You are on page 1of 294

Table of Contents

Page

Section 1

Introduction and General Planning Requirements

Purpose of This Volume


Who Should Use This Volume
Related Reference Material
General Planning and Design Approval Requirements
Guidelines for Design Calculations
Guidelines for Drawings

3
3
3
4
5
7

Table 1.1

Recommended Population Equivalent

Figure 1.2 Typical Process and Installation Diagram

10

Figure 1.4 Typical Mass Balance Diagram

12

1.1
1.2
1.3
1.4
1.5
1.6

Figure 1.1 Typical Hydraulic Profile

Figure 1.3 Typical Process Flow Diagram

Figure 1.5 Typical Electrical Single Line Diagram


Section 2

2.1

Design Overview

2.2

2.3

11

12

Treatment Plant Classification

15

2.1.2 Classification by Treatment Plant Capacity

16

2.2.1 General Selection Considerations

16


2.1.1 Classification by Biological Treatment

Processes

Treatment System Selection / Design


2.2.2 Design Stages

2.2.3 Detailed Design Criteria


Safety and Health Principles
2.3.1 General Safety

2.3.2 Structural Safety

2.3.3 Equipment and Electrical Safety

15

16
20
20

23

23
24

25

Table 2.1

Classification by Treatment Plant Capacity

Section 3

Sewage Characteristics and Effluent Discharge Requirements

3.1

3.2

16

Introduction

29

3.2.1 Purpose of Effluent Standards

29

EQA Effluent Standards

3.2.2 Interpretation of EQA Effluent Standards

29
29

3.3

3.4

Design Requirements to Achieve EQA Effluent Standards

30

3.3.2 Design Values

30

3.3.1 Purpose of Design Requirements


Sewage Pollutants Removal

31

3.4.3 Chemical Oxygen Demand (COD)

32

3.4.2 Total Suspended Solid (TSS)

3.4.4 Oil and Grease (O&G)

3.5

3.4.5 Nitrogenous Compound


3.4.6 Phosphorus Compound

Sludge Characteristics and Treatment Requirements

Table 3.1

Design Influent Values

Section 4

Requirements for Physical Design

Table 3.2

4.1

4.2

4.3

4.4

ii

31

3.4.1 Biochemical Oxygen Demand (BOD5)

30

Design Effluent Values

32

32

33

33

34
30

31

Introduction

37

4.2.1 Buffer Zones

37

Treatment Plant Siting


4.2.2 Siting Criteria

4.2.3 Environmental Impact Assessment


4.2.4 Hazard and Operability Studies
Treatment Plant Sizing
4.3.1 Modular Units
4.3.2 Standby Units

4.3.3 Back-up Capacity


4.3.4 Design Flow

Land Area Requirements

4.4.1 Class 1 and 2 Plants

4.4.2 Mechanised Class 3 to 4 Plants

4.4.3 Aerated Lagoons and Stabilisation Ponds


4.4.4 Imperfect Sites

4.4.5 Reduced Land Areas for STPs

37

39

39

40

40

40

40

41

42

42

42

42

43

43

43

4.5

Mechanical and Electrical Requirements

53

4.5.2 Vibration

54

4.5.1 Mechanical Installation

4.5.3 Noise

4.5.4 Safety Around Equipment

4.5.5 Motors, Controllers and Motor Starters


4.5.6 Power Supply Systems
4.5.7 Back-up Generator

4.5.8 Switchgear and Control Gear Assemblies


4.5.9 Control Cabinets

4.5.10 Control Requirements

4.5.11 Supervisory Control and Data Acquisition

Systems (SCADA)

53
54
55

55

57
58

59
60
62

64

4.5.12 Early Warning System (EWS)

65

4.5.14 Cables and Cabling Installation

67

4.6

Table 4.1

Table 4.3

Table 4.2

Table 4.4

Table 4.5

Table 4.6

4.5.13 Instrumentation

4.5.15 Earthing and Lightning Protection


4.5.16 General Purpose Power

4.5.17 Manuals, Drawings and Labelling


4.5.18 Hazardous Areas

Material Requirements for STP Structures and Installations


4.6.1 Concrete and Reinforcement
4.6.2 Steel

4.6.3 Fibre Reinforced Plastic (FRP)


4.6.4 Aluminium

4.6.5 HDPE (High Density Polyethylene)


Modulation Requirements

Land Area Requirements for Class 1


Land Area Requirement for Class 2
Land Area Requirements for

Land Area Requirements for

Required Land Area for Stabilisation Pond and Aerated


Lagoons

65

68

69
69
70

70
70

72

74
76

77
40
44

45
45

46

47

iii


Figure 4.1

STP Land Area Requirements for Planning Layout Approval 49


for New Development

Guidelines For Buffer Zone

Figure 4.2

Figure 4.4

Figure 4.3

Figure 4.5
Section 5

5.1

5.2

5.3

5.4

5.5





5.6



5.7



5.8




iv

STP Land Area Requirements for Structure Plans

50

Plan View of Buffer Zone Requirements

52

Clear Working Space

Requirements for Individual Treatment Processes

51

57

Introduction

81

5.2.1 Purpose of Primary Screens

84

Design of Primary Screens


5.2.2 Inlet Chamber

5.2.3 Design Requirements for Primary Screens


5.2.4 General Requirements
Design of Pump Stations

5.3.1 Purpose of Pump Stations


5.3.2 Design Requirements

5.3.3 General Requirements

84

84

85

86

91

91

91

95

Design of Secondary Screens

100

5.4.2 Design Requirements

100

5.4.1 Purpose of Secondary Screens


Design of Grit and Grease Chambers

5.5.1 Purposes of Grit and Grease Chambers


5.5.2 General Requirements
5.5.3 Design Criteria
Design of Balancing Tanks
5.6.1 Purposes of Balancing Tanks
5.6.2 Design Requirements
Design of Primary Sedimentation Stage
5.7.1 Purposes
5.7.2 Design Requirements
Design of Biological Treatment Stage
5.8.1 Introduction
5.8.2 Conventional Activated Sludge System (CAS)
5.8.3 Extended Aeration System (EA)
5.8.4 Rotating Biological Contactors (RBC)
5.8.5 Trickling Filter

100

101

101
102
103
105
105
105
106
106
106
108
108
109
111
114
116


5.8.6 Sequencing Batch Reactors (SBR) System
117

5.8.7 Design Requirements for Hybrid Systems
120

5.8.8 Design for Nutrient Removal for Sensitive
120

Receiving Water

5.9
Design of Secondary Clarifiers
122

5.9.1 Purpose
122

5.9.2 Design Requirements
122

5.9.3 Multiple Hoppers
123

5.10
Disinfection
125

5.10.1 Design Requirements
126

5.11
Design of Flow Measurement Devices
130

5.11.1 Purpose of Flow Measuring Devices
135

5.11.2 Design Requirements for Flow Devices
135

5.12
Sludge Holding, Treatment and Disposal
136

5.12.1 Introduction
136

5.12.2 Sludge Strategy in General
137

5.12.3 Provision of Sludge Holding, Treatment and Disposal 138

5.12.4 Design Criteria
139

5.13
Tertiary Treatment
144

5.13.1 Introduction
144

5.13.2 Design Requirement
144

Table 5.1

Table 5.2

Table 5.3

Table 5.4

Table 5.5

Table 5.6

Table 5.7

Table 5.8

Table 5.9

Table 5.10

Table 5.11

Table 5.12


Table 5.13

Table 5.14

Requirement for Inlet Chamber


Provision of Primary Screens
Design Parameters for Primary Screens
Recommended Design Parameters for Inlet Pump Stations
Provision Requirement of Secondary Screens
Design Parameters for Secondary Screens
Provision Requirement of Grit and Grease Removal System
Design Parameters for Grit Chambers
Design Parameters for Grease Chambers
Design Parameters for Balancing Tanks
Design Parameters for Primary Sedimentation
Design Parameters for Conventional Activated Sludge
System
Design Parameters for Extended Aeration
Design Parameters for RBC Plants

84
85
86
99
100
101
103
103
104
106
108
110
111
112
v

Table 5.15

Table 5.16


Table 5.17

Table 5.18

Table 5.20

Table 5.19

Table 5.21

Table 5.22

Table 5.23

Table 5.24

Table 5.25

Table 5.26

Table 5.27
Figure 5.1

Figure 5.2
Figure 5.3


Figure 5.4

Figure 5.5


Figure 5.6

Figure 5.7

Figure 5.9

Figure 5.8

Design Parameters for Trickling Filter

117

Design Requirement for Biological Nutrient Removal


System

120

Requirements for Disinfection Facility

126

Design Requirements for SBR System

Design Parameters for Secondary Clarifiers

124

Design Guides for Disinfection with Ultra-Violet (UV)

130

Design Guide for Disinfection with Hypochlorite


Design Guide for Intermittent Disinfection
Design Parameters for Flow Devices
Sludge Generation Rates

Design Parameters for Sludge Thickening

Design Parameters for Aerobic and Anaerobic Digestion


Recommended Design Parameters for Sludge Treatment
Typical Treatment Process Flow Chart

Typical Elements and Process Flow Diagram of a Sewage


Treatment Plant
Typical Drawing of Double Penstock

Quantities of Screenings Collected From Primary Screens


Typical drawing of screen chamber based on depth.
(<5m for different PE)

133

134

135

136

139

140

141

82
83

85

88
89

Typical drawing of screen chamber based on depth.


(<5m for different PE)

90

Typical Dimensions of Dry-well Submersible Pump Station

94

Typical Dimensions of Wet-well Submersible Pump Station

93

Typical details of wet-well pump station

97

Figure 5.10 Typical details of dry-well pump station

98

Figure 5.11 Fine Bubble Diffuser Air Extended Aeration System

113

Figure 5.13 Deep Shaft Activated Sludge System

116

Figure 5.12 Oxidation Ditch Activated Sludge System

Figure 5.14 Rotating Biological Contactor (RBC) Systems


Figure 5.15 Typical Process Flow Diagram for Biological Nutrient

Removal System


Figure 5.16 Schematic illustration of ultraviolet disinfection system

with stilling plate for flow conditioning and elongated

weir for level control

vi

119

114
119

121
126


Figure 5.17 Profile schematic of lamp modules relative to inlet and

outlet structure

Figure 5.19 Chemical-feed system schematic

127

146

Figure 5.20 Sludge Treatment and Disposal Strategy

Section 6

Figure 5.21 Typical Roof Details for Covered Sludge Drying Bed

6.1

6.3

6.2

6.4

6.5

6.6

6.7

6.8

6.10

6.12

6.14

6.9

6.11

6.13

6.15

6.16

6.17

6.18
6.19

6.20

6.21

6.22

6.23

6.24


Table 6.1


Table 6.2

Table 6.3

Requirements for Ancillary Facilities

127
143

Introduction

149

Mess Facilities and Ablutions

150

Water Supply and Wash Water


Roads and Access
Drainage

Fencing and Security

Beautification Zone and Landscape

Stores and Workshops


Spares

Yard Lighting

Sampling Facilities

Auto Restart Facilities


Safety Facilities
Doors

Fire Hydrant

Power Supply

Internal Sanitation (Toilet)


Lifting Requirement
Ventilation

Process Water
Aesthetic

Close Turfing

Standard Roofing and related requirement

Painting

149

152
153

154
159
159

159

161
162

162
163
163

163
164

164

164
165

168
168
168
168

169

Minimum Number of Recommended Water Stand


150
Pipe and Location
Spare Part
161
Numbers of Unit and Location of Compound Lighting

161

vii

Table 6.4

Common ventilation rates

167

Figure 6.1

Standard Details for Stand Pipe

151

Table 6.5

Figure 6.2

Figure 6.3

Figure 6.4

Figure 6.5

Figure 6.6

Figure 6.7

Figure 6.8

Figure 6.9

Painting System Index Colour Standards


Typical for Administration and Mess Facilities Building
Typical Details of Road Pavement

Typical Road Section of Site Road

Typical Drawing of Brickwall Fencing and Gate


Brickwall Fencing
Precast Fencing

Masonry Fencing

Typical Details of Compound Lighting

Figure 6.10 Typical Detail of Guard Rail

Figure 6.11 Typical Detail of Lifting Davit

Figure 6.12 Typical Detail of A-Frame Lifting Facilities


Section 7

7.1

170

152

152

152

155

156

157

158

162

171

172

172

Special Requirements
Temporary Treatment Plants

175


7.1.2 Category 1: Temporary Treatment Plant for

Upgrading of Facilities

175

7.2

7.3

7.4

7.1.1 Definition

7.1.3 Category 2: Temporary Plants for New Housing


Development

176

7.2.1 Introduction

172

Treatment Plants Located Within Buildings

179

7.2.2 Specific Guidelines and Requirements

180

Fully Enclosed Treatment Plant


7.3.1 Definition

7.3.2 General Requirements

7.3.3 Specific Requirements

Covered and Buried Treatment Plants


7.4.1 Definition
7.4.2 General




7.4.3 Specific Requirements for Covered or Buried

Plants under 5,000 PE or Less

viii

175

181

185

185
186

194

194

194

194

7.5

Guidelines for Homestead Developments


7.5.1 Single Developments up to 30 Units or 150

PE in Total

197
197

7.5.2 Single Developments Over 30 Units in Total


with Average Housing Density Greater Than

Five Units per Hectare

197


7.5.3 Single Developments Over 30 Units in Total with

Average Housing Density Less Than Five Units

per Hectare

197

Non-Compliance with Standards

198


7.6.2 Types of Incidents that Can Cause Treatment

Plant Failure

198

198

7.6

7.7

7.8

Section 8

8.1

8.3

8.2

8.4

7.6.1 Introduction

Energy Saving

Recycle and Reuse


Package Sewage Treatment Plant

201
201

Definition

205

Design Requirement

206

Land Area Requirement


Components of Package Sewage Treatment Plant


8.4.1 Layout, Piping and Arrangement of Prefabricated

Biological Treatment System

205

206
206

8.4.2 Prefabricated Tanks

206

Appurtenances

208


8.5

8.6

8.4.3 Process Treatment Units/Components


8.5.1 Piping system

8.5.2 Pumping System


8.5.3 Diffuser

8.5.4 Flow Distribution Chamber

8.5.5 Manhole Cover/Inspection Chamber Cover


8.5.6 Anchor System Loading
8.5.7 Landscaping

8.5.8 Odour Treatment

8.5.9 Ancillary Facilities


Marking and Labelling

207
208
209

210

210
210
211
211
211

212
212

ix


Table 8.1

Minimum Design Life Span of Package Sewage


Treatment Plant Components

206

Technical Requirements of Pumping System

209


Table 8.2

Table 8.3

Table 8.4

Recommended Number of Tanks and Effective Volume


Consideration for Various Unit Processes

207

Technical Requirements of Manhole Cover

210

Appendices
Appendix A Table

Table A1

Table A2


Table A3

Table A4

Table A6

Table A5

Table A7

Table A8

Contaminants of Concern in Sewage Treatment

216

Major Biological Treatment Processes Used for Sewage


Treatment

218

Typical Composition of Untreated Domestic Sewage

217

Interim National River Water Quality Standards for Malaysia 220


River Clarification

221

Permissible limits for potentially toxic elements in soil

223

The Occupational Safety and Health Act 514, 1994 - Brief


Summary of Contents
Options for disposal of Sludge and reuse of bio-solids

Appendix B References

222

224

Malaysian Standards

227

European Standard

229

British Standard

ASTM Standard

AS Standard

Other Reference Materials

Other Guidelines in This Set

Appendix C Supervisory Control and Data Acquisition System (SCADA)

228

231
232

232
232

C-1

Introduction: Overview

237

C-3

General Requirements

238

C-2

C-4

C-5

C-6

C-7

C-8

C-9

C-10
C-11

C-12

C-13

Purpose

Architecture

SCADA Requirement
Operator Interface
Database

Alarm/Event Management
Historian

Graphical Trending
Report Format
Security

Scripting

238
238

239
240

241
241
243

243
244

244

245

xi

C-14

Interfaces

245

C-16

Web Server

245

C-15

Distributed Server Architecture

245

C-17

Digital Video Monitoring

246

C-19

Application Report

247

C-18

C-20

C-21
C-22

Integrated Maintenance Management


Application Programming Interface
User Documentation

Specifications and Sizing

246

247

248
248

Appendix D Duty and Standby Requirements



Table D.1

Duty and Standby Requirements for Activated Sludge


Systems (Utilising Diffused Aeration)

268


Table D.3

Duty and Standby Requirements for Rotating Biological


Contactor Systems

270


Table D.2

Table D.4

Duty and Standby Requirements for Activated Sludge


Systems (Utilising Mechanical Surface Aerator)

269

Duty and Standby Requirements for Trickling Filter Systems 271

Appendix E Glossary of Abbreviations


xii

Glossary of Abbreviations

275

Section 1
Introduction and General
Planning Requirements

Introduction and General Planning Requirements

Volume 4

Malaysian Sewerage
Industry Guidelines

Introduction and General Planning Requirements

1.1

Purpose of This Volume


This volume sets out the requirements of the National Water Services
Commission (SPAN) (referred to as the Commission in this document)
for the planning, design and construction of sewage treatment plants.
This volume contains the following:
a)
b)
c)
d)
e)
f)
g)

An overview of considerations and criteria for sewage treatment


plant design.
Effluent discharge standards requirements and the capacity of
different sewage treatment processes to meet these standards.
Requirements for the siting and sizing of sewage treatment
plants.
Requirements for each stage of sewage treatment.

Minimum requirements for facilities ancillary to a sewage treatment


plant.
Other special requirements for temporary treatment plants, treatment
plants within buildings, homestead developments and exemptions
for non-compliance with standards.
Requirements of sludge treatment process and disposal.

The owner must comply with the requirements set out in this volume
when submitting an application for approval to the Commissioner.
This volume does not cover any aspect other than Sewage Treatment
Plant requirements. All internal plumbing approvals need to be approved
by Local Authorities.

1.2

Who Should Use This Volume


This Volume is primarily for owners, developers, consulting engineers
and Public Authorities whose developments include sewage treatment
plants.

1.3

Related Reference Material


This Volume does not cover all aspects of design and construction of
sewage treatment plants. Where information is not covered in this volume,
the designer shall follow the requirements given in MS 1228.
However, the information in this Volume shall take precedence over
MS1228 where similar aspects are covered in these documents or where
there is conflicting information between the two documents.

Sewage Treatment Plants

Volume 4

Introduction and General Planning Requirements

The procedures for certification of sewerage services are given in the


Malaysia, Volume 2 Sewerage Works Procedures.
All Standards references adopted during this revision exercise are compiled
and given in Appendix B.

1.4

General Planning and Design Approval Requirements


The application procedures for sewage treatment plants approval shall
follow the requirements given in MSIG Volume 2. In general, the
application for approval of a treatment plant shall include:
a)
b)
c)

d)

e)
f)
g)

h)
i)
j)
k)
l)

Sufficient land area for the sewage treatment plants plus additional
area to allow for extensions to the plant, where necessary.
Land of suitable configuration shall be provided.
Sufficient buffer zones.

The location of a sewage treatment plant in relation to a particular


catchment area. The plant unit processes shall be located at an
elevation which is not subject to flooding/wave action, or shall
otherwise be adequately protected against all flooding/wave
action.
Sufficient topographic features shall be included to indicate its
location in relation to streams and the point of discharge of the
treated effluent.
Schematic flow diagrams showing utility systems serving the
plant processes and the flow through various plant units.

Pipeworks, including any arrangements for bypass from individual


units. The direction of flow and the content in the pipes shall
also be clearly and permanently painted onto all exposed piping
works.
Hydraulic profiles showing the flow of sewage, supernatant liquor,
and sludge.

Location, dimensions and elevations of all existing and proposed


plant facilities.

Capacity of the effluent receiving drain/water course shall be able


to cater for additional discharge flow from the treatment plant.

Consideration for odour and noise mitigation and control through


good facility design, effective operation, containment, collection
and treatment.

Point of discharge of treated effluent (effluent outfall) and elevations

Volume 4

Malaysian Sewerage
Industry Guidelines

Introduction and General Planning Requirements

m)
n)
o)
p)
q)
r)

s)
t)

u)
v)

w)

Type, size, features, and operating capacity of all pumps, blowers,


motors and other mechanical devices together with manufacturer
catalogues.
Minimum, average and maximum hydraulic flows, velocities and
top water level in profiles.
Accessibility, landscaping and fencing.
Flow measurement facilities.

Materials, dimensions and specifications.

Ground conditions including levels, type, groundwater level and


safe bearing pressure of foundation.

Details of foundation and other structural design. Slope protection


works are required, where applicable.
All other components of the sewage treatment plant.

A technical report, which covers the whole life cost evaluation


of the plant.
Process and instrumentation diagram.
Mass balance calculation

x)

Clean and legible detailed drawings in standard format

z)

Where required, an EA or EIA report is needed to identify,


predict, evaluate and communicate information concerning the
adverse and beneficial impacts of the proposed treatment plant.

y)

aa)

1.5

of high and low water levels of the receiving watercourse to


which the plant effluent is to be discharged.

Operation and Maintenance needs of the plant to be addressed


at the early planning stage.

HAZOP requirement is necessary to identify the safety and


operability deficiencies in the design and operation of the treatment
plant.

Guidelines for Design Calculations


Design calculation for all unit processes shall be in sequence starting
from inlet works to biological treatments and sludge treatments as
shown in Figure 5.1. The calculation shall include:
a)
b)
c)

Sizing of each unit processes and all mechanical equipment


involved.
Mass balance for overall system and each unit process.
Influent values.

Sewage Treatment Plants

Volume 4

Introduction and General Planning Requirements

d)
e)
f)
g)
h)

Design influent and effluent values in compliance with Section


3.3.2.
Treatment plant shall be designed based on design flow.
Hydraulic profile across the treatment units to be indicated onto
to the drawings.
Each unit process must comply with the design parameters set
in Section 5.
Calculation of PE to be based on Table 1.1.

Table 1.1 Recommended Population Equivalent


Type of Premises/ Establishment

Population Equivalent
(Recommended))

Residential

5 per house

Commercial:

3 per 100 m2 gross area

Includes offices, shopping complex,


entertainment/ recreational centres,
restaurants, cafeteria, theatres
Schools/ Educational Institutions:
- Day schools/ Institutions

0.2 per student

- Partial residential

0.2 per non-residential student

- Fully residential

1 per student

1 per residential student

Hospitals

4 per bed

Hotels with dining and laundry facilities

4 per room

Factories, excluding process water

0.3 per staff

Market (wet type)

3 per stall

Market (dry type)

1 per stall

Petrol kiosks/Service stations

15 per toilet

Bus terminal

4 per bus bay

Taxi terminal

4 per taxi bay

(Ref: Malaysian Standard 1228)

Volume 4

Malaysian Sewerage
Industry Guidelines

Introduction and General Planning Requirements

Table 1.1 - Recommended Population Equivalent (Cont)


Type of Premises/ Establishment

Population Equivalent
(Recommended)

Mosque/ Church/ Temple

0.2 per person

Swimming pool/ Sports complex

0.5 per person

Stadium

0.2 per person

Public toilet

15 per toilet

Airport

0.2 per passenger


0.3 per employee

Laundry

10 per machine

Prison

Golf course
(Ref: Malaysian Standard 1228)

1.6

1 per person
20 per hole

Guidelines for Drawings


All drawings shall be of standard format and orientation. The drawings
required include:
a)
b)
c)

d)

e)

Overall development plan showing the whole sewerage system


and plant location.
Site layout plan showing the arrangement of the plant, buffer
zone, internal set backs and all neighbouring developments.

Site layout plans showing all the process units, main pipe runs,
electrical conduit corridors, site services (water, drains, lighting,
other services), roads and paving, landscaping, buildings, fencing
and finished level contours (or spot levels). The set out and
overall dimensions of the plant shall also be shown.

Site elevations of the plant with at least one section through


the plant in each direction. These sections shall extend at least
30 m from the plant boundary and include an indication of the
surrounding development (in block form only).
Process and instrumentation diagram (P&ID) showing all tanks,
pipes, channels, valves, mechanical equipment, instrumentation
and control loops. The P&ID can also act as a summary of
the design. It provides key details of each piece of equipment,
tank, piping, valves and instruments.

Sewage Treatment Plants

Volume 4

Introduction and General Planning Requirements

f)

g)
h)

i)
j)

Hydraulic profile showing all hydraulic pathways through the


plant including bypasses. Information to be shown includes
pipe sizes, invert levels, flow velocities, tank coping level, top
water level and freeboard. Top water level and velocities at
minimum flow, average flow and peak flow under design load
must be clearly indicated.
Schematic flow diagrams and mass balances showing flow through
all process units in the plant.

General arrangement drawings of each unit process. These


drawings shall be in sufficient details to clearly describe the shape,
size and function of each unit. The drawings shall show the
structure of the unit, piping, valves and fittings, instrumentation,
mechanical and electrical equipment, buildings, handrails, stairs,
ladders, step irons, site services such as water and lighting,
adjoining paving, roadworks, fencing, drainage, etc. Drawings
of all items should show the elevations, plan view and sectional
view (horizontally and vertically), where applicable.
Details are required of any object that would affect the operation
or maintenance of the plant that is not covered by a standard
drawing.
Required to use standard symbols and legend formats for all
drawings.

Volume 4

Malaysian Sewerage
Industry Guidelines

Sewage Treatment Plants

Volume 4

Sewage Treatment Plants

Volume 4

0.2m

0.4m

0.6m

0.8m

1.0m

1.2m

1.4m

1.6m

1.8m

2.0m

F.G.L.

-0.6M
PRIMARY PUMPING VALVE
SCREEN STATION CHAMBER

-0.4m

-0.2m

FGL

F.F.L.

PRIMARY PUMPING VALVE


SCREEN STATION CHAMBER

I.L.

F.G.L.

SECONDARY SCREEN

SECONDARY SCREEN

F.G.L.

CL

I.L.

AERATION TANK

AERATION TANK

TWL

CL

I.L.

TWL
TWL
F.G.L.

CLARIFIER DISTRIBUTION
CHAMBER

CLARIFIER DISTRIBUTION
CHAMBER

F.G.L.

HYDRAULIC PROFILE

I.L.

CLARIFIERS

CLARIFIERS

TWL
TWL
TWL
TWL

F.G.L.

NOTES :

OUTFALL MEASUREMENT
FLUME

HIGHEST FLOOD WATER LEVEL


NORMAL WATER LEVEL

NORMAL WATER LEVEL

FLOOD LEVEL IN RECEIVING


WATERCOURSE

OF ACTUAL PLANT DESIGN AND ACTUAL SITE SURVEY.

2. ACTUAL LEVELS SHALL BE DETERMINE FROM HYDRAULIC CALCULATIONS

1. THE LEVELS SHOWN ARE FOR INDICATIVE PURPOSES ONLY.

CHLORINE CONTACT
TANK

OUTFALL MEASUREMENT
FLUME
CHLORINE CONTACT
TANK

F.G.L.

Introduction and General Planning Requirements


Introduction and General Planning Requirements

Figure 1.1 Typical Hydraulic Profile


Figure 1.1 Typical Hydraulic Profile

Page 7

Introduction and General Planning Requirements

Figure 1.2 Typical Process and Instrumentation Diagram

10

Volume 4

Malaysian Sewerage
Industry Guidelines

Sewage Treatment Plants

Sewage Treatment Plants

Volume 4

Volume 4

Pump

Pump

Raw Sewage

Raw Sewage

Screen

PUMPING STATION (EXISTING)

RAW SEWAGE

SS =

BOD =

Q=

RAW SEWAGE M

SS =

BOD =

Q=

RAW SEWAGE

SS =

BOD =

Q=

Screen

Filtrate =

SCREEN CHAMBER

Filtrate =

=
=

Q
BOD

Skimmer

Water =

Oil Discharge Tank

=
=
=

Q
BOD
SS

Floor Drain Pit

Transfer Pump

GREASE CHAMBER

Oil & Grease Pump

Grit Pump

Grit Classifier

Vortex

Oil Holding Tank

SS

BOD =

GRIT CHAMBER

Mixer
Pump

Balancing

BALANCING TANK

=
=
=

Q
BOD
SS

=
=

Q
BOD
SS

MLSS =

Aerator

Supernatant Decanter

REACTOR

SEQUENCING BATCH

=
=
=

Q
BOD
SS

HOLDING TANK

SLUDGE

Pump

Waste Sludge

TANK

MEASURING

SS

BOD

BLOWER

Introduction and General Planning Requirements


Introduction and General Planning Requirements

Figure 1.3 Typical Process Flow Diagram


Figure 1.3 Typical Process Flow Diagram

11

Introduction and General Planning Requirements


Introduction
Introductionand
andGeneral
GeneralPlanning
Planning Requirements
Requirements

Figure 1.4 Typical Mass Balance Diagram


Figure
Balance Diagram
Diagram
Figure 1.4
1.4 Typical
Typical Mass Balance
INFLOW
INFLOWPARTICULARS
PARTICULARS
QQ = =
BOD
BOD= =
10%
10%SS
SStotobe
beremoved
removed
SS= =
SS
PHYSICALTREATMENT
TREATMENT
PHYSICAL
PRIMARYSCREEN
SCREEN
1)1)PRIMARY
SECONDARYSCREEN
SCREEN
2)2)SECONDARY

QiQi= =
BOD= =
BOD
SS= =
SS

Qi ++ Qr
Qr ++ Qw
Qw
QQ == Qi
BOD ==
BOD
SS ==
SS

Qe
Qe ==
BOD
BOD ==
SS
SS ==

SECONDARY
SECONDARY CLARIFIER
CLARIFIER

AERATIONTANK
TANK
AERATION
MLSS= =
MLSS

OUTLET
OUTLET

OVERFLOW
OVERFLOW SS
SS CONC
CONC==
BOD
BOD ==

Qr
Qr++Qw
Qw==
BOD =
BOD =
SS =
SS =

Qr, Xr
Qr,
Xr
Qr = X Qi =
Qr = X
BOD
= Qi =
BOD
=
SS =
SS =

AEROBIC DIGESTED
AEROBIC DIGESTED
SLUDGE HOLDING TANK
SLUDGE HOLDING TANK

Qw =
Qw ==
BOD
BOD
SS ==
SS ==
1%DS
1%DS =
SLUDGE THICKENER
SLUDGE THICKENER

Qw =
BOD
Qw ==
SS ==
BOD
4%DS
SS =
4%DS =

Qw OVERFLOW =
Qw OVERFLOW =

Sludge to be pumped to Sand Drying Bed


For
Dewatering
to 25% to
Dry
SolidDrying Bed
Sludge
to be pumped
Sand
For Dewatering to 25% Dry Solid

Figure 1.5 Typical Electrical Single Line Diagram


Figure 1.5 - Typical Electrical Single Line Diagram
Figure 1.5 - Typical Electrical Single Line Diagram

SPARE

SPARE

TO COMPOUND LIGHTING (2 nos)


TO COMPOUND LIGHTING (2 nos)

TO 13A SOCKET OUTLET


TO 13A SOCKET OUTLET

24T

24T

20A

20A

0 -3 0 A
0 -5 0 0 V

0 -3 0 A
3 0 A T P + N 1 0SK/s
AwM C C B
4 0 /0 .3 A 4 p R C C B

10A

0 -5 0 0 V

10A

S /s w
S /s w
4 0 /0 .3 A 4 p R C C B

20A

3x5A

TO 36W FLOUERECENT LIGHT


TO 36W FLOUERECENT LIGHT

B
6A

R SY/s wB

20A

RAW SEWAGE
SUBMERSIBLE
RAW SEWAGE
SUBMERSIBLE
PUMP PUMP
NO.2 (2.4kW)
Using
4c x 2.5mm
ARM Cable
NO.2 (2.4kW)
Using 4c
x 2.5mm
ARM Cable

TO CONTROL
CIRCUIT
TO CONTROL
CIRCUIT
2 x sq.
1.5mm
Using 2 Using
x 1.5mm
PVCsq. PVC
R

3x5A

0 -4 0 A
S /s w 0 -5 0 0 V
S /s w
PSR P HA SE S EQ UENC E
R E L A Y0 -4 0 A
S /s w
4 0 /0 .3 A 4 p R C C B
PSR P HA SE S EQ UENC E
R E LA Y
40A TP N 10KA M C C B
4 0 /0 .3 A 4 p R C C B

3x5A

D IS T R IB U T IO N B O X F O R
L IG H T IN G A N D P O W E R
D IS T R IB U T IO N B O X F O R
L IG H T IN G A N D P O W E R

6A

0 -5 0 0 V

TOR

TOR

w
YS /sB

TPN20A TPN20A
TOR
MCB
MCB
DOL
DOL
A
A

20A SPN20A SPN


MCB
MCB

TPN20A TPN20A
TOR
MCB
MCB
DOL
DOL
A
A

SPN6A SPN6A
MCB
MCB

13A Socket
Outlet Outlet
13A Socket
Using 2Using
x 2.5mm
sq. PVCsq. PVC
2 x 2.5mm

To Control Circuit
To Control Circuit
E. STOP
x 1.5mm sq. PVC
E. STOP Using 2Using
2 x 1.5mm sq. PVC

EQ Pump no. 2 (0.6kW)


EQ Pump no. 2 (0.6kW)
Using 4c x 2.5mm ARM Cable
Using 4c x 2.5mm ARM Cable
R

3x5A

PSR

6A SPN
SPN
MCB 6APSR
MCB

EQ Pump no. 1 (0.6kW)


EQ Pump no. 1 (0.6kW)
Using 4c x 2.5mm ARM Cable
Using 4c x 2.5mm ARM Cable

TOR

16A TPN
TOR
TPN
MCB 16A
DOL
MCB
DOL

Air blower motor no.2 (3.7kW)


Air blower motor no.2 (3.7kW)
Using 4c x 2.5mm ARM Cable
Using 4c x 2.5mm ARM Cable

TOR

TOR

20A TPN
TOR
MCB 20A
TPN
DOL
MCB
DOL

20A TPN
TOR
MCB 20A
DOL
TPN
MCB
DOL

TOR

16A TPN
TOR
TPN
MCB 16A
DOL
MCB
DOL

Air blower motor no.1 (3.7kW)


Airx blower
no.1 (3.7kW)
Using 4c
2.5mmmotor
ARM Cable
Using 4c x 2.5mm ARM Cable

M O T O R S E .Q P U M P S A N D S S T P U M P

RAW SEWAGE
SUBMERSIBRE
PUMP PUMP
RAW SEWAGE
SUBMERSIBRE
NO.1 (2.4kW)
Using
4c x 2.5mm
ARM Cable
NO.1 (2.4kW)
Using 4c
x 2.5mm
ARM Cable

S IN G L E L IN E L A Y O U T D IA G R A M F O R
R A W S E W A G E S U B M E R S IB L E P U M P
S IN G L E L IN E L A Y O U T D IA G R A M F O R
R A W S E W A G E S U B M E R S IB L E P U M P

S IN G L E L IN E L A Y O U T D IA G R A M F O R A IR B L O W E R
M O T O R S E .Q P U M P S A N D S S T P U M P
S IN G L E L IN E L A Y O U T D IA G R A M F O R A IR B L O W E R

4 0 /0 .1 A
2P R CCB

S P +N 30K A
1 04 0K/0
A .1
MAC C B
2P R CCB
U S IN G 4 C x 1 6 m m P V C /S W A P V C A R M . C A B L E
U S IN G 4 C x 1 0 m m P V C /S W A /P V C A R M . C A B L E
U S IN G 2 C x 6 m
E m P V C /S W A /P V C A R M . C A B L E
S P +N 30K A
40A TP N 10KA M C C B
30A TP +N 10KA M C C B
10 KA M CCB
40A TP+N
30A TP +N
30A SP+N
U S IN G 4 C x 1 6 m m P V C /S W A P V C A R M . C AMBCL C
EB
U S IN G 4 C x 1 0 m m P V C /S W A /P V C A R M . CMACBCLB
E
U S IN G 2 C x 6 m m P V C /S W A /P V C A R M .MCCAC
BB
LE
R

40A TP+N
MCCB

6A
3 x 6 0 /5 A

3 x 6 0 /5 A

0 -50 0V

R
6A
PSR

V .s .s w
Y B

30A TP +N
MCCB

30A SP+N
MCCB

0 -6 0 A

V .s .s w
0 -50 0V
V .s
wS E S E Q U E N C E
P .s
HA
R E L A Y 0 -6 0 A

.sC
wB
6 3 /0 .3 A 4 pV .s
RC
PSR PHASE SEQUENCE
6 0 A T P + N 2R5EKLAA Y
(4 P O L E ) M C C B

6 3 /0 .3 A 4 p R C C B
6 0 A T P + N 2 5 K A (4 P O L E ) M C C B
415 V S U P P LY
3 PHASE
T N B M E T E R IN G
PANEL
M U L T IC O R E A R M O U R E D
C ABLE TO
T N B R E Q U IM E N T

415 V S U P P LY
3 PHASE

S IN G L E L IN E L A Y O U T D IA G R A M F O R
M A IN S W IT C H B O A R D

S IN G L E L IN E L A Y O U T D IA G R A M F O R
M A IN S W IT C H B O A R D

T N B M E T E R IN G
PANEL
M U L T IC O R E A R M O U R E D

OR O M
IN C O M IN G S C
U APBPLLEYT F
T N B R E Q U IM E N T
M A IN D B 4 1 5 V

IN C O M IN G S U P P L Y F R O M
M A IN D B 4 1 5 V

12

10

10

Volume 4
Volume 4

Volume 4

Malaysian Sewerage
Malaysian
Sewerage
Industry Guidelines
Industry Guidelines
Malaysian Sewerage
Industry Guidelines

Section 2
Design Overview

Design Overview

14

Volume 4

Malaysian Sewerage
Industry Guidelines

Design Overview

2.1
2.1.1

Treatment Plant Classification


Classification by Biological Treatment Processes
The microorganisms in sewage treatment can be grown in a form of
fixed film, suspension or a combination of both. Hence, biological
treatment processes for sewage treatment works can be classified under
one of the following headings:
a)

Attached Growth Processes

c)

Combined Processes (Hybrid)

b)

2.1.1.1

Suspended Growth Processes

Attached Growth Processes


In an attached growth process, the active microorganisms grow and
attach on the mobile or immobile medium (rock or plastic) that is in
contact with sewage. The surface area of the biomass is used as the
practical measure of the total organism activity. Types of attached
growth processes include:
a)

Trickling Filter (TF)

c)

Submerged Biological Contactor (SBC)

b)
d)
e)
2.1.1.2

Rotating Biological Contactor (RBC)


Fluidised Bed

Packed Bed Reactor

Suspended Growth Processes


In a suspended growth process, active microorganisms remain in
suspension in the sewage and their concentration is usually related to
mixed liquor suspended solid (MLSS) or mixed liquor volatile suspended
solid (MLVSS). This system was developed as a result of studies
that showed that if sewage is aerated over a long period of time, the
organics in the sewage are removed by the active microorganisms grow
during the process.
Types of suspended growth processes include:
a)

Waste Stabilisation Pond System

c)

Conventional Activated Sludge (CAS)

b)

Aerated Lagoon

Sewage Treatment Plants

Volume 4

15

Design Overview

d)
e)
f)
g)
h)
2.1.1.3

Extended Aeration (EA)


Oxidation Ditch (OD)
Deep Shaft (DS)
Sequencing Batch Reactor (SBR)
Any other treatment processes which comply with the design
principles of one of the above processes.

Hybrid Processes - Attached Growth with Suspended


Growth
Recent developments in sewage treatment technology include the
combination of various attached growth and suspended growth processes
to obtain the best performance and most economical treatment of
sewage.
One of the advantages of Hybrid Process is the process combines the
stability and resistance to shock loads of an attached growth process
and the capability to produce high-quality effluent of an suspended
growth system.
Hybrid processes can be used to upgrade existing attached growth and
suspended growth process, in particularly plants with high suspended
solids in the final effluent due to poor solids settlement in the final
clarifier.

2.1.2

Classification by Treatment Plant Capacity


Sewage treatment plants are also classified in accordance to the design
capacity in terms of population equivalent (PE). Table 2.2 tabulates 4
clarifications to be adopted.
Table 2.1 - Classification by Treatment Plant Capacity
Classification

PE

Class 1
Class 2
Class 3
Class 4

1000
1001 5000
5001 20000
> 20000

2.2

Treatment System Selection / Design

2.2.1

General Selection Considerations


The following factors must be considered when selecting a sewage
treatment process:

16

Volume 4

Malaysian Sewerage
Industry Guidelines

Design Overview

Process

The applicability of a process is evaluated on the basis of past


experience, data from full-scale plants and pilot data from
treatment plant studies. If new or unusual conditions are
encountered, pilot-plant studies are necessary.

Flow Range

The selected process should be matched to the expected flow


range.

Flow Variation

Most unit operation and processes work best with a constant


flow rate, although some variation can be tolerated. If the flow
variation is too great, flow equalisation may be necessary.

Influent Sewage

The characteristics of the influent will affect the types of


processes to be used and the requirements for their proper
operation.

Inhibiting
Constituents

Identify the constituents present that may be inhibitory, and the


conditions they are in.

Climatic
Constraints

Temperature affects the rate of reaction of most treatment


processes.

Reaction Kinetics
and Reactor
Selection

Reactor sizing is based on the governing reaction kinetics. Data


for kinetic expressions are usually derived from experience,
literature and results of pilot-plant studies.

Performance

Performance is usually measured in terms of effluent quality,


which must be consistent with the given effluent discharge
requirements.

Treatment Residuals The types and amounts of solid, liquid and gaseous residuals
produced must be known or estimated.
Sludge Handling
Constraints

In many cases, a treatment method should be selected only


after the sludge processing and handling options have been
explored.

Environmental
Constraints

Nutrient requirements must be considered for biological


treatment processes. Environmental factors, such as the
prevailing winds and wind directions, may restrict the use of
certain processes, especially where odours may be produced.

Sewage Treatment Plants

Volume 4

17

Design Overview

Chemical
Requirements

Classify chemicals and amounts that must be committed for


a long period of time for the successful operation of the unit
operation or process.

Energy
Requirements

The energy requirements, as well as probable future energy


costs, must be known if cost-effective treatment systems are to
be designed.

Other Resource
Requirements

Identify additional resources that must be committed to the


successful implementation of the proposed treatment system
using the unit operation or process in question.

Reliability

Consider the long-term record of the reliability of the unit


operation or process under consideration.

Complexity

Evaluate the complexity of the process to operate under


routine conditions and under emergency conditions
such as shock loadings, as well as the level of training
the operator must have to operate the process.

Ancillary Processes

Identify the required support process and the effect on the


effluent quality, especially when they become inoperative.

Compatibility

The unit operation or process shall be used successfully with


existing facilities, plant expansion and modifications.

Odour and Noise

Odour and noise pollution should be minimised to the lowest


possible level.

Aesthetics

The selected treatment process should aesthetically suit the


development site.

Safety and
Operability

The chosen treatment process shall be designed with utmost care


to facilitate safe operations at all times as well as to incorporate
safety features for the protection of operators. See Section 2.3.

18

Volume 4

Malaysian Sewerage
Industry Guidelines

Design Overview

Land Requirements

A more compact plant component may perform equally well to a


component taking up more land and thus would be preferential,
provided there was no significant component cost differences.

Ease of Operation
and Maintenance

This will dictate whether plant has to be continuously or


intermittently operated and whether skilled or relatively
unskilled personnel would be required to carry out the operations
and maintenance works.

Modulation

Modulation refers to the ability of process units to be expanded


in tandem with flow increases. Modulation minimises the time
that the plant sits idle before utilisation and lowers initial capital
outlay.

Standardisation

This brings about economics on design effort, material


procurement, quality checks, spares and maintenance costs.

Adaptability

Adaptability refers to the ability to readily upgrade or uprate


the performance of a treatment plant with relatively minor extra
works.

Sludge Management This is an important aspect that needs careful evaluation.


Treatment systems that minimise waste sludge production,
and which produce a relatively stable sludge should be given
preference. See Section 5.12
Overall Cost

Sewage Treatment Plants

This will include considerations of capital, operation and


maintenance costs. Spare parts costs related to maintenance
can be hidden costs that also need consideration, particularly
where there may be long time delays obtaining parts or specialist
inputs are required.

Volume 4

19

Design Overview

2.2.2

Design Stages

The design of a sewage treatment plant comprises the following


stages:
Process Design

In this stage, a suitable sequence of processes are selected


to meet stipulated final effluent requirements for the plant
concerned.

Functional Design

In this stage, calculation of capacities required are conducted


for all major units, channels, pumps and pipework and also
definition of control requirements. These include designs for
hydraulic, organic and solid loadings.

Detailed Design

In this stage, structural design of units and channels, detailing


of pipelines, fittings and control valves, and selection of
mechanical, electrical and control equipment are conducted.

2.2.3

Detailed Design Criteria


For the following characteristics and requirements of a treatment plant,
the designer needs to consider a number of detailed design criteria:
a)

Biochemical characteristics

c)

Hydraulic characteristics

b)
d)
e)
f)
2.2.3.1

Physical characteristics

Mechanical & engineering requirements


Structural requirements

Constructional characteristics

Biochemical Characteristics
These involve the consideration of the following parameters:
a)

Chemical characteristics of sewage

c)

Optimal substrate concentration

b)
d)
e)
f)

g)

20

Good activity between microorganisms and waste materials


Operational stability (half-life and activity decay profile)
Availability of suitable nutrients

Maintenance of favourable environment

Effect of filamentous growth & sludge bulking

Volume 4

Malaysian Sewerage
Industry Guidelines

Design Overview

h)

Effect of dissolved oxygen

j)

Minimum and maximum residence times

i)

k)
l)

m)
n)
o)
p)
q)
2.2.3.2

Productivity in lifetime usage


By-product formation

pH and temperature sensitivity


Storage stability

Reactor effluent quality-composition, colour, odour, etc.


Sludge production and frequency of desludging
Effective material balance analysis

Development of biochemical kinetic coefficient through pilot


plants

Physical Characteristics
These involve the examination of:
a)

Particle shape and size distribution

c)

Swelling behaviour

b)
d)
e)
f)

g)
h)
2.2.3.3

Dry and wet bulk density


Compressibility

Cohesion and particle attrition


Settlement

Floc formation

Settling velocity and sedimentation

Hydraulic Characteristics
These involve the examination of:
a)

Hydraulic velocities in all unit processes

c)

Axial dispersion and channelling

b)
d)
e)
f)

g)
h)

Mode of flow, upflow versus downflow

Pressure drop and head loss through plant

Residence time distribution and retention time


Stratification

Length to width ratio

Minimum velocity for onset of fluidisation

Sewage Treatment Plants

Volume 4

21

Design Overview

i)
j)
2.2.3.4

Weir loadings

Overflow rate

Construction Characteristics
These involve the examination of:
a)

Ground conditions and soil characteristics

c)

Type of plant depending on density and type of community to


be served

b)

d)
e)
f)

g)
h)
i)
2.2.3.5

b)
c)

d)
e)

Delivery and construction time

Recommended maintenance requirements


Start-up time and procedure
Noise levels

Technical capability to construct, operate and maintain the


system

Wall, slab, beams, columns and structure for sewage treatment


plant shall be in reinforced concrete.
Wall shall have minimum thickness of 225 mm.

Special foundation shall be provided where necessary.


Proper jointing to prevent breakage and leakage.

Water retaining and slope protection where applicable.

Mechanical & Electrical Requirements


a)
b)
c)
d)

22

Distance to nearest habitation

Structural Requirements
a)

2.2.3.6

Land availability

The design shall simplify the equipment required, control system,


maintenance and operational procedures, while fulfilling the
intended performance and standard of service.
Equipment selected shall be from manufacturers (and models)
approved by the Commission.

Equipment, cable and cabling design and installation shall follow


IEE and TNB requirements.

Foundations shall be structurally designed and anchored to


withstand all loads imposed by the equipment. Reinforced
concrete foundations are preferred.
Volume 4

Malaysian Sewerage
Industry Guidelines

Design Overview

e)
f)
g)
h)
i)
j)

k)
l)

2.3

Joints shall be provided in all piping to allow removal of


equipment, meters, valves and other special items without causing
dismantling of the pipeline.

Equipment shall be equipped with safety protection (i.e. emergency


stop button, warning signage & etc.). See Section 4.5.
Pipeworks shall be neatly arranged and properly supported.

Appropriate type of control system provided for the treatment


plant. See Section 4.5.

Construction materials to be protected against corrosion due to


high humidity.
Earthing and protection against lightning.

System manuals, plant function diagrams, electrical system,


electrical circuit and instrument loop diagrams shall be provided
before the plant is pre-commissioned.
Detailed and shop drawing for equipment, instrumentation and
cable & cabling shall be provided.

Safety and Health Principles


Throughout the design, construction, commissioning, operation and
maintenance stages of a project, the following safety principles shall
apply:

2.3.1

General Safety
a)
b)
c)
d)
e)
f)
g)

Malaysian Safety and Health legislations, standards and procedures


under Occupational Safety and Health Act (OSHA) 1994, Factories
and Machinery Act 1967 and etc. shall be followed.
Workforce, contractors, visitors and the public shall be safeguarded
against hazards, risk of serious injury and disease.
Adequate training shall be made available for the use of all
related equipment.

