Professional Documents
Culture Documents
COST
March/April 2015
ENGINEERING
SOFT SKILLS
PROJECT CONTROLS
CALCULATING THE
AS-BUILT
CRITICAL PATH
TRENDS IN
CONSTRUCTION
CLAIMS AND
DISPUTES
www.aacei.org
CONTENTS
COST ENGINEERING
TECHNICALARTICLES
4Soft Skills are Vital for
Effective Project Controls
Christopher W. Carson, CEP DRMP PSP FAACE and Patrick Kelly, PSP
ALSOFEATURED
2
2
11
38
38
41
41
42
44
COSTENGINEERINGMARCH/APRIL 2015
AACE INTERNATIONAL
BOARD OF DIRECTORS
PRESIDENT
MartinDarley,FRICSCCP
713.372.2426/president@aacei.org
PRESIDENT-ELECT
CONTENTS
COST ENGINEERING
Established1958
Vol.57,No.2/March/April2015
JulieK.Owen,CCPPSP
213.922.7313/preselect@aacei.org
Managing Editor
PA ST PRESIDENT
MarvinGelhausen
mgelhausen@aacei.org
JohnJ.Ciccarelli,PECCPPSP
609.497.2285/pastpres@aacei.org
Art Director
VICE PRESIDENT-ADMINISTRATION
NoahKinderknecht
nkinderknecht@aacei.org
NicholasKellar,CCPEVPPSP
907.830.5217/vpadmin@aacei.org
Advertising Sales
GarthLeech
304.296.8444fax-304.291.5728
gleech@aacei.org
VICE PRESIDENT-FINANCE
JosephW.Wallwork,PECCPCFCCPSP
516.477.7383/vpfinance@aacei.org
HEADQUARTERS
DanMelamed,CCPEVP
202.586.6239/vptechboard@aacei.org
1265SuncrestTowneCentreDr
Morgantown,WV26505-1876
800.858.COSTfax-304.291.5728
OURVISION-Tobetherecognizedtechnicalauthorityincostandschedulemanagement
forprograms,projects,products,assets,andservices.
DIRECTOR-REGION 1
CindyL.Hands,CCP
403.383.7374/dirregion1@aacei.org
DIRECTOR-REGION 2
CalvinJ.Speight,Jr.,CCP
703.254.9538/dirregion2@aacei.org
DIRECTOR-REGION 3
MarkG.Cundiff,PSP
770.315.0486/dirregion3@aacei.org
DIRECTOR-REGION 4
JaquelineT.Doyle,PEPSP
630.613.7170/dirregion4@aacei.org
DIRECTOR-REGION 5
DavidA.Norfleet,CCPCFCCDRMP
303.932.7450/dirregion5@aacei.org
DIRECTOR-REGION 6
JohnL.Haynes,PSP
925.570.4647/dirregion6@aacei.org
DIRECTOR-REGION 7
MohammedRafiuddin,CCPPSP
+966.13.8079303/dirregion7@aacei.org
DIRECTOR-REGION 8
GhulamMujtabaShaikh,PEPMP
1818.74592101/dirregion8@aacei.org
DIRECTOR-REGION 9
OURMISSION-ThemembersofAACE enableorganizationsaroundtheworldtoachieve
thierinvestmentexpectationsbymanagingandcontrollingprojects,programs,andportfolios;wecreatevaluebyadvancingtechnicalknowledgeandprofessionaldevelopment.
Cost Engineering (ISSN:0274-9696/15)ispublishedbi-monthlybyAACEInternational,Inc,1265SuncrestTowneCentreDr,
Morgantown,WV26505USA.PeriodicalspostagepaidatMorgantown,WV,andatadditionalmailingoffice.POSTMASTER:
Send address changes to AACE International; 1265 Suncrest Towne Centre Dr, Morgantown, WV 26505-1876 USA. Customer #7012359 (APC), Publications Mail Agreement No 40624074, Return undeliverable Canadian addresses to PO Box
503, RPO West Beaver Creek, Richmond Hill, ON L4B 4R6. Copyright2014byAACEInternational,Inc.Allrightsreserved.
Thispublicationoranypartthereofmaynotbereproducedinanyformwithoutwrittenpermissionfromthepublisher.
AACEassumesnoresponsibilityforstatementsandopinionsadvancedbythecontributorstoitspublications.ViewsexpressedbythemortheeditordonotnecessarilyrepresenttheofficialpositionofCost Engineering,itsstaff,orAACEInternational,Inc.Printed in York, PA, USA. Cost Engineering isarefereedjournal.Alltechnicalarticlesaresubjecttoareview
bytheAACEInternationalCostEngineeringJournalReviewCommittee.AbstractsareonlyacceptedinourannualAACE
CallforPapersforourAnnualMeetingandITCMConference.AcceptedabstractsmustbefollowedupwithafullapprovedmanuscriptthatispresentedandattendeeevaluatedatoneoftheAACEAnnualMeetingsorITCMConferences.
