Professional Documents
Culture Documents
03
MASS & ENERGY BALANCES
Dr. Abdulhadi Al-Juhani
Department of Chemical Engineering,
King Fahd University of Petroleum & Minerals
3-12-07
Terminal Objective:
upon completion of this module, you will be able to
calculate:
-
Enabling Objectives:
In order to achieve the terminal objective, you will be able to:
1.
2.
3.
4.
5.
6.
Figure 1:
The difference between PFD and PID, and the use of each
Figure 2:
Figure 3:
10
11
Figure 4:
13
14
PFD Information
Figure 5:
16
17
PID/PFD Data
B/CD = B/SD x 0.9
SpGr60 = 141.5 / (131.5 + API) ..............(1)
18
Exercise 1
for each stream entering or leaving the attached figure, calculate the
following:
-
sp. gr. @ 60 oF
Ib/hr
Gpm @ actual conditions
19
20
Exercise 1 (contd)
Answer:
Stream
Feed
OVHD
API
77
118.5
68.8
68.8
SpGr60
(eq 1)
B/SD
0.679
0.566
0.706
0.706
32, 110
6, 308
9, 742
16, 060
317, 956
52, 067
0.57
0.54
0.69
0.69
1116
193
291
479
Ib/hr
(eq 2)
Given
SpGr
Gpm
(eq 3)
21
Example Problem 1:
Calculate the amount of fuel required for the boiler in fig 6. Then,
calculate the furnace efficiency
23
Answer:
The following enthalpy data are available:
Stream
T (oF)
P (psia)
174.7
HL
(Btu/Ib)
343.5
HV
(Btu/Ib)
1196.4
Blowdown
370
Steam
434
154.7
--
1237.6
Feedwater
190
214.7
158.0
-24
=
=
Heat Out
1, 032.34
QA = 888.56 MBtu/hr
25
=
=
=
=
=
=
888.56 x 106
Net Fuel =
16,450
Gross fuel = 1.02 x 54,016
= 54,016 lb/hr
= 55,096 lb/hr
LHV efficiency =
888.56 x 106
6
1, 068.9 x 10
x 100 = 83.1%
26
100 + Q L
27
Exercise 2
Calculate the fuel and Feedwater required for the boiler in fig 15.
How can the furnace efficiency be improved. Use 2% for heat
losses, and use 10% blowdown.
The following enthalpy data are available:
Stream
T (oF)
P (psia)
633
HL
(Btu/Ib)
478.5
HV
(Btu/Ib)
1203.1
Blowdown
492
Steam
700
600
--
1351.8
Feedwater
180
--
148.0
-28
29
Exercise 2 (contd)
Answer:
Feedwater rate
Blowdown
Steam product
=
=
=
F
0.1 F
250, 000
F = 250,000 + 0.1 F
F
Blowdown
30
Exercise 2 (contd)
Heat Balance: Water side/Process
Heat In:Feedwater = (277, 778 Ib/hr) (148 Btu/Ib) = 41.11 MBtu/hr
heat absorbed
=
QA
Total
= 41.11 + QA
Heat Out: Steam
=
Blowdown =
Total
Heat In
41.11 + QA
=
=
Heat Out
351.24
QA = 310.13 MBtu/hr
31
Exercise 2, Contd
Heat in = Heat out 41.11 + QA = 351.24
Heat absorbed
QA = 351.24 - 41.11 = 310.13 MBtu/hr
Heat loss (Given)
= 2%
Fuel LHV (Given)
= 19,400
Heat available
Net fuel
Gross fuel
Heat fired
LVH efficiency =
310.13x10 6
6
x 100 = 84.5%
366.93x10
Shortcut efficiency assuming the atmospheric air temperature is 100F:
Efficiency= [100 -(0.0237 + 0.000189 EA)(TST - TA )][100/(100 + QL)]
= [100 -(0.0237 + 0.000189)(20))(600 - 100)][100/(100 + 2)]
= [(100 - 13.74)][0.9804] = 84.5%
ChE 101.03 V (26)
32
Exercise 2, Contd
To Increase Efficiency:
Lower stack temperature.
- Add more surface to convection section and increase
boiler feedwater preheat.
- Add more surface to convection section and preheat
another process stream. A 50F reduction in stack
temperature would increase efficiency from 84.5% to 85.9%.
Reduce blowdown rate.
- If boiler feedwater quality allows, the blowdown rate can be
reduced.
