500 MW
ERECTION
T1-08-0909G
Page No. 1of 9
STEAM TURBINE
500 MW
ERECTION
T1-08-0909G
Page No. 3of 9
During installation of spring units, additional shims are provided for this 5.00 mm additional
compression and which are removed at the time of loosening of the spring elements before
final alignment of the machine. These additional shim are removed in minimum two stages
after ensuring, that all the major parts of the machine are installed and condenser have been
filled upto operating water level including CW pumps in operation for full load condition of
the machine. It is also not necessary to remove this complete 5.00 mm shims from each spring
unit and the same may vary from spring unit to spring unit depending upon the variation of
column level/elevation and variation in level of spring cover plate etc.
Releasing of TG Deck Spring for removal of additional shims.
Refer section
STEAM TURBINE
500 MW
ERECTION
T1-08-0909G
Page No. 5of 9
springs are permitted after final alignment of the rotors. During any subsequent adjustment of
TG deck spring the final alignment of all rotors are to be checked.
After placement of TG deck springs in locked condition with shims and resistance pad etc, an
equal air gap between 5 .00 to 10.00 mm is left between all the springs and bottom of the steel
cover plate. The exact value of air gap can be determined by the civil engineer depending
upon his experience but generally it is between 5.00 to 10.00 mm only. The form work and
support of TG deck are removed once the concrete has hardened sufficiently. This is
generally done after 28 days of casting of the deck and all load of deck is transferred over
the spring units . Afterwards TG pedestals are placed /aligned and their elevation are
maintained as per required catenary of the machine before grouting the pedestals with the
non-shrinking cements . During releasing of TG deck spring while this additional 5.00 mm
shims (for additional compression) are removed the catenary of the machine is to be achieved
within + 0.20 mm bearing No. 1&4 with the help of TG deck springs by adjusting the shims
and afterwards only the rotors alignments should be taken up. Any minor variation in catenary
left after releasing of TG deck spring may be adjusted in the spherical/cylindrical seat of the
bearings for achieving the correct alignment of the shaft.
The height of TG deck spring are taken on four corners near the springs. Here some punch
mark may be provided on all springs so that measurements are taken at the same place always.
Certain minor variations on height of the spring units are permitted , if it is required for
achieving the Catenary of the machine. The TG deck spring shims are adjusted with the help
of hydraulic jacks. Either two/four numbers hydraulic jacks are used for this purpose which
are supplied by the spring supplier. Similar methods are used for release of the spring locking
bolts also. These hydraulic jacks are group operated type and works with one pumping unit
which is electrically operated. The ready-made galvanized shims are also supplied in required
sizes alongwith spring unit in 3.00 mm and 2.00 mm thickness so an adjustment of upto 1.00
mm is possible in spring Units.
After finally release of TG deck spring and with water in condenser hotwell upto operating
level including CWP in operation then spring heights are measured on four corners for all
future reference. The sizes of the shims are also recorded for each spring. A bench mark may
also be preserved on TG floor as reference for LP rear pedestal parting plane height for all
future reference. During realignment of machine in subsequent overhauling the `catenary of
the machine are to be checked and if necessary the shims of the springs are to be adjusted to
achieve the correct catenary or at least to the old values . The catenary checking and
STEAM TURBINE
500 MW
ERECTION
alignment of rotors may be done together but all major adjustment for correction of catenary
is to be done by adjusting the shims of the spring units. Any minor adjustment for alignment
may be done on bearing if it is in permissible values and margins is available on the bearings
seals bores.
T1-08-0909G
Page No. 7of 9
Before neck welding all the major components of the condenser are to be installed including
its tubing , water boxes, dome wall assembly and its stiffener pipe, etc. After installation of all
the major components of the condenser the spring are released i.e. condenser is floated for
welding with the Turbine.
After floating the condenser, the spring height is recorded on its four corner and further they
are pre-compressed for the value of welding shrinkages by an amount of 3.00 mm depending
upon the designer requirements. The required pre-compression of the condenser spring can be
done by filling the equivalent weight of the water in the hot well of condenser and then locking
the condenser spring at that position. The locking of springs can be avoided if water is filled
up to required level and level is maintained during neck welding of the condenser. Sometime
during floating of condenser an additional weight of water is filled up in condenser depending
upon the designers requirement.
The TG deck springs are kept in locked condition during the neck welding of the condenser.
After completing the neck welding and draining of condenser ( for equivalent value of the
pre-compression of the condenser springs) the condenser springs height are recorded and if
variation are noticed for more than +/- 1.00 mm than the necessary adjustment is to be
carried out. This can be done by adjusting the shims in the springs although if proper care is
taken during the neck welding no such variation are noticed.
Further during floating of TG deck springs the condenser spring heights are also monitored
and if necessary the shims may be adjusted on condenser springs to maintain the old values of
the condenser spring at the time of floating of condenser. During subsequent overhaul of the
unit the condenser spring height alongwith TG deck spring height need a monitoring. As a
general practice whenever the TG deck spring height are checked then the condenser springs
height are also to be checked.
STEAM TURBINE
500 MW
ERECTION
During floating of the condenser it is to be ensured that condenser is free all a round and
none of the pipe line are obstructing the movement of the condenser. All the connected pipe
lines of the condenser are to be ensured on permanent hangers before floating of the
condenser. The condenser neck welding is carried out as per the back-step method for which
the procedure is laid down in KWU manual of steam Turbine assembly sheet No 1-2-63300001/1.
During neck welding the complete height of L.P. inner and L.P. outer casing is installed in
position.
T1-08-0909G
Page No. 9of 9