You are on page 1of 29

STANDARD CHECK LISTS

MECHANICAL

VOLUME V
Section A : I.C. Engines
Section B : Driers
Section C : Soot blowers
Section D : Electrostatic Precipitator
Section E : Ash handling Plant
Section F : Miscellaneous

BHARAT HEAVY ELECTRICALS LIMITED


(A Government of India Undertaking)
Power Sector Southern Region
474, Anna Salai, Nandanam, Chennai 600 035.

STANDARD CHECK LISTS


MECHANICAL
VOLUME V
CONTENTS
NO.

TITLE
COMMISSIONING/TESTING ESSENTIAL PREREQUISITES
SECTION A

1)

Driers without Regeneration


SECTION-B

1)

Long Retractable Soot blowers

2)

Wall Deslaggers
SECTION-C

1)

Emitting Electrode Rapping Mechanism

2)

Collecting Electrode Rapping Mechanism


SECTION-D

1)

Clinker Grinder

2)

Scraper Conveyer
SECTION-E

1)

Lubricator-Compressed air line

2)

Windbox Assembly

SCL.REF.NO

LIST OF MANUALS
STANDARD CHECK LISTS
MECHACAL
VOLUME I

VOLUME II

VOLUME III

VOLUME IV

VOLUME V

Section A

Valves

Section B

Pipe Work System

Section A

Tanks & Pr. Vessel

Section B

Pumps

Section C

Filter & Strainer

Section D

Hoat Exchanger

Section A

Fans & Compressors

Section B

Dampers

Section C

Duct Work

Section D

Cranes and Lift

Section E

Power Transmission

Section A

Fuel handling equipment

Section B

C.M. Plant

Section A

I.C. Engines

Section B

Driers

Section C

Soot blowers

Section D

Electrostatic precipitator

Section E

Ash handling Plant

Section F

Miscellaneous

MECHANICAL
STATION

PLANT ITEM :

STANDARD CHECK LIST

SHEET 1 OF 1

COMMISSIONING/TESTING ESSENTIAL PREREQUTSITES

PLANT NOMENCLATURE: _________________________________________________


UNIT____________________________ SYSTEM _________________________________
MANUFACTURER ___________________ SRL. NO. __________________________
LOCATION: _______________________________________________________________
NO.

ACTIVITY

1.

Access to the plant item is adequate

2.

Illumination in the plant area is adequate.

3.

Any other requisite safety provision is adequate for the


immediate commissioning activity.

4.

Plant item is in a clear condition.

5.

All necessary locks and keys for padlocks, interlocks etc.


are available.

6.

Hot surfaces lagged or screened or screened sufficiently


to provide protection for personnel.

WITNESSED
NTPC

BHEL

DATE

REMARKS :
SCL REF: MS 1/1

MECHANICAL
STATION

: STANDARD CHECK LIST

PLANT ITEM :

SHEET 2 OF 2

DRIERS WITHOUT REGENERATION

NO.

ACTIVITY

7.

Safety valves in position?

8.

Sight glass in position?

9.

Sight glass flanges and joints are tight.

10.

Check for the proper tightness of the flange bolts and


joints at the inlot and outlot pipe segments.

11.

Supports of proper strength have been provided.

12.

Provision for refilling of adsorbant in drier ssatisfactory.

13.

Precalibrated pressure gauges installed at inlot and out


lot?

WITNESSED
NTPC

BHEL

REMARKS :
SCL REF: M 15/1

DATE

MECHANICAL
STATION

: STANDARD CHECK LIST

PLANT ITEM :

SHEET 1 OF 1

DRIERS WITHOUT REGENERATION

PLANT NOMENCLATURE: _________________________________________________


UNIT____________________________ SYSTEM _________________________________
MANUFACTURER ___________________ SRL. NO. __________________________
LOCATION: _______________________________________________________________
NO.

ACTIVITY

1.

General conditions satisfy the site standing instructions as


listed in the Plant Item Commissioning Essential Prerequisites (SCL MS 1/ 1).

2.

The name plate legend agrees with the approved NTPC


Plant nomenclature is clearly visible, securely fixed
durable and correlates with remote labels.

3.

The installation is complete and correct in accordance with


approved drawings and specifications.

4.

Access to the plant satisfactory.

5.

Permanent lighting available.

6.

Adequate clearance towall / stool work around drier?

