLADE RING
IP No.4 STATIONARY
BLADE RING
GEN. SIDE
1
2
3
4
5
ROTOR BLADES
INLET
OUTLET
A
B
E
F
24 11.5 23.6 17.1
27.3 8.5
47.1
27.3 8.5 29.9 17.1
21.0 8.5 23.6 17.1
32.8 8.5
47
6 21.0
8.5
60.1
GOV. SIDE
4R
3R
2R
5R
7R
8R
ROW No.
7C
1R
6R
x
SEAL STRIP
SEAL STRIP
HIP ROTOR
MM-M05.01
Rev.001
HIP ROTOR
SEAL STRIP
SEAL STRIP
HIP ROTOR
HIP ROTOR
MPTD-3-0246
FIGURE 5-7
Main Turbine
Mitsubishi
5-50
Chapter 5
NOMINAL CLEA.
LOCATION
LENGTH
460.75
578.75
676.75
761.75
866.50
943.50
1013.50
1353.30
1408.15
1455.65
1503.55
1601.70
1656.65
1712.95
1764.65
1814.75
1866.45
1916.55
1968.25
2048.35
2100.05
2150.15
2201.85
2251.95
2303.65
2466.50
2928.75
3001.75
3083.75
3156.75
3229.75
3385.75
3847.10
3972.30
4067.40
4171.20
4302.60
4406.40
4500.95
4591.35
4679.55
4785.15
4917.55
5007.90
5139.15
5229.50
5317.75
5429.95
5632.87
5732.87
5843.87
5965.37
866.50
943.50
3001.75
0.65
0.65
0.60
0.60
1.40
1.20
0.70
0.85
0.65
0.90
0.65
0.90
0.65
0.90
0.65
0.90
0.65
0.90
0.65
0.80
0.65
0.80
0.65
0.80
0.65
1.00
0.85
1.55
0.85
0.85
0.85
0.95
0.40
0.80
0.60
0.80
0.60
0.95
0.60
1.05
0.60
1.10
0.60
1.05
0.60
1.05
0.60
1.10
0.60
0.60
0.60
0.60
0.40
0.40
0.55
0.65
0.65
0.60
0.60
1.40
1.20
0.70
0.85
0.65
0.90
0.65
0.90
0.65
0.90
0.65
0.90
0.65
0.90
0.65
0.80
0.65
0.80
0.65
0.80
0.65
1.00
0.85
1.55
0.85
0.85
0.85
0.95
0.40
0.80
0.60
0.80
0.60
0.95
0.60
1.05
0.60
1.10
0.60
1.05
0.60
1.05
0.60
1.10
0.60
0.60
0.60
0.60
0.40
0.40
0.55
0.02
0.01
-0.01
-0.01
-0.02
-0.03
-0.04
-0.07
-0.07
-0.08
-0.08
-0.09
-0.09
-0.10
-0.10
-0.10
-0.11
-0.11
-0.11
-0.12
-0.12
-0.12
-0.12
-0.13
-0.13
-0.13
-0.14
-0.14
-0.14
-0.14
-0.14
-0.14
-0.13
-0.12
-0.12
-0.11
-0.11
-0.10
-0.10
-0.09
-0.09
-0.08
-0.07
-0.07
-0.06
-0.05
-0.05
-0.04
-0.02
-0.01
0.01
0.03
0.02
-0.03
-0.14
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
ELEMENT
OUTER GLAND
(GOV. END)
INNER GLAND
(GEN. END)
NO.2 DUMMY
RING
HP8~9C
DIAPHRAGM
HP4~7C
DIAPHRAGM
NO.1
DUMMY RING
HP NOZZLE
HORIZONTAL DIRECTION
AFT. ASS'Y
CASING DEFLEC.
NOMINAL CLEA.
23
24
NOTE:
1. RADIAL CLEARANCES AT ASSEMBLY OF HIP TURBINE
IS AS SHOWN IN THIS DRAWING IN CASE THAT SETTING
OF EACH PART AND DEFLECTION OF THE ROTOR IS
TAKEN INTO ACCOUNT.
10
11
10 11
+0.15
-0.05
+0.10
-0.05
+0.15
-0.05
+0.10
-0.05
21
22
0.65
0.65
0.60
0.60
0.70
0.70
0.70
0.65
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.60
0.65
0.60
0.65
0.60
0.65
1.00
0.85
0.85
0.85
0.85
0.85
0.95
0.40
0.60
0.60
0.60
0.60
0.75
0.60
0.85
0.60
0.90
0.60
0.85
0.60
0.85
0.60
0.90
0.60
0.60
0.60
0.60
0.70
0.70
0.85
0.65
0.65
0.60
0.60
0.70
0.70
0.70
0.65
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.60
0.65
0.60
0.65
0.60
0.65
1.00
0.85
0.85
0.85
0.85
0.85
0.95
0.40
0.60
0.60
0.60
0.60
0.75
0.60
0.85
0.60
0.90
0.60
0.85
0.60
0.85
0.60
0.90
0.60
0.60
0.60
0.60
0.70
0.70
0.85
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Y
-
+
+
Rev.001
ROTATION
MM-M05.01
26
27
28
0.65
0.65
0.60
0.60
0.70
0.70
0.70
0.65
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.60
0.65
0.60
0.65
0.60
0.65
1.00
0.85
0.85
0.85
0.85
0.85
0.95
0.40
0.60
0.60
0.60
0.60
0.75
0.60
0.85
0.60
0.90
0.60
0.85
0.60
0.85
0.60
0.90
0.60
0.60
0.60
0.60
0.70
0.70
0.85
0.65
0.65
0.60
0.60
0.70
0.70
0.70
0.65
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.70
0.65
0.60
0.65
0.60
0.65
0.60
0.65
1.00
0.85
0.85
0.85
0.85
0.85
0.95
0.40
0.60
0.60
0.60
0.60
0.75
0.60
0.85
0.60
0.90
0.60
0.85
0.60
0.85
0.60
0.90
0.60
0.60
0.60
0.60
0.70
0.70
0.85
TOP CLEARANCE
25
29
30
29 30
ROTOR AFT. ASY AFT. ASY CASING CASING AT SET. AT SET.
FROM
AFT. ASY AFT. ASY CASING CASING AT SET. AT SET. TOLERANCE
NOMINAL NOMINAL ELEMENT ROTOR
NOMINAL NOMINAL ELEMENT ROTOR
TOLERANCE
No.1 BRG. TOP
SETTING SETTING RIGHT
LEFT
DEFLEC. DEFLEC. RIGHT
BOTTOM SETTING DEFLEC. SETTING TOP
LEFT
BOTTOM
RIGHT
LEFT
BOTTOM DEFLEC. DEFLEC. TOP
LEFT
CLEARA. CLEARA.
CLEARA. CLEARA.
CLEARA. CLEARA.
CLEARA. CLEARA. RIGHT
BOTTOM CLEARA. CLEARA.
CLEARA. CLEARA. TOP
6
+0.15
-0.05
+0.10
-0.05
+0.15
-0.05
+0.10
-0.05
- 5
24
25
BOTTOM CLEARANCE
MPTD-3-0247
FIGURE 5-8
Main Turbine
Mitsubishi
5-51
Chapter 5
10
10
10
15
13
8
G
I
2
8
1
A-A
B-B
1
7
12
12
3
"X"
C
B
13
13
14
14
6
10
3
2
10
15
10
11
15
DETAIL "X"
"Y"
DETAIL "Y"
INNER CASING SUPPORT
15
16
C-C
20
15
18
17
17
3
16
3
15
15
DETAIL "Z"
14
18
17
17
MM-M05.01
Rev.001
17
16
17
18
2
6
19
15
20
"Z"
4
NO.1 DUMMY RING SUPPORT
FIGURE 5-9
Main Turbine
Mitsubishi
5-52
MPTD-4-0249
MPTD-4-0248
MM-M05.01
Rev.001
Chapter 5
FIGURE 5-10
Main Turbine
Mitsubishi
5-53
Chapter 5
5.2
Preparation
If LP1 turbine disassembly becomes necessary, all associated equipment
must be mechanically and electrically isolated and an authorized
clearance and work permit must be in place prior to the commencement of
work. The following points must also to be considered when preparing for
disassembly and reassembly:
CAUTION
Spigot joints between the turbine stationary components
(such as outer and inner casings, blade rings, etc.) could bind
due to scale formation during operation under the high
temperature environment.
CAUTION
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-54
Chapter 5
CAUTION
Personnel working inside the turbine should not carry any
loose items in the pockets and should take special care not to
drop tools or debris into the turbine.
CAUTION
Any surface irregularity or damage caused by the reasons
described above, must be ground off smoothly, or
reconditioned by build-up welding and facing to reinstate the
original surface finish and clearance if any between mating
parts.
CAUTION
Wear proper goggles and face masks when working on the
insulation. Insulation material is harmful to the respiratory
system.
b)
Disassembly
Refer to Figures 2-8 and E-2.
During normal operation, before the Unit is shut down for overhaul,
perform a thorough external visual inspection of the entire turbine unit
to detect any obvious deficiencies. These are to be rectified during
the turbine overhaul.
Note
Label and identify all components as they are disassembled.
Tag and bag all hardware and fasteners with the associated
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Remove the insulation from the IP turbine exhaust to LP1 and LP2
turbines steam inlet flanges.
5-55
Chapter 5
Refer to Figure 2-14. Remove the nuts from the flange joints and then
remove the crossover piping connecting the IP exhaust to the LP1
and LP2 turbines inlet. Remove the top seal ring from between the
LP1 inner and outer casings.
Loosen the flange bolts on all LP1 outer casing manhole covers.
Support the weight of the manhole covers using the lifting gear.
Remove the Gov End and Gen End shaft upper half gland casings
and remove the seal rings from the gland casings into storage.
Note
The following steps 10~15, to disassemble the Gov End and
Gen End exhaust flow guides are performed inside the outer
casing. Refer to Figure 5-18.
Rev.001
14 Adjust the lifting gear to support the weight of exhaust flow guide
upper half, and alternately tighten the jack screws and loosen the
adjacent bolts until the locating eccentric pins have been pulled free
from the inner casing.
MM-M05.01
15 Remove the jackscrews from the flange, lift the exhaust flow guide
upper half, and fasten it securely to the inside of the outer casing
cover.
16 Remove the horizontal joint bolts from the LP1 outer casing base.
Main Turbine
Mitsubishi
5-56
Chapter 5
17 Install jack screws in the outer casing cover horizontal joint flange and
manually tighten to contact the outer casing base horizontal joint
face.
18 Turn the jack screws half a turn at a time to open the horizontal joint,
maintaining equal loading on the jack screws and equal gap at the
horizontal joint opening.
Note
During operation of the turbine, oxides and deposits
accumulate between the mating surfaces of the casings. The
forces required to separate these surfaces may be noticeably
greater than those required to suspend the weight of the outer
casing cover.
19 Install the lifting gear to the LP1 outer casing cover in accordance
with Appendix H.
20 Tension the wire ropes and position the hook over the center of
gravity, make a trial lift and adjust the lifting equipment until an even
lift is achieved.
CAUTION
Follow the upward motion of the LP1 outer casing with the
crane attached to the lifting device. Do not overload the lifting
cables.
21 Attach a tag line to each end of the LP1 outer casing cover to control
any rotation of the casing during the lift.
22 Evenly raise the LP1 outer casing cover in small increments until it
stands clear of the bolts.
23 Lift the LP1 outer casing cover clear of the turbine and transport it to
the lay-down area.
24 Set wooden supports on the floor to support the outer casing cover.
25 Protect the horizontal joints of the LP1 outer casing cover.
26 Lower the LP1 outer casing cover onto the wooden supports.
27 Disconnect and remove the lifting gear.
Rev.001
Note
Ensure that the openings in the lower half turbine exposed by
the removal of the outer casing cover are protected. It is
MM-M05.01
Main Turbine
Mitsubishi
5-57
Chapter 5
CAUTION
When working in or over the condenser plenum, take special
care not to drop tools or debris into the condenser tube area.
Damage to the condenser tubes could result in condenser tube
leakage.
1
Match mark and remove the access cover plates to expose the
internal horizontal joint bolts.
Note
Refer to Appendix F to identify the horizontal joint bolts, and
to determine the required bolt heater type and size. Remove
the bolts from both LS and RS of the LP1 inner casing starting
at the transverse centerline of both LS and RS, working
outwards toward each end. Remove the bolts parallel to the
transverse axis starting at the extreme end and working
towards the turbine longitudinal axis.
Using four bolt heaters (two on each side), heat the bolts 213 224 in
accordance with Bolt Heater Instruction in Appendix I, avoiding
heating adjacent bolts, and loosen the nuts from both the RS and LS
of the casing in the following sequence:
(i)
Note
Rev.001
MM-M05.01
Main Turbine
Mitsubishi
5-58
Chapter 5
Install safety hoist ring and copper washer into the nut to be
removed.
(ii) Connect suitable lifting gear to the safety hoist ring and remove
the nuts.
5
Loosen and remove the nuts from bolts 201 212 and 225 272 in
the following sequence:
Note
Bolts 201 212 and 225 272 do not have provision for a bolt
heater.
(i)
(ii) Bolts 237 241, 243 251, 253 263, 265 271
(iii) Reamer bolts 201 and 236
(iv) Reamer bolts 242, 252, 264 and 272.
6
Lubricate and install jackscrews into the inner casing cover horizontal
joint flange and hand tighten until contact is made with the inner
casing base horizontal joint flange.
Note
During the operation of the turbine, oxides and the deposits
accumulate between the mating surfaces of the casings. The
forces required to separate these surfaces may be noticeably
greater than those required to suspend the weight of the inner
casing cover.
Install the inner casing guide bolts (supplied as Special Tools) on the
inner casing base as indicated in Figure 5-17.
Turn the jack screws half a turn at a time to open the horizontal joint
and maintain an equal gap at the horizontal joint openings.
CAUTION
MM-M05.01
Rev.001
Follow the upward motion of the inner casing cover with the
crane attached to the lifting device. Do not overload the lifting
cables.
Main Turbine
Mitsubishi
5-59
Chapter 5
Note
Ensure that the openings left by the removal of the inner
casing cover are protected.
CAUTION
When working in or over the condenser plenum, take special
care not to drop tools or debris into the condenser tube area.
Damage to the condenser tubes could result in tube leakage.
1
Match mark and remove the access cover plates to expose the
internal horizontal joint bolts.
Note
Refer to Appendix F to identify the bolts and determine the
Rev.001
Loosen and remove the nuts and washers from bolts 301 318 in the
following sequence:
MM-M05.01
(i)
5-60
Chapter 5
Note
Bolts 301 318 do not have provision for a bolt heater.
Note
During the operation of the turbine, oxides and the deposits
accumulate between the mating surfaces of the steam
chamber. The forces required to separate these surfaces may
be noticeably greater than those the required to suspend the
weight of the steam chamber cover.
Turn the jack screws half a turn at a time to open the horizontal joint
and maintain an equal gap at the horizontal joint openings.
CAUTION
Follow the upward motion of the steam chamber cover while
the crane is hoisting. Do not overload the wire rope slings.
Continue turning the jack screws, measuring for equal distance at all
points until the steam chamber cover is raised approximately 10 mm.
With the hook over the center of gravity, tension the wire ropes.
Make a trial lift to confirm that the cover horizontal joint is parallel to
the base horizontal joint.
10 Attach tag lines to each end of the steam chamber cover to control
any rotation of the steam chamber during the lift.
11 Evenly raise the steam chamber cover in small increments until the
cover is clear of the bolts.
12 Transport the steam chamber cover to the lay-down area.
Note
Rev.001
Ensure that the openings left in the LP1 casing are covered.
MM-M05.01
5-61
Chapter 5
Label the Gov End LP1 blade ring bolts and nuts with their respective
numbers and indicate RS or LS.
Loosen and remove the nuts and washers from bolts 401 403 in the
following sequence:
(i)
Install eye bolts into the LP1 blade ring upper half and tighten.
Lubricate and install jackscrews in the LP1 blade ring upper half
horizontal joint flange, and hand tighten until contact is made with the
lower half flange.
Note
During the operation of the turbine, oxides and the deposits
accumulate between the mating surfaces of the blade ring.
The forces required to separate these surfaces may be
noticeably greater than those the required to suspend the
weight of the upper half blade ring.
Turn the jack screws half a turn at a time to open the horizontal joint
and maintain an equal gap at the horizontal joint openings.
Connect suitable lifting gear to the blade ring upper half and make a
trial lift.
Adjust the chain blocks to evenly lift the blade ring upper half.
CAUTION
Carefully lift the upper half blade rings from the turbine
casings to avoid contact between the stationary and rotating
blades.
Rev.001
Lift the blade ring clear of the lower half joint bolts and transport it to
the lay-down area.
MM-M05.01
11 Using a similar procedure, remove the Gen End LP1 blade ring upper
half after removing the horizontal joint nut from bolts 404 406.
Main Turbine
Mitsubishi
5-62
Chapter 5
Remove the nuts and washers from the horizontal joint studs which
secure the LP1 inner flow guide ring upper half to the lower half.
Install eye bolts into the LP1 inner flow guide ring upper half and
tighten.
Lubricate and install jackscrews in the upper half inner flow guide ring
and hand tighten until contact is made with the lower half flange.
Turn the jack screws half a turn at a time to open the horizontal joint
and maintain an equal gap at the horizontal joint openings.
Connect suitable lifting gear to the upper half flow guide ring and
make a trial lift.
Adjust the chain blocks to evenly lift the upper half inner flow guide
ring.
Lift the upper half inner flow guide ring clear of the lower half joint
bolts and transport it to the lay-down area.
Note
As all axial clearances are based on the correct setting of the
rotor in the K position, the target tolerance is 0 mm.
MM-M05.01
Rev.001
Measure and record the clearances between the LP1 Gov End and Gen
End shaft glands and the surface of the rotor at the RS and LS as
described in the mechanical maintenance manual M 05.03, Gland
Steam Condenser System and GSC Exhaust Fan.
Main Turbine
Mitsubishi
5-63
Chapter 5
Note
Measure and record the following clearances at the RS and LS.
Measure and record the axial clearance (A) between the base of the
Gov End first stage stationary blade outlet and the shroud of the first
stage rotating blade inlet.
Note
Clearance A for the Gov End first stage is clearance K.
