Professional Documents
Culture Documents
RESMAC
(Remote Substation Monitoring & Control)
VIII-1
8.1.03
(i)
(ii)
(iii)
(iv)
The ability to carry out planned load shedding when supply is restricted
due to either lack of generation and/or failure of major circuits.
(v)
(vi)
By having the ability to accurately monitor the network and transfer loads
at times of peak and/or under fault conditions, major capital savings can
be made by deferring reinforcement works.
(vii)
Benefits of Telecontrol
(i)
(ii)
(iii)
(iv)
To carry out mathematic studies of the system o calculate load laws and
fault level of various running conditions to ensure that plant is not overstressed.
(v)
VIII-1
8.1.04 Substation Monitoring Equipment forms the fundamental and essential building block in
any Distribution Automation System, as it is required to furnish continuously information
pertaining to the electrical parameters like active and reactive powers, bus voltage, etc.
8.1.05 With increasing trend towards Distribution Automation there is a growing need to
modernize the Sub-station Monitoring equipment. At present the existing sub-stations have local
data monitoring facility in the form of conventional electromechanical devices for monitoring the
electrical parameters and the parameters are recorded manually. With the advent of
microprocessor based systems dedicated data loggers connected with conventional
measurements transducers have gained popularity. As Distribution Automation demands the data
availability at a centralized location for effective network Co-ordination, the Sub-station Monitoring
Equipment should be capable of transferring the error-free data with high efficiency at regular
intervals, in addition to the existing local monitoring.
8.1.06 The data loggers alone are not adequate to meet these requirements and it is necessary
to use a Remote Terminal Unit (RTU) along with this equipment to carry out the desired functions.
As the configuration of a separate data logger and a separate RTU poses problems of
compatibility besides the high costs, it will be useful to orient a system design which will integrate
these functions into a single unit.
8.2.00 A PROJECT
8.2.101 Example
In the month of February, 1990; a joint project BHEL (R&D) and APSEB was
first thought of for development of such a system for Indira Park Sub-Station in the City and a
team of four Engineers from A.P.S.E.B. and three from B.H.E.L. (R&D) worked hand in hand and
finally brought out a prototype by October, 1990. Brief description of the main design
consideration of the system is given below.
8.2.2
The following are the consideration which go into the design of the system:
(i)
the system should be cost effective so as to be within reasonable cost limits for
use even in small sub-stations.
(ii)
(iii)
The system should be easily upgradeable from a local data acquisition system to
an RTU for telecontrol applications.
(iv)
The system should have automatic data and event logging so that critical data is
not lost due to operator shortcomings.
(v)
VIII-2
RMS voltage
(ii)
RMS current
(iii)
Active Power
(iv)
Reactive Power
(v)
Power Factor
8.3.04 As the method employs computation of parameters after multiplexing, the addition of
extra channels will have ka minimum increase in cost per channel measurement, as the cost of
auxiliary transformers is significantly less. In contrast with the existing measurement devices, the
increase in number of channels does not result in proportional increase in system cost, due to the
increased number of transducers. However, the impediment is on the update rate which is
normally within acceptable limits for moderate burden.
8.4.00 SYSTEM EXPANSION
8.4.01 The system design is modular in nature to accommodate any expansion in the sub
station. As the various functions outlined above are not achievable by the single microprocessor,
the design is based on multiple processor architecture, where each processor works in an
isolated manner in achieving the functions assigned to it and at the same co-ordinates with other
processors for showing the results. This concept renders modularity both in software and
hardware.
VIII-3
VIII-4
Typical procedures are those relating to switching schedules, logging, issue of safety
documentation operation of switchgear, isolation of particular pieces of plant, etc., A Control and
Operation manual setting out these procedure is recommended
The term Safety Document refers to one of the following:
(i)
Permit-to-work
A safety Document specifying the High Voltage apparatus which has been made safe to
work and work which is to be carried out.
A permit-to-work can only be issued with the authority of the Control Engineer by a Senior
Authorized Person to a competent Person. It shall be issued before any work is carried out on
any apparatus or conductor and the recipient shall confirm that he understands it and is
conversant with the nature and extent of work to be carried out.
(ii)
Sanction-for-test
A sanction-for-rest can only be issued with the authority of the Control Engineer by a
Senior authorized person to an Authorized person. It shall be issued before any testing is carried
out and the Authorized Person shall confirm that he understands and is conversant with the
nature and extent of the testing to be done.
(iii)
Limitations-of-Access
A Safety Document defining the limits and nature of work which may be carried out when
verbal instructions are not considered sufficient for the purpose and where a permit-for-work or
Sanction for Test is not applicable.
A limitation-of-Access can be issued by Senior Authorized Person or an Authorized
Person when it is considered necessary to have written instructions to avoid danger. Typical
situations are work in proximity to high voltage conductors, work in underground chambers, plant
operated by compressed air, etc.
8.10.00 SYSTEM CONFIGURATION
The SCADA network will contain the following 3 systems:
Instrumentation Sub-system
Telementary/Computer Sub-system
Communication Sub-system
VIII-5
Bus voltage and currents from all feeders input is taken from standard
potential and current transformers.
Power factor from group circuit breaker.
