Professional Documents
Culture Documents
Page
Section 1
3
3
3
4
5
7
Table 1.1
10
12
1.1
1.2
1.3
1.4
1.5
1.6
2.1
Design Overview
2.2
2.3
11
12
15
16
16
2.1.1 Classification by Biological Treatment
Processes
15
16
20
20
23
23
24
25
Table 2.1
Section 3
3.1
3.2
16
Introduction
29
29
29
29
3.3
3.4
30
30
31
32
3.5
Table 3.1
Section 4
Table 3.2
4.1
4.2
4.3
4.4
ii
31
30
32
32
33
33
34
30
31
Introduction
37
37
37
39
39
40
40
40
40
41
42
42
42
42
43
43
43
4.5
53
4.5.2 Vibration
54
4.5.3 Noise
Systems (SCADA)
53
54
55
55
57
58
59
60
62
64
65
67
4.6
Table 4.1
Table 4.3
Table 4.2
Table 4.4
Table 4.5
Table 4.6
4.5.13 Instrumentation
65
68
69
69
70
70
70
72
74
76
77
40
44
45
45
46
47
iii
Figure 4.1
Figure 4.2
Figure 4.4
Figure 4.3
Figure 4.5
Section 5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
iv
50
52
51
57
Introduction
81
84
84
84
85
86
91
91
91
95
100
100
100
101
101
102
103
105
105
105
106
106
106
108
108
109
111
114
116
5.8.6 Sequencing Batch Reactors (SBR) System
117
5.8.7 Design Requirements for Hybrid Systems
120
5.8.8 Design for Nutrient Removal for Sensitive
120
Receiving Water
5.9
Design of Secondary Clarifiers
122
5.9.1 Purpose
122
5.9.2 Design Requirements
122
5.9.3 Multiple Hoppers
123
5.10
Disinfection
125
5.10.1 Design Requirements
126
5.11
Design of Flow Measurement Devices
130
5.11.1 Purpose of Flow Measuring Devices
135
5.11.2 Design Requirements for Flow Devices
135
5.12
Sludge Holding, Treatment and Disposal
136
5.12.1 Introduction
136
5.12.2 Sludge Strategy in General
137
5.12.3 Provision of Sludge Holding, Treatment and Disposal 138
5.12.4 Design Criteria
139
5.13
Tertiary Treatment
144
5.13.1 Introduction
144
5.13.2 Design Requirement
144
Table 5.1
Table 5.2
Table 5.3
Table 5.4
Table 5.5
Table 5.6
Table 5.7
Table 5.8
Table 5.9
Table 5.10
Table 5.11
Table 5.12
Table 5.13
Table 5.14
84
85
86
99
100
101
103
103
104
106
108
110
111
112
v
Table 5.15
Table 5.16
Table 5.17
Table 5.18
Table 5.20
Table 5.19
Table 5.21
Table 5.22
Table 5.23
Table 5.24
Table 5.25
Table 5.26
Table 5.27
Figure 5.1
Figure 5.2
Figure 5.3
Figure 5.4
Figure 5.5
Figure 5.6
Figure 5.7
Figure 5.9
Figure 5.8
117
120
126
124
130
133
134
135
136
139
140
141
82
83
85
88
89
90
94
93
97
98
113
116
Figure 5.15 Typical Process Flow Diagram for Biological Nutrient
Removal System
Figure 5.16 Schematic illustration of ultraviolet disinfection system
with stilling plate for flow conditioning and elongated
weir for level control
vi
119
114
119
121
126
Figure 5.17 Profile schematic of lamp modules relative to inlet and
outlet structure
Figure 5.19 Chemical-feed system schematic
127
146
Section 6
Figure 5.21 Typical Roof Details for Covered Sludge Drying Bed
6.1
6.3
6.2
6.4
6.5
6.6
6.7
6.8
6.10
6.12
6.14
6.9
6.11
6.13
6.15
6.16
6.17
6.18
6.19
6.20
6.21
6.22
6.23
6.24
Table 6.1
Table 6.2
Table 6.3
127
143
Introduction
149
150
Yard Lighting
Sampling Facilities
Fire Hydrant
Power Supply
Process Water
Aesthetic
Close Turfing
Painting
149
152
153
154
159
159
159
161
162
162
163
163
163
164
164
164
165
168
168
168
168
169
161
vii
Table 6.4
167
Figure 6.1
151
Table 6.5
Figure 6.2
Figure 6.3
Figure 6.4
Figure 6.5
Figure 6.6
Figure 6.7
Figure 6.8
Figure 6.9
Masonry Fencing
7.1
170
152
152
152
155
156
157
158
162
171
172
172
Special Requirements
Temporary Treatment Plants
175
7.1.2 Category 1: Temporary Treatment Plant for
Upgrading of Facilities
175
7.2
7.3
7.4
7.1.1 Definition
176
7.2.1 Introduction
172
179
180
7.4.3 Specific Requirements for Covered or Buried
Plants under 5,000 PE or Less
viii
175
181
185
185
186
194
194
194
194
7.5
7.5.1 Single Developments up to 30 Units or 150
PE in Total
197
197
197
7.5.3 Single Developments Over 30 Units in Total with
Average Housing Density Less Than Five Units
per Hectare
197
198
7.6.2 Types of Incidents that Can Cause Treatment
Plant Failure
198
198
7.6
7.7
7.8
Section 8
8.1
8.3
8.2
8.4
7.6.1 Introduction
Energy Saving
201
201
Definition
205
Design Requirement
206
8.4.1 Layout, Piping and Arrangement of Prefabricated
Biological Treatment System
205
206
206
206
Appurtenances
208
8.5
8.6
207
208
209
210
210
210
211
211
211
212
212
ix
Table 8.1
206
209
Table 8.2
Table 8.3
Table 8.4
207
210
Appendices
Appendix A Table
Table A1
Table A2
Table A3
Table A4
Table A6
Table A5
Table A7
Table A8
216
218
217
221
223
Appendix B References
222
224
Malaysian Standards
227
European Standard
229
British Standard
ASTM Standard
AS Standard
228
231
232
232
232
C-1
Introduction: Overview
237
C-3
General Requirements
238
C-2
C-4
C-5
C-6
C-7
C-8
C-9
C-10
C-11
C-12
C-13
Purpose
Architecture
SCADA Requirement
Operator Interface
Database
Alarm/Event Management
Historian
Graphical Trending
Report Format
Security
Scripting
238
238
239
240
241
241
243
243
244
244
245
xi
C-14
Interfaces
245
C-16
Web Server
245
C-15
245
C-17
246
C-19
Application Report
247
C-18
C-20
C-21
C-22
246
247
248
248
268
Table D.3
270
Table D.2
Table D.4
269
xii
Glossary of Abbreviations
275
Section 1
Introduction and General
Planning Requirements
Volume 4
Malaysian Sewerage
Industry Guidelines
1.1
The owner must comply with the requirements set out in this volume
when submitting an application for approval to the Commissioner.
This volume does not cover any aspect other than Sewage Treatment
Plant requirements. All internal plumbing approvals need to be approved
by Local Authorities.
1.2
1.3
Volume 4
1.4
d)
e)
f)
g)
h)
i)
j)
k)
l)
Sufficient land area for the sewage treatment plants plus additional
area to allow for extensions to the plant, where necessary.
Land of suitable configuration shall be provided.
Sufficient buffer zones.
Volume 4
Malaysian Sewerage
Industry Guidelines
m)
n)
o)
p)
q)
r)
s)
t)
u)
v)
w)
x)
z)
y)
aa)
1.5
Volume 4
d)
e)
f)
g)
h)
Population Equivalent
(Recommended))
Residential
5 per house
Commercial:
- Partial residential
- Fully residential
1 per student
Hospitals
4 per bed
4 per room
3 per stall
1 per stall
15 per toilet
Bus terminal
Taxi terminal
Volume 4
Malaysian Sewerage
Industry Guidelines
Population Equivalent
(Recommended)
Stadium
Public toilet
15 per toilet
Airport
Laundry
10 per machine
Prison
Golf course
(Ref: Malaysian Standard 1228)
1.6
1 per person
20 per hole
d)
e)
Site layout plans showing all the process units, main pipe runs,
electrical conduit corridors, site services (water, drains, lighting,
other services), roads and paving, landscaping, buildings, fencing
and finished level contours (or spot levels). The set out and
overall dimensions of the plant shall also be shown.
Volume 4
f)
g)
h)
i)
j)
Volume 4
Malaysian Sewerage
Industry Guidelines
Volume 4
Volume 4
0.2m
0.4m
0.6m
0.8m
1.0m
1.2m
1.4m
1.6m
1.8m
2.0m
F.G.L.
-0.6M
PRIMARY PUMPING VALVE
SCREEN STATION CHAMBER
-0.4m
-0.2m
FGL
F.F.L.
I.L.
F.G.L.
SECONDARY SCREEN
SECONDARY SCREEN
F.G.L.
CL
I.L.
AERATION TANK
AERATION TANK
TWL
CL
I.L.
TWL
TWL
F.G.L.
CLARIFIER DISTRIBUTION
CHAMBER
CLARIFIER DISTRIBUTION
CHAMBER
F.G.L.
HYDRAULIC PROFILE
I.L.
CLARIFIERS
CLARIFIERS
TWL
TWL
TWL
TWL
F.G.L.
NOTES :
OUTFALL MEASUREMENT
FLUME
CHLORINE CONTACT
TANK
OUTFALL MEASUREMENT
FLUME
CHLORINE CONTACT
TANK
F.G.L.
Page 7
10
Volume 4
Malaysian Sewerage
Industry Guidelines
Volume 4
Volume 4
Pump
Pump
Raw Sewage
Raw Sewage
Screen
RAW SEWAGE
SS =
BOD =
Q=
RAW SEWAGE M
SS =
BOD =
Q=
RAW SEWAGE
SS =
BOD =
Q=
Screen
Filtrate =
SCREEN CHAMBER
Filtrate =
=
=
Q
BOD
Skimmer
Water =
=
=
=
Q
BOD
SS
Transfer Pump
GREASE CHAMBER
Grit Pump
Grit Classifier
Vortex
SS
BOD =
GRIT CHAMBER
Mixer
Pump
Balancing
BALANCING TANK
=
=
=
Q
BOD
SS
=
=
Q
BOD
SS
MLSS =
Aerator
Supernatant Decanter
REACTOR
SEQUENCING BATCH
=
=
=
Q
BOD
SS
HOLDING TANK
SLUDGE
Pump
Waste Sludge
TANK
MEASURING
SS
BOD
BLOWER
11
QiQi= =
BOD= =
BOD
SS= =
SS
Qi ++ Qr
Qr ++ Qw
Qw
QQ == Qi
BOD ==
BOD
SS ==
SS
Qe
Qe ==
BOD
BOD ==
SS
SS ==
SECONDARY
SECONDARY CLARIFIER
CLARIFIER
AERATIONTANK
TANK
AERATION
MLSS= =
MLSS
OUTLET
OUTLET
OVERFLOW
OVERFLOW SS
SS CONC
CONC==
BOD
BOD ==
Qr
Qr++Qw
Qw==
BOD =
BOD =
SS =
SS =
Qr, Xr
Qr,
Xr
Qr = X Qi =
Qr = X
BOD
= Qi =
BOD
=
SS =
SS =
AEROBIC DIGESTED
AEROBIC DIGESTED
SLUDGE HOLDING TANK
SLUDGE HOLDING TANK
Qw =
Qw ==
BOD
BOD
SS ==
SS ==
1%DS
1%DS =
SLUDGE THICKENER
SLUDGE THICKENER
Qw =
BOD
Qw ==
SS ==
BOD
4%DS
SS =
4%DS =
Qw OVERFLOW =
Qw OVERFLOW =
SPARE
SPARE
24T
24T
20A
20A
0 -3 0 A
0 -5 0 0 V
0 -3 0 A
3 0 A T P + N 1 0SK/s
AwM C C B
4 0 /0 .3 A 4 p R C C B
10A
0 -5 0 0 V
10A
S /s w
S /s w
4 0 /0 .3 A 4 p R C C B
20A
3x5A
B
6A
R SY/s wB
20A
RAW SEWAGE
SUBMERSIBLE
RAW SEWAGE
SUBMERSIBLE
PUMP PUMP
NO.2 (2.4kW)
Using
4c x 2.5mm
ARM Cable
NO.2 (2.4kW)
Using 4c
x 2.5mm
ARM Cable
TO CONTROL
CIRCUIT
TO CONTROL
CIRCUIT
2 x sq.
1.5mm
Using 2 Using
x 1.5mm
PVCsq. PVC
R
3x5A
0 -4 0 A
S /s w 0 -5 0 0 V
S /s w
PSR P HA SE S EQ UENC E
R E L A Y0 -4 0 A
S /s w
4 0 /0 .3 A 4 p R C C B
PSR P HA SE S EQ UENC E
R E LA Y
40A TP N 10KA M C C B
4 0 /0 .3 A 4 p R C C B
3x5A
D IS T R IB U T IO N B O X F O R
L IG H T IN G A N D P O W E R
D IS T R IB U T IO N B O X F O R
L IG H T IN G A N D P O W E R
6A
0 -5 0 0 V
TOR
TOR
w
YS /sB
TPN20A TPN20A
TOR
MCB
MCB
DOL
DOL
A
A
TPN20A TPN20A
TOR
MCB
MCB
DOL
DOL
A
A
SPN6A SPN6A
MCB
MCB
13A Socket
Outlet Outlet
13A Socket
Using 2Using
x 2.5mm
sq. PVCsq. PVC
2 x 2.5mm
To Control Circuit
To Control Circuit
E. STOP
x 1.5mm sq. PVC
E. STOP Using 2Using
2 x 1.5mm sq. PVC
3x5A
PSR
6A SPN
SPN
MCB 6APSR
MCB
TOR
16A TPN
TOR
TPN
MCB 16A
DOL
MCB
DOL
TOR
TOR
20A TPN
TOR
MCB 20A
TPN
DOL
MCB
DOL
20A TPN
TOR
MCB 20A
DOL
TPN
MCB
DOL
TOR
16A TPN
TOR
TPN
MCB 16A
DOL
MCB
DOL
M O T O R S E .Q P U M P S A N D S S T P U M P
RAW SEWAGE
SUBMERSIBRE
PUMP PUMP
RAW SEWAGE
SUBMERSIBRE
NO.1 (2.4kW)
Using
4c x 2.5mm
ARM Cable
NO.1 (2.4kW)
Using 4c
x 2.5mm
ARM Cable
S IN G L E L IN E L A Y O U T D IA G R A M F O R
R A W S E W A G E S U B M E R S IB L E P U M P
S IN G L E L IN E L A Y O U T D IA G R A M F O R
R A W S E W A G E S U B M E R S IB L E P U M P
S IN G L E L IN E L A Y O U T D IA G R A M F O R A IR B L O W E R
M O T O R S E .Q P U M P S A N D S S T P U M P
S IN G L E L IN E L A Y O U T D IA G R A M F O R A IR B L O W E R
4 0 /0 .1 A
2P R CCB
S P +N 30K A
1 04 0K/0
A .1
MAC C B
2P R CCB
U S IN G 4 C x 1 6 m m P V C /S W A P V C A R M . C A B L E
U S IN G 4 C x 1 0 m m P V C /S W A /P V C A R M . C A B L E
U S IN G 2 C x 6 m
E m P V C /S W A /P V C A R M . C A B L E
S P +N 30K A
40A TP N 10KA M C C B
30A TP +N 10KA M C C B
10 KA M CCB
40A TP+N
30A TP +N
30A SP+N
U S IN G 4 C x 1 6 m m P V C /S W A P V C A R M . C AMBCL C
EB
U S IN G 4 C x 1 0 m m P V C /S W A /P V C A R M . CMACBCLB
E
U S IN G 2 C x 6 m m P V C /S W A /P V C A R M .MCCAC
BB
LE
R
40A TP+N
MCCB
6A
3 x 6 0 /5 A
3 x 6 0 /5 A
0 -50 0V
R
6A
PSR
V .s .s w
Y B
30A TP +N
MCCB
30A SP+N
MCCB
0 -6 0 A
V .s .s w
0 -50 0V
V .s
wS E S E Q U E N C E
P .s
HA
R E L A Y 0 -6 0 A
.sC
wB
6 3 /0 .3 A 4 pV .s
RC
PSR PHASE SEQUENCE
6 0 A T P + N 2R5EKLAA Y
(4 P O L E ) M C C B
6 3 /0 .3 A 4 p R C C B
6 0 A T P + N 2 5 K A (4 P O L E ) M C C B
415 V S U P P LY
3 PHASE
T N B M E T E R IN G
PANEL
M U L T IC O R E A R M O U R E D
C ABLE TO
T N B R E Q U IM E N T
415 V S U P P LY
3 PHASE
S IN G L E L IN E L A Y O U T D IA G R A M F O R
M A IN S W IT C H B O A R D
S IN G L E L IN E L A Y O U T D IA G R A M F O R
M A IN S W IT C H B O A R D
T N B M E T E R IN G
PANEL
M U L T IC O R E A R M O U R E D
OR O M
IN C O M IN G S C
U APBPLLEYT F
T N B R E Q U IM E N T
M A IN D B 4 1 5 V
IN C O M IN G S U P P L Y F R O M
M A IN D B 4 1 5 V
12
10
10
Volume 4
Volume 4
Volume 4
Malaysian Sewerage
Malaysian
Sewerage
Industry Guidelines
Industry Guidelines
Malaysian Sewerage
Industry Guidelines
Section 2
Design Overview
Design Overview
14
Volume 4
Malaysian Sewerage
Industry Guidelines
Design Overview
2.1
2.1.1
c)
b)
2.1.1.1
c)
b)
d)
e)
2.1.1.2
c)
b)
Aerated Lagoon
Volume 4
15
Design Overview
d)
e)
f)
g)
h)
2.1.1.3
2.1.2
PE
Class 1
Class 2
Class 3
Class 4
1000
1001 5000
5001 20000
> 20000
2.2
2.2.1
16
Volume 4
Malaysian Sewerage
Industry Guidelines
Design Overview
Process
Flow Range
Flow Variation
Influent Sewage
Inhibiting
Constituents
Climatic
Constraints
Reaction Kinetics
and Reactor
Selection
Performance
Treatment Residuals The types and amounts of solid, liquid and gaseous residuals
produced must be known or estimated.
Sludge Handling
Constraints
Environmental
Constraints
Volume 4
17
Design Overview
Chemical
Requirements
Energy
Requirements
Other Resource
Requirements
Reliability
Complexity
Ancillary Processes
Compatibility
Aesthetics
Safety and
Operability
18
Volume 4
Malaysian Sewerage
Industry Guidelines
Design Overview
Land Requirements
Ease of Operation
and Maintenance
Modulation
Standardisation
Adaptability
Volume 4
19
Design Overview
2.2.2
Design Stages
Functional Design
Detailed Design
2.2.3
Biochemical characteristics
c)
Hydraulic characteristics
b)
d)
e)
f)
2.2.3.1
Physical characteristics
Constructional characteristics
Biochemical Characteristics
These involve the consideration of the following parameters:
a)
c)
b)
d)
e)
f)
g)
20
Volume 4
Malaysian Sewerage
Industry Guidelines
Design Overview
h)
j)
i)
k)
l)
m)
n)
o)
p)
q)
2.2.3.2
Physical Characteristics
These involve the examination of:
a)
c)
Swelling behaviour
b)
d)
e)
f)
g)
h)
2.2.3.3
Floc formation
Hydraulic Characteristics
These involve the examination of:
a)
c)
b)
d)
e)
f)
g)
h)
Volume 4
21
Design Overview
i)
j)
2.2.3.4
Weir loadings
Overflow rate
Construction Characteristics
These involve the examination of:
a)
c)
b)
d)
e)
f)
g)
h)
i)
2.2.3.5
b)
c)
d)
e)
22
Structural Requirements
a)
2.2.3.6
Land availability
Malaysian Sewerage
Industry Guidelines
Design Overview
e)
f)
g)
h)
i)
j)
k)
l)
2.3
2.3.1
General Safety
a)
b)
c)
d)
e)
f)
g)
Volume 4
23
Design Overview
h)
i)
j)
k)
l)
m)
n)
o)
2.3.2
Structural Safety
a)
c)
b)
d)
e)
f)
g)
h)
i)
24
Concrete slabs over wet wells, tanks and chambers shall have
double steel reinforcing.
Lifting eyes and bolts for slabs to be stainless steel or any other
durable and non-corrosive material.
Protection against falling (i.e. handrail, kick plate and toe plate)
to be provided.
Volume 4
Malaysian Sewerage
Industry Guidelines
Design Overview
j)
k)
l)
d)
e)
f)
g)
h)
i)
j)
Volume 4
25
Section 3
Sewage Characteristics and
Effluent Discharge
Requirements
28
Volume 4
Malaysian Sewerage
Industry Guidelines
3.1
Introduction
The Environmental Quality Act (EQA) 1974 specifies two standards
for effluent discharge: Standard A for discharge upstream of any raw
water intake, and Standard B for discharge downstream of any raw
water intake.
The current Third Schedule of the Environmental Quality Act 1974,
under the Environmental Quality (Sewage and Industrial Effluents)
Regulations, 1979, regulations 8 (1), 8 (2) and 8 (3) has been revisited
and the Department of Environment has proposed 8th Schedule for the
Act which stipulate effluent discharge limits for parameters specific
to domestic wastewater. The effluent discharge limits in 8th Schedule
are summarised in Table 3.2. All sewage treatment plants design shall
take into consideration of the 8th Schedule and shall comply with the
proposed limits.