Measure and record the clearance B between the end of the first
stage stationary blade outlet and the base of the first stage rotating
blade inlet.
Measure and record the clearance F between the base of the first
stage rotating blade outlet and the end of the second stage stationary
blade inlet.
Measure and record the rotating and stationary blading seal strip
radial clearances.
Note
If the seal strip clearances exceed 200% of the design
clearances, seal strip replacement should be considered.
MM-M05.01
Rev.001
10 Repeat the above procedure to measure the LP1 Gen End rotor and
casing clearances.
Main Turbine
Mitsubishi
5-64
Chapter 5
Note
Before attempting to remove the rotor, it is necessary to
remove other equipment to eliminate interference or provide
clearance.
Install the LP rotor guide pillars (supplied as Special Tools) at the Gov
End and Gen End of the outer casing base, as shown in Figure 5-17.
Confirm that there is clearance between the HP-IP and LP1 coupling
flange faces.
Confirm that there is clearance between the LP1 and LP2 coupling
flange faces.
Install the LP rotor lifting gear to the LP1 rotor as shown in Appendix
H.
Adjust the wire rope slings from the center of the lifting beam to lift the
rotor evenly.
10 Using the turn buckle, level the rotor with a machinist spirit level.
11 Lift the LP1 rotor high enough to make sure that there is sufficient
axial clearance for the rotor removal.
MM-M05.01
Rev.001
12 Tie a tag line to each end of the LP1 rotor to allow control of the rotor
during the lift.
Main Turbine
Mitsubishi
5-65
Chapter 5
CAUTION
Slow and careful removal of the LP rotor must be performed to
ensure that damage does not occur to the rotor or casing
blades.
13
Lift the LP1 rotor in small increments and ensure that no binding
occurs.
14
15
16
Note
Ensure that the rotor journals are protected prior to setting the
rotor in the support stand.
Remove the set screws and then remove the nuts from the inner flow
guide ring fixing studs which secure the lower half inner flow guide
ring to the lower half steam chamber. Refer to Figure 5-19 for details.
Install eye bolts in the inner flow guide ring lower half.
Adjust the chain blocks to evenly lift the inner flow guide ring.
Transport the inner flow guide ring to the lay-down area and set it on
wooden blocks.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Install eye bolts in the lower half LP1 blade ring at the Gov End.
5-66
Chapter 5
Lift the lower half blade ring clear of the steam chamber base.
Transport the blade ring to the lay-down area and set it on wooden
blocks.
Following a similar procedure, remove the lower half LP1 blade ring
at the Gen End.
Remove the hexagonal socket head bolts which secure the steam
chamber base to the inner casing base.
Adjust the chain blocks to evenly lift the steam chamber base.
Lift the steam chamber base clear of the inner casing base.
Transport the steam chamber base to the lay-down area and set it on
wooden blocks.
Transport the inner casing base to the lay-down area and set it on
wooden blocks.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-67
Chapter 5
c)
Manually clean the following areas and the associated bolts and nuts:
(i)
Visually inspect the following areas for erosion, wear, steam cuts,
cracks, or other damage:
(i)
Note
Any discrepancies found should be corrected by stoning or
honing.
Rev.001
Note
MM-M05.01
Main Turbine
Mitsubishi
Visually inspect the following areas for erosion, wear, steam cuts,
cracks, or other damage:
5-68
Chapter 5
(i)
Note
Any discrepancies found should be corrected by stoning or
honing.
Visually inspect the following areas for erosion, wear, steam cuts,
cracks, or other damage:
(i)
Rev.001
(iii) Steam chamber to inner casing, LP blade ring and inner flow
guide fits
MM-M05.01
Main Turbine
Mitsubishi
5-69
Chapter 5
Note
Any discrepancies found should be corrected by stoning or
honing.
Note
Replace seal strips if damaged.
Note
Any discrepancies found should be corrected by stoning or
honing.
Rev.001
(i)
MM-M05.01
Main Turbine
Mitsubishi
5-70
Chapter 5
Visually inspect the stationary blade diaphragms to LP1 blade ring fits
and packing strips for looseness and wear.
Note
Replace seal rings if damaged.
Note
Any discrepancies found should be corrected by stoning or
honing.
Visually inspect the threaded portion of the joint bolts for deformation,
galling, binding or excessive wear.
LP1 Rotor
Rev.001
MM-M05.01
Note
Replace seal strips if damaged.
Main Turbine
Mitsubishi
5-71
Chapter 5
Retaining pin
Rotating blades
(ii) Shrouds
(iii) Erosion protection shields.
Note
Any discrepancies found should be corrected by stoning,
honing or component replacement.
Rotating blades
d)
Reassembly
Rev.001
MM-M05.01
Ensure that all components are free from burrs and bruises, blending
away the defects using fine files, carborundum stones and emery cloth.
All contact surfaces are to be cleaned before starting reassembly. The
reassembly procedure is described below:
Main Turbine
Mitsubishi
5-72
Chapter 5
CAUTION
Prior to the installation of turbine components, thoroughly
inspect the internals for foreign materials. Ensure that the
utmost standards of cleanliness are applied at all times.
Clean the inner casing base to outer casing and steam chamber
horizontal joint fit areas.
Clean and lubricate the dowel and mating areas on the inner casing
base.
Ensure that the liners are secured correctly to the inner casing base.
Refer to Figure 5-19 for details.
Make a trial lift and adjust to evenly lift the inner casing base.
Transport the inner casing base from the lay-down area to the LP1
turbine base and align it over the outer casing base.
Lower the inner casing slowly and evenly into the outer casing base
ensuring that the dowel engages the inner casing smoothly. Continue
to lower the inner casing until the horizontal joint is even with that of
the outer casing and the weight is on the outer casing base.
Replace and tighten the nuts onto the stud bolts and secure the inner
casing base to the outer casing base.
Install the dowel pins in the inner casing which locate the steam
chamber in the inner casing.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Clean the steam chamber base to inner casing, LP1 blade ring and
inner flow guide ring horizontal joint fit areas.
Clean and lubricate the dowel and mating areas on the steam
chamber base.
Ensure that the liners are secured correctly to the steam chamber
base. Refer to Figure 5-19 for details.
5-73
Chapter 5
Make a trial lift and adjust to evenly lift the steam chamber base.
Transport the steam chamber base from the lay-down area to the LP1
turbine and align it over the inner casing base.
Lower the steam chamber base slowly and evenly into the inner
casing base ensuring that the dowel engages the steam chamber
smoothly. Continue to lower the steam chamber base until the
horizontal joint is even with that of the inner casing and the weight is
on the inner casing base.
Replace and tighten the hexagonal socket head bolts and secure the
steam chamber base to the inner casing base.
Rev.001
Clean the Gov End LP1 blade ring to steam chamber horizontal joint
fit areas.
Clean and lubricate the dowel and mating areas on the lower half LP1
blade ring.
Install the dowel pins in the blade rings which locate the LP1 blade
rings in the steam chamber.
Install eye bolts in the lower half blade ring and tighten.
Make a trial lift and adjust to evenly lift the lower half blade ring.
Transport the lower half blade ring from the lay-down area to the LP1
turbine and align it over the steam chamber base.
Lower the lower half blade ring into the steam chamber base
ensuring that the dowel enters the steam chamber smoothly and the
horizontal joint is even with that of the steam chamber base.
Ensure that the lower liners are installed on the steam chamber base.
Replace the aligning plates on the lower half blade ring, if removed
during disassembly, and secure them with the hexagonal socket
head bolts. Refer to Figure 5-19 for details.
MM-M05.01
5-74
Chapter 5
Clean the lower half inner flow guide ring to steam chamber
horizontal joint fit areas.
Clean and lubricate the dowel and mating areas of the lower half
inner flow guide ring.
Install eye bolts on the inner flow guide ring and tighten.
Make a trial lift and adjust to evenly lift the inner flow guide ring.
Transport the inner flow guide ring lower half from the lay-down area
to the LP1 turbine and align it over the steam chamber.
Lower the inner flow guide ring slowly and evenly into the steam
chamber base and place it on the liners secured to the steam
chamber base until the horizontal joint is even with the horizontal joint
of the steam chamber and the weight is on the liners.
10 Lubricate the lower half inner flow guide ring fixing studs and install
the washers and nuts.
11 Tighten the nuts and install the set screws.
Install the lower halves of No.3 and No.4 bearings in their original
locations.
Visually inspect the LP1 casing base to make sure it is clean and free
of foreign objects before rotor installation.
Install the Gen End and Gov End rotor guide pillars.
Note
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Install the LP rotor lifting gear to the LP1 rotor in accordance with
Appendix H.
5-75
Chapter 5
Adjust the slings from the center of the lifting beam to lift the rotor
evenly and adjust the turnbuckles to make a level lift.
Move the LP1 rotor to the LP1 turbine and align it over the rotor guide
pillars.
Attach tag lines to each end of the rotor to control rotation of the rotor
during installation.
10 Place a machinist spirit level on the rotor shaft to check the level of
the rotor.
CAUTION
Take care when installing the rotor to ensure that the blading
and the journal areas are not damaged. Clearances between
the fixed and moving blades are limited, as required for
efficient operation. Damage to blading, bearings or rotor
journals can cause serious delays in assembly of the steam
turbine if additional repairs are required.
11 Lower the rotor slowly into the rotor guide pillars while constantly
watching the rotor level.
12 Stop lowering at any change in rotor inclination to determine and
eliminate the cause.
13 Slowly lower the rotor until it is supported by No.3 and No.4 bearings.
14 Check the bearing to journal contact using blue marking on the
journal surface.
15 Lift the rotor slowly, remove the blue marking and smear lubricating
oil on the bearing surfaces.
16 Lower the rotor slowly again until it is supported in the bearings.
17 Remove the rotor guide pillars and block the LP1 rotor to prevent
axial movement.
CAUTION
Rev.001
MM-M05.01
18 Rotate the LP1 rotor slowly to ensure that the rotor turns freely
without rubbing.
Main Turbine
Mitsubishi
5-76
Chapter 5
Note
As all axial clearances are based on the correct setting of the
rotor in the K position, the target tolerance is 0 mm.
Note
If LP1 turbine blade top and bottom clearances must be checked,
refer to Appendix G for the procedure.
Note
Measure and record the following clearances at the RS and LS.
Measure and record the axial clearance (A) between the base of the
Gov End first stage stationary blade outlet and the shroud of the first
stage rotating blade inlet.
Note
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Measure and record the clearance B between the end of the first
stage stationary blade outlet and the base of the first stage rotating
blade inlet.
5-77
Chapter 5
Measure and record the clearance F between the base of the first
stage rotating blade outlet and the end of the second stage stationary
blade inlet.
Measure and record the rotating and stationary blading seal strip
radial clearances.
Note
If the seal strip clearances exceed 200% of the design
clearances, seal strip replacement should be considered.
10 Repeat the above procedure to measure the LP1 Gen End rotor and
casing clearances.
Confirm that the oil clearances for No.3 and No.4 bearings are within
the acceptance criteria in accordance with mechanical maintenance
manual M05.04, Turbine Bearings and Thrust Bearing.
Install the upper halves of the No.3 and No.4 main bearings.
Install the coupling spacers for the HP-IP ~ LP1 and LP1 ~ LP2
couplings and the coupling bolts into the respective couplings in
accordance with mechanical maintenance manual M05.05.
Replace the coupling guards and restore the coupling cooling oil
connections.
Install the upper half of the coupling guards and the cooling oil lines
for the HP-IP ~ LP1 and LP1 ~ LP2 couplings.
Install the shaft gland seal ring upper halves in accordance with
mechanical maintenance manual M05.03.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Install eye bolts on the inner flow guide ring upper half.
Rig and transport the inner flow guide ring upper half over the LP1
rotor.
Apply a thin coat of triple boiled linseed oil to the horizontal joint
flanges or a special compound for flange surface.
5-78
Chapter 5
Lower the inner flow guide ring upper half slowly and evenly over the
joint studs until the horizontal joint is closed.
Install the safety hoist eye bolts on the Gov End LP1 blade ring upper
half.
Rig and transport the upper half blade ring over the LP1 turbine.
Apply a thin coat of triple boiled linseed oil or a special compound for
flange surface to the horizontal joint flanges and to the aligning plate
and liner surfaces.
Lower the upper half blade ring slowly and evenly over the lower half
blade ring until the horizontal joint is closed and the weight is on the
aligning plates.
CAUTION
Care must be taken when installing the upper half blade ring to
ensure that the turbine blading are not damaged. The blading
are installed with tight axial clearances which must remain
intact for correct operation. Damages to the blading can cause
serious delays in turbine assembly if additional repairs are
necessary.
6
Rev.001
Following a similar procedure, install the Gen End LP1 blade ring
upper half by torque-tightening the nuts on the reamer bolt 404 and
on the bolts 405 and 406.
MM-M05.01
Visually inspect the LP1 turbine for foreign material prior to installing
the steam chamber cover.
5-79
Chapter 5
CAUTION
When working in or over the condenser plenum, take special
care not to drop tools or debris into the condenser tube area.
Damage to the condenser tubes could result in tube leakage.
2
Install the safety hoist eye bolts on the steam chamber cover.
Rig and transport the steam chamber cover over the LP1 turbine.
Ensure that the upper liners are secured to the steam chamber cover.
Refer to Figure 5-19 for details.
Apply a thin coat of triple boiled linseed oil or a special compound for
flange surface to the horizontal joint flanges and to the liner surfaces.
Lower the steam chamber cover slowly and evenly over the dowels
and the horizontal joint studs until the horizontal joint is closed.
Visually inspect the LP1 casing for foreign material prior to installing
the inner casing cover.
CAUTION
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Install the inner casing guide bolts in the locations indicated in Figure
5-18.
Make a trial lift and adjust the chain blocks or turn buckle, to provide a
level lift.
5-80
Chapter 5
Transport the inner casing cover and position it above the inner
casing base.
Ensure that the liners are secured to the inner casing cover. Refer to
Figure 5-19 for details.
Align the inner casing cover with the inner casing guide bolts.
10 Apply a coat of triple boiled linseed oil or a special compound for the
flange surface of the inner casing horizontal joint and to the liner
surfaces.
11 Check that the inner casing cover horizontal joint is parallel to the
base horizontal joint.
12 Slowly lower and align the inner casing cover with the studs and
dowels.
13 Continue lowering the cover until the horizontal joint is closed.
14 Remove the lifting gear and the inner casing guide bolts.
15 Install the nuts and washers onto the studs and hand tighten.
Note
Refer to the Bolt Heating Data in Appendix F to identify the
bolts and determine the required heater type and size. Heat
the bolts in accordance with Bolt Heater Instruction in
Appendix I.
Note
Tighten the nuts without bolt heaters to the torque specified in
Rev.001
Appendix F.
Note
MM-M05.01
Main Turbine
Mitsubishi
5-81
Chapter 5
16 Install the nuts on the bolts 201 to 272 in the following sequence:
(i)
(ii) Torque tighten reamer bolts 201, 236, 242, 252, 264 and 272
(iii) Heat and tighten bolts 217 213 and 219 224
(iv) Torque tighten bolts 212 202 and 225 235
(v) Torque tighten bolts 241 237, 251 243, 263 255 and 271
267.
17 Install the access cover plates.
18 Slowly rotate the LP1 rotor to ensure that it turns freely.
19 Install the LP1 shaft gland casing upper halves.
Transport the outer casing cover over the outer casing base and align
it to the outer casing base.
Attach tag lines to each end of the outer casing cover to control the
rotation of the cover during installation.
Lubricate the outer casing cover horizontal flange with triple boiled
linseed oil or special compound for flange surface.
Slowly lower the outer casing cover, ensuring that the outer cover is
aligned with the outer casing base.
Lubricate the jack screws with Molykote and install them in the outer
casing cover.
10 Turn the jack screws in the outer casing cover until they protrude 10
mm below the horizontal joint.
Rev.001
11 Lower the outer casing cover slowly until the jack screws rest on the
horizontal joint of the outer casing base.
MM-M05.01
Main Turbine
Mitsubishi
5-82
Chapter 5
Note
Follow the downward motion of the outer casing cover with
the crane to ensure that the load is transferred to the jack
screws.
13 Continue to lower the outer casing cover until the horizontal joint is
closed.
14 Remove the lifting gear.
15 Place the washers over the open bolt holes in the outer casing cover
flange.
16 Install the nuts on top of the bolts and tighten.
17 Tighten the outer casing horizontal joint flange bolts in a diametrically
opposite pattern in the following order:
(i)
Reamer bolts.
(ii) Joint bolts starting at the gland bores working outward toward the
corners (transverse direction).
(iii) Joint bolts starting at the transverse centerline towards the
corners (longitudinal direction).
18 Replace the top seal ring between the outer casing cover and the
inner casing cover.
Note
The following items 19 to 22 are performed inside the LP outer
casing cover. Refer to Figure 5-18.
19 Install the lifting gear, and evenly lower the LP exhaust flow guides
into place aligning the eccentric pins as they are lowered.
20 Install and securely tighten the flange bolts into the Gov End and the
Gen End exhaust flow guide upper halves.
21 Remove the lifting gear and jack screws.
22 Install the spray nozzle piping to the exhaust flow guides.
23 Install the lifting gear on the manhole covers.
Rev.001
MM-M05.01
25 Install a new gasket on the manhole cover and lower into place.
26 Remove the eye bolts.
27 Install the cover flange bolts and tighten.
Main Turbine
Mitsubishi
5-83
Chapter 5
Return to Service
Have the electricians connect thermocouple lead wires to the outer
casing cover.
Replace the insulation and metal cladding removed from the turbine.