For all the analogue measurements, industry standard transducers giving an output of 420mA/1-5VDC will have to be fitted.
Status Inputs: Parameters to be monitored are
(i)
(ii)
(iii)
(ii)
VIII-6
The main monitoring is carried out in the control center through the data acquisition
equipment which does the function of periodically selecting each Sub-station through the radiopolling circuit. When the selected station sends the data burst, it will be received and passed on
to the host computer, which has in its memory the schematic of each sub-station. On getting the
data it will display on the monitor the schematic along with current or power data with each
feeder. These data with respect to time, can also be stored in a floppy for off line analysis.
Printers can be attached for taking a print out.
For supervisory control, the control center can initiate action on the return link with the
sub-station to close or trip any circuit breaker. At the sub-station end, the interface is provided
before the circuit breaker. The interface identifies the nature of the command and sends either
power data or circuit breaker data or operates a circuit breaker depending upon the nature of the
command. In case of any emergency condition, that is by way of tripping of a circuit breaker, or a
local operator trying to change the status of the circuit breaker, the equipment takes the initiative
and sends emergency signals alerting the control center, which interrupts its scanning, takes
necessary corrective action pertaining to the sub-station and then resumes scanning.
8.12.02 Scan Rate
The Sub-station parameters to be monitored by the control center contains a mixture of
analogue, non-fleeting status inputs, high priority and fleeting events. The scanning rate will
depend on two factors:
Nature of the Sub-station parameters.
Type of Sub-station, i.e., 220KV or 132KV or 33KV or 11KV
While non-fleeting status inputs and analogues would require a scanning rate 2 to 3
minutes, high priority and fleeting events like circuit breaker operation, alarms etc. would require
a scanning rate of the order event information is more important in 220KV and 132KV Sub-station
compared to 33KV and 11KV sub-stations. The scanning rate will therefore be decide by the substation parameter which require the fastest scanning. As the communication link between the
control center and the sub-stations is a high speed TDMA link, the cost factor involved in the
choice of the scan rate would depend on the speed of the modems at the control center and the
sub-stations, and this cost is insignificant. Based on the above considerations it is suggested that
the control center scan rate of the sub-stations should be 5 10 secs.
12.03
The hose computer at the control center will have a number of lines buffers
(communication ports), and each line buffer will transfer data at selectable rates of 600, 1200,
2400, 4800,9600 bits per second to a number of RTUs located at the sub-station through a
modern and the associated communication channel. Data transfer from RTU to control center
takes place in the return communication channel through the same line buffers and modern. The
total time including call set up time and transmission time for data transfer from one sub-station to
control center will be of the order of 0.5 to 1 second depending upon the total number of analogue
and status Inputs to be transmitted to the control center. Now the control center scans the substations through the TDMA polling circuit every 5 to 10 seconds. Therefore 100 sub-stations can
share one TDMA channel. As the total number of sub-station location is 95 by the year 2004-05,
the number of TDMA channels required is 10.
VIII-7
The hose computer world require on line buffer capable of driving 10 RTUs for one
communication channel. Based on the above considerations the host computer should have a
minimum of 10 communication pots and 10 modems.
8.12.04 Man-Machine Interface at Control Centre
To control the Power system successfully the Operator needs to have an overall picture
of the system. He has to be able to determine the state of the system exactly and be able to
pinpoint the trouble area and act in response to any disturbances in time etc. The interface
between the human operator and the computer called MMI is vital for the above operations. The
MMI consist of following hardware and software:
- Console
Two consoles will be provided in the control center for switching and supervisory control.
The consoles will have all functional capabilities including data retrieval, display and control.
Typically one console will be provided for data base editing and updating. It will not have the
control capability.
-
Loggers
Printers
Plotters
Mimic sub-system
Software package
The host software program drives the data acquisition display and remote control
equipment in real time collects the system data from all the sub-stations and displays the data on
colour monitor and printer. The data is displaced in table format, trend format, alarm format and in
alarm reports. Typically the system will be menu driven with extensive use made of function keys
to reduce operator input. Other typical features of the host software will be:
-
VIII-8
Data Base Generation Function describes the Characteristics of the real-time data base
and the software modules which generate, initialize, and maintain that data base. The data base
generation function operates to generate and initialize a complete, consistent, and secure data
base for all application programming.
The primary function of the data base is to provide a structured organization to
information so that system and application program needing the information have direct and
efficient access to it. Within a given CPU, less frequently referenced data resides on disk storage
to conserve memory space while high usage data is kept memory resident for efficient access.
(ii)
The real time data base is referenced by many functions including data acquisition, manmachine display generation, and automatic generation control, to name of a few. Therefore, data
base access routines are available to applications programs to facilitate data retrieval.
(iii)
Data Base Editing Functions allows the user to display and alter the real-time data base
without the necessity for a complete data base generation and reinitialization. Editing is
performed on-line using C.T. displays and keyboards entries. Three on-line facilities are provided
to meet the editing requirements of the user.
VIII-9
Acquisition data base edition for display and editing of the data
acquisition data base.
Data base utilities support the data maintenance function in moving data from one CPU
or device to another utilities are provided for the following functions:
-
Network parameters
Network Topology
Network State
(i)
VIII-10
(ii)
Obtain data from RTUs and store it in a buffer in the memory of the
on-line computer system.