TopratedmanuscriptswillbeconsideredforpublicationintheCEjournal.Anyunsolicitedabstractsreceivedatothertimes
throughoutayearwillreceivee-mailnoticetosubmitinournextCallforPapers.PHOTOCOPY PERMISSION:Authorizationtophotocopyarticleshereinforinternalorpersonaluse,ortheinternalorpersonaluseofspecificclients,isgranted
byAACEInternational,Inc.,providedthatthebasefeeofUS$4.00ispaiddirectlytoCopyrightClearanceCenter,222RosewoodDrive,Danvers,MA01923USA.Telephone:978.750.8400.ForthoseorganizationsthathavebeengrantedaphotocopylicensebyCCC,aseparatesystemofpaymenthasbeenarranged.Thefeecodeforusersofthetransactionalreporting
serviceisISSN-0274-9696/02US$4.00.PaymentshouldbesentdirectlytoCCC.Copyingforotherthanpersonalorinternal
referenceusewithouttheexpresspermissionofAACEisprohibited.E-mailrequestsforphotocopypermissiononbulkordersmaybesenttoeditor@aacei.org.ADVERTISING COPY: ContactGarthLeech,1265SuncrestTowneCentreDr.,Morgantown,WV26505-1876.Telephone:304.296.8444.E-mail:gleech@aacei.comforrates.Advertisersandadvertisingagencies
assumeliabilityforallcontent(includingtext,representation,andillustrations)ofadvertisementsprintedandalsoassume
responsibilityforanyclaimsarisingtherefrommadeagainstthepublisher.Thepublisherreservestherighttorejectanyadvertisingthatisnotconsideredinkeepingwiththepublicationsmissionandstandards.Thepublisherreservestherightto
placethewordadvertisement withcopywhich,inthepublishersopinion,resembleseditorialmatter.AlladvertisingacceptedforpublicationinCost Engineering islimitedtosubjectsthatdirectlyrelatetothecostmanagementprofession.
Currentratecardavailableonrequest.COST ENGINEERING DEADLINES:SubmissionsforCostEngineeringmustbereceived
atleast8weeksinadvanceoftheissuedate.Sendto:Editor,1265SuncrestTowneCentreDr,Morgantown,WV265051876USA.Deadlinesdonotapplytotechnicalpapers.
GarvanGerardMcCann
+27.11.5188214/dirregion9@aacei.org
DIRECTOR-REGION 10
AldoD.Mattos,CCP
55.11.967973058/dirregion10@aacei.org
EXECUTIVE DIRECTOR
CharityA.Golden
304.296.8444/cgolden@aacei.org
Viewpointsexpressedincolumns,features,andarticlespublishedinCostEngineeringjournalare
solelythoseoftheauthorsanddonotrepresentanofficialpositionofAACEInternational.AACEInternationalisnotendorsingorsponsoringtheauthorswork.Allcontentispresentedsolelyforinformationalpurposes.Columns,features,andarticlesnotdesignatedasTechnicalArticlesarenot
subjecttothepeer-reviewprocess.
TECHNICAL ARTICLE
Communications
o critical (objective) thinking;
o reading and comprehension;
o writing; and,
o succinctness.
Motivation
o motivational leadership;
o networking and relationship
building;
o partnering, teambuilding, and
teamwork; and,
o empathy and tactfulness.
Presentation
o interpretation;
o public speaking; and,
o negotiation and persuasion.
Closing/Resolution
o persistence;
o managing expectations; and,
o mentoring and training.
The plan established for the project is not the only way to accomplish
the scope of work, but rather, it is the
PM teams best plan at the time of the
planning session.
The PC expert needs to have the
ability to elicit the construction plan
from the PM team, facilitate turning it
into a schedule, explain the plan then
modeled by the schedule, analyze the
schedule as production advances,
make recommendations for actions
based on performance, and gain acceptance from all stakeholders that
those recommendations are appropriate and important. This effort makes
use of a variety of soft skills and the
better the PC expert is with those soft
skills, the more likely it is that the team
will work together for the common
goal.
A large part of those abilities center around the ability to take a complex
and highly analytical effort, glean the
vital information from that effort, and
explain it in common sense and simple
language. A good story is more convincing than a pile of technical analysis
printouts. This is probably one of the
greatest weaknesses in a project controls staff, and the place where impressive improvements can be made.
