Effective Date :

Document No : MS-29-ICLF
Revision No
:A
Approved By :

PROJECT

METHOD STATEMENT FOR INSTALLATION OF


CHAIN LINK FENCE
****
(CIVIL)

AMENDMENTS
REV. NO

PAGE
NUMBER

DESCRIPTION OF AMENDMENT

APPROVED BY
(SIGNATURE)

EFFECTIVE
DATE

METHOD STATEMENT FOR INSTALLATION OF CHAIN


LINK FENCE

DESCRIPTION
Prepared by

TITLE

SIGNATURE

ENGR. PRASATH.S

Reviewed by
Approved by

ENGR. RANA ANASTAS

Page 1 of 11

DATE

Effective Date :
Document No : MS-29-ICLF
Revision No
:A
Approved By :

PROJECT
CONTENTS
1. ACTIVITY
2. INTRODUCTION
3. TERMINOLOGY
4. SIGNIFICANT HAZARDS IDENTIFIED
5. ROLES & RESPONSIBILITY AND ORGANIZATION CHART
6. SEQUENCE OF ACTIVITIES WITH RESPONSIBILITIES
6.1
6.2
6.3
6.4
6.5

Pre-commencement Requirements
General Requirements
Co-ordination with Other Trades
Delivery, Storage & Handling of Materials
Execution

7. REQUIREMENTS
7.1 Plans/Records & Job instructions (Documentations)
7.2 Training
7.3 PPE (Personal Protective Equipment)
7.4 Equipment & Tools required
7.5 Risk Assessment
8. EMERGENCY PROCEDURES
9. REFERENCES
10. ATTACHMENTS

1). ACTIVITY: INSTALLATION OF CHAIN LINK FENCE


This activity deals with the installation of chain link fence as per approved drawings and
project specifications.
2). INTRODUCTION
Page 2 of 11

Effective Date :
Document No : MS-29-ICLF
Revision No
:A
Approved By :

PROJECT
The purpose of this method statement is to describe the procedure which shall be followed for
Installation of chain link fence works to comply with schedule of finishes, the General, Architectural
& Civil Specifications for the Project and Owner / Engineer requirements.
3). TERMINOLOGY
O/E: Owner / Engineer
PPE: Personal Protective Equipment
QC: Quality Control
4). SIGNIFICANT HAZARDS IDENTIFIED

Injury to person
Wrist Pain/Stress/fatigue
Slip/trip/fall hazards
Back injury
Sharp edges
Collapse of mobile cranes
Cut Injury
Injury to Eye/Eye Irritation
Collapse of precast element
Collapse of scaffolding
Electric Shock

5). ROLES & RESPONSIBILITIES AND ORGANIZATION CHART

Project Manager (Main Contractor)


o Site construction and his team will report to project manager.

Construction Manager (Main Contractor)


o Make arrangement for availability of all relevant documents.
o Ensure the availability of necessary documents & resources available with
Subcontractor.
o Liaison with Owner/Engineer & Subcontractor in-charges for necessary test &
inspection.
o Tracks the schedule & plan work accordingly.
o Liaison with all Electrical/MEP work in-charges for all interfaces works and plans
the work accordingly at site.

Engineer (Main Contractor)


o Ensures the control at work spots in person.
Page 3 of 11

Effective Date :
Document No : MS-29-ICLF
Revision No
:A
Approved By :

PROJECT
o Verifying the percentage compliance as per risk assessment.
o Ensures the emergency preparedness of team and taking the part in Subcontractors
TBT (Tool Box Talk)
o Ensures the work carried out as per latest approved drawings.
o Ensure availability of necessary resources and approved documents.
o Inspects the incoming materials in line with approved documents.
o Ensure the quality of work/material and readiness for inspection.

Safety Officer (Main Contractor)


o Responsible for ensuring HSE at all stages of work.
o Ensures the compliance of all control measures at site as per approved risk
assessment plan.
o Ensures for all checklist as per HSE plan.