3.2
3.2.1
3.2.2
b)
c)
Volume 4
29
3.3
3.3.1
3.3.2
Design Values
Typical composition of untreated domestic sewage is given in Table
A.2, while Table 3.1 tabulates the design influent values to be adopted
in the design of a treatment plant.
Table 3.1 - Design Influent Values
Value (g/
capita.day)
Value (mg/l)
56
250
68
300
113
500
11
50
30
10
11
50
Parameter
30
Volume 4
Malaysian Sewerage
Industry Guidelines
Standard A
Absolute Design
BOD5
SS
COD
AMN
Nitrate
Nitrogen
Total
Phosphorus
O&G
Standard B
Absolute Design
Effluent Discharge to
Stagnant Water Bodies*
Standard A
Standard B
Absolute Design Absolute Design
20
50
120
10
10
20
60
5
50
100
200
20
20
40
100
10
20
50
120
5
10
20
60
2
50
100
200
5
20
40
100
2
20
10
50
20
10
10
N/A
N/A
N/A
N/A
10
10
10
Notes:
NA = Not Applicable
All values in mg/l unless otherwise stated.
* Stagnant Water Bodies refer to enclosed water bodies such as lakes, ponds and
slow moving watercourses where dead zone occur.
3.4
3.4.1
Volume 4
31
3.4.3
3.4.4
32
Volume 4
Malaysian Sewerage
Industry Guidelines
Nitrogenous Compound
Removal of nitrogenous compounds needs to be considered in STP design.
These compounds found in various forms (ammonia or ammoniacal
nitrogen, nitrate nitrogen and nitrite nitrogen) could be detrimental to
natural water bodies and potable consumption. Total organic nitrogenous
compounds in raw sewage typically comprise of nitrogen in the form
of proteins, amino acids and urea along with ammoniacal nitrogen.
Ammoniacal nitrogen results from the decomposition of organic nitrogen
particularly from hydrolysis of urea. Total Kjedhal Nitrogen (TKN)
analysis determines the organic nitrogen and the ammoniacal nitrogen
fractions.
3.4.6
Volume 4
33
3.5
34
Volume 4
Malaysian Sewerage
Industry Guidelines
Section 4
Requirements for Physical Design
36
Volume 4
Malaysian Sewerage
Industry Guidelines
4.1
Introduction
The induced physical, chemical and biological reactions that occur in a
sewage treatment plant (STP) lead to waste emissions in the following
forms:
a)
b)
c)
d)
e)
f)
g)
4.2
4.2.1
Buffer Zones
Suitable buffer distances should separate a sewage treatment plant from
its surrounding areas. Buffer Guidelines for the Siting and Zoning of
Industries as recommended by the Department of Environment (DOE)
should be referred to during the planning of suitable location for
treatment plants. The buffer distances recommended in the guidelines
depend on the category of industry being considered.
Volume 4
37
d)
e)
Plants with PE less than 150 but are provided with proper odour
and noise mitigation measure may have a 10 m reduced buffer
at the discretion of the Commission.
The buffer zone can be used for any purpose except permanent habitable
buildings. For example, the buffer zone maybe used as a drainage
reserve, road or highway reserve, transmission reserve, utility reserve
or public park.
In the case where buffer area is to be regularly used by the residents
such as car park and playgrounds, proper precautions during design
stage must be taken to minimise nuisance such as odour, noise and
unpleasant sight to the surrounding environmental. Adequate and proper
screening, odour containment and treatment facilities must be provided
at the sewage treatment plant to address these issues.
38
Volume 4
Malaysian Sewerage
Industry Guidelines
4.2.2
Siting Criteria
The following criteria shall be observed when siting treatment plants.
a)
b)
c)
d)
e)
f)
g)
h)
ii)
iii)
Eating places.
i)
j)
k)
Emergency bypass shall be provided either at the last manhole or wetwell. The bypass shall discharge to the nearest drain which shall have
sufficient capacity to cater for the discharge during rainfall.
4.2.3
Volume 4
39
EQA, 1974 respectively). The type and scope of the study will depend
on the classification of the plant and the environmental sensitivity of
the locality being considered. EIA shall be conducted in compliance
with Volume 2 of the MSIG.
4.2.4
4.3
4.3.1
Modular Units
Stage development of a STP is governed to a large extend by the timeframe
of the overall development plan of the catchments and the size, shape
and soil condition of the land reserved for the STP. Modular units will
be constructed to cater for the stage development. In determining the
appropriate number of modules and corresponding timing for a staged
development, it is crucial for the designer to estimate the flow capacity
build-up over the entire development phases. The modules must have
sufficient capacity to treat the sewage to meet the efficient discharge
standard, without compromising the economical viability of operation
and maintenance. Too many modules and unit processes will definitely
increase equipment maintenance. On the other hand, inadequate modules
will result in an inefficient treatment performance due to insufficient
capacity and flexibility during the early stage.
Table 4.1 Modularisation Requirements
STP Classifications
No. of Modules
No. of Trains
Class 1 (<1,000PE)
N/a
Class 3 (5,001PE
20,000PE)
Min. 2, Max. 3
Class 4 (>20,000PE)
Min. 4, Max. 10
Max 2
40
Volume 4
Malaysian Sewerage
Industry Guidelines
Standby Units
To avoid significant down time in sewage treatment and overloading
of the process units, standby units shall be provided for the following
processes:
a)
Inlet Works/Pumps
c)
Grit Chambers
b)
d)
e)
f)
Screen Facilities
Biological Treatment
Secondary Clarifiers
Sludge Facilities
c)
Blowers
b)
d)
Mechanical screens
Back-up Capacity
The back-up capacity provided shall be such that when one unit process
is taken out of operation, the remaining units shall not be overloaded
beyond 50% of their rated capacities.
Volume 4
41
4.3.4
Design Flow
4.4
The land area requirements and buffer allowance for temporary sewage
treatment plants maybe reduced at the discretion of the Commission on
a case by case basis.
4.4.1
The recommended land area requirements for Class 1 and 2 plants (up
to 5000 PE) are given in Table 4.2 and Table 4.3 respectively. The net
area does not include the 30 m buffer zone surrounding the plant, but
does include appropriate set backs and access paths within the plant. The
area requirements given are sufficient to achieve an effluent conforming
to Standard A discharge requirements. It is important that allowance
is made for sufficient buffers in planning approvals, to avoid future
complaints in relation to the siting of the plant.
4.4.2
42
Volume 4
Malaysian Sewerage
Industry Guidelines
4.4.3
4.4.4
Imperfect Sites
Thus, the shape and elevations of the land allocated for the STP development
must be determined during planning stage so that the configuration of
the STP can be planned properly in order to allocate adequate land for
the purpose. This also enables estimates for additional land required. It
may also be required to cut or fill operations to level the land.
4.4.5
The area requirements, as stipulated in Table 4.2, 4.3, 4.4, 4.5 and 4.6,
must be adhered to as strictly as possible. The required areas in these
tables include appropriate setbacks and access paths within the plant.
However the areas have not include any buffer zone surrounding each
plant as indicated in Section 4.2.1.
Volume 4
43
Population
Equivalent
Land Area
Requirement *
(acre)
(m2)
100
210
0.052
150
285
0.070
200
360
0.089
250
430
0.106
300
485
0.120
350
545
0.135
400
600
0.148
450
655
0.162
500
700
0.173
550
745
0.184
600
790
0.195
650
835
0.206
700
870
0.215
750
905
0.224
800
940
0.232
850
980
0.242
900
1010
0.250
950
040
0.257
1000
1070
0.264
Note: * The required area only includes appropriate setbacks and access paths
within the plant but not the buffer zone surrounding each plant as indicated in
Section 4.2.1.
44
Volume 4
Malaysian Sewerage
Industry Guidelines
1100
1200
1300
1400
1500
1600
1700
1800
1900
2000
3000
4000
5000
Land Area
Requirement *
(m2)
1115
1160
1200
1240
1275
1310
1340
1370
1395
1420
2226
2671
3076
(acre)
0.276
0.287
0.297
0.306
0.315
0.324
0.331
0.339
0.345
0.351
0.55
0.66
0.76
Land Area
Requirement *
(ha)
(acre)
5001
0.31
0.76
6000
0.40
0.99
7000
0.49
1.21
8000
0.59
1.46
9000
0.69
1.71
10 000
0.78
1.93
15 000
1.00
2.47
20 000
1.19
2.95
Note: * The required area only includes appropriate setbacks and access paths
within the plant but not the buffer zone surrounding each plant as indicated in
Section 4.2.1.
Sewage Treatment Plants
Volume 4
45
20 001
25 000
30 000
35 000
40 000
45 000
50 000
55 000
60 000
65 000
70 000
75 000
80 000
85 000
90 000
95 000
100 000
110 000
120 000
130 000
140 000
150 000
160 000
170 000
180 000
190 000
200 000
250 000
300 000
450 000
1.19
1.37
1.53
1.81
1.97
2.12
2.23
2.37
2.52
2.67
2.93
3.27
3.49
3.69
3.89
4.07
4.25
4.57
4.87
5.14
5.39
5.63
5.84
6.05
6.25
6.43
6.60
7.36
7.98
9.36
2.95
3.38
3.79
4.48
4.88
5.25
5.52
5.84
6.22
6.61
7.23
8.07
8.61
9.12
9.61
10.06
10.49
11.29
12.02
12.70
13.32
13.90
14.44
14.95
15.43
15.89
16.32
18.20
19.73
23.14
Note: * The required area only includes appropriate setbacks and access paths
within the plant but not the buffer zone surrounding each plant as indicated in
Section 4.2.1.
46
Volume 4
Malaysian Sewerage
Industry Guidelines
Standard A*
Standard B*
(ha)
(acre)
(ha)
(acre)
2000
0.48
1.18
0.45
1.10
4000
0.89
2.20
0.71
1.75
3000
5000
10 000
15 000
20 000
25 000
30 000
35 000
40 000
45 000
50 000
55 000
0.69
1.09
2.03
2.92
3.78
4.62
2.68
5.01
7.2
9.3
11.4
5.45
13.5
7.05
17.4
6.26
7.85
8.63
9.40
60 000
10.16
70 000
11.68
65 000
1.69
10.92
15.5
19.4
21.3
23.2
0.59
0.82
1.31
1.72
2.09
2.42
2.74
3.04
3.32
3.59
3.86
2.04
3.24
4.25
5.16
5.99
6.77
7.50
8.2
8.9
9.5
4.11
10.2
4.60
11.4
25.1
4.36
28.9
4.83
27.0
1.45
10.8
11.9
75 000
12.42
30.7
5.06
12.5
85 000
13.91
34.4
5.50
13.6
80 000
90 000
95 000
100 000
13.17
14.64
15.37
16.10
110 000
17.54
130 000
20.38
120 000
18.97
32.5
36.2
30.0
39.8
43.3
46.9
50.4
Volume 4
5.28
5.72
5.93
6.13
6.54
6.93
7.31
13.1
14.1
14.6
15.2
16.2
17.1
18.1
47
140 000
150 000
160 000
170 000
180 000
190 000
200 000
Standard A*
Standard B*
(ha)
(acre)
(ha)
(acre)
21.79
53.8
7.69
19.0
24.57
60.7
8.40
20.8
27.32
67.5
23.18
25.95
28.68
30.04
57.3
8.05
19.9
64.1
8.75
21.6
70.9
9.43
23.3
74.2
9.09
9.76
22.5
24.1
Note: * The required area only includes appropriate setbacks and access paths within the
plant but not the buffer zone surrounding each plant as indicated in Section 4.2.1.
48
Volume 4
Malaysian Sewerage
Industry Guidelines
Start
Determine catchment
served
Determine ultimate PE
Identified effluent
requirement
Is development
> 2000 PE?
Is development
in urban area?
End
Volume 4
49
Start
Local plan
Plan
formulation
Formulation
Determine suitable
receiving waters
Calculate ultimate
catchment PE
Identify effluent
standards
Look up land area
requirements in
Tables 4.2, 4.3, 4.4 or 4.5
Table 4.2:
Up to 1000
1,000PE
PE
Consider multi-use of
buffer areas
End
50
Volume 4
42
V ol ume 4
Malaysian Sewerage
Industry Guidelines
M al aysi an S ewerage
I ndustry G ui del i nes
Residential /
Commercial Plot
5m Min.
Access And
Screening
Property
Boundary
STW Fence
Open Treatment
Plant
Beautification
Zone
Residential /
Commercial Plot
5m Min.
Access and
Screening
Enclosed Plant
Property
Boundary
STW Fence
5m Min.
Access And
Screening
Property
Boundry
STW Fence
Buried / Covered
Plant
5m Min.
Access and
Screening
Enclosed Plant
Property
Boundary
STW Fence
Industrial Plot
5m Min.
Access And
Screening
Open Treatment
Plant
Factory Fence
STW Fence
Note : The buffer area can be used for roads, drains, utility reserve, agricultural or other similar
purposes.
Volume 4
Volume 4
51
43
52
Volume 4
44
Volume 4
10 m
20 m
30 m
The land shall be relatively flat and of a regular shape. Any unusable
area within the plot shall be minimised.
Note: Buffer areas can be used for roads, drains, utility reserve, public
parks, agricultural or similiar purposes other than permanent
habitable buildings.
10 m
20 m
30 m
Figure
PlanView
View of
of Buffer
Figure
4.44.4- Plan
BufferZone
ZoneRequirements
Requirements
Malaysian Sewerage
Industry Guidelines
Malaysian Sewerage
Industry Guidelines
4.5
4.5.1
Mechanical Installation
I)
Design Considerations
g)
h)
i)
II)
a)
b)
c)
Water storage tanks shall not be placed on the roof top of any
control room; all water supply system shall be homed with
separate entrance.
Installation
The base frame of rotational equipment or any equipment that may
induce vibration shall be provided with anti-vibration mount.
All moving parts shall be designed and installed in a manner
that is inherently safe to operate.
Volume 4
53
d)
g)
h)
k)
4.5.2
The designer must ensure that the unit processes are arranged
in such a way to prevent/reduce criss-crossing of piping works,
unnecessary bends, choking of interconnected pipe and excessive
hydraulic losses through the system.
Vibration
All revolving parts shall be properly balanced both statically and
dynamically so that in running up to, at full normal operating speeds,
and at any loads up to the maximum there shall be no undue vibration
anywhere in the machine or transmitted to the adjacent structure. The
criteria adopted for vibration severity shall be the RMS value of the
vibration velocity in millimeters per second.
The bare frame of rotational equipment or any equipment that may induce
vibration shall be provided with anti-vibration mount. Where rotational
equipment or equipment which may induce vibration is connected to
piping, then vibration isolator shall be provided.
4.5.3
Noise
Noise levels from machinery shall comply with the Factories and
Machinery (Noise Exposure) Regulations 1989 and Occupational Health
and Safety Act. Noise control measures and appropriate safety protection
for operators must be provided where necessary.
54
Volume 4
Malaysian Sewerage
Industry Guidelines
Volume 4
55
b)
c)
d)
e)
f)
g)
h)
56
Volume 4
Malaysian Sewerage
Industry Guidelines
Wall
Equipment
Wall
1 m or 1.5 W or
whichever greater
Equipment
L
4.5.5
1 m or 1.5 W or
whichever
greater
Motors
Provide readily replaceable anti-condensation heaters for motors
that do not require frequent operation.
At least three thermistors to be provided for motors which are
>50 kW.
Electrical motors should be rated as continuous run.
d)
e)
f)
II)
a)
b)
Volume 4
57
c)
III)
Motor Starters
d)
c)
e)
Category
Supply Requirements
Sewage Treatment
Plant
STP Class 4
58
Malaysian Sewerage
Industry Guidelines
b)
e)
f)
g)
h)
i)
j)
4.5.7
All metering panel shall be located flush with the fence and
door opening from outside to enable TNB inspector to read the
kWh and kVAhr reading.
Provide earthing connected with Current Transformer (CT) for
Large Power Consumer (LPC) (i.e. consumption with more than
100A or 10kW).
Back-up Generator
a)
b)
Volume 4
59
c)
d)
e)
4.5.8
d) Use separate panel boards for general purpose light and power
e)
f)
g)
h)
i)
4.5.9
For incomer above 400 A, provide over current and earth fault
protection on all starter circuits in excess of 200 A
Where a circuit has a main and standby supply, provide an
isolator in each supply circuit
Control Cabinets
(I)
a)
b)
60
General
Provide 900 mm minimum clearance between an open door and
any fixed object.
Volume 4
Malaysian Sewerage
Industry Guidelines
c)
d)
e)
f)
g)
m)
(II)
a)
b)
c)
d)
e)
f)
g)
Outdoor Cabinets
Self contained, free-standing, weatherproof cabinets to be
constructed of marine grade aluminium, stainless steel grade
316 or glass reinforced plastic.
Mount control indication and alarm facilities on internal
doors enclosing compartments housing electrical plant and
equipment.
Provide external doors with security locking facilities.
Volume 4
61
4.5.10
Control Requirements
This section outlines the general philosophy on control requirements
for the whole facilities.
NO.
TYPE OF PLANT
EWS + PC
(monitoring) /
Data Logger
SCADA
1.
100 000 PE
2a.
Class 3 STPs
Class 4 STPs
2b.
Class 1, 2 and 3
Class 4 STPs
2c.
Class 1, 2 and 3
Class 4 STPs
I)
a)
b)
c)
d)
e)
f)
g)
h)
i)
62
General Considerations
PLC shall restart automatically once the power supply reinstate
after a power supply interruption.
PLC shall be equipped with manual over-ride features.
Volume 4
Malaysian Sewerage
Industry Guidelines
II)
a)
b)
III)
a)
Manual Control
Interlocks shall be provided to prevent damage to the equipment
during equipment start up, for example, bearing overload,
overheated, temperature, loss of cooling water, no flow when
operating.
Selector switches to be provided at one location so that an
equipment can be manually operated from that location.
Drive Systems
Each drive must be independently provided with the following
features :
i. ON
ii. OFF
iii.
AUTO
-
-
-
b)
d)
c)
e)
IV)
a)
b)
c)
d)
e)
Volume 4
63
4.5.11
Control Systems
a)
b)
Supervisory Systems
Where supervisory systems are used, schedule all graphic displays
required to control plant using columns to define:
i)
64
Graphic Name
Volume 4
Malaysian Sewerage
Industry Guidelines
ii)
iii)
Information displayed
Control features
c) Nominate the alarm title to be used/displayed for each processgenerated fault input or fault generated internally by the PLC
program.
f)
4.5.12
The EWS is used to monitor the status of the equipment operating inside
the treatment plants such as pumps and aeration equipment. It shall act
as the means to communicate information via Short Messaging Service
(SMS), e-mail or via other telecommunication mean to technical staff
for the fast recovery of the treatment system.
EWS system shall be able to transmit digital and analog values from
the remote module to the operator through their inputs (equipment) via
SMS and e-mail messages in text mode. The modules shall be able to
interpret SMS message from the operator to activate or deactivate long
distance machine (remote control).
4.5.13
Instrumentation
Volume 4
65
Aeration
Blower
Decanter
Effluent
Sludge (WAS/RAS)
Electrical Drive
Disinfection
Polymer
Sludge Feed
Instrumentation
STP Class
Level/ Pressure
Flow Measurement
Gas Detector (H2S, CO2, O2 &
Combustible gases)
All
All
4
All
Flow Measurement
All
DO/pH/ Turbidity
Temperature
4
4
All
Flow Measurement
Am/Volt/HR/kW/Power Factor
meter
All
All
Dosage/Transmittance /
Flowrate/outlet water level
indicator
All
Flowrate/ Pressure
All
For STP with PE 10 000 and above, a digital power meter is required to
be installed at all individual panel of major equipment such as raw sewage
pump, air blower, aerators, mechanical dewatering unit etc. The digital
power meter shall be able to monitor the following:
Real-Time Readings
Energy Readings
Other:
66
Volume 4
Malaysian Sewerage
Industry Guidelines
4.5.14
b)
c)
d)
e)
f)
g)
II)
General
Segregate cables into the following categories:
i)
ii)
instrumentation/telemetry
iii)
control
Buried Cables
Install cables without trees or through joints, unless approved.
All buried cables shall be laid in ducts.
Underground Ducts
Construct road crossings from uPVC conduit of minimum 100
mm diameter with 900 mm cover and encased on all sides with
150 mm concrete.
Volume 4
67
b)
c)
d)
e)
(V)
a)
b)
Conduits
All cabling within buildings or structures where cable trays are
not permitted, and in all external locations, shall be installed
within conduits.
Conduits installed externally shall be arranged to minimise their
length and exposure. PVC heavy duty conduit is permissible,
where it is protected from physical damage and UV. Otherwise,
metal or flexible conduits shall be used.
