Professional Documents
Culture Documents
VOL-II
DESIGN CRITERIA
DESIGN
MUMBAI
Section - 3
REV. 0
Sheet
1 of 1
PART IV
SECTION 3
DESIGN CRITERIA
FOR
9 WELL PLATFORMS PROJECT
OFFSHORE DESIGN
OIL AND NATURAL GAS CORPORATION LIMITED
MUMBAI REGION, MUMBAI
INDIA
PREPARED APPROVED
BY
BY
45
REMARKS
NO. OF
PAGES
0
DATE
REV.
OFFSHORE
DESIGN CRITERIA
DESIGN
MUMBAI
VOL-II
Section - 3
SECTION - 3
TABLE OF CONTENTS
SUB-SECTION
TITLE
3.0
DESIGN CRITERIA
3.1
GENERAL
3.2
PROCESS
3.3
PIPING
3.4
STRUCTURAL
3.5
ELECTRICAL
3.6
INSTRUMENTATION
3.7
REV. 0
Sheet
2 of 2
OFFSHORE
DESIGN
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
PART-IV
SECTION 3.1
DESIGN CRITERIA
GENERAL
VOL-II
Section - 3
REV. 0
Sheet
3 of 3
OFFSHORE
DESIGN
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
3.0
DESIGN CRITERIA
3.1
GENERAL
VOL-II
Section - 3
Objectives
The Contractors design must be done in a manner to assure that the
following objectives will be met -
REV. 0
Sheet
4 of 4
OFFSHORE
DESIGN
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
VOL-II
Section - 3
3.1.2
3.1.2.1
The wind, tidal, wave and current parameters are defined in report by
A.H.Glenn & Associates (relevant parameters based on this report
are included in Appendix 3.2.1). The complete report will be given
to the contractor to be used in his final design.
3.1.2.2
3.1.2.3
3.1.3
REV. 0
Sheet
5 of 5
OFFSHORE
DESIGN
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
3.1.4
VOL-II
Section - 3
3.1.5
Material of Construction
The Contractor shall note that in this bid document, wherever NACE
Carbon Steel or Carbon Steel with MR-01-75 is specified, it shall
mean NACE Carbon Steel meeting the requirement of NACE MR01-75 specification. This requirement shall be applicable to risers
and submarine pipelines, piping components, vessels, instruments
and other related facilities. The Contractor shall clearly specify this
requirement while procuring the necessary equipment / piping.
REV. 0
Sheet
6 of 6
OFFSHORE
DESIGN
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
PART-IV
SECTION 3.2
DESIGN CRITERIA
PROCESS
VOL-II
Section - 3
REV. 0
Sheet
7 of 7
OFFSHORE
MUMBAI
9 Well Platforms Project
3.2
VOL-II
DESIGN CRITERIA
DESIGN
Section - 3
PROCESS
This section of the bid document outlines design criteria for
Process and utility systems on ZB, RS-1, RS-2, RS-3, RS-5, RS-7,
RS-11 RS-4 and RS-8 well platforms.
In addition to above contractor shall supply loose material
for the following
-
=
- ONE
NO. MPFM as per
instrumentation specification no 3209.
detail
mention
in
REV. 0
Sheet
8 of 8
OFFSHORE
DESIGN
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
VOL-II
Section - 3
within the scope of this tender. The design of process and associated
utility systems for ZB, RS-1, RS-2, RS-3, RS-5, RS-7, RS-11, RS-4
and RS-8 well Platforms shall be suitable for these rates. Contractor
shall also develop detailed Piping and Instrumentation Diagrams and
SAFE charts, incorporating all suppliers information..
For ZB, RS-1, RS-2, RS-3, RS-5, RS-7, RS-11, RS-4 and RS-8 well
platforms, the routing / distribution of various utilities (namely Vent/
CD/ OHD/ ODD headers, instrument gas, utility gas, fire water etc.)
shown in the bid P & IDs are indicative. The Contractor shall
complete these as per final engineering requirements.
