You are on page 1of 26

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

Page
Page 2 of 16

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.


WELDING PROCEDURE SPECIFICATION (WPS)
0
07 Nov
2013

Rev. date

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

Page
Page 3 of 16

CONTENTS
ITEM

DESCRIPTION

PAG
E

QUALIFICATION OF WELDING PROCEDURE

SPECIFICATION (WPS).
1.1

General

1.2

Proposed Welding Procedure Specification (PWPS)

1.3

Grouping of

Materials
1.4

..
Welding Procedure Qualification Record (PQR)

1.5

.
Testing of Qualification

Welds
1.6

Qualification of Repair Welding

1.7

Procedures.
Re-

Tests
1.8

..
Procedure Qualification Records (PQR's) and final approval of

WPS's..

PROCEDURE TO ESTABLISH WPS FOR PROJECT PIPELINE

WELD JOINTS..
2.1

WPS Grade X-56, Diameter 36 and WT 7.93mm, WT 9.53, 12.7mm,

2.2

15.88mm Pipes weld joint.


WPS Grade X-65, Diameter 36 and WT 7.93mm, WT 9.53, 12.7mm,

2.3

15.88mm Pipes weld joint.


Types of tests & certificates for

2.4

PQR..
Certificates for Filler Metals & Base

Materials
WPS for API 5L, 36, Grade X56, Pipe Joint Weld with Internal

Clamp.
WPS for API 5L, 36, Grade X56, Pipe Joint Weld with External

Clamp
WPS for API 5L, 36, Grade X56, Pipe Joint Weld Full Penetration

Appendix1
Appendix2
Appendix3

Repair

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

Appendix4
Appendix5
Appendix6
Appendix7
Appendix8
Appendix9
Appendix10
Appendix11

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

Page
Page 4 of 16

WPS for API 5L, 36, Grade X56, Pipe Joint Weld Partial

10

Repair
WPS for API 5L, 36, Grade X56, Pipe Tie-in

11

Weld
WPS for API 5L, 36, Grade X65, Pipe Joint Weld with Internal

12

Clamp
WPS for API 5L, 36, Grade X65, Pipe Joint Weld with External

13

Clamp
WPS for API 5L, 36, Grade X65, Pipe Joint Weld Full Penetration

14

Repair
WPS for API 5L, 36, Grade X65, Pipe Joint Weld Partial

15

Repair
WPS for API 5L, 36, Grade X65, Pipe Tie-in

16

Weld..
Coupon Test Report.

16a

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

1.
i.

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

Page
Page 5 of 16

QUALIFICATION OF WELDING PROCEDURE SPECIFICATION


(WPS)
General
Accredited and experienced test laboratory has to be nominated to perform all
necessary destructive testing (DT) and non-destructive testing (NDT) as per
requirements of specification of Standard API 1104, Sept 2013 Welding pipeline
and related facilities or ASME Sec.IX Qualification for welding and brazing. Further,
WPS shall be and follow according to the contract specifications.

ii.

Proposed Welding Procedure Specification (PWPS)


Proposed (PWPS) submit for review and approval prior to the beginning of welding
procedure qualification. The proposed (WPS) shall be in accordance with the
requirements of the applicable standard API 1104, Sept 2013 or ASME section- IX.

iii.

Grouping of Materials
The applicable welding standards API 1104, Sept 2013 and ASME Section IX allow a
wide range of materials to be grouped for the qualification of welding procedures.
This can be considered sufficient for most applications in pipeline construction.

iv.

Welding Procedure Qualification Record (PQR)


The qualification test welds will be performed simulating production like clamping,
lifting and lowering. All welding parameters and conditions influencing the
essential variables will be recorded using calibrated equipment. All welding for
procedure qualification and for production will do by using calibrated welding
machines.
The quality of the qualification welds will be determined by non-destructive testing
(NDT) and destructive testing (DT) as per applicable standards.

v.

Testing of Qualification Welds


Preparation of test samples and testing will be performed at an approved test
laboratory. All qualifications welds will be subjected to (NDT) after completion of
welding, if post - weld heat treatment is necessary (NDT) will be performed after
treatment. Non-destructive testing consists of the following.
Visual Exam
Radiographic/ Ultrasonic Test.
As applicable to the design and specification requirement by using approved
equipment and procedures that will be employed for production.
The (NDT) acceptance criteria are defined in the applicable standards and any
welds failing to meet the acceptance criteria not be subjected to destructive
testing. For destructive testing as a minimum all qualification welds subjected to
hardness test. Supplemented by further tests and required in applicable standards.

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

Page
Page 6 of 16

vi. Qualification of Repair Welding Procedures: All repairs welding shall be


performed in accordance with an approved repair welding WPS and shall be
executed by qualified welders. The repair welding WPS is separate from the
original welding procedure with the addition of the following:
Method of defect removal
NDT requirements to determine complete removal of detect
To qualify a repair welding procedure, a production weld shall be produced in
accordance with the approved WPS and shall be non-destructive tested after
completion. If acceptable, a section within the allowable limits has to be removed
and re-welded in accordance with the proposed repair procedure. Finally this repair
weld has to pass all required test described in the relevant sections of the
applicable standards and this specification.

vii.

