Professional Documents
Culture Documents
I. INTRODUCTION
Manuscript received December 31, 2010; revised June 12, 2011; accepted
July 06, 2011. Date of current version December 16, 2011. This work was supported by Endeavour Energy, New South Wales, Australia.
The authors are with the Endeavour Energy Power Quality and Reliability Centre, School of Electrical, Computer and Telecommunications
Engineering, University of Wollongong, Wollongong, NSW, 2522, Australia
(e-mail: kz965@uow.edu.au; ashish@uow.edu.au; kashem@uow.edu.au;
sarath@uow.edu.au).
Color versions of one or more of the figures in this paper are available online
at http://ieeexplore.ieee.org.
Digital Object Identifier 10.1109/TSTE.2011.2166281
ZOU et al.: DISTRIBUTION SYSTEM PLANNING WITH INCORPORATING DG REACTIVE CAPABILITY AND SYSTEM UNCERTAINTIES
113
FOR
In this paper, DG technologies including synchronous machine-based biomass generators, doubly fed induction generator (DFIG)-based wind systems, and voltage source inverter
(VSI)-based PV systems are considered as candidate DG systems that can be integrated into the network. The static reactive
capability limitations of these DG technologies are discussed in
the following subsections.
(5)
where
and
are the equivalent main and stator impedances of a DFIG-based wind unit,
respectively, and the power factor angle
can be derived as
(6)
With the inclusion of the mechanical power limit of the wind
turbine and the limits described in (4) and (5), the reactive capability of the DFIG-based wind unit is shown in Fig. 1(b).
C. VSI-Based PV System
The active and reactive power output from a voltage source
inverter (VSI)-based PV system can be independently controlled by the power angle and modulation index [14]. The
reactive capability limits of VSI interfaced PV system, as
shown in Fig. 1(c), are usually dependent on the inverter rating
114
and the rated active power output of the PV cells [15]. The
lower and upper reactive capability limits imposed by the
inverter current
can be calculated as
(7)
where
PV unit.
Therefore, the approach using the single sub-distribution function is adopted in this paper for modeling the associated uncertainties. In this case, the statistical mean and standard deviation in (8) can be directly estimated based on the historical
data set as
(9)
(10)
where
is the total number of data points in a data set and
is the th data point.
The probability distribution functions used in this paper for
modeling the uncertainties associated with wind speed, solar
radiation, and load demand are presented as follows.
1) Wind Speed: Wind speed, as an essential measurement for
selecting a candidate site, is influenced by many factors such as
the weather conditions, the land terrain, and the height above the
ground surface [20]. Although wind speed exhibits an intermittent feature throughout both short-term and long-term periods,
the wind speed characteristics in a predefined time period can
be statistically described by using Weibull distribution [21] as
illustrated in Fig. 2. In the Weibull distribution, the probability
function for the wind speed over a time interval can be expressed as
(11)
and scale
In (11), the shape parameter
parameter
can be estimated using the Gamma
function
, the mean
, and standard deviation
related
to wind speeds in the predefined time period.
2) Solar Radiation: The uncertainty in solar radiation cannot
be directly modeled using a probability distribution function due
to the fact that the solar radiation has very strong diurnal patterns. The uncertainty in solar radiation incident on a PV array
mainly comes from the stochastic nature of weather conditions.
In this paper, a method using a clearness index [22] representing
the weather conditions is adopted to address the uncertainty in
solar radiation. The clearness index is defined as the ratio of the
solar radiation on a horizontal plane to the extraterrestrial solar
radiation. It is assumed that the solar radiation on a horizontal
ZOU et al.: DISTRIBUTION SYSTEM PLANNING WITH INCORPORATING DG REACTIVE CAPABILITY AND SYSTEM UNCERTAINTIES
plane can be fully collected by the PV array, thus the solar radiation incident on the PV array
can be evaluated as
(12)
where
is the extraterrestrial solar radiation which can be
accurately calculated based on the site and the orbit of the earth,
and
is the clearness index.
The random behavior of the clearness index can be statistically described by using the Beta distribution function [22], as
shown in Fig. 3. In the Beta distribution, the probability function
for the clearness index over a time interval can be expressed
as
(13)
where the Beta parameters and can be obtained using the
mean
and standard deviation
of clearness index in a predefined time period
(14)
(15)
3) Load Demand: The Gaussian distribution uses
as the
lower limit and
as the upper limit, which is not suitable for
load representation. This is because load has specific minimum
and maximum values. Therefore, a Gaussian distribution with
specified lower and upper limits [23] is used in this paper to
describe the variation of load demand over a period of time.