Placed below, is the list of sizing calculations/ documents/ drawings
which shall be submitted by Contractor, for review and approval
-
SAFE charts
Cause & Effect Diagram
Process Data Sheets for Instruments
Process Data Sheets for Equipments
Line List
Equipment List
Pressure & Temperature Profiles (for pipelines)
Fire Water Hydraulic calculations ( RS-7,ZB )
Vent Dispersion Calculations
REV. 0
Sheet
9 of 9
OFFSHORE
DESIGN
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
VOL-II
Section - 3
On ZB, RS-1, RS-2, RS-3, RS-5, RS-7, RS-11, RS-4 and RS-8 well
platforms. space provision shall be kept for installation of future
facilities as shown in P & IDs, layouts and elsewhere in the bid
document. It shall be ensured that these future facilities can be
installed and operated with ease. Engineering shall be done to take
care of future facilities. The built-up of future facilities requirement
in local and main shutdown panels are in firm scope of supply of the
Contractor. Adequate care shall be exercised when developing the
existing platforms modification requirement with special emphasis
towards safety, operability and hook up with the existing system
with minimum shutdown time requirements. It shall be ensured that
modifications to be implemented, do not affect the safety and
operability of the systems at the existing platforms.
The following sections outline the design criteria for ZB, RS-1,
RS-2, RS-3 RS-5, RS-7, RS-11, RS-4 and RS-8 well platforms.
Also, the size of topside piping, riser and pipeline from barrel to
barrel to be maintained same to ensure smooth piggability.
Documentation
The Contractor shall submit all documentation as per the
requirements given elsewhere in the bid document. In addition,
Contractor shall prepare 8 Nos. process packages and submit to the
Company & their Consultants, within one month of approval of all
these documents. The process package shall consist of the following
documents:
Design basis (with approved deviations, if any)
AFC P & IDs/ Suppliers P & IDs )
AFC Equipment Layouts
) (A0 & A3 size & bound
)
together)
PFDs & Material Balance
)
Data Sheets for Equipments
Data Sheets for Instruments
SAFE Charts
Logic Diagram
Line List
Equipment List
All process / sizing calculations
REV. 0
Sheet
10 of 10
OFFSHORE
DESIGN
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
3.2.1
VOL-II
Section - 3
REV. 0
Sheet
11 of 11
NAME OF PLATFORMS
3.2.1.2
DESIGN LIFE
3.2.1.3
PLATFORM LOCATION
WGS-84
:
EVEREST-1830
LOCATION
UTM
ZB
19 23 20.77
GEOGRAPHIC
AL
RS1
(FJ1)
732625mE
2145375mN
UTM
GEOGRAPHIC
AL
7112 53.939
750413mE
2147021mN
1924 6.566
25 years
732603.358mE
2145123.510m
N
19 23
18.255N
71 12
54.264E
750391.263mE
2146769.469m
N
19 24
04.054N
Bombay High
Datum
(EVEREST 1830)
732778.358mE
2145128.510mN
19 2318.345N
71 13 00.263E
750566.263mE
2146774.469mN
19 24 04.138N
OFFSHORE
DESIGN
