Executive Summary
The Spotted Dog Mine is an open pit gold mine located in western United States. Operations at the mine
include drilling, blasting, loading/hauling material, Recovering gold from ore, and dumping waste.
American Mining Services (AMS) is responsible for providing reliable dump truck transportation
between the loading shovels and the various material destinations at the mine.
Operations at the Spotted Dog Mine are scheduled to advance through four phases in the coming years.
Hauling distances for the trucks will grow with each phase. AMS must determine the optimal number of
trucks required for each of the four stages in order to maximize profits by exceeding production targets
and maintaining a high level of truck utilization.
This report documents the problem solving approach that was used to arrive at a set of recommendations
for expanding trucking capacity as time goes forward. The following steps were taken to arrive at a
reliable set of solutions:
Upon running the simulation with the provided haul profiles for each stage, the optimal number of trucks
was determined to be 30 trucks in Phases 1 and 2, 31 trucks in Phase 3, and 33 trucks in Phase 4. It is
recommended that AMS provide this amount of trucks for phases of operation in order to achieve the
highest expected profit.
Table of Contents
Executive Summary.....................................................................................................................................i
List of Tables..............................................................................................................................................iii
List of Figures............................................................................................................................................iii
1.0)
Problem Statement...........................................................................................................................1
1.1)
1.2)
Problem Scope.............................................................................................................................3
2.0)
2.1)
Input Data....................................................................................................................................3
2.2)
Model Specifications...................................................................................................................4
3.0)
Experimental Design.......................................................................................................................5
4.0)
Results.............................................................................................................................................6
4.1)
Phase 1.........................................................................................................................................7
4.2)
Phase 2.........................................................................................................................................8
4.3)
Phase 3.........................................................................................................................................9
4.4)
Phase 4.......................................................................................................................................10
5.0)
Analysis.........................................................................................................................................11
5.1)
Warm-Up Period........................................................................................................................11
5.2)
Number of Replications.............................................................................................................11
6.0)
6.1)
6.2)
6.3)
Numerical Calculation...............................................................................................................13
6.4)
6.5)
7.0)
Implementation Plan......................................................................................................................15
8.0)
Bibliography..............................................................................................................................................16
Appendix A - Representative Data Distributions.......................................................................................17
Appendix B - Gradient Speed Reduction Calculation................................................................................18
Appendix C - Monthly Truck Operating Cost Estimation..........................................................................21
Appendix D Expected Profit Tables........................................................................................................22
Appendix E Utilization Tables................................................................................................................24
Appendix F Productivity Slope Calculation...........................................................................................26
List of Tables
Table 1 - Experiment Summary Table.........................................................................................................6
Table 2 - Expected Profit (Phase 1), Selection.............................................................................................7
Table 3 - Expected Profit (Phase 2), Selection.............................................................................................8
Table 4 - Expected Profit (Phase 3).............................................................................................................9
Table 5 - Expected Profit (Phase 4)...........................................................................................................10
Table 6 - Trial Run Results........................................................................................................................11
Table 7 - Implementation Plan...................................................................................................................15
Table 8 - Representative Data Distributions..............................................................................................17
Table 9 - Uphill Speed Factor....................................................................................................................18
Table 10 - Pit Ramp Downhill Speed Factor..............................................................................................20
Table 11 - Dump Ramp Downhill Speed Factor........................................................................................20
Table 12 - Expected Profit (Phase 1).........................................................................................................22
Table 13 - Expected Profit (Phase 2).........................................................................................................22
Table 14 - Expected Profit (Phase 4).........................................................................................................23
Table 15 - Expected Profit (Phase 3).........................................................................................................23
Table 16 - Asset Utilization (Phase 2)........................................................................................................24
Table 17 - Asset Utilization (Phase 1)........................................................................................................24
Table 18 - Asset Utilization (Phase 4)........................................................................................................25
Table 19 - Asset Utilization (Phase 3)........................................................................................................25
List of Figures
is paid. If too many trucks are onsite, lines will form at the various stations, resulting in a decrease of
truck utilization. AMS must provide a number of trucks that will balance both these considerations. In
addition, the nature of an open pit mine is to expand over time. The Spotted Dog Mine breaks its
expansion into four phases. The distance trucks will be required to haul material out of the mine will
increase with each phase. As such, the number of trucks provided in each phase is expected to increase as
well.
