Professional Documents
Culture Documents
I.CO.P.
Company Profile
I.CO.P. is a dynamic company much focused on the market and on technological
innovations. Its core business includes constructions, roadworks, water control
works, railway and road underpasses (constructed using innovative technologies),
microtunnelling and all kinds of special foundation works.
Established in the 60s, I.CO.P. became a joint-stock company in 1986. During the
years the company has been constantly growing and it has considerably improved
the technological level of the works, constructed employing the best techniques and
technologies available on the market and using all top standard equipments. This
has allowed the company to consolidate its market position all through the years.
Today I.CO.P. can offer a full range of specialized works: project and construction of
bridges and viaducts, construction of diaphragm walls, piles and micropiles, tie
beams and anchors, jet-grouting, sheet piling for different soil conditions. It is also
one of the two Italian companies using the freezing soil technology, a new kind of
technology that allows to temporary improve the soil conditions. Since 1992 I.CO.P.
has also been constructing underground crossings using the trenchless
technologies, which are less disruptive, environmentally friendly and more cost
effective than traditional methods, since they either minimise or eliminate surface
disruption allowing for the installation or renewal of underground utility systems with
minimum disruption of the surface.
A great effort has been made in the construction of underground crossings (sewers,
gas pipe lines, service pipes) using the microtunnelling technique. With over 70 km
of installed pipes, our company is a leader in the domestic and European market.
The search for technical solutions to fulfil construction requirements has led I.CO.P.
to invest remarkable resources in research and in the development of the
constructing processes. Many technical and operative solutions have been
developed and some of them are patented.
I.CO.P. offers the Customer an internal consulting and project service and a
constant commitment and dedication sharing its heritage of experience, built during
an over 50-year-long activity.
In order to always grant also full reliability and skills, since 1996 I.CO.P. has certified
its quality system according to the ISO 9001 (today called VISION 2000) standards.
It was one of the first Italian contractors to achieve this goal.
The focus on new technologies and a niche market oriented strategy are I.CO.P
resources for future challenges.
I.CO.P.
Construction and working perspectives
I.CO.P. is focusing in a niche market, where its human and technological resources
can be successfully employed, and in such sectors has tried to introduce innovative
techniques gaining a position of technological leadership in all kinds of deep
foundations works, underground works and specialized works in general.
In particular, over the last years I.CO.P has successfully introduced on the Italian
market the microtunnelling technology, becoming a leading company in the domestic
market. The company owns several sets of complete microtunnelling equipment,
which, fitted with special modification kits, can cover a whole range of sizes from
DN800 to DN3000, thus placing I.CO.P. among the first European companies in the
large-diameter industry. Today microtunnelling plays an essential role in the
activities of the company.
Main types of works I.CO.P. is specialized in:
Road and railway precast underpasses built on site and launched in 3/5
hours time during the night by oleodynamic jacking slabs.
Drilled piles driven into the ground by vibro close-ended casings and
subsequent casting of concrete (without soil removal).
Rock bolting
Execution of drains
Jet-panel walls
Grouted columns executed by drilling and mixing natural soil using special
rotating augers (DEEP MIXING)
I.CO.P.
Organization and Resources
I.CO.P. is a leading construction company located in Friuli Venezia Giulia region
(North East of Italy) operating both in Italy and abroad.
The value of production outside the Italian territory is on average between 15% and
20% of total production.
YEAR
TURN OVER
I.CO.P. GROUP
2008
70.608.913
2009
87.147.853
2010
78.053.201
2011
66.296.530
2012
97.501.848
total
399.608.345
I.CO.P.
Health and Safety System
In order to guarantee the Clients a constant commitment on reliability and
responsibility, since 1996 ICOP has certified its Quality System as per the
international norms called ISO 9001.
It has been one of the first Italian contractors to reach such an aim.
Furthermore, the environmental issues for a sustainable development, which are
becoming more and more relevant in the latest years, have led the Company to take
the ISO norm 14001:2004 as international standard reference for the certification of
its quality system, respecting the main environmental dispositions regarding its filed
of activity. Environment protection, prevention from pollution and social economical
request have all been considered.
To the previous two certificates, a third relevant one follows: the consciousness of
the great importance of the issues related to health and safety in working areas led
I.CO.P. S.p.A to clearly demonstrate its commitment, obtaining the certificate
according to the international norm OHSAS 18001:2007 and carefully managing the
risks. All prevention and protection measures have been adopted.
Recently, to complete the certification process, the company has certificated its
managing system according to the terms of the SA 8000:2008 norm. In particular it
refers to its social responsibility. The aim is to promote profitable cooperation among
the personnel mutually beneficial relationship outside and inside the company, able
to motivate people and to give effect to rights of man and labour rights.
Having gained the 4 certificates is considered by the company a starting point and a
challenge to constantly improve the managing systems and the working methods, to
continue cooperating and involving all the members of the organization.
COMPANY ORGANIZATION
AND DATA
MICROTUNNELLING
BRIEF DESCRIPTION
OF THE MICROTUNNELLING TECHNOLOGY
I.CO.P.
Microtunnelling technology and its employment in the construction of underground
crossings
Over the last years, the rapid growth of the transport and communication systems
has caused a growing demand for tunnelling equipment able to operate in
increasingly difficult conditions.
Both the techniques and the equipment in this industry have been improved,
especially when dealing with loose and watered soils, which generally is the most
complex site condition facing tunnel construction.
On the one hand, the construction industry has managed to build tunnels of
increasingly large size also thanks to the development of techniques and
equipment once inconceivable, such as soil consolidation, special injections,
freezing, shielded equipment and so on on the other hand, in the small-diameter
tunnel construction the sector was still bound by the minimum size required for
personnel entry and inspection. This is why until about ten years ago it was not
possible to build tunnels smaller than1500 mm in diameter.
The improvement of the shielded cutter heads technology from large- to small-size
tunnelling has led to the development of the micro tunnelling method, which was
developed for two main reasons.
One was the massive spread of technological services in the cities, which has
caused an intensive and often not well-planned exploitation of the urban
underground. The installation of sewers, water supply systems, gas pipelines and
power and telecommunication networks has in fact turned the underground into a
virtually untouchable maze of pipes and cables.
Owing to this situation and to the lack of adequate work areas, the installing and
maintenance of underground utilities are usually carried out using traditional
techniques, which involve deep excavations and interruptions of other utility lines
and of the traffic flow.
Studies carried out in different parts of the world have shown that the costs citizens
have to bear because of the inconveniences deriving from open-cut trench
excavations in urban areas far exceed the building costs.
The second factor that favoured the development of the microtunnelling technique
was the application in civil engineering of advanced techniques of miniaturization,
laser guiding and so on.
In conclusion, the need to develop techniques other than trench excavation has
favoured the advent of microtunnelling methods and small-size pipe guiding
techniques where no personnel entry is required.
Microtunnelling, which was first introduced in Germany and Japan at the beginning
of the 1980s, is now successfully employed all over the world.
The Microtunnelling Process
Today microtunnelling allows pipes to be automatically installed without digging open
trenches and without employing manpower inside the tunnel. The full-face
excavation is carried out by a cutter head (also called microtunneller) that is pushed
into the ground together with the pipe to be installed (see Figure 1).
After locating the depth at which the pipe is to be laid so as to avoid interferences
with existing infrastructures, a starting shaft and an arriving shaft are excavated. The
microtunneller is initially positioned inside the starting shaft, from where it is pushed
into the ground, together with the pipe, by the main thrust station until it reaches the
arriving shaft.
Microtunnelling is the best solution for building rail, road and river crossings in urban
areas, as it ensures an accurate construction in all ground conditions with minimal
restoring requirements, thanks to the mechanical and hydraulic support offered to
the front face, the constant monitoring of the microtunneller direction with a laser
system, and the simultaneous control of the boring and advancing parameters.
The technique employed in the laying of pipes requires the use of a remotelycontrolled shield followed by the pipes to be installed, which are pushed by a
thrusting unit. The shield is equipped with a rotating cutter head that crushes the
excavated material while advancing. The spoil is then brought to the surface by a
closed-loop slurry system.
The microtunneller is remotely controlled by the operator from a control board that
allows monitoring and changing the advancing parameters according to the soil
conditions. No personnel are required inside the tunnel in order to bore it.
The microtunneller position is constantly monitored by a laser beam focused on a
photosensitive target installed inside the machine. The information is then
transmitted to a computer, which calculates the exact position of the microtunneller
and whatever adjustments may be necessary. The adjustments are made in course
of boring thanks to a 3-4 individually-operated hydraulic jacks that act on the cutter
head. Thus it is possible to obtain tolerances of +/- 5 cm vertically and of +/-10 cm
horizontally. The boring system allows pipe installation even under groundwater. The
closed cutting head and the launch seal ensure watertightness even under a level
pressure of 30 m.
MICROTUNNEL RECORDS
SINGLE SECTION 1.271,00 mt
Baricella (Bologne - Italy)
Customer: Edison S.p.A.
Works: Construction of the
minitunnel for the Reno river
crossing for the DN 36" Cavarzere
Minerbio natural gas pipeline
being built: Section 2 (CopparoMinerbio) in Baricella (BO)
i.d. 2400 mm e.d. 3000 mm
Period of execution: 2007
Description:
- With its 1271 m it represents
the longest river crossing
bored in a single section.
- An AVN 2000D with 3000 mm
external diameter fit with a 3070
mm diameter excavation head for
clay was used in this work.
- A series of additional
equipment was designed and
built specifically for the project:
a Back Up for conical
advancement (tunnel lining) in
case it proves impossible to
advance with the pipe thrust
technique; 10 kW transformer
unit; Stand Alone hydraulic unit to
drive the intermediate thrust
stations.
CELLULAR ARCH
Underground
TECHNOLOGIES
Trench Cutter Slurry Walls
The traditional method realized removing soil through traditional means presents two
major limitations. On the one hand rock or highly consolidated composite layers are
difficult to cut. On the second hand when increasing excavation depth, also
imprecision in verticality rapidly increases, until it does not fit anymore with the
building requirements, especially of the walls water resistance. These problems can
be solved thanks to the new equipments available. They remove the watered soil
through a rotating cutter head. The slurry is then mixed with bentonite and conveyed
to separation plants. They separate the solid part from the fluid that is introduced in
the excavation while advancing. The considerable weight and the remarkable
dimension of the trench cutter, it weighs from 35 to 50 ton and is over 15 mt long,
together with a control system checking verticality (it allows to modify in real time the
cutter position when changing the direction) allow the construction of panels with
small errors in verticality also in cases of outstanding depths. This technology is
extremely helpful when precision plays a big role in the good result of the work.
Drilled Piles
Bored piles are the best answer for foundations of heavy structures especially in
unstable or difficult soil conditions. They are made in reinforced concrete with
dimensions varying from 60 to 200 cm and can reach lengths of over 50 meters and
support loads of hundreds of tons. Excavation is normally accomplished using
rotating equipment (buckets or drills). Bentonite slurry is used to support the
excavation. Should the geological conditions not allow its use, sheet piles are used
as an alternative.
Diaphragm walls
The diaphragm method allows the construction of continuous walls in reinforced
concrete with a maximum depth of 25-30 mt below ground level. Installed in
sequences, in linear, box type, circular or polygonal forms, they suite very well for
the construction of containment walls, dumps, underground car parks, defences of
river banks, underpasses, etc. They are built excavating with free grabs (gravity
grabs) or with Kelly bars which have a variable width (normally 250 cm) and a
thickness between 40 and 120 cm. The stability of the excavation is ensured by the
use of bentonite or polymeric slurries. They form a thin waterproof layer (cake) on
the sidewalls, allowing the hydrostatic thrust of the slurry to reinforce them by
replacing the removed soil.
In the specific case of the construction of waterproof diaphragm walls (=bulkheads),
the joint between two subsequent walls is made watertight by using a plastic joint
(water-stop). The water-stop tape, firmly anchored in the concrete, prevents any kind
of infiltration.
Plastic diaphragms
The excavation method is basically similar to the one used for traditional reinforced
concrete diaphragm walls. The significant difference is in the materials employed
and in the site requirements.
Constructed without reinforcement cages and concrete, they are formed from the
same bentonitic slurry used for the excavation, then cement is added in order to give
them solidity and integrity over time. Rather than structures they can be considered
ground lenses with improved geomechanical characteristics. Particularly suited in
defences of river banks, waste dumps, earth-dam cores and whenever stopping the
flow of water or other fluid is preferred to the action of earth containment, typical of
bulkheads.
Micropiles
Peculiar to the micropiling method is the
construction of vertical or sub-horizontal
bores reinforced introducing steel pipes
with concrete or premixed mortar grout.
Diameters can vary from 90 to 400 mm.
Installed for foundation consolidations of
structures subject to differential setting,
they find large application, together with
anchoring tie rods, in the supporting of
landsliding slopes and in vertical facings
excavations.
Micropiles
are
also
frequently used as a foundation element
since they can transmit the above loads
to depth.
Jet grouting
The jet grouting method is the injection at high pressure (up to 600 bar) in the
ground of water and cement mixtures in bores drilled with the same kind of
technology used for micropiles and tie rods. Using a monofluid it is possible to obtain
piles with a diameter varying from 40 to 100 cm. Using a bifluid (that combined with
high pressure air allows the creation of a homogenous mass) it is possible to reach
diameters of 2 m.
Jet grouting is used in a wide range of
applications that can go from tank
plugs or underground parking areas in
presence
of
groundwater,
to
bulkheads for waterproofing river
embankments. This method can also
be used to improve soil conditions:
with grout injections loose soils can be
consolidated and the mechanical
conditions improved, improving load
bearing.
As in all free of steel concrete
structures, also the consolidated piles
are not able to resist to tensile or
flexure stress. When jet grouting is
used to build load bearing structures,
it can be reinforced with a second
drilling and the introduction of steel
pipes, with the same kind of methods
used for micropiles.
CFA piles
or augered cast-in-place (ACIP) piles
CSM
The soil mixing methods involve
combining soil with a cementitious
material in-situ and allow incisive
improvements of the geotechnical
characteristics, thanks to the
adding of opportunely dosed
cementitious mixes.
