3458 Federal Register / Vol. 73, No.

13 / Friday, January 18, 2008 / Notices

j. Deadline for filing comments, only those who file a motion to Energy LLC is jointly owned by TCPL
motions to intervene, and protest: intervene in accordance with the USA LNG, Inc. (a subsidiary of
February 11, 2008. All documents Commission’s Rules may become a TransCanada Corporation) and Shell
(original and eight copies) should be party to the proceeding. Any comments, Broadwater Holdings LLC (a subsidiary
filed with: Secretary, Federal Energy protests, or motions to intervene must of Shell Oil Company). Broadwater
Regulatory Commission, 888 First be received on or before the specified Pipeline LLC is owned by Broadwater
Street, NE., Washington, DC 20426. comment date for the report. Energy LLC.
The Commission’s Rules of Practice o. Any filings must bear in all capital The proposed LNG terminal would be
and Procedure require all intervenors letters the title ‘‘COMMENTS’’, located in New York State waters of
filing documents with the Commission ‘‘PROTEST’’, or ‘‘MOTION TO Long Island Sound, approximately 9
to serve a copy of that document on INTERVENE’’, as applicable, and the miles from the nearest shoreline of Long
each person whose name appears on the Project Number of the particular Island, and about 10 miles from the
official service list for the project. application to which the filing refers. nearest shoreline in Connecticut. The
Further, if an intervenor files comments p. Agency Comments: Federal, state, terminal would be a floating storage and
or documents with the Commission and local agencies are invited to file regasification unit (FSRU) that would be
relating to the merits of an issue that comments on the described report. A attached to a yoke mooring system
may affect the responsibilities of a copy of the report may be obtained by (YMS) that includes a mooring tower
particular resource agency, they must agencies directly from the Applicant. If embedded in the seafloor. The FSRU
also serve a copy of the document on an agency does not file comments would look like a marine vessel and
that resource agency. A copy of any within the time specified for filing would remain moored in place for the
motion to intervene must also be served comments, it will be presumed to have duration of the Project (expected to be
upon each representative of the no comments. One copy of an agency’s 30 years or more). The YMS would
Applicant specified in the particular comments must also be sent to the allow the FSRU to pivot or
application. Applicant’s representatives. ‘‘weathervane’’ around the YMS,
k. Description of the Report: q. Comments, protests and enabling the FSRU to orient in response
Consumers Energy Company filed the interventions may be filed electronically to the prevailing wind, tide, and current
Retirement Study Report, pursuant to via the Internet in lieu of paper. See, 18 conditions.
Articles 204 and 205 of the licenses. CFR 385.2001(a)(1)(iii) and the LNG would be delivered to the FSRU
Consumers prepared the report in instructions on the Commission’s Web by LNG carriers, temporarily stored,
accordance with the Retirement Study site at http://www.ferc.gov under the ‘‘e- vaporized (regasified), and then
Plans, which was approved by the Filing’’ link. transported in a new subsea natural gas
Commission on April 7, 2005 (111 FERC
Kimberly D. Bose, pipeline that would extend from the
¶ 62,029).
l. Locations of the Report: A copy of Secretary. seafloor beneath the FSRU
the report is available for inspection and approximately 21.7 miles to an offshore
[FR Doc. E8–863 Filed 1–17–08; 8:45 am]
reproduction at the Commission’s connection with the existing Iroquois
BILLING CODE 6717–01–P
Public Reference Room, located at 888 Gas Transmission System (IGTS)
First Street, NE., Room 2A, Washington, pipeline in Long Island Sound.
DC 20426, or by calling (202) 502–8371. DEPARTMENT OF ENERGY Natural gas would be routed from the
This filing may also be viewed on the FSRU to the subsea pipeline and into
Commission’s Web site at http:// Federal Energy Regulatory the IGTS pipeline for delivery at an
www.ferc.gov using the ‘‘eLibrary’’ link. Commission average flow rate of about 1.0 billion
Enter the docket number excluding the cubic feet per day. LNG would be
[Docket No. CP06–54–000; CP06–55–000] delivered to the FSRU by 2 to 3 LNG
last three digits in the docket number
field to access the document. You may Broadwater Energy LLC; Broadwater carriers per week to meet the Project’s
also register online at http:// Pipeline LLC; Notice of Availability of planned send-out volumes of natural
www.ferc.gov/docs-filing/ the Final Environmental Impact gas. LNG carriers would transit from the
esubscription.asp to be notified via e- Statement for the Proposed Atlantic Ocean to either the Point Judith
mail of new filings and issuances Broadwater LNG Project Pilot Station (northeast of Block Island)
related to this or other pending projects. or the Montauk Pilot Station (southwest
For assistance, call 1–866–208–3676 or January 11, 2008. of Block Island). From the Point Judith
e-mail FERCOnlineSupport@ferc.gov, The staff of the Federal Energy Pilot Station, carriers would transit
for TTY, call (202) 502–8659. A copy is Regulatory Commission (FERC or Block Island Sound north of Block
also available for inspection and Commission) in cooperation with the Island, head generally west to enter
reproduction at the address in item (h) U.S. Coast Guard (Coast Guard); U.S. Long Island Sound at its eastern end (an
above. Environmental Protection Agency; U.S. area known as the Race), and then
m. Individuals desiring to be included Army Corps of Engineers (COE); proceed to the FSRU. From the Montauk
on the Commission’s mailing list should National Oceanic and Atmospheric Pilot Station, carriers would head
so indicate by writing to the Secretary Administration, National Marine generally northwest to approach the
of the Commission. Fisheries Service; and the New York Race, then proceed to the FSRU.
n. Comments, Protests, or Motions To Department of State has prepared a final The final EIS addresses the potential
Intervene: Anyone may submit Environmental Impact Statement (EIS) environmental effects of the
comments, a protest, or a motion to for a liquefied natural gas (LNG) import construction and operation of the
intervene in accordance with the terminal and natural gas pipeline following LNG and natural gas pipeline
rwilkins on PROD1PC63 with NOTICES

