You are on page 1of 28

DEGREE CERTIFICATE

8
SHORT TERM
PRIMAVERA
SHORT TERMCOURSE
COURSEINCERTIFICATE
PUBLIC
ON HEALTH ENGINEERING.-
NEW DEVELOPMENT CHENNAI -- INDIA
IN WATER TREATMENT. KOLKOTTA—INDIA.

9
EXPEERIENCE CERTIFICATE FROM SKS Co - KUWAIT

10
PLANNING ENGINEER IN MINA ABDULLAH PROJECT CB/1208-KUWAIT

11
PLANNING ENGINEER IN MINA AHMADI PROJECT CA/PD/ 3631-KUWAIT

12
PLANNING ENGINEER IN MINA AHMADI PROJECT CA/PD/ 3638- KUWAIT

13
APPRECIATION LETTER FROM KNPC- KUWAIT

14
WEEKLY PROGRESS MEETING
No. 004

EPIC for Upgrading of Existing Gabbro Berths Crane Facilities at


Project:
Mesaieed Port.

Contract No.: GTC 07/108/ED

Client: Qatar Petroleum -Engineering Department (Onshore Operations)


Date of Meeting: 10-09-2007 Time: 9 – 11:00 A.M.
Venue: QP Refinery Building Site Office Date of Issue: 04-09-2007

List of Attendees : Qatar Petroleum / MIC


Sl No. Name Designation
1 Mr.Roger Cullen EDM/32
2 Mr.Antonio Asdillo EBN 64
3 Mr. Nayyer Hassan EDM / 412
4 Mr. Ariel Guilles EDM/ 424
List of Attendees : Aljaber Engineering
1 Mr. Fadi N.Haddad Project Director
2 Mr. N.Benergy Operations Manager – M&E
3 Mr.Redda Hajalli Engineering Manager-M&E
4 Mr.Omar Ballouz Sr.Project Manager[Electrical]
5 Mr.G.Muthu Head Of HSE
6 Mr. Abu Thahir Planning Engineer

Item
Minutes Action
No.

1.0 Review of all Matters arising from previous minutes:

On subsequent review of previous minutes, it has been observed that


JEC
JEC submitted all relevant documents with the exception of Planning
Package incorporating all vendor deliverables.
JEC to submit the same on / before 13-09-07

2.0 Works Progress:

2.1 Mobilization
JEC briefed QP that the mobilization is in progress and awaiting MIC QP
approval for Land Lease to proceed further. JEC requested QP
assistance to expedite this matter.
EXPERIENCE CERTIFICATE FROM METRO WATER

15
MY POSITION IN THE METRO WATER ORGANIZATION CHART.

MOHAMED ABUTHAHIR ABDUL SALAM. PPort No E6057491. INDIA


PASSPORT DETAILS- COPY
16
KUWAIT

CIVIL ID

COPY

*
*
*
*
*
*
*
*
*
*
*
*
*

KUWAIT

DRIVING

LISENCE

COPY
*
*
*
*
*
*
*
*
*
*
*
*
*
KUWAIT NATIONAL PETROLIUM CORPORATION- ENTRANCE PASS
MEDICAL FITTNESS CERTIFICATE
WEEKLY PROGRESS MEETING
No. 010

EPIC for Upgrading of Existing Gabbro Berths Crane Facilities at


Project:
Mesaieed Port.

Contract No.: GTC 07/108/ED

Client: Qatar Petroleum - Engineering Department (Onshore Operations)


Date of Meeting: 29-10-2007 Time: 9:00 – 10:00 A.M.
Venue: JEC site office Date of Issue: 30-10-2007

List of Attendees : Qatar Petroleum / MIC


Sl No. Name Designation
1 Mr. Roger Cullen EDM/32
2 Mr. Antonio Asdillo EBN 64
3 Mr. Ariel Guilles EDM/ 424
4 Mr. Yusufuddin EDM/417
List of Attendees : Aljaber Engineering
1 Fadi N. Haddad Project Director
2 Mr. N. Benergy Operations Manager – M&E
3 Mr. Reda Hajali Engineering Manager-M&E
4 Mr. Nemer Project Manager
5 Mr. Abu Thahir Planning Engineer
6 Mr. Vijay Anand Lead HSE Engineer
7 Mr. Jeyan Safety Engineer

Item
Minutes Action
No.

1.0 Review of all Matters arising from previous minutes:


JEC
NIll

2.0 Works Progress:

2.1 EDM group requested JEC to submit the Daily report by fax. 477-1007 to Mr. John D. JEC
Munro (A/EDM/4).

2.2 JEC informed QP that Kranbau is currently carrying out fabrication works. Info

2.3 JEC stated that Fantuzzi will be in Qatar by 05.11.2007 and a meeting is proposed with
QP on 06.11.2007. Info

P 1/4
WEEKLY PROGRESS MEETING
No. 010

2.4 JEC stated that MA consultant will carryout the HV System Design Engineering works. Info
QP informed JEC to proceed the Engineering works if they are proceed the Engineering
works if they are satisfied with their qualification.

