EDT
Nombre de tarea
Duracin
Comienzo
Fin
Predecesoras
19.5 das
mi 24/02/16
vie 18/03/16
1.1
1 da
mi 24/02/16
jue 25/02/16
1.1.1
0.25 das
mi 24/02/16
mi 24/02/16
1.1.2
0.25 das
mi 24/02/16
mi 24/02/16
1.1.3
0.5 das
mi 24/02/16
jue 25/02/16
1.2
4.5 das
jue 25/02/16
mar 01/03/16
mar 23 feb
ENTREGA DE CISTERNA
jue 25 feb
sb 27 feb
lun 29 feb
mi 02 mar
vie 04 mar
lun 14 mar
mi 16 mar
0.25 das
jue 25/02/16
jue 25/02/16
0.75 das
jue 25/02/16
vie 26/02/16
1.2.3
1 da
vie 26/02/16
sb 27/02/16
10
1.2.4
0.25 das
sb 27/02/16
sb 27/02/16
11
1.2.5
0.75 das
sb 27/02/16
lun 29/02/16
10
12
1.2.6
1 da
lun 29/02/16
mar 01/03/16
11
13
1.2.7
0.5 das
mar 01/03/16
mar 01/03/16
12
14
1.3
12 das
mi 02/03/16
mi 16/03/16
15
1.3.1
5 das
mi 02/03/16
mar 08/03/16
16
1.3.1.1
0.5 das
mi 02/03/16
mi 02/03/16
13
17
1.3.1.2
0.25 das
mi 02/03/16
mi 02/03/16
16
18
1.3.1.3
0.5 das
mi 02/03/16
jue 03/03/16
17
C1
19
1.3.1.4
0.25 das
jue 03/03/16
jue 03/03/16
18
C1
20
1.3.1.5
2 das
vie 04/03/16
lun 07/03/16
43
21
1.3.1.6
1 da
jue 03/03/16
vie 04/03/16
19
22
1.3.1.7
1 da
vie 04/03/16
sb 05/03/16
21
23
1.3.1.8
Montaje de accesorios
0.5 das
sb 05/03/16
lun 07/03/16
22
24
1.3.1.9
0 das
mar 08/03/16
mar 08/03/16
20,22,57,58,59
25
1.3.2
4 das
jue 03/03/16
mar 08/03/16
C1
C1
C1
C1
C1
C1
C1
C1
C2
C2
C2
C1
08/03
C1
26
1.3.2.1
0.5 das
jue 03/03/16
jue 03/03/16
19
27
1.3.2.2
0.5 das
vie 04/03/16
vie 04/03/16
26
28
1.3.2.3
Limpieza interior del tanque y retiro de polvillo generado por limpieza mecnica
0.5 das
vie 04/03/16
vie 04/03/16
27
29
1.3.2.4
2 das
sb 05/03/16
mar 08/03/16
44
30
1.3.2.5
0 das
mar 08/03/16
mar 08/03/16
29,57,58,59
08/03
31
1.3.3
6.5 das
mar 08/03/16
mi 16/03/16
08/03
C1
C1
C2
32
1.3.3.1
Reparaciones terminadas
0 das
mar 08/03/16
mar 08/03/16
24,30,23
33
1.3.3.2
Montaje de accesorios
0.5 das
mar 08/03/16
mi 09/03/16
32
34
1.3.3.3
Prueba hidrosttica
1 da
mi 09/03/16
jue 10/03/16
33
35
1.3.3.4
Prueba neumtica
1 da
jue 10/03/16
vie 11/03/16
34,51
36
1.3.3.5
1 da
vie 11/03/16
sb 12/03/16
35,52
37
1.3.3.6
2 das
sb 12/03/16
mar 15/03/16
36
38
1.3.3.7
1 da
mar 15/03/16
mi 16/03/16
37
C2
39
1.3.3.8
Limpieza de corrosin de vlvulas, tuberas, sistema de accionamiento (inc. Pintado tuberas), rotogage, etc.
1 da
mar 15/03/16
mi 16/03/16
37
C2
40
1.3.3.9
1 da
mar 15/03/16
mi 16/03/16
37
C2
41
1.4
9.25 das
mi 02/03/16
lun 14/03/16
42
1.4.1
9.25 das
mi 02/03/16
lun 14/03/16
43
1.4.1.1
0.5 das
jue 03/03/16
jue 03/03/16
19
44
1.4.1.2
0.5 das
sb 05/03/16
sb 05/03/16
28
45
1.4.1.3
1 da
mi 02/03/16
jue 03/03/16
17
SGS
46
1.4.1.4
1 da
mi 02/03/16
jue 03/03/16
17
SGS
47
1.4.1.5
Ensayo de microdureza
1 da
vie 04/03/16
sb 05/03/16
21
48
1.4.1.6
1 da
vie 04/03/16
sb 05/03/16
21
49
1.4.1.7
1 da
jue 03/03/16
vie 04/03/16
45
50
1.4.1.8
3 das
lun 07/03/16
jue 10/03/16
20
SGS
51
1.4.1.9
1 da
mi 09/03/16
jue 10/03/16
34CC
SGS
52
1.4.1.10
1 da
jue 10/03/16
vie 11/03/16
35CC
53
1.4.1.11
Inspeccin de revestimiento
1 da
sb 12/03/16
lun 14/03/16
36
SGS
54
1.4.1.12
Cubicacin
1 da
sb 12/03/16
lun 14/03/16
36
SGS
55
1.4.1.13
0 das
lun 14/03/16
lun 14/03/16
53,54
56
1.4.2
3 das
vie 04/03/16
mar 08/03/16
Trabajos de reparaciones
C1
C1
C1
C1
C2
SGS
SGS
SGS
SGS
SGS
SGS
14/03
57
1.4.2.1
3 das
vie 04/03/16
mar 08/03/16
20CC
SGS
58
1.4.2.2
3 das
vie 04/03/16
mar 08/03/16
20CC
SGS
59
1.4.2.3
3 das
vie 04/03/16
mar 08/03/16
20CC
SGS
60
1.5
2 das
mi 16/03/16
vie 18/03/16
vie 18 mar
C1
1.2.2
Pruebas y Acabados
sb 12 mar
OL
1.2.1
jue 10 mar
C1
mar 08 mar
REPSOL
dom 06 mar
OL
61
1.5.1
0.25 das
mi 16/03/16
mi 16/03/16
55,38,39,40
62
1.5.2
Inertizado de tanque
0.75 das
jue 17/03/16
jue 17/03/16
61
63
1.5.3
0.5 das
jue 17/03/16
vie 18/03/16
62
64
1.5.4
Regasificado de tanque
0.5 das
vie 18/03/16
vie 18/03/16
63
REPSOL
65
1.5.5
Unidad lista
0 das
vie 18/03/16
vie 18/03/16
64
18/03
C1
C1
Tarea
Resumen
Hito inactivo
solo duracin
solo el comienzo
Hito externo
Divisin crtica
Divisin
Resumen inactivo
solo fin
Fecha lmite
Progreso
Hito
Tarea inactiva
Tarea manual
Resumen manual
Tareas externas
Tareas crticas
Progreso manual
Pgina 1
dom 20 mar