- Reduction of blowdown from 10% to 2% would not increase
the efficiency, but would directly reduce fuel use by
decreasing the process heat absorbed.
Reduce percent excess air.
- A reduction of excess air from 20% to 10% increases
efficiency from 84.5% to 85.4%.
ChE 101.03 V (27)
33
Exercise 2, Contd
Furnace Fuel Savings
Case
Base
Lower
Stack Temp.
Percent blowdown
10
10
10
310.13
310.13
302.63
310.13
Stack temperature, F
600
550
600
600
20
20
20
10
Furnace efficiency,
percent
84.5
85.91
84.52
85.40
Base
1.62
2.42
1.04
Heat absorbed,
MBtu/hr
Reduce
Reduce
Blowdown Excess Air
34
Exercise 2, Contd
Calculation for efficiency Improvement:
Case
Heat in
277,778 x 148 =
1
Base
2
Lower
St ack Temp.
41.11
41.11
3
R educe
B lowdown
255,102 x 148
4
R educe %
Excess A ir
= 37.76
41.11
Heat out
13.29
337.95
351.24
351.24
340.39
351.24
Heat absorbed
St ack
Percent excess air
Heat loss
Fuel LHV
Heat avail.*
310.13
600
20
2%
19,400
16,725
310.13
550
20
2%
19,400
17,000
302.63
600
20
2%
19,400
16,725
310.13
600
10
2%
19,400
16,900
Net fuel
Gross fuel
Heat fired
18,543
18,914
366.93
18,243
18,608
360.99
18,095
18,457
358.06
18,351
18,718
363.13
84.52
85.91
84.52
85.40
Fuel savings
Base
1.62%
2.41%
1.04%
27,778 x 478.5 =
250,000 x 1,351.8 =
5,102 x 478.5
= 2.44
250,000 x 1,351.8 = 337.95
*Maxwell p. 185
ChE 101.03 V (29)
35
Hot
Cold
36
Example Problem 2
The hot stream is to
be cooled to 300F.
Hot
300F
H = 258 Btu/lb
500,000 lb/hr
500F
H = 410 Btu/lb
Cold
10,000 lb/hr
200F
API = 70
VABP = 210F
CP+B
0.677
0.736
0.794
B
0.08
0.08
0.08
CP
0.597
0.656
0.714
37
Avg CP = 0.597
Q = mCPT
TOUT =
Q
+ 200
mC P
T = (TOUT - 200)
76 x 10 6
+ 200 = 12, 930F
10, 000 x 0.597
38
TX
TX
Cold
200F
39
190,000 380 TX
= 5.97 TX 1194
191,194
TX
= 385.97 TX
= 495.4
40
= 0.85
0.597 + 0.77
2
= 0.6835
CP
CP = 0.77
41
We want to heat integrate a lean oil and feed stream in exercise 1, where it is
proposed to use exchanger E6 to replace E1 in exercise 1 to provide preheat for
the debutanizer feed
42
E-2
Lean
Oil
D-1 115F
143F
148 psig
148 psig
P-1
T-1
Debutanizer
Overhead
6,308 B/SD
118.5API
100F
sp. gr. = 0.54
E-6
258F
H=99.270
H=103.270
6
x10 Btu/hr
154 psig
x10 6
322F
346F
E-4
Btu/hr
E-3
Naphtha Product
9,742 B/SD
130F
E-5
Feed
P-2
E-6
Figure 16
ChE 101.03 V (36)
E-7B
E-7A
Lean Oil
16,060 B/SD
68.8API
100F
sp. gr. = 0.69
43
Find the exit temperature for the lean oil leaving E6 after
preheating the tower feed?
Answer:
E6 Duty:
253 oF to 258 oF
Q = H = 103.277 99.270 = 4.0 MBtu/hr
Q = mCpT
m = 165, 284 Ib/hr (from exercise 1)
44
= (346 TOUT ) =
TOUT
CP
= 346
310.5
100
TOUT
= 346 - 36 = 310F
Rate from
Exercise 1
0.681
0.658
0.524
45
= 0.66
Avg CP
0.524
46
CP, Btu/lbF
346
0.681
100
0.524
47
310F
120F
100F
95F
48
Example Problem 3
Consider a 6 in. nominal size, Schedule 40, Grade B steel pipe filled
with oil. The pipeline is unrestrained and above ground. The
ambient temperature is 100 F. The line is blocked-in at 110 F and
150 psi. What is the maximum temperature the line will reach?