4.5.15
68
d)
e)
Malaysian Sewerage
Industry Guidelines
4.5.16
4.5.17
d)
ii)
Volume 4
69
f)
4.5.18
Hazardous Areas
a)
b)
4.6
4.6.1
b)
c)
70
Volume 4
Malaysian Sewerage
Industry Guidelines
d)
e)
f)
g)
h)
ii)
i)
j)
k)
m)
i)
l)
Volume 4
71
4.6.2
Steel
I)
Structural steel
a)
i)
ii)
II)
a)
ii)
72
Volume 4
Malaysian Sewerage
Industry Guidelines
i)
ii)
c)
g)
h)
ii)
i)
ii)
III)
a)
All areas within 5 km from the coast line or salt water bodies
shall be classified as marine environment. Sewerage facilities
in marine and corrosive environment e.g. where the atmosphere
Volume 4
73
b)
ii)
c)
ii)
e)
4.6.3
d)
SS316L
Aluminium alloy
74
Volume 4
Malaysian Sewerage
Industry Guidelines
d)
e)
f)
All surfaces shall have a resin rich layer, gel coat. Surfaces in
contact with sewage, water or any moisture shall comprise of
a resin rich layer at least 1 mm thick. All other surfaces shall
comprise of a resin rich layer at least 0.25 mm thick. Up to 10%
by mass of corrosion resistant glass fibres, (that is, C-glass or
E-CR glass), polyester fibres or acrylic fibres may be used in
the surface layer.
A barrier layer shall be provided behind the surface layer and
shall be at least 1.5 mm thick. The barrier layer shall comprise
of 70 to 80 % by weight resin with the remainder by weight
being E glass or E-CR glass.
The structural layer shall comprise resin impregnated layers of
E glass or E-CR glass and shall comprise at least 25 % E glass
or E-CR glass. Aggregate and filler may be included.
E glass and E-CR glass shall conform to the requirements of:
i)
ii)
Volume 4
75
g)
h)
i)
j)
k)
l)
m)
n)
4.6.4
ii)
Aluminium
a)
b)
ii)
76
Volume 4
Malaysian Sewerage
Industry Guidelines
v)
4.6.5
Tensile Strength
no break Kj/m2
650C
Volume 4
77
78
Volume 4
Malaysian Sewerage
Industry Guidelines
Section 5
Requirements for Individual
Treatment Processes
80
Volume 4
Malaysian Sewerage
Industry Guidelines
5.1
Introduction
All new applications for sewage treatment plant approval shall follow
the design requirements as stipulated in this section. These requirements
have been formulated as a gradual change in sewage treatment methods
for Malaysia prior to enforcement of ultimate requirements as stipulated
in Sections 3 and 4 of this volume.
Design requirements for each stage of the sewage treatment process, as
shown in Figure 5.1 are given in this section.
Figure 5.2 gives an overview of the typical flow diagram and elements
of a sewage treatment plant. Figure 5.2 also shows how one facility
is closely related to another and thus has an impact upon the overall
design.
Sewage treatment plants must be designed to produce an effluent quality
that conforms to either Standard A or Standard B or any other special
requirements under the provisions of the Environmental Quality Act.
The major indices are those of BOD5, Suspended Solids, COD, Oil &
Grease, Ammoniacal Nitrogen, Nitrate Nitrogen and Total Phosphorus.
The requirement to comply with absolute standards, where no failures
are permitted by law, means that new sewage treatment plants must be
designed to produce average effluent qualities well below those permitted
by the Standard figures. Design values for final effluent shall be used in
the design of new treatment works are given in Table 3.2. These design
effluent levels serve as the basis for the design requirement of each unit
process given in the following sub sections.
General ventilation systems shall be provided in compliance to the OSHA.
The potential for odour generation, its impact and treatment, shall be
considered in all aspects of design. Odour treatment equipment shall be
selected that such odours be reduced to the lowest possible level and
in compliance to the EQA.
Volume 4
81
Pre
Treatment
Primary
Treatment
Secondary
Treatment
Treatment
Processes
1
Primary
Screen
Pump
Station
Design
Requirements
Section 5.2
Function
M/O
Section 5.3
Secondary
Screen
Section 5.4
Removes smaller/finer
particles from sewage
Grit/Grease
Removal
Section 5.5
Balancing
Tank
M/O
Section 5.6
Primary
Sedimentation
M/O
Section 5.7
Removes settleable
solids/materials
Biological
Treatment
Section 5.8
Secondary
Sedimentation
Section 5.9
Disinfection
Section 5.10
Flow Meter
Section 5.11
10
Bio Solids
Handling
Requirements
Mandatory (M)
Optional (O)
11
Thickener
Stabilisation
Holding
Dewatering
M/O
Section 5.12
Reduces potential
detrimental effect on the
environment and converts
sludge to a form suitable for
ultimate disposal
Sludge Disposal
82
70
Volume 4
V ol ume 4
Malaysian Sewerage
Industry Guidelines
M al aysi an S ewerage
I ndustry G ui del i nes
Raw
Sewage
Inlet
Ultimate Disposal
Balancing
Tank
Grit/Grease
Secondary
Screen
Incinerator/Dryer
Sewage
Pump Station
Primary
Screen
Volume 4
Volume 4
Return
Mechanical Sludge
Dewatering
Alternate
Alternative
Primary Clarifier
Alternative
Final Clarifier
Mechanical Sludge
Thickener
Flow
Distribution
Sludge Holding
Tank
Sludge Digester
Liquor
Return Sludge
Pump Station
C. Trickling Filter
D. RBC
B. Extended Aeration
Activated Sludge
A. Conventional
Activated Sludge
Biological System
Disinfection
10
Effluent To
Nearest
Receiving
Watercourse
Flow Meter
Figure5.2
5.2 Typical
Typical
Elements
Process
Diagram
of a
Figure
Elements
and and
Process
Flow Flow
Diagram
of a Sewage
Sewage
Treatment
Treatment
PlantPlant
83
71
5.2
5.2.1
b)
5.2.2
Inlet Chamber
Provision for inlet chamber before the primary screen channel is necessary
for proper operational and maintenance. The summarised requirements
for inlet chamber are as follows:
Table 5.1 Requirements for Inlet Chamber
Unit
Process
Requirements
> 20 000
PE
> 50 000
PE
Yes
n/a
n/a
Dual
n/a
Yes
Yes
Motorised
n/a
No
Yes
Inlet
Chamber
Type
20 000
PE
Single
Mandatory
Notes
84
Volume 4
Malaysian Sewerage
Industry Guidelines
CLEAR SPACING
MANUAL FINE SCREEN
FIRST PENSTOCK
SECOND PENSTOCK
OVERFLOW PIPE
DISCHARGETO DRAIN
PRIMARY
SCREEN
CHAMBER
INLET
CHAMBER
450mm
1:2
5.2.3
IL
Requirements
Duty
Standby
5000 PE
> 5000 PE
1 Unit
Mechanical
1 Unit
Manual
Mechanical
1 Unit
1 Unit
1 Unit
Manual
By Pass
Volume 4
85
Description
Unit
mm
Design Criteria
Manually
Mechanically
Raked
Raked#
25
25
30o 45o
15o 45o
m/s
1.0
1.0
m/s
1.0
1.0
Minimum freeboard
mm
150*
30
150
day
m3 / 106 m3
mm
500
500
1 unit
Anti-skid and
non-corrosive
Anti-skid and
non-corrosive
mm
500
500
Notes:
*
Designer shall ensure that with 50% of blockage at the face of screen, sufficient
freeboard is provided to prevent the approach channel from overflowing
#
5.2.4
General Requirements
All plants must include:
a)
b)
86
Volume 4
Malaysian Sewerage
Industry Guidelines
Volume 4
87
Requirements
Individual
Treatment
Processes
Requirements for
for Stages
of Sewage
Treatment
Figure
ScreeningsCollected
CollectedFrom
From
Primary
Screens
Figure 5.4 Quantities
Quantities of
of Screenings
Primary
Screens
100
80
Screenings, m 3/ 10 6m 3 of Sewage
Average
Maximum
60
40
20
88
76
Volume 4
Malaysian Sewerage
Industry Guidelines
Volume 4
Malaysian Sewerage
Industry Guidelines
INCOMING SEWER
Volume 4
Volume 4
INCOMING SEWER
R.C STAIRCASE
TO ENGR'S DETAIL
HANDRAIL
HANDRAIL
PENSTOCK
R.C STAIRCASE TO
ENGR'S DETAIL
PENSTOCK
CHAIN GUARD
GRATING COVER
PLAN
(PE > 5000)
SECTION A-A
STOP LOG
DRAIN
RAMP DOWN
PERFORATED SLAB
WP
GRATING
COVER
HANDRAIL
HANDRAIL
PENSTOCK
PENSTOCK
CHAIN GUARD
INCOMING SEWER
R.C STAIRCASE
TO ENGR'S DETAIL
INCOMING SEWER
STOP LOG
CONC. APRON
LAID TO FALL
DRAIN
SECTION A-A
PLAN
(PE 5000)
R.C STAIRCASE TO
ENGR'S DETAIL
RAMP
DOWN
WP
S.S PERFORATED
TROUGH
< 5m
< 5m
89
77
< 5m
INCOMING SEWER
STOP LOG
R.C STAIRCASE
TO ENGR'S DETAIL
HANDRAIL
HANDRAIL
PENSTOCK
R.C STAIRCASE TO
ENGR'S DETAIL
INCOMING SEWER
CHAIN GUARD
PENSTOCK
A
DRAIN
CONCRETE APRON
LAID TO FALL
SECTION A-A
MECHANICAL
COARSE SCREEN
PLAN VIEW
(PE > 5000)
RAMP
DOWN
DN
WP
OPENINGS
CAT LADDER
SCREENINGS
COLLECTION BIN
MECHANICAL COARSE
SCREEN
R.C STAIRCASE
TO ENGR'S DETAIL
> 5m
INCOMING SEWER
STOP LOG
HANDRAIL
PENSTOCK
R.C STAIRCASE TO
ENGR'S DETAIL
CHAIN GUARD
PENSTOCK
HANDRAIL
DRAIN
CONCRETE APRON
LAID TO FALL
SECTION A-A
PLAN VIEW
(PE 5000)
RAMP
DOWN
MANUAL COARSE
SCREEN
OPENINGS
S.S PERFORATED
TROUGH
CAT LADDER
SCREENINGS
COLLECTION BIN
DN
WP
90
Volume 4
Malaysian Sewerage
Industry Guidelines
78
Volume 4
Malaysian Sewerage
5.3
5.3.1
c)
b)
5.3.2
Design Requirements
(I)
Structural Requirements
a)
b)
c)
d)
e)
f)
g)
Volume 4
91
II)
Ventilation Requirements
a)
b)
c)
d)
e)
III)
a)
b)
c)
d)
e)
f)
g)
h)
92
Volume 4
Malaysian Sewerage
Industry Guidelines
Requirements
for Individual
Treatment
Processes
Requirements
for Stages of
Sewage Treatment
b)
b)
c)
c)
d)
d)
e)
e)
f)
f)
g)
g)
h)
h)
i)
i)
Benching shall
shallbebe
such
to minimise
deposition
solid
Benching
such
that that
to minimise
deposition
of solid of
matters
matters
on
the
floor
or
walls
of
wet
wells.
The
minimum
slope
on the floor or walls of wet wells. The minimum slope of benching
of benching
be 45o to the horizontal.
shall
be 45o toshall
the horizontal.
Benching shall
shallpreferably
preferably
extended
the pump
Benching
be be
extended
up toupthetopump
intake.intake.
Minimum hopper
hopper bottom
bottom slope
slopeshall
shallbe
be1.5
1.5vertical
verticaltoto1.0
1.0horizontal.
horizontal.
Minimum
Tapered slope
slopeshall
shallbebe
provided
upthe
to suction
the suction
section.
Tapered
provided
up to
section.
Automatic flushing
flushingofofgrit
gritand
andsolids
solids
recommended
plants
Automatic
is is
recommended
for for
plants
of
of
PE
>
2
000.
PE > 2,000.
The difference
differencebetween
betweenstop
stopand
andstart
start
levels
shall
a maximum
The
levels
shall
be abemaximum
of
of
900
mm
and
a
minimum
of
450
mm.
900 mm and a minimum of 450 mm.
The difference
difference in
in level
level between
between start
start oror stop
stop ofof duty
duty and
and assist
assist
The
pumps
shall
be
greater
than
or
equal
to
150
mm.
pumps shall be greater than or equal to 150 mm.
The minimum internal width of wet well shall not less than 2m.
The minimum internal width of wet well shall not less than 2m
Where possible, wet wells shall be open and guarded by a handrail
Where possible, wet wells shall be open and guarded by a handrail
or open mesh grating. The grating shall be easily and safely
or open mesh grating. The grating shall be easily and safely
removed.
removed.
Figure
ofWet
WetWell
Well
Figure 5.7
5.7 Typical
Typical Dimensions
Dimensions of
Submersible
PumpStation
Station
Submersible Pump
MIN 2000
(/S)
QO (I/S)
i
INCOMING SEWER
Qi (I/S)
(/S)
D2
150
CUT IN LEVEL
D1
Note :
Q1 = Incoming flow rate
QO = Forcemain Discharge rate
D2 = Forcemain Diameter, min 100
d
= Difference between stop & start level, Min 450 Max 900
Volume 4
93
Volume 4
81
ER
150
CUT IN LEVEL
CUT OUT LEVEL
LOW LEVEL ALARM/EMERGENCY
CUTOUT
D1
150
D2 to D2
3
D2 to D2
4
D2
QO (l/s)
150 (min)
IN
Qi COM
(I/S I NG
SE
)
WE
R
150 S
CUT IN LEVEL
CUT OUT LEVEL
D2 TO D2
D2
Q0 (l/S)
150
D1
Note :
Q1 = Incoming flow rate
QO =
D2 =
Bellmouth Diameter
Difference between stop start level, Min 450 and Max 900
V)
(V)
Lighting Requirements
Lighting Requirements
a)
a)
b)
b)
c)
c)
If lights
lights are
arefitted
fittedoutside
outsidethethe
well,
then
a spotlight
system
If
well,
then
a spotlight
system
may may
be
be
used
to
provide
adequate
illumination.
used to provide adequate illumination.
94
Volume 4
Malaysian Sewerage
Industry Guidelines
82
Volume 4
Malaysian Sewerage
Industry Guideline
VI)
Level Controls
a)
b)
c)
d)
e)
ii)
System curves
Pump curves
b)
c)
d)
e)
f)
g)
5.3.3
General Requirements
a)
Volume 4
95
b)
d)
Pipework
c)
Where separate valve pits are used, the connecting pipes shall
incorporate at least two flexible joints to allow for differential
settlement.
i) Pipe work shall be of ductile iron or cast iron with cement
internal lining. Other approved material by the Commission
may be used.
ii) External surface of pipework in chambers and wells shall be
epoxy coated.
iii) Buried ductile iron pipe shall have polyethylene sleeving.
iv) Pipe within wells and pits shall have flanged joints, while
pipe laid in the ground shall have spigot and socket joints.
v) Pipe work shall be adequately supported on concrete plinths
or steel structural supports.
vi) Flanges shall be located at least 150 mm away from
structures.
vii) Dismantling joints such as bends shall be provided.
viii) Pumping thrust shall be resisted using pipe supports inside
chambers and by mass concrete thrust blocks poured against
undisturbed soil in the ground outside chambers.
ix) No welding joints are allowed.
e) Valves
i) Gate valves are preferred with rising spindles operated by
a tee piece.
ii) The uses of counterweights are recommended. Tapping
(12 mm BSP) shall be located upstream and downstream of
check valves.
Also refer to additional requirements in relevant Clause of MS 1228.
96
Volume 4
Malaysian Sewerage
Industry Guidelines
STEPS
GRATING COVER
OVERFLOW PIPE
DISCHARGE TO DRAIN
V.C.P
STAND PIPE
CONC. APRON
COLLECTION BIN
CLEAR SPACING
S.STEEL MANUAL
FINE SCREEN
OVERFLOW
CHAMBER
INFLUENT PUMP
PRIMARY SCREEN
A
GRATING COVER
17 18 19 20 21 22 23
STEPS
A
PUMP SUMP
S.STEEL HANDRAIL
PENSTOCK
16 15 14 13 12 11 10 9 8 7 6 5 4 3 2
EXPLOSION PROOF
SPOT LIGHT
CHECK VALVE
FLEXIBLE COUPLING
GATE VALVE
DELIVERY PIPE
PLAN VIEW
LIFTING I-BEAM C/W
CARRIER
HANDRAIL
CLEAR SPACING
MANUAL FINE SCREEN
PENSTOCK
OVERFLOW
PIPE DISCHARGE
TO DRAIN
OVERFLOW
CHAMBER
DELIVERY PIPE
GUIDERAIL
S.S PERFORATED
TROUGH
PUMP SUMP
LIFTING CHAIN
PRIMARY SCREEN
CHAMBER
CONC. SLAB
R.C WALL TO
ENGR'S DETAIL
IL
1:2
IL
OPENING
ALARM
START
SECTION A-A
Volume 4
Volume 4
97
85
Figure
Typical
Details
of Dry-well
Pump Station
Figure5.10
5.10 Typical
Details
of Dry-well
Pump Station
OVERFLOW PIPE DISCHARGE
TO MONSOON DRAIN
OVERFLOW CHAMBER
DRAIN
RAMP DOWN
WP
FORCEMAIN
MECHANICAL COARSE SCREEN
GATE VALVE.
NCOMING SEWER
AIR EXTRACTOR FAN
14 15 16 17 18 19 20 21
3 LAYER CONC.
VENTILATION BLOCK
AT TOP AND BOTTOM
LEVEL
CHECK VALVE.
12
11
10
9
8
7
6
5
4
3
2
1
EXTRACTOR FAN
R.C STAIRCASE TO ENGR'S DETAIL.
CONCRETE VENTILATION
BLOCK AT TOP AND BOTTOM LEVEL
DN
CHAIN GUARD.
DN
13 12 11 10 9 8 7 6 5 4 3 2 1
13
14
15
16
17
18
19
20
21
22
23
ADJUSTABLE GLASS
LOUVRES WINDOW
SPOT LIGHT
CHEQUER PLATE
DOOR
PLAN VIEW
COPPER TYPE
LIGHTNING ARRESTOR
PENSTOCK
HANDRAIL
DOOR
BRICKWALL C/W
CEMENT PLASTER ON BOTH SIDES
WINDOW
CHEQUER PLATE
HANDRAIL
R.C STAIRCASE TO ENGR'S DETAIL
WET WELL
DRY WELL
PERFORATED SLAB
CAT LADDER
OPENINGS
INCOMING SEWER
(FLOAT SWITCH)
CHECK VALVE
GATE VALVE
ALARM
1st. STANDBY PUMP START
STOP LOG
SUMP BWL
DEWATERING PUMP
SECTION VIEW
86
98
Volume 4
Volume 4
Malaysian Sewerage
Industry Guideline
Malaysian Sewerage
Industry Guidelines
Unit
Type of station
Number of pumps
(all identical and work
sequentially)
Pumps design flow
PE 1,000
Wet well
2
1 duty,
1 standby
(100 % standby)
Each at Q
Wet well
2
1 duty,
1 stand-by
(100 % standby)
Each at Q
peak
peak
min
30
30
mm
75
75
mm
100
100
ave
start/
hour
6 min
15 max
Lifting davit
6 min
15 max
lifting beam and
block
Design Parameters
Description
Type of station
Unit
Number of pumps
(all identical and work
sequentially)
PE > 20,000
min
mm
75
75
mm
100
100
start/
hour
6 min
15 max
6 - 15
Lifting device*
mechanical
Note: * Motorised hoists shall be provided when the lifting weight exceeds 100 kg
Volume 4
99
5.4
5.4.1
5.4.2
Design Requirements
Plants of all sizes must be installed with secondary screens. The channel
shall be designed for Qpeak or pump flow whichever is greater. Approach
channel shall be design to ensure good contribution of velocity
A minimum of two screens are required for duty and standby. Facility
for a screened bypass must be provided in the event of clogging. Where
mechanically cleaned screening devices are installed auxiliary manually
cleaned screen shall be provided.
Table 5.5 Provision Requirement of Secondary Screens
Requirements
Duty
Standby
Bypass
100
Manual
Mechanical
Manual
Mechanical
Screen
Volume 4
1 Unit
1 Unit
1 Unit
1 Unit
1 Unit
Malaysian Sewerage
Industry Guidelines
Description
Unit
mm
Design Criteria
Manually
Mechanically
Raked
Raked #
12
30o 45o
12
15o 45o
m/s
1.0
1.0
m/s
1.0
1.0
mm
150*
150
m3 / 106 m3
day
mm
mm
1 unit
7
500
500
Anti-skid and
non-corrosive
Notes:
* Designer shall ensure that with 50% of blockage at the face of screen, sufficient
freeboard is provided to prevent the approach channel from overflowing
# Washing and dewatering of screenings shall be provided.
5.5
5.5.1
Volume 4
101
5.5.2
General Requirements
A manual bypass shall be provided. In case of grit removal system
failure and/or power outages, the flow shall be automatically directed
to the bypass.
Where mechanical grit separator is used, they shall be installed at an
angle of at least 10 to allow drainage and foul water to be returned to
the inlet channel.
Where manual systems are used, allow for safe and easy access to remove
grit to a storage bin.
If pump systems are used, the suction pipe shall be short and straight.
Tees and short radius bends shall be avoided, if at all possible. Flanges
at strategic locations shall be provided so that they can be dismantled
to remove any blockages.
The mechanical oil and grease skimming device shall be designed to
minimise the water being remove while skimming the oil and grease.
Sand pit may be used for further dewatering of the grease removed before
ultimate disposal. The drainage from the sand pit shall be returned to
the inlet channel for further treatment.
102
Volume 4
Malaysian Sewerage
Industry Guidelines
Requirements
Manual
Mechanical
5000 PE
> 5000 PE
Standby
Manual
Mechanical
5.5.3
Manual
Mechanical
Design Criteria
Design criteria are given in Tables 5.8 and 5.9.
