Professional Documents
Culture Documents
Introduction
To rectify the problems:-
Through extensive testing with operators in Australia, • Two connectors were cleaned, checked and re-
Africa, Asia/Pacific, USA and Europe, we estimate more mated.
than 60% of existing sites have some form of PIM • Two connecters within the cabin were re-terminated.
problem, of which around 80% are connector related. • A masthead connector which had suffered lightning
damage (visible burn) was cut back 6 inches and new
The following are a small selection of examples we have connector fitted.
discovered in the field. • All the resistive loads where replaced with low IM
cable loads.
Case Study 1 - South East Asia
Upon completion of testing, all 6 sectors were in the range
Located in a major South-East Asia capital, this site is a -150dBc to -145dBc. With just a few hours of rectification
GSM900 macro cell, using 6 main feeders with pre- work, Dropped Calls improved by greater than 50% in first
combined Transmit/Receive Units (TRU’s) for channel week.
capacity and a 47m tower.
Case Study 2 – Australia
Figure 2
In this case the GSM900 and WCDMA800 were co-located Checks on the diversity feeder of sector ‘g’ revealed:
with resulting PIM products degrading the receiver
noise floor to as high as -95dBm/30kHz. This loss in
• RL and DTF sweeps were acceptable (pre-post).
receiver sensitivity is a loss in coverage and capacity.
• The main feeder failed PIM tests.
Using the Triasx test set the operator was able to locate
• An antenna jumper failed PIM tests.
numerous faulty connections, correcting these to produce
• A 5/8” connector was “spinning” under
an excellent result.
weatherproofing. Water poured out of the feeder
when the connector was removed.
Figure 3
During a visit to a series of mid-western US base station Testing for PIM at the BTS, in conjunction with Return
sites, 4 out of 5 failed PIM in some capacity. Loss (RL) and Distance to Fault (DTF) measurements is
proving to be the most effective way to eliminate or
A six sector site using a Lucent compact 4 BTS, with roof significantly reduce problems with the RF interconnection.
mounted EMS antennas was investigated more closely due
to its repeated diversity alarms. A relatively new site, it With the series of portable PIM test equipment developed
has been installed within the last 18 months, and used by Triasx and Summitek Instruments, it is now possible to
5/8” Andrew AVA copper mainline and ½” jumpers. carry out complete RF interconnection testing at the BTS
receiver input with ease.