Appropriate training for end users to be identified and stipulated


in construction and procurement documents.
Appropriate responsibilities to be assigned throughout each stage
of a project.

Safety consciousness to be promoted by effective internal


communication, signs and media.
Safety performance shall be easily audited during operation and
maintenance.

Sewage Treatment Plants

Volume 4

23

Design Overview

h)
i)
j)
k)

l)
m)
n)
o)

2.3.2

Risk assessment to be undertaken at design of projects and


selection stage of procurement.
Safety information and operating documents to be provided by
suppliers.

Emergency contact list, showing telephone numbers of key


personnel and emergency services during office hours and out
of office hours, to be circulated to all parties involved in a
project.

Plant (certain sized) should be provided with Emergency Response


Plan (ERP)
All treatment plants, installation and construction sites, shall be
provided with perimeter fencing adequate to protect the public
from entry. All fencing shall be securely fixed and inspected.
All treatment plants, installations and construction sites shall
have adequate warning signs at or near the perimeter.

Access to construction sites shall be controlled to prevent


unauthorised access.

Structural Safety
a)

Safe access to all working areas to be provided.

c)

Any confined space requiring routine person entry, which contains


sewage, sludge or other foul water, to be ventilated.

b)

d)
e)
f)
g)
h)
i)

24

All accidents or potential serious incidents to be reported and


investigated.

Routine requirement to enter confined spaces to be eliminated,


where practicable.

Concrete slabs over wet wells, tanks and chambers shall have
double steel reinforcing.

Lifting eyes and bolts for slabs to be stainless steel or any other
durable and non-corrosive material.
Protection against falling (i.e. handrail, kick plate and toe plate)
to be provided.

Within plants and installations, all wells, sumps, channels,


chambers, tanks, etc. containing any liquid shall be covered,
walled or railed.
Major hazards to be identified and posted on site.

Protection and counter measures against spillage of dangerous


chemicals to be provided.

Volume 4

Malaysian Sewerage
Industry Guidelines

Design Overview

j)
k)
l)

Permanent staircase shall be provided at inlet sumps, inlet wells,


inlet chambers and dry-wells. Steps and riser shall follow UBBL
Standard.
Adequate lifting facility shall be provided for heavy equipment,
which requires maintenance work.
Blower room shall not share common wall and foundation with
the control and genset room

2.3.3 Equipment and Electrical Safety


a)
b)
c)

d)
e)
f)
g)
h)
i)

j)

Electrical equipment and controls to be protected from unauthorised


access.
Individual electrical drives to be capable of being isolated and
locked off.
Electrical motors should be rated as continuous run.

Junction boxes for submersible pumps and float controls shall


be above floor level outside the wet-well.
All electrical equipment in sumps, wet-wells, inlet channels, inlet
chambers, sited below coping level to be explosion proof.
Lighting, appropriate to the needs of the end user, to be provided
in working areas.

Registration of electrical / motorised equipment with Department


of Safety and Health (DOSH).

Emergency stop button / isolator shall be provided for each


equipment.
Power driven machinery to be guarded.

All equipment to be regularly checked and prominently marked


accordingly

Sewage Treatment Plants

Volume 4

25

Section 3
Sewage Characteristics and
Effluent Discharge
Requirements

Sewage Characteristics and Effluent Discharge Requirements

28

Volume 4

Malaysian Sewerage
Industry Guidelines

Sewage Characteristics and Effluent Discharge Requirements

3.1

Introduction
The Environmental Quality Act (EQA) 1974 specifies two standards
for effluent discharge: Standard A for discharge upstream of any raw
water intake, and Standard B for discharge downstream of any raw
water intake.
The current Third Schedule of the Environmental Quality Act 1974,
under the Environmental Quality (Sewage and Industrial Effluents)
Regulations, 1979, regulations 8 (1), 8 (2) and 8 (3) has been revisited
and the Department of Environment has proposed 8th Schedule for the
Act which stipulate effluent discharge limits for parameters specific
to domestic wastewater. The effluent discharge limits in 8th Schedule
are summarised in Table 3.2. All sewage treatment plants design shall
take into consideration of the 8th Schedule and shall comply with the
proposed limits.

3.2

EQA Effluent Standards

3.2.1

Purpose of Effluent Standards


Effluent standards are used to regulate the disposal of effluent from
STP to any receiving waters. The regulation of such discharges will
protect receiving waters and their associated aquatic ecosystems, and
will also protect public health from the harmful effects of untreated
sewage.
The need for these standards has been influenced by the fact that sewage
discharges contribute a significant amount of the biodegradable organic
matters, suspended solids and ammoniacal nitrogen to the nations
waterways.

3.2.2

Interpretation of EQA Effluent Standards


The EQA effluent standards have the following characteristics:
a)

They represent maximum or absolute values which may not be


normally exceeded. For this reason, EQA effluent standards are
also referred to as absolute standards

b)

Measurement of effluent quality is to be taken using a single


grab sample rather than a time averaged composite sample

c)

Generally, effluent standards do not allow the flexibility for


them to be compromised through dilution and the assimilative
capacity of receiving water.

Sewage Treatment Plants

Volume 4

29

Sewage Characteristics and Effluent Discharge Requirements

3.3

Design Requirements to Achieve EQA Effluent


Standards

3.3.1

Purpose of Design Requirements


The purpose of design requirements is to ensure that the effluent standards
can be met under the normal operations of a sewage treatment plant. The
quality of effluent from a STP is expected to vary due to the natural
variability in the flows and loads into the plant. Therefore, the design
effluent parameter shall be less than the required effluent standards to
ensure that, when the plant is under normal operation, any grab sample
of effluent will comply with the consent EQA effluent standards.

3.3.2

Design Values
Typical composition of untreated domestic sewage is given in Table
A.2, while Table 3.1 tabulates the design influent values to be adopted
in the design of a treatment plant.
Table 3.1 - Design Influent Values
Value (g/
capita.day)

Value (mg/l)

Biochemical Oxygen Demand (BOD5)

56

250

Suspended Solids (SS)

68

300

Chemical Oxygen Demand (COD)

113

500

Total Nitrogen (TN)

11

50

Ammoniacal nitrogen (AMN)

30

Total Phosphorus (TP)

10

Oil and Grease (O&G)

11

50

Parameter

These design values allow for transient reductions in treatment efficiency,


due to periodic plant maintenance and unforeseen high impulse of
hydraulic and organic loadings on sewage treatment process units. All
STP shall be designed to produce final effluents with BOD5, SS, COD,
O&G and AMN values less than or equal to the design effluent values.
This is to ensure a high degree of consistent compliance with the
required effluent standards. The effluent E.Coli compliance is subject
to the sensitivity of the receiving watercourse and of the Commissions
directive.

30

Volume 4

Malaysian Sewerage
Industry Guidelines

Sewage Characteristics and Effluent Discharge Requirements

Table 3.2 - Design Effluent Values


Effluent Discharge to Rivers / Stream
Parameter

Standard A
Absolute Design

BOD5
SS
COD
AMN
Nitrate
Nitrogen
Total
Phosphorus
O&G

Standard B
Absolute Design

Effluent Discharge to
Stagnant Water Bodies*
Standard A
Standard B
Absolute Design Absolute Design

20
50
120
10

10
20
60
5

50
100
200
20

20
40
100
10

20
50
120
5

10
20
60
2

50
100
200
5

20
40
100
2

20

10

50

20

10

10

N/A

N/A

N/A

N/A

10

10

10

Notes:
NA = Not Applicable
All values in mg/l unless otherwise stated.
* Stagnant Water Bodies refer to enclosed water bodies such as lakes, ponds and
slow moving watercourses where dead zone occur.

In cases where treatment plant discharge capacity is higher than the


receiving river flow rates, the final effluent quality has to be designed
to ensure minimal environmental impact.

3.4

Sewage Pollutants Removal

3.4.1

Biochemical Oxygen Demand (BOD5)


BOD5 is used to measure the biodegradable organic fraction in raw sewage.


Based on standard BOD5 measurement, the oxygen demand measured
is usually influenced by the following three (3) phenomena:
a)
b)
c)

Oxygen demand by breakdown of soluble carbonaceous matter

Oxygen demand by breakdown of suspended particulate carbonaceous


matter
Oxygen demand by oxidation of ammonia to nitrate by nitrifying
bacteria present in the effluent sample

After undergoing biological treatment in the secondary reactor, residual


soluble carbonaceous BOD 5 matter present in the effluent reduces
in concentration to below 15 mg/l. Subsequently, nitrifying bacteria
populations tend to grow rapidly feeding on ammonia which is present
Sewage Treatment Plants

Volume 4

31

Sewage Characteristics and Effluent Discharge Requirements

in the partially treated sewage. Nitrification may not be complete at


levels of 5 mg/l of residual soluble carbonaceous biodegradable matter.
It depends on whether sufficient oxygen is available for the oxidation
of ammonia to nitrate. Hence, all BOD 5 measurements shall adopt
nitrification inhibition step to ensure that the carbonaceous oxygen
demand is reflected accurately in the overall BOD5 measurement.
3.4.2

Total Suspended Solid (TSS)


Sewage contains solid materials that can settle at the bottom and also
give impact on the benthic life. They can also appear in suspension
solids form that can increase turbidity and affect the light availability
for aquatic life. The amount of solids in sewage is usually measured as
total suspended solids or TSS. The desired solid removal in sewage
treatment plants should not exceed the absolute TSS discharge limit of
50mg/l and 100mg/l for Standard A and Standard B, respectively.
To ensure effluent consistently complies with Department of Environments
Effluent Limits, provisions must be made to allow for future incorporation
of a flocculator in the clarifier. This will enhance clarification performance.
Chemical (polymer) can also be added in flocculation clarifiers to
further enhance solids settlement in the clarifiers. Otherwise, a dual
media filtration system following conventional secondary clarifiers can
also be used to ensure that TSS concentration of 20 mg/l to 40mg/l is
consistently achieved.

3.4.3

Chemical Oxygen Demand (COD)


COD content reflects the chemically oxidized organic matter. Hence,
it includes refractory fractions of organic matter as well as reduced
inorganic constituents present in the wastewater. The COD measurement
offers quick estimate of carbonaceous material compared to conventional
BOD measurement. Additionally, high COD reflects inert reduced
inorganic elements and also unbiodegradable organic that comes from
industrial contamination. Based on the bi-substrate hypothesis, COD
fractions comprising of readily biodegradable, slowly biodegradable
and unbiodegradable estimates are adopted in advanced modeling for
STP design. Such advanced modeling takes into consideration the
treatment process requirements of different COD fractions as it varies
in susceptibility to microbial respiration and degradation.

3.4.4

Oil and Grease (O&G)


O&G that is detected in domestic sewage refers to the fraction of organic
matter that is soluble in organic solvents such as hexane.

32

Volume 4

Malaysian Sewerage
Industry Guidelines

Sewage Characteristics and Effluent Discharge Requirements

The composition comprise primarily of wax, edible oils and fatty


matter of animal or vegetable origins. O&G (mixture of tri, di and
mono-glycerides) in its liquid form results in floatable scum formation
in treatment systems whilst its solid form causes the clogging of
systems.
O&G is separated from raw sewage by provision of grease chambers (be
it manual or mechanized scum skimmer removal) at primary treatment
stage. Removal at the primary stage is essential to prevent interference
of oil particles on biological reactions in the secondary treatment. It
also prevents undesirable organic load of extremely slow biodegradable
constituents into aerobic systems. Such first line oil and grease removal
protects against contamination in the treatment plant as well as in the
receiving water.
3.4.5

Nitrogenous Compound
Removal of nitrogenous compounds needs to be considered in STP design.
These compounds found in various forms (ammonia or ammoniacal
nitrogen, nitrate nitrogen and nitrite nitrogen) could be detrimental to
natural water bodies and potable consumption. Total organic nitrogenous
compounds in raw sewage typically comprise of nitrogen in the form
of proteins, amino acids and urea along with ammoniacal nitrogen.
Ammoniacal nitrogen results from the decomposition of organic nitrogen
particularly from hydrolysis of urea. Total Kjedhal Nitrogen (TKN)
analysis determines the organic nitrogen and the ammoniacal nitrogen
fractions.

3.4.6

There are two main biological processes for removing nitrogenous


compounds, namely the assimilation of ammonia nitrogen into the
microbial biomass and the nitrification-denitrification process. The
latter involves two conversion steps. Firstly, nitrification followed
by denitrification by microbial heterotrophs that convert nitrates into
nitrogen gas. Nitrification comprises two-step oxidation of ammonia
nitrogen into nitrate by nitrifying bacteria. All treatment systems shall
provide full nitrification and denitrification in the secondary biological
reactors with sufficient air supply to facilitate nitrification. This will
ensure that effluent discharge complies with the required discharge
limits.
Phosphorus Compound
The constituents of total phosphorus compounds in raw sewage are
organically bound phosphorus and inorganic phosphorus (orthophosphates
and polyphosphates).

Sewage Treatment Plants

Volume 4

33

Sewage Characteristics and Effluent Discharge Requirements

Some fractions of the essential phosphorus nutrients from the influent


will be assimilated for microbial growth during secondary biological
treatment. However, excessive phosphorus nutrient will occur when above
the assimilated with stagnant receiving water bodies (e.g. ponds), which
will result in nutrient enrichment and produce harmful algae blooms.
Hence, the design for sewage treatment plant effluent that discharges
into stagnant water bodies should take into considerations the impact
of excess phosphorus contamination.

3.5

Sludge Characteristics and Treatment Requirements


Sludge treatment and management are as important as the sewage
treatment to minimise impacts to the environment. Sludge produced
from treatment process is usually in liquid form, which typically
contains 0.25 to 4.0% of solids, depending on the type of treatment
process being used. It also contains grease, fats, organic and inorganic
chemicals. High concentrations of certain components will determine
the type of sludge treatment process to be used.
Sludge shall be thickened, stabilized, conditioned and dewatered before
it is finally disposed off in accordance to requirement stipulated by
Department of Environment. The dried sludge must attain a minimum
of 20% dry solid content before off-site disposal. Close attention is
required when planning and designing sludge treatment processes to
ensure bio-solid to be disposed do not contain any harmful substance
that will affect the environment. Additionally, stabilization process should
be designed to reduce any potential presence of microbial pathogens.
Options of ultimate disposal include landfill and land application.

34

Volume 4

Malaysian Sewerage
Industry Guidelines

Section 4
Requirements for Physical Design

Requirements for Physical Design

36

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

4.1

Introduction
The induced physical, chemical and biological reactions that occur in a
sewage treatment plant (STP) lead to waste emissions in the following
forms:
a)
b)
c)
d)
e)
f)
g)

gases and vapours, some of which contain obnoxious compounds,


including bacteria and viruses.
noise.
odour.
vibration.
unwanted solid matter.
undesirable by-product liquors containing highly concentrated
pollutants.
heat.

As such, a sewage treatment plant can degrade the amenity of its


surroundings, especially in residential areas.
Careful consideration of siting is required to minimise nuisance to the
public. Sufficient land needs to be set aside during the planning stage
to take into account regional treatment plant development and the
proper sewerage planning for housing, commercial and institutional
developments.
This section sets out the important factors and considerations associated
with the identification of proper sites to locate sewage treatment plants.
Typical workflows in the site for sewage treatment plants are illustrated
in Figures 4.1 and 4.2. It also addresses the selection of appropriate
treatment concepts and sufficient land area requirements for treatment
plants in relation to the effluent standards.

4.2

Treatment Plant Siting

4.2.1

Buffer Zones
Suitable buffer distances should separate a sewage treatment plant from
its surrounding areas. Buffer Guidelines for the Siting and Zoning of
Industries as recommended by the Department of Environment (DOE)
should be referred to during the planning of suitable location for
treatment plants. The buffer distances recommended in the guidelines
depend on the category of industry being considered.

Sewage Treatment Plants

Volume 4

37

Requirements for Physical Design

The provision of buffer zones is essentially an environmental requirement


controlled by the relevant planning authority. The agreement of the Local
Planning Department on buffer zone and plant siting should be sought
at an early stage in the Town and Country planning procedures.
The buffer zone requirements for treatment plants to be observed under
this Guideline are as follows. Refer to Figures 4.3 and 4.4 in this
section for further clarification.
a)
b)
c)

d)

e)

Minimum distance of 30 m from the fence of the treatment plant


to the nearest habitable building property line within residential
and commercial development.
Minimum distance of 20 m from the fence of the treatment plant
to the nearest property line within industrial development.

Minimum distance of 10 m from the fence of the treatment plant


to the nearest habitable building property line if the proposed
treatment plant is fully enclosed. A fully enclosed plant is defined
in section 7.3.1.
A minimum distance of 10 m from the fence of the treatment
plant to the nearest habitable building property line if the
proposed treatment plant is covered or buried. However, this
reduction in buffer requirement does not apply if the nearby
habitable buildings are of high rise type. A covered or buried
plant is defined in section 7.4.1.

Plants with PE less than 150 but are provided with proper odour
and noise mitigation measure may have a 10 m reduced buffer
at the discretion of the Commission.

The buffer zone can be used for any purpose except permanent habitable
buildings. For example, the buffer zone maybe used as a drainage
reserve, road or highway reserve, transmission reserve, utility reserve
or public park.
In the case where buffer area is to be regularly used by the residents
such as car park and playgrounds, proper precautions during design
stage must be taken to minimise nuisance such as odour, noise and
unpleasant sight to the surrounding environmental. Adequate and proper
screening, odour containment and treatment facilities must be provided
at the sewage treatment plant to address these issues.

38

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

4.2.2

Siting Criteria
The following criteria shall be observed when siting treatment plants.
a)
b)
c)
d)
e)
f)
g)

h)

Plants shall be located as far as possible from habitable building


to minimise nuisance to the surrounding.

Plants shall be located at the lowest point of a sewerage catchment


basin so that sewage can gravitate into the plant.
Plants shall be located near to a suitable watercourse that is able
to receive and assimilate treated effluent from the plant without
reducing beneficial uses of the water course downstream.
Plants shall be located on an area that is relatively flat or with
relatively mild slope across the site that would be useful in
promoting efficient hydraulics.

The shape of the land area selected shall be such as to minimise


the extent of unusable area within the lot.
Plants shall not be located in an area that will result in long
term operational problems or rapid deterioration of the assets.
Plants shall have proper access road leading to it.
Plants shall be sited away from the followings:
i)

ii)

iii)

Existing cemeteries and gazetted reserves for cemetery.


Religious centres.

Eating places.

i)

Plants shall be located such that sewers are easily connected/


conveyed to the proposed site.

j)

If temporary treatment plants are to be provided, they shall be


located as near as possible to public trunk sewers.

k)

For safety reasons, plants shall be located away from children


playgrounds.

Emergency bypass shall be provided either at the last manhole or wetwell. The bypass shall discharge to the nearest drain which shall have
sufficient capacity to cater for the discharge during rainfall.
4.2.3

Environmental Impact Assessment


An environmental appraisal or environmental impact assessment (EIA)
study shall follow Environmental Quality (Prescribed Activities)
(Environmental Impact Assessment) Order, 1987 under Section 34A
of the Environmental Quality Act, 1974 (the EIA Order, 1987 and the

Sewage Treatment Plants

Volume 4

39

Requirements for Physical Design

EQA, 1974 respectively). The type and scope of the study will depend
on the classification of the plant and the environmental sensitivity of
the locality being considered. EIA shall be conducted in compliance
with Volume 2 of the MSIG.
4.2.4

Hazard and Operability Studies


Hazards and Operability (HAZOP) study shall be conducted in compliance
with Volume 2 of the MSIG. The type and scope of the study will
depend on the classification of the plant.

4.3

Treatment Plant Sizing

4.3.1

Modular Units
Stage development of a STP is governed to a large extend by the timeframe
of the overall development plan of the catchments and the size, shape
and soil condition of the land reserved for the STP. Modular units will
be constructed to cater for the stage development. In determining the
appropriate number of modules and corresponding timing for a staged
development, it is crucial for the designer to estimate the flow capacity
build-up over the entire development phases. The modules must have
sufficient capacity to treat the sewage to meet the efficient discharge
standard, without compromising the economical viability of operation
and maintenance. Too many modules and unit processes will definitely
increase equipment maintenance. On the other hand, inadequate modules
will result in an inefficient treatment performance due to insufficient
capacity and flexibility during the early stage.
Table 4.1 Modularisation Requirements
STP Classifications

No. of Modules

No. of Trains

Class 1 (<1,000PE)

N/a

Class 3 (5,001PE
20,000PE)

Min. 2, Max. 3

Class 2 (1,001PE 5000PE)

Class 4 (>20,000PE)

Min. 4, Max. 10

Max 2

Max 2 for each


Module
Max 2 for each
Module

Table 4.1 indicates the modularisation requirements in accordance to


sewage treatment plant classes to attain an efficient modularisation of
sewage treatment plant development. Each module shall be of equal size

40

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

and of similar treatment process. If the proposed process is different from


the original system, special approval is required from the Commission.
Certain unit processes are subject to the modularisation requirements
in Table 4.1 while other unit processes are designed for the ultimate
phase during the first stage of the development. An example of this
is the headworks of a STP designed for the ultimate phase while the
secondary processes are added progressively as the future phases come
on-line.
Modular treatment plants that are designed with two (2) or more parallel
streams must be provided with pipeworks and valves to isolate each
stream of unit process during maintenance and major shut down without
interfering normal operation of the remaining stream.
4.3.2

Standby Units
To avoid significant down time in sewage treatment and overloading
of the process units, standby units shall be provided for the following
processes:
a)

Inlet Works/Pumps

c)

Grit Chambers

b)
d)
e)
f)

Screen Facilities

Biological Treatment
Secondary Clarifiers
Sludge Facilities

The common standby mechanical equipments are as follows:a)

Pumps (raw sewage, effluent, sludge, etc)

c)

Blowers

b)
d)

Mechanical screens

Any other mechanical equipment

Detailed requirements of standby units shall follow the requirements


in Section 5.
4.3.3

Back-up Capacity
The back-up capacity provided shall be such that when one unit process
is taken out of operation, the remaining units shall not be overloaded
beyond 50% of their rated capacities.

Sewage Treatment Plants

Volume 4

41

Requirements for Physical Design

4.3.4

Design Flow

It is recommended that unit processes that are designed on average flow


basis are sized to allow for infiltration in accordance with MS 1228.
Conveyance networks shall be sized to cater for peak flows, except for
those networks located downstream of an equalisation tank. All unit
processes shall be designed based on the maximum ultimate design
flow.

4.4

Land Area Requirements

The recommended land area requirements for various sewage treatment


plants capacities are derived from relevant treatment process concepts
and also taken into consideration other design criteria.

The land area requirements and buffer allowance for temporary sewage
treatment plants maybe reduced at the discretion of the Commission on
a case by case basis.

4.4.1

Class 1 and 2 Plants

The recommended land area requirements for Class 1 and 2 plants (up
to 5000 PE) are given in Table 4.2 and Table 4.3 respectively. The net
area does not include the 30 m buffer zone surrounding the plant, but
does include appropriate set backs and access paths within the plant. The
area requirements given are sufficient to achieve an effluent conforming
to Standard A discharge requirements. It is important that allowance
is made for sufficient buffers in planning approvals, to avoid future
complaints in relation to the siting of the plant.

4.4.2

Mechanised Class 3 to 4 Plants

For Class 3 and 4 plants with mechanised systems, the recommended


land area requirements are given in Table 4.4 and 4.5. These systems
are to be used in normal developed and urbanised areas. The net area
does not include the 30 m buffer zone surrounding the plant, but does
include appropriate set backs and access paths within the plant. The area
requirements given are sufficient to achieve an effluent conforming to
Standard A discharge requirements. It is important that allowance is made
for sufficient buffers in planning approvals, to avoid future complaints
in relation to the siting of the plant.

42

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

4.4.3

Aerated Lagoons and Stabilisation Ponds

For aerated lagoon and stabilisation pond treatment systems, the


recommended land area is as shown in Table 4.6. Sufficient buffer areas
shall be allowed for surrounding the plant as per paragraph 4.2.1.

4.4.4

Imperfect Sites

The recommended land area requirements represent an ideal case, where


it is possible to locate the STP within a rectangular land area that is
relatively flat. In practice, the allocated land may be irregular in shape,
sited in low lying or undulating to steep valley terrain. For such cases,
suitable adjustments to the land area requirement have to be made.

Thus, the shape and elevations of the land allocated for the STP development
must be determined during planning stage so that the configuration of
the STP can be planned properly in order to allocate adequate land for
the purpose. This also enables estimates for additional land required. It
may also be required to cut or fill operations to level the land.

4.4.5

Reduced Land Areas for STPs

The area requirements, as stipulated in Table 4.2, 4.3, 4.4, 4.5 and 4.6,
must be adhered to as strictly as possible. The required areas in these
tables include appropriate setbacks and access paths within the plant.
However the areas have not include any buffer zone surrounding each
plant as indicated in Section 4.2.1.

In developments where land is really a constraint the Commission may


consider for a reduced land area requirement. The project proponent will
have to demonstrate clearly the need for a reduced land area before an
approval can be granted. For this case, detailed design calculations of
all unit processes, together with the proposed layout, shall be submitted
at the planning stage for consideration of approval by the Commission.
Otherwise, the land area required under these guidelines must be
followed.

Sewage Treatment Plants

Volume 4

43

Requirements for Physical Design

Table 4.2 Land Area Requirements for Class 1

Population
Equivalent

Land Area
Requirement *
(acre)
(m2)

100

210

0.052

150

285

0.070

200

360

0.089

250

430

0.106

300

485

0.120

350

545

0.135

400

600

0.148

450

655

0.162

500

700

0.173

550

745

0.184

600

790

0.195

650

835

0.206

700

870

0.215

750

905

0.224

800

940

0.232

850

980

0.242

900

1010

0.250

950

040

0.257

1000

1070

0.264

Note: * The required area only includes appropriate setbacks and access paths
within the plant but not the buffer zone surrounding each plant as indicated in
Section 4.2.1.

44

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

Table 4.3 Land Area Requirement for Class 2


Population
Equivalent

1100
1200
1300
1400
1500
1600
1700
1800
1900
2000
3000
4000
5000

Land Area
Requirement *
(m2)

1115
1160
1200
1240
1275
1310
1340
1370
1395
1420
2226
2671
3076

(acre)

0.276
0.287
0.297
0.306
0.315
0.324
0.331
0.339
0.345
0.351
0.55
0.66
0.76

Table 4.4 Land Area Requirements for


Mechanised Class 3 Plants
Population
Equivalent

Land Area
Requirement *
(ha)

(acre)

5001

0.31

0.76

6000

0.40

0.99

7000

0.49

1.21

8000

0.59

1.46

9000

0.69

1.71

10 000

0.78

1.93

15 000

1.00

2.47

20 000

1.19

2.95

Note: * The required area only includes appropriate setbacks and access paths
within the plant but not the buffer zone surrounding each plant as indicated in
Section 4.2.1.
Sewage Treatment Plants

Volume 4

45

Requirements for Physical Design

Table 4.5 Land Area Requirements for


Mechanised Class 4 Plants
Population
Equivalent

20 001
25 000
30 000
35 000
40 000
45 000
50 000
55 000
60 000
65 000
70 000
75 000
80 000
85 000
90 000
95 000
100 000
110 000
120 000
130 000
140 000
150 000
160 000
170 000
180 000
190 000
200 000
250 000
300 000
450 000

Land Area Requirement *


(ha)
(acre)

1.19
1.37
1.53
1.81
1.97
2.12
2.23
2.37
2.52
2.67
2.93
3.27
3.49
3.69
3.89
4.07
4.25
4.57
4.87
5.14
5.39
5.63
5.84
6.05
6.25
6.43
6.60
7.36
7.98
9.36

2.95
3.38
3.79
4.48
4.88
5.25
5.52
5.84
6.22
6.61
7.23
8.07
8.61
9.12
9.61
10.06
10.49
11.29
12.02
12.70
13.32
13.90
14.44
14.95
15.43
15.89
16.32
18.20
19.73
23.14

Note: * The required area only includes appropriate setbacks and access paths
within the plant but not the buffer zone surrounding each plant as indicated in
Section 4.2.1.

46

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

Table 4.6 Required Land Area for


Stabilisation Pond and Aerated Lagoons
Population
Equivalent

Standard A*

Standard B*

(ha)

(acre)

(ha)

(acre)

2000

0.48

1.18

0.45

1.10

4000

0.89

2.20

0.71

1.75

3000

5000

10 000
15 000
20 000
25 000
30 000
35 000
40 000
45 000
50 000
55 000

0.69

1.09
2.03
2.92
3.78
4.62

2.68
5.01
7.2
9.3

11.4

5.45

13.5

7.05

17.4

6.26
7.85
8.63
9.40

60 000

10.16

70 000

11.68

65 000

1.69

10.92

15.5
19.4
21.3
23.2

0.59

0.82
1.31
1.72
2.09
2.42
2.74
3.04
3.32
3.59
3.86

2.04
3.24
4.25
5.16
5.99
6.77
7.50
8.2
8.9
9.5

4.11

10.2

4.60

11.4

25.1

4.36

28.9

4.83

27.0

1.45

10.8
11.9

75 000

12.42

30.7

5.06

12.5

85 000

13.91

34.4

5.50

13.6

80 000
90 000
95 000

100 000

13.17
14.64
15.37
16.10

110 000

17.54

130 000

20.38

120 000

Sewage Treatment Plants

18.97

32.5
36.2
30.0

39.8

43.3

46.9
50.4

Volume 4

5.28
5.72
5.93

6.13

6.54

6.93

7.31

13.1
14.1
14.6

15.2

16.2

17.1

18.1

47

Requirements for Physical Design

Table 4.6 Required Land Area for Stabilisation Pond and


Aerated Lagoons (Continued)
Population
Equivalent

140 000

150 000

160 000

170 000

180 000

190 000

200 000

Standard A*

Standard B*

(ha)

(acre)

(ha)

(acre)

21.79

53.8

7.69

19.0

24.57

60.7

8.40

20.8

27.32

67.5

23.18

25.95

28.68

30.04

57.3

8.05

19.9

64.1

8.75

21.6

70.9

9.43

23.3

74.2

9.09

9.76

22.5

24.1

Note: * The required area only includes appropriate setbacks and access paths within the
plant but not the buffer zone surrounding each plant as indicated in Section 4.2.1.

48

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

Figure 4.1 STP Land Area Requirements for Planning Layout


Approval for New Development

Start

Determine catchment
served

Determine ultimate PE

Identified effluent
requirement

Apply sitting criteria

Is development
> 2000 PE?

Is development
in urban area?

Use land area from


Table 4.2
(Class 1 plants)

Use land area from


Table 4.3,4 and 5
(Class 2 to 4 plants)

Use land area from


Table 4.6
(pond systems)

End

Sewage Treatment Plants

Volume 4

49

Requirements for Physical Design

Requirements for Physical Design

Figure 4.2 STP Land Area Requirements for Structure Plans


Figure 4.2 STP Land Area Requi

rements for Structure Plans

Start

Local plan
Plan
formulation
Formulation

Perform the next two


steps concurrently
Determine natural
drainage catchments

Determine suitable
receiving waters

Calculate ultimate
catchment PE

Identify effluent
standards
Look up land area
requirements in
Tables 4.2, 4.3, 4.4 or 4.5

Table 4.2:
Up to 1000
1,000PE
PE

Table 4.3, 4 and 5:


Greater than1000
than1,000PE
PE
for urban areas

Table 4.5: For remote


area siting of STP

Apply siting criteria

Select and zone


suitable site

Consider multi-use of
buffer areas

Reserve land for STP

End

50

Volume 4

42

V ol ume 4

Malaysian Sewerage
Industry Guidelines

M al aysi an S ewerage
I ndustry G ui del i nes

Requirements for Physical Design


Requirements for Physical Design

Figure 4.3 Guidelines For Buffer Zone


Figure 4.3 Guidelines For Buffer Zone
Plants Situated In Residential / Commercial Areas
Treatment Plant Site

Buffer Zone 30m Min.

Residential /
Commercial Plot

5m Min.
Access And
Screening

Property
Boundary

STW Fence

Open Treatment
Plant

Beautification
Zone

Treatment Plant Site

Buffer Zone 10m Min.

Residential /
Commercial Plot

5m Min.
Access and
Screening

Enclosed Plant

Property
Boundary

STW Fence

Treatment Plant Site

Buffer Zone 10m Min.

Residential / Commercial Plot

5m Min.
Access And
Screening
Property
Boundry

STW Fence

Buried / Covered
Plant

Buffer Zone 30m Min.

Treatment Plant Site

Residential / High Rise

5m Min.
Access and
Screening

Enclosed Plant

Property
Boundary

STW Fence

Plants Situated In Industrial Areas


Treatment Plant Site

Buffer Zone 20m Min.

Industrial Plot

5m Min.
Access And
Screening
Open Treatment
Plant

Factory Fence

STW Fence

Note : The buffer area can be used for roads, drains, utility reserve, agricultural or other similar
purposes.

Sewage Treatment Plants

Volume 4

Sewage Treatment Plants

Volume 4

51

43

52

Volume 4

44

Volume 4

30m Surround For Residential and Commercial


Development
20m Surround For Industrial Development
10m Surround For Fully - Enclosed Plants

10 m

20 m

30 m

STP LAND AREA


REQUIREMENT

The land shall be relatively flat and of a regular shape. Any unusable
area within the plot shall be minimised.

Note: Buffer areas can be used for roads, drains, utility reserve, public
parks, agricultural or similiar purposes other than permanent
habitable buildings.

10 m

20 m

30 m

Requirements for Physical Design


Requirements for Physical Design

Figure
PlanView
View of
of Buffer
Figure
4.44.4- Plan
BufferZone
ZoneRequirements
Requirements

Malaysian Sewerage
Industry Guidelines
Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

4.5

Mechanical and Electrical Requirements


Some general guidelines on the design and installation of mechanical
and electrical equipment are outlined below.

4.5.1

Mechanical Installation
I)

Design Considerations

The designer shall consider incorporating the following criteria:


a)
b)
c)

The design shall simplify the equipment required, control system,


maintenance and operational procedures, while fulfilling the
intended performance and standard of service.

The brand and models of major drive equipment (e.g.: pumps,


blowers, aerators, clarifier scrappers, etc.) shall be those approved
by the Commission.

The types and makes of equipment provided throughout the


facility shall be standardised, whenever possible.

d) Only new and genuine equipment shall be provided.


e)
f)

g)
h)
i)

II)
a)
b)
c)

Equipment sizing and selection shall minimise energy and other


consumables costs.
The minimum economic life of equipment.

Material selection shall be in accordance with the Commission


specifications or/and other relevant international standards.
Components shall be robust and suitable for use. Where thin metal
sheeting is used, it shall be stiffened to minimise distortion.

Water storage tanks shall not be placed on the roof top of any
control room; all water supply system shall be homed with
separate entrance.
Installation
The base frame of rotational equipment or any equipment that may
induce vibration shall be provided with anti-vibration mount.
All moving parts shall be designed and installed in a manner
that is inherently safe to operate.

Foundations shall be adequately designed to include all dynamic


load and anchored to withstand all loads imposed by the equipment.
Reinforced concrete foundations are preferred.

Sewage Treatment Plants

Volume 4

53

Requirements for Physical Design

d)

Equipment shall be accurately located, levelled and secured


by holding down bolts. Non-shrink grout shall then be used to
complete the foundation. In some cases, a resilient connection
to the foundation is required, in which case, the manufacturers
instructions shall be followed.

e) Holding down bolts shall be of stainless steel and shall be of a


minimum grade 316 if in contact with sewage.
f)

g)
h)

Puddle collar is required for all pipe passing through all


walls.

Appropriate joints shall be provided in all pipeworks to facilitate


the removal of equipment, meters, valves and other special items
without dismantling the entire pipeline.
Valves shall be provided for isolation purpose.

i) Outdoor and dry installation pump shall be provided with


housing.
j)

k)

4.5.2

The designer must ensure that the unit processes are arranged
in such a way to prevent/reduce criss-crossing of piping works,
unnecessary bends, choking of interconnected pipe and excessive
hydraulic losses through the system.

The platform level of mechanical equipment and controllers of


any process unit shall be located above design flood level.

Vibration
All revolving parts shall be properly balanced both statically and
dynamically so that in running up to, at full normal operating speeds,
and at any loads up to the maximum there shall be no undue vibration
anywhere in the machine or transmitted to the adjacent structure. The
criteria adopted for vibration severity shall be the RMS value of the
vibration velocity in millimeters per second.
The bare frame of rotational equipment or any equipment that may induce
vibration shall be provided with anti-vibration mount. Where rotational
equipment or equipment which may induce vibration is connected to
piping, then vibration isolator shall be provided.

4.5.3

Noise
Noise levels from machinery shall comply with the Factories and
Machinery (Noise Exposure) Regulations 1989 and Occupational Health
and Safety Act. Noise control measures and appropriate safety protection
for operators must be provided where necessary.

54

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

Noise control measures shall be implemented to control the generated


noise level to below 65 dB at a distance of 2 m from the boundary
of the housed noise source at all times. Additionally, the general
noise levels generated shall be measured 10 m from any point of the
plant site within the nearest public space and/or occupied space to an
acceptable level stipulated by the appropriate regulators. Silencers and
acoustic enclosures shall be provided as required to achieve the above
noise level reduction.
Enclosures used to achieve these noise reductions shall permit ready access
to the equipment for routine maintenance. Adequate air ventilation shall
be provided to allow cooling of the enclosure to prevent overheating
of the equipment/motors.
Noise level measurement shall be made with a sound level meter which
complies with BS EN 60651 and which is fitted with an A weighting
network. The sound pressure level shall be measured in dB (A).
Noise level for all electronically operated electrical device such as soft
starters, variable speed drives and others shall be conform to IEC, EN.
Thus it shall fulfil all EMC Immunity requirements complying with
EN500082-1, EN50082-2, EN50082-3.
4.5.4

Safety Around Equipment


All designs and equipment shall be made and installed with safety in
mind. Nothing in this Design Guidelines shall remove the designers
obligation to incorporate equipment or designs that would increase the
safety of the plant.
The installation layout and equipment design shall not allow any item
of equipment to be so positioned that danger could arise to operating
personnel and equipment during normal operation and maintenance.
Particular attention shall be paid to the positioning of switch board,
control panel, cables, switch gears, lighting, small power, rotational
equipment, other electrical equipment and accessories.
All facilities shall be designed to comply with the Occupational Safety
and Health Act 514, 1994; properly designed treatment plants will
enable the operator to safely handle the treatment plant throughout
its design life. The plant shall also be designed to comply with other
related Acts such as IEE, Akta Bekalan Elektrik 1990 (Akta 448) and
Peraturan-Peraturan Elektrik 1994.
Safety level for all electronically operated electrical device such as soft
starters, variable speed drive and others shall conform to IEC, EN, UL,
NFC and VDE. Thus it shall fulfill EN 50178, EN 60204-1, EN 60950
(2000, 3rd edition), IEC 61800-5.
Where appropriate, IEE and Akta 448 (1990) and Peraturan Elektrik
1994 must be complied within all electrical installation.

Sewage Treatment Plants

Volume 4

55

Requirements for Physical Design

The following shall be provided:


a)

b)

c)

d)
e)

f)

g)
h)

All moving parts shall be protected by suitable guards. Where


inspection is required, an open mesh with frame and suitably
supported maybe used. The maximum aperture of the mesh shall
be 6 mm.

All guards shall be readily removable and replaceable to they


correct orientation only. However the guard shall be designed
with features to prevent accidental dislocation from its original
position. The fasteners when dropped during dismantling, must
be easily retrievable and should not damage any equipment or
endanger personnel, else fixed fasteners shall be used.
An emergency stop button, preferably of mushroom head type
shall be located adjacent to all equipment. More than one
emergency stop button shall be used, if access around the item
is restricted.

Long items, such as conveyor belts, shall have an emergency


lanyard applied to each accessible length of conveyor.
Surfaces which are greater than 50C shall be guarded.

Permanent warning signs shall be posted at visible location at


all dangerous areas and shall clearly indicate the nature of risk
at that area. This includes warning signage at digesters area,
high tension room, low voltage room, generator room and other
hazardous areas.
Clear working space as recommended in Figure 4.5 shall be
provided.
Automatic CO2 discharge triggered by heat and smoke sensors
shall be installed in high voltage switch room, transformer room,
low voltage switch room and generator room.

i) High tension room shall have signage to clearly indicate the


purpose of the room and also safety signage to prevent unauthorised
entry.

56

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

Figure 4.5 - Clear Working Space


1 m or 1.5 W or
whichever greater

Wall

Equipment

Wall

1 m or 1.5 W or
whichever greater

Equipment
L

4.5.5

1 m or 1.5 W or
whichever
greater

Motors, Controllers and Motor Starters


I)
a)
b)
c)

Motors
Provide readily replaceable anti-condensation heaters for motors
that do not require frequent operation.
At least three thermistors to be provided for motors which are
>50 kW.
Electrical motors should be rated as continuous run.

d)

Motors > 22kW shall be protected with soft starter or variable


speed drive.

e)

Where water hammer prevails, frequency inverter shall be


provided.

f)

II)
a)

b)

The appropriate cooling system based on the requirements of


the equipment shall be provided.
Controllers
Start push buttons to be green and recessed
Stop push buttons to be red and recessed

Sewage Treatment Plants

Volume 4

57

Requirements for Physical Design

c)

Emergency stop push button to be red and mushroom head


type

d) ON signal lamps to be green


e) OFF signal lamps to be red
f)

III)

Trip signal lamps to be amber

Motor Starters

a) Up to 3.7 kW Direct-On-Line starters


b)

Above 3.7 and up to 7.5 kW Star/Delta starters

d)

More than 22 kW Soft starter

c)
e)

Above 7.5 and up to 22 kW Auto-transformer starters


Above 50 kW Variable speed drive is preferred

Soft starting of motors above 30kW or greater in size is necessary to


minimise power disturbances (e.g. power surge) and process disturbances
(e.g. water hammer). Variable speed drive shall be considered at
application where variable capacity maybe need to enhance the process
flexibility, for example, aeration device and blowers.
4.5.6

Power Supply Systems


Power supply to sewage treatment plants shall be as follows:

Category

Supply Requirements

Sewage Treatment
Plant

Single incomer with properly design control All Class 1, 2 and 3


overflow system during power failure (all STPs
electrical control system shall be located above
design flood level)

B1) Single incomer with diesel generators for


back-up supply.

STP Class 4

B2) Single incomer with control overflow system


and genset contribution fee.
a)

58

Where a SCADA system is provided and essential parameters are


to be monitored during power supply interruptions, a DC supply
or a UPS (uninterrupted power supply) must be provided.
Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

b)

Batteries/UPS shall have the capacity to operate the SCADA


system for a minimum 6 hrs during power failure to safe last
event, to monitor the essential parameters and to enable early
warning system.

c) No direct tapping of power is allowed from distribution board


(DB). Proper protection shall be provided for any direct connection
from switchboard. Earth leakage current breaker (ELCB) shall
be provided for DB.
d)

e)

f)

g)

h)
i)
j)

4.5.7

The power system distribution shall be designed to achieve a


minimum power factor of 0.9. For phase development, the plant
and power system distribution shall be designed for maximum
load and installed in appropriate modular unit to ensure that
the minimum power factor is achievable at all phases of
operation.

Equipment shall be protected by either moulded case circuit


breaker (MCCB) or miniature circuit breaker (MCB) based on
its suitability. Electrical design calculations shall be provided to
justify each selection.
Every control circuit shall be protected with separate MCB.

TNB meter panels shall be installed close to the site entrance or


adjacent to but physically separated from the main switchboard.
Suitable flexible steel conduit with approved adaptors shall be
supplied and fitted between the main switchboard.

All metering panel shall be located flush with the fence and
door opening from outside to enable TNB inspector to read the
kWh and kVAhr reading.
Provide earthing connected with Current Transformer (CT) for
Large Power Consumer (LPC) (i.e. consumption with more than
100A or 10kW).

To provide earthing connected to ELCB/RCCB/ELR or Over


Current & Earth Fault relay to protect overcurrent and surge
current to all wiring connected to TNB metering panel for Large
Power Customer (LPC) or Ordinary Power Customer (OPC). Test
for earthing system shall be below or equal 1 Ohm.

Back-up Generator
a)

b)

If diesel generators are to be provided they shall be used for


essential loads only (these include influent pumping in pump
station, feeding pumps in balancing tank, decanter for SBR;
minimum 30% aeration requirement; emergency services system,
essential lighting and ventilation system.
Where generators are installed, they must be accompanied with
the necessary supporting systems, including automatic cut-in

Sewage Treatment Plants

Volume 4

59

Requirements for Physical Design

c)
d)

e)
4.5.8

in the event of mains failure, fuel storage and transfer; and if


installed indoors, including ventilation, fire detection/protection
and working alarms.

In the event of power interruption/failure; when diesel generators are


used, the SCADA shall be powered by UPS or DC battery.
For plants 100 000 PE, the capacity of the back-up generator
may vary provided detail calculation must be provided to justify
that sewage can be kept in aerobic condition for a maximum
duration of 6 hours
Gen-set shall be sized to the incoming TNB voltage requirement.

Switchgear and Control Gear Assemblies


a)
b)
c)

For simplicity, separate the Supply Authority Metering from the


main switchboard
Electro galvanised plates to be used to protect materials against
corrosion due to high humidity
Panel isolators and door locks to be capable of padlocking open
with 6 mmc - hasp padlock

d) Use separate panel boards for general purpose light and power
e)
f)
g)
h)
i)

4.5.9

Cabinets are to be constructed to prevent the ingress of insects


and vermin

For incomer above 400 A, provide over current and earth fault
protection on all starter circuits in excess of 200 A
Where a circuit has a main and standby supply, provide an
isolator in each supply circuit

Junction boxes for submersible pumps and float controls shall


be above the floor or any possibility of flood level and must
not be located in the wet well.

Control Cabinets
(I)
a)
b)

60

Group all motor starting equipment for an area into multi-motor,


starter control board

General
Provide 900 mm minimum clearance between an open door and
any fixed object.

Provide 900 mm clearance between open cabinet doors of facing


cabinets.

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

c)
d)
e)
f)

g)

Front access cubicles to have the electrical clearance distances


between door mounted equipment and gear tray mounted equipment
as specified in the regulations.
Mount all equipment inside cabinets on gear trays.

All cabinets to have a base frame, at least 50 mm high.

All control panels shall be provided with phase sequence


relay.

All control rooms shall be isolated from invasive environment


of the sewerage system, where carbonisation, corrosion or
condensation may occurs that lead to short-circuiting.

h) Height to be no greater than 1600 mm internally.


i)
j)
k)
l)

m)

Mount cabinet on reinforced concrete plinth, 200 mm minimum


above ground.
Provide a reinforced concrete paved area for the full width of
the cabinet and extending 1 m in front of the cabinet doors,
when they are opened.
Cable entry from the top only.

Provide forced ventilation fan for cubicles housing PLC


equipment.
Provide ventilation for variable speed drives and soft starters.

n) Natural ventilation is suitable for direct-on-line, star-delta and


auto transformer starters.
o)

(II)
a)
b)
c)

d)
e)
f)
g)

The minimum acceptable IP rating and tests required shall be


clearly specified.

Outdoor Cabinets
Self contained, free-standing, weatherproof cabinets to be
constructed of marine grade aluminium, stainless steel grade
316 or glass reinforced plastic.
Mount control indication and alarm facilities on internal
doors enclosing compartments housing electrical plant and
equipment.
Provide external doors with security locking facilities.

Provide double roofs on cabinets to reduce solar effects.

Wall mounted outdoor weather proof control panel shall come


with an awning extended by at least 2 m from the wall.
Floor mounted outdoor weather proof control panel shall come
with a roof extended 2 m from the panel.

External weather proof control panel of equal and more than


100 A shall be provided with permanent CO2 fire extinguisher.

Sewage Treatment Plants

Volume 4

61

Requirements for Physical Design

4.5.10

Control Requirements
This section outlines the general philosophy on control requirements
for the whole facilities.

NO.

TYPE OF PLANT

EWS + PC
(monitoring) /
Data Logger

SCADA

1.

Network Pumping Station


(NPS)

< 100 000 PE

100 000 PE

2a.

Sewage Treatment Plant

Class 3 STPs

Class 4 STPs

2b.

Sewage Treatment Plant


requires full automation, e.g.
sequencing batch reactor.

Class 1, 2 and 3

Class 4 STPs

2c.

Sewage Treatment Plant


(Standard A)

Class 1, 2 and 3

Class 4 STPs

Notes : EWS Early Warning System

I)
a)
b)
c)

d)
e)
f)

g)
h)
i)

62

SCADA Supervisory Control and Data Acquisition

General Considerations
PLC shall restart automatically once the power supply reinstate
after a power supply interruption.
PLC shall be equipped with manual over-ride features.

Continuously running drives shall restart automatically after a


power supply interruption.
Plant to have time delayed restarting sequences for equipment
to avoid overloading power supply.

Transducers shall be used to sense the signal for related warning


alarms.
Trip and shutdown to be measured by separate relays.

The operating status and condition of the process shall be verified


by measuring appropriate performance indicator and not by
inference.
SCADA room shall be air-conditioned.

Telephone line must be laid during construction for all sewerage


works to be equipped with SCADA.