Fig. 4 depicts a sample truncated Gaussian distribution. In the
truncated Gaussian distribution, the probability function for the
loading level
over a time interval can be expressed as
115
(16)
where
and
are statistical mean and standard deviation
of the load demand in a predefined period of time respectively,
and
and
are minimum and maximum loading levels,
respectively.
116
In the suboptimization problem, the optimal active and reactive power from DG units will be derived so as to minimize the
state dependent cost
expressed as
(20)
The DG operation and maintenance (O&M) cost
can be
evaluated based on the total active power generated by the DG
units as
(21)
ZOU et al.: DISTRIBUTION SYSTEM PLANNING WITH INCORPORATING DG REACTIVE CAPABILITY AND SYSTEM UNCERTAINTIES
where
is the total number of planning years,
is the present
worth factor of cost in a year ,
is total hours for a system
state
in a year , and
,
, and
are cost factors
(in $/kWh) for estimation of operation and maintenance (O&M)
costs for wind, solar PV, and biomass generator, respectively.
The total fuel cost
of biomass generators can be estimated
based on their total energy generation in a planning horizon as
formulated in
(22)
is the cost factor (in $/kWh) for estimating fuel cost.
where
The cost
for purchased energy from grid can be assessed
in relation to the active power loss, the active power injected
by DG units, and the active power consumed by the loads as
expressed in
117
(23)
is the cost factor (in $/kWh) for evaluating the cost
where
associated with the purchased energy from grid,
is a set of
feeder sections,
is the branch current,
is the feeder
resistance, and
is the load demand.
The cost
for emissions can be estimated associated with
the total energy imported from grid and the energy injected by
biomass-based generators as indicated in
(24)
is the cost factor (in $/kg) for evaluating the cost aswhere
sociated with emissions, and
and are emission factors (in
kg/kWh) of emissions associated with the actual energy consumption by the system and total energy supplied by biomass
generators, respectively.
The cost
for system reliability is evaluated based on the
cost associated with energy not supplied (ENS) as calculated in
(25)
where
is the cost factor (in $/kWh), derived from the practical reliability studies conducted in Australia, for evaluating
(28)
(29)
(30)
where
is the specified lower limit of the operating power
factor of a DG site,
and
are total active and reactive
,
, and
power injections of a DG site respectively,
are reactive power injections from wind, solar PV, and
biomass-based DG units, respectively.
4) DG Reactive Capability Limits: The reactive power injection and absorption of individual DG unit should be within
the upper and lower limits associated with the steady-state DG
operation as discussed in Section II.
V. SOLUTION ALGORITHM
In this paper, a solution algorithm based on TRIBE PSO and
OO is proposed in order to find an optimal solution for the formulated problem with high performance and accuracy. The proposed algorithm can also derive a set of near-optimal solutions
for system planners to compare in case these solutions are practically more feasible. In the proposed algorithm, TRIBE PSO is
dedicated to exploring feasible candidate solutions through approximate evaluation using a crude model to form a representative set for OO. Subsequently, OO is used to allocate intensive
assessment using an accurate model for candidate solutions involved in a selected subset so as to find the optimal and near-optimal solutions. In this paper, the crude and accurate models can
be built with the representative states determined based on the
specified number of segments for each normalized variable as
developed in Section III-C. The solution accuracy and computational burden will be increased with the increase of the number
118
Fig. 8. Movement of a particle by using (a) simple pivot strategy, (b) noisy
pivot strategy.
of representative states in crude and accurate models. The flowchart shown in Fig. 7 summarizes the proposed algorithm.
A. Determination of Feasible Solutions Using TRIBE PSO
In the proposed algorithm, the master TRIBE PSO is used to
obtain the candidate DG allocation schemes in terms of sizes,
types, and locations of DG units. Associated with the DG allocation scheme generated by the master TRIBE PSO, the subTRIBE PSO is applied to obtain the state dependent operation
strategies in terms of active and reactive power from individual
DG unit.