The DAS will check every analogue value against high and low limits
set by the operation and will draw the attention o the operator
whenever the limits are violated. This will also be recorded in the
event logger.
Status checking routine will detect any invalid breaker or status data
viz neither open nor closed and shall inform the dispatcher via alarm.
Control Commands
The control center shall be provided with the supervisory control software
to perform the following functions:
Switch off of switch on circuit breaker provide at the Sub-station o ran a
line.
The sequence of operation for execution of supervisory control
commands are indicated below:
Step-1- The DAS software sends the command code and the selected
point address
Step-2- The RTU checks the messages and responds with an
acknowledgment or an error return. If the message is correct, the RTU
will execute the control command immediately, if the RTU responds with
an error return or no reply received from the RTUn, the DAS will repeat
Step-1. If an error is received after the second trial, the DAS software will
link back to the control feed back function in the Man Machine interface
software.
The DAS software will provide for error checking and error alarming statistics.
8.12.07 Application Software
(i)
Load Management
This software application function shall be capable of analyzing, the data acquired from
the net work in order to fulfill the objective of meeting the demand in the most optimal manner. It
shall also be capable of providing the best strategy for meeting the varying demand conditions.
The management of the load shall be done by exercising control over the distribution feeders
which are under the purview of the SCADA system. Flexibility should be inbuilt into this
application software to accommodate time to use metering of customer loads, varying maximum
demand intervals, sub-station load transfer and control, and load surveys.
VIII-11
(ii)
The objective of this applications is to minimize the losses on the distribution network.
The control element used by the software to achieve the objective are : scheduling of capacitor
on the network; recommendations for transformer tap settings and optimal configuration of the
network. In an office mode, the function shall be capable of recommending the optimal conductor
size, optimal capacitor size and optimal capacitor location to achieve minimum losses. The
essential factor which drives this software function is that the reactive power profile should be
optimally managed to achieve minimum losses.
8.12.8
Host Computer
Dual Processor configuration with automatic switchover to the host
standby in case of failure of working processor.
CPU 32 Bit.
Main memory 2 Mega Bytes
Access Time 300 nanoseconds or less
Auxiliary memory 240 Mega Bytes Hard Disk Drive & 100 Mega Bytes
Magnetic Tape Drive.
Communication Ports (Line Buffers) 12
Each line buffer should be capable of connecting upto 10 RTUs. The
data transfer rate of the line buffers should be adjustable by strapping
among 600, 1200m 2400, 4800, 9600 bits per second.
CCITT/X.25 HDLC. This port is for connection to the computer system at
the Main Load Dispatch Centre.
Modems 600/1200/2400/4800/9600 bits per second star selectable
confirming to CCIT/V.23,V.26, V.27, V.29 standards.
Interfacing Host computer to modems
EIARS 232C/CCITT V.24
(i)
Console
Two colour VDU monitors. Each VDU monitor should display 48 lines
with 80 characters per line. The VDU should also display standard
alphanumeric characters and 60 more of power system symbols for
construction of single line diagram. The minimum screen size of VDU
should be 50 cms with aspect ration of 2:4.
VIII-12
Logger
Two numbers shall be provided with the following minimum characteristic:
Speed of 250 characteristics per second
Line length of at least 132 characters per line.
Bi-directional printing capability of near letter quality.
(c)
Printer
1 No. of the following minimum characteristics.
Speed of 600 lines per minute.
Line length of at least 132 characters per line.
Capability to print 96 standard ASCII character set.
(d)
Plotter
1No. of the following minimum characteristics.
Accepting plain paper of a minimum A3 size.
Having 8 pen holdings.
Plotting speed of at least 20 cm/sec
VIII-13
(e)
Mimic
1No. mimic board having a flat sub-system surface with dimensions of
approximately 10 meters in length and 3 metres in height. There will be
15 sub-stations to be displayed on the mimic board with a maximum of
30 sub-stations.
Operating System
The main scan tasks which surveys all field inputs and updates the
data structure according to the set up parameters associated with
each channel, it also changes the output based on information in the
data structure. The main scan task launches the users program.
Auxiliary scan task which surveys auxiliary input also carries periodic
diagnostic functions.
VIII-14
(ii)
Command Language
Typically this will be structural command language which is used to communicate with the
RTU. It defines the syntax used to read input channels, change outputs, tailor data processing
and change system parameters. The command language .usually consists of commands and
responses. While a command is a message sent into the RTU, a response is a message elicited
from the RTU. The response will be of two kinds; a reply response resulting from successful
command execution and an error response resulting from unsuccessful command execution.
(iii)
Programming Language
VIII-15
LPAT LED: This will be illuminated if the input voltage is too low.
Status LED: This gives a binary coded output if the system fails a
software confidence test.
8088 or similar
ROM
128K bytes
RAM
64K bytes
NON VOLATILE
COMMUNICATION PORT
BAUD RATES
VIII-16
Figure 3
Sub-station-Scada
VIII-17
APSEB has taken a rather bold decision to automate Hyderabad system and to cover all
Sub Stations in and around the twin cities of Hyderabad and Secunderabad by a SCADA
connected to a Master Station. Also DAS (Distribution Automation System) is provided in the
scheme which is under execution.
