Professional Documents
Culture Documents
Vol:3 2009-04-21
603
a
ICq
b
ICq =
c
ICq
D. Load Model
Load models are represented by the equivalent injected
currents, ILq ,
B. Shunt Capacitors
Shunt capacitors, which act as sources of reactive power,
are often placed at strategic locations throughout distribution
networks. Shunt capacitors are represented by their equivalent
injected currents. Let Q qa 0 , Q qb 0 and Q qc 0 be the rated value
of shunt capacitors at phase a, b and c at bus q. The injected
currents are
( )
( )
( )
( )
( )
( )
a
a
a
a
a
a
Vp I pq Vq Iqp
LPpqa + jLQpq
LSpq
b b
b
b
b
b
b
c c
c
b
b
b
b
LS
LP
jLQ
+
pq pq
pq
Vp I pq Vq Iqp
and
E. Loss Calculation
For distribution line, the power loss in the pq branch of the
actual feeder can be written as:
Where
(2)
ILbq
A. Distribution Line
In general, the voltage at pth bus Vp, and at qth bus, Vq, are
related by
abc abc
(1)
Vqabc = V pabc I pq
Y pq
Y pqabc
(3)
C. Transformers
Copper loss and core loss (which is a function of the
voltage on the secondary side of the transformer), winding
connections, the phase shifting between primary and
secondary windings and the off-nominal tapping are
incorporated into transformer models. Transformer coreloss
functions are represented in per unit on the system. Several
different types of transformer connections should be
considered.
jQqa 0
Va
jQqb 0
Vb
jQqc 0
Vc
(4)
604
Minimize f =
nb
abc
P
pq =1 loss pq
(5)
subject to
Voltage constraint
Voltage magnitude at each node must lie with their
permissible ranges to maintain power quality.
Vqmin Vq Vqmax
International Science Index Vol:3, No:4, 2009 waset.org/Publication/8582
(1V )
(6)
Vindex =
(13)
Current constraint
Current magnitude of each branch (feeder, laterals,
and switches) must lie with their permissible ranges.
max
I pq I pq
B. DG Size
(7)
(9)
lossG
pq
Ploss
(10)
pq
q =1
q =1
q =1
q =1
QGq 0.2QLq
(11)
(12)
A. Location of DG Placement
The location of DG is chosen as the one that gives the best
voltage profile. This could be done by injecting the 20% of
the DG at each node calculating the voltage index by using
eqn. (13). The best location is selected as the node with least
voltage index.
Voltage index ( Vindex ) is defined as
605
TABLE 1
VOLTAGE PROFILE FOR IEEE 25-BUS URDS
Bus
No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Before DG placement
|Va| (p.u) |Vb| (p.u) |Vc| (p.u)
1.0000
1.0000
1.0000
0.9702
0.9711
0.9755
0.9632
0.9644
0.9698
0.9598
0.9613
0.9674
0.9587
0.9603
0.9664
0.9550
0.9559
0.9615
0.9419
0.9428
0.9492
0.9529
0.9538
0.9596
0.9359
0.9367
0.9438
0.9315
0.9319
0.9395
0.9294
0.9296
0.9376
0.9284
0.9284
0.9366
0.9287
0.9287
0.9368
0.9359
0.9370
0.9434
0.9338
0.9349
0.9414
0.9408
0.9418
0.9483
0.9347
0.9360
0.9420
0.9573
0.9586
0.9643
0.9524
0.9544
0.9600
0.9548
0.9563
0.9620
0.9537
0.9549
0.9605
0.9518
0.9525
0.9585
0.9565
0.9584
0.9648
0.9544
0.9565
0.9631
0.9520
0.9547
0.9612
606
After DG placement
|Va| (p.u) |Vb| (p.u) |Vc| (p.u)
1.0000
1.0000
1.0000
0.9758
0.9765
0.9799
0.9689
0.9699
0.9744
0.9654
0.9667
0.9719
0.9644
0.9657
0.9710
0.9660
0.9666
0.9708
0.9584
0.9589
0.9634
0.9639
0.9646
0.9689
0.9576
0.9580
0.9627
0.9585
0.9584
0.9632
0.9595
0.9592
0.9641
0.9504
0.9511
0.9557
0.9627
0.9622
0.9671
0.9525
0.9532
0.9577
0.9504
0.9511
0.9557
0.9573
0.9579
0.9625