Re-Tests
General
If the mechanical test fails for whatever reason, it should investigate the cause of
the failure, and re-test or re-evaluation of PQR parameters.
If after re-testing the qualification weld finally fails to meet the minimum
requirements, a new WPS proposal shall be established and qualification welding
and testing repeated.
Tensile and Bend Tests
If one tensile test or bend specimens does not meet the acceptance criteria, two
additional specimens shall be tested and both have to meet the acceptance
criteria.
Hardness Tests
If only one hardness result exceeds the specified maximum then three further
impressions shall be made in close proximity to that which failed such that they do
not mutually interfere. If all of the further tests are below the specified maximum
then the test shall be accepted.

viii.

Procedure Qualification Records (PQR's) and final approval of WPS's


During procedure qualification all the parameters used shall be recorded. After
complication of the welding procedure qualification a procedure qualification
record shall be complied, containing the following information:
Revised WPS based on "as-run" parameters
Printout or datasheet of the "as-run" parameters and welding details
Summary of the welding parameters
Certificates of base materials
Certificates of filler metals and other welding consumables
Calibration certificates of equipment
Pre-heated treatment records
PWHT (Post Weld Heat Treatment) records
Visual inspection report of NDT

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

Page
Page 7 of 16

Radiographic and Ultrasonic Reports.


Result of destructive testing
Coupon Test Reports
Certificate of Welders
Certificate of NDT Inspectors

The final WPS, accompanied by the PQR, shall be submitted for review and
approval. Based on satisfactory results the WPS will be stamped and signed as
"APPROVED FOR CONSTRUCTION".

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

2.

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

Page
Page 8 of 16

PROCEDURE TO ESTABLISH WPS FOR PROJECT PIPELINE


WELD JOINTS
1. WPS Grade X-56, Diameter 36 and WT 7.93mm, WT 9.53, 12.7mm,
15.88mm Pipes weld
joints
Prepare WPS for following weld joints for API 5 L, X-56 grade and wall thickness
from 4.8mm to 19.1 mm; Pipe outside diameter > 12.750 inch as per API 1104,
Sept 2013

2.1.1

For: Transmission & distribution line. Standard: API 1104, Welding


process: SMAW + FCAW; Type of clamp: External, Direction of welding: Uphill/
Downhill, Position:5 G fixed, min 2 welders
2.1.2
For: Transmission & distribution line. Standard: API 1104, Welding
process: SMAW + FCAW; Type of clamp: Internal Clamp. Position: 5G Fixed.
Direction of welding: Downhill
2.1.3
For: Full Penetration Repair, Standard: API 1104, Welding process:
SMAW; Direction of welding: Uphill/ Downhill, Position: 5G Fixed
2.1.4
For Partial Repair, Welding process: SMAW, Direction of welding:
Downhill.
2.1.5
For: Tie-In Weld. Welding Process: SMAW, External clamp. Uphill/
Downhill. No. of Welders: min 2 welders.
Note: WPS & PQR for weldolet & Fillet-welding for branch-connection with main
pipeline based on ASME Boiler & Pressure Vessel Code- IX will be submitted later
for base material API 5L, X-56 grade.
2. WPS Grade X-65, Diameter 36 and WT 7.93mm, WT 9.53, 12.7mm,
15.88mm Pipes weld
joint
Prepare WPS for following weld joints for API 5 L, X-65 grade and wall thickness
from 4.8mm to 19.1 mm; Pipe outside diameter > 12.750 in as per API Standard
1104 21st Edition, Sept 2013.

2.2.1

For: Transmission & distribution line. Standard: API 1104, Welding


process: SMAW + FCAW; Type
of clamp: External, Direction of welding:
Uphill/ Downhill, Position:5 G fixed, min 2 welders
2.2.2
For: Transmission & distribution line. Standard: API 1104, Welding
process: SMAW + FCAW; Type
of clamp: Internal Clamp. Position: 5G Fixed.
Direction of welding: Downhill
2.2.3
For: Full Penetration Repair, Standard: API 1104, Welding process:
SMAW; Direction of welding: Uphill/ Downhill, Position: 5G Fixed
2.2.4
For Partial Repair, Welding process: SMAW, Direction of welding:
Downhill.
2.2.5
For: Tie-In Weld. Welding Process: SMAW, External clamp. Uphill/
Downhill. No. of
Welders: min 2 welders.
Note: Base Material (API 1104 Sept.2013; 5.4.2.2) group b: Specified Minimum
Yield Strength greater than 42,000 psi but less than 65,000 psi. Group c: For