Table 5.8 Design Parameters for Grease Chambers
Description
Unit
PE 5000*
Design Criteria
> 5000PE
Grease removal
Chamber type
Rectangular
Baffled tank
Aerated type
min
Minimum detention
time (Qpeak)
> 5000PE
Mechanical
Volume 4
103
Unit
Design Criteria
PE 5000*
>5000PE
>5000PE
Grit removal
Manual
(tanker)
Mechanical
Mechanical
Chamber type
Horizontal
flow (2 units
required for
duty and
standby during
cleaning)
vortex also
acceptable
Square, rotary or
vortex type simple
mechanised grit
chamber
Aerated
minute
m/s
0.20
0.20
0.20
m/s
n/a
<1.0
<1.0
35% of depth
l/s/meter
length of tank
10.0
1:2
Manufacturers
Specification
Manufacturers
Specification
Minimum
detention time at
Qpeak
Maximum gravity
flow through
velocity at Qpeak
Maximum
centrifugal flow
through velocity
Head loss
(at parshall flume)
Aeration
requirement
Chamber
dimension:
Depth: Width
Length: Width
Estimated grit
quantity
Washing and
dewatering of grit
2:1
m3/103 m3 of
sewage
0.03
0.03
0.03
No
Yes
Yes
Notes:
* Air lift pump for removal of grit is not acceptable.
* Water depth in tank to be controlled by weir outlet.
104
Volume 4
Malaysian Sewerage
Industry Guidelines
5.6
5.6.1
c)
b)
5.6.2
Design Requirements
The design requirements for balancing tanks are:
a)
c)
b)
d)
e)
f)
Volume 4
105
Mixing power
requirements
Aeration
W/m3 of
sewage
5.7
Unit
Volume of tanks
Design Criteria
m3 air/hour/
m3 sewage
Yes
5.7.1
Purposes
The purposes of primary sedimentation are:
a)
b)
c)
5.7.2
Design Requirements
The design requirements of primary sedimentation include the
followings:
a)
b)
106
Volume 4
Malaysian Sewerage
Industry Guidelines
c)
e)
d)
f)
g)
h)
i)
j)
i)
(k)
Volume 4
107
Unit
Design Criteria
m /m /d
3
- rectangular (maximum)
Weir loading at Qpeak
2
45
m /m /d
m /m/d
45
150
m/hr
1.2 - 2.0
> 3:1
2.5
1 : 1 to 2.5 : 1
5.8
5.8.1
Introduction
> 3.0
1:12
b)
c)
108
Volume 4
Malaysian Sewerage
Industry Guidelines
5.8.2.1
General Description
The conventional activated sludge process is one of the many versions
of the activated sludge process. The activated sludge process is most
suitably used where land is limited and expensive, and where large
volumes must be treated economically, without creating nuisance to
neighbours.
The process involves the production of activated mass of microorganisms
capable of stabilising sewage aerobically. This is achieved by introducing
organic waste, produced from pre-treatment and primary treatment
facilities, into reactors where suspended aerobic bacterial culture oxidises
the organic matter into stable matters. These active bacteria cultures are
commonly known as activated sludge. During the process, new bacteria
cell are also produced.
5.8.2.2
Volume 4
109
Unit
Sludge yield
hrs
kgO2/kg substrate
mg/l
kg sludge
produced/kg BOD5
consumed
Sludge age #
day
m3/d
Must be provided
2
Design Criteria
m3/d
0.25 - 0.50
1500 -3000
Typical: 2500
1.0
Continuous, 24 hrs
0.8 - 1.0
5 - 10
Cu is underflow concentration
QRAS / QINFLOW
0.75-1.0
4 6 of Qavg
hrs/day
24
Organic loading
kg BOD5/kg MLSS
0.25 - 0.5
W/ m3
20
Volumetric loading
110
kg BOD5/m3.d
Volume 4
0.3 - 0.6
Malaysian Sewerage
Industry Guidelines
Unit
Unit
Tank dimension
Tank dimension
Water depth
Water depth
Length:Width
Length:Width
Max width
width of
of joined
joined tank
tank
Max
# Sludge Age =
m
m
Design Criteria
Design Criteria
35
<30
3:1
35
3:1
< 30
VT u MLSS
Q avg u SSeff
T sludge
WAS =
Cu
>
Where:
vT
= volume of reactor (m3)
3
MLSS = mixed liquor suspended solids (kg/m )
Tsludge
Qavg
SSeff
Cu
Refer Table D1 and D2 for aeration equipment duty / standby and also to
Refer
Table
D1ofand
forfor
aeration
equipment duty/standby and also to
relevant
clause
MSD2
1228
more details.
relevant clause of MS 1228 for more details.
5.8.3
5.8.3
5.8.3.1
5.8.3.1
Volume 4
111
Volume 4
99
5.8.3.2
Description
Minimum number of aeration tanks
F/M ratio
Sludge age #
Waste activated sludge flow, QWAS
Return activated sludge flow, QRAS
Unit
18 - 24
2.0
mg/l
2500 - 5000
Typical: 3000
2.0
mg/l
kg sludge produced/kg
BOD5 consumed
day
m3/d
m3/d
24
0.5 - 1.0
Water depth
Length:Width
Max width of joined tank
m
ratio
m
Volume 4
> 20
Refer to equation
Cu is underflow
concentration
hours/day
W/m3
0/66
[ 4DYJ
&X 0/66
kg BOD5/m .d
112
0.05 - 0.1
hrs
kgO2/kgsubstrate
Design Criteria
4 6 times of Qavg
0.1 - 0.4
20
35
3:1
< 60
Malaysian Sewerage
Industry Guidelines
Requirements
for Individual
Treatment
Requirements
for Stages
of SewageProcesses
Treatment
Notes:
#
Sludge Age =
Notes:
#
Sludge Age =
VT u MLSS
Q avg u SSeff
T sludge
WAS =
Cu
>
VT u MLSS
Where:
T sludge
in effluen
WAS =
= volume+ofsolids
reactor
(m3)
vT excess sludge wasting/day
Cu
MLSS
= mixed liquor suspended solids (kg/m3)
Tsludge
= sludge age (days)
Where:
= average flow (m3/day)
Qavg
= volume of reactor (m3)
vT
SSeff
= effluent suspended solids (kg/m3)3
MLSS
= mixed liquor suspended solids (kg/m
)
Cu
= underflow concentration (kg/m3)
Tsludge
= sludge age (days)
= average flow (m3/day)
Qavg
Refer
Table D1 and D2 for aeration equipment duty /
SSeff
= effluent suspended solids (kg/m3)
relevant
clauseconcentration
of MS 1228(kg/m
for3more
details.
Cu
= underflow
)
Anoxic Zone
Aeration Tank
Flow
Final Clarifier
Figure 5.11 Fine Bubble Diffuse
Air
Extended
Aeration System
Distribution
Grit Removal Diffuse Air Extended Aeration System
Figure 5.11 FineScreens,
Bubble
Raw
Sewage
Inlet
Anoxic Zone
Aeration Tank
Flow
Distribution
Sewage
Pump Station
Screens, Grit Removal
Effluent
To River
Final Clarifier
Effluent
To River
Return Sludge
Pump Station
Raw
Sewage
Inlet
Sewage
Pump Station
Return Sludge
Liquor
Pump Station
Chemical
Dosing
Mechanical Sludge
Dewatering
Liquor
Chemical Mechanical Sludge
Thickener
Dosing
Ultimate Disposal
Mechanical Sludge
Dewatering
Mechanical Sludge
Thickener
Ultimate Disposal
OPTIONAL
Sludge Drying Bed
OPTIONAL
Volume 4
Volume 4
113
101
M echanical R otor
Flow
Distribution
Final Clarifier
Flow
M easurem ent
E ffluent
To River
O xidation Ditch
S ewage
P um p S tation
R eturn S ludge
P um p S tation
Chem ical
D osing
M echanical S ludge
Dewatering
M echanical Sludge
Thickener
O P TIO N AL
5.8.4
5.8.4
Rotating Biological
BiologicalContactors
Contactors
(RBC)
Rotating
(RBC)
5.8.4.1
5.8.4.1
General Description
Description
General
Rotatingbiological
biological
contactors
series
of media
rotating
media for
Rotating
contactors
use a use
seriesa of
rotating
for biological
biological
treatment.
The
rotating
medium,
typically
made
from
sheets
treatment. The rotating medium, typically made from sheets of high quality
of highprovides
quality aplastic,
surface on
which
organisms
grow.
plastic,
surface provides
on which aorganisms
grow.
As the
media rotate,
As
the
media
rotate,
the
fixed
film
biomass
is
in
contact
with
organic
the fixed film biomass is in contact with organic pollutions in sewage and
pollutions
in sewage alternately.
and oxygenLayers
in atmosphere
oxygen
in atmosphere
of biomassalternately.
are sheared Layers
from theof
biomassofare
from the
the rotation
surface to
of prevent
the media
during of
thetherotation
surface
thesheared
media during
overgrown
fixed
film.
to prevent overgrown of the fixed film.
RBCs
RBCs are
are conventionally
conventionally submerged
submergedtoto40%
40%ofof disc
discdiameter.
diameter. Increased
Increased
submergence
90%
is also
acceptable
if sufficient
air
submergence ofofdiscs
discsupuptotoabout
about
90%
is also
acceptable
if sufficient
supply
is
provided
at
the
base
of
the
tank.
This
system
is
normally
called
air supply is provided at the base of the tank. This system is normally
the
submerged
biologicalbiological
contactor contactor
(SBC).
called
the submerged
(SBC).
5.8.4.2
5.8.4.2
Design
RBC
Plants
Design Requirements
Requirementsforfor
RBC
Plants
Preceding
Preceding the
the RBC
RBC must
must be
be aa primary
primary sedimentation
sedimentationtank
tankororaa secondary
secondary
screening with <6 mm opening. A flow balancing tank must also be
screening with < 6 mm opening. A flow balancing tank must also be
provided unless the plant is designed to peak flow.
provided unless the plant is designed to peak flow.
Units must be covered for aesthetics and odour control, and only approved
Units must
for aesthetics and odour control, and only approved
media
typesbe
arecovered
accepted.
media types are accepted.
114
Volume 4
102
Volume 4
Malaysian Sewerage
Industry Guidelines
Malaysian Sewerage
Industry Guidelines
Unit
Unit
Total BOD
specific
loading
g/m /d
Minimum
number
of stages
5
5 - 10 3
Total
BOD5 specific loading
Total tank
volume
Design Criteria
Design Criteria
5 -210
Based on
hrs at Qavg
g/m2/d
0.9
kg excess sludge/
Based on 2 hrs at Qavg
kg BOD5 consumed
Sludge yield
kg excess sludge/
0.9
Disc diameter
m
kg BOD5 consumed 2.5 - 3.5
Speed of rotation
rev / min
0.5 - 1.0
Disc diameter
M
2.5 - 3.5
Maximum peripheral velocity m/s
0.3
Speed of rotation
rev / min
0.5 - 1.0
Depth of disc submergence
%
40 - 90
Maximum peripheral velocity m/s
0.3
Sludge yield
Total tank volume
40 - 90
Refer also to Table D.3 for duty standby requirements and relevant clause of
MS
1228
Refer
alsofor
to more
Table details.
D.3 for duty standby requirements and relevant clause of MS
1228 for more details.
Figure 5.13 Rotating Biological Contactor (RBC) Systems
Figure 5.13 Rotating Biological Contactor (RBC) Systems
Rotating Biological
Contactor
Screens, Grit Removal,
Flow Measurement
Fine Screen
Raw
Sewage
Inlet
Flow
Distribution
Final Clarifier
Balancing
Tank
Sewage
Pumping
Station
Effluent To
River
Liquor
Chemical
Dosing
Mechanical
Sludge Dewatering
Mechanical
Sludge Thickener
Ultimate Disposal
SludgeDrying Bed
OPTIONAL
Volume 4
Volume 4
115
103
5.8.5
Trickling Filter
5.8.5
Trickling Filter
5.8.5.1 General Description
5.8.5.1
General Description
The trickling filter is an established biological treatment process removing
65 to 85%
and suspended
solids.treatment
The process
of a bed
The trickling
filterBOD
is an5 established
biological
processconsists
removing
65 to 85%
BOD
and
suspended
solids.
The
process
consists
of
a
bed
of
of highly 5permeable medium. An overhead rotating distributor applies
highlysewage
permeable
An The
overhead
to medium.
the media.
flowrotating
tricklesdistributor
over andapplies
flows sewage
downward to
to the the
media.
The
flow
trickles
over
and
flows
downward
to
the
underdrain
underdrain system.
system.
The media provides a large surface area to develop biological slime
The media
provides
to developfilm.
biological
slimecontains
growth living
growth
whichaislarge
alsosurface
knownarea
as zoogleal
The film
which organisms
is also known
as
zoogleal
film.
The
film
contains
living
organisms
that break down organic material in the sewage.
that break down organic material in the sewage.
Many variations of the trickling filters have been constructed, however
Many the
variations
of the trickling
have been
constructed,
recommended
designsfilters
are given
in Table
5.15. however the
recommended designs are given in Table 5.15.
Biofilter
Pump
Station
Fine
Screen
Flow
Distribution
Final Clarifier
Filter
Raw
Sewage
Inlet
Effluent
To River
Sewage
Pump Station
Liquor
Chemical
Dosing
Mechanical Sludge
Dewatering
Mechanical Sludge
Thickener
Ultimate Disposal
OPTIONAL
116
104
Volume 4
Volume 4
Malaysian Sewerage
Industry Guidelines
Malaysian Sewerage
Industry Guidelines
Unit
Organic loading
Design Criteria
kg BOD5/day/m3
0.08 - 0.15
0.15 - 0.5
0.5 - 2.0
> 1.0
Hydraulic loading
m3/day/m2
Sludge Yields
kg sludge / kg
BOD5 influent
Low rate
Intermediate rate
High rate
Low-rate filters
Intermediate filters
High-rate filters
1.5
Refer also to Table D.4 for duty standby requirements and relevant clause
MS 1228 for more details.
5.8.6
5.8.6.1
General Description
Sequencing Batch Reactors system is suspended activated sludge system.
In this system, sewage flows into one or more reactors where biological
oxidation and clarification of sewage take place within the same reactors
sequentially on cyclical mode. There are five (5) basic sequences in a
cycle, namely:
Volume 4
117
1.
Fill
3.
Settle
2.
4.
5.
React (Aeration)
Decant
Idle
118
Volume 4
Malaysian Sewerage
Industry Guidelines
unit
Minimum 2
Minimum 2
Hydraulic retention
time at Qavg (at
average water level)
hr
18 24
18 24
F/M ratio
d-1
0.05 0.08
0.05 0.30
Sludge age
20 30
10 30
kg Sludge
0.75 0.85
0.75 1.10
mg/l
3000 4500
3000 4500
hr
48
48
DO (Reactor)
mg/l
0 ~ 6.5
0 ~ 6.5
DO (Effluent)
mg/l
2.0
2.0
Parameter
No. of Reactors
Sludge Yield
kg BOD5 load
Oxygen Requirement
kg O2
kg Substrate
Cycle time
Aeration Time
2.0 kg O2
kg substrate
Cycle time
Aeration Time
2.0 kg O2
kg substrate
Decant time
hrs
1.0
1.0
Decant depth
Max 0.5
max 1.0
Decant volume
m3/m/hr
2 nos. independent
decanter per tank
4.0
4.0
Decanting device
loading rate*
Minimum number of
decanter
Max. pecanter length
WAS
kg sludge/d
Fill volume
*
*
m3
Total solids in system
Total solids in system
Was=
Was=
Slude age
Slude age
Vfill = (QP m3/hr x 1.5hr)
+ (Tfill 1.5) x QAVG (if no
balancing tank)
Vfill = QAVG x Tfill (if
preceded by
balancing tank)
Volume 4
119
5.8.7
5.8.8
Biological treatment.
c)
Chemical treatment.
b)
Physical treatment.
120
Design Parameters
HRT
(hrs)
MLSS
(mg/l)
1
2
1-2
2-4
2 000 6 000
2 000 6 000
8 - 12
2 000 6 000
4
5
6
2-4
1-2
4
2 000 6 000
2 000 6 000
2 000 6 000
Volume 4
Internal recycle
To get
phosphate
To get
nitrate bac k
Back
1st.
Anaerobic
1st.
Anoxic
1st.
Aerobic
2nd
Anoxic
2nd.
2nd.
Anaerobic Aerobic
Clarifier
Effluent
RAS
Alternatively,
both both
physical
and chemical
treatment
may be used
Alternatively,
physical
and chemical
treatment
maytoberemove
used to
Phosphorus
wastewater.in wastewater.
remove in
phosphorus
TheThe
designer
shallshall
taketake
all necessary
consideration
in theindesign
in relation
designer
all necessary
consideration
the design
in relation
to the
specific
requirements
of
the
receiving
water
in
determining
the
actual
to the specific requirements of the receiving water in determining the
nutrient
removal
requirement
the case byon
case
actual
nutrient
removal on
requirement
thebasis.
case by case basis.
Volume 4
Volume 4
121
109
5.9
5.9.1
Purpose
Effluent from biological processes contains large populations of microorganisms (MLSS). Secondary clarifiers provided after the biological
system allow the mixed liquor organisms/ solid to settle. Clear supernatant
is discharged as the effluent, while some of the settled microorganisms
are returned to the biological treatment system to maintain the MLSS
concentration and excess microorganisms are removed as biosolid to the
sludge treatment facility.
5.9.2
Design Requirements
The design requirements shall include:
I)
a)
c)
b)
d)
e)
f)
g)
h)
j)
i)
k)
l)
m)
II)
a)
122
General
Properly designed air lift pumps are only permitted for PE less
than 1000.
Weirs
If insufficient length is available, then considerations shall be
given for the use of double weir.
Volume 4
Malaysian Sewerage
Industry Guidelines
b)
d)
c)
e)
f)
III)
Circular clarifiers
a)
b)
c)
d)
The minimum side water depth shall be 3.0 m. Greater side water
depths may be used if it can be shown that the mixed liquor is
well denitrified in the aeration tank.
Flow distribution channel/chamber shall be provided for flow
isolation or equalise flow distribution.
The scraper tip travelling speed shall not exceed 0.03 rpm. A
multiple stage reduction unit must be incorporated to achieve
such speed.
IV)
Rectangular clarifiers
b)
d)
a)
c)
e)
Shall not be wider than 6 m per tank to allow for scraper removal,
unless other approved scraper units are available.
Multiple Hoppers
Multiple hoppers are not accepted. This is due to the settling characteristics
of the particles in the flow. Larger and heavier particles settle faster
than smaller and lighter particles, creating difference in the distribution
of sedimentation in different hoppers. This will present operational
difficulties because sludge removal from the hoppers is unequal. To
avoid the non-uniform withdrawal of sludge, each hopper in the multiple
hopper configuration needs a separate pipe and pump or valve on each
outlet.
Volume 4
123
Table 5.18
Description
Design Criteria
Unit
PE 5,000
PE > 5,000
2*
Tank configuration
Square
Circular
Rectangular
Circular
Rectangular #
3**
hrs
m3/d/m2
30
30
kg/d/m2
<150
<150
kg/d/m2
<50
<50
m3/day/m
<180
<180
Continuous
Continuous
Continuous or
batch
Continuous or
batch
3:1 or greater.
m
Width : Depth
3.0
1 : 1 to 2.5 : 1
3.0 **
1:12
Notes:
* For PE less than or equal to 1000 a single clarifier is acceptable.
#
Rectangular tanks are acceptable if equipped with automatic scraping and
desludging devices.
** For square clarifier with 600 slope minimum 1 m side water depth shall
be provided.
124
Volume 4
Malaysian Sewerage
Industry Guidelines
5.10
Disinfection
Disinfection refers to the selective destruction of disease causing organisms
in sewage effluent.
Methods of disinfection can be physical, chemical or radiation.
Continuous disinfection is required for those areas where the discharge
from the sewage works will cause detrimental effect onto the receiving
water course, such as bathing beaches, lakes, etc.
The Commission reserves the right to determine the need for the provision
of a continuous disinfection facility.
The common forms of disinfection that are available for wastewater
applications are:
a)
Chlorination
b)
Ultra-violet (UV)
c)
Others
Chlorination is by far the most common type of disinfection used worldwide. This is due to its effectiveness in providing a good pathogen
kill with relative simplicity in operation and maintenance. However,
chlorination using chlorine gas, requires a higher degree of operational
skills and poses potential health and safety hazards in the shipping and
handling aspects. Therefore, to reduce these hazards, only liquid or
solid hypochlorite (sodium or calcium) shall be used.
Ultra-violet (UV) disinfection differs from chemical disinfection in
that it uses irradiation to induce photobiochemical changes within the
micro-organisms. To ensure effective photochemical reaction taking
place, one of the conditions is that such radiation must be absorbed by
the target molecule (organism). The other condition is that sufficient
radiation energy to alter chemical bonds is made available. Given the
conditions above, it is critical that the effluent prior to disinfection must
be relatively clear of suspended solids. As such, for UV disinfection to
be highly effective in wastewater applications, filtration of upstream of
the UV unit must be made available.