Certain extracts from the draft specifications drawn up for the purpose are reproduced
below.
8.13. FUNCTIONAL REQUIREMENTS
This chapter specifies capabilities that are required of the DAS for APSEBs distribution
operations:
Supervisory Control and Data Acquisition (SCADA)
Historical Accounting and Reporting.
Load Control of HT Consumers.
Automatic Meter Reading
Feeder SCADA including fault localization, restoration of supply and load balancing.
Integrated VolWAR control
Automatic Mapping and Facilities Management.
Trouble Call Management System.
8.13.1 DATA BASE
8.13.1.1 General Requirements
All data acquired from the electrical power system, all calculated data and historical data,
and all control commands or parameters to be output to the power system shall be stored in one
database. The database shall be the central interface among all elements of the DAS including
the SCADA functions, load control functions, automatic meter reading function, feeder SCADA
functions, Integrated VolWAR control functions, HAR accounts and operator interfaces.
As the common interface, the system database shall include all information necessary for
the proper operation of all application programs, including telemetered data, data which is
program calculated or operator entered, as well as all program constants, historical accounts and
reporting (HAR) data, and DAS communication statistics. The database shall comprise a realtime portion optimized for fast access, and a historical portion which meets the requirements of
Section 13.12.1, HAR Database. The system database shall have a logical structure and shall
be initially sized, upon delivery, to accommodate the Ultimate sizing requirements specified in
Exhibit 2.3-1, i.e., no programming or system regeneration shall be required in order to add
substations, data points, DAS devices, load control groups and capacitor switches, automatically
read meters, etc., up to the Ultimate limits. The database may be distributed between various
processors and storage devices, but it shall be of a consistent design, and data residency shall
be transparent to the accessing function. Each database item shall be defined In the OAS only
once; duplicate definition of the same data in various database structures is not acceptable.
VIII-18
VIII-19
Distribution
Automatic Meter Reading
System (DAS and Radio Communications System)
Training.
8.13.1.4 Connectivity Analysis
A connectivity analysis function shall be provided to maintain up to date the following
information:
a.
Lists of all power system elements that belong to each distribution circuit. A List
devices connected to a feeder shall be accessible by pointing to the circuit
breaker that energizes the feeder.
b.
The circuit breaker which currently connects each circuit element to a substation
bus.
c.
All circuit segments that belong to each substation, i.e., the circuit segments that
are energized from the substation breaker or breakers.
VIII-20
In order to facilitate the procurement of pole-top RTUs and additional RTUs from other
suppliers, a widely accepted protocol is required. Protocols which comply with IEC- TC57
recommendations are preferred. If the suppliers offered protocol is a proprietary protocol, the
supplier will additionally undertake to provide APSEB with the following information:
a.
b.
Outline protocol details, sufficient for other manufacturers to tender for additional
RTUs under any future contract.
c.
If, under any future contract, APSEB wish to procure RTUs from a different
manufacturer, the supplier under this contract, shall agree to provide (at no
additional cost) full and complete current protocol details to the new
manufacturer, via APSEB, under a suitable project specific non-disclosure
agreement.
Substation RTUs
Status
4 seconds
Analog
30 seconds
Reporting by exception may also be used. In this case, a forced or integrity scan shall
be performed every 15 mi.1utes. This shall be a complete scan in which every RTU point reports
its status or value. Forced scanning is also required in the following situations:
Upto a warm on cold system startup
When any RTU is put back into service after being off-line for any reason
On manual request by operators. Such requests shall be processed at higher priority than
periodic scans.
b.
Pole-Top RTUs
It shall be possible to scan all points at least once every 30 minutes. This scan interval
shall be programmer adjustable, to once per day. Sanning of pole-top RTUs shall be distributed
over time in order to minimize the impact on the faster substation scan. To obtain information from
pole-top RTUs when needed, such as after control commands are sent, operators shall be able to
manually request the polling of any specific pole-top RTU. It shall be possible to issue such
polling ! requests for an RTU by selecting a cursor target from any display, tabular schematic, on
VIII-21
which data from that RTU is displayed. Manual polling requests shall be processed at a higher
priority than any periodic scan activities.
8.13.2.3 Error Detection and Recovery
Each scan reply shall be immediately checked for certain basic error conditions including
incorrect response. RTU data buffer overflow and invalid message security codes. Such checking
is required for periodic scans as well as forced scans. All detected errors shall be recorded for
maintenance purposes. Attempts shall be made to recover from the error conditions by repeating
the particular data scan for a selected number of times, as defined in the database. If no more
errors are detected in at least one of the retries, then the earlier error shall be considered as a
recoverable error. Otherwise, it shall be considered as a non-recoverable. error. Statistics shall be
kept on communication activities and detected errors, and a Communication Report containing a
summary of the communications statistics for each channel, shall be displayable and printed daily
providing details on the total number of transmissions and the errors, by category for each hour of
the day.
The detection of a non-recoverable error or the occurrence of a high number of
recoverable errors (e.g., 30% programmable parameter) shall be considered as channel-failure
and shall result in the suspension of scanning for the particular RTU and the creation of an alarm.