Recently developed, the Cutter
Soil Mix gives the opportunity to
obtain panels dozens meters
deep in consolidated soil with a
thickness varying from 50 cm to 1
m. The two cutter gears (each
driving a standard vertically driven
cutter wheel) breaks up the soil,
while bentonite slurry is pumped
in (continuously and at low
pressure). This mix of slurry and
loosened soil creates a plastic
bentonite-soil
mixture
with
strength that can vary from 5 to
18 MPa.
Deep mixing
Differently from the jet grouting
methods, the Cutter Soil Mix
method can deal also with
conglomerated soils and cobbles,
which are broken up and made
homogeneous thanks to the cutter
action.
Deep mixing methods are used
when
mono-directional
consolidations are requested. A
rotating
flight
(conveniently
shaped) breaks up the soil and
mixes it with cement grout or
concrete, as previously indicated.
The result is piles with a diameter
varying from 50 to 120 cm that
can be used in the construction of
walls, road embankments, etc.
Underpasses
UNDERPASSES
By underpass we mean the set of all works
realized to grade-separate a crossing of
existing roads and railways.
The construction of underpasses usually
impacts the traffic, causing road and/or rail
delay for at least part of the construction
duration.
In order to minimize these disruptions,
expensive solutions are typically adopted, e.g.
use of alternative paths or temporary outages.
In recent decades, in different areas of the
world, the goal of limiting these costs has driven
the development of several underpass
construction methods, but a definitive solution
was never reached.
I.CO.P. SPA has developed the ultimate solution to solve the cost and delay problems, and
after 15 years of research has patented (PCT ref.: PCT/IB2010/003354) a new technology
called ONE NIGHT SOLUTION. This technology limits total traffic interruption to only one
night, or, if the launch can be done in two separate nights the traffic flow can be maintained
continuously on one rail line or one road lane.
Phase 1
This phase consist of construction of two bulkheads
(Larssen sheet piles, or micropiles or jet-grouting
columns) placed transversely to the railway and
parallel to the underpass axis along the access ramps.
Work should be executed during scheduled
maintenance of way (MOW) windows or during time
with limited traffic.
The bulckheads allow for the subsequent excavation
that will be done under the launched deck, in perfectly
safe conditions
Fig. scheme of
bulkheads machine
used to drive metallic
sheet piles.
Phase 2
Phase 3
After completion of phases 1 and 2, the deck is placed in its final position using hydraulic
jacks. Once rail service is interrupted, the excavation and the simultaneous advancement of
the deck are executed.
Launching of the deck and complete restoration of service take place during the night, within
a maximum duration of 10 hours. The preference to conduct this activity at night stems from
restricted MOW windows in Europe, minimize impact on commuter rail service.
The described method allows rail authorities to re-open the railroad to traffic within one night.
Once the deck is put in its final place and rail services are restored, completion of the
remaining work may be accomplished without any further interference with the railway.
In order to avoid delay due to equipment failure, all machine used during launching phase
are redundant (100% redundancy).
The scheme described above can be used for road underpass construction, too, and it can
be modified to match specific project requirements. For example, two or more tracks make it
possible to avoid total traffic interruption. Performing launch over two nights enables rail
traffic to be active on one track at all times.
One night solution Time schedule
The following schedule indicates the work (including all phase 3 works)to be completed:
Work program (indicative)
Activity description
1 De-energize electric line(s)
2
duration
cumulative
duration
30'
30'
1h40'
2h10'
50'
3h00'
2h00'
5h00'
5 Launch deck
2h20'
7h20'
6 Restore tracks
1h40'
9h00'
7 Safety margin
1h00'
10h00'
Note
This schedule is based on a real railway underpass work performed by ICOP Spa. Time
values have an indicative purpose and they can be subject to modifications depending on
specificity of project.
I.CO.P Spa is able to guarantee the service of highway during all construction phases; using
two decks, it is possible to close alternatively only a part of the road. By reducing number of
open lanes and using temporary lane modifications (width and direction) it is possible to
avoid road traffic interruption and consequent traffic load increase on alternative paths.
Here below is presented a work scheme adopted to build a highway underpass without
complete traffic interruption:
Phase 1-2 (fig.: A): bulkheads (Larssen sheet piles, or micropiles or jet-grouting columns) are
placed parllel to highway axis on the external sides.
In order to excavate the access ramps and in order to construct the precast decks on lateral
highway sides, abutments (concrete diaphragm walls, drilled piles or other kind of
foundation) and connecting beams are built. After completion of beams, decks on left and
right sides can be precast.This work does not interfere with highway activities.
Phase 3 (fig.: B): Road width is reduced. Only one or two middle lanes are closed to traffic in
order to permit the construction of deck central supports. Bulkheads are driven along central
highway axis and central abutments with supporting beams are built.
Phase 4 (fig.: C): Right deck is placed in its final position. Half width of the highway is
available to the traffic. Before deck launch, right lanes are closed to traffic. Bulkheads are
driven orthogonally to axis of lanes in order to permit safe excavation under right deck.
Phase 4 (fig D): Right half of road is now open to traffic. Left deck is launched in its final
position. Only left lanes are close to traffic. As done for right deck, before launch operations,
bulkheads are driven orthogonally to lane axis in order to permit further safe excavation.
After launch all lanes are restored. Completion work could be carried out without any traffic
interference.
For track support structure, ICOP has usually employed a system called Essen bridge.
This support structure is a steel grating composed of several kinds of interconnected
beams:
Essen beams: there are 4 beams per each track, H shaped (Height 20 cm
width 12 cm) laid out parallel to each track and pairs connected through saddles;
Tie beams: two beams (H beam or truss) with high flexural rigidity are used to
connect the Maneuver beams. These two beams are placed parallel to track in order
to contrast horizontal stress due to supporting structure sliding over the upper slab
face of the monolith.
Slip beams: these beams are fixed over monolith (orthogonal to underpass
road axis), they work as bearings for the Maneuver beams during launch phase.
Wood piles (diameter 300 mm length 5m) are driven inside rail embankment; these piles
are removed during work face progress, at those time the grating will be supported on one
side by the monolith and on the other side (not yet excavated) by wood piles;
Before underpass launch some works must be done (e.g. micro piles, struts, tie rods etc.)
in order to guarantee safety of excavation, stability of rail embankment and stability of
support structures.
4. Monolith launch and underpass completion
During launch, excavating machines located inside concrete box structure remove the soil
on the advancing work face, facilitating the concrete box progress.
During this phase, which will take several days/weeks, tracks alignment (horizontal and
vertical) must be regularly verified and eventually restored since an excessive track
deformation would stop the train traffic.
The following time schedule provides approximate duration of each phase work:
Work program (indicative)
Activity description
duration
7 days
cumulative
duration
Note
7days
2 Underpass launch
20 days
27days
7 days'
34 days
This schedule is based on a real railway underpass work performed by ICOP Spa. Time
values have an indicative purpose and they can be subject to modifications depending on
specificity of project.
Impervious structure
(waterproof joints)
Geometry of structure
Excavations
Reinforcement
Launch method
Hydraulic jacks
Hydraulic jacks
Launch operations
Structure - type
After the first experiences I.CO.P. SpA has developed the above
constructing method, modifying and adapting it in order to meet different
constructing demands, letting both the flexibility characteristics and the
appeal be part of the characterising elements both of the construction
environment.
mentioned
and critical
aesthetical
and of the
All bridges and viaducts constructed by I.CO.P. SpA are designed by the company
technical staff and become the historic memory trace of the company know how.
Working in very difficult site conditions and with extremely short execution times are
also distinctive elements of our commitment to clients. Nowadays I.CO.P. SpA is a
reliable company for many important contractors, such as Anas Spa (the national
road and motorway agency) and the Italian Civil Protection organization (ICP).
Precast segment bridge designed and constructed by I.CO.P. in Rome (Palidoro area).
ENVIRONMENTAL SOLUTIONS
ENVIRONMENTAL SOLUTIONS
Technologies
After having been one of the first Italian groups to develop trenchless technologies,
which minimize or even eliminate surface disruption and can be therefore considered
environmentally friendly technologies, in the latest years the companies belonging to
the I.CO.P. group have committed themselves applying their geotechnical know-how
in the environmental field, studying integrated solutions for waste disposal and
sediment treatment and remediation, especially in case of dredged mud. The aim is
to treat and improve the quality of muds and sediments both from an environmental
and from a geotechnical point of view.
I.CO.P. group keeps studying and applying innovative technologies in the
environmental field:
construction of impermeable barriers to retain contaminated sites;
projects of integrated solutions for environmental reclamation and ecological
engineering works;
research of environmental friendly systems for dredged mud;
special in situ mixings that can offer innovative solutions also for sediments,
drilling slurry and excavation waste.
ALLU System
The mass stabilization is a fast, cheap way to consolidate land and dredged
sediments with poor mechanical properties, mixing them with dry binders.
This technology is particularly suitable for in situ remediation. With the mass
stabilization, consolidation and contaminants inertization occur simultaneously
through the process of Stabilization and Solidification. The stabilization/solidification
process can be utilized for both improving the properties of poor soil masses and
binding the harmful particles into the stabilized mass. In detail, the process consists
of two distinct mechanisms:
stabilization, which by chemical reactions converts pollutants into less soluble
compounds;
solidification, which physically incapsulate contaminants within the
ground/sendiments and prevent migration to the surrounding areas.
The opportunities and the main purposes offered by the application of mass
stabilization are many and include:
improving the deformation properties of soils (reduce settlements);
increasing the mechanical strength of soils;
increasing the dynamic stiffness of soils;
remediation of contaminated matrix (soils and sediments).
Moreover, mass stabilization method can also be used in combination with columns
stabilization and offers several benefits, including:
execution speed;
economic benefits in terms of saving material and energy;
cut of costs both for material handling and offsite transport;
consequent reduction of traffic pollution and no need for disposal sites;
no need of material from borrow pits and consequent money saving.
To realize mass stabilization I.CO.P. applies the ALLU technology, which offers the
opportunity of minimal invasive matrix treatment. This innovative system has been
developed in Northern Europe, where stabilization and in situ remediation of soils
are now of primary importance because of peculiar soil conditions and difficulties in
finding suitable materials for engineering works.
The ALLU SYSTEM is based on the mixing of an appropriate amount of dry binders,
with the environmental matrix. It allows a substantial enhance of matrix mechanical
behaviour and/or reduction of contaminants mobility.
Mass stabilization is the most widely used technology for the recovery of dredged
material and is the simplest system for its reuse in the construction of port
infrastructures, such as CDFs.
In particular, the new Italian law regarding dredging operations and sediments
management (D.M. 7th November 2008), considers sediments as a resource" and
not as "waste", as it used to be. Subsequently, ALLU technology can be successfully
used for all applications in environmental remediation and contextual development of
port areas.
With the microdrainage method, radial drains of small diameter are drilled in the
main microtunnel by a remote control robot in order to remove groundwater. The
robotic drilling module moves inside a microtunnel bored under the landfill and sets
up a draining layout. The mobile caterpillar unit, fitted with buffer elements, is able to
stop at locations requiring draining manifold insertions
.
FDP
FDP (Full Displacement Piles) are cast-in-situ screw piles installed by rotation and
crowd. The FDP drill string is made up of a hollow Kelly bar that will excavate the
soil and move it, for displacement laterally, with a minimum generation of spoil.
The FDP method has multiple qualities some of which are:
they are installed without vibrations in the soil or in the surrounding
area/building
they produce little or no spoil to be removed. This is particularly convenient
in contaminated areas or when the waste disposal areas are distant from the
working site.
FDP piles are installed drilling dry, without the use of bentonite or
reinforcing cages to sustain the boreholes.
making compact the surrounding soil, the piles develop a very good soil/pail
interaction, increasing the geotechnical soil characteristics and the piles
bearing capacities. Since the piles have a higher bearing capacity they can
be shortened.
pile sections are very steady and consistent, there is little overbreak and
consequently reduced consumptions of concrete;
The drilling and concreting processes are continuous "One Pass",
procedures, allowing automatic controls.
Both drilling and extraction phases can be completely automated thereby
guaranteeing high levels of productivity, reduced drilling costs and quality control of
the piles and productivity during the construction.
Freezing
When it is necessary to drill large diameter tunnels or shafts, in soft or compact
ground or also conglomerate, in presence of groundwater, and when it is not
possible to drain it, it is possible to use ground freezing methods. This kind of
method allows the separation between the groundwater and the soil, eliminating
dewatering. Ground freezing is done along the perimeter of the tunnel or shaft inside
of which is then passed the piping where the liquid refrigerant (normally CaCl2 or
nitrogen) with temperature in the order of -45C, - 120C to freeze the terrain around,
thus forming a frozen column with diameter up to 2.0 mt. The excavation can then be
done using a drilling probe, but in the case of tunnels, it is preferred to use tools of
greater sizes. With such machines, horizontal holes with height from the level of the
wheels up to 10,20 mt can be constructed, with notable advantages of continuing the
work in steps of 8-9 mt.
Publications
DIRECT PIPE
MICROTUNNELLING
UNDERGROUND
| January-February 2010
MT March 2011
| January-February 2011
Perforazione
a elica continua
in modalit intubata
La C850 DH, una
macchina per pali
realizzata dalla
Casa friulana
con uno speciale
allestimento
doppia testa, si
recentemente resa
protagonista in un
cantiere a Udine,
dove ICOP ha svolto
con successo un
intervento con
una metodologia
molto recente e
innovativa
74
La geometria dellintervento
Lintervento, dellimporto complessivo di
7 milioni e 350 mila euro, si propone di risolvere le criticit attualmente presenti nellintersezione citata e derivanti dagli elevati
flussi veicolari esistenti e dalle molteplici
manovre di svolta consentite.
La macchina per pali
Casagrande C850 DH si basa
sul gi esistente carro C850
opportunamente modificato
e allestito con due teste
idrauliche di perforazione
indipendenti
PF | gennaio-febbraio 2011
lingegner Grillo della Icop consiste principalmente nella produttivit, che in questo
caso di circa 78-85 metri lineari al giorno.
Con le tecniche tradizionali sarebbe stata
di 35-40 metri al giorno, quindi la resa
pi che raddoppiata! La novit sta anche
nellaver portato la tecnologia dei pali secanti nei terreni ghiaiosi.
PF | gennaio-febbraio 2011
76
PF | gennaio-febbraio 2011
del tubo di 400 kN; sempre in questa versione, la profondit di perforazione CFA di
25 m con 900 mm di diametro. La massima
forza di estrazione sullelica di 1.000 kN.
