Professional Documents
Culture Documents
DOI 10.1007/s00170-006-0466-x
1 Introduction
As competition increases, firms have been trying to find
ways of having the competitive advantage in the market
place. In the late 1940s managers and workers learned to
question the need for every work sequence, every item of
in-process-inventory, and every second that people, material and machines were idle. Managers and employees
learned to identify and eliminate waste, increasing both
production and quality [1].
Besides that they had to take the changing market
demand into consideration. Product differentiation, high
quality, speedy delivery and reasonable prices became
M. Cakmakci (*) . M. K. Karasu
Dokuz Eyll University, Engineering Faculty,
Industrial Engineering Department,
zmir, Turkey
e-mail: mehmet.cakmakci@deu.edu.tr
2 Whats SMED?
The SMED system is a theory and set of techniques that
make it possible to perform equipment setup and changeover operations in under 10 min. SMED improves setup
process and provide a setup time reduction up to 90% with
moderate investments. Setup operation is the preparation or
after adjustment that is performed once before and once
after each lot is processed [2]. Shingo divides the setup
operation into two parts:
Internal setup The setup operation that can be done only
when the machine is shut down (attaching or removing the
dies).
External setup The setup operation that can be done when
the machine is still running. These operations can be
performed either before or after the machine is shut down.
For example getting the equipment ready for the setup
operation before the machine is shut down.
In Figure 1, setup operation periods are showed. The
setup period is constituted by internal setup and external
335
Step 2)
Converting internal setup to external setup
In order to achieve the single digit setup time objective
SMED introduces this step. At this step internal setup
activities tried to be converted to external activities. So
the total time that the machine is shut down will be
reduced. Advance preparation of operating conditions,
function standardization, and use of intermediary jigs
are the techniques to support the second step.
Step 3)
Streamlining all aspects of the setup operation
At this step specific principles are applied to shorten
the setup times. Implementing parallel operations,
using functional clamps, eliminating adjustment and
mechanization techniques are used to further setup
time reduction.
All these steps are figured in Fig. 2.
2.1 The need for an improved SMED
Fig. 1 Setup operation periods and output level during changeover
336
337
Macro Analysis
Method
Optimization
SMED
Micro Analysis
Motion
Optimization
Internal
Setup
Operations
MOTION
AND
TIME
STUDY
MTM
UAS
338
Experienced workers,
Well defined work content,
High level of job organization,
Well defined work-flow,
Similar duties.
339
machine. Routine daily maintenance checks, minor adjustments, lubrication, and minor part change out are the
responsibility of the operator. Plant maintenance personnel
handle extensive overhauls and major breakdowns with the
operator assisting. This is an important point because
changeover operations cannot be called minor part changes.
Especially at heavy industries the dies that form thick
materials are very heavy and big. The changeover process of
these dies takes a long time. An experienced changeover
team can perform setup operations faster than operators.
Another important point is changeover team efficiency.
Changeover activities must be planned carefully in order not
to encounter conjunctions that means a changeover activity
waiting to be performed.
This special changeover team performs setup operations
as a pit stop crew. The goal is performing setup activity as
soon as possible and starting desired quality production.
The number of team member that will perform the
changeover depends on the complexity of the task. For
small dies the operator of the machine may perform
changeover whereas for big and heavy dies and complex
setup operations parallel operation option (specialized
changeover teams) should be used.
After macro and micro method optimization (that was
depicted in Fig. 5) is completed, documentation of the
optimal operator / changeover team member motions can
be prepared by using MTM systems to create standard
procedures. At this point it should be noted that there are
different MTM systems (MTM-1, MTM-M, UAS etc.).
These systems are different from each other depending on
the complexity of the system. Choosing the most
appropriate MTM system for changeover operations is an
important issue. The matrix in Table 1 is prepared by MTM
Association and shows the decision criteria for choosing
the most appropriate MTM system.
Order information shows the level of detail of order
operations. At the 5th level, the operator is given the most
detailed operation information (basic motions, reach, grasp,
and move). At the 4th level the level of detail become less.
Information at this level shows basic motion sequence (get,
place). The following level includes information of
operations elements (screwing, rotating a crank). The
2nd and 1st level have less detail. Whole chase assembly
can be given as an example for part order.
On the second column workflow levels are given.
Changeover operations take a longer time than most of the
basic production operations. So these operations are long
cycle operations. On the third column material organization
classes are given. During setup operation required equipment must be prepared before the setup activity starts (third
level). On the last column work place classification is
given.
MTM-UAS systems simplify the analysis by reducing
the information level required. This system uses 7 basic
motions and 3 distance units and provides the precise
standard times with a variation of 5 percent.
6 Case study
6.1 PHASE 0 (INITIAL PHASE): Problem definition
& analysis
On the way to the optimal standardized changeover procedure it was vital to choose the correct company. We were
looking for production environments in which set-up
operations constitute an important part of the production
operations. It should be noted that changeover frequency
defined our industry choosing criteria as it affects the method
degree. So, high changeover frequency provides an available
environment for high specialization and high level of method
degree. It is clear that in heavy industries dies are used to
form thick materials and damage frequently. So it was
decided to find an industry, which uses thick materials in its
production processes. As a consequence ABC Company,
which manufactures rims for lorries and midi trucks was
chosen for study. ABC Company has a capacity of 1.2
million rims per year and has a large customer portfolio.