Confirm that all instruments removed for the overhaul have been
installed and are available.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-84
Chapter 5
0.3~0.5
0.3~0.5
0.2+-0.05
0.2+-0.05
STEAM
CHAMBER
STEAM
CHAMBER
STEAM CHAMBER
STEAM CHAMBER
0.2+-0.05
0.2+-0.05
INNER CASING
INNER CASING
E
E
A
B
STATIONARY BLADE
6R
7R
5C
A
B
4R
5R
4C
A
B
3C
3R
A 2C 1C A
B B
2R
7C
4C
E
E
1R
A 1C
A
B
2C A 3C A
B
1R
B
2R
3R
4R
5R
GEN. SIDE
E
5C
7C
6C
STATIONARY BLADE
6R
7R
F
RIGHT SIDE
LEFT SIDE
LP1 ROTOR
Rev.001
INNER CASING
1
2
3
4
5
6
7
1
2
3
4
5
6
7
13.5
13.5
13.5
13.5
35.5
32.6
46.1
14.3
14.3
14.3
14.3
13.7
16.1
16.1
24.5
50.6
24.5
37.6
25.3
51.4
25.3
37.6
27.1
27.1
24.5
24.5
24.5
46.5
43.6
57.1
25.3
25.3
25.3
25.3
24.7
27.1
27.1
13.5
39.6
13.5
26.6
14.3
40.4
14.3
26.6
16.1
16.1
-
LP1 ROTOR
INNER FLOW
GUIDE
6C
MM-M05.01
24.5 +1.5
-0.5
0.2+-0.05
0.2 +-0.05
16.1 +1.5
-0.5
INNER FLOW
GUIDE
27.1 +1.5
-0.5
STATIONARY BLADE
6C
INNER CASING
STATIONARY BLADE
Main Turbine
Mitsubishi
K=24.5 +- 0.0
GOV. SIDE
6C
ROW No.
7C
ROW No.
7C
MPTD-3-0249
5-85
Chapter 5
SEAL RING
SEAL RING
GLAND
CASING
0.5+-0.1
GLAND
CASING
0.5+-0.1
X
SEAL STRIP
SEAL STRIP
OUTER CASING
COVER
CL OF LP1 ROTOR
GLAND
CASING
0.5+-0.1
SEAL STRIP
GLAND
CASING
LP1 ROTOR
0.5+-0.1
SEAL STRIP
LP1 ROTOR
MM-M05.01
Rev.001
NOTE: REFER TO FIGURE 5-16 FOR BLADE SEAL RADIAL CLEARANCES (X)
MPTD-4-0250
FIGURE 5-12
Main Turbine
Mitsubishi
5-86
Chapter 5
SEAL RING
SEAL RING
GLAND
CASING
0.5+-0.1
GLAND
CASING
0.5+-0.1
X
SEAL STRIP
SEAL STRIP
OUTER CASING
COVER
C
L OF LP1 ROTOR
GLAND
CASING
LP1 ROTOR
SEAL STRIP
GLAND
CASING
0.5+-0.1
0.5+- 0.1
LP1 ROTOR
SEAL STRIP
MM-M05.01
Rev.001
NOTE: REFER TO FIGURE 5-16 FOR BLADE SEAL RADIAL CLEARANCES (X)
MPTD-4-0251
FIGURE 5-13
Main Turbine
Mitsubishi
5-87
Chapter 5
0.3 0.1
STATIONARY BLADE
+-
ROTATING BLADE
INNER CASING
ROTATING BLADE
INNER CASING
6R
0.3 0.1
SEAL STRIP
5R
4R
EXHAUST
FLOW GUIDE
7C
3R
7R
ROTATING BLADE
LP1 BLADE RING
ROTATING
BLADE
6C
SEAL STRIP
5C
1R
4C
2R
1C
2C
0.3 0.1
3C
STATIONARY
BLADE
LP1 ROTOR
0.0
1R
2R
3R
4R
5R
7C
6R
7R
ROTATING BLADE
7.5
1C
LP1 ROTOR
27.1
0.3 0.1
STATIONARY
BLADE
6C
4C
5C
LP1 ROTOR
3C
2C
STATIONARY BLADE
MM-M05.01
Rev.001
3
SEAL STRIP
MPTD-3-0252
LP1 ROTOR
SEAL STRIP
NOTE: REFER TO FIGURE 5-16 FOR BLADE SEAL RADIAL CLEARANCES (X)
FIGURE 5-14
Main Turbine
Mitsubishi
5-88
Chapter 5
0.3 0.1
STATIONARY BLADE
+-
ROTATING BLADE
INNER CASING
ROTATING BLADE
6R
INNER CASING
0.3 0.1
5R
SEAL STRIP
EXHAUST
FLOW GUIDE
4R
7C
3R
7R
ROTATING BLADE
ROTATING
BLADE
6C
SEAL STRIP
5C
STATIONARY
BLADE
3C
2C
4C
0.3 0.1
1C
2R
1R
LP1 ROTOR
6R
7R
5R
4R
3R
ROTATING BLADE
2R 1R
3.5
0.0
7C
1C
LP1 ROTOR
16.1
0.3 0.1
0.5
0.5
STATIONARY
BLADE
4C
5C
6C
3C
2C
Rev.001
LP1 ROTOR
STATIONARY BLADE
MM-M05.01
MPTD-3-0253
SEAL STRIP
LP1 ROTOR
SEAL STRIP
NOTE: REFER TO FIGURE 5-16 FOR BLADE SEAL RADIAL CLEARANCES (X)
FIGURE 5-15
Main Turbine
Mitsubishi
5-89
Chapter 5
NOMINAL CLEA.
ELEMENT
OUTER GLAND
(GOV. END)
LOCATION
LENGTH
407.75
481.25
555.75
629.75
1.20
1.20
1.20
1.20
0.95
0.90
0.90
0.90
0.25
0.25
0.25
0.25
-0.01
-0.02
-0.03
-0.04
0.00
0.00
0.00
0.00
1.46
1.47
1.48
1.49
0.69
0.63
0.62
0.61
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.46
1.47
1.48
1.49
0.69
0.63
0.62
0.61
974.85
10.00
10.00
0.25
-0.06
0.00
10.31
9.69
0.00
0.00
10.31
9.69
1433.10
1536.50
1641.40
1816.50
1911.90
1990.20
2050.05
2104.40
2154.70
2232.00
2282.30
2333.50
2379.80
2725.20
2771.50
2822.70
2873.00
2950.30
3000.60
3054.95
3114.80
3193.10
3288.50
3463.60
3568.50
3671.90
2.67
4.00
1.65
2.00
1.50
1.60
1.50
1.30
1.10
1.30
1.10
1.30
1.10
1.10
1.30
1.10
1.30
1.10
1.30
1.50
1.60
1.50
2.00
1.65
4.00
2.67
2.67
4.00
1.65
2.00
1.50
1.60
1.50
1.30
1.10
1.30
1.10
1.30
1.10
1.10
1.30
1.10
1.30
1.10
1.30
1.50
1.60
1.50
2.00
1.65
4.00
2.67
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
-0.08
-0.09
-0.09
-0.10
-0.10
-0.11
-0.11
-0.11
-0.11
-0.11
-0.12
-0.12
-0.12
-0.12
-0.12
-0.12
-0.11
-0.11
-0.11
-0.11
-0.11
-0.10
-0.10
-0.09
-0.09
-0.08
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
3.00
4.34
1.99
2.35
1.85
1.96
1.86
1.66
1.46
1.66
1.47
1.67
1.47
1.47
1.67
1.47
1.66
1.46
1.66
1.86
1.96
1.85
2.35
1.99
4.34
3.00
2.34
3.66
1.31
1.65
1.15
1.24
1.14
0.94
0.74
0.94
0.73
0.93
0.73
0.73
0.93
0.73
0.94
0.74
0.94
1.14
1.24
1.15
1.65
1.31
3.66
2.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
3.00
4.34
1.99
2.35
1.85
1.96
1.86
1.66
1.46
1.66
1.47
1.67
1.47
1.47
1.67
1.47
1.66
1.46
1.66
1.86
1.96
1.85
2.35
1.99
4.34
3.00
4130.15
10.00
10.00
0.25
-0.06
0.00
10.31
9.69
0.00
0.00
4475.25
4549.25
4623.75
4697.25
1.20
1.20
1.20
1.20
0.90
0.90
0.90
0.95
0.25
0.25
0.25
0.25
-0.03
-0.03
-0.02
-0.01
0.00
0.00
0.00
0.00
1.48
1.48
1.47
1.46
0.62
0.62
0.63
0.69
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
LP7C (GOV.)
LP6R (GOV.)
LP6C (GOV.)
LP5R (GOV.)
LP5C (GOV.)
LP4R (GOV.)
LP4C (GOV.)
LP3R (GOV.)
LP3C (GOV.)
LP2R (GOV.)
LP1 BLADE RING
LP2C (GOV.)
(GOV. END)
LP1R (GOV.)
STEAM FLOW
GUIDE INLET
LP1R (GEN.)
LP1 BLADE RING
LP2C (GEN.)
(GEN. END)
LP2R (GEN.)
LP3C (GEN.)
LP3R (GEN.)
LP4C (GEN.)
LP4R (GEN.)
LP5C (GEN.)
LP5R (GEN.)
LP6C (GEN.)
LP6R (GEN.)
LP7C (GEN.)
LP7R (GEN.)
OUTER GLAND
(GEN END)
HORIZONTAL DIRECTION
AFT. ASS'Y
CASING DEFLEC.
NOMINAL CLEA.
23
24
0.75
0.50
0.50
0.50
0.00
0.00
0.00
0.00
10.00
10.00
+0.10
-0.05
2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67
9.69
+0.50
-0.00
0.62
0.62
0.63
0.69
+0.15
-0.05
29
30
6
7
8
9
10
11
10 11
29 30
ROTOR AFT. ASY AFT. ASY CASING CASING AT SET. AT SET.
FROM
AFT. ASY AFT. ASY CASING CASING AT SET. AT SET. TOLERANCE
NOMINAL NOMINAL ELEMENT ROTOR
NOMINAL NOMINAL ELEMENT ROTOR
TOLERANCE
No.3 BRG. TOP
SETTING
DEFLEC.
SETTING
SETTING
SETTING
RIGHT
LEFT
DEFLEC.
DEFLEC.
BOTTOM
RIGHT
LEFT
BOTTOM
LEFT
RIGHT
TOP
BOTTOM DEFLEC. DEFLEC. TOP
CLEARA. CLEARA.
LEFT
CLEARA. CLEARA.
CLEARA. CLEARA.
CLEARA. CLEARA. RIGHT
BOTTOM CLEARA. CLEARA.
CLEARA. CLEARA. TOP
NOTE:
1. RADIAL CLEARANCES AT ASSEMBLY OF LP-1 TURBINE
IS AS SHOWN IN THIS DRAWING IN CASE THAT SETTING
OF EACH PART AND DEFLECTION OF THE ROTOR IS
TAKEN INTO ACCOUNT.
25
26
27
28
0.00
0.00
0.00
0.00
0.75
0.50
0.50
0.50
0.75
0.50
0.50
0.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.75
0.50
0.50
0.50
0.75
0.50
0.50
0.50
+0.15
-0.15
0.00
0.00
10.00
10.00
0.00
0.00
10.00
10.00
+0.50
-0.00
2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67
2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67
2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67
+0.10
-0.05
10.00
10.00
0.00
0.00
10.00
10.00
0.00
0.00
10.00
10.00
+0.50
-0.00
0.50
0.50
0.50
0.75
0.50
0.50
0.50
0.75
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.50
0.50
0.50
0.75
0.50
0.50
0.50
0.75
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.50
0.50
0.50
0.75
0.50
0.50
0.50
0.75
+0.15
-0.05
21
22
+0.15
-0.05
0.75
0.50
0.50
0.50
+0.50
-0.00
2.34
3.66
1.31
1.65
1.15
1.24
1.14
0.94
0.74
0.94
0.73
0.93
0.73
0.73
0.93
0.73
0.94
0.74
0.94
1.14
1.24
1.15
1.65
1.31
3.66
2.34
10.31
1.48
1.48
1.47
1.46
TOP CLEARANCE
+
+
- 5
24
25
BOTTOM CLEARANCE
Rev.001
MM-M05.01
MPTD-3-0254
FIGURE 5-16
Main Turbine
Mitsubishi
5-90
MM-M05.01
Rev.001
Chapter 5
FIGURE 5-17
Main Turbine
Mitsubishi
5-91
Chapter 5
3
A
HORIZONTAL JOINT
2
A
B-B
B-B
8
DETAIL "D"
MM-M05.01
Rev.001
DETAIL "C"
FIGURE 5-18
Main Turbine
Mitsubishi
5-92
Chapter 5
16
4
20
8
7
21
E
6
B
6
7
8
20
HORIZONTAL JOINT
21
2
18
16
21
A-A
FLOW GUIDE
20 INNER
(LOWER HALF)
E-E
B-B
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
ALIGNING PLATE
13
8
16
12
15
18
14
19
15
17
17
17
3
12
16
14
HORIZONTAL JOINT
"X"
18
11
11
13
H-H
18
Rev.001
18
F-F
20
16
13
DETAIL "X"
16
G-G
STEAM CHAMBER SUPPORT
MM-M05.01
MPTD-3-0626
FIGURE 5-19
Main Turbine
Mitsubishi
5-93
Chapter 5
5.3
Preparation
If LP2 turbine disassembly becomes necessary, all associated equipment
must be mechanically and electrically isolated and an authorized
clearance and work permit must be in place prior to the commencement of
work. The following points must also to be considered when preparing for
disassembly and reassembly:
CAUTION
Spigot joints between the turbine stationary components
(such as outer and inner casings, blade rings, etc.) could bind
due to scale formation during operation under the high
temperature environment.
CAUTION
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-94
Chapter 5
CAUTION
Personnel working inside the turbine should not carry any
loose items in their pockets and should take special care not
to drop tools or debris into the turbine.
CAUTION
Any surface irregularity or damage caused by the reasons
described above, must be ground off smoothly, or
reconditioned by build-up welding and facing to reinstate the
original surface finish and clearance if any between mating
parts.
CAUTION
Wear proper goggles and face masks when working on the
insulation. Insulation material is harmful to the respiratory
system.
b)
Disassembly
Refer to Figures 2-10 and E-2.
During normal operation, before the Unit is shut down for overhaul,
perform a thorough external visual inspection of the entire turbine unit
to detect any obvious deficiencies. These are to be rectified during
the turbine overhaul.
Note
Label and identify all components as they are disassembled.
Tag and bag all hardware and fasteners with the associated
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Remove the insulation from the IP turbine exhaust to LP1 and LP2
turbines steam inlet flanges.
5-95
Chapter 5
Refer to Figure 2-14. Remove the nuts from the flange joints and then
remove the crossover piping connecting the IP exhaust to the LP1
and LP2 turbines inlet. Remove the top seal ring from between the
LP2 inner and outer casings.
Loosen the flange bolts on all LP2 outer casing manhole covers.
Support the weight of the manhole covers using the lifting gear.
Remove the Gov End and Gen End shaft upper half gland casings
and remove the seal rings from the gland casings into storage.
Note
The following steps 10~15, to disassemble the Gov End and
Gen End exhaust flow guides are performed inside the outer
casing. Refer to Figure 5-18.
Rev.001
14 Adjust the lifting gear to support the weight of exhaust flow guide
upper half, and alternately tighten the jack screws and loosen the
adjacent bolts until the locating eccentric pins have been pulled free
from the inner casing.
MM-M05.01
15 Remove the jackscrews from the flange, lift the exhaust flow guide
upper half, and fasten it securely to the inside of the outer casing
cover.
16 Remove the horizontal joint bolts from the LP2 outer casing base.
Main Turbine
Mitsubishi
5-96
Chapter 5
17 Install jack screws in the outer casing cover horizontal joint flange and
manually tighten to contact the outer casing base horizontal joint
face.
18 Turn the jack screws half a turn at a time to open the horizontal joint,
maintaining equal loading on the jack screws and equal gap at the
horizontal joint opening.
Note
During operation of the turbine, oxides and deposits
accumulate between the mating surfaces of the casings. The
forces required to separate these surfaces may be noticeably
greater than those required to suspend the weight of the outer
casing cover.
19 Install the lifting gear to the LP2 outer casing cover in accordance
with Appendix H.
20 Tension the wire ropes and position the hook over the center of
gravity, make a trial lift and adjust the lifting equipment until an even
lift is achieved.
CAUTION
Follow the upward motion of the LP2 outer casing with the
crane attached to the lifting device. Do not overload the lifting
cables.
21 Attach a tag line to each end of the LP2 outer casing cover to control
any rotation of the casing during the lift.
22 Evenly raise the LP2 outer casing cover in small increments until it
stands clear of the bolts.
23 Lift the LP2 outer casing cover clear of the turbine and transport it to
the lay-down area.
24 Set wooden supports on the floor to support the outer casing cover.
25 Protect the horizontal joints of the LP2 outer casing cover.
26 Lower the LP2 outer casing cover onto the wooden supports.
27 Disconnect and remove the lifting gear.
Rev.001
Note
Ensure that the openings in the lower half turbine exposed by
the removal of the outer casing cover are protected. It is
MM-M05.01
Main Turbine
Mitsubishi
5-97
Chapter 5
CAUTION
When working in or over the condenser plenum, take special
care not to drop tools or debris into the condenser tube area.
Damage to the condenser tubes could result in condenser tube
leakage.
Match mark and remove the access cover plates to expose the
internal horizontal joint bolts.
Note
Refer to Appendix F to identify the horizontal joint bolts, and
to determine the required bolt heater type and size. Remove
the bolts from both LS and RS of the LP2 inner casing starting
at the transverse centerline of both LS and RS, working
outwards toward each end. Remove the bolts parallel to the
transverse axis starting at the extreme end and working
towards the turbine longitudinal axis.
Using four bolt heaters (two on each side), heat the bolts 513 524 in
accordance with Bolt Heater Instruction in Appendix I, avoiding
heating adjacent bolts, and loosen the nuts from both the RS and LS
of the casing in the following sequence:
(i)
Note
Rev.001
MM-M05.01
Main Turbine
Mitsubishi
5-98
Chapter 5
Install safety hoist ring and copper washer into the nut to be
removed.
(ii) Connect suitable lifting gear to the safety hoist ring and remove
the nuts.
5
Loosen and remove the nuts from bolts 501 512 and 525 572 in
the following sequence:
Note
Bolts 501 512 and 525 572 do not have provision for a bolt
heater.
(i)
(ii) Bolts 537 541, 543 551, 555 563, 567 571
(iii) Reamer bolts 501 and 536
(iv) Reamer bolts 542, 552, 564 and 572.
6
Lubricate and install jackscrews into the inner casing cover horizontal
joint flange and hand tighten until contact is made with the inner
casing base horizontal joint flange.
Note
During the operation of the turbine, oxides and the deposits
accumulate between the mating surfaces of the casings. The
forces required to separate these surfaces may be noticeably
greater than those required to suspend the weight of the inner
casing cover.