WITNESSED
NTPC

BHEL

DATE

REMARKS :
SCL REF: M 15/1

MECHANICAL
STATION

: STANDARD CHECK LIST

PLANT ITEM :

SHEET 1 OF 1

LONG RETRACTABLE SOOT BLOWERS

PLANT NOMENCLATURE: _________________________________________________


UNIT____________________________ SYSTEM _________________________________
MANUFACTURER ___________________ SRL. NO. __________________________
LOCATION: _______________________________________________________________
NO.

ACTIVITY

1.

General conditions satisfy the site stranding Instructions


listed in the Plant Item Commissioning Essential Prerequisites (SCL MS 1/1).

2.

The nameplate legend agrees with the approved NTPC


Plant Nomenclature and is clearly visible, securely fixed,
durable and correlates with remote labels.

3.

The installation is complete and correct in accordance with


the latest drawings.

4.

Access for adjustments, maintenance and repairs is


satisfactory.

5.

Check the blower number with reference to the location


drawing to ensure the installation of correct blower in
correct location.

WITNESSED
NTPC

BHEL

DATE

REMARKS :
SCL REF: M 16/1

MECHANICAL
STATION

: STANDARD CHECK LIST

SHEET 2 OF 2

PLANT ITEM :

NO.

ACTIVITY

6.

The rotary and traverse powerpacks are flushed and then


filled and then filled with the recommended lubricant.

7.

Check that the lubrication of travelling parts is carried out


(servegem HTXX)

8.

Check that there is no rusting on chains and sprocket and


the lubrication is carried out.

9.

Check for the accessibility of the hand crank for manual


operation.

10.

Check for proper tensioning of chains.

11.

Check whether stop pin is present on the cam bracket.

12.

Check the position of valve opening cam.

13.

Check the terminal box is properly covered to prevent any


ingress of water.

14.

Check the proper slope consideration is given, as per


drawing, for horizontal and vertical expansion of the boiler
when the unit is working (valves to be supplied by the
erection staff).

15.

Check the refractory filling in the seal box is done.

WITNESSED
NTPC

BHEL

REMARKS :
SCL REF: M 16/1

DATE

MECHANICAL
STATION

: STANDARD CHECK LIST

SHEET 2 OF 2

PLANT ITEM : WALL DE SLAGGERS

NO.

ACTIVITY

6.

Check the perpendicularity of wall sleeve and swivel type


(90 deg + 30 ) (Certificate from erection personnel to be
obtained)

7.

Check the accessibility for hand crank and the switch box
assembly.

8.

Check that the soot blower piping adjacent to the blower is


supported on boiler steel and is not likely to foul with
structural steel when the boiler expansion will take place.

9.

The rotary and traverse gear boxes are thoroughly flushed


and filled with the recommended lubricant.

10.

Check that the lubrication of the linkages is properly


carried out.

11.

Check that the stop nuts are in place on the guide rods.

12.

Check that the drain holes in the motor frames point


downwards and are open.

13.

The SBV head valve is serviced for proper opening and


closing.

WITNESSED
NTPC

BHEL

DATE

REMARKS :
SCL REF: M 16/2

MECHANICAL
STATION

: STANDARD CHECK LIST

SHEET 3 OF 3

PLANT ITEM : WALL DE-SLAGGERS

NO.

ACTIVITY

14.

Check that the blower, before starting or at the end of its


operation is in the correct parking position.

15.

Check that a minimum clearance of 1mm is maintained


between the drive serew and SBV head valve stem. (to
ensure tight valve seating).

16.

Check the refractory filling in the seal box is done.

WITNESSED
NTPC

BHEL

DATE

REMARKS :
SCL REF: M 16/2

MECHANICAL
STATION

: STANDARD CHECK LIST

PLANT ITEM :

SHEET 1 OF 2

ELECTROSTATIC PRECIPITATOR (MECHANICAL)


EMITTING ELECTRODE RAPPING MECHANISM

PLANT NOMENCLATURE: _________________________________________________


UNIT____________________________ SYSTEM _________________________________
MANUFACTURER ___________________ SRL. NO. __________________________
LOCATION: _______________________________________________________________
NO.

ACTIVITY

1.

General conditions satisfy the site Standing Instructions as


listed in the Plant Item Commissioning Testing Essential
Pre-requisites (SCL/msi/1).

2.

The name plate legend agrees with the approved NTPC


Plant Nomenclature, is clearly visible, securely fixed, is
durable and correlated with any remote labels.

3.

Installation is correct and complete as per the latest


approved drawings.

4.

Ensure that there is no foreign material inside the ESP and


check the cleanliness of hoppers and walls.

5.

Check the disposition of inner arms on rapping shaft set at


proper phase angle.

