Professional Documents
Culture Documents
Clause
2.1.1
&
2.23 (D) to
(H)
Comments of SJVN
Separate
TS
sections
have
system,
LP
air
system
thereby accepted
and
2.2.1.3
shall be clarified.
Selection of Turbine
capacity
as Accepted
2.2.2.1
this head.
Supporting documents for selecting
Accepted
2.2.2.2
be submitted.
The figure of 356 does not have any Wapcos
has
submitted
the
5.
2.2.2.6
be
356mWC
(879.75-
weighted
average
efficiency
2.2.2.7 (III)
(b) & (c)
95%.
The 343.43m3/sec is rated discharge Not agreed. The comment was that
corresponding to rated output ( 900MW)
would
in this
increase.
The
increased
2.2.2.8
dimensioning
and
equipment
layout
10.
2.2.3
2.2.3.1
2.2.4.1 &
2.2.4.2 (a)
modified as following:
The following turbine outputs and
efficiencies shall be guaranteed by
the bidders in their bids
a)
output.
b) One hundred and ten percent
(110%) output of generator at
100% (full) guide vane opening
at the minimum (rated) head.
c) Turbine efficiencies at 110%,
100%, 90%, 80%, 75% and
70%
of
the
rated
turbine
range.
At
lower
12.
2.2.4.2
13.
2.2.4.3 (1)
14.
2.2.4.4 (4)
15.
2.2.4.4 (7)
16.
2.2.5.1
17.
2.2.5.3
18.
2.2.5.4 (1)
per
be specified).
clause
1.8.7.1
are
0.33g
for
19.
2.2.6.8 (3)
20.
2.3.2.4 &
2.3.2.5
21.
2.3.6.1
22.
2.3.6.1.2
Analysis document with merit & demerits Supporting document not attached
shall be provided for selecting material
and manufacturing methodology for
Runner so that suitability at Arun-III HEP
shall be ensured.
23.
2..4.13..1
24.
2.5.3.1 (i)
25.
2.6.1.2
Supporting documents for limiting the Not agreed. The period for runaway
runaway speed test period as two (2) speed test has to be provided in the
minutes shall be provided.
specification or minimum of CEA
guidelines has to be adhered to.
Reason for selecting wicket gate closing Range to be supplied along with
time range from 0-20 seconds shall be supporting document.
supplied. It is understood that being a
hydro-mechanical item closing of wicket
gate in 0 seconds is impossible.
287.0m is design head for the machine, Ok. To be incorporated in technical
whereas static head corresponding to specification.
FRL & M/c Centre line is higher (845-525
= 320m), Therefore, discrepancy in the
value shall be clarified as it will impact the
design of MIV.
Kindly
submit
the
supporting
document along with relevant
standard.
To be changed.
29.
2.6.2 (C)
30.
2.6.2 (D)
per
clause
1.8.7.1
are
0.33g
for
31.
2.6.5.1 (d)
32.
2.6.5.16
Justification for selecting Ultrasonic flow Both methods provide for flow
detector shall be provided as winter measurement (one equipment to be
Kennedy type flow meter is also proposed provided only)
in clause 2.9.1.
33.
2.7.1
34.
2.7.7
The guide vane control through head is Ok. Same shall be incorporated.
not considered in governor as per clause
2.5.3 whereas it has been described in
this clause. Contradiction in this regard
shall be clarified.
35.
2.14.1
36.
2.16