Variability is also an important part of Spotted Dog Mine operations. This includes the speeds that trucks
travel, the rate that trucks are loaded/unloaded, as well as shovel breakdown rates and repair times. In
order to incorporate this variation and determine the number of trucks required to haul material at each
stage, an Arena model was built. This model was validated and ran under a variety of experiments to
determine the optimal amount of trucks for each phase of operations.
1.1)
When solving any problem, criteria are required in order to evaluate and compare solutions. Three key
performance indicators (KPI) were identified to analyze results from the Spotted Dog Mine simulation.
All model variations will be evaluated using these KPI:
Profit:
Profit refers to AMS revenue multiplied by the provided pay factor of PF = 0.8p 75 + p100 + 1.2p130. In this
equation, p75, p100, and p130 are the ratio of production days in the month where production was <75%,
between 75 and 100%, and between 100 and 130% of production targets, respectively. Thus:
^ o ( n ) d^ o+ 0.65 P
^ w ( n) dw )
E [ R ( n ) ] =226.8 30 PF ( 0.9 P
where E [ R ( n ) ] is the expected monthly revenue a system with n trucks .
where ^
Po ( n ) ^
Pw ( n ) are the expected number of loads of production per day for n truck .
Expected profit per month is the main indicator used to evaluate the different experiments ran. This
evaluation is ultimately used to build the set of recommendations made.
Truck Utilization:
Truck utilization refers to the percentage of time a truck is actively participating by being loaded or
delivering material for the mine. Trucks are not utilized if there is consistently an empty queue of trucks
waiting to be loaded by a shovel.
Shovel Utilization:
Shovel Utilization is defined as the percentage of time a shovel is being used to load a truck. The
utilization of shovels and trucks are inherently related; as the number of trucks increases, truck utilization
decreases while shovel utilization approaches 100%. Ultimately, revenue increases with more trucks, but
the benefit of each additional truck is not as great as the previous truck.
1.2)
Problem Scope
As with any system, the mining operations at the Spotted Dog Mine have an inherent variability.
Specifically to this system, variability includes extracted material classification, overall production, truck
travel speeds and loading/unloading times. If variability is not accounted for in a model, decision makers
have a limited ability to understand and account for the systems true behaviour. This limits their ability to
make a well informed decision. Arena is designed to account for the stochastic nature of these processes,
so it was used to build a model to analyze the problem described in Section 1.0.
Several aspects of mining operations at the Spotted Dog Mine were deemed to be out of scope for this
project. The market demand for gold is not included in the model, nor is staffing requirements. In
addition, the required operations to process material before excavation and after unloading are out of
scope. As such, only the material handling aspect of the mine is modelled. Section 2.0 describes all the
assumptions made throughout the construction of the model in further detail.
2.1)
Input Data
Data regarding loaded truck speeds, empty truck speeds, shovel failure rates, shovel repair times, shovel
loading times and truck dumping times were provided to describe operating conditions at the Spotted Dog
Mine. As distributions representing data sets is more representative than exact past data, the Arena Input
Analyzer was used to determine the most accurate distributions that should be used in the model. Results
from this analysis are presented in Appendix A.
The 793F Mining Truck specifications indicate the maximum unloaded speed of the truck is 60 km/h, or
1000 m/min. Some of the data provided included values above this speed; these data points were
considered outliers and removed from the dataset. It was assumed that all of the trucks speeds were
collected while trucks were travelling on flat ground and calculated by dividing total time by total
distance travelled. The specifications also indicated that truck speeds must decrease when traversing
downhill to prevent the brakes from overheating. Using the Standard Retarding graphs in Appendix B, a
factor of 8/15 was applied to the calculated empty truck speed distribution in order to appropriately slow
the trucks down.
The truck specifications also indicated that when loaded trucks are travelling uphill, their speed should
also be reduced. Using the provided gradeability graph, a factor for speed reduction was calculated to be
2. As such, the speed of loaded trucks travelling uphill is half that of loaded trucks travelling on flat
ground.