3.0 Safety:

3.1 Accident / Incidents:

SL. PARTICULARS / Till last week During this week Total


NO DETAILS
1 Number of first aid JEC…0…+ S.C…0…. = 0 JEC…0…+ S.C…0…. = 0 JEC…0…+ S.C…0…. = 0
cases.

2 Number of minor JEC…0…+ S.C…0…. = 0 JEC…0…+ S.C…0…. = 0 JEC…0…+ S.C…0…. = 0


injury cases sent to
hospital.

3 Number of serious JEC…0…+ S.C…0…. = 0 JEC…0…+ S.C…0…. = 0 JEC…0…+ S.C…0…. = 0


incidents without
injury, if any

4 Number of LTI JEC…0…+ S.C…0…. = 0 JEC…0…+ S.C…0…. = 0 JEC…0…+ S.C…0…. = 0


accidents, if any

5 Loss of man days JEC…0…+ S.C…0…. = 0 JEC…0…+ S.C…0…. = 0 JEC…0…+ S.C…0…. = 0


due to the
accidents.

6 Total man hours Till last week..160…hours During this week 64 hours Total …224 hours
worked since
beginning of the
project.

3.2 Productive Manhours: 900 hrs. (for this week)

3.3 Loss of Manhours: Nill

4.0 Progress Achieved against Planning Schedule:

4.1 JEC stated that the progress achieved as of today is 16.28% Vs planned 11.% as JEC
detailed below:
PREVIOUS PERIOD THIS PERIOD TODATE
Wt.
Planned Actual Variance Planned Actual Variance Planned Actual Variance
1 Engineering 3.90% 93.13 82.13 -11.00 0.90 1.90 1.00 94.03 84.03 -10.00

2 Procurement 75.96% 3.33 14.64 11.31 6.17 2.38 -3.79 9.51 17.02 7.51

3 Construction 20.14% 1.14 0.20 -0.94 0.22 0.18 -0.04 1.36 0.38 -0.99

Total 100.00% 6.40 14.37 7.97 4.77 1.92 -2.85 11.16 16.28 5.12

P 2/4
WEEKLY PROGRESS MEETING
No. 010

5.0 Engineering and Design:

5.1 QP stated all documents submitted by JEC are under review. QP

6.0 Documentation:

6.1 JEC informed QP that subsequent approval for Building Permit DC1 will be carried out JEC
by MA consultant.

6.2 JEC stated that all relevant Method Statements pertaining to Electrical and Civil works JEC
are submitted. QP requested JEC to give advance copy to EDM/4 group.

7.0 Procurement:

7.1 JEC stated that HV cable is approved and procurement is in progress. JEC

7.2 RMU is approved with comments, however JEC to expedite the final approval from JEC
Kahramaa.

7.3 QP stated that JEC to submit all other outstanding items such as cable Tiles, Ducts and JEC
warning tapes etc. at the earliest.

8.0 Construction:

8.1 QP stated that all S/D related activities for Kangaroo Crane and other works to be JEC
discussed with Port Manager. (Captain Claudio).

8.2 QP stated that JEC to carryout the conditions survey before TOP of any renovation / JEC
refurbishment works. Survey Report to be recorded and agreed with Port authorities.

9.0 QA/QC

9.1 JEC submitted all documents related to QA/QC Info

10.0 Areas of Concern:

10.1 QP emphasized JEC to achieve the Milesstone-1 as per the schedule and requested JEC
JEC to update the delivery status of all the Milestone-1 items.

P 3/4
WEEKLY PROGRESS MEETING
No. 010

11.0 Commercial and Contractual:


Nill.

12.0 Any other Matter:

12.1 JEC stated that M/s Fantuzzi will be in Qatar on 5th Nov. 07 and will meet QP on 6th Nov JEC
07 as per QP schedule sent to JEC earlier.

12.2 QP requested JEC to submit the QP/JEC Inspection visits schedule to Kranbau in JEC
Germany. JEC advised that as agreed during the Oct. 11, 2007 Meeting in Doha. There
will be three visits, as follows:

Visit 1 – Upon finalization of material procurement in Germany.

Visit 2 – Upon finalization of Fabrication works and during assemble stage.

Visit 3 – F.A.T.

13.0 Next Meeting:

QP informed the next meeting will be on the 5th November 2007 at 9:00 AM at JEC site Info
office.

14.0 The meeting ended with mutual thanks.

Fadi N. Haddad – Project Director Roger Cullen – EDM 32


For JEC For QP

P 4/4