Jobs Description
7. Determine accuracy of all meters and calibrate watthour meters .Verify multipliers
8. Perform phasing check on double ended or dual source switchgear to insure correct bus phasing from each source
9. Control power transformer
1. Perform insulation-resistance tests. Perform measurements from winding to winding and each winding to ground. Test voltage shall be in
accordance table 100.1 unless otherwise specified by manufacturer.
2. Perform secondary wiring integrity test. Disconnect transformer at secondary terminals and connect secondary wiring to a rated secondary
voltage source. Verify correct potential at all devices.
3. Verify correct secondary voltage by energizing primary winding with system voltage.Measure secondary voltage with the secondary wiring
disconnected.
4. Verify correct function of control transfer relays located in switchgear with multiple control power sources.
12. Voltage Transformer
1. Perform insulation resistance tests. Perform measurements from winding to winding and each winding to ground. Test voltages shall be in
accordance with tabel 100.1
2. Perform secondary wiring integrity test. Verify correct potential at all devices.
3. Verify secondary voltages by energizing primary winding with system voltage.
13. Verify operation of cubicle switchgear space heaters.
Feeder J02 BBVT
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
2. Inspect physical and mechanical condition
3. Inspect ground connections to switchgear ground bus.
4. Verify the unit is clean ( CB Copartement, Busbar Compartement and Cable compartement )
5. Perform mechanical operator tests in accordance with Site Acceptance Test MV Switchgear
6. Verify operation and squencing of interlocking system
7. Inspect bolted electrical connections for high resistance using of the following methode
1. Use of low resistance ohm meter
2. Verify tightness of accessible bolted electrical connections by calibrated toque-wrench methode in accordance with manufacture publish data
8. Inspect insulating assemblies for evidence of physical damage or contaminated surfaces.
9. Verify that each fuseholder has adequate support and contact integrity.
10. Verify that fuse sizes and types are in accordance with drawings, short-circuit studies, and coordination study.
11. Lubrication requirements
1. Verify appropriate lubrication on moving current carrying parts
2. Verify appropriate lubrication on moving and sliding surface
12. Inspect operation of the drawout mechanism including mechanical interlocks, position indicators, and safety features
13. Confirm correct operation and squencing of electrical and mechanical interlock system
14. Inspect insulators for evidence of physical damage of contaminated surfaces.
15. Verify corret barrier and shutter installation and operation
16. Inspect mechanical indicating devices for correct operation
17. Perform visual mechanical inspection of instrument transformers section 7.10
18. Inspect control power transformers
1. Inspect for physical damage, cracked insulation, broken lead, tightness of connections, defective wiring and overall general condition
2. Verify the primary and secondary fuse or circuit breaker rating match drawings.
3. Verify correct functioning of drawout disconnecting VT Truck
2. Electrical Tests
1. Perform electrical test on instrument transformer in accordance with section 7.10
2. Perform ground resistance test in accordance with section 7.13
3. Perform resistance measurement through bolted electrical connection with a low resistance ohmmeter in accordance with section 7.1.1
4. Perform insulation resistance test on each bus section phase to phase and phase to ground for one minute in accordance with tabel 100.1
5. Perform an overpotensial test each bus section, each phase to ground with phases not under test grounded, in accordance with manufacturer publish data.
If manufacturer has no recommendation for this test, it shall be in accordance with tabel 100.2 The test voltage shall be applied for one minute
6. Perform current injection test on the entire current in each section of switchgear.
1. Perform current test by secondary injection with magnitude sich that a minimum current of 1.0 ampere flow in the secondary circuit. Verify correct magnitude of
current at each device in the circuit.
2. Perform current test by primary injection with magnitude such that a minimum of 1.0 ampere flows in the secondary circuit. Verify correct magnitude of current at
each device in the circuit.
7. Determine accuracy of all meters and calibrate watthour meters .Verify multipliers
8. Perform phasing check on double ended or dual source switchgear to insure correct bus phasing from each source
9. Control power transformer
1. Perform insulation-resistance tests. Perform measurements from winding to winding and each winding to ground. Test voltage shall be in
accordance table 100.1 unless otherwise specified by manufacturer.
2. Perform secondary wiring integrity test. Disconnect transformer at secondary terminals and connect secondary wiring to a rated secondary
voltage source. Verify correct potential at all devices.
3. Verify correct secondary voltage by energizing primary winding with system voltage.Measure secondary voltage with the secondary wiring
disconnected.