Project Manager (Subcontractor)


o Ensure that appropriate resources are provided for the safe delivery of the work

QA/QC Engineer (Subcontractor)


o
o
o
o

Ensuring quality of work carried out at site


Ensuring for inspection on hold points
Maintaining all QC records
Coordinating with O/E for inspections

Site In charge (Subcontractor)


o Ensuring the relevant document
o Plans the necessary men and material resources for timely completion and quality

Site Engineer (Subcontractor)


o
o
o
o
o
o
o

Ensuring the controls at work spot in person


Verifying the % compliance as per risk assessment.
Ensuring the emergency preparedness.
Arranging the required inspections and permit
Ensures all scaffolding erected safely and scaffolding tag system followed
Ensures availability of the necessary resources.
Ensuring availability of all activity relevant latest approved drawing and
documents

Supervisor / Foreman (Subcontractor/Supplier)


Page 4 of 11

Effective Date :
Document No : MS-29-ICLF
Revision No
:A
Approved By :

PROJECT
Obtaining the permit (if required -e.g. Steel cutting)
Conducting Tool Box Talk (TBT) based on risk assessment
Arranging for appropriate tools and necessary skilled work force as required.
Ensuring the works are carried out as per approved and latest drawing/documents
Ensuring for Housekeeping always at work place
Implementing the control measures as per risk assessment and also as mentioned in
the permit.
o Close monitoring till completion of work.
o Close the work permit after restoration of work spot.
o
o
o
o
o
o

Workmen (Subcontractor/Supplier)
o
o
o
o
o

Safety Officer (Subcontractor)


o
o
o
o
o

Wearing appropriate PPEs.


Understanding and following the instructions given by line staff.
Following the scaffolding tag system
No horseplay and shortcuts.
Informing the supervisor/foreman about any near misses, injuries and unusual

Ensures all safety measures implemented/followed as per risk assessment and HSE
Plan
Should inform the site engineer for any deviations from required
procedure/standard practice
Should conduct a safety briefing in co-ordination with site engineer/supervisor
over a specific HSE issue
Ensure all First aid cases are entered in first aid register and necessary awareness
given to the victim
Ensures for inspection of power tools and scaffoldings

Surveyor (Subcontractor)
o To check the levels, coordinates and alignments of every work activity at site.

Organization Chart (see for attachment)

6). SEQUENCE OF ACTIVITIES WITH RESPONSIBILITIES


Page 5 of 11

Effective Date :
Document No : MS-29-ICLF
Revision No
:A
Approved By :

PROJECT
6.1

6.2

Pre-commencement Requirements
Approved drawings and work procedures shall be obtained from O/E prior to the start of
activity.
Safety regulations as per specifications and standard.
All HSE activities related to the project will be based on the company issued HSE
Management System Guidelines
Area clearance obtained from other discipline / sub contractor
General Requirements

Before start of the work the following shall be ensured:

6.3

6.4

Tools, Equipment & Machinery is suitable and approved for use.


Availability of suitable quantity of approved material for the works as per specification and
O/E requirements.
Area clearance obtained from other discipline/subcontractor.
Erection of scaffolding shall be installed by certified scaffolders.
Proper erection of scaffolding shall be inspected by HSE before using.
Delivery, Storage & Handling of Materials
All materials shall comply with the specifications regarding quality, dimensions, strength etc.
The material shall be approved and shall be used as per the Approved drawings.

Execution

A) Surface Preparation

Clean the surfaces of the area where to start the installation of Chain link fence.
Installation of scaffolding for work place shall be inspected and marked by green tag prior to
use.
Layout markings including coordinates and levels shall be done by the surveyor for the
execution of work.

B) Installation/Erection of Beams and Channels

Page 6 of 11

Effective Date :
Document No : MS-29-ICLF
Revision No
:A
Approved By :

PROJECT

Prior to start of the activity, the location of intermediate / straining / corner post & temporary
gate post shall be marked all around the capacitor bank

Necessary holes shall be drilled in the marked location for fixing the posts with anchor bolts

Intermediate / straining / corner post & temporary gate post welded with base plate shall be
properly aligned over the drilled holes and shall be fixed rigidly with anchor bolts.

The door frames shall be fixed with approved hinges and screws to the gate posts.

Doors are aligned to the line, level and elevation as per the approved drawings.

The line wires shall be provided and fixed to the posts with approved accessories as per
approved drawings.

The line wires shall be strained between straining post to straining post, end post to straining
post and gate post to straining post by fixing clamps & short winders to strain the wires.

Once the line wires are strained, then it shall be secured to the posts by means of stirrup wire.

Unroll the fence fabric near the line posts and weave the end mesh to get the required length
from straining post to straining post.

Weave stretcher bars through the end mesh and secure it to the first straining / end / gate posts
(whichever is applicable). The other end of the fence fabric shall be pulled to the required
tension and then in a similar way stretcher bars shall be weaved through the mesh and secured
to the next straining post.

Once the fencing is strained between straining posts, it shall be tied to the line wire at every
300 mm centres throughout the fence line and also to the posts additionally to give maximum
reinforcement to the structure.