2.2)
Model Specifications
A simulation model was needed to model the complex and dynamic behavior of the stochastic processes
at the Spotted Dog Gold Mine. The processes and their interactions were mapped, and an Arena model
was created to approximate them. The replication lengths and resource schedules are based on two nine
hour shifts per day, and a monthly payment schedule. In order to compare the benefits of purchasing
additional trucks, a VBA controller uses a MS Excel spreadsheet to drive a set of experiments and recover
continuous responses from the system based on the controls defined by the experiment. These
experiments are described in Section 3.0. Several methodologies and assumptions were used in order to
create a simplified, yet representative model. These are summarized below:
Shovel Process Model
With sufficiently high number of trucks, the shovels will be the constraint to production at the mine. The
shovelling process seizes two resources, (a truck and a shovel), delays for a random loading time, releases
the shovel, and the truck proceeds to deliver the loaded material to its destination. The shovel model
makes use of the following assumptions about the system:
results in a permanent allocation of one shovel mining gold ore, and two shovels mining waste
Shovel operators are scheduled for two 9 hour shifts a day
Each shovel has a dedicated repair crew. When two failures occur simultaneously they are still
repaired according to the same distribution
Shovels stop operations at 9 hours while the rest of the system continues to work until it is empty
Trucks haul material at the full capacity of 250 tonnes
There are no capacity constraints associated with roads, ramps, or intersections in the model
Trucks do not experience failures
Route times are calculated by dividing effective distance by a stochastic velocity; effective
distances are defined in Appendix B
One distribution is fit to a set of data and used to model dumping at all destinations
There are no capacity restrictions on leach & waste dumps
Ore production targets consist of the amount of both leach and ore material hauled each month
The pay factor is calculated according to the total amount of ore material and waste material
Experiment
Range of Trucks
Experiment
Number of
parameters
replications (days)/
Filename
truck quantity
Phase 1 Truck
{1,5,10,15,20,23,25,27,29,30
Phase 1 Route
Optimization
Phase 2 Truck
31,32,33,34,35,36,37,38,39,40}
Times
Phase 2 Route
Optimization
Phase 3 Truck
31,32,33,34,35,36,37,38,39,40}
Optimization
Phase 4 Truck
31,32,33,34,35,36,37,38,39,40}
Optimization
31,32,33,34,35,36,37,38,39,40}
{1,5,10,15,20,23,25,27,29,30
{1,5,10,15,20,23,25,27,29,30
{1,5,10,15,20,23,25,27,29,30
Times
Phase 3 Route
Times
Phase 3 Route
Times
1800
Scenarios\ScenariosP1004.xlsx
1800
Scenarios\ScenariosP2004.xlsx
1800
Scenarios\ScenariosP3004.xlsx
1800
Scenarios\ScenariosP4008.xlsx
4.0) Results
The Spotted Dog Mine simulation was run using the current and future average haul profiles in order to
determine the optimal number of trucks in each phase. These results are presented in the following
subsections, each with an Expected Monthly Profit table, graph and an Asset Utilization graph. The
figures of Expected Monthly Profit and Asset Utilization show the relationship between the number of
trucks provided by AMS, and the service level that would be achieved, as the higher the service level, the
more AMS will be paid.
The Expected Monthly Profit graph displays the relationship between the number of trucks and the profit
AMS should expect to receive. The method used to calculate costs in these graphs is reviewed in
Appendix C. The Expected Monthly Profit table shows a selection of the number of truck values as well
as correlating expected profit. The highest expected profit value for each phase is highlighted in dark
green, while the second highest value is highlighted in light green. The complete tables are displayed in
Appendix D. The Asset Utilization graph shows the trade-off between truck utilization and shovel
utilization. The number of trucks and the truck utilization level at the shovel and truck utilization
intersection is highlighted. The tables used to create these graphs can be found in Appendix E. In each
phase, the highest expected profit was achieved when shovel utilization reached its maximum and truck
utilization was at approximately 80%.
4.1)
Phase 1
The following graphs and table show the results of the simulation for Phase 1 of the mine.