La massa della macchina completa di circa 145 t e essendo una soluzione multifunzionale pu essere predisposta per
CFA tradizionale fino a 34 m di profondit e in tutti gli altri allestimenti per pali,
kelly per diaframmi, gru per fondazioni e
idrofrese.
Un aspetto molto importante da sottolineare per quanto riguarda questa
macchina speciale anche quello della sicurezza. A tal proposito, conferma
Dobrigna: La caratteristica principale della macchina, che consente di fregiarla del
merito di rispettare i pi alti standard di
sicurezza in cantiere, il sistema di pulizia
dellelica rotante, posto sulla testa inferiore.
Questo particolare meccanismo, unesclusiva Casagrande brevettata a livello italiano ed europeo, garantisce la pulizia
dellelica continua sul tratto esterno al tubo eliminando il rischio di caduta dallalto
(altezza che in questo caso arriva anche
a 15-20 m) del materiale di perforazione.
Il materiale, quindi, viene convogliato a terra in sicurezza tramite un nuovo sistema di
scarico telescopico. Sicurezza la filosofia che sottende la progettazione Made
in Casagrande.
Grandi lavori
I.CO.P.
Opere infrastrutturali
sulla tangenziale di Udine
Si basa sullimpiego di tecniche
dintervento innovative e macchine
operatrici multifunzionali lintervento
presentato in queste pagine.
Complessit tecniche e vincoli logistici
per un cantiere che ha rappresentato un
severo banco di prova per uomini e mezzi
n di Roberto Ottoboni
64
M T
M A R Z O
2 0 1 1
loperativit di cantiere.
Lintervento presentato in
queste pagine, che ha come oggetto la realizzazione
di un sottopasso destinato
a risolvere una serie di problemi di viabilit che rendevano difficoltosa la circolazione stradale lungo il
tracciato della tangenziale
di Udine, ha quindi rappresentato un severo banco di
prova per uomini e mezzi.
Brillantemente affrontato
e risolto grazie alladozione di tecniche selezionate
al fine di garantire un rapido ed efficiente svolgimento dei lavori minimizzando
limpatto sulla viabilit.
Il cantiere
Ci troviamo a Basaldella, in
provincia di Udine, nel cuore
di un ampio comprensorio
industriale che rappresenta al contempo anche un
importante nodo stradale
essendo collocato lungo il
tracciato della strada statale 13 Tangenziale Ovest di
Udine. Proprio in prossimit
di uno degli snodi della tangenziale, pi precisamente
nel punto in cui questultima incrocia la Strada Provinciale 89, la situazione viabilistica presentava da tempo
notevoli criticit per la presenza di un incrocio semaforico che, nelle ore di massimo traffico, determinava
la frequente formazione di
code e rallentamenti. Il problema, quindi, richiedeva un
importante intervento di risistemazione a livelli sfalsati
dellincrocio, con la creazione di un sottopasso e della relativa viabilit avente
la funzione di fluidificare il
M A R Z O
2 0 1 1
M T
65
zione delle opere sopra citate. La loro esecuzione, infatti, comportava la necessit
di una serie di interventi di
consolidamento e protezione dellarea del sottopasso
mediante palificazioni aventi il compito sia di sostenere
temporaneamente limpalcato del sottopasso e ladiacente viabilit, sia di realizzare il paramento murario
definitivo dellopera.
La soluzione
66
M T
M A R Z O
2 0 1 1
grandi lavori
Il cantiere in breve
Lavori di sistemazione a livelli sfalsati dellincrocio
semaforico tra la SS. 13 (tangenziale Ovest di Udine)
e la Sp. n.89 in localit Basaldella (Ud)
Importo: 7 milioni e 350 mila euro
Impresa esecutrice: I.CO.P.. Basiliano (Ud)
Direttore di cantiere: Ing. Luca Grillo (I.CO.P.)
Scavi e movimento terra: Friulana Bitumi
Martignacco (Ud)
Macchine per fondazioni speciali: Casagrande
Fontanafredda (Pn); Bauer Italia Mordano (Bo)
Opere di consolidamento: 730 pali accostati
e secanti da 900 mm
Anno di realizzazione: 2010/2011
M A R Z O
2 0 1 1
M T
67
68
M T
M A R Z O
2 0 1 1
grandi lavori
za variabile da 5 a 15,5 m.
I pali accostati sono stati realizzati in via provvisoria a sostegno temporaneo
dellimpalcato del sottopasso e delladiacente viabilit,
collocati al centro delle due
corsie esistenti della tangenziale Sud di Udine, lungo la direttrice Nord-Sud,
con un interasse di 1 m
e spaziati di circa 10 cm
in maniera da costituire una
fila di lunghezza circa 350 m.
I pali sono collegati da una
trave di testa, che funge da
elemento di contrasto contro eventuali cedimenti differenziali. Parallelamente a
questultima, alla distanza di
2
1. Sezione trasversale
costante impalcato Tipo 1
2. Planimetria generale
di progetto
3. Dettaglio planimetria
generale di progetto del
ponte
M A R Z O
2 0 1 1
M T
69
Chi I.CO.P.
Lesecuzione
dei pali
Per la realizzazione delle
palificazioni sono state utilizzate una macchina per
pali Casagrande C850 DH
(Double Head doppia testa) per lesecuzione di pali a elica continua (CFA) in
modalit intubata, con carro modificato in modo da
accogliere due teste idrauliche di perforazione indi70
M T
M A R Z O
2 0 1 1
grandi lavori
calcestruzzo allinterno
dello scavo, recuperando
progressivamente la doppia testa di perforazione.
A fresco vengono quindi
posizionate per gravit le
gabbie di armatura.
Le opere
Una volta eseguite le palificazioni si proceduto allo scavo del terreno tra le
due file di pali fino al raggiungimento della quota
di fondo del sottopasso.
Sulle spalle laterali dellopera e i pali provvisori centrali
saranno collocate in appoggio le travi prefabbricate in
calcestruzzo precompresso
destinate a sostenere limpalcato del viadotto, successivamente solidarizzate tramite getto in opera.
Gli scavi non hanno presentato particolari problematiche, poich avvenuti in assenza di falda, e la
tipologia costruttiva adottata per il sottopasso, non
prevedendo lesecuzione di
un manufatto a spinta ma
in semplice appoggio, non
ha richiesto specifiche opere accessorie.
Il programma dei lavori ha
previsto la realizzazione di
una carreggiata alla volta,
con deviazione provvisoria
del traffico su quella libera in modo da evitare interruzioni del traffico. Attualmente la prima delle due
corsie si trova in fase di
completamento, cui seguir il varo della prima sezione dellimpalcato. La conclusione dei lavori prevista
per il prossimo maggio, per
un totale di nove mesi circa
di lavorazioni.
Il movimento terra
Accanto alle importanti opere di consolidamento e sostegno provvisorio
eseguite in via propedeutica alla realizzazione del sottopasso, un ruolo
importante nel quadro dellintervento hanno avuto i lavori di scavo e movimento terra richiesti per la preparazione della nuova viabilit e le successive operazioni di livellamento, stabilizzazione e asfaltatura dei piani stradali.
Questa importante fase delle lavorazioni stata affidata alla Friulana Bitumi di Martignacco (Ud), realt specializzata nella produzione e messa in opera di conglomerati bituminosi tradizionali e speciali e, come impresa generale, operante nel settore
delle infrastrutture private e pubbliche, opere stradali, difese idrauliche, gasdotti,
acquedotti e fognature e opere accessorie. Per la realizzazione delle opere di scavo
M A R Z O
2 0 1 1
M T
71
ENVIRONMENTAL SOLUTIONS
COMPLETED PROJECTS
AND WORKS IN PROGRESS
Civil works
Ena S.p.A. Reggio Emilia
Project and construction of a branch sewer serving the south-west area of Reggio Emilia as part of the works for the
water reclamation plan of the Crostolo river.
Period of execution: in progress
Contract value 6.322.274,00 - I.CO.P. SpA share 50.01%
Orvieto Municipality (TR)
Construction of a multi-storey car park in Orvieto - Italy.
Period of execution: 01.2004 05.2009
Calabria Region Department of Public Works and Water systems - Sector 23 - Catanzaro
Hydraulic works on Esaro river and hydraulic regimentation in the Esaro river North area, from the Railway Station
bridge to S. Francesco bridge (in the Crotone municipality)
Period of execution: 08.2000 04.2004
Works value 3.601.313,00
Province of Salerno
Intervention for the protection and consolidation of the coastal littoral - Municipality of Ispani.
Period of execution: 2006 -2007
Works value 2.937.529,84
Valle d'Aosta Region Territory, Environment and Public Works Department - Aosta
Hydraulic works on Saint-Barthelemy river - Nus Municipality 3rd lot.
Period of execution: 09.2002 08.2004
Works value 2.630.625,90
Central Government Authority of Malta / Department of Contracts - Floriana (Malta)
Design and build tender for the consolidation of unstable terrain and restoration works of the historic ramparts
underlying despuig bastion and magazine curtain area at Mdina (Malta).
Period of execution: in progress
Contract value 3.364.628,00 - I.CO.P. SpA share 1.892.603,00
Valle d'Aosta Region - Territory, Environment and Public Works Department - Aosta
Hydraulic and geotechnical works in Cogne (AO).
Period of execution: 11.2003 07.2007
Works value 1.819.046,99
Municipality of Civita Castellana (VT)
Works to implement the interventions related to former discrisct contracts (Ex Contratti di Quartiere II) (building in
C1 compartment and covering of railway trench).
Period of execution: in progress
Contract value 3.268.494,00 - I.CO.P. SpA share 1.666.932,00
G.O.R.I. S.p.A. Torre Annunziata (NA)
Works for the functional upgrading of the works of municipal sewage treatment plants in the Municipality of Torre del
Greco (NA).
Period of execution: 2007
Works value 1.388.562,13
IRISACQUA S.r.l. - Gorizia
Works to rationalize the sewerage-purifying system in the area on the right bank of the Isonzo river Cormons
branch Mariano del Friuli Gradisca dIsonzo first section.
Period of execution: in progress
Contract value 1.032.363,00- I.CO.P. SpA share 505.858,00
Underpasses
Venice Municipality
Construction of an underpass to the S.S.13 Terraglio roadway with the S.S. 14 bis roadway to connect to the new
Mestre hospital and to the new manufacturing district.
Period of execution: 07.2005 12.2006
Works value 5.843.331,00
Treviso Province
Works for the requalification of the crossing between S.S. no. 13 roadway (km 29+956) and S.P. 102 roadway in
Castrette di Villorba area (TV).
Period of execution: 03.2004 11.2005
Works value 4.079.832,33
ORION S.c.a r.l. Cavriago (RE)
Construction of an underpass to Via Cristoforo Colombo in Rome as part of the ground-level expansion of the road
to Ostia, traffic circle at the exit from the underpass at Via Brasini, and a whole series of accessory and connection
works.
Period of execution: 03.2006 11.2007
Works value 2.956.103,73
Gorizia Province
Construction of an underpass to remove the railway crossing at the 115+077 km on the Mestre -Trieste railway line
and of the railway crossing at the km 1+019 of the railway siding Ronchi North and Ronchi South. Construction of a
roundabout between San Polo street and Pocar street. Construction of the roads to connect to the new hospital in
Monfalcone (GO).
Period of execution: 01.2007 05.2009
I.CO.P. SpA works value 2.272.509,00
Milan Municipality
Construction of a siphon for the underpass of the Gronda Basso collector to Lambro Settentrionale river, on the
South area of Bonfadini street.
Period of execution: 02.2004 04.2005
I.CO.P. SpA works value 2.200.976,94
Guerrino Pivato S.p.A.
Construction of underpasses to remove the railway crossing of the Venice Trieste railway in the Municipality of
Fossalta di Portogruaro. Underpass no. SP 92 - underpass no. SP 72 and Frattine underpass.
Periodo di esecuzione: 02.2004 01.2008
I.CO.P. SpA works value 1.445.000,00
Underground
Societ per la Realizzazione delle Metropolitane della Citt di Roma a .r.l. - Rome
Project and construction of the underground in Rome line B1: line B branch form Piazza Bologna to Piazza Conca
DOro.
Period of execution: 11.2005 in progress
Contract value 167.648.975,00+163.065.520,00 - Works performed by I.CO.P. SpA at 31.10.2012: 22.287.244,00
Intesa Sanpaolo S.p.A. - Turin
Excavations, construction of diaphragms and complementary works for the construction of the new head offices of
the Intesa Sanpaolo bank in Turin.
Period of execution:12.2008 07.2010
Works value 21.591.490,00
Copenhagen Metro Team I/S - Denmark
Foundation work as part of the The Cityringen Metro Project - Copenhagen Denmark: Enghave Plads,
Frederiksberg, Vibenshus Runddel, Trianglen Plads.
Period of execution: 12.2012 in progress
Works value 9.508.609,00
ITALFERR S.p.A. - Rome
Adjustments of the bridge on Po river between the stations of Pontelagoscuro and Occhiobello on the Bologna Padua railway line to comply with standards and including civil works to consolidate the piles in the river bed.
Period of execution: 07.2003 09.2006
Works value 4.680.505,00
Smetra Societ Monegasque dEtudes et de Travaux Monte Carlo (Principality of Monaco)
Construction of drilled piles, sub-horizontal tie rods, drainages, shotcrete (sprit-beton) works and complementary
works.
Period of execution: 12.2008 10.2010
Works value 3.310.156,00
Milanofiori 2000 S.r.l. Milan
Construction of vibro reinforced concrete foundation piles, diam. mm 420 e 520 for the Commercial Units, the square
and the related parking lots in Assago (MI). Construction of deep sub-foundation works by reinforced concrete piles
of the CFA kind. Construction of reinforced concrete piles with CFA method, diam. 600mm and 800 mm in the
parking lot no, 10.
Period of execution: 05.2007 09.2007
Works value 3.225.938,78
Palazzo del Cinema S.c.a r.l. Marghera (VE)
Construction of diaphragms with the CSM method and valve steel tie rods as part or the works for the construction of
the new Congress and Cinema Palace in Venice (Lido).
Period of execution: 03.2009 05.2011
Contract value 1.401.371,00
Central Government Authority of Malta / Department of Contracts - Floriana (Malta)
Design and build tender for the consolidation of unstable terrain and restoration works of the historic ramparts
underlying despuig bastion and magazine curtain area at Mdina (Malta).
