You are on page 1of 2

Footprint

Changing the RF cost performance paradigm

Transparent Infrastructure – (Part 2 of 6)


Frequency transparent RF infrastructure is key to providing cost efficient communications in today’s busy spectrum. This
paper explores the concept of transparency, benefits and methodology to confirm it has been achieved.

Introduction
Although these are an excellent measure of electrical
Frequency transparency allows multiple RF signals to be ‘match’ in the RF chain, the operator can still be left with
overlaid on common infrastructure without degradation or performance issues that result in dropped calls and reduce
distortion, by providing a linear RF transmission conduit, coverage and capacity. Other symptoms of poor
essential for spread spectrum architectures or any mix of transparency are:
more traditional technologies formerly considered • Site alarms.
incompatible. • Parasitic noise rise, and
• Desensitized or degraded receiver noise floor.
Holma and Toskala (WCDMA & UTMS Nokia Finland 2004)
believe 1dB loss in CDMA and UTMS receiver sensitivity Experience suggests RF interference being present as the
can mean as much as 11% loss of coverage. Feedback result of infrastructure build quality or from an outside
from network operators around the world suggests this source. Spectral analysis can help, but often the cause is
may be a conservative estimate, but it is agreed that traced to RF system non-linearity, introduced by poor
receiver sensitivity is a key element of network construction or component deterioration. This can be best
performance. confirmed by testing for the presence of PIM.

This paper introduces using Passive Intermodulation (PIM) Part 3 of this series of papers deals with PIM in more
as an efficient and practical way to measure RF system detail, however in summary it can generate potential
linearity and detect non-linear elements that maybe receiver interference in proportion to the degree of system
limiting RF transparency at the BTS. non-linearity at a given RF power, and therefore makes an
ideal construction Quality Control (QC) performance
Benefits of Transparency metric.

A transparent RF infrastructure should perform as closely High Linearity = High Transparency


as possible to an ideal RF conduit having no loss, perfect
RL and complete linearity. High linearity => Low PIM => High construction quality

Applying equally to both uplink and downlink, the benefits The value of PIM testing
of achieving transparency include:
• Maximum coverage and capacity performance. PIM and DTF/RL are
• Integration of merging technologies on a different but equally
common feed system. important tests.
• Lower cost of service.
• An improved end user subscriber experience “Line sweeps”, or a resulting
with less poor quality or dropped calls, leading DTF plot and RL
to lower churn. measurement are critical
tests that cannot replace or be
Figure 1.
In reality system performance is determined by: replaced by a PIM
• Quality and performance of individual RF measurement. In isolation they present an incomplete
components used, and analysis of how well the RF interconnection will support
• Quality of the component installation. receiver performance.

While the individual components will determine the RF It is often found that DTF and RL test results appear
performance limits, the system construction and acceptable, yet the PIM performance is inferior. RL and
integration quality will determine the RF transparency and DTF sweeps alone can often be unsuccessful in uncovering
whether optimum performance is ever achieved. non linearity faults due to:
• The skills and experience needed to configure test
Achieving Transparency equipment and interpret results.
• Low RF power used during testing, or
The causes of poor transparency can include: • The fault being able to be seen only with a PIM test.
• High Insertion Loss (IL).
• High Return Loss (RL), and A network performance discussion with almost any
• In-band and out-of-band Passive maintenance team will reveal they are often involved in
Intermodulation (PIM). resolving unexplained receiver noise rise, or unreliable
reception of signals from subscribers considered to be
Traditionally we have had to rely on Return Loss (RL) and within the coverage ‘footprint’.
Distance to Fault (DTF) measurements/sweeps to
determine infrastructure performance. PIM is generally present as the result of the physical
condition of the RF infrastructure, and without adequate

Further information visit our websites


www.summitekinstruments.com
www.triasx.com

Page 2 - Footprint Two - 1


Footprint
Changing the RF cost performance paradigm

test equipment, detection can be difficult and time


consuming with component substitution generally being a
last but necessary resort.

Jumper cables and other RF components can be PIM


sources, but site reports reveal that the most likely cause
of poor BTS sector performance can be traced to
construction practices. There is a growing pool of evidence
to suggest that a major contributor is badly terminated or
damaged and loose RF connectors, with case studies
supporting this presented in Part 5 of this series.

Analysis of PIM levels in the RF system are the simplest,


quickest and most sure way of detecting physical Figure 2.
conditions likely to limit RF transparency. Triasx and
Summitek Instruments are jointly promoting a range of Care must be taken to ensure that all new joints made
portable test sets designed to be used at the BTS for this between the test equipment and the system under test,
purpose. are clean and adequately tightened to a torque
recommended by the component manufacturers in order
PIM - A dynamic test to avoid test errors. Once this has been achieved and the
test set configured as required, the test is commenced by
IEC62037 is the international standard for measuring PIM. switching on the RF test power.
It provides a block diagram for the test apparatus required
and defines the test parameters, scope and techniques The PIM level is recorded while the whole system is
that should be used during the process. subjected to a reasonable amount of physical impact and
bending force as per IEC62037. This activity will result in a
It is important to note the dynamic process (physical pass or fail outcome.
treatment) that should be applied as a necessary element
of this test process. In the event that the system or section under test fails,
the test is repeated by breaking the RF interconnection
PIM is an absolute. The average performance of system and moving the cable load forward toward an accessible
components can not compensate for poor construction of mid-point.
the BTS infrastructure.
Test results are recorded as each PIM source is located
Measurement simplicity and corrected.

Triasx/Summitek test sets have been designed for easy This process is repeated until the whole RF
interconnection is certified as PIM source free. At this
use in measuring and recording the reflected PIM.
stage the installation can be regarded as a physically
The equipment requires significantly less experience to set sound, linear and RF transparent conduit ready for RL and
up and use than more familiar test sets used to take RL DTF sweeps to carried out and recorded.
and DTF sweeps. Test levels for RF power, length of the
test, test tone frequencies and pass or fail criteria are Frequency transparent RF infrastructure under pins the
either set at the factory or by a supervising engineer cost performance paradigm for BTS now and into the
before going onsite. future.

The test set operator need only connect correctly to the In part 3 of this series we will investigate the RF
device or system to be analysed, turn on the RF power, phenomenon of PIM, its causes and prevention.
dynamically load or impact the points of interest and
record the result. It is very much a go no-go test.
This paper has been jointly prepared by Triasx Pty Ltd (Brisbane,
The level of expertise required is limited to common work Australia) and Summitek Instruments (Denver, USA).
practices pertaining to health and safety, working with RF
and general fault diagnosis and correction techniques.

Making a PIM test at the BTS

This is an intrusive test and requires the BTS radio to be


isolated from the interconnection RF system. The test set
is connected in its place, as shown in Figure 2, with each
feeder system being tested in turn.

At the discretion of network management the antenna


may be replaced by a low PIM cable load to prevent
unwanted or unauthorized radiation of the RF test power.

Further information visit our websites


www.summitekinstruments.com
www.triasx.com

Page 3 - Footprint Two - 2

You might also like