C) Inspection and Testing

Before steel structures erection works to be started, O/E shall be notified through inspection
request.
Page 7 of 11

Effective Date :
Document No : MS-29-ICLF
Revision No
:A
Approved By :

PROJECT

O/E comments on work shall be rectified and notified for re-inspection, if any.

7). REQUIREMENTS
7.1 Plans /Records and Job instructions (Documentations)
Before commencing the work the following things should be available:

Inspection request for materials, erection & installation


Approved drawings / Material approval for the work
Method statement for the work
Key site plan for that work area
All inspected tools & machineries
Emergency escape route without obstructions
Clearance from electro mechanical in charge

7.2 Trainings

Trained/Experienced & Skilled persons shall be used for the work


All operator / Laborers are safety trained and toolbox shall be conducted for the each potential
hazards mentioned in the Risk assessments.

7.3 PPE (Personal Protective Equipment)

Protective clothing
Protective gloves
Safety helmet
Safety goggles
Hard Gloves
Hi-visibility jacket
Flagging tape
Warning tape
Flasher light
Safety Harness (above 1.8m)

7.4 Equipment and Tools required

Manpower requirement
1.

General Supervisor/Foreman - 02 nos.


Page 8 of 11

Effective Date :
Document No : MS-29-ICLF
Revision No
:A
Approved By :

PROJECT
2.
3.
4.
5.
6.
7.
8.
9.
10.

Charge hand
Welders
Helpers
Scaffolding erectors
Crane operator
Rigger
Steel structure erector
Electrician
Surveyor

- 02 nos.
- 02 nos.
- 06 nos.
-04 nos.
-01 nos.
-01 nos.
-06 nos.
- 01 no.
- 01 No.

Equipment
1. Surveying instrument ( Level machine)
2. Hard/soft brush for cleaning
3. Electric air blower/Air compressor for cleaning
4. Vacuum machine for cleaning
5. Welding machine
6. Drilling Machine
7. Hammer
8. Measuring Tapes
9. Straight Edges /PVC Floats
10. Rigger certificate
11. Crane operator certificate
12. Crane certificate
13. Scaffolder certificate

7.5 Risk Assessment

Risk assessment to be ensured that it is available in the work spot


All control measures as per risk assessed to be implemented and ensured before start of work
All workers shall be made aware of the risk involved in carrying out the activity and
requirement of control measures during toolbox talk

8). EMERGENCY PROCEDURES

In case of any emergency situation the workmen should follow the emergency response
procedure and must gather in the assembly point. The emergency response procedure should
be conveyed to the work men through the toolbox talk in prior to the carrying out of the
activity.
The necessary safety measures will be taken to prevent the accident or injury all the times.
This may include barriers, warning tape, net, signage, watchman, flashing & rotating lights at
night.
MSDS shall be made available prior to the start of the job
Page 9 of 11

Effective Date :
Document No : MS-29-ICLF
Revision No
:A
Approved By :

PROJECT

Heat stress training will be provided during summer season.


Provision of adequate cool drinking water, shades if necessary and salt tablets will be in place.
Plants & equipment will be provided with back up lights and all other applicable safety
devices.
In case of major Injuries

Do not panic. Call ambulance and notify emergency team at site


Do not move the injured unless he is in danger
If danger exists, he shall be assessed by a trained and qualified first aider
before moving. Use a stretcher.
Do not crowd around the victim. Do not give anything to eat or drink.
Ensure adequate air and lighting.
Only trained and qualified first aider shall treat the victim and ensure that
his airway is kept clear.
Victim shall be transported to hospital in an ambulance.
Preserve the accident scene for further investigation.
In case of Fire
Follow Transco/s approved emergency procedure as per HSE Plan.

In Case of Flood
Evacuate immediately to the nearest highest location you are in.
Notify the Emergency Controller of the site

EMERGENCY CONTACT NUMBERS:


Name

Position

Phone No

Project Manager
Site Manager
Safety Officer
Fire Fighter / First
Aider
Pick Up driver
POLICE

999

AMBULANCE

998

FIRE SERVICE

997

HOSPITAL

MAFRAQ
02 5823100

Page 10 of 11

Effective Date :
Document No : MS-29-ICLF
Revision No
:A
Approved By :

PROJECT
9) REFERENCES :

10). ATTACHMENTS :

ORGANIZATION CHART
RISK ASSESSMENT SHEETS
APPROVED COPY OF CHAIN LINK FENCE & GATE
REFERENCE DRAWING

Page 11 of 11