In TRIBE PSO, the particles, informers, and tribes are three
basic elements. A particle made up with problem variables is
the representation of a candidate solution for an optimization
problem. The informer is a particle, which passes useful information to other particles. The tribe is a group of particles
that share the information with each other. The TRIBE PSO applies unique strategies, named the simple pivot strategy and
the noisy pivot strategy, to guide the movements of particles
for exploring the optimal solution without fine tuning any algorithm parameters [27]. By using the simple pivot strategy,
the new position of a particle representing a new DG allocation scheme and associated operation strategies can be obtained
based on its previous best position and the previous best position of its informer depicted in their respective hyper-spheres as
illustrated in Fig. 8(a). In this case, the candidate DG allocation
schemes and operation strategies inside the intersection of two
hyper-spheres will be explored. On the other hand, the noisy
pivot strategy allows particles to explore candidate DG allocation schemes and operation strategies outside the hyper-spheres
as shown in Fig. 8(b) by adding random noise to the particle position reached through the simple pivot strategy. As a whole,
the simple pivot strategy allows TRIBE PSO to explore similar but potentially better DG allocation schemes and operation
strategies, whereas the noisy pivot strategy allows TRIBE
PSO to generate distinct but possibly better solution in case of
the particles are trapped in a local optimal solution.
Since only feasible solutions will be preserved, there is no
need for master TRIBE PSO to evaluate a DG allocation scheme
for all system states if any of the defined constraints are violated. In such a case, a new scheme will be generated. This
strategy allows the master TRIBE PSO to evaluate more feasible
solutions effectively with less computational efforts. Similarly,
a strategy for reducing the computational time is also applied
for sub-TRIBE PSO. It can be observed from the flowchart that
the sub-TRIBE PSO will be terminated (a) if no feasible solution is obtained for maximum number of iterations or (b) if no
improvement in the feasible solution is achieved for specified
number of iterations. The use of these termination conditions
can significantly reduce the computational time for performing
the suboptimization of each system state if only approximate estimation is required.
B. Selection of Optimal and Near-Optimal Solutions Using OO
The feasible candidate solutions identified by TRIBE PSO
will be preserved to form a representative set representing the
whole problem space. The size of the representative set is a
problem independent parameter which can be obtained [28]
based on the requisite quality of the sample solutions and the
specified probability of achieving such quality as given in
(31)
where is the size of the representative set,
(in percentage)
is the specified quality in terms of at least one of the sample
solutions in top
of the entire solution space, and
is the
associated probability for achieving the requisite quality.
It is noted that the total cost as fitness value of a candidate solution is only approximately evaluated by using a crude model
with limited system states in TRIBE PSO. The true optimal and
near-optimal solutions in the representative set can be identified
only if all candidate solutions are re-estimated with an accurate model consisting of more system states. To avoid exhausted
evaluation of all candidate solutions in the representative set, the
ZOU et al.: DISTRIBUTION SYSTEM PLANNING WITH INCORPORATING DG REACTIVE CAPABILITY AND SYSTEM UNCERTAINTIES
selection rules specified in OO can be applied to allocate intensive assessment for candidate solutions involved in a selected
subset. The size of the selected subset can be determined [28]
based on the size of the representative subset and the user-defined requirements in terms of the size of the good enough
subset , the alignment level , and the alignment probability
. The good enough subset is a set of top best solutions defined as satisfied solutions in the problem space. The alignment
level is the number of solutions involved in both selected subset
and the good enough subset. The alignment probability is the
probability that the specified alignment level is achieved. In this
paper, the size of the selected subset is estimated by using the
method based on the ordered performance curve (OPC), which
can be obtained by sorting the solutions in the representative set
according to their approximately evaluated fitness values. The
obtained OPC can be categorized into one of the five standard
OPCs and the size of the selected subset can be accordingly determined [28] as
119
(32)
where , , , and are constants associated with the OPC
shape, noise characteristics, and prespecified requirements.
VI. SIMULATION AND DISCUSSION
In this section, simulation studies are carried out in order to illustrate the proposed methodology for distribution system planning with incorporating reactive capability of different DG systems and system uncertainties.
A. Test System and Data
A rural 11-kV distribution system with a total length of 35 km
is derived from a practical distribution network in the Cattai region of New South Wales, Australia. The diagrammatic representation of the test feeder is shown in Fig. 9. The average load
demand of the test feeder is 590 kVA with an average power
factor of 0.9 lagging. The substation voltage for the distribution system is 10.7 kV set by the utility. The voltage limit is
set to 5% of the nominal voltage in the simulation as one of
the constraints. Moreover, it is also assumed that the feeder has
an annual load growth of 1% and the overall planning period is
30 years. The corresponding data and DG parameters for cost
calculations are given in the Appendix.
In this paper, it is also assumed that the variation in load demand at each load point has the same trend because of predominantly residential type. The daily average load demand, wind
speed, and solar radiation for each month, derived based on historical data [29], [30], are shown in Fig. 10. These data sets are
used as baseline data in the corresponding probabilistic models
to generate synthetic data.
