Professional Documents
Culture Documents
EuroProjex
rodneyturner@europrojex.co.uk
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
Project Organization
The problem of organizing
External organization
Internal organization
Responsibility charts
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
A cooperative system
individuals act rationally towards a common
EuroProjex
rodneyturner@europrojex.co.uk
Aims of organizing
jrt/epm/mar06
Achieve cooperation
Share goals
Act rationally
EuroProjex
rodneyturner@europrojex.co.uk
Achieving cooperation
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
Crafting cooperation
Design of
Organization
Assumptions
about People
Shaping
Social Norms
Legitimization
of Behaviour
Common
Language
Desired
Behaviour
Delegitimization
of Others
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
Crafting cooperation
Assumptions
Development
Cooperation
Trust
Legitimization
Friendship
Trust
Cooperation
Norms
Conversation
Cooperation
Development
Language
Trust
Communication
We not I
Behaviour
Delegitimization
SelfSelf-promotion
Competition
Aggressiveness
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
Benefit
Value to
Owner
Facility/Asset
Output
Price
Value to
Contractor
Project
Work
Cost
Contractor
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
Objectives
Optimum solution
Value for money
Finance
Contract between
Owner and
Contractor
Sponsor
Resources
Results
Manager
Team Ldrs
Contractor
jrt/epm/mar06
ContractEuroProjex
between
parties involved
Objectives
Maximum profit
Satisfied client
rodneyturner@europrojex.co.uk
Two contracts
External
Organization
Milestone Plan
Responsibility Chart
Specify results
throughout the project
Report on a copy
of the plan
Organization
Procedures
Priorities
Schedule
Activity
list
Progress
report
Response
Chart
Bar
Chart
Contract
between project
management
and corporate
management
Contract
between project
participants
EuroProjex
jrt/epm/mar06
rodneyturner@europrojex.co.uk
Two decisions
External organization
relationship project to parent organization
managerial responsibility and authority
Internal organization
relationship of the participants to the task
leadership style of the project manager
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
Project Organization
The problem of organizing
External organization
Internal organization
Responsibility charts
EuroProjex
jrt/epm/mar06
rodneyturner@europrojex.co.uk
Secondment
Matrix
Functional
Hierarchy
Project
Hierarchy
EuroProjex
Project organization
Company
Dept A
Permanent
Structures
Dept B
Temporary
Structures
jrt/epm/mar06
Dept C
EuroProjex
Projects
Dept
rodneyturner@europrojex.co.uk
Dept A
Dept B
Dept C
Projects
Dept
Small
Project
Permanent
Structures
jrt/epm/mar06
Temporary
Structures
EuroProjex
rodneyturner@europrojex.co.uk
Dept A
Dept B
Projects
Dept
Dept C
Small
Project
Large
Project
Permanent
Structures
Temporary
Structures
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
Dept A
Dept B
Dept C
Projects
Dept
Small
Project
Large
Project
Mixed
Work Pack
Permanent
Structures
jrt/epm/mar06
Temporary
Structures
People seconded
for duration of
their involvement
EuroProjex
rodneyturner@europrojex.co.uk
Dept A
Dept B
Small
Project
Dept C
Projects
Dept
Single
Work Pack
Project Manager
gives work to
Functional Manager
to resource
Large
Project
Mixed
Work Pack
Permanent
Structures
Temporary
Structures
jrt/epm/mar06
People seconded
for duration of
their involvement
EuroProjex
rodneyturner@europrojex.co.uk
Development projects
Goals not well defined
Users involved
Implementation projects
Goals well defined
Users not involved
jrt/epm/mar06
Functional
hierachy
Coordinated
EuroProjexBalanced
matrix
matrix
Project
Secondment
rodneyturner@europrojex.co.uk
matrix
hierarchy
Project Organization
The problem of organizing
External organization
Internal organization
Responsibility charts
EuroProjex
jrt/epm/mar06
rodneyturner@europrojex.co.uk
Leadership styles
Involvement of Team in
Decision Making Decision Taking
Flexibility
LaissezLaissez-Faire
High
High
High
Democratic
High
Low
High
Autocratic
Low
Low
High
Bureaucratic
Low
Low
Low
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
Isomorphic structures
Stage
Feasibility
Design
Execution
Close
jrt/epm/mar06
Structure
Egoless
Matrix
Hierarchy
Surgical
Leadership
Laissez-faire
Democratic
Autocratic
Bureaucratic
EuroProjex
Team
Experts
Mixed
Task
Task force
rodneyturner@europrojex.co.uk
Internal structures
jrt/epm/mar06
Isomorphic
Egoless
Speciality, (matrix)
Task
Surgical
EuroProjex
rodneyturner@europrojex.co.uk
Project work
Task 2
Task 1
Specialist 1
Project team
Task 3
Specialist 2
Manager
Specialist 3
EuroProjex
jrt/epm/mar06
rodneyturner@europrojex.co.uk
Project work
Task 1
Task 2
Task 3
Specialist 2
Project team
Specialist 3
Specialist 1
Manager
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
Project work
Task 1
Task 2
Task 3
Project team
Team 1
Team 2
Team 3
Manager
EuroProjex
jrt/epm/mar06
rodneyturner@europrojex.co.uk
Project work
Task 1
Task 2
Task 3
Manager
Specialist 2
Project team
jrt/epm/mar06
Specialist 1
EuroProjex
Specialist 3
rodneyturner@europrojex.co.uk
Project Organization
The problem of organizing
External organization
Internal organization
Responsibility charts
EuroProjex
jrt/epm/mar06
rodneyturner@europrojex.co.uk
Responsibility chart
OBS
Companies/Departments/Functions
Resources/People
PBS
Milestones
Activity/Task
jrt/epm/mar06
WBS
Roles/Responsibilities
EuroProjex
rodneyturner@europrojex.co.uk
Symbols
jrt/epm/mar06
manages Progress
must be Consulted
must be Informed
available to Advise
EuroProjex
rodneyturner@europrojex.co.uk
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
jrt/epm/mar06
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
rodneyturner@europrojex.co.uk
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk