1. The water in a borehole was bailed to a depth of 11m below the ground level and
the recorded rise in the water level in the borehole are as follows:
h1 = 60cm in 24 hrs; h2 = 55cm in 24 hrs; and h3 = 50cm in 24 hrs.
2. A building is proposed in an area having thick deposit of silty clay. The heaviest
column in the building is likely to carry a load of 100t. Determine the minimum
depth of exploration required for foundation design.
3. In a borehole, a layer of fine sand was encountered at a depth of 8m from the
ground surface. A dense sand layer overlies the fine sand layer. The N value
recorded in the field was 23. Determine the correct N value for the layer at 8m
depth. The water table was found to be at a depth of 2m from surface.
4. In a geophysical exploration by resistivity method the following results were
obtained:
Spacing
of
electrodes,m
Resistivity
cm
4.5
7.5
675
1250
1720
1825
1800
1700
1550
6. The following data were collected from a seismic refraction test in an area.
Determine the depth from the ground level at which there is a change in the
formation.
Distance
of
peg
from 10.0
15.0
20.0
30.0
400
500
600
25.0
33.0
50.0
225.0
250.0
275.0
geophone, m
Time
by
taken
the
first
7. A load test conducted at the soil surface on a 30cm square plate provided the
following results:
Load, kg
Settlement,
mm
500
1000
1500
2000
2500
3000
1.25
2.50
3.75
5.00
7.50
15.00
Similarly, H2 = 6.05m
H3 = 5.00m
Therefore, DW.T. (from H1 = 7.20) = 11.00 7.20 = 3.80m
DW.T. (from H2 = 6.05m) = 3.80m
water table
s = perimeter shear
11450 = (60x60)q + 2(60 + 60)S
and
( L1 + L2 ) / T2 =
600.0 m / s
( L1 + L2 + L3 ) / T3 =
600.0 m / s
( L1 + L2 + L3 + L4 ) / T4 =
600.0 m / s
Plotting these on a graph and drawing a best fit straight line through them, the
velocity of surface layer is obtained as 603.0 m/s.
5
L
i
i =1
Again,=
1777 m / s 603.0m / s.
T
5
Hence, the wave which reached the geophone at L5 in time T5 did not travel
through surface layer entirely.
Similarly, V2 = 4000 m/s
From H1 = (T5 (L1 + L2 + L3 + L4 + L5) / V2) V1/2 = 37.68 m
7. The points are plotted and the point of definite break occurs at load
2000 / 302 = 2.22 kg/cm2
Hence, the ultimate bearing capacity of the plate is 2.22 kg/cm2.
(a) From
B prototype
q prototype = q plate
B plate
= 222t / m 2
q prototype = q plate