Even in situations when there is a
dispute, such as when the owners
agent can not recommend acceptance
and approval of a contractors schedule, it is soft skills that will settle the
case, not the detailed analysis. As Chris
Carson wrote in his 2012 AACE International Transactions article, The goal is
to use the data to meet with the contractor, convince them to cooperate, fix
the schedules, and convince them that
documentation is a strong rebuttal to
loose/inaccurate claims. It also shows
that the owners analysis process is accurate and convincing. Once convinced, the contractor is more likely to
provide approvable schedules, and to
accept the reasonableness of the suggested settlement [4].
The stakeholders on the project
will be many different types of people
with varying degrees of technical skills,
however, none of them will likely have
the level of understanding of project
the exercise and development of empathy. Empathy can be uniquely challenging to those who have solely
studied analytical subjects through
their schooling. Lets face it, not many
project controls professionals are coming from liberal arts colleges or acting
schools these days. While the focus in
our field and its continuing education
seems to be technical enhancement
and certification progression, the
rounding of ones ability to empathize
should be a treated as important to the
progression of the career of the project
control professional as any analysis
technique.
Technical Nature of the Role
A large part of the problem with
failure to develop vital soft skills in project controls professionals is the nature
of the role; highly technical and analytical. This attracts engineers and analytical people, who often do not have the
natural soft skills. In addition, the profession places maximum priority on
those technical skills, with requirements for understanding the methodologies and software support for those
roles, and very little priority on the soft
side of the skills. In a world of complex
calculations, complicated software,
and a lack of appreciation for the precision of the data, it is easy to drop into
that technical world. But, if no one understands the issues but the experts,
they will not be resolved. Just as in a
dispute, it is the expert who can condense the complicated and detailed
data that was analyzed into a single
slide that will prove his or her case.
Need for Development of Relationships
Often, PC professionals do not see
any need to develop intra-project relationships, when that is really vital to
performing the task effectively. Relationship building involves development
of trust from daily interactions, but beyond that, it requires some effort to interact with the other stakeholders. This
is why the communications plan is so
important, it can help identify which
stakeholders the PC team needs to engage and how frequently. Done correctly, the relationships which are built
nication skills, the first step is in thinking, ensuring that critical thinking is
prevalent. Critical thinking is objective
review of issues, ideas, arguments,
data, opinions, and allows the PC practitioner to look at these things without
any preconceived notions. This is a vital
step since it lowers the barriers to the
exchange of information that is a daily
task for this role. A critical thinker will
listen without judging and gain a better
understanding of the situation or the
data transmitted from another team
member or stakeholder. This includes a
fair assessment of information provided by the contractor when working
for an owners CM, or a fair assessment
of the owners position when working
for a contractor.
The ability to read a multitude of
documents and information channels
and understand the data included, with
no deviation from the original data, is
absolutely necessary for this role. This
comprehension often does not come
easily to professionals, but it is a skill
that has to be developed. This is the
difference between knowledge and
evaluation in the commonly called
Blooms Taxonomy of Educational Objectives; knowledge is just hearing and
learning facts and data, whereas evaluation includes grasping the meaning
of the facts and data, analyzing the
data, and evaluating the data objectively [3]. As the project controls professional becomes more and more
competent, the professional should be
using higher levels of critical thinking;
moving through the levels; knowledge,
comprehension, application, analysis,
synthesis (or evaluation by the revised
taxonomy), and evaluation (or creating
by the revised taxonomy).
The last soft skills in this category
include writing clearly but equally as
important, the ability to write succinctly, reducing the data to the pertinent issues. Often reports and
communications are so riddled with
technical information that it takes another highly technical professional to
understand. This is a huge risk and a
true PC professional must gain the soft
skills to bridge this concern.
When the soft skills are missing or
limited, reports tend to delve into spe-
extraversion or introversion;
sensing or intuition;
thinking or feeling; and,
judging or perceiving.
10
3.
Conclusion
Ignoring the soft skills that are so
vital to performing a project controls
function will quickly cause failure in a
number of areas. In addition to learning how to estimate, how to analyze
risk, how to schedule a project, it is imperative that PC staff learn and gain expertise in these soft skills. No matter
how technically proficient the project
controls analysis is, the inability to
communicate it phonetically and empathetically to the client will ultimately
doom the analysis to failure.
Knowing your strengths and weaknesses, from a personality perspective,
and rounding out that side will push
you to being an effective project controls consultant, just as much as learning the latest analysis technique or
mastering the latest revision to an
AACE recommended practice. Identifying your client, knowing their motivations, building consensus, producing
the analysis and communicating that
analysis will serve to make your client
appreciate your value as a project controls consultant. Soft skills are an integral part of that communication that
should not be ignored.
