You are on page 1of 30

John Jones, 19th September 2011, APC9 IChemE, York Conference

Keeping the Plant on-line during an


Automation Hot Cutover
ABB Group
September 18, 2011 | Slide 1

Requirement For Change !


Pneumati
c Control

Obsolete
Panel
Control

Obsolete
Computer
Control Systems

Poor
Reliability

Poor
Information
Flow
ABB Group
September 18, 2011 | Slide 2

Poor Control
Room
Environment

Existing Control System

High
Maintenance
Costs

Upgraded Automation System


Field bus

Maintenance
Systems

Enabling
Infrastructure

Optimisation
MIS

Integrated Control & Information System


APC
Safety
Systems
Labs
ABB Group
September 18, 2011 | Slide 3

Evolution of Control Systems Upgrade


The DCS
New Generation
The PLC
A = Panel to DCS -> lower complexity
B = DCS to DCS -> Higher complexity

The first industrial


control computer
system

The PID Controller


Watt Governor

1788

1922
Panel

1959

1968 1975 1996

2000

Pneumatic / Electronic
Early DCS

ABB Group
September 18, 2011 | Slide 4

2011

Time

Modern DCS

Why do you want to upgrade ?

ABB Group
September 18, 2011 | Slide 5

Drivers:

Obsolescence

Maintenance / Reliability issues

Productivity / Quality

Functionality

Profitability - Business demands

System capacity limits

Automation Upgrade Road Map


Requirement
for
change

Feasibility /
Migration
study

On-line
FEED

Detail Design &


Enabling work
Cut Over
Procedures

Shutdown

Cut Over

Detail Design

Decommissioning
Pre Shutdown
work

Shutdown
Installation
Test &
Commission

ABB Group
September 18, 2011 | Slide 6

Upgraded
Automation
System

Shutdown Window,

Advantages

Potential reduction in time for the control system upgrade

Perceived Easy option

Reduced risk & cost

Plant buy-in

Disadvantages

Shutdowns are for maintenance/overhaul activities

DCS will always become the critical path another reason why shutdowns
get extended!

Process Cold/black start up on a new DCS system

Control system brought on-line immediately!

No fallback

Plant modifications/projects happening impact on new DCS

ABB Group
September 18, 2011 | Slide 7

On-Line

Advantages

No requirement for an shutdown window

Reduction of risk

Limited, or no impact on the plants production

Ability for a phased implementation over a period of time in line with


Business requirements

The plant does not have to be restarted after an extended shutdown on


a new control system

Benefit from the new DCS system NOW rather than having to wait for a
shutdown

Disadvantages

Need to plan for an extended period of time compared with a shutdown

Will have 2 systems running in parallel during cutover

More effort is required to ensure the cutover is successful

ABB Group
September 18, 2011 | Slide 8

Perceived more expensive than a shutdown

Automation Upgrade Road Map: Hot Cut Over


Requirement
for
change

Feasibility /
Migration
study
Detail Design &
Enabling work
Cut Over
Procedures

FEED

Cut Over

Detail Design

Decommissioning
Pre Shutdown
work

Shutdown
Installation
Test &
Commission

ABB Group
September 18, 2011 | Slide 9

Upgraded
Automation
System

Feasibility / Migration study

Purpose :

Understand the plant (As is)

Determine where the plant wants to be (2B)

Gap Analysis of As-is Vs 2 B

How will they get there - options

ABB Group
September 18, 2011 | Slide 10

How & When ?

Migration study activities

Existing Automation system ( & Plant if necessary) is surveyed

Options are investigated

URS (User Requirements Specification) produced

Issued to Automation vendors

Tender analysis performed

Commercial

Technical

Recommendation of options

Budget estimate of project cost

Project programme produced

ABB Group
September 18, 2011 | Slide 11

FEED stage

Chosen migration path validated

Site surveyed to validate proposed solution path

Documentation gathered/quality

Cutover points - confirmed

Identification of How it will be done with regards the location of the new
DCS equipment

System rationalisation addressed - graphics, redundant areas

Safety - voltages, process

Technical issues resolved with Automation vendor

Estimate refined

Critical loops identification - criteria

Identify enabling work if required

Implementation strategy/plan on-line cutover plan

ABB Group
September 18, 2011 | Slide 12

FEED - On-Line Upgrade


Criticality Review (1st Risk Assessment)

Loop by loop assessment of importance / availability

Allocate each loop a criticality grading based upon grading scale developed
for project

Systems implementation review what can not be done on-line?

