PROPOSAL
Prepared for:
: Inquiry No:
: January 24, 2014
Our Ref
Date
TABLE OF CONTENTS
PART I
DESIGN PARAMETER
1.
2.
3.
4.
PART II
PROCESS SELECTION
Wastewater Treatment Plant
PART III
1.0
2.0.
3.0.
PART IV
Exclusion
Deviation
PART V
COMMERCIAL PROPOSAL
ANNEXES
Annex 1
Annex 2
P&I D
Process Flow Diagram
This proposal is provided to the Buyer for its confidential use in connection with the evaluation of this
project only and has to be returned upon request.
The information given must not be used except for the specific purpose for which it is submitted or
reproduced in any form, without the written permission of the Seller.
It is understood that the technical details, specifications and other features of the process and
equipment are of preliminary nature. In case Seller may find it necessary to modify, delete, add to
these on completion of detailed engineering, these changes shall be incorporated in the final designs,
provided that the overall performance and guarantees are maintained.
The present proposal will not constitute a binding obligation of PT. Indosol Multidaya, also if accepted
by Buyer, unless an agreement is reached and entered into force by written instruments duly signed by
the legal representative of both parties.
PART I
DESIGN PARAMETERS
1.0
Inlet Condition
Name of
wastewater
Volume
wwt
Freq
pH
SS
Mg/l
COD
Mg/l
Oil
mgl
Fe
Mg/
l
P
M
gl
N
m
gl
BOD
Mg/l
P
Mp
a
Tmp
C
1
2
3
4
5
6
7
The analysis of the waste water has been extracted from the specification document
Attachment #. Process Data
2
Plant Performance
The waste water treatment plant is capable of treating 50 m3/hr (Oily wastewater) and 3
m3/h (Sanitary wastewater) from above wastewater and discharging them to the site
discharge channel or for recovery water.
35
< 30
C
mg/l
mg/1
6-9
mg/l
mg/l
mg/l
mg/l
<3
mg/l
< 0.05 mg/l
mg/l
mg/l
mg/l
mg/l
Tin
Arsenic (As)
Selenium (Se)
Nickel
Cobalt
Cyanide (CN)
Sulfide (H2S)
Fluoride
Free chlorine (Cl2)
Ammonia
(NH3-N)
Urea
Nitrate (NO3-N)
Nitrite (NO2-N)
BOD5
COD
Blue methyl
Phenol
Total oil
Radioactive
4
< 0.5
<5
<1
< 10
<1
< 30
< 80
<5
-
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
Terminal Points/Conditions
Terminal points of piping works:
The raw water line will terminate 1 m outside from water and wastewater treatment
building area.
The service air inlet line will terminate 1 m outside from water and wastewater
treatment building area.
The instrument air inlet line will terminate 1 m outside from water and wastewater
treatment building area.
All chemical unloading points will terminate 1 m outside the bund wall adequate for
connection to the tanker unloading pumps.
Terminal points of the electrical works:
The power will terminate at MCC panel terminal
The race way will terminate 1 m outside from WWTP building area.
Terminal points of the I & C works:
The cables between equipments supplied and Local control panel are our
scope of supply
PART II
PROCESS SELECTION
The wastewater system will be for the following requirement:
A. Wastewater based on type of the sources:
1. Oily wastewater :
- Oily wastewater from Ammonia, Urea & Utility plant
The oily wastewater from ammonia, urea & utility plant will be collected to oily water
basin capacity 1000 m3 then will be pumped into CPI oil water separator integral with oil
separator basin. The effluent from CPI water separator will flow into dissolved air flotation
(DAF).
The emulsified oil will be break and seperated into the dissolved air flotation. The scum in
the top will be collected by scrapper and flow into the scum collecting drum
The clean water from DAF will flow to final staorage basin. The treated water will be
filtered by activated carbon filter to dispose to rain water sewer
PART III
LIST AND SPECIFICATION OF EQUIPMENT
1. Oily water basin (by other)
2. Oily water pumps
Item
:
Quantity
T yp e
Capacity
Head
Material
Motor
: 2 x 100%
: Submersible
: 50 m3/hr
: 1.5 kg.cm2
: Cast iron(casing), Cast iron(impeller/shaft)
: 4 kw, 400 V, 50 hz, 3 ph
: 1 x 100%
: CPI
: Settler : FR P, Frame: 304SS
: 50
m3/hr
: 5.0 x 1.8 x 1.6 m
: Less than 10.0mg/L
: Tank: R.C. + epoxy (by other)
: 2 x 100%
: Submersible
: 50 m3/hr
: 2 kg.cm2
: Cast iron(casing), Cast iron(impeller/shaft)
: 5.5 kw, 400 V, 50 hz, 3 ph
5. Static mixer
Item
:
Quantity
Type
Size
Material
: 1 x 100%
: In line tube static mixer
: dia. 159 mm x 1100 mm
: SS 304
: 1 x 100%
: vertical cylindrical
Capacity
M a te r i al
Complete with
: 2 m3
: FRP or PE.
: Mixer, Matl 304 SS, 0.37 kW, 380 V, 1400 rpm
: 2 x 100%
: Diaphragm
: 50
l/hr
:5
kg/cm2
: Head: PVDF, Diaphragm: Teflon, valve: ALA ceramic
: 0.55 kw, 3 ph, 50hz,
: 1 x 100%
: vertical cylindrical
: 2 m3
: FRP or PE.