Other forms of wastewater disinfection that are available are maturation
ponds and ozonation. Maturation ponds have been used widely and
successfully in Malaysia. However, the drawback is that a relatively
large area of land is required to provide sufficient retention time in the
pond for the decay of pathogens. Ozone disinfection involves the direct
ozone oxidation or by reaction with the radical by-products of ozone
decomposition. However, due to ozonations relatively new status in
wastewater applications and higher costs at small scale facilities, its
usage for disinfection is still limited.
Volume 4
125
5.10.1
5.10.1
Design Requirements
Requirements
Design
All new STPs must have provision for disinfection infrastructure such
All
new STPs
provision
for structures.
disinfection infrastructure
as contact
tankmust
andhave
other
necessary
The provisionsuch
of as
the
contact
tankfacilities
and other
The provision
of 5.19
the
disinfection
and necessary
equipmentstructures.
shall be in accordance
to Table
disinfection
facilities andshall
equipment
shallout
be in
in continuous
accordance or
to intermittent
Table 5.19
below. The disinfection
be carried
below.
mode. The disinfection shall be carried out in continuous or intermittent
mode.
Table 5.19: Requirements for Disinfection Facility
Table 5.19: Requirements for Disinfection Facility
Description
Description
Class of STP*
Continuous
Continuous
Class 4
Class of STP*
Intermittent
Intermittent
Class 1
Class1 2
Class
Class 4
Class2 3
Class
Type of Disinfection
Chlorination
Chlorination
Class 3
Ultra-violet (UV)
Type of Disinfection
Chlorination
Chlorination
Ozone
Ultra-Violet (UV)
Facility
(1duty/1standby) for
Basic facility structure.
equipment
Ozone
(1Duty/1Standby)
for requirements
Basic facility
*Facility
The Commission may
impose separate
on case by case
equipment
structure.
basis.
* The
Commission
may impose
separateofrequirements
case by case basis.
Figure
5.16
Schematic
illustration
ultravioletondisinfection
system with stilling plate for flow conditioning and
Figure 5.16 Schematic
illustration
ultraviolet
disinfection system with
elongated
weiroffor
level control
stilling plate for flow conditioning and elongated weir for level control
"A"
"A"
FLOW
PDC
TOP VIEW
(Cables removed for Clarity)
FRONT ACCESS
LEVEL PROBE
FLOW
126
Volume 4
114
Volume 4
Malaysian Sewerage
Industry Guidelines
Malaysian Sewerage
Industry Guidelines
5.17 schematic
Profile schematic
of lamp relative
modules
relative
Figure Figure
5.17 Profile
of lamp modules
to inlet
and outlet
to inlet and
outlet structure
structure
Figure 5.17 Profile schematic of lamp modules relative to inlet and outlet
structure
Flapper Gate
Level Control
Disinfection Module
Power & Data
Interconnect Cables
Flapper Gate
Level Control
Flow
Effluent
Channel
UV Protective
Disinfection Module
Effluent
Channel
Station Cleaning
Liner with covet
304 Stainless Steel
Station Cleaning
Liner with covet
304 Stainless Steel
Service
Electrically Operated
Area Jib Host
Electrically Operated
Jib Host
Inffluent
Channel
Flow
Service
Area
UV Protective
Inffluent
Channel
Flow
Flow
Power Distribution
Data center (PDDC)
Power Cable
Signal Cable
from Plant Flow meter
PLAN VIEW
Power Distribution
Data center (PDDC)
Power Cable
Signal Cable
from Plant Flow meter
PLAN VIEW
Influent
Channel
Influent
Channel
Influent
Channel
Influent
Channel
Figure 5.18
Chemical-feed system schematic
Figure 5.18 Chemical-feed system schematic
Figure 5.18
Chemical-feed system schematic
CALIBRATION COLUMN
RELIEF VALVE
CALIBRATION COLUMN
RELIEF VALVE
CHEMICAL
FEED PUMP
CHEMICAL
FEED PUMP
STORAGE TANK
BACK PRESSURE
CONTROL
BACK PRESSURE
CONTROL
STORAGE TANK
Volume 4
Volume 4
Volume 4
127
115
115
c)
d)
e)
f)
g)
h)
i)
j)
128
Volume 4
Malaysian Sewerage
Industry Guidelines
k)
l)
m)
n)
Volume 4
129
UV system
Description
Design Criteria
< 10 mg/l
20 microns
UV Transmittance at 254 nm
65%
Lamp life
12 000 hours
80%
Operating Temperature
18 40 oC
Relative Humidity
> 95% at 40 oC
UV detection System
Standby lamps
Disinfection Standards
Note:
II)
130
Malaysian Sewerage
Industry Guidelines
b)
c)
d)
e)
f)
g)
h)
Volume 4
131
i)
j)
k)
l)
m)
n)
o)
132
Volume 4
Malaysian Sewerage
Industry Guidelines
Dosage
Mixing
Hypochlorinator
system
Equipment
Contact Tank
Contact Period
Maximum depth
Depth : Width
Min no. of passes
Length : Width at
each pass
Wetted Depth :
Width
Calcium or Sodium
6 10 mg/l
Mechanical, baffles or hydraulic jump.
Feed rate adjustable
1 duty/ 1 standby
15 minutes at Qpeak
3m
2:1
4
6:1
< 2:1
Due to the infrequent usage and other health and safety considerations
in an intermittent disinfection system, ONLY liquid hypochlorite,
either calcium or sodium, shall be used.
A chlorine contact chamber shall be provided with a minimum of
15 minutes hydraulic retention time at peakflow. This chamber
shall be of a rectangular configuration with aspect ratios optimised
to promote plug flow conditions. The recommended aspect ratios
are as follows:
i)
ii)
iii)
iv)
Volume 4
133
v)
vi)
c)
d)
e)
f)
g)
134
Calcium or Sodium
Dosage
6 10 mg/l
Mixing
Hypochlorinator
system
Equipment
1 duty/ 1 standby
Volume 4
Malaysian Sewerage
Industry Guidelines
Calcium or Sodium
Contact Tank
Contact Period
15 minutes at Qpeak
Maximum depth
Depth : Width
Min no. of passes
Length : Width at each
pass
Wetted Depth : Width
3m
2:1
4
6:1
< 2:1
5.11
5.11.1
5.11.2
Volume 4
135
Description
Location of flow
meter
Type of Flow
Measurement
Type of flow meter
Method of
measurement
Measurement
times
PE 5,000
PE > 5,000
Inlet or Outlet
Electromagnetic
Electromagnetic
Ultrasonic
Automated or manual
measurement of Staff gauge
to measure height of crest
with calibration curves /
tables
Continuous or Intermittent
Ultrasonic
Automated devices linked to
data logging with integrator
and transmitted to chart
recorder
(minimum 7 days chart time)
Continuous
5.12
5.12.1
Introduction
All treatment processes are capable of producing significant quantities
of sludge which requires to be further treated. The sludge comprises
essentially inert and organic matters that are biodegradable and nonbiodegradable present in sewage, and bacterial cells generated by the
biological treatment processes. The treated sludge, often referred as
biosolids is ready for safe disposal or reuse.
The importance of sludge management increases with the increase in the
amount of sewage treated. Space has to be allowed within the premises
of an STP to accommodate sludge treatment, handling and storage
facilities.
All sludge need to be treated for safe disposal back to the environment.
The minimum requirement for sludge treatment is to achieve stabilize
sludge with a 20% dry solid content.
136
Volume 4
Malaysian Sewerage
Industry Guidelines
For large scale development whereby the full sludge generation will
only be achieved over a certain time period, proper sizing/modulation
of sludge treatment facilities need to be provided in order to achieve
the immediate needs for sludge treatment.
5.12.2
c)
b)
I)
Volume 4
137
b)
III)
138
Volume 4
Malaysian Sewerage
Industry Guidelines
Comments
Primary Sludge
Primary Clarifier
Based on continuous
sludge withdrawal
Imhoff Tank
Conventional
Activated Sludge
System
Standard A/B
Extended Aeration or
Oxidation Ditch
Standard A/B
RBC/SBC/High
Rate Trickling Filter
System
Hybrid System
Secondary Sludge
Note:
Based on the above assumptions, the quantity of waste sludge requiring treatment and disposal can
be estimated. Refer also to design guides related to each of the above individual processes.
5.12.4
Design Criteria
The ultimate aim of sludge treatment is to achieve at a minimum
stabilised sludge with dry solids content of 20% for final disposal.
A combination of various unit processes may be used to achieve this
minimum requirement.
I)
a)
b)
c)
Volume 4
139
d)
e)
f)
II)
Type of Thickening
% Dry
Solids
1.5
Dissolved Air
Flotation
Belt Thickener
Drum Thickener
Centrifuge
Polymer
System
Speed of
Sludge
feed
pump
Backwash
water
system
n/a
n/a
n/a
Yes
Yes with
appropriate
polymer
turndown
ratio
Note:
a) Mechanical thickener shall be designed for 8 hrs/day and 5 days/week
operation.
b) For belt, drum and centrifuge thickener, three polymer injection
points shall be provided
c) Potable water to be provided for polymer mixing system.
140
Volume 4
Malaysian Sewerage
Industry Guidelines
III)
Solid Digestion
b)
c)
Description
Unit
No.
Days
KgVS/m3.d
%
Type of Mixing
Dissolved Oxygen
Aerobic
Digestion
Anaerobic
Digestion
10
18
1.6 4.8
2
Aerators
Diffusers
Tank Shape
Design Criteria
mg/L
Volume 4
Cylindrical
Rectangular
25 diameter
25 length
1-2
0.8 1.6
2-6
Gas Injection
Mechanical
Stirring
Mechanical
Pumping
7.5
Cylindrical
Egg-Shaped
25 diameter
-
141
IV)
Sludge Dewatering
Sludge Stabilisation
Type of stabilisation
process
Design Considerations
Unit
PE 2,000
PE > 2,000
Simple anaerobic or
aerobic digestion
Ambient anaerobic
digestion with good mixing
facility
Days
Dewatering
Type of device
30
30
Belt press
Centrifuge
Filter press
Drying bed
Belt press
Centrifuge
Filter press
Drying bed *
Operating period of
mechanical thickening
and dewatering facility
5 days/week #
8 hours/day
250 days/year
5 days/week #
8 hours/day
250 days/year
1 month holding
Handling capacity of
drying bed
20
4 weeks cycle on
450 mm thick feed
20
4 weeks cycle on
450 mm thick feed
1 month holding
Notes:
a)
Access ramp of at least 1.5 m wide shall be provided at all sludge drying
beds
*
#
142
Malaysian Sewerage
Industry Guidelines
conditions.
Screening
Primary Thickening
Preliminary
Treatment
and Digestion
Anaerobic Digestion
Secondary Thickening
(Optional)
Possible disposal
of Liquid Sludge
Chemical Conditioning
Conditioning
and
Dewatering
Mechanical Dewatering
Drying Beds
Drying Lagoons
Storage at works
Utilisation
and
Disposal
To inlet of STW
or
on-site Liquor Treatment Plant
Composting
Transportation from works
Land Reclamation
Land Application
Forestry/Agriculture
Landfill Site
Volume 4
Volume 4
143
131
V)
Ultimate Disposal
The treatment plant project proponent has to indicate in the
proposal the ultimate disposal options and actual volume for
disposal throughout the life time of the plant.
5.13
Tertiary Treatment
5.13.1
Introduction
Tertiary treatment is associated with the requirements to further reduce
or remove pollutants beyond the levels achieved by common secondary
treatment processes. Such requirements can be in the forms of the
removal of nutrients, such as, nitrogen and phosphorus; lower BOD5 or
SS levels; or trace elements of toxic constituents, such as, heavy metals
or refractory organics.
The various methods of tertiary treatment include simple maturation ponds,
adsorption, chemical treatment and filtration; air stripping, mambrane or
reoxygenation.
Tertiary treatment is required before discharging to very sensitive receiving
waters. The Commission will specify the need for such treatment on a
case-by-case basis, depending upon the sensitivity of the project.
5.13.2
Design Requirement
I)
Filtration system
a)
b)
c)
d)
e)
f)
144
Volume 4
Malaysian Sewerage
Industry Guidelines
g)
II)
b)
a)
c)
d)
e)
III)
Chemical Treatment
b)
a)
c)
IV)
Air Stripping
b)
a)
V)
Reoxygenation
a)
Volume 4
145
b)
Requirements
for
Individual Treatment
Processes
c)
Cascade
reoxygenation
d)
b)
e)
d)Design
Mechanical
reoxygenation
is achieved using
mechanicalisequipment
of structures
or mechanical
equipment
based
such as surface aerators, jet diffusers or diffused air (coarse, fine
amount
of
DO
required
for
the
effluent.
bubble, etc.)
VI)
a)
Mechanical
reoxygenation
is achieved
using mechanical equipment
reoxygenation
and mechanical
reoxygenation
as surface
aerators,is jet
diffusers
or the
diffused
(coarse,
fine
c)such Cascade
reoxygenation
achieved
using on
hydraulicair
design
of
bubble,
etc.) such as, weir overflows, flumes, spillways, etc.
structures,
e)
on the
amount of DO
required for the effluent.
Maturation
ponds
PondMaturation
systems are
normally not encouraged because it requires
ponds
large land area and the inherent difficulty in controlling algal
a)
Pond systems are normally not encouraged because it requires large
growth.
In special
cases, difficulty
where land
is in abundance,
land area
and the inherent
in controlling
algal growth.the
In project
proponent
may where
choose
use
this system.
special cases,
landtois in
abundance,
the project proponent may
(VI)
Figure 5.21 Typical Roof Details for Covered Sludge Drying Bed
Figure 5.21 Typical Roof Details for Covered Sludge Drying Bed
134
146
Volume 4
Volume 4
Malaysian Sewerage
Industry Guidelines
Malaysian Sewerage
Industry Guidelines
Section 6
Requirements for
Ancillary Facilities
148
Volume 4
Malaysian Sewerage
Industry Guidelines
6.1
Introduction
This section defines the minimum requirements of ancillary facilities
to be provided at the sewage treatment plants. These requirements are
crucial in ensuring the workability and operability of the plants.
6.2
i)
ii)
All water supplies and its installation (piping, tanks, air conditioning
drainpipes, gutters and etc.) must be totally isolated from all potential
contact of electrical system by means of total enclosure or suitably
located the electrical system above flood level.
Where required, wash water shall be equipped with booster pump and
where possible, obtain from reclaimed water.
Drawings submitted for approval shall indicate locations of water tapping
point and piping layout. Approval for water tapping should be obtained
from water authority for permanent water supply before submitting
inspection form. All related document, such as water bills and transfer
of ownership, to be submitted before final inspection.
Table 6.1 tabulates the minimum number and location of stand pipe
required in a sewage treatment plant. Typical drawing of stand pipe
are shown in Figure 6.1
Sewerage Treatment Plants
Volume 4
149
1
1
22
33
4
4
Population
Population
Equivalent
Equivalent
1,000
1000
1,001
1001 5000
5,000
5001
20 000
5,001
20,000
>20 000
>20,000
Minimum
Minimum
Numbers
Numbers
Location
Location
1
1
2 2
Inlet Works
Inlet Works
Inlet
Works
and
Treatment
Inlet
Works
and
TreatmentProcess
ProcessUnit
Unit
2 2
Inlet
Works
and
TreatmentProcess
ProcessUnit
Unit
Inlet
Works
and
Treatment
800
76
648
76
64
8
76
608
15 G.I PIPE
76
80
0
100
STAND PIPE
6.3
6.3
Mess
Facilitiesand
andAblutions
Ablutions
Mess Facilities
All
plants shall
shallhave
havea aminimum
minimum
sanitary
set consisting
All treatment
treatment plants
of of
oneone
sanitary
set consisting
of
of
a
toilet
and
wash
basin.
Washing
facilities,
toilets
and
showers
shall
a toilet and wash basin. Washing facilities, toilets and showers shall be
be
provided
operators
all Class
and 4Class
plants
PE
provided
for for
operators
at allatClass
3 and 3Class
plants4with
PE with
greater
150
138
Volume 4
Volume 4
Malaysian Sewerage
Industry Guidelines
Malaysian Sewerage
Industry Guidelines
Guard house with water and power supply shall also be provided for
Guard house with water and power supply shall also be provided for plant
plant more than 20 000 PE.
more than 20,000 PE.
Figure 6.2 Typical for Administration and Mess Facilities Building
Figure 6.2 Typical for Administration and Mess Facilities
Building
16
Covered Porch
Managers /
Engineers Office
Reception Area
General Office
Supervisor's Office
5
Meeting /
Briefing Room
14
8
Workshop
Sample Reception
& Preparation
Male
Toilet
Female
Toilet
Prayer
Room
12
Control Room
10
Pantry
13
11
General Store
Eating Area
16
Note :
9
Toilet / Shower
Volume 4
Volume 4
151
139
6.4
6.4
6.4
Roads and
Roads
andAccess
Access
Roads and Access
All-weather, surfaced
surfaced roads
All-weather,
roads shall
shall be
be provided
provided to
to permit
permit access
access toto all
all
treatment
plants.
The
roads
must
withstand
a
load
of
at
least
15
tonnes.
All-weather,
surfaced
roads
shall
be
provided
to
permit
access
to
all
treatment plants. The roads must withstand a load of at least 15 tonnes.
Such roads
roads
must
also
be
within
plant
access
to
treatment
plants.
must withstand
a the
load
of
atproviding
least
15 tonnes.
Such
mustThe
alsoroads
beconstructed
constructed
within
the
plant
providing
access
each
process
The
construction
shall
with
Such
roads
must unit.
also
be
constructed
within
thecomply
plant
providing
accessWork
to
to
each
process
unit.
The
construction
shall
comply
withPublic
Public
Work
Department
requirement.
Figure
6.3
and
Figure
6.4
illustrate
the
typical
The
construction
shall
comply
with
Public
Work
each
process
unit.
Department requirement. Figure 6.3 and Figure 6.4 illustrate the typical
section of road pavementFigure
and site road.
Department
Figure 6.4 illustrate the typical
section of requirement.
road pavement and 6.3
siteand
road.
section of road pavement and site road.
Figure 6.3
Typical Details of Road Pavement
Figure 6.3 Typical Details of Road Pavement
Figure 6.3
Typical Details of Road Pavement
40 THK. WEARING COURSE
60 THK.
PREMIXCOURSE
BINDER COURSE
40 THK.
WEARING
10 THK. SAND/QUARRY DUST
60 THK. PREMIX BINDER COURSE
10 THK. SAND/QUARRY DUST
Figure 6.4
Typical Road Section of Site Road
Figure
6.4 6.4 Typical
TypicalRoad
RoadSection
Section of Site
Figure
SiteRoad
Road
4000
4000
ROAD KERB
ROAD KERB
ROAD KERB
FALL
FALL
FALL
ROAD KERB
FALL
152
140
140
The on-site road shall be able to provide safe and convenient access for
trucks
or other
equipment
usedsafe
for and
maintenance
purposes.
The
The
on-site
road machinery
shall be able
to provide
convenient
access for
trucks or other machinery equipment
used
for
maintenance
purposes.
The
Volume 4
Malaysian Sewerage
Industry Guidelines
Volume 4
Volume 4
Malaysian Sewerage
IndustrySewerage
Guidelines
Malaysian
The on-site road shall be able to provide safe and convenient access for
trucks or other machinery equipment used for maintenance purposes.
The minimum width of the road shall be 4 meter Where vehicles need
to pass frequently or parking is required along the road, the minimum
width shall be 6 m.
Corner of junction for perimeter internal road for tankers or trucks
access shall have a minimum inside radius of 6 meter. Inside radius
for perimeter road not intended for tankers or trucks access shall be
not less than 4 m.
Cul-de-sac at the end of roads shall be provided with turning area
reserve of not less than 9 m.
Where roads for maintenance vehicles or machineries are not required,
concrete or hard surfaced walkways of at least 900 mm width shall
be provided between each process unit. Concrete hardstanding area
can be laid where storage bins are located. The use of steps shall be
avoided, where possible.
Where the ingress or egress of the treatment plant is near a junction of
a public road, an adequate acceleration and deceleration lane must be
made available between the access road and the junction for vehicles
to safely enter and leave the treatment plant.
Vehicular access shall be provided to all unit processes that require
daily operation and maintenance.
6.5
Drainage
The area of the treatment plant shall be adequately drained and this
shall be arranged to prevent surface water run-off from entering the
process units.
Any cleaning or maintenance process wash water must be returned to
the inlet works via a separate drainage system.
External drainage facilities must be provided for treatment plant along the
slope area. Cut off drainage at the entrance must also be provided.
Volume 4
153
6.6
154
Volume 4
Malaysian Sewerage
Industry Guidelines
600
Volume 4
Volume 4
INTERNAL
COLUMN @ 3m
CONCRETE
6"x6"
X
X
BRICKWALL FENCE
3000
X
X
63 x 63 x 6
THK. ANGLE
225
X X
150
225
M.S. POST
4200
X
X
600 SQ.
X
X
2100
X
X
X
X
X
X
BRICKWALL FENCE
X
X
900
150
2400
155
14 3
300
2200
MIN. 900
2T12
750
300
300
750
75
2T12
2T12
750
45
2T12
T12
R6-200
T12
T12
150
R6-200
T12
T12
T12
T12
R6-100
300
750
4T12 B/W
SURFACE TO BE ROUGHENED
LINKS R6-150
4T12
230
2.) TWO BANDS OF IWK'S COLOUR WITH OVERALL HEIGHTS OF 400mm SHALL BE PAINTED ON EXTERIOR FACE OF THE WALL.