Install the inner casing guide bolts (supplied as Special Tools) on the
inner casing base as indicated in Figure 5-17.
Turn the jack screws half a turn at a time to open the horizontal joint
and maintain an equal gap at the horizontal joint openings.
CAUTION
MM-M05.01
Rev.001
Follow the upward motion of the inner casing cover with the
crane attached to the lifting device. Do not overload the lifting
cables.
Main Turbine
Mitsubishi
5-99
Chapter 5
Note
Ensure that the openings left by the removal of the inner
casing cover are protected.
CAUTION
When working in or over the condenser plenum, take special
care not to drop tools or debris into the condenser tube area.
Damage to the condenser tubes could result in tube leakage.
Match mark and remove the access cover plates to expose the
internal horizontal joint bolts.
Note
Refer to Appendix F to identify the bolts and determine the
required torque values.
Rev.001
Loosen and remove the nuts and washers from bolts 601 618 in the
following sequence:
(i)
MM-M05.01
Main Turbine
Mitsubishi
5-100
Chapter 5
Note
Bolts 601 618 do not have provision for a bolt heater.
Note
During the operation of the turbine, oxides and the deposits
accumulate between the mating surfaces of the steam
chamber. The forces required to separate these surfaces may
be noticeably greater than those the required to suspend the
weight of the steam chamber cover.
Turn the jack screws half a turn at a time to open the horizontal joint
and maintain an equal gap at the horizontal joint openings.
CAUTION
Follow the upward motion of the steam chamber cover while
the crane is hoisting. Do not overload the wire rope slings.
Continue turning the jack screws, measuring for equal distance at all
points until the steam chamber cover is raised approximately 10 mm.
With the hook over the center of gravity, tension the wire ropes.
Make a trial lift to confirm that the cover horizontal joint is parallel to
the base horizontal joint.
Attach tag lines to each end of the steam chamber cover to control
any rotation of the steam chamber during the lift.
10 Evenly raise the steam chamber cover in small increments until the
cover is clear of the bolts.
11 Transport the steam chamber cover to the lay-down area.
Note
Rev.001
Ensure that the openings left in the LP2 casing are covered.
MM-M05.01
5-101
Chapter 5
Label the Gov End LP2 blade ring bolts and nuts with their respective
numbers and indicate RS or LS.
Loosen and remove the nuts and washers from bolts 701 704 in the
following sequence:
(i)
Install eye bolts into the LP2 blade ring upper half and tighten.
Lubricate and install jackscrews in the LP2 blade ring upper half
horizontal joint flange, and hand tighten until contact is made with the
lower half flange.
Note
During the operation of the turbine, oxides and the deposits
accumulate between the mating surfaces of the blade ring.
The forces required to separate these surfaces may be
noticeably greater than those the required to suspend the
weight of the upper half blade ring.
Turn the jack screws half a turn at a time to open the horizontal joint
and maintain an equal gap at the horizontal joint openings.
Connect suitable lifting gear to the blade ring upper half and make a
trial lift.
Adjust the chain blocks to evenly lift the blade ring upper half.
CAUTION
Carefully lift the upper half blade rings from the turbine
casings to avoid contact between the stationary and rotating
blades.
Rev.001
Lift the blade ring clear of the lower half joint bolts and transport it to
the lay-down area.
MM-M05.01
11 Using a similar procedure, remove the Gen End LP2 blade ring upper
half after removing the horizontal joint nut from bolts 705 708.
Main Turbine
Mitsubishi
5-102
Chapter 5
Remove the nuts and washers from the horizontal joint studs which
secure the LP2 inner flow guide ring upper half to the lower half.
Install eye bolts into the LP2 inner flow guide ring upper half and
tighten.
Lubricate and install jackscrews in the upper half inner flow guide ring
and hand tighten until contact is made with the lower half flange.
Turn the jack screws half a turn at a time to open the horizontal joint
and maintain an equal gap at the horizontal joint openings.
Connect suitable lifting gear to the upper half flow guide ring and
make a trial lift.
Adjust the chain blocks to evenly lift the upper half inner flow guide
ring.
Lift the upper half inner flow guide ring clear of the lower half joint
bolts and transport it to the lay-down area.
Note
As all axial clearances are based on the correct setting of the
rotor in the K position, the target tolerance is 0 mm.
MM-M05.01
Rev.001
Measure and record the clearances between the LP2 Gov End and Gen
End shaft glands and the surface of the rotor at the RS and LS as
described in the mechanical maintenance manual M 05.03, Gland
Steam Condenser System and GSC Exhaust Fan.
Main Turbine
Mitsubishi
5-103
Chapter 5
Note
Measure and record the following clearances at the RS and LS.
Measure and record the axial clearance (A) between the base of the
Gov End first stage stationary blade outlet and the shroud of the first
stage rotating blade inlet.
Note
Clearance A for the Gov End first stage is clearance K.
Measure and record the clearance B between the end of the first
stage stationary blade outlet and the base of the first stage rotating
blade inlet.
Measure and record the clearance F between the base of the first
stage rotating blade outlet and the end of the second stage stationary
blade inlet.
Measure and record the rotating and stationary blading seal strip
radial clearances.
Note
If the seal strip clearances exceed 200% of the design
clearances, seal strip replacement should be considered.
MM-M05.01
Rev.001
10 Repeat the above procedure to measure the LP2 Gen End rotor and
casing clearances.
Main Turbine
Mitsubishi
5-104
Chapter 5
Note
Before attempting to remove the rotor, it is necessary to
remove other equipment to eliminate interference or provide
clearance.
Install the LP rotor guide pillars (supplied as Special Tools) at the Gov
End and Gen End of the outer casing base, as shown in Figure 5-17.
Confirm that there is clearance between the LP1 and LP2 coupling
flange faces.
Install the LP rotor lifting gear to the LP2 rotor as shown in Appendix
H.
Adjust the wire rope slings from the center of the lifting beam to lift the
rotor evenly.
10 Using the turn buckle, level the rotor with a machinist spirit level.
11 Lift the LP2 rotor high enough to make sure that there is sufficient
axial clearance for the rotor removal.
MM-M05.01
Rev.001
12 Tie a tag line to each end of the LP2 rotor to allow control of the rotor
during the lift.
Main Turbine
Mitsubishi
5-105
Chapter 5
CAUTION
Slow and careful removal of the LP rotor must be performed to
ensure that damage does not occur to the rotor or casing
blades.
13
Lift the LP2 rotor in small increments and ensure that no binding
occurs.
14
15
16
Note
Ensure that the rotor journals are protected prior to setting the
rotor in the support stand.
Remove the set screws and then remove the nuts from the inner flow
guide ring fixing studs which secure the lower half inner flow guide
ring to the lower half steam chamber. Refer to Figure 5-19 for details.
Install eye bolts in the inner flow guide ring lower half.
Adjust the chain blocks to evenly lift the inner flow guide ring.
Transport the inner flow guide ring to the lay-down area and set it on
wooden blocks.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Install eye bolts in the lower half LP2 blade ring at the Gov End.
5-106
Chapter 5
Lift the lower half blade ring clear of the steam chamber base.
Transport the blade ring to the lay-down area and set it on wooden
blocks.
Following a similar procedure, remove the lower half LP2 blade ring
at the Gen End.
Remove the hexagonal socket head bolts which secure the steam
chamber base to the inner casing base.
Adjust the chain blocks to evenly lift the steam chamber base.
Lift the steam chamber base clear of the inner casing base.
Transport the steam chamber base to the lay-down area and set it on
wooden blocks.
Transport the inner casing base to the lay-down area and set it on
wooden blocks.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-107
Chapter 5
c)
Manually clean the following areas and the associated bolts and nuts:
(i)
Visually inspect the following areas for erosion, wear, steam cuts,
cracks, or other damage:
(i)
Note
Any discrepancies found should be corrected by stoning or
honing.
Rev.001
Note
MM-M05.01
Main Turbine
Mitsubishi
Visually inspect the following areas for erosion, wear, steam cuts,
cracks, or other damage:
5-108
Chapter 5
(i)
Note
Any discrepancies found should be corrected by stoning or
honing.
Visually inspect the following areas for erosion, wear, steam cuts,
cracks, or other damage:
(i)
Rev.001
(iii) Steam chamber to inner casing, LP blade ring and inner flow
guide fits
MM-M05.01
Main Turbine
Mitsubishi
5-109
Chapter 5
Note
Any discrepancies found should be corrected by stoning or
honing.
Note
Replace seal strips if damaged.
Note
Any discrepancies found should be corrected by stoning or
honing.
Rev.001
(i)
MM-M05.01
Main Turbine
Mitsubishi
5-110
Chapter 5
Visually inspect the stationary blade diaphragms to LP2 blade ring fits
and packing strips for looseness and wear.
Note
Replace seal rings if damaged.
Note
Any discrepancies found should be corrected by stoning or
honing.
Visually inspect the threaded portion of the joint bolts for deformation,
galling, binding or excessive wear.
LP2 Rotor
Rev.001
MM-M05.01
Note
Replace seal strips if damaged.
Main Turbine
Mitsubishi
5-111
Chapter 5
Retaining pin
Rotating blades
(ii) Shrouds
(iv) Erosion protection shields.
Note
Any discrepancies found should be corrected by stoning,
honing or component replacement.
Rotating blades
d)
Reassembly
Rev.001
MM-M05.01
Ensure that all components are free from burrs and bruises, blending
away the defects using fine files, carborundum stones and emery cloth.
All contact surfaces are to be cleaned before starting reassembly. The
reassembly procedure is described below:
Main Turbine
Mitsubishi
5-112
Chapter 5
CAUTION
Prior to the installation of turbine components, thoroughly
inspect the internals for foreign materials. Ensure that the
utmost standards of cleanliness are applied at all times.
Clean the inner casing base to outer casing and steam chamber
horizontal joint fit areas.
Clean and lubricate the dowel and mating areas on the inner casing
base.
Ensure that the liners are secured correctly to the inner casing base.
Refer to Figure 5-19 for details.
Make a trial lift and adjust to evenly lift the inner casing base.
Transport the inner casing base from the lay-down area to the LP2
turbine base and align it over the outer casing base.
Lower the inner casing slowly and evenly into the outer casing base
ensuring that the dowel engages the inner casing smoothly. Continue
to lower the inner casing until the horizontal joint is even with that of
the outer casing and the weight is on the outer casing base.
Replace and tighten the nuts onto the stud bolts and secure the inner
casing base to the outer casing base.
Install the dowel pins in the inner casing which locate the steam
chamber in the inner casing.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Clean the steam chamber base to inner casing, LP2 blade ring and
inner flow guide ring horizontal joint fit areas.
Clean and lubricate the dowel and mating areas on the steam
chamber base.
Ensure that the liners are secured correctly to the steam chamber
base. Refer to Figure 5-19 for details.
5-113
Chapter 5
Make a trial lift and adjust to evenly lift the steam chamber base.
Transport the steam chamber base from the lay-down area to the LP2
turbine and align it over the inner casing base.
Lower the steam chamber base slowly and evenly into the inner
casing base ensuring that the dowel engages the steam chamber
smoothly. Continue to lower the steam chamber base until the
horizontal joint is even with that of the inner casing and the weight is
on the inner casing base.
Replace and tighten the hexagonal socket head bolts and secure the
steam chamber base to the inner casing base.
Rev.001
Clean the Gov End LP2 blade ring to steam chamber horizontal joint
fit areas.
Clean and lubricate the dowel and mating areas on the lower half LP2
blade ring.
Install the dowel pins in the LP2 blade rings which locate the blade
rings in the steam chamber base.
Install eye bolts in the lower half blade ring and tighten.
Make a trial lift and adjust to evenly lift the lower half blade ring.
Transport the lower half blade ring from the lay-down area to the LP2
turbine and align it over the steam chamber base.
Lower the lower half blade ring into the steam chamber base
ensuring that the dowel enters the steam chamber smoothly and the
horizontal joint is even with that of the steam chamber base.
Ensure that the lower liners are installed on the steam chamber base.
Replace the aligning plates on the lower half blade ring, if removed
during disassembly, and secure them with the hexagonal socket
head bolts. Refer to Figure 5-19 for details.
MM-M05.01
5-114
Chapter 5
Clean the lower half inner flow guide ring to steam chamber
horizontal joint fit areas.
Clean and lubricate the dowel and mating areas of the lower half
inner flow guide ring.
Install eye bolts on the inner flow guide ring and tighten.
Make a trial lift and adjust to evenly lift the inner flow guide ring.
Transport the inner flow guide ring lower half from the lay-down area
to the LP2 turbine and align it over the steam chamber.
Lower the inner flow guide ring slowly and evenly into the steam
chamber base and place it on the liners secured to the steam
chamber base until the horizontal joint is even with the horizontal joint
of the steam chamber and the weight is on the liners.
10 Lubricate the lower half inner flow guide ring fixing studs and install
the washers and nuts.
11 Tighten the nuts and install the set screws.
Install the lower halves of No.5 and No.6 bearings in their original
locations.
Visually inspect the LP2 casing base to make sure it is clean and free
of foreign objects before rotor installation.
Install the Gen End and Gov End rotor guide pillars.
Note
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Install the LP rotor lifting gear to the LP2 rotor in accordance with
Appendix H.
5-115
Chapter 5
Adjust the slings from the center of the lifting beam to lift the rotor
evenly and adjust the turnbuckles to make a level lift.
Move the LP2 rotor to the LP2 turbine and align it over the rotor guide
pillars.
Attach tag lines to each end of the rotor to control rotation of the rotor
during installation.
10 Place a machinist spirit level on the rotor shaft to check the level of
the rotor.
CAUTION
Take care when installing the rotor to ensure that the blading
and the journal areas are not damaged. Clearances between
the fixed and moving blades are limited, as required for
efficient operation. Damage to blading, bearings or rotor
journals can cause serious delays in assembly of the steam
turbine if additional repairs are required.
11 Lower the rotor slowly into the rotor guide pillars while constantly
watching the rotor level.
12 Stop lowering at any change in rotor inclination to determine and
eliminate the cause.
13 Slowly lower the rotor until it is supported by No.5 and No.6 bearings.
14 Check the bearing to journal contact using blue marking on the
journal surface.
15 Lift the rotor slowly, remove the blue marking and smear lubricating
oil on the bearing surfaces.
16 Lower the rotor slowly again until it is supported in the bearings.
17 Remove the rotor guide pillars and block the LP2 rotor to prevent
axial movement.
CAUTION
Rev.001
MM-M05.01
18 Rotate the LP2 rotor slowly to ensure that the rotor turns freely
without rubbing.
Main Turbine
Mitsubishi
5-116
Chapter 5
Note
As all axial clearances are based on the correct setting of the
rotor in the K position, the target tolerance is 0 mm.
Note
If LP2 turbine blade top and bottom clearances must be checked,
refer to Appendix G for the procedure.
Note
Measure and record the following clearances at the RS and LS.
Measure and record the axial clearance (A) between the base of the
Gov End first stage stationary blade outlet and the shroud of the first
stage rotating blade inlet.
Note
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Measure and record the clearance B between the end of the first
stage stationary blade outlet and the base of the first stage rotating
blade inlet.
5-117
Chapter 5
Measure and record the clearance F between the base of the first
stage rotating blade outlet and the end of the second stage stationary
blade inlet.
Measure and record the rotating and stationary blading seal strip
radial clearances.
Note
If the seal strip clearances exceed 200% of the design
clearances, seal strip replacement should be considered.
10 Repeat the above procedure to measure the LP2 Gen End rotor and
casing clearances.
Confirm that the oil clearances for No.5 and No.6 bearings are within
the acceptance criteria in accordance with mechanical maintenance
manual M05.04, Turbine Bearings and Thrust Bearing.
Install the upper halves of the No.5 and No.6 main bearings.
Install the coupling spacer/ spacer gear for the LP1~LP2 and
LP2~generator couplings and the coupling bolts into the respective
couplings in accordance with mechanical maintenance manual
M05.05.
Replace the coupling guards and restore the coupling cooling oil
connections.
Install the upper half of the coupling guards and the cooling oil lines
for the LP1~LP2 and LP2~generator couplings.
Install the shaft gland seal ring upper halves in accordance with
mechanical maintenance manual M05.03.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Install eye bolts on the inner flow guide ring upper half.
Rig and transport the inner flow guide ring upper half over the LP2
rotor.
5-118
Chapter 5
Apply a thin coat of triple boiled linseed oil to the horizontal joint
flanges or a special compound for flange surface.
Lower the inner flow guide ring upper half slowly and evenly over the
joint studs until the horizontal joint is closed.
Install the safety hoist eye bolts on the Gov End LP2 blade ring upper
half.
Rig and transport the upper half blade ring over the LP2 turbine.
Apply a thin coat of triple boiled linseed oil or a special compound for
flange surface to the horizontal joint flanges and to the aligning plate
and liner surfaces.
Lower the upper half blade ring slowly and evenly over the lower half
blade ring until the horizontal joint is closed and the weight is on the
aligning plates.
CAUTION
Care must be taken when installing the upper half blade ring to
ensure that the turbine blading are not damaged. The blading
are installed with tight axial clearances which must remain
intact for correct operation. Damages to the blading can cause
serious delays in turbine assembly if additional repairs are
necessary.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-119
Chapter 5
Visually inspect the LP2 turbine for foreign material prior to installing
the steam chamber cover.
CAUTION
When working in or over the condenser plenum, take special
care not to drop tools or debris into the condenser tube area.
Damage to the condenser tubes could result in tube leakage.
Install the safety hoist eye bolts on the steam chamber cover.
Rig and transport the steam chamber cover over the LP2 turbine.
Ensure that the upper liners are secured to the steam chamber cover.
Refer to Figure 5-19 for details.
Apply a thin coat of triple boiled linseed oil or a special compound for
flange surface to the horizontal joint flanges and to the liner surfaces.
Lower the steam chamber cover slowly and evenly over the dowels
and the horizontal joint studs until the horizontal joint is closed.
Visually inspect the LP2 turbine for foreign material prior to installing
the inner casing cover.
CAUTION
Rev.001
MM-M05.01
2
3
Main Turbine
Mitsubishi
Install the inner casing guide bolts in the locations indicated in Figure
5-26.
Install the appropriate lifting gear to the inner casing cover.
