The building process has been refined over thousands of years. While
every projects process is slightly different, projects generally progress
along these major phases. Its important to know the right type and
level of information thats needed within each phase to add the most
value.
Project Phases
In the construction industry, the design process is described by the phases of pre-design,
conceptual design, design development, and final design. The building life cycle process is
described by the phases of construction and building operation.
LOD 100: Modeled elements are at a conceptual point of development. Information can be conveyed
with massing forms, written narratives, and 2D symbols.
LOD 200: Modeled elements have approximate relationships to quantities, size, location, and
orientation. Some information may still be conveyed with written narratives.
LOD 300: Modeled elements are explained in terms of specific systems, quantities, size, shape, location,
and orientation.
LOD 400: Continuation of LOD 300 with enough information added to facilitate fabrication, assembly,
and installation.
LOD 500: Modeled elements are representative of as installed conditions and can be utilized for ongoing
facilities management.
It is worth mentioning that a relationship between LOD and design phases can be loosely established.
However, it should be emphasized this relationship is not empirical. For instance a project as a whole may
be in design development, but in the digital model, the building envelope system may be fully detailed
with exact materials and thicknesses. More so, plumbing systems might be represented with single lines,
not modeled geometries.
Secondly, digital methods of BPA are dependent upon the amount of information that is digitally
modeled. Therefore it becomes beneficial to comprehend what LOD a model is at, and what that
means in terms of available data, so analysis methods can be associated with the digital
information that is readily available . For example, a model at LOD 100 will not allow one to
conduct energy modeling that is required for LEED certification, but energy modeling with a
LOD 100 can identify how the buildings energy consumption can be influenced by solar
radiation. For these reasons, the LOD of a model and BPA practices share a feedback loop that at
times are not as linear as the steps to developing levels of detail in the BIM model. This may be
best explained with the following graphic.
Pre-Design
Phase Objectives:
Identify the requirements of the project, existing conditions, and unearth any essential
information that will inform the design process. Common activities include preparing a building
program, conducting a site analysis, and inventorying local code requirements.
What passive sustainable design strategies should be considered in the building design?
LOD Assumptions:
If a new project, there is no digital model available. If an existing building, a digital project
model might be available at least a LOD 300.
BPA Actions:
Decide what climate data is most appropriate for the geographic location.
Conduct a site analysis that minimally includes investigation of solar radiation , wind patterns , presence
and condition of existing structures, inventorying existing vegetation, and documenting any acoustic
challenges that exist.
Analyze climate charts and determine if building is likely to be heating or cooling dominated.
Research what sustainable design strategies would be applicable to both the geographic location, and
climate zone of the project. Tools such as the 2030 Palette and Climate Consultant can help with this.
Establish measurement matrices that are to be used throughout the duration of the project to confirm
sustainable design goals are being accounted for. This can be formularized rating systems such as LEED
and Breeam.
Conceptual Design
Phase Objectives:
Decide on the direction of the design by experimenting, iterating, and obtaining integrated
design input from all parties. The principle objective during this phase is to make high-level
decisions that will provide direction to the entire design process.
LOD Assumptions:
Most of the architectural model is at LOD 100. The building form is digitally modeled in
massing geometries, and the spatial relationships of the building program are sketched out with
bubble diagrams.
BPA Actions:
Run conceptual energy analysis using and modifying massing forms and determine how the Energy Use
Intensity (EUI) can be reduced by changes in building form, and orientation. Doing so can help determine
the most energy efficient building form.
Conduct basic shade/shadow analysis of the massing model to determine what areas of the building could
potentially support daylighting, and consequently inform interior space planning. This also informs the
positioning of the building on the site.
Do solar radiation studies of the mass model to maximize opportunities for solar collection.
Study how the orientation of the massing model interacts with wind on the site. Orientation of the
building can optimize opportunities for passive cooling and ventilation.
Design Development
Phase Objectives:
Verify and edit performative attributes of proposed design, while refining material, mechanical,
and structural systems with specificity. This phase involves a lot of detailed experimentation and
rigorous decision making.
How should the floor plan be modified to improve the quality of day lighting?
LOD Assumptions:
Architecture model is at LOD 200/LOD 300 with generic cladding materials identified, and floor
plan is modeled with appropriate wall thicknesses and materials. Structural model is at least at
LOD 200 with generic framing systems.
MEP model is at LOD 200 with plumbing, heating ventilation, and cooling systems laid out, and ready to
be sized.
BPA Actions:
Run whole building energy analysis of building model, and identify how changes in wall construction can
reduce energy demands. This also presents a good opportunity to test the performance of HVAC systems
that were initially selected in Concept Design.
Complete simulations that determine the general geometry of performative features to determine if
shades, light shelves, and solar chimneys are working as predicted. If not revise model geometry to do so.
Run interior daylighting analysis of spaces, and confirm proper light levels are being achieved.
After maximizing the efficiency of the building envelope, run cooling/heating load simulation so that
HVAC equipment can be sized for efficiency.
Perform structural analysis of model so that structural systems can be optimized. When structural
members are not optimized for efficiency, the building consumes more construction materials then is
needed.
Phase Objectives:
Provide detailed direction, and specification, to construct the most comprehensive iteration of the
building. Assure that the constructed manifestation of the design will be as sustainable as
feasibly possible.
LOD Assumptions:
All models completed to LOD 300, with sizes and material selections finalized for all primary
building elements.
BPA Actions:
Perform detailed whole building energy analysis of the final design to document expected performance,
and measure against baselines. And compare final design against the measurement matrices that were
defined in Pre-Design.
Audit final building materials for costs and green qualities (recycled content, close proximity to
construction site, low VOCs).
Construction
Phase Objectives:
Bring the building design into physical reality, by practicing sustainable construction methods
and utilizing quality control methods.
LOD Assumptions:
Architecture, MEP, and Structural models are at LOD300 and are being evolved to LOD400 with
enhanced information that supports fabrication and construction coordination.
BPA Actions:
Analyze building quantities to assure that exact material quantities are delivered to the project site. Doing
so will avoid excess material that gets turned into waste.
Analyze best fabrication methods with digital automation. This step reduces waste material in the
production of building assemblies.
Run construction scheduling simulations that identify how to reduce equipment operations on the project
site. Less use of construction equipment reduces both energy consumption and air pollution.
Phase Objectives:
The building becomes occupied and has all equipment operating.
Is maintenance being done that assures environmental control systems can continue to perform at their
optimum?
LOD Assumptions:
All models are at LOD500, represent physical conditions, and are being updated in parallel with
facility management operations.
BPA Actions:
Perform initial and ongoing commissioning of environmental systems to assure they are working as
anticipated. Poorly performing environmental systems can result in compromised occupant comfort, and
unnecessary energy consumption.
Add ongoing utility cost/demand data to energy model, and compare/identify differences between
designed and actual performance.
Administer occupancy survey to verify occupant satisfaction, and make recommendations to facilities
management for improving occupant satisfaction.
- See more at: http://sustainabilityworkshop.autodesk.com/buildings/project-phases-leveldevelopment#sthash.JXjB4iRp.dpuf