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
UTM
RS2
(P02)
GEOGRAPHIC
AL
UTM
RS3
(P06)
RS7
(P-17)
GEOGRAPHIC
AL
RS-4
(P-04)
GEOGRAPHIC
AL
RS-11
( FJ-7)
736875mE
2146625mN
736853.337mE
2146373.496m
N
19 23
57.104N
71 15
20.442E
737028.337mE
2146378.496mN
19 23
59.616
71 15
20.098
744934.789mE
2145186.803mN
71 19
55.555
758 375 mE
19o 18
33.141 N
71o 27
31.883 E
743 625 mE
19o 25
01.719 N
71o 19
12.272 E
2138 500 mN
UTM
12 of 12
71 23 10.481E
2148 625 mN
UTM
Sheet
71 23
04.482E
2136 875 mN
UTM
Section - 3
REV. 0
71 23 4.079
19 23 9.378
GEOGRAPHIC
AL
VOL-II
739 125 mE
744913.079mE
2144935.292m
N
19 23
06.862N
71 19
55.934E
2136 623.512
mN
758 353.201
mE
19o 18 30.601
N
71o 27 32.320
E
2148 373.473
mN
743 603.303
mE
19o 24 59.212
N
71o 19 12.646
E
2138 248.537
mN
739 103.310
mE
19 23 57.192N
71 15 26.441E
745088.079mE
2144940.292mN
19 23 06.947N
71 20 01.932E
2136 628.512
mN
758 528.201 mE
19o 18 30.683
N
71o 27 38.315 E
2148 378.473
mN
743 778.303 mE
19o 24 59.298
N
71o 19 18.645 E
2138 253.537
mN
739 278.31 mN
OFFSHORE
DESIGN
MUMBAI
9 Well Platforms Project
GEOGRAPHIC
AL
RS-8
(FJ-2)
GEOGRAPHIC
AL
742 625 mE
19o 17
51.427 N
71o 18
31.943 E
2151 875 mN
UTM
RS-5
( P-01)
GEOGRAPHIC
AL
3.2.1.4
Section - 3
2135 375 mN
UTM
VOL-II
DESIGN CRITERIA
737 125 mE
19o 26
50.180 N
71o 15
31.022 E
2135 123.548
mN
742 603.285
mE
o
19 17 48.885
N
o
71 18 32.310
E
2151 623.466
mN
737 103.345
mE
o
19 26 47.683
N
o
71 15 31.368
E
REV. 0
Sheet
13 of 13
19o 19 32.076
N
71o 16 39.864 E
2135 128.548
mN
742 778.285 mE
19o 17 48.972
N
o
71 18 38.305 E
2151 628.466
mN
737 278.345 mE
19o 26 47.771
N
o
71 15 37.368 E
3.2.1.5
FIELD MAP
OFFSHORE
DESIGN
VOL-II
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
3.2.1.6
Section - 3
ZB PLATFORM
MAX.OIL/ GAS/
MAX.WATER
CASE
CASE
MAX.
LIQUID
OIL, BOPD
13667
997
1 1734
WATER,
BWPD
3778
16615
7765
LIQUID,
17445
17612
19499
0.746
0.462
0.677
MAX.OIL/
MAX.WATER
BLPD
TOTAL GAS
MMSCMD
RS-1 PLATFORM
CASE
CASE
OIL, BOPD
3791
1202
WATER,
4210
9560
MAX.
LIQ/GAS
4927
6543
REV. 0
Sheet
14 of 14
OFFSHORE
DESIGN
VOL-II
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
Section - 3
BWPD
LIQUID,
8001
10762
11471
0.228
0.305
MAX.OIL/ GAS/
MAX.WATER
BLPD
TOTAL GAS
MMSCMD
0.402
RS-2 PLATFORM
CASE
CASE
MAX.
LIQUID
OIL, BOPD
3019
807
2421
WATER,
12579
14999
13501
LIQUID,
BLPD
15598
15805
15922
TOTAL GAS
MMSCMD
0.320
0.282
0.302
MAX.OIL/ GAS/
MAX.WATER
BWPD
RS-3 PLATFORM
CASE
OIL, BOPD
4032
CASE
2909
MAX.
LIQUID
3185
REV. 0
Sheet
15 of 15
OFFSHORE
DESIGN CRITERIA
DESIGN
MUMBAI
VOL-II
Section - 3
WATER,
BWPD
10944
12082
12125
LIQUID,
BLPD
14976
14991
15310
TOTAL GAS
MMSCMD
0.516
0.476 0.486
RS-4 PLATFORM
MAX.OIL/ GAS/
LIQUID CASE
MAX.WATER
CASE
OIL, BOPD
3951
743
WATER,
6096
7975
10047
8718
0.406
0.30
MAX.OIL/GAS
LIQUID CASE
MAX.WATER
CASE
OIL, BOPD
5865
1641
WATER,
BWPD
6734
9446
BWPD
LIQUID,
BLPD
TOTAL GAS
MMSCMD
RS-5 PLATFORM
.