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

Page
Page 9 of 16

material with a SMYS great or equal to 65,000 psi, each grade shall receive a
separate qualification test.
Note: WPS & PQR for weldolet & Fillet-welding for branch-connection with main
pipeline based on ASME Boiler & Pressure Vessel Code- IX will be submitted later
for base material API 5L, X-65 grade.
3. Types of tests & certificates for PQR
Following Types of tests & certificates are required for establishing Procedure
Qualification Record (PQR) as per API Standard 1104 21st Edition, Sept 2013
from approved laboratory.
2.3.1 Destructive Test of weld joint of API 5L PSL2, X-56 grade and wall thickness
of pipe less than or equal to 12.7 mm for pipe outside diameter > 12.75
inches.
Tensile strength . 4 no.
Nick-Break.. 4 no.
Root Bend 4 no.
Face Bend... 4 no. Total 16 no. (Table 2)
Radiographic Test (RT) and 16 destructive tests are require for following
weld joints of pipe
sample of same material grade API 5L, PSL2, X-56 of
Transmission & Distribution pipeline.
Weld joint of pipeline produced from Internal or External clamp pipe
aligning device. (16 tests) Table 2. For Table 2 & Table 5 refer API
standard 1104, 21st Edition, Sept 2013.
Weld joint of Tie-in.(16 tests). Refer Table 2.
Root Repair of weld joint/ full penetration repair. (5 tests). Refer Table 5.
Partial Repair of weld joint.(4 tests) Refer Table 5.
2.3.2 Destructive Test of weld joint of API 5L PSL2, X-56 grade and wall thickness
of pipe > 12.7 mm for pipe outside diameter > 12.75 inches.
Tensile strength 4 no.
Nick-Break.. 4 no.
Side Bend. 8 no. Total 16 no. (Refer Table 2)
Radiographic Test (RT) and 16 destructive tests are require for following
weld joints of pipe
sample of same material grade API 5L, PSL2, X-56 of
Transmission & Distribution pipeline.
Weld joint of pipeline produced from Internal or External clamp pipe
aligning device. (16 tests). Refer Table 2.
Weld joint of Tie-in.(16 tests). Refer Table 2
Root Repair of weld joint/ full penetration repair. (5 tests) Refer Table 5.
Partial Repair of weld joint.(4 tests)Refer Table 5.
2.3.3

Destructive Test of weld joint of API 5L PSL2, X-65 grade and wall
thickness of pipe > 12.7 mm for pipe outside diameter > 12.75 inches.
Tensile strength . 4 no.
Nick-Break.. 4 no.
Side Bend. 8 no. Total 16 no. (Refer Table 2)

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

Page
Page 10 of
16

Radiographic Test (RT) and 16 destructive tests are require for following
weld joints of pipe sample of same material grade API 5L, PSL2, X-56 of
Transmission & Distribution pipeline.
Weld joint of pipeline produced from Internal or External clamp pipe
aligning device. (16 tests). Refer Table 2.
Weld joint of Tie-in.(16 tests) Refer Table 2.
Root Repair of weld joint/ full penetration repair. (5 tests) Refer Table 5.
Partial Repair of weld joint.(4 tests). Refer Table 5.
4. Certificates for Filler Metals & Base Materials
Following certificates are required for Filler metal group (Electrode & FCAW wire) &
base material:
Inspection certificate of Filler metal group (All electrodes and FCAW wire) issued by
manufacturer covering chemical analysis & classification (EN#, AWS & ISO #).
2.4.1 Certificate of compliance of base material (pipe) supplied for Testing.
2.4.1.1 Mill Inspection & Test certificate:
Nondestructive Testing
Destructive Testing
Hydrostatic Testing. D) Dimensional
Inspection.
2.4.1.2 Pipe Manufacturers QA Report: Chemical Composition, Tensile,
Charpy Impact Test, Guided Bend Test, Viker Hardness Test.
2.4.1.3 Packing list of Pipe Manufacturer.

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

Page
Page 11 of
16

APPENDIX-1: WPS FOR API 5L, 36, Grade X56, PIPE JOINT WELD WITH INTERNAL CLAMP
Project / Contract No
WTS-PH1-CPL-MECREV 3
WPS-001
WTS-PH1-CPL-MECPAGE 1
PQR-001

WELDING PRECEDURE
SPECIFICATION

Standard
For
Welding process
Material
Diameter & Wall thickness
Joint design
Filler metal
Position
Direction of welding
Number of welders
Time lapse between
welding
Type and removal of lineup
clamp
Cleaning & or grinding
Preheat temperature
Temperature between
passes
Shielding gas & flow rate
Shielding flux
Plasma gas composition
Plasma gas orifice size
Plasma gas flow rate

:
:
:
:
:
:
:
:
:
:
:

API 1104, Sept 2013


Transmission and Distribution Line
SMAW+FCAW
API-5L , Grade X-56
OD>12.75" & from 4.8 to 19.1 mm thickness
V Groove
AWS, A-5.1 E6010 /A-5.29 E71T8
5G Fixed
Downhill
Min.2 welders
Between root & hot pass 15 min;
weld interruption after finishing 70% of welding only