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

II)
a)

b)
III)
a)


Manual Control
Interlocks shall be provided to prevent damage to the equipment
during equipment start up, for example, bearing overload,
overheated, temperature, loss of cooling water, no flow when
operating.
Selector switches to be provided at one location so that an
equipment can be manually operated from that location.
Drive Systems
Each drive must be independently provided with the following
features :

i. ON
ii. OFF
iii.
AUTO

-
-
-

starts and runs the drive


stops the drive
operates the drive in accordance with
automatic control system

b)

Indicate operation by an ammeter

d)

Local annunciation on motor starter of each fault condition.

c)

e)

IV)
a)
b)
c)
d)
e)

Record running hours with a local indicator and by computation


in a central SCADA system where applicable.
Record kilo-Watt.hour (kWh) of major drive equipment.
Automatic System Control Facilities
Displays operator adjustable parameters, examples set point of
top water level in a tank and the target dissolved oxygen level
for a process.
Ability for the authorised operator to adjust the set point of
operator adjustable parameters. A default value should always
be provided.

Displays to advise operator of the set points of non-operator


adjustable parameters. Examples would include the overflow
level on a tank and the trip temperature for a bearing.
Displays measured values by all instruments, used to measure
flow, level, DO, pH, temperature or applicable parameters.

The process control sequences must ensure system problems


such as water hammer overtorque or overpressure the equipment
of air compressors. Time delayed in starting and stopping of
equipment where multiple duty units are installed, use a value
with slower rate the final stage of closing, vary the speed of
equipment during starting and stopping are some of the option
for consideration in careful process automation.

Sewage Treatment Plants

Volume 4

63

Requirements for Physical Design

4.5.11

Supervisory Control and Data Acquisition Systems


(SCADA)
SCADA is the acronym for Supervisory Control and Data Acquisition.
The term refers to a large-scale, distributed measurement (and control)
system. SCADA systems are used to monitor or/and to control chemical,
physical or transport processes. The following briefly describe the
requirements of SCADA while the detail requirements of SCADA are
listed in Appendix C.
The term SCADA usually refers to a central system that monitors
and controls a complete site. The bulk of the site control is actually
performed automatically by a Programmable Logic Controller (PLC).
Host control functions are almost always restricted to basic site override or supervisory level capability. Provision of SCADA system shall
be in accordance with Section 4.5.10.
I)

Control Systems

a)
b)

All equipment shall be tagged in the SCADA system.


Develop sequential function diagrams to specify the control logic
to suit the process operation for each system.
c)
Check the process operation against the resulting sequential
function diagram.
d)
PLC programs to be written in modular form to aid fault finding
and commissioning.
e)
Design programs to be fail to safety. That is, PLC failure will
cause plant to stop.
f) On restoration of supply, all controlled system shall be returned
to the ready position before automatic restart takes place.
g)
Bench test all application programs for PLC, before program
installation on site.
h)
Conduct functional control circuits tests for all items of
equipment.
i)
Ensure PLC programming software licences are delivered.
j)
Provide paper copy listing of all PLC application programs and soft
copies of application program (two copies of each required).
k)
Despite the PE, all plants which requires automation and control
shall be provided with human machine interface (HMI) at site.
II)
a)

Supervisory Systems
Where supervisory systems are used, schedule all graphic displays
required to control plant using columns to define:

i)
64

Graphic Name
Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

ii)

iii)

Information displayed
Control features

b) Update times for screens to be not more than one second.

c) Nominate the alarm title to be used/displayed for each processgenerated fault input or fault generated internally by the PLC
program.

d) Nominate critical and non-critical alarms and the method of


differentiation. Examples would be: nominating an alarm on a
limit which has been reached as critical and an alarm on a limit
which is being approached as non-critical; differentiated by, for
example, red/amber lights or horn/bell).
e)

f)

At least eight variables to be displayed on a trend graph


simultaneously for ease of monitoring and comparison. This is
a measure of the level of software sophistication which should
be expected.
Supervisory system to log running hours for all plant items.

g) Nominate the reports to be generated for plant operation,


management and history. For example, reports to be daily,
weekly and monthly and the list of parameters to be reported
on in each.
h)

Alarm analysis, that is, frequency of occurrence, similar plant


faults, etc, to be provided as part of the supervising programs.

4.5.12

Early Warning System (EWS)

The EWS is used to monitor the status of the equipment operating inside
the treatment plants such as pumps and aeration equipment. It shall act
as the means to communicate information via Short Messaging Service
(SMS), e-mail or via other telecommunication mean to technical staff
for the fast recovery of the treatment system.

EWS system shall be able to transmit digital and analog values from
the remote module to the operator through their inputs (equipment) via
SMS and e-mail messages in text mode. The modules shall be able to
interpret SMS message from the operator to activate or deactivate long
distance machine (remote control).

4.5.13

Instrumentation

Provision for instrumentation shall be in accordance with the following


Table 4.7. Instruments shall be installed in such a way that they can be
removed for maintenance without interrupting the process.

Sewage Treatment Plants

Volume 4

65

Requirements for Physical Design

Table 4.7 Required Process Instrumentation


Treatment Unit

Inlet Pump Station

Aeration
Blower
Decanter
Effluent

Sludge (WAS/RAS)
Electrical Drive
Disinfection
Polymer
Sludge Feed

Instrumentation

STP Class

Level/ Pressure
Flow Measurement
Gas Detector (H2S, CO2, O2 &
Combustible gases)

All
All
4

Air flow/ pressure/ temperature/


rpm

All

Flow Measurement

All

DO/pH/ Turbidity
Temperature

4
4

Position Indicator /Speed

All

Flow Measurement

Am/Volt/HR/kW/Power Factor
meter

All

Dosage/ Level Indicator/


Flowrate

All

Dosage/Transmittance /
Flowrate/outlet water level
indicator

All

Flowrate/ Pressure

All

For STP with PE 10 000 and above, a digital power meter is required to
be installed at all individual panel of major equipment such as raw sewage
pump, air blower, aerators, mechanical dewatering unit etc. The digital
power meter shall be able to monitor the following:
Real-Time Readings

Current, Voltage, Real Power, Reactive Power,


Apparent Power, THD (V and I)

Energy Readings

Accumulated Energy (Real kWh, Reactive kVarh,


Apparent KVAh)

Demand and peak


Readings

Current, Real Power, Reactive Power, Apparent


Power

Other:

Power Factor, Load Operating Time

All parameters measured as mentioned must be retrievable at all time.

66

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

4.5.14

Cables and Cabling Installation


I)
a)

b)
c)
d)
e)
f)
g)
II)

General
Segregate cables into the following categories:
i)

power (less than 1000 V phase to phase)

ii)

instrumentation/telemetry

iii)

control

Wherever possible, use a separate cable-support system for each


cable category.

Separate such cable support systems by minimum clear distances


of 300 mm.
When one cable support system has to be used, separate cable
categories by minimum clear distances of 150 mm.

Secure cable at 900 mm intervals for horizontal runs and 300


mm for vertical runs.
Cable ties shall be made of non-corrosive material and if exposed
to the environment, shall have UV protection.
All cables shall be at least of double PVC protection, and if exposed
to the environment then armoured cable shall be provided.
Instrumentation

a) Use separate cables for digital and analog signals.


b)
Marshal cables in a process or geographical area into junction
boxes.
c) Use multipair cables between areas.
III)
a)
b)
IV)
a)

Buried Cables
Install cables without trees or through joints, unless approved.
All buried cables shall be laid in ducts.
Underground Ducts
Construct road crossings from uPVC conduit of minimum 100
mm diameter with 900 mm cover and encased on all sides with
150 mm concrete.

Sewage Treatment Plants

Volume 4

67

Requirements for Physical Design

b)
c)

All other ducts to be PVC conduit laid with a minimum cover


of 600 mm. Ducts to be bedded in 75 mm sieved sand.
Provide draw strings in all ducts.

d)

Provide cable pits to suit cabling layout and to allow drain-in of


cables through the duct work. Cable pits shall be provided no
greater than 100 m apart. They shall be fitted with trafficable
cast iron covers and equipped with drainage.

e)

Seal ducts into buildings with approved systems providing a fire


rating of 30 minutes.

(V)
a)
b)

Conduits
All cabling within buildings or structures where cable trays are
not permitted, and in all external locations, shall be installed
within conduits.
Conduits installed externally shall be arranged to minimise their
length and exposure. PVC heavy duty conduit is permissible,
where it is protected from physical damage and UV. Otherwise,
metal or flexible conduits shall be used.

c) Use flexible steel reinforced conduit for connections, where relative


movement and removal for maintenance has to be considered.
VI)
a)
b)

4.5.15

Cable Support Systems


Ensure cable support systems in electrical switch rooms, equipment
(for example, pump) rooms and service galleries.

When run in common service galleries, ensure cables are not


adjacent to hot services.

Earthing and Lightning Protection


a)

Provide earthing and lightning protection to meet local


regulations.

b) Use a specialist inspector to verify the installation.


c)

68

Earthing test results shall be submitted and results shall be below


or equal to 1 ohm.

d)

Lightning arrestor test results shall be submitted and results shall


not more than 5 ohms.

e)

Earthing and lightning arrestor chamber shall be of pre-cast


material.
Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

4.5.16

General Purpose Power


Provide general purpose power socket outlets as follows:
a)
b)
c)
d)

4.5.17

Single phase outlet rated at 10 A adjacent to, or inside each


control cabinet and within 10 m of all equipment installations.
Three phase outlet rated at 50 A within 20 m of every screen,
sludge scraper, clarifier rake, grit collector and conveyor.

Three (3) phase (with neutral) outlet rated at 50 Amp shall be


provided at an interval of at least 20 m.

These outlets shall be water proofed industrial type switch socket


outlets (SSO).

Manuals, Drawings and Labelling


a)
b)
c)

d)

Provide equipment manuals that are specific to the plant and


instrumentation supplied.

System manuals describe the way each system manages the


individual items of plant. Ensure these are available in draft
form, before testing and commissioning commences.

Provide plant function diagrams, electrical system, electrical


circuit, Process and Instrumentation Diagram(P&ID), instrument
loop diagrams, electrical design calculations and single line
diagrams with endorsement by qualified person, before the plant
is pre-commissioned.
All plant and equipment are to be provided with inscriptions and
labels to facilitate understanding and safe operation and to satisfy
the requirements of any standards and regulations applying to
the works. Labelling includes:
i)

inscriptions on equipment, cubicles, instruments, process


controllers and on small equipment such as relays, control
switches, indicating lights, etc

ii)

identification of cables at both ends and along their


lengths

iii) identification of terminations for cable cores and cubicle


wiring in accordance with the circuit diagrams
e)

Drawings submitted shall show all unit processes to be constructed,


and equipment to be installed based on the ultimate capacity of
the sewerage system, especially for phase development where
the construction of unit processes and installation of equipment
will be based on phasing.

Sewage Treatment Plants

Volume 4

69

Requirements for Physical Design

f)

4.5.18

Hazardous Areas
a)

b)

4.6

For treatment plant with PLC/SCADA systems, ladder diagram,


programme source codes and programming console unit shall be
provided before pre-commissioning of the treatment plant.

A plan setting out various hazardous areas and classes of electrical


hazard is required. For example, flameproof area in the vicinity
of anaerobic digesters/sludge gas compressors, chemical storages
or laboratories.

Ensure the plant and methods of construction and installation


conform to the requirements of each defined area, as this plan
will be used by the Supply Authority to inspect the area for
conformance.

Material Requirements for STP Structures and


Installations
Materials permitted for structural fabrication in treatment plants are
concrete, reinforced concrete, steel, fibreglass reinforced plastic and
aluminium. The requirements for such materials shall be in accordance
with information provided in the following sub-sections. Any others
material used for STP structures and installations shall obtain special
approval from the Commission.
Structural design of treatment plant structures shall be submitted by
registered professional engineers. They shall be in accordance with the
requirements and standards given in this section and any other relevant
standards, as well as, sound engineering practices.

4.6.1

Concrete and Reinforcement


a)

b)
c)

70

Concrete structures shall be designed in accordance with MS


1195, except that concrete structures for retaining sewage and
other aqueous liquids shall be designed in accordance with BS
8007.
Concrete shall generally comply with the relevant requirements
in MS 523.
Concrete for structures retaining sewage shall have a strength
grade not less than grade C35A. Strength grades higher than
C35A may be specified as required by the Commission.

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

d)
e)

f)
g)

h)

Concrete for structures retaining sewage shall be designed for


buoyancy due to ground condition.

Concrete for purposes other than structures retaining sewage shall


have a strength grade not less than grade C20 where unreinforced,
and not less than grade C30 where reinforced. Strength grades
higher than the minimum may be specified as required by the
Commission.
Concrete structures retaining sewage, shall be lined with high
alumina cement mortar of 20 mm minimum thickness or other
approved liners/lining materials.

Concrete and cement mortar exposed to soils or groundwater


shall be made using a cement suitably resistant to sulphate attack,
as specified in this section. Where part of a concrete structure
is exposed to soils or groundwater, cement suitably resistant to
sulphate attack shall be used for the entire structure.
Cement to be used to resist sulphate attack shall be one of the
following:
i)

ii)

i)
j)
k)

Aggregates shall comply with MS 29 and shall be coarse aggregate


of 20 mm nominal maximum size.

Approval for admixtures shall be obtained prior to inclusion in


the concrete mix. All admixtures shall comply with MS 822.
Steel reinforcement shall comply with:
ii)

m)

portland pulverised fuel ash cement complying with MS


1227.

iii) ground granulated blast furnace slag complying with


MS 1387.
iv) high silica content portland cement
v) supersuphated cement complying with BS 4248.

i)

l)

sulphate-resisting portland cement complying with MS


1037.

MS 144 for cold reduced mild steel wire.


MS 145 for steel fabric.

iii) MS 146 for hot rolled steel bars.


Welding of steel reinforcement shall be in accordance with
BS 7123.
Waterstops for sealing joints in concrete shall comply with
MS 1292.

Sewage Treatment Plants

Volume 4

71

Requirements for Physical Design

4.6.2

Steel
I)

Structural steel

a)

Structural steel sections shall comply with BS 4 or otherwise


with:

i)

EN 10162 for cold rolled steel sections.

ii)

EN 10210 for hot rolled steel sections.

iii) EN 10025 for weldable structural steel.


b)
c)

iv) EN 10296, EN 10297 and EN 10305 for steel tube.

The use of structural steel in building shall be in accordance


with MS 416.

Minor structural steelwork shall be Grade 43A complying with


EN 10025. All other steelwork shall be of appropriate grade, as
determined using MS 416 and other appropriate standards. These
shall be determined by a qualified structural engineer.

II)

Coating for steel

a)

Steelwork that may be in contact with sewage through immersion,


splash or spray, or that is over tanks containing sewage, shall be
protected against corrosion using one of the following coating
systems:
i)

high build tar epoxy system complying with AS 3750.2


and applied in two or more coats to give a total dry film
thickness of not less than 200 m.

ii)

high build micaceous iron oxide pigmented epoxy system


complying with AS 3750.12 and applied in two or more coats
to give a total dry film thickness of not less 200 m.

iii) hot dip galvanised coating of 140 m nominal thickness in


accordance with MS 740.
iv) sealed sprayed zinc coating of 150 m nominal thickness
in accordance with EN ISO 2063.
b) Other coatings providing 10 to 20 years service, before first
maintenance, as selected using Table 3 Part 8 of BS 5493 shall
be considered for approval by the Commission. Steelwork that
is exposed to the external atmosphere, except severe marine
atmospheres, shall be protected against corrosion using one of
the following coating systems:

72

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

i)

ii)

c)

a prime coat of a two pack polyamide cured epoxy zinc


phosphate of dry film thickness 60 to 80 m with a finishing
coat of a high build micaceous iron oxide chlorinated rubber
paint, spray applied to a dry film thickness of 60 to no
more than 80 m.

hot dip galvanised coating of 85 m nominal thickness, in


accordance with MS 740.

iii) sealed sprayed zinc coating of 150 m nominal thickness,


in accordance with EN ISO 2063.

Steel substrates shall be prepared before application of coatings,


in accordance with BS 7079.

d) Other corrosion protection coating systems for steelwork shall be


determined using BS 5493 or AS 2312 for tropical atmospheres
so as to provide 20 or more years to first maintenance.
e) Unprotected steelwork in contact with sewage shall be stainless
steel grade 316S31 complying with EN 10088: Part 1 and 3 or
EN 10029 and EN ISO 9445.
f)

g)
h)

Successive coatings of the one component shall be tinted a


different colour to facilitate overcoating and inspection.
All coatings shall be applied strictly in accordance with the
coating manufacturers printed instructions.
Bolts, nuts, screws and other fasteners shall have either:
i)

ii)
i)

hot dip galvanised, in accordance with MS 739

sherardized zinc coating, in accordance with BS 4921

iii) electro plating


Washers and other small components shall have either:
i)

hot dip galvanised, in accordance with MS 740

ii)

a sherardized zinc coating, in accordance with BS 4921

j) Nuts, bolts, screws and washers in contact with sewage shall be


stainless steel of Grade 316S31 steel complying with EN 10088:
Part 1 and 3 or EN 10029 and EN ISO 9445.
k)

Fasteners of incompatible material to the component being


fastened shall have suitable isolating washers and sleeves.

III)

Marine and Corrosive Environment

a)

All areas within 5 km from the coast line or salt water bodies
shall be classified as marine environment. Sewerage facilities
in marine and corrosive environment e.g. where the atmosphere

Sewage Treatment Plants

Volume 4

73

Requirements for Physical Design

b)

or soil contains high levels of chloride, sulphates and corrosive


chemical elements or compounds shall be adequately designed
to withstand the corrosive actions of the chemicals prevalent in
the environment. Necessary protections shall be provided against
all corrosive actions of the environment.
Design requirement for facilities in marine and corrosive
environment shall include:
i)

ii)
c)

ii)

e)

4.6.3

Concrete shall be resistant to all chemical attacks and be


designed in accordance with BS 8110 Part 1: 1997.

Exposed metal shall be of corrosion resistant and of marine


grade. Proper smooth surface finishing shall be provided for the
metal. Unprotected metals acceptable for use are as follows:
i)

d)

Two coats of sodium silicate shall be applied to all external


surfaces of concrete structures.

SS316L
Aluminium alloy

iii) Materials suitable for use in corrosive environment acceptable


by the Commission
All structural steelwork shall be thoroughly descaled to BS 7079
second quality and shall be painted with 2 coats of two pack
epoxy based red lead primer before leaving the manufacturers
works. In addition, all structural steelwork shall be provided
with protective paint for chloride, sulphate or the prevailing
chemicals in the site after installation.

Cathodic protection shall be provided for all load bearing steel


structures in marine environment for a minimum life of 50
years.

Fibre Reinforced Plastic (FRP)


Only FRP products approved by the Commission shall be used and
FRP products shall not be used for access purposes.
FRP tanks, vessels and appurtenances for sewage treatment processes
shall be designed in accordance with BS 4994 and EN 13923. The
thickness of the structural section of the FRP tank wall shall not be
less than 5 mm and shall be at least of wall thickness as given in
ASTM D 4097.
All other FRP products shall meet the requirements of ASTM C 582
for FRP laminates.

74

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

Notwithstanding any other requirements in standards, all FRP products,


including FRP tanks and vessels for sewage treatment processes, shall
conform to the following material requirements:
a)

FRP properties shall be as determined by design to standards


mentioned in this Section and other relevant standards, but shall
not be less than the following values:

Tensile strength - 80 MPa


Tensile modulus - 7000 MPa
Flexural strength - 140 MPa
Flexural modulus - 6000 MPa
Water absorption - 0.75 %
Barcol hardness - 40
Operating temperature - -40oC to +50oC
Specific gravity - 1.5
Fire rating ASTM E84, < 25s or Class 1 BS476

b) Unsaturated polyester resins shall be used but shall only be


isophthallic, bisphenol A fumurate or terephthalic polyester resins
meeting the requirements of Type B or C of BS 3532.
c)

d)

e)
f)

All surfaces shall have a resin rich layer, gel coat. Surfaces in
contact with sewage, water or any moisture shall comprise of
a resin rich layer at least 1 mm thick. All other surfaces shall
comprise of a resin rich layer at least 0.25 mm thick. Up to 10%
by mass of corrosion resistant glass fibres, (that is, C-glass or
E-CR glass), polyester fibres or acrylic fibres may be used in
the surface layer.
A barrier layer shall be provided behind the surface layer and
shall be at least 1.5 mm thick. The barrier layer shall comprise
of 70 to 80 % by weight resin with the remainder by weight
being E glass or E-CR glass.
The structural layer shall comprise resin impregnated layers of
E glass or E-CR glass and shall comprise at least 25 % E glass
or E-CR glass. Aggregate and filler may be included.
E glass and E-CR glass shall conform to the requirements of:
i)

ii)

EN 14020 for glass rovings.

EN 14118 for chopped strand mat.

iii) BS 3396 for woven fabric.

iv) BS 3749 for woven roving fabric.

Sewage Treatment Plants

Volume 4

75

Requirements for Physical Design

g)
h)

i)
j)
k)
l)

Glass fibres shall have a surface treatment compatible with the


manufacturing process to ensure bonding to the resin.
Aggregates shall only be used in FRP structural layers and
external layers. Aggregates shall be clean, washed, high grade
silica sand containing not less than 95 % silica. Aggregates
shall be of a size not greater than 20 % of the thickness of the
FRP structural layer with a particle size not less than 0.05 mm
and not greater than 5 mm.
Fillers shall only be used as a resin extender and shall comprise
of clean inert material, for example, silica, with particle size less
than 0.05 mm.

Surfaces exposed to sunlight shall incorporate provisions to


minimise ultraviolet degradation, such as, ultraviolet inhibitors,
screening agents or pigment in the outer resin rich layer.
Pigments and dyes shall not normally be required, but where
required by the Commission, shall be of a type and colour
specified by the Commission.
FRP water tanks shall comply with the above requirements and
requirements in:
i)

m)

n)
4.6.4

ii)

MS 1241: 1991 where not constructed of FRP panels.


MS 1390: 1995 where constructed of FRP panels.

All design of package plants using FRP materials shall take


into account for the buoyancy effects. This effect is of concern
during high ground water conditions and emptying of the tank
content during desludging works.
Anchor strap shall be at least stainless steel grade 304.

Aluminium
a)

b)

Aluminium is found primarily as the ore bauxite and is remarkable


for its resistance to corrosion (due to the phenomenon of
passivation) and its light weight. Structural components made
from aluminium and its alloys are very important in which light
weight, durability, and strength are needed.
Wrought aluminium and aluminium alloys shall comply with:
i)

ii)

BS 1161 for structural purposes.

EN 485 for sheet plate and strip.

iii) EN 754 for drawn tube.

iv) EN 755 for bars, extruded round tubes and sections.

76

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Physical Design

v)

EN 1676 for ingots and castings.

vi) BS 4868 for profiled sheet.


c)
d)

4.6.5

Anodic oxidation coating on aluminium shall be in accordance


with EN 12373.
Requirements for structural design, materials, workmanship and
protection of aluminium shall be in accordance with BS 8118

HDPE (High Density Polyethylene)


High-density polyethylene (HDPE) is the high density version of PE
plastic. Its molecules have an extremely long carbon backbone with
no side groups. As a result, these molecules align into more compact
arrangements, accounting for the higher density of HDPE. HDPE is
stiffer, stronger, and less translucent than low-density polyethylene.
HDPE is lighter than water, and can be moulded, machined and joined
together using welding.
High-density polyethylene shall comply to the following physical
properties:

Tensile Strength

0.20 0.40 N/mm2

Notched Impact Strength

no break Kj/m2

Max Cont Use Temp

650C

Thermal Coefficient of expansion


Density

Minimum Require Strength

Sewage Treatment Plants

Volume 4

100 220 x 10-6


0.944 0.965g/cm3
8.0 MPa

77

Requirements for Physical Design

78

Volume 4

Malaysian Sewerage
Industry Guidelines

Section 5
Requirements for Individual
Treatment Processes

Requirements for Individual Treatment Processes

80

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

5.1

Introduction
All new applications for sewage treatment plant approval shall follow
the design requirements as stipulated in this section. These requirements
have been formulated as a gradual change in sewage treatment methods
for Malaysia prior to enforcement of ultimate requirements as stipulated
in Sections 3 and 4 of this volume.
Design requirements for each stage of the sewage treatment process, as
shown in Figure 5.1 are given in this section.
Figure 5.2 gives an overview of the typical flow diagram and elements
of a sewage treatment plant. Figure 5.2 also shows how one facility
is closely related to another and thus has an impact upon the overall
design.
Sewage treatment plants must be designed to produce an effluent quality
that conforms to either Standard A or Standard B or any other special
requirements under the provisions of the Environmental Quality Act.
The major indices are those of BOD5, Suspended Solids, COD, Oil &
Grease, Ammoniacal Nitrogen, Nitrate Nitrogen and Total Phosphorus.
The requirement to comply with absolute standards, where no failures
are permitted by law, means that new sewage treatment plants must be
designed to produce average effluent qualities well below those permitted
by the Standard figures. Design values for final effluent shall be used in
the design of new treatment works are given in Table 3.2. These design
effluent levels serve as the basis for the design requirement of each unit
process given in the following sub sections.
General ventilation systems shall be provided in compliance to the OSHA.
The potential for odour generation, its impact and treatment, shall be
considered in all aspects of design. Odour treatment equipment shall be
selected that such odours be reduced to the lowest possible level and
in compliance to the EQA.

Sewage Treatment Plants

Volume 4

81

Requirements for Individual Treatment Processes


Requirements for Stages of Sewage Treatment

Figure 5.1 Typical Treatment Process Flow Chart


Figure 5.1 Typical Treat
ment Process Flow Chart
Treatment
Stage

Pre
Treatment

Primary
Treatment

Secondary
Treatment

Treatment
Processes
1

Primary
Screen

Pump
Station

Design
Requirements
Section 5.2

Function

Removes rocks, roots and


rags

Lifts sewage and provides


consistent flow to the
treatment system

M/O

Section 5.3

Secondary
Screen

Section 5.4

Removes smaller/finer
particles from sewage

Grit/Grease
Removal

Section 5.5

Removes sand, gravel and


other inorganic materials;
separates oil & grease

Balancing
Tank

M/O

Section 5.6

Balances and equalises flow

Primary
Sedimentation

M/O

Section 5.7

Removes settleable
solids/materials

Biological
Treatment

Section 5.8

Remove major polutants


(BOD and SS)

Secondary
Sedimentation

Section 5.9

Separates treated effluent


and settled sludge

Disinfection

Section 5.10

Destroy disease causing


organisms

Flow Meter

Section 5.11

Measures and records flows

10

Bio Solids
Handling

Requirements
Mandatory (M)
Optional (O)

11

Thickener
Stabilisation
Holding
Dewatering

M/O

Section 5.12

Reduces potential
detrimental effect on the
environment and converts
sludge to a form suitable for
ultimate disposal

Sludge Disposal
82

70

Volume 4

V ol ume 4

Malaysian Sewerage
Industry Guidelines

M al aysi an S ewerage
I ndustry G ui del i nes

Raw
Sewage
Inlet

Sewage Treatment Plants

Sewage Treatment Plants

Ultimate Disposal

Balancing
Tank

Sludge Storage Area

Grit/Grease

Secondary
Screen

Incinerator/Dryer

Sewage
Pump Station

Primary
Screen

Volume 4

Volume 4
Return

Sludge Drying Bed

Mechanical Sludge
Dewatering

Alternate

Alternative

Primary Clarifier

Alternative

Final Clarifier

Mechanical Sludge
Thickener

Flow
Distribution

Sludge Holding
Tank

Sludge Digester

Liquor

Return Sludge
Pump Station

C. Trickling Filter
D. RBC

B. Extended Aeration
Activated Sludge

A. Conventional
Activated Sludge

Biological System

Disinfection
10

Effluent To
Nearest
Receiving
Watercourse

Flow Meter

Requirements for Stages of Sewage Treatment


Requirements for Individual Treatment Processes

Figure5.2
5.2 Typical
Typical
Elements
Process
Diagram
of a
Figure
Elements
and and
Process
Flow Flow
Diagram
of a Sewage
Sewage
Treatment
Treatment
PlantPlant

83

71

Requirements for Individual Treatment Processes

5.2

Design of Primary Screens

5.2.1

Purpose of Primary Screens


Upon reaching the sewage treatment plant, sewage flows through the
primary screening facility which is the first stage of treatment. The
screens must be provided upstream of all inlet pump stations and shall be
designed to protect downstream processes and equipment. The purposes
of primary screens are:
a)

b)
5.2.2

to protect equipment from rags, wood and other debris

to reduce interference with in-plant flow and performance

Inlet Chamber
Provision for inlet chamber before the primary screen channel is necessary
for proper operational and maintenance. The summarised requirements
for inlet chamber are as follows:
Table 5.1 Requirements for Inlet Chamber

Unit
Process

Requirements

> 20 000
PE

> 50 000
PE

Yes

n/a

n/a

Dual

n/a

Yes

Yes

Motorised

n/a

No

Yes

Inlet
Chamber

Type

20 000
PE

Single

Mandatory

Notes

Single and dual


penstocks are referring
to members of penstocks
required. For more
than 50 000 PE, the
main penstock must be
motorised.

n/a Not applicable


a)
b)
c)

84

A penstock shall be installed upstream to isolate the pump station


in the event of flooding in relation to the bypass and emergency
overflow.

For safety reasons, a double penstock system shall be provided


at the inlet works of all plants with pump station above
20 000 PE.

The penstock spindle shall extend to pump station ground level


and shall be suitably positioned to allow unrestricted operation of
the penstock.

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

Figure 5.3 Typical Details of Double Penstock

CLEAR SPACING
MANUAL FINE SCREEN

FIRST PENSTOCK

SECOND PENSTOCK

OVERFLOW PIPE
DISCHARGETO DRAIN

PRIMARY
SCREEN
CHAMBER

INLET
CHAMBER

450mm

1:2

5.2.3

IL

Design Requirements for Primary Screens


Table 5.2

Provision of Primary Screens


Numbers of Primary Screen

Requirements

Duty
Standby

5000 PE

> 5000 PE

1 Unit

Mechanical

1 Unit

Manual

Mechanical

1 Unit

1 Unit

1 Unit

Manual

By Pass

Sewage Treatment Plants

Volume 4

85

Requirements for Individual Treatment Processes

Table 5.3 Design Parameters for Primary Screens

Description

Unit

Maximum clear spacing

mm

Slope to the vertical

Design Criteria
Manually
Mechanically
Raked
Raked#
25

25

30o 45o

15o 45o

Maximum approach velocity at


the feed channel

m/s

1.0

1.0

Maximum flow through velocity


at the screen face

m/s

1.0

1.0

Minimum freeboard

mm

150*
30

150

See Figure 5.4

day

Estimated volume of screenings


per volume of sewage

m3 / 106 m3

screenings skip storage capacity


Minimum channel width
Minimum channel depth

RC Staircase with riser detail

mm

500

500

1 unit

Anti-skid and
non-corrosive

Anti-skid and
non-corrosive

mm

500

500

Notes:
*
Designer shall ensure that with 50% of blockage at the face of screen, sufficient
freeboard is provided to prevent the approach channel from overflowing
#

Washing and dewatering of screenings shall be provided.

5.2.4

General Requirements
All plants must include:
a)

An emergency manual bypass screen. In the event of system


failure and/or power outages, the flow shall be automatically
directed to the bypass. It shall also be able to cope with
maximum flow.

b)

Hand railings, kick plates, standing platforms and other safety


features to improve maintenance

Screen chambers must be of open channel construction with proper ventilation.


Forced ventilation must be used if chambers are enclosed.

86

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

Screens must be designed to withstand the flushing velocity. In the


event of the manual bypass screen being blocked, sewage must be able
to flow over the top of the screen without causing excessive backup
flooding or overflows.
Chambers design must have taken into consideration necessary health
and safety aspects. The chamber must also be hydraulically efficient to
prevent the settlement of solids in the chamber.
Macerators and communitors as replacements for primary screens are
generally not recommended. It may be considered if the consultant is
able to provide good engineering reasons for its application.
Reinforced concrete staircase with proper handrailing must be provided
to access screen chambers.
Shaftless screw conveyors and belt conveyors may be used where
required. The screw conveyor shall be equipped with easy to remove
covers. The frame and support of screw conveyor shall be of minimum
stainless steel Grade 304 while the screw shall be of high tensile steel.
The belt conveyors shall be of heavy duty reinforced rubber belts on
a protected mild steel frame. Conveyors shall normally be installed on
a very slight grade to allow drainage, with foul water returned to the
inlet channel.
All screenings raked from mechanical screen shall be dropped into a
skip.
A proper standpipe shall be provided and located within 3 m to the
screen chamber.
Figure 5.5 and 5.6 illustrate typical arrangement of screen chambers of
various depths.
Refer also to relevant clause of MS 1228 for more details.

Sewage Treatment Plants

Volume 4

87

Requirements
Individual
Treatment
Processes
Requirements for
for Stages
of Sewage
Treatment

Figure
ScreeningsCollected
CollectedFrom
From
Primary
Screens
Figure 5.4 Quantities
Quantities of
of Screenings
Primary
Screens

100

80

Screenings, m 3/ 10 6m 3 of Sewage

Average
Maximum
60

40

20

Opening Between Bars, cm

88

76

Volume 4

Malaysian Sewerage
Industry Guidelines

Volume 4

Malaysian Sewerage
Industry Guidelines

INCOMING SEWER

Sewage Treatment Plants

Volume 4

Sewage Treatment Plants

Volume 4

INCOMING SEWER

R.C STAIRCASE
TO ENGR'S DETAIL

HANDRAIL

HANDRAIL

PENSTOCK

R.C STAIRCASE TO
ENGR'S DETAIL

PENSTOCK

CHAIN GUARD

GRATING COVER

MECHANICAL COARSE SCREEN

CONC. APRON LAID TO FALL

PLAN
(PE > 5000)

SECTION A-A

STOP LOG

DRAIN

RAMP DOWN

PERFORATED SLAB

SCREENINGS COLLECTION BIN

WP

GRATING
COVER

HANDRAIL

HANDRAIL

PENSTOCK

PENSTOCK

CHAIN GUARD

INCOMING SEWER

R.C STAIRCASE
TO ENGR'S DETAIL

INCOMING SEWER

STOP LOG

CONC. APRON
LAID TO FALL

DRAIN

SECTION A-A

PLAN
(PE 5000)

R.C STAIRCASE TO
ENGR'S DETAIL

RAMP
DOWN

WP

S.S PERFORATED
TROUGH

SCREENINGS COLLECTION BIN

Requirements for Stages of Sewage Treatment

Requirements for Individual Treatment Processes

Figure 5.5 Typical Drawing of Screen Chamber based on depth


Figure 5.5 Typical
Drawing of Screen Chamber based on depth
(<5 m for different PE)
(<5m for different PE)

< 5m

< 5m

89

77

< 5m

INCOMING SEWER

STOP LOG

R.C STAIRCASE
TO ENGR'S DETAIL

HANDRAIL

HANDRAIL

PENSTOCK

R.C STAIRCASE TO
ENGR'S DETAIL

INCOMING SEWER
CHAIN GUARD
PENSTOCK
A

M.S GRATING COVER

DRAIN
CONCRETE APRON
LAID TO FALL

SECTION A-A

MECHANICAL
COARSE SCREEN

PLAN VIEW
(PE > 5000)

RAMP
DOWN

DN

WP

OPENINGS

CAT LADDER

R.C PERFORATED SLAB

SCREENINGS
COLLECTION BIN

MECHANICAL COARSE
SCREEN

R.C STAIRCASE
TO ENGR'S DETAIL

> 5m
INCOMING SEWER
STOP LOG

HANDRAIL

PENSTOCK

R.C STAIRCASE TO
ENGR'S DETAIL

CHAIN GUARD
PENSTOCK

HANDRAIL

M.S GRATING COVER


INCOMING SEWER

DRAIN
CONCRETE APRON
LAID TO FALL

SECTION A-A

PLAN VIEW
(PE 5000)

RAMP
DOWN

MANUAL COARSE
SCREEN

OPENINGS

S.S PERFORATED
TROUGH

CAT LADDER

R.C PERFORATED SLAB

SCREENINGS
COLLECTION BIN

DN

WP

Requirements for Individual Treatment Processes

Requirements for Stages of Sewage Treatment

Figure 5.6 Typical Drawing of Screen Chamber based on Depth.


(>5 m for different PE)

90

Volume 4

Malaysian Sewerage
Industry Guidelines

78

Volume 4

Malaysian Sewerage

Requirements for Individual Treatment Processes

5.3

Design of Pump Stations

5.3.1

Purpose of Pump Stations


Inlet pump stations must be preceded by primary screens to protect
the pumps from being damaged or clogged. The inlet pumps of the
treatment works must be capable of handling raw unscreened sewage.
Water pumps must not be used as they are not designed to cope with
matters that may be found in sewage and the variability and quantity of
sewage flow. The purposes of pump stations are:
a)

to lift sewage to a higher point for treatment

c)

to prevent overflow of raw sewage

b)

5.3.2

to provide consistent inlet flows to the treatment system

Design Requirements
(I)

Structural Requirements

a)

Substructure shall be constructed with reinforced concrete


using cement resistant to chemical attack, aggressive soils and
groundwater.

b)
c)
d)
e)
f)
g)

Safe and suitable access to the wells shall be provided.

If cement used is not resistant to the chemical attack, internal


walls shall be made resistant to sulphide corrosion by coating
with high alumina cement or approved equivalent coating.
A controlled overflow from the last manhole upstream of the pump
installation shall be provided to allow emergency maintenance
works.
Access shall be provided at all locations where operation and
maintenance works take place.
Static screen shall be provided at specific locations where it needs
to protect downstream unit processes.
Access covers shall be hinged with a lifting weight not exceeding
16 kg.

Sewage Treatment Plants

Volume 4

91

Requirements for Individual Treatment Processes

II)

Ventilation Requirements

a)

Ventilation shall be provided for all hazardous zones of the


pump station.
Below ground pits shall have mechanical ventilation.
Separate ventilation shall be provided for wet wells and dry
wells.
Lighting systems shall be interconnected with ventilation.
Permanent ventilation rate and air changes shall comply with
Section 6 of this Guidelines.

b)
c)
d)
e)
III)

Odour Control Requirements

a)

Isolate odorous gases from general ventilation by containing


identified odour generating sources with a separate local exhaust
system.
Containment of the odour sources shall be by installing lightweight
and corrosion resistant covers/enclosures designed for practical
operation and maintenance works.
Local exhaust rates for containment shall be designed to provide
a negative pressure preventing build up of toxic, corrosive or
explosive gases and to include provision for process air or air
displaced by changes in the level of liquid inside the covered
space.
The odourus air in the local exhaust system shall be conveyed
through well designed and balanced ductworks by a centrifugal
fan to an effective odour treatment system.
Odour treatment equipment shall be selected such that odour is
reduced to the lowest possible level and in compliance to the
EQA.
In situation where specific gases such as hydrogen sulphide and
ammonia are significantly present, provide a pre-scrubber unit
upstream of the main odour treatment equipment.
Containment, exhaust and treatment shall be designed as an
integrated package.

b)
c)

d)
e)
f)
g)
h)

Consideration must be given to the life span of the odour control


system and associated costs in operating and maintaining such
a system.

IV) Wet Wells Requirements


a)

92

Suction channels shall be designed to avoid dead zones, i.e.,


prevent solids and scum accumulation. All dead zones shall be
chamfered.

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements
for Individual
Treatment
Processes
Requirements
for Stages of
Sewage Treatment

b)
b)
c)
c)
d)
d)
e)
e)
f)
f)
g)
g)
h)
h)
i)
i)

Benching shall
shallbebe
such
to minimise
deposition
solid
Benching
such
that that
to minimise
deposition
of solid of
matters
matters
on
the
floor
or
walls
of
wet
wells.
The
minimum
slope
on the floor or walls of wet wells. The minimum slope of benching
of benching
be 45o to the horizontal.
shall
be 45o toshall
the horizontal.

Benching shall
shallpreferably
preferably
extended
the pump
Benching
be be
extended
up toupthetopump
intake.intake.
Minimum hopper
hopper bottom
bottom slope
slopeshall
shallbe
be1.5
1.5vertical
verticaltoto1.0
1.0horizontal.
horizontal.
Minimum
Tapered slope
slopeshall
shallbebe
provided
upthe
to suction
the suction
section.
Tapered
provided
up to
section.

Automatic flushing
flushingofofgrit
gritand
andsolids
solids
recommended
plants
Automatic
is is
recommended
for for
plants
of
of
PE
>
2
000.
PE > 2,000.
The difference
differencebetween
betweenstop
stopand
andstart
start
levels
shall
a maximum
The
levels
shall
be abemaximum
of
of
900
mm
and
a
minimum
of
450
mm.
900 mm and a minimum of 450 mm.
The difference
difference in
in level
level between
between start
start oror stop
stop ofof duty
duty and
and assist
assist
The
pumps
shall
be
greater
than
or
equal
to
150
mm.
pumps shall be greater than or equal to 150 mm.
The minimum internal width of wet well shall not less than 2m.
The minimum internal width of wet well shall not less than 2m
Where possible, wet wells shall be open and guarded by a handrail
Where possible, wet wells shall be open and guarded by a handrail
or open mesh grating. The grating shall be easily and safely
or open mesh grating. The grating shall be easily and safely
removed.
removed.
Figure
ofWet
WetWell
Well
Figure 5.7
5.7 Typical
Typical Dimensions
Dimensions of
Submersible
PumpStation
Station
Submersible Pump
MIN 2000
(/S)
QO (I/S)
i

INCOMING SEWER
Qi (I/S)
(/S)

D2

HIGH LEVEL ALARM

150

STANDBY CUT IN LEVEL

CUT IN LEVEL

CUT OUT LEVEL

LOW LEVEL ALARM

D1

Note :
Q1 = Incoming flow rate
QO = Forcemain Discharge rate
D2 = Forcemain Diameter, min 100
d

= Difference between stop & start level, Min 450 Max 900

= Minimum submergence, depends on manufacturer recommendation

= Minimum clearance between pump suction and wet-well invert

All dimension are in mm unless otherwise state

Sewage Treatment Plants

Volume 4

93

Sewage Treatment Plants

Volume 4

81

Requirements for Individual Treatment Processes


Requirements for Stages of Sewage Treatment

Figure 5.8 Typical Dimensions of Dry Well


Figure 5.8 Typical Dimensions of Dry Well
Submersible Pump Station
Submersible Pump Station
IN
Qi COMI
(I/S NG
SE
)
W

ER

HIGH LEVEL ALARM

150

STANDBY CUT IN LEVEL

CUT IN LEVEL
CUT OUT LEVEL
LOW LEVEL ALARM/EMERGENCY
CUTOUT

D1

150

D2 to D2

3
D2 to D2
4

D2

QO (l/s)

150 (min)

ALLOW ADDITIONAL DEPTH


FOR SOLID HEAVY OBJECTS

IN
Qi COM
(I/S I NG
SE
)
WE
R

150 S

HIGH LEVEL ALARM


STANDBY CUT IN LEVEL

CUT IN LEVEL
CUT OUT LEVEL

D2 TO D2

D2

LOW LEVEL ALARM/EMERGENCY


CUTOUT

Q0 (l/S)

150

D1

Note :
Q1 = Incoming flow rate
QO =

Forcemain Discharge rate

D2 =

Bellmouth Diameter

ALLOW ADDITIONAL DEPTH


FOR SOLID HEAVY OBJECTS

D1 = Suction Diameter, Min 100


D =
S

Difference between stop start level, Min 450 and Max 900

= Minimum depth above pump intake to prevent vortex formation

V)
(V)

Lighting Requirements
Lighting Requirements

a)
a)
b)
b)

Wet wells and dry-wells shall be adequately lit.


Wet wells and dry wells shall be adequately lit.
Electrical installations
installationsshall
shallbebewater
waterproof
and vapour
vapour proof
prooforor
Electrical
proof and
explosion
proof.
explosion proof.

c)
c)

If lights
lights are
arefitted
fittedoutside
outsidethethe
well,
then
a spotlight
system
If
well,
then
a spotlight
system
may may
be
be
used
to
provide
adequate
illumination.
used to provide adequate illumination.

94

Volume 4

Malaysian Sewerage
Industry Guidelines

82

Volume 4

Malaysian Sewerage
Industry Guideline

Requirements for Individual Treatment Processes

VI)

Level Controls

a)

Either floats or ultrasonic level controller may be used for the


start-stop levels of pumps. Instrument with environmental friendly
features are recommended.
Ultrasonic level control is recommended due to its clog-free
nature.
Non-mercury type floats are recommended.
Hollow tube electrodes are not acceptable.
Level controller shall be placed where they are not affected by
the turbulence of incoming flow and where they can be safely
removed.

b)
c)
d)
e)

VII) Pump Hydraulic Design


a)

The submission of pump hydraulic design and performance shall


include:
i)

ii)

System curves
Pump curves

iii) Operating points of pumps with respect to flow and total


dynamic head (TDH)

b)
c)
d)
e)
f)
g)

5.3.3

iv) Operating characteristics such as efficiency, horsepower and


motor rating

Pump shall be operating within their best efficiency range at


normal operating condition.
Pumps are to be equipped with an auto restart mechanism in the
event of power failure.

Dry-well mounted pumps shall be equipped with auxiliary services


such as cooling and gland seal water supply.

Pumps equipped with cutting or macerating facilities are not


acceptable.
Guide rail, lifting device and other wet well fittings must be
fabricated of stainless steel that is corrosion resistant. The use
of hot dip galvanised iron is not recommended.

Horizontal installation of pumps is not allowed. All pumps shall


be installed vertical, unless the Consultant is able to provide good
engineering reasons for horizontal installation.

General Requirements
a)

Drainage of dry-wells and valve pits shall be provided. Drainage


lines shall be equipped with back flow protection to ensure that
the chamber is not flooded.

Sewage Treatment Plants

Volume 4

95

Requirements for Individual Treatment Processes

b)

The wet well shall not be housed with a building structure.

d)

Pipework

c)

Where separate valve pits are used, the connecting pipes shall
incorporate at least two flexible joints to allow for differential
settlement.
i) Pipe work shall be of ductile iron or cast iron with cement
internal lining. Other approved material by the Commission
may be used.
ii) External surface of pipework in chambers and wells shall be
epoxy coated.
iii) Buried ductile iron pipe shall have polyethylene sleeving.
iv) Pipe within wells and pits shall have flanged joints, while
pipe laid in the ground shall have spigot and socket joints.
v) Pipe work shall be adequately supported on concrete plinths
or steel structural supports.
vi) Flanges shall be located at least 150 mm away from
structures.
vii) Dismantling joints such as bends shall be provided.
viii) Pumping thrust shall be resisted using pipe supports inside
chambers and by mass concrete thrust blocks poured against
undisturbed soil in the ground outside chambers.
ix) No welding joints are allowed.

e) Valves
i) Gate valves are preferred with rising spindles operated by
a tee piece.
ii) The uses of counterweights are recommended. Tapping
(12 mm BSP) shall be located upstream and downstream of
check valves.
Also refer to additional requirements in relevant Clause of MS 1228.

96

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes


Requirements for Stages of Sewage Treatment

Figure 5.9 Typical Details of Wet-well Pump Station


Figure 5.9 Typical Details of Wet-well Pump Station

MECH. COARSE SCREEN


INCOMING SEWER

STEPS

GRATING COVER

OVERFLOW PIPE
DISCHARGE TO DRAIN

V.C.P
STAND PIPE
CONC. APRON

COLLECTION BIN
CLEAR SPACING
S.STEEL MANUAL
FINE SCREEN

OVERFLOW
CHAMBER

INFLUENT PUMP
PRIMARY SCREEN

A
GRATING COVER
17 18 19 20 21 22 23
STEPS

A
PUMP SUMP

S.STEEL HANDRAIL
PENSTOCK

16 15 14 13 12 11 10 9 8 7 6 5 4 3 2

EXPLOSION PROOF
SPOT LIGHT
CHECK VALVE
FLEXIBLE COUPLING
GATE VALVE

DELIVERY PIPE

R.C STAIRCASE TO ENGR'S DETAIL

PLAN VIEW
LIFTING I-BEAM C/W
CARRIER
HANDRAIL
CLEAR SPACING
MANUAL FINE SCREEN

MECH. COARSE SCREEN


CHAIN GUARD
CHECK VALVE
FLEXIBLE COUPLING
GATE VALVE
DELIVERY PIPE

PENSTOCK

OVERFLOW
PIPE DISCHARGE
TO DRAIN

NON-EXPLOSION SPOT LIGHT

OVERFLOW
CHAMBER

DELIVERY PIPE
GUIDERAIL

S.S PERFORATED
TROUGH

PUMP SUMP

LIFTING CHAIN

PRIMARY SCREEN
CHAMBER
CONC. SLAB
R.C WALL TO
ENGR'S DETAIL

IL

1:2

IL

FRP STOP LOG C/W


HAND WHEEL
IL

OPENING
ALARM
START

MANUAL COARSE SCREEN


STOP

SECTION A-A

Sewage Treatment Plants

Sewage Treatment Plants

Volume 4

Volume 4

97

85

Requirements for Individual Treatment Processes


Requirements for Stages of Sewage Treatment

Figure
Typical
Details
of Dry-well
Pump Station
Figure5.10
5.10 Typical
Details
of Dry-well
Pump Station
OVERFLOW PIPE DISCHARGE
TO MONSOON DRAIN

OVERFLOW CHAMBER
DRAIN

RAMP DOWN

CONC. APRON LAID TO FALL

3 LAYER CONC. VENTILATION


BLOCK AT TOP AND BOTTOM LEVEL

LIQUID RETURN FROM OTHER UNIT PROCESSES

WP

FORCEMAIN
MECHANICAL COARSE SCREEN

GATE VALVE.