REFERENCES
1.
2.
4.
5.
6.
7.
8.
9.
11
Some Universities
OPEN DOORS.
We Chart New Courses.
T
he MS in P
roject Management pr
WSB blends the
ogram a
The
Project
program
att the G
GWSB
study of advanced pr
al
oject management techniques with gener
project
general
management principles.
T
he innova
tive, ethics-infused curriculum balances rreal-world
actice
eal-world pr
The
innovative,
practice
and academic theory
ate
ory
y,, developing the skills managers need to integr
theory,
integrate
comple
x pr
ojects, motiva
te people, and achieve
chieve cost-ef
ffective
fective rresults.
esults.
complex
projects,
motivate
cost-effective
L
Learn
earn on campus in W
Washington,
ashington,
DC, or wher
wherever
ever it
its
s convenient
for you.
T
The
he fle
flexibility
xibility of our pr
program
ogram allows you
to cr
create
eate a course of study tha
thatt work
workss with
your schedule. Our online and on-campus
courses shar
share
professors,
e the same pr
ofessors,
lectures,
projects
lectur
es, pr
ojects and assignments, and
university rresources.
esources.
The
degree
T
he MSPM degr
ee may be completed:
On campus
Entirely
Entirely online
online
study from
from any location
location
A highly specialized pr
program
ogram
applicable to all industries.
ovide
Rigorous
Rigorous projects
projects that
that pr
provide
exposure
exposure to all aspects of
project
project management
Unique, disciplineindependent curriculum
Courses
thatt immerse you
C
ourses tha
teamwork
team
in te
amwork and te
am dynamics,
developing the sskills
kills tto
o ttackle
ackle
complex
projects
and
comple
x pr
ojects a
nd synthesize
diverse perspectives
MASTER
MAS
TER OF SCIENCE
PROJECT
IN PRO
JECT
MANAGEMENT
MANA
GEMENT
(MSPM)
Innova
Innovative
tive curriculum goes
beyond the PMBOK Guide
to deliver the skills you need
to integr
integrate
ate comple
complex
x pr
projects,
ojects,
motiva
motivate
te people and achieve
cost-ef
cost-effective
ffective
fec
rresultsfrom
esultsfrom
projects to billion$10,000 projects
programs.
dollar programs.
Innovative
that
Innovative curriculum that
can be applied to any industry
World-class
World-class faculty with
deep expertise
international
experrtise in interna
tional
methodologies, advanced
project
project management
applica
applications,
tions, decision
sciences and
and management
management
Application
Deadline:
TECHNICAL ARTICLE
Calculating the
13
14
tical, change the long negative FS relationship to a short positive finish-to-finish (FF) relationship, as shown in figure
2.
Guideline 3If the as-built date conditions produced a long SS relationship
and the as-built conditions allow for a
reasonable and shorter FS relationship,
then, where practical, change the long
SS relationship to a short FS relationship. For example, a SS +35 day relationship between two activities in the
as-built condition could be changed to
a FS +10 day relationship between the
same predecessor and successor activities, as shown in figure 3, example A.
In other cases, a short negative FS lag
may be more realistic for modeling actual work sequences than a long SS lag,
as shown in figure 3, example B.
Guideline 4If the as-built date conditions produced a long FF relationship
and allow for a reasonable FS tie, then,
where practical, change the FF relationship to a FS relationship. For example,
a FF +55 day relationship between two
activities in the as-built condition could
15
16
the entire project duration to better account for how the critical path changed
over time. The purpose of the as-built
calculation schedule is to calculate the
as-built critical and near-critical paths
and as-built float values. The selection
of the schedule analysis windows is
typically based on the availability of the
schedule updates, key contractual
events and issues, changes in the critical path, and cost and time considerations.
In commonly used scheduling software, such as Primavera, actual dates
override the schedule logic and the actual start and finish dates of activities
become fixed regardless of the logic
when actual dates are input to record
as-built progress. Therefore, the asbuilt critical path and float values,
which can only be determined from the
schedule logic, are not provided by the
software calculations for the work that
and finish dates. The removal of the actual dates is referred to as destatusing
the schedule.
17
19
Table 1 Actual Date Conditions and Corresponding Actions for Destatusing Schedule Activities
20
If using Primavera scheduling software calendar rules, the activity calendar for the predecessor activity should
be used in performing the conversion of
an activity date to a workday number. If
the activity date is an actual start and
falls on a non-workday, then the next
higher workday is used. If the activity
date is an actual finish and the date falls
21
Driving Predecessor
Lag Determinations
To properly create an as-built calculation schedule, it is necessary to determine the driving predecessor
relationships in the as-built schedule
when there are multiple predecessors
to an activity. If a predecessor is not
driving, the actual lag duration should
be reduced to the originally planned
lag value to create float in the as-built
calculation schedule.
