Professional Documents
Culture Documents
I. INTRODUCTION
Terrestrial GSM networks now cover more than 80% of the
worlds population [1]. The telecommunications industry is an
energy intensive industry, where large quantities of electrical
energy are consumed by the base transceiver stations for the
running and cooling of electrical equipment. For example,
Grameen Phone is the largest mobile phone service provider in
Bangladesh, covering 99% of the countrys polulation and 89%
of the land area. There are 13,000 base stations in 7,200 sites
around the country, as of December 2010[2]. In comparison,
only 48% of the population have access to grid electricity [3].
Just as people living in off-grid locations have in many cases
resorted to using solar home systems to access rudimentary
electricity, the communications equipment of telecom
companies can also use renewable energy for electricity. This
has been shown to not only reduce the maintenance, operating
and fuel costs, but also to prevent power outages, which results
in disrupted services and lost customers and revenues.
At present Bangladesh has six mobile phone operators
(Grameen Phone, Robi, Banglalink, Airtel, Teletalk, CityCell)
and all together they have 1762 Off grid BTS, Most of them run
using a diesel generator set with a battery backup system. If all
these BTSs change their energy system to Solar-Diesel hybrid
Solar
9 11
year
Diesel
13
15
17
19
P
5.87
G 0.5
0.5
Es
Battery
Maximum battery energy backup will be required in the
lowest irradiation days (Lowest irradiation= 1.6 kWh/m2/day).
The battery capacity required is:
= 630Ah
Generator
Generator backup is considered for 10 Hours 1.5 10
15
The generator will run for 2.5 hours, So the capacity of the
generator should be at least 6 kW
Considering the availability and also the life time of the diesel
generator we have chosen a 8 kW ( 10kVA) generator.
Considering the aging of the generator and the declination of
the efficiency, we assume the fuel consumption per hour is
2.5 Litres. That is 3.2 kW/litre.
Rectifier
The rectifier will rectify the ac power to dc to charge the
battery as well as supply power to the BTS equipment.
Rectifier size at 48V =
166 A.
As all the BTS has existing rectifier. So, the rectifier price is
not included in the initial capital cost.
IV. FINANCIAL DESCRIPTION OF THE PROJECT
The energy supply to the BTSs in the day time will be from
PV panels and at night, partially from the energy stored in the
battery and partly from the generator. The system is
connected to a generator, so in extreme weather condition or
in emergency situations the BTS will be powered by the
generator. The size of the generator is determined by the load
supplied to the BTS and also by the charge from the battery
bank. To ensure a higher battery life, the battery is operated at
a maximum DOD of 60%. The costs and their components for
powering 1 BTS are summarized as follows (The prices are
collected from the local market/vendor/enterprises, converted
to US$):
Equipment
Units
required
Total cost
(US$)
Solar panel
1.5 / Wp
6000
9000
0.5 /Ah
9600
Battery Rack
125
250
350
350
500
1500
250
250
1300
1300
1500
1500
Generator-10 KVA
6000
6000
120
120
1000
1000
1000
1000
31870
1000
0.67/L
6.25L/day
1530
We can see how the NPV and IRR values of the project
change when we use various tariffs per KWh of electricity,
starting from US$ 0.6 to 0.66.
12
IRR (%)
10
8
6
4
2
0
0.6
0.62
0.64
0.66
Tariff Rate (US$)
Fig. 2 Project IRR according to tariff per kWh
6000
NPV in US$
4000
2000
0
-2000
-4000
0.6
0.62
0.64
0.66
(a)
(b)
(c)
(d)
Fig. 5 HOMER Analysis Outputs (a) Monthh wise Global Horizontal Radiation of Dhaka (also showing the clearness Index), (b)
Monthly average electric production (contriibution of energy from Solar PV and from diesel geneerator), (c) Cost wise cash flow
summary (net present cost) of the project coonsidering the project life 20 years,
(d) Componennt wise cash flow summary (net
present cost).
HOMER Output Data: The yearly energy output from PV is
proportional to the solar radiation data.
d
The energy
contribution from solar is 59% and that from diesel generator
is 41% (Renewable Fraction is 58.7%), The
T cost of energy
stands at USD 0.628. Cost wise, net presentt cost is highest for
the initial capital cost followed by fuel cosst (diesel) and then
by replacement cost (as batteries need to be
b replaced after 5
years and the generator needs to be replacced after 10 years.
0.8
Renewable fraction
100
80
0.7
60
40
0.6
20
0
0.5
2
Cost of Energy
7
12
PV panel size (kWp)