1.) ALL EXPOSED WALL SHALL BE PAINTED WITH ONE UNDERCOAT OF APPROVED RESISTING PRIMER SEALER AND TWO COATS OF
PAINTING
7. PLASTERING AND RENDERING TO SURFACE OF BRICKWALL SHALL BE FINISHED TO A MINIMUM THICKNERS OF 20mm WITH 1:3 CEMENT-SAND NORTAR.
5. BRICKWORK WALLS SHALL BE ANCHORED TO CONCRETE FACES USING GALVANISED FISHTAIL A NCHORS TO LAP IN WITH THE BRICK REINFORCEMENT AT EVERY
FOURTH COURSE COMMENCING TWO COURSES ABOVE GROUND BEAM LEVEL.
4. BRICKWORK SHALL BE REINFORCED WITH EXPANDED METAL OR "EXMET" AT EVERY FOURTH COURSE COMMENCINGS TWO COURSES ABOVE GROUND BEAM LEVEL.
230
SECTION C-C
T12
T12
2T12
2T12
SECTION B-B
750
300
NOTES :
SECTION A-A
T12
125
2T12
115 x 300mm GROUND BEAM
R6-150
2T12
R6-200
100 x 125mm COPING BEAM
R6-150
R6-200
100 x 125mm COPING BEAM
230
2T12
100
2T12
800
2200
MIN. 900
Volume 4
230
230
800
2200
MIN. 900
156
230
3200
Malaysian Sewerage
Industry Guidelines
800
2200
Volume 4
800
PRE-CAST CONCRETE WALL
75mm THICK
T12
T12
SURFACE TO BE ROUGHENED
LINKS R6-150
4T12
230
45
300
2200
- GREEN
PAINTING
1.) ALL EXPOSED WALL SHALL BE PAINTED WITH ONE UNDERCOAT OF APPROVED RESISTING
PRIMER SEALER AND TWO COATS OF APPROVED WEATHER RESISTANT EMULSION PAINT.
2.) TWO BANDS OF IWK'S COLOUR WITH OVERALL HEIGHTS
OF 400mm SHALL BE PAINTED ON EXTERIOR FACE OF THE WALL.
NOTES :
230
SECTION A-A
T12
230
T12
R6-100 C/C
PRE-CAST CONCRETE
WALL 75mm THICK
230 x 230mm
RC COLUMN
AT 3m INTERVALS
2200
75
3200
800
3200
157
158
146
Volume 4
Volume 4
1 NO HORIZONTAL REINFORCEMENT
ANTI-CLIMB
ELEVATION
- GREEN
PAINTING
1 NO HORIZONTAL REINFORCEMENT
SECTION A-A
NOTE :-
SECTION B-B
Requirements for
Requirements
for Ancillary
AncillaryFacilities
Facilities
Figure
6.86.8 Masonry
Masony
Fencing
Figure
Fencing
Malaysian Sewerage
Industry Guidelines
Malaysian Sewerage
Industry Guidelines
6.7
6.8
6.9
Spares
All mechanical units shall be provided with an adequate reserve supply of
critical spare parts. A list of proposed spare parts should be forwarded
for approval when detailed designs are submitted for verification and
approval.
All parts recommended by the manufacturer to be provided with spares
shall be so delivered at the stage of final inspection. Notwithstanding
that, all parts with a life span of 3 years or less shall be provided with
spares
Typical spare parts requirements are provided in Table 6.2. Spare parts
shall be obtained from the original manufacturer of the equipment and
shall be packed and protected for storage to BS1133 requirement.
A set of special tools if required and specific to an equipment including
lifting tackle and greasing equipment necessary for the maintenance,
repair, testing and overhauled of the equipment shall be supplied together
with the spares at the stage of final inspection.
Volume 4
159
1.
2.
Pumps:
Raw Sewage
Submersible
Pumps.
Grit Pumps.
Feeding Pumps.
RAS Pumps.
Sludge Pumps.
Effluent Pumps.
Motors (Electric):
Drives
a)Direct Couple
b)Chain
c)Belt
Mechanically Raked
Screens
5.
Diaphragm Pump
6.
7.
8.
9.
10.
160
Equipment
Progressive Cavity
(Mono) Pump
Blowers
Spare Parts
Bearing
o-ring
oil seal
mechanical seal
wear ring
Impeller (for 3 or more
pump of similar model)
(see Pumps, Motors,
Drives)
one set
one set
one set
one set
one set
one set
one set, whichever parts is
relevant
Bearing
o-ring
oil seal
mechanical seal
one set
one set
one set
one set
gear bearing
chain
sprocket
V-belt
Chain
Chain link
Gear sprocket
(also see Motors,
Drives)
diaphragm
one set
one set
one set
one set
one set
one set
one set
one set, whichever parts is
relevant
one set
rubber stator
Aerator:
Diffused Air
Diffusers
Mechanical (surface, (see Motors, Drives)
brush)
Scraper
rotating collectors
wheel
(see Motors, Drives)
Conveyor
Quantity
Volume 4
one set
Malaysian Sewerage
Industry Guidelines
6.10
Yard Lighting
No.
Equipment
Spare Parts
Quantity
11.
Filter Press
one set
one pair out of every five
pair of plates
12.
Belt Press
one set
one set if the STP has only
one press
13.
Centrifuges
(see Drives)
6.10
Yard Lighting
Population
Equivalent
Minimum
Numbers
of Unit
1 000
1001 5000
5 001 20 000
> 20 000
4
50 meter
Volume 4
Location
Requirements
for Ancillary
Facilities Facilities
Requirements
for Ancillary
250
290
6000
105
105
670
STANDARD GALVANISED
STREET LAMP POST
FRONT VIEW
SIDE VIEW
LAMP POST
6.11
6.12
6.11
Sampling Facilities
Sampling Facilities
6.12
162
150
Volume 4
Volume 4
Malaysian Sewerage
Industry Guidelines
Malaysian Sewerage
Industry Guidelines
6.13
Safety Facilities
Safe access and walkways shall be provided at all process units and
equipment (valves, penstocks, aeration tanks, etc.) that require service
and maintenance. Safety handrails shall also be installed at walkways
and other working areas with a fall greater than 2 m. Typical details
of hand rail are shown in Figure 6.10
All chemical storage facilities shall be provided with a safety shower
and eyewash as well as appropriate warning signs. Liquid chemical
storage facilities shall be bund. Access to the area shall be restricted
using lockable doors/gates.
Provision for fire detection, alarm and fire fighting equipment shall
be complying with the latest requirements in the Uniform Building
Bylaws, the Institute of Electrical Engineers (IEE) guidelines and other
statutory requirements.
All tanks shall not exceed 1.2 m above ground.
Stair case and ladder exceeding 1.2 m shall be provided with
handrail
All plants located adjacent to earth slopes shall be provided with proper
slope protection structures. The slope protection design must be certified
by Qualified Professional Engineer.
6.14
Doors
All external doors shall be of weather proof and suitable for out-door
installation.
Door with sufficient width for the manoeuvre of equipment shall be
provided at the building of pump station, blower room, etc. For opening
more than 4 m wide or 5 m high, motorized roller shutter shall be
provided complete with manual over-ride button, which enables it to
be operated during power interruption.
6.15
Fire Hydrant
For treatment plants above 20 000PE, fire hydrant shall be provided
complying with the requirements of Jabatan Bomba.
Volume 4
163
6.16
Power Supply
Power supply shall be provided to each plant from the approved
source. Drawings submitted for approval shall indicate the locations of
electrical power tapping point and schematic layout plan. Approval for
power supply tapping should be obtained from relevant authority for
permanent power supply before submitting inspection form. All related
document, such as electrical bills, transfer of ownership: to be submitted
before final inspection. Requirement of power shall be finalised prior
to obtaining design approval
Requirement of incoming permanent power supply shall be inline with
Section 4 this Volume.
6.17
6.18
Lifting Requirement
Safe lifting weight in unrestricted area is 16 kg. For heavier objects and/
or very tight locations, provision of crane or access for truck mounted
crane to be made.
Lifting requirements are as follows:
-
-
164
Malaysian Sewerage
Industry Guidelines
All fixed 3 axis type gantry shall come with additional safety features
such as travel stop limit switch, hoist over run limit switch, slow &
fast speed mode and emergency stop (for all type of hoist).
All fixed type outdoor lifting facility futures shall comprise of hoist
parking bay with shade. All fixed type lifting facility shall come with
working platform and excess ladder.
Typical drawings of lifting davits and A-frame lifting facilities are
shown in Figure 6.11 and Figure 6.12.
6.19
Ventilation
Ventilation is the process of letting in outside air into a space so that it
mixes with the inside atmosphere to dilute contaminants and replenish
oxygen. The purpose of ventilation in a sewage treatment plant is
to provide a comfortable and safe working environment for all plant
personnel.
Hence proper ventilation shall be provided as a mean of providing
sufficient fresh air and reducing poisonous or explosive gases in enclosed
or semi-enclosed spaces where access to human is allowed. Ventilation
can be achieved naturally or mechanically:
b)
Volume 4
165
c)
d)
e)
f)
g)
h)
i)
j)
166
Volume 4
Malaysian Sewerage
Industry Guidelines
Table 6.4
Space
Remarks
Wet-Well
30 intermittent
12 continuous
Dry-Well
30 intermittent
12 continuous
Grit Removal/
Screen Area
30 intermittent
12 continuous
Digester Gas
Control Room
30 intermittent
Sludge Gas
Compressor Room
30 intermittent
Enclosed Grit
Loading Areas
30 intermittent
Enclosed Primary
Sedimentation Tanks
30 intermittent
Scum Concentration
Tank
30 intermittent
Chlorine and
Sulphur Dioxide
Rooms
60 intermittent
Filter/Dewatering
Area
12 continuous
30 intermittent
12 continuous
12 continuous
12 continuous
12 continuous
12 continuous
12 continuous
12 continuous
Volume 4
167
k)
l)
m)
6.20
Process Water
The designer is encouraged to provide recycle water facilities from
the treated effluent. The recycle water can be utilised for cleaning and
landscaping purposes.
6.21
Aesthetic
The structure of a treatment plant shall blend with the surrounding
development to improve the aesthetic value of the area. Roof, structure
wall or brickwall fancing can be designed with other than conventional
finishing.
6.22
Close Turfing
Unpaved area within the STP reserve shall be turfed with close turfing.
The type of grass must be cow grass. For slope area, turf must be
pegged to avoid grass wash away during water run-off.
6.23
168
Volume 4
Malaysian Sewerage
Industry Guidelines
Type of insulation
6.24
Painting
Painting shall include all plant and machinery inside buildings, including
pipework, grating, handrailing, internal walls below ground level and
all metal work including machinery.
The conduits and piping shall be appropriately named and labelled
indicating flow directions and painted with the following colour codes
for easy identification:
Chlorine line
orange
-
-
-
-
green
blue
black
grey
brown
Volume 4
169
Colour
Equivalent Colour
Guide
Penstocks/Valves/Manhole Covers
Black
Machinery Guards/Railings/Runways/
Overhead Cranes/Lifting Davit
Yellow
Switchboards
Light Grey
Fencing poles/Gates
Green
Dulux A365-13449
Par Green 3666
Grey
(Weathersheild)
Dulux BS 00A0510235
White
Grey
Dulux BS 00A0510235
Green
Building Stripes
Green
Dulux A910-13448
Par Green 3666
Blue
Dulux A910-11482
Par Blue 2686
Indah Water
Green
Dulux A365-13449
Par Green 1006
Indah Water
Blue
Dulux A365-11483
Par Blue 1007
Notes:
The above painting requirements are not applicable to stainless steel, aluminium,
galvanised metal surfaces except where necessary to comply with statutory health
and safety requirement.
170
Volume 4
Malaysian Sewerage
Industry Guidelines
550
Figure 6.10
1100
21/4
150-250
100
33
550
TUBULAR STANDARDS
1100
1
21/4
150-250
100
12
100
36
TRIANGULAR BASE
3000 C/C
550
1100
550
3000 C/C
Volume 4
Volume 4
159
171
90
50
75
25
25
25
20
20
FL
FL
30
450
30
120
10
6 FILLET WELDED
50
OD=98
0
90
PLAT THICKNESS 10
75
SAFE WORKING
LOAD TO BE
INDICATED
50
25
260
250
1775
25
30
25
20
20
FL
30
450
FL
120
DETAIL `A'
10
6 FILLET WELDED
OD = 118
OD=98
SAFE WORKING
LOAD TO BE
INDICATED
DETAIL `A'
PLAT THICKNESS 10
SECTION
LIFTING DAVIT
250
1775
260
SIDE VIEW
LIFTING DAVIT
DETAIL `A'
OD = 118
SECTION
LIFTING DAVIT
SIDE VIEW
LIFTING DAVIT
2160
1200
1800
203x203x46Kg/m UB
203x133x25Kg/m UB
203x133x
25Kg/m UB
2340
2160
1800
203x203x46Kg/m UB
180
1200
2340
315
203x133x25Kg/m UB
203x133x
25Kg/m UB
300x300x12 PLATE BOLTED TO CONCRETE
1500
TO PROVIDE WITH ROLLER OR FIX TO THE CONCRETE
FLOOR (TO SYSTEM SUPPLIER DESIGN)
2340
2340
SIDE VIEW
FRONT VIEW
A-FRAME WITH I-BEAM
1500
TO PROVIDE WITH ROLLER OR FIX TO THE CONCRETE
FLOOR (TO SYSTEM SUPPLIER DESIGN)
FRONT VIEW
SIDE VIEW
160
172
160
Volume 4
Volume 4
Volume 4
Malaysian Sewerage
Industry Guidelines
Malaysian Sewerage
Industry Guidelines
Malaysian Sewerage
Section 7
Special Requirements
Special Requirements
174
Volume 4
Malaysian Sewerage
Industry Guidelines
Special Requirements
7.1
7.1.1
Definition
Category 1
For temporary treatment of sewage during the upgrading of an existing
sewerage treatment facility
Category 2
For temporary treatment of sewage during initial stage of a new housing
development where it is not feasible to construct a plant of ultimate
capacity during initial stage or it is located within the catchment of a
centralised sewerage system.
7.1.2
During the upgrading of an existing treatment plant, the sewage flows into
that plant shall be directed to a temporary treatment plant for treatment
before discharge. The treatment process of the temporary plant shall
be designed and calculated based on: the duration of the project, total
existing flow and the compliance requirements. The temporary treatment
shall be monitored at regular interval. Approval from the Commission
and DOE must be obtained prior any direct discharge of the untreated
sewage into the receiving watercourse. The temporary treatment plant
shall be located within the compound of the existing site. The temporary
treatment plant shall not be built on other site area unless approval is
granted by the Commission
7.1.2.1
Volume 4
175
Special Requirements
a)
b)
7.1.2.3
7.1.3
176
Volume 4
Malaysian Sewerage
Industry Guidelines
Special Requirements
b)
c)
(II)
7.1.3.2
Volume 4
177
Special Requirements
7.1.3.3
7.1.3.4
7.1.3.5
178
Volume 4
Malaysian Sewerage
Industry Guidelines
Special Requirements
7.2
7.2.1
Introduction
The installation of treatment facilities within buildings whether occupied
or not, including basements of buildings, are not desirable and will
not normally approve. Every effort must be made to come up with an
alternative site or an arrangement to connect to a public system.
Owners must resolve these issues at an early stage of the planning
process. The Commission should be contacted early to establish if an
alternative option is feasible.
If approved, such installations will be subjected to stringent service
condition requirements for the following criteria:
a)
Access
c)
b)
d)
e)
f)
g)
h)
i)
j)
Ventilation
Noise control
Process type
Inlet works
Pre-treatment
Confined space safety
Odour Control
Discharge systems
k)
m)
l)
n)
Sludge handling
o)
p)
Volume 4
179
Special Requirements
7.2.2
Access
a)
b)
c)
d)
e)
g)
f)
h)
II)
180
d)
e)
f)
g)
Malaysian Sewerage
Industry Guidelines
Special Requirements
h)
i)
j)
III)
a)
b)
c)
d)
e)
IV)
Noise Control
a)
b)
c)
d)
Volume 4
181
Special Requirements
V)
Process Type
The type of treatment process must be limited to systems that are easy
to operate and maintain for reasons of:
a)
b)
VI)
Inlet Works
VII)
Pre-treatment
a)
b)
c)
reduce toilet waste and large solids into smaller and finer
particles,
reduce the quantity of screenings
Operators must:
i)
ii)
b)
c)
d)
182
Volume 4
Malaysian Sewerage
Industry Guidelines
Special Requirements
e)
f)
g)
electrical failure
vi)
i)
flooding
explosion
drowning
nausea
IX)
Odour Control
a)
b)
c)
d)
e)
Volume 4
183
Special Requirements
X)
Discharge Systems
Most basement plants will lie below the level of the running drain
levels. Therefore, it is essential to:
a)
provide an effluent collecting sump prior to pumped discharge.
b)
provide a check valve at the end of the discharge pipe to prevent
the backflow from the monsoon drain to the treatment plant.
c)
provide a 100% redundancy of the discharge pumping
capacity.
XI)
a)
b)
XII)
a)
b)
c)
184
Volume 4
Malaysian Sewerage
Industry Guidelines
Special Requirements
XV)
a)
7.3
7.3.1
Definition
A fully enclosed plant is defined as a treatment plant that is designed
such that their treatment unit processes are located within dedicated
buildings.
A fully enclosed plant is to be equipped with additional features
and requirements to minimize adverse impact to the surrounding
environment.
Fully enclosed treatment plant shall comply with the following
criteria:
a)
b)
c)
d)
e)
General Requirements
When approved, fully enclosed treatment plants must comply with the
general requirements set out in Section 3, 4 and 5 of this Volume and
also specific requirements in this Section 7.3 for the following:
i)
ii)
Volume 4
185
Special Requirements
iii)
v)
iv)
I)
Odour Control
The potential for odour generation, its impact and treatment, shall be
considered in all aspects of design.
The range of odorous constituents in such biogenic odours is very
wide and they include: hydrogen sulphide, ammonia, thiols and other
organic sulfur compounds, amines, indole and skatole, volatile fatty
acids and a wide range of organic compounds produced by anaerobic
fermentation.
II)
Noise Control
186
Volume 4
Malaysian Sewerage
Industry Guidelines
Special Requirements
III)
Aerosol Effects
IV)
Specific Requirements
I)
c)
d)
Bins used for the storage of screenings and grit collected in the
pre-treatment area shall be completely covered to reduce visual
impact, odour and to keep vectors away. The designer shall
provide further considerations on the size, type and method of
emptying the bins.
Generally, all unit processes shall be covered or housed within
a building enclosure. This shall include all pre-treatment units,
aeration tanks, and sludge treatment and handling facilities. The
only exception is the secondary clarifier.
The bin shall be located on a bunded, paved area adjacent to an
access road to the treatment plant.
Volume 4
187
Special Requirements
e)
f)
ii)
iii)
g)
h)
i)
j)
k)
Coatings for the concrete and steel shall include coal tar, vinyls
and epoxies in accordance to Section 4.
Covers should be hinged and weigh less than 16 kg to enable
lifting unaided. Beyond a cover weight of 16 kg, assisted lifting
is required.
The materials used for the cover structure depend on the type of
cover selected and the characteristics of the odorous environment.
In general, the materials shall be selected to provide durability, ease
of maintenance, corrosion resistance and be relatively inexpensive.
The three most common materials used for containing odours
are concrete, aluminum and FRP. The design requirements for
each of these are outlined below.
i)
188
Concrete
Volume 4
Malaysian Sewerage
Industry Guidelines
Special Requirements
II)
ii)
Aluminum
iii)
FRP
For waste areas that workers must enter, both blowing and
drawing air shall be used to eliminate dead spots.
Areas designed for personnel entry must include relief systems
to avoid overpressure conditions. Designers must estimate cover
system leakage to determine fan capacity.
Force air ventilation systems should be inspected and tested
periodically to ensure proper air flow and air distribution.
Volume 4
189
Special Requirements
f)
g)
h)
i)
j)
ii)
iii)
iv)
190
Volume 4
Malaysian Sewerage
Industry Guidelines
Special Requirements
k)
III)
a)
b)
c)
d)
e)
f)
g)
h)
IV)
Volume 4
191
Special Requirements
V)
Noise Level
VI)
Sludge Handling
VII)
b)
192
IX)
Groundwater Conditions
a)
Volume 4
Malaysian Sewerage
Industry Guidelines
Special Requirements
b)
The top of the plant shall be located at least 150 mm above the
finished surface level to prevent the inflow of surface run off
into the enclosed plant.
c)
X)
e)
XI)
XII)
Volume 4
193
Special Requirements
7.4
7.4.1
Definition
Covered and buried treatment plants refer to treatment plants with covers
that are placed below ground or not more than 1.2 m above ground level.
Covers are provided to reduce the odour, noise and visual impact.
7.4.2
General
Covered and buried treatment plants have inherent hazard and restriction
in operability in their actual operation and maintenance. The requirements
in the following sections serve to highlight the minimum improvements
that must be made to these plants in addition to those set out in Section
3, 4, 5 and 6 of this Volume.
7.4.3
I)
The design of these tanks must allow for adequate openings so that
the operator can carry out routine operation and maintenance works
in a safe, efficient and effective manner. These requirements apply to
all unit processes that are covered or buried from the inlet works to
the effluent chamber. Staggered square openings of roughly 600 mm
x 600 mm employed in the past for plants of this nature would not be
acceptable. These openings, as a minimum, must be opened top around
the periphery of the tank.