Identify enabling work if required

Enabling work

Work required to allow cutover on-line System Hardware / Process

Implementation plan for enabling work

Some design now or later (shutdown driven)?

ABB Group
September 18, 2011 | Slide 13

End of FEED review - Is everything still OK ?

ABB Group
September 18, 2011 | Slide 14

Implementation strategy still valid in-line with migration study.

Plant operations no changes

Business buy-in

On-Line Upgrade Detail Design

ABB Group
September 18, 2011 | Slide 15

Documentation gathered

Enabling I/E Design

I/E design

Cabinet design

Cutover points

Ancillary systems design e.g. UPS, lighting,


H&V

Cable routing

Control room design - including nonautomation hardware e.g. F&G, Telecoms,


CCTV

Interconnection wiring

DCS vendor liaison

Detailed plan

Pre and Hot Cutover procedures

Reviews

Reviews / Risk Assessment

ABB Group
September 18, 2011 | Slide 16

Loop Critically Review

Risk Analysis Study

Implementation Strategy Review

Cut-Over Methods Review

Hazcon Reviews

Training and Validation Requirement Review

Detail design reviews

Failure Mode Effect Analysis (FMEA) Review

Ensure that each step in the procedure was the


correct step to be made and in the correct order

Ensure that there is a fallback position available for


every step

To guarantee that if all the steps are followed in the


correct order then the result would be a successful
cutover of the loop

Highlight any design or construction/commissioning


problems that may occur

Highlight any tools or specialist equipment that may be


required during the cutover

Measurement Function & Control Complexity

Legacy code issues

Eccentricities of system

Poor documentation of
control schemes

Potential requirement to
reverse engineer system.

ABB Group
September 18, 2011 | Slide 17

On-Line Cutover procedures

What are they ?

ABB Group
September 18, 2011 | Slide 18

Pre-Cutover procedure

Hot Cutover procedure

Hot Cut Over Methodology

ABB Group
September 18, 2011 | Slide 19

Pre Cutover Procedure


Key stage, risk assessment - Go / No-Go for Hot Cutover

Does the new system mimic the old system? no surprises!!

Cutover point confirmation

Format is a detailed line by line checklist

Ensures loops are operational prior to cutover

Ensures graphics details and alarm pages are correct

Ensures Loop configuration details are correct, including


ranges, alarm settings, titles, controller actions etc.

Check existing plant equipment associated with the Cutover


operates correctly

ABB Group
September 18, 2011 | Slide 20

Example: Test manual bypass valves, Do manual hand


jacks work?, etc.

Typical Analogue Input Pre Cutover Procedure


Method statements that detail loop testing requirements prior to Hot Cutover

Prerequisites

Work control permit in place.

Ferrule & termination details


are in accordance with loop
diagrams.

Procedure

Check DCS configuration, using


data from the project database
Confirm knife edge terminals
within DCS cabinet are open.

Disconnect signal source &


open knife edge terminals in
DCS cabinet.

Confirm primary control button


on the DCS faceplate links to the
correct graphic.

Suppress DCS alarm.


New transmitter, impulse
lines & secondary isolation
valves are installed in
accordance with hook-up.

Connect relevant signal source at the


transmitter cutover point as shown on
the loop diagram & hook-up.
Completion
Remove DCS alarm suppression.

New cables are installed,


ferruled & terminated, tight &
secure

New transmitter, impulse


lines & secondary isolation
valves are installed in
accordance with hook-up

Close knife edge terminals in


DCS cabinet.
Simulate transmitter input signal to the DCS confirm
the following:
Correct representation of DCS graphic
Process alarms active on DCS, if applicable
Bad PV alarm activates on high & low signal
Correct representation on graphic

ABB Group
September 18, 2011 | Slide 21

Complete & sign relevant


section of loop control
documentation.