The channel shall then be periodically tested to see if communications can be restored, and the
RTU returned to scanning after a programmable number of consecutive good scans; appropriate
alarm messages shall be generated. Operators shall also be able to manually suspend and
resume scanning of an RTU. When scanning of an RTU is suspended, whether automatically or
manually, all its points shall be marked as Failed (F). Manual suspension and resumption RTU
scanning shall be treated as events.
The hardware and software must be designed so that data reported by RTUs will not be
lost because of insufficient buffer size or insufficient time to service the reply data. If processing
has not been completed for a certain data point or data group before the new data value for the
same point or group are received in the next scan, an alarm shall be generated.
8.13.3 PROCESSING OF RTU DATA
The following types of data processing are required:
VIII-22
Data conversion to engineering units and storage in the database, in floating point format
Rate-of-change checking
VIII-23
Low limits
High limits
Emergency limits.
Crossing of an analog limit in either direction shall result in appropriate alarm reporting.
Each of the above six (three sets of high and low) alarm limits shall be treated separately, i.e., a
unique alarm is required when each limit is crossed. A dead band shall be applied to each of the
limits to derive the return-to-normal level, so that repeated alarming does not occur for point
hovering around the limit. The dead band shall be specified in the data base for each individual
point.
All analog points whose values are outside the low limits shall be included in Abnormal
Summaries.
The set of alarm limit shall be shown for each point in tabular substation displays. The
operators shall be able to change the limits for the substation displays; this capability shall be
limited to points in AORs that are assigned to the operator.
8.13.3.1.5 Max/Min and Average Values
In order to prepare data for the historical database, the following calculation shall be
performed for every telemetered analog point during the processing of data acquired from the
RTUs.
a.
Average Values - The average value shall be calculated for every 15 minute
period, synchronized with the hour.
b.
Maximum Minimum Values -The daily instantaneous maximum and minimum
values shall be saved and the time of their occurrence shall be recorded.
Data quality codes shall be assigned to calculated values according to the rules specified
for calculated points in Section 13.1.2.
8.13.3.1.6 Energy Calculations
Hourly MWh and Mvarh values shall be calculated through integration of telemetered MW
and Mvar values. Integration shall be performed at the analog scan rate. Data quality codes shall
be assigned to the calculated energy values according to the rules specified for calculated points
in Section 13.1.2.
Energy values shall be transferred into HAR accounts at the end of each hour.
8.13.3.1.7 AID Accuracy Monitoring
Analog reference points will be included for each Analog to Digital converter (AID) in the
RTUs. These precision reference points shall be scanned and used to determine the extent of
inaccuracy (drift) of the AID converters. The percent inaccuracy of the AIDs in all the RTUs shall
be shown in an ATU Communications Maintenance Display. If any inaccuracy is larger than a preset tolerance, an alarm indicating the problem and the magnitude of the inaccuracy shall be
VIII-24
output. Deadbands for return-to-normal alarming shall be provided. Tolerance levels and dead
band values r shall be assignable from the operator terminals while in Programmer mode.
As part of the analog data processing, system shall adjust each analog value so as to
compensate for the drift in the AID converter to which the analog point belongs.
8.13.3.2 Status Data Processing
Newly acquired status data shall be compared against the current status data in the
database to determine if changes have taken place. Uncommented changes of state shall be
processed as alarms and commanded changes of state as events, Points for which a normal
state is defined in the database shall be included in Abnormal Summaries while they are not in
their normal state. All status changes shall result in an immediate update of all displays on which
the points are currently shown. The scan processing shall be designed to ensure that no change
of status IS lost.
For each status point, it shall be possible to define the relationship between the position
of the contact Input to the ATU and the state of the device. So, for Instance, an open contact may
represent Closed or Open.
8.13.3.2.1 Reporting of Multiple Status Changes
For points designated in the database as subject to change detection, the System shall
detect, identify, and alarm the following operations which may occur between two subsequent
status scans.
From close to open
VIII-25
Square root
Absolute value
Running average.
Structured conditional statements such as IF, THEN, ELSE with Boolean operators
(AND, OR, NOT, XOR) are comparison operators (>, ~ =.s, <) to define conditions.
VIII-26
NOT
Calculated status points shall be treated the same as monitored status points with
respect to alarming and alarm acknowledgement.
8.13.5 SUPERVISORY CONTROL
Operators shall be able to control power system devices via RTUs. Select before operate
(SBO) control procedures apply to RTUs. For RTUs, SBO practices are required for both the
operator procedure, and the communications with the RTU; an RTU shall be instructed to execute
VIII-27
a command only after the master station verifies that the correct selection of point and control
function were reported by the RTU.
A supervisory control request shall be sent to an RTU only after the controlled point was
checked for proper conditions. The request shall be rejected if:
The device is not subject to supervisory control of the type being attempted;
The requested control operation is inhibited by a tag placed on the device;
The point has been deactivated or the points RTU is inactive;
There is no match between the area-of-responsibility of the device and of the
console initiating the control request;
The operators console is in a mode which does not permit supervisory control;
A control request for the same device from another console is still pending (it has
not yet been EXECUTED);
A previous control command for the same device is incomplete (see Section
13.5.3; applies only to control via RTUs).
