You are on page 1of 2

PT.

CIPUTRA ADIGRAHA
Ciputra World Jakarta

CIPUTRA

PROJECT MANAGER'S FINAL CERTIFICATE


PERBAIKAN RETAKAN LANTAI
PROJECT
PACKAGE
CONTRACTOR
WORK ELEMENT
CONTRACT REFERENCE
The Employer

The Contractor / Supplier

Project Address

Ref:
Date:

Section ALL

435/SPK-CAG/CW-STR/XI/2013

Ciputra World Jakarta


Perbaikan retakan lantai
CV. WIBAWA PERKASA
Parking Podium
435/SPK-CAG/CW-STR/XI/2013

Date 29th November 2013

PT. CIPUTRA ADIGRAHA


Jl. Prof Dr Satrio Lot 3-5
Kuningan - Jakarta Selatan
CV. WIBAWA PERKASA
Jl. Merpati VI No. 6
Pesanggrahan - Jakarta Selatan
CIPUTRA WORLD 1 JAKARTA
Jl. Prof Dr Satrio Lot 3-5
Kuningan - Jakarta Selatan

This Final Certificate is issued pursuant to the Contract Ref : as noted aboved and subject to the final commercial agreement.
On behalf of the Employer and in accordance with the Conditions of Contract we here by confirm that with the exception of the items as listed in the Final Account Agreement, the above
mentioned Works have been completed to the satisfaction of the
Project Manager as of the
29th November 2015 (the Date of Final Certification)
Expiry Defects Liability Period
Defects Liability Period Injection and Self Penetration Works
6 months following the issue of the Taking Over Certificate Leak Podium
dated 27th May 2015
Expiry Defects Liability Period Leak Podium
27th November 2015
The Final Certificate Issued as Instructed by the Employer

Angela Hanggi
Associate Director of PT. CIPUTRA ADIGRAHA
The Final Certificate Accepted on behalf of the Contractor

Date:

27th November 2015

Agus Tinus
Project Manager of CV. Wibawa Perkasa
The Final Certificate Accepted on behalf of the Employer

Date:

27th November 2015

M. Zairin
Contruction Manager PT. Jaya CM
The Final Certificate Withnessed on behalf of the Employer

Date:

27th November 2015

Attachments:
Scope of Works included
List of Outstanding / Defective Works
As Built Drg Hardcopy & Soft Copy

Copies To:
CAG

JCM

OTHER

CONTRACTOR

REYNOLD

FILE

PT. CIPUTRA ADIGRAHA


Ciputra World Jakarta

CIPUTRA

PROJECT MANAGER'S FINAL CERTIFICATE


PERBAIKAN RETAKAN LANTAI
PROJECT
PACKAGE
CONTRACTOR
WORK ELEMENT
CONTRACT REFERENCE
The Employer
The Contractor / Supplier
Project Address
a.

Ref:
Date:

Section ALL

435/SPK-CAG/CW-STR/XI/2013

Ciputra World Jakarta


Perbaikan retakan lantai
CV. WIBAWA PERKASA
Parking Podium
435/SPK-CAG/CW-STR/XI/2013

Date 29th November 2013

PT. CIPUTRA ADIGRAHA


CV. WIBAWA PERKASA
Jl. Prof. Dr. Satrio lot 3-5 Karet Kuningan Jakarta Selatan

Areas included in this Final Certificate all as per the attached drawings referenced
LEVEL 09
LEVEL 07
LEVEL 10
LEVEL 11
LEVEL 08
LEVEL 12

AREA P1, P2, P5, P6, 02, 03, H3, H2, P3, P4, P9, A3, A1, P7, P8, A2, RAMP
AREA P5
AREA P1, P2, P3, P4, P5, P6, P7, P8, P9, 02, 03, H2, H3, A1, A2, A3, RAMP
AREA P5, P6, P7, P8, P9, A1, A2
AREA P1, P2, P3, P4, P5, P6, P7, P8, P9, 01, 02, 03, H1, H2, H3, A1, A2, A3
AREA P6, P7, P8, P9, A2

b.

Works included in this Final Certificate as per the attached drawings as referenced above and listed as follows
INJECTION CRACKS PODIUM FLOOR AREA PARKING

c.

Works excluded in this Final Certificate

d.

Defective Works

For the Employer

Attachments:
Scope of Works included
List of Outstanding / Defective Works
As Built Drg Hardcopy & Soft Copy

For JCM

For the Contractor

Copies To:
CAG

JCM

OTHER

CONTRACTOR

REYNOLD

FILE