: Internal Clamp, removal of clamp after finishing root pass


: Mechanical Brushing & Grinding
: 50 C
: 300 C max
:
:
:
:
:

NA
NA
NA
NA
NA
Joint Design Sketch

CAP
FILL
HP

3035

R
P

2
(0.5)

2 (0.5)
Electrical
Characteristics and Travel Speed
LAYER
ROOT
HOT

PROCESS

2
SMAW
(0.5)
FCAW

FILLER MATERIAL
AWS No

(mm)
2
(0.5)

VOLTAGE
(V)

CURRENT
A

POLARITY

E6010

3.2 4

25 30

100 110

DC ( - )

E71T8

2.0

17 - 21

160 - 260

DC ( + )

DIRECTIO
N
OF
WELD
DOWNHIL
L
DOWNHIL

TRAVEL
SPEED
cm/min
12 15
15 - 26

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

FILL

FCAW

E71T8

2.0

17 - 21

160 - 260

DC ( + )

CAP

FCAW

E71T8

2.0

17 - 21

160 - 260

DC ( + )

CONTRACTOR

THIRD PARTY NDT/WELDING


INSPECTOR

Page
Page 12 of
16

L
DOWNHIL
L
DOWNHIL
L
CONSULTANT

15 26
15 26

APPENDIX-2: WPS FOR API 5L, 36, Grade X56, PIPE JOINT WELD WITH EXTERNAL CLAMP
EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL
Project / Contract No
WTS-PH1-CPL-MECREV 3
WPS-002
WTS-PH1-CPL-MECPAGE 1
PQR-002

WELDING PRECEDURE
SPECIFICATION

Standard
For
Welding process
Material
Diameter & Wall thickness
Joint design
Filler metal
Position
Direction of welding
Number of welders
Time lapse between
welding
Type and removal of lineup
clamp
Cleaning & or grinding
Preheat temperature
Temperature between
passes
Shielding gas & flow rate
Shielding flux
Plasma gas composition
Plasma gas orifice size
Plasma gas flow rate

:
:
:
:
:
:
:
:
:
:
:

API 1104, Sept 2013


Transmission and Distribution Line
SMAW+FCAW
API-5L , Grade X-56
OD>12.75" & from 4.8 to 19.1 mm thickness
V Groove
AWS, A-5.1 E6010 /A-5.29 E71T8
5G Fixed
Uphill / Downhill
Min.2 welders
Between root & hot pass 15 min;
weld interruption after finishing 70% of welding only
: External Clamp, removal of clamp after finishing 50% of
root pass
: Mechanical Brushing & Grinding
: 50 C
: 300 C max
:
:
:
:
:

NA
NA
NA
NA
NA
Joint Design Sketch

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

Page
Page 13 of
16

CAP
FILL
HP

3035

R
P

2
(0.5)

2 (0.5)
Electrical
Characteristics and Travel Speed
LAYER

PROCES
S

FILLER MATERIAL

CURRENT

VOLTAGE
(V)

E6010

3.2- 4

25 30

100 110

POLARIT
Y
DC ( - )

FCAW

E71T8

2.0

17 - 21

160 - 260

DC ( + )

FILL

FCAW

E71T8

2.0

17 - 21

160 - 260

DC ( + )

CAP

FCAW

E71T8

2.0

17 - 21

160 - 260

DC ( + )

ROOT
HOT

2
SMAW
(0.5)

2 (mm)
(0.5)

AWS No

CONTRACTOR

DIRECTI
ON
OF
WELD
UPHILL
DOWNHIL
L
DOWNHIL
L
DOWNHIL
L

TRAVEL
SPEED
cm/min
12 15
15 - 26
15 26
15 26

CLIENT

APPENDIX-3: WPS FOR API 5L, 36, Grade X56, PIPE JOINT WELD FULL PENETRATION REPAIR
EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL
Project / Contract No
WTS-PH1-CPL-MECREV 3
WPS-003
WTS-PH1-CPL-MECPAGE 1
PQR-003

WELDING PRECEDURE
SPECIFICATION

Standard
For
Welding process
Material
Diameter & Wall thickness
Joint design
Filler metal
Position
Direction of welding
Number of welders
Time lapse between
welding
Type and removal of lineup
clamp
Cleaning & or grinding
Preheat temperature

:
:
:
:
:
:
:
:
:
:

API 1104, Sept 2013


Full Penetration Repair
SMAW
API-5L , Grade X-56
OD>12.75" & from 4.8 to 19.1 mm thickness
V Groove
AWS, A-5.1 E6010 /A-5.5 E7010
5G Fixed
Uphill / Downhill
1 welders

: NA
: NA
: Mechanical Brushing & Grinding
: 100 C

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.