5-120
Chapter 5
Make a trial lift and adjust the chain blocks or turn buckle, to provide a
level lift.
Transport the inner casing cover and position it above the inner
casing base.
Ensure that the liners are secured to the inner casing cover. Refer to
Figure 5-19 for details.
Align the inner casing cover with the inner casing guide bolts.
10 Apply a coat of triple boiled linseed oil or a special compound for the
flange surface of the inner casing horizontal joint and to the liner
surfaces.
11 Check that the inner casing cover horizontal joint is parallel to the
base horizontal joint.
12 Slowly lower and align the inner casing cover with the studs and
dowels.
13 Continue lowering the cover until the horizontal joint is closed.
14 Remove the lifting gear and the inner casing guide bolts.
15 Install the nuts and washers onto the studs and hand tighten.
Note
Refer to the Bolt Heating Data in Appendix F to identify the
bolts and determine the required heater type and size. Heat
the bolts in accordance with Bolt Heater Instruction in
Appendix I.
Note
Rev.001
MM-M05.01
Appendix F.
Main Turbine
Mitsubishi
5-121
Chapter 5
Note
Install the bolts from both the LS and RS of the LP casing
starting at the transverse centerline, working outwards toward
each end.
16 Install the nuts on the bolts 501 to 572 in the following sequence:
(i)
(ii) Torque tighten reamer bolts 501, 536, 542, 552, 564 and 572
(iii) Heat and tighten bolts 517 513 and 519 524
(iv) Torque tighten bolts 512 502 and 525 535
(v) Torque tighten bolts 541 537, 551 543, 563 555 and 571
567.
17 Install the access cover plates.
18 Slowly rotate the LP2 rotor to ensure that it turns freely.
19 Install the LP2 shaft gland casing upper halves.
Transport the outer casing cover over the outer casing base and align
it to the outer casing base.
Attach tag lines to each end of the outer casing cover to control the
rotation of the cover during installation.
Lubricate the outer casing cover horizontal flange with triple boiled
linseed oil or special compound for flange surface.
Rev.001
Slowly lower the outer casing cover, ensuring that the outer cover is
aligned with the outer casing base.
MM-M05.01
Lubricate the jack screws with Molykote and install them in the outer
casing cover.
Main Turbine
Mitsubishi
5-122
Chapter 5
10 Turn the jack screws in the outer casing cover until they protrude 10
mm below the horizontal joint.
11 Lower the outer casing cover slowly until the jack screws rest on the
horizontal joint of the outer casing base.
12 Continue lowering the outer casing cover by slackening the jack
screws equally half a turn at a time.
Note
Follow the downward motion of the outer casing cover with
the crane to ensure that the load is transferred to the jack
screws.
13 Continue to lower the outer casing cover until the horizontal joint is
closed.
14 Remove the lifting gear.
15 Place the washers over the open bolt holes in the outer casing cover
flange.
16 Install the nuts on top of the bolts and tighten.
17 Tighten the outer casing horizontal joint flange bolts in a diametrically
opposite pattern in the following order:
(i)
Reamer bolts.
(ii) Joint bolts starting at the gland bores working outward toward the
corners (transverse direction).
(iii) Joint bolts starting at the transverse centerline towards the
corners (longitudinal direction).
18 Replace the top seal ring between the outer casing cover and the
inner casing cover.
Note
The following items 19 to 22 are performed inside the LP outer
casing cover. Refer to Figure 5-18.
19 Install the lifting gear, and evenly lower the LP exhaust flow guides
into place aligning the eccentric pins as they are lowered.
Rev.001
20 Install and securely tighten the flange bolts into the Gov End and the
Gen End exhaust flow guide upper halves.
MM-M05.01
Main Turbine
Mitsubishi
5-123
Chapter 5
Return to Service
Have the electricians connect thermocouple lead wires to the outer
casing cover.
Replace the insulation and metal cladding removed from the turbine.
Confirm that all instruments removed for the overhaul have been
installed and are available.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
5-124
Chapter 5
0.3~0.5
0.3~0.5
0.2+-0.05
0.2+-0.05
STEAM
CHAMBER
STEAM
CHAMBER
STEAM CHAMBER
STEAM CHAMBER
0.2+-0.05
0.2+- 0.05
INNER CASING
INNER CASING
A
B
STATIONARY BLADE
6R
7R
A
B
A
B
4R
5R
3C
3R
A 2C 1C A
B B
2R
1R
5C
E
E
4C
A 1C
A
B
2C A3C A
B
1R
B
2R
B
3R
F
F
5R
4R
7C
4C
GEN. SIDE
5C
7C
6C
STATIONARY BLADE
6R
7R
F
RIGHT SIDE
K=29.0 +- 0.0
LEFT SIDE
29.0 +1.5
-0.5
0.2+-0.05
0.2 +-0.05
LP2 ROTOR
6C
Rev.001
MM-M05.01
11.6 +1.5
-0.5
INNER FLOW
GUIDE
31.6 +1.5
-0.5
STATIONARY BLADE
1
2
3
4
5
6
7
ROTOR BLADES
INLET
OUTLET
9.0
9.0
9.0
9.0
31
28.1
46.1
9.8
9.8
9.8
9.8
9.2
11.6
11.6
29
29
29
68.2
29.8
29.8
29.8
68.2
31.6
31.6
29.0
29.0
29.0
51
48.1
61.6
29.8
29.8
29.8
29.8
29.2
31.6
31.6
9.0
9.0
9.0
48.2
9.8
9.8
9.8
48.2
11.6
11.6
-
6C
INNER CASING
STATIONARY BLADE
Main Turbine
Mitsubishi
1
2
3
4
5
6
7
LP2 ROTOR
INNER FLOW
GUIDE
INNER CASING
GOV. SIDE
6C
ROW No.
7C
ROW No.
7C
MPTD-3-0257
5-125
Chapter 5
SEAL RING
SEAL RING
GLAND
CASING
0.5+-0.1
GLAND
CASING
0.5+-0.1
X
SEAL STRIP
SEAL STRIP
OUTER CASING
COVER
CL OF LP2 ROTOR
GLAND
CASING
0.5+-0.1
SEAL STRIP
GLAND
CASING
LP2 ROTOR
0.5+-0.1
SEAL STRIP
LP2 ROTOR
MM-M05.01
Rev.001
NOTE: REFER TO FIGURE 5-25 FOR BLADE SEAL RADIAL CLEARANCES (X)
MPTD-4-0258
FIGURE 5-21
Main Turbine
Mitsubishi
5-126
Chapter 5
SEAL RING
SEAL RING
GLAND
CASING
0.5+-0.1
GLAND
CASING
0.5+-0.1
X
SEAL STRIP
SEAL STRIP
OUTER CASING
COVER
C
L OF LP2 ROTOR
GLAND
CASING
LP2 ROTOR
SEAL STRIP
GLAND
CASING
0.5+- 0.1
0.5+- 0.1
LP2 ROTOR
SEAL STRIP
MM-M05.01
Rev.001
NOTE: REFER TO FIGURE 5-25 FOR BLADE SEAL RADIAL CLEARANCES (X)
MPTD-4-0259
FIGURE 5-22
Main Turbine
Mitsubishi
5-127
Chapter 5
0.3 0.1
STATIONARY BLADE
+-
ROTATING BLADE
INNER CASING
LP2 BLADE RING
ROTATING BLADE
6R
0.3 0.1
SEAL STRIP
5R
4R
EXHAUST
FLOW GUIDE
7C
3R
7R
ROTATING BLADE
LP2 BLADE RING
ROTATING
BLADE
6C
SEAL STRIP
5C
1R
4C
2R
1C
0.3 0.1
3C
2C
STATIONARY
BLADE
LP2 ROTOR
0.0
2R
3R
4R
7C
5R
6R
7R
1R
ROTATING BLADE
12
1C
LP2 ROTOR
31.6
0.3 0.1
STATIONARY
BLADE
4C
6C
5C
LP2 ROTOR
MM-M05.01
Rev.001
3C
2C
STATIONARY BLADE
7.5
SEAL STRIP
MPTD-3-0260
LP2 ROTOR
SEAL STRIP
NOTE: REFER TO FIGURE 5-25 FOR BLADE SEAL RADIAL CLEARANCES (X)
FIGURE 5-23
Main Turbine
Mitsubishi
5-128
Chapter 5
0.3 0.1
STATIONARY BLADE
+-
ROTATING BLADE
INNER CASING
ROTATING BLADE
6R
0.3 0.1
SEAL STRIP
5R
EXHAUST
FLOW GUIDE
4R
7C
3R
7R
ROTATING BLADE
ROTATING
BLADE
6C
SEAL STRIP
5C
STATIONARY
BLADE
3C
2C
4C
0.3 0.1
1C
2R
1R
LP2 ROTOR
6R
7R
4R
5R
3R
2R
ROTATING BLADE
1R
0.0
7C
1C
LP2 ROTOR
11.6
0.3 0.1
STATIONARY
BLADE
4C
5C
6C
3C
2C
LP2 ROTOR
STATIONARY BLADE
MM-M05.01
Rev.001
7.5
SEAL STRIP
M PTD-3-0261
LP2 ROTOR
SEAL STRIP
NOTE: REFER TO FIGURE 5-25 FOR BLADE SEAL RADIAL CLEARANCES (X)
FIGURE 5-24
Main Turbine
Mitsubishi
5-129
Chapter 5
NOMINAL CLEA.
ELEMENT
OUTER GLAND
(GOV. END)
LOCATION
LENGTH
407.75
481.25
555.75
629.75
1.20
1.20
1.20
1.20
0.95
0.90
0.90
0.90
0.25
0.25
0.25
0.25
-0.01
-0.02
-0.03
-0.04
974.85
10.00
10.00
0.25
1433.10
1536.50
1641.40
1816.50
1911.90
2016.30
2076.15
2130.50
2180.80
2232.00
2282.30
2333.50
2379.80
2725.20
2771.50
2822.70
2873.00
2924.20
2974.50
3028.85
3088.70
3193.90
3288.50
3463.60
3568.50
3671.90
2.67
4.00
1.65
2.00
1.50
1.60
1.50
1.30
1.10
1.30
1.10
1.30
1.10
1.10
1.30
1.10
1.30
1.10
1.30
1.50
1.60
1.50
2.00
1.65
4.00
2.67
2.67
4.00
1.65
2.00
1.50
1.60
1.50
1.30
1.10
1.30
1.10
1.30
1.10
1.10
1.30
1.10
1.30
1.10
1.30
1.50
1.60
1.50
2.00
1.65
4.00
2.67
4130.15
10.00
4475.25
4549.25
4623.75
4697.25
1.20
1.20
1.20
1.20
LP7C (GOV.)
LP6R (GOV.)
INNER CASING
LP6C (GOV.)
(GOV. END)
LP5R (GOV.)
LP5C (GOV.)
LP4R (GOV.)
LP4C (GOV.)
LP2 BLADE RING LP3R (GOV.)
LP3C (GOV.)
(GOV. END)
LP2R (GOV.)
LP2C (GOV.)
LP1R (GOV.)
STEAM FLOW
GUIDE INLET
LP1R (GEN.)
LP2C (GEN.)
LP2 BLADE RING LP2R (GEN.)
LP3C (GEN.)
(GEN. END)
LP3R (GEN.)
LP4C (GEN.)
LP4R (GEN.)
LP5C (GEN.)
LP5R (GEN.)
INNER CASING
LP6C (GEN.)
(GOV. END)
LP6R (GEN.)
LP7C (GEN.)
LP7R (GEN.)
OUTER GLAND
(GEN END)
HORIZONTAL DIRECTION
AFT. ASS'Y
CASING DEFLEC.
NOMINAL CLEA.
23
24
0.75
0.50
0.50
0.50
0.00
0.00
0.00
0.00
10.00
10.00
+0.10
-0.05
2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67
9.68
+0.50
-0.00
0.61
0.61
0.62
0.68
+0.15
-0.05
26
27
28
29
30
29 30
ROTOR AFT. ASY AFT. ASY CASING CASING AT SET. AT SET.
FROM
AFT. ASY AFT. ASY CASING CASING AT SET. AT SET. TOLERANCE
NOMINAL NOMINAL ELEMENT ROTOR
NOMINAL NOMINAL ELEMENT ROTOR
TOLERANCE
No.5 BRG. TOP
SETTING SETTING RIGHT
LEFT
DEFLEC. DEFLEC. RIGHT
BOTTOM SETTING DEFLEC. SETTING TOP
LEFT
BOTTOM
RIGHT
LEFT
BOTTOM DEFLEC. DEFLEC. TOP
LEFT
CLEARA. CLEARA.
CLEARA. CLEARA.
CLEARA. CLEARA.
CLEARA. CLEARA. RIGHT
BOTTOM CLEARA. CLEARA.
CLEARA. CLEARA. TOP
0.00
0.00
0.00
0.00
0.75
0.50
0.50
0.50
0.75
0.50
0.50
0.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.75
0.50
0.50
0.50
0.75
0.50
0.50
0.50
+0.15
-0.15
0.00
0.00
10.00
10.00
0.00
0.00
10.00
10.00
+0.50
-0.00
2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67
2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67
2.67
4.00
1.65
2.00
1.50
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.10
1.10
0.85
0.85
0.85
0.85
0.85
0.85
0.85
1.50
2.00
1.65
4.00
2.67
+0.10
-0.05
10.00
10.00
0.00
0.00
10.00
10.00
0.00
0.00
10.00
10.00
+0.50
-0.00
0.50
0.50
0.50
0.75
0.50
0.50
0.50
0.75
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.50
0.50
0.50
0.75
0.50
0.50
0.50
0.75
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.50
0.50
0.50
0.75
0.50
0.50
0.50
0.75
+0.15
-0.05
10
11
10 11
21
22
0.00
0.00
0.00
0.00
1.46
1.47
1.48
1.49
0.69
0.63
0.62
0.61
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.46
1.47
1.48
1.49
0.69
0.63
0.62
0.61
+0.15
-0.05
0.75
0.50
0.50
0.50
-0.06
0.00
10.31
9.69
0.00
0.00
10.31
9.69
+0.50
-0.00
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
-0.09
-0.10
-0.10
-0.11
-0.12
-0.12
-0.12
-0.12
-0.12
-0.13
-0.13
-0.13
-0.13
-0.13
-0.13
-0.13
-0.13
-0.13
-0.12
-0.12
-0.12
-0.12
-0.11
-0.11
-0.10
-0.10
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
3.01
4.35
2.00
2.36
1.87
1.97
1.87
1.67
1.47
1.68
1.48
1.68
1.48
1.48
1.68
1.48
1.68
1.48
1.67
1.87
1.97
1.87
2.36
2.01
4.35
3.02
2.33
3.65
1.30
1.64
1.13
1.23
1.13
0.93
0.73
0.92
0.72
0.92
0.72
0.72
0.92
0.72
0.92
0.72
0.93
1.13
1.23
1.13
1.64
1.29
3.65
2.32
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
3.01
4.35
2.00
2.36
1.87
1.97
1.87
1.67
1.47
1.68
1.48
1.68
1.48
1.48
1.68
1.48
1.68
1.48
1.67
1.87
1.97
1.87
2.36
2.01
4.35
3.02
2.33
3.65
1.30
1.64
1.13
1.23
1.13
0.93
0.73
0.92
0.72
0.92
0.72
0.72
0.92
0.72
0.92
0.72
0.93
1.13
1.23
1.13
1.64
1.29
3.65
2.32
10.00
0.25
-0.07
0.00
10.32
9.68
0.00
0.00
10.32
0.90
0.90
0.90
0.95
0.25
0.25
0.25
0.25
-0.04
-0.04
-0.03
-0.02
0.00
0.00
0.00
0.00
1.49
1.49
1.48
1.47
0.61
0.61
0.62
0.68
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.49
1.49
1.48
1.47
NOTE:
1. RADIAL CLEARANCES AT ASSEMBLY OF LP-2 TURBINE
IS AS SHOWN IN THIS DRAWING IN CASE THAT SETTING
OF EACH PART AND DEFLECTION OF THE ROTOR IS
TAKEN INTO ACCOUNT.
TOP CLEARANCE
+
+
- 5
24
25
BOTTOM CLEARANCE
Rev.001
MM-M05.01
25
MPTD-3-0262
FIGURE 5-25
Main Turbine
Mitsubishi
5-130
MM-M05.01
Rev.001
Chapter 5
FIGURE 5-26
Main Turbine
Mitsubishi
5-131
Chapter 6
Corrective Maintenance
C h a p t er
6 Corrective Maintenance
Corrective maintenance means the repair or replacement work to be performed in case of
sudden failure of any part or component of the steam turbine. Though a well-planned
preventive maintenance program is able to reduce the probability of sudden failure of the
steam turbine, unscheduled corrective maintenance is still necessary. Corrective
maintenance is given priority depending on the seriousness of the problem faced and
impact on the plant operation. The schedule for repair of any equipment must be carefully
planned to keep outage time at the minimum.
During such repair or replacement work, inspection must be performed carefully to
determine why the equipment has failed. Good corrective maintenance not only requires
quick restoration of the failed equipment back into service but also demands every effort to
identify and record the cause of the failure. The inspection results will help to find the cause
of the failure. The findings along with possible rectification proposals are to be used as a
feedback to update the preventive maintenance procedures.
6.1
Prerequisites
The prerequisites for the corrective maintenance of the main turbine are as follows:
a)
Scheduling
Unlike preventive maintenance, the scheduling of the corrective maintenance
can be started only after a failure occurred. Depending on the severity of the
problem, the importance of the service provided by the failed equipment and
the availability of manpower to be assigned to the problem, a corrective
maintenance schedule must be prepared to solve the problem at the earliest
opportunity. The schedule should clearly indicate the critical path and the
priority for different parallel activities. Once the schedule is decided, be sure
to observe the schedule so that the maintenance should be completed timely.
b)
Departmental Interface/Notification
Refer to Section 4.1.2, Departmental Interface / Notification.
c)
Isolation of Equipment
d)
Safety Precautions
Refer to Section 4.1.4, Safety Precautions
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
6-1
Chapter 6
6.2
Corrective Maintenance
Preparation
a)
b)
Documentation
Refer to Subsection 4.2.1 b), Documentation.