WITNESSED
NTPC

BHEL

DATE

REMARKS :
SCL REF: M 17/1

MECHANICAL

STATION

: STANDARD CHECK LIST

SHEET 2 OF 2

PLANT ITEM : ELECTROSTATIC PRECIPITATOR (MECHANICAL)


EMITTING ELECTRODE RAPPING MECHANISM

NO.

ACTIVITY

6.

Check the distance between centre line of rapping shaft to


the centre line of shock beam.

7.

Check the direction of serow provided for emitting rapping


drive.

8.

Check the working clearance of 5mm at the back of the


serow.

9.

Check the radial and axial alignment of clutch and


coupling.

WITNESSED
NTPC

BHEL

DATE

REMARKS :
SCL REF: MS 17/1

MECHANICAL
STATION

: STANDARD CHECK LIST

SHEET 1 OF 2

PLANT ITEM : ELECTROSTATIC PRECIPITATOR (MECHANICAL)


COLLECTING ELECTRODE RAPPING MECHANISH
PLANT NOMENCLATURE: _________________________________________________
UNIT____________________________ SYSTEM _________________________________
MANUFACTURER ___________________ SRL. NO. __________________________
LOCATION: _______________________________________________________________
NO.

ACTIVITY

1.

General conditions satisfy the site Standing Instructions as


listed in the Plant Item Commissioning Testing Essential
Pre-requisites (SCL MS 1/1)

2.

The name plate legend agroes with the approved NTPC


Plant Nomenclature, is clearly visible, securely fixed, is
durable and correlates with any remote labels.

3.

Installation is correct and complete as per the latest


approved drawings.

4.

Ensure that there is no foreign material inside the ESP and


check the cleanliness of hoppers and walls.

5.

Check the disposition and tightness of inner arms on


rapping shaft set at proper phase angle.

WITNESSED
NTPC

BHEL

DATE

REMARKS :
SCL REF: M 17/2

MECHANICAL
STATION

: STANDARD CHECK LIST

SHEET 2 OF 2

PLANT ITEM :

NO.

ACTIVITY

6.

Check the support bracket provided in the middle of two


hammers.

7.

Check the distance between centre line of rapping shaft to


centre line of shock bar.

8.

Ensure that the shock pad face and shaft axis are in the
same vertical plane.

9.

Check the lateral shift to hammers with reference to shock


pad centre.

10.

Check the proper sealing of the rapping shaft in the


bearing.

11.

Check the set rings position and their welding.

12.

Check the clearance between collecting electrode and gas


screen.

13.

Check the radial & axial alignment of clutch & coupling.

WITNESSED
NTPC

BHEL

REMARKS :
SCL REF: M 17/2

MECHANICAL

DATE

STATION

: STANDARD CHECK LIST

PLANT ITEM :

SHEET 1 OF 3

CLINKER GRINDER

PLANT NOMENCLATURE: _________________________________________________


UNIT____________________________ SYSTEM _________________________________
MANUFACTURER ___________________ SRL. NO. __________________________
LOCATION: _______________________________________________________________
NO.

ACTIVITY

1.

General conditions satisfy the site standing Instructions as


listed in the Plant Item Commissioning Essential PreRequisties (SCL MS1/1).

2.

The name plate legend agrees with the approved NTPC


Plant Nomenclature is cloarly visible, securely fixed,
durable and correlates with remote labels.

3.

Installation is complete and correct in accordance with


approved drawings and specification.

4.

Adequate access for adjustment, maintenance and repairs


is provided.

WITNESSED
NTPC

BHEL

DATE

REMARKS :
SCL REF: M 18/1

MECHANICAL
STATION

: STANDARD CHECK LIST

PLANT ITEM :

NO.

SHEET 2 OF 3

CLINKER GRINDER

ACTIVITY

6.

Verify that sliding wheel is provided.

7.

Check that fluid coupling is provided.

8.

Verify that Reduction Gearbox is provided.

9.

Check that sprocket and chains are installed correctly.

10.

Verify that sealing water connections to roller bearings are


made.

11.

Check that pressure gauges and pressure switches are


mounted properly on the sealing water line.

12.

Check the fluid coupling as per SCL

13.

Check reduction gearbox as per SCL

14.

Check that clinker grinder roller bearings, sprocket and


chain lubrication is complete.

15.

Check that motor trial run has been taken satisfactorily.

16.

Verify that start permissive and protection of clinker grinder


checked is satisfactory.

WITNESSED
NTPC

BHEL

REMARKS :
SCL REF: M 15/1

DATE

MECHANICAL
STATION

: STANDARD CHECK LIST

SHEET 3 OF 3

PLANT ITEM : CLINKER GRINDER

NO.

