Professional Documents
Culture Documents
Procedure for
MAINLINE WELDING
Project: Kalol Mehsana Gas Pipeline Project
(Job No: GSPL/113)
0
Rev.
No
22.02.06
Dt. of Rev
Description
Docum
Contr
Prepared
By (HCCNOVA
-JV)
Checked By
(Manager QA
HCC-NOVA
JV)
Reviewed
by (ABS)
Approved By
(Dorsch Consult (I)
Pvt. Ltd / GSPL)
Project:
Owner:
Consultant:
TPIA:
Contractor:
HCC-NOVA JV.
Approved and
Issued for
Construction
by
GSPL
(KMPL Project)
Page 1 of 9
Releas
Constru
(HCC-NO
S.NO
DESCRIPTION
PAGE NO
Scope
Reference
Method
3, 4 & 5
4
5
6
6
Page 2 of 9
SCOPE
This Procedure covers the work method for Mainline Welding of
pipeline works.
2.
REFERENCE
1. GSPL Specification 1013 113 103
2. API 1104
3. ASME B 31.8
4. ASME Sec II C and
5. Approved WPS.
3.
METHOD
1.
Before the fit up, pipe shall be checked for correct thickness, free from
pitting and dent, etc. Bevel ends shall be visually checked and repairing
is as mentioned below.
a.
b.
c.
d.
2.
Before fit-up pipe ends inside / outside shall be cleaned by power wire
brush at least for one inch so that the welds are free from rust, paint and
other foreign matters. Manual cutting and repairing of pipes and bevels
by welding is not allowed.
3.
Page 3 of 9
During alignment and fit up, first pipe will be rested and locked on the
pre - positioned skids and the second pipe will be held by hydra crane
with internal fit-up clamp (Mechanical), the second
pipe will be
carefully lowered on pre positioned skids. Skidding arrangement shall
be as shown below and skids may be removed only after completion
of the entire welding and the pipe shall be rested on the sand bags. The
height of the Support must be such that each weld is at 50 cm above the
ground during welding and after weld, height of support shall be 30 cm.
4.
WELD JOINT
12000mm Typ
Skid
Skid
30 Cm
Ground
5.
Maximum offset of the same nominal wall thickness pipe shall not be
more than 1.6 mm.
6.
7.
8.
9.
After alignment & fit up, pre heating shall be carried out(minimum
100 degree C) and the same shall be checked with thermo chalks /
temperature indicating pyrometer before starting the root run.
10.
Earthing clamps used for welding return circuit shall only be placed on
bevel area or circumferential welds.
11.
Internal line up clamps shall not be released before the root and hot
pass runs are completed. Weld joints shall be protected from rains /
sand storms. Wind shield shall be used in the aforesaid conditions.
Page 4 of 9
13.
Before any pipe length is cut the painted serial No. & Heat No shall be
transferred to the either side of the joint which is to be made by cutting &
record shall be prepared as per approved format. The length of the pup
to be welded shall be at least 1 m. On either side of each circular joint,
only one round joint shall be permitted within a distance of 8m. Where
different wall thickness pipes are to be welded and the difference in wall
thickness 1:4 taper internal grinding on the higher thickness shall be
done.
14.
15.
Welder No. 1 shall start from 12 O Clock position and proceed towards
6 O Clock. Welder No.2 shall start from 9 O Clock position and
proceed towards 6 O clock and then from 12 O Clock to 9 O Clock.
Proper Overlap shall be ensured.
16.
17.
18.
Arc Strike outside the beveled area on the pipe surfaces is not
permitted.
Acceptance criteria for arc strike / arc burn:
=< 0.5 mm acceptable if ground out,
>0.5mm un-acceptable and cut out.
19.
20.
Page 5 of 9
Welders shall be qualified as per the approved WPS and all the welders
should have identity cards duly signed by GSPL/Dorsch and TPIA.
22.
After completion of welding visual inspection shall be done and all the
surface defects shall be removed as per the specification. NDT shall be
carried out as per the approved NDT procedures. Repairs shall be done
as per approved WPS and if required it shall be tested for NDT.
23.
24.
At the end of the days work or every time when joining and welding
operations are interrupted, the open ends are to be closed with
nightcaps.
4.0
5.0
DOCUMENTATION
Inspection and Test Plan
Inspection Report
:
:
HCC NOVA T 46 17 09
HCC NOVA F 46 17 09 01
Note:
In case of any conflict between the requirements of this procedure of this
procedure and that of GSPL standard specification, then the requirement of
GSPL specification intention is meant.
Page 6 of 9
Consultant
Revision : 0
TPIA
Date :
Contractor
Format No:
Project
Sr.
No
Activity Description
Controlling
Specification
Acceptance
Criteria
Verifying
Document
Frequency
of Insp./
Testing
Inspection Category
Remarks
HCC
NOVA
JV
TPIA
Dorsch/
GSPL
Approved Procedure
HCC NOVA
P 46 17 09
Approved WPS P 46
17 21 and API 1104
HCC NOVA
P 46 17 09 01
Every Weld
W/R
RM
Approved Procedure
HCC NOVA
P 46 17 09
Approved Procedure
HCC NOVA
P 46 17 09 and API
1104
HCC NOVA
P 46 17 09 01
Every Weld
RM
Approved Procedure
HCC NOVA
P 46 17 38
P 46 17 43
P 46 17 29
Approved Procedure
HCC NOVA
P 46 17 38
P 46 17 43
P 46 17 29 and API
1104
Every Pipe
Weld
W/R
RM
Approved Procedure
HCC NOVA
P 46 17 09
Contract Specification
1013-113-103 and API
1104
Laboratory Test
Reports
1 in 1000
Weld
W/RM
Legend
W
: Witness
RM : Random Inspection
R
: Review Documents
Name:
Name:
Name:
Sign:
Sign:
Sign:
Date:
Date:
Date:
Page 7 of 9
INSPECTION REPORT
MAINLINE WELDING
Owner
Revision
TPIA
Report No:
:0
Date
Project
Pipe Size :
Spread :
From CH:
To CH:
Thickness:
WPS No: 01
Weather :
Pipe No
Heat NO
Length(in
metres)
Coating No
Todays progress
Root/Hot
F&C
Joint number
Previous Progress
Visual
inspection
Remarks
Cumulative Progress
No. of Joints
Length in Mtr.
Name:
Name:
Name:
Sign:
Sign:
Sign:
Date:
Date:
Date:
Page 8 of 9
INSPECTION REPORT
MAINLINE / TIE-IN WELDING
Owner
Revision
TPIA
Report No:
:0
Date
Project
Pipe Size :
Spur Line :
From CH:
To CH:
Pipe No
Heat NO
Thickness:
WPS No:
A.S.L. No
Todays progress
Length(in
metres)
Weather :
Rev_______________
Joint No
Welder No.
Previous Progress
Visual
inspection
Remarks
Cumulative Progress
No. of Joints
Length in Mtr.
Name:
Name:
Name:
Sign:
Sign:
Sign:
Date:
Date:
Date:
Page 9 of 9