NCOMING SEWER
AIR EXTRACTOR FAN

14 15 16 17 18 19 20 21

R.C STAIRCASE TO ENGR'S DETAIL

G.I CHAIN GUARD.

G.I CHAIN GUARD


PENSTOCK
GRATING COVER

3 LAYER CONC.
VENTILATION BLOCK
AT TOP AND BOTTOM
LEVEL

CHECK VALVE.

CONC. THRUST BLOCK.

12
11
10
9
8
7
6
5
4
3
2
1

CONC. THRUST BLOCK.

EXTRACTOR FAN
R.C STAIRCASE TO ENGR'S DETAIL.
CONCRETE VENTILATION
BLOCK AT TOP AND BOTTOM LEVEL

DN

CHAIN GUARD.

DN
13 12 11 10 9 8 7 6 5 4 3 2 1

13
14
15
16
17
18
19
20
21
22
23

ADJUSTABLE GLASS
LOUVRES WINDOW

SPOT LIGHT
CHEQUER PLATE

DOOR

BRICKWALL C/W CEMENT


PLASTER ON BOTH SIDES
DRY PIT PUMPS

PLAN VIEW
COPPER TYPE
LIGHTNING ARRESTOR

LIFTING I-BEAM C/W


CARRIER

RAIN WATER DOWN PIPE


TO NEAREST SUMP

MECHANICAL COARSE SCREEN

PENSTOCK
HANDRAIL

R.C GUTTER TO ENGR'S DETAIL

DOOR

SCREENINGS COLLECTION BIN

BRICKWALL C/W
CEMENT PLASTER ON BOTH SIDES
WINDOW

CHEQUER PLATE

3 LAYER CONC. VENTILATION


BLOCK

HANDRAIL
R.C STAIRCASE TO ENGR'S DETAIL

WET WELL

DRY WELL

PERFORATED SLAB
CAT LADDER
OPENINGS

INCOMING SEWER

(FLOAT SWITCH)

CHECK VALVE

2nd. STANDBY PUMP START


2nd. DUTY PUMP START

GATE VALVE

1st.. DUTY PUMP START

ALARM
1st. STANDBY PUMP START

ALL PUMP STOP

STOP LOG

SUMP BWL

DEWATERING PUMP

DRY PIT PUMPS

SECTION VIEW

86

98

Volume 4

Volume 4

Malaysian Sewerage
Industry Guideline

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

Table 5.4 Recommended Design Parameters for Inlet Pump Stations


1000 Design Parameters
Description

Unit

Type of station
Number of pumps
(all identical and work
sequentially)
Pumps design flow

PE 1,000

1,000 < PE 5,000

Wet well
2
1 duty,
1 standby
(100 % standby)
Each at Q

Wet well
2
1 duty,
1 stand-by
(100 % standby)
Each at Q

peak

peak

Maximum retention time at Q

min

30

30

Min pass through openings


Minimum suction and discharge
openings
Pumping cycle
(average flow conditions)
Lifting device*

mm

75

75

mm

100

100

ave

start/
hour

6 min
15 max
Lifting davit

6 min
15 max
lifting beam and
block

Design Parameters
Description

Type of station

Unit

5,000 < PE 20 000

Wet well or dry-well


up to 10,000 PE
10,000 PE above wet
well and dry-well
4 (2 sets)
1 duty, 1 assist,
per set
(100 % standby)

Number of pumps
(all identical and work
sequentially)

PE > 20,000

Wet well and dry


well
6 (3 sets)
1 duty, 1 assist,
per set
(50 % standby)

min

each at 0.5 Qpeak


30

each at 0.25 Qpeak


30

Min pass through openings

mm

75

75

Minimum suction and discharge


openings
Pumping cycle
(average flow conditions)

mm

100

100

start/
hour

6 min
15 max

6 - 15

Pumps design flow


Maximum retention time at
Qave

Lifting device*

Mechanical and block

mechanical

Note: * Motorised hoists shall be provided when the lifting weight exceeds 100 kg

Sewage Treatment Plants

Volume 4

99

Requirements for Individual Treatment Processes

5.4

Design of Secondary Screens

5.4.1

Purpose of Secondary Screens


After the inlet pump station, further screening is required to reduce the
remaining floating matter and finer particles in the sewage that will
disrupt the treatment process downstream. The purposes of secondary
screens are:
a)
b)

5.4.2

to remove material such as plastic, paper, cloth and other particles


that may cause problems to the treatment process downstream.

to minimise blockages in sludge handling and treatment


facilities.

Design Requirements
Plants of all sizes must be installed with secondary screens. The channel
shall be designed for Qpeak or pump flow whichever is greater. Approach
channel shall be design to ensure good contribution of velocity
A minimum of two screens are required for duty and standby. Facility
for a screened bypass must be provided in the event of clogging. Where
mechanically cleaned screening devices are installed auxiliary manually
cleaned screen shall be provided.
Table 5.5 Provision Requirement of Secondary Screens
Requirements

Duty
Standby
Bypass

100

Manual

Mechanical

Manual

Mechanical

Screen

Volume 4

Numbers of Secondary Screen


5000 PE
>5000 PE

1 Unit

1 Unit

1 Unit

1 Unit

1 Unit

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

Table 5.6 Design Parameters for Secondary Screens

Description

Unit

Maximum clear spacing

mm

Maximum approach velocity at


the feed channel
Maximum flow through velocity
at the screen face
Minimum freeboard

Slope to the vertical

Estimated volume of screenings


per volume of sewage
Screenings skip storage capacity
Minimum channel width
Minimum channel depth
RC Staircase with riser detail

Design Criteria
Manually
Mechanically
Raked
Raked #
12
30o 45o

12
15o 45o

m/s

1.0

1.0

m/s

1.0

1.0

mm

150*

150

m3 / 106 m3
day
mm
mm
1 unit

See Figure 5.4


7
500
500
Anti-skid and
non-corrosive

7
500
500
Anti-skid and
non-corrosive

Notes:
* Designer shall ensure that with 50% of blockage at the face of screen, sufficient
freeboard is provided to prevent the approach channel from overflowing
# Washing and dewatering of screenings shall be provided.

5.5

Design of Grit and Grease Chambers

5.5.1

Purposes of Grit and Grease Chambers


This unit process is important to minimise problems associated with grit
and grease. Grit creates problems to pumps and also sludge digestion
and dewatering facilities. Grease creates problems at the clarifier and
is carried over in the final effluent.
In grit removal system, grit or discrete particles that have subsiding
velocities or specific gravities substantially greater than those of organic
putrescible solids, e.g. eggshells, sands, gravel are removed by gravitate
settlement or centrifugal separation. Same principle apply to oil and
grease removal system, where free oil and grease globules lighter than
water rise through the liquid and skimmed from the top surface.

Sewage Treatment Plants

Volume 4

101

Requirements for Individual Treatment Processes

The particles must be removed at an early stage of the process


because:
a)
b)
c)

5.5.2

the grit particles cannot be broken down by any biological


treatment.

the grit particles are abrasive and wear down equipment.

the biological treatment in sewage treatment works is not designed


to degrade grease.

General Requirements
A manual bypass shall be provided. In case of grit removal system
failure and/or power outages, the flow shall be automatically directed
to the bypass.
Where mechanical grit separator is used, they shall be installed at an
angle of at least 10 to allow drainage and foul water to be returned to
the inlet channel.
Where manual systems are used, allow for safe and easy access to remove
grit to a storage bin.
If pump systems are used, the suction pipe shall be short and straight.
Tees and short radius bends shall be avoided, if at all possible. Flanges
at strategic locations shall be provided so that they can be dismantled
to remove any blockages.
The mechanical oil and grease skimming device shall be designed to
minimise the water being remove while skimming the oil and grease.
Sand pit may be used for further dewatering of the grease removed before
ultimate disposal. The drainage from the sand pit shall be returned to
the inlet channel for further treatment.

102

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

Table 5.7 Provision Requirement of Grit and Grease


Removal System
Number of Unit Processes

Requirements

i) Grit Removal System


Duty

Manual
Mechanical

5000 PE

> 5000 PE

1 Unit @ design flow

-1 Unit @ design flow


(up to 10 000 PE)
-2 unit @ 50% design flow each
( >10 000 PE)
Yes

Standby

Manual
Mechanical

1 Unit @ design flow


Bypass
ii) Grease Removal System
Duty
Manual
1 Unit
Mechanical
Standby
Bypass

5.5.3

Manual
Mechanical

1 Unit @ design flow


-

-1 Unit @ design flow


(up to 10 000 PE)
-2 unit @ 50% design flow each
( >1000 PE)
Yes

Design Criteria
Design criteria are given in Tables 5.8 and 5.9.
Table 5.8 Design Parameters for Grease Chambers
Description

Unit

PE 5000*

Design Criteria
> 5000PE

Grease removal

Chamber type

Rectangular

Baffled tank

Aerated type

min

Minimum detention
time (Qpeak)

Simple manual Manual interceptor

> 5000PE

Mechanical

Grit and grease storage


period before off-site
day
30
7
7
disposal
Note:
* Combined grit & grease chamber is allowed. If combined, then total detention
time shall comply to 6 minutes at Qpeak.
Sewage Treatment Plants

Volume 4

103

Requirements for Individual Treatment Processes

Table 5.9 Design Parameters for Grit Chambers


Description

Unit

Design Criteria
PE 5000*

>5000PE

>5000PE

Grit removal

Manual
(tanker)

Mechanical

Mechanical

Chamber type

Horizontal
flow (2 units
required for
duty and
standby during
cleaning)
vortex also
acceptable

Square, rotary or
vortex type simple
mechanised grit
chamber

Aerated

minute

m/s

0.20

0.20

0.20

m/s

n/a

<1.0

<1.0

35% of depth

l/s/meter
length of tank

10.0

1:2

Manufacturers
Specification

Manufacturers
Specification

Minimum
detention time at
Qpeak

Maximum gravity
flow through
velocity at Qpeak
Maximum
centrifugal flow
through velocity

Head loss
(at parshall flume)
Aeration
requirement
Chamber
dimension:
Depth: Width
Length: Width
Estimated grit
quantity
Washing and
dewatering of grit

2:1
m3/103 m3 of
sewage

0.03

0.03

0.03

No

Yes

Yes

Notes:
* Air lift pump for removal of grit is not acceptable.
* Water depth in tank to be controlled by weir outlet.

104

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

5.6

Design of Balancing Tanks


Balancing tanks are mandatory for all treatment processes that are not
designed at peak flow. The tanks are effective means of equalising
sewage flow. For extended aeration plants that are designed with a
retention time of more than 18 hours and clarifiers designed at peak
flow, the use of balancing tanks is not required.

5.6.1

Purposes of Balancing Tanks


The purposes of balancing tanks are to:
a)

prevent flow variations entering secondary treatment processes.

c)

reduce potential overflows that may cause health hazard and


pollution.

b)

5.6.2

reduce hydraulic loading into secondary treatment processes.

Design Requirements
The design requirements for balancing tanks are:
a)

All balancing tanks must be completely aerated and mixed.

c)

Allowance must be made for an emergency overflow.

b)

d)
e)
f)

Flow control shall be by a non-mechanical constant flow device,


such as an orifice, in order to avoid double pumping.
Bypass and drain down facilities as well as suitable access for
cleaning shall be provided.
A dead water depth of 0.6 - 1.0 m is normally required.
For plants with PE > 10 000, where balancing tank is used,
minimum one (1) unit of balancing tank shall be provided. The
design flow of the upstream and downstream unit processes are
recommended as follow:
i) Where no balancing tanks is provided, design flow of unit
process at

Upstream = Peak/pumped flow

Downstream = Peak/pumped flow
ii) Where balancing tank is provided, design flow of unit process
at

Upstream = Peak/pumped flow

Downstream = Average flow

Sewage Treatment Plants

Volume 4

105

Requirements for Individual Treatment Processes

Table 5.10 Design Parameters for Balancing Tanks


Description

Mixing power
requirements
Aeration

W/m3 of
sewage

Overflow bypass to downstream unit requirement

5.7

Unit

Volume of tanks

Design Criteria

1.5 hr detention at Qpeak


5 at TWL

m3 air/hour/
m3 sewage

1 m3 of air supply for every


m3 of sewage stored per
hour at TWL

Yes

Design of Primary Sedimentation Stage


At primary sedimentation stage, the velocity of sewage is reduced to
subside settleable suspended organic matters in the sewage. The settled
matter is known as primary sludge.

5.7.1

Purposes
The purposes of primary sedimentation are:
a)
b)
c)

5.7.2

to remove maximum amount of pollutants such as settleable


solids quickly and economically.

to separate sewage into sludge and settled sewage, which by


being treated separately are normally dealt with more efficiently
and economically.
When used as a preliminary step for further treatment, the main
function of primary sedimentation tank is to reduce the organic
loadings on the secondary treatment units and is a essential
component of secondary sewage treatment.

Design Requirements
The design requirements of primary sedimentation include the
followings:
a)

b)

106

Provide sufficient time for maximum settling under quiescent


conditions. Therefore, design factors require careful consideration
include: overflow rate, detention period, weir-loading rate, shape
and dimensions of the basin, inlet and outlet structures, and
sludge removal system.
Tanks can either be rectangular, circular or upward flow
(square).

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

c)

Provisions for the removal of sludge on a daily basis.

e)

V-notch weirs with baffle shall be provided at the outlet.


Weirs shall be adjustable with notches 100 mm deep. Typical
variation in water level shall be no more than 50 mm under all
conditions.

d)

f)
g)

h)
i)

j)

Holding tanks for wasted sludge must be provided.

Multiple hopper are not permitted.

Scum skimming shall be provided to remove both floating


materials and scum. These materials can be either discharged
to biosolid holding tank or sand drying bed. They shall not be
returned to the preliminary treatment units.

Flow distribution channel/ chamber shall be provided for flow


isolation or equal flow distribution.
Rectangular tank

i)

Sludge hopper shall have side slopes of 60 or more


from horizontal with the sludge pump located in a pit at
hopper invert level. The length of suction pipe shall be
minimised. Provision for withdrawal pipe from the tanks
shall be provided.
ii) The capacity of hopper shall be equivalent to 2 hours
detention time at Qpeak.
iii) Additional water depth of minimum 400 mm should be
provided above the hopper in the vertical side-wall section
between the top of the hopper and the top water level. The
side-wall height should not be less than 400 mm.
iv) Equalise flow distribution across the inlet of the tank shall
be achieved using a multi-port wall and baffles.
Circular Tank
i)
ii)

(k)

Circular tanks shall be no more than 50 m in diameter


and minimum water depth shall be 3.0 m.
Circular tanks with more than 30 m diameter shall be
provided with perimeter walkway for cleaning the weir
and shall have appropriate drive system.

The floor slab of the sedimentation tank shall be of reinforced


concrete type construct to gradient to enhance the sludge scraping
effectiveness.

Sewage Treatment Plants

Volume 4

107

Requirements for Individual Treatment Processes

Table 5.11 Design Parameters for Primary Sedimentation


Description

Unit

Design Criteria

Sedimentation followed by secondary treatment


hr
Detention time at Qpeak
Surface overflow rate at Qpeak
- circular (maximum)

m /m /d
3

- rectangular (maximum)
Weir loading at Qpeak

2
45

m /m /d
m /m/d

45
150

m/hr

1.2 - 2.0

> 3:1
2.5
1 : 1 to 2.5 : 1

Upward flow rate at Qpeak

Sizing of rectangular tanks


Length : Width
Min water depth
Width : Depth
Sizing of circular tanks
Min. side water depth
Floor slope wall

5.8

Design of Biological Treatment Stage

5.8.1

Introduction

> 3.0
1:12

Biological treatment is the heart of the sewage treatment process. It is


the processes where the dissolved and non- settleable organic material
remaining in the sewage are removed by living organisms.
For reasons of long term whole life economics, ease of operation and
maintenance, consistent effluent standards and standardisation, the
following types of biological treatment processes are recommended for
use in Malaysia.
Suspended Growth System
a)

Conventional activated sludge (CAS) system

b)

Extended aeration (EA)/Oxidation Ditch (OD) System

c)

108

Sequencing Batch Reactor (SBR)/Intermittent Decant Extended


Aeration (IDEA)

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

Attached Growth System


a)
Rotating biological contactor (RBC) system
b)
Trickling filter (TF) System
c)
Hybrid System/Combination multistage design
All plants must be strictly designed to meet DOE Standard A/Standard
B requirements including, nitrification and denitrification to reduce
ammonia and total nitrogen removal level that ensure compliance with
the requirement stipulated in Section 3 earlier. Total phosphorus removal
must also be taken into account for plants where treated effluent is to
be discharged into stagnant water bodies.
Mass balance calculation must be computed and submitted for all biological
treatment system and other unit processes proposed for the STP.
5.8.2

Conventional Activated Sludge System (CAS)

5.8.2.1

General Description
The conventional activated sludge process is one of the many versions
of the activated sludge process. The activated sludge process is most
suitably used where land is limited and expensive, and where large
volumes must be treated economically, without creating nuisance to
neighbours.
The process involves the production of activated mass of microorganisms
capable of stabilising sewage aerobically. This is achieved by introducing
organic waste, produced from pre-treatment and primary treatment
facilities, into reactors where suspended aerobic bacterial culture oxidises
the organic matter into stable matters. These active bacteria cultures are
commonly known as activated sludge. During the process, new bacteria
cell are also produced.

5.8.2.2

Design Requirements for CAS


For the design of conventional activated sludge system, the aeration
tank shall be preceded with primary sedimentation system. An appropriate
amount of the bacteria culture, known as activated sludge must be recycled
to the upstream of the reactor while the remaining excess sludge must
be removed at secondary sedimentation system.
All conventional activated sludge system used at STPs for Class 3,
Class 4 and at where requested by the Commission must be designed with
anoxic zone to achieve a total nitrogen removal in order to comply with
the requirements in Section 3 of this Guidelines, as well as to minimise
potential rising sludge at secondary sedimentation system. The anoxic
zone must be mixed without inducing dissolve oxygen.
Sludge treatment and dewatering must be available on-site to handle the
large quantity of unstable sludge generated.

Sewage Treatment Plants

Volume 4

109

Requirements for Individual Treatment Processes

Table 5.12 Design Parameters for Conventional/ Activated


Sludge System
Description

Unit

Primary Sedimentation System

Minimum number of aeration tanks


F/M ratio

Hydraulic retention time (HRT)

Oxygen requirements (for BOD and


ammonia nitrogen removal)
Mixed liquor suspended solids
(MLSS)

Sludge yield

hrs

kgO2/kg substrate
mg/l

kg sludge
produced/kg BOD5
consumed

Sludge age #

day

Return activated sludge flow, QRAS

m3/d

Waste activated sludge, QWAS

Must be provided
2

Dissolved oxygen (DO) level in tank mg/l


Aeration device rating

Design Criteria

m3/d

0.25 - 0.50

6 -16 (for system where


only ammonia removal is
require)
12 -16 (for plants require
total nitrogen removal)
2.0

1500 -3000
Typical: 2500
1.0

Continuous, 24 hrs
0.8 - 1.0

5 - 10

Refer to equation below


0/66
[ 4DYJ
&X  0/66

Cu is underflow concentration

QRAS / QINFLOW

0.75-1.0

Mixed liquor suspended solids


recirculation for denitrification
purpose

4 6 of Qavg

RAS pump rating

hrs/day

24

Organic loading

kg BOD5/kg MLSS

0.25 - 0.5

W/ m3

20

Volumetric loading

Minimum mixing requirement

110

kg BOD5/m3.d

Volume 4

0.3 - 0.6

Malaysian Sewerage
Industry Guidelines

Requirements for Stages of Sewage Treatment


Requirements for Individual Treatment Processes

Table 5.12 Design Parameters for Conventional


Table 5.12Activated
DesignSludge
Parameters
Conventional
Systemfor
(cont.)
Activated Sludge System (continued)
Description
Description

Unit
Unit

Tank dimension
Tank dimension
Water depth
Water depth
Length:Width
Length:Width
Max width
width of
of joined
joined tank
tank
Max
# Sludge Age =

m
m

Design Criteria
Design Criteria

35

<30

3:1

35
3:1

< 30

total solids in aeration tank


excess sludge wasting / day + solids in effluent

VT u MLSS

 Q avg u SSeff
T sludge
WAS =
Cu

>

Where:
vT
= volume of reactor (m3)
3
MLSS = mixed liquor suspended solids (kg/m )

Tsludge
Qavg
SSeff
Cu

= sludge age (days)


= average flow (m3/day)
= effluent suspended solids (kg/m3)
= underflow concentration (kg/m3)

Refer Table D1 and D2 for aeration equipment duty / standby and also to
Refer
Table
D1ofand
forfor
aeration
equipment duty/standby and also to
relevant
clause
MSD2
1228
more details.
relevant clause of MS 1228 for more details.
5.8.3
5.8.3
5.8.3.1
5.8.3.1

Extended Aeration System (EA)


Extended Aeration System (EA)
General Discription
General Discription
The extended aeration process is similar to the conventional activated
The
extended
is similar
to the conventional
sludge
process aeration
except thatprocess
it operates
in the endogenous
respirationactivated
phase of
sludge
process
it operates
in theloading
endogenous
respiration
the growth
curve,except
which that
requires
a low organic
and long
aeration
phase
of the
growth
curve,high
which
requires
a low organic
loading
and
time. The
system
produces
MLSS
concentration,
high RAS
pumping
rate and
low sludge
long
aeration
time. wastage.
The system produces high MLSS concentration, high
RAS pumping rate and low sludge wastage.
The advantage of having long hydraulic retention times is that it allows the
plantadvantage
to operateofeffectively
overhydraulic
widely varying
flow
and is
waste
The
having long
retention
times
that loadings.
it allows
Secondary
be designed
to thevarying
variations
hydraulic
the
plant toclarifiers
operate must
effectively
over widely
flowin and
waste
loadings
and
high
MLSS
concentrations
associated
with
this
process.
loadings. Secondary clarifiers must be designed to the variations in
hydraulic loadings and high MLSS concentrations associated with this
process.

Sewage Treatment Plants

Volume 4

111

Sewage Treatment Plants

Volume 4

99

Requirements for Individual Treatment Processes

5.8.3.2

Design Requirements for EA


EA plants shall be designed as either plug flow or completely mixed.
Anoxic zone at the head of the reactor must be provided for denitrification.
The anoxic zone must be mixed without inducing dissolved oxygen
For Oxidation Ditches, the minimum velocity within the channel shall
be sufficient to keep the activated sludge in suspension. The minimum
velocity within the channel shall not be less than 0.3 m/s. The tank
configuration and aeration and mixing devices shall promote unidirectional
channel flow, so that the energy used for aeration is sufficient to provide
mixing in a system with a relatively long hydraulic retention time.
Table 5.13

Design Parameters for Extended Aeration

Description
Minimum number of aeration tanks
F/M ratio

Hydraulic retention time (HRT)


Oxygen requirements(for BOD and
ammonia nitrogen removal)
Mixed liquor suspended solids (MLSS)
Dissolved oxygen (DO) level in tank
Sludge yield

Sludge age #
Waste activated sludge flow, QWAS
Return activated sludge flow, QRAS

RAS pump rating


Recirculation ratio, QRAS/QINFLOW

Unit

18 - 24
2.0

mg/l

2500 - 5000
Typical: 3000
2.0

mg/l
kg sludge produced/kg
BOD5 consumed

day
m3/d
m3/d

24
0.5 - 1.0

Water depth
Length:Width
Max width of joined tank

m
ratio
m

Volume 4

> 20
Refer to equation

Cu is underflow
concentration

hours/day

W/m3

0.4 (at 24 hrs HRT)


0.6 (at 18 hrs HRT)

0/66
[ 4DYJ
&X  0/66

kg BOD5/m .d

112

0.05 - 0.1

hrs
kgO2/kgsubstrate

MLSS recycle ratio


Volumetric loading

Minimum mixing requirement


Tank dimension

Design Criteria

4 6 times of Qavg
0.1 - 0.4
20

35
3:1
< 60

Malaysian Sewerage
Industry Guidelines

Requirements
for Individual
Treatment
Requirements
for Stages
of SewageProcesses
Treatment

Notes:
#

Sludge Age =

Notes:
#

Requirements for Stages of Sewage Treatment

total solids in aeration tank

excess sludge wasting/day + solids in effluen

Sludge Age =

total solids in aeration tank

VT u MLSS

 Q avg u SSeff
T sludge
WAS =
Cu

>

VT u MLSS
Where:

 > Q avg u SSeff @

T sludge
in effluen
WAS =
= volume+ofsolids
reactor
(m3)
vT excess sludge wasting/day
Cu
MLSS
= mixed liquor suspended solids (kg/m3)
Tsludge
= sludge age (days)
Where:
= average flow (m3/day)
Qavg
= volume of reactor (m3)
vT
SSeff
= effluent suspended solids (kg/m3)3
MLSS
= mixed liquor suspended solids (kg/m
)
Cu
= underflow concentration (kg/m3)
Tsludge
= sludge age (days)
= average flow (m3/day)
Qavg
Refer
Table D1 and D2 for aeration equipment duty /
SSeff
= effluent suspended solids (kg/m3)
relevant
clauseconcentration
of MS 1228(kg/m
for3more
details.
Cu
= underflow
)

standby and also to

Refer Table D1 and D2 for aeration equipment duty/standby and also to


relevant
clause
of MS
1228
for more
details.duty / standby and also to
Refer
Table
D1 and
D2 for
aeration
equipment
relevant clause of MS 1228 for more details.
Figure 5.11 Fine Bubble Diffuse Air Extended Aeration System

Anoxic Zone
Aeration Tank
Flow
Final Clarifier
Figure 5.11 Fine Bubble Diffuse
Air
Extended
Aeration System
Distribution
Grit Removal Diffuse Air Extended Aeration System
Figure 5.11 FineScreens,
Bubble
Raw
Sewage
Inlet

Anoxic Zone

Aeration Tank

Flow
Distribution

Sewage
Pump Station
Screens, Grit Removal

Effluent
To River

Final Clarifier
Effluent
To River

Return Sludge
Pump Station

Raw
Sewage
Inlet
Sewage
Pump Station

Return Sludge
Liquor
Pump Station
Chemical
Dosing

Sludge Storage Area

Mechanical Sludge
Dewatering
Liquor
Chemical Mechanical Sludge
Thickener
Dosing

Ultimate Disposal

Sludge Holding Tank


Sludge Storage Area

Mechanical Sludge
Dewatering
Mechanical Sludge
Thickener

Sludge Drying Bed

Sludge Holding Tank

Ultimate Disposal

OPTIONAL
Sludge Drying Bed

OPTIONAL

Sewage Treatment Plants

Sewage Treatment Plants

Volume 4

Volume 4

113

101

Requirements for Individual Treatment Processes


Requirements for Individual Treatment Processes

Figure 5.12 Oxidation Ditch Activated Sludge System


Figure 5.12 Oxidation Ditch Activated Sludge System

M echanical R otor

Flow
Distribution

S creens, G rit R em oval


R aw
S ewage
Inlet

Final Clarifier

Flow
M easurem ent

E ffluent
To River

O xidation Ditch
S ewage
P um p S tation
R eturn S ludge
P um p S tation

Chem ical
D osing

S ludge Storage A rea

M echanical S ludge
Dewatering

M echanical Sludge
Thickener

S ludge Holding Tank

Ultim ate D isposal


S ludge D rying B ed

O P TIO N AL

5.8.4
5.8.4

Rotating Biological
BiologicalContactors
Contactors
(RBC)
Rotating
(RBC)

5.8.4.1
5.8.4.1

General Description
Description
General
Rotatingbiological
biological
contactors
series
of media
rotating
media for
Rotating
contactors
use a use
seriesa of
rotating
for biological
biological
treatment.
The
rotating
medium,
typically
made
from
sheets
treatment. The rotating medium, typically made from sheets of high quality
of highprovides
quality aplastic,
surface on
which
organisms
grow.
plastic,
surface provides
on which aorganisms
grow.
As the
media rotate,
As
the
media
rotate,
the
fixed
film
biomass
is
in
contact
with
organic
the fixed film biomass is in contact with organic pollutions in sewage and
pollutions
in sewage alternately.
and oxygenLayers
in atmosphere
oxygen
in atmosphere
of biomassalternately.
are sheared Layers
from theof
biomassofare
from the
the rotation
surface to
of prevent
the media
during of
thetherotation
surface
thesheared
media during
overgrown
fixed
film.
to prevent overgrown of the fixed film.
RBCs
RBCs are
are conventionally
conventionally submerged
submergedtoto40%
40%ofof disc
discdiameter.
diameter. Increased
Increased
submergence
90%
is also
acceptable
if sufficient
air
submergence ofofdiscs
discsupuptotoabout
about
90%
is also
acceptable
if sufficient
supply
is
provided
at
the
base
of
the
tank.
This
system
is
normally
called
air supply is provided at the base of the tank. This system is normally
the
submerged
biologicalbiological
contactor contactor
(SBC).
called
the submerged
(SBC).

5.8.4.2
5.8.4.2

Design
RBC
Plants
Design Requirements
Requirementsforfor
RBC
Plants
Preceding
Preceding the
the RBC
RBC must
must be
be aa primary
primary sedimentation
sedimentationtank
tankororaa secondary
secondary
screening with <6 mm opening. A flow balancing tank must also be
screening with < 6 mm opening. A flow balancing tank must also be
provided unless the plant is designed to peak flow.
provided unless the plant is designed to peak flow.
Units must be covered for aesthetics and odour control, and only approved
Units must
for aesthetics and odour control, and only approved
media
typesbe
arecovered
accepted.
media types are accepted.

114

Volume 4

102

Volume 4

Malaysian Sewerage
Industry Guidelines

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes


Requirements for Stages of Sewage Treatment

Table 5.14 Design Parameters for RBC Plants


Table 5.14 Design Parameters for RBC Plants
Description
Description
Minimum number
of stages

Unit

Unit

Total BOD
specific
loading
g/m /d
Minimum
number
of stages
5

5 - 10 3

Total
BOD5 specific loading
Total tank
volume

Design Criteria
Design Criteria

5 -210
Based on
hrs at Qavg

g/m2/d

0.9
kg excess sludge/
Based on 2 hrs at Qavg
kg BOD5 consumed
Sludge yield
kg excess sludge/
0.9
Disc diameter
m
kg BOD5 consumed 2.5 - 3.5
Speed of rotation
rev / min
0.5 - 1.0
Disc diameter
M
2.5 - 3.5
Maximum peripheral velocity m/s
0.3
Speed of rotation
rev / min
0.5 - 1.0
Depth of disc submergence
%
40 - 90
Maximum peripheral velocity m/s
0.3

Sludge yield
Total tank volume

Depth of disc submergence

40 - 90

Refer also to Table D.3 for duty standby requirements and relevant clause of
MS
1228
Refer
alsofor
to more
Table details.
D.3 for duty standby requirements and relevant clause of MS
1228 for more details.
Figure 5.13 Rotating Biological Contactor (RBC) Systems
Figure 5.13 Rotating Biological Contactor (RBC) Systems
Rotating Biological
Contactor
Screens, Grit Removal,
Flow Measurement

Fine Screen

Raw
Sewage
Inlet

Flow
Distribution

Final Clarifier

Balancing
Tank
Sewage
Pumping
Station

Effluent To
River

Liquor
Chemical
Dosing

Sludge Storage Area

Mechanical
Sludge Dewatering
Mechanical
Sludge Thickener

Sludge Holding Tank

Ultimate Disposal
SludgeDrying Bed

OPTIONAL

Sewage Treatment Plants

Sewage Treatment Plants

Volume 4

Volume 4

115

103

Requirements for Individual Treatment Processes

Requirements for Individual Treatment Processes

5.8.5
Trickling Filter
5.8.5
Trickling Filter
5.8.5.1 General Description
5.8.5.1
General Description
The trickling filter is an established biological treatment process removing
65 to 85%
and suspended
solids.treatment
The process
of a bed
The trickling
filterBOD
is an5 established
biological
processconsists
removing
65 to 85%
BOD
and
suspended
solids.
The
process
consists
of
a
bed
of
of highly 5permeable medium. An overhead rotating distributor applies
highlysewage
permeable
An The
overhead
to medium.
the media.
flowrotating
tricklesdistributor
over andapplies
flows sewage
downward to
to the the
media.
The
flow
trickles
over
and
flows
downward
to
the
underdrain
underdrain system.
system.
The media provides a large surface area to develop biological slime
The media
provides
to developfilm.
biological
slimecontains
growth living
growth
whichaislarge
alsosurface
knownarea
as zoogleal
The film
which organisms
is also known
as
zoogleal
film.
The
film
contains
living
organisms
that break down organic material in the sewage.
that break down organic material in the sewage.
Many variations of the trickling filters have been constructed, however
Many the
variations
of the trickling
have been
constructed,
recommended
designsfilters
are given
in Table
5.15. however the
recommended designs are given in Table 5.15.

5.8.5.1 Design Requirements for Trickling Filters


5.8.5.1
Design Requirements for Trickling Filters
Secondary
(<and
6 mm)
flow balancing
tanks to
the
Secondary
screensscreens
(< 6mm)
flow and
balancing
tanks to equalise
theequalise
flow
flow
must before
be provided
before
must be
provided
trickling
filters.trickling filters.
Provisions
shall
be available
for distribution
even distribution
to achieve
complete
Provisions
shall be
available
for even
to achieve
complete
of the
filter media.
wettingwetting
of the filter
media.
Figure
Trickling
Filter Systems
Figure
5.14 5.14
Trickling
Filter Systems

Biofilter
Pump
Station

Fine
Screen

Screens, Grit Removal

Flow
Distribution
Final Clarifier

Filter

Raw
Sewage
Inlet

Effluent
To River

Sewage
Pump Station
Liquor

Chemical
Dosing

Sludge Storage Area

Mechanical Sludge
Dewatering
Mechanical Sludge
Thickener

Sludge Holding Tank

Ultimate Disposal

Sludge Drying Bed

OPTIONAL

116

104

Volume 4

Volume 4

Malaysian Sewerage
Industry Guidelines

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

Table 5.15 Design Parameters for Trickling Filter


Description

Unit

Organic loading

Design Criteria

kg BOD5/day/m3

(depending on filter type)


Low rate
Intermediate rate
High rate

0.08 - 0.15
0.15 - 0.5
0.5 - 2.0

> 1.0

Recirculation of flow to head of plant


Qrecycle
Qinflow

(to maintain wetting rate and improve


flow)
Acceptable media

Hydraulic loading

m3/day/m2

Sludge Yields

kg sludge / kg
BOD5 influent

Minimum depth of media

Low rate
Intermediate rate
High rate

Low-rate filters
Intermediate filters
High-rate filters

HDPE, PVC, stone,


slag, coke, etc.
(random or standard
arrangement)
1-4
4 - 10
10 - 40
0.5
0.6 - 0.8
1.0

1.5

Refer also to Table D.4 for duty standby requirements and relevant clause
MS 1228 for more details.
5.8.6

Sequencing Batch Reactors (SBR) System

5.8.6.1

General Description
Sequencing Batch Reactors system is suspended activated sludge system.
In this system, sewage flows into one or more reactors where biological
oxidation and clarification of sewage take place within the same reactors
sequentially on cyclical mode. There are five (5) basic sequences in a
cycle, namely:

Sewage Treatment Plants

Volume 4

117

Requirements for Individual Treatment Processes

1.

Fill

3.

Settle

2.
4.
5.

React (Aeration)
Decant
Idle

Typically, all actions in the reactor occur at different sequence of time.


In other words, the system is intermittently fill and intermittently decant.
Typical SBR plant consists of a minimum of two (2) reactors in a plant.
When one unit of the reactors is in fill mode, the other reactor(s) may be
in the stage of react, settle, decant or idle. Recent development of SBR
system leads to the emergence of variation in the operating sequences.
Continuous fill and intermittently decant system is one of the variations
of this system, where feeding into all rectors are continuous but the
other phases (react, settle, decant, idle) are run in sequence.
In the reaction stage, oxygen supplied to the system shall be in
accordance to the load to the system within the time frame of reaction
cycle. This generally requires higher oxygen capacity per unit time than
a continuously aerate system.
In the decant stage, there shall be sufficient time to allow for mixed
liquor suspended solids (MLSS) to settle before effluent decanting begins.
Decanting time is normally much shorter than fill time. Consequently,
the effluent flow rate will also be much higher than influent flow rate.
Hence the design of the decanting weir must be capable to handle high
over-flow rate without scouring the settled sludge. Therefore, sufficient
clear water depth between the minimum water level after decant and
the top of the settled sludge blanket must be allowed for to minimise
sludge carry over. Hence the depth of water decanted must be restricted
to prevent scouring of solids.
5.8.6.2

Design Requirements for SBR Plants


All SBR plants must be designed to cater for peak flows. A minimum
of a two (2) tanks system is required. Proven control system in the form
of Programmable Logic Controller (PLC) with complete instruction, and
operational and training manuals must be submitted together with the
design. All SBR systems must be preceded with complete preliminary
works. Allowance shall be provided to completely empty a tank for
maintenance purposes without interrupting the operating sequence of
the plant.
Table 5.16 highlights the key design requirements for an SBR plant.

118

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

Table 5.16 Design Requirements for SBR System


Unit

Continuous Fill and


Intermittently Decant

Intermittently Fill and


Intermittently Decant

unit

Minimum 2

Minimum 2

Hydraulic retention
time at Qavg (at
average water level)

hr

18 24

18 24

F/M ratio

d-1

0.05 0.08

0.05 0.30

Sludge age

20 30

10 30

kg Sludge

0.75 0.85

0.75 1.10

mg/l

3000 4500

3000 4500

hr

48

48

DO (Reactor)

mg/l

0 ~ 6.5

0 ~ 6.5

DO (Effluent)

mg/l

2.0

2.0

Parameter
No. of Reactors

Sludge Yield

kg BOD5 load

MLSS (End of decant)


Cycle Time

Oxygen Requirement

kg O2
kg Substrate

Cycle time
Aeration Time

2.0 kg O2
kg substrate

Cycle time
Aeration Time

2.0 kg O2
kg substrate

Decant time

hrs

1.0

1.0

Decant depth

Max 0.5

max 1.0

Decant volume

Not more than 25% of


volume of Biological
Reactor at TWL

Not more than 30% of volume


of Biological Reactor at TWL

m3/m/hr

20 for decant draw-down


from TWL

20 for decant draw-down


from TWL

2 nos. independent
decanter per tank

2 nos. independent decanter


per tank

4.0

4.0

Decanting device
loading rate*
Minimum number of
decanter
Max. pecanter length
WAS

kg sludge/d

Fill volume

*
*

m3


Total solids in system
Total solids in system
Was=
Was=

Slude age

Slude age
Vfill = (QP m3/hr x 1.5hr)
+ (Tfill 1.5) x QAVG (if no
balancing tank)
Vfill = QAVG x Tfill (if
preceded by
balancing tank)

Vfill = (QP m3/hr x 1.5hr) +


(Tfill 1.5) x QAVG (if no EQ)
Vfill = QAVG x Tfill (if preceded
by balancing tank)

For continuous fill, length to width ratio shall be based on 3 : 1


Decanting device loading rate shall be based on Vfill/decant time during
decanting.
RAS maybe necessary where length to width ratio poses dilution affect
into the inlet.

Sewage Treatment Plants

Volume 4

119

Requirements for Individual Treatment Processes

5.8.7

Design Requirements for Hybrid Systems


A hybrid system is a recent development in biological treatment combining
suspended solids and fixed film growth processes. The treatment system
may be considered if the design criterion to be adopted has proven
performance and result.

5.8.8

Design for Nutrient Removal for Sensitive Receiving Water


Nutrient removal is required for effluent discharge to lakes and stagnant
water bodies to prevent eutrophication or other potential impacts that
may impede the sensitivity of the receiving water. Nutrient removal can
be achieved via:
a)

Biological treatment.

c)

Chemical treatment.

b)

Physical treatment.

It has been emphasised in the beginning of this chapter, all biological


treatment system shall be designed to achieve ammonia reduction and
where necessary anoxic zone/stage to be added to encourage denitrification
for total nitrogen removal.
The biological phosphorus removal mechanism is based on the fact that
bacteria are capable of storing excess phosphorus as polyphosphate and
removing simple fermentation substrates produced in the anaerobic zone
and assimilating them into storage products within their cells. Hence,
the design for of the biological treatment shall follow the following for
plants where nutrient removal (nitrogen and phosphorus) is required,
design parameters:
Table 5.17 Design Requirement for Biological
Nutrient Removal System
Item

120

Design Parameters

HRT
(hrs)

MLSS
(mg/l)

1
2

1st stage anaerobic


1st stage anoxic

1-2
2-4

2 000 6 000
2 000 6 000

1st stage aerobic (oxic)

8 - 12

2 000 6 000

4
5
6

2nd stage anoxic


2nd stage anaerobic
2nd stage aerobic (oxic)

2-4
1-2
4

2 000 6 000
2 000 6 000
2 000 6 000

Volume 4

Internal recycle

RAS from clarifier


2 to 1 (MLSS
recirculation ratio)
3 to 2 (MLSS
recirculation ratio)
Mixing
Mixing
Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes


Requirements for Stages of Sewage Treatment

It has been emphasised in the beginning of this chapter, all biological


It has
been emphasised
in be
the designed
beginningtoofachieve
this chapter,
all reduction
biological and
treatment
system shall
ammonia
treatment
shallanoxic
be designed
to achieve
ammonia
reduction and
where
wheresystem
necessary
zone/ stage
to be added
to encourage
denitrification
necessary
anoxic
zone/stage
to
be
added
to
encourage
denitrification
for
for total nitrogen removal.
total nitrogen removal.
Figure 5.15 Typical Process Flow Diagram for
Figure 5.15 - Typical Process Flow Diagram
Biological Nutrient Removal System
for Biological Nutrient Removal System

To get
phosphate

To get
nitrate bac k

Back

1st.
Anaerobic

1st.
Anoxic

1st.
Aerobic

2nd
Anoxic

2nd.
2nd.
Anaerobic Aerobic

Clarifier

Effluent

RAS

Alternatively,
both both
physical
and chemical
treatment
may be used
Alternatively,
physical
and chemical
treatment
maytoberemove
used to
Phosphorus
wastewater.in wastewater.
remove in
phosphorus
TheThe
designer
shallshall
taketake
all necessary
consideration
in theindesign
in relation
designer
all necessary
consideration
the design
in relation
to the
specific
requirements
of
the
receiving
water
in
determining
the
actual
to the specific requirements of the receiving water in determining the
nutrient
removal
requirement
the case byon
case
actual
nutrient
removal on
requirement
thebasis.
case by case basis.

Sewage Treatment Plants

Sewage Treatment Plants

Volume 4

Volume 4

121

109

Requirements for Individual Treatment Processes

5.9

Design of Secondary Clarifiers

5.9.1

Purpose
Effluent from biological processes contains large populations of microorganisms (MLSS). Secondary clarifiers provided after the biological
system allow the mixed liquor organisms/ solid to settle. Clear supernatant
is discharged as the effluent, while some of the settled microorganisms
are returned to the biological treatment system to maintain the MLSS
concentration and excess microorganisms are removed as biosolid to the
sludge treatment facility.

5.9.2

Design Requirements
The design requirements shall include:
I)
a)

Minimum retention time for settlement.

c)

Sludge hopper to collect settled sludge.

b)
d)

e)

f)

g)

Maximum settling velocity for settlement.


All clarifiers must be equipped with sludge scrapers to skim
sludge from the bottom unless they are designed with a 60o
hopper bottom.

All clarifiers must be equipped with scum skimmer to remove


scum from the surface. The scum collected must be drained
(where necessary) and disposed off. Returning the scum to the
preliminary system or the biological system is not permitted.
Multiple hopper are not permitted.

Stilling basin to prevent hydraulic shock circuiting.

h)

Bottom slope at clarifier floor.

j)

Appropriate feed and outlet pipe with hydraulic consideration.

i)

k)
l)

m)
II)
a)

122

General

Facilities to dispose scum and sludge.

Effluent collection channel to be of glazed finish/tiles.


Proper maintenance access to all components.

Properly designed air lift pumps are only permitted for PE less
than 1000.

Weirs
If insufficient length is available, then considerations shall be
given for the use of double weir.
Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

b)

Cascading V-notch is preferred over rectangular weirs.

d)

Broad crested weirs are not encouraged.

c)

e)
f)

Slots in the weir shall be provided to allow for level adjustment


during the installation stage.
All parts of the weirs must be visible and accessible for regular
cleaning.
Type of weir and the hydraulic calculation for the weir proposed
must be submitted.

III)

Circular clarifiers

a)

The maximum diameter permissible is 50 m and a reasonable


allowance between tanks shall be provided for vehicle access.

b)
c)
d)

The minimum side water depth shall be 3.0 m. Greater side water
depths may be used if it can be shown that the mixed liquor is
well denitrified in the aeration tank.
Flow distribution channel/chamber shall be provided for flow
isolation or equalise flow distribution.

The scraper tip travelling speed shall not exceed 0.03 rpm. A
multiple stage reduction unit must be incorporated to achieve
such speed.

IV)

Rectangular clarifiers

b)

Multiport wall and baffled inlet shall be provided.

d)

Allowance also shall be provided for vehicle movement between


unit processes for maintenance purposes.

a)

c)

e)

Shall not be wider than 6 m per tank to allow for scraper removal,
unless other approved scraper units are available.

Slide gates shall be used to isolate each tank.

Scraper travelling speed shall be between 0.3 0.6 m/min.

Refer also to relevant clause of MS 1228 for more details.


5.9.3

Multiple Hoppers
Multiple hoppers are not accepted. This is due to the settling characteristics
of the particles in the flow. Larger and heavier particles settle faster
than smaller and lighter particles, creating difference in the distribution
of sedimentation in different hoppers. This will present operational
difficulties because sludge removal from the hoppers is unequal. To
avoid the non-uniform withdrawal of sludge, each hopper in the multiple
hopper configuration needs a separate pipe and pump or valve on each
outlet.

Sewage Treatment Plants

Volume 4

123

Requirements for Individual Treatment Processes

Table 5.18

Design Parameters for Secondary Clarifiers

Description

Design Criteria

Unit

PE 5,000

PE > 5,000

Minimum number of tanks

2*

Tank configuration

Square
Circular
Rectangular

Circular
Rectangular #

Minimum side water depth

3**

Minimum hydraulic retention time


(HRT) at Qpeak

hrs

Surface overflow rate at Qpeak

m3/d/m2

30

30

Solids loading rate at Qpeak

kg/d/m2

<150

<150

Solids loading rate at Qavg

kg/d/m2

<50

<50

Weir loading rate at Qpeak

m3/day/m

<180

<180

Return activated sludge (RAS)


pumping rate

Continuous

Continuous

Waste activated sludge (WAS)


pumping rate

Continuous or
batch

Continuous or
batch

Sizing of rectangular tanks


Length : Width
Maximum side water depth

3:1 or greater.
m

Width : Depth

3.0
1 : 1 to 2.5 : 1

Sizing of circular tanks


Side water depth, minimum

Floor slope wall

3.0 **
1:12

Notes:
* For PE less than or equal to 1000 a single clarifier is acceptable.
#
Rectangular tanks are acceptable if equipped with automatic scraping and
desludging devices.
** For square clarifier with 600 slope minimum 1 m side water depth shall
be provided.

124

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

5.10

Disinfection
Disinfection refers to the selective destruction of disease causing organisms
in sewage effluent.
Methods of disinfection can be physical, chemical or radiation.
Continuous disinfection is required for those areas where the discharge
from the sewage works will cause detrimental effect onto the receiving
water course, such as bathing beaches, lakes, etc.
The Commission reserves the right to determine the need for the provision
of a continuous disinfection facility.
The common forms of disinfection that are available for wastewater
applications are:
a)
Chlorination
b)
Ultra-violet (UV)
c)
Others
Chlorination is by far the most common type of disinfection used worldwide. This is due to its effectiveness in providing a good pathogen
kill with relative simplicity in operation and maintenance. However,
chlorination using chlorine gas, requires a higher degree of operational
skills and poses potential health and safety hazards in the shipping and
handling aspects. Therefore, to reduce these hazards, only liquid or
solid hypochlorite (sodium or calcium) shall be used.
Ultra-violet (UV) disinfection differs from chemical disinfection in
that it uses irradiation to induce photobiochemical changes within the
micro-organisms. To ensure effective photochemical reaction taking
place, one of the conditions is that such radiation must be absorbed by
the target molecule (organism). The other condition is that sufficient
radiation energy to alter chemical bonds is made available. Given the
conditions above, it is critical that the effluent prior to disinfection must
be relatively clear of suspended solids. As such, for UV disinfection to
be highly effective in wastewater applications, filtration of upstream of
the UV unit must be made available.
Other forms of wastewater disinfection that are available are maturation
ponds and ozonation. Maturation ponds have been used widely and
successfully in Malaysia. However, the drawback is that a relatively
large area of land is required to provide sufficient retention time in the
pond for the decay of pathogens. Ozone disinfection involves the direct
ozone oxidation or by reaction with the radical by-products of ozone
decomposition. However, due to ozonations relatively new status in
wastewater applications and higher costs at small scale facilities, its
usage for disinfection is still limited.