WELDING PROCEDURE SPECIFICATION (WPS)
0
07 Nov
2013

Rev. date

1
08 Dec
2013

Temperature between
passes
Shielding gas & flow rate
Shielding flux
Plasma gas composition
Plasma gas orifice size
Plasma gas flow rate

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

Page
Page 14 of
16

: 300 C max
:
:
:
:
:

NA
NA
NA
NA
NA
Joint Design Sketch

Weld Preparation;
40

DL CAP

40

FILL
HP
R
P

50

50

Repair Area
DL : Defect
Length
LAYER

Electrical Characteristics and Travel Speed

PROCES
S

FILLER MATERIAL
AWS No

(mm)

ROOT

SMAW

E6010

3.2 4.0

HOT

SMAW

E7010

4.0 5.0

FILL

SMAW

E7010

4.0 5.0

CAP

SMAW

E7010

4.0 5.0

CONTRACTOR

VOLTAGE
(V)
24 28
24 28
24 28
24 28

CURRENT

90 100

POLARIT
Y
DC ( - )

100 - 110

DC ( + )

135 145

DC ( + )

130 - 140

DC ( + )

CLIENT

DIRECTI
ON
OF
WELD
UPHILL
DOWNHIL
L
DOWNHIL
L
DOWNHIL
L

TRAVEL
SPEED
Cm/min
7 - 13
10 - 15
13 - 15
13 - 15

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

APPENDIX-4: WPS FOR API 5L, 36, Grade X56, PIPE JOINT WELD PARTIAL REPAIR
EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL
Project / Contract No
WTS-PH1-CPL-MECWPS-004
WTS-PH1-CPL-MECPQR-004

WELDING PRECEDURE
SPECIFICATION

Standard
For
Welding process
Material
Diameter & Wall thickness
Joint design
Filler metal
Position
Direction of welding
Number of welders
Time lapse between
welding
Type and removal of lineup
clamp
Cleaning & or grinding
Preheat temperature
Temperature between
passes
Shielding gas & flow rate
Shielding flux
Plasma gas composition
Plasma gas orifice size
Plasma gas flow rate

:
:
:
:
:
:
:
:
:
:

Page
Page 15 of
16

REV 3
PAGE 1

API 1104, Sept 2013


Partial Repair
SMAW
API-5L , Grade X-56
OD>12.75" & from 4.8 to 19.1 mm thickness
V Groove
AWS, A-5.5 E7010
5G Fixed
Downhill
1 welders

: NA
: NA
: Mechanical Brushing & Grinding
: 100 C
: 300 C max
:
:
:
:
:

NA
NA
NA
NA
NA
Joint Design Sketch

CAP
FILL
HP
Electrical Characteristics
and Travel Speed

LAYER
FILL

PROCESS
SMAW

FILLER MATERIAL
AWS No

(mm)

E7010

4.0 5.0

P
VOLTAGE
(V)

26 28

CURRENT
A

POLARITY

120 - 130

DC ( + )

DIRECTIO
N
OF
WELD
DOWNHIL
L

TRAVEL
SPEED
cm/min
10 15

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

CAP

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013
SMAW

1
08 Dec
2013
E7010

CONTRACTOR

2
12 May
2014
4.0 5.0

3
15 June
2014
26 - 28

Document No
WTS-PH1-CPL-MEC-QAC002

115 - 125

DC ( + )
CLIENT

DOWNHIL
L

Page
Page 16 of
16
7 13

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

APPENDIX-5: WPS FOR API 5L, 36, Grade X56, PIPE TIE-IN WELD
EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL
Project / Contract No
WTS-PH1-CPL-MECWPS-005
WTS-PH1-CPL-MECPQR-005

WELDING PRECEDURE
SPECIFICATION

Standard
For
Welding process
Material
Diameter & Wall thickness
Joint design
Filler metal
Position
Direction of welding
Number of welders
Time lapse between
welding
Type and removal of lineup
clamp
Cleaning & or grinding
Preheat temperature
Temperature between
passes
Shielding gas & flow rate
Shielding flux
Plasma gas composition
Plasma gas orifice size
Plasma gas flow rate

Page
Page 17 of
16

REV 3
PAGE 1

:
:
:
:
:
:
:
:
:
:
:

API 1104, Sept 2013


Tie-in Weld
SMAW
API-5L , Grade X-56
OD>12.75" & from 4.8 to 19.1 mm thickness
V Groove
AWS, A-5.1 E6010 /A-5.5 E7010
5G Fixed
Uphill / Downhill
1 welders
Between root & hot pass 15 min;
weld interruption after finishing 70% of welding only
: External Clamp, removal of clamp after finishing 50% of
root pass
: Mechanical Brushing & Grinding
: 50 C
: 300 C max
:
:
:
:
:

NA
NA
NA
NA
NA
Joint Design Sketch

CAP
FILL
HP

3035

R
P

2
(0.5)

2 (0.5)
Electrical
Characteristics and Travel Speed
LAYER
ROOT
HOT

PROCESS

2SMAW
(0.5)
SMAW

FILLER MATERIAL
AWS No
E6010
E7010

(mm)
2
(0.5)

3.2 4.0
4.0 5.0

VOLTAGE
(V)
27 35
25 32

CURRENT
A

POLARITY

80 95
130 - 150

DC ( - )
DC ( + )