requirements of Rules of Practice and (referred to as the Broadwater LNG facilities:


Procedure, 18 CFR 385.210, .211, .214. Project) proposed by Broadwater Energy • A double-hulled FSRU
In determining the appropriate action to LLC and Broadwater Pipeline LLC approximately 1,215 feet long and 200
take, the Commission will consider all (jointly referred to as Broadwater) in the feet wide, with a closed-loop shell-and-
protests or other comments filed, but above-referenced dockets. Broadwater tube vaporization system and a total

VerDate Aug<31>2005 16:37 Jan 17, 2008 Jkt 214001 PO 00000 Frm 00011 Fmt 4703 Sfmt 4703 E:\FR\FM\18JAN1.SGM 18JAN1
Federal Register / Vol. 73, No. 13 / Friday, January 18, 2008 / Notices 3459

storage capacity of 350,000 cubic meters Coast Guard intends to adopt all or you with notification of these filings,
(approximately 8 billion cubic feet); portions of the EIS being prepared by document summaries and direct links to
• A berthing facility at the FSRU for FERC to serve as the NEPA analysis for the documents. Go to the eSubscription
receiving LNG ships with capacities up the Letter of Recommendation. The link on the FERC Internet Web site.
to 250,000 cubic meters; Letter of Recommendation will not be
• A YMS embedded in the seafloor to Kimberly D. Bose,
issued until after the NEPA process has
moor the FSRU; been completed. Secretary.
• Approximately 2 to 3 LNG carriers The final EIS also evaluates [FR Doc. E8–868 Filed 1–17–08; 8:45 am]
per week that would call at the FSRU; alternatives to the proposal, including BILLING CODE 6717–01–P
• LNG carriers that would transit alternative energy sources, system
through waters subject to federal alternatives, alternative sites for the
jurisdiction as well as waters under the LNG import terminal, alternative DEPARTMENT OF ENERGY
jurisdiction of the state of New York, designs, pipeline alternatives, and
and in some cases, may transit waters alternatives to the Coast Guard Letter of Federal Energy Regulatory
under the jurisdiction of the states of Recommendation action. Based on the Commission
Rhode Island and Connecticut; analysis included in the final EIS, the [Docket No. CP08–33–000]
• Approximately 21.7 miles of 30- FERC staff concludes that approval of
inch-diameter natural gas pipeline, a pig the proposed Project with appropriate Dominion Transmission, Inc.; Notice of
launcher and receiver facility, and a mitigating measures as recommended, Intent To Prepare an Environmental
meter station at the interconnect with would have limited adverse Assessment for the Proposed
the IGTS pipeline; and environmental impacts. Dominion Hub I Project and Request
• Onshore facilities at either The final EIS has been placed in the for Comments on Environmental
Greenport or Port Jefferson, New York, public files of the FERC and is available Issues
including administrative offices, a for distribution and public inspection
warehouse, guardhouse, and an existing at: Federal Energy Regulatory January 11, 2008.
commercial pier. Commission, Public Reference Room, The staff of the Federal Energy
Broadwater proposes to construct the 888 First Street, NE., Room 2A, Regulatory Commission (FERC or
Project in two phases. The first phase Washington, DC 20426, (202) 502–8371. Commission) will prepare an
would include installation of the subsea A limited number of hard copies and environmental assessment (EA) that will
pipeline between October 2009 and CDs are available at the Public discuss the environmental impacts of
April 2010. The second phase would Reference Room identified above. CD the Dominion Hub I Project, involving
include installation of the YMS, hookup copies of the final EIS have been mailed construction and operation of natural
of the FSRU, and connection of the to federal, state, and local agencies; gas facilities by Dominion