ACTIVITY

17.

Verify that S.C.C. is taken. Record the ref. no. and


effective date.

18.

Simulate the operation of emergency push button.

19.

Short the clinker grinder trial run, continue run for 4 Hrs
and observe:-

WITNESSED
NTPC

BHEL

19.1 Motor Bearing Vibration.


19.2 No over heating of clinker grinder roller bearings.
19.3 Interlock with seal water pressure and clinker grinder
working satisfactorily.
19.4 Reverse rotation of clinker grinder.
20.

Check smooth operation of inlot chute flap gate.

REMARKS :
SCL REF: M 18/1

DATE

MECHANICAL
STATION

: STANDARD CHECK LIST

PLANT ITEM :

SHEET 1 OF 3

SCRAPER CONVEYOR

PLANT NOMENCLATURE: _________________________________________________


UNIT____________________________ SYSTEM _________________________________
MANUFACTURER ___________________ SRL. NO. __________________________
LOCATION: _______________________________________________________________
NO.

ACTIVITY

1.

General conditions satisfy the Site Standing Instruction as


listed in the PLANT ITEM COMMISSIONING ESSENTAL
PRE REQUISITES (SCL MSI/1).

2.

The name plate legend agrees with the approved NTPC


Plant nomenclature is clearly visible, securely fixed,
durable and correlates with remote labels.

3.

Installation is complete and correct in accordance with


approved drawings and specification.

4.

Adequate access for adjustment, maintenance and repairs


is provided.

5.

Verify that all construction Dobris is removed from the


scraper conveyer through.

WITNESSED
NTPC

BHEL

DATE

REMARKS :
SCL REF: M 18/2

MECHANICAL
STATION

: STANDARD CHECK LIST

PLANT ITEM :

SHEET 2 OF 3

SCRAPER CONVEYOR

NO.

ACTIVITY

6.

Check that LP water connection to scraper conveyer


trough is made correctly.

7.

Check that HP water connection to scraper bar cleaning is


made and nozzle is installed correctly.

8.

Check the reduction gearbox as per SCL

9.

Verify that drive chin sprocket bearings are greased and


chains have been lubricated properly.

10.

Check that scraper conveyer pulleys are rotating smoothly


and freely.

11.

Check that conveyer bars coated with lubricant.

12.

Check that motor trial run has been taken satisfactorily.

13.

Verify that protection and interlocks of scraper conveyor


checked out satisfactorily.

14.

Verify that S.C.C. is taken. Record the ref.no. and effective


date.

WITNESSED
NTPC

BHEL

REMARKS :
SCL REF: M 18/2

DATE

MECHANICAL
STATION

: STANDARD CHECK LIST

SHEET 3 OF 3

PLANT ITEM : SCRAPER CONVEYOR

NO.

ACTIVITY

15.

Verify that the operation of emergency push button has


been checked.

16.

Start the scraper conveyor trial run and continue the trial
run for 6 hrs. and observe.

WITNESSED
NTPC

BHEL

16.1 Smooth functioning of scraper conveyer.


16.2 Smooth functioning of tension adjusting device.
16.3 Smooth functioning of nozzles for cleaning of scraper
bars.

REMARKS :
SCL REF: M 18/2

DATE

MECHANICAL
STATION

: STANDARD CHECK LIST

SHEET 1 OF 2

PLANT ITEM : LUBRICATOR COMPRESSED AIR LINE


PLANT NOMENCLATURE: _________________________________________________
UNIT____________________________ SYSTEM _________________________________
MANUFACTURER ___________________ SRL. NO. __________________________
LOCATION: _______________________________________________________________
WITNESSED

NO.

ACTIVITY

1.

General conditions satisfy the site standing instruction as


listed in the Plant Item Commissioning Essential Pre
requisites (SCL MSI/1).

2.

The name plate legend agrees with the approved NTPC


Plant nomenclature and is clearly visible, securely fixed,
durable and correlates with remote labels.

3.

The installation is complete and correct in accordance with


the latest drawings and specification.

4.

Check that quick opening cap arrangement for oil filling is


provided.

5.

Check that air line connected at inlet and outlet


lubrication are tested and blown.

NTPC

BHEL

DATE

of

REMARKS :
SCL REF: M 20/1

MECHANICAL
STATION

: STANDARD CHECK LIST

PLANT ITEM :

SHEET 2 OF 2

LUBRICATOR COMPRESSED AIR LINE

NO.

ACTIVITY

6.