The actual lag duration for each relationship within the schedule analysis
window should be calculated but it is
not necessary to apply all of the actual
lags to all relationships in the as-built
calculation schedule. If all lags in the
as-built calculation schedule are converted into the actual lags, the activity
dates in the as-built calculation schedule would be correct but all activities
would have zero total float and the entire schedule network would be on the
as-built critical path.
To determine the driving relationship, the shortest duration variance
between the planned lag and the actual lag for each predecessor to a successor should be calculated. In other
words, it is necessary to identify the
predecessor tie that most probably
caused the successor activity to start or
finish based on the closest predecessor to the successor activity with consideration for planned lag durations. If
the variance between the planned lag
and the actual lag is negative, then the
relationship must become a driving relationship to maintain the correct asbuilt dates in the as-built calculation
schedule. If multiple relationships have
22
When there are multiple predecessor activities to a successor activity, the predecessor with the
smallest variance between the actual lag and the planned lag is
used as the driving predecessor
and all other positive lags for predecessors to the same successor
are reset to the planned lag value
contained in the verified as-built
schedule. The planned lag typically
is the lag value input contemporaneously by the project scheduler,
or may be a lag duration that has
been rectified by the schedule analyst based on documented facts
regarding the reasonable lag duration required between two activities.
If a successor activity has only one
predecessor, then the actual lag
value must be used as the driving
lag value to correctly calculate the
successor activity dates to correspond with the verified as-built
schedule dates.
If two or more predecessors to an
activity are equally driving, meaning that they have equal variances
between the actual lag and
planned lag, then each predecessor should be assigned the required driving lag values such that
they equally drive the successor
activity dates.
All actual negative lags must remain negative to retain the original dates in the verified as-built
schedule.
If a predecessor is not driving,
calculation schedule to the verified asbuilt schedule to ensure that there are
no date variances. If date variances are
found when performing this comparison, it is necessary to identify the date
inconsistencies and document the reasons for any acceptable variances. Date
variances may arise from activities having different calendars or when the asbuilt date falls on a non-work day as
defined by the schedule calendar.
Finally, the calculated critical and
near critical paths from the data date
at the start of the window through
project completion should be checked
for reasonableness. Subsection 4.3.C of
AACE International Recommended
Practice 29R-03, Forensic Schedule
Analysis, discusses questions to consider regarding whether activities on
the as-built critical path are reasonable, including:
Finally, if a delay to any as-built activity would have delayed the overall
project completion date by that same
duration, it is reasonable to conclude
that the activity was on the as-built
critical path.
Conclusion
Calculating the as-built critical
path involves:
4.
RECOMMENDED READING
1.
2.
3.
5.
23
TECHNICAL ARTICLE
Trends in Construction
24
These trends may have been exacerbated by what the construction bar
refers to as the vanishing trial. In regard to this issue, it is noted that
In 1938, about 20% of federal civil cases went to trial. By
1962, the percentage was down to
12%. By 2009, the number has sunk
to 1.7%. The percentage of jury trials in federal civil cases was down
to just under 1%, and the percentage of bench trials was even lower.
So between 1938 and 2009, there
was a decline in the percentage of
civil cases going to trial of over 90%
and the pace of the decline was accelerating toward the end of that
25
3.
4.
5.
6.
26
2006, that case filings with the International Chamber of Commerce (ICC),
the American Arbitration Association
(AAA), and the International Center
for Dispute Resolution (ICDR) have
increased between three and five fold
over the past 25 years [28]. A major
university in the UK documented an
8.5% growth among 22 arbitral institutions between 2003 and 2007 [42].
In preparing this research perspective, the Navigant Construction
Forum conducted a survey of Navigant senior claims consultants in-house
and an e-mail survey of a number of
external claims professionals with national and international claims experience. Juxtaposed to the results of the
studies above, the Forum found that at
least in the US, the numbers of claims
filed with project owners has increased
substantially over the past few years.
However, like the EC Harris study, the
Forums survey determined that the
value of the claims filed has fallen substantially and fewer and fewer claims
are being prosecuted to arbitration or
litigation.
Some of the findings of the
Forums survey related to the conclusions above follow:
Increased Limitations on
Recovery of Damages
Another trend observed by the Navigant Construction Forum is that it is
becoming increasingly difficult for contractors to recover on claims in litigation on government contracts. Courts
seem less likely to rule in favor of contractors in a number of areas. Some
limitations on contractor claim recovery are set forth below.