6.3
Troubleshooting
MM-M05.01
Rev.001
This section provides information about troubleshooting and servicing for the main
turbine, pertaining to the mechanical maintainer. Tables of faults, possible causes
and remedies have been provided to assist in troubleshooting by qualified
personnel. If any new problem which is not listed in the following table occurs
contact the manufacturer for assistance.
Main Turbine
Mitsubishi
6-2
Chapter 6
TABLE 6-1
Fault
External leakage of steam
from rotor gland
Corrective Maintenance
Remedy
Erosion of turbine
components and horizontal
flange joint
Routine overhaul
Replace damaged parts
Replenish lubricant
Malfunction of rotor
grounding device
Electrostatic erosion of
bearings
Rotor vibration
Blade failure
Rotor unbalance
Replace blades
Perform balancing of rotor
MM-M05.01
Rev.001
Sinking of foundation
Main Turbine
Mitsubishi
6-3
Chapter 6
Corrective Maintenance
Rev.001
Possible Cause
Remedy
Damaged bearings
Identify source of
foreign .particle and rectify
Water induction
MM-M05.01
Main Turbine
Mitsubishi
6-4
Chapter 6
Corrective Maintenance
Fault
Fault
Fault
Age deterioration
Routine renewal
Routine inspection
Clearance adjustment
Control dust/cleanliness
Blocked filters
Blocked filter
Stem is bent
Replace stem
LVDT is faulty
Check by overhauling
Hysteresis increased
Pump misalignment
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
6-5
Chapter-7
Recommended Lubrication
Recommended
7 L u b r ic a t io n
C h a p t er
MM-M05.01
Rev.001
The major requirement of the main turbine lubrication is to lubricate the turbine journal and thrust
bearings and the sliding surfaces of the turbine casings at certain locations. Details of the
lubrication for the turbine casing sliding surfaces are provided in this chapter. For details of the
turbine journal and thrust bearings lubrication, refer to the mechanical maintenance manual
M 05.08, Turbine Main Oil Tank and Auxiliary Pumps.
Main Turbine
Mitsubishi
7-1
Recommended Lubrication
MM-M05.01
Rev.001
Chapter-7
Main Turbine
Mitsubishi
7-2
Recommended Lubrication
MM-M05.01
Rev.001
Chapter-7
Main Turbine
Mitsubishi
7-3
Appendix A
A p p en d i x
A Torque Chart
TABLE A-1
Bolt
Size
(mm)
0.82
0.90
0.74
0.51
0.56
0.46
0.43
0.47
0.39
2.0
2.2
1.8
1.2
1.3
1.1
1.0
1.1
0.9
10
3.9
4.3
3.5
2.5
2.8
2.2
2.1
2.3
1.9
12
6.8
7.5
6.1
4.2
4.6
3.8
3.6
4.0
3.2
14
11
12
10
6.7
7.4
6.0
5.7
6.3
5.1
16
16
18
14
10
11
9.0
8.6
9.5
7.7
18
22
24
20
14
15
13
12
13
11
20
32
35
29
20
22
18
17
19
15
22
42
46
38
26
29
23
22
24
20
24
54
59
49
34
37
31
29
32
26
27
79
87
71
50
55
45
42
46
38
30
108
119
97
67
74
60
57
63
51
33
145
160
130
91
100
82
77
85
69
36
188
207
169
117
129
105
100
110
90
39
242
266
218
151
166
136
129
142
116
42
300
330
270
188
207
169
160
176
144
45
375
412
338
234
257
211
199
219
179
48
453
498
408
283
311
255
241
265
217
52
583
641
525
365
402
328
310
341
279
56
722
794
650
451
496
406
383
421
345
60
892
981
803
557
613
501
474
521
427
64
1073
1180
966
671
738
604
570
627
513
68
1292
1421
1163
807
888
726
686
755
617
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
A-1
Appendix A
TABLE A-2
Bolt Diameter
Torque (kg-m)
Inch
mm
SCM435
(SAE4135/AISI4137)
W-10705BU
(AISI616 Type 22)
W-15106FD
(AISI690)
1/2
(12.7)
5.4
6.2
8.1
5/8
(15.9)
10.9
12.5
16.3
3/4
(19.1)
18.2
20.8
27.0
7/8
(22.2)
29.1
33.4
43.4
(25.4)
44.5
50.8
66.0
1-1/8
(28.6)
64.5
73.7
95.8
1-1/4
(31.8)
90.7
103.7
134.8
1-3/8
(34.9)
123.4
141.0
183.3
1-1/2
(38.1)
145.3
166.0
215.8
1-5/8
(41.3)
199.5
228.0
296.4
1-3/4
(44.5)
272.1
311.0
404.3
1-7/8
(47.6)
363.1
415.0
539.5
(50.8)
399.0
456.0
592.8
Example
SCM435
Bolt Diameter
1 inch
Required Torque
145.3 kg-m
1.5 m
96.9 kg
MM-M05.01
Rev.001
Bolt Material
Main Turbine
Mitsubishi
A-2
Appendix B
Recommended
B Spare Parts
MM-M05.01
Rev.001
A p p en d i x
Main Turbine
Mitsubishi
B-1
Appendix B
TABLE B-1
Supplier
Name
Eqt. ID No.
Eqt.
Description
Qty
03MAA31AE101
Steam Turbine
1 set
MHI
03MAA31AE101
Steam Turbine
1 set
MHI
03MAA31AE101
Steam Turbine
1 set
MHI
03MAA31AE101
Steam Turbine
1 set
MHI
03MAA31AE101
Steam Turbine
1 set
MHI
03MAA31AE101
Steam Turbine
1 set
MHI
03MAA31AE101
Steam Turbine
1 set
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MM-M05.01
Rev.001
MHI
Main Turbine
Mitsubishi
B-2
Appendix B
Eqt. ID
No.
Parts Description
Eqt.
Description
Qty
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MHI
03MAA31AE101
Steam Turbine
MM-M05.01
Rev.001
MHI
Main Turbine
Mitsubishi
B-3
Appendix B
TABLE B-2
MM-M05.01
Rev.001
ON HAND QTY.
STRATEGIC
SPARE PARTS
LEAD
TIME
(PO TO
FOB) Wk
STEAM TURBINE
62
NO. 2 JOURNAL
BEARING
STEAM TURBINE
62
03MAA31AE101
NO.3,4,5 JOURNAL
BEARING METAL
STEAM TURBINE
62
MHI
03MAA31AE101
NO. 6 JOURNAL
BEARING
STEAM TURBINE
62
MHI
03MAA31AE101
THRUST BEARING
STEAM TURBINE
62
MHI
03MAA31AE101
OUTER CASING
BOLT
STEAM TURBINE
1 SET
47
MHI
03MAA31AE101
OUTER CASING
NUT
STEAM TURBINE
1 SET
47
MHI
03MAA31AE101
OUTER CASING
WASHER
STEAM TURBINE
1 SET
47
MHI
03MAA31AE101
STEAM TURBINE
1 SET
47
MHI
03MAA31AE101
STEAM TURBINE
1 SET
47
MHI
03MAA31AE101
STEAM TURBINE
1 SET
47
MHI
03MAA31AE101
STEAM TURBINE
1 SET
47
MHI
03MAA31AE101
STEAM TURBINE
37
MHI
03MAA31AE101
STEAM TURBINE
37
SUPPLIER
NAME
EQT .
MHI
03MAA31AE101
NO. 1 JOURNAL
BEARING
MHI
03MAA31AE101
MHI
Main Turbine
Mitsubishi
PARTS
ID
PARTS DESCRIPTION
SUB-ASSEMBLY/
EQT DESCRIPTION
MAN.
PARTS NO.
MAN.
DWG. NO.
EQT. SUPPLIER
PARTS NO.
SPARE
PARTS 1 YR
B-4
REMARKS
Appendix B
MM-M05.01
Rev.001
ON HAND QTY.
STRATEGIC
SPARE PARTS
LEAD
TIME
(PO TO
FOB) Wk
STEAM TURBINE
47
STEAM TURBINE
62
03MAA31AE101
PISTON RING OF
COOLING STEAM
INLET
STEAM TURBINE
62
MHI
03MAA31AE101
EARTH BRUSH
(COPPER BRAID)
STEAM TURBINE
17
MHI
03MAA31AE101
22
MHI
03MAA31AE101
50
MHI
03MAA31AE101
50
MHI
03MAA31AE101
50
MHI
03MAA31AE101
50
MHI
03MAA31AE101
50
MHI
03MAA31AE101
50
MHI
03MAA31AE101
50
SUPPLIER
NAME
EQT .
MHI
03MAA31AE101
SLACK RING OF
MAIN STEAM INLET
MHI
03MAA31AE101
MHI
Main Turbine
Mitsubishi
PARTS
ID
PARTS DESCRIPTION
SUB-ASSEMBLY/
EQT DESCRIPTION
MAN.
PARTS NO.
MAN.
DWG. NO.
EQT. SUPPLIER
PARTS NO.
SPARE
PARTS 1 YR
B-5
REMARKS
Appendix B
MM-M05.01
Rev.001
ON HAND QTY.
STRATEGIC
SPARE PARTS
LEAD
TIME
(PO TO
FOB) Wk
50
50
03MAA31AE101
50
MHI
03MAA31AE101
50
MHI
03MAA31AE101
50
MHI
03MAA31AE101
74
MHI
03MAA31AE101
74
MHI
03MAA31AE101
74
MHI
03MAA31AE101
HIP/LP 3A COUPLING
PART REAMER BOLT
50
MHI
03MAA31AE101
HIP/LP 3A COUPLING
PART NUT
50
MHI
03MAA31AE101
LP3A/3B COUPLING
PART REAMER BOLT
50
MHI
03MAA31AE101
LP3A/3B COUPLING
PART NUT
50
SUPPLIER
NAME
EQT .
MHI
03MAA31AE101
LP 5R SEAL RING
ASSY (RH/LH)
MHI
03MAA31AE101
MHI
Main Turbine
Mitsubishi
PART
ID
PARTS DESCRIPTION
SUB-ASSEMBLY/
EQT DESCRIPTION
MAN.
PARTS NO.
MAN.
DWG. NO.
EQT. SUPPLIER
PARTS NO.
SPARE
PARTS 1 YR
B-6
REMARKS
Appendix B
MM-M05.01
Rev.001
INITIAL QUANTITY
ON HAND QTY.
STRATEGIC
SPARE PARTS
LEAD
TIME
(PO TO
FOB) Wk
50
LP3B/GEN COUPLING
PART NUT
50
BUSHING
38
03MAA02AA1
BONNET GASKET
18
MHI
03MAA02AA1
MAIN VALVE
40
MHI
03MAA02AA1
VALVE STEM
30
MHI
03MAA02AA1
PLUG
18
MHI
03MAA02AA1
PILOT VALVE
22
MHI
03MAA02AA1
VALVE NUT
26
MHI
03MAA02AA1
SPRING SUPPORT
10
26
MHI
03MAA02AA1
SPRING
15
26
MHI
03MAA02AA1
10
BUSHING
16
38
MHI
03MAA02AA1
11
BUSHING
17
38
MHI
03MAA02AA1
12
HEX.SOCKET HEAT
BOLT
19
12
22
MHI
03MAA02AA1
13
20
30
MHI
03MAA02AA1
14
PIN
21
18
MHI
03MAA02AA1
15
LINER
22
58
SUPPLIER
NAME
EQT .
MHI
03MAA31AE101
LP3B/GEN COUPLING
PART REAMER BOLT
MHI
03MAA31AE101
MHI
03MAA02AA1
MHI
Main Turbine
Mitsubishi
PART
ID
PARTS DESCRIPTION
SUB-ASSEMBLY/
EQT DESCRIPTION
MAN.
PARTS NO.
PER EACH
QTY.
TOTAL
PLANT
SPARE
PARTS 1 YR
B-7
REMARKS
Appendix B
MM-M05.01
Rev.001
SUPPLIER
NAME
EQT .
PART
ID
PARTS DESCRIPTION
SUB-ASSEMBLY/
EQT DESCRIPTION
MAN.
PARTS NO.
PER EACH
QTY.
TOTAL
PLANT
ON HAND QTY.
SPARE
PARTS 1 YR
STRATEGIC
SPARE PARTS
LEAD
TIME
(PO TO
FOB) Wk
MHI
03MAA02AA1
16
STUD BOLT
23
16
42
MHI
03MAA02AA1
17
CUP NUT
24
16
22
MHI
03MAA02AA1
18
SPHERICAL WASHER
25
16
26
MHI
03MAA02AA1
19
SPHERICAL WASHER
26
16
26
MHI
03MAA02AA1
20
STUD BOLT
27
18
36
42
MHI
03MAA02AA1
21
CUP NUT
28
18
36
36
MHI
03MAA02AA1
22
SPHERICAL WASHER
29
18
36
26
MHI
03MAA02AA1
23
SPHERICAL WASHER
30
18
36
26
MHI
03MAA02AA1
24
PLUG
31
18
36
18
MHI
03MAA02AA1
25
PLUG
32
18
36
18
MHI
03MAA02AA1
26
BUSHING
71
38
MHI
03MAA02AA1
27
VALVE SEAT
38
MHI
03MAA03AA1
STUD BOLT
GOVERNING VALVE
12
48
12
42
MHI
03MAA03AA1
CAP NUT
GOVERNING VALVE
12
48
12
38
MHI
03MAA03AA1
SPHERICAL WASHER
GOVERNING VALVE
12
48
12
20
MHI
03MAA03AA1
SPHERICAL WASHER
GOVERNING VALVE
12
48
12
26
MHI
03MAA03AA1
BONNET GASKET
GOVERNING VALVE
13
18
MHI
03MAA03AA1
VALVE
GOVERNING VALVE
14
22
MHI
03MAA03AA1
VALVE NUT
GOVERNING VALVE
15
30
Main Turbine
Mitsubishi
B-8
REMARKS
Appendix B
MM-M05.01
Rev.001
SUPPLIER
NAME
EQT .
PART
ID
PARTS DESCRIPTION
SUB-ASSEMBLY/
EQT DESCRIPTION
MAN.
PARTS NO.
PER EACH
QTY.
TOTAL
PLANT
ON HAND QTY.
SPARE
PARTS 1 YR
STRATEGIC
SPARE PARTS
LEAD
TIME
(PO TO
FOB) Wk
MHI
03MAA03AA1
PIN
GOVERNING VALVE
16
16
42
MHI
03MAA03AA1
VALVE STEM
GOVERNING VALVE
17
30
MHI
03MAA03AA1
10
BUSHING
GOVERNING VALVE
18
38
MHI
03MAA03AA1
11
BUSHING
GOVERNING VALVE
19
30
MHI
03MAA03AA1
12
GOVERNING VALVE
20
24
22
MHI
03MAA03AA1
13
STUD BOLT
GOVERNING VALVE
29
36
42
MHI
03MAA03AA1
14
NUT
GOVERNING VALVE
30
36
22
MHI
03MAA03AA1
15
SPHERICAL WASHER
GOVERNING VALVE
31
36
26
MHI
03MAA03AA1
16
SPHERICAL WASHER
GOVERNING VALVE
32
36
26
MHI
03MAA03AA1
17
GOVERNING VALVE
38
16
22
MHI
03MAA03AA1
18
PIN
GOVERNING VALVE
39
18
MHI
03MAA03AA1
19
PIN
GOVERNING VALVE
43
18
MHI
03MAB02AA1
VALVE
REHEAT VALVE
42
MHI
03MAB02AA1
VALVE STEM
REHEAT VALVE
50
MHI
03MAB02AA1
BUSHING
REHEAT VALVE
38
MHI
03MAB02AA1
BUSHING
REHEAT VALVE
26
MHI
03MAB02AA1
BUSHING
REHEAT VALVE
38
MHI
03MAB02AA1
BUSHING
REHEAT VALVE
10
38
Main Turbine
Mitsubishi
B-9
REMARKS
Appendix B
MM-M05.01
Rev.001
SUPPLIER
NAME
EQT .
PART
ID
PARTS DESCRIPTION
SUB-ASSEMBLY/
EQT DESCRIPTION
MAN.
PARTS NO.
PER EACH
QTY.
TOTAL
PLANT
ON HAND QTY.
SPARE
PARTS 1 YR
STRATEGIC
SPARE PARTS
LEAD
TIME
(PO TO
FOB) Wk
MHI
03MAB02AA1
SHOULDER RING
REHEAT VALVE
20
26
MHI
03MAB02AA1
RETAINING RING
REHEAT VALVE
21
50
MHI
03MAB02AA1
KEY
REHEAT VALVE
28
18
MHI
03MAB02AA1
10
BONNET GASKET
REHEAT VALVE
34
18
MHI
03MAB02AA1
11
REHEAT VALVE
35
18
MHI
03MAB02AA1
12
NUT
REHEAT VALVE
36
22
MHI
03MAB02AA1
13
PIN
REHEAT VALVE
37
18
MHI
03MAB02AA1
14
STUD BOLT
REHEAT VALVE
39
24
48
12
42
MHI
03MAB02AA1
15
STUD BOLT
REHEAT VALVE
40
12
24
42
MHI
03MAB02AA1
16
CAP NUT
REHEAT VALVE
41
24
48
12
38
MHI
03MAB02AA1
17
NUT
REHEAT VALVE
42
24
48
12
38
MHI
03MAB02AA1
18
STUD BOLT
REHEAT VALVE
43
12
24
42
MHI
03MAB02AA1
19
SPHERICAL WASHER
REHEAT VALVE
44
24
48
12
26
MHI
03MAB02AA1
20
SPHERICAL WASHER
REHEAT VALVE
45
24
48
12
26
MHI
03MAB02AA1
21
SPHERICAL WASHER
REHEAT VALVE
46
24
48
12
26
MHI
03MAB02AA1
22
SPHERICAL WASHER
REHEAT VALVE
47
24
48
12
26
MHI
03MAB02AA1
23
DISC SPRING
REHEAT VALVE
55
16
26
MHI
03MAB02AA1
24
REHEAT VALVE
58
12
24
18
Main Turbine
Mitsubishi
B-10
REMARKS
Appendix B
MM-M05.01
Rev.001
SUPPLIER
NAME
EQT .
PART
ID
PARTS DESCRIPTION
SUB-ASSEMBLY/
EQT DESCRIPTION
MAN.
PARTS NO.
PER EACH
QTY.
TOTAL
PLANT
ON HAND QTY.