II)
The designer must take into account the confined space and other related
safety issues for entry into such a tank. Provision of proper access into
each individual tank is mandatory. Where the depth exceeds 2.5 m,
steps with intermediate landings must be included. Other requirements,
such as adequate ventilation prior to tank entry, must be considered and
provided in the design.
194
Volume 4
Malaysian Sewerage
Industry Guidelines
Special Requirements
III)
Piping for buried plant shall be exposed and accessible for ease of
maintenance. PVC pipes are not allowed.
The aeration system (diffuser) must be retrievable from top opening
without emptying the tank.
VI)
Lighting
Hand Railings
Hand railing provisions must be made to prevent falling into open spaces.
These hand rails must be provided on the perimeter of the open tanks
and further enhanced with kick plates.
VI) Desludging Activities
Adequate access within the proposed treatment plant site is to be made
available to allow for desludging tankers to be within the reach of the waste
activated sludge storage tanks without undue difficulty of maneuvering
the vehicle or damaging the buried tanks or pipe works.
VII) Labeling of Treatment Unit Process
Labeling of each treatment unit is to be provided, from the inlet works
to the secondary clarifiers, to avoid confusion with the similar geometry
and sizes used for most treatment units.
VIII) Noise Control
Due to the compromised buffer requirements and proximity to adjacent
developments, the potential for noise pollution is accentuated. The designer
must ensure all noise generating mechanical and electrical equipment
within the treatment plant must be contained and treated acoustically to
meet compliance to existing noise levels stipulated by the Department
of Environment and that set out in Section 4.
IX) Ventilation
Adequate ventilation must be made available to allow for the safe routine
operation and scheduled maintenance of the treatment plant. During
Volume 4
195
Special Requirements
Odour Control
Buoyancy Effects
The designer must account for the buoyancy effects in the design of buried
or covered tanks. This effect is of concern during high groundwater
conditions and emptying of the tank content during desludging works.
Furthermore, the designer must ensure that the design of these tanks
accounts for the hydrostatic force exerted on the floor from the outside
does not exceed the compressive strength of these covered or buried
tanks. This is to prevent any breakthrough of the floor and subsequent
failure of the tank.
The designer must ensure that the design of these tank at worse case
scenario where the tank is fully emptied. This is to prevent any breakthrough
of the floor and subsequent failure of the tank.
XII) Covers
Covers if employed for odour, visual and noise impacts shall be subjected
to the following requirements:
a)
Lifting may be unaided if the covers are hinged and weigh less
16 kg.
b)
Assisted lifting is required if the covers weigh equal to or above
16 kg.
c)
The cover shall comply with BS EN124 loading requirements.
d)
If the cover is exposed to the environment,
i) Plastic or fibreglass cover if used, must be manufactured with
UV inhibitor and will not warp or deform due to weathering
effect.
ii) Metal covers if used, must have appropriate corrosion resistant
coating in accordance to Section 4 of this Volume.
iii) Where chipping might occurs at the edge of the cover,
stainless steel reinforcement frame on all sides of a plastic
or FRP cover shall be provided.
XIII) Fencing
Adequate fencing must be provided for all plants. Adequate security
shall be provided against unauthorised access.
196
Volume 4
Malaysian Sewerage
Industry Guidelines
Special Requirements
7.5
7.5.1
The owner must provide all septic tanks as part of the owners infrastructure
works.
7.5.2
7.5.3
i)
ii)
Volume 4
197
Special Requirements
iii)
iv)
v)
7.6
7.6.1
Introduction
This section describes the types of incidents, which are outside the
control of the operator that may cause a sewage treatment plant to fail its
effluent consent. Generally, the more sophisticated the treatment process,
the more a process is at risk of failure from one of these incidents. It
would be unreasonable to expect the operator of the treatment plants to
perform within the effluent quality standards following such incidents.
However, the operator must always use his best endeavours to rectify
the situation as soon as practicable following such an incident.
7.6.2
Power Interruption
198
Volume 4
Malaysian Sewerage
Industry Guidelines
Special Requirements
On new works, all treatment plants will be fitted with auto-restart facilities
for immediate resumption of operation when power is reconnected.
II)
Lightning
During periods of very heavy rain, areas of the local sewer network may
suffer such ingress of storm water that surcharge of the sewer system
will result, causing abnormally large flows to arrive at the STP inlet.
Under these conditions, the treatment plant would receive much higher flows
than that designed for and would suffer severe hydraulic overloading.
The effect would be a rapid wash through of sewage and solids causing
the works to fail to meet standards.
IV)
All new plants must be equipped with standby units having an automatic
change over system in the event of failure.
Existing plants may be out of action for several days while repairs are
carried out to failed equipment. To help alleviate this problem, the operator
needs to carry critical spare parts to help speed the repair process.
V)
Volume 4
199
Special Requirements
VI)
Accidental Discharge of
Substances
Defect
200
a)
Minor Defect
b)
Major Defect
Volume 4
Malaysian Sewerage
Industry Guidelines
Special Requirements
7.7
Energy Saving
7.8
a)
b)
c)
Volume 4
201
Special Requirements
202
Volume 4
Malaysian Sewerage
Industry Guidelines
Section 8
Package Sewage
Treatment Plant
204
Volume 4
Malaysian Sewerage
Industry Guidelines
8.1
Definition
A package sewage treatment plant is a form of treatment plant both for fixed
film and suspended growth processes. It shall consist of a prefabricated
biological treatment system and be limited to the development of the
sewage treatment system between the ranges of 150 to 5000 populations
equivalent (PE).
Inlet works
Primary screen.
Pump Station (if applicable).
Secondary screen.
Grit and grease chambers.
II)
a)
b)
c)
d)
e)
f)
III)
Outlet works
a)
8.2
Volume 4
205
8.3
Design Requirement
a)
b)
c)
d)
e)
ii)
The structural design of a tank shall consider all factors that can
affect the strength and integrity of the tank, like soil conditions,
area of installation, etc. All tanks shall be structurally designed
to withstand the maximum earth load and hydrostatic pressure
equivalent to a backfill depth of 1 m.
All civil works of blower house, pump house and control panel room
shall be as recommended in Section 4 and 5 of this Guidelines.
The minimum design life span of the components of the package
sewage treatment plant shall be as Table 8.1 below:
> 50 years
> 50 years
10 years
8.4
8.4.1
8.4.2
Prefabricated Tanks
The physical properties of the tanks for package plants shall meet the
material requirements for STP structures as stipulated in Section 4 of this
MSIG. The prefabricated tanks shall come as complete tanks, thus no
206
Volume 4
Malaysian Sewerage
Industry Guidelines
8.4.2
8.4.3
8.4.3
Prefabricated Tanks
welding, jointing, fabrication/moulding of tanks components is allowed
at The
site. physical
The routeproperties
for delivery
of tanks
tanks shall
be planned
so as
of the
for package
plantsproperly,
shall meet
the
notmaterial
to cause
any
damage
to
road
facilities
and
harm
to
road
users.
requirements for STP structures as stipulated in Section 4 of this
MSIG. The prefabricated tanks shall come as complete tanks, thus no
Process
Units/Components
welding,Treatment
jointing, fabrication/moulding
of tanks components is allowed at
site. The route for delivery of tanks shall be planned properly, so as not to
The following table provides the recommended number of tanks for each
cause any damage to road facilities and harm to road users.
unit process against the PE size. The effective volume consideration is
also
incorporated
in the Units/Components
table.
Process
Treatment
The following table provides the recommended number of tanks for each
unit process against the P.E size. The effective volume consideration is also
incorporated in the table.
Table 8.2 Recommended Number of Tanks and Effective Volume
Table 8.2: Consideration
Recommendedfor
Number
ofUnit
Tanks
and Effective Volume
Various
Processes
Consideration for Various Unit Processes
Max Number of
Tanks
PE 1 000
Max Number of
Tanks
Tanks
PE >1 000
Aeration Tank
Anoxic Tank
Clarifier
Sludge
Holding Tank
Name of Tank
Balancing
Tank
Effective Volume
Volume 4
Volume 4
207
191
Note:
Low water level (LWL) is the minimum submergence level of the pumps
to protect it from damage. It is dependent on the type of the pumps, thus
the low water level shall be set according to the pumps manufacturers
requirement Top Water Level (TWL) is the normal operating water level
with adequate freeboard provided.
8.5
Appurtenances
8.5.1
Piping system
8.5.1.1 General
a)
b)
c)
d)
e)
f)
g)
208
The air distribution pipe used shall be rigid and can withstand
temperatures up to 150 C and pressures of 25% more than the
design pressure of the blower.
Volume 4
Malaysian Sewerage
Industry Guidelines
b)
The air pipe from the blower to the process unit shall be above
ground.
Pumping System
The pumps installed in the package system shall meet the requirements
as stated in Table 8.3 below:
Table 8.3 Technical Requirements of Pumping System
Name of Pump
Transfer Pump
Sludge Transfer
Pump
RAS/WAS Pump
Application Area
Balancing Tank
Sludge Holding
Tank
Clarifier
Minimum Throughlet
50 mm
50 mm
50 mm
Control
Number of Pump
1 duty, 1 standby
Type of Pump
Mechanical
Submersible
Pump
Mechanical
Submersible
Pump or Self
Priming Pump
Necessities
Mandatory
Accessories
Volume 4
Automatic control
by timer and
solenoid valve
1 duty for each tank
PE < 1000 : Air lift
PE 1000 :
Mechanical Pump
209
Note:
1)
2)
8.5.3
Diffuser
a)
b)
c)
8.5.4
8.5.5
FRP
HDPE
Ductile/Cast Iron
Size
Installation
Maximum Deflection
Limit
Class
Personnel Load
210
Volume 4
Malaysian Sewerage
Industry Guidelines
FRP
HDPE
Ductile/Cast Iron
Temperature Range
Standard colour
Black
Coating
Aliphatic acrylic
polyurethane
non-skid coating
Resin
UV Protection
Note:
1.
2.
3.
4.
8.5.6
Black
NA
Black
- Epoxy coating of
200 m
Corrosion
resistant
general purpose
polyester
NA
NA
Ultraviolet-light
inhibitors shall
be added to the
laminate
Carbon black
NA
8.5.7
Landscaping
The landscaping of the sewage package system shall be in accordance
with those recommended in Section 6 of this Guidelines.
8.5.8
Odour Treatment
The odour treatment shall be incorporated into the package sewage treatment
plant and shall follow the requirements stipulated in Section 7.4.
Volume 4
211
8.5.9
8.6
Ancillary Facilities
The requirement and criteria of other ancillaries such as lifting facilities,
road, water tank, stand pipe, etc shall be in accordance with the design
criteria as stipulated in Section 6 and special requirements in Section
7.4.
212
Volume 4
Malaysian Sewerage
Industry Guidelines
Appendix A
Tables
Appendix A - Tables
214
Volume 4
Malaysian Sewerage
Industry Guidelines
Appendix A
Appendix A Tables
Table A1
Table A3
Table A2
Table A4
Table A6
Table A5
Table A7
Table A8
River Clarification
Volume 4
215
Appendix A - Tables
Contaminants
Suspended solids
Biodegradable
organics
Pathogens
Nutrients
Refractory organics
Heavy metals
Dissolved inorganic
solids
216
Volume 4
Malaysian Sewerage
Industry Guidelines
Appendix A - Tables
Constituent
Strong
Solids, total
Medium
Weak
1200
720
350
850
500
250
Fixed
525
300
145
Volatile
325
200
105
350
220
100
75
55
20
275
165
80
20*
10*
5*
400
250
110
290
160
80
1000
500
250
Nitrogen (total as N)
85
40
20
Organic
35
15
Free ammonia
50
25
12
Nitrites
Nitrates
15
Inorganic
10
Chlorides
100
50
30
200
100
50
Grease
150
100
50
Dissolved, total
Suspended, total
Fixed
Volatile
Phosphorus (total as P)
Organic
Volume 4
217
Appendix A - Tables
Table A3
Type
Common Name
Use
Aerobic processes
Suspended
growth
Activated-sludge process
Conventional (plug flow)
Continuous-flow stirred-tank
Step aeration
Pure oxygen
Modified aeration
Contract stabilisation
Extended aeration
Oxidation ditch
Suspended-growth nitrification
Nitrification
Aerated lagoons
Aerobic digestion
Conventional air
Pure oxygen
Combined
processes
Trickling filters
Low-rate
High-rate
Roughing filters
Packed-bed reactors
Anoxic processes
Suspended
growth
Suspended-growth denitrification
Denitrification
Attached
growth
Fixed-film denitrification
Denitrification
218
continued
Volume 4
Malaysian Sewerage
Industry Guidelines
Appendix A - Tables
Table A3
(continued)
Type
Common Name
Use
Anaerobic processes
Suspended
growth
Attached
growth
Anaerobic digestion
Two-stage
Anaerobic filter
Single-stage nitrificationdenitrification
Nitrification-denitrification
Nitrification, denitrification
Attached
growth
Combined
processes
Anaerobic-facultative lagoons
Anaerobic-facultative-aerobic
lagoons
Volume 4
219
Appendix A - Tables
Table A4
Parameters (units)
II
IIA
IIB
III
IV
Ammoniacal Nitrogen
(mg/l)
0.1
0.3
0.3
0.9
2.7
>2.7
BOD5 (mg/l)
12
>12
COD (mg/l)
10
25
25
50
100
>100
DO (mg/l)
5-7
5-7
3-5
<3
<1
PH
6.5-8.5
6-9
6-9
5-9
5-9
Colour (TCU)
15
150
150
Elect. Cond.#
(mmhos/cm)
1000
1000
6000
Floatables
Odour
Salinity# (0/00)
0.5
Taste
500
1000
4000
Total SS (mg/l)
25
50
50
150
300
>300
Temperature (0C)
Normal
2
Normal
2
Turbidity (NTU)
50
50
F. Colif. (counts/100
ml)
10
100
400
5000
5000
5000
5000
(20 000)
(20 000)
> 50 000
50 000
50 000
Geometric mean
220
Volume 4
Malaysian Sewerage
Industry Guidelines
Appendix A - Tables
Table A5
River Clarification
Class
Uses
IIA
IIB
III
IV
Irrigation
Note: This data is adapted from the Water Quality Criteria and Standards for
Malaysia, Final Report July 1986, Department of Environment.
Volume 4
221
Appendix A - Tables
Table A6
Part No.
Content
Preliminary
II
Appointment of Offices
III
IV
VI
VII
VIII
IX
XI
XII
XIII
Appeals
XIV
Regulations
XV
Miscellaneous
The Occupational Safety and Health Act (OSHA) was enacted by the Parliament
in 1994. In general, it is an enabling law in that the duties, responsibilities,
penalties and guidelines are to be followed by each specific industry. The
following table provides an outline of OSHA.
Parts of OSHA have a specific target audience. For example, if the professional
is a designer, then Part V would be applicable with respect to Occupational,
Safety and Health in their design.
222
Volume 4
Malaysian Sewerage
Industry Guidelines
Appendix A - Tables
Table A7
Limits (mg/kg)
Zinc
900
Copper
250
Nickel
150
Cadmium
12
Lead
1000
Mercury
Chromium
1000
Arsenic
150
Volume 4
223
Appendix A - Tables
Table A8
No
Pond sludge
Digested sludge
10
Compost product
Incinerator ash
Source/ Treatment
Process
Option for
Disposal or
Utilization
- Imhoff tanks
- Primary and secondary
clarifiers
- Septic Tanks
- Oxidation ponds
- Aerated lagoons
- Waste stabilization
ponds
D, F, R
- Digesters
- Sludge lagoons
- Anaerobic ponds
D, F, R
- Lime stabilisation
C, D, F, R, S
- Thermal drying
A, C, D, F, L, R,
S, SP
- Drying beds
- Mechanical dewatering
equipment
C, D, I, S
- Drying beds
- Mechanical dewatering
C, D, F, I, R, S
- Drying beds
- Mechanical dewatering
C, D, F, I, R, S
- Composting
A, C, D, F, L, R, S
- Incineration
C, D, S, SP
NOTES:
A = Use in agriculture
C = Disposal to controlled dumpsites
D = Disposal to dedicated sludge disposal sites
F = Use in forestry/non-food crops
I = Incinerate
L = Use for landscaping at public amenity areas
S = Disposal to sanitary landfill sites
R = Use in rehabilitation of degraded
SP = Recycled into special product, e.g. building material
224
Volume 4
Malaysian Sewerage
Industry Guidelines
Appendix B
References
Appendix B - References
226
Volume 4
Malaysian Sewerage
Industry Guidelines
Appendix B - References
Malaysian Standards
MS 29
Specification for aggregates from natural sources for concrete
MS 144
Specification for cold reduced mild steel wire for reinforcement of concrete
MS 145
Specification for steel fabric for the reinforcement of concrete
MS 146
Specification for hot rolled steel bars for reinforcement of concrete
MS 416
Code of practice for the use of structural steel in building
MS 523
Specification for concrete including ready mixed concrete
Part 1
Guide to specifying concrete
Part 2
Methods for specifying concrete mixes
Part 3
Procedures to be used in producing and transporting concrete
Part 4
Procedures to be used in sampling, testing and assessing compliance of
concrete
MS 739
Specification for hot-dip galvanised coatings on threaded fasteners
MS 740
Specification for hot-dip galvanised coatings on iron and steel articles
MS 822
Specification for sawn-timber foundation piles
MS 1037
Specification for sulphate resisting portland cement
MS 1195
Code of practice for structural use of concrete
Part 1
Design and construction
Part 2
Part 3
Special circumstances
Design charts for singly reinforced, doubly reinforced beams and
rectangular columns
MS 1227
Specification for portland pulverised fuel ash cement
MS 1228: 1991
Volume 4
227
Appendix B - References
MS 1241
Specification for fibreglass water tanks - effective capacity of less than 2000
litres
MS 1292
Specification for rubber seals water stops for sealing joints in concrete
MS 1387
Specification for ground granulated blast furnace slag for use with portland
cement
MS 1390
BS 476
BS 1161
BS 1615
BS 3396
BS 3532
BS 3749
Specification for E glass fibre woven roving fabrics for the reinforcement of
polyester and epoxy resin systems
BS 4248
BS 4848
Part 2
Specification for hot finished hollow sections
BS 4921
Specification for sherardized coatings on iron and steel
BS 5493
Code of practice for protective coating of iron and steel structures against
corrosion
228
Volume 4
Malaysian Sewerage
Industry Guidelines
Appendix B - References
BS 7079
reinforcement
European Standard
EN 10088
Stainless Steel
Part 1
Part 3
EN 10029
Specification for tolerances on dimensions, shape and mass for hot rolled steel
plates 3 mm thick or above
EN ISO 9445
Continuously cold-rolled stainless steel narrow strip, wide strip, plate/sheet and cut
lengths. Tolerances on dimensions and form
EN 754
1
2
7
8
EN 755
1
2
3
4
5
6
7
8
Volume 4
229
Appendix B - References
Part 9
EN 1676
Specifications for aluminium and aluminium alloy. Alloyed ingots for remelting.
EN 12373
EN 10162
Specification for cold rolled steel sections. Technical delivery conditions. Dimensional
and cross-sectional tolerances.
EN 13923
EN ISO 8503
EN 10025
EN ISO 2063
Thermal spraying. Metallic and other inorganic coatings. Zinc, aluminium and their
alloys.
EN 14020
Designation
Part 3
Specific requirements
Part 2
Specification for hot finished structural hollow sections of non-alloy and fine grain
steels
230
Volume 4
Malaysian Sewerage
Industry Guidelines
Appendix B - References
Part 2
Welded circular steel tube for mechanical and general engineering purposes. Technical
delivery conditions.
Part 1
Part 2
EN 10297
Seamless circular steel tubes for mechanical and general engineering purposes.
Technical delivery conditions.
Part 1
EN 10305
1
2
3
4
Part 5
Part 6
Reinforcements. Specification for textile glass mats. (chopped strand and continuous
filament mats).
Part 1
Part 2
Part 3
Designation
Methods of tests and general requirements
Specific requirements
EN 10083
ASTM Standard
ASTM D4097
Volume 4
231
Appendix B - References
ASTM E84
ASTM C582
AS 3750.2
AS/NZS 3750.12
AS/NZS 2312
Guide to the protection of structural steel against atmospheric corrosion by the use
of protective coatings.
Other Reference Materials
232
Water Quality Criteria and Standards for Malaysia, Final Report, July 1986,
Department of Environment
Volume 4
Malaysian Sewerage
Industry Guidelines
Appendix B - References
Volume 1
Volume 3
Volume 2
Volume 5
Volume 4
233
Appendix C
Supervisory Control and Data
Acquisition System (SCADA)
236
Volume 4
Malaysian Sewerage
Industry Guidelines
C-1
Introduction: Overview
SCADA is the acronym for Supervisory Control And Data Acquisition, SCADA
or Human-Machine Interface (HMI). The system allows distributed input to be
continuously monitored without the intervention of an operator and allows supervisor
or operator (depending on security level) to remotely control of equipment operating
status.
Data acquisition begins at the Programming Logic Controller, PLC level and includes
meter readings and equipment statuses that are communicated to the SCADA as
required. Data is then compiled and formatted in such a way that a control room
operator using the HMI can make appropriate supervisory decisions that may be
required to over-ride normal PLC controls. (A SCADA system includes all the
pieces, HMI, controllers, I/O devices, networks, software, etc.).