Sewage Treatment Plants

Volume 4

125

Requirements for Individual Treatment Processes


Requirements for Individual Treatment Processes

5.10.1
5.10.1

Design Requirements
Requirements
Design
All new STPs must have provision for disinfection infrastructure such
All
new STPs
provision
for structures.
disinfection infrastructure
as contact
tankmust
andhave
other
necessary
The provisionsuch
of as
the
contact
tankfacilities
and other
The provision
of 5.19
the
disinfection
and necessary
equipmentstructures.
shall be in accordance
to Table
disinfection
facilities andshall
equipment
shallout
be in
in continuous
accordance or
to intermittent
Table 5.19
below. The disinfection
be carried
below.
mode. The disinfection shall be carried out in continuous or intermittent
mode.
Table 5.19: Requirements for Disinfection Facility
Table 5.19: Requirements for Disinfection Facility
Description
Description
Class of STP*

Continuous
Continuous
Class 4

Class of STP*

Intermittent
Intermittent
Class 1
Class1 2
Class

Class 4

Class2 3
Class

Type of Disinfection

Chlorination

Chlorination
Class 3
Ultra-violet (UV)
Type of Disinfection

Chlorination
Chlorination

Ozone
Ultra-Violet (UV)
Facility
(1duty/1standby) for
Basic facility structure.
equipment
Ozone
(1Duty/1Standby)
for requirements
Basic facility
*Facility
The Commission may
impose separate
on case by case
equipment
structure.
basis.

* The
Commission
may impose
separateofrequirements
case by case basis.
Figure
5.16
Schematic
illustration
ultravioletondisinfection
system with stilling plate for flow conditioning and
Figure 5.16 Schematic
illustration
ultraviolet
disinfection system with
elongated
weiroffor
level control
stilling plate for flow conditioning and elongated weir for level control
"A"

"A"
FLOW

PDC

COVER PLATES OR GRATING

STAINLESS STEEL WEIR

TOP VIEW
(Cables removed for Clarity)

CONTROL PANEL AND


POWER DISTRIBUTION CENTRE

FRONT ACCESS

ULTRAVIOLET LAMP RACKS


COVER PLATES OR GRATING
STILING PLATES

LEVEL PROBE

FLOW

SECTION 'A' - 'A'

126

Volume 4

114

Volume 4

Malaysian Sewerage
Industry Guidelines

Malaysian Sewerage
Industry Guidelines

Requirements for Stages of Sewage Treatment


Requirements for Individual Treatment Processes
Requirements for Stages of Sewage Treatment

5.17 schematic
Profile schematic
of lamp relative
modules
relative
Figure Figure
5.17 Profile
of lamp modules
to inlet
and outlet
to inlet and
outlet structure
structure
Figure 5.17 Profile schematic of lamp modules relative to inlet and outlet
structure
Flapper Gate
Level Control

Disinfection Module
Power & Data
Interconnect Cables

Flapper Gate
Level Control

Flow

Power & Data


Interconnect Cables

Effluent
Channel

UV Protective

Disinfection Module

Effluent
Channel

Station Cleaning
Liner with covet
304 Stainless Steel
Station Cleaning
Liner with covet
304 Stainless Steel

Service
Electrically Operated
Area Jib Host

Station Cleaning drain

Electrically Operated
Jib Host

Inffluent
Channel
Flow

Service
Area

UV Protective

Inffluent
Channel
Flow
Flow

Power Distribution
Data center (PDDC)

Power Cable
Signal Cable
from Plant Flow meter

Station Cleaning drain

PLAN VIEW

Power Distribution
Data center (PDDC)

Power Cable
Signal Cable
from Plant Flow meter

PLAN VIEW

Influent
Channel
Influent
Channel

Influent
Channel

Influent
Channel

SECTION "A - A"


SECTION "A - A"

Figure 5.18
Chemical-feed system schematic
Figure 5.18 Chemical-feed system schematic
Figure 5.18
Chemical-feed system schematic

CALIBRATION COLUMN

RELIEF VALVE

CALIBRATION COLUMN

RELIEF VALVE

CHEMICAL
FEED PUMP
CHEMICAL
FEED PUMP

STORAGE TANK

BACK PRESSURE
CONTROL
BACK PRESSURE
CONTROL

STORAGE TANK

Sewage Treatment Plants

Volume 4

Sewage Treatment Plants

Volume 4

Sewage Treatment Plants

Volume 4

127

115
115

Requirements for Individual Treatment Processes

5.10.1.1 Continuous Disinfection


I)

Disinfection with Ultra-Violet (UV)


a)
b)

c)
d)

e)
f)

g)
h)

i)

j)

128

Filtration ahead of the ultra-violet disinfection is a must in order


to ensure consistent and reliable disinfecting performance, as well
as, to reduce maintenance, such as, fouling of the UV lamps.

The performance of the UV unit shall meet a UV transmittance


level of secondary effluent of at least 60% on a filtered basis. If
a lower transmittance level is encountered, it shall be compensated
with the reduction in the spacing of lamps and/or usage of
an advanced higher intensity system to compensate the lower
tranmissibility of the sewage effluent.
The channel for the UV shall be open, long and narrow to
encourage plug flow and avoid short circuiting.

As a guide, the average sizing is roughly 10 conventional 1.5 meter


lamps per 1,000 m3/day at peak flow. However, the actual sizing
shall be site specific and subjected to effluent quality desired as
well as the level of upstream treatment provided.

In the design to house the UV modules, it is important to include


proper inlet and outlet structures and consider the approach and
exit flow conditions.

A stilling well is required to distribute the flows and equalise the


velocities across the cross-section of the channel. The stilling
plate shall be placed at least 5 meters in front of the first lamp
bank. Otherwise, the channel should have an undisturbed straight
line of two (2) or three (3) lamps length.

Sufficient distance shall be allowed between lamp banks (0.5 m


to 1.0 m) and two (2) to three (3) lamp lengths between the last
bank and the downstream level control device.

In large system applications, a multichannel configuration is


required. This is to allow the inlet structure to satisfy the dual
requirements of inducing flow and to allow even distribution of
flow among operational channels. Channel inlet structures shall
allow for hydraulic isolation of individual channels during low
flow and routine maintenance. In operation, the multichannel
design shall be controlled to maintain a minimum velocity through
any one channel.
Wastewater within the channel must be maintained at a constant
level with little fluctuations. This shall be accomplished by
using a mechanical counter balance gate downstream of the lamp
batteries.

It is crucial to avoid a dryness state in the channel during low


or no flow conditions to prevent the fouling of the quartz jackets

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

surrounding the lamps and/or causing damage to the UV modules.


To alleviate this, for a small STP, a fixed or adjustable weir
should be used.

k)

l)

m)

n)

However, sufficient weir length shall be provided to avoid water


level fluctuations. In larger STPs using the multichannel design,
these flow fluctuations can be attenuated by the opening and
closing of channels as needed.
Control systems should be simple. Its objective is to ensure that
the system loading can be maintained and disinfection accomplished,
while conserving the operating life of the lamps. In small STPs,
the control system shall consists, of a full duty unit in operation
at all times with a similar redundant unit on standby. Manual
control and flexibility should be made available to enable the
operator to bring portions of the systems in and out of operation,
as needed, to adjust for the changes in flow or water quality. In
larger STPs, a complete automation is warranted for plants using
the multi channel design.

Safety aspects of an UV disinfection facility involve mainly


the electrical hazards and protection from the exposure to UV
radiation. The exposure risks could be minimised as long as the
operating lamps are submerged and the lamp batteries are shielded.
The UV lamps shall not be operated in air and unshielded. All
systems must be equipped with safety interlocks that shut down
the modules if they are moved out of their operating positions
or the wastewater level falls, leaving any or all lamps exposed
to air. Electrical hazards can be minimised by the inclusion of
ground-fault-interruption circuitry with each module. This feature
is a requirement for all UV systems.
The design of the UV system shall allow for easy access to the
lamp modules for cleaning and other maintenance tasks. The
installation shall have adequate working area for maintenance
and servicing of the modules when taken out of the channels.
Cleaning of the lamps shall be accomplished using mechanical
wipers which may be fitted with chemical injectors and with
chemical baths when taken out of the channels.
A drainage system back to the head of the treatment works shall
be provided to drain back water from the reactors, channels
and other related tankage. In addition, a permanent clean-water
system is to be made available to allow for rinsing and cleaning
needs. A bypass around the UV disinfection facility is to be
made available in the event the system is shut down completely
for maintenance.

Sewage Treatment Plants

Volume 4

129

Requirements for Individual Treatment Processes

Table 5.20 Design Guides for Disinfection with Ultra-Violet(UV)

UV system

Description

Design Criteria

Mounted in open channel type*


Must be preceeded with filtration.

Minimum UV Dose (at 254 nm) at end of


lamp life

30 mJ/cm2 (30,000 Ws/cm2)


at Qpeak

Maximum Total Suspended Solids in


effluent to UV system

< 10 mg/l

Maximum Mean Particle Size in effluent

20 microns

UV Transmittance at 254 nm

65%

Lamp life

12 000 hours

Minimum UV output at end of lamp life

80%

Operating Temperature

18 40 oC

Relative Humidity

> 95% at 40 oC

UV detection System

UV sensor, transmittance, dose pacing

Lamp Sleeve Cleaning system

a. Mechanical wipers and out of


channel chemical cleaning.
b. Additional 25% more lamps shall be
provided for mechanical wipers.

Standby lamps

25% to be provided with min 2 lamp


banks

Disinfection Standards

In accordance with receiving water


requirement or effluent usage

Note:

*Enclosed system shall be permitted under special circumstances

II)

Disinfection with Hypochlorite


a)

130

Calcium and sodium hypochlorite are hazardous chemicals to


handle and use. Calcium hypochlorite is classified as a corrosive
Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

and rapid oxidant, while sodium hypochlorite is a corrosive


agent. Eye protection, access to an emergency eyewash system
and showers must be made available to the operators.

b)

c)

d)

e)

f)

g)

h)

Also, direct contact with the undiluted hypochlorite is likely to


cause burns to the skin and clothing. Therefore, it is imperative
that protective clothing which includes rubber gloves, must be
worn by operators when working with these chemicals. When
calcium hypochlorite is being transported in the powder form and
mixed in water to form solutions, the operator should always wear
eye protection and dust masks. All areas exposed to hypochlorite
should be washed thoroughly.
Chlorine dosage ranges from 6 to 10 mg/l for effluent. The
dosage rate is affected by the suspended solids and ammonia
present in the effluent, mixing employed, contact time and the
control strategies used for dosing.
Proper mixing is important for effective disinfection.

If a hydraulic jump is employed as a mixing device, the submergence


of the diffuser shall not be less than 230 mm (9 in.) below
the water surface and placed before the hydraulic jump at the
minimum flow. The hydraulic jump is effective in mixing when
the head loss exceeds 0.6 m (2 ft). To ensure adequate mixing
is achieved, the evaluation of the flow characteristics should be
carried out. As a minimum, the Reynolds number shall be 2.1
x 104 for pipe flow and Froude numbers between 4.5 and 9 for
open channels is recommended.

Hypochlorinators are chemical-feed pumps used for feeding


sodium or calcium hypochlorite. The basic components are a
storage reservoir or mixing tank for the hypochlorite solution; a
metering pump that consists of a positive displacement pumping
mechanism, motor or solenoid and a feed rate adjustment device;
and an injection device. Depending on the size of the system, a
plastic or fiber-glass vessel may be used to hold a low-strength
hypochlorite solution. It is not acceptable to use metals commonly
used in the construction of storage tanks to hold the hypochlorite
solutions because of the corrosive nature of the chemical which
will also expedite the decomposition of the liquid hypochlorite.

Feeding of calcium hypochlorite will require a mixing device,


usually a motorised propeller or agitator located in the tank.
Also, in the tank is a foot-valve and suction strainer connected
to the suction inlet of the hypochlorinator.

The hypochlorinator shall be feed rate adjustable.

The injection fitting shall be similar to that used in the gas


chlorinator.

Sewage Treatment Plants

Volume 4

131

Requirements for Individual Treatment Processes

i)

A chlorine contact tank shall take the form of rectangular


serpentine chamber. Circular chambers for disinfection are not
acceptable.

j)

Local supply of water shall be made available for the dilution of


powder calcium or sodium hypochlorite. A breaker tank for supply
of water is required for the proper running of the hypochlorinator.
If deemed necessary, the water pressure maybe increased with the
provision of water booster pump.

k)

Pipe works should be suitable for chlorination applications and


well supported.

l)

m)

n)
o)

Provision for draining the chlorine contact chamber is required


for cleaning and maintenance purposes. This shall include a drain
valve located at the bottom of the downstream end of the chamber.
The point of discharge shall ensure that adequate treatment is
given and this could be done through pumping the content from
the chamber and return to the head of the treatment plant.
A bypass around the chlorine contact chamber shall also be
provided to enable flows to be bypassed during maintenance or
servicing. There shall be penstocks upstream and downstream
of the chlorine contact chamber for isolation purposes.

Adequate access with sufficient turning radius for the vehicle


to carry in the chemicals to the disinfection system shall be
provided.

A small housing structure shall be provided to house hypochlorinator,


associated chemicals and ancillaries. Some important consideration
have to be given in the design of adequate space for the operators
to replace and fill the chemicals, washing facility, eyewash, record
keeping of chemical dosing, effluent flowmeter data among others.
Due to the hazardous nature of the disinfection system housed,
a locking system shall be made available to deter vandalism and
promote safety of the plant.

The structure housing the hypochlorinator and the chemicals shall be


bunded to prevent the possibility of spillage. The sizing of bunds shall
correspond to the total volume of the storage/solution tanks.

132

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

Table 5.21 - Design Guide for Disinfection with Hypochlorite


Type

Dosage
Mixing
Hypochlorinator
system
Equipment
Contact Tank
Contact Period

Maximum depth
Depth : Width
Min no. of passes
Length : Width at
each pass
Wetted Depth :
Width

Calcium or Sodium

6 10 mg/l
Mechanical, baffles or hydraulic jump.
Feed rate adjustable
1 duty/ 1 standby
15 minutes at Qpeak
3m
2:1
4
6:1

< 2:1

5.10.1.2 Intermittent Disinfection


The design requirements for intermittent disinfection facility shall comply
to the following:
a)
b)

Due to the infrequent usage and other health and safety considerations
in an intermittent disinfection system, ONLY liquid hypochlorite,
either calcium or sodium, shall be used.
A chlorine contact chamber shall be provided with a minimum of
15 minutes hydraulic retention time at peakflow. This chamber
shall be of a rectangular configuration with aspect ratios optimised
to promote plug flow conditions. The recommended aspect ratios
are as follows:
i)
ii)
iii)
iv)

Sewage Treatment Plants

Length to width (each Pass): 6:1


Minimum number of passes: 4
Height to width of the cross-section of the wetted section:
< 2:1
Depth of chlorine contact chamber is typically 2 3 m.
The corners shall be rounded to reduce the dead flow
areas and the velocity through the contact chamber shall
be sufficient to minimise solids deposition.

Volume 4

133

Requirements for Individual Treatment Processes

v)

horizontal baffles shall be used to ensure the plug flow


conditions are maintained and to minimise the possibility
of short circuiting.

vi)

Upstream of the contact chamber, a dosing coupling for


easy hook-up of the mobile hypochlorite disinfection system
shall be an inherent part of the chamber design.

c)

A breaker tank for supply of water adjacent to the contact tank is


required to provide water for the mixing of powder hypochlorite
and for cleaning or cleansing of the contact chamber. If deemed
necessary, a water booster system shall be provided to increase
the water pressure for the intended application.

d)

Draining provision must be made available to allow for complete


drainage of the chlorine contact tank. For this purpose, a drain
valve shall be provided at the bottom of the downstream end of
the chamber.

e)

f)

g)

Penstock/slide gate shall be provided at the upstream and downstream


end of the contact chamber. This allows for the effluent flow
from the treatment plant to bypass this chamber when its service
is not required.

Adequate access shall be provided for a portable hypochlorinator


unit mounted on a skid to be brought by a truck to the contact
chamber area when disinfection is required. A concrete pad
adjacent to the contact chamber shall be provided for the skid
mounted hypochlorinator to be situated when in use.
Power supply shall be adequately provided and located close to
the contact chamber to run the intermittent disinfection system.
Table 5.22 Design Guide for Intermittent Disinfection
Type

134

Calcium or Sodium

Dosage

6 10 mg/l

Mixing

Mechanical, baffles or hydraulic jump.

Hypochlorinator
system

Feed rate adjustable

Equipment

1 duty/ 1 standby

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

Table 5.22 Design Guide for Intermittent Disinfection (cont.)


Type

Calcium or Sodium

Contact Tank
Contact Period

15 minutes at Qpeak

Maximum depth
Depth : Width
Min no. of passes
Length : Width at each
pass
Wetted Depth : Width

3m
2:1
4
6:1
< 2:1

5.11

Design of Flow Measurement Devices

5.11.1

Purpose of Flow Measuring Devices


Flow measuring devices are necessary for monitoring of plant operation
and process control continuously. The purposes of flow devices are:
a)
b)
c)
d)

5.11.2

to maintain flow records periodically for future reference, especially


when plant expansion is needed.

to identify the flow pattern which may be due to population


growth or infiltration.
Statutory requirement by the DOE to maintain flow records at
all sewage works.
To establish operational cost for treatment of sewage.

Design Requirements for Flow Devices


Flow devices are mandatory for all STP, regardless of size.

Sewage Treatment Plants

Volume 4

135

Requirements for Individual Treatment Processes

Table 5.23 Design Parameters for Flow Devices


Design Criteria

Description

Location of flow
meter
Type of Flow
Measurement
Type of flow meter

Method of
measurement

Measurement
times

PE 5,000

PE > 5,000

Inlet or Outlet

Inlet and Outlet

Closed Conduit or Open


Channel
V- notch (Outlet Only)
Rectangular Weir (Outlet Only)
Flumes

Closed Conduit or Open


Channel
V-notch (Outlet Only)
Rectangular (Outlet Only)
Flumes

Electromagnetic

Electromagnetic

Ultrasonic
Automated or manual
measurement of Staff gauge
to measure height of crest
with calibration curves /
tables
Continuous or Intermittent

Ultrasonic
Automated devices linked to
data logging with integrator
and transmitted to chart
recorder
(minimum 7 days chart time)
Continuous

5.12

Sludge Holding, Treatment and Disposal

5.12.1

Introduction
All treatment processes are capable of producing significant quantities
of sludge which requires to be further treated. The sludge comprises
essentially inert and organic matters that are biodegradable and nonbiodegradable present in sewage, and bacterial cells generated by the
biological treatment processes. The treated sludge, often referred as
biosolids is ready for safe disposal or reuse.
The importance of sludge management increases with the increase in the
amount of sewage treated. Space has to be allowed within the premises
of an STP to accommodate sludge treatment, handling and storage
facilities.
All sludge need to be treated for safe disposal back to the environment.
The minimum requirement for sludge treatment is to achieve stabilize
sludge with a 20% dry solid content.

136

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

For large scale development whereby the full sludge generation will
only be achieved over a certain time period, proper sizing/modulation
of sludge treatment facilities need to be provided in order to achieve
the immediate needs for sludge treatment.
5.12.2

Sludge Strategy in General


Figure 5.20 shows the typical sludge treatment and disposal strategy
which consists of three main stages.
a)

Stage 1 - Preliminary treatment and digestion

c)

Stage 3 - Utilisation and disposal

b)

I)

Stage 2 - Conditioning and dewatering

Stage 1 - Preliminary Treatmentand Digestion

Preliminary treatment may include reception or holding facility for


screened sludge, primary thickening and digestion facilities.
For imported sludge the reception facility may comprise of an unloading
area, screen chamber, reception tank and transfer pump(s).
Thickening equipment, such as, centrifuge, drum thickener or gravity
belt thickener is provided to thicken the raw screened sludge from
about 1% dry solids content to about 6% dry solids content. To assist
the thickening process, an in-line polymer dosing system or chemical
conditioning shall be provided.
Two types of digestion facilities are available for digestion after the
thickening: aerobic and anaerobic digestion.
Secondary thickening is recommended to reduce the volume of digested
sludge, which will then reduce the size and the number of the next
treatment process unit, i.e., dewatering equipment.
II)

Stage 2 - Conditioning and Dewatering

Dewatering can be achieved by two (2) methods : mechanical dewatering


and non-mechanical dewatering.
a)

Mechanical dewatering such as belt filter press, centrifuge or


filter press is provided for sludge dewatering purposes. To assist
the mechanical dewatering equipment in achieving optimum level
of cake dryness, an in-line polymer dosing system or chemical
conditioning shall be provided.

Sewage Treatment Plants

Volume 4

137

Requirements for Individual Treatment Processes

b)

Non-mechanical dewatering, e.g. drying beds or sludge lagoons


is often used
For a facility serving 10,000 PE, the drying beds must be
designed to support mechanical/machine lift for the purpose of
clearing the dried sludge.
Sludge lagoons of about 2 m depth are also used for sludge
stabilisation and drying. The sludge lagoons shall be sized to
receive sludge for a period of at least 6 months and are allowed
to undergo stabilisation through evaporation and drying for
another 6 months period. The lagoons shall be lined with either
PVC lining, concrete or 600 mm thick clay lining. An access
ramp shall be provided to allow mechanical equipment access
to clean dried sludge.

III)

Stage 3 - Utilisation and Disposal

After the dewatering process, an on-site storage for 30 days of the


treated bio-solid shall be provided. The storage structure shall be
covered with roof and provided with partly opened walls to allow for
proper ventilation.
Finally, the bio-solid is either composted and/or applied directly for
land reclamation (i.e., for ex-mining land), land application (i.e., for
certain types of agriculture land and forest land/reforestation) or used
as top soil cover at land fill site. The ultimate disposal of bio-solid is
the responsibility of the plant operator.
5.12.3

Provision of Sludge Holding, Treatment and Disposal


The Service Licensee will advise on current capacity in its existing
sludge treatment facilities, suitable sludge stabilisation, dewatering and
final disposal of the sludge shall be provided.
If the Service Licensee has the capacity to receive sludge generated from
the development, then the project proponent has the option to negotiate
with the Service Licensee to dispose off the sludge at the existing
facility. In this case, a sludge storage tank with a minimum capacity to
hold for 30 days with the sludge thickened to 1% solids is acceptable.
Otherwise, the sludge shall be stabilised, dewatered and prepared in a
suitable form for disposal.
Different types of STPs produce different quantities of bio-solid. The
principal assumptions adopted on waste generation rates are summarised
in Table 5.24.

138

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

Table 5.24 - Sludge Generation Rates


Treatment System

Unit Generation Rates

Comments

Primary Sludge
Primary Clarifier

0.5 kg sludge/kg solids input

Based on continuous
sludge withdrawal

Imhoff Tank

0.15 kg sludge/kg SS input

Based on average 6 month


desludging period

Conventional
Activated Sludge
System

0.8 to 1.0 kg sludge/kg BOD5


removed

Standard A/B

Extended Aeration or
Oxidation Ditch

0.4 to 0.6 kg sludge/kg BOD5


removed

Standard A/B

RBC/SBC/High
Rate Trickling Filter
System

0.8 kg sludge/kg BOD5 removed Standard A/B

Hybrid System

0.4 kg sludge/kg BOD5 removed Standard A/B

Secondary Sludge

Note:
Based on the above assumptions, the quantity of waste sludge requiring treatment and disposal can
be estimated. Refer also to design guides related to each of the above individual processes.

5.12.4

Design Criteria
The ultimate aim of sludge treatment is to achieve at a minimum
stabilised sludge with dry solids content of 20% for final disposal.
A combination of various unit processes may be used to achieve this
minimum requirement.
I)
a)
b)
c)

Sludge Reception/Sludge Holding


An unloading area is normally provided to receive sludge tankers
delivering imported sludge to the facility, if necessary. It should
also includes a parking area for sludge tankers.
A mechanically raked screen with 12 mm opening together
with a manually raked by-pass screen shall be provided where
necessary.
Connection fitted female coupling with ball valve shall be
provided at the reception facility for the connection of desludging
tankers hose.

Sewage Treatment Plants

Volume 4

139

Requirements for Individual Treatment Processes

d)

Minimum three (3) days sludge holding capacity of between


1 to 4% dry solids content sludge (depending on the types of
sludge) shall be provided after the screening process.

e)

Overflow pipe shall be provided at sludge holding tank to


aeration tank to avoid overflowing.

f)

II)

Adequate ventilation/air extraction fan shall be provided at the


thickening/dewatering house.
Solid Thickening

Thickening is a process used to increase the solids content of sludge by


removing a portion of the liquid fraction. It is generally accomplished
by physical means, including co-settling, gravity settling, flotation,
centrifugation, gravity belt and rotary drum. The design parameters for
sludge thickening equipment shall follow Table 5.25 below:
Table 5.25 - Design Parameters for Sludge Thickening

Type of Thickening

Picket Fence Gravity


Thickener

% Dry
Solids

1.5

Dissolved Air
Flotation

Belt Thickener

Drum Thickener

Centrifuge

Polymer
System

Speed of
Sludge
feed
pump

Backwash
water
system

n/a

n/a

n/a

< 300 rpm

Yes

Yes with
appropriate
polymer
turndown
ratio

Note:
a) Mechanical thickener shall be designed for 8 hrs/day and 5 days/week
operation.
b) For belt, drum and centrifuge thickener, three polymer injection
points shall be provided
c) Potable water to be provided for polymer mixing system.

140

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

III)

Solid Digestion

Sewage biosolids in its natural state (raw) is rich in pathogenic organisms,


easily putrescible and rapidly developing unpleasant smells. Stabilization
processes were developed with the purpose of stabilizing the biodegradable
fraction of organic matter present in the bio-solids, thus reducing the risk
of putrefaction as well as diminishing the concentration of pathogens.
The stabilization processes can be divided into:
a)

b)
c)

Biological stabilization specific bacteria promote the stabilization


of the biodegradable fraction of the organic matter.

Chemical stabilization chemical oxidation of the organic matter


accomplishes sludge stabilization.
Thermal stabilization heat stabilizes the volatile fraction of
sludge in hermetically sealed containers.

The most widely used stabilization process is biological stabilization


via anaerobic and aerobic digestion.
Table 5.26 - Design Parameters for Aerobic and Anaerobic Digestion

Description

Number of Tank, Minimum

Min. Solids Retention Time


Organic Loading Rate

Typical Feed Solids


Concentration

Unit

No.

Days

KgVS/m3.d
%

Type of Mixing

Tank Dimension, maximum

Dissolved Oxygen

Sewage Treatment Plants

Aerobic
Digestion

Anaerobic
Digestion

10

18

1.6 4.8
2

Aerators
Diffusers

Min. Water Depth, minimum

Tank Shape

Design Criteria

mg/L

Volume 4

Cylindrical
Rectangular
25 diameter
25 length
1-2

0.8 1.6
2-6

Gas Injection
Mechanical
Stirring
Mechanical
Pumping
7.5

Cylindrical
Egg-Shaped
25 diameter
-

141

Requirements for Individual Treatment Processes

IV)

Sludge Dewatering

Table 5.27 Recommended Design Parameters


for Sludge Stabilisation and Dewatering
Descriptions

Sludge Stabilisation
Type of stabilisation
process

Hydraulic retention time


(HRT) minimum

Design Considerations

Unit

PE 2,000

PE > 2,000

Simple anaerobic or
aerobic digestion

Ambient anaerobic
digestion with good mixing
facility

Days

Dewatering

Type of device

30

30

Belt press
Centrifuge
Filter press
Drying bed

Belt press
Centrifuge
Filter press
Drying bed *

Operating period of
mechanical thickening
and dewatering facility

5 days/week #
8 hours/day
250 days/year

5 days/week #
8 hours/day
250 days/year

Covered storage area

1 month holding

Minimum dry solids


(content after dewatering)

Handling capacity of
drying bed

20

4 weeks cycle on
450 mm thick feed

20

4 weeks cycle on
450 mm thick feed

1 month holding

Notes:
a)
Access ramp of at least 1.5 m wide shall be provided at all sludge drying
beds
*
#

142

Drying beds must be designed to support mechanical/machine lift for more


than 10 000 PE.
Design to be based on one full-time working shift only.
In computing the area requirements of a sludge drying bed, the designer may
assume a maximum 450 mm depth of sludge feed to the bed. The actual
quantity of sludge from the upstream unit processes needs to be computed
before sizing the bed. Each bed may be designed to handle a maximum of
7 days continuous feed. The next feed to the same bed shall only be after
a minimum of 21 days from the last feed. A one-third (1/3) reduction in
actual land area requirement will be acceptable if fully covered drying beds
are provided. Reduction shall only apply to the total surface area of drying
Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes


for thickness.
Stages of Sewage
Treatment and
bed. No reduction is allowed for theRequirements
drying bed
Structures
materials used for the drying bed covers shall be designed to an acceptable
structural
strength
andused
of acceptable
to withstand
local weather
Structures and
materials
for the dryingquality
bed covers
shall be designed
to an
conditions.
acceptable structural strength and of acceptable quality to withstand local weather

conditions.

Figure 5.20 Sludge Treatment and Disposal Strategy


Figure 5.20 Sludge Treatment and Disposal Strategy
Untreated Sludge

Screening

Primary Thickening
Preliminary
Treatment
and Digestion

Anaerobic Digestion

Aerobic Digestion (Optional)

Secondary Thickening
(Optional)

Possible disposal
of Liquid Sludge

Chemical Conditioning
Conditioning
and
Dewatering
Mechanical Dewatering

Drying Beds

Drying Lagoons

Storage at works
Utilisation
and
Disposal

To inlet of STW
or
on-site Liquor Treatment Plant

Composting
Transportation from works

Land Reclamation

Sewage Treatment Plants


Sewage Treatment Plants

Land Application
Forestry/Agriculture

Landfill Site

Volume 4
Volume 4

143
131

Requirements for Individual Treatment Processes

V)

Ultimate Disposal
The treatment plant project proponent has to indicate in the
proposal the ultimate disposal options and actual volume for
disposal throughout the life time of the plant.

5.13

Tertiary Treatment

5.13.1

Introduction
Tertiary treatment is associated with the requirements to further reduce
or remove pollutants beyond the levels achieved by common secondary
treatment processes. Such requirements can be in the forms of the
removal of nutrients, such as, nitrogen and phosphorus; lower BOD5 or
SS levels; or trace elements of toxic constituents, such as, heavy metals
or refractory organics.
The various methods of tertiary treatment include simple maturation ponds,
adsorption, chemical treatment and filtration; air stripping, mambrane or
reoxygenation.
Tertiary treatment is required before discharging to very sensitive receiving
waters. The Commission will specify the need for such treatment on a
case-by-case basis, depending upon the sensitivity of the project.

5.13.2

Design Requirement
I)

Filtration system

a)

Filtration is the most common tertiary treatment system used to


remove suspended or colloidal matter in the effluent.

b)

c)
d)
e)
f)

144

Backwashing shall be limited to once per day. The volume


of backwash water shall not exceed 10% of plant throughout.
Backwash water shall be stored in a buffer tank before being
return to the inlet of the plant.
Where used, the facility for dosing conditioners shall be provided
at the inlet of the filter system.
On-line turbidity meter, level detector and flow measurement shall
be utilized to measure filter performance.

If the filters are housed in a building, adequate and safe access


shall be provided for maintenance purposes.

The filters shall have automated backwash features and sized


adequately to allow continuous filtration.

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Individual Treatment Processes

g)

For package plants, it is preferred to use FRP as the filter vessel.


However, fabricated steel is also acceptable provided that protective
coatings are included. For larger plants, the use of reinforced
concrete is encouraged.

II)

Adsorption (Activated Carbon)

b)

Adsorption shall be preceded by filtration using granular media


to ensure a consistant feed quality, which is affected by pH,
temperature and flow rate.

a)

c)
d)
e)

Activated carbon is used to remove small quantities of refractory


organics, as well as inorganic compounds, such as nitrogen,
sulficles and heavy metals.

Uniform feedwater to avoid any surges that might adversely affect


the carbon adsorption.
Clarity of feedwater is important to avoid restriction of pores or
build up of materials within the pore structure.

Backwashing rate and the frequency required depend on the


hydraulic loading and operational method. Typical duration of
backwashing is 10-15 minutes.

III)

Chemical Treatment

b)

Phosphorous precipitation requires the addition of coagulants,


which usually are lime, alum, sodium aluminate, ferric chloride
and ferrous sulfate.

a)

c)

Chemicals can be used as tertiary treatment for acid-base


neutralisation and precipitation of phosphorous.

Dosing systems and safety features to be provided to assure the


operation and maintenance of the systems can be carried out in
a safe and healthy environment.

IV)

Air Stripping

b)

The design features shall depend on the required level of nitrogen


removal with the critical parameters being tower packing, quantity
of air supply, air and liquid temperatures and process control
measures.

a)

This method is used to remove ammonia nitrogen (NH4 N)


from effluent.

V)

Reoxygenation

a)

This method is used to increase the dissolved oxygen (DO) levels


in the effluent.

Sewage Treatment Plants

Volume 4

145

Requirements for Individual Treatment Processes

b)

The different types of reoxygenation systems are cascade,


reoxygenation and mechanical reoxygenation

Requirements
for
Individual Treatment
Processes
c)
Cascade
reoxygenation

is achieved using on the hydraulic design


of structures, such as, weir overflows, flumes, spillways, etc.

d)

b)

e)

d)Design
Mechanical
reoxygenation
is achieved using
mechanicalisequipment
of structures
or mechanical
equipment
based
such as surface aerators, jet diffusers or diffused air (coarse, fine
amount
of
DO
required
for
the
effluent.
bubble, etc.)

VI)
a)

The different types of reoxygenation systems are cascade,

Mechanical
reoxygenation
is achieved
using mechanical equipment
reoxygenation
and mechanical
reoxygenation
as surface
aerators,is jet
diffusers
or the
diffused
(coarse,
fine
c)such Cascade
reoxygenation
achieved
using on
hydraulicair
design
of
bubble,
etc.) such as, weir overflows, flumes, spillways, etc.
structures,

e)

on the

Design of structures or mechanical equipment is based on the

amount of DO
required for the effluent.
Maturation
ponds

PondMaturation
systems are
normally not encouraged because it requires
ponds
large land area and the inherent difficulty in controlling algal
a)
Pond systems are normally not encouraged because it requires large
growth.
In special
cases, difficulty
where land
is in abundance,
land area
and the inherent
in controlling
algal growth.the
In project
proponent
may where
choose
use
this system.
special cases,
landtois in
abundance,
the project proponent may

(VI)

choose to use this system.

Figure 5.21 Typical Roof Details for Covered Sludge Drying Bed
Figure 5.21 Typical Roof Details for Covered Sludge Drying Bed

134

146

Volume 4

Volume 4

Malaysian Sewerage
Industry Guidelines

Malaysian Sewerage
Industry Guidelines

Section 6
Requirements for
Ancillary Facilities

Requirements for Ancillary Facilities

148

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Ancillary Facilities

6.1

Introduction
This section defines the minimum requirements of ancillary facilities
to be provided at the sewage treatment plants. These requirements are
crucial in ensuring the workability and operability of the plants.

6.2

Water Supply and Wash Water


Water shall be supplied to each site from standpipes and taps, to provide
for sanitary cleansing of plant areas, personal hygiene, safety, fire
fighting, process use and for equipment cooling and/or sealing. Water
shall be connected to potable supply that provides a minimum pressure
of 20 m head across the site. A ring main system shall be provided for
all treatment plants larger than 5000 PE.
Each sewage treatment plant or sludge treatment facility shall be
provided with water tank of at least 445 litre storage capacities or one
day water usage or whichever is higher.
Double backflow prevention shall be provided in all cases. This is to prevent
contamination of any potable water service, including the incoming supply
line.
The water supply system shall be sized to meet the following cases:

i)
ii)

Fire fighting demand as instructed by the local regulations and


any essential plant water demands.

All potentially simultaneous process uses, equipment uses and a


for plant cleansing.

All water supplies and its installation (piping, tanks, air conditioning
drainpipes, gutters and etc.) must be totally isolated from all potential
contact of electrical system by means of total enclosure or suitably
located the electrical system above flood level.
Where required, wash water shall be equipped with booster pump and
where possible, obtain from reclaimed water.
Drawings submitted for approval shall indicate locations of water tapping
point and piping layout. Approval for water tapping should be obtained
from water authority for permanent water supply before submitting
inspection form. All related document, such as water bills and transfer
of ownership, to be submitted before final inspection.
Table 6.1 tabulates the minimum number and location of stand pipe
required in a sewage treatment plant. Typical drawing of stand pipe
are shown in Figure 6.1
Sewerage Treatment Plants

Volume 4

149

Requirements for Ancillary Facilities


Requirements for Ancillary Facilities

Table 6.1 Minimum Number of Recommended Water


Table 6.1 Minimum Number of Recommended Water
Stand Pipe and Location
Stand Pipe and Location
Class of
Class of
STP
STP

1
1
22

33
4
4

Population
Population
Equivalent
Equivalent

1,000
1000
1,001

1001 5000
5,000
5001
20 000
5,001
20,000
>20 000
>20,000

Minimum
Minimum
Numbers
Numbers

Location
Location

1
1
2 2

Inlet Works
Inlet Works
Inlet
Works
and
Treatment
Inlet
Works
and
TreatmentProcess
ProcessUnit
Unit

2 2

Inlet
Works
and
TreatmentProcess
ProcessUnit
Unit
Inlet
Works
and
Treatment

Inlet Works, Secondary Screen Area,


Inlet Works, Secondary Screen Area,
Treatment Process Units and Dewatering
Treatment Process Units and Dewatering
Facilities.
Facilities.

Figure 6.1 Standard Details for Stand Pipe


Figure 6.1
Standard Details for Stand Pipe

800
76

648

76

64
8

76

608

15 G.I PIPE

76

80
0

100

STAND PIPE

6.3
6.3

Mess
Facilitiesand
andAblutions
Ablutions
Mess Facilities

All
plants shall
shallhave
havea aminimum
minimum
sanitary
set consisting
All treatment
treatment plants
of of
oneone
sanitary
set consisting
of
of
a
toilet
and
wash
basin.
Washing
facilities,
toilets
and
showers
shall
a toilet and wash basin. Washing facilities, toilets and showers shall be
be
provided
operators
all Class
and 4Class
plants
PE
provided
for for
operators
at allatClass
3 and 3Class
plants4with
PE with
greater

150

138

Volume 4

Volume 4

Malaysian Sewerage
Industry Guidelines
Malaysian Sewerage
Industry Guidelines

Requirements for Ancillary Facilities


Requirements for Ancillary Facilities

greater than 5000. Additionally, mess accommodation shall be provided


than
mess accommodation
at 5,000.
Class 4Additionally,
treatment plants
with PE greatershall
thanbe20provided
000. at Class
4 treatment plants with PE greater than 20,000.

Guard house with water and power supply shall also be provided for
Guard house with water and power supply shall also be provided for plant
plant more than 20 000 PE.
more than 20,000 PE.
Figure 6.2 Typical for Administration and Mess Facilities Building
Figure 6.2 Typical for Administration and Mess Facilities
Building

16

Visitors / Staff Parking

Covered Porch

Managers /
Engineers Office

Reception Area

General Office

Supervisor's Office

5
Meeting /
Briefing Room

14
8

Workshop

Sample Reception
& Preparation

Male
Toilet

Female
Toilet

Prayer
Room

12

Control Room

Clean Locker Room


Recreation Area

10
Pantry

13

11

General Store

Eating Area

16

Note :

Sewerage Treatment Plants

Sewage Treatment Plants

Dirty Locker Room

9
Toilet / Shower

Motorcycles / Operational Vehicles Parking

The numbers on the layout correspond to the numbers in Table B.1.


The layout is only for indicative purposes only and can be changed ( i.e. floor space and other arrangement)
to suit the plants needs and requirements.

Volume 4

Volume 4

151

139

Requirements for Ancillary Facilities


Requirements for Ancillary Facilities
Requirements for Ancillary Facilities

6.4
6.4
6.4

Minimum internal floor area of mess facilities are 400 meter 2 .


Minimum from
internal
area of mess
facilities
are 400
meter2. floor
Approval
Approval
thefloor
Commission
shall
be sought
if smaller
area
2
from
theinternal
Commission
shallofarrangement
be
sought
ifof smaller
floor
is to bein
Minimum
floor
area
mess
facilities
are 400
meterarea
. is
Approval
is
to be
provided.
Typical
mess
facilities
shown
provided.
Typical arrangement
mess facilities
is shown
Figure
6.2be
from
the 6.2
Commission
shall be ofsought
if smaller
floor in
area
is to
Figure
provided. Typical arrangement of mess facilities is shown in Figure 6.2

Roads and
Roads
andAccess
Access
Roads and Access

All-weather, surfaced
surfaced roads
All-weather,
roads shall
shall be
be provided
provided to
to permit
permit access
access toto all
all
treatment
plants.
The
roads
must
withstand
a
load
of
at
least
15
tonnes.
All-weather,
surfaced
roads
shall
be
provided
to
permit
access
to
all
treatment plants. The roads must withstand a load of at least 15 tonnes.
Such roads
roads
must
also
be
within
plant
access
to
treatment
plants.
must withstand
a the
load
of
atproviding
least
15 tonnes.
Such
mustThe
alsoroads
beconstructed
constructed
within
the
plant
providing
access
each
process
The
construction
shall
with
Such
roads
must unit.
also
be
constructed
within
thecomply
plant
providing
accessWork
to
to
each
process
unit.
The
construction
shall
comply
withPublic
Public
Work
Department
requirement.
Figure
6.3
and
Figure
6.4
illustrate
the
typical
The
construction
shall
comply
with
Public
Work
each
process
unit.
Department requirement. Figure 6.3 and Figure 6.4 illustrate the typical
section of road pavementFigure
and site road.
Department
Figure 6.4 illustrate the typical
section of requirement.
road pavement and 6.3
siteand
road.
section of road pavement and site road.
Figure 6.3
Typical Details of Road Pavement
Figure 6.3 Typical Details of Road Pavement
Figure 6.3
Typical Details of Road Pavement
40 THK. WEARING COURSE

60 THK.
PREMIXCOURSE
BINDER COURSE
40 THK.
WEARING
10 THK. SAND/QUARRY DUST
60 THK. PREMIX BINDER COURSE
10 THK. SAND/QUARRY DUST

300 THK. CRUSHER RUN


50 THK SAND
300 THK. CRUSHER RUN
50 THK SAND

Figure 6.4
Typical Road Section of Site Road
Figure
6.4 6.4 Typical
TypicalRoad
RoadSection
Section of Site
Figure
SiteRoad
Road
4000
4000
ROAD KERB
ROAD KERB

ROAD KERB
FALL

FALL

FALL

ROAD KERB

FALL

40 THK. WEARING COURSE


60 THK. PREMIX BINDER COURSE
40 THK. WEARING COURSE
250 THK.
ROADBASE
60 THK.
PREMIX
BINDER COURSE
THK.
SUB-BASE
250150
THK.
ROADBASE
GEOTEXTILE MEMBRANE APPROVED BY ENGINEERS
150 THK. SUB-BASE
GEOTEXTILE MEMBRANE APPROVED BY ENGINEERS

152

140
140

The on-site road shall be able to provide safe and convenient access for
trucks
or other
equipment
usedsafe
for and
maintenance
purposes.
The
The
on-site
road machinery
shall be able
to provide
convenient
access for
trucks or other machinery equipment
used
for
maintenance
purposes.
The
Volume 4
Malaysian Sewerage
Industry Guidelines

Volume 4
Volume 4

Malaysian Sewerage
IndustrySewerage
Guidelines
Malaysian

Requirements for Ancillary Facilities

The on-site road shall be able to provide safe and convenient access for
trucks or other machinery equipment used for maintenance purposes.
The minimum width of the road shall be 4 meter Where vehicles need
to pass frequently or parking is required along the road, the minimum
width shall be 6 m.
Corner of junction for perimeter internal road for tankers or trucks
access shall have a minimum inside radius of 6 meter. Inside radius
for perimeter road not intended for tankers or trucks access shall be
not less than 4 m.
Cul-de-sac at the end of roads shall be provided with turning area
reserve of not less than 9 m.
Where roads for maintenance vehicles or machineries are not required,
concrete or hard surfaced walkways of at least 900 mm width shall
be provided between each process unit. Concrete hardstanding area
can be laid where storage bins are located. The use of steps shall be
avoided, where possible.
Where the ingress or egress of the treatment plant is near a junction of
a public road, an adequate acceleration and deceleration lane must be
made available between the access road and the junction for vehicles
to safely enter and leave the treatment plant.
Vehicular access shall be provided to all unit processes that require
daily operation and maintenance.

6.5

Drainage
The area of the treatment plant shall be adequately drained and this
shall be arranged to prevent surface water run-off from entering the
process units.
Any cleaning or maintenance process wash water must be returned to
the inlet works via a separate drainage system.
External drainage facilities must be provided for treatment plant along the
slope area. Cut off drainage at the entrance must also be provided.

Treatment plant platform level shall be designed above flood level.


If the treatment plant is located in a flood prone area, flap gate shall
be provided to avoid back flow from the river/ main drain. The plant
hydraulic must be designed properly to ensure the discharge head is
adequate to open the flap valve at any circumstances.

Sewerage Treatment Plants

Volume 4

153

Requirements for Ancillary Facilities

The effluent discharge shall be directed to the main drain or river


to avoid discharging effluent into a drain within the residential area.
Discharge to a retention pond is not allowed unless prior approval has
been granted.
The receiving drain/watercourse shall have sufficient capacity to accept
the run-off from the plant as well as the effluent discharge from the
treatment plant.

6.6

Fencing and Security


The boundary of a treatment plant, pumping station and/or sludge
treatment facility shall be secured by 3.0 meter high fence. The perimeter
fence shall have an entrance by double gates or sliding barrier to allow
access of maintenance vehicles. The gates shall be secured by padlocks
and shall comply with the requirements of the Commission. Where the
treatment plant is situated in a building, access to the plant must be
secured.
The fence shall be 2.4 meter solid wall with three strands of 0.6 meter
high barbed wire. Typical details of the fence are given in Figure 6.5,
6.6, 6.7 and 6.8.
STP project proponent is required to provide adequate warning/safety
and the Commission signboard before handing over the sewerage system
to the Commission.

154

Volume 4

Malaysian Sewerage
Industry Guidelines

600

Sewerage Treatment Plants

Volume 4

Sewage Treatment Plants

Volume 4

INTERNAL

COLUMN @ 3m

CONCRETE

6"x6"

3 NOS. 2.5 DIA. BARBED WIRE

X
X

BRICKWALL FENCE

3000

X
X

63 x 63 x 6
THK. ANGLE

225

X X

150

225

M.S. POST

150 DIA. X 14.6 #

600 x 600 x 900 DEEP GRADE 20


MASS CONCRETE STUMP

3 THK. M.S. PLATE

4200

X
X

600 SQ.

X
X

2100

X
X

X
X

X
X

BRICKWALL FENCE

X
X

3 NOS. 2.5mm DIA. BARBED WIRE

Requirements for Ancillary Facilities


Requirements for Ancillary Facilities

Figure 6.5 Typical Drawing of Brickwall Fencing and Gate


Figure 6.5
Typical Drawing of Brickwall Fencing and Gate

900
150

2400

155

14 3

300

2200

MIN. 900

2T12

750

300

300

750

75

2T12

2T12

750

63 x 63 x 6mm M.S. ANGLE


WITH 3 STRANDS OF BARBED WIRE

750 x 750 x 230mm FOOTING

150 x 300mm GROUND BEAM

115mm THICK CEMENT / SAND


BRICKWALL WITH 20 PLASTERING
BOTH SIDES

100 x 125mm COPING BEAM

45

2T12

T12

R6-200

750 x 750 x 230mm


RC FOOTING

T12

T12

150

R6-200

T12

T12
T12

T12

R6-100

300

750

4T12 B/W

FINISHED GRD. LEVEL

SURFACE TO BE ROUGHENED

LINKS R6-150

4T12

TYPICAL RC COLUMN DETAIL

230

3.) NTERIOR/EXTERIOR WALL COLOUR STANDARDS - DULUX TUNGSTEN (10412) OR EQUIVALENT

2.) TWO BANDS OF IWK'S COLOUR WITH OVERALL HEIGHTS OF 400mm SHALL BE PAINTED ON EXTERIOR FACE OF THE WALL.

APPROVED WEATHER RESISTANT EMULSION PAINT.

1.) ALL EXPOSED WALL SHALL BE PAINTED WITH ONE UNDERCOAT OF APPROVED RESISTING PRIMER SEALER AND TWO COATS OF

PAINTING

7. PLASTERING AND RENDERING TO SURFACE OF BRICKWALL SHALL BE FINISHED TO A MINIMUM THICKNERS OF 20mm WITH 1:3 CEMENT-SAND NORTAR.