B. Parameters for the Proposed Solution Algorithm
The proposed method can be applied for determination of
both single DG and multiple DG solutions. The number of DG
units has to be planned in advance at the planning stage. For
demonstration of the capability of the proposed method, two
nodes will be selected for installation of DG units. Three DG
Fig. 10. Daily average load demand, wind speed, and solar radiation for 288
time segments (24 hours 12 months).
(33)
The exhaustive search for exact global minimum total cost
associated with a DG allocation scheme in such large solution
space is not practical due to immense computational burden.
Instead, the exploration of a set of high quality solutions that
potentially involve optimal and near-optimal solutions with
high probability and reasonable computational time seems more
practical for system planners. For demonstration purposes, the
specified parameters used in proposed solution algorithm are
given as follows:
A crude model is built with 125 representative states
(5 segments for each normalized variable).
120
TABLE I
OBTAINED OPTIMAL AND NEAR-OPTIMAL DG ALLOCATION SCHEMES
during the day time but also due to its reactive capability to support system in peak load condition during the night. Although
the wind-based DG unit can support system in the same manner
by means of reactive power injection, its low capacity factor is
again a main limiting factor for its deployment. By increasing
the capacity factor of wind-based DG units to 18.8% to match
the capacity factor of solar PV-based DG units in case (c), it is
observed that the wind-based DG units become more attractive
than other two candidate DG units due to increased active power
injection and the matching between wind profile and load profile at certain time segments (as shown in Fig. 10). Moreover,
the wind-based DG units with reactive power injection further
enhance their capability for voltage support especially with the
peak load demand.
Fig. 11 shows the costs associated with the optimal DG allocation schemes for three cases. It can be seen that the total cost
of
can be achieved in case (b), which shows reduction of 6.16% as compared to case (a). It is also highlighted
that the fuel cost associated with the biomass-based DG unit
can be significantly reduced if reactive power injections from
DG units are allowed. The reduction of fuel cost in case (b) is
achieved through the injection of reactive power from solar PV
and biomass-based DG units. The reactive power injected by the
solar PV-based DG unit can help to reduce frequent start of the
biomass-based DG unit especially in the situations of high load
demand and low solar radiation. Moreover, the fuel consumption associated with the biomass-based DG unit can be reduced
if reactive power generated from biomass-based DG unit is used
as much as possible for system voltage support. The reactive
power injections of the solar PV and biomass-based DG units
[for optimal solution found in case (b)] over varying system conditions, in terms of different solar radiation levels and loading
levels, are shown in Figs. 12 and 13, respectively. It is observed
that the solar PV-based DG unit always injects reactive power
to the system in order to reduce system power losses as well as
121
ZOU et al.: DISTRIBUTION SYSTEM PLANNING WITH INCORPORATING DG REACTIVE CAPABILITY AND SYSTEM UNCERTAINTIES
BY
The simulation results indicate that it is important to incorporate reactive capabilities of DG units in the planning model
in order to obtain better planning options with minimum total
cost. Moreover, the obtained near-optimal solutions along with
the optimal solution allows planners to compare in case of these
solutions are practically more feasible.
D. Comparative Study
The comparative results highlighting optimal solutions obtained from different optimization algorithms are tabulated in
Table II. In TRIBE PSO, the optimal solution is obtained by directly performing evaluation with the accurate model over the
optimization process. In OO, the representative set is generated
by random search and the optimal solution is obtained by applying the same requirements used in the proposed algorithm
as specified in Section VI-B. Simulations are carried out on a
Core2 machine with 2.4-GHz CPU and 2-GB RAM.
As compared to OO, the total cost obtained by the proposed
algorithm is 1.57% less than that found by OO. This is due to the
fact that the proposed algorithm can explore the problem space
in a more intelligent manner with its unique search strategies.