50
Do = 6.625/12 = 0.552
assume a max. T of 160 F for the 1st trial:
Tp = 160 + 460 = 620 R
Ta = 100 + 460 = 560 R
QC / L = 0.844(Do)0.75 (Tp Ta)1.25
= 0.844(0.552)0.75 (620 560)1.25 = 90.25 Btu/hr/ft
QR / L = 0.246 Do [(Tp/100)4 (Ta/100)4]
= 0.246 (0.552) [(620/100)4 (560/100)4] = 67.1 Btu/hr/ft
total heat loss: QT/L = QC/L + QR/L
= 90.25 + 67.1 = 157.4 Btu/hr/ft
51
QS / L = 300 (Do L) / L
= 300 (0.552) = 165.6 Btu/hr/ft
Tp (oF)
QC / L
(Btu/hr/ft)
QR / L
(Btu/hr/ft)
QT / L
QS / L
(Btu/hr/ft) (Btu/hr/ft)
160
90.25
67.1
157.4
165.6
163
95.9
71.0
166.9
165.6
52
Temperatures, F
Air = 50 Sky = -50
Qc /L
Qt /L
Btu/hr ft
Btu/hr ft
1409.6
2150.8
1293.1
1975.5
1178.7
1805.0
1066.5
1639.3
956.6
1478.3
849.1
1322.2
744.4
1171.1
642.4
1025.2
543.7
884.6
448.4
749.5
357.0
620.4
270.1
497.8
188.5
382.3
113.6
275.4
47.8
179.3
0.0
103.0
-47.8
28.3
Q = m C p t
L (Q T /L )Ave = Q
L=
m C p t
(Q T /L) Ave
Wind, mph
Flow, lb/hr
5
50,000
Cp
Length
Cum.
Pipe
Btu/lb F
ft
Length, ft
Temp, R
0.5
121.2
121.2
660
0.5
132.3
253.4
650
0.5
145.2
398.6
640
0.5
160.4
559.0
630
0.5
178.5
737.5
620
0.5
200.5
938.1
610
0.5
227.7
1165.7
600
0.5
261.8
1427.5
590
0.5
306.0
1733.5
580
0.5
365.0
2098.5
570
0.5
447.2
2545.6
560
0.5
568.1
3113.8
550
0.5
760.2
3874.0
540
0.5
1099.8
4973.8
530
0.5
1771.6
6745.4
520
0.5
3809.8
10555.1
510
0.5
500
( Q T /L)1 + (Q T /L) 2
for line 1
(Q T /L) Ave =
2
2150.8 +1975.5
= 2063.2
2
( 50,000)(0.5 )(10 )
2063.2
=121.2
Figure 7
ChE 101.03 V (46)
Figure 7:
53
1.
CP+B
CP
200
0.51
0.025
0.485
Inlet CP
= Ave CP = 0.485
= QLOSS = m CP
TOUT
= T - T = 200 - 58 = 142F
5.664 x 10 6
= 58F
200, 000 x 0.485
55
CP+B
CP
142
0.485
0.025
0.460
TOUT
= 200 - 60 = 140F
Check Q.
Q
56
Qr /L
Btu/hr ft
741.2
682.4
626.3
572.8
521.7
473.1
426.8
382.7
340.9
301.1
263.4
Temperatures, F
Air = 50 Sky = -50
Qc /L
Btu/hr ft
1409.6
1293.1
1178.7
1066.5
956.6
849.1
744.4
642.4
543.7
448.4
357.0
Qt /L
Btu/hr ft
2150.8
1975.5
1805.0
1639.3
1478.3
1322.2
1171.1
1025.2
884.6
749.5
620.4
Wind, mph
5
Cp
Btu/lb F
0.485
0.480
0.476
0.469
0.467
0.462
0.458
0.454
0.450
0.446
0.442
Length
ft
467.7
759.7
825.1
901.4
997.0
1108.5
1247.5
1422.2
1647.4
1947.5
Flow, lb/hr
200,000
Cum.
Length, ft
467.7
1227.4
2052.5
2953.9
3950.9
5059.4
6307.0
7729.1
9376.6
11324.1
Pipe
Temp, R
660
650
640
630
620
610
600
590
580
570
560
57
58
2nd Trial
192F
652R
100
100
4
4
1848.8 Btu/hr/ft
= 0.246(10) 647 - 570 = 1, 714.0 Btu/hr/ft
100
100
59