6. MORTAR FOR BRICKWORK SHALL BE SET IN 1:1:5 CEMENT-LIME-SAND MORTAR.

5. BRICKWORK WALLS SHALL BE ANCHORED TO CONCRETE FACES USING GALVANISED FISHTAIL A NCHORS TO LAP IN WITH THE BRICK REINFORCEMENT AT EVERY
FOURTH COURSE COMMENCING TWO COURSES ABOVE GROUND BEAM LEVEL.

4. BRICKWORK SHALL BE REINFORCED WITH EXPANDED METAL OR "EXMET" AT EVERY FOURTH COURSE COMMENCINGS TWO COURSES ABOVE GROUND BEAM LEVEL.

3. ALL BRICKS USED SHALL BE FIRST QUALITY CEMENT / SAND BRICKS.

2. MINIMUM COVER TO REINFORCEMENT SHALL BE 25mm.

230

SECTION C-C

T12

T12

FINISHED GRD. LEVEL

115mm THK BRICKWALL


PLASTERED ON BOTH SIDE

230 x 230mm RC COLUMN


AT 3.2m INTERVALS

50mm LEAN CONCRETE

2T12

2T12

SECTION B-B

750

300

1. ALL CONCRETE USED SHALL BE GRADE C25.

NOTES :

SECTION A-A

T12

125

2T12
115 x 300mm GROUND BEAM

R6-150

2T12

R6-200
100 x 125mm COPING BEAM

FRONT VIEW OF BRICKWALL FENCING

50mm LEAN CONCRETE

115 x 300mm GROUND BEAM

R6-150

R6-200
100 x 125mm COPING BEAM

TYPICAL CROSS SECTION OF BRICKWALL FENCING

3 STRANDS P.V.C. COATED BARBED


WIRE ATTACHED TO POST BY
HEAVY SPLIT PINS

230

2T12

100

2T12

800

2200

MIN. 900

Volume 4

230

230

800
2200
MIN. 900

156
230

3200

Requirements for Ancillary Facilities

Figure 6.6 Brickwall Fencing

Malaysian Sewerage
Industry Guidelines

800

Sewerage Treatment Plants

2200

Volume 4
800
PRE-CAST CONCRETE WALL
75mm THICK

T12

T12

FINISHED GRD. LEVEL

SURFACE TO BE ROUGHENED

LINKS R6-150

4T12

230

TYPICAL RC COLUMN DETAIL

45

300

2200

- GREEN

- DULUX GLOSS FINISH


(PANTONE 354C) OR EQUIVALENT

3.) COLOUR STANDARDS


A.) INTERIOR/EXTERIOR WALL
- DULUX TUNGSTEN (10412) OR EQUIVALENT
B.) BANDS - BLUE
- DULUX GLOSS FINISH
(PANTONE 300C) OR EQUIVALENT

PAINTING
1.) ALL EXPOSED WALL SHALL BE PAINTED WITH ONE UNDERCOAT OF APPROVED RESISTING
PRIMER SEALER AND TWO COATS OF APPROVED WEATHER RESISTANT EMULSION PAINT.
2.) TWO BANDS OF IWK'S COLOUR WITH OVERALL HEIGHTS
OF 400mm SHALL BE PAINTED ON EXTERIOR FACE OF THE WALL.

3. FOUNDATION AS PER THE DESIGN OF THE ENGINEER-IN-CHARGE.

1. ALL CONCRETE USED SHALL BE GRADE C25.


2. MINIMUM COVER TO REINFORCEMENT SHALL BE 25mm.

NOTES :

230

SECTION A-A

T12

230

PRE-CAST CONCRETE WALL


75mm THICK

63 x 63 x 6mm M.S. ANGLE


WITH 3 STRANDS OF BARBED WIRE

T12

R6-100 C/C

FINISHED GRD. LEVEL

PRE-CAST CONCRETE
WALL 75mm THICK

230 x 230mm
RC COLUMN
AT 3m INTERVALS
2200

TYPICAL CROSS SECTION OF PRE-CAST FENCING

75

FRONT VIEW OF PRE-CAST FENCING

3200

800

3 STRANDS P.V.C. COATED BARBED


WIRE ATTACHED TO POST BY
HEAVY SPLIT PINS

3200

Requirements for Ancillary Facilities

Figure 6.7 Precast Fencing

157

158

146

Volume 4

Volume 4

390mmx190mmx190mm BOND BEAM BLOCK

1 NO HORIZONTAL REINFORCEMENT

390mmx190mmx114mm FULL BLOCK

390mmx190mm190mm BOND BEAM BLOCK

1 NO. HORIZONTOL REINFORCEMENT

ANTI-CLIMB

ELEVATION

2. ALL MASONRY UNITS (CONCRETE BLOCKS) USED MUST BE UNDER


SIRIM CERTIFICATION SCHEME

- GREEN

B.) BANDS - BLUE

- DULUX TUNGSTEN (10412)

(PANTONE 354C) OR EQUIVALENT

- DULUX GLOSS FINISH

(PANTONE 300C) OR EQUIVALENT

- DULUX GLOSS FINISH OR EQUIVALENT

A.) INTERIOR/EXTERIOR WALL

3.) COLOUR STANDARDS

2.) TWO BANDS OF IWK'S COLOUR WITH OVERALL HEIGHTS


OF 400mm SHALL BE PAINTED ON EXTERIOR FACE OF THE WALL.

1.) ALL EXPOSED WALL SHALL BE PAINTED WITH ONE UNDERCOAT


OF APPROVED RESISTING PRIMER SEALER AND TWO COATS OF
APPROVED WEATHER RESISTANT EMULSION PAINT.

PAINTING

4. CEMENT MORTAR USED FOR JOINTS TO BE 1:3 MIX

3. CONCRETE MIX USED FOR GROUTING TO BE GRADE 20

390mm x 190mm x 190mm BOND BEAM BLOCK

1 NO HORIZONTAL REINFORCEMENT

390mmx190mmx190mm FULL BLOCK

390mmx190mmx190mm BOND BEAM BLOCK

63 x 63 x 6mm M.S. ANGLE


WITH 3 STRANDS OF BARBED WIRE

SECTION A-A

1. FOUNDATION AS PER THE DESIGN OF THE ENGINEER-IN-CHARGE

NOTE :-

SECTION B-B

3 STRANDS P.V.C. COATED BARBED- WIRE


ATTACHED TO POST BY
HEAVY SPLIT PINS

Requirements for
Requirements
for Ancillary
AncillaryFacilities
Facilities

Figure
6.86.8 Masonry
Masony
Fencing
Figure
Fencing

Malaysian Sewerage
Industry Guidelines
Malaysian Sewerage
Industry Guidelines

Requirements for Ancillary Facilities

6.7

Beautification Zone and Landscape


Treatment plants shall be effectively and visually screened by a
beautification zone within the treatment plant site of not less than
2 m wide, on which selected species of trees and shrubs can be planted.
In congested or difficult locations, the Commission should be consulted
on these requirements.
Premix or Paved area shall be provided at this zone for all class 1
treatment plants with loading equal or less than 1000 PE or where
necessary.

6.8

Stores and Workshops


All Class 4 Treatment plants that exceed 20 000 PE and have a pump
station within the premises shall be provided with an active store and
workshop.

6.9

Spares
All mechanical units shall be provided with an adequate reserve supply of
critical spare parts. A list of proposed spare parts should be forwarded
for approval when detailed designs are submitted for verification and
approval.
All parts recommended by the manufacturer to be provided with spares
shall be so delivered at the stage of final inspection. Notwithstanding
that, all parts with a life span of 3 years or less shall be provided with
spares
Typical spare parts requirements are provided in Table 6.2. Spare parts
shall be obtained from the original manufacturer of the equipment and
shall be packed and protected for storage to BS1133 requirement.
A set of special tools if required and specific to an equipment including
lifting tackle and greasing equipment necessary for the maintenance,
repair, testing and overhauled of the equipment shall be supplied together
with the spares at the stage of final inspection.

Sewerage Treatment Plants

Volume 4

159

Requirements for Ancillary Facilities

Table 6.2 Spare Part


No.

1.

2.

Pumps:
Raw Sewage
Submersible
Pumps.
Grit Pumps.
Feeding Pumps.
RAS Pumps.
Sludge Pumps.
Effluent Pumps.

Motors (Electric):

Drives
a)Direct Couple
b)Chain

c)Belt
Mechanically Raked
Screens

5.

Diaphragm Pump

6.
7.
8.

9.

10.

160

Equipment

Progressive Cavity
(Mono) Pump
Blowers

Spare Parts

Bearing
o-ring
oil seal
mechanical seal
wear ring
Impeller (for 3 or more
pump of similar model)
(see Pumps, Motors,
Drives)

one set
one set
one set
one set
one set
one set
one set, whichever parts is
relevant

Bearing
o-ring
oil seal
mechanical seal

one set
one set
one set
one set

gear bearing
chain
sprocket
V-belt
Chain
Chain link
Gear sprocket
(also see Motors,
Drives)
diaphragm

one set
one set
one set
one set
one set
one set
one set
one set, whichever parts is
relevant
one set

(see Motors, Drives)

one set, whichever parts is


relevant

rubber stator

Aerator:
Diffused Air
Diffusers
Mechanical (surface, (see Motors, Drives)
brush)
Scraper
rotating collectors
wheel
(see Motors, Drives)
Conveyor

Quantity

(see Motors, Drives)

Volume 4

one set

10% of total numbers


one set, whichever parts is
relevant
one set
one set per clarifier
one set, whichever parts is
relevant
one set, whichever parts is
relevant

Malaysian Sewerage
Industry Guidelines

Requirements for Ancillary Facilities

Table 6.2 Spare Part (continued)

6.10

Yard Lighting

No.

Equipment

Spare Parts

Quantity

11.

Filter Press

oil seal for hydraulic


pump
membrane cloth

one set
one pair out of every five
pair of plates

12.

Belt Press

oil seal for hydraulic


pump
Belt

one set
one set if the STP has only
one press

13.

Centrifuges

(see Drives)

one set, whichever parts is


relevant

6.10

Yard Lighting

Effective yard and building lighting systems shall be incorporated within


the treatment plant site in order to provide sufficient illumination for
operation and maintenance schedules to be carried out during day and
night periods. In addition, the entire treatment plant site shall have
sufficient street lights and perimeter lights for various operations, safety
and security reasons.

Compound lighting shall be provided at every 50 m interval for all


manned and security plants. However, sufficient lighting is required at
the strategic location such as entrance gate, inlet works and necessary
areas. Refer to Table 6.3.

All lighting shall be accessible for maintenance / removal. Typical details


of compound lighting are shown in Figure 6.9.

Table 6.3 Numbers of Unit and Location of Compound Lighting


Class of
STP

Population
Equivalent

Minimum
Numbers
of Unit

1 000

1001 5000

5 001 20 000

> 20 000

Sewerage Treatment Plants

4
50 meter

Volume 4

Location

Inlet Works or Entrance


Inlet Works and Treatment Process
Unit
Every Internal Corner of STP boundry
and nearby to Inlet Works, Treatment
Process Unit and Sludge Treatment
Entrance, Inlet Works, Mess Building,
Process Treatment Unit, Secondary
Treatment Unit and Sludge Treatment.
161

Requirements
for Ancillary
Facilities Facilities
Requirements
for Ancillary

Figure 6.9 Typical Details of Compound Lighting


Figure 6.9 Typical Details of Compound Lighting

250

290

6000

105

105

670

STANDARD GALVANISED
STREET LAMP POST

FRONT VIEW

SIDE VIEW

LAMP POST

6.11

6.12

6.11

Sampling Facilities
Sampling Facilities

Suitable sampling facilities shall be provided (preferably in the form of


Suitable
sampling
facilities
shallthe
be boundary
provided (preferably
form
of an
an open
chamber)
within
of the STP in
to the
allow
representative
open samples
chamber)towithin
the boundary
theperson.
STP toFor
allow
representative
be taken
safely by ofone
treatment
plants up to
samples
to
be
taken
safely
by
one
person.
For
treatment
plants up
to
20 000 PE, sufficient space shall be allowed for proper
preparation
20,000of PE,
sufficient
proper preparation
samples
to bespace
takenshall
awaybetoallowed
central for
laboratories
for furtheroftesting
samples
to
be
taken
away
to
central
laboratories
for
further
testing
and space
and analysis. The sampling area shall contain sufficient
bench
analysis.
sampling
contain
bench
space
and than
and The
storage
spacearea
for shall
samples.
Forsufficient
treatment
plants
greater
storage
space
for
samples.
For
treatment
plants
greater
than
20,000
PE,
20 000 PE, the sampling area shall be provided in accordance the
with MS
sampling
shall ladder
be provided
withsampling
MS 1228.
Access where
1228.area
Access
shall in
be accordance
provided for
facilities
ladder shall be provided for sampling facilities where necessary. Internal
necessary. Internal surface area for sampling point shall be tiled with
surface area for sampling point shall be tiled with clear coloured tiles
clear coloured tiles

6.12

Auto Restart Facilities


Auto Restart Facilities
All electrical equipment shall be fitted with auto restart facilities for quick
All electrical
equipment
be fitted
with auto restart facilities for
re-operation
in the event
of failureshall
of power
facilities.
quick re-operation in the event of failure of power facilities.

162

150

Volume 4

Volume 4

Malaysian Sewerage
Industry Guidelines
Malaysian Sewerage
Industry Guidelines

Requirements for Ancillary Facilities

6.13

Safety Facilities
Safe access and walkways shall be provided at all process units and
equipment (valves, penstocks, aeration tanks, etc.) that require service
and maintenance. Safety handrails shall also be installed at walkways
and other working areas with a fall greater than 2 m. Typical details
of hand rail are shown in Figure 6.10
All chemical storage facilities shall be provided with a safety shower
and eyewash as well as appropriate warning signs. Liquid chemical
storage facilities shall be bund. Access to the area shall be restricted
using lockable doors/gates.
Provision for fire detection, alarm and fire fighting equipment shall
be complying with the latest requirements in the Uniform Building
Bylaws, the Institute of Electrical Engineers (IEE) guidelines and other
statutory requirements.
All tanks shall not exceed 1.2 m above ground.
Stair case and ladder exceeding 1.2 m shall be provided with
handrail
All plants located adjacent to earth slopes shall be provided with proper
slope protection structures. The slope protection design must be certified
by Qualified Professional Engineer.

6.14

Doors
All external doors shall be of weather proof and suitable for out-door
installation.
Door with sufficient width for the manoeuvre of equipment shall be
provided at the building of pump station, blower room, etc. For opening
more than 4 m wide or 5 m high, motorized roller shutter shall be
provided complete with manual over-ride button, which enables it to
be operated during power interruption.

6.15

Fire Hydrant
For treatment plants above 20 000PE, fire hydrant shall be provided
complying with the requirements of Jabatan Bomba.

Sewerage Treatment Plants

Volume 4

163

Requirements for Ancillary Facilities

6.16

Power Supply
Power supply shall be provided to each plant from the approved
source. Drawings submitted for approval shall indicate the locations of
electrical power tapping point and schematic layout plan. Approval for
power supply tapping should be obtained from relevant authority for
permanent power supply before submitting inspection form. All related
document, such as electrical bills, transfer of ownership: to be submitted
before final inspection. Requirement of power shall be finalised prior
to obtaining design approval
Requirement of incoming permanent power supply shall be inline with
Section 4 this Volume.

6.17

Internal Sanitation (Toilet)


All plants shall be provided with toilet. The toilet shall consist of water
tap, water closet, shower and wash basin. The area for toilet shall
comply with Uniform Building By Laws. Toilet to be located beside
the control panel building. Toilets can also be located in the mess or
office building.

6.18

Lifting Requirement
Safe lifting weight in unrestricted area is 16 kg. For heavier objects and/
or very tight locations, provision of crane or access for truck mounted
crane to be made.
Lifting requirements are as follows:
-
-

164

Weight < 16 kg:


Manual lifting
16 kg Weight 250 kg: A davit or A frame shall be arranged
to allow items lifted by using manual
chain hoist to be projected on a 1.2
m truck tray and positioned at 2 m
above road level. In the pump station,
motorized hoist is required for lifting
weight exceeding 100 kg.
Weight > 250 kg:
A gantry with motorised hoist shall
be arranged to allow items to be
projected on a 1.2 m truck tray and
positioned at 2 m above road level
truck tray.
Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Ancillary Facilities

Lifting equipment shall be subjected to DOSH approval standards and


guidelines.
Safe Working Load with approved method of installation shall be rated
and printed for all lifting facilities. Height and lifting method must be
considered in the design for Safe Working Load of lifting facilities.
All portable motorised hoist shall be of 230 V operating voltage and fixed
electrical hoist shall be of 415 V operating voltage.

All fixed 3 axis type gantry shall come with additional safety features
such as travel stop limit switch, hoist over run limit switch, slow &
fast speed mode and emergency stop (for all type of hoist).
All fixed type outdoor lifting facility futures shall comprise of hoist
parking bay with shade. All fixed type lifting facility shall come with
working platform and excess ladder.
Typical drawings of lifting davits and A-frame lifting facilities are
shown in Figure 6.11 and Figure 6.12.

6.19

Ventilation
Ventilation is the process of letting in outside air into a space so that it
mixes with the inside atmosphere to dilute contaminants and replenish
oxygen. The purpose of ventilation in a sewage treatment plant is
to provide a comfortable and safe working environment for all plant
personnel.
Hence proper ventilation shall be provided as a mean of providing
sufficient fresh air and reducing poisonous or explosive gases in enclosed
or semi-enclosed spaces where access to human is allowed. Ventilation
can be achieved naturally or mechanically:

Natural ventilation uses the force of nature such as air currents,


breezes, thermal gradients and pressure differences to move air
in and out of the space.

Mechanical ventilation uses fans and blowers to force air


through space. It is also sometimes called forced ventilation.

Particular requirements are:


a)

Ventilation shall be intrinsically safe with respect to explosive


gases (such as methane) where such gases may be present.

b)

Ventilation shall be designed to deal with the different densities


of the various gases.

Sewerage Treatment Plants

Volume 4

165

Requirements for Ancillary Facilities

c)

d)
e)
f)
g)
h)
i)
j)

166

Ventilation fans shall be located outside the enclosed space to


induce forced air into the plant. Intake locations shall be such
that only fresh air is drawn into the system and not air recirculated
from the exhaust.
Mechanical ventilation shall be used if the system is required to
remove contaminants.
Ventilation exhaust shall be directed to a suitable location for
discharge and it shall not be adjacent to the intake point.

Ventilation at rooms where heat generation may take place must


be adequate to dissipate the heat generated to ensure a comfortable
making ambient for the equipment and the operator.
Noise levels associated with operating fans and blowers, particularly
in a confined space, shall conform to the requirements in Section
4 of this Guidelines and other stationary requirements.
Optimise recurring cost for operation, maintenance and
replacement.
Regular testing and inspection of the equipment

Compliance with the suggested ventilation requirements. Table6.4


presents some commonly used values for ventilation rates in typical
enclosed spaces of a sewage treatment plant: -

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Ancillary Facilities

Table 6.4
Space

Common ventilation rates

Minimum Ventilation Rate


(Air Changes/hour, ac/hr)

Remarks

Wet-Well

30 intermittent
12 continuous

Dry-Well

30 intermittent
12 continuous

Grit Removal/
Screen Area

30 intermittent
12 continuous

Same as wet well

Digester Gas
Control Room

30 intermittent

Same as wet well

Sludge Gas
Compressor Room

30 intermittent

Same as wet well

Enclosed Grit
Loading Areas

30 intermittent

Same as wet well

Enclosed Primary
Sedimentation Tanks

30 intermittent

Same as wet well

Scum Concentration
Tank

30 intermittent

Same as wet well

Chlorine and
Sulphur Dioxide
Rooms

60 intermittent

Hazardous areas, toxic fumes,


floor level exhaust required.
Interlock fans with manual
switches located at each
entrance. Also interlock fans
with chlorine and sulphur
dioxide detection. Use 100%
outside air

Filter/Dewatering
Area

12 continuous

Consider odour control for


exhaust air from dewatering
area, where warranted

All other enclosed


unit processes not
mentionedelsewhere

30 intermittent

In particular at blower room,


high tension room, low voltage
room, switchboard and control
panel rooms, where there are
tendency of heat generation

Sewerage Treatment Plants

12 continuous
12 continuous
12 continuous
12 continuous
12 continuous
12 continuous

12 continuous

Volume 4

Use 100% outside air. Step up


to 24 ac/hr if hazardous gases
are detected. Consider odour
control, where warranted

167

Requirements for Ancillary Facilities

k)
l)
m)

6.20

An audible and visible warning shall be provided at all entry


points. This shall automatically operate if the fan fails.
Where natural or forced ventilation is provided, it shall be
installed in such a manner so as to avoid any ingress of water
due to rain or other sources.

In areas with routine entry by personnel, the ventilation strategy


shall emphasize adequate control of contaminants and the
ventilation system shall be continuously operated.

Process Water
The designer is encouraged to provide recycle water facilities from
the treated effluent. The recycle water can be utilised for cleaning and
landscaping purposes.

6.21

Aesthetic
The structure of a treatment plant shall blend with the surrounding
development to improve the aesthetic value of the area. Roof, structure
wall or brickwall fancing can be designed with other than conventional
finishing.

6.22

Close Turfing
Unpaved area within the STP reserve shall be turfed with close turfing.
The type of grass must be cow grass. For slope area, turf must be
pegged to avoid grass wash away during water run-off.

6.23

Standard Roofing and related requirement


Roof for control panel shall be of flat roof and shall be installed with
water proving material on the final layer. The slope of flat roof shall
be 1: 20 and gutter shall be provided.
However, for the aesthetic purpose Pitch type roof may be provided.
The slope shall be 30 degree from horizontal. Suitable material for roof
such as roof tile is recommended.
The design of roof shall be considered from the following:
i)
ii)

Suitable material for roof (flat or slope) including colour


Adequate air for ventilations

iii) Enough heights for lifting facilities

168

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Ancillary Facilities

iv) Enough heights for access and headroom


v)

Type of insulation

vi) Acoustic treatment where applicable

6.24

Painting
Painting shall include all plant and machinery inside buildings, including
pipework, grating, handrailing, internal walls below ground level and
all metal work including machinery.
The conduits and piping shall be appropriately named and labelled
indicating flow directions and painted with the following colour codes
for easy identification:
Chlorine line

yellow with double green bands

Fuel gas line

orange

Compressed air line

Potable water supply line


Raw sewage line

Final effluent line


Sludge line

Non-potable water line

Other disinfectant lines


Biogas line

-
-

-
-

green
blue

black
grey

brown

blue with double black bands

yellow with double red bands


yellow

The labels shall be stencilled on the piping in a contrasting colour with


the colour coded bands, if any, located at appropriate and strategic
points.
Colour codes selected for general equipment, building and others items
in a sewage treatment plants shall be adhered to colour standards as
detailed in Table 6.5. The types of paint and surface preparation used
shall be as recommended by the paint manufacturer.

Sewerage Treatment Plants

Volume 4

169

Requirements for Ancillary Facilities

Table 6.5 Painting System Index Colour Standards


Item

Colour

Equivalent Colour
Guide

General Equipment including motors


Dark Blue
(unless come with the original manufacturer
approved colour code)

Dulux Regal Blue


0013

Penstocks/Valves/Manhole Covers

Black

Par Bituminous Black

Machinery Guards/Railings/Runways/
Overhead Cranes/Lifting Davit

Yellow

Dulux Lemon 2024

Switchboards

Light Grey

Par Mandarin Blue


0013

Par Golden Yellow


Dulux Pewter 695
Par Willow Grey
00A05

Fencing poles/Gates

Green

Dulux A365-13449
Par Green 3666

Building and Walls Exterior

Grey
(Weathersheild)

Dulux BS 00A0510235

Building and Walls - Interior

White

Fencewall Interior and Exterior

Grey

Dulux BS 00A0510235

Floors - Concrete Interior

Green

Leigh Green 3666

Building Stripes

Green

Dulux A910-13448
Par Green 3666

Blue

Dulux A910-11482
Par Blue 2686

Indah Water Logo (where applicable)

Indah Water
Green

Dulux A365-13449
Par Green 1006

Indah Water
Blue

Dulux A365-11483
Par Blue 1007

Notes:
The above painting requirements are not applicable to stainless steel, aluminium,
galvanised metal surfaces except where necessary to comply with statutory health
and safety requirement.

170

Volume 4

Malaysian Sewerage
Industry Guidelines

Requirements for Ancillary Facilities


Requirements for Ancillary Facilities

Figure 6.10 Typical Detail of Guard Rail

Typical Details og Guard Rail

550

Figure 6.10

1100

21/4

150-250

100

33

SIDE PALM BASE


TYPICAL RUN OF HANDRAIL AS
VIEWED FROM WALKWAY SIDE
FLAT BASE

550

TUBULAR STANDARDS

1100

1
21/4

150-250

100

12

TYPICAL RUN OF HANDRAIL AS

100

36

TRIANGULAR BASE

VIEWED FROM WALKWAY SIDE


ROUND BASE
TUBULAR STANDARDS

3000 C/C

550

1100

550

3000 C/C

DETAIL OF HOT DIPPED G.I. RAILING

Sewage Treatment Plants

Sewerage Treatment Plants

Volume 4

Volume 4

159

171

Requirements for Ancillary Facilities


Requirements for Ancillary Facilities

Figure 6.11 Typical Detail of Lifting Davit


6.11 : Typical Detail of Lifting Davit
50

90

50

75

Requirements for Ancillary Facilities

25
25

25

20

20

FL

FL

30

450

6.11 : Typical Detail of Lifting Davit

30

120

10

6 FILLET WELDED
50

OD=98

0
90
PLAT THICKNESS 10
75

SAFE WORKING
LOAD TO BE
INDICATED

50

25

260

250

1775

25

30

25

20

20

FL

30

450

FL

120
DETAIL `A'

10

6 FILLET WELDED
OD = 118
OD=98

SAFE WORKING
LOAD TO BE
INDICATED

DETAIL `A'

PLAT THICKNESS 10

SECTION
LIFTING DAVIT

250

1775

260

SIDE VIEW
LIFTING DAVIT

NOTE : DEPTH OF SLEEVE SHALL VARIOUS WITH HEIGHT OF POLE ACCORDINGLY

DETAIL `A'

Figure 6.12 : Typical DetailDETAIL


of A`A'Frame Lifting Facilities

OD = 118

SECTION
LIFTING DAVIT

SIDE VIEW
LIFTING DAVIT
2160

1200

1800

203x203x46Kg/m UB

NOTE : DEPTH OF SLEEVE SHALL VARIOUS WITH HEIGHT OF POLE ACCORDINGLY


180

Figure 6.12 Typical Detail of A-Frame Lifting Facilities


315

203x133x25Kg/m UB

203x133x
25Kg/m UB

2340

2160
1800

203x203x46Kg/m UB

180

1200

2340

Figure 6.12 : Typical Detail of A Frame Lifting Facilities

315

203x133x25Kg/m UB

203x133x
25Kg/m UB
300x300x12 PLATE BOLTED TO CONCRETE

300x300x12 PLATE BOLTED TO CONCRETE

1500
TO PROVIDE WITH ROLLER OR FIX TO THE CONCRETE
FLOOR (TO SYSTEM SUPPLIER DESIGN)

2340

2340

TO PROVIDE WITH ROLLER OR FIX TO THE CONCRETE


FLOOR (TO SYSTEM SUPPLIER DESIGN)

SIDE VIEW

FRONT VIEW
A-FRAME WITH I-BEAM

A-FRAME WITH I-BEAM

300x300x12 PLATE BOLTED TO CONCRETE

300x300x12 PLATE BOLTED TO CONCRETE

1500
TO PROVIDE WITH ROLLER OR FIX TO THE CONCRETE
FLOOR (TO SYSTEM SUPPLIER DESIGN)

TO PROVIDE WITH ROLLER OR FIX TO THE CONCRETE


FLOOR (TO SYSTEM SUPPLIER DESIGN)

FRONT VIEW

SIDE VIEW

A-FRAME WITH I-BEAM

A-FRAME WITH I-BEAM

160

172

160

Volume 4

Volume 4

Volume 4

Malaysian Sewerage
Industry Guidelines

Malaysian Sewerage
Industry Guidelines

Malaysian Sewerage

Section 7
Special Requirements

Special Requirements

174

Volume 4

Malaysian Sewerage
Industry Guidelines

Special Requirements

7.1

Temporary Treatment Plants

7.1.1

Definition

Temporary treatment plants refer to STP that are built to operate on a


temporary basis. The sewage will eventually be diverted to a centralised
sewerage system. After then, the temporary treatment plant will be
decommissioned.

There are 2 categories of temporary treatment plants:

Category 1
For temporary treatment of sewage during the upgrading of an existing
sewerage treatment facility

Category 2
For temporary treatment of sewage during initial stage of a new housing
development where it is not feasible to construct a plant of ultimate
capacity during initial stage or it is located within the catchment of a
centralised sewerage system.

7.1.2

Category 1: Temporary Treatment Plant for Upgrading of


Facilities

During the upgrading of an existing treatment plant, the sewage flows into
that plant shall be directed to a temporary treatment plant for treatment
before discharge. The treatment process of the temporary plant shall
be designed and calculated based on: the duration of the project, total
existing flow and the compliance requirements. The temporary treatment
shall be monitored at regular interval. Approval from the Commission
and DOE must be obtained prior any direct discharge of the untreated
sewage into the receiving watercourse. The temporary treatment plant
shall be located within the compound of the existing site. The temporary
treatment plant shall not be built on other site area unless approval is
granted by the Commission

7.1.2.1

Compliance Standards for Category 1 Temporary Treatment


Plants

Category 1 temporary treatment plant shall comply with the requirements


as stipulated in this Guideline and shall be operated and maintained
to the satisfaction of the Commission and the Director General of the
Department of Environment (DOE) at all times.

The temporary treatment plant shall be designed to comply with the


following minimum effluent requirements:

Sewage Treatment Plants

Volume 4

175

Special Requirements

a)

b)

Standard B for STP located downstream of water intake points


and non-water catchment zones
Standard A for STP located upstream of water intake points

The above levels shall be interpreted as absolute pollutant levels.


Final effluents will be monitored over the life of the temporary plant.
A license to contravene shall be obtained before the construction of any
temporary plant and the commencement of any upgrading works.
The temporary plant shall incorporate provisions to minimize adverse impacts
such as visual, noise, odour nuisance etc. to the surroundings.
7.1.2.2

Process Requirements for Temporary Treatment Plants


Alternative or innovative designs may be used for temporary plant to
meet the general design compliance as stipulated above.
Unit processes within the temporary treatment plant can be designed
to absolute standards. For example, a Standard A the effluent level of
temporary treatment plant of this category can be designed to 20 mg/l
BOD and 50 mg/l SS.
Materials for construction can be of semi-permanent installation such
as fiberglass tanks, mild-steel with epoxy coat, etc.

7.1.2.3

Operation of Temporary Treatment Plants


During the upgrading of an existing plant, the project proponent shall
appoint a class license to operate and maintain the temporary plant. If
the upgrading contractor is a licensed operator, they may be appointed
as the operator of the temporary plant.

7.1.3

Category 2: Temporary Plants for New Housing Development


I)

176

Multiple Phases Hosing Development

Temporary plant shall be provided for multiple phases housing


development where it is not feasible to construct a plant with ultimate
capacity during initial stage.

STP reserves must be located as far as practicable from habitable


buildings. The needs of a temporary plant in a multiple phases housing
development project depend on phases of development, size of each
development phase, location of initial development and duration of the
phase lag and entire development plan.

Volume 4

Malaysian Sewerage
Industry Guidelines

Special Requirements

The project proponent will construct a temporary treatment plant in


compliance with the following criteria:a)

b)
c)

(II)

Temporary plant will be decommissioned by the developer within


time frame agreed between the Commission and the developer.
Implementation program for ultimate plant is confirmed in
accordance to an approved catchment study.

All temporary plant shall remain as private plant and shall be


operated and maintained by a licensed operator appointed by the
project proponent.
Future Connection to Centralised STP

This applies to a catchment where implementation program to construct


a centralised STP is approved but the completion date could not meet
the project proponents needs. Under such circumstances, the project
proponent may be allowed to build a temporary treatment plant.
7.1.3.1

Provision of Land for Temporary Treatment Plants


The owner will be required to allocate land within the housing
development for the construction of all temporary works. However,
the site of the temporary treatment plant shall not be located on future
public amenities land.
The project proponent of the temporary treatment plant will be required
to construct the temporary sewer reticulation within the development to
convey sewage to the temporary treatment plant. At the same time, the
project proponent must also construct the permanent sewer reticulation
for the connection to the permanent plants or the centralised sewerage
system.

7.1.3.2

Compliance Standards for Temporary Treatment Plants


This category of temporary treatment plant shall comply with the
requirements as stipulated in this Guideline. The plant shall also be
maintained to the satisfaction of the Commission and the Director
General of the Department of Environment (DOE) at all times.
The temporary treatment plant shall be designed and maintained to
comply with the following minimum effluent requirements:
a)
b)

Standard B for STP located downstream of water intake points


and non-water catchment zones.
Standard A for STP located upstream of water intake points.

Sewage Treatment Plants

Volume 4

177

Special Requirements

7.1.3.3

Process Requirements for Temporary Treatment Plants


Temporary treatment plants shall be designed to the requirements set
out in Sections 3, 4 and 6 of this volume.
An alternative design may be considered for the temporary treatment
plant that will be decommissioned within time frame agreed between
the Commission and the developers.
Materials for construction can be of semi-permanent installation such
as fiberglass tanks, mild-steel with epoxy coat, etc.
Filter systems may use refurbished filter material that meet the relevant
standards. However, other equipment used within the works shall be
new. Second-hand equipment is strictly prohibited.

7.1.3.4

Operation of Temporary Treatment Plants


Temporary plant shall remain as private plant. The owner must appoint
a licensed operator to operate and maintain the plant.
Temporary treatment plants shall strictly comply to the requirements as
stipulated by this Guideline and shall be operated to the satisfaction of
the Commission and the Director General of DOE at all times.
Temporary treatment plants shall be designed and constructed so as
not to present any nuisance in terms of odour, noise, safety and visual
impact to the nearby community.

7.1.3.5

Ancillary Requirement of Temporary Treatment Plants


Temporary treatment plants shall be provided with proper security
fencing in compliance with Section 6 of this Volume.
Adequate access roads and drainage shall be provided.
Landscaping of treatment plant shall be provided for better aesthetic
value surrounding the plant.

178

Volume 4

Malaysian Sewerage
Industry Guidelines

Special Requirements

7.2

Treatment Plants Located Within Buildings

7.2.1

Introduction
The installation of treatment facilities within buildings whether occupied
or not, including basements of buildings, are not desirable and will
not normally approve. Every effort must be made to come up with an
alternative site or an arrangement to connect to a public system.
Owners must resolve these issues at an early stage of the planning
process. The Commission should be contacted early to establish if an
alternative option is feasible.
If approved, such installations will be subjected to stringent service
condition requirements for the following criteria:
a)

Access

c)

Electrical requirements for lighting system

b)
d)
e)
f)

g)
h)
i)
j)

Ventilation
Noise control
Process type
Inlet works

Pre-treatment
Confined space safety
Odour Control

Discharge systems

k)

Flood mitigation measures

m)

General safety and health

l)

Operation and maintenance

n)

Sludge handling

o)

Sanitary and plumbing facilities

p)

Fire Fighting Equipment

Treatment plants within buildings will be considered as private treatment


plants subject to eventual phasing out and replacement by a centralised
system.

Sewage Treatment Plants

Volume 4

179

Special Requirements

7.2.2

Specific Guidelines and Requirements


The specific guidelines and requirements for the criteria specified in
7.2.1 are listed below.
I)

Access

a)

Vehicle access must be provided from the nearest public


highway.

b)
c)

d)

Parking space for a desludging and service vehicle must be


within operating range.
Access must be continuously available and unobstructed.
Accessible to water and electricity supplies.

e)

Sampling point to be available for final effluent.

g)

Provision must be made for lifting of heavy equipment.

f)

h)
II)

Allowance must be made for installation and removal of


equipment.
Suitable arrangements must be made for service and repair of
equipment.
Ventilation

Ventilation design shall be in compliance with the requirements in


Section 6 and the specific requirements listed below:
a)
b)
c)

180

Suitable system must be provided to address poisonous, explosive


and lack of oxygen conditions.
Separate and independent (from the basement) ventilation must
be provided for the confined spaces.
Ventilation shall be of forced mechanical type.

d)

Ventilation must be intrinsically safe with respect to explosive


gases such as methane.

e)

Ventilation must be designed to deal with the different densities


of the various gases.

f)

Ventilation fan must be located outside the enclosed space to


induce forced air into the plant. Intake locations shall be such
that only fresh air from outside the building id drawn into the
system and not air re0circulated within the building.

g)

Ventilation exhaust must be directed outside the building for


discharge.
Volume 4

Malaysian Sewerage
Industry Guidelines

Special Requirements

h)

Ventilation air exchanges shall be as follows:

Intermittent: Minimum of 30 complete air changes per


hour
ii) Continuous: Minimum of 12 complete air changes per
hour
A backup fan must be provided in the event of duty fan failure
and must be automatic on entry.
i)

i)
j)

A petrol driven generator with an auto restart facility must be


provided to continually operate the ventilation system in the event
of power failure.

III)

Electrical Requirements for Lighting System

a)

Only high-intensity, low-voltage discharge lamps to be used for


floodlighting of plant area during operation and maintenance.

b)
c)
d)
e)

The lighting and electrical equipment must be both vapour and


explosion proof.

A separate housing must be provided for electrical controls to


prevent electrical sparks from coming into contact with flammable
and explosive gases.
All electrical equipment must be water proof against
submersion.

Standby generators must be provided to allow the plant to operate


independently of the mains supply.

IV)

Noise Control

a)

Adequate dampening of noise must be provided to meet minimum


stipulated requirements by the local Building By-laws, DOE and/
or other regulatory bodies. Silencers and acoustic enclosures shall
be provided where required to achieve the stipulated noise level
reduction.

b)
c)

d)

Noise control measures shall be implemented to control the


generated noise level to below 65 dB at a distance of 2 m from
the boundary of the housed noise source.

General noise levels (measured in decibel units) must also be


measured 10 m from any point of the plant site within the nearest
public space or occupied space or both to an acceptable level
stipulated by the regulator.
Enclosures used to achieve these noise reductions shall permit
ready access to equipment for routine maintenance. Adequate air
ventilation shall be provided to allow cooling of the air inside
the enclosure to prevent over heating of the equipment/motors.

Sewage Treatment Plants

Volume 4

181

Special Requirements

V)

Process Type

The type of treatment process must be limited to systems that are easy
to operate and maintain for reasons of:
a)
b)

lower sludge yield and more stable sludge characteristics


lower operational and maintenance requirements

VI)

Inlet Works

The design shall incorporate some means of controlling the influent


velocity to prevent:
a)
b)
c)
d)

excessive wear due to scouring effects


excessive head loss in the inlet
uncontrolled overflow of raw sewage
release of sewer gases

VII)

Pre-treatment

a)

The design must include a macerator to


i)
ii)

b)
c)

reduce toilet waste and large solids into smaller and finer
particles,
reduce the quantity of screenings

iii) improve the ease of handling.

Screening must be provided at 10 to 12 mm clear spacing to


remove fine particles.
A combined grit and grease removal system must be provided.

VIII) Confined Space Safety


a)

Operators must:
i)
ii)

b)
c)
d)

182

attend a recognised confined spaces training course,


obtain training certificates, and

iii) be certified competent to operate in such an environment.

Confined space areas within the plant site must be clearly


identified before handover for operation.
Confined space areas must be demarcated and warning notices
placed.
Confined space procedures must be established and followed by
operatives.

Volume 4

Malaysian Sewerage
Industry Guidelines

Special Requirements

e)

The following must be provided:


i)
ii)

f)

gas detection equipment, preferably electronic, and serviced


regularly

The design of the treatment plant shall be subject to a Hazard


and Operability Review (HAZOP) exercise to identify and reduce
the potential risks under the following scenarios:
i)
ii)
iii)
iv)
v)

g)

rescue sets of breathing apparatus

electrical failure

blockage of inlet and outlet

equipment failure including lighting and ventilation


blockage of any pipework

flooding of external discharge point

vi)

failure of building drainage system

i)

flooding

The consequences of such failures to operators may include:


ii)
iii)
iv)
v)
vi)
vii)

explosion
drowning

falling into open voids


asphyxia
poison

nausea

IX)

Odour Control

a)

Isolate odorous gases from general ventilation exhausts by


containing identified odour generating sources with a separate
local exhaust system.

b)

Containment of the odour sources shall be by installing lightweight


and corrosion resistant covers/enclosures designed for practical
operation and maintenance works.

c)
d)
e)

The local exhaust odorous air shall be conveyed through well


designed and balanced ductworks by a centrifugal fan to an
effective odour treatment equipment.
Odour treatment equipment shall be selected such that odours
be reduced to the lowest possible level and in compliance with
the EQA.
The potential of odour generation, its impact and treatment, shall
be considered in all aspects of design.

Sewage Treatment Plants

Volume 4

183

Special Requirements

X)

Discharge Systems

Most basement plants will lie below the level of the running drain
levels. Therefore, it is essential to:
a)
provide an effluent collecting sump prior to pumped discharge.
b)
provide a check valve at the end of the discharge pipe to prevent
the backflow from the monsoon drain to the treatment plant.
c)
provide a 100% redundancy of the discharge pumping
capacity.
XI)

Flood Mitigation Measures

a)

Provision must be made for the isolation of the treatment plant


from flooding by external sources.

b)

A sump pump shall be provided.

XII)

Operation and Maintenance Agreements

a)

All treatment plants installed in basements of buildings must be


subject to an Operation and Maintenance Agreement. An example
of the standard Operation and Maintenance Agreement is given
in MSIG Volume 2.

b)

All treatment plants located within buildings must be operated by


a fully licensed operator and will be subject to periodic checks
by the Commission to ensure compliance.

XIII) Occupational Safety and Health


a)

All treatment plants shall be designed to comply with the


Occupational Safety and Health Act, 1994. Properly designed
treatment plants will enable the operator to safely handle the
treatment plant throughout its design life. A brief summary of
the contents of Act 514 is attached in Appendix A.

XIV) Sludge Handling


a)
b)

c)

184

An aerated sludge holding tank shall be provided to keep the


sludge from going septic

Permanent pipe work with proper coupling and isolation valve


should be provided adjacent to the access gate for easy coupling
sludge tankers hose of hose for during desludging of the sludge
holding tank.
To provide sludge pump for desludging purpose.

Volume 4

Malaysian Sewerage
Industry Guidelines

Special Requirements

XV)
a)

Sanitary and Plumbing facilities


To provide stand pipe for cleaning purposes. Waste water to be
channelled back to the inlet of plant.

XVI) Fire fighting system


a)

To provide appropriate fire fighting systems in accordance to


Fire Department and other statutory requirements.

7.3

Fully Enclosed Treatment Plant

7.3.1

Definition
A fully enclosed plant is defined as a treatment plant that is designed
such that their treatment unit processes are located within dedicated
buildings.
A fully enclosed plant is to be equipped with additional features
and requirements to minimize adverse impact to the surrounding
environment.
Fully enclosed treatment plant shall comply with the following
criteria:
a)
b)
c)
d)
e)

Must be located within a dedicated sewage treatment site.


Provide with appropriate architectural enclosures building.
No unit processes shall be located outside the enclosed buildings/
architectural enclosures.
Individual treatment unit process may be covered with a permanent
structure or housed in an enclosed building.
Provide appropriate landscaping to adequately screen the treatment
plant from other developments in the vicinity.

Appropriate architecture style, landscaping, architecture surrounding


the treatment plant and fencing type must be used.
7.3.2

General Requirements
When approved, fully enclosed treatment plants must comply with the
general requirements set out in Section 3, 4 and 5 of this Volume and
also specific requirements in this Section 7.3 for the following:
i)
ii)

Provision of odour control


Noise control and mitigation measures

Sewage Treatment Plants

Volume 4

185

Special Requirements

iii)

Minimize visual impact

v)

Enhance safety, health and operability

iv)

I)

Avoid aerosol effects

Odour Control

The potential for odour generation, its impact and treatment, shall be
considered in all aspects of design.
The range of odorous constituents in such biogenic odours is very
wide and they include: hydrogen sulphide, ammonia, thiols and other
organic sulfur compounds, amines, indole and skatole, volatile fatty
acids and a wide range of organic compounds produced by anaerobic
fermentation.

Particular problems can be found at: Inlet works, primary tanks,


secondary treatment, sites for transfer, storage and treatment of raw
sludges and leakages.
A separate local exhaust system, for containment and exhaust of odorous
air to treatment, will isolate such odours from the general ventilation
system.

Odour treatment equipment shall be selected such that odour is reduced


to the lowest possible level and in compliance with the EQA.

Containment, exhaust and treatment shall be designed as an integrated


package.

II)

Noise Control

Adequate dampening of noise must be provided to meet minimum


stipulated requirements by the local Building By-laws, DOE and/or other
regulatory bodies. Silencers and acoustic enclosures shall be provided
required to achieve the stipulated noise level reduction.
Noise control measures shall be implemented to control the generated
noise level to below 65 dB at a distance of 2 m from the boundary of
the housed noise source.
The general noise levels generated shall also be measured 10 m from any
point of the plant site within the nearest public space and/or occupied
space to an acceptable level stipulated by the appropriate regulators.
Enclosures used to achieve these noise reductions shall permit ready
access to equipment for routine maintenance. Adequate air ventilation
shall be provided to allow cooling of the air inside the enclosure to
prevent over heating of the equipments/motors.

186

Volume 4

Malaysian Sewerage
Industry Guidelines

Special Requirements

III)

Aerosol Effects

Aerosol is defined as a suspension of colloidal particles in gases/


atmosphere. Aerosol control measures are important because aerosol
affects the human respiratory system.
If uncontrolled, aerosol could present a health hazard to the operator and
residents due to the reduced buffer zone around the treatment plant.
Screens, open channels and aeration tanks, where violent and turbulent
actions are encountered, may release aerosol. The design of the treatment
plant shall take into consideration any unit processes that are likely to
emit aerosol and mitigating measures shall be undertaken to counter
aerosol release to the atmosphere.

IV)

Safety, Health and Operability

The design of a fully enclosed treatment plant shall address safety,


health and operability aspects. The guidelines given for treatment plants
located within buildings in Section 7.2 shall be followed.
7.3.3

Specific Requirements

I)

Covers for Treatment Unit Processes

The purposes of these covers are to contain odour emission at source


and to reduce visual impact.
The design requirements for treatment unit processes are outlined
below.
a)
b)

c)

d)

Covers to contain odour emission shall be provided at all potential


sources of odour generation for all unit processes located within
the sewage treatment works.

Bins used for the storage of screenings and grit collected in the
pre-treatment area shall be completely covered to reduce visual
impact, odour and to keep vectors away. The designer shall
provide further considerations on the size, type and method of
emptying the bins.
Generally, all unit processes shall be covered or housed within
a building enclosure. This shall include all pre-treatment units,
aeration tanks, and sludge treatment and handling facilities. The
only exception is the secondary clarifier.
The bin shall be located on a bunded, paved area adjacent to an
access road to the treatment plant.

Sewage Treatment Plants

Volume 4

187

Special Requirements

e)

f)

The cover shall comply with BS EN 124 if subject to loading.


It shall also be designed to meet the operating condition of the
odour extraction system as well as the location and application
appropriation.
If the cover is exposed to the environment,
i)

ii)
iii)
g)
h)
i)

j)
k)

Metal covers if used, must have appropriate corrosion


resistant coating in accordance to Section 4 of this
Volume.

Where chipping might occurs at the edge of the cover,


stainless steel reinforcement frame on all sides of a plastic
or FRP cover shall be provided.

Coatings for the concrete and steel shall include coal tar, vinyls
and epoxies in accordance to Section 4.
Covers should be hinged and weigh less than 16 kg to enable
lifting unaided. Beyond a cover weight of 16 kg, assisted lifting
is required.

All unit processes with covers or are housed in a building for


odour and visual impact reduction shall be provided with proper
air extraction and air scrubbing system. These devices shall be
safe to operate and maintain. Odour, noise and visual impact,
and aerosol are the major components for consideration in the
design of an enclosed wastewater treatment plant. Windows
and access hatches that give the operator an extended and
uninterrupted view of the treatment process are mandatory for
all unit processes that are covered.
Covers shall be designed to allow for easy dismantling and easy
access for cleaning of the enclosed plant.

The materials used for the cover structure depend on the type of
cover selected and the characteristics of the odorous environment.
In general, the materials shall be selected to provide durability, ease
of maintenance, corrosion resistance and be relatively inexpensive.
The three most common materials used for containing odours
are concrete, aluminum and FRP. The design requirements for
each of these are outlined below.
i)

188

Plastic or fiberglass cover if used, must be manufactured


with UV inhibitor and will not warp or deform due to
weathering effect.

