You are on page 1of 27

20/04/2015

Project Management
Cost Estimating
Prof. Mauro Mancini

e-mail: Mauro.Mancini@polimi.it
tel.: +39-02-23994057
POLITECNICO DI MILANO
Department of Management, Economics and Industrial Engineering

Cost Estimating
The project’s costs management evolves during the
whole project life cycle and can be distinguished in
three phases:

1. Estimating
2. Cost control
3. Estimate to finish

1
20/04/2015

Estimates’ Accuracy
The cost estimating’ accuracy is connected to:

•Project’s phase (labour portion not yet performed)

•Level of the engineering progress (required


resources definition)

•Reliability for the cost data available (database of


historical data availability)

Estimates’ Accuracy

Estimate’s
error

Project Life Cycle t

2
20/04/2015

Cost estimating levels


Different cost estimating levels correspond to
different grades of belief:

• Ball Park estimate (preliminary information to the


customer)

• Semi-analytic estimate (feasibility study)

• Analytic estimate (proposal)

Cost estimating levels


Increasing the cost estimating levels the estimate’s
cost exponentially increases in terms of:

•Resources allocated

•Time requested

From few hours for the lower level to:

•5-10% of the total project engineering’s hours


•1-2% of the whole investment cost

3
20/04/2015

Cost estimating techniques


At different cost estimating levels correspond two
cost estimating techniques:

• Parametric (cost driver)

• Analytic (cost = quantity x unit cost)

Ball Park Estimate


The Ball Park estimate (also called order of
magnitude) presupposes well-known:

•Plant typology

•Plant Size

•The whole cost for same type plants

4
20/04/2015

Ball Park Estimate – Scale Factor


On the basis of the previous information, the scale
factor is used in the following equation:
M
P
C  C0   
 P0 
C = Cost estimate for the new plant
C0 = Historical cost for the plant in the database
P = New Plant size
P0 = Historical plant size
M = Scale factor (0.6 < M < 0.9)

Ball Park Estimate – Scale Factor

€/MWe
Validity Zone

MWe

10

5
20/04/2015

Ball Park Estimate – Scale Factor

Economy of scale
1,6

1,5

1,4

M
[$/kWe]

1,3

1,2

1,1

0,9
200 400 600 800 1000 1200
[MWe]

11

Ball Park Estimate – Scale Factor


M M M
 P  C  P C    P 
C  C 0      log 
    log 
 
 P0  C 0  C 0 
 P0   P0 
 C 
log  
 C   P   C 0 
 log    M log    M 
 C 0   P0   P 
log  
 P0 

 log C  log C 0  M (log P  log P 0 )
 log C  M log P  M log P 0  log C 0

 log C  M log P  log C 0  M log P 0 


C 0
 log C  M log P  log
P 0M

y  M  x  q

12

6
20/04/2015

Ball Park Estimate – Scale Factor


Bi-logarithmic axis
C
100

10

10 100
P

13

Ball Park Estimate – Scale Factor


Example: Values for a Nuclear Power Plant
ACCOUNT Scale exponent
Direct costs
Land and land rights 0
Structures and improvements 0.5
Reactor/boiler plant equipment 0.6
Turbine plant equipment 0.8
Electric plant equipment 0.4
Miscellaneous plant equipment 0.3
Main condenser heat rejection system 0.8
Indirect costs
Construction services 0.45
Home office engineering and services 0.2
Field office engineering and services 0.4
Owner's costs 0.5

14

7
20/04/2015

Ball Park Estimate – Scale Factor


The Ball Park estimate accuracy increase more:

• P is close to P0
• The historical data is recent

If data for the same Plant type are not available, is


possible to divide the plant in its components.

15

Ball Park Estimate – Corrective Factors


It is necessary considering also:

• Location Factor (LF): Per cent whole plant cost


variation connected to the specific environmental
conditions presents where the plat is build
• Escalation Factor (EF): index summarizing the
temporal cost trend for the resource used to build
the plant

16

8
20/04/2015

Ball Park Estimate – Corrective Factors


Example 1

New plant (1986)


•Size: 75.000 T/Y
•Location: Saudi Arabia

Reference plant (1974)


•Size: 90.000 T/Y
•Location: Italy
•Cost: 14 M€ (without draining purification plant)

Scale Factor: 0.6


Escalation Factor: 1113.3 / 263.9 = 4.22
Location factor: 2.3 / 2 = 1.15

17

Ball Park Estimate – Corrective Factors


Example 1

DESCRIPTION COST

Plant build in the 1986 14 x 4.22= 59.08 M€


0 .6
 75 
59.08     52.96 M€
Size reduction:  90 

Draining purification plant (estimate): 7 M€

Total plant cost build in Italy: 52.96 + 7 = 59.96 M€


Total p. c. build in Saudi Arabia: 59.96 x 1,15 = 68.95 M€

18

9
20/04/2015

Ball Park Estimate – Corrective Factors


Example 2
It is necessary to estimate the plant cost calculated
with a scale factor equal to 25 M€ and characterized
by the following breakdown:

