Professional Documents
Culture Documents
PURPOSE
The purpose of this memorandum is to describe the basic design criteria for the
project regarding hydrology, low flow values, flood flow values, GLOF
possibilities and expected sediment load in the water. These are basic data for
determining installation, power production and safe values for floods. It is also
important information for the overall layout of headworks and for the detailed
layout of the settling facilities.
(b)
KHIMTI KHOLA
Background
The field flow measurements for the gauging station 650 at Rasnalu,
undertaken by Department of Hydrology and Meteorology HMGN, are the
main source for hydrological information. The feasibility study for Khimti I
Hydropower project analysed hydrologic data for the Khimti Khola from 1964
to 1982. In the meantime, additional hydrologic data has become available, and
the analysis has been extended to 1994.
The previous analysis indicated that the low to medium flow range data was
reasonable accurate, but that higher flows were not reliable due to absence of
high flow current meter gaugings. This had little impact on the results in
respect to the run-of-river Khimti I Project. The results were therefore
considered acceptable for Khimti I, but were to be treated with caution when
applying them for purposes other than energy output from that project (eg. for
flood analysis etc.)
_____________________________________________________________________
______
Document written date: XXX
by
XXXXX
_ _ _ _ _ Consultant
I:\MAI_1\2_1.DOC
25.01.96
Rating equation
Q = 11.99 (H + 0.443)2.424
0.9989
Q = 25.50 (H + 0.212)2.206
0.9967
Q = 39.05 (H + 0.063)2.050
0.9975
Q = 26.95 (H + 0.230)2.143
0.9976
Q = 22.00 (H + 0.322)2.257
0.9978
Q = 19.23 (H + 0.362)2.195
0.9952
Q = 23.77 (H + 0.176)2.154
0.9980
Q = 21.00 (H + 0.232)2.219
0.9964
ratings end
R2
The flows for the full period of record, May 1964 to October 1994, were recalculated using the new ratings. There were some gaps in the data. Minor
gaps (one to two days) were filled using synthetic stage data given by DHM.
The only significant gap is from September 1987 to March 1988, when DHM
report that the record is lost. Mean flows for the recording site at Rasnalu have
been calculated, for each of: i) the comparable period to that of the feasibility
study, ii) the new period of record, and iii) overall. The comparison is given in
Table 1.4.1. Similarly, the minimums and maximums for the relative periods are
compared.
I:\MAI_1\2_1.DOC
25.01.96
Table 1.4.1
Jan.
Feb.
Mar.
Apr.
May
June
July
Aug.
Sep.
Oct.
Nov.
Dec.
Year
7.00
30.6
74.8
76.1
48.8
21.0
10.2
6.60
24.6
7.33
29.6
67.7
69.8
47.1
22.1
10.9
6.86
23.4
9.21
42.8
99.7
101
56.6
29.0
16.0
8.57
32.1
8.12
35.1
81.1
82.8
50.9
24.9
12.8
7.51
27.0
(64 - 82)
64 - 82
0.4
-2.3
-4.5
-1.1
4.7
-3.3
-9.5
-8.3
-3.5
5.2
6.9
3.9
-4.9
64 - 94
5.1
1.6
-1.3
-1.7
16.0
14.7
8.4
8.8
4.3
18.6
25.5
13.8
9.8
Feas. St.
3.49 3.37 3.11
64 - 82
updated
3.38 3.15 2.73
64 - 82
updated
3.23 3.15 1.85
64 - 94
Maximum daily mean flow
2.76
2.72
3.79
10.3
30.5
15.3
7.98
5.71
3.73
---
2.33
2.49
3.48
14.2
29.2
15.6
8.39
5.84
3.66
---
1.26
0.88
3.48
14.2
29.2
15.6
8.39
5.84
3.66
---
Feas. St.
64 - 82
updated
64 - 82
updated
64 - 94
6.53
7.44
6.57
31.8
105
186
306
276 (390)
102
19.2
11.2
---
8.08
7.81
8.39
39.9
120
178
249
236
276
125
21.5
11.6
---
13.6
7.81
8.39
39.9
161
809
523
710
308
125
103
20.1
---
Application of data
The river flow data for Rasnalu was adjusted to that at the proposed Khimti 1
intake, using ratio of the catchment below 5000 m, less a constant value to
cover losses to irrigation from the tributaries between the recording site and the
proposed Khimti 1 intake.
1.4.1
Equation
In addition, for the analysis, it was assumed that there was a residual flow
requirement downstream of the intake (as per the licence) of 0.5 m3/s, made up
of seepage under the dam (assumed to be 0.15 m3/s) which would re-surface
immediately downstream, and specific mitigation releases. Further to the
downstream residual flow, there would be losses from the tunnel through
seepage, assumed to be the same as given in the DBM section 4.3.3(0.15 m3/s).