Concurrent Delay
Concurrent delay is defined as:
[t]wo or more delays that take place
or overlap during the same period, either of which occurring alone would
have affected the ultimate completion
date [19]. Concurrent delay has been
a contentious and hotly debated issue
since its creation in 1867 [56]. One in
depth article on the issue of concurrent delay examined the origins of the
doctrine of concurrent delay. The authors summarized the history of concurrent delay as follows:
it is evident that the modern doctrine of concurrent delay is
premised not on the equitable resolution of construction delays, but
is instead based on past litigants
failure or inability to effectively
prove their cases and the older
courts hostility toward liquidated
damages Over time, these factors merged and evolved into the
legal doctrine of concurrent delay.
27
28
2.
3.
Compensable Delay:
29
Finally, this set of contract documents also states that any claim not in
compliance with these requirements
shall be conclusively deemed to
have been waived by contractor. (Lest
readers conclude that this particular
set of perquisites is unique to this particular state, the author of this research perspective has encountered
similar requirements in many contracts
across the US).
This article goes on to discuss enforcement of notice requirements at
the federal and the state levels. With
respect to enforcement of notices requirement in federal courts, the article
notes five general exceptions to notice
requirements, as follows
30
compensable changes and delay. Redondo filed claims, but before these
claims could be resolved, went into
bankruptcy. The various claims were
tried in Bankruptcy Court, which
awarded some $12 million in damages
to Redondo, plus pre-judgment interest.
On appeal to the Federal District
Court, the District Court affirmed the
damages awarded in all respects. The
Authority appealed this decision to the
First Circuit Court of Appeals. The Appellate Court upheld some of the lower
Courts findings, but focused in on the
issue of home office overhead recovery. Citing C.B.C. Enterprises, Inc. v.
United States [17] and Aniero Concrete
Co. v. N.Y. C. Constr. Auth. [9], the court
concluded that
When a projects completion is delayed because of necessary but unanticipated work for
which the contractor is entitled to
compensation, extended overhead
is usually calculated as a percentage
of the direct costs of the additional
work. This percentage-of-directcost approach comports with standard practice in the construction
industry under which a contractor
normally charges an owner a percentage of a projects direct costs to
cover its overhead.
at least some of the project delays were attributable to
extra work for which the debtor
was compensated. (Citation omitted.) For those delays, extended
overhead should have been
awarded as a percentage of the direct costs associated with the projects change orders and extra work
orders. (Citation omitted.) It is inappropriate to use the Eichleay formula to calculate home office
overhead for contract extensions
because adequate compensation
for overhead expenses may usually
be calculated more precisely using
a fixed percentage formula.
It is true that some federal government agencies use fixed markup rates
in their construction contracts specif-
31
Based upon these cases, contractors seeking recovery under the differing site conditions clause
32
excusable delay).
This same respondent also commented that he had been asked to review two sets of bridging documents
which were approximately 90% complete design (versus the more typical
30% design). The design/build entities
in these cases claim that given this
level of design detail done by the
owners consultant prior to bidding,
the Spearin Doctrine should apply. The
owner, as might be expected, asserted
that since this is a design/build contract the design/builder is solely responsible for the design and the
bridging documents were intended for
general guidance only. Strictly speaking, this is not risk transfer but has the
effect of substantially increasing the
design/builders risk if the owner holds
the design/build entity to the requirements of the bridging documents as if
they
were
crafted
by
the
design/builder.
A very recent Civilian Board of
Contract Appeals (CBCA) case related
to construction of a U.S. embassy
under a design/build contract [35]. According to the CBCA, the design/build
contract transferred all risk under the
contract to the design/build entity by
using clause such as the following:
The contractor remains
solely responsible and liable for design sufficiency and should not depend on reports provided by the
government as part of the contract
documents.
Offerors shall not rely on
any information provided by the
government concerning the host
country, such as climatology data at
the site, local laws and customs,
currency restrictions, taxes, or the
availability of local labor, etc.
With respect to the infrastructure
that was supposed to be available to
the site at the outset of construction,
the board commented that while the
contract documents stated the local
government had committed to provide utilities to the site by June
2003, nothing in these statements
can be construed as a promise from
Increased Use of
False Claim Actions
False claims allegations are becoming much more frequent in construction today than at any time
previously. With the increased emphasis on the False Claims Actsince
1986, contractors who certify a claim
to the US government are potentially
liable to the government if any portion
of a passed through subcontractor
claim is determined to be a false claim
[1]. Subsequent to the Deficit Reduction Act of 2005, some 28 States have
adopted State False Claim Acts and
others apparently are contemplating
doing the same [53, 57]. Not only are
government agencies more likely to
counter contractor claims with allegations of false claims, but the legal profession has become very active in this
arena also. If one Googles whistleblower attorneys, youll find some
2.95 million hits in 0.22 seconds most
of which advertise firms ready, willing,
and able to assist potential whistleblowers with qui tam lawsuits under
the False Claims Act (FCA).