Rejection of a control request shall occur before any transmission IS made to the RTU or
control purposes. Rejection of a control request shall in a CRT message being issued. The point
name and the reason for request refusal shall be identified in the message.
If the RTUs allow the master station to specify the duration of or act closure, it shall be
possible to specify in the database either an individual contact closure period for each two-state,
three-state, and incremental control device, or a minimum of eight typical contact closure periods
to be used for different types of controlled devices. This would be permitted the in Programming
Mode only.
8.13.5.1 Control of the Two and Ti fee State Devices
Select-Before-Operate (Sac) control shall be provided for various types of two-state and
three-state devices, including:
Selection of a point for control shall be cancelled after the Executive command is
initiated. The point shall also be automatically de-selected if the operator does not choose a
specific control operation within a control time-out period after the point was selected, or does not
issue an Execute command within the same control time-out period after the operation was
VIII-28
chosen. A system-wide control time-out period shall be adjustable from a console in the
Programming mode in the range of 10 seconds to 60 seconds.
VIII-29
generated. 80th the displayed message and the alarm shall identify each affected breaker and
the reason for the failure. The displayed message(s) shall not be deleted or superseded without
authorization by the system operator. Failure to control one or more breakers in a group shall not
affect controlling the other breakers in the same group.
It shall also be possible to operate (trip or close) each individual breaker from the load
shed display for the group.
Initiation of a block load shed operation shall automatically start a timer. After an operator
entered time-out period, an alarm shall be generated to remind the operator to restore the loads.
Normal breaker closing commands will be used to restore previously shed groups.
8.13.6 LOAD CONTROL
Load control of HT consumer loads is required to reduce the system peak load during the
evening peak hours. Synthesis or load curves of the feeders to which the HT consumers are
connected has to be performed for flattening of the load curve by shifting of the peak load to
valley portions of the load curve.
Shedding/restoration of individual HT consumer loads shall be possible using a two way
MARS remote radio, pole-top RTU and a vacuum switch located at the customer premises.
8.13.6.1 Operational Methodology
Load control of HT loads shall be possible either for single discrete loads or for the load
groups where the loads are divided into load groups. The additional points to be considered are:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
8.13.6.2 Reports/Displays
The following reports/displays are required:
VIII-30
Summary of loads shed, total relief obtained and relief obtained on the feeders to
which the HT consumers are connected indicating the name of Substation, name
of feeder and name of HT consumer.
Real time display of active and reactive load of HT consumers along with name
of substation and name of feeder to which each HT consumer is connected.
Trending of load curves of loads/load groups with provision to display (i) hourly
load curves, (ii) weekly load curves, (iii) monthly load curves.
It shall be possible to effect load control from a user friendly display provided on
the monitor giving the details of loads/load groups, priorities, present loading
status and the time when the load was last switched off. Scramming of individual
loads/load groups shall be possible with a single command from the display
provided on the operator console. It shall be possible to control loads from any
display showing the loads/load groups.
Graphical displays showing the single line diagrams of substation, feeders, HT consumer
loads connected with real time display of active and reactive loads.
8.13.6.3 Alarms/Messages
VIII-31
Billing data shall be available for display. The display shall show the customer name for
each meter, and shall show the date and time when the displayed information was obtained.
Operators shall be able to add or modify customer names and also demand the reading of billing
data from any specific meter from the display.
The most recent billing data shall be available for transfer by magnetic tape or diskette to
APSEBs Customer Information System in ASCII format.
8.13.7.2 Hourly Meter Readings
Selected data shall be read from the meters every hour on the hour. The following is a
tentative list of data to be read; the final list will be developed during project implementation:
a.
Three-phase volts
b.
c.
d.
Items a and b shall be stored in the real-time database, and shall be available for
display and storing in HAR accounts.
The date and time readings shall be used to detect and alarm meter clock problems.
Detection of tampering shall be alarmed, and a Tamper indicator shall be set for the
affected meter in the metering display. This flag shall flash until the alarm is acknowledged by an
operator, and shall continue to be displayed until it is manually deleted.
8.13.7.3 Meter Management and Programming
The DAS shall issue all initialization, time synchronization, and register reset commands
needed by the meters to support the specified requirements. It shall also be possible to specify
time of use (TaU) periods and other necessary parameters for the meters from the metering
display.
8.13.8 INTEGRATED VOLT -VAR NTROL
One of the important requirements of any distribution system is to provide a good voltage
profile/voltage within acceptable limits to the consumers and mini mise the distribution losses.
This is achieved by supplying the required reactive power at the appropriate locations in the
distribution system by installing switched shunt capacitor banks and voltage regulators on
distribution feeders and controlling them remotely from DCC.
8.13.8.1 Function inputs
The following inputs are required by the function:
VIII-32
Network data.
The Graphical user interface for displays/reports of SCADA and all application
functions shall be the standard MOTIF. The displays/reports required by the
software are:
Status of switched capacitors and tap position of voltage regulators are also to be
displayed.
8.13.8.4 Alarms/Messages
The following alarms and messages are required:
Feeder name, amount of voltage violation and its location on the feeder, if
violation is expected to exist even after using all Volt/VAR sources on that feeder.
VIII-33
(b)
Report indicating the time of occurrence of fault and time at which the fault has
been isolated.