As compared to TRIBE PSO, it is found that proposed algorithm
presents more than 10-fold reduction in computation time with
122
TABLE III
PARAMETERS FOR CALCULATING CORRESPONDING COSTS
VII. CONCLUSION
This paper has presented a new optimization framework for
distribution system planning with incorporating DG reactive
capability and system uncertainties. The reactive capabilities
of renewable DG technologies including the synchronous machine-based biomass generator, the DFIG-based wind unit, and
the VSI-based solar PV unit were considered in distribution
system expansion planning. The system uncertainties associated with the time-varying load demand and intermittent renewable power generation in the planning framework have been addressed and solutions using probabilistic models and clustering
technique have been developed. The integrated solution algorithm with TRIBE PSO and OO has been developed to determine optimal and near-optimal solutions that provide the options to the system operator to compare and decide for the best
feasible solution for practical implementation. The total cost associated with different DG systems, comprised of capital cost,
operation and maintenance cost, reliability cost, cost of deferred
energy, and emission cost has been minimized for evaluating optimal allocation of DGs. The simulation results also highlighted
the reduction in total cost with the consideration of DG reactive
capabilities at the planning stage. It was also observed that the
solar PV and wind-based DG units can offset the biomass-based
generator with reactive capability considerations. The effectiveness of proposed solution algorithm in terms of computational
time and accuracy has also been emphasized in this paper.
APPENDIX
A. Parameters for Cost Calculations
The parameters used for calculating various costs in the
simulation study are obtained based on the work of [31][34].
The parameters as listed in Table III are assumed to be kept
unchanged over the planning horizon. It is also assumed in
the planning horizon of 30 years that the annual average electricity price
will be linearly increased from $59/MW to
$110/MW and the annual average carbon price
will be
from $20/tonne to $67/tonne.
B. DG Parameters
It is assumed that the maximum active power output of a DG
unit will be rated at 90% of the nominal DG capacity. The machine parameters (on the generator kVA base) for different DG
systems are given below.
1) Synchronous Machine-Based Biomass Generator: In this
paper, the synchronous machine-based biomass generator is approximated as a cylindrical rotor machine [11]. The direct axis
reactance
of 1.54 pu is used. It is assumed that the maximum
stator current
is 1 pu and the maximum rotor voltage
is 2.17 pu. The startup limit is assumed to be 30% of the nominal active real power output.
TABLE IV
PARAMETERS FOR DFIG-BASED WIND UNITS
ZOU et al.: DISTRIBUTION SYSTEM PLANNING WITH INCORPORATING DG REACTIVE CAPABILITY AND SYSTEM UNCERTAINTIES
[7] A. Piccolo and P. Siano, Evaluating the impact of network investment deferral on distributed generation expansion, IEEE Trans. Power
Syst., vol. 24, no. 3, pp. 15591567, Aug. 2009.
[8] A. Kumar and W. Gao, Optimal distributed generation location using
mixed integer non-linear programming in hybrid electricity markets,
IET Gener. Trans. Distrib., vol. 4, pp. 281298, Feb. 2010.
[9] R. A. Jabr and B. C. Pal, Ordinal optimisation approach for locating
and sizing of distributed generation, IET Gener. Trans. Distrib., vol.
3, pp. 713723, Aug. 2009.
[10] P. R. Lopez, M. G. Gonzalez, N. R. Reyes, and F. Jurado, Optimization of biomass fuelled systems for distributed power generation using
particle swarm optimization, Elect. Power Syst. Res., vol. 78, pp.
14481455, Aug. 2008.
[11] P. A. Lof, G. Andersson, and D. J. Hill, Voltage dependent reactive
power limits for voltage stability studies, IEEE Trans. Power Syst.,
vol. 10, no. 1, pp. 220228, Feb. 1995.
[12] R. J. Konopinski, P. Vijayan, and V. Ajjarapu, Extended reactive capability of DFIG wind parks for enhanced system performance, IEEE
Trans. Power Syst., vol. 24, no. 3, pp. 13461355, Aug. 2009.
[13] T. Lund, P. Sorensen, and J. Eek, Reactive power capability of a wind
turbine with doubly fed induction generator, Wind Energy, vol. 10, pp.
379394, Apr. 2007.
[14] F. Delfino, G. B. Denegri, M. Invernizzi, R. Procopio, and G.
Ronda, A P-Q capability chart approach to characterize grid connect
PV-units, in Proc. CIGRE/IEEE PES Joint Symp., Calgary, Canada,
Jul. 2009.
[15] L. J. Borle, M. S. Dymond, and C. V. Nayar, Development and testing
of a 20-kW grid interactive photovoltaic power conditioning system in
Western Australia, IEEE Trans. Ind. Appl., vol. 33, no. 2, pp. 502508,
Mar. 1997.
[16] M. E. Tarter and M. D. Lock, Model-Free Curve Estimation. New
York: Chapman & Hall, 1993.
[17] B. W. Silverman, Density Estimation for Statistics and Data Analysis. London, U.K.: Chapman & Hall, 1986.
