#9 No proper tendering process even though acquisition and spending went through
PROC manager
#10 No proper tendering process for purchasing of IT assets, leading to budget overrun
#16 No monitoring reports to review as none were properly documented
#18 Hardware and software delivery were still being negotiated with potential vendors
while there are only four months left to complete the project
1.1 Introduction
Project procurement management, defined by PMBOK is the process necessary to purchase or
acquire the products, services or results needed from outside the project team (Carr, 2011).
There are four main process groups in project procurement management, which will be
mentioned below. The processes are:
i.
Plan Procurements (Planning): the first major process, which involves the creation of
the procurement plan for a project. The project manager is pivotal here as to making
decisions, such as which items are to be outsourced and which are to be self-made by
the project team. Procurement documents are preempted in this phase, in which a
selection of vendors are chosen. Documents include risk register, scope baseline and
ii.
project schedules.
Conducting Procurements (Executing): the second process in procurement
management. In this phase, vendors are shortlisted and given a procurement contract.
There are many types of tools and techniques used for conducting procurements, such
as a bidders conference, a make-or-buy-analysis and expert judgement to obtain the
best vendor for the project outsourcing. One vendor will be chosen and a contract will
iii.
be awarded.
Administering Procurement (Monitor and Control): the third process in procurement
management. This is the phase where the project team has to manage relationships
with the chosen vendor, ensure seller performance meets the procurement
requirements, corrective actions and controlling the changes if any exists within the
procurement stage.
iv.
BUY
-Usually costs more, less in rarest of cases
-Depends on skill level of supplier
-Indirect control
-Project management able to spend time on
primary business
-Less time consumed as no extra work for
related departments
because it matches the requirements of the project. Furthermore, an example spreadsheet for
prices can be obtained from China or Thailand, who have their services already up and running.
Thus, an estimation of costs and necessary equipment can be easily obtained. The project
manager and his procurement team will identify all items that are required for the project to
commence. The list of items are then compiled and reviewed by the Project Management Office
(PMO). Below is an example of items that are required for GSCMP.
Number
1
2
3
4
Category
Hardware
7
8
Specifications
(Firewalls)
Telecommunication
5
6
Product
Servers
Backup Servers
Internet Routers
Security Measures
Software
Wires
Supply Chain
System
Database
Helpdesk System
The project management team will have to work cohesively with the procurement management
department in order to obtain said products. The procurement department will then request for a
Request for Proposal (RFP) or a Request for Quote (RFQ). In this situation, a Request for
Quote should be more appropriate, as a spreadsheet of the equipment needed can be obtained
from China or Thailand, complete with pricing for all the items defined by the project team. This
tool can be used to solve problem #9 and #10. A sample RFQ is shown below.
We would like you to quote your price for supplying products as aforementioned together with a
possible discount of said products are bought in larger volumes.
Please also indicate in the quotation:
Yours Truly,
_____________________
Lim Keng Liang
Procurement Manager
016-9286362
In the Request for Quotation shown above, a company name (lets say Company A) is selected
for the procurement process. The quotation is then generated as of the above and sent either via
email or presented formally face-to-face. Depending on the items required from the supplier, all
of items that are required from them are to be stated down in the quotation, including all details
and versions of the items. This is because there might be different variations of a single item,
such as hardware for a computer, which can vary depending on brand, model and performance.
All items quoted should also be cross-checked by the supplier, with the possibility of the supplier
offering a better product or package to the buyer. As pricing is extremely important with a given
budget, the supplier should also note that any other offers that may be recommended by the
supplier should be no higher than said budget, as suggested by the spreadsheets obtained from
China and Thailand. Lastly, the quotation should also include details such as tax-inclusive
products or not, delivery times and duration and the possibility of technical support as an aftersales service.
Criteria
Weightage Vendor A
Vendor B
Vendor C
Satisfying projects
(%)
20%
18
15
20
needs
Price
Ability to meet
20%
10%
17
10
15
8
10
5
levels
Product quality
Delivery services on
20%
10%
19
9
19
8
20
6
time
Abiding to quality
20%
20
18
18
customer service
program guidelines
By calculating the total scores of each vendor from the Supplier Evaluation Matrix, a buyer can
determine which vendor is more suitable and is able to cater to his or her needs for the
procurement process. The total weightages for all vendors are 93(A), 83(B), and 79 (C)
respectively. Based on the weightages stated above, there are a few conclusions that can be
drawn. First, Vendor A and C understands the requirements of the project to a higher extent
compared to Vendor B. Vendor C has the highest understanding, thus the price of Vendor C is
also higher, suggesting that Vendor C might be a company that caters to other high-end
companies. It also reflects on the product quality, which shows that Vendor C has the highest
product quality among the three vendors. Due to Vendor C being a larger company, it may have
other delivery services, thus the lower points in delivery services time. This is an important
factor as time isnt a luxury that the current project procurement team have. Thus, the suggested
vendor that can be chosen is Vendor A, since it has a higher total weightage and most importantly
has better after sales services and delivery time compared to the other two vendors.