0.9513
0.9522
0.9563
0.9630
0.9641
0.9689
0.9581
0.9599
0.9645
0.9605
0.9618
0.9666
0.9594
0.9604
0.9651
0.9575
0.9580
0.9631
0.9622
0.9638
0.9693
0.9601
0.9620
0.9677
0.9577
0.9602
0.9657
TABLE II
SUMMARY OF TEST RESULTS FOR 25 BUS URDS
Description
Distributed generator
placed
13
node and size of DG
Minimum Voltage
Voltage regulation (%)
Improvement of Voltage regulation (%)
Active Power Loss (kW)
Total Active Power Loss reduction (%)
Reactive Power Loss (kVAr)
Total Reactive Power Loss reduction (%)
Total Demand (kW)
Total Released Demand (kW)
Total Reactive Power Demand (kVAr)
Total Released Reactive Power Demand
(kVAr)
Total Feeder Capacity (kVA)
Total Released Feeder Capacity (kVA)
Before DG Placement
Phase a Phase b Phase c
After DG Placement
Phase a
Phase b
Phase c
215 kW
215 kW
215 kW
at 0.85 p.f at 0.85 p.f at 0.85 p.f
0.9504
0.9511
0.9557
4.96
4.89
4.43
0.9284
7.16
0.9284
7.16
0.9366
6.34
30.72
31.70
30.12
52.82
58.32
1126.12
850.32
55.44
53.29
1138.74
854.29
41.86
55.69
1125.16
855.69
32.01
39.39
37.08
36.42
1105.31
20.81
829.08
33.39
39.77
33.66
36.83
1116.69
22.05
834.66
25.04
40.18
35.40
36.43
1108.34
16.82
835.4
21.24
19.63
20.29
1411.09
-
1423.57
-
1413.57
-
1381.69
29.4
1394.14
29.43
1387.91
25.65
607
TABLE III
VOLTAGE PROFILE FOR IEEE 37BUS URDS
Bus
No.
799
701
702
703
730
709
708
733
734
737
738
711
741
713
704
720
706
725
705
742
727
744
729
775
731
732
710
735
740
714
718
707
722
724
728
736
712
Before DG Placement
|Va| (p.u)
|Vb| (p.u)
|Vc| (p.u)
1.0000
1.0000
1.0000
0.9878
0.9894
0.9812
0.9808
0.9825
0.9722
0.9720
0.9779
0.9652
0.9658
0.9736
0.9593
0.9636
0.9720
0.9581
0.9600
0.9705
0.9559
0.9558
0.9715
0.9535
0.9505
0.9727
0.9490
0.9437
0.9746
0.9471
0.9418
0.9754
0.9454
0.9421
0.9758
0.9432
0.9422
0.9760
0.9425
0.9805
0.9797
0.9703
0.9797
0.9752
0.9694
0.9816
0.9685
0.9672
0.9819
0.9674
0.9674
0.9820
0.9667
0.9675
0.9811
0.9807
0.9704
0.9812
0.9791
0.9707
0.9703
0.9777
0.9642
0.9690
0.9776
0.9641
0.9682
0.9777
0.9642
0.9636
0.9720
0.9581
0.9640
0.9699
0.9584
1.0000
1.0000
1.0000
0.9510
0.9717
0.9464
0.9511
0.9719
0.9453
0.9422
0.9760
0.9421
0.9792
0.9752
0.9695
0.9764
0.9756
0.9699
0.9832
0.9580
0.9675
0.9833
0.9569
0.9675
0.9834
0.9559
0.9678
0.9686
0.9772
0.9637
0.9514
0.9683
0.9469
0.9813
0.9809
0.9691
After DG Placement
|Va| (p.u)
|Vb| (p.u)
|Vc| (p.u)
1.0000
1.0000
1.0000
0.9987
0.9967
0.9871
1.0000
0.9957
0.9813
0.9976
0.9954
0.9763
0.9968
0.9948
0.9715
0.9965
0.9945
0.9705
0.9956
0.9949
0.9690
0.9923
0.9962
0.9661
0.9886
0.9980
0.9608
0.9828
1.0000
0.9584
0.9814
1.0009
0.9565
0.9820
1.0015
0.9542
0.9822
1.0017
0.9534
1.0023
0.9949
0.9803
1.0053
0.9935
0.9807
1.0122
0.9910
0.9810
1.0125
0.9901
0.9810
1.0127
0.9894
0.9811
1.0007
0.9941
0.9792
1.0009
0.9925
0.9794
0.9964
0.9954
0.9751
0.9955
0.9954
0.9747
0.9949
0.9956
0.9747
0.9965
0.9945
0.9705
0.9971
0.9926
0.9707
1.0000
1.0000
1.0000
0.9897
0.9973
0.9578
0.9900
0.9974
0.9566
0.9822
1.0017
0.9530
1.0049
0.9935
0.9807
1.0025
0.9940
0.9808
1.0219
0.9881
0.9873
1.0230
0.9880
0.9881
1.0226
0.9863
0.9873
0.9952
0.9951
0.9743
0.9910
0.9943
0.9576
1.0011
0.9943
0.9779
TABLE IV
SUMMARY OF TEST RESULTS FOR 37 BUS IEEE URDS
Description
Distributed generator
722
placed bus and size of DG
Minimum Voltage
Voltage regulation (%)
Improvement of Voltage regulation (%)