: Mixer, Matl 304SS, 0.37 kw, 380 V, 1400 rpm
: 2 x 100%
: Diaphragm
: 50
l/hr
:5
kg/cm2
: Head: PVDF, Diaphragm: Teflon, valve: ALA ceramic
: 0.55 kw, 3 ph, 50hz,
: 1 x 100%
: Circular
: 50 m3/hr
: dia. 7.0 m x H 3.5
: 3 m dia, 2 m dpth
: Surface and bottom
: speed 1 2 rpm
: 0.37 kw, 400 v, 50hz
: Ladder, Top/Bottom scrapper, floater hand rail
: CS + epoxy lined
: 1 x 100%
: dia. 800 x SS 4000 mm
: Pressure gauge
: 2 x 100%
: Centrifugal horizontal
: 25 m3/hr
: 4 kg.cm2
: 304SS(casing)304SS(impeller/shaft)
: 5.5 kw, 400 V, 50 hz, 3 ph
: 1 x 100%
: Rectangular
: 100 m3
: 6.0 x 4.5 x 4.0 m
: Tank: R.C. (by other)
: 2 x 100%
: Centrifugal horizontal
: 50 m3/hr
: 3 kg.cm2
: CI (casing) / 304SS(impeller/shaft)
: 7.5 kw, 400 V, 50 hz, 3 ph
: 2 x 100%
: Vertical
: 50 m3/hr
: dia 2200 x SS 1500 mm
: Activated carbon
: CS + epoxy lined
: 2 x 100%
Type
Capacity
Head
Material
Motor
: Centrifugal horizontal
: 45 m3/hr
: 2.5 kg.cm2
: CI (casing) / 304SS(impeller/shaft)
: 7.5 kw, 400 V, 50 hz, 3 ph
: 1 x 100%
: Rectangular
: 10
m3
: Tank: R.C. (by other)
: 2 x 100%
: Centrifugal horizontal
: 10 m3/hr
: 4.0 kg.cm2
: CI (casing) / CI (impeller/shaft)
: 2.2 kw, 400 V, 50 hz, 3 ph
: 1 x 100%
: Vertical Gravity Separator
: 10 m3/hr
: dia 900 x SS 3000 mm
: Housing: HDPE, Packing: HDPE
: Piping & valves
: 2 unit
: Drum
: dia 1100 x H 1200 mm
: CS
: PVC, ANSI
: Control valves, On/off valves, butterfly valves,
Ball valves
: PVC
10
:
:
:
:
:
:
Instrument air
Control valves
Dry, dew point 20 C
4 Nm3/h
6 barg
Ambient
Miscellaneous:
1. All piping, fitting, valves, flanges, gaskets, bolts and nuts, expansion joints including pipe
supports, anchor bolt and nut, pipe rack, hangers within wastewater treatment
system Battery Limits.
2. Complete piping systems installed on pipe rack and/or pipe sleeper where
necessary, with any type of valves, supports, hangers, etc. and air flushing assembly
pipe line for skid mounted equipment.
3. All minor pipes(including sleeve, insert) necessary for maintenance and operation as
drainage pipes, vents, etc. in Suppliers scope.
4. Local push button
5. All power and control cables, tray, conduit and supporting materials such as
hanger, support, material and embedded channel within Battery Limits.
6. Spare parts and consumables for start-up, commissioning and performance test
7. Spare parts for 2 years operation
8. Chemical consumable for 6 months
PT. Indosol Multidaya
11
9. All & counter flanges with bolts, nuts and gaskets at the terminal points
10. Structural steel for wastewater treatment system equipment such as platform,
stairway, ladders and supports for installation, operation and maintenance
11. Touch up paint and initial charge oil (Grease and oil for initial filling and flushing)
12. Shop test and inspection
13. Coupling, coupling cover and associated (if required)
14. Lifting lugs
15. Painting according to the owners standard
16. Drawings & documents of all Mfg. supplied equipment with sufficient details for
installation and maintenance
17. Foundation design information including loading data and arrangement and
assembly drawings
18. All required documentation including O & M manual
19. Startup and testing assistance
20. Introduction in operation and maintenance of the operators and maintenance
staff during installation and commissioning.
21. Embedded material such as base plates, shims, anchor bolts/nuts, foundation
anchor bolts, nuts and electrical conduits within pedestal zone
22. All bulk materials (cables, cable gland, raceways, grounding power sockets, etc.)
23. All instrument installation materials such as impulse tube, air piping, manifold valves,
supports, etc.
12
PART IV
EXCLUSIONS AND DEVIATIONS
EXCLUSIONS
-
All civil engineering work is excluded; this covers engineering and structural steelwork design
(checking civil work and structural work), buildings., foundations, concrete sumps, bunds
and linings, trench covers, unit drains, floor drains, gulleys and drainpipes.
All piping from remote sump pits outside WWTP area to WWTP
Battery limit for feld instrumentations are at junction box.
All installation of piping and cabling outside WWTP area / battery limits
Plant heating and lighting.
Electricity, air and water for testing and commissioning.
Lifting beams and hoists for plant maintenance (if required).
Connecting to and from the plant.
Switchgear and starters..
All third party inspection, design calculation checks, surveillance fees and associated costs.
Site establishment.
DEVIATION