Period of execution: 10.2011 in progress
Contract value 3.364.628,00 - I.CO.P. SpA works value 1.892.603,00
SELCO Cimentaciones y Construccionse SL Barcellona (Spain)
U.T.E. Ponts Pliola. Segarra Garrigues channel, between P.K.S 0+000 and 5+200Construction of diaphragm walls
Period of execution: 08.2007 12.2007
Works value 326.390,34
Microtunnel
Snam Rete Gas San Donato Milanese (MI)
Works for the construction of the pipe-line Camisano Vicentino - Zimella ND 1400 (56") of the by-pass line to Zimella
junction ND 1200 (48") and restoring of the tunnel for the underground crossing of Gu and Bacchiglione rivers on
the Sergnano - Tarvisio pipeline ND 850 (34").
Period of execution: 03.2005 07.2007
I.CO.P. SpA works value 21.191.691,84
SHELL Deutschland Oil Gmbh 50389 Wesseling (Germany)
Contract to perform services for the Tunneling Works, Lots 1, & 2, CONNECT PROJECT over both locations
Rheinland Refinery North (RRN) - Godorf and Rheinland Refinery South (RRS) Wesseling (Germany)
Period of execution: 09.2011 02.2013
Works value 20.621.501,00
Snam Rete Gas S.p.A. San Donato Milanese (MI)
Works for the construction of a pipeline: substitution of pipeline Tarvisio Malborghetto (UD) - ND 900 (36) with
pipeline ND 1200 (48).
Period of execution: 04.2008 09.2010
Contract value 40.960.000,00 - I.CO.P. SpA works value 18.571.569,00
4.200.000,00
Environmental
Prime Ministers Office Struttura di Missione (Organization for the organization of the 150th anniversary of
the National Unity celebrations) - Rome
Sediment treatment as part of the requalification of the former La Maddalena Armoury site (OT).
Period of execution: 11.2008 07.2009
Works value 4.605.823,00
Pordenone Municipality
Environmental clean-up and renovation of urban solid waste dump in Vallenoncello (Italy)
Period of execution: 01.1997 08.2002
Works value 3.405.976,48
Special works
Prime Ministers Office Italian Civil Protection Department
Convention for the fulfillment of the Italian Government dispositions (art.2 DL 28/04/09 no.39): management and
coordination of the works for the construction of temporary housing for the homeless citizens of LAquila after the
April 6, 2009 quake. The C.A.S.E. project, comprising 185 seismically isolated and environmentally sustainable
buildings, for 15,000 people, were erected in 19 areas of the municipality of LAquila.
Period of execution: 05.2009 04.2010
Works value 700.000.000,00
Prime Ministers Office Italian Civil Protection Department
Installation of a "Bailey" one-lane bridge over the Payee River in South Sudan.
Period of execution: 11.2005 11.2006
Microtunnel
1293 Gasducto
Tamazunchale - El Sauz
Ixmiquilpan (Mexico)
Microtunneling at KP 94 Gasoducto
Tamazunchale - El Sauz microtunel DI1800 Ixmiquilpan (Mexico)
Customer
Transcanada
Execution period
April 2013 - December 2013
Work value
6.920.680,00
Technical data
No.
Microtunnel
Machine
Lenght
ID
OD
Straight drive/slope
Ixmiquilpan
AVN1800D
672 m
1800 mm
2120 mm
672 m / +8.5 %
Jobsite overview
The Tamazunchale pipeline is a 130 km (81 mi) pipelines in east Central Mexico that connects facilities of Mexicos
state-owned petroleum company to natural gas power generation plants near Tamazunchale, Mexico.
For the pipeline installation in the section included in KP 90 and KP 97+500, where unstable soil conditions have been
identified, an alternative solution to open trench has been selected. The solution is the construction of a microtunnel with
the installation of reinforced concrete pipe ID1800mm, total length approx. 670m.
After the construction of the microtunnel and the pipeline pull in, the space between the pipeline and the concrete pipe
had been filled with a cement bentonite mixture.
The drives passes a mountain with related problems regarding the inert level (up to 150 meters) and geostatic pressure
with consequences on the slurry treatment management, lubrication effectiveness and jacking pressure. The Bauer
slurry treatment plant linked to the filter press unit provided the required capacity to manage the huge excavated soil
production, even though the unforeseen basalt layers found during tunnelling operations.
Operating in a very rough mountainous area, quite distant from urban centres, represented on of the greatest challenge
for I.Co.P S.p.A. The major suppliers were in the areas of Queretaro and Pachuca (respectively distant about 150 and
120 km from Ixmiquilpan).
TBM breakthrough
Microtunnel
Customer
SAMSUNG ENGINEERING CO. LTD. (SECL)
Execution period
Completed
Total Length
5,544.08 m
1,134.79 m
Microtunnel
Machine
Length
ID
OD
Straight drive/slope
Curve
Section
Curve radius/slope
1*
SH #21 SH #22
AVN1800TB
955.10 m
1800 mm
2200 mm
250 m / - 0.1%
705.10 m
476.92 m
374.91 m
Straight drive/slope
Curve
Section
Curve radius/slope
SH #21 SH #20
AVN1800TB
586.92 m
1800 mm
2200 mm
210 m / + 0.1%
3*
SH #47 TLS
AVN1800TB
891.25 m
1800mm
2200mm
891.25 m / -0.1%
SH #47 SH #46
AVN1800TB
473.55 m
1800mm
2200mm
473.55 m / +0.1%
SH #29 SH #28
AVN1800D
656.91 m
1800 mm
2200 mm
281 m / + 0.1%
SH #29 SH #29B
AVN1800D
244.58 m
1800mm
2200mm
244.58 m / -0.1%
SH #43 SH #42
AVN1800D
344.10 m
1800mm
2200mm
344.10 m / +0.1%
SH #43 SH #44
AVN1800D
328.75 m
1800mm
2200mm
328.75 m / -0.1%
SH #45 SH #44
AVN1800D
319.64 m
1800mm
2200mm
319.64 m / +0.1%
10
SH #45 SH #46
AVN1800D
323.28 m
1800mm
2200mm
323.28 m / -0.1%
11
SH #37A SH #38
AVN1800D
420.00 m
1800mm
2200mm
420.00 m / -0.1%
1* - Longest Multiple Curvature Microtunnelling Drive in Middle East (3 sets of continuous S-Curves)
3* - Longest Sea Crossing Microtunnelling DN1800 Drive in the Middle East
Microtunnel
Machine
Length
ID
OD
12
SH #34 SH #35
AVN1800D
317.73 m
1800 mm
2200 mm
40 m / + 0.1%
277.73 m
13*
SH #12A SH #11
AVN1500TC
483.06 m
1800 mm
2200 mm
318 m / + 0.1%
165.06 m
14*
SH #10 SH #11(2)
AVN1800D
334.00 m
1800mm
2200mm
85 m / -0.1%
249.00m
With the exceptional growth of population and strategic plans and 2030 Vision to provide capacity to meet the needs of
existing and future development in Muharraq Governorate, a BOOT Sewerage Treatment Plant and Conveyance system
project was built in Kingdom of Bahrain. The project set out and covers the area of Muharraq, HIDD and Arad, consist of
two parts, civil construction of the STP plant, and the other parts, sewer conveyance system. The Sewer conveyance
system are constructed in two major section, main collection tunnel Deep Gravity Sewer (DGS) and lateral connection
to replace two major sewage pumping stations and 22 minor ones across the coverage area Waste water collection
network (WWCN). The WWCN pipeline collects the sewerage and directs it towards the DGS pipeline. The DGS conveys
the sewerage through a gravity tunnel to the treatment plan through an intermediate lifting station (ILS). Concerning the
environmental effects, disturbance to the population and neighbourhood and impact on the UNESCO Heritage Site (Fort
Arad), the DGS route consist of 15.9 km of pipeline of DN1000, DN1400 & DN1800 was executed by Micro-tunnelling
method. Whereas the WWCN route consist of 4.1km of DN300 to DN800 pipeline constructed mainly with trenchless
technology. The success of the project contributed the reduction of energy use, reduced risk of odour, traffic disruption
during maintenance, sewers backing up and associated sewage flooding. The sewage undergoes treatment process to
produce Treated Sewage Effluent (TSE) suitable for re-use in industrial application, irrigation or landscaping.
47 nos. of shafts are constructed with Secant Pilling method to provide a watertight pit for the micro tunnelling activities.
Upon completion of the pipeline installation works, the shafts are then converted to permanent manholes. Trenchless
installation methods have less impact on the environment and the existing infrastructure than other methods applying
open cut trenching. I.CO.P. had undertaken 5.5 km of the DN1800 pipeline. Two sets of Herrenknecht AVN1800 were
utilized to tunnel the GRP Encased RC Jacking Pipe. The major challenges encountered during the execution of the
works are the existing ground conditions (Layered of Anisotropic sequence of rock), high ground water table with
influents of sea tidal, long and multiple curvature drives, historical and protected areas and tight construction tolerances.
I.CO.P claims two major milestone records on the project by executing the longest DN1800 Sea Crossing (892m) and
longest DN1800 Longest Multi Curvature Micro tunnelling Drive (955.10m with 2 sets of S-curves). Both records are not
only valid in the Kingdom of Bahrain but throughout the Middle East Region.
MICROTUNNEL no. 1 (Longest Multi Curvature Micro tunnelling Drive in the Middle East)
During the project commencement and design phase, I.CO.P, EPC Contractor and the design consultant had been
closely working on the tunnelling route, material optimization and value engineering to optimize the feasibility to construct
the DGS pipeline considering the challenges and actual conditions on site. The table below compares the status of the
pipe route/criteria based on the original pre engineering stage and post value engineering stage.
Pre Engineering/Tender Pipeline Route along Fort Arad area (PS B2 to PS B3)
Microtunnel
Technical data of the pre and post value engineering stage (Fort Arad Section PS B2 to PS B3)
Pipe DN Total no.
No. of Start
No. of Arrival
Distance
Stage
of Shaft
Shaft
Shaft
between Shafts
Post/Tender
1400
5
3
2
Av. 280m
Pre/Construction
1800
2
1
1
942m
Drive
Criteria
Straight
S-Curves
Post Engineering/Optimization of Pipeline Route along Fort Arad area (PS B2 to PS B3)
The optimization of the tunnelling route was finalized and approved by the project owner in the benefits of all parties.
Shaft no. 21 that was originally 10A was designated as the launching shaft for the long DN1800 multi curvature drive
towards the arrival shaft no. 22 that was originally 10E. The shafts (10B, 10C and 10D) allocated in between the drives
were omitted. The drive was completed 25 days ahead of schedule.
MICROTUNNEL no. 3 (Longest Sea Crossing Microtunnelling DN1800 Drive in the Middle East)
TBM Breakthrough
TBM Launching
Microtunnel
Customer
Snam Rete Gas S.p.A. - San Donato
Milanese MI
Execution period
July 2011- March 2012
Work value
1.550.000,00
Technical data
No.
Microtunnel
Machine
Lenght
ID
OD
Straight drive/slope
Curved drive
Curve radius/slope
Torrente Rujo
AVN1600D
306 m
1600 mm
1940 mm
33 m / 7,32 %
270 m
Strada Comunale
S. Salvatore
AVN1800D
726 m
1800 mm
2160 mm
381 m / -1,2 %
345 m
Bosco Buricolat
AVN1600D
213 m
1600 mm
1940 mm
213 m / 0,25 %
The 3 microtunnels driven by ICoP S.p.A. are part of the wide Snam Rete Gas project to develope the gas pipelines
network by starting from the San Polo di Piave connection plant and passing through the municipality of Vazzola, Santa
Lucia di Piave and Susegana (Treviso). The whole project develops under the Collalto hills, an high worthy area from the
point of view of wine production, natural and cultural interest. ICoP S.p.A. pipe jacking technology was able to provide
the most suitable tecnique to minimize the visual impact during and after the tunnelling operations and the installation of
the gas pipeline (ID 600 mm 24) was possible.
MICROTUNNEL 1 TORRENTE RUJO
The large height gap between the jacking shaft (86 m above m.s.l.) and the receiving one (167 m above m.s.l.) and the
relative short horizontal distance (289 meters) rappresented the greatest challenge for ICoP S.p.A.. After the first 33
meters long span with a 7,32% slope, the inclination of the tunnel axis increased constantly with a 600 m vertical radius
and reached a final slope of 45%. These percentages requires the solution of many technical problems regarding jacking
pressure, slurry pumping network, fluid losses, safe access to the tunnel by properly trained workers. A suitable ropes
and breeching system was developed to ensure the safety and to continue the tunnelling works althought the high slope
percentage. Despite the described problems the microtunnel was completed within the foreseen period of time.
Microtunnel
Microtunnel
Customer
SHELL Deutschland Oil GmbH
Execution period
July 2011 May 2013
Contract value
15.885.606,00
Technical data
No.
Microtunnel
Machine
Length
ID
OD
Godorf-Tunnel
AVN D 2000 AB
1300 m
2000 mm
2500 mm
Wesseling-Tunnel
AVN D 2000 AB
1200 m
2000 mm
2500 mm
Pipeline description
Starting shaft
Shell Deutschland Oil GmbH planned the construction of an underground pipeline to connect the two Shell refineries in
Wesseling and Cologne. The line is about 3,8 km and crosses the Rhine twice. The aim was to avoid the installation of
the pipeline in the densely populated area on the left side of the Rhine. Both crossings, with a length of respectively
1.191 m and 1.299 m, were executed in microtunnelling process. The drilling was executed with reinforced concrete
pipes DN 2000, which later acted as casing pipes for several product lines.
To perform the
project river Rhine
was crossed twice.
Here you can see
a map of the
project, which
required also the
installation of 1.5
km of pipeline in
between to
connect the two
Shell refineries.
Microtunnel
I.CO.P. was awarded both drilling projects thanks to its expertise based on the successful execution of many similar
projects in the field of microtunnelling. The contract was concluded according to international / English contract law
(EPCM Contract Engineering / Procurement / Construction / Management), so that it can be spoken not only of
construction performance but also of project success.
Technical challenges:
Crossing of several dikes in in homogenous ground conditions and work within a potential flooding-area.
Several layers of brown coal had to be tunnelled through.