In summary, the water available for power generation at any time is determined
as follows:
QPOWERHOUSE = QIINTAKE - residual - tunnel seepage (m3/s)
1.4.2
Equation
I:\MAI_1\2_1.DOC
25.01.96
where
residual = intake seepage + release = 0.15 + 0.35 = 0.5 m3/s
tunnel seepage = 0.15 m3/s
(c)
LOW FLOWS
The lowest flow recorded at gauge site is 0.88 m3/s. This is an extreme value
and the next lowest value is 2.33 m3/s. The mean annual one day low flow is
3.25 m3/s, and the standard deviation is 0.74. Using extreme value analysis, the
10 year return period one day flow comes to between 2.16 and 2.43 m3/s,
depending on distribution. Flow duration curves at the intake at Palati are
shown in Figure 2.1.1 and 2.1.2.
(d)
(e)
20
50
100
200
500
reason is partly meteorological, it appears that the heavy monsoon rain has lost
its power when it reaches that high elevation. Part of the explanation is also
the rain shadow in areas above that level.
The present design turbine setting is 593.3 m. The normal water level in Tama
Koshi at the outlet in winter is about 585 m and in summer about 586 to 587
m. Last summer's recording of water level close to the outlet confirmed this.
Flood water levels at the tailwater area and at the access tunnel area are
assessed by use of backwater analysis in a numerical model. The results of the
backwater analysis are:
Return period
year
2
5
10
20
50
100
500
1,000
(f)
Flood flow
m3/sec.
At access
tunnel (m)
At tailrace
tunnel (m)
603.4
604.2
604.7
605.2
605.7
606.2
607.7
588.2
589.1
589.6
590.1
590.7
591.1
592.1
592.6
1,030
1,370
1,600
1,820
2,110
2,300
2,780
3,000(est.)
I:\MAI_1\2_1.DOC
25.01.96
SEDIMENTOLOGY
Systematic suspended sediment load measurement in Khimti Khola has been
carried out for two seasons. The results from the 1994 monsoon are reported.
Samples were taken 08.00 and 17.00 every day for 3.5 months. The sampling
period was from 20 June to 8 October. The results show concentrations of
suspended load up to 8500 ppm.
A summary based on the results from the sampling period gives the following
concentration figures for the 1994 monsoon (in ppm):
June
October
(from 21)
8)
Maximum
28
Minimum
5
Average
13
July
August
September
(to
632
8,536
5,633
1,486
18
13
26
12
91
339
370
141
Higher values will occur during high floods and after landslides in the near
catchment. A suspended load concentration of 20,000 ppm with a duration of 2
hours will be used as design value for the settling basin flushing capacity.
A few samples of fine sediments in the river bed have been analysed in a
laboratory and from 38 to 85 % of the particles in the samples are quartz. For
the suspended load samples from a few days in July/August 94, 30-40% of the
particles in the samples are quartz.
(i)
REFERENCES
Surface water records of Nepal. 1971 to 1976. Department of Hydrology and
Meteorology.
Detailed gauging station and rainfall station data records.
Hydrology and Meteorology.
Department of
I:\MAI_1\2_1.DOC
25.01.96
Design manuals for irrigation projects in Nepal, M.3 Hydrology and agrometeorology manual. Sir M. MacDonald and Partners for MoWR, Department
of Irrigation, UNDP/World Bank, February 1990
Methodologies for estimating hydrologic characteristics of un-gauged locations
in Nepal. (2 volumes). MoWR, WECS and Department of Hydrology and
Meteorology, July 1990
Khimti Khola Hydroelectric Project, Feasibility Study. BPC/Norpower, April
1993
4. River characteristics (Volume 1)
Hydrology (Volume 2)
Hydrological data (Volume 3)
Khimti Hydropower Project. Flood gauging at the Khimti Khola gauging
station. Draft report September 1994.
Hazard assessment at Tsho Rolpa, Rolwaling Himal, northern Nepal. Reynolds
Geoscience Ltd., December 1994
Khimti I Hydropower Project, Hydrology and Energy. BPC Hydroconsult
internal report, July 1995
Tsho Rolpa. Proposed GLOF Early Warning System. BPC Hydroconsult
internal report, June 1995
Khimti I Hydropower Project, Investigations on Sedimentology in Khimti
Khola during monsoon 1994 are reported. Norwegian Hydraulic Laboratory,
August 1995
I:\MAI_1\2_1.DOC
25.01.96