Escalation Factors

15% engineering 5% annual


50% materials 10% annual
25% construction 8% annual
10% subcontractors 4% annual

19

Ball Park Estimate – Corrective Factors


Example 2
0 12 16 20 24 30 38
months

The Barycentre method is usually used


20

10
20/04/2015

Ball Park Estimate – Corrective Factors


Example 2
Barycentre calculation

I 12 + 6= 18 months = 1.5 years


M 12 + 4 + 7 = 23 months = 1.92 years
C 12 + 8 + 12*= 32 months = 2.6 years
S 12 + 8 + 12*= 32 months = 2.6 years
* For this phases the barycentre is usually placed at 2/3
Cost Calculation:
I 25 • 0.15 • (1 + 0.05)1.5 = 4.03
M 25 • 0.5 • (1 + 0.1)1.92 = 15.01
C 25 • 0.25 • (1 + 0.08)2.6 = 4.03
S 25 • 0.1 • (1 + 0.04)2.6 = 2.77
25.84 Ml€
21

Fixed Rate of Interest

0 1 2 3 … n Time
[years]
P
T0  S0 = P
T1  S1 = P + i x P = P(1+i)1
T2  S2 = (P + i x P) + i (P + i x P) =
= (P + i x P) (1 + i) = P(1+i) (1+i) = P (1+i)2
T3  S3 = P (1+i)2 + i (P (1+i)2) = P(1+i) (1+i)2 = P (1+i)3

Tn Sn = P (1+i)n
22

11
20/04/2015

Factorial Estimate
It is used to:
• Estimate using the comparison of the different
design choices
• Perform feasibility studies
• Estimate the stock in hand allocation (budget)

It is based on the cost breakdown and considers:


• Analytic cost items estimate
• Other costs estimate by per cent factors

23

Factorial Estimate

Equipment Cost ( E )

Fb Bulk factor (40 - 100 % of E)


Materials Cost ( M )

Fc Construction factor (50 - 80% of M)


Erected Cost ( M + L )

Fs Services factor (15 - 30 % of M + L)


Total Base Cost ( BC )

Fk Markup factor (10 - 20 % of BC)


Total Investment Cost ( TIC )

24

12
20/04/2015

Factorial Estimate
The Mark – up factor considers:

•Escalation
•Contingencies
•Overheads
•Financial costs
•Insurances
•Guarantees
•Taxes
•Exchanges
•Profits

25

Analytic Estimate
It is the cost estimate for each account in the
breakdown cost:

•Engineering
•Materials
•Transport
•Construction
•Supervision
•…

+ Mark up (in order to determinate the cost)

26

13
20/04/2015

Analytic Estimate
For each account it is necessary to point out the
single resources allocated (quantity x unit cost)

• Labour
• Material
• Means of production
• Services

27

Analytic Estimate - Design


It consists in the accounts relative to the base and
detail engineering.

The project cost on the whole plant cost is a very


variable component and depends on the plant type
and size.

28

14
20/04/2015

Analytic Estimate - Materials


It is possible to distinguish:

• Items

• Bulk materials (piping, instrumentation, electrical


material, metallic structures etc.)

•Various material (Spear parts, catalysts)

29

Analytic Estimate – Materials

ITEMS

They are evaluated one by one, according to


statistical data about orders, demands, supplies
etc.
The principal analysis instruments are the cost
curves. They show the recent orders costs
correlated to ad hoc parameters (weight, surface,
power…)
Curves represent the most effective market
situation synthesis

30

15
20/04/2015

Analytic Estimate – Materials


CRITICAL ACCOUNTS

Items estimates usually characterized by the major


evaluation risks are:

•Special apparatus (having special material or


processing)
•Big compressors and ovens
•Special valves and piping special materials
•Piping quantity and weight
•Specific features requested by the customer

31

Analytic Estimate – Materials


BULK MATERIALS

Is made using the “material take-off”, that is the


estimate quantity of the technical documents
requested by the engineering. It can be manual or
computerized.

The piping account is not the more expensive, but


imply the greatest part of assembly labour.