Added to this are some recent
33
come to light earlier in the performance of its work. However, appellant would have us decide that the
governments alleged failure to perform an early adequate inspection
shifts the contract performance issues to the governments shoulders. This we cannot do. The
contract clauses and the relevant
law clearly establish that it was appellants legal responsibility to
maintain an adequate inspection
system to ensure that its work conformed to the contract requirements. The government proved
that appellant was in default and
appellant did not establish that the
default was excusable.
Tawazuh, like Amigo before it, lost
their argument that owner underinspection entitled them to additional
money and time to repair the substandard work, and/or excused the substandard work and deprived the owner
of the right to terminate for default.
However, the Navigant Construction
Forum believes it foreseeable that as
less experienced, less skilled contractors undertake to perform more complex projects, this type of claim will
occur more frequently.
Equipment Productivity Loss
Lost labor productivity claims in US
construction law are hardly new. Wunderlich Contracting Co. v. United States
involved a request for delay damages
and lost labor productivity arising from
contract issued in 1950 and completed
in 1951 [12]. Although the Wunderlich
joint venture did not prevail in this
case, their failure to recover was based
on lack of causation that is, they did
not establish the nexus between the
governments actions and the damages
sought not because the court rejected their theory of entitlement.
However, the Navigant Construction Forum survey revealed that
some contractors have started to assert
34
ents, etc.).
The contractor has not proven entitlement to any of these allegations under the contract.
The contractor has not expended
any additional costs as a result of
any of these allegations. And,
There is not yet any cause and effect relationship between any of
the potential future problems the
contractor anticipates and the cost
the contractor is presently seeking.
Recommendations
Claimsmanship has not declined
over the past two decades and is projected to continue based upon this review of current trends. Based on
perception, the Navigant Construction
Forum offers the following recommendations for all stakeholders in the
construction industry.
For Owners
35
For Contractors
36
winnable. And,
Contractors trying out a new theory of entitlement on a public
works project must obtain legal
advice from attorneys familiar
with both US federal and State
False Claims Acts, in order to avoid
counterclaims of false claims from
the owner.
Conclusion
Owners and contractors seeking to
practice claimsmanship need to keep in
mind a paraphrase of one of Sir Arthur
Conan Doyles Sherlock Holmes quotations
What one man can invent,
another can circumvent!
At a time when owners and contractors say they want to discourage
disputes on construction projects and
find ways to deliver projects on time, in
budget, safely and with the required
quality by the contract, claimsmanship
seems counterproductive and wasteful. The recommendations set forth
above should help stakeholders
achieve their stated goals.
REFERENCES
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
31 U.S.C. 3729(a).
41 U.S.C. 605.
62 Fed. Cl. 84 (2004).
64 Fed. Cl. 229, February 23, 2005.
65 Fed. Cl. 264 (2005).
73 Fed. Cl. 47 (2006), affd 557 F.3d
1332 (Fed. Cir. 2009), cert. denied
130 S.Ct. 490 (2009).
79 F.3d 1129, 1132 (Fed. Cir. 1996).
199 Cal. App. 4th 1107 (2011), 132
Cal. Rptr. M3d, 170 Court of Appeal, Fifth District, California (Oct.
6, 2011).
307 F. Supp. 2d 164, 209 (S.D.N.Y.
2003).
324 F.3d 1364, 1370 (Fed. Cir.
2003).
331 F.3d 878, 882 (Fed. Cir. 2003).
351 F.2d 956 (Ct. Cl.1965).
393 F.3d 1321 (2005).
401 F.2d 1012, 1016 (Ct. Cl. 1968).
609 F.3d (Fed. Cir. June 17, 2010).
609 F.3d 1323 (Fed. Cir. June 17,
2010).
1144872.
36. Galanter, Marc and Angela
Frozena, A Grin Without A Cat:
Civil Trials in the Federal Courts,
2010 Civil Litigation Conference,
Judicial Conference Advisory Committee on Civil Rules, Durham,
N.C., May, 2010.
37. General Conditions for Washington State Facility Construction,
www.ga.wa/gov.
38. Goldhaber, Michael D., 2011 Arbitration Scorecard, americanlawyer.com/focuseurope, Summer
2011.
39. Greg Opinski Construction, Inc. v.
City of Oakdale, ibid.
40. Harris, E.C., Global Construction
Disputes 2012: Moving in the
Right Direction, E.C. Harris, London, May 28, 2012.
41. Hoel-Steffen Constr. Co. v. United
States, 456 F. 2d 760, 763 (Ct. Cl.