Soil conditions :
Launching pit:
Gravel, sandy Gravel, clay
Receiving pit:
Gravel, sandy Gravel
Drilling section: Gravel, sandy Gravel, clay, brown coal
(more than 750 m)
AVN D 2000 AB
Cutting wheels
Launching Pit
Break through
Microtunnel
Execution period
November 2010
Work value
2.600.000,00
Technical Data
No. MT / Direct Pipe Machine
Length
ID
OD
Straight sections
360 m
1200mm
83,13m + 36,10m
96,99m + 114,14m
Dosolo (DP)
AVN1000XC
596 m
1200mm
209,57m+148,56 + 29,60m
211,13m
Fiumazzo (DP)
AVN1000XC
371 m
1200mm
97,00m + 114,14m
Reno 1 (MT)
AVN2000D
462 m
2000mm
2500mm
29,94m + 35,94m
396,08m
Reno 2 (DP)
AVN1000XC
721 m
1200mm
241,48m+149,34
329,93m
/ gradient
Curved
sections
As part of the works for the construction of the pipeline SNAM Poggio Renatico Sala Bolognese, I.CO.P. has been
using a new trenchless technology called Direct Pipe to carry out three crossings.
Patented by Herrenknecht AG, the Direct Pipe technology combines a typical microtunneling drilling system with a
special thrusting unit called Pipe Thruster, enabling the laying of product pipelines without need of previously
realized casings, as it is the case in microtunneling works.
The Pipe Thruster consists in a clamping unit connected to a base structure by means of two hydraulic cylinders. By
means of this system the steel pipeline is fastened and thrust into the soil, advancing as drilling takes place.
In this way, long pipe strings are pulled in at a time, while considerably reducing both drilling and pull-in times, if
compared to other trenchless technologies. The crossing of the channel Scolo Riolo - nearby Galliera (Bologna) worked as pilot project for the launch of this technology in Italy.
Microtunnel
The drilling consisted in the crossing of a river and a B-road. The drilling section, with bowing effect, had a total length
of about 380 m, with a starting gradient of 7% and final gradient of 8% at the receiving pit. The drilling mainly took
place in clay soils of medium consistency, with a few sections in clay sands. Two 48-inch pipe strings of 190 m each
were pulled in and welded together after the first pull-in sequence. The crossing, including welding operations, was
completed in about 10 days from the launch of the TBM. Maximum daily production amounted to 100m.
View of the starting shaft and the pipe string being pulled in
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Microtunnel
Customer
Snam S.p.A.
Execution period
august 2010
Work value
1.820.000,00
Technical Data
Microtunnel
Area
L(m)
ID(mm)
ED(mm)
Offshore
Livorno-Italy
750
2000
2500
AVN 2000
Construction of a 32" pipeline which, from the OLT LNG terminal, located off the Tuscan coast, reaches the mainland
and joins the national transportation system in the municipality of Collesalvetti (Livorno). From the environmental point
of view Livorno and its ecosystem are considered protected areas, but in the junction area have been found traces of
contaminants that characterized the materials handled during the excavation as hazardous waste. For this reason,
treatment and disposal of polluted materials would have constituted a significant burden in terms of cost and
implementation time for the project. The alternative to digging an open trench was the trenchless technology, by
means of a microtunnel able to pass under the polluted areas and to reduce the amount of material being handled.
This technology implied an horizontally moving forward, towards the open sea, of a cutter head with ED of 2.5 m. The
microtunnelling profile was determined by considering the maximum share of polluted sediments and the point closest
to the coast with depth at least of -3.50 m (necessary in order to place a barge with a crane to recover the TBM). This
resulted in a total length of microtunnel equal to 750m at a depth ranging from -8.80 m to - 6.00 m.
Microtunnel
The cutter head was placed in a 11.50 m deep shaft, dug in a "artificial temporary peninsula", previously constructed
near the Canal Calambrone Bridge. Once, reached the final length of 741m, as provided in the project, the operations
for the recovery commenced of TBM started following the listed steps: dredging around the cutting head, shaft and
tunnel flooding with sea water, disconnection of the TBM from the first concrete ring, coupling and removal of the TBM
by means of a suitable crane placed on the pontoon. The excavation of the tunnel reached peaks of 53 meter daily
progress, respecting the timeframe of the program and without facing any technical problem. The drilling equipment
installation was complicated by the small size of the thrust shaft and by the different structures necessary for its
stability. After the necessary work to allow the TBM through the thrusting wall the installation of the microtunnel began.
The need to pass through sediments with very small bearing capacity has made the implementation very difficult,
requiring additional controls throughout the work activity in order to prevent mismatches with the quota and the
directions of the project. The excavated material has been treated by means of filter presses that have allowed the
transport to a waste recycling by reusing the water for the process of excavation and thus minimizing the use of
resources.
Backflling plant
Starting shaft
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Microtunnel
1232 - Cremona
Microtunnel River Crossing: Vacchelli Canal and Serio River as
part of the works for the construction of the Snam Rete Gas "
Cremona -Sergnano" pipline. Lot no. 3.
Customer
Snam S.p.A.
Execution period
august 2010 - may 2011
Work value
2.120.000,00
Technical Data
No. Crossings
Length
ID (mm)
ED (mm)
Vacchelli Canal
374,29 m
2000
2400
AVN 1500TI
boring
machine
Serio River
782,72 m
2400
3000
AVN 2000D
boring
machine
Machines
Snam Rete Gas has started laying the Poggio Renatico Cremona gas pipeline, which will have a total length of
about 150 Km, a nominal diameter of 1,200 mm (48) and a working pressure of 75 bars. It will take the place of the
existing, old ND 550 mm (22) pipeline in operation since 1959, which runs from Minerbio to Cremona, thus increasing
the capacity, flexibility and reliability of gas transport.
The gas pipeline runs through the Regions Emilia Romagna and Lombardy and the route of the new gas pipeline runs
along many watercourses, such as the rivers Reno, Panaro, Secchia, Taro and Po, which will be crossed with
trenchless technology to reduce the environmental impact of the work site to a minimum.
The works we are referring to in this technical sheet are part of Lot no. 3 of the pipeline, belonging to the Cremona Sergano increase.
Microtunnel
The new pipeline - DN 1200 (48) starts near the existing Snam Rete Gas plant called Cremona Junktion; it then
continues north-west ward, joining the existing pipeline DN 500 (20) as far as the existing Snam Rete Gas plant called
Sergnano Junktion where it ends.
The project involved the construction of two river crossings using the microtunnelling technique.
The Vacchelli Canal crossing has a catenary layout: initial straight section with a gradient of -10,5%, then curving with
radius R=1600m. Final straight section with a gradient of + 10,5%. The tunnel crosses sandy layers, with gravels quite
small in size (2 3 cm), at the beginning and at the end, it also crosses larger gravels alternate with silty and clayey
layers in its central part. Ground water level varies from 2 to 3 from ground surface.
The Serio River crossing has an initial straight section with a gradient of -10,5%, vertically curving with radius
R=2000m up to a gradient of +0,5%; a straight section of about 295 m and another vertical curve with radius R=2000m
follow in order to connect it with the breakthrough straight section with a gradient of 9,3%. The tunnel crosses sandy
layers, with gravels (maximum size: 10 cm) at the beginning and at the end; there is a presence of alternate sandy
and gravelly layers in the central part. Ground water level varies from 1 to 2 from ground surface.
In both cases the starting pit perimeter walls are made of sheet-piles. Inside that area it was then built the concrete
box construction, including the thrusting and insertion walls.
Mixed boring head for M591 used for the Vacchelli Canal
crossing
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Microtunnel
Customer
DENYS NV
Execution period
april 2010 - may 2011
Work value
3.034.202,00
Technical Data
No. Microtunnel
Length
ID(mm)
ED(mm)
PK0-PK13
1174 m
2000
2500
Pk53-V66
447 m
1600
2000
Jacking station
The work consisted in the construction of 3 microtunnel with lengths of 1174 m, 884 m and 447 m and the relative
starting and receiving pits.
Peculiarity of the work was the recover of the AVN2000 M-583 machine from the sea ("OUTFALL" technique). The
recovery was carried out and coordinated together with our client, the company SIDRA of Rome, as part of the work in
Livorno for the regasification plant called OLT Offshore LNG Toscana. Special features of this work was the machine
equipment, which was designed and built by I.CO.P. s engineers and technicians in order to perform the recovery of
the shield ensuring perfect water tightness of electromechanical equipment.
After I.CO.P.'s work in Mira (Portugal) this is the first case in Italy of shore approach and its great success will help the
use of the microtunnelling technique any time it is necessary to use trencheless technology to solve problems related
to pipeline installation near the coastline.
Microtunnel
Injection plant
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Microtunnel
Customer
BEP Bunde-Etzel-Pipeline GmbH & Co KG
Execution period
november 2009 - november 2010
Work value
4.255.644,40
Technical Data
No. Microtunnel
Area
Length
ID(mm)
ED(mm)
Leer, Germany
1070 m
2000
2500
Ems river
Inner area
Microtunnel
Characteristics of the track: length L=1070m, initial descendent slope with a gradient of roughly 7%, Euler spiral for
about 200m until the middle section (without gradient); final uphill part for about 150m with a gradient of about 4%.
Level difference between the entrance and the exit of approximately 1m. Time of the drilling: 6 weeks
Drilling in clayey peat with presence of wood stumps at the beginning; then the material was mostly sandy loam, until
the last part where it was again clayey peat.
Installation of the pipeline by pulling from the arrival shaft with a rig for HDI. Installation of sledges for the pulling
phase in the tunnel.
Staff
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Microtunnel
Customer
Pescanova Group
Execution period
april 2008 - september 2008
Work value
3.375.000,00
Technical Data
Nr.
Microtunnel
Area
L(m)
ID(mm)
OD(mm)
1350
2600
3300
Machine
Model
Herrenknecht
AVND2000AB
Str../Curve
w/ ext.3300 - 1.1%
In 2008 I.CO.P SpA was awarded a special project in a small town near Mira in Portugal. Pescanova Group had
planned to execute this project in the expansion of the existing cultivation plant in Spain. The project consists of two
parts: civil construction of buildings, structures, ponds for the cultivated fish and the construction of a pipeline
connecting the cultivated area with the sea. The pipeline construction comes in 4 sections. Two sections (T1 & T2) are
for pipeline for the intake of the sea water and the remaining two sections (V1 & V2) are for the ones for the discharge
of the sea water. Concerning the environmental effects of the water used to grow the fish, a feasibility plan had been
studied and microtunneling method had been seriously considered as the most effective method to construct the 4
sections of the pipeline. The tunnelled outfall constructions are often an effective and sustainable possibility to
improve the quality of live in coastal areas. With the sea outfalls the water from the fish tanks can be transported away
from the coastline and discharged at locations where diffusion, dispersion and decomposition are enhanced.
Microtunnel
The tunnel starts from a shaft (dia.18m, depth 12m - diaphragm wall method) and exist towards the sea (subsea
recovery method).
The project was successfully completed in 10 weeks, 4 weeks ahead of schedule with 1 week of standstill due to
tunnel engulfment. 12 nos. Of Intermediate Jacking Station been installed along the tunnel but non had been utilized.
The tunnel was completed and push through for subsea recovery with maximum force of 1100tons. The project was a
trademark for the microtunnelling works with combination of best implementation results through proper engineering
and planning, use of lubrication, controls and guidance including the team works in this project.
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Microtunnel
Committente
Snam S.p.A.
Periodo esecuzione
Giugno 2004 - Febbraio 2005
Importo lavoro
3.000.000,00
Dati tecnici
N.
Microtunnel
Localit
L (m)
DI (mm)
DE (mm)
Leila
Fusine
600
2000
2400
R/p.20%
Valbruna
Malborghetto
585
2000
2400
C/ r.425
Rett./Curvo
I microtunnel sono stati realizzati per superare dossi montuosi, evitando aree boschive di elevato pregio naturalistico
(M.te Leila) e linteressamento di versanti acclivi e potenzialmente instabili (Valbruna), nellambito della realizzazione
del metanodotto Malborghetto-Tarvisio DN 900. Nel caso del microtunnel Valbruna lo scavo ha interessato la
formazione geologica dei calcari di Bellerophon, nelle sue facies dolomitiche ed argillitiche. Per meglio determinare i
rapporti tettonici-stratigrafici tra queste due formazioni sono stati realizzati 2 sondaggi a carotaggio continuo e 2
sondaggi a distruzione di nucleo (circa 120m di sondaggi complessivi): i risultati hanno evidenziato la presenza per
buona parte del tracciato dei calcari in facies argillitica. Per evitare frequenti fermi macchina dovuti allimpastamento
della testa nelle argille, stato ottimizzato il tracciato (curvilineo con raggio di curvatura = 4250 m) riducendo al
minimo lattraversamento di questultima formazione geologica a favore dei sovrastanti calcari dolomitici.
Microtunnel
Laccorgimento ha permesso di terminare la perforazione in circa 8 settimane, con produzioni fino a 115 metri
settimanali senza fermi macchina. Il microtunnel Leila stato invece scavato per i primi 450 metri allinterno della
Dolomia dello Schlern, dolomie e calcari dolomitici con locali fratture (UCS da 50 a 120 MPa) e per gli ultimi 150
metri nella Formazione di Buchenstein, calcari e calcari marnosi (UCS=80 MPa). Lelevata pendenza del tracciato
(20%) ha imposto ladozione di un particolare accorgimento "pipe-brake" (freno condotta), posizionato nel pozzo di
partenza, per evitare lo scivolamento della stessa durante le fasi di installazione di nuovi tubi in c.a. In entrambi i casi
stata utilizzata unAVN 2000D, dotata di una testa chiusa e dischi da roccia, con fronte ispezionabile dallinterno
della macchina nelleventualit di sostituire gli utensili di perforazione durante lo scavo.