(c)
Graphical display of faulted feeder with switches, highlighting the, faulted section
in different colour.
VIII-34
(d)
(e)
Number of switching and the sequence of switching to identify the fault.
8.13.9.1.3 Alarms/Messages
Alarms/Messages are generated in the following cases:
(a)
(b)
Alarm to alert the operator about the occurrence of fault on a feeder indicating
the name of substation, name of feeder and time of occurrence of fault.
(c)
Transformer capacity of the adjoining substations and the current loading status.
(b)
Present loading status of alternative feeder, conductor size, thermal limits, over
current relay settings for the feeders and node voltage limits.
Out of the available alternatives. the best alternatives have to be indicated. The
possible results of the function are:
(a)
(b)
None of the alternative sources are viable i.e., restoration is not possible as the
constraints cannot be satisfied.
VIII-35
(c)
(d)
Only partial restoration is possible. In this case, the sections for which restoration
is possible and the sections for which restoration is not possible have to be
indicated.
The alternate source/adjoining substation name, feeder name selected must also
be indicated.
Restoration is possible for all sections beyond the faulted sections. The best
alternative(s) have to be indicated.
8.13.9.2.2 Reports/Displays
(a)
(b)
(c)
(d)
(e)
(f)
(g)
8.13.9.2.3 Alarms/Messages
Alarms/Messages are generated in the following cases:
(a)
(b)
(c)
VIII-36
intermediate overloads during switching. For load balancing between transformers in the same
substation having different per unit impedances operation on different taps may be required. The
function should provide for this exigency. It is invoked by the operator or automatically on
overloads, likely overloads, un equal loadings of the feeders and the transformers.
8.13.9.3.2 Operational Methodology
The problem of load balancing can be looked upto as an optimization problem where the
objective function must reflect the following objectives:
A solution is then found to optimize the most critical objective among the above
objectives.
The objective must be achieved by minimal number of switching operations of the
switches. Provision must be available for selecting either automatic operation of switches by
software program or operation of switches by the operator through SCADA.
8.13.9.3.3 Reports/Displays
The following reports/displays are required.
(i)
(ii)
(iii)
(iv)
8.13.9.3.4 Alarms/Messages
Alarms/messages are generated in the following cases: r ~
VIII-37
Display of dynamic information of various devices like status, analog values etc.
On-line modification of the geographical and network maps with the help of the
map editor.
Network schematics
VIII-38
8.13.10.3 Reports/Displays
VIII-39
(a)
Call entry form for entering the consumer name/identifier, nature of trouble call
reported and time of outage.
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
(j)
(k)
(I)
VIII-40
It shall be possible to establish an HAR account for any point in the DAS database,
including data that is derived from other HAR accounts. Procedures are required to :
(a)
(b)
(c)
(d)
(e)
(f)
Dispatcher oriented procedure are required for the HAR management functions
described above.
8.13.12.3 HAR Calculations
It shall be possible to define calculated HAR accounts based on any other HAR
account(s). Calculations shall be definable via interactive CRT procedures. Each such calculated
account shall be defined by a series of calculation steps wherein each step defines the operation
to be performed and the associated operands. Operands shall be logically acetified; internal data
IDs and offsets shall not be required. As a minimum, the calculation capabilities for arithmetic
calculations specified in Section 13.4.2 Calculated Analog Points, are required. The capability to
calculate sums of values across a group of HAR accounts is specifically required. A calculated
account shall have all the attributes of any other HAR account. Any account, including calculated
accounts, shall be usable as an input for calculating other accounts. It shall be possible to
calculate an account from shorter time frame accounts, e.g., calculate a daily account from hourly
accounts or a monthly account from daily accounts.
8.13.12.4 Viewing and Editing of Accounts
An operator shall be able to view and edit any HAR account on his terminal. The operator
shall, however, not be allowed to override calculated values. Operator-entered values shall be
flagged with the Manually Entered (M) data quality indicator. When historical values are changed,
calculated values which depend on them shall automatically be updated. As an alternative the
operator can be required to manually demand data recalculation, but in this case a conspicuous
message indicating the need to do so shall be displayed until the recalculation is performed.
8.13.12.5 Exporting and Archiving of HAR Data
It shall be possible to copy HAR data in a format which is suitable for import into a
database or spreadsheet on an external computer. An intermediate file format which is supported
by several commercially available databases and spreadsheets is required. The intermediate
format shall be subject to approval by APSEB.
VIII-41
The HAR database and archival files shall be structured to facilitate transfer of data for
one calendar month at a time. Data transfers shall be by category (such as operational data,
radio communication statistics, etc.) and sub category, as defined by APSEB, but not by individual
accounts. Operator procedures, based on screen selection of the data to transfer and the
destination storage device, are greatly preferred over procedures which require programming
skills.
8.13.12.6 Required Accounts Categories
8.13.12.6.1 Operational Accounts
The HAR accounts described below shall be set up by the Contractor for all analog points
in the system, including MW, Mvar and volts. Other accounts shall be set up as needed to
generate data for required reports.
(a)
(b)
(c)
Additional accounts shall be set up if needed to supply data to any of the required
reports.