$50,000,000
$40,000,000
Monthly Values
Profit
Revenue
Costs
$30,000,000
$20,000,000
$10,000,000
$0
0
10
15
20
25
Number of Trucks
Figure 2 - Expected Monthly Profit (Phase 1)
Table 2 - Expected Profit (Phase 1), Selection
# Trucks
25
27
29
30
31
32
E[Profit]
$43,884,200.59
$48,188,519.40
$48,595,555.38
$48,824,497.98
$47,926,955.35
$47,833,640.87
30
35
40
45
Shovel Utilization
Truck Utilization
0.60
0.40
0.20
0.00
0
10
15
20
25
30
35
40
45
Number of Trucks
4.2)
Phase 2
$52,700,645.84
$50,000,000
Profit
Revenue
Costs
$40,000,000
Monthly Values
$30,000,000
$20,000,000
$10,000,000
$0
0
10
15
20
25
30
35
40
Number of Trucks
The following graphs and table show the results of the simulation for Phase 2 of the mine.
# Trucks
25
27
29
30
31
32
E[Profit]
$45,563,883.49
$47,866,630.94
$52,664,305.29
$52,700,645.84
$52,363,084.08
$52,231,892.43
Shovel Utilization
Truck Utilization
0.60
0.20
0.00
0
10
15
20
25
30
35
40
45
Number of Trucks
4.3)
Phase 3
The following graphs and table show the results of the simulation for Phase 3 of the mine.
$56,434,501.75
Profit
Revenue
Costs
$40,000,000
Monthly Values
$30,000,000
$20,000,000
$10,000,000
$0
0
10
15
20
25
30
35
40
45
Number of Trucks
# Trucks
E[Profit]
29 $52,762,373.86
30 $55,506,655.85
31 $56,434,501.75
32 $56,422,539.31
33 $56,395,519.02
34 $56,276,585.62
0.6000
Shovel Utilization
Truck Utilization
0.4000
0.2000
0.0000
0
10
15
20
25
Number of Trucks
30
35
40
45
4.4)
Phase 4
The following graphs and table show the results of the simulation for Phase 3 of the mine.
$60,450,155.45
Profit
Revenue
Costs
$40,000,000
$20,000,000
$0
0
10
15
20
25
Number of Trucks
# Trucks
31
32
33
34
35
36
E[Profit]
$57,675,666.5
4
$59,807,701.7
6
$60,450,155.4
5
$60,225,660.7
9
$60,028,961.5
2
$59,616,718.4
5
30
35
40
45
Shovel Utilization
Truck Utilization
0.6
0.4
0.2
0
0
10
15
20
25
30
35
40
45
Number of Trucks
5.0) Analysis
The conclusions from the results presented in Section 3.0 are dependent on AMSs policy on truck
utilization. If an increased profit with lower truck utilization is acceptable, AMS should employ 30 trucks
in Phases 1 and 2, 31 trucks in Phase 3 and 33 trucks in Phase 4. However, if AMS desires a certain
threshold for truck utilization to be met, Appendix E should be consulted. For instance, if AMS wishes
their trucks to maintain 80% utilization, then a policy of 29 trucks in Phase 1, 30 trucks in Phase 2, 32
trucks in Phase 3 and 33 trucks in Phase 4 would be desirable. Alternately, if they wish to meet certain
shovel utilization standards (and keep a constant flow of production), Appendix E should again be
consulted.
5.1)
Warm-Up Period
The Spotted Dog Mine operates two 10 hour shifts each day. As these are discrete time blocks, a warm-up
period is not required for the simulation. The mine only has 18 hours of effective operations, so it is
assumed that any waste and ore in a truck will leave the system, and the trucks will immediately be
available to the shovels once operations start anew.
5.2)
Number of Replications
The number of replications is important to determine for statistical accuracy in the model. The larger the
number of replications, the smaller the confidence interval, and the more accurate the model is. However,
the more replications required, the longer the model takes to run.
To determine the appropriate number of replications, a trial run of 30 months was conducted for 30 trucks
during Phase 4. The pay for each month was calculated, and the 95% confidence interval was calculated.