REV. 0
Sheet
16 of 16
OFFSHORE
DESIGN
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
VOL-II
Section - 3
LIQUID,
BLPD
12599
11088
TOTAL GAS
MMSCMD
0.594
0.508
MAX.OIL/ GAS
MAX.WATER
LIQUID CASE
CASE
OIL, BOPD
2201
780
WATER,
BWPD
702
1030
LIQUID,
BLPD
2904
1810
TOTAL GAS,
MMSCMD
0.383
0.374
MAX.OIL/GAS
MAX.WATER
LIQUID CASE
CASE
OIL, BOPD
2527
478
WATER,
BWPD
6871
7671
LIQUID,
BLPD
9398
8149
TOTAL GAS,
MMSCMD
0.253
0.221
RS-7 PLATFORM
RS-8 PLATFORM
.
REV. 0
Sheet
17 of 17
OFFSHORE
DESIGN
VOL-II
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
Section - 3
REV. 0
Sheet
18 of 18
RS-11 PLATFORM
MAX.OIL
MAX.WATER
MAX. LIQUID/
CASE
CASE
GAS
OIL, BOPD
3908
857
3616
WATER,
BWPD
4928
9152
7684
LIQUID,
BLPD
8836
10009
11300
TOTAL GAS,
MMSCMD
0.427
0.362
0.431
.
CASE
Additionally, surge factor of 25% on max. well fluid flow rates and
swell factor of min. 15% on oil flow rates shall be considered for the
design of topside facilities.
3.2.1.7
WELL DATA
3.2.1.7.1
WELL CONFIGURATION
ZB WELL PLATFORM
No. of Wells to be drilled
12 (twelve) nos.
No. of Producers
11 (eleven) nos.
(single completion)
No .of injector
One no.
(Single completion)
OFFSHORE
DESIGN
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
No.of free slots
VOL-II
Section - 3
Nill
6 (six) nos.
No. of Producers
6 (six) nos.
(5 nos. single completion &
1 nos. duel completion)
Nil
5 (five) nos.
No. of Producers
1 (one ) nos.
6 (six) nos.
No. of Producers
6 (six) nos.
No. of Producers
6 (six) nos.
4 nos. (single completion)
2 nos. (Duel completion)
3 (three ) nos.
REV. 0
Sheet
19 of 19
OFFSHORE
DESIGN CRITERIA
DESIGN
MUMBAI
VOL-II
Section - 3
7 (seven) nos.
No. of Producers
5 (five) nos.
5 nos. (single completion )
2 (two) nos.
2 nos. (single completion)
.
5 (five) nos.
No. of Producers
5 (five) nos.
2 nos. (single completion)
3 nos.(Duel completion)
4 (four) nos.
5 (five) nos.
No. of Producers
5 (five) nos.
4 nos.( single completion)
one(dual ompletion wells)
1 (one)
REV. 0
Sheet
20 of 20
OFFSHORE
DESIGN CRITERIA
DESIGN
MUMBAI
VOL-II
Section - 3
3.2.1.7.2
3.2.1.7.3
4 (four) nos.
No. of Producers
4 (four) nos.