Confirm the integrity of the joints at inlet and outlet of


lubricator.

7.

Check the oil level in the lubricator.

8.

Adjust the drip rate to 1 drop/minute by adjustor


mechanism.

9.

Check that the drip rate is clearly visible through


transparent polycarbonate bowl and sight tube.

WITNESSED
NTPC

BHEL

REMARKS :
SCL REF: M 20/1

DATE

MECHANICAL
STATION

: STANDARD CHECK LIST

SHEET 1 OF 3

PLANT ITEM : WINDBOX ASSEMBLY


PLANT NOMENCLATURE: _________________________________________________
UNIT____________________________ SYSTEM _________________________________
MANUFACTURER ___________________ SRL. NO. __________________________
LOCATION: _______________________________________________________________
NO.

ACTIVITY

1.

General conditions satisfy the site standing Instructions as


listed in the Plant Item Commissioning Essential Prerequisites (SCL MS 1/1).

2.

The installation is complete and correct in accordance with


the latest drawings.

3.

Access for adjustments, maintenance and repairs is


satisfactory.

4.

The correct wind box assembly is installed in correct


furnace corner.

5.

Burner tilt position indicator with pointer is provided in each


corner.

6.

There is no obstruction to the movement of wind box


dampers when opening and closing and the dampers are
free in operation.

WITNESSED
NTPC

BHEL

DATE

REMARKS :
SCL REF: M 20/1

MECHANICAL
STATION

: STANDARD CHECK LIST

SHEET 2 OF 3

PLANT ITEM : WINDBOX ASSEMBLY

NO.

ACTIVITY

7.

The wind box dampers remain 5 deg open in closed


condition.

8.

Ensure that the tilting mechanism is properly erected.

9.

Inspect tilt linkages to ensure components are in good


condition and there is no interforance with other
components, building steel, platforms etc.

10.

Stipulated clearance from wind box assembly to structural


steel is provided to take care of thermal expansion of the
boiler.

11.

Check Burner nozzle tips have stipulated clearance from


waterwalls.

12.

Check burner tilt mechanism for smooth operation.

13.

Set the burner tilt at zero degrees as indicated in the


position indicator and check all the nozzles are herizental.

14.

Set the burner tilt at + 30 deg as indicated on position


indicator. Measure actual angle of nozzle tilt at all
elevations and check that they are within (30 + 1 ) deg

WITNESSED
NTPC

BHEL

REMARKS :
SCL REF: M 20/2

DATE

MECHANICAL
STATION

: STANDARD CHECK LIST

SHEET 2 OF 2

PLANT ITEM : WINDBOX ASSEMBLY

NO.

ACTIVITY

15.

Set the burner tilt at-30 deg as indicated on position


indicator. Measure actual angle of nozzle tilt at elevations
and check that they are within (-30+ 1 ) deg.

16.

Obtain the Certificate from erection personnel stating that


the assemblies are installed to give a correct firing angle
and stating the actual firing angle.

17.

Check all the dampers as per dampers standard check list.

WITNESSED
NTPC

BHEL

REMARKS :
SCL REF: M 20/2

DATE

LOG SHEET FOR CLINKER GRINDER

DATE :
APPENDIX NO:

SIMHADRI 2 X 500 MW

TIME
Hrs.

CHRRENT
Amps.

VOLTAGE
Volts.

MOTOR BODY
TEMPERATURE
C deg

MOTOR BEARING
TEMP.
NDE
C deg

DE
C deg

CLINKER GRINDER NO: A/B


UNIT NO :

GEARBOX HOUSING
VIBRATION
H

V
Mm

REMARKS

A
Sec

STARTING TIME:
STARTING CURRENT :

SIGNATURE :
OPERATOR :
COMMISSIONING IN CHARGE (NTPC) :
COMMISSIONING IN CHARGE ( CONTRACTOR) :

LOG SHEET FOR CLINKER GRINDER

DATE :
APPENDIX NO:

SIMHADRI 2 X 500 MW

TIME
Hrs.

CHRRENT
Amps.

VOLTAGE
Volts.

MOTOR BODY
TEMPERATURE
C deg

CLINKER GRINDER NO: A/B


UNIT NO :

MOTOR BEARING
TEMP.
NDE
C deg

DE
C deg

GEARBOX HOUSING
VIBRATION
H

V
Mm

REMARKS

A
Sec

STARTING TIME:
STARTING CURRENT :

SIGNATURE :
OPERATOR :
COMMISSIONING IN CHARGE (NTPC) :
COMMISSIONING IN CHARGE ( CONTRACTOR) :

You might also like