It was decided that this confidence interval should be no larger than 1% then the average value of monthly
pay. This value was chosen because the optimal number of trucks can be changed with slight variations in
the model. The results from this trial run are displayed in Table 6.
Table 6 - Trial Run Results
Variable
Alpha
Average
Standard Deviation
95% Confidence Interval
Confidence Interval/Average
Value
1.96
$ 32,655,016.72
$ 288,595.89
$ 103,272.71
0.32%
The calculated confidence interval from the trial run was 0.32% of the average monthly pay, therefore
thirty replications for each phase was deemed adequate
800
600Approximation
Shovel/ Constraint
Avg. Loads Delivered
Day
400
200
Shovel Constraint Approximation w/ Failures
0
0
5
10
15
20
25
30
35
40
Number of Trucks
A mining operation has some characteristics that allow for accurate analytic models in certain
circumstances. The validation phase of model creation compared a variety of analytic and simplified
numerical models to the output of the simulation model. This comparison is summarized by Figure 10
Figure 10 - Model Comparison
below:
Each of these models was created based on the system structure, and validated to the output
characteristics presented in Appendix A. The reasoning and calculations supporting the key
approximations are described below.
45
6.1)
When the number of trucks is increased beyond the optimum level, the shoveling process becomes a
bottleneck in the material handling process. In this situation, a large queue of empty trucks forms at the
shovel stations and the productivity of the mine (as a function of number of trucks) approaches a constant
value. This value can be given by the following equation:
Ps ( n )
1080 3
t load
The loading times are represented by a shifted lognormal distribution. The average loading time is:
Ps ( n ) 920.45
6.2)
( loads
day )
When shovel failures are added to the model, the new steady state productivity can be given by
multiplying the equation in Section 5.1 by the steady state availability of the shovel:
P' s ( n )
MTBF
1080 3
Where shovel failure times follow the Weibull distribution, and repair times follow a lognormal
distribution, this equation becomes:
1
(
k)
1080 3
P ( n)
t
1
(1+ )+1.4
k
1+
'
P' s ( n ) 879.422
load
6.3)
( loads
day )
Numerical Calculation
Using a simple set of processes to model shovels in Arena, steady state productivity was estimated (see
file ShovelValidation.doe for further information):
()880.33
6.4)
When the number of trucks is reduced below the optimum level, the trucking process becomes a
bottleneck in the material handling process. In this situation, the shovels must wait for trucks to arrive,
and the average loads/day can be approximated by the linear function:
Pt ( n )i
1080 v^
ni
d^ i+ v^ (t load +t dump )
( loads
day )
( minm )
6.5)
Due to the capacity constraints in the crushing or dumping processes, the shovels will never have to wait
for trucks. As such, the utilization level of the shovels provided by the trucking system can be estimated
analytically using a birth-death process to model the queue of empty trucks waiting to be filled at the
shovels. An example is shown in Figure 11 below.
In this model, the arrival rate is defined as the rate that empty trucks are added to the queue. The service
rate is defined as the rate that the shovels can fill trucks and cause them to exit this simplified system.
This model is analogous to an M/M/s queuing system with finite calling population.
To apply this model to the Spotted Dog gold mine, the arrival and service rates were estimated from the
model parameters for Phase 4 of operations. The arrival rate was found by calculating the average amount
of time a truck spends delivering a load. The total arrival rate to the queue is the number of trucks in the
system that are currently delivering loads, divided by the average time to deliver a load, as shown in the
following equation:
1080 ^v
1080 472.82
=
=36.711
13482.23+ 472.82 0.90423
d^ + ^v t dump
)(
1080 1080
=
=306.818
t load
3.52
Phase Number
Number of Trucks
Phase 1
Phase 2
Phase 3
Phase 4
30
30
31
33
reliability of this result. These results taken from the current perspective will result in a plan to purchase
one truck for phase 3, and then two more additional trucks for the final phase of mine operations.
Bibliography
Catepillar Inc. (2010). 793F Mining Truck Operating Specifications. AEHQ6038-03 (03-2010).
Hillier, F. S., & Lieberman, G. J. (2010). Introduction to Operations Research, 9th Edition.