DIRECTIO
N
OF
WELD
UPHILL
DOWNHIL

TRAVEL
SPEED
cm/min
12 - 15
15 - 26

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

FILL
CAP

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

SMAW

E7010

SMAW

E7010

2
12 May
2014

4.0 5.0
4.0 5.0

3
15 June
2014

25 30
25 30

Document No
WTS-PH1-CPL-MEC-QAC002

120 140

DC ( + )

130 - 140

DC ( + )

CONTRACTOR

L
DOWNHIL
L
DOWNHIL
L

Page
Page 18 of
16

15 - 26
15 - 26

CLIENT

APPENDIX-6: WPS FOR API 5L, 36, Grade X65, PIPE JOINT WELD WITH INTERNAL CLAMP
EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL
Project / Contract No
WTS-PH1-CPL-MECREV 3
WPS-006
WTS-PH1-CPL-MECPAGE 1
PQR-006

WELDING PRECEDURE
SPECIFICATION

Standard
For
Welding process
Material
Diameter & Wall thickness
Joint design
Filler metal
Position
Direction of welding
Number of welders
Time lapse between
welding
Type and removal of lineup
clamp
Cleaning & or grinding
Preheat temperature
Temperature between
passes
Shielding gas & flow rate
Shielding flux
Plasma gas composition
Plasma gas orifice size
Plasma gas flow rate

:
:
:
:
:
:
:
:
:
:
:

API 1104, Sept 2013


Transmission and Distribution Line
SMAW+FCAW
API-5L , Grade X-65
OD>12.75" & from 4.8 to 19.1 mm thickness
V Groove
AWS, A-5.1 E6010 /A-5.29 E71T8
5G Fixed
Downhill
Min.2 welders
Between root & hot pass 15 min;
weld interruption after finishing 70% of welding only

: Internal Clamp, removal of clamp after finishing root pass


: Mechanical Brushing & Grinding
: 50 C
: 300 C max
:
:
:
:
:

NA
NA
NA
NA
NA
Joint Design Sketch

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

Page
Page 19 of
16

CAP
FILL
HP

3035

R
P

2
(0.5)

2 (0.5)
Electrical
Characteristics and Travel Speed
LAYER

ROOT

PROCES
S

2
SMAW
(0.5)

FILLER MATERIAL

CURRENT

VOLTAGE
(V)

2 (mm)
(0.5)

AWS No

POLARIT
Y

E6010

3.2 4.0

25 30

100 110

DC ( - )

HOT

FCAW

E71T8

2.0

17 - 21

160 - 260

DC ( + )

FILL

FCAW

E71T8

2.0

17 - 21

160 - 260

DC ( + )

CAP

FCAW

E71T8

2.0

17 - 21

160 - 260

DC ( + )

CONTRACTOR

DIRECTI
ON
OF
WELD
DOWNHIL
L
DOWNHIL
L
DOWNHIL
L
DOWNHIL
L

TRAVEL
SPEED
cm/min
12 15
15 - 26
15 26
15 26

CLIENT

APPENDIX-7: WPS FOR API 5L, 36, Grade X65, PIPE JOINT WELD WITH EXTERNAL CLAMP
EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL
Project / Contract No
WTS-PH1-CPL-MECREV 3
WPS-007
WTS-PH1-CPL-MECPAGE 1
PQR-007

WELDING PRECEDURE
SPECIFICATION

Standard
For
Welding process
Material
Diameter & Wall thickness
Joint design
Filler metal
Position
Direction of welding
Number of welders
Time lapse between
welding
Type and removal of lineup
clamp
Cleaning & or grinding

:
:
:
:
:
:
:
:
:
:
:

API 1104, Sept 2013


Transmission and Distribution Line
SMAW+FCAW
API-5L , Grade X-65
OD>12.75" & from 4.8 to 19.1 mm thickness
V Groove
AWS, A-5.1 E6010 /A-5.29 E71T8
5G Fixed
Uphill / Downhill
Min.2 welders
Between root & hot pass 15 min;
weld interruption after finishing 70% of welding only
: External Clamp, removal of clamp after finishing 50% of
root pass
: Mechanical Brushing & Grinding

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

Preheat temperature
Temperature between
passes
Shielding gas & flow rate
Shielding flux
Plasma gas composition
Plasma gas orifice size
Plasma gas flow rate

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

Page
Page 20 of
16

: 50 C
: 300 C max
:
:
:
:
:

NA
NA
NA
NA
NA
Joint Design Sketch

CAP
FILL
HP

3035

R
P

2
(0.5)

2 (0.5)
Electrical
Characteristics and Travel Speed
LAYER

PROCES
S

FILLER MATERIAL

CURRENT

VOLTAGE
(V)

E6010

3.2 4.0

25 30

100 110

POLARIT
Y
DC ( - )

FCAW

E71T8

2.0

17 - 21

160 - 260

DC ( + )

FILL

FCAW

E71T8

2.0

17 - 21

160 - 260

DC ( + )