Hot Cutover Procedure


Written procedure to allow the safe transfer of the existing
system to the new whilst on-line

ABB Group
September 18, 2011 | Slide 22

Standard procedure

Complex / bespoke procedure

Format is a detailed line by line checklist

Hot Cutover procedures need to be reviewed using FMEA


process

Typical Analogue Input Hot Cutover Procedure


Method statements that detail loop testing requirements to complete the Hot Cutover, inclusive of any prerequisites
and post cutover testing.

Prerequisites

Procedure

Pre-cutover loop tests are complete.

Ensure DCS input point is displayed on


the DCS.

Work control permit is current and


applicable to the loop detailed.

Confirm the existing loop is stable,


record the PV.

Record the DCS PV.

Confirm the DCS and


existing PVs are similar, if
not find out why before
moving onto next procedure.

Completion
A copy of the loop diagram is
available for reference.

Identify the field instrument, with


process, isolate & blow down lines.
Confirm no leaks from isolations.

DCS loop isolations are complete, i.e.


knife edge terminals are open.

Carry out any work identified on the field


hook-up.

All relevant test certificates are in


place.

Confirm DCS input tag is reading zero.

Connect the DCS signal by closing the


appropriate knife edge terminals
DCS alarm suppression is removed

Correct PPE available

ABB Group
September 18, 2011 | Slide 23

With process & using the works


procedure, open isolation valves putting
process onto the transmitter, confirm no
leaks.

Complete & sign changeover


notification label(s) and fix to
appropriate locations.

Complete & sign relevant


section of loop control
documentation.

Develop detailed Pre & Hot Cutover packs

Work Packages for Pre cutover and Hot cutover

Good clear and simple check sheets

ABB Group
September 18, 2011 | Slide 24

Typical sections:

Purpose

Prerequisites

Procedure

Completion

For each type of generic loop develop a detailed method

Involve those who are to perform actual cut-over

Identify the equipment required - special tools, chocks etc.

Test the methods on none critical loops

Perform trial run and follow up with review

On-line Cutover stage

Cutover team

DCS / System Engineer

Process Operator / FLM

Technicians / Electrician

Project Designer

Pre Cutover activities:

Follow pre cutover procedures

loops to be cutover as soon as possible

Hot Cutover activities:

ABB Group
September 18, 2011 | Slide 25

Cut-over team, managed by Commissioning Manager


comprising:

Follow plan and Cutover procedures !!!

Hot Cutover implementation Main Plan & Daily Activities

Main Cutover Plan

Master overall status of cutover

Plan down to loop level

Details sequence for cutover


including daily cutover activities.

Daily Cutover Activities

Short meeting held prior to start in control room


of cutover team to ensure:

Plant is operating normally

Resources are all in place

Plan usually MS Excel spreadsheet


based.
Multiple columns can detail
associated information i.e. loop
diagram details

Confirm all documentation is in place

Relevant operator training completed

Control/Safety system platform is fully


operational

Multiple work fronts pre cutover &


cutover

Check feedback from overnight shifts

Impact of any other work in area

Permit to work situation

ABB Group
September 18, 2011 | Slide 26

Toolbox talks

Reservations / punch listing

Update end of day report

Decommissioning

ABB Group
September 18, 2011 | Slide 27

Leave old system operator station running for a period of


time - to be used for reference purposes

Can you pull the plug ????

On-line Upgrade - Success factors!

Ensure business understands inherent risks

Operations buy-in to deliver

The project process used

The review process undertaken

The documentation quality

The implementation strategy for cut-over

The cutover team resource

The cutover methods developed

Cutover methods followed

Enabling work

Training

ABB Group
September 18, 2011 | Slide 28

It is very important to remember...


Plants are process driven NOT
Engineering driven! & Operations is
always King!
ABB Group
September 18, 2011 | Slide 29

ABB Group
September 18, 2011 | Slide 30

You might also like