SPARE
PARTS 1 YR
STRATEGIC
SPARE PARTS
LEAD
TIME
(PO TO
FOB) Wk
MHI
03MAB02AA1
25
SPRING
REHEAT VALVE
66
26
MHI
03MAB02AA1
26
BEARING
REHEAT VALVE
73
26
MHI
03MAB02AA1
27
PLUG
REHEAT VALVE
74
18
MHI
03MAB02AA1
28
PLUG
REHEAT VALVE
76
36
72
18
18
MHI
03MAB02AA1
29
PLUG
REHEAT VALVE
77
12
24
18
MHI
03MAB02AA1
30
REHEAT VALVE
78
42
MHI
03MAB03AA1
VALVE STEM
INTERCEPTOR V/V
50
MHI
03MAB03AA1
BUSHING
INTERCEPTOR V/V
38
MHI
03MAB03AA1
BUSHING
INTERCEPTOR V/V
38
MHI
03MAB03AA1
RETAINER
INTERCEPTOR V/V
30
MHI
03MAB03AA1
INTERCEPTOR V/V
38
42
MHI
03MAB03AA1
PRESSURE SEAL
RING
INTERCEPTOR V/V
42
MHI
03MAB03AA1
STUD BOLT
INTERCEPTOR V/V
17
32
42
MHI
03MAB03AA1
STUD BOLT
INTERCEPTOR V/V
18
28
112
28
42
MHI
03MAB03AA1
NUT
INTERCEPTOR V/V
19
28
112
28
42
MHI
03MAB03AA1
10
SPHERICAL WASHER
INTERCEPTOR V/V
20
28
112
28
26
MHI
03MAB03AA1
11
SPHERICAL WASHER
INTERCEPTOR V/V
21
28
112
28
26
Main Turbine
Mitsubishi
B-11
REMARKS
Appendix B
MM-M05.01
Rev.001
SUPPLIER
NAME
EQT .
PART
ID
PARTS DESCRIPTION
SUB-ASSEMBLY/
EQT DESCRIPTION
MAN.
PARTS NO.
PER EACH
QTY.
TOTAL
PLANT
ON HAND QTY.
SPARE
PARTS 1 YR
STRATEGIC
SPARE PARTS
LEAD
TIME
(PO TO
FOB) Wk
MHI
03MAB03AA1
12
SPHERICAL WASHER
INTERCEPTOR V/V
22
32
26
MHI
03MAB03AA1
13
SPHERICAL WASHER
INTERCEPTOR V/V
23
32
26
MHI
03MAB03AA1
14
LINER
INTERCEPTOR V/V
26
18
MHI
03MAB03AA1
15
SCREW
INTERCEPTOR V/V
29
18
MHI
03MAB03AA1
16
SCREW
INTERCEPTOR V/V
30
18
MHI
03MAB03AA1
17
NUT
INTERCEPTOR V/V
36
32
38
MHI
03MAB03AA1
18
MAIN VALVE
SUBASSEMBLY
INTERCEPTOR V/V
42
MHI
03MAB03AE1
101
BOLT
32
32
42
MHI
03MAB03AE1
102
CAP NUT
64
64
16
22
MHI
03MAB03AE1
103
SPHERICAL WASHER
32
32
26
MHI
03MAB03AE1
104
SPHERICAL WASHER
32
32
26
MHI
03MAB03AE1
105
WASHER
32
32
26
MHI
03MAB03AE1
106
FLANGE GASKET
18
MHI
03MAB03AE1
107
PLUG
64
64
16
18
MHI
03MAB03AE1
108
PLUG
32
32
16
MHI
03MAB03AE1
109
BOLT
HR STEAM INLET
PIPING
40
40
10
42
Main Turbine
Mitsubishi
B-12
REMARKS
Appendix B
MM-M05.01
Rev.001
SUPPLIER
NAME
EQT .
PART
ID
PARTS DESCRIPTION
SUB-ASSEMBLY/
EQT DESCRIPTION
MAN.
PARTS NO.
PER EACH
QTY.
TOTAL
PLANT
ON HAND QTY.
SPARE
PARTS 1 YR
STRATEGIC
SPARE PARTS
LEAD
TIME
(PO TO
FOB) Wk
MHI
03MAB031AE1
110
CAP NUT
HR STEAM INLET
PIPING
80
80
20
38
MHI
03MAB031AE1
111
SPHERICAL WASHER
HR STEAM INLET
PIPING
40
40
10
26
MHI
03MAB031AE1
112
SPHERICAL WASHER
HR STEAM INLET
PIPING
40
40
10
26
MHI
03MAB031AE1
113
WASHERS
HR STEAM INLET
PIPING
40
40
10
26
MHI
03MAB031AE1
114
FLANGE GASKET
HR STEAM INLET
PIPING
18
MHI
03MAB031AE1
115
PLUG
HR STEAM INLET
PIPING
80
80
20
18
MHI
03MAB031AE1
116
PLUG
HR STEAM INLET
PIPING
40
40
10
18
MHI
03LB001AA500
MHI
03LB001AA501
MHI
03LB002AA500
MHI
03LB003AA500
PACKING AND
GASKET SET FOR
NONRETURN VALVE
EXTRACTION
NON-RETURN
VALVE
26
MHI
03LB004AA500
MHI
03LBS03AA500
MHI
03LBS04AA500
MHI
03MAA02AE101
MSV ACTUATOR
62
MHI
03MAA02AE102
Main Turbine
Mitsubishi
B-13
REMARKS
Appendix B
MM-M05.01
Rev.001
INITIAL QUANTITY
ON HAND QTY.
STRATEGIC
SPARE PARTS
LEAD
TIME
(PO TO
FOB) Wk
62
62
ICV ACTUATOR
32
TRIP SOLENOID
VALVE
32
03MAY03AA502
EMERGENCY PISTON
VALVE
62
MHI
03MAY03AA502
12
12
32
MHI
03MAY03AA502
32
32
32
MHI
03MAY03AA502
SERVO VALVE
10
10
32
MHI
03MAY03AA502
OPC SOLENOID
VALVE
32
MHI
03MAY03AA502
O-RING (AS568-8)
16
16
SUPPLIER
NAME
EQT .
MHI
03MAA03AE101
MHI
03MAA03AE102
MHI
03MAA03AE103
MHI
03MAA03AE104
MHI
03MAB02AE101
MHI
03MAB02AE102
MHI
03MAB03AE101
MHI
03MAB03AE102
MHI
03MAB03AE103
MHI
03MAB03AE104
MHI
03MAB04AA101
MHI
03MAB04AA102
MHI
Main Turbine
Mitsubishi
PART
ID
PARTS DESCRIPTION
SUB-ASSEMBLY/
EQT DESCRIPTION
MAN.
PARTS NO.
PER EACH
QTY.
TOTAL
PLANT
GV ACTUATOR
RSV ACTUATOR
SPARE
PARTS 1 YR
B-14
REMARKS
Appendix B
MM-M05.01
Rev.001
INITIAL QUANTITY
ON HAND QTY.
STRATEGIC
SPARE PARTS
LEAD
TIME
(PO TO
FOB) Wk
32
O-RING (AS568-8)
03MAY03AA502
O-RING (AS568-12)
MHI
03MAY03AA502
FILTER ELEMENT
12
12
12
22
MHI
03MAY03AA502
BACK UP RING
12
12
12
22
MHI
03MAY03AA502
O-RING (AS568-214)
12
12
12
MHI
03MAY03AA502
O-RING (G60)
12
12
12
MHI
03MAY03AA502
O-RING (P16)
36
36
36
MHI
03MAV03AP101
OIL SEAL
18
MHI
03MAV03AP101
V-RING
18
MHI
03MAV03AP101
O-RING
18
MHI
03MAV03AP101
COUPLING RING
18
MHI
03MAV04AP101
OIL SEAL
MHI
03MAV04AP101
V-RING
18
MHI
03MAV04AP101
O-RING
18
MHI
03MAV04AP101
COUPLING RING
18
SUPPLIER
NAME
EQT .
MHI
03MAY03AA502
MHI
PART
ID
PARTS DESCRIPTION
SUB-ASSEMBLY/
EQT DESCRIPTION
MAN.
PARTS NO.
PER EACH
QTY.
TOTAL
PLANT
O-RING (AS568-12)
03MAY03AA502
MHI
03MAY03AA502
MHI
Main Turbine
Mitsubishi
AOP
TOP
SPARE
PARTS 1 YR
18
B-15
REMARKS
Appendix B
MHI
03MAV05AP101
OIL SEAL
MHI
03MAV05AP101
V-RING
18
MHI
03MAV05AP101
O-RING
18
MHI
03MAV05AP101
COUPLING RING
18
MHI
03MAV01BB101
OIL FILTER
03MAV07AN101
MAN.
PARTS NO.
PER EACH
QTY.
TOTAL
PLANT
SPARE
PARTS 1 YR
STRATEGIC
SPARE PARTS
18
EOP
18
18
MM-M05.01
Rev.001
PARTS DESCRIPTION
SUB-ASSEMBLY/
EQT DESCRIPTION
LEAD
TIME
(PO TO
FOB) Wk
EQT .
MHI
PART
ID
ON HAND QTY.
SUPPLIER
NAME
Main Turbine
Mitsubishi
B-16
REMARKS
Appendix B
TABLE B-3
RECOMMENDED LISTS OF STRATEGIC SPARE PARTS LIST FOR ONE YEAR OPERATION (OFF SHORE)
MM-M05.01
Rev.001
INITIAL QUANTITY
SUPPLIER
NAME
PART
ID
EQT .
MHI
03MAA31AE101
RELIEF DIAPHRAGM
MHI
03MAA31AE101
MHI
PARTS DESCRIPTION
SUB-ASSEMBLY/
EQT DESCRIPTION
MAN.
PARTS NO.
PER EACH
QTY.
TOTAL
PLANT
ON HAND QTY.
SPARE
PARTS 1 YR
STRATEGIC
SPARE PARTS
LEAD
TIME
(PO TO
FOB) Wk
4 pcs
15
1 set
15
03MAA31AE101
GASKETS FOR LP
PEDESTAL
1 set
15
MHI
03MAA31AE101
GASKET FOR
CROSSOVER
1set
30
MHI
03MAA02AA101,
102,103,104
MSV GASKET
8 pcs
16
MHI
03MAA02AA101,
102,103,104
GV GASKET
4 pcs
16
MHI
03MAA02AA101,
102,103,104
6 pcs
16
MHI
03MAB02AA101,
102,103,104
6 pcs
16
MHI
03MAB02AA101,
102,103,104
6 pcs
16
MHI
03MAB03AA101,
102,103,104
ICV GASKET
8 sets
16
MHI
03MAA31AE101
2 sets
16
MHI
03MAA31AE101
2 sets
16
MHI
03MAV03AP101
1 set
MHI
03MAV04AP101
1 set
MHI
03MAV05AP101
1 set
Main Turbine
Mitsubishi
STEAM TURBINE
MAIN VALVES
B-17
REMARKS
Appendix B
RECOMMENDED LISTS OF STRATEGIC SPARE PARTS LIST FOR ONE YEAR OPERATION (OFF SHORE)
INITIAL QUANTITY
MAN.
PARTS NO.
LEAD
TIME
(PO TO
FOB) Wk
EQT .
MHI
03MAV01BB101
MHI
03MAV07AN101
1 set
MHI
03MAV01AT101,
102
FILTER CARTRIDGE
OIL FILTER
1 set
MHI
03MAV21AT201
FILTER CARTRIDGE
OIL PURIFIER
1 set
MHI
03MAV07AT101
FILTER CARTRIDGE
OIL MIST
SEPARATOR
1 set
MHI
03MAY04AT504
BACK UP FILTER
ELEMENT
EH OIL UNIT
4pcs
MHI
03MAY05AT502
POLISHING FILTER
ELEMENT
2pcs
MHI
03MAY02AT503,
504
4pcss
MHI
03MAY04AT501,
502
RETURN FILTER
ELEMENT
4pcs
MHI
03MAY04AT504
EARTH FILTER
ELEMENT
16pcs
PARTS DESCRIPTION
SUB-ASSEMBLY/
EQT DESCRIPTION
PER EACH
QTY.
TOTAL
PLANT
SPARE
PARTS 1 YR
STRATEGIC
SPARE PARTS
MM-M05.01
Rev.001
PART
ID
ON HAND QTY.
SUPPLIER
NAME
Main Turbine
Mitsubishi
B-18
REMARKS
Appendix C
A p p en d i x
MM-M05.01
Rev.001
C Special Tools
Main Turbine
Mitsubishi
C-1
Appendix C
TABLE C-1
Eqt. ID
*(Note 1)
Tool
ID
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
RF
BEAM FOR
LIFTING GEAR
STEAM TURBINE
3741
RF
SADDLE FOR
LIFTING GEAR
STEAM TURBINE
256
RF
CHAIN BLOCK
FOR LIFTING
GEAR
STEAM TURBINE
245
RF
CHAIN BLOCK
FOR LIFTING
GEAR
STEAM TURBINE
85
RF
SHACKLE FOR
LIFTING GEAR
STEAM TURBINE
MM-M05.01
Rev.001
PJ No.
Main Turbine
Mitsubishi
Size
RS25
100
225
21
RS80
180
445
132
RS16
80
205
10
Remarks
C-2
Appendix C
PJ No.
RF
Tool
ID
SHACKLE FOR
LIFTING GEAR
Suppliers
ID No.
(Note 2)
RF
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
Remarks
STEAM TURBINE
Total Qty.
Supplied
for Plant
STEAM TURBINE
Size
RS32
220
380
48
56
12710
146
44
7140
62
44
4770
42
44
4830
42
36
13330
65
36
5680
30
48
5320
62
48
5410
63
C-3
Appendix C
PJ No.
RF
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
STEAM TURBINE
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
32
2200
44
2900
21
60
3900
55
RF
GUIDE PILLAR
FOR HP ROTOR
(GEN. SIDE)
STEAM TURBINE
31
RF
10
GUIDE PILLAR
FOR HP ROTOR
(GOV. SIDE)
STEAM TURBINE
31
Remarks
MM-M05.01
Rev.001
Tool
ID
Main Turbine
Mitsubishi
C-4
Appendix C
PJ No.
Tool
ID
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
RF
11
GUIDE PILLAR
FOR LP ROTOR
STEAM TURBINE
164
RF
12
GUIDE PILLAR
FOR LP INNER
CASING
STEAM TURBINE
46
RF
13
OVERHAUL TOOL
FOR NO. 1
BEARING
STEAM TURBINE
123
MM-M05.01
Rev.001
Remarks
Main Turbine
Mitsubishi
C-5
Appendix C
PJ No.
Tool
ID
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
RF
14
OVERHAUL TOOL
FOR NO. 2
BEARING
STEAM TURBINE
134
RF
15
OVERHAUL TOOL
FOR NO. 3
BEARING
STEAM TURBINE
223
RF
16
OVERHAUL TOOL
FOR NO. 4
BEARING
STEAM TURBINE
230
MM-M05.01
Rev.001
Remarks
Main Turbine
Mitsubishi
C-6
Appendix C
PJ No.
Tool
ID
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
RF
17
OVERHAUL TOOL
FOR NO. 5
BEARING
STEAM TURBINE
230
RF
18
OVERHAUL TOOL
FOR NO. 6
BEARING
STEAM TURBINE
310
RF
19
MICROMETER
FOR THRUST END
STEAM TURBINE
0.1
RF
20
STEAM TURBINE
0.1
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Remarks
C-7
Appendix C
PJ No.
RF
21
22
MM-M05.01
Rev.001
RF
Main Turbine
Mitsubishi
Tool
ID
OVERHAUL TOOL
FOR LP OUTER
GLAND
BOLT HEATER
STEAM TURBINE
STEAM TURBINE
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
Remarks
393
Type
26
1560
Straight
18
26
1310
Straight
26
1160
Straight
23
1490
Straight
23
1100
Straight
20
1140
Straight
18
850
Straight
18
530
Straight
26
1210
Flexible
26
1040
Flexible
C-8
Appendix C
PJ No.
RF
22
(cont)
BOLT HEATER
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
26
770
Flexible
24
960
Flexible
24
790
Flexible
20
950
Flexible
20
720
Flexible
17.5
770
Flexible
15
670
Flexible
15
610
Flexible
RF
23
STEAM TURBINE
10
RF
24
DISTRIBUTION
PANEL FOR BOLT
HEATER
STEAM TURBINE
45
25
SLEEVE FOR
BOLT STRETCH
MEASURING
DEVICE
STEAM TURBINE
RF
Main Turbine
Mitsubishi
Remarks
STEAM TURBINE
MM-M05.01
Rev.001
Too
l ID
26
195
0.9
31.5
200
37
210
1.3
C-9
Appendix C
PJ No.
RF
26
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Tool
ID
STEAM TURBINE
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
15.8
450
15.8
405
04
15.8
470
0.5
15.8
495
0.5
15.8
510
0.5
15.8
535
0.5
15.8
465
0.5
18.8
410
0.4
18.8
435
0.5
18.8
490
0.5
18.8
505
0.5
18.8
625
0.6
18.8
760
0.7
18.8
805
0.7
21.8
1030
1.1
21.8
1100
1.2
21.8
505
0.7
21.8
585
0.7
21.8
785
0.9
21.8
810
0.9
24.3
810
0.9
24.3
525
0.7
Remarks
0.4
C-10
Appendix C
RF
26
(Cont)
Too
l ID
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
24.3
650
0.8
24.3
860
24.3
1025
1.1
24.3
1050
1.1
24.3
1440
1.4
27.8
1095
1.7
27.8
630
1.1
27.8
905
1.5
27.8
1015
1.6
27.8
1075
1.7
27.8
1125
1.8
27.8
1185
1.8
27.8
1275
27.8
1470
2.2
27.8
1485
2.2
27.8
1525
2.3
Remarks
STEAM TURBINE
MM-M05.01
Rev.001
Eqt. ID
*(Note 1)
Main Turbine
Mitsubishi
C-11
Appendix C
Tool
ID
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
RF
27
RF
28
RATCHET FOR
TURNING GEAR
STEAM TURBINE
RF
29
GREASE GUN
STEAM TURBINE
RF
30
WRENCH FOR
ROTOR BALANCE
PLUG
STEAM TURBINE
MM-M05.01
Rev.001
PJ No.