3 nos. single completion
1 no. dual completion
2 (two )
4000
OIL PERCENTAGE
(OF TOTAL LIQUID)
UPTO 100
WATER PERCENTAGE
(OF TOTAL LIQUID)
UPTO 94
GLR (SM/M)
250
4000
OIL PERCENTAGE
(OF TOTAL LIQUID)
UPTO 100
WATER PERCENTAGE
(OF TOTAL LIQUID)
UPTO 75
GLR (SM/M)
1150
REV. 0
Sheet
21 of 21
OFFSHORE
VOL-II
DESIGN CRITERIA
DESIGN
MUMBAI
Section - 3
3.2.1.8
3.2.1.9
: As per ANNEXURE-1
15-21
Temp. degree C
60 - 93
3.2.1.10
3.2.1.10.1
Pipe Separator
Chemical
COREXIT-7730 or equivalent
Dosage rate
REV. 0
Sheet
22 of 22
OFFSHORE
DESIGN CRITERIA
DESIGN
MUMBAI
3.2.1.10.2
VOL-II
Section - 3
Storage capacity
15 days
Dilutant
Nil
Mode of Injection
3.2.1.11
WELL TESTING
Platform shall be provided with adequate facilities for well testing
which shall include the following:
3.2.1.11.1
PRODUCTION MANIFOLD
The wellhead producer well strings (flow arms) shall be connected to
test and production headers.
One
REV. 0
Sheet
23 of 23
OFFSHORE
DESIGN
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
VOL-II
Section - 3
Capacity
Type
Surge factor
Swell factor
15% minimum
Design Basis
15-21
Operating Temperature, C
60-93
47.0
Design Temperature C
104.0
: 3%
H2S
: 230 ppm
REV. 0
Sheet
24 of 24
OFFSHORE
DESIGN CRITERIA
DESIGN
MUMBAI
Water
: Saturated
Mol. Wt.
: 21-24
VOL-II
Section - 3
3.2.1.12.1
PURPOSE
3.2.1.12.2
HOLD-UP
: 2 M (Minimum)
3.2.1.12.3.
LIQUID DISPOSAL
REV. 0
Sheet
25 of 25
OFFSHORE
DESIGN
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
VOL-II
Section - 3
3.2.1.15
3.2.1.16
DIESEL STORAGE
REV. 0
Sheet
26 of 26
OFFSHORE
DESIGN
VOL-II
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
Section - 3
Diesel shall be stored in the deck crane pedestal. The size shall be
sufficient to cater for 48 hrs. continuous operation of the deck crane.
3.2.1.17
LAUNCHERS/ RECEIVERS
PLATFORM
ZB
RS-1
RS-2
RS-3
LAUNCHERS/ RECEIVERS
i)
ii)
iii)
iv)
2 Nos.12 Launcher/Receiver
(Space only)
i)
ii)
iii)
2 Nos.12 Launcher/Receiver
(Space only)
i)
ii)
iii)
2 Nos. 12 Launcher/Receiver
(Space only)
i)
ii)
iii)
REV. 0
Sheet
27 of 27
OFFSHORE
DESIGN
MUMBAI
9 Well Platforms Project
RS-5
RS-4
RS-8
RS-7
Section - 3
i)
ii)
iii)
i)
ii)
iii)
2 Nos.12 Launcher/Receiver
(Space only)
iii)
2 Nos.12 Launcher/Receiver
(Space only)
i)
ii)
RS-11
VOL-II
DESIGN CRITERIA
6 LG Receiver (from
Complex)
SH
iii)
iv)
i)
REV. 0
Sheet
28 of 28
OFFSHORE
VOL-II
DESIGN CRITERIA
DESIGN
MUMBAI
Section - 3
3.2.1.18
3.2.1.18.1
Purpose
The system shall be provided to cater to the requirement of
instrumentation, blowing down crude / condensate to departing well
fluid pipeline and pneumatic supply to OCI transfer pump.
3.2.1.18.2
3.2.1.18.3
- Normal/minimum/Design
8/7.5/10.6
60/40/75
REV. 0
Sheet
29 of 29
OFFSHORE
DESIGN
VOL-II
DESIGN CRITERIA
MUMBAI
REV. 0
Section - 3
Sheet
30 of 30
CAPACITY
Utility Gas
To meet the requirement
Cooler
Cooler/ Air
of inst. & utility gas
Cooled Finned
Pipe Heat Exchanger
NUMBER
One
TYPE
Finned
Pipe
(*)_
(*) Shall be manifolded with multiple smaller bore pipes having extended
surfaces.
ii)
IG/UG Filter
Separator
One
iii)
Hairpin type
double pipe
prod.
heat exchanger
gas
One
3.2.1.18.5
Based on heat
transfer from
header to inst.