Concrete

Concrete can support the greatest weight but limits the


plant maintenance workers ability to remove the cover
for major repairs. Concrete covers are subject to corrosion
and should be treated with a protective coating, such as
an epoxy resin.

Volume 4

Malaysian Sewerage
Industry Guidelines

Special Requirements

II)

ii)

Aluminum

Aluminum covers provide the greatest tensile strength with


the thinnest cross-sectional area and can be placed on a
light weight frame. The lightweight nature and thin crosssectional area of aluminum makes it easier to remove and
store the covers during maintenance operations.

Aluminum covers are generally less expensive than FRP and


concrete, but periodic maintenance in the form of an anodised
coating is necessary to help prevent corrosion. The design
of an aluminum cover shall consider the incompatibility of
aluminum with concrete and other metals. If not, disintegration
of the materials occurs and the structural integrity of the
system could be jeopardized.

iii)

FRP

FRP is light weight and generally can be removed by


plant operator and stored during maintenance operations.
FRP covers also offer resistance to corrosion, but require
periodic maintenance with an ultraviolet inhibitor to enhance
durability, particularly, if exposed to sunlight on a prolonged
basis.
Ventilation system

Ventilation systems are required to supply fresh air for workers to


work in a more comfortable environment and to minimise health and
safety concerns.
All covered unit processes must have proper ventilation systems.
a)
b)
c)
d)
e)

An exhaust ventilation system shall be provided with air distribution


patterns that effectively purge work areas.

For waste areas that workers must enter, both blowing and
drawing air shall be used to eliminate dead spots.
Areas designed for personnel entry must include relief systems
to avoid overpressure conditions. Designers must estimate cover
system leakage to determine fan capacity.
Force air ventilation systems should be inspected and tested
periodically to ensure proper air flow and air distribution.

Ventilation of enclosed plants can be either intermittent or


continuous. However, intermittent ventilation is not recommended
because it has a lower degree of safety and more difficult to
operate and maintain than continuous ventilation. Continuous
ventilation is typically more expensive to operate because of
higher electricity costs for running the blowers. Intermittent

Sewage Treatment Plants

Volume 4

189

Special Requirements

f)

g)

h)

i)
j)

ventilation typically requires a higher rate of ventilation. For


example, the wet well and grit removal facility requires 12 air
exchanges for continuos ventilation versus 30 air exchanges for
intermittent ventilation.

The requirement in Section 6 shall be refer for the design of


exchange rate. If the work site is classified as a confined space,
workers without proper respiratory equipment must not occupy
spaces that cannot be ventilated to less than 25% of the permissible
exposure limit (PEL) of the contaminant and less than 10% of
the lower explosive limit (LEL). For example, hydrogen sulfide
which is one of the most common contaminants in enclosed areas
exposed to wastewater has a ceiling concentration of 30 mg/m3
(20 ppm).
Combustible alarms set at a percentage of the LEL and ventilation
failure alarms should be installed in wet wells, screen rooms,
or other enclosed areas where a volatile atmosphere could exist.
These alarms must have both audible and visual indicators to
alert workers that the area is now potentially dangerous as well
as alerting those who are about to enter the problem area.

Before entering the enclosed plant, where there is potential for a


hazardous atmosphere to exist, the operator and/or worker must
be able to test for oxygen deficiency, and combustible and toxic
gases or vapors.
Ventilation systems shall be designed on the basis that the
potential odourous gases have been isolated and contained by
the local exhaust system for odour control.
Ventilation design criteria for work space are as follows:
i)

ii)

iii)
iv)

190

Avoid positioning supply and exhaust registers at equal


elevations and on the same enclosure wall. This will
prevent short-circuiting the ventilation system and creating
dead zones (areas with no apparent ventilation or air
motion).
Equip the makeup air supply and exhaust registers with
volume dampers to control the airflow rate. Makeup air
supply should be less than what is exhausted to create
negative air pressure within the enclosure.
A duty and standby ventilation system are mandatory.
The standby shall be 100% that of duty.
An external visual indicator, such as green/red light, to be
provided outside the enclosed plant to warn of ventilation
systems failure.

Volume 4

Malaysian Sewerage
Industry Guidelines

Special Requirements

k)

The design of the ventilation system shall take into account


the noise aspects. Generally, the design work shall include for
sound insulating material, resilient mountings or other appropriate
devices to ensure that the plant runs without noise or vibration
in its final installed position. Noise level from machinery shall
not exceed the level stipulated by the regulators.

III)

Odour Control System

a)

Isolate odorous gases from general ventilation systems by


containment of identified odour generating sources with a separate
local exhaust system.

b)
c)

d)
e)
f)

g)
h)

IV)

Containment of the odour sources shall be by installing lightweight


and corrosion resistant covers/enclosures designed for practical
operation and maintenance works.
Local exhaust rates for containment shall be designed to provide a
negative pressure, prevent build up of toxic, corrosive or explosive
gases and include provision for process air or air displaced by
changes in the level of liquid inside the covered space.
The local exhaust odorous air shall be conveyed through well
designed and balanced ductworks by a centrifugal fan to effective
odour treatment equipment.

The overall performance of the odour control system shall


comply with the requirements of the Department of Environment
(DOE).
In situations where specific gases such as hydrogen sulphide and
ammonia are significantly present, consideration shall be given
for the installation of a pre-scrubber unit upstream of the main
odour treatment equipment.
Effective odour treatment equipment to be a minimum 90%
removal efficient.
Consideration must be given to the life span of the odour control
system and associated costs in operating and maintaining such
a system.
Vent Stack

The vent stack shall at a minimum 5 m above ground level to ensure


sufficient dispersion of air. Where the stack is located adjacent to a
building, it should be located at least 1 m above the roof line of this
building.

Sewage Treatment Plants

Volume 4

191

Special Requirements

V)

Noise Level

All mechanical equipment that are likely to generate noise such as


blowers, compressor and pumps, shall be acoustically isolated to ensure
the noise generated are contained and reduced to below the levels
stipulated by the regulators.

VI)

Sludge Handling

a) Due to the compactness of the site, it is not conceivable to have


sludge drying beds in an enclosed environment.

Instead, an aerated sludge holding tank shall be provided to


prevent the sludge from turning septic. Sand drying beds (either
covered or otherwise) are not an acceptable form of sludge
treatment in an enclosed plant.

b) Permanent pipework with female coupling and isolation valve


should be provided adjacent to the access gate for easy coupling
of tankers hose during desludge of the holding tank.

VII)

Treatment Process Type

It is preferred that treatment in an enclosed environment employs extended


aeration activated sludge because it offers greater process stability and
less potential for generating odours. However, other treatment processes
warrant further considerations if proven that they have other distinct
advantages in an enclosed environment.

VIII) Siting of Plant


a)

b)

192

The enclosed plant needs to be located away from driveways


to allow for regular maintenance of the screens, grit and grease
removal units and wet well of pump stations. If this is not
possible, then bollards shall be erected to protect the workers
while maintaining the plant.
Where plants are located within the premise of a private property,
direct vehicle access is to be provided from the public road to
the plant via a gate in the perimeter fence.

IX)

Groundwater Conditions

a)

Adequate provision must be made to resist the uplift of the


structure due to hydrostatic ground water pressures. The side
and bottom walls shall be designed to withstand the anticipated
hydrostatic pressures.

Volume 4

Malaysian Sewerage
Industry Guidelines

Special Requirements

b)

The top of the plant shall be located at least 150 mm above the
finished surface level to prevent the inflow of surface run off
into the enclosed plant.

c)

Good perimeter drainage is to be provided to ensure that the


plant is not flooded.

X)

Installation and Removal

Installation and the subsequent removal of all mechanical and electrical


equipment need to be taken into account during the design of the cover.
The following requirements must be carefully catered for:
a)
b)
c)
d)

e)

XI)

Adequate space for servicing must be provided in the design of


the enclosed plant.

If the installation and/or removal of the equipment require the


service of a crane or any lifting vehicle, then access must be made
available within the treatment plant for these lifting vehicles.

An adequate number of access covers and sizes of openings for the


removal and installation of the equipment shall be provided.

The design of an enclosed plant must allow for the plant to be


fully operational during the installation and/or removal of any
equipment. Alternatively, provisions for temporary bypass should
be accommodated to prevent disruption to the sewage flow while
this work is being carried out.
In situations where it is not possible to readily install a duty
and standby unit, the standby unit can be supplied as a separate
item which is kept in store, provided that the faulty unit can be
removed and the spare unit can be installed within two hours by
general maintenance workers using normal tools.
Mechanical and Electrical Requirements

The wiring, lighting and other electrical or mechanical equipment and


appliances that have the potential to generate sparks that may trigger
an explosion shall be designed and installed to meet the relevant safety
codes to avert the possibility of an explosion.

XII)

Building Plan Approval

If a building structure is used to house the enclosed treatment plant,


then the design of this building must comply with the requirements
stipulated by the relevant Building By-Laws.

Sewage Treatment Plants

Volume 4

193

Special Requirements

7.4

Covered and Buried Treatment Plants

7.4.1

Definition

Covered and buried treatment plants refer to treatment plants with covers
that are placed below ground or not more than 1.2 m above ground level.
Covers are provided to reduce the odour, noise and visual impact.

This type of plant is only applicable to Class 1 and Class 2 sewage


treatment plant with treatment capacity no more than 5000 PE. Special
approval by the Commission must be obtained if the plant capacity
exceeds 5000 PE. A compromised buffer zone of 10 m minimum from
the fence to the nearest building boundary line must be provided for
this type of plants. However, the height of the structure is normally
limited to 1.2 m above ground.

7.4.2

General

Covered and buried treatment plants have inherent hazard and restriction
in operability in their actual operation and maintenance. The requirements
in the following sections serve to highlight the minimum improvements
that must be made to these plants in addition to those set out in Section
3, 4, 5 and 6 of this Volume.

7.4.3

Specific Requirements for Covered or Buried Plants of 5,000PE


or Less

I)

The design of these tanks must allow for adequate openings so that
the operator can carry out routine operation and maintenance works
in a safe, efficient and effective manner. These requirements apply to
all unit processes that are covered or buried from the inlet works to
the effluent chamber. Staggered square openings of roughly 600 mm
x 600 mm employed in the past for plants of this nature would not be
acceptable. These openings, as a minimum, must be opened top around
the periphery of the tank.

II)

The designer must take into account the confined space and other related
safety issues for entry into such a tank. Provision of proper access into
each individual tank is mandatory. Where the depth exceeds 2.5 m,
steps with intermediate landings must be included. Other requirements,
such as adequate ventilation prior to tank entry, must be considered and
provided in the design.

194

Openings of Covered and Buried Tanks

Access for Routine Operations and Maintenance of the


Plant

Volume 4

Malaysian Sewerage
Industry Guidelines

Special Requirements

III)

Pipework and Aeration System Requirements

Piping for buried plant shall be exposed and accessible for ease of
maintenance. PVC pipes are not allowed.
The aeration system (diffuser) must be retrievable from top opening
without emptying the tank.
VI)

Lighting

Adequate lighting must be provided through adequate opening at the


top of these covered or buried tanks to provide a good view of the
treatment process such as the air diffusion system, screening, degritting
and secondary clarification. This is important for daily plant operations
through visual inspection of the individual unit process and routine
maintenance of the plant.
V)

Hand Railings

Hand railing provisions must be made to prevent falling into open spaces.
These hand rails must be provided on the perimeter of the open tanks
and further enhanced with kick plates.
VI) Desludging Activities
Adequate access within the proposed treatment plant site is to be made
available to allow for desludging tankers to be within the reach of the waste
activated sludge storage tanks without undue difficulty of maneuvering
the vehicle or damaging the buried tanks or pipe works.
VII) Labeling of Treatment Unit Process
Labeling of each treatment unit is to be provided, from the inlet works
to the secondary clarifiers, to avoid confusion with the similar geometry
and sizes used for most treatment units.
VIII) Noise Control
Due to the compromised buffer requirements and proximity to adjacent
developments, the potential for noise pollution is accentuated. The designer
must ensure all noise generating mechanical and electrical equipment
within the treatment plant must be contained and treated acoustically to
meet compliance to existing noise levels stipulated by the Department
of Environment and that set out in Section 4.
IX) Ventilation
Adequate ventilation must be made available to allow for the safe routine
operation and scheduled maintenance of the treatment plant. During

Sewage Treatment Plants

Volume 4

195

Special Requirements

design, this ventilation aspect must be considered. The type of ventilation,


portable or permanent, must also be determined during design stage.
X)

Odour Control

Odour Control systems to be provided as required in compliance to the


EQA.
XI)

Buoyancy Effects

The designer must account for the buoyancy effects in the design of buried
or covered tanks. This effect is of concern during high groundwater
conditions and emptying of the tank content during desludging works.
Furthermore, the designer must ensure that the design of these tanks
accounts for the hydrostatic force exerted on the floor from the outside
does not exceed the compressive strength of these covered or buried
tanks. This is to prevent any breakthrough of the floor and subsequent
failure of the tank.
The designer must ensure that the design of these tank at worse case
scenario where the tank is fully emptied. This is to prevent any breakthrough
of the floor and subsequent failure of the tank.
XII) Covers
Covers if employed for odour, visual and noise impacts shall be subjected
to the following requirements:
a)
Lifting may be unaided if the covers are hinged and weigh less
16 kg.
b)
Assisted lifting is required if the covers weigh equal to or above
16 kg.
c)
The cover shall comply with BS EN124 loading requirements.
d)
If the cover is exposed to the environment,
i) Plastic or fibreglass cover if used, must be manufactured with
UV inhibitor and will not warp or deform due to weathering
effect.
ii) Metal covers if used, must have appropriate corrosion resistant
coating in accordance to Section 4 of this Volume.
iii) Where chipping might occurs at the edge of the cover,
stainless steel reinforcement frame on all sides of a plastic
or FRP cover shall be provided.
XIII) Fencing
Adequate fencing must be provided for all plants. Adequate security
shall be provided against unauthorised access.
196

Volume 4

Malaysian Sewerage
Industry Guidelines

Special Requirements

7.5

Guidelines for Homestead Developments

7.5.1

Single Developments up to 30 Units or 150 PE in Total

Individual septic tanks may be allowed for single developments of up


to 30 units or 150 PE in total.

Septic tanks will be regarded as temporary treatment plants.

The owner must provide all septic tanks as part of the owners infrastructure
works.

Septic tanks must be constructed to standard design in compliable with


MSIG Volume 5.

7.5.2

Single Developments Over 30 Units in Total With Average


Housing Density Greater Than Five Units per Hectare

For single developments over 30 units in total with an average housing


density greater than 25 persons per hectare, a sewer reticulation and a
communal treatment plant must be provided.

The treatment plant may be classified as permanent.

Sewer reticulation must be appropriately designed to achieve acceptable


hydraulic conditions within topographic and routing parameters.

7.5.3

Single Developments Over 30 Units in Total with Average


Housing Density Less Than Five Units per Hectare

For single developments over 30 units in total and with an average


housing density of less than 25 persons per hectare, a sewer reticulation
and a communal treatment plant is preferred.

The treatment plant may be classified as permanent.

Where the terrain of the development is such that if a communal system


is constructed it will require the construction of too many intermediate
pump stations, then individual treatment facilities may be considered,
subject to the following conditions:

i)

ii)

The individual system must be a system approved by the


Commission.
Where the ground conditions permit, soakaway trenches must
be used for disposal of the final effluent from the treatment
systems.

Sewage Treatment Plants

Volume 4

197

Special Requirements

iii)

iv)
v)

Developers shall ensure that home owners enter into an agreement


with the supplier of the systems or licensed contractors, to carry
out operation and maintenance of the system as per design
requirements.

Tanks shall be desludged by the Service Licensee as per terms


of the agreement signed between the Services Licensee and the
Commission.

The Commission and DOE may impose stringent conditions, if


they believe that such measures are required to ensure that the
sewage from the development will not result in an adverse impact
on the environment.

All septic tanks shall be designed in accordance with the requirements


in MSIG Volume 5.

7.6

Non-Compliance with Standards

7.6.1

Introduction

This section describes the types of incidents, which are outside the
control of the operator that may cause a sewage treatment plant to fail its
effluent consent. Generally, the more sophisticated the treatment process,
the more a process is at risk of failure from one of these incidents. It
would be unreasonable to expect the operator of the treatment plants to
perform within the effluent quality standards following such incidents.
However, the operator must always use his best endeavours to rectify
the situation as soon as practicable following such an incident.

The following potential incidents are treated as special cases when


meeting absolute compliance with Standard A or Standard B.

7.6.2

Types of Incidents that Can Cause Treatment Plant Failure


I)

Power Interruption

An interruption in the power supply to a treatment plant will cause


failure in all mechanical treatment processes.
Some large treatment plants have emergency generators which can be
brought on stream to ensure inlet pumping continues.
However, the crude sewage will pass through the plant receiving only
rudimentary treatment and will probably fail to comply with Standard
A and Standard B.
Furthermore, all existing sewage treatment plants have to be restarted
manually once they are tripped through power failure.

198

Volume 4

Malaysian Sewerage
Industry Guidelines

Special Requirements

On new works, all treatment plants will be fitted with auto-restart facilities
for immediate resumption of operation when power is reconnected.
II)

Lightning

When buildings or cabinets housing electrical control equipment are struck


by lightning, fail safe surge protection equipment trips all mechanical
equipment.
This requires all the equipment to be reset and switched on again. On
an unmanned plant there will be a delay between the trip-out following
the lightning strike and the operators getting to the plant to reset the
equipment.
During this period the plant may fail to comply with the relevant
standards.
III)

Storm and Flood

During periods of very heavy rain, areas of the local sewer network may
suffer such ingress of storm water that surcharge of the sewer system
will result, causing abnormally large flows to arrive at the STP inlet.
Under these conditions, the treatment plant would receive much higher flows
than that designed for and would suffer severe hydraulic overloading.
The effect would be a rapid wash through of sewage and solids causing
the works to fail to meet standards.
IV)

Major Mechanical Breakdown

In many existing sewage treatment plants, particularly the small ones,


insufficient standby equipment has been provided by the developer.

All new plants must be equipped with standby units having an automatic
change over system in the event of failure.
Existing plants may be out of action for several days while repairs are
carried out to failed equipment. To help alleviate this problem, the operator
needs to carry critical spare parts to help speed the repair process.
V)

Vandalism, Theft and Criminal Damage

If a treatment plant is subject to this form of interference, then the


treatment process is at risk until the necessary repairs are carried out.
Reasonable measures must be taken to deter vandalism.

Sewage Treatment Plants

Volume 4

199

Special Requirements

VI)

Deliberate Discharge of Toxic Chemicals

From time to time, irresponsible industrialists may discharge chemical


waste to the sewer in contravention of all the relevant legislation.
This may occur as a one-off dumping exercise, or may be the result
of a small continuous discharge from a trade process which affects the
treatability of the sewage and causes the treatment plant to fail.
VII)

Accidental Discharge of
Substances

Strong Loads or Toxic

From time to time, genuine accidents occur on industrial premises or


on the highway that result in abnormal discharges to the sewer. These
may take the form of serious fires at industrial premises, the sudden
failure of large storage tanks or a major traffic incident involving the
transport of liquid products.
Such discharges to the sewer system would almost always result in the
sewage treatment plant failing to comply until the effects of the discharge
have passed through the system.
VIII) Major Blockages in the Sewer Network System
A blockage in the main sewer network system often causes the sewage
to build up behind the blockage and turn septic.
The sudden release of this large volume of septic sewage by the clearance
of the blockage, may cause temporary overloading of the treatment plant
and lead to a reduction in effluent quality beyond the absolute standard
for a short period of time.
IX)

Defect

Completed treatment plant to be inspected by competent personal. Visual


inspection to be conducted during the final stage of construction. Two
type of defect generally detected during inspection :

200

a)

Minor Defect

b)

Major Defect

Non-critical, do not immediately or unduly affect the performance


of the plant but nevertheless, require attention to rectify faults
within reasonable time frame.
Critical or serious and require immediate action to be taken in
rectifying faults, impair plant performance, unit processes, or
system components.

Volume 4

Malaysian Sewerage
Industry Guidelines

Special Requirements

Consultants responsibility to ensure compliance of the design standard


and good engineering practice.

7.7

Energy Saving

In selection of treatment process or equipment, the designer should


consider the best product which minimized the power consumption for
process and major plant equipment without compromising on the quality
of treatment discharge.

7.8

Recycle and Reuse

a)

b)

c)

To promote/encourage designer to look into potential of energy


reuse.
To utilize the recycle water (reclaim water) for cleaning and
landscaping purposes,

To promote and encourage design to identify potential of sludge


reuse and/or recycle.

Sewage Treatment Plants

Volume 4

201

Special Requirements

202

Volume 4

Malaysian Sewerage
Industry Guidelines

Section 8
Package Sewage
Treatment Plant

Package Sewage Treatment Plant

204

Volume 4

Malaysian Sewerage
Industry Guidelines

Package Sewage Treatment Plant

8.1

Definition

A package sewage treatment plant is a form of treatment plant both for fixed
film and suspended growth processes. It shall consist of a prefabricated
biological treatment system and be limited to the development of the
sewage treatment system between the ranges of 150 to 5000 populations
equivalent (PE).

The package sewage treatment plant is only applicable to Class 1 and


Class 2 STP as defined in Section 4 of this Guidelines. The prefabricated
biological treatment system shall have been given approval by the
Commission prior to the application.

The major components of a package sewage treatment plant are:


I)
a)
b)
c)
d)

Inlet works
Primary screen.
Pump Station (if applicable).
Secondary screen.
Grit and grease chambers.

II)
a)
b)
c)
d)
e)
f)

Biological treatment system


Balancing Tank.
Aeration/Anoxic Tank.
Clarifier.
Sludge Holding Tank.
Aeration System including blower house.
Sludge Dewatering System.

III)

Outlet works

a)

Disinfection that can be physical, chemical or radiation.

Package sewage treatment plants fall under the category of covered/


buried treatment plants.

8.2

Land Area Requirement


The land area requirements for package sewage treatment plants shall
comply with those recommended for Class 1 and Class 2 Plants in Section
2 of this Guidelines.
The net area does not include the 10 m buffer zone surrounding each
plant, but does include the 5 m set backs and access paths within the
plant.

Sewage Treatment Plants

Volume 4

205

Package Sewage Treatment Plant

8.3

Design Requirement
a)
b)

All calculations regarding the inlet works, outlet works, biological


processes and hydraulics shall follow the design criteria as stipulated
in the Section 4 and Section 5 of this Guidelines.

All units of package sewage treatment plant and foundation shall


be designed to meet the extreme case scenario as follows:
i)

c)

d)
e)

ii)

When the tanks are fully emptied;

During high groundwater conditions.

The structural design of a tank shall consider all factors that can
affect the strength and integrity of the tank, like soil conditions,
area of installation, etc. All tanks shall be structurally designed
to withstand the maximum earth load and hydrostatic pressure
equivalent to a backfill depth of 1 m.

All civil works of blower house, pump house and control panel room
shall be as recommended in Section 4 and 5 of this Guidelines.
The minimum design life span of the components of the package
sewage treatment plant shall be as Table 8.1 below:

Table 8.1 Minimum Design Life Span of Package Sewage


Treatment Plant Components
Component

Prefabricated tank and other structural


components
Civil

Mechanical & Electrical

Design Life Span

> 50 years
> 50 years
10 years

8.4

Components of Package Sewage Treatment Plant

8.4.1

Layout, Piping and Arrangement of Prefabricated Biological


Treatment System
The prefabricated biological treatment system shall be packaged in terms of
layout, piping, arrangement of the tanks and the biological processes.
The dimension of each tank shall be fixed for each model of the prefabricated
system. All these items shall not be changed once approved.

8.4.2

Prefabricated Tanks
The physical properties of the tanks for package plants shall meet the
material requirements for STP structures as stipulated in Section 4 of this
MSIG. The prefabricated tanks shall come as complete tanks, thus no

206

Volume 4

Malaysian Sewerage
Industry Guidelines

Package Sewage Treatment Plant


Package Sewage Treatment Plant

8.4.2

8.4.3

8.4.3

Prefabricated Tanks
welding, jointing, fabrication/moulding of tanks components is allowed
at The
site. physical
The routeproperties
for delivery
of tanks
tanks shall
be planned
so as
of the
for package
plantsproperly,
shall meet
the
notmaterial
to cause
any
damage
to
road
facilities
and
harm
to
road
users.
requirements for STP structures as stipulated in Section 4 of this
MSIG. The prefabricated tanks shall come as complete tanks, thus no
Process
Units/Components
welding,Treatment
jointing, fabrication/moulding
of tanks components is allowed at
site. The route for delivery of tanks shall be planned properly, so as not to
The following table provides the recommended number of tanks for each
cause any damage to road facilities and harm to road users.
unit process against the PE size. The effective volume consideration is
also
incorporated
in the Units/Components
table.
Process
Treatment

The following table provides the recommended number of tanks for each
unit process against the P.E size. The effective volume consideration is also
incorporated in the table.
Table 8.2 Recommended Number of Tanks and Effective Volume
Table 8.2: Consideration
Recommendedfor
Number
ofUnit
Tanks
and Effective Volume
Various
Processes
Consideration for Various Unit Processes
Max Number of
Tanks
PE 1 000

Max Number of
Tanks
Tanks
PE >1 000

Aeration Tank

Anoxic Tank

Clarifier

Sludge
Holding Tank

Name of Tank

Balancing
Tank

Sewage Treatment Plants

Sewage Treatment Plants

Effective Volume

Volume 4

Volume 4

207

191

Package Sewage Treatment Plant

Note:

Low water level (LWL) is the minimum submergence level of the pumps
to protect it from damage. It is dependent on the type of the pumps, thus
the low water level shall be set according to the pumps manufacturers
requirement Top Water Level (TWL) is the normal operating water level
with adequate freeboard provided.

8.5

Appurtenances

8.5.1

Piping system

8.5.1.1 General
a)
b)
c)
d)
e)
f)
g)

The piping used shall be an approved product, supplied and


manufactured by a supplier/manufacturer approved by the Commission
and shall be suitable for the application.
The arrangement of the piping system and interconnection pipes
in the tanks shall not obstruct maintenance work of the equipment
in the tanks.
All the buried piping shall be properly bedded and supported with
the selected compacted fill material.

All the above ground piping shall have a minimum distance of


75 mm from the ground level.
It shall be provided with a proper pipe support and bracket. The
bracket shall be made of hot dipped galvanised steel.

The arrangement/layout of the above ground piping shall minimise


obstruction and maneuverability.

Any installation or assemblies of pipe support that is attached to


the prefabricated tank is not allowed.

8.5.1.2 Inlet and Outlet Pipes


All inlet and outlet pipes of the units of prefabricated biological treatment
system must be pre-fitted at the factory. On-site drilling for holes is
strictly prohibited. All jointing and pipe holes connection shall be factory
fabricated/moulded.
8.5.1.3 Aeration Pipes
a)

208

The air distribution pipe used shall be rigid and can withstand
temperatures up to 150 C and pressures of 25% more than the
design pressure of the blower.

Volume 4

Malaysian Sewerage
Industry Guidelines

Package Sewage Treatment Plant

b)

The air pipe from the blower to the process unit shall be above
ground.

8.5.1.4 Sludge Transfer Pipes


a)
b)

No thread union/coupling is allowed at the sludge transfer pump


piping. The connection shall be double flange with Grade 304
stainless steel bolt and nut.
No bending is allowed for the sewage distribution pipe. A chamber
shall be provided for any changing direction of the flow.

8.5.1.5 Effluent Pipes


The effluent discharge piping system that passes through/bypasses the
disinfection treatment facility shall be designed so as not to cause any
nuisance.
8.5.2

Pumping System
The pumps installed in the package system shall meet the requirements
as stated in Table 8.3 below:
Table 8.3 Technical Requirements of Pumping System

Name of Pump

Transfer Pump

Sludge Transfer
Pump

RAS/WAS Pump

Application Area

Balancing Tank

Sludge Holding
Tank

Clarifier

Minimum Throughlet

50 mm

50 mm

50 mm

Control

Automatic control Manual control


by float switch
by timer

Number of Pump

1 duty, 1 standby

1 duty for each


tank

Type of Pump

Mechanical
Submersible
Pump

Mechanical
Submersible
Pump or Self
Priming Pump

Necessities

Mandatory

Accessories

All pumps shall be completely installed with duct foot, guide


rail and lifting chain made of Grade 304 stainless steel.

Sewage Treatment Plants

Volume 4

Automatic control
by timer and
solenoid valve
1 duty for each tank
PE < 1000 : Air lift
PE 1000 :
Mechanical Pump

209

Package Sewage Treatment Plant

Note:

1)

Non-submersible pumps shall be provided with parking bay with


shade.

2)

The duct foot shall be installed and assembled at the factory. No


installation/assemblies at site are allowed except for the connection
of the transfer pipe and the guide rail. All fasteners of the duct
foot shall be watertight.

8.5.3

Diffuser
a)
b)
c)

8.5.4

The diffuser shall not be bolted to the bottom of the tank.


The diffuser shall be removable and easy to re-install.

Flow Distribution Chamber


a)
b)

8.5.5

All diffusers must be supported from the tank base. A typical


drawing of the diffuser support is shown in Figure 8.1.

Distribution box shall be provided with adjustable features. A


typical drawing of the distribution box is shown in Figure 8.2.
The design and construction of the distribution chamber shall
prevent any sedimentation.

Manhole Cover/Inspection Chamber Cover


The manhole cover shall follow the requirements as in Table 8.4:
Table 8.4 Technical Requirements of Manhole Cover
Description

FRP

HDPE

Ductile/Cast Iron

Size

600 mm x 600 mm or 600 mm diameter

Installation

At any location on top of the tank except at assembly


joints, rib or reinforced ring location.

Load Bearing Capacity

3.5 kN/m2 (BS EN 12255-1:2002(E))

Maximum Deflection
Limit

10 mm or the span divided by 200, whichever is smaller


(BS EN 12255-1:2002(E))

Class

B 125 in accordance to BS EN 124:1994 or equivalent

Personnel Load

125 kN (fully walk-able) (BS EN 124:1994)

Design Safety Factor

4:1 for allowable stresses shall be met for all load


combinations (ANSI/ASCE 7-98)

210

Volume 4

Malaysian Sewerage
Industry Guidelines

Package Sewage Treatment Plant

Table 8.4 Technical Requirements of Manhole Cover (Continued)


Description

FRP

HDPE

Ductile/Cast Iron

Temperature Range

27C 35C (to incorporate thermal expansion and


contraction)

Standard colour

Black

Coating

Aliphatic acrylic
polyurethane
non-skid coating

Resin

UV Protection

Note:

1.
2.
3.
4.

8.5.6

Black
NA

Black
- Epoxy coating of
200 m

- Hot dip galvanised


of 200 m

Corrosion
resistant
general purpose
polyester

NA

NA

Ultraviolet-light
inhibitors shall
be added to the
laminate

Carbon black

NA

The collar of the manhole shall be raised with a minimum height


of 100 mm above ground level.
The cover shall be equipped with a frame support and hinge, and
attached to the manhole opening.
Each manhole cover must be properly labeled / marked for ease
of identification of the unit process of the system.
NA not applicable

Anchor System Loading


The tank anchor system (straps, cables, turnbuckles, etc.) shall have
strength of at least 1.5 times the maximum uplift force of an empty tank
without backfill in place. All wire straps, cables and turnbuckles must
be made of Grade 304 stainless steel.

8.5.7

Landscaping
The landscaping of the sewage package system shall be in accordance
with those recommended in Section 6 of this Guidelines.

8.5.8

Odour Treatment
The odour treatment shall be incorporated into the package sewage treatment
plant and shall follow the requirements stipulated in Section 7.4.

Sewage Treatment Plants

Volume 4

211

Package Sewage Treatment Plant

8.5.9

8.6

Ancillary Facilities
The requirement and criteria of other ancillaries such as lifting facilities,
road, water tank, stand pipe, etc shall be in accordance with the design
criteria as stipulated in Section 6 and special requirements in Section
7.4.

Marking and Labelling


Each tank shall at a minimum be marked with the following
information:

Manufactures name or trademark

Manufacturing serial number

Manufacturing date (MM/YY)


Diameter and Capacity

Citation of the standard

The markings shall be printed and adhered to the tank.

212

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix A
Tables

Appendix A - Tables

214

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix A

Appendix A Tables
Table A1

Contaminants of Concern in Sewage Treatment

Table A3

Major Biological Treatment Processes Used for Sewage Treatment

Table A2

Typical Composition of Untreated Domestic Sewage

Table A4

Interim National River Water Quality Standards for Malaysia

Table A6

The Occupational Safety and Health Act 514, 1994 Brief


Summary of Contents

Table A5

Table A7
Table A8

River Clarification

Permissible limits for potentially toxic elements in soil


Options for disposal of Sludge and reuse of biosolids

Sewage Treatment Plants

Volume 4

215

Appendix A - Tables

Table A1 Contaminants of Concern in Sewage Treatment

Contaminants

Reason for Concern

Suspended solids

Suspended solids can lead to the development of sludge


deposits and anaerobic conditions when untreated sewage
is discharged in the aquatic environment.

Biodegradable
organics

Composed principally of proteins, carbohydrates and fats,


biodegradable organics are measured most commonly in
terms of BOD (biochemical oxygen demand). If discharged
untreated to the environment, their biological stabilisation
can lead to the depletion of natural oxygen resources and to
the development of septic conditions.

Pathogens

Communicable diseases can be transmitted by the


pathogenic organisms in sewage.

Nutrients

Both nitrogen and phosphorus, along with carbon, are


essential nutrients for growth. When discharged to the
aquatic environment, these nutrients can lead to the growth
of undesirable aquatic life. When discharged in excessive
amounts on land, they can also lead to the pollution of
groundwater.

Refractory organics

These organics tend to resist conventional methods of


sewage treatment. Typical examples include surfactants,
phenols and agricultural pesticides.

Heavy metals

Heavy metals are usually added to sewage from commercial


and industrial activities and may have to be removed if the
sewage is to be reused.

Dissolved inorganic
solids

Inorganic constituents such as calcium, sodium and sulphate


are added to the original domestic water supply as a result
of water use and may have to be removed if the sewage is
to be reused.

216

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix A - Tables

Table A2 Typical Composition of Untreated Domestic Sewage


Concentration (mg/l)

Constituent

Strong

Solids, total

Medium

Weak

1200

720

350

850

500

250

Fixed

525

300

145

Volatile

325

200

105

350

220

100

75

55

20

275

165

80

Settleable solids, ml/l

20*

10*

5*

Biochemical oxygen demand,


5 day, 20C (BOD5, 20C)

400

250

110

Total organic carbon (TOC)

290

160

80

1000

500

250

Nitrogen (total as N)

85

40

20

Organic

35

15

Free ammonia

50

25

12

Nitrites

Nitrates

15

Inorganic

10

Chlorides

100

50

30

Alkalinity (as CaCO3)

200

100

50

Grease

150

100

50

Dissolved, total

Suspended, total
Fixed
Volatile

Chemical oxygen demand (COD)

Phosphorus (total as P)
Organic

* All values except settleable solids are expressed in mg/l.

Sewage Treatment Plants

Volume 4

217

Appendix A - Tables

Table A3

Major Biological Treatment Processes Used for Sewage


Treatment

Type

Common Name

Use

Aerobic processes
Suspended
growth

Carbonaceous BOD removal (nitrification)

Activated-sludge process
Conventional (plug flow)

Carbonaceous BOD removal (nitrification)

Continuous-flow stirred-tank

Carbonaceous BOD removal (nitrification)

Step aeration

Carbonaceous BOD removal (nitrification)

Pure oxygen

Carbonaceous BOD removal (nitrification)

Modified aeration

Carbonaceous BOD removal (nitrification)

Contract stabilisation

Carbonaceous BOD removal (nitrification)

Extended aeration

Carbonaceous BOD removal (nitrification)

Oxidation ditch

Carbonaceous BOD removal (nitrification)

Sequencing batch reactor

Carbonaceous BOD removal (nitrification)

Suspended-growth nitrification

Nitrification

Aerated lagoons

Carbonaceous BOD removal (nitrification)

Aerobic digestion

Carbonaceous BOD removal (nitrification)

Conventional air

Stabilisation, carbonaceous BOD removal

Pure oxygen

Stabilisation, carbonaceous BOD removal


Carbonaceous BOD removal

High-rate aerobic algal pond


Attached
growth

Combined
processes

Trickling filters
Low-rate

Carbonaceous BOD removal (nitrification)

High-rate

Carbonaceous BOD removal (nitrification)

Roughing filters

Carbonaceous BOD removal

Rotating biological contactors

Carbonaceous BOD removal (nitrification)

Packed-bed reactors

Carbonaceous BOD removal (nitrification)

Trickling filter, activated sludge

Carbonaceous BOD removal (nitrification)

Activated sludge, trickling filter

Carbonaceous BOD removal (nitrification)

Anoxic processes
Suspended
growth

Suspended-growth denitrification

Denitrification

Attached
growth

Fixed-film denitrification

Denitrification

218

continued
Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix A - Tables

Table A3

(continued)

Type

Common Name

Use

Anaerobic processes
Suspended
growth

Attached
growth

Stabilisation, carbonaceous BOD removal

Anaerobic digestion

Standard-rate, single-stage Stabilisation, carbonaceous BOD removal


High-rate, single-stage

Stabilisation, carbonaceous BOD removal

Two-stage

Stabilisation, carbonaceous BOD removal

Anaerobic contact process

Carbonaceous BOD removal

Anaerobic filter

Carbonaceous BOD removal, stabilisation


(denitrification)

Anaerobic lagoons (ponds)

Carbonaceous BOD removal (stabilisation)

Aerobic/anoxic or anaerobic process


Suspended
growth

Single-stage nitrificationdenitrification

Carbonaceous BOD removal, nitrification,


denitrification

Nitrification-denitrification

Nitrification, denitrification

Attached
growth

Facultative lagoons (ponds)

Carbonaceous BOD removal

Combined
processes

Maturation or tertiary ponds

Carbonaceous BOD removal

Anaerobic-facultative lagoons

Carbonaceous BOD removal

Anaerobic-facultative-aerobic
lagoons

Carbonaceous BOD removal

Sewage Treatment Plants

Volume 4

219

Appendix A - Tables

Table A4

Interim National River Water Quality Standards for


Malaysia
Classes*

Parameters (units)

II

IIA

IIB

III

IV

Ammoniacal Nitrogen
(mg/l)

0.1

0.3

0.3

0.9

2.7

>2.7

BOD5 (mg/l)

12

>12

COD (mg/l)

10

25

25

50

100

>100

DO (mg/l)

5-7

5-7

3-5

<3

<1

PH

6.5-8.5

6-9

6-9

5-9

5-9

Colour (TCU)

15

150

150

Elect. Cond.#
(mmhos/cm)

1000

1000

6000

Floatables

Odour

Salinity# (0/00)

0.5

Taste

Total Diss. Solid#


(mg/l)

500

1000

4000

Total SS (mg/l)

25

50

50

150

300

>300

Temperature (0C)

Normal
2

Normal
2

Turbidity (NTU)

50

50

F. Colif. (counts/100
ml)

10

100

400

5000

5000

5000

5000

(20 000)

(20 000)

> 50 000

50 000

50 000

Tot. Colif. (counts/100 100


ml)
N

No visible floatable materials/debris, or no objectionable odour, or no objectionable


taste

Classes are described on the following table

Related parameters, only one recommended for use

Geometric mean

Maximum not to be exceeded

220

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix A - Tables

Table A5

River Clarification

Class

Uses

Conservation of natural environment


Water supply I - practically no treatment necessary (except by
disinfection or boiling only)
Fishery I - very sensitive aquatic species

IIA

Water supply II - conventional treatment required


Fishery II - sensitive aquatic species

IIB

Recreational use with body contact

III

Water supply III - extensive treatment required


Fishery II - common, of economic value, and tolerant species
Livestock drinking

IV

Irrigation

None of the above

Note: This data is adapted from the Water Quality Criteria and Standards for
Malaysia, Final Report July 1986, Department of Environment.

Sewage Treatment Plants

Volume 4

221

Appendix A - Tables

Table A6

The Occupational Safety and Health Act 514, 1994 - Brief


Summary of Contents

Part No.

Content

Preliminary

II

Appointment of Offices

III

National Council for Occupational Safety and Health

IV

General Duties of Employers and Self Employed Persons

General Duties of Designers, Manufacturers and Suppliers

VI

General Duties of Employees

VII

Safety and Health Organisations

VIII

Notification of Accidents, Dangerous Occurrence, Occupational Poisoning and


Occupational Diseases and Inquiry

IX

Prohibition Against use of Plant or Substance

Industry Codes of Practice

XI

Enforcement and Investigation

XII

Liability for Offences

XIII

Appeals

XIV

Regulations

XV

Miscellaneous

The Occupational Safety and Health Act (OSHA) was enacted by the Parliament
in 1994. In general, it is an enabling law in that the duties, responsibilities,
penalties and guidelines are to be followed by each specific industry. The
following table provides an outline of OSHA.
Parts of OSHA have a specific target audience. For example, if the professional
is a designer, then Part V would be applicable with respect to Occupational,
Safety and Health in their design.

222

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix A - Tables

Table A7

Permissible limits for potentially toxic elements in soil


Parameters

Limits (mg/kg)

Zinc

900

Copper

250

Nickel

150

Cadmium

12

Lead

1000

Mercury

Chromium

1000

Arsenic

150

Sewage Treatment Plants

Volume 4

223

Appendix A - Tables

Table A8

No

Options for disposal of Sludge and reuse of bio-solids


Type of sludge/
by-product

Liquid primary sludge and


septage

Dewatered primary sludge


and dewatered septage

Pond sludge

Dewatered pond sludge

Digested sludge

Dewatered digested sludge

Lime stabilised sludge

Thermally dried sludge


(pellets/granules)

10

Compost product

Incinerator ash

Source/ Treatment
Process

Option for
Disposal or
Utilization

- Imhoff tanks
- Primary and secondary
clarifiers
- Septic Tanks

- Oxidation ponds
- Aerated lagoons
- Waste stabilization
ponds

D, F, R

- Digesters
- Sludge lagoons
- Anaerobic ponds

D, F, R

- Lime stabilisation

C, D, F, R, S

- Thermal drying

A, C, D, F, L, R,
S, SP

- Drying beds
- Mechanical dewatering
equipment

C, D, I, S

- Drying beds
- Mechanical dewatering

C, D, F, I, R, S

- Drying beds
- Mechanical dewatering

C, D, F, I, R, S

- Composting

A, C, D, F, L, R, S

- Incineration

C, D, S, SP

NOTES:
A = Use in agriculture
C = Disposal to controlled dumpsites
D = Disposal to dedicated sludge disposal sites
F = Use in forestry/non-food crops
I = Incinerate
L = Use for landscaping at public amenity areas
S = Disposal to sanitary landfill sites
R = Use in rehabilitation of degraded
SP = Recycled into special product, e.g. building material
224

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix B
References

Appendix B - References

226

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix B - References

Malaysian Standards

MS 29
Specification for aggregates from natural sources for concrete

MS 144
Specification for cold reduced mild steel wire for reinforcement of concrete

MS 145
Specification for steel fabric for the reinforcement of concrete

MS 146
Specification for hot rolled steel bars for reinforcement of concrete

MS 416
Code of practice for the use of structural steel in building

MS 523
Specification for concrete including ready mixed concrete
Part 1
Guide to specifying concrete
Part 2
Methods for specifying concrete mixes
Part 3
Procedures to be used in producing and transporting concrete
Part 4
Procedures to be used in sampling, testing and assessing compliance of
concrete

MS 739
Specification for hot-dip galvanised coatings on threaded fasteners

MS 740
Specification for hot-dip galvanised coatings on iron and steel articles

MS 822
Specification for sawn-timber foundation piles

MS 1037
Specification for sulphate resisting portland cement

MS 1195
Code of practice for structural use of concrete
Part 1
Design and construction
Part 2
Part 3

Special circumstances
Design charts for singly reinforced, doubly reinforced beams and
rectangular columns

MS 1227
Specification for portland pulverised fuel ash cement

MS 1228: 1991

Code of Practice for Design and Installation of Sewerage Systems

Sewage Treatment Plants

Volume 4

227

Appendix B - References

MS 1241

Specification for fibreglass water tanks - effective capacity of less than 2000
litres

MS 1292

Specification for rubber seals water stops for sealing joints in concrete

MS 1387

Specification for ground granulated blast furnace slag for use with portland
cement

MS 1390

Specification for glass-reinforced polyester panels and panel water tanks


British Standards

BS 476

Fire tests on building materials and structures


BS 1161

Specification for aluminium alloy sections for structural purposes


BS 1615

Specifications for anodic oxidation coatings on aluminium.


BS 3396

Woven glass fibre fabrics for plastics reinforcement


BS 3532

Method of specifying unsaturated polyester resin systems


BS 3749

Specification for E glass fibre woven roving fabrics for the reinforcement of
polyester and epoxy resin systems

BS 4248

Specification for supersulfated cement


BS 4848

Hot rolled structural steel sections

Part 2
Specification for hot finished hollow sections

BS 4921
Specification for sherardized coatings on iron and steel

BS 5493

Code of practice for protective coating of iron and steel structures against
corrosion

228

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix B - References

BS 7079

Preparation of steel substrates before application of paints and related products


BS 7123

Specification for metal arc welding of steel and concrete


BS 8118

reinforcement

Structural use of aluminium


Part 1
Part 2

Code of practice for design


Specification for materials, workmanship and protection

European Standard
EN 10088

Stainless Steel
Part 1
Part 3

List of Stainless Steels


Technical delivery conditions for semi-finished products, bars, rods, wire,
sections and bright products of corrosion resisting steels for general
purposes

EN 10029

Specification for tolerances on dimensions, shape and mass for hot rolled steel
plates 3 mm thick or above
EN ISO 9445

Continuously cold-rolled stainless steel narrow strip, wide strip, plate/sheet and cut
lengths. Tolerances on dimensions and form
EN 754

Aluminium and aluminium alloys. Cold drawn rod/bar and tube.


Part
Part
Part
Part

1
2
7
8

Technical conditions for inspection and delivery


Mechanical properties
Seamless tubes, tolerances on dimensions and form
Porthole tubes, tolerances on dimensions and form

EN 755

Aluminium and aluminium alloys. Extruded rod/bar, tube and profiles.


Part
Part
Part
Part
Part
Part
Part
Part

1
2
3
4
5
6
7
8

Technical conditions for inspection and delivery


Mechanical properties
Round bars, tolerances on dimensions and form
Square bars, tolerances on dimensions and form
Rectangular bars, tolerances on dimensions and form
Hexagonal bars, tolerances on dimensions and form
Seamless tubes, tolerances on dimensions and form
Porthole tubes, tolerances on dimensions and form

Sewage Treatment Plants

Volume 4

229

Appendix B - References

Part 9

Profile, tolerances on dimensions and form

EN 1676

Specifications for aluminium and aluminium alloy. Alloyed ingots for remelting.

EN 12373

Specification for aluminium and aluminium alloys. Anodizing.


Part 1

Method for specifying decorative and protective anodic oxidation coatings


on aluminium and its alloys.

EN 10162

Specification for cold rolled steel sections. Technical delivery conditions. Dimensional
and cross-sectional tolerances.

EN 13923

Filament-wound FRP pressure vessels. Materials, design, manufacturing and


testing.

EN ISO 8503

Preparation of steel substrates before applications of paints and related products.


Surface roughness characteristics of blast-cleaned steel substrates.
Part 1

Specifications and definitions for ISO surface profile comparators for


the assessment of abrasive blast-cleaned surfaces.

EN 10025

Hot rolled products of structural steels.


Part 1
Part 3
Part 4

General technical delivery conditions.


Technical delivery conditions for normalized/normalized rolled weldable
fine grain structural steels.
Technical delivery conditions for thermomechanical rolled weldable fine
grain structural steels

EN ISO 2063

Thermal spraying. Metallic and other inorganic coatings. Zinc, aluminium and their
alloys.

EN 14020

Reinforcements. Specification for textile glass roving.


Part 1

Designation

Part 3

Specific requirements

Part 2

Methods of test and general requirements


EN 10210

Specification for hot finished structural hollow sections of non-alloy and fine grain
steels

230

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix B - References

Part 2

Tolerances, dimensions and sectional properties.


EN 10296

Welded circular steel tube for mechanical and general engineering purposes. Technical
delivery conditions.
Part 1
Part 2

Non-alloy and alloy steel tubes.


Stainless steel

EN 10297

Seamless circular steel tubes for mechanical and general engineering purposes.
Technical delivery conditions.
Part 1

Non-alloy and alloy steel tubes.

EN 10305

Steel tubes for precision applications. Technical delivery conditions.


Part
Part
Part
Part

1
2
3
4

Part 5
Part 6

Seamless cold drawn tubes


Welded cold drawn tubes
Welded cold sized tubes
Seamless cold drawn tubes for hydraulic and pneumatic power
systems
Welded and cold sized square and rectangular
Welded cold drawn tubes for hydraulic and pneumatic power systems
EN 14118

Reinforcements. Specification for textile glass mats. (chopped strand and continuous
filament mats).
Part 1
Part 2
Part 3

Designation
Methods of tests and general requirements
Specific requirements
EN 10083

Specification for steels for quenching and tempering


Part 3

Technical delivery conditions for alloy steels

ASTM Standard

ASTM D4097

Standard specification for contact-moulded glass-fibre-reinforced thermo set resin


corrosion-resistant tanks.