CAP

FCAW

E71T8

2.0

17 - 21

160 - 260

DC ( + )

ROOT
HOT

2
SMAW
(0.5)

2 (mm)
(0.5)

AWS No

CONTRACTOR

DIRECTI
ON
OF
WELD
UPHILL
DOWNHIL
L
DOWNHIL
L
DOWNHIL
L

TRAVEL
SPEED
cm/min
12 15
15 - 26
15 26
15 26

CLIENT

APPENDIX-8: WPS FOR API 5L, 36, Grade X65, PIPE JOINT WELD FULL PENETRATION REPAIR
EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL
Project / Contract No
WTS-PH1-CPL-MECREV 3
WPS-003
WTS-PH1-CPL-MECPAGE 1
PQR-003

WELDING PRECEDURE
SPECIFICATION

Standard
For
Welding process
Material
Diameter & Wall thickness
Joint design
Filler metal

:
:
:
:
:
:
:

API 1104, Sept 2013


Full Penetration Repair
SMAW
API-5L , Grade X-65
OD>12.75" & from 4.8 to 19.1 mm thickness
V Groove
AWS, A-5.1 E6010 /A-5.5 E8010

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.


WELDING PROCEDURE SPECIFICATION (WPS)
0
07 Nov
2013

Rev. date

1
08 Dec
2013

Position
Direction of welding
Number of welders
Time lapse between
welding
Type and removal of lineup
clamp
Cleaning & or grinding
Preheat temperature
Temperature between
passes
Shielding gas & flow rate
Shielding flux
Plasma gas composition
Plasma gas orifice size
Plasma gas flow rate

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

Page
Page 21 of
16

: 5G Fixed
: Uphill / Downhill
: 1 welders
: NA
: NA
: Mechanical Brushing & Grinding
: 100 C
: 300 C max
:
:
:
:
:

NA
NA
NA
NA
NA
Joint Design Sketch

Weld Preparation;
40

DL CAP

40

FILL
HP
R
P

50

50

Repair Area
DL : Defect
Length
LAYER

Electrical Characteristics and Travel Speed

PROCES
S

FILLER MATERIAL
AWS No

(mm)

ROOT

SMAW

E6010

3.2 - 4.0

HOT

SMAW

E8010

4.0 - 5.0

FILL

SMAW

E8010

4.0 5.0

CAP

SMAW

E8010

4.0 5.0

CONTRACTOR

VOLTAGE
(V)
24 28
24 28
24 28
24 28

CURRENT

90 100

POLARIT
Y
DC ( - )

100 - 110

DC ( + )

135 145

DC ( + )

130 - 140

DC ( + )

CLIENT

DIRECTI
ON
OF
WELD
UPHILL
DOWNHIL
L
DOWNHIL
L
DOWNHIL
L

TRAVEL
SPEED
cm/min
7 - 13
10 - 15
13 - 15
13 - 15

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

APPENDIX-9: WPS FOR API 5L, 36, Grade X65, PIPE JOINT WELD PARTIAL REPAIR
EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL
Project / Contract No
WTS-PH1-CPL-MECWPS-004
WTS-PH1-CPL-MECPQR-004

WELDING PRECEDURE
SPECIFICATION

Standard
For
Welding process
Material
Diameter & Wall thickness
Joint design
Filler metal
Position
Direction of welding
Number of welders
Time lapse between
welding
Type and removal of lineup
clamp
Cleaning & or grinding
Preheat temperature
Temperature between
passes
Shielding gas & flow rate
Shielding flux
Plasma gas composition
Plasma gas orifice size
Plasma gas flow rate

:
:
:
:
:
:
:
:
:
:

Page
Page 22 of
16

REV 3
PAGE 1

API 1104, Sept 2013


Partial Repair Procedure
SMAW
API-5L , Grade X-65
OD>12.75" & from 4.8 to 19.1 mm thickness
V Groove
AWS, A-5.5 E8010
5G Fixed
Downhill
1 welders

: NA
: NA
: Mechanical Brushing & Grinding
: 100 C
: 300 C max
:
:
:
:
:

NA
NA
NA
NA
NA
Joint Design Sketch

CAP
FILL
HP
Electrical Characteristics
and Travel Speed

LAYER

FILL

PROCES
S
SMAW

FILLER MATERIAL
AWS No

(mm)

E8010

4.0 5.0

R
P

VOLTAGE
(V)
26 28

CURRENT
A

POLARIT
Y

120 - 130

DC ( + )

DIRECTI
ON
OF
WELD
DOWNHIL
L

TRAVEL
SPEED
cm/min
10 15

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

CAP

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013
SMAW

1
08 Dec
2013
E8010

CONTRACTOR

2
12 May
2014
4.0 5.0

3
15 June
2014
26 - 28

Document No
WTS-PH1-CPL-MEC-QAC002

115 - 125

DC ( + )
CLIENT

DOWNHIL
L

Page
Page 23 of
16
7 13

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

APPENDIX-10: WPS FOR API 5L, 36, Grade X65, PIPE TIE-IN WELD
EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL
Project / Contract No
WTS-PH1-CPL-MECWPS-005
WTS-PH1-CPL-MECPQR-005