4. Verify correct function of control transfer relays located in switchgear with multiple control power sources.
12. Voltage Transformer
1. Perform insulation resistance tests. Perform measurements from winding to winding and each winding to ground. Test voltages shall be in
accordance with tabel 100.1
2. Perform secondary wiring integrity test. Verify correct potential at all devices.
3. Verify secondary voltages by energizing primary winding with system voltage.
13. Verify operation of cubicle switchgear space heaters.
Feeder J03 Outgoing to TR
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
2. Inspect physical and mechanical condition
6. Perform current injection test on the entire current in each section of switchgear.
1. Perform current test by secondary injection with magnitude sich that a minimum current of 1.0 ampere flow in the secondary circuit. Verify correct magnitude of
current at each device in the circuit.
2. Perform current test by primary injection with magnitude such that a minimum of 1.0 ampere flows in the secondary circuit. Verify correct magnitude of current at
each device in the circuit.
7. Determine accuracy of all meters and calibrate watthour meters .Verify multipliers
8. Perform phasing check on double ended or dual source switchgear to insure correct bus phasing from each source
9. Control power transformer
1. Perform insulation-resistance tests. Perform measurements from winding to winding and each winding to ground. Test voltage shall be in
accordance table 100.1 unless otherwise specified by manufacturer.
2. Perform secondary wiring integrity test. Disconnect transformer at secondary terminals and connect secondary wiring to a rated secondary
voltage source. Verify correct potential at all devices.
3. Verify correct secondary voltage by energizing primary winding with system voltage.Measure secondary voltage with the secondary wiring
disconnected.
4. Verify correct function of control transfer relays located in switchgear with multiple control power sources.
12. Voltage Transformer
1. Perform insulation resistance tests. Perform measurements from winding to winding and each winding to ground. Test voltages shall be in
accordance with tabel 100.1
2. Perform secondary wiring integrity test. Verify correct potential at all devices.
3. Verify secondary voltages by energizing primary winding with system voltage.
13. Verify operation of cubicle switchgear space heaters.
Feeder J04 Outgoing to CV
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
2. Inspect physical and mechanical condition
3. Inspect ground connections to switchgear ground bus.
4. Verify the unit is clean ( CB Copartement, Busbar Compartement and Cable compartement )
5. Perform mechanical operator tests in accordance with Site Acceptance Test MV Switchgear
6. Verify operation and squencing of interlocking system
7. Inspect bolted electrical connections for high resistance using of the following methode
1. Use of low resistance ohm meter
2. Verify tightness of accessible bolted electrical connections by calibrated toque-wrench methode in accordance with manufacture publish data
8. Inspect insulating assemblies for evidence of physical damage or contaminated surfaces.
9. Verify that each fuseholder has adequate support and contact integrity.
10. Verify that fuse sizes and types are in accordance with drawings, short-circuit studies, and coordination study.
11. Lubrication requirements
1. Verify appropriate lubrication on moving current carrying parts
2. Verify appropriate lubrication on moving and sliding surface
12. Inspect operation of the drawout mechanism including mechanical interlocks, position indicators, and safety features
13. Confirm correct operation and squencing of electrical and mechanical interlock system
14. Inspect insulators for evidence of physical damage of contaminated surfaces.
15. Verify corret barrier and shutter installation and operation
16. Inspect mechanical indicating devices for correct operation
17. Perform visual mechanical inspection of instrument transformers section 7.10
18. Inspect control power transformers
1. Inspect for physical damage, cracked insulation, broken lead, tightness of connections, defective wiring and overall general condition
2. Verify the primary and secondary fuse or circuit breaker rating match drawings.
3. Verify correct functioning of drawout disconnecting VT Truck
2. Electrical Tests
1. Perform electrical test on instrument transformer in accordance with section 7.10
2. Perform ground resistance test in accordance with section 7.13
3. Perform resistance measurement through bolted electrical connection with a low resistance ohmmeter in accordance with section 7.1.1
4. Perform insulation resistance test on each bus section phase to phase and phase to ground for one minute in accordance with tabel 100.1
5. Perform an overpotensial test each bus section, each phase to ground with phases not under test grounded, in accordance with manufacturer publish data.