OFFSHORE
VOL-II
DESIGN CRITERIA
DESIGN
MUMBAI
Section - 3
REV. 0
Sheet
31 of 31
3.2.1.19
One
Capacity
Pressure, kg/cm(g)
Normal/min./Design
7.5/5.5/10.6
Temperature, deg. C
Normal/Min./Design
55/30/10
IQ well platform
3 nos. (*)
(all single completion)
95.0 kg/cm2g
Pipeline
Departing
Arrival
OFFSHORE
VOL-II
DESIGN CRITERIA
DESIGN
MUMBAI
Section - 3
IQ-ZB
Pres.,kg/cm2g Temp.,deg c
IQ
103.0
28
REV. 0
Sheet
32 of 32
Pres.,kg/cm2g Temp.,deg c
ZB
96.0
28
Sl.No.
Max.
1
3.2.1.20
ZB Platform
- Wellwise
- Total
1600
3000
1000
2400
Min.
500
500
ED well Platform
2 nos. (*)
(all single completion)
95.0 kg/cm2g
Departing and arrival pressure and temperature for ED- RS-7 water
injection pipeline are given below
Sl.No.
Pipeline
ED-RS-7
Departing
Pres.,kg/cm2g Temp.,deg c
ED
Arrival
Pres.,kg/cm2g Temp.,deg c
RS-7
OFFSHORE
VOL-II
DESIGN CRITERIA
DESIGN
MUMBAI
Sheet
Section - 3
REV. 0
27.47
33 of 33
133
36.98
Sl.No.
Max.
1
3.2.1.21
RS-7 Platform
- RS-7 BH
RS-7 CH
Total
1000
400
1400
Min.
750
250
1000
3.2.1.22
350
150
500
OFFSHORE
DESIGN
VOL-II
DESIGN CRITERIA
MUMBAI
Section - 3
REV. 0
Sheet
34 of 34
80.0 kg/cm2g
Departing and arrival pressure and temperature for lift gas pipelines
are given below
Sl.No.
Pipeline
IB-ZB
SC1-RS1
NM-RS2
BHS-RS3
Departing
Pres.,kg/cm2g Temp.,deg c
IB
88.0
27
SC1
86.7
29
NM
85.0
28
SA
87.1
36
Arrival
Pres.,kg/cm2g Temp.,deg c
ZB
83.0
25
RS1
84.8
28
RS2
83.8
26
RS3
85.3
27
Lift gas facilities shall be designed for the following flow rates
Sl.No.
Max.
1
2
3
4
ZB Platform
- Wellwise
- Total
RS1 Platform
- Wellwise
- Total
RS2 Platform
- Wellwise
- Total
RS3 Platform
- Wellwise
- Total
MMSCMD
Nor.
Min.
0.06
0.506
0.03 - 0.045
0.405
0.01
0.02
0.075
0.300
0.03 0.06
0.240
0.01
0.02
0.06
0.338
0.03 0.045
0.270
0.01
0.02
0.1125
0.413
0.045 0.090
0.330
0.01
0.02
OFFSHORE
DESIGN
VOL-II
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
Section - 3
Lift gas pipelines shall be designed for a design pressure and design
temperature of 105.0 kg/cmg and 75 deg. centigrade, respectively.
Lift Gas composition
ANNEXURE-2
As per
Lift gas facilities shall include Lift Gas Manifold, lift gas flow arm
piping, instrumentation, safety system and etc.
3.2.1.23
`
4 nos. (3 nos. single compl. & 1 no. dual compl.) RS-8 platform
80.0 kg/cm2g
REV. 0
Sheet
35 of 35
OFFSHORE
DESIGN
VOL-II
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
Section - 3
REV. 0
Sheet
36 of 36
Departing and arrival pressure and temperature for lift gas pipelines
are given below
Sl.No.