Sewage Treatment Plants

Volume 4

231

Appendix B - References

ASTM E84

Standard test method for surface burning characteristics of building materials.


ASTM C582

Standard specification for contact-moulded reinforced thermosetting Plastic (RTP)


laminates for corrosion-resistant equipment.
AS Standard

AS 3750.2

Paints for steel structures Ultra high-build paint


AS/NZS 3750.12

Paints for steel structures Alkyd/micaceous iron oxide


AS/NZS 2312

Guide to the protection of structural steel against atmospheric corrosion by the use
of protective coatings.
Other Reference Materials











232

Buffer Guidelines for the Siting and Zoning of Industries, Department of


Environment
Environmental Quality Act 1974

Environmental Quality (Sewage and Industrial Effluents) Regulations,


1979
Occupational Safety and Health Act, 1994 (OSHA)

Water Quality Criteria and Standards for Malaysia, Final Report, July 1986,
Department of Environment

Environmental Impact Assessment Guidelines for Municipal Solid Waste,


Sewage Treatment and Disposal Projects, Department of Environment.
Factories and Machinery Act 1967 (Revised 1974)
Uniform Building By-Law (UBBL), 1984
Town and Country Planning Act, 1976
Sewerage Services Act 1993

Water Services Industry Act 2006


Electrical Act

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix B - References

Other Guidelines in This Set


The Malaysian Sewerage Industry Guidelines is comprised of 5 volumes:



Volume 1

Sewerage Policy for New Developments

Volume 3

Sewer Networks and Pump Stations

Volume 2
Volume 5

Sewage Treatment Plants

Sewerage Works Procedures


Septic Tanks

Volume 4

233

Appendix C
Supervisory Control and Data
Acquisition System (SCADA)

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

236

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

C-1

Introduction: Overview

SCADA is the acronym for Supervisory Control And Data Acquisition, SCADA
or Human-Machine Interface (HMI). The system allows distributed input to be
continuously monitored without the intervention of an operator and allows supervisor
or operator (depending on security level) to remotely control of equipment operating
status.
Data acquisition begins at the Programming Logic Controller, PLC level and includes
meter readings and equipment statuses that are communicated to the SCADA as
required. Data is then compiled and formatted in such a way that a control room
operator using the HMI can make appropriate supervisory decisions that may be
required to over-ride normal PLC controls. (A SCADA system includes all the
pieces, HMI, controllers, I/O devices, networks, software, etc.).
SCADA systems typically implement a distributed database which contains data
elements called tag points. A tag point represents a single input or output value
monitored or controlled by the system. Tag points can be either hard or soft.
A hard point is representative of an actual input or output connected to the system,
while a soft point represents the result of logic and math operations applied to
other hard and soft points. The point values are normally stored as value-timestamp
combinations; the value and the timestamp when the value was recorded or calculated.
A series of value-timestamp combinations is the history of that point.
The SCADA provides a user-friendly front-end to a control system containing
programmable logic controller (PLC) that provide automated, pre-programmed control
over a process. This enables the SCADA system to gather data automatically and
remotely rather than manually and site in-situ.
A SCADA software can be linked to a database (normally SQL-Structured Query
Language), to provide instant trending, diagnostic data, scheduled maintenance
procedures, logistic information, detailed schematics for a particular sensor or
machine, and expert-system troubleshooting guides. Most major PLC manufacturers
have offered integrated HMI/SCADA systems, many of them using open and nonproprietary communications protocols (such as MODBUS or Profibus).
In short, interfacing on of SCADA with PLC offers efficient monitoring and control
of process in a large installation site and with large number of distributed equipment
at a site. SCADA provide alarm notification, historical and on-line trending plots of
control parameters for effective process monitoring and control. SCADA system can
also be implemented with PPM schedule maintenance notification and reminder.
The SCADA that are installed at the remote sites can be linked to a Master Station
via communication system (Radio frequency or WIFI or other on-line communication
channels). The data from an equipment is collected via on-line data acquisition or,
unless otherwise allowed, on batch mode via data logging devices.

Sewage Treatment Plants

Volume 4

237

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

The SCADA software can also activate alarm messaging to inform the operator
station for exceptional event (critical alarm) reporting. Remote Access Server (RAS)
features can provide for either via Internet or other dial-up method (fixed line and/
or wireless modem).
All the proposed SCADA software shall be scalable and flexible enough to allow the
integration of any additional SCADA controller in future expansion. It shall provide
with many industrial standard protocols to allow the user to integrate easily.

C-2

Purpose

This document will provide basic technical requirement for implementation of


integrated SCADA/HMI in sewerage system.

C-3

General Requirements

The SCADA system shall be scalable process control solutions designed to meet
the required automation needs in the sewerage industries. The system shall provide
the required level of performance, flexibility, ease of use, and low life-cycle cost
of ownership, making use of the following technology that includes:
The SCADA system shall be Window based client/server system and make use of
the following technologies:


C-4

Dynamic data caching, alarming, human machine interface, history collection,


and reporting functions;
Web viewable, providing secure, advanced user interface HMI capabilities
based on an open industry standard html file format and Web Browser
access;
Extensive list of communication interfaces;
Secure Internet Browser based on-line documentation and support.

Architecture

The SCADA architecture shall be flexible and scalable to allow expansion requirements.
The basic architecture shall incorporate all but not limited to the followings:




238

Standard based workstations;


powerful Windows based server(s);
Windows based clients;
Industry communication standards shall follow IEEE specification;
object-based configuration tools;

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

C-5

controllers/remote terminal units;


with power surge protection;
Modem: digital or analog;
Network switches or routers;
Uninterrupted Power Supply (UPS);
data logger & storage devices for continuous monitoring of operation in
the event of cessation of communication;

SCADA Requirement

The SCADA shall utilize all but not limited to the followings available technologies
and features:

HMI Web A web-based architecture that allows HMI and application


data which uses HTML display format to provide casual access of process
graphic displays.
Real-time Database a true Client/Server architecture where a real-time
database on the server provides data to a number of client applications
including:
o Operator stations
o Microsoft office applications (such as Microsoft Excel or Microsoft
Access)
o Internet explorer
Open Systems incorporates open technologies and standards including
SQL, ODBC, DDE, Visual Basic, and other OLE for process control.
Infrastructure in cooperate alarm/event management system; configure
reports, history collection and a variety of standard system trends.
On-line documentation provides users access to system information and
documentation.
Interfaces Data acquisition ability from a wide variety of remote terminal
units and controllers.

Other powerful supervisory control features include:










Integrated detail displays, custom graphics, alarms, history, and reports


Standard control functions
Operator security
Redundant Windows XP/server operation
A common interface for SCADA and other control types such as Hybrid
Control
Database and diagnostic integration with process and discrete controllers
Graphical building tools
Standard and user-definable application templates
International system and local language support

Sewage Treatment Plants

Volume 4

239

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Optional applications such as Alarm Pager interface, Downtime Analysis,


and statistical Process Quality Control

Standard facilities shall include but not limited to the followings:


Windows based HMI

Multiple local and remote operator stations


Interface: TCP/IP, fieldbus, Modbus, Hart

Support for redundant controller/RTU communications

Integration of multiple systems


Real-time data access for a wide variety of process connected devices
Supervisory data acquisition and control of controllers and remote terminal
units
alarm management
Extensive historian and trending
Flexible standard or customized reports
Optional Live Video Capture integration
Industry standard local and wide area network integration
Secure data integration with third party applications
ActiveX Document and Scripting support

C-6

Operator Interface

The operator interface station shall allow object based graphics to provide the
HMI for the user with object concern. The system shall employ industry de-factor
standards, such as Microsoft Windows, HTML and the Internet so as to minimize
operator training due to familiarity of operating environment.
Critical information is conveyed using dedicated enunciators for alarms, controller
communication failures, operator/controller messages and equipment downtime
conditions. A dedicated alarm line shows the most recent (or oldest) highest priority,
unacknowledged alarm at all times.
Software system displays shall include but not limited to the followings: Menu/navigation displays
Alarm summary
Event summary
Trends
Operating groups
System status displays
Configuration displays
Loop Tuning displays
Diagnostic and maintenance displays
Summary displays

240

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Optional Live Video integration shall provide remote viewing and viewing control
features.
Security software feature shall provide restricted access, no access and full access
(plant management).
Network access shall permit authorized operator stations on a network to share a
preconfigured number of connections to the system. This allows a number of users
on a network to access production data on off-line basis.

C-7

Database

The SCADA software shall but not limited to the following real-time database:
Analog configuration parameters
Digital configuration parameters
Accumulator configuration parameters
User defined configuration parameters
Each point in the database has a number of associated configurable parameters, all
of which can be referenced relative to a single tag name.
SCADA shall maintain the real time database that requires frequent high-speed
access as memory resident information and other less frequently accessed data as
disk resident data. Memory resident data is logged to data storage device every
specified time frame defined by the administrator to minimize the loss of data in
the event of loss of power.

C-8

Alarm/Event Management

The SCADA software System shall provide comprehensive alarm and event detection,
management, and reporting facilities. Alarm presentation of alarm / event management
shall include but not limited to the followings:







Multiple alarm priorities


Dedicated alarm zone
Configurable alarm priority colors
Associated display
Audible alarms
Alarm cutout
Area assignment
Operator log

Sewage Treatment Plants

Volume 4

241

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Hierarchical alarming
Alarm/event reporting
Alarm/communication/ message/downtime annunciator
Alarm priority escalation

The standard Alarm Summary display shall allow operators to focus on the problem
at hand by supporting filters. Alarms may be filtered by:


Area or location or unit processes


Acknowledge Status
Priority

Colors for the various priority levels of alarms can be configured by the user for
display purposes in the Alarm Summary and on custom graphics. The recommended
color codes are provided in Appendix 1. The software shall support configuration
of alarm priority colors and display on all process graphic displays to enables
operators immediately determine critically of the alarm.
The alarm shall annunciate in the status zone blinks with the color of the highest
priority for unacknowledged alarm. The alarms configuration shall consist but not
limited to the followings:





SPV Hi
SPV Lo
Transmitter Hi
Transmitter Lo
Trip
Time out

With each of the configured alarms assigns a priority ranging from "Attention" acknowledge of non-critical alarm that required maintenance attention, "Responsive"
- action required with predefined period, "Urgent" - action required immediately.
The Alarm/Event summary shall list but not limited to the followings:
Alarms

Alarm Acknowledgments
Return to normal

Operator Control Actions

Operator Login & Security Level Changes


On-line Database Modifications
Communications Alarms

System Restart Messages


242

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

C-9

Historian

Historical trend shall provide wide range of sampling frequencies in both datapoint and average formats. The history trend intervals are shall be able to but not
limited to the following displays:
second data-point of pre-defined scale
minute data-point of pre-defined scale
hour data-point of pre-defined scale
minute-average of pre-defined scale
hour-average of pre-defined scale
day-average of pre-defined scale
Month-average of pre-defined scale
The historical data is to be display in various formats describe herewith:
Graphical trend plot displays (average, max, min, and other statically
format)
Tabulation displays (average, max, min, and other statically format)
Query databases of selected parameters.

C-10 Graphical Trending


Graphical trending configuration shall be able to configure by selecting the parameters
to be plot and its time-scales. Minimum trend types shall include but not limited
to the followings:
Single and Multi bar graphs (selectable scales)
Single and Multi-line trends plot (selectable scales)
Multi-range trends plot (selectable scales)
X-Y line and scatter trend plots (selectable scales)

Mathematical plots (logarithm scale, moving average, etc)

Functions provided for analyzing and manipulating data include:


Combination real-time/historical plots
zooming, panning, and scrolling
Configurable trend density
Saving of trend plot and expert to various format (*.xls, HTML, XLM,
etc)
clipboard copy/paste enable

Sewage Treatment Plants

Volume 4

243

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

C-11 Report Format


The software shall provide but not limited to the following report formats:



Alarm/Event Log reports - selectable time frame, filterable events and


alarms to enable traceability of alarm.
Exportable Excel / Access format - able to save selected data/report format
to Microsoft Excel/Access format.
Statistical data analysis format - generates reports of selectable statistical
functions such as Max/Min and standard deviation.
Point Attribute Log - displaying specific attributes selectable from a
list.

Reports should be generated as required time frame (interval), event-driven, or ondemand basis. Report may be directed to screen, printer, file, or directly to another
computer for analysis or viewing electronically.

C-12 Security
The SCADA software shall provide configurable security levels, control levels
and area assignments. These may be configured for each individual operator or
alternatively for each operator station. The security levels shall be able to configure
the following security levels:
Level
Level
Level
Level

1:
2:
3:
4:

Sign-on for View mode only


View only mode with alarm acknowledge
Level 2 plus control of field parameters
Level 3 plus field parameters of level 4, configure standard system
infrastructure such as reports
Level 5: Level 4 plus user configured field parameters
Level 6: Unlimited access
Operator sign-on/sign-off shall be logged. Any actions initiated by an operator are
logged in the Event database with the operator identifier. In addition any control
actions to a given point is only allowed if the control level configured in the
operator profile exceeds the level assigned to the point.
Logon password shall not be less than 6 alphanumeric characters and shall be
encrypted. Operators may change own passwords; however, new password shall
not be the same as the last 10 passwords used in the previous 3 months. Three
unsuccessful attempts of logon shall lock the operator out for a lock-out period.
Once logged on, an operator can log off at any time or will be automatically signed
off after a defined period of inactivity.

244

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Area assignments limit operator access to graphics, alarms and point data to assigned
areas, providing effective plant partitioning. Individual operator profiles, including
security levels, control levels and area assignments, are activated when operators
sign on to the system. In addition, area profiles can be created enabling plant areas
to be enabled or disabled for control, between certain time and date criteria.

C-13 Scripting
The software shall have the VB or VBA scripting language enable to allow user to
create script that will run when a display is active or scripts can also be attached
to server objects like point parameters, alarm events, report completion and other
events.

C-14 Interfaces
SCADA software provides Data Acquisition and Control facilities to communicate
with a wide range of controllers and Remote Terminal Units (RTUs). The controllers
connection type shall comply with the following communication protocol:
Serial / TCP/IP / ControlNet / Modbus+ / ASCII / TCP/IP / Ethernet
Data Acquisition supports acquisition of data using either:
Periodic Scanning

C-15 Distributed Server Architecture


Distributed Server Architecture is integrated processes when there are multiple control
stations, or for segmenting control across units, providing the ultimate flexibility
for both operations and control. Distributed Server Architecture also provides the
maximum flexibility for geographically distributed sites.

C-16 Web Server


SCADA software shall provide Web Server capability to provide integration
mechanism for plant-centric operational information. Based on the SCADA software
Distributed Server Architecture, a web server bridges the Process Control and
Enterprise domains, dynamically tracking the pulse of the enterprise. Web server
brings many benefits to the end user:

Isolation of non-critical enterprise functions from the process control


system
Consolidated business system integration to/from many SCADA software
systems

Sewage Treatment Plants

Volume 4

245

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Consolidation of casual users accounts and licenses in one location


Cross-system reporting
Minimal engineering requirements

C-17 Digital Video Monitoring


The software may have optional Digital Video Monitoring that integrates digital
video controls and storage with the software to assist in process monitoring. Some
of the features are:




Remote monitoring of unmanned sites


Integration with SCADA software, providing event-based capture and
storage of video images
Event-activated, user-activated, and scheduled recording
Ability to search stored video, based on SCADA software events
Scalability from 4 cameras to more than 1,000 cameras.

The DVM shall base on open system hardware that digitizes video from standard
video cameras and transports the video to SCADA software clients anywhere on
the network for real-time viewing.

C-18 Integrated Maintenance Management


Integrated Maintenance Management (IMM) delivers computerized maintenance management
system (CMMS) completely integrated with SCADA software. IMM shall deliver but

not limited to the following key benefits:





More efficient preventive and predictive maintenance


Reduced downtime of critical plant equipment
Effective work scheduling
Automated creation of work orders from SCADA software events and data
values

IMM enables the automated creation, assignment, tracking and closing of maintenance
work orders. If required, work orders can also be manually raised. This is all
managed from either your IMM SQL server database with full access available
through the open Web-based interface of IMM.

246

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

C-19 Application Report


The SCADA software shall have the capability to produce but not limited to the
following reports:





Batch Report
Downtime analysis
Schedule maintenance
Statistical Process & Quality Control (SPQC)
Event archiving
Alarm messaging (SMS or pager)

Batch Reporting integrated reporting of batches process data, to be compiled


and archived by the SCADA software. The batch reports either as a CSV file or
Microsoft Excel, if available.
Downtime Analysis to detect, record and code any equipment breakdowns or process
delays to provide plant downtime analysis. A list of all current downtime events is
maintained as well as the history of previous downtime events, with each assigned
a category and a reason code. Downtime reports may be printed periodically or
on-demand, showing downtime duration sorted by categories and reasons.
Schedule Maintenance allows supervisory control to schedule at a specified time.
The maintenance report of the equipment is to be reported.
Statistical Process & Quality Control (SPQC) - generates statistical report of average
(of specified time period) of the real-time data collected by the system.
Event Archiving archiving events logged data by the system that based on sampling
frequency and storage capacity.
Alarm Messaging reports the alarm messages sent designated supervisors. The report
shall incorporate summary of alarm messages by alarm type and supervisors.

C-20 Application Programming Interface


Application programming interface (API) shall be provided for interfacing with
SCADA software server and the client network based.
The API (programmed in C/C++(visual) or programmed in VB (Visual Basic)) on
the server includes the following functions:

read and write to control module parameters in the database


access to historical data

Sewage Treatment Plants

Volume 4

247

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

initiate supervisory control actions


access to the alarm/event subsystem
access to user-defined database
provide a prompt for operator input
create alarms/events

C-21 User Documentation


SCADA software documentation shall be made available in three basic forms:

Electronic On-line Documentation using HTML Internet Browser

On-line Help (F1 function key from within applications)


Printed documentation

C-22 Specifications and Sizing


SCADA software Client/Server Specifications

Basic Server Workstation Specifications


Processor
Memory
Hard Disk Size
Display Resolution
Operating System (Minimum)
Network Protocols

Pentium Processor (Latest version)


1 GB
200 GB
1024 x 768, 65K colors
Microsoft Windows (Latest edition)
TCP/IP

Basic Client Workstation


Specifications
Processor
Memory
Hard Disk Size
Display Resolution
Operating System (Minimum)
Network Protocols

248

Pentium Processor (Latest version)


1 GB
200 GB
1024 x 768, 65K colors
Microsoft Windows NT (Latest
edition)
TCP/IP, NFS

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

SCADA software Server Performance

Operational Display Update


Maximum Continuous Display Update Rate

1 sec

Typical Field Change to Display Update Time with


100 Parameters Per Display on a Single Station/
Server

< 2 sec

Typical Display Call Up Time with 100 Parameters


on a Single Station/Server (call up time is dependent
on display complexity; this excludes the first initial
call up)

< 2 sec

SCADA Storage Sizing

Standard
Sampling
Rate

Default
Duration

1 minutes

24 hours

1441

69 days

100 000

6 minute
average

7 days

1682

416 days

100 000

1 hour
average

7 days

170

11.4 years

100 000

8 hour
average

3 months

281

91.2 years

100 000

24 hour
average

1 year

368

273.8 years

100 000

Sewage Treatment Plants

Default
Samples

Volume 4

Maximum
Duration

Storage Capacity
(maximum no. of
samples)

249

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Attachment C - 1:
Status/Alarm
Event State

250

Color Coding for Equipment Status

Color & Blinking


Status

Notes of Event

Running

Green (Non-Blinking)

Equipment is in operating
status

Standby

Red (Non-Blinking)

Equipment is in standby
operating status

Off

Red (Blinking)

Equipment is Off or Manual


mode.

Trip

Amber (Blinking):

Equipment Tripped due to the


followings reasons:
1) ELR detection;
2) PSR detection;
3) Over-current;
4) Over-heated motor;
5) MCB Trip;

SP High Level

Yellow (Non-Blinking)

Alarm event of high level than


set point

SP Low Level

Light Blue (NonBlinking)

Alarm event of lower level than


set point

Transmitter Hi

Yellow (Blinking)

Alarm event due to transmitter


high (<=4mA) value.

Transmitter Lo

Light Blue (Blinking)

Alarm event due to transmitter


low (<=4mA) value.

Time Out

Amber (Blinking)

Alarm due to time out by PLC


timer or other timer.

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Instrumentation Panel - Local

Instrumentation Panel - Remote


Instrumentation Panel - Battery
Low
TNB Power (kWh meter)

PLC System

PLC (battery Low)

DO

DI

AO

Indicator

Data Record

Indicator

Measure

Battery Charger

Penstock

SCADA Control /
Monitoring

Indicator
Indicator

Analog (A)/
Digital (D)
AI

Description
of Control
Point
(For Each
Equipment)

Description of Monitoring
Point
(For Each Equipment)

Instrumentation
Panel

SCADA Control and Monitoring Function


Requirement

Qty

Item

Attachment C - 2:

Alarm Low (Fault Report)

Alarm (Fault Report)

Penstock Panel: Manual Switch

Indicator

Penstock Position Actuator (%)

IP open close
control

RTU via RS-485 Serial Link


Alarm - High torque

Penstock - Fully Open

Indicator

Penstock Panel: Auto Switch

Penstock - Fully Close

Penstock - To Open / To Close

Penstock - UPS Low

UPS (battery Low)


Penstock

Primary Coarse Screen

Indicator

Inlet

Indicator
Remote
Control
Indicator

Measure

Screen - Trip

Indicator

Alarm (Fault Report)

Screen - Manual Mode

Screen - To Start / Stop

Screen - Run-hour record

Indicator
Remote
Control
Reset of HourRun meter

Software counter running hours

Differential Level : Upstream

Differential
Downstream

Control Start / Stop operation by


diff. level

Screen - Run

Indicator

Screen - Auto Mode

Level

RSP Pumps
Pump - Run
Pump - Trip
Pump - Off (MCCB)

Pump - To Start / Stop

Pump - Run-hour record

Pump - Ampere
Pump - Voltage

Sewage Treatment Plants

Indicator

Indicator
:

Indicator

Indicator
Indicator
Indicator
Remote Start/
Stop
Reset of HourRun meter
Reading
Reading

Counter - Number of start / stop

Ref level for upstream.

1
1
1

1
1
1

Record number of Start / stop


Alarm (Fault Report)
Record non-operation hours

Software control / PLC

Software counter running hours

1
1

1
1

Record when operation


Record when operation

Volume 4

251

AO

DI

DO

RJ45 / RS485

Cut-off operation
Control Start / Stop operation
by diff. level
Control Start / Stop operation
by diff. level
Control Start / Stop operation
by diff. level
Control Start / Stop operation
by diff. level

For fault identification (Alarm


Fault report)
For fault identification (Alarm
Fault report)
For fault identification (Alarm
Fault report)
For fault identification (Alarm
Fault report)
For fault identification (Alarm
Fault report)

Record number of Start / stop

Record non-operation hours

Pump - Soft Starter Amp/Volt


Comm.

Parameters Setting
/ Review

Float level
US Level

Float Level - L0 On/Off


Float Level - L1 On/Off

Level
measurement

Float Level - L2 On/Off

Indicator

Float Level - L3 On/Off

Indicator

Float Level - L4 On/Off

Indicator

Float Level - L0 Fault

Indicator

Float Level - L1 Fault

Indicator

Float Level - L2 Fault

Indicator

Float Level - L3 Fault

Indicator

Float Level - L4 Fault

Indicator

Sump Pump / Dewatering


Pump
Pump - Run

Indicator

Pump - Off (MCCB)


Pump - To Start / Stop

Pump - Trip

Indicator
Indicator

Indicator

Pump - Run-hour record

Ampere / Volmeters

Indicator
Remote Start /
Stop
Reset of Hour-Run
meter

Pump - Ampere

Reading

Float level

Pump - Voltage

Alarm (Fault Report)

Software control / PLC

Software counter running hours

Record when operation

Record when operation

Indicator

Screen - Run

Indicator

Record number of Start / stop

252

Screen - Trip

Screen - Auto Mode

Screen - Manual Mode

Screen - To Start / Stop

Indicator

Indicator
Indicator

Remote Control

1
1

Volume 4

1
1
1

Indicator

Float Level - L0 Fault

Float Level - L1: ON / OFF

Indicator

Float Level - L1 Fault

Secondary Fine Screen

Indicator

Cut-off operation
Control Start / Stop operation
by diff. level
For fault identification

Float Level - L0: ON / OFF

Reading

SCADA Control /
Monitoring

AI

Description of
Control Point
(For Each
Equipment)

Description of Monitoring
Point
(For Each Equipment)

Analog (A)/
Digital (D)

Qty

Item

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

For fault identification

Alarm (Fault Report)

Malaysian Sewerage
Industry Guidelines

Screen c/v - Trip

Screen c/v - Run

Screen c/v - Auto Mode

Screen c/v - Manual Mode

Screen c/v - To Start / Stop

DO

DI

Mechanical Differential Level :


Upstream
Mechanical Differential Level :
Downstream

Screenings Conveyor

AO

Screen - Run-hour record

AI

Description of
Control Point
(For Each
Equipment)

Description of Monitoring
Point
(For Each Equipment)

Analog (A)/
Digital (D)

Qty

Item

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

SCADA Control /
Monitoring

Software counter running hours

Indicator

Indicator

Ref level for upstream.

Indicator

Record number of Start / stop

Reset of Hour-Run
meter

Indicator

Indicator

Indicator

Remote Control

1
1

1
1
1

Control Start / Stop operation


by diff. level

Alarm (Fault Report)

Screen c/v - Run-hour record

Reset of Hour-Run
meter

Screenings Wash Water Pumps

Software counter / Interlock


with screen operation with delay
off.

Wash-water Pump - Trip

Indicator

Alarm (Fault Report)

Wash-water Pump - Run

Wash-water Pump - Auto Mode


Wash-water Pump - Manual
Mode
Wash-water Pump - To Start /
Stop

Indicator

Indicator

1
1

Indicator

Remote Control

Wash-water Pump - Run-hour


record

Reset of Hour-Run
meter

Grit Blower - Run

Indicator

Indicator

Software counter / Interlock


with screen operation with delay
off.

Alarm (Fault Report)

Grit / Grease System


Grit Blower - Trip

Grit Blower - Auto Mode

Grit Blower - Manual Mode

Grit Blower - To Start / Stop

Indicator

Indicator

Remote Control

1
1

1
1
1

Grit Blower - Run-hour record

Reset of Hour-Run
meter

Grit Pump : On

Indicator

Grit Pump - To Start / Stop

Remote Control

Record number of Start / stop

Grit Pump : Trip

Indicator

Record number of Start / stop

Software counter / software


Timer control operation by
rotation.
Record number of Start / stop
Alarm (Fault Report)

Grit Pump - Run-hour record

Reset of Hour-Run
meter

Grit Classifier : On

Indicator

Software counter / software


Timer control operation by
rotation.
Record number of Start / stop

Grit Classifier - To Start / Stop

Remote Control

Grit Classifier : Trip

Indicator

Grit Classifier - Run-hour record

Reset of Hour-Run
meter

Grit Auger : On

Indicator

Grit Auger : Trip

Sewage Treatment Plants

Indicator

Volume 4

Alarm (Fault Report)

Software counter / software


Timer control operation by
rotation.

Record number of Start / stop


Alarm (Fault Report)

253

Description of
Control Point
(For Each
Equipment)

AO

DI

DO

SCADA Control /
Monitoring

AI

Description of Monitoring
Point
(For Each Equipment)

Analog (A)/
Digital (D)

Qty

Item

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Grit Auger - To Start / Stop

Remote Control

Grit Auger - Run-hour record

Reset of Hour-Run
meter

Grit Drum Screen : On

Indicator

Software counter / software


Timer control operation by
rotation.

Record number of Start / stop

Remote Control

Grit Drum Screen : Trip


Grit Drum Screen - To Start /
Stop

Grit Drum Screen - Run-hour


record

Reset of Hour-Run
meter

Auxiliary

Software counter / software


Timer control operation by
rotation.

Indicator

Status

Indicator

Alarm (Fault Report)

Indicator

Alarm (Fault Report)

Reading

Record

Reading

Record

Reading

Indicator

Reading

Record

LV System
Main LV Board Main Breaker
: ON
Main LV Board Main Breaker :
TRIP (Earth Fault)
Main LV Board Main Breaker :
TRIP (Over Current)
Main LV Board Main Breaker :
Ampere
Main LV Board Main Breaker :
Voltage
Room Temperature Monitoring
/ Alarm
Bus Couple : ON

kWHr Meter:

HT System

Bus Couple : OFF

HT Income Panel VCB : ON


HT Income Panel VCB: TRIP
(Earth Fault)
HT Income Panel VCB: TRIP
(Over Current)
HT Income Panel VCB: Ampere

Battery Charger

HT Income Panel VCB: Voltage


Battery Low

Room Temperature Monitoring


/ Alarm

254

Indicator

Indicator

Indicator

Alarm (Fault Report)

Status

Indicator

Alarm (Fault Report)

Indicator

Alarm (Fault Report)

Reading

Record

Indicator

Record (Alarm fault)

Reading

Indicator

1
1

1
1

Record

Record (Alarm Low)

Reading

Record / Alarm (High)

kWHr Meter

Transformer System

Reading

Record

Transformer Pressure Alarm

CO2 System
TNB Room: CO2 Panel
Activated
Switch Gear: CO2 Panel
Activated
Transformer Room: CO2 Panel
Activated

Indicator

Record / Alarm (High)

Transformer Temperature Alarm

Indicator

Record / Alarm (High)

Indicator

Record / Alarm (activated)

Indicator

Record / Alarm (activated)

Indicator

Record / Alarm (activated)

Volume 4

Malaysian Sewerage
Industry Guidelines

CO2 Panel DC supply Battery


Low

Gen Set System

Gen Set - Trip

Gen Set - Run

Gen Set - To Start / Stop


(Remote)
Gen Set - To Stop (Remote)

Gen Set - Run-hour record

Gen Set -Battery Charge

Gen Set -DC Battery Low

Gen Set -Diesel Fuel oil low

Surge Vessel Compressors


System
Air Compressor - Run

Air Compressor - Auto Mode

Air Compressor - Trip

Air Compressor - Manual Mode

Air Compressor - To Start / Stop


Air Compressor - Run-hour
record
Surge Vessel Level Indicator

Fan : Manual

Surge Vessel Pressure Indicator

Force Ventilation: Grit System


Fan : Auto
Fan : ON / OFF

Indicator
Indicator
Indicator

Indicator

Remote Start /
Stop
Remote Start /
Stop
Reset of Hour-Run
meter
Indicator
Indicator

Record / Alarm (activated)

Record / Alarm (activated)

Record / Alarm (activated)

Record number of Start / stop

Alarm (Fault Report)

Software control / PLC

Software control / PLC

Software counter running hours

Record / Alarm (Fault)

Record / Alarm (Low)

Record / Alarm (Low)

Indicator

Record number of Start / stop

Indicator

Indicator

Indicator

Remote Control
Reset of Hour-Run
meter
Level Measure
Pressure Measure

Indicator
Indicator
Indicator

Scrubber Fan : Auto


Scrubber Fan : ON / OFF

Indicator
Indicator

Indicator

Scrubber Fan : Trip


Scrubber Fan : To Start / Stop

Aeration Blower

Indicator
Remote Start /
Stop

Blower - Trip

Indicator

Sewage Treatment Plants

Record / Alarm (activated)

Blower - Off (MCCB)

Gas Scrubber System

Blower - Run

Indicator
Remote Start /
Stop

Indicator

Fan : Trip
Fan : To Start / Stop

Scrubber Fan : Manual

Indicator

DO

Indicator

DI

Main Switch Room: CO2 Panel


Activated
MCC Room: CO2 Panel
Activated
Gen Set- CO2 Panel Activated

SCADA Control /
Monitoring

AO

Description of Monitoring
Point
(For Each Equipment)

Analog (A)/
Digital (D)
AI

Description of
Control Point
(For Each
Equipment)

Qty

Item

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Indicator

Indicator

1
1

1
1

Alarm (Fault Report)

Software counter running hours

Status & Software counter


running hours

1
1

1
1

Record number of Start / stop

Volume 4

Status & Software counter


running hours
Alarm (Fault Report)

Alarm (Fault Report)

Alarm (Fault Report)

Record non-operation hours

255

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Blower - Ampere
Blower - Voltage

Temperature Sensor

Blower - Temperature
Air Flow Meter
Air Flow Meter

Force Ventilation: Blower


Room
Fan : Manual

Fan : Trip

Fan : Run-Hour record

Fan : Auto
Fan : ON / OFF

Fan : To Start / Stop

D.O. Meter
D.O. Meter

Anoxic Mixer

Anoxic Mixer - Run


Anoxic Mixer - Trip

Anoxic Mixer - Off (MCCB)

Anoxic Mixer - To Start / Stop

Anoxic Mixer - Run-hour record

Anoxic Mixer - Ampere

Anoxic Mixer - Voltage

Primary or Secondary Clarifier


Clarifier - Run

Clarifier - Trip

Clarifier - Off (MCCB)

Clarifier - To Start / Stop

Clarifier - Run-hour record

Clarifier - Ampere

256

Clarifier - Voltage

Reset of Hour-Run
meter
Measure
Measure

Software control / PLC

RTU via RS-485 Serial Link


Software counter / software
Timer control operation by
rotation.
Record when operation

Measure

Measure

Indicator
Indicator
Indicator
Remote Start /
Stop
Reset of Hour-Run
meter

Indicator
Indicator

Remote Start /
Stop
Reset of Hour-Run
meter
Measure
Measure

Indicator
Remote Start /
Stop
Reset of Hour-Run
meter
Measure

Record when operation

Record & Alarm (High Temp)

Record & Alarm (low level)

Status & counter no. of start /


stop
Alarm (Fault Report)

Status & counter no. of start /


stop
Alarm (Fault Report)

Software control / PLC

Software counter

Record when operation

Indicator

Indicator

Measure

Indicator

Measure

Indicator

DO

Blower - Run-hour record

DI

Blower - VSD Parameters

AO

Remote Start /
Stop
Speed Control

SCADA Control /
Monitoring

AI

Blower - To Start / Stop

Analog (A)/
Digital (D)
Qty

Item

Description of
Control Point
(For Each
Equipment)

Description of Monitoring
Point
(For Each Equipment)

Record / Control Speed &


Alarm (Low)

Record non-operation hours

Record when operation

Software control / PLC

Software counter

Record when operation

Volume 4

Software counter / software


Timer control operation by
rotation.

Status & counter no. of start /


stop
Alarm (Fault Report)

Record non-operation hours

Record when operation

Malaysian Sewerage
Industry Guidelines

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Description of
Control Point
(For Each
Equipment)

Analog (A)/
Digital (D)
AI

AO

DI

DO

SCADA Control /
Monitoring

Qty

Item

Description of Monitoring
Point
(For Each Equipment)

Pump - Run

Indicator

Pump - Trip

Indicator

Pump - To Start / Stop

Software control / PLC

Pump - Run-hour record

Software counter

Pump - Ampere

Indicator
Remote Start /
Stop
Reset of Hour-Run
meter
Measure

Status & counter no. of start /


stop
Alarm (Fault Report)

Record when operation

RAS/WAS Flow Rate Meter

Pump - Off (MCCB)

Pump - Volt

Sludge Flow Meter

RAS/WAS Flow Rate Totalizer

Flow Meter System

Flow Meter
(Data record of flow rate)

Measure

Measure

Measure

1
1

Record non-operation hours

Record when operation

Record
Record

Measure

Record

Flow Meter (Totalizer)

Gravity Thickener

Measure / Reset

G. Thickener - Run

Indicator

G. Thickener - Trip

Indicator

SCADA Software Accumulator

Status & counter no. of start /


stop
Alarm (Fault Report)

G. Thickener - To Start / Stop

G. Thickener - Run-hour record

G. Thickener - Ampere

G. Thickener - Off (MCCB)

G. Thickener - Voltage

Thickened Sludge Digester Feed


Pump: Primary & Secondary

Indicator
Remote Start /
Stop
Reset of Hour-Run
meter
Measure
Measure

Feed Pump - Run

Indicator

Feed Pump - Trip

Indicator

Feed Pump - To Start / Stop

Feed Pump - Run-hour record

Feed Pump - Ampere

Indicator
Remote Start /
Stop
Reset of Hour-Run
meter
Measure

Feed Pump - VSD Parameters

Speed Control

Sludge Feed Flow Rate Meter

Measure

Feed Pump - Off (MCCB)

Feed Pump - Voltage

Sludge Flow Meter

Sludge Feed Flow Rate Totalizer

Gas Blower

Measure

Measure

Gas Blower - Trip

Indicator

Sewage Treatment Plants

Volume 4

Record non-operation hours


Software control / PLC
Software record of running
hours
Record when operation

Record

1
1

Status & counter no. of start /


stop
Alarm (Fault Report)

Indicator
Indicator

Record when operation

Gas Blower - Run


Gas Blower - Off (MCCB)

Software control / PLC


Software record of running
hours
Record when operation

Record when operation


Speed control : RTU via RS-485
Serial Link

Record non-operation hours

Record

Status & counter no. of start /


stop
Alarm (Fault Report)
Record non-operation hours

257

Gas Blower - Run-hour record

Gas Blower - Ampere

Gas Blower - Temperature

Measure

Gas Blower - Voltage

Temperature Sensor
Gas Flow Meter

Gas Flow Meter

Digester Gas Detector Meters

Measure

Measure

DO

Remote Start /
Stop
Reset of Hour-Run
meter
Measure

DI

Gas Blower - VSD Parameters

SCADA Control /
Monitoring

AO

Analog (A)/
Digital (D)
AI

Description of
Control Point
(For Each
Equipment)

Description of Monitoring
Point
(For Each Equipment)

Qty

Item

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Speed control : RTU via RS-485


Serial Link
Software record of running
hours
Record when operation

Record & Alarm (High)

Record when operation

Record

Record & Alarm (Detection &


Fault)
Record & Alarm (Detection &
Fault)
Record & Alarm (High-Low &
Fault)
Record & Report

Record & Alarm (High-Low &


Fault)
Alarm (High)

H2S Meter at Dewatering House

Measure

Methane Gas Meter

Measure

PVRV Sensor Meter

Measure

Internal Digester Gas Analyzer

Floating Roof Gas Holder

Measure

Floating Roof Level

Measure

High Lever Alarm

Indicator

PVRV Sensor Meter

Measure

Alarm (Low)
Record & Alarm (High-Low &
Fault)

Indicator

Record & Timer

Indicator

Record & Timer

Indicator

Indicator

Program Control operation

Indicator

Status & counter no. of start /


stop

Indicator

Alarm (Fault Report)

Software control / PLC

Software control / PLC

Low Lever Alarm

Gas Flare System


Gas Control Actuator
Open
Gas Control Actuator
Close
Gas Control Actuator
Manual
Gas Control Actuator
Auto

Indicator

Valve: Full
Valve: Full
Valve:
Valve:

Gas Control Actuator Valve: ON

Gas Control Actuator Valve:


TRIP
Gas Control Actuator Valve: To
Turn Clockwise
Gas Control Actuator Valve: To
Turn Counter-Clockwise

Flare Igniter : Manual

Indicator

Flare Igniter : ON

Indicator

Pilot Light Igniter

Flare Igniter : Auto

Remote Start /
Stop
Remote Start /
Stop

Indicator
Indicator

Record & Alarm (flame


distinguished)

Program Control operation

Flare Indicator

Indicator

Pressure Indicator: Inlet

Measure

Program Control operation


Record & Alarm (flame
distinguished)

Record & Report Fault

Belt Press Feed Pump - Manual

Indicator

258

Pressure Indicator: Discharge

Sludge Feed Pump to Belt Press

Measure

Volume 4

Record & Report Fault

Malaysian Sewerage
Industry Guidelines

Description of
Control Point
(For Each
Equipment)

AO

DI

DO

SCADA Control /
Monitoring

AI

Description of Monitoring
Point
(For Each Equipment)

Analog (A)/
Digital (D)
Qty

Item

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Belt Press Feed Pump - Auto

Indicator

Belt Press Feed Pump - Run

Indicator

Belt Press Feed Pump - Trip


Belt Press Feed Pump - Off
(MCCB)
Belt Press Feed Pump - To Start/
Stop
Belt Press Feed Pump - Run-hour
record
Belt Press Feed Pump - Ampere

Indicator

Program Control operation


Status & counter no. of start /
stop
Alarm (Fault Report)

Indicator

Record non-operation hours

Software control / PLC

Speed Control

Indicator

Belt Press Feed Pump - Voltage


Belt Press Feed Pump - VSD
Parameters

Belt Press Compressors System

Air Compressor - Trip

Air Compressor - Run

Air Compressor - Auto Mode

Air Compressor - Manual Mode

Air Compressor - To Start/Stop/


Stop
Air Compressor - Run-hour
record

Sludge Cake Conveyor

Screen c/v - Trip

Screen c/v - Run

Screen c/v - Auto Mode

Screen c/v - Manual Mode

Screen c/v - To Start / Stop / Stop

Screen c/v - Run-hour record

Belt Backwash Washwater


Pumps
Washwater Pump - Run

Washwater Pump - Auto Mode

Washwater Pump - Trip

Washwater Pump - Manual Mode

Washwater Pump - To Start /


Stop / Stop

Remote Start /
Stop
Reset of Hour-Run
meter
Measure
Measure

Indicator

Indicator

Indicator

Remote Control
Reset of Hour-Run
meter

Indicator
Indicator
Indicator
Remote Control

1
1
1

Record when operation


Speed control : RTU via RS-485
Serial Link

Alarm (Fault Report)

Record number of Start / stop


Program Control operation

Software control / PLC

Software counter running hours

Alarm (Fault Report)

1
1

Indicator

Software record of running


hours
Record when operation

1
1

Program Control operation

Indicator

Record number of Start / stop

Indicator

Program Control operation

Indicator

1
1

Record number of Start / stop

Reset of Hour-Run
meter

Software counter / Interlock


with screen operation with delay
off.

Indicator

Alarm (Fault Report)

Remote Control

Washwater Pump - Run-hour


record

Reset of Hour-Run
meter

Polymer Preparation Unit

Software counter / Interlock


with screen operation with delay
off.

Polymer Mixing - Trip

Indicator

Alarm (Fault Report)

Polymer Mixing - Run

Polymer Mixing - Auto Mode

Polymer Mixing - Manual Mode

Polymer Mixing - To Start / Stop

Sewage Treatment Plants

Indicator

Indicator
Indicator

Remote Control

1
1

Volume 4

1
1
1

Software control / PLC

Record number of Start / stop


Program Control operation

Software control / PLC

259

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Description of
Control Point
(For Each
Equipment)

AI

AO

DI

DO

SCADA Control /
Monitoring

Qty

Item

Description of Monitoring
Point
(For Each Equipment)

Analog (A)/
Digital (D)

Polymer Mixing - Run-hour


record

Reset of Hour-Run
meter

Software counter / Interlock


with screen operation with
delay off

Polymer Dilution Skid - Trip

Indicator

Alarm (Fault Report)

Polymer Dilution Skid - Run

Polymer Dilution Skid - Auto


Mode
Polymer Dilution Skid - Manual
Mode
Polymer Dilution Skid - To Start/
Stop

Indicator

Record number of Start / stop

Indicator

Program Control operation

Indicator

Remote Control

Software control / PLC

Polymer Dilution Skid - Runhour record

Reset of Hour-Run
meter

Software counter / Interlock


with screen operation with delay
off.

Fan : Manual

Indicator

Fan : Run

Indicator

Fan : Off

Fan : To Start / Stop

Fan : Run-Hour record

Indicator
Remote Start /
Stop
Reset of Hour-Run
meter

Status & counter no. of start /


stop
Alarm (Fault Report)

Software record of running


hours

Force Ventilation: Sludge Feed


& Dewatering Room
Fan : Auto

Notes:
AI = Analog Input
Qty = Quantity

260

Indicator

AO = Analog Output DI = Digital Input

Volume 4

DO = Digital Output

Malaysian Sewerage
Industry Guidelines

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Attachment C - 3: Representation of SCADA Control Symbols


Attachment C - 3: Representation of SCADA Control Symbols
PUMPS & AERATION DEVICES
PUMPS & AERATION DEVICES

OFF MODE

EQUIPMENT


PUMPS
(Centrifugal)

PUMPS
(Progressive Cavity)
BLOWER

SURFACE AREATOR

Sewage Treatment Plants

234




ON MODE

































Volume 4

Volume 4

261

Malaysian Sewerage
Treatment Plant

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

ACCESSORIES & FITTINGS


ACCESSORIES & FITTINGS
EQUIPMENT

OFF MODE

ON MODE

Valves
(General)

BUTTERFLY VALVE

AGITATOR

CONVEYORS

CONVEYORS SCREW

262

Volume 4

Sewage Treatment Plants

Third Edition
Volume 4

Malaysian Sewerage
Industry Guidelines

Page 235

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

Appendix C - Supervisory Control and Data Acquisition System (SCADA)

OTHERS
OTHERS
SYMBOLS

EQUIPMENT
PLC CONTROLLER

WIRELESS COMMUNICATION

SCADA WORKSTATION

POWER TRANSMISSION

METER

COMPRESSOR

TANK

Sewage Treatment Plants

236

Volume 4

Volume 4

263

Malaysian Sewerage
Treatment Plant

Appendix D
Duty and Standby Requirements

Appendix D - Duty and Standby Requirements

266

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix D - Duty and Standby Requirements

Appendix D
Table D1
Table D2
Table D3
Table D4

Duty and Standby Requirements

Duty and Standby Requirements for Activated Sludge Systems


(Utilising Diffused Aeration)

Duty and Standby Requirements for Activated Sludge Systems


(Utilising Mechanical Surface Aerator)

Duty and Standby Requirements for Rotating Biological Contactor


Systems
Duty and Standby Requirements for Trickling Filter Systems

Sewage Treatment Plants

Volume 4

267

Appendix D - Duty and Standby Requirements

268

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix D - Duty and Standby Requirements

Sewage Treatment Plants

Volume 4

269

Appendix D - Duty and Standby Requirements

270

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix D - Duty and Standby Requirements

Sewage Treatment Plants

Volume 4

271

Appendix E
Glossary of Abbreviations

Appendix E - Glossary of Abbreviations

274

Volume 4

Malaysian Sewerage
Industry Guidelines

Appendix E - Glossary of Abbreviations

Glossary of Abbreviations
ABF

Activated Biofilter

AL

Aerated Lagoon

AS

Activated Sludge

ATU

Allyl Thio Urea

BOD

Biochemical Oxygen Demand

BOD5

Total Five Day Biochemical Oxygen Demand

CAS

Conventional Activated Sludge

CF

Certificate of Fitness

CMAL

Complete Mixed Aerated Lagoon

CMAS

Conventional Mode Activated Sludge

COD

Chemical Oxygen Demand

CPR

Cardio Pulmonary Resuscitation

DMF

Dual Media Filtration

DO

Dissolved Oxygen

DOE

Department of Environment

DOSH

Department of Occupational Safety and Health

DS

Deep Shaft

EA

Extended Aeration

EAMAS

Extended Aeration Mode Activated Sludge

F/M

Food to Microorganism ratio

FAL

Facultative Aeration Lagoon

FWSP

Facultative Waste Stabilisation Ponds

GRP

Glass Reinforced Plastic

HAZOP

Hazard and Operability Review

HRT

Hydraulic Retention Time

HRTF

High Rate Trickling Filter

MCRT

Mean Cell Residence Time

MLSS

Mixed Liquor Suspended Solids

MLVSS

Mixed Liquor Volatile Suspended Solids

Sewage Treatment Plants

Volume 4

275

Appendix E - Glossary of Abbreviations

276

MOD

Modified Oxidation Ditch

MP

Maturation Pond

MS 1228

Malaysian Standard 1228: Code of Practice for Design


and Installation of Sewerage Systems

OD

Oxidation Ditch

OP

Oxidation Pond

OASH

Occupational Safety and Health Act

PE

Population Equivalent

Qavg

Average Flow

Qpeak

Peak Flow

QRAS

Return Activated Sludge Flow

RAS

Return Activated Sludge

RBC

Rotating Biological Contactor

SBC

Submerged Biological Contactor

SBR

Sequential batch Reactor

SIRIM

Standards and Industrial Research Institute of Malaysia

SS

Suspended Solids

SPAN

Suruhanjaya Perkhidmatan Air Negara (National Water


Services Commission)

SST

Secondary Settlement Tank

STP

Sewage Treatment Plant

TDH

Total Dynamic Head

TF

Trickling Filter

TOL

Total Organic Load

VSS

Volatile Suspended Solids

WAS

Waste Activated Sludge

Volume 4

Malaysian Sewerage
Industry Guidelines

PRINTED BY
PERCETAKAN NASIONAL MALAYSIA BERHAD
KUALA LUMPUR, 2009
www.printnasional.com.my
email: cservice@printnasional.com.my
Tel: 03-92366895 Fax: 03-92224773

You might also like