If manufacturer has no recommendation for this test, it shall be in accordance with tabel 100.2 The test voltage shall be applied for one minute
6. Perform current injection test on the entire current in each section of switchgear.
1. Perform current test by secondary injection with magnitude sich that a minimum current of 1.0 ampere flow in the secondary circuit. Verify correct magnitude of
current at each device in the circuit.
2. Perform current test by primary injection with magnitude such that a minimum of 1.0 ampere flows in the secondary circuit. Verify correct magnitude of current at
each device in the circuit.
7. Determine accuracy of all meters and calibrate watthour meters .Verify multipliers
8. Perform phasing check on double ended or dual source switchgear to insure correct bus phasing from each source
9. Control power transformer
1. Perform insulation-resistance tests. Perform measurements from winding to winding and each winding to ground. Test voltage shall be in
accordance table 100.1 unless otherwise specified by manufacturer.
2. Perform secondary wiring integrity test. Disconnect transformer at secondary terminals and connect secondary wiring to a rated secondary
voltage source. Verify correct potential at all devices.
3. Verify correct secondary voltage by energizing primary winding with system voltage.Measure secondary voltage with the secondary wiring
disconnected.
4. Verify correct function of control transfer relays located in switchgear with multiple control power sources.
12. Voltage Transformer
1. Perform insulation resistance tests. Perform measurements from winding to winding and each winding to ground. Test voltages shall be in
accordance with tabel 100.1
2. Perform secondary wiring integrity test. Verify correct potential at all devices.
3. Verify secondary voltages by energizing primary winding with system voltage.
13. Verify operation of cubicle switchgear space heaters.
MV Switchgear 4,16 kV
Feeder M05 Incoming
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
2. Inspect physical and mechanical condition
3. Inspect ground connections to switchgear ground bus.
4. Verify the unit is clean ( CB Copartement, Busbar Compartement and Cable compartement )
5. Perform mechanical operator tests in accordance with Site Acceptance Test MV Switchgear
6. Verify operation and squencing of interlocking system
7. Inspect bolted electrical connections for high resistance using of the following methode
1. Use of low resistance ohm meter
2. Verify tightness of accessible bolted electrical connections by calibrated toque-wrench methode in accordance with manufacture publish data
8. Inspect insulating assemblies for evidence of physical damage or contaminated surfaces.
9. Verify that each fuseholder has adequate support and contact integrity.
10. Verify that fuse sizes and types are in accordance with drawings, short-circuit studies, and coordination study.
11. Lubrication requirements
1. Verify appropriate lubrication on moving current carrying parts
2. Verify appropriate lubrication on moving and sliding surface
12. Inspect operation of the drawout mechanism including mechanical interlocks, position indicators, and safety features
13. Confirm correct operation and squencing of electrical and mechanical interlock system
14. Inspect insulators for evidence of physical damage of contaminated surfaces.
15. Verify corret barrier and shutter installation and operation
16. Inspect mechanical indicating devices for correct operation
17. Perform visual mechanical inspection of instrument transformers section 7.10
18. Inspect control power transformers
1. Inspect for physical damage, cracked insulation, broken lead, tightness of connections, defective wiring and overall general condition
2. Verify the primary and secondary fuse or circuit breaker rating match drawings.
3. Verify correct functioning of drawout disconnecting VT Truck
2. Electrical Tests
1. Perform electrical test on instrument transformer in accordance with section 7.10
2. Perform ground resistance test in accordance with section 7.13
3. Perform resistance measurement through bolted electrical connection with a low resistance ohmmeter in accordance with section 7.1.1
4. Perform insulation resistance test on each bus section phase to phase and phase to ground for one minute in accordance with tabel 100.1
5. Perform an overpotensial test each bus section, each phase to ground with phases not under test grounded, in accordance with manufacturer publish data.
If manufacturer has no recommendation for this test, it shall be in accordance with tabel 100.2 The test voltage shall be applied for one minute
6. Perform current injection test on the entire current in each section of switchgear.
1. Perform current test by secondary injection with magnitude sich that a minimum current of 1.0 ampere flow in the secondary circuit. Verify correct magnitude of
current at each device in the circuit.
2. Perform current test by primary injection with magnitude such that a minimum of 1.0 ampere flows in the secondary circuit. Verify correct magnitude of current at
each device in the circuit.
7. Determine accuracy of all meters and calibrate watthour meters .Verify multipliers
8. Perform phasing check on double ended or dual source switchgear to insure correct bus phasing from each source
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low resistance ohmmeter, if applicable.