One of the inputs of project procurement is a Statement of Work Contract, which highlights
the scope of work for the supplier so that they know what they have to come up with and also the
accompanying details, such as work requirements, location and duration of work and so on.
Below is an example of a Statement of Work Contract.
the bidders conference and only the best supplier will be chosen. Software is also expected to
be delivered by the supplier within the time limit. Suppliers are also expected to provide and
complete training for staff for the new software within the time frame.
Acceptance Criteria:
The project team will monitor performance of hardware and software purchased from the
supplier. If there are any changes or dissatisfactions, buyer can renegotiate terms with the
seller.
Other requirement :
All hardware and software should be acquired legally. A certificate for products purchased
must be present, proving that the product is genuine and warranted by the products
manufacturer
Approval
Approved by
________________________
(Name)
(Position)
(Date)
Company Name
Contract/Service Agreement
Date
Title of Work:
This is an Agreement made as of __________ by _______________________________ (the
Seller), and __________________________________ (the Buyer).
2. Delivery of the Work: The Seller agrees to deliver to the Buyer the Work in form and content
acceptable to the Buyer on or before the dates outlined in Exhibit B of this Agreement, time
being of the essence to the Buyer.
3. Right to Terminate: If the Seller materially departs from the agreed-upon schedule or if the
Work is not satisfactory to the Buyer (based on reviews of drafts, market conditions, and/or other
criteria as determined by the Buyer), the Buyer may at its option:
A. Allow the Seller to finish, correct, or improve the Work by a date specified by the Buyer;
B. Terminate this Agreement by giving written notice to the Seller.
4. Payments: The Buyer will pay the Seller _________________ upon accepted completion of
the Work.
5. Exhibit: The following Exhibit is hereby incorporated by reference into this Agreement:
Buyer
By:
Seller
________________________
____________________________
Date: ________________________
____________________________
Product Quality
Product Delivery
Cost for Products
Setup Time for
System
After Sales Services
Business
Satisfactory
x
Acceptable
Unsatisfactory
x
x
x
x
x
transparency and
efficiency
In the procurement performance review above, it is shown that the supplier has done an overall
satisfactory job with his overall performance in administering the procurement. Good product
quality suggests that all products are of graded quality and presumably has undergone quality
checking after manufacture and delivered to wholesale sellers. The product delivery is also
acceptable, which can be assumed as on time, but not ahead of schedule. This is because of a
limited time frame for the project to be completed, thus anything that can be completed quickly
enough is considered as a boost in morale and efficiency. The cost for products are also
satisfactory, meaning that it can be well under the allocated budget, thus saving resources for the
company and potentially investing the money in somewhere more pivotal and can stem the
growth of the project. The setup time is acceptable, which concurs with the product delivery
time. As time is extremely limited in the project, all procurement steps should be completed as
soon as possible to make way for project cutover and contract completion. This includes the
setup time for the system, which can take a while. After sales services is also acceptable, which
can be caused by less interactions by suppliers staff with the buyers staff. The suppliers staff
should interact more and educate the buyers staff on how to setup and use the current system so
that there will not be any hiccups in using the system in the future. Business transparency and
efficiency is at its highest, so it is safe to presume that both parties have agreed upon the contract
and its clauses; thus are well aware of their roles in the procurement activity.
The last process of project procurement. It involves resolving any open issues or problems
existing in the project. Once the issues are solved, the contract between the supplier and buyer is
said to be completed. The project team should take necessary actions in this phase, such as
determine if all work as promised by the supplier is completed accurately and satisfactorily,
updating records so that it matches all final results of the project and finally to archive all
information for future references. The contract itself that was created and agreed upon by the
supplier and buyer should include all requirements for the formal acceptance and closure
procedure.
1.9 Tools and Techniques (Closing)
Procurement Audit
A procurement audit is a systematic analysis whether an activity and its results correspond with
the demanded requirements and whether the demands are effective and suitable to aid in
achieving the activitys primary objectives. Audits can be done by external professionals so that
it can help decision makers within a project to get a clear idea of the performance status of its
procurement department. Completing a procurement audit will enable an organization to identify
and manage risks related to procurement processes and purchasing to help uncover potential
savings in terms of money spent.