Pipeline
NM RS-5
SHP-RS-7
IC-RS-11
SB-RS-4
5.
ID- RS-8
Departing
Pres.,kg/cm2g Temp.,deg c
NM
SHP
95.0
58
IC
89.0
55
SB
83.0
24
ID
84.4
24
Arrival
Pres.,kg/cm2g Temp.,deg c
RS-5
84.47
30.00
RS-7
94.09
21.32
RS-11
87.10
29.80
RS-43
83.013
22.72
RS-8
81.55
27.30
Lift gas facilities shall be designed for the following flow rates
Sl.No.
Max.
1
2
3
4
5
RS-5 Platform
- Wellwise
- Total
RS-7 Platform
- Wellwise
- Total
RS-11 Platform
- Wellwise
- Total
RS4 Platform
- Wellwise
- Total
RS-8 Platform
- Wellwise
- Total
MMSCMD
Nor.
Min.
0.075
0.60
0.03 - 0.06
0.36
0.01
0.02
0.075
0.325
0.03 0.06
0.225
0.01
0.02
0.06
0.48
0.03 0.045
0.30
0.01
0.02
0.105
0.63
0.045 0.090
0.405
0.01
0.02
0.06
0.30
0.03-0.06
0.225
0.01
0.02
Lift gas pipelines shall be designed for a design pressure and design
temperature of 105.0 kg/cmg and 75 deg. centigrade, respectively.
OFFSHORE
DESIGN
VOL-II
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
Section - 3
REV. 0
Sheet
37 of 37
As per
Lift gas facilities shall include KO Drum, lift gas manifold, lift gas
flow arm piping, instrumentation, safety system and etc.
3.2.1.24
KO Drum
3
KO Drum is proposed to be installed downstream of scrapper tee for
removal of liquid condensed in lift gas pipeline. Contractor shall
size KO Drum considering separation of 15 lb/ MMSCF liquid.
However, size of KO Drum shall be maintained same on all 5 nos.
well platforms. The P&ID and process data sheets are placed
elsewhere in the bid document.
Bidder shall review the P&ID and process data sheets and suggest
necessary changes for automatic drainage (no manual drainage
envisaged) of liquid into well fluid pipeline, within the scope of this
tender.
3.2.1.25
3.2.1.26
Corrosion
Allowance
WELL FLUID
CS-NACE
6 MM
LIFT GAS
CS-NACE
6 MM
INJECTION WATER
CS
3 MM
OFFSHORE
DESIGN
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
3.2.1.27
VOL-II
Section - 3
RTU PARAMETERS
In general, RTU parameters required to be monitored are shown in
P&IDs. However, these are indicative and minimum and Contractor
is required to supplement the same, based on the list placed at
ANNEXURE-4.
.
3.2.1.28
REV. 0
Sheet
38 of 38
OFFSHORE
DESIGN
VOL-II
DESIGN CRITERIA
MUMBAI
Section - 3
ANNEXURE-1
(Sheet 1 of 4)
WELL FLUID COMPOSITION (TYPICAL) MUMBAI
FIELD
COMPONENT
MOL PERCENT
(ON DRY BASIS)*
FOR GOR-703
N2
CO2
H2S
C1
C2
C3
IC4
NC4
IC5
NC5
C6
CUT-1
CUT-2
CUT-3
CUT-4
CUT-5
CUT-6
CUT-7
CUT-8
CUT-9
CUT-10
CUT-11
CUT-12
1.16
3.00
0.023
69.994
5.866
4.409
0.879
1.064
0.197
0.169
0.089
2.093
0.639
1.873
1.086
1.174
0.973
0.657
0.968
0.773
0.633
0.401
1.880
------------100.0000
--------------
HIGH
REV. 0
Sheet
39 of 39
OFFSHORE
VOL-II
DESIGN CRITERIA
DESIGN
MUMBAI
Section - 3
(Sheet 2 of 4)
PSEUDO-CUT DETAILS
CUT
ABP (DEG C)
CUT-1
CUT-2
CUT-3
CUT-4
CUT-5
CUT-6
CUT-7
CUT-8
CUT-9
CUT-10
CUT-11
CUT-12
*
SP GR
40
65
95
125
155
185
215
245
275
305
335
465
0.645
0.702
0.767
0.778
0.796
0.799
0.801
0.840
0.848
0.862
0.863
0.888
38-40
TRACES
27.0
WAX CONTENT, % WT
14-15% w/w
0.7 kg/cmA(Max.)