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Microtunnel
Customer
Arge Stollen Backental
Execution period
February 2004 - July 2004
Work value
2.806.413,18
Technical Data
Nr
Microtunnel
Area
Backental
Mettmenstetten
Straight
L. (mt)
ID (mm)
grad. 1,4%
655
2000
OD (mm)
2500
The microtunnel is part of the project for the construction of a pipe for meteoric water collection connecting the
national road nr. 4.1.6 and the Backental treatment plant. This 1460 mt long pipe has been constructed contemporary
excavating on both sides of the tunnel with two different techniques, chosen according to their geological function. On
one end of the tunnel an open TBM Robbins cut the rocky part of the excavation (762 mt), on the other end the
Hydroshield AVN2000D drilled the glacial deposits (in presence of groundwater) with the microtunnel technique. In the
preliminary phase two investigations were conducted in order to determine the limit between the rock basis and the
upper morainal deposits. The results led to the definition of the exact route to be drilled with the AVN 2000D and the
one to be drilled with the TBM Robbins. A further geognostic investigation revealed the geomechanic characteristics of
the rock basis (constituted by sandstones, siltites and hard marles, with UCS 480-800 Kg/cm) and of the loose soil,
constituted by fluvioglacial and full of water morainal deposits.
Microtunnel
The AVN 2000 D was equipped with a closed rock cutting head, with a diameter of 2525 mm and 12" discs to drill both
the cobbles and the final rocky part.
Peculiar of the work was the recovery phase of AVN machine inside the tunnel drilled by TBM.
Separation plant
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Microtunnel
Customer
Praoil S.p.A.
Execution period
February 2003 - June 2003
Work value
3.617.328,00
Technical Data
Nr.
Area
Machine
Genova Pegli
Herrenknecht
Model
Drill.diam.
Curved tunnel
ID (mm)
AVN2000D
3025 mm
r.2150mm
2600
OD (mm)
L. (mt)
3000
643
In the project aiming to reorganize oil transportation, Praoil Oleodotti Italiani SpA, which is part of the Eni group,
decided to use the microtunneling technique in order to directly connect the Porto Petroli in Genova Multedo and the
Genova Pegli deposit.
The microtunnel construction avoided to cross all morphological asperities and also all structures and infrastructures
on the route. The use of an AVN2000D microtunneler allowed the crossing of the litotypes investigated by the
geognostic report: clays, calcitic lime, ophiolites, flowage.
The need to launch a pipeline made of nr. 4 pipes DN750mm and nr. 2 pipes DN300mm inside the microtunnel,
imposed the total respect of the very small lying tolerances. The guide system usually employed was used adopting
special devices, in order to reduce the tolerances typical of this kind of method. The area where the microtunnel was
excavated is geologically characterized by Quaternary covering and reduced lenses of plyocenic deposits (Argilliti di
Ortovero) laying on a cristallinic base, constituted by rocks related to oceanic crust (Gruppo di Voltri).
Microtunnel
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Microtunnel
9929 - Savona
Works to connect the deep ocean wharf of the Port of Savona
to the city cable-car lines
Customer
FUNIVIE S.p.A.
Execution period
january 2004 - 2010
Work value
35.472.374,28
Technical Data
tunnel hosting a
connecting shaft
conveyor belt
length.
480 m
DN microtunnel
2500
vol
1600 mC
microtunnel leng
1077 m
microtunnel gradi
22%
14,20 m
Intermediate shaft
Box tunnel
Construction of civil works and systems for the transport of raw materials offloaded from ships, to replace the old
cableway that crossed through the centre of Savona. The civil works involved a: sorting tower to gather the raw
materials as they are unloaded from the ships; a 480 m long tunnel running just under wharf ground level to host a
conveyor belt to carry the raw materials to the storage pit; connection well servig as storage for the materials (volume
approx. 1600 m3, depth 37.50 m below sea level and diameter 14,20 m).
Microtunnel
Inside the microtunnel DN 2500, lenght 1077 m, constructed onslope with a gradiente of 22%, there is a special
conveyor belt to move the raw materials from the port to the overlying hillside. To the already mentioned civil works, an
intermediate microtunnel aeration pit was added.
The route along which the work has developed: from sea
level - gradient: 22%
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Microtunnel
Execution period
August 2005-December 2006
Work value
20.678.000,00
Technical Data
Nr
Microtunnel
Crossing
I.D. (mm)
Nr
Microtunnel
Crossing
Ceresone River
Camisano (Vi)
Curved/St. L. (mt)
C/r.1800
159
2000
LEB channel
Mossano (Vi)
C/r.1800
306
Rio Puina
Camisano (Vi)
C/r.1800
261
2000
10
Bisatto channel
Barbarano (Vi)
C/r.2000
213
2000
Grimana Rd21
Camisano (Vi)
C/r.2000
213
2000
11
Scolo Rion
Villaga (Vi)
C/r.1800
189
2000
C/r.2000
216
2000
12
Scolo Seonega
Villaga (Vi)
S/g.1.61%
93
2000
Main road 11
Grisignano (Vi)
S/g.0.5%
90
2000
13
Scolo Liono
Sossano (Vi)
C/r.2000
273
2000
Rio Settimo
Grisignano (Vi)
S/g.0.4%
60
2000
14
Scolo Ronego
Orgiano (Vi)
S/g.1.53%
60
2000
Bacchiglione r.
Montegalda (Vi)
C/r.2000
738
2000
15
LEB channel
72
1800
Main road 16
Montegaldella(Vi) S/g.0.5%
90
2000
16
Gu river
318
2000
Curved/St. L. (mt)
I.D. (mm)
2000
In the area of Vicenza and Verona I.CO.P constructed 18 microtunnels. 16 of them were constructed along the new
pipeline Camisano Vicentino-Zimella DN 1400 (56) and 2 of them on the Sergnano-Tarvisio DN 850 (34) pipeline.
The work also included the construction of all starting and arriving shafts.
4.295 mt were drilled, in drilling sections going from the 738 mt of the Bacchiglione River microtunnel to the 60 mt of
Scolo Ronego one. Underground channel and river (Gu and Bacchiglione rivers) crossings, motorway and main road
crossings were constructed constantly checking the drilling pressure during the excavation, executed using two
Herrencknecht machines (AVN2000D machine for microtunnels nr. 1, 2, 3, 4, 7, 9, 10, 16 and AVN 1600 machines for
microtunnels nr 5, 6, 8, 11, 12, 13, 14, 15). The drilling involved alluvial river deposits, and more in general from
medium to fine sands with loam; near the main rivers (Gu river and Bacchiglione river) there were peat and clay
levels thick up to some meters; only locally there were gravellous strata.
Microtunnel
The drilling did not present any particular difficulty. Some problems of watertightness emerged in those shafts where
the excavation was executed within fine sand with loam deposits. In this cases the difficulties were overcome both by
the execution of well points and by using the jet grouting technique for the construction of reinforced concrete
diaphragm walls and sheet piles.
Cutting head
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Microtunnel
Customer
Snam Rete Gas S.p.A.
Execution period
2008 - 2009
Work value
42.150.000,00
Technical Data
N.
Microtunnel
L(m)
ID(mm)
ED(mm)
Castelluccio
960 m
2400
3080
Piano di Comi
915 m
2400
3080
TECHNICAL DETAILS OF THE CONSTRUCTION of the microtunnel Castelluccio in Villafranca Tirrena (ME) Italy:
The starting pit, situated inside the river shore, is constructed excavating and executing the concrete structure; the
arrival is inside a trench. The maximum depth under the mountain is of about 200m. The tunnel is constructed by
means of an AVN2500D with an external diameter of 3080mm.
Characteristics of the track: length L=960m, constant gradient of 5,6%, planimetric alignment with one curve of
radius R=4000m. Level difference between the entrance and the exit of about +55m.
Drilling in metamorphic rock with high degree of alterations and cracks, presence of more than one area of fault with
oblique direction compared to the alignment. Prolonged stop of the drilling process cause by the huge pressure and
friction made by the rocks passed during the advancement in a fault area. Realization of works to remove the
blockage and restart with the normal process of pipe jacking.
Insertions of sections with triple joint followed by pipeline installation from starting pit (thrust by a winch and pulleys).
Microtunnel
TECHNICAL DETAILS OF THE CONSTRUCTION of the microtunnel Piano di Comi in Villafranca Tirrena (ME) Italy:
The starting pit, situated inside the river shore, is constructed excavating and executing the concrete structure; the
arrival is inside a trench.
The maximum depth under the mountain is of about 120m;
The tunnel is constructed by means of an AVN2000D with an external diameter of 3080mm.
Characteristics of the track: length L=915m, first section without gradient followed by a vertical curve with radius
R=2500m and a final slope with a gradient of about 22%. Level difference between the entrance and the exit of about
+52m.
Drilling in metamorphic rock with high degree of alterations and cracks, crossing of a channel and an existing
pipeline with a cover of 6m.
Installation of the pipeline from the starting pit through the thrust made by a winch and pulleys. Insertions of sections
of line made with triple joint.
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Microtunnel
Customer
Snam Rete Gas S.p.A.
Execution Period
january 2008 december 2010
Work value
40.960.000,00
Technical data
No.Microtunnel
1 Bosco di Colma
2 Coston Tedesco
3 Lussari
Machine
Gradient
ID (mm)
AVN2000D
AVN2500D
AVN2000D
11%
5%
1,8%
2000
2500
2000
ED (mm)
3100
3100
3100
Bosco di Colma: drilling rig used to pull the pipeline in the tunnel
Microtunnel "BOSCO DI COLMA" (crossing of a mountain with a maximum depth of about 250m)
The starting pit, situated near the mountainside entrance, is realized with excavation and execution of the concrete
structure. The arrival point is realized in a open trench on the opposite side of the mountain.
The tunnel is realized with an AVN2500D with external diameter of 3100mm.
Characteristics of the track: length L=1320m, constant slope with a gradient of about 11%, absence of curve. Difference
in level between the entrance and the exit about +150m.
Drilling in rock through different formations; presence of fault areas and rocks with variable consistence and rank of
3
cracks. Huge quantities of water from the mountain with pressure over 2bar and flow about 15-20m /hr.
Usage of the intermediate jacking stations to complete the drive.
Installation of the pipeline by pulling from the arrival shaft with a drilling rig for HDI. Installation of sledges for the pulling
phase in the tunnel.
Microtunnel "COSTON TEDESCO" (crossing of a mountain with a maximum depth of about 100m)
The starting pit, situated near the mountainside entrance, is realized with excavation and execution of the concrete
structure. The arrival point is inside an open trench in the riverbed of a mountain torrent.
The tunnel is made with an AVN2500D with external diameter of 3100mm.
Characteristics of the track: length L=1065m, constant slope of about 5%, absence of curve. Difference in level
between the entrance and the exit about +50m.
Drilling in rock through different formation of lime; presence of rocks with variable consistence and rank of cracks,
3
crossing two areas of fault. Presence of huge quantities of water with pressure over 2bar and flow about 20m /hr.
Installation of the pipeline by pulling from the arrival shaft with a drilling rig for HDI. Installation of sledges for the pulling
phase in the tunnel.
Microtunnel
Geological section
Foundations
Client
CMT Cityringen Metro Project
Execution time
June 2013 - on going
Work value
1.713.000,00
Technical data
Pile diameter
1000-mm
6.140,00 m
Interaxis
800 mm
Bauer BG39
Pile depth
15 28 m
Bauer BG30
Site view
I.CO.P. Denmarks Aps is responsible for the execution of the secant piles which will build the main box and the
ventilation shaft of the new station of the metro in Skjold Plads.
This is one of the 17 new stations which the consortium Cityringen is building in Copenhagen as part of the works for the
construction of the new 16-kilometer-long ring to connect the central areas of Copenhagen (Kbenhavn H via
Rdhuspladsen and Kongens Nytorv; Frederiksstaden via sterport, Triangeln, sterbro, Nrrebro, Frederiksberg,
Vesterbro and back to Kbenhavn H) with the existing metro line.
I.CO.P. is executing secant piles with diameter of 1000mm and interaxis of 800mm for a total length of 6.140,0m. The
station consists in two parts: main box where 28-meter-long piles were executed and ventilation shaft with 15meter-long piles.
I.CO.P. has been employing for the execution of the piles two Bauer drilling rigs (BG40 and BG39) equipped with kelly
bar and rotary drive with diameter of 1000 mm. Bauer and Brunello casings are installed over the entire length of the
piles.
Particular attention is paid during the excavation to the following conditions:
Soil stratigraphy (sandy layers alternating with sedimentary rocks and clay layers down to 22 m; CPH Clay
limestone down to the trench end) ;
Presence of confined and not confined aquifers;
Closeness to apartment houses built without foundations in the early XXth century, still inhabited.
In order to prevent neighbouring structures from settling, casings are permanently kept in advanced position with respect
to the drilling tool during excavation. At the same time, in order to keep stable the hydraulic gradient between the trench
and the surrounding aquifers, the trench is continuously filled up with polymer-added water.
Great attention is paid to the installation of reinforcement cages as well. Indeed, as per technical specifications strict
tolerances are to be observed, in particular with regard to pile length (+15/-5 cm), rotational motion (<5) and vertical
deviation (<1/100).
Further preventive measures are taken, furthermore, in order to comply with very strict noise emission standards in urban
areas. In order to be able to comply with the 80-dBa limit, state-of-the-art technologies and special noise-attenuating
equipment are employed. As to environmental protection, I.CO.P. installed the particulate filter on all its machines.
Concreting
Casing removal
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Foundations
Client
CMT Cityringen Metro Project
Execution time
September 2013- February 2013
Work value
2.717000,00
Technical data
Trench width
1200 mm
Work size
5900 sqm
Trench length
2800 mm
Drilling rig
Bauer BG28
Trench depth
31,50 m
Trench cutter
Bauer BC 32
I.CO.P. Denmarks Aps is executing reinforced-concrete diaphragm walls, which will be part of the new station of the
metro in Trianglen Plads.
This is one of the 17 new stations which the consortium Cityringen is building in Copenhagen as part of the works for the
construction of the new 16-kilometer-long ring to connect the central areas of Copenhagen (Kbenhavn H via
Rdhuspladsen and Kongens Nytorv; Frederiksstaden via sterport, Triangeln, sterbro, Nrrebro, Frederiksberg,
Vesterbro and back to Kbenhavn H) with the existing metro line.
I.CO.P. Denmarks Aps will execute reinforced-concrete diaphragm walls having trench width of 1200 mm, length of 2800
mm and depth of 31,50 m, for a total area of about 6000 sqm.
I.CO.P. is employing for the execution of D-walls a drilling rig Bauer BG28 equipped with a trench cutter Bauer BC 32.
The excavation is carried out by hydromill technology. The use of bentonite mud to stabilize the excavation and as
medium to dig away the excavated material enables, indeed, high production rates, while minimizing the transmission of
vibrations to the ground and to the surrounding buildings.
