ATO SHUNT

100% production adherence is achieved

No production this week due to Mcase Plus transfer

Shipments are made via boat

We have very high demand from TYCOs consignment


BF2/BFINLINE

Good job team! 100% production adherence is achieved

Current production is set at 30.2k pcs

OPEN Issues:
o 153.5395.6502 - we have delayed supply of raw materials due to forwarder issue
BRAKESWITCH

Production hit only 100% producing 1200 pcs as planned.

Current production is set at 1200 pcs

OPEN issues
o We have inventory discrepancy on the spring PN 912-294.
o SAP shows 5,868 Pieces, but the material is not physically at the plant. Affected material is 94Z
o E&O brakeswitch raw materials were electronically scrapped last 3/27
CABLE

PRO
Production achieved 100% adherence result
Current weeks plan is set at 12.43k pcs
Need to continue running at this pace
OPEN issues
o High orders from Yazaki for 200 A cable pro materials.
o New demand from Delphi on new cable pro part numbers

DIODE

Production only able to produce 126k pcs as planned

This week, target is to run 178k pcs

OPEN issues
o Late movement of stocks from MOA/QM location due to burrs on housing
o 104P Quality issue raised by Delphi. Doing expedited shipments to NL2 due to missed production.
o 107P Urgent; Quality already approved the deviation/no approval yet from SEWS
JCASE

We got 100% adherence from last week production producing 2.09M

Current weeks production is set at 1.8M pcs

OPEN issues
o Stocks are depleting already due to series of missed production.
o All materials are being air shipped and some are for expedite shipment
o Series of Line down claims globally mainly on 30 and 40 OLD JCASE
SMARTUSE

Production resulted to 100% producing 83k pcs

This week we need to run MINI and ATO smartfuses which totals to 99k pcs

Misses will not be adjusted. Need to hit target since we are seeing very high aftermarket requirement

OPEN Issues:
o Staffing issue and absenteeism

Action Plan
o 2 new manpower are in the line right now to hit the target

BRAKE SWITCH
Production hit the target of 1200 pcs
Current week production is set at 1200 pcs
o Open Issues:
o We need to monitor ATB and active parts of Ford to avoid scorecard deductions
o ATB from Ford is already at the system. Marcos needs to verify the raw materials availability before
advising how we can serve Ford
CF FUSE

Production is on track
Next week plan is 6.5k pcs
No sales last week

CABLE PRO
Production did last week as we were able to hit the plan of 9.95k pcs
Production this week totals to 12.1k
DIODE
Production team was able to complete 13k pcs last week resulting to 66.67% adherence result due ANFUSE
issue
As per Sergio, issue was related to the Molding tool, it had some cavities damaged by the stamping die
progression, both issues were fixed late and are under evaluation.
This week is target to run 170k pcs
We need to hit the target
Next weeks plan is 140k pcs as we will run ATO Diode
Open Issues:
o 118P resistors from Crestwood did not conform the standards. old supplier (Vishay) already OB the
parts
o 108P no more resistor. Next availability will be on 3/27 per Monica
o 112P we have quality issue on the resistors.
o 104P, 113P and 110P very high requirements
FUSE HOLDERS
We got 100% production volume adherence from last week production
This week is target to run 110k pcs
We need to stabilize production on the following weeks to 100k
Sales is very low at 44k pcs
HSB

We are behind our schedule due to machine issues


This week is target to run 340k pcs to recover some of the quantity we missed last week
Sales is high at 246k pcs

Very high requirements from Tyco, WPG, Setron, Fujikura, Shnaghai Charles, Globe
With returns from TTI >> 170k pcs expected to be used to serve customer orders
Will proceed to expedited shipment on PN 156.5677.6172 at NL2

TVS DIODE
No production last week
No production this week due to repair of machines