32

16
20/04/2015

Analytic Estimate – Transport


It includes the following accounts:

•PACKING: like percentage of materials costs


•TRANSPORTS: special (unit price)
normal (€/Kg)
The local transportation could be very risky
and difficult to evaluate:

•INSURANCE: percentage of the material and


transport cost
•CUSTOMS AND PORT FEES

33

Analytic Estimate – Construction


It is the cost component with major uncertainty and
evaluation risks, particularly for plants in foreign
countries:

Two, not alternative, ways are available:

•Market research through preliminary subcontractor


proposal

•Internal evaluation through:


oStandard Man Hours (SMh)
oEffective Man Hours Estimated (EMh)
34

17
20/04/2015

Analytic Estimate – Construction


INTERNAL EVALUATION

Is based on the ideas of:


Q
Yield: Y 
SMh
SMh
Productivity: P 
EMh
Where:
Q = Physical quantities
SMh = Standard Man hour
EMh = Effective Man hour
35

Analytic Estimate

36

18
20/04/2015

Analytic Estimate

37

Analytic Estimate - Supervision


It is the labour cost associated to the staff sent in
the site for the technical supervision and to manage
the project during the construction.

From the organization chart and the permanence


time is calculated the total men/months necessary,
and it is multiplied by:

• standard cost for the internal staff


• travelling allowance, board and accommodation
• other fees

38

19
20/04/2015

Analytic Estimate - Contingency


It includes the major cost for:

• Project indeterminateness and incompleteness


• Costs’ uncertain grade
• Delays
• Forgetfulness and estimate’s errors
• Unexpected and incidental facts
• etc.

39

Analytic Estimate - Contingency


It not includes great risk from:

•Socio-economical upheaval, wars and revolutions

•Geothermic surprises

•Legislations changes

•Supplier bankruptcy

•Failure to pay

40

20
20/04/2015

Cost Trends
(Annual Averages)
• Asphalt
– Jan-Dec 2003 $53.93/ton
– Jan-Dec 2005 $77.66/ton
• Concrete (Structural) 44.0%
– Jan-Dec 2003 $549.82/CY
– Jan-Dec 2005 $761.71/CY
• Steel (Reinforcing) 38.5%
– Jan-Dec 2003 $.52/LB
– Jan-Dec 2005 $0.91/LB
75.0%

Figures based on Weighted Averages

Rising Asphalt Costs


by Quarter

$85.38

$51.60
+20.1%

21
20/04/2015

Rising Concrete Costs


by Quarter

$1,045.14

$490.02
+64.2%

Rising Steel Costs


by Quarter

$1.28

$0.53
+48.8%

22
20/04/2015

Causes for Major Cost Increases


• Construction market saturation:
– “Hot” Market, both public and private
sector
– Labor and equipment shortages, due to
hurricane recovery efforts
– Material shortages
• Fuel cost increases
• Project requirements:
– Hours of operation
– Night work
– Delayed start

Creating the Estimate


Finally, once you determine the technique to use in
creating your estimates, it is time to actually create
them.
In this step, you will pull together your project
team and ask them to determine the estimate. You
can apply more precision to your estimates by doing
the following:

• Have the person doing the work create the


estimate.
• Use task information from other projects.
• Use the PERT technique
46

23
20/04/2015

An Example
TPMP has just placed you at the Pinnacle Candy Company as
a temporary project manager. You have been assigned the
EspressoFix Bar project. This project is going to create a new
candy that will satisfy every coffee addict’s need for coffee
all wrapped up in a candy bar. The management at Pinnacle
only wants to see if this new candy bar is marketable.
Production of the finished product will be another project
initiated later. The budget of $100,000 was established
before you started work on the project. You are just about
done with the project planning and wonder whether
$100,000 will be enough money to cover the project. Your
team has already created the WBS with duration estimates
illustrated, the network diagram, and effort estimates shown
in the next slides.

47

Effort Estimates for the Espresso Fix Project

Effort
Task Resource Rate
Estimate
Market surveys Marketing 20 days $1,200 per day
Marketing plan Marketing 25 days $1,200 per day
Ad campaign Advertising 10 days $1,000 per day
Legal clearance on
Legal 10 days $1,600 per day
the name
Chef 7 days $800 per day
Create recipe
Test kitchen 15 days $1,000 per day
Chef 6 days $800 per day
Create product
Test kitchen 10 days $1,000 per day
Employees on break 0
Internal taste testing
Employee cafeteria 0
Firm fixed
Focus group taste testing $50,000
price contract

48

24
20/04/2015

WBS with duration estimates

49

Network diagram

50

25
20/04/2015

Questions

1. How long is this project?

2. What is the cost baseline? Why?

51

Answers

1. This is a 90-day project

2. The cost baseline is the total project budget minus the


managerial reserve. Since this project does not have a
managerial reserve, the cost baseline is $165,400.

52

26
20/04/2015

Cost Estimate form: a real case

Best practices…

27

You might also like