2. Perform insulation resistance tests on contactors, phase to ground, phase to phase, and across the open contacts for one minute in accordance with table 100.1
3. Perform system function test
4. Test control power transformer
5. Perform overpotential test in accordance with manufacturer's publish data. If manufacturer has no recommendation for this test, it shall be in accordance with table
6. Perform vacuum bottle integrity test (overpotential), if applicable, across each vacum bottle with the contacts in the open position in strict accordance with
manufacturer's publish data. DO NOT EXCEED MAXIMUM VOLTAGE stipulated for this test
7. Perform contact resistance tests
8. Measure blowout coil circuit resistance
9. Measure resistance of power fuse
10. Energize contactor using an auxiliary source. Adjust armature to minimize operating vibration where applicable
11. Test motor protection devices in accordance with manufacturer's published data. In the absence of manufacturer's data.
12. Test starting transformers, if applicable.
13. Verify operation of cubicle space heater.
Motor Feeder M03
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications
2. Inspect physical and mechanical condition
3. Inspect anchorage, alignment, and grounding
4. Verify the unit is clean
5. Inspect bolted electrical connections for high resistance using of the following methode
1. Use of low resistance ohm meter
2. Verify tightness of accessible bolted electrical connections by calibrated toque-wrench methode in accordance with manufacture publish
data or table 100.12
3. Perform thermographic survey in accordance.
6. Test all electrical and mechanical interlock systems for correct operation and sequencing
7. Verify correct barrier and shutter installation and operation
8. Exercise all active components nad confirm correct operation of all indicating devices
9. Inspect contactors
1. Verify mechanical operation
2. Verify contact gap, wipe, alignment, and pressure are in accordance with manufacturer's published data.
10. Verify overload protection rating is correct for its application. Set adjustable or programmable devices according to the protective device coordiantion study
11. Lubrication requirements
1. Verify appropriate lubrication on moving current carrying parts
2. Verify appropriate lubrication on moving and sliding surface
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low resistance ohmmeter, if applicable.
2. Perform insulation resistance tests on contactors, phase to ground, phase to phase, and across the open contacts for one minute in accordance with table 100.1
3. Perform system function test
4. Test control power transformer
5. Perform overpotential test in accordance with manufacturer's publish data. If manufacturer has no recommendation for this test, it shall be in accordance with table
6. Perform vacuum bottle integrity test (overpotential), if applicable, across each vacum bottle with the contacts in the open position in strict accordance with
manufacturer's publish data. DO NOT EXCEED MAXIMUM VOLTAGE stipulated for this test
7. Perform contact resistance tests
8. Measure blowout coil circuit resistance
9. Measure resistance of power fuse
10. Energize contactor using an auxiliary source. Adjust armature to minimize operating vibration where applicable
11. Test motor protection devices in accordance with manufacturer's published data. In the absence of manufacturer's data.
12. Test starting transformers, if applicable.
13. Verify operation of cubicle space heater.
Motor Feeder M02
1. Visual and Mechanical Inspection
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low resistance ohmmeter, if applicable.
2. Perform insulation resistance tests on contactors, phase to ground, phase to phase, and across the open contacts for one minute in accordance with table 100.1
3. Perform system function test
4. Test control power transformer
5. Perform overpotential test in accordance with manufacturer's publish data. If manufacturer has no recommendation for this test, it shall be in accordance with table
6. Perform vacuum bottle integrity test (overpotential), if applicable, across each vacum bottle with the contacts in the open position in strict accordance with
manufacturer's publish data. DO NOT EXCEED MAXIMUM VOLTAGE stipulated for this test
7. Perform contact resistance tests
8. Measure blowout coil circuit resistance
9. Measure resistance of power fuse
10. Energize contactor using an auxiliary source. Adjust armature to minimize operating vibration where applicable
11. Test motor protection devices in accordance with manufacturer's published data. In the absence of manufacturer's data.