REV. 0
Sheet
40 of 40
OFFSHORE
VOL-II
DESIGN CRITERIA
DESIGN
MUMBAI
REV. 0
Sheet
Section - 3
41 of 41
(Sheet 3 of 4)
VISCOSITY
2nd Stage
3rd Stage Separator Oil Sample from
Storage Tanker
Separator Sample
Oil Sample
(Temp. 18C)
(Collected at 3.5
(Collected at
kg/cmg & 85C)
Atmospheric
Temp. & Pressure)
Temp
Increasing
Temp.
Decreasing
Temp.
Reheating
Cooling
Increasing
Temp/
Decreasing
Temp.
Increasing
Temp/
Decreasing
Temp.
Increasing
Temp/
Decreasing
Temp.
24C
Ball does
not roll
Ball does
not roll
Ball does
not roll
26C
4.9827
-do-
-do-
Ball does
not roll
18.2242
*
28C
3.9370
-do-
-do-
Ball does
not roll
2.7762
Ball does
not roll
Ball does
not roll
29C
2.8903
-do-
3.5561
30C
3.5936
2.4961
2.4746
3.5136
1.4455
4.5309
Ball does
not roll
5.4875
3.2371
35C
2.8276
2.2177
2.2249
3.0789
1.2244
See Note
4
4.4834
-do-
4.9931
3.0115
40C
2.5279
1.9677
2.0396
2.7728
1.0891
4.2723
2.9075
4.7326
2.8282
50C
2.1858
1.8047
1.7688
2.0455
0.9613
2.6399
2.1525
2.5252
2.1624
80C
1.3316
1.2488
2)
OFFSHORE
VOL-II
DESIGN CRITERIA
DESIGN
MUMBAI
Section - 3
(Sheet 4 of 4)
3)
Viscosity of 3rd Stage Separator Oil and Storage tanker oil sample was
determined at atmospheric pressure.
4)
mg/l
Ca++
290
Mg++
36
9483
Cl-
14200
SO4=
230
CO3=
120
HCO3=
1281
TDS
25640
Salinity AS Nacl
23400
TSS
40
pH
8.3
1.018
REV. 0
Sheet
42 of 42
OFFSHORE
DESIGN
VOL-II
DESIGN CRITERIA
MUMBAI
Section - 3
ANNEXURE-2
LIFT GAS COMPOSITION - MUMBAI HIGH FIELD
COMPONENT
MOL%
N2
1.365
CO2
3.475
C1
81.613
C2
6.505
C3
4.314
IC4
0.706
NC4
0.764
IC5
0.094
NC5
0.068
C6
1.070
H2S
0.026
REV. 0
Sheet
43 of 43
OFFSHORE
DESIGN
VOL-II
DESIGN CRITERIA
MUMBAI
Section - 3
REV. 0
Sheet
44 of 44
APPENDIX- 3.2.1
List of applicable codes for Fire Suppression System and design of other
well platform facilities as applicable-
Recommended Practices
Other relevant Codes and good engineering practices followed in the industry.
OFFSHORE
DESIGN
DESIGN CRITERIA
MUMBAI
9 Well Platforms Project
VOL-II
Section - 3
ANNEXURE-3
LIST OF RTU PARAMETERS
I. WELL PLATFORM
-
REV. 0
Sheet
45 of 45