Active Power Loss (kW)
Total Active Power Loss reduction (%)
Reactive Power Loss (kVAr)
Total Reactive Power Loss reduction (%)
Total Demand (kW)
Total Released Demand (kW)
Total Reactive Power Demand (kVAr)
Total Released Reactive Power Demand (kVAr)
Total Feeder Capacity (kVA)
Total Released Feeder Capacity (kVA)
Before DG Placement
Phase a Phase b Phase c
-
0.9418
5.03
31.56
24.01
885.56
442.01
989.74
-
0.9559
4.12
23.67
22.32
789.67
397.32
883.99
-
0.9425
5.55
30.44
29.19
1163.4
521.81
1275.1
-
608
Phase a
After DG Placement
Phase b
Phase c
160 kW
At 0.85 p.f
0.9814
1.87
62.82
25.13
20.37
22.76
5.20
879.13
6.43
440.76
1.25
983.43
6 31
160 kW
at 0.85 p.f
0.9863
1.37
66.74
2.91
87.70
2.91
87.52
768.91
20.76
376.91
20.41
856.31
27 68
160 kW
at 0.85 p.f
0.9534
4.70
15.45
23.16
23.91
23.16
20.16
1156.12
7.28
515.78
6.03
1265.95
9 15
APPENDIX
TABLE A1
Load data and line connectivity of 25-bus unbalanced radial distribution system
Branch
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Sending
End
1
2
2
3
3
4
4
6
6
7
7
7
9
10
11
11
14
14
18
18
20
21
23
24
Receiving
End
2
3
6
4
18
5
23
7
8
9
14
16
10
11
12
13
15
17
20
21
19
22
24
25
Type
1
a
b
c
a
b
c
a
b
c
Conductor
type
1
1
2
1
2
2
2
2
2
2
2
2
2
2
3
3
2
3
2
3
3
3
2
3
a
0.3686 + j0.6852
0.0169 + j0.1515
0.0155 + j0.1098
0.9775 + j0.8717
0.0167 + j0.1697
0.0152 + j0.1264
1.9280 + j1.4194
0.0161 + j0.1183
0.0161 + j0.1183
Length,
ft
1000
500
500
500
500
500
400
500
1000
500
500
500
500
300
200
200
300
300
500
400
400
400
400
400
Impedance in ohms/mile
b
c
0.0169 + j0.1515
0.0155 + j0.1098
0.3757 + j0.6715
0.0188 + j0.2072
0.0188 + j0.2072
0.3723 + j0.6782
0.0167 + j0.1697
0.0152 + j0.1264
0.9844 + j0.8654
0.0186 + j0.2275
0.0186 + j0.2275
0.9810 + j0.8648
0.0161 + j0.1183
0.0161 + j0.1183
1.9308 + j1.4215
0.0161 + j0.1183
0.0161 + j0.1183
1.9337 + j1.4236
[8]
REFERENCES
[1]
[2]
[3]
[4]
[5]
[6]
[7]
[9]
[10]
[11]
[12]
[13]
[14]
609
[15]
[16]
[17]
[18]
[19]
web:
http://www.ewh.ieee.org/soc/pes/dsacom/testfeeders.html
JBV Subrahmanyam received the B.Tech degree from JNTU Kakinada, and
M.E degree from Jadavpur University Kolkata and presently pursuing Ph.D
from JNTU-Hyderabad, India. He has very rich experience in application of
latest condition monitoring techniques to reduce industry equipment
breakdowns & application of modern GPS & GIS technologies to power
utilities to reduce power losses & manage the power distribution utility
business effectively. At present he is a professor in the Electrical &
Electronics Engineering Department, TRREC, AP, India. He is actively
involved in the research of planning and optimization of unbalanced power
distribution systems. His research interests are computer applications in power
systems planning, analysis and control.
C. Radhakrishna has more than 35 years of experience in teaching & research
in Electrical engineering and published more than 85 papers in international,
national journals & conferences. He is the recipient of Best Teacher award
from Govt. of Andhra Pradesh, India and Jawaharlal Birth Centenary award
from IE(I), India. He was associated with Jawaharlal Nehru Technological
University (JNTU)-Hyderabad for several years in various positions and was
the founder Director of Academic Staff College-JNTU-Hyderabad, India.
610