Rossetti, M. D. (January 2009). Simulation Modeling and Arena.
Walpole, R. E., Myers, R. H., Myers, S. L., & Ye, K. (2007). Probability & Statistics for Engineers &
Scientists, 8th Edition.
Data Set
Loaded Truck
Distribution
Beta
Arena Code
311 + (211*BETA(2.99,3.9))
Speed
Mean
Comments
311+211
( + )
402.566
Empty Truck
Erlang
308+k
Speed
543.074
Shovel Time
Weibull
WEIB(30.7,1.06)
1
1+
k
( )
Between
Failure
30.0054
Shovel Time
Lognormal
LOGN(1.4,1.79)
to Repair
Shovel
Lognormal
2+ LOGN(1.52, 0.716)
1.4
2+1.52
Loading Time
3.52
Truck
Gamma
GAMM(0.459,1.97)
Dumping
Time
0.904
Figure 12 - Gradeability/Speed/Rimpull
Figure 12 was used to calculate the proper gear (and, subsequently, the maximum speed) of the 793F
Mining Truck while travelling uphill. Table 9 displays the factor used to decrease the truck speed while
travelling uphill.
Table 9 - Uphill Speed Factor
Phase 1
Phase 2
Phase 3
Phase 4
Gea
r
4th
4th
4th
4th
60
60
60
60
Factor
1/2
1/2
1/2
1/2
If the effective grade is anywhere between 10% and 15%, the truck must be in 4 th gear.
Figure 13 was used to calculate the proper gear (and, subsequently, the maximum speed) of the 793F
Mining Truck while travelling downhill, for roads that are longer than 1500 metres.
Figure 14 was used to calculate the proper gear (and, subsequently, the maximum speed) of the 793F
truck while travelling downhill, for roads that are roughly 1500 metres. Tables 10 and 11 show the factor
used to decrease the truck speed while travelling downhill.
Table 10 - Pit Ramp Downhill Speed Factor
Phase 1 (1500 m)
Phase 2 (Continuous)
Phase 3 (Continuous)
Phase 4 (Continuous)
Phase 1 (1500 m)
Phase 2 (1500 m)
Phase 3 (1500 m)
Phase 4 (1500 m)
If the effective grade is anywhere between 10% and 15%, the truck must be in 4 th gear.
( PA , MARR , N ) C + C ( AF , MARR , N ) C
Ctotal =
var
salvage
Dollars
Month
1(1+i)n
A
where
,i , n =P
P
i
# Trucks
1
5
10
15
20
23
25
27
29
30
31
32
33
34
35
36
37
38
39
E[Profit]
# Trucks
$1,553,642.61
$7,723,433.41 1
$15,319,636.12 5
$22,595,391.83 10
$37,313,804.07 15
$41,716,646.82 20
$43,884,200.59 23
$48,188,519.40 25
$48,595,555.38 27
$48,824,497.98 29
$47,926,955.35 30
$47,833,640.87 31
$47,743,951.15 32
$47,467,660.40 33
$47,146,301.85 34
$46,993,081.76 35
$46,889,898.79 36
$46,673,331.14 37
38
$46,393,974.62
39
E[Profit]
$1,570,720.59
$7,835,940.23
$15,541,409.76
$22,945,474.01
$37,041,522.96
$42,951,935.56
$45,563,883.49
$47,866,630.94
$52,664,305.29
$52,700,645.84
$52,363,084.08
$52,231,892.43
$51,650,254.05
$51,674,900.23
$51,400,145.60
$51,507,074.61
$50,947,364.44
$50,691,272.29
$50,443,769.11
# Trucks
1
5
10
15
20
23
25
27
29
30
31
32
33
34
35
36
37
38
39
40
E[Profit]
$1,592,735.82
$7,928,563.88
$15,748,115.31
$23,310,727.64
$30,425,661.02
$44,081,801.28
$46,917,027.16
$49,500,386.77