The desanding unit is better suited, as opposed to other technologies, to collect the excavated material in a clean and
orderly way, so as to ease its removal and transport to landfill.
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Foundations
Client
CMT Cityringen Metro Project
Execution time
March 2013- November 2013
Work value
3.001.640,00
Technical data
Pile diameter
1000-mm
9.880,00 m
Interaxis
800 mm
Bauer BG39
Pile length
13 36 m
Bauer BG40
Further preventive measures were taken in order to comply with very strict noise emission standards in urban areas.
Besides, in order to be able to comply with the 80-dBa limit, state-of-the-art technologies and special noise-attenuating
equipment were employed. As to environmental protection, I.CO.P. installed the particulate filter on all its machines.
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Foundations
1290 Frederiksberg
Copenhagen - Denmark
Execution of drilling and grouting works at the Frederiksberg
Station for the TBM breakthrough in grout plug - The
Cityringen Metro Project - Copenhagen - Denmark.
Client
CMT Cityringen Metro
Execution time
January 2013 - April 2014
Work value
Project: 1.471.600,00
Wiide shot of the site Area 5: Works on the surface with drilling rig Casagrande C6xp and ongoing construction of the station
Technical data
Drilling diameter (with casing)
114 mm
Comacchio MC400
350 - 1300 mm
Interaxis
Borehole length
15 25 m
Grouting plant
Total length
10.100,0 m
Slurry pump
Lorenzetto Loris
4 injectors Elena 80/200
1 agitator L500
Duplex L01
TAM
D40/50 2valves/m
Storage silos
Injection packers
Compressor
Casagrande C6xp
cement silo 30 t
bentonite silo 30 t
Atlas Copco XAS 75 DD
Mixing plant (on the left) and grouting unit (on the right).
Further preventive measures were taken in order to comply with very strict noise emission standards in
urban areas. With the cooperation of CMT, soundproof material was installed on each wall during the first
working phase in the basement of the shopping centre; a proper soundproof barrier was installed, instead,
for outdoor works. Besides, in order to be able to comply with the 80-dBa limit, state-of-the-art technologies
and special noise-attenuating equipment were employed. As to environmental protection, I.CO.P. installed
the particulate filter on all its machines.
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Foundations
1233 Basaldella
Project and construction of the renewed road
crossing between S.S. 13 roadway and S.P. 89
roadway in Basaldella (Udine - Italy).
Client
Udine Province
Execution time
June 2010- September 2011
Contract value
5.571.586,00
Technical data
CFA piles
Underpass
730
Total length:
1 km
Piles diameter
900 mm
4+2
Piles length
from 5 to 15,5 m
Other works:
Total length
350 m
excavations;
new sewers and drainage systems;
road paving;
etc.
Work site
The intervention aimed to solve serious problems of traffic congestion in the area. It required a major change of the
crossroad, which was split in different levels. It was necessary to build an underpass, which had to be executed without
interfering massively with the viability and therefore without totally closing the road. The underpass construction required
a number of consolidation and protection works. In particular it was necessary to install a piling both to temporarily bear
the deck and the adjacent roads and to allow the final masonry works to be carried out. The composition of the soil led to
use, for such piling, the Cased Secant Piling Technology (CSP) since the installations made with secant piles provide
excellent sealing characteristics, improved verticality and a higher quality finishing.
730 piles were drilled, both contiguous and secant ones. The secant piles were left in place, since they became the final
masonry support of the land adjacent to the new road.
Once the piling was ready it was possible to carry out the excavation of the ground between the two rows of piles until
reaching the underpass ground level. The precast support beams in prestressed concrete supporting the deck of the
viaduct were placed on the side abutments of the underpass and on the provisional central piles. The procedure ended
with in-situ concrete casting.
.
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Technical specifications
Floor dimension
180,00 x 60,00 ml
110 - 2,40 ml
Panel depth
18,50 ml
110 - 2,80 ml
2,80 ml
The works consisted in the construction of the underground portion of the new Palazzo del Cinema of Venice outer
containment walls of the of the. The work was performed by means of CSM technique, which provides for the use of
special equipment able to consolidate the ground by drilling and mixing the soil and contemporary adding a mixture of
water, cement and bentonite. The resulting consolidated soil can develop a compressive strength of more than 5 Mpa
and K permeability coefficients of less than 1 x 10-9 m / s.
The treated soils are predominantly silty sands with the presence of man-made material in the first three meters from the
worktop and local clay layers in the deepest areas.
The work consisted in an approximately rectangular plant measuring 180 x 60 meters made of interpenetrated panels of
consolidated soil with thickness of 65 cm, depth of 18.5 ml and an average width of 240 cm. The cast-in situ panels were
then reinforced placing in each of them 4 welded HSL 550 bars connected together.
The consolidation work had to guarantee water tightness since the water table was at - 3.00 lm from ground level.
The work was carried out by means of a drilling rig equipped with cutter wheels able to drill the upper layers
characterized by the presence of masonry.
The excavation of the panels was carried out starting from primary ones. Once all primary panels were in place the
drilling of the secondary ones started. Secondary panels are interposed to the primary ones and clamped on them. The
interpenetration is ensured by the partial drilling of the primary panes for about 15 - 20 cm in order to obtain
homogeneous contact surfaces of consolidated soil.
The effectiveness of such technique allowed the consolidation of an average size of 140 sq m / day.
Customer
SMETRA
Execution period
March 2010 July 2010
Work value
1.200.000,00
Technical specifications
No. of micropiles
105
120
25,00 lm
Up to 15 meters
Pile diameter
250 mm
152 mm
The aim of the works was the execution of the foundation works building the new maternity unit of the Hospital Centre in
Monaco. This included the execution of micropiles DN 250 mm with variable lengths ranging from 20 to 28 lm for a total
length of about 2.700 meters and tie rods with lengths up to 15 meters and variable number of strands between 3 and
5 totalling 1.800 meters.
The soil crossed mainly consisted in marly limestone and clayey marl.
Being the works executed next to the existing hospital building, it was necessary to use small-size but high-torque drilling
rings, able to reach the narrowest spaces and, at the same time, ensure drilling diameters up to 250 mm.
Customer
Smetra
Execution period
February 2009 May 2010
Work value
3.200.000,00
Technical specifications
No. of piles
95
250
25,00 lm
Variable, 15-25 lm
Pile diameter
880 mm
152 mm
The aim of the works was the execution of foundation works as soil retaining structures during the excavation of the
basement for the underground parking area of the Technical High School. This included the execution of four- and eightstrand tie rods with variable length between 15 and 25 lm for a total length of about 5.000 meters and piles with lengths
up to 25 lm and diameter of 880 mm, totalling 2.400 meters.
The soil crossed mainly consisted in limestone rocks.
Execution period
August 2007 October 2007
Work value
405.000,00
Technical Data
Total length
460 lm
Trench thickness
0,50 lm
6.400 m2
Soil conditions
12 18 lm
Panel excavation
The works consisted in the execution, nearby the built-up area of Ponts, in Spain, of a watertight barrier
placed around the pipe trench meant for the laying of a reinforced concrete pipeline DN 3000 mm for
drinking water.
The pipeline, with total length of some kilometers, crosses different soils in presence of ground water. The
installation of the pipeline was made possible only by sealing the area of excavation and lowering the level
of the ground water inside the area enclosed by the plastic diaphragm barrier.
The excavation of diaphragm walls took place in mainly sandy soils and some centimeter-thin conglomerate
layers. Drilling depth ranged from 12 to 18 meters, down to about 1 meter into the underlying rock substrate.
Construction site
Construction site
Construction site
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Technical specifications
Average floor dimensions
75,00 lm x 22,00 lm
38, 2,50 lm
Trench depth
36,00 48,00 lm
38, 2,80 lm
Trench thickness
1,20 lm
The works consisted in the execution by trench cutter of perimeter diaphragm walls to act as retaining walls for the
stations of Venizelos, Agia, Sofia, Sindrivani, Panepistimio and Papafi, as part of the works for the construction of the
Thessaloniki Metro.
To this aim trench cutters were used to drill and cast diaphragm walls with variable depth between 36,00 and 48,00 lm
and thickness of 1,0 and 1,20 lm.
As opposed to conventional equipment used for the execution of diaphragm walls, trench cutters are effective also in
presence of rock masses or particularly compacted layers, which would be otherwise difficult to cross; they ensure,
furthermore, watertight surfaces and minimize verticality deviations, which may easily result, due to the length of the
panels, in the failure to meet project requirements.
The excavation of diaphragm walls by trench cutter takes place inside two reinforced concrete guide walls, which are
built on purpose to enable the exact positioning of the drilling rig. Each panel is excavated in one stage and is as wide as
the cutter, that is 2,80 m. The excavation of primary panels is followed, after setting for at least 3 4 days, by the
execution of intermediate secondary or closing panels.
During the execution of secondary panels, in order to obtain the exact overlapping of the different casting sections,
primary panels are partly cut through. The overcut thickness, which is mainly dependant on drilling depth, ranges from 15
to 20 cm for panels with depth between 20 and 40 lm. The overcutting of primary panels enabled the formation of coarse
and clean contact surfaces, thus creating high quality joints able to ensure a very high watertightness degree.
Technical specifications
No. of columns
4.350
Injected length
10 + 2 lm
43,00 lm
Type
Bi-fluid
Column diameter
1.500 mm
The works consisted in the construction of perimeter and central bearing walls for the underground station of piazza
Annibaliano, in Rome, along with the execution of the jet grouted bottom plug, in order to counteract buoyancy forces.
The execution of the bottom plug took place in mixed soils, at a depth of about 30,00 to 45,00 lm from ground level.
To this aim special equipment was used, able to reach the requested depths by way of an automatic rod loading system
and, for one of the three rigs employed, through the use of a over-53-lm-long mast, thus enabling the effective and
continuous execution of the works. The jet grouted columns, with a diameter of 1500 mm, were obtained by using the bifluid (i.e. grout and air) method.
Drilling rig BG28: Washing up of the rods after completion of injection works
Drilling rigs BG28 and C14 for the execution of the bottom plug
Subsoil
Customer
Municipality of Venice
Execution period
July 2005 - December 2006
Work value
6.075.640,43
Technical Data
Prestressed concrete deck
510 sm
Ramp length:
375 m
Ramp width:
20,50 m
Underpass view
The works consisted in the construction of an underpass with prestressed-concrete slab and the later
excavation of the underlying ground in presence of ground water, with a pumping system of 11 wells.
Prior to excavation, a tensile test was executed on the anchoring piles of the foundation slabs of the ramps
in order to counteract ground water buoyancy forces.
The walls of the ramps were faced with sound-absorbing panels and sound-absorbing bituminous
conglomerate was used for paving.
Subsoil
Final surveys
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Customer
Consorzio G.T. & P.
Principal
SUDMETRO S.c.a.r.l. - Napoli NA
Execution period
April 2002 October 2002
Work value
2.080.000,00
Technical specifications
Average floor dimensions
45,00 lm x 19,00 lm
24, 2,35 lm
Trench length
45,00 lm
24, 2,80 lm
Trench thickness
1,00 lm
Trench cutter BC30 mounted on a Liebherr 882 (Station no. 1, Piazza Duomo)
5,760 mq
The aim of the works was the construction of the perimeter walls of 2 underground stations in Naples. The works mainly
included the excavation and casting of diaphragm walls with average depth of 45,00 lm and thickness of 1,00 lm. The
floor dimensions of the stations (i.e. 45,00 lm x 19,00 lm) required, for each site, the excavation of 48 watertight
reinforced concrete panels, considering the presence of ground water at -3,00 lm from road level.
The works were executed by using a trench cutter, that is a drilling machine able to cross both the loamy upper layers
(over the first 20 linear meters) and the deepest lithotypes, mainly made up of tuff. The ability to cut even through the
concrete of the primary panels also ensured the regular and smooth interfacing among the diaphragms, thus
guaranteeing the necessary concrete adherence and continuousness of casting operations and obtaining, in this way,
the required water tightness degree.
The use of a suitable desanding and slurry treatment plant enabled, furthermore, a fast and easy spoil disposal.
Technical specifications
Average floor dimensions
160,00 lm x 25,00 lm
110, 2,50 lm
Trench length
44,00 lm
110, 2,80 lm
Trench thickness
0,80 1,20 lm
The works consisted in the construction of perimeter and central bearing walls for the underground station of piazza
Annibaliano, in Rome, along with the execution of the jet grouted bottom plug, in order to counteract buoyancy forces.
To this aim diaphragm walls with average depth of 44,00 lm and variable thickness ranging from 0,80 to 1,20 lm were
drilled and cast.
The presence of ground water at -7,50 lm from ground level required the use of technologies able to ensure a suitable
water tightness degree. Indeed, a trench cutter was employed for the execution of the works, that is a machine able to
easily cross both the loamy and clay-loam upper layers (over the first 25 linear meters) and the deeper partly compacted
gravels (down to the required project depth). Using the trench cutter enabled the execution of high quality joints, thus
ensuring a very high water tightness degree. The exact overlapping of casting sections is ensured, indeed, by the ability
of the trench cutter to partly cut through the primary panels while drilling secondary ones, creating in this way coarse and
clean contact surfaces. The overcut thickness, which is mainly dependant on drilling depth, ranges from 15 to 20 cm for
panels with depth between 20 and 40 lm.
The use of a suitable desanding and slurry treatment plant enabled, furthermore, a fast and easy spoil disposal as well
as the effective treatment of bentonite slurries. The specific treatment solution adopted enabled, indeed, to preserve over
a longer time the properties of the slurries, used to stabilize the ground and ease the discharge of the excavated spoil.
Drilling rigs BG28 and C14 for the execution of the bottom plug
Technical specifications
Station dimensions
100,00 lm x 10,00 lm
Trench depth
Up to 35,00 m
Trench thickness
0,80 lm
~ 12.000 m
As part of the works for the construction of the Line C of the Rome Metro, diaphragm walls were executed by trench
cutter to act as retaining walls for the Station Torrespaccata.
The works included the excavation and casting of diaphragm walls with variable depths up to 35,00 lm and thickness of
0,80 lm.