[18] R. DAgostino and M. Stephens, Goodness-of-Fit Techniques. New
York: Marcel Dekker, 1996.
[19] R. Singh, B. C. Pal, and R. A. Jabr, Statistical representation of distribution system loads using Gaussian mixture model, IEEE Trans.
Power Syst., vol. 25, no. 1, pp. 2937, Feb. 2010.
[20] T. Burton, D. Sharpe, N. Jenkins, and E. Bossanyi, Wind Energy Handbook. Hoboken, NJ: Wiley, 2001.
[21] S. H. Jangamshetti and V. G. Rau, Optimum siting of wind turbine
generators, IEEE Trans. Energy Convers., vol. 16, no. 1, pp. 813,
Mar. 2001.
[22] V. A. Graham and K. G. T. Hollands, A method to generate synthetic
hourly solar radiation globally, Solar Energy, vol. 44, pp. 333341,
1990.
[23] Y. V. Makarov, C. Loutan, M. Jian, and P. de Mello, Operational impacts of wind generation on california power systems, IEEE Trans.
Power Syst., vol. 24, no. 2, pp. 10391050, May 2009.
[24] P. Giorsetto and K. F. Utsurogi, Development of a new procedure for
reliability modeling of wind turbine generators, IEEE Trans. Power
Appl. Syst., vol. 102, no. 1, pp. 134143, Jan. 1993.
[25] S. Conti and S. Raiti, Probability load flow using monte carlo techniques for distribution networks with photovoltaic generators, Solar
Energy, vol. 81, pp. 14731481, Dec. 2007.
[26] A. Pregelj, M. Begovic, and A. Rohatgi, Quantitative techniques for
analysis of large data set in renewable distributed generation, IEEE
Trans. Power Syst., vol. 19, no. 3, pp. 12771285, Aug. 2004.
[27] M. Clerc, Tribes, a parameter free particle swarm optimizer, in Proc.
OEP03, Paris, France, 2003.
[28] T. W. E. Lau and Y. C. Ho, Universal alignment probabilities and
subset selection for ordinal optimization, J. Optimization Theory
Appl., vol. 93, pp. 455489, Jun. 1997.
[29] (2010) Bureau of Meteorology [Online]. Available: http://www.bom.
gov.au/climate/how/contacts.shtml
123
Kai Zou (S09A10) received the B.Eng. degree in electrical power engineering in 2005 from the Huazhong University of Science and Technology,
China, and the M.Eng. degree in 2006 from the University of Wollongong,
Australia. He is currently working toward the Ph.D. degree in the area of power
distribution system planning and optimization with embedded generation at
University of Wollongong, Wollongong, Australia.
Ashish Prakash Agalgaonkar (M09) received the Ph.D. degree from Indian
Institute of Technology-Bombay, Mumbai, India, in 2006.
Currently, he is working as a Lecturer at the Endeavour Energy Power Quality
and Reliability Centre, School of Electrical, Computer, Telecommunications
Engineering, University of Wollongong, Wollongong, Australia, where he also
worked as a Postdoctoral Research Fellow from February 2008 to November
2010. He was associated with the School of Engineering, University of Tasmania, Australia, as a Postdoctoral Research Fellow from October 2007 to January 2008. He also worked as a Scientist in the Energy Technology Centre,
NTPC Limited, India, from 2005 to 2007. His research interests include load
modeling, impact of distributed generation on distribution systems, micro-grids,
and system stability.
Kashem M. Muttaqi (M01SM05) received the Ph.D. degree from Multimedia University, Malaysia, in 2001.
Currently, he is an Associate Professor at the School of Electrical, Computer, and Telecommunications Engineering, University of Wollongong, Wollongong, Australia. He was associated with the University of Tasmania, Australia as a Research Fellow/Lecturer/Senior Lecturer from 2002 to 2007, and
with the Queensland University of Technology, Australia as a Research Fellow
from 2000 to 2002. Previously, he also worked for Multimedia University as a
Lecturer for three years. His special fields of interests include distributed generation, renewable energy, distribution system automation, and power system
planning.
Sarath Perera (M95) received the B.Eng. degree in electrical power engineering from the University of Moratuwa, Sri Lanka, the M.Eng. degree from
the University of New South Wales, Sydney, Australia, and the Ph.D. degree
from the University of Wollongong, Wollongong, Australia.
He was a Lecturer at the University of Moratuwa. Currently he is an Associate
Professor with the University of Wollongong, where he is also the Technical
Director of the Endeavour Energy Power Quality and Reliability Centre.