Main Turbine
Mitsubishi
STEAM TURBINE
1.7
Remarks
21.7
2000
10.1
21.7
1200
6.5
21.7
500
3.3
13.8
400
1.5
C-12
Appendix C
PJ No.
Tool
ID
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
A
T
RF
31
32
MM-M05.01
Rev.001
RF
Main Turbine
Mitsubishi
SPECIAL EYE
BOLT
SINGLE ENDED
SPANNER
STEAM TURBINE
STEAM TURBINE
Weight
M12
82
0.3
M20
105
0.6
M24
140
M40
160
2.7
M36
180
3.8
M42
200
5.4
90
Remarks
0.1
95
0.1
10
110
0.1
13
135
0.1
17
165
0.1
19
180
0.1
C-13
Appendix C
PJ No.
RF
32
(CONT)
Special Tool
Name/ Description
SINGLE ENDED
SPANNER
STEAM TURBINE
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
22
205
0.2
24
220
0.2
27
245
0.3
30
270
0.4
32
285
0.4
36
320
0.5
41
360
0.7
46
400
50
430
1.2
55
470
1.7
65
550
2.3
70
590
3.3
75
630
Remarks
MM-M05.01
Rev.001
Tool
ID
Main Turbine
Mitsubishi
C-14
Appendix C
PJ No.
Tool
ID
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
RF
33
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
DOUBLE
HEXAGONAL
SHOCK SPANNER
STEAM TURBINE
Weight
Remarks
41
223
0.8
46
237
0.9
50
250
1.1
55
270
1.6
60
308
2.5
65
308
2.5
75
345
3.5
80
365
4.2
85
365
4.2
95
392
4.5
105
420
7.5
110
443
8.8
54
270
1.5
63
308
2.1
71
345
3.4
77
345
3.9
C-15
Appendix C
PJ No.
RF
34
RING SPANNER
STEAM TURBINE
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
19
166
0.2
22
187
0.2
24
231
0.3
27
231
0.5
30
265
0.4
32
265
0.4
36
292
0.7
46
365
1.7
55
441
2.7
65
508
4.2
75
584
6.1
Remarks
MM-M05.01
Rev.001
Tool
ID
Main Turbine
Mitsubishi
C-16
Appendix C
PJ No.
35
HEXAGONAL
WRENCH KEY
STEAM TURBINE
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
63
0.1
70
0.1
80
0.1
90
0.1
100
0.1
112
10
0.1
125
12
0.2
140
14
0.3
160
17
0.4
180
19
0.6
200
22
0.8
250
27
2.1
315
32
3.1
355
36
4.0
Remarks
MM-M05.01
Rev.001
RF
Tool
ID
Main Turbine
Mitsubishi
C-17
Appendix C
PJ No.
RF
36
37
SCREW DRIVER
SCREW DRIVER
Suppliers
ID No.
(Note 2)
Total
Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
Remarks
STEAM TURBINE
215
100
28
0.2
280
150
32
0.3
STEAM TURBINE
360
200
37
0.1
395
250
37
10
0.2
MM-M05.01
Rev.001
RF
Tool
ID
Main Turbine
Mitsubishi
C-18
Appendix C
PJ No.
RF
RF
38
39
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
Tool
ID
EYE BOLT
DRAWING BOLT
STEAM TURBINE
STEAM TURBINE
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
M10
41
59.3
0.1
M12
50
73
0.2
M16
60
87
0.3
M20
72
101
0.4
M24
90
128
0.8
M30
110
155
1.5
M36
133
186.5
2.8
M42
151
215.5
4.3
M48
170
240
M6
38
150
0.1
M8
38
200
0.1
M
10
13
51
200
0.3
M
12
13
56
200
0.3
Remarks
C-19
Appendix C
PJ No.
RF
RF
41
PLUG WRENCH
A TYPE
SPECIAL
WRENCH
HANDLE
STEAM TURBINE
STEAM TURBINE
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
70
17
0.2
75
19
0.1
95
26
0.6
110
32
1.1
150
41
2.4
165
46
3.2
80
50
4.5
Remarks
0.1
MM-M05.01
Rev.001
40
Tool
ID
Main Turbine
Mitsubishi
C-20
Appendix C
PJ No.
Rev.001
RF
RF
RF
42
43
44
Tool
ID
BOX SPANNER
BOX SPANNER
MONKEY
WRENCH
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
STEAM TURBINE
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
750
46
46
6.9
750
54
54
7.1
400
46
46
3.8
400
54
54
380
120
46
3.6
470
130
54
4.8
Remarks
STEAM TURBINE
STEAM TURBINE
MM-M05.01
Main Turbine
Mitsubishi
310
0.7
385
1.3
C-21
Appendix C
PJ No.
RF
45
JACKING BOLT
STEAM TURBINE
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
W2
360
5.9
W1.1/2
560
5.6
W1.1/2
460
4.6
M10
80
0.1
M12
300
0.3
M20
140
0.4
M24
400
1.6
M36
500
4.5
M24
300
1.2
M24
560
2.1
M24
130
0.6
M24
120
0.5
M12
140
0.2
12
M30
140
Remarks
MM-M05.01
Rev.001
Tool
ID
Main Turbine
Mitsubishi
C-22
Appendix C
PJ No.
RF
45
(Cont.)
46
Special Tool
Name/ Description
JACKING BOLT
TURN BUCKLE
FOR LP
TURBINE FLOW
GUIDE
STEAM TURBINE
Suppliers
ID No.
(Note 2)
Total Qty.
Supplied
for Plant
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
M12
140
0.1
M36
240
2.6
M48
220
4.5
M24
250
1.0
M16
100
0.2
M24
500
2.0
M30
400
2.4
M20
110
0.3
M24
360
1.4
M16
140
0.3
M12
180
0.2
Remarks
STEAM TURBINE
950
700
50
23.6
1740
700
50
29.6
MM-M05.01
Rev.001
RF
Tool
ID
Main Turbine
Mitsubishi
C-23
Appendix D
A p p en d i x
D Coupling Alignment
MM-M05.01
Rev.001
Specific procedures for the alignment of the main turbine rotor couplings are provided in
Maintenance Manual M-05.05, Turbine Couplings and Alignment.
Main Turbine
Mitsubishi
D-1
Appendix E
A p p en d i x
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
E-1
MM-M05.01
Rev.001
Appendix E
MPTD-3-0692
Main Turbine
Mitsubishi
FIGURE E-1
MM-M05.01
Rev.001
Appendix E
MPTD-3-0590
Main Turbine
Mitsubishi
FIGURE E-2
Appendix F
A p p en d i x
Shows the horizontal surface of the right side of the relevant turbine cylinder with the
related inner casings, blade rings, nozzle boxes, etc. clearly indicated.
The number located adjacent to the bolt holes is the mark number of the installed stud,
stud bolt, reamer (or fitting) bolt.
Shows the stud or bolt mark numbers, and the alphabetical letters in the adjacent
column indicate the relevant stud or bolt section.
Example (refer to Figure F-1).
Bolt mark no. 1 = A = Reamer (fitting) stud
Bolt mark no. 11 = E = Reamer bolt
Bolt mark no. 2 = B = Stud bolt
Provides the information such as the bolt diameter, bolt free length, nut first torque,
nut turn angle, arc length from zero angle and the amount of bolt stretch or tightening
torque. The type and size of the required bolt heater is also indicated.
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
F-1
MM-M05.01
Rev.001
Appendix F
MPTD-3-0526
Main Turbine
Mitsubishi
FIGURE F-1
MM-M05.01
Rev.001
Appendix F
MPTD-3-0527
Main Turbine
Mitsubishi
FIGURE F-2
MM-M05.01
Rev.001
Appendix F
MPTD-3-0528
Main Turbine
Mitsubishi
FIGURE F-3
MM-M05.01
Rev.001
Appendix F
MPTD-3-0529
Main Turbine
Mitsubishi
FIGURE F-4
MM-M05.01
Rev.001
Appendix F
MPTD-3-0530
Main Turbine
Mitsubishi
FIGURE F-5
Appendix G
A p p en d i x
Place a length of 1.5 mm lead wire around the shroud of the bottom center blade in
the lower half stationary blade rings, and around the shroud of the center blade in the
upper half stationary blade rings, gently shaping the lead wire to the contour of the
shroud and the seal strips.
Place a similar length of lead wire around the top center and bottom center blades on
each row of rotating blade shrouds, again gently shaping the lead wire to the contour
of the blade shroud surface.
Note
Selection of lead wire should be such that the diameter of the wire is
higher than the clearance to be measured.
3
Secure the lead wires in their positions using tape or any other suitable method.
When the lead wires have been securely positioned, lift the rotor according to the
procedure described in Appendix H and lower it into the turbine cylinder.
Stop lowering the rotor before the journals seat in the bearings, and set the rotor in the
K position. K position is indicated in the turbine clearance drawings provided in
Chapter 5.
Note
MM-M05.01
Rev.001
Clean all horizontal joint surfaces using a smooth file to remove any burrs, then using
suitable lifting equipment lower the upper half stationary blade rings into position.
Install and tighten the horizontal joint bolts, then measure the horizontal joint gap with
feeler gauges and confirm that the joints are completely closed.
Main Turbine
Mitsubishi
G-1
Appendix G
Using the jacking bolts provided raise each upper half stationary blade ring by about 5
mm.
10
Attach the lifting equipment to each upper half stationary blade ring, remove the blade
rings in sequence, then using the rotor lifting beam and following the prescribed
procedure raise and remove the rotor.
11
Carefully remove the lead wires from both the stationary and the rotating blades
taking care not to misplace the wires on removal.
12
To prevent the loss of, or damage to, the lead wires, they should be affixed to a piece
of cardboard in the sequence in which they were removed. Each should be clearly
marked with the location from which they were removed, stating cylinder identification,
top or bottom, row and whether stationary or rotating blade.
13
When all lead wires have been removed, measure the indentations in the lead wire
using an appropriate wire gauge, micrometer, or similar measuring device, and record
the clearances for inclusion in the final blade clearance charts.
LP1/LP2 Turbine
MM-M05.01
Rev.001
Following a similar procedure, the top and bottom radial seal clearances in the LP1 and LP2
turbines can be measured by fixing suitable size lead wires and lifting the inner casing and
LP blade rings.
Main Turbine
Mitsubishi
G-2
Appendix H
A p p en d i x
H Lifting Methods
The attached drawing shows the recommended lifting method for the turbine rotor and the
casings.
When lifting the heavy turbine parts, it is of utmost importance that the lifted object level
shall be maintained and without rotational or swaying movement during the period of the
lift.
It is therefore necessary to ascertain the center of gravity of the object to be lifted at the
commencement of erection work and to determine the relative axial position between the
object and the lifting gear elements for convenience in application thereafter.
This can be achieved at the commencement of the turbine installation on site, by marking
on the lifting beam the position of the beam clamps required to obtain a level lift of each
casing or rotor.
Lifting slings shall be adjusted to the correct length by the turn buckle. Insert a suitable
material between the sling and the contact surface of the object to be lifted, for protection.
When removing the turbine casing covers, separate the horizontal flanges clearly using
the jacking bolts provided before application of lifting gear and crane. For the LP1/LP2
turbine inner cylinder, the covers shall be lifted (or installed) vertically through "casing
guide bolts" which are round bar rods installed temporarily at the corners of the inner
casing horizontal flange.
When removing (or installing) the turbine rotor, out of or into the casing base, the "rotor
guide pillars" provided are to be installed at the outer casing horizontal joint, one at each
end of the rotor, to prevent rotor swing.
Frequent inspection of all lifting equipment is essential.
MM-M05.01
Rev.001
Avoid the use of slings in which there is a kink, dent, or some other harmful flaw.
Main Turbine
Mitsubishi
H-1
MM-M05.01
Rev.001
Appendix H
MPTD-3-0693
Main Turbine
Mitsubishi
FIGURE H-1
Appendix I
A p p en d i x
I
1
Lubricate threads and face of the bolt and nut with anti-seize compound.
CAUTION
Excessive grease may enter the bolt heating hole and carbonize during
heating, creating the possibility of an electrical short.
Note
Where cap nuts are used, excessive lubricant may squeeze through the thread,
run over the top of the bolt and enter the heating hole. It is recommended that
the nut be run down through the lubricated bolt and the excessive lubricant
removed from the cap nut and the top of the bolt.
Note
MM-M05.01
Rev.001
Run the nut onto the bolt or stud threads to ensure free fitting.
Clean the bottom of the bolt heating hole with compressed air followed by a swab, the
swab end being smeared with a little clean grease.
Measure the stud or bolt length, with the nut loose using the adapter and the extension
rod.
Tighten all nuts with a 90 kg pull on a wrench handle length of 12 centimeter per one
centimeter of bolt diameter.
Repeat until all the nuts are pulled up uniformly over the entire joint.
Main Turbine
Mitsubishi
I-1
Appendix I
Example:
Bolt Diameter:
2.5 inch
120 cm
Required torque:
Required force:
57 kg (6658/120)
Obtain the required nut turn from the chart, in Appendix F, and chalk mark reference
points on the nuts and adjacent flange. For a through bolt, the holding nut on the
opposite end and the flange should also be marked to observe if the bolt turns during
tightening.
Heat the stud or bolt and turn the nuts until the reference points coincide.
After the stud or bolt has cooled to the same temperature as before heating, clean
bottom of the hole and measure to see if the required stretch, within tolerance of 10%
has been obtained.
10705BU
330 mm
0.5
19.5 mm
0.5 mm
104 degrees
19 mm
0.5 mm
MM-M05.01
Rev.001
Main Turbine
Mitsubishi
I-2
Appendix I
Amount of Stretch
The amount of stretch for alloy steel bolts or studs should be as shown in the following table.
Bolt Material
28
0.0013
32
0.0015
42
0.00195
JIS-SCM435
Equivalent material
SAE 4135 or AISI 4137
W-10705BU
Equivalent material
AISI 616 Type 22
W-15106FD
Equivalent material
AISI 690,
Refractaloy 26, M8B
The free length of stud is the thickness of the flange from joint face to spot facing, plus one
stud diameter plus washer thickness, if washers are used. The free length of a bolt
extending through both flanges is the thickness of both flanges between spot facings, plus
one bolt diameter, plus thickness of both washers, if washers are used.
Lubrication
The threads of bolts and studs and the bearing faces of nuts should be well lubricated with a
good anti-seize compound to reduce friction and to avoid thread seizure at high
temperature service. We recommend a compound of molybdenum disulphide.
Stretching
The larger size bolts and studs are provided with holes in the center for stretching by means
of electric heating elements. Never use gas flame directly on the bolt or stud because of
possible damage to the material.
MM-M05.01
Rev.001
The smaller bolts and studs must be stretched by wrenching. It is preferable to tighten these
with a steady pull by using an extension wrench.
Tighten all nuts with a 90 kg pull on a wrench handle length of 12 cm for each centimeter of
bolt diameter. Repeat until all the nuts are pulled up uniformly over the entire joint. Then
obtain the required nut turn from the chart provided in Appendix F, and chalk mark
reference points on the nuts and adjacent flange. Turn the nuts until the reference points
coincide.
Main Turbine
Mitsubishi
I-3
Appendix I
The above procedure is expected to give a total stretch which corresponds to the required
initial stress. The permissible tolerance on the measured stretch is 10%.
Measuring Stretch
The only positive way to determine the stretch of a bolt or a stud is by micrometer
measurement. Bolts and studs 50 mm diameter and above have a center hole into which a
rod, adapter and depth micrometer can be inserted as per Figure I-1.
The stretch of studs without holes can usually be measured by means of special adapters,
slipped over the nut and a depth micrometer.
The stretch of through bolts with standard hex nuts but without holes can be measured over
the bolt ends using an ordinary outside micrometer.
Note
With ordinary care it should have a long life. Even if the heater is bent, the
usefulness of the heater is not impaired as long as actual contact does not
occur between the heating element and the sheath.
The heater may be used on either alternating or direct current circuits, with the usual
protection of fuses or circuit breakers, and with wiring adequate to carry the required current.
However, when used in a direct current circuit, the connector when provided should not be
used as an interrupting device. An additional interrupting device should be provided.
MM-M05.01
Rev.001
It is desirable, but not imperative, that neither side of the circuit be grounded. Absence of a
ground would reduce the likelihood of a short circuit on a heater. It is recommended that
heaters be used until they actually fail in service.
However, when being used, if the required bolt elongation is not obtained in seven minutes
per inch of bolt diameter the cause should be investigated to avoid unnecessary burning out
of the heater.
Main Turbine
Mitsubishi
I-4
Appendix I
No attempt should be made to protect any part of the heater surface by wrapping it with
asbestos or other insulating material since this would cause hot spots and would certainly
result in burning out of the heating coil.
The heater should never be handled with the current on, and care should be exercised in
handling it while hot to avoid burns.
MM-M05.01
Rev.001
The lead wires, while flexible, are heavy and rigid enough to use in handling the heater and
securing it in place when necessary to use the heater in a upside down position.
Main Turbine
Mitsubishi
I-5
Appendix I
TABLE I-1
Capacity
(kW)
Voltage (V)
Hole (mm)
Remarks
4.5
400
26
1050
28
STRAIGHT
5.5
400
23
1450
25
STRAIGHT
4.0
400
23
1100
25
STRAIGHT
4.5
400
20
1350
22
STRAIGHT
2.5
400
20
800
22
STRAIGHT
1.6
400
20
600
22
STRAIGHT
4.5
400
19
1350
20
STRAIGHT
3.5
400
18
1150
19
STRAIGHT
2.2
400
18
800
19
STRAIGHT
10
1.7
400
18
650
19
STRAIGHT
11
1.4
400
18
550
19
STRAIGHT
12
1.4
400
15.3
650
16
STRAIGHT
13
1.1
400
15.3
550
16
STRAIGHT
14
1.0
400
15.3
480
16
STRAIGHT
15
2.7
400
20
950
22
FLEXIBLE
16
1.5
400
17.5
700
19
FLEXIBLE
MM-M05.01
Rev.001
Marks
Main Turbine
Mitsubishi
I-6
Appendix I
MICROMETER
MEASUREMENT
AFTER HEATING
MEASURING
ROD
MEASUREMENT
BEFORE HEATING
Rev.001
MEASURING
SLEEVE
MM-M05.01
MGL-4-4959
FIGURE I-1
Main Turbine
Mitsubishi
I-7