8.13.12.6.2 Radio Communication System Accounts
APSES will monitor the operation of the Radio Communication System described in
Section 1.1.4. RTUs may be used to monitor all radio equipment at the sites of the backbone
TDMA radios and repeaters, and remote MARS radios may also be monitored. Alternatively, RTU
communications data may be available from optional communications maintenance functions
specified in Sections 13.13. All data from the Radio Communications System shall be stored by
HAR every hour on the hour. The list of monitored data will be compiled after Contract award.
8.13.12.7 Report Requirements
8.13.12.7.1 Creation of Reports
A Report Editor is required to allow easy interactive CRt creation, modification, and
deletion of reports. Any account data store in the HAR database shall be eligible for inclusion in
any or all reports. Report definition shall include the following:
VIII-42
Definitions of calculations
Printout periodicity (on demand, time of day, day/time of week, day/time of
month)
Assignment of printers.
When reports are printed on the laser printers it shall be possible to specify the portrait
or Landscape printing modes, and to support scalable fonts. On other printers it shall be
possible to create reports which are 80 columns wide which use standard paper and 132 columns
wide which use wide paper.
It shall be possible to concatenate separately reports to be printed out together.
8.13.12.7.2 Printing and Viewing of Reports
A report shall be automatically printed at the time periods which were specified when the
reports was created. In addition, an operation shall able to demand the printout of any report at
any time. An operator shall also be able to select any report for viewing on a terminal, and to
page through multi-page reports.
Printing of reports shall start at the top of a new page. However, if the printer is already at
the top of the page, a new top of the page command shall not be issued. Under no
circumstances, including system failover, shall the printing of a report be omitted. Once started, a
report shall not be interrupted until it is completed, unless cancelled by the operator. Multiage
output may be interrupted on page boundaries if the printer is serving its primary task and is
simultaneously backing up another printers function. Each page of multiple page report shall
have a specially designed header for that report, identifying pertinent data including time and
date. At no time shall a page or printed output contain any information other than for that report.
If the designated printer is unavailable, the report shall automatically be routed to an
operator-specified backup device. If no backup printer is available, the report shall be spooled to
bulk storage until a printer becomes available. at which time the report shall automatically by
printed.
8.13.12.8 Required Reports
The reports described below shall be included by the Contractor in the delivered system.
8.13.12.8.1 Daily Power Distribution Report
By substation, this report shall include the daily minimum and maximum readings, with
the time of occurrence for:
A limited number of amp and voltage readings telemetered from feeders (if poletop RTUs are installed).
VIII-43
(b)
A good data communication system to transmit the control commands & data
between DCC & large number of devices remotely located on the distribution
network is a prerequisite for the good performance of Distribution Automation
System (DAS). The communication requirements of each DAS is unique,
depending upon the DA functions selected for implementation. A wide range of
communication technologies are available to perform the tasks of DAS. The
choice of communication technology has also big impact on the cost of DAS.
Selecting an appropriate communication system for DAS calls for understanding
of
VIII-44
8.14.03
Radio communications
1.
2.
8.14.05
Power line communication (PLC) : The main advantage of using the power network as a
communication medium is that the network is completely by the utility. It reaches any
point on the network and automatically extends to the newly added network elements.
Three PLC technologies are applicable for DAS.
Ripple control
In the Indian power networks the distribution line joints are made manually using binding i
wire and the quality of joint is not very good. This will cause serious problems of signal for
propagation. A maximum baud rate of 1,.200 B~S will be achieved with this Power Line ~
Communication. Hence PLC technology IS considered not suitable for Indian networks at the
present stage.
VIII-45
8.14.06
Ultra High Frequency (UHF) Radio System operates in 154 MHz band.
Suitable for one way control of load control switches. It also requires line
of sight.
8.14.07
on
various
combinations
of
Radio
Considering one DAS system for districts, the farthest points are about 150 KM from the
DCC. The service area was divided into a set of areas 30 KM radius. The center of each area
was designated as nodal point. One of these nodal points is at the DCC.
The nodal points will be interconnected by a TDMA system for backbone network, with
TDMA central station at DCC and TDMA outstation at each nodal point. TDMA has the advantage
of providing 64 KBPS data rate and high quality voice communication. TDMA repeater stations
will be providing 64 KBPS data rate and high quality voice communication. TDMA repeater
stations will be provided at suitable locations where line of sight cannot be guaranteed.
MARS master radio will be installed in each nodal point for communication with RTUs in
substation, at distribution transformers, and other required points in the distribution network.
Substation RTUs will be scanned periodically, and others probably once an hour, and on demand
by a DAS operator Though radio frequencies- in the 400 MHz band are easier to obtain and
provide better coverage, operation in the 900 MHz band was chosen because robust and nonconspicuous short stick antennas can be used. This makes radio equipment installed in
exposed locations less prone to vandalism by customers opposed to load control. The MAR
master stations will be suitably interfaced to the TDMA outstations and the data collected at the
TDMA outstations will be transmitted to the central station.
One-way VHF radio will be used for load control because low cost load control switches
are available for this technology. VHF radio switches can also be used for capacitor control on the
distribution network, in view of more expensive RTUs with remote MARS radios, if monitoring is
not essential at the capacitor banks.
VIII-46
VIII-47
VIII-48
VIII-49