12. Test starting transformers, if applicable.
13. Verify operation of cubicle space heater.
Motor Feeder M01
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications
2. Inspect physical and mechanical condition
3. Inspect anchorage, alignment, and grounding
4. Verify the unit is clean
5. Inspect bolted electrical connections for high resistance using of the following methode
1. Use of low resistance ohm meter
2. Verify tightness of accessible bolted electrical connections by calibrated toque-wrench methode in accordance with manufacture publish
data or table 100.12
3. Perform thermographic survey in accordance.
6. Test all electrical and mechanical interlock systems for correct operation and sequencing
7. Verify correct barrier and shutter installation and operation
8. Exercise all active components nad confirm correct operation of all indicating devices
9. Inspect contactors
1. Verify mechanical operation
2. Verify contact gap, wipe, alignment, and pressure are in accordance with manufacturer's published data.
10. Verify overload protection rating is correct for its application. Set adjustable or programmable devices according to the protective device coordiantion study
11. Lubrication requirements
1. Verify appropriate lubrication on moving current carrying parts
2. Verify appropriate lubrication on moving and sliding surface
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low resistance ohmmeter, if applicable.
2. Perform insulation resistance tests on contactors, phase to ground, phase to phase, and across the open contacts for one minute in accordance with table 100.1
3. Perform system function test
4. Test control power transformer
5. Perform overpotential test in accordance with manufacturer's publish data. If manufacturer has no recommendation for this test, it shall be in accordance with table
6. Perform vacuum bottle integrity test (overpotential), if applicable, across each vacum bottle with the contacts in the open position in strict accordance with
manufacturer's publish data. DO NOT EXCEED MAXIMUM VOLTAGE stipulated for this test
7. Perform contact resistance tests
8. Measure blowout coil circuit resistance
9. Measure resistance of power fuse
10. Energize contactor using an auxiliary source. Adjust armature to minimize operating vibration where applicable
11. Test motor protection devices in accordance with manufacturer's published data. In the absence of manufacturer's data.
12. Test starting transformers, if applicable.
13. Verify operation of cubicle space heater.
Battery
1. Visual and Mechanical Inspection
1. Verify ventilation of battery room or enclosure
2. Verify existence of suitable eye wash equipment
Drawing
Reference
PO231-901
PO231-801
PO231-801
Drawing number
Report
- Take Picture
- Check If Okay
- Enter Note if deficient
- Enter N/A if not Applicable
PROGRESS
COMMISIONING E-HOUSE
DMLZ CV 511
Project Name
Contract No
Scope of supply
Customer
Periode Report
Update
: DMLZ CV 511
: TP1400071-001-002
: Commissioning DMLZ CV 511 and DMLZ CV510
: PT.Freeport Indonesia
: 11 February 2015 s/d 26 February 2015
: 26 - February - 2015
No
Jobs Description
Page 31 of 69
PROGRESS
COMMISIONING E-HOUSE
DMLZ CV 511
Project Name
Contract No
Scope of supply
Customer
Periode Report
Update
: DMLZ CV 511
: TP1400071-001-002
: Commissioning DMLZ CV 511 and DMLZ CV510
: PT.Freeport Indonesia
: 11 February 2015 s/d 26 February 2015
: 26 - February - 2015
No
Jobs Description
F&G System
- Installation support pipe F&G building 1
- Verify F&G setting unit accordance with FAT ducument section F&G Setting
- Pressure test for Pipe F&G
Page 32 of 69
PROGRESS
COMMISIONING E-HOUSE
DMLZ CV 511
Project Name
Contract No
Scope of supply
Customer
Periode Report
Update
: DMLZ CV 511
: TP1400071-001-002
: Commissioning DMLZ CV 511 and DMLZ CV510
: PT.Freeport Indonesia
: 11 February 2015 s/d 26 February 2015
: 26 - February - 2015
No
Jobs Description
4
4.1
4.2
VISUAL CHECK
Purpose of check is to ensure all equipment, main and/or auxiliary, shall
comply with the requirement specified in the tender specification, applicable
regulation, and the respected design.The specifications to check consist of:
J01
Progress
J02
J03
J04
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
Page 33 of 69
PROGRESS
COMMISIONING E-HOUSE
DMLZ CV 511
Project Name
Contract No
Scope of supply
Customer
Periode Report
Update
: DMLZ CV 511
: TP1400071-001-002
: Commissioning DMLZ CV 511 and DMLZ CV510
: PT.Freeport Indonesia
: 11 February 2015 s/d 26 February 2015
: 26 - February - 2015
No
Jobs Description
- Type of designation
- Ratings
- Physical fitness
- Physical damage
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
- Completeness of equipment
100%
100%
100%
100%
4.3
100%
100%
100%
100%
4.4
100%
100%
100%
100%
The inter panel wiring connections shall be verified in the conformance with the wiring diagram to ensure no miss
wiring before energized the control supply.