WELDING PRECEDURE
SPECIFICATION

Standard
For
Welding process
Material
Diameter & Wall thickness
Joint design
Filler metal
Position
Direction of welding
Number of welders
Time lapse between
welding
Type and removal of lineup
clamp
Cleaning & or grinding
Preheat temperature
Temperature between
passes
Shielding gas & flow rate
Shielding flux
Plasma gas composition
Plasma gas orifice size
Plasma gas flow rate

Page
Page 24 of
16

REV 3
PAGE 1

:
:
:
:
:
:
:
:
:
:
:

API 1104, Sept 2013


Tie-in Weld
SMAW
API-5L , Grade X-65
OD>12.75" & from 4.8 to 19.1 mm thickness
V Groove
AWS, A-5.1 E6010 /A-5.5 E8010
5G Fixed
Uphill / Downhill
1 welders
Between root & hot pass 15 min;
weld interruption after finishing 70% of welding only
: External Clamp, removal of clamp after finishing 50% of
root pass
: Mechanical Brushing & Grinding
: 50 C
: 300 C max
:
:
:
:
:

NA
NA
NA
NA
NA
Joint Design Sketch

CAP
FILL
HP

3035

R
P

2
(0.5)

2 (0.5)
Electrical
Characteristics and Travel Speed
LAYER
ROOT
HOT

PROCES
S

2
SMAW
(0.5)
SMAW

FILLER MATERIAL
AWS No
E6010
E8010

VOLTAGE
(V)

2 (mm)
(0.5)
3.2 4.0
4.0 5.0

27 35
25 32

CURRENT
A
80 95
130 - 150

POLARIT
Y
DC ( - )
DC ( + )

DIRECTI
ON
OF
WELD
UPHILL
DOWNHIL

TRAVEL
SPEED
cm/min
12 - 15
15 - 26

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.


WELDING PROCEDURE SPECIFICATION (WPS)
0
07 Nov
2013

Rev. date

FILL
CAP

1
08 Dec
2013

SMAW

E8010

SMAW

E8010

2
12 May
2014

4.0 5.0
4.0 5.0

3
15 June
2014

25 30
25 30

Document No
WTS-PH1-CPL-MEC-QAC002

120 140

DC ( + )

130 - 140

DC ( + )

L
DOWNHIL
L
DOWNHIL
L

Page
Page 25 of
16

15 - 26
15 - 26

COUPON TEST REPORT


Date______________________________________________
Test No_____________________________________
_
Location____________________________________________________________________________________________
_
State______________________________________________
Weld Position:
Roll
_
Fixed
Welder____________________________________________
Mark_______________________________________
_
Welding
Time of
Time________________________________________
day__________________________________
Mean
Wind break
Temperature___________________________________
used______________________________
Weather
conditions____________________________________________________________________________________
Voltage___________________________________________
Amperage__________________________________
__
_
Welding machine
Welding machine
type_________________________________
size__________________________
Filler
metal___________________________________________________________________________________________
Reinforcement______________________________________________________________________________________
__
Pipe type and
grade____________________________________________________________________________________
Wall
Outside
thickness_______________________________________
diameter_____________________________
Coupon stenciled

Original specimen
dimension
Original specimen
area
Maximum load
Tensile strength
Fracture location
Procedure
Welder

Qualified test
Line test

Qualified
Disqualified

Maximum
tensile___________________

Minimum tensile

Average tensile

Project

EXTENSION OF PHASE-1 WATER SUPPLY PROJECT TO VILLAGES AT HAIL

Client

MINISTRY OF WATER AND ELECTRICITY (MOWE)

Consultant

OTAISHAN CONSULTING ENGINEERS

Contractor
Document
Name
Rev. No

BIN SAMMAR CO.

Rev. date

WELDING PROCEDURE SPECIFICATION (WPS)


0
07 Nov
2013

1
08 Dec
2013

2
12 May
2014

3
15 June
2014

Document No
WTS-PH1-CPL-MEC-QAC002

Page
Page 26 of
16

Remarks on tensile-strength
test__________________________________________________________________________
1.
__________________________________________________________________________________________________
2.
__________________________________________________________________________________________________
3.
__________________________________________________________________________________________________
4.
__________________________________________________________________________________________________
Remarks on bend
test___________________________________________________________________________________
1.
__________________________________________________________________________________________________
2.
__________________________________________________________________________________________________
3.
__________________________________________________________________________________________________
4.
__________________________________________________________________________________________________
Remarks on nick-break
test______________________________________________________________________________
1.
__________________________________________________________________________________________________
2.
__________________________________________________________________________________________________
3.
__________________________________________________________________________________________________
4.
__________________________________________________________________________________________________
Test made at
__________________________________________
Tested by
____________________________________________

Date
_________________________________________
Supervised by
__________________________________

You might also like