SCADA systems typically implement a distributed database which contains data
elements called tag points. A tag point represents a single input or output value
monitored or controlled by the system. Tag points can be either hard or soft.
A hard point is representative of an actual input or output connected to the system,
while a soft point represents the result of logic and math operations applied to
other hard and soft points. The point values are normally stored as value-timestamp
combinations; the value and the timestamp when the value was recorded or calculated.
A series of value-timestamp combinations is the history of that point.
The SCADA provides a user-friendly front-end to a control system containing
programmable logic controller (PLC) that provide automated, pre-programmed control
over a process. This enables the SCADA system to gather data automatically and
remotely rather than manually and site in-situ.
A SCADA software can be linked to a database (normally SQL-Structured Query
Language), to provide instant trending, diagnostic data, scheduled maintenance
procedures, logistic information, detailed schematics for a particular sensor or
machine, and expert-system troubleshooting guides. Most major PLC manufacturers
have offered integrated HMI/SCADA systems, many of them using open and nonproprietary communications protocols (such as MODBUS or Profibus).
In short, interfacing on of SCADA with PLC offers efficient monitoring and control
of process in a large installation site and with large number of distributed equipment
at a site. SCADA provide alarm notification, historical and on-line trending plots of
control parameters for effective process monitoring and control. SCADA system can
also be implemented with PPM schedule maintenance notification and reminder.
The SCADA that are installed at the remote sites can be linked to a Master Station
via communication system (Radio frequency or WIFI or other on-line communication
channels). The data from an equipment is collected via on-line data acquisition or,
unless otherwise allowed, on batch mode via data logging devices.
Volume 4
237
The SCADA software can also activate alarm messaging to inform the operator
station for exceptional event (critical alarm) reporting. Remote Access Server (RAS)
features can provide for either via Internet or other dial-up method (fixed line and/
or wireless modem).
All the proposed SCADA software shall be scalable and flexible enough to allow the
integration of any additional SCADA controller in future expansion. It shall provide
with many industrial standard protocols to allow the user to integrate easily.
C-2
Purpose
C-3
General Requirements
The SCADA system shall be scalable process control solutions designed to meet
the required automation needs in the sewerage industries. The system shall provide
the required level of performance, flexibility, ease of use, and low life-cycle cost
of ownership, making use of the following technology that includes:
The SCADA system shall be Window based client/server system and make use of
the following technologies:
C-4
Architecture
The SCADA architecture shall be flexible and scalable to allow expansion requirements.
The basic architecture shall incorporate all but not limited to the followings:
238
Volume 4
Malaysian Sewerage
Industry Guidelines
C-5
SCADA Requirement
The SCADA shall utilize all but not limited to the followings available technologies
and features:
Volume 4
239
C-6
Operator Interface
The operator interface station shall allow object based graphics to provide the
HMI for the user with object concern. The system shall employ industry de-factor
standards, such as Microsoft Windows, HTML and the Internet so as to minimize
operator training due to familiarity of operating environment.
Critical information is conveyed using dedicated enunciators for alarms, controller
communication failures, operator/controller messages and equipment downtime
conditions. A dedicated alarm line shows the most recent (or oldest) highest priority,
unacknowledged alarm at all times.
Software system displays shall include but not limited to the followings: Menu/navigation displays
Alarm summary
Event summary
Trends
Operating groups
System status displays
Configuration displays
Loop Tuning displays
Diagnostic and maintenance displays
Summary displays
240
Volume 4
Malaysian Sewerage
Industry Guidelines
Optional Live Video integration shall provide remote viewing and viewing control
features.
Security software feature shall provide restricted access, no access and full access
(plant management).
Network access shall permit authorized operator stations on a network to share a
preconfigured number of connections to the system. This allows a number of users
on a network to access production data on off-line basis.
C-7
Database
The SCADA software shall but not limited to the following real-time database:
Analog configuration parameters
Digital configuration parameters
Accumulator configuration parameters
User defined configuration parameters
Each point in the database has a number of associated configurable parameters, all
of which can be referenced relative to a single tag name.
SCADA shall maintain the real time database that requires frequent high-speed
access as memory resident information and other less frequently accessed data as
disk resident data. Memory resident data is logged to data storage device every
specified time frame defined by the administrator to minimize the loss of data in
the event of loss of power.
C-8
Alarm/Event Management
The SCADA software System shall provide comprehensive alarm and event detection,
management, and reporting facilities. Alarm presentation of alarm / event management
shall include but not limited to the followings:
Volume 4
241
Hierarchical alarming
Alarm/event reporting
Alarm/communication/ message/downtime annunciator
Alarm priority escalation
The standard Alarm Summary display shall allow operators to focus on the problem
at hand by supporting filters. Alarms may be filtered by:
Colors for the various priority levels of alarms can be configured by the user for
display purposes in the Alarm Summary and on custom graphics. The recommended
color codes are provided in Appendix 1. The software shall support configuration
of alarm priority colors and display on all process graphic displays to enables
operators immediately determine critically of the alarm.
The alarm shall annunciate in the status zone blinks with the color of the highest
priority for unacknowledged alarm. The alarms configuration shall consist but not
limited to the followings:
SPV Hi
SPV Lo
Transmitter Hi
Transmitter Lo
Trip
Time out
With each of the configured alarms assigns a priority ranging from "Attention" acknowledge of non-critical alarm that required maintenance attention, "Responsive"
- action required with predefined period, "Urgent" - action required immediately.
The Alarm/Event summary shall list but not limited to the followings:
Alarms
Alarm Acknowledgments
Return to normal
Volume 4
Malaysian Sewerage
Industry Guidelines
C-9
Historian
Historical trend shall provide wide range of sampling frequencies in both datapoint and average formats. The history trend intervals are shall be able to but not
limited to the following displays:
second data-point of pre-defined scale
minute data-point of pre-defined scale
hour data-point of pre-defined scale
minute-average of pre-defined scale
hour-average of pre-defined scale
day-average of pre-defined scale
Month-average of pre-defined scale
The historical data is to be display in various formats describe herewith:
Graphical trend plot displays (average, max, min, and other statically
format)
Tabulation displays (average, max, min, and other statically format)
Query databases of selected parameters.
Volume 4
243
Reports should be generated as required time frame (interval), event-driven, or ondemand basis. Report may be directed to screen, printer, file, or directly to another
computer for analysis or viewing electronically.
C-12 Security
The SCADA software shall provide configurable security levels, control levels
and area assignments. These may be configured for each individual operator or
alternatively for each operator station. The security levels shall be able to configure
the following security levels:
Level
Level
Level
Level
1:
2:
3:
4:
244
Volume 4
Malaysian Sewerage
Industry Guidelines
Area assignments limit operator access to graphics, alarms and point data to assigned
areas, providing effective plant partitioning. Individual operator profiles, including
security levels, control levels and area assignments, are activated when operators
sign on to the system. In addition, area profiles can be created enabling plant areas
to be enabled or disabled for control, between certain time and date criteria.
C-13 Scripting
The software shall have the VB or VBA scripting language enable to allow user to
create script that will run when a display is active or scripts can also be attached
to server objects like point parameters, alarm events, report completion and other
events.
C-14 Interfaces
SCADA software provides Data Acquisition and Control facilities to communicate
with a wide range of controllers and Remote Terminal Units (RTUs). The controllers
connection type shall comply with the following communication protocol:
Serial / TCP/IP / ControlNet / Modbus+ / ASCII / TCP/IP / Ethernet
Data Acquisition supports acquisition of data using either:
Periodic Scanning
Volume 4
245
The DVM shall base on open system hardware that digitizes video from standard
video cameras and transports the video to SCADA software clients anywhere on
the network for real-time viewing.
IMM enables the automated creation, assignment, tracking and closing of maintenance
work orders. If required, work orders can also be manually raised. This is all
managed from either your IMM SQL server database with full access available
through the open Web-based interface of IMM.
246
Volume 4
Malaysian Sewerage
Industry Guidelines
Batch Report
Downtime analysis
Schedule maintenance
Statistical Process & Quality Control (SPQC)
Event archiving
Alarm messaging (SMS or pager)
Volume 4
247
248
Volume 4
Malaysian Sewerage
Industry Guidelines
1 sec
< 2 sec
< 2 sec
Standard
Sampling
Rate
Default
Duration
1 minutes
24 hours
1441
69 days
100 000
6 minute
average
7 days
1682
416 days
100 000
1 hour
average
7 days
170
11.4 years
100 000
8 hour
average
3 months
281
91.2 years
100 000
24 hour
average
1 year
368
273.8 years
100 000
Default
Samples
Volume 4
Maximum
Duration
Storage Capacity
(maximum no. of
samples)
249
Attachment C - 1:
Status/Alarm
Event State
250
Notes of Event
Running
Green (Non-Blinking)
Equipment is in operating
status
Standby
Red (Non-Blinking)
Equipment is in standby
operating status
Off
Red (Blinking)
Trip
Amber (Blinking):
SP High Level
Yellow (Non-Blinking)
SP Low Level
Transmitter Hi
Yellow (Blinking)
Transmitter Lo
Time Out
Amber (Blinking)
Volume 4
Malaysian Sewerage
Industry Guidelines
PLC System
DO
DI
AO
Indicator
Data Record
Indicator
Measure
Battery Charger
Penstock
SCADA Control /
Monitoring
Indicator
Indicator
Analog (A)/
Digital (D)
AI
Description
of Control
Point
(For Each
Equipment)
Description of Monitoring
Point
(For Each Equipment)
Instrumentation
Panel
Qty
Item
Attachment C - 2:
Indicator
IP open close
control
Indicator
Indicator
Inlet
Indicator
Remote
Control
Indicator
Measure
Screen - Trip
Indicator
Indicator
Remote
Control
Reset of HourRun meter
Differential
Downstream
Screen - Run
Indicator
Level
RSP Pumps
Pump - Run
Pump - Trip
Pump - Off (MCCB)
Pump - Ampere
Pump - Voltage
Indicator
Indicator
:
Indicator
Indicator
Indicator
Indicator
Remote Start/
Stop
Reset of HourRun meter
Reading
Reading
1
1
1
1
1
1
1
1
1
1
Volume 4
251
AO
DI
DO
RJ45 / RS485
Cut-off operation
Control Start / Stop operation
by diff. level
Control Start / Stop operation
by diff. level
Control Start / Stop operation
by diff. level
Control Start / Stop operation
by diff. level
Parameters Setting
/ Review
Float level
US Level
Level
measurement
Indicator
Indicator
Indicator
Indicator
Indicator
Indicator
Indicator
Indicator
Indicator
Pump - Trip
Indicator
Indicator
Indicator
Ampere / Volmeters
Indicator
Remote Start /
Stop
Reset of Hour-Run
meter
Pump - Ampere
Reading
Float level
Pump - Voltage
Indicator
Screen - Run
Indicator
252
Screen - Trip
Indicator
Indicator
Indicator
Remote Control
1
1
Volume 4
1
1
1
Indicator
Indicator
Indicator
Cut-off operation
Control Start / Stop operation
by diff. level
For fault identification
Reading
SCADA Control /
Monitoring
AI
Description of
Control Point
(For Each
Equipment)
Description of Monitoring
Point
(For Each Equipment)
Analog (A)/
Digital (D)
Qty
Item
Malaysian Sewerage
Industry Guidelines
DO
DI
Screenings Conveyor
AO
AI
Description of
Control Point
(For Each
Equipment)
Description of Monitoring
Point
(For Each Equipment)
Analog (A)/
Digital (D)
Qty
Item
SCADA Control /
Monitoring
Indicator
Indicator
Indicator
Reset of Hour-Run
meter
Indicator
Indicator
Indicator
Remote Control
1
1
1
1
1
Reset of Hour-Run
meter
Indicator
Indicator
Indicator
1
1
Indicator
Remote Control
Reset of Hour-Run
meter
Indicator
Indicator
Indicator
Indicator
Remote Control
1
1
1
1
1
Reset of Hour-Run
meter
Grit Pump : On
Indicator
Remote Control
Indicator
Reset of Hour-Run
meter
Grit Classifier : On
Indicator
Remote Control
Indicator
Reset of Hour-Run
meter
Grit Auger : On
Indicator
Indicator
Volume 4
253
Description of
Control Point
(For Each
Equipment)
AO
DI
DO
SCADA Control /
Monitoring
AI
Description of Monitoring
Point
(For Each Equipment)
Analog (A)/
Digital (D)
Qty
Item
Remote Control
Reset of Hour-Run
meter
Indicator
Remote Control
Reset of Hour-Run
meter
Auxiliary
Indicator
Status
Indicator
Indicator
Reading
Record
Reading
Record
Reading
Indicator
Reading
Record
LV System
Main LV Board Main Breaker
: ON
Main LV Board Main Breaker :
TRIP (Earth Fault)
Main LV Board Main Breaker :
TRIP (Over Current)
Main LV Board Main Breaker :
Ampere
Main LV Board Main Breaker :
Voltage
Room Temperature Monitoring
/ Alarm
Bus Couple : ON
kWHr Meter:
HT System
Battery Charger
254
Indicator
Indicator
Indicator
Status
Indicator
Indicator
Reading
Record
Indicator
Reading
Indicator
1
1
1
1
Record
Reading
kWHr Meter
Transformer System
Reading
Record
CO2 System
TNB Room: CO2 Panel
Activated
Switch Gear: CO2 Panel
Activated
Transformer Room: CO2 Panel
Activated
Indicator
Indicator
Indicator
Indicator
Indicator
Volume 4
Malaysian Sewerage
Industry Guidelines
Fan : Manual
Indicator
Indicator
Indicator
Indicator
Remote Start /
Stop
Remote Start /
Stop
Reset of Hour-Run
meter
Indicator
Indicator
Indicator
Indicator
Indicator
Indicator
Remote Control
Reset of Hour-Run
meter
Level Measure
Pressure Measure
Indicator
Indicator
Indicator
Indicator
Indicator
Indicator
Aeration Blower
Indicator
Remote Start /
Stop
Blower - Trip
Indicator
Blower - Run
Indicator
Remote Start /
Stop
Indicator
Fan : Trip
Fan : To Start / Stop
Indicator
DO
Indicator
DI
SCADA Control /
Monitoring
AO
Description of Monitoring
Point
(For Each Equipment)
Analog (A)/
Digital (D)
AI
Description of
Control Point
(For Each
Equipment)
Qty
Item
Indicator
Indicator
1
1
1
1
1
1
1
1
Volume 4
255
Blower - Ampere
Blower - Voltage
Temperature Sensor
Blower - Temperature
Air Flow Meter
Air Flow Meter
Fan : Trip
Fan : Auto
Fan : ON / OFF
D.O. Meter
D.O. Meter
Anoxic Mixer
Clarifier - Trip
Clarifier - Ampere
256
Clarifier - Voltage
Reset of Hour-Run
meter
Measure
Measure
Measure
Measure
Indicator
Indicator
Indicator
Remote Start /
Stop
Reset of Hour-Run
meter
Indicator
Indicator
Remote Start /
Stop
Reset of Hour-Run
meter
Measure
Measure
Indicator
Remote Start /
Stop
Reset of Hour-Run
meter
Measure
Software counter
Indicator
Indicator
Measure
Indicator
Measure
Indicator
DO
DI
AO
Remote Start /
Stop
Speed Control
SCADA Control /
Monitoring
AI
Analog (A)/
Digital (D)
Qty
Item
Description of
Control Point
(For Each
Equipment)
Description of Monitoring
Point
(For Each Equipment)
Software counter
Volume 4
Malaysian Sewerage
Industry Guidelines
Description of
Control Point
(For Each
Equipment)
Analog (A)/
Digital (D)
AI
AO
DI
DO
SCADA Control /
Monitoring
Qty
Item
Description of Monitoring
Point
(For Each Equipment)
Pump - Run
Indicator
Pump - Trip
Indicator
Software counter
Pump - Ampere
Indicator
Remote Start /
Stop
Reset of Hour-Run
meter
Measure
Pump - Volt
Flow Meter
(Data record of flow rate)
Measure
Measure
Measure
1
1
Record
Record
Measure
Record
Gravity Thickener
Measure / Reset
G. Thickener - Run
Indicator
G. Thickener - Trip
Indicator
G. Thickener - Ampere
G. Thickener - Voltage
Indicator
Remote Start /
Stop
Reset of Hour-Run
meter
Measure
Measure
Indicator
Indicator
Indicator
Remote Start /
Stop
Reset of Hour-Run
meter
Measure
Speed Control
Measure
Gas Blower
Measure
Measure
Indicator
Volume 4
Record
1
1
Indicator
Indicator
Record
257
Measure
Temperature Sensor
Gas Flow Meter
Measure
Measure
DO
Remote Start /
Stop
Reset of Hour-Run
meter
Measure
DI
SCADA Control /
Monitoring
AO
Analog (A)/
Digital (D)
AI
Description of
Control Point
(For Each
Equipment)
Description of Monitoring
Point
(For Each Equipment)
Qty
Item
Record
Measure
Measure
Measure
Measure
Measure
Indicator
Measure
Alarm (Low)
Record & Alarm (High-Low &
Fault)
Indicator
Indicator
Indicator
Indicator
Indicator
Indicator
Indicator
Valve: Full
Valve: Full
Valve:
Valve:
Indicator
Flare Igniter : ON
Indicator
Remote Start /
Stop
Remote Start /
Stop
Indicator
Indicator
Flare Indicator
Indicator
Measure
Indicator
258
Measure
Volume 4
Malaysian Sewerage
Industry Guidelines
Description of
Control Point
(For Each
Equipment)
AO
DI
DO
SCADA Control /
Monitoring
AI
Description of Monitoring
Point
(For Each Equipment)
Analog (A)/
Digital (D)
Qty
Item
Indicator
Indicator
Indicator
Indicator
Speed Control
Indicator
Remote Start /
Stop
Reset of Hour-Run
meter
Measure
Measure
Indicator
Indicator
Indicator
Remote Control
Reset of Hour-Run
meter
Indicator
Indicator
Indicator
Remote Control
1
1
1
1
1
Indicator
1
1
Indicator
Indicator
Indicator
1
1
Reset of Hour-Run
meter
Indicator
Remote Control
Reset of Hour-Run
meter
Indicator
Indicator
Indicator
Indicator
Remote Control
1
1
Volume 4
1
1
1
259
Description of
Control Point
(For Each
Equipment)
AI
AO
DI
DO
SCADA Control /
Monitoring
Qty
Item
Description of Monitoring
Point
(For Each Equipment)
Analog (A)/
Digital (D)
Reset of Hour-Run
meter
Indicator
Indicator
Indicator
Indicator
Remote Control
Reset of Hour-Run
meter
Fan : Manual
Indicator
Fan : Run
Indicator
Fan : Off
Indicator
Remote Start /
Stop
Reset of Hour-Run
meter
Notes:
AI = Analog Input
Qty = Quantity
260
Indicator
Volume 4
DO = Digital Output
Malaysian Sewerage
Industry Guidelines
OFF MODE
EQUIPMENT
PUMPS
(Centrifugal)
PUMPS
(Progressive Cavity)
BLOWER
SURFACE AREATOR
234
ON MODE
Volume 4
Volume 4
261
Malaysian Sewerage
Treatment Plant
OFF MODE
ON MODE
Valves
(General)
BUTTERFLY VALVE
AGITATOR
CONVEYORS
CONVEYORS SCREW
262
Volume 4
Third Edition
Volume 4
Malaysian Sewerage
Industry Guidelines
Page 235
OTHERS
OTHERS
SYMBOLS
EQUIPMENT
PLC CONTROLLER
WIRELESS COMMUNICATION
SCADA WORKSTATION
POWER TRANSMISSION
METER
COMPRESSOR
TANK
236
Volume 4
Volume 4
263
Malaysian Sewerage
Treatment Plant
Appendix D
Duty and Standby Requirements
266
Volume 4
Malaysian Sewerage
Industry Guidelines
Appendix D
Table D1
Table D2
Table D3
Table D4
Volume 4
267
268
Volume 4
Malaysian Sewerage
Industry Guidelines
Volume 4
269
270
Volume 4
Malaysian Sewerage
Industry Guidelines
Volume 4
271
Appendix E
Glossary of Abbreviations
274
Volume 4
Malaysian Sewerage
Industry Guidelines
Glossary of Abbreviations
ABF
Activated Biofilter
AL
Aerated Lagoon
AS
Activated Sludge
ATU
BOD
BOD5
CAS
CF
Certificate of Fitness
CMAL
CMAS
COD
CPR
DMF
DO
Dissolved Oxygen
DOE
Department of Environment
DOSH
DS
Deep Shaft
EA
Extended Aeration
EAMAS
F/M
FAL
FWSP
GRP
HAZOP
HRT
HRTF
MCRT
MLSS
MLVSS
Volume 4
275
276
MOD
MP
Maturation Pond
MS 1228
OD
Oxidation Ditch
OP
Oxidation Pond
OASH
PE
Population Equivalent
Qavg
Average Flow
Qpeak
Peak Flow
QRAS
RAS
RBC
SBC
SBR
SIRIM
SS
Suspended Solids
SPAN
SST
STP
TDH
TF
Trickling Filter
TOL
VSS
WAS
Volume 4
Malaysian Sewerage
Industry Guidelines
PRINTED BY
PERCETAKAN NASIONAL MALAYSIA BERHAD
KUALA LUMPUR, 2009
www.printnasional.com.my
email: cservice@printnasional.com.my
Tel: 03-92366895 Fax: 03-92224773