Professional Documents
Culture Documents
1. INTRODUCTION:
A. Power System protection:
In this paper, we have designed all types of protective
relaying schemes on Matrix laboratory software using
SIMULINK utility. Simulation of under and over voltage
protection relaying for instantaneous and definite time,
Over current & coordination relaying protection, insaneness over current, over current, sample frequency, universal relay and differential protection relays using comparison digital logics have been added. Utilities are responsible for the generation, transmission, and distribution of electricity to customers. For the purpose of safety
and protecting transmission and distribution networks
from faults, utilities worldwide have sophisticated protective equipment installed on their power system equipment [1] . Similarly method of classification for adaptive
relay protection scheme/setting system based on different
analysis technique and diagnosis were being discussed
earlier [3][11] and [12].
Dr.Zahir J. Paracha
University of Lahore
zahir.paracha@live.vu.edu.au
phase are monitored and protected. The inputs are quantized because the operation of a numerical relay is processed in digital form.
START
Input port
from
instruments
NO
Functions
Time to time
comparison with
Reference Set
Values and for time
grading
YES
Signaling to
breaker
TRIP
B.
Relaying setting and action
Relay have reference values of voltage to take the action,
definite time constant for particular delay in operation
and reset pin. Programmable voltage source is used to
visualize the faults; initially it begins at time 0.2 sec with
primary delay of 0.05 sec for operation. The relay will
not be functional until the completion of definite time.
Then the DTOV will signal to breaker to trip out. The
predetermine voltage and definite time can be set for
relay operation. The operating procedure catches the
similar pattern of visual relaying simulation system [9].
C.
D.
Evaluation tests
The active mechanism of DTOV relay was methodically
investigated through collected real-time library power
system blocks (PSB) prepared with the developed simu-
TABLE I
Table: Execution Time for the Implemented DTOV Relay on Simulink
Fault
level
(RMS
values
being
shown)
Voltage
amplitude
3e 4
5e 4
*8e 4
Time
for
fault
(s)
0.1
to
0.12
0.2
to
0.5
*0.1
to
0.12
Relay
time
grading
(s)
Breaker
tripping
Trip
Value
0.05
Not
action
0.05
Action
taken
*0.05
*Not
action
* The values of input voltage source are changed for transient study.
E. Transient Testing
Transient voltages and voltage overshoots that are generated due to non-fault events or switching should not lead
to trips the relay. In order to avoid this, the relay must be
able to detect and process the information of the input
efficiently. The transient testing is performed on the implemented relay model to test the capability of the Power
System relay to detect sudden change of input voltage so
that fail-to-trip or mal-trip event is avoided. This relay is
bound to complete the time of operation.
Fig. 2.3: Scope results for analysis of voltage protection relaying action
D.
Evaluation tests
Simulation results are added for visualization of differential protection with schematic colors. The three phase
fault current out of zone is not cleared by relay, that is at
0.2 second as shown here and similar decision for higher
level faults out-of-zone.
Table 2
Execution Time for the Implemented Differential Relay on Simulink
Fig. 3.1: Simulink model of differential relay for protection of a transformer or it may be a bus bar scheme or generator to be protected
B.
Relaying Setting and action
Referring to figure 3.1, current values for both ends of
transformer (A case study) are compared. If the differential value is exceeded to prescribed value (percent differential protection) the relay operates. Simulink model is
designed for differential protection of power system [14].
The three phase fault nearest to transformer is detected
and relaying action will be taken. Breaker and both values of currents for LV and HV are regulated within the
relay subsystem.
Fault level
(RMS
values
being
shown)
0.25 e4
Time for
fault
Zone
Breaker
tripping
Trip
Value
Not action
1
0
1
(s)
0.2 to
0.25
0.35
Action
taken
*2 e5
*0.25 to
0.25
*Not action
* The values of input voltage source are changed for transient study.
C.
Simulation subsystem development
The absolute value of differential quantity from HV and
LV side is regulated with comparators and relational
operator. Then using SR latches the values is set or reset
for operation. Here fault is specified at 0.35 seconds, and
then the differential unit subsystem orders for breakout
particularly for the faults with-in the zone. We can also
make is percent differential for proper time lag. Fault out
of zone is unnoticed as in relevant case.
Fig. 3.3: Results/ outputs for currents in Scope 02 to visualize the faults
within the zone.
DTOV characteristics is that the greater the fault currents, the shorter are their operating time. Different types
of inverse characteristics such as standard inverse, very
inverse, extremely inverse and long inverse can be obtained by varying and C constants.
C.
Simulation sub-system development
Two similar sub-systems are developed with some different time constants. Both the subsystem is active and likely to be same as developed earlier for definite time over
current relays.
Fig. 4.2: Subsystem of definite time over current relay for coordination
with subsystem 01
D.
Results
The output results are shown in figure 4.3. The relaying
action taken place at 0.25 sec with 0.02 sec time lag defined by relay subsystem 01.
B.
Relaying setting and Action
The operational over current (DTOCs) relays must be in
proper coordination with time grading/discrimination of
action. For proper operation, relay sub-system 01 will
have to operate first as it is surety that the remaining
system is healthy. Symmetric ground fault occurred at
0.25 second simultaneously within the power system but
the time discrimination make the relay possible to operate
and functional nearest to load side. The time constant is
made different for proper time lag to be operational time
viz. Subsystem 01 will trip out first as its having lower
time lag value i.e., 0.02 sec (A case study is added). Simulink model is shown in fig. 4.1 for the operation of power system [16].
The DTOC relay is used as the primary scheme to protect
power systems. For DTOC characteristics, the relay starts
to operate after an intended time delay. The time delay is
also known as operation time. The advantage of the
lab and simulink are in the same atmosphere, communication and testing is comfortable and can be
done easily. Especially that matrix lab has powerful
capabilities for statistical/arithmetic strong function
and graphics. It also has powerful capabilities for
graphical user interface and modeling for protection
Table: 3
Operation Time of the Overcurrent Relay from Matlab/Simulink Simulation
Amplitude
input
current (A)
213
227
500
According to
IEC standard
Simulation from
MATLAB/Simulink
329.9419
19.2614
0.9948
329.9
19.26
0.9948
scheme simulation of generation, transmission and distribution & utilization system of electric power network etc.
These advantages help the power engineer for industry/electrical network for effective protection to enhance
the performance of digital design sequence, protective
selection and the determination of the setup.
REFERENCES
[1]
1.2
1
[2]
fault time
trip value Subsystem
trip Value Subsystem 01
0.8
0.6
[3]
0.4
0.2
[4]
[5]
-0.2
0
0.05
0.1
0.15
0.2
0.25 0.3
time axis -->
0.35
0.4
0.45
0.5
[6]
[7]
[8]
Table: 4
Execution Time for the Implemented Differential Relay on Simulink
Fault level
(RMS
values
being
shown)
0.25 e4
Time for
fault
Subsystem
Breaker
tripping
Trip
Value
Not action
Action
taken
*Not action
[9]
(s)
0.25
0.25
01
*2 e5
*0.25 to
0.25
01
* The values of input voltage source are changed for transient study.
[10]
[11]
CONCLUSION
Power System Block (PSB) tools for electrical power system network built. The fact that both matrix
[12]
[13]
[16] Gruhonjic-Ferhatbegovic, Seila, and Rinan Al-Tawil. "Application and settings inverse time relay characteristics for
feeders overcurrent protection." Electricity Distribution,
2005. CIRED 2005. 18th International Conference and Exhibition on. IET, 2005.