To this aim trench cutters were used, which as opposed to conventional diaphragm wall construction equipment, are
effective also in those soils which would be otherwise difficult to cross, such as in presence of rock masses or particularly
compacted layers. A further advantage of trench cutter is, moreover, their ability to minimize verticality deviations, which
may easily result, due to the length of the panels, in the failure to meet project requirements.
The excavation of diaphragm walls by trench cutter takes place inside two reinforced concrete guide walls, which are
built on purpose to enable the exact positioning of the drilling rig. Each panel is excavated in one stage and is as wide as
the cutter, that is 2,80 m.
The excavation of diaphragm walls consists in the execution of two different types of panels: first, primary panels and,
after setting for at least 3 4 days, secondary or closing panels.
During the execution of secondary panels, in order to obtain the exact overlapping of the different casting sections,
primary panels are partly cut through. The overcut thickness, which is mainly dependant on drilling depth, ranges from 15
to 20 cm for panels with depth between 20 and 40 lm. The overcutting of primary panels enables the formation of coarse
and clean contact surfaces, thus creating high quality joints able to ensure a very high watertightness degree.
Technical specifications
2
Station dimensions
86,00 lm x 25,00 lm
~ 5.000 m
Trench depth
Up to 50,00 m
~ 17.500 m2
Trench thickness
1,20 lm
As part of the works for the construction of the Line 6 of the Naples Metro, diaphragm walls were executed by trench
cutter to act as supporting and retaining walls for the Station San Pasquale.
The works included the excavation and casting of both linear and T-shaped diaphragm walls with variable depths up to
50 lm and thickness of 1,20 lm.
For the execution of the works trench cutters were used. As opposed to conventional equipment used for the execution
of diaphragm walls, trench cutters ensure effective operation also in presence of rock masses or particularly compacted
layers, which would be otherwise difficult to cross; they ensure, furthermore, the formation of watertight wall surfaces and
minimize verticality deviations, which may easily result, due to the length of the panels, in the failure to meet project
requirements.
The excavation of diaphragm walls by trench cutter takes place inside two reinforced concrete guide walls, which are
built on purpose to enable the exact positioning of the drilling rig.
The excavation of each panel having the same width as the cutter, that is 2,80 m takes place at one sitting. First
primary panels are executed. After setting for at least 3 4 days, the excavation of intermediate secondary or closing
panels starts.
In the specific case of the works at the Station San Pasquale, due to the particular geometry of T-shaped diaphragm
walls, trench excavation was thought to take place in two stages thus positioning the rig anew prior to proceeding
with casting operations. The use of a special machine called HTS able to turn the trench cutter 180 enabled instead
the execution of such challenging diaphragm walls from the same initial position.
During the execution of secondary panels, the exact overlapping of the different casting sections is obtained by partly
cutting through primary panels, what enables the formation of coarse and clean contact surfaces, thus creating high
quality joints able to ensure a very high watertightness degree. The overcut thickness, which is mainly dependant on
drilling depth, ranges from 15 to 20 cm for panels with depth between 20 and 40 lm.
Technical Specifications
Municipio Station
Duomo station
~ 21.000 lm
~ 56.000 lm
~ 1.050 m3
~ 3.700 m3
Chemical injections
Chemical injections
~ 12.700 m3
600 m3
By combining the expertise and competence of its technical staff with the cooperation of some of the best designers and
experts in the field, I.CO.P. has been developing and setting up state-of-the-art soil consolidation technologies both at
design and at a technological and operational level finding itself relying on equipment and machinery (e.g. drill rigs,
cement and chemical grout mixing plants, injection plants) able to perform soil consolidation works in the widest range of
situations, both outdoors and underground, not least thanks to the most advanced software tools for the collection,
monitoring and recording of drilling and injection parameters.
In the case of the works at the Naples Metro (Intermediate Stations Municipio and Duomo) the need to execute injections
(completed in June 2010) was due to the low permeability and consolidation degree of the tuff and pozzolanic layers in
the area of the works (station shafts and platform tunnels).
6-injector auto-station
The works usually consist in the execution of two different injection types, to be performed separately.
The first is the injection of bentonite-stabilised cement suspensions (C/W ratio: 0, 30,5) aimed at grouting major
cracks and intergranular spaces and creating, in this way, a kind of shell meant to contain the following injection.
The latter is, instead, the injection of three-component grouts (excluding water), that is high-penetrability sodium
silicate solutions meant to fill up and grout small-sized cracks and intergranular spaces which cannot be treated with
the previous injection type.
They are silica-based inorganic solutions characterised by syneresis absence, low initial viscosity and adjustable
setting time depending on the percentage of reagent, and obtained by mixing with water, before injection, different
volumes of three main elements:
Sodium salt solution (active reagent affecting the initial setting phase);
High-density cement suspensions (C/W<0,5) with addition of specific products aimed at ensuring high
fluency, expansion, fast initial setting time (30-45 min) and high compressive strength of the final product;
One or two component water-reactive resins characterised by very high penetrability, limited range, very fast
reaction (7-8 sec) and high expansion (30-40 times greater than the initial volume); such grouts are employed in
structural works and/or in natural grounds characterised by continuous and significant flows of water due to
inconsistency and/or micro cracks, which are therefore difficult to treat with the previous injection type.
Customer
FUNIVIE S.p.A.
Execution period
August 2004 - June 2006
Work value
22.975.909,84
Technical Data
Internal shaft diameter
14,20 mt
10,
2,05 ml
41,00 mt
10,
2,80 ml
1,00 mt
Separation plant
Construction of the perimeter walls of microtunnel DN 2005 starting shaft. Inside the tunnel there is a
special conveyor for the carbon transportation from the port to the above hill. The shaft will be then
completed with a stocking silo and with the needed works of inspection and control.
The shaft is a cylindrical structure (with an internal diameter of 14,20 ml) constructed by the excavation and
the casting of reinforced concrete diaphragm walls 41,00 mt deep and 1,00 mt thick. Due to the presence of
groundwater at 2,20 ml above the ground surface it was necessary to use techniques able to guarantee
water retention.
For the excavation it was used a trench cutter able cut both upper sandly soft ground (first 28 mt) and the
deepest hard ground rocks, constituted by quartzytes with UCS until 100 Mpa. The possibility to cut the hard
layers, but also the primary panels concrete allowed the construction, between the diaphragms, of regular
interfaces free of waste perfectly suitable to guarantee concrete bond conditions and casting continuity. In
this way it is possible to reach the requested water retention.
The use of an appropriate desander and desilter for bentonite slurry has allowed an easy and quick mucking
waste disposal.
Separation plant
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
0101 - Delizia
Construction of a new bridge over the Tagliamento River
Customer
Anas - Roadway Construction Department for Friuli Venezia
Giulia S.p.A.
Execution period
April 1992 - October 1994
Work value
4.530.323,51
Technical Data
Main works executed:
- new bridge;
- new underpass;
- new access ramp
- new service road.
The construction of a new roadway junction between roadway no. 13 called "Pontebbana" and roadway no.
463 in Delizia area included the construction of a new bridge and the complete reorganization of the local
viability. The work was devided into two funcional batches. Among the numerous works performed, the two
continuous, prestressed reinforced concrete viaducts with curved progession, respectively 452 and 263 m in
length and 8,20 m in width with maximum span length of 36,60 m are worthy of particular mention.
Another very important constuction is the underpass for the Venice - Udine railway line, which was installed
by means of hydraulic thrust. It has a 21,10 x 5,30 m section.
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Customer
Municipality of Portomaggiore - FE
Execution period
March 2004 - Mai 2006
Work value
4.322.978,32
Technical Data
Road length:
3.650,00 m
No. of roundabouts:
Other works:
joints replacement
lengthening of r.a.
The project mainly consisted in the direct connection of two A-roads the A-road 16 Adriatica and the
former A-road 495 with straight course and quite wide turns (radius=300m) and the construction of 5
roundabouts to connect the existing roads.
Several works were executed for the crossing of outlet channels, including the construction of box culverts
made up of cast-in-situ sections with maximum span of 280 cm or vibrated reinforced concrete pipes
1000.
The project also included several works at crucial existing junctions connecting with the municipality of
Ferrara, among them: the installation, after milling, of a wearing course type Splittmastixasphalt over the
entire length; the removal and replacement of the expansion joints of an existing railway overpass; the
installation of the new street lighting and the new road signs.
The technical solution adopted for the execution of the road embankment was meant to minimize earth
movement. For this reason, indeed, the embankment bearing the road structure was executed by mixing
after on-site soil analyse earth with lime. This considerably increased its bearing capacity, preventing,
therefore, possible deformations of the project road. The lime stabilization made it, furthermore, possible not
only to reduce earth movement to a minimum, but also to best exploit the potential of the lithoid elements
contained in the soil.
TECHNICAL DATA
a) asphalt-treated ridable section: 2 x 3,75 = 7,50 m;
b) asphalt-treated shoulders: 2 x 1.50 = 3.00 m;
c) road embankment sides: 2 x 1.00 = 2.00 m;
d) road embankment gradient: 2/3;
e) minimum depth of ditches
from ground level: m 0,50;
f) minimum width of ditches: m 1.50;
g) minimum buffer strip (unbuilt space): m 18;
h) minimum roadbed depth: m 0,60;
l) maximum cross slope: 2.5%;
m) maximum longitudinal slope: 3.2%;
n) road embankment composition: earth-lime mixture.
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
1210 - Pianzano
Extension of the highway A28 from Pordenone to Conegliano.
By-pass of the B-road 41 in Pianzano
Customer
Autovie Venete S.p.A.
Execution period
March 2009 - September 2010
Work value
9.137.572,99
Technical Data
Road length:
m 3.550,00
Other works:
1) 4-way r.a.
2) big-diameter r.a.
3) underpass
The project mainly consisted in the execution of the final section of the extension of the highway A28 from
Pordenone to Conegliano lots 28 and 29 between Sacile Ovest and Conegliano. This connecting road,
named variante della S.P. n 41 (i.e. bypass of the B-road 41), starts from the north-west roundabout under construction placed outside the tollbooth in Godega, crosses the B-road 165 Ungaresca with a
crossroads roundabout, underpasses the railway line Venice Tarvisio, then heads north again with a
second, wide turn, crosses via Trieste and via Montegrappa with a second roundabout and finally meets the
A-road 13. On the whole, the new section, running over the municipalities of Godeda SantUrbano and San
Fior, extends for 3.550m. The bypass was executed following the model of the typical roadbed of
secondary extra-urban roads, as per category C2 of the Italian Ministerial Decree dated 05.11.2001, i.e. one
single lane with length of 3,50 m in both directions and shoulders of 1,25 m each, for a total paved width of
9,50 m. The project included just one main construction work of particular structural relevance and some
other secondary works.
1) Underpass of the railway line Venezia Udine, with total length of about 700,00 lm and consisting in the
execution of: double diaphragm wall over the entire length of the ramps; double wall of vertical jet-grouted
columns, under the rails; bottom plug made up of successive jet-grouted columns over the entire ramp
section under ground water; launching ditch right under the railway embankment and, inside, a precast box
culvert to be pushed under rail by using (short-stroke) hydraulic jacks steered by hydraulic power pack;
temporary bridging structure (type ESSEN) to support the railway line during pull-in; precast reinforcedconcrete box culvert to be pushed through under the railway, with length of about 26 m, span of 11,50 x
6,00 m and 1,05 m thickness; floor slabs and D-walls concrete slabs.
2) Execution of a four-way roundabout on the A-road 13 placed at the centre of the traffic lights crossroad
named delle 4 strade, in the municipality of Godega, while keeping the existing crossroad.
3) Execution of a big-diameter roundabout outside the tollbooth in Godega SantUrbano in order to connect
the highway with the existing B-road 41.
MINOR CONSTRUCTION WORKS
1) Outlet channels: the continuous functioning of the existing water systems on the surface was ensured by
using box culverts with section 2,00 x 1,50 m or reinforced concrete pipes i.d. 1000;
2) Noise mitigation measures: instead of classic artificial barriers, natural sound barrier systems were
installed, made up of trapezoidal earth embankments of 2,00 2,50 m height made green and planted
on which artificial barriers of moderate height find place.
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Customer
Prime Minister's Office - Italian Civil Protection Department
Execution period
November 2005 - November 2006
Work value
1.706.525,37
Technical Data
Total Length:
85,34 m
Total width:
7,18
Roadway width:
3,29 m
50,00 t
5,84 m
532,00 m
Walkway width:
0,85 m
Total weight:
206,00 t
The bridge over the Payee River has been built at the intersection of the " Rumbeck - Yirol" track in
correspondence with the existing ford. The structure consists of a Bailey type metal bridge of the overall
length of approximately 85 m, with two central spans of approximately 24 m each and two side spans of
about 16 m each. The three piers, each one consisting of two 66 cm in diameter metallic columns, and the
two abutments are based on 30 cm diameter steel piles. The rigid pile - pile and pile abutment
connections have been constructed using a special metal structure which, during the execution of piles,
worked as a foundation profile (a template) for their placement.
Each element of the bridge was previously prepared and tested in Italy.
Works phases: preparation of the projects and materials (in Italy); preparation of the field support base for
the Italian workers; layout and construction of micropiles; assembly of piles, abutments and bridge;
construction of an embankment to protect the adjacent town.
In the design of the bridge it was taken into account , among other things : the lack of specific construction
materials on site, the lack of specific means of excavation and transport on site, the impracticability of some
tracks, of the need to complete the installation before the rainy season.
Installation of micropiles
Construction phase
Load test
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000
Customer
Anas - Roadway Construction Department for Friuli Venezia
Giulia Region
Execution period
April 1992 - July 1998
Work value
14.551.147,31
Technical Data
Works executed:
- new bridge;
- new viability.
The construction of the new bridge over the Cellina mountain stream bordered on the Belluno roadway no.
251 in the Val di Zoldo and Valcellina. It implied a massive movement of land and materials in order to allow
the installation of large diameter driven-in-piles. Reinforced concrete works were perfomed both for the
foundations and for above-ground works for abutements and piles of varying sections. The deck scaffolding
mixed structure has been built by means of metal structures and reinforced concrete and prefabricated
beams. After foundation and construction works also road paving has been performed, together with a large
number of completion works.
This major intervention required, together with a new viability, a new waterway rearrangement.
I.CO.P. S.p.a.
Via S. Pellico, 2
33031 Basiliano
(UD) Italia
ISO 9001
ISO 14001
OHSAS 18001
SA 8000