METHOD STATEMENT

Description of
Task / Activity:

METHOD STATEMENT FOR PAINTING WORKS

Project Name:

Company:

Document Reference:

Associated JSA

Reference
Number

Attached
Yes

No

Prepared By:
Mechanical Engineer

Date:

05th July,2015

Mechanical Engineer

Date:

05th July, 2015

Position:

MEP Manager

Date:

05th July, 2015

DL Discipline
Engineer/Manager Review:

Bassam Alameer

Position:

MEP Manager

Date:

05th July, 2015

Position:
Discipline Engineer:
Position:
Contractor Project
Manager Review:

DL HSE Manager Review:


Position:

Date:

WPF Review:
Position:

DL/HSE/MS/0001

Date:

Rev. 01

METHOD STATEMENT
Key Plant and Tools
Required:

Paint brush, roller, Scaffolding and Ladder

Key Materials
Required:

Paint
(ie: access platforms/winches/ladders etc)

Other Essential
Equipment:
Specific Identified
Residual Hazards:
(or refer to the task
specific risk
assessment(s))

Specific Staff Training


Requirements:

Temporary Supports
and Props needed to
facilitate the works:

Method of Access and


Egress to the work
area:
Fall Protection
Measures:

WORKING AT HEIGHT

NONE

LADDERS
SCAFFOLDS

SAFETY HARNESS

(Where work at height cannot


be eliminated - consider both
Personnel & Materials)

Hazardous
Substances:
(Attach COSHH Assessments
and MSDS)

Applicable:

Very Toxic

Harmful/
Irritant

Corrosive

Dangerous
for the
environment

Oxidising

Highly
flammable

Explosive

No

Yes

No

Yes

Yes

Yes

No

(Detail any limits on the loadings applicable to temporary plant/equipment or fixed elements of the structure
where the work is taking place.)

SWL's:

DL/HSE/MS/0001

Rev. 01

METHOD STATEMENT
OTHER:
1: Coveralls
2: Gas Detector
3: Gas Mask/Hood

Required Personnel
Protective Equip.:

Safety
Boots

Hard Hats

High
Visibility

Welder
Shield

Safety
Gloves

Hearing
Protection

Respiratory
Protection

Eye
Protection

Face Shield

Fall Arrest

Disposable
Mask

Goggles

Emergency
Procedures:

Name of On-Site First Aider:

ABBAS

First Aid Box Location:

First Aid Facilities:

Location of Nearest Hospital:

Other Information &


Comments:

1) All work will be undertaken by qualified competent persons with experience of the
type of work described above, and in all cases in full accordance with safety
procedures specified.
RESPONSIBILITIES

2) It is the responsibility of the supervisor to ensure prior to giving any personnel the
job of Painting that they are fully aware of the hazards involved and are
competent to carry out the work safely.
3) The supervisor must ensure that this procedure is fully complied with.

DL/HSE/MS/0001

Rev. 01

METHOD STATEMENT
1) Ensure the surface is free from any grease and dust prior to application of
painting.
2) Paint/ Primer to properly mixed in a steel pail separately.
3) Apply the primer by means of paint roller/ brush to as many as coat to
achieve the thickness.
4) Allow the painted surface to fully cue as per the painting procedure and
project specification.
5) Carry out the second coat and final coat painting as per approved project
specification.
6) After the completion of Final Inspection remove ladders and scaffolds for the
work area.
7) Remove all the debris and garnet spillage from the work spot
8) All the tools from the work area to be removed and area to be thoroughly
Sequence of
Operations:

clean the area.


9) For Mixing ratio and dry time refer Data Sheet.

(Specifying methods of
working, tools, materials and
equipment utilised)

DL/HSE/MS/0001

Rev. 01

METHOD STATEMENT
METHOD STATEMENT ACCEPTANCE FORM
TITLE

PAINTING WORKS ON PIPES IN POWER GENERATION BUILDING

I HAVE READ AND UNDERSTOOD THE METHOD STATEMENT


FOR THE WORK ACTIVITIES ABOVE

DATE

TRADE

NAME
PRINT

SIGNATURE

RESPONSIBLE ENGINEER / SUPERVISOR

DL/HSE/MS/0001