project components between September public interest groups; and individuals Transmission, Inc. (Dominion) in
and December 2010. Broadwater who requested a copy of the final EIS or Westmoreland County, Pennsylvania.
anticipates that the Project would be in provided comments during scoping; The EA will be used by the Commission
service by the end of December 2010. libraries and newspapers in the Project in its decision-making process to
As part of this evaluation, FERC staff area; and parties to this proceeding. determine whether the project is in the
has prepared a final EIS to assess the Hard copy versions of the final EIS were public convenience and necessity.
environmental impacts of the Project. mailed to those specifically requesting This notice announces the opening of
The final EIS was prepared to satisfy the them. the scoping period that will be used to
requirements of the National Additional information about the gather environmental input from the
Environmental Policy Act (NEPA). Project is available from the public and interested agencies on the
The Coast Guard has assessed Commission’s Office of External Affairs, project. Your input will help the
potential risks to navigation safety and at 1–866–208–FERC or on the FERC Commission staff determine which
port security associated with the Internet Web site (http://www.ferc.gov) issues need to be evaluated in the EA.
proposed Project. The Coast Guard’s using the eLibrary link. Click on the Please note that the scoping period will
safety and security assessment is eLibrary link, click on ‘‘General Search’’ close on February 11, 2008. Details on
documented in the Captain of the Port and enter the docket number excluding how to submit comments are provided
Long Island Sound’s Waterways the last three digits in the Docket in the Public Participation section of
Suitability Report (WSR). The final EIS Number field. Be sure you have selected this notice.
includes an analysis of the an appropriate date range. For If you are a landowner receiving this
environmental impacts related to the assistance, please contact FERC Online notice, you may be contacted by a
Coast Guard’s Letter of Support at Dominion representative about the
Recommendation regarding the FERCOnlineSupport@ferc.gov or toll acquisition of an easement to construct,
suitability of the involved waterways for free at 1–866–208–3676, or for TTY, operate, and maintain the proposed
LNG carrier operations. contact (202) 502–8659. The eLibrary project facilities. The pipeline company
The Coast Guard Captain of the Port link on the FERC Internet website also would seek to negotiate a mutually
Long Island Sound will issue a Letter of provides access to the texts of formal acceptable agreement. However, if the
Recommendation to Broadwater Energy documents issued by the Commission, project is approved by the Commission,
and the appropriate federal, state and such as orders, notices, and that approval conveys with it the right
local agencies, in accordance with 33 rulemakings. of eminent domain. Therefore, if
CFR 127.009. The Letter of In addition, the Commission now easement negotiations fail to produce an
Recommendation, which will be based offers a free service called eSubscription agreement, Dominion could initiate
rwilkins on PROD1PC63 with NOTICES

on the Coast Guard’s WSR, is an official which allows you to keep track of all condemnation proceedings in
determination regarding the suitability formal issuances and submittals in accordance with Pennsylvania state law.
or unsuitability of Long Island Sound to specific dockets. This can reduce the A fact sheet prepared by the FERC
support the proposed FSRU and amount of time you spend researching entitled ‘‘An Interstate Natural Gas
associated LNG marine traffic. The proceedings by automatically providing Facility on My Land? What Do I Need