Page 34 of 69
PROGRESS
COMMISIONING E-HOUSE
DMLZ CV 511
Project Name
Contract No
Scope of supply
Customer
Periode Report
Update
: DMLZ CV 511
: TP1400071-001-002
: Commissioning DMLZ CV 511 and DMLZ CV510
: PT.Freeport Indonesia
: 11 February 2015 s/d 26 February 2015
: 26 - February - 2015
No
Jobs Description
4.5
4.6
Ensure that the protection relay is working based on system requirement and
100%
100%
100%
100%
100%
100%
100%
100%
50%
50%
50%
50%
Logic diagram
4.7
MEASUREMENT
Ensure that the measurement equipment is working properly with in tolerance.
4.8
Insulation measurement by DC megger aims at observing insulation level before and after power frequency test. If
insulation value after is considerably much lower than before power frequency test, the switchgear or equipment
tested is considered experiencing insulation degradation; thereafter, the equipment is subject to further
examination.
Megger test is made to measure insulation between phases and each phase to ground. For Main circuit of MV
switchgear, the megger tension shall not exceed 10 kV dc with duration maximum of 5 seconds.
The power frequency test on the main circuit of switchgear is to demonstrate the
insulation capability. The switchgear shall pass the test if no flash over or
disruptive leakage current occur.
MV Switchgear 4,16 kV
Progress
Page 35 of 69
PROGRESS
COMMISIONING E-HOUSE
DMLZ CV 511
Project Name
Contract No
Scope of supply
Customer
Periode Report
Update
: DMLZ CV 511
: TP1400071-001-002
: Commissioning DMLZ CV 511 and DMLZ CV510
: PT.Freeport Indonesia
: 11 February 2015 s/d 26 February 2015
: 26 - February - 2015
No
5
5.1
5.2
Jobs Description
MV Switchgear 4,16 kV
M01
M02
M03
M04
M05
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
0%
100%
0%
100%
0%
100%
0%
100%
0%
100%
100%
100%
100%
100%
VISUAL CHECK
Purpose of check is to ensure all equipment, main and/or auxiliary, shall
comply with the requirement specified in the tender specification, applicable
regulation, and the respected design.The specifications to check consist of:
- Type of designation
- Ratings
- Physical fitness
- Physical damage
' - Completeness of equipment
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
INSTALLATION CHECK
Main Busbar
- Cleanness of the Cross Connection of Bus bar
- Cleanness of Bus bar Compartment
Contactor Compartement
- Cleanness of Contactor Spout
- Cleanness of Contactor Compartment
- Cleanness of Unit Contactor
- Door Condition
- Install the Unit Contactor Into Contactor Compartment
Cable Compartement
- Cleanness of Cable Compartment
- Check Tightness of Cable Connection
Page 36 of 69
PROGRESS
COMMISIONING E-HOUSE
DMLZ CV 511
Project Name
Contract No
Scope of supply
Customer
Periode Report
Update
: DMLZ CV 511
: TP1400071-001-002
: Commissioning DMLZ CV 511 and DMLZ CV510
: PT.Freeport Indonesia
: 11 February 2015 s/d 26 February 2015
: 26 - February - 2015
No
Jobs Description
5.3
100%
100%
100%
100%
100%
5.4
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
The inter panel wiring connections shall be verified in the conformance with the wiring diagram to ensure no miss
wiring before energized the control supply.
5.5
5.6
Ensure that the protection relay is working based on system requirement and
Logic diagram
5.7
MEASUREMENT
Ensure that the measurement equipment is working properly with in tolerance.
0%
0%
0%
0%
0%
5.8
50%
50%
50%
50%
50%
Insulation measurement by DC megger aims at observing insulation level before and after power frequency test. If
insulation value after is considerably much lower than before power frequency test, the switchgear or equipment
tested is considered experiencing insulation degradation; thereafter, the equipment is subject to further
examination.
Page 37 of 69
PROGRESS
COMMISIONING E-HOUSE
DMLZ CV 511
Project Name
Contract No
Scope of supply
Customer
Periode Report
Update
: DMLZ CV 511
: TP1400071-001-002
: Commissioning DMLZ CV 511 and DMLZ CV510
: PT.Freeport Indonesia
: 11 February 2015 s/d 26 February 2015
: 26 - February - 2015
No
Jobs Description
Megger test is made to measure insulation between phases and each phase to ground. For Main circuit of MV
switchgear, the megger tension shall not exceed 10 kV dc with duration maximum of 5 seconds.