1972).
42. International Arbitration: Corporate Attitudes and Practices,
Queen Mary University of London
School of International Arbitration
and PriceWaterhouseCoopers,
2008.
43. J.J. Barnes Constr. Co. v. U.S.,
ASBCA No. 27876, 85-3 B.C.A.
(CCH) 18,503 (1985) and Adams
v. United States, 358 F.2d 986 (Ct.
Cl. 1966).
44. Keating, Geoffrey T., Government
Contracts Feast or Famine, Insight from Hindsight, Issue No. 4,
Navigant Construction Forum,
December,
2012,
www.navigant.com/NCF.
45. Levering & Garrigues Co. v. U.S.,
73 Ct. Cl. 566, 578 (1932); Schmoll
v. U.S., 91 Ct. Cl. 1, 28 (1940); PCL
Constr. Servs., Inc. v. U.S., 53 Fed.
Cl. 479, 484 (2002), affd, 96 Fed.
Appx. 672 (Fed. Cir. 2004).
46. Mega Const. Co. v. U.S., 29 Fed. Cl.
396, 424 (1993).
47. Mitigation of Risk in Construction: Strategies for Reducing Risk
and Maximizing Profitability, McGraw Hill Construction, Navigant
Consulting & Pepper Hamilton,
LLP, New York, 2011.
48. Nash, Ralph C. and John Cibinic,
49.
50.
51.
52.
53.
54.
55.
56.
57.
58.
59.
37
VOTE NOW
38
40
PROFESSIONALSERVICESDIRECTORY
ipe
Consulting Services
Estimating Software
Infrastructure Cost Data
www.infrastructurecost.com
The Chief Estimator Software
INDEX TO ADVERTISERS
ARES Corporation, back cover
Booz Allen Hamilton, page 3
Deltek, page 39
D.R. McNatty and Associates, this page
Eastwood Harris, this page
EcoSys, inside front cover
George Washington University, page 12
Infinitrac, this page
ipe, this page
www.primaskills.com.au
Primavera P6 & Microsoft Project books
& training material: www.eh.com.au
COSTENGINEERINGMARCH/APRIL 2015
41
Cost Engineering
The international journal
of cost estimation,
cost/schedule control,
project management,
and total cost
management.
Subscriptions are
accepted on an annual
basis. An automatic
benet of AACE
International
membership, also
available to nonmembers.
5060-07 - US$72.00 (US)
- US$90.00 (other countries)
Please add US$8.00 for airmail
- US$61 electronic subscription
The
The AACE
AACE International
International Professional
Professional Practice
Practice Guides
Guides (PPGs)
(PPGs)
Value; Earned Value Reporting; Applications of Earned
Value Project Management; and more.
Dr. Douglas D. Gransberg, PE CCP, Tammy L. McCuen, and Keith Molenaar, Editors, 2008
Covers: Design-Bid-Build (DBB) DBB Estimating,
DBB Scheduling, DBB Project Management; Construction Management (CM) CM Estimating, CM
Scheduling, CM Project Management; Design-Build
(DB) DB Estimating, DB Scheduling, DB Project
Management; International Project Delivery; Constructability; and Partnering.
Covers: General Topics On Contingency; Cost Estimating and Contingency; Risk Analysis and Contingency; and Other Related Topics.
CALENDAROFEVENTS
MARCH 2015
JUNE 2015
Contact: www.cmaasc.org
Chinook-Calgary Section of
AACE International
The International Hotel
Calgary, Canada
Contact:
www.aaceicalgary.org
Fair Guangzhou,
China Import and Export
Fair Complex,
Guangzhou, China
APRIL 2015
Contact:
sps@china.messefrankfurt.com
Contact: johnk@trueventus.com
MAY 2015
6 Cost Estimating and Project
Control - Closing the Loop,
Cost Engineering
Hotel Ara
Zwijndrecht, the Netherlands
Contact:
www.costengineering.eu
Contact: www.cmaasc.org
44
Please submit items for future calendar listings at least 60 days in advance
of desired publication.
AACE International,
1265 Suncrest Towne Centre Dr,
Morgantown, WV 26505-1876
USA
phone: 304-296-8444
fax: 304-291-5728
e-mail: editor@aacei.org
website: www.aacei.org
Quality candidates
www.aacei.org/career
Seeing half
Trust ARES PRISM to give you the
complete picture.
Relying solely upon a CPM schedule puts your project at
risk. You need integrated cost management. PRISM G2 is
the industrys best integrated cost management software
that simplifies projects controls by delivering dependable
forecasts and accurate views of project performance so
you can make informed decisions.
www.aresprism.com/completepicture