Product types depend on rim dimension (57 different rim
sizes), tire dimension (112 different sizes), number of holes
for lug wrench (5, 6, 8, 10), lug types and sizes, weight
(7.9 kg to 81 kg), internal/external offset sizes and max
340
341
Fig. 7 Changeover Steps Pie
Chart
Fig. 8 New stopper stud design for the ease of centering process
342
Fig. 10 Centering mechanism
and die using frequencies.
a) Density of use for each
centering mechanism. b) Density of use for each dies
343
die height and clamping devices eliminates unnecessary motions during internal setup. So it would be easy
to analyze by MTM and document as a standard
procedure.
6.4 Phase 2: Micro optimization and standard
procedure documentation
In the second phase of the study microanalysis of BPD
changeover team for internal setup is performed. In this
phase the improvements developed in the first phase are
used as inputs and these improvements simplify the
microanalysis and facilitate standardization of the body
motions during internal setup using MTM codes. The
actions taken by microanalysis are as follows:
1. Microanalysis for each setter was performed separately. In order to facilitate the body motions during
internal setup, two portable holders containing required equipment located on the two side of the
machine as in Fig. 12.
External or internal
2
3
4
5
6
7
8
Before BPD machine is shut down for setup, centering mechanism changers is going to prepare
the spare die and centering mechanism for the next product on the worksheet for BPD machine.
(Converting internal setup to external setup)
Before BPD machine is shut down for setup, forklift is going to carry the die, which was prepared
by centering mechanism changers, and put it nearby the BPD.
Before BPD machine is shut down for setup, all equipments that are required for setup will be ready
on portable holder near the operator.
After the last product is produced, the machine will be shut down and two operators will dismount
the die on the machine.
The die on the machine is going to be removed and put near the machine and the new die which
was prepared and located near the BPD machine before will be placed on the machine by forklift.
Two operators will mount the new die.
BPD machine will be set depends on the mathematical values of important factors that
was derived by experimental design and will be started.
After BPD machine starts, removed die will be transported to die center.
E
E
I
I
I
I
E
344
Table 3 MTM-UAS analysis of a die fastening operation
Code
TMU
Frequency
AE3
AE1
ZB1
HB2
ZA2
ZC2
ZD
PB1
ZA2
ZC2
ZD
TOTAL
70
30
10
60
15
45
20
20
15
45
20
1
1
2
1
1
2
1
1
1
2
1
Total TMU
70
30
20
60
15
90
20
20
15
90
20
450
7 Conclusion
Up to now many companies have implemented SMED
methodology to their production systems and obtained
successful results. By reducing the setup time, companies
become more flexible. Smaller batch sizes and higher
product variations provide companies the ability of quick
reaction to the customers wants. Also SMED solves the
bottleneck problem by reducing the setup time of bottleneck workstation.
Successful implementation of new production methods
requires sustainability and permanent solutions. The key of
sustainability is the standardization of that optimal solution.
References
1. Spann MS, Adams M, Rahman M, Czarnecki H, Schroer BJ
(1999) Transferring lean manufacturing to small manufacturers:
The role of NIST-MEP. University of Alabama in Huntsville
2. Shingo S (1985) A revolution in manufacturing, the SMED
system. Productivity Press, University Park, IL
3. Eti MC, Ogaji SOT, Robert SD (2004) Implementing total
productive maintenance in Nigerian manufacturing industries.
Appl Energy 79:385401
4. Chand G, Shirvani B (2000) Implementation of TPM in cellular
manufacture. J Mater Process Technol 103:149154
5. Sun H, Yam R, Wai-Keung NG (2003) The implementation and
evaluation of total productive maintenance (TPM)an action
case study in a Hong Kong manufacturing company. Int J Adv
Manuf Technol 22:224228
6. Prado JC (2001) Beyond quality circles and improvement
teams. Total Qual Manage 12(6):789798
7. Bamber L, Dale BG (2000) Lean production: A study of
application in a traditional manufacturing environment. ProdnPlan
Control 11(3):291298
8. McAdam R, McGeough F (2000) Implementing total productive
maintenance in multi-union manufacturing organizations: Overcoming job demarcation. Total Qual Manage 11(2):187197
9. Gilmore M, Smith DJ (1996) Set-up reduction in pharmaceutical manufacturing: an action research study. Int J Oper Prod
Manage 16(3):417
10. Moxham C, Greatbanks R (2001) Prerequisites for the
implementation of the SMED methodology: A study in a
textile processing environment. Int J Qual Reliab Manage 18
(4):404414
11. McIntosh R, Culley S, Gest G, Mileham T, Owen G (1996) An
assessment of the role of design in the improvement of changeover
performance. Int J Oper Prod Manage 16(9):522
12. Van Goubergen D, Van Landeghem H (2002) Rules for
integrating fast changeover capabilities into new equipment
design. Robot Comput Integr Manuf 18:205214
13. Mileham AR, Culley SJ, Owen GW, McIntosh RI (1999) Rapid
changeover- a pre-requisite for responsive manufacture. Int J
Prod Manage 19(8):785796
14. Patel S, Shaw P, Dale BG (2001) Set-up time reduction and
mistake proofing methods: A study of application in a small
company. Bus Process Manage J 7(1):6575
15. Niebel BW, Freivalds A (2003) Methods, standards, and work
design. McGraw-Hill, New York
16. MTM-UAS (1995) Instructor manual. German MTM Association