The power frequency test on the main circuit of switchgear is to demonstrate the
insulation capability. The switchgear shall pass the test if no flash over or
disruptive leakage current occur.
Prepared by
PT. Schneider Indonesia
Aknowledge
PT. Freeport Indonesia
Aknowledge
PT. Freeport Indonesia
Heru Sulistiyono
ID.
Tri Budianto
ID.
Page 38 of 69
Page 39 of 69
OGRESS
ONING E-HOUSE
LZ CV 511
Progress
Remark
66%
100%
100%
Waiting delivery material from Jakarta
ETA in the MP68 tgl 20-Feb-15
0%
date : 20/02/2015
==> Material already in E-House DMLZ CV511
On Progress
Waiting delivery material from Jakarta
ETA in the MP68 tgl 19-Feb-15
100%
95%
date : 20/02/2015
==> Material already in E-House DMLZ CV511
date : 23/02/2015
==> Reflector for outdoor lamp HPS 70 Watt for equipment number H15 & H17 has been installed
==> Reflector for outdoor lamp HPS 70 Watt for equipment number H16 Not yet Installed because light mounted above a
the ground so need special tools/support
0%
92%
Ready to energized
Waiting for the availability of power supply
100%
100%
100%
100%
100%
Page 40 of 69
OGRESS
ONING E-HOUSE
LZ CV 511
Progress
Remark
100%
100%
100%
100%
100%
100%
100%
0%
0%
75%
100%
100%
0%
Page 41 of 69
OGRESS
ONING E-HOUSE
LZ CV 511
Progress
Remark
100%
Total Progress
98%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
Page 42 of 69
OGRESS
ONING E-HOUSE
LZ CV 511
Progress
Remark
100%
100%
100%
100%
At the Panel J04 Phase L2, Capacitive devider p/n AMT000155-05 not yet installed.Qty 1 Unit ,Waiting delivery material from jakarta
ETA in the MP68 tgl 20-Feb-15
100%
date : 20/02/2015
==> Material already in E-House DMLZ CV511
Date 23/02/2014
Capacitive Insulator has been installed with use two bolt M10 x 20 take from GBC EBB Panel J23
100%
100%
Page 43 of 69
OGRESS
ONING E-HOUSE
LZ CV 511
Progress
Remark
100%
100%
50%
Total Progress
Page 44 of 69
OGRESS
ONING E-HOUSE
LZ CV 511
Progress
Remark
88%
100%
100%
100%
100%
100%
100%
100%
100%
0%
100%
100%
100%
100%
100%
100%
Page 45 of 69
OGRESS
ONING E-HOUSE
LZ CV 511
Progress
Remark
100%
100%
100%
100%
0%
50%
Perform Ac High Voltage and Megger test
In collaboration with Freeport Commissioning and QC Team
- Megger test has been completed
Page 46 of 69
OGRESS
ONING E-HOUSE
LZ CV 511
ort Indonesia
Progress
Remark
Wiring Scheme
Setting Parameter
REMAIN
COMMISION
DMLZ CV 511
Project Name
Contract No
Scope of supply
Customer
Periode Report
Update
No
REMAINING WORK
COMMISIONING E-HOU
DMLZ CV 511 & DMLZ CV
oject Name
ntract No
ope of supply
stomer
riode Report
date
Jobs Description
WORK
G E-HOUSE
DMLZ CV 510
Replacement Ballast Emergency, battery and Normal Ballast, wiring see attachment
Outdoor lamp has been installed but lamp is not illuminated, please check wiring and ballast
Reflector for outdoor lamp HPS 70 Watt for equipment number H16 Not yet Installed because light
mounted above a height of more than 2 meters from the ground so need special tools/support
Misising
Please pick up material from DHL
for Installation please see drawing schematic F&G DMLZ CV 511
PO080-701_02_2
Coordination with team construction DMLZ CV 510
Replacement Normal Ballast 2 x 36 watt
Replacement Ballast Emergency, battery ,wiring see attachment
Replacement Normal Ballast 2 x 36 watt
Tracing cable for correction wiring,make sure cable from panel 26-UP-0510 CKT -Q5 connected to
wiring control M01 and M02
Currently wiring control panel M01 and M02 have power supply from panel 26-P-0510B, CKT -Q25
CKT -Q25 should be for power supply heater and lamp only for panel M03