$52,762,373.86
$55,506,655.85
$56,434,501.75
$56,422,539.31
$56,395,519.02
$56,276,585.62
$55,749,645.45
$55,609,048.07
$55,476,091.01
$54,727,985.95
$54,913,216.20
$54,470,698.24
# Trucks
1
5
10
15
20
23
25
27
29
30
31
32
33
34
35
36
37
38
39
40
E[Profit]
$1,608,044.23
$8,018,633.19
$15,946,018.73
$23,644,373.72
$30,896,561.24
$44,099,016.40
$47,871,327.21
$50,925,169.68
$53,229,384.20
$54,493,700.57
$57,675,666.54
$59,807,701.76
$60,450,155.45
$60,225,660.79
$60,028,961.52
$59,616,718.45
$59,707,959.29
$59,101,739.63
$59,104,619.37
$58,564,448.33
# Trucks
1
5
10
15
20
23
25
27
29
30
31
32
33
34
35
36
37
38
39
40
Shovel
Utilization
0.04
0.22
0.43
0.63
0.82
0.91
0.96
0.99
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
Truck
Utilizatio
n
0.98
0.97
0.96
0.95
0.92
0.89
0.87
0.83
0.77
0.75
0.72
0.70
0.68
0.66
0.64
0.62
0.61
0.59
0.58
0.56
# Trucks
1
5
10
15
20
23
25
27
29
30
31
32
33
34
35
36
37
38
39
40
Shovel
Utilizatio
n
0.04
0.20
0.40
0.60
0.78
0.87
0.93
0.97
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
Truck
Utilizatio
n
0.97
0.97
0.97
0.95
0.93
0.91
0.89
0.86
0.82
0.80
0.77
0.75
0.72
0.70
0.68
0.67
0.65
0.63
0.61
0.60
# Trucks
1
5
10
15
20
23
25
27
29
30
31
32
33
34
35
36
37
38
39
40
Shovel
Utilizatio
n
0.04
0.19
0.38
0.57
0.74
0.83
0.89
0.94
0.98
0.99
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
Truck
Utilization
0.98
0.97
0.97
0.96
0.94
0.92
0.90
0.89
0.86
0.84
0.82
0.79
0.77
0.75
0.72
0.71
0.69
0.67
0.65
0.63
# Trucks
1
5
10
15
20
23
25
27
29
30
31
32
33
34
35
36
37
38
39
40
Shovel
Utilizatio
n
0.04
0.18
0.36
0.54
0.70
0.80
0.85
0.91
0.95
0.97
0.99
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
Truck
Utilization
0.98
0.98
0.97
0.96
0.94
0.93
0.91
0.90
0.88
0.87
0.85
0.84
0.81
0.79
0.77
0.74
0.73
0.71
0.69
0.67
( 12 ) E [ v
v^ =
loaded
]+
( 12 ) E [ v
empty
v loaded is given by a shifted beta distribution, and v empty is given by a shifted gamma distribution:
( 12 )( A+ + )+( 12 ) ( B+ k)
v^ =
(( )(( ) (
1
d^ i=
3
211 2.99
( 12 )(311 + 2.99+3.9
)+( 12 ) ( 308+57.94.06)=472.82
()
(( )(( )
()
(( )(( )
()
(( )(( )
()
(( )(( )
()
1
d^ 1=
3
1
d^ 2=
3
1
d^ 3=
3
1
d^ 4 =
3
)()
2
3
2
d crush +d crush ) +
d leach +d crush ) +
(
( d +d )
5
5
3 dump crush
)( )
2
3
2
( 4749+ 4553.38 ) +
( 4483+ 4287.38 ) +
( 6125+5828.63 ) =10963.48
5
5
3
)()
)( )
2
3
2
( 5049+4834.625 ) +
( 4783+ 4568.625 ) +
(6625+ 6297.375 ) =11803.058
5
5
3
2
3
2
( 5349+5115.875 ) +
(5083+ 4849.875 ) +
( 7125+6766.125 ) =12642.642
5
5
3
)()
2
3
2
(5649+5397.13 )+
( 5383+5131.13 ) +
(7625+ 7234.88 ) =13482.23 The
5
5
3
loading times are represented by a shifted lognormal distribution. The average loading time is:
t load =E [ 2+ LOGN ( 1.52,0 .716 ) ]=2+1.52=3.52 The dumping times at each of the truck
destinations are represented by a gamma distribution: