Professional Documents
Culture Documents
CONTINGENCY
Dalia Mohamed1, Florida Srour1, Wael Tabra1, and Tarek Zayed2
1
736
Copyright ASCE 2009
Downloaded 13 Sep 2011 to 132.205.59.19. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelib
737
consequently have a negative impact on the quality and budget of the project.
Therefore, estimating time contingency is seen as a major factor for achieving a
successful construction project. Although several industrial sectors developed and
used software for estimating time and cost contingencies in order to minimize delays
and over budget, yet limited efforts are reported in the literature in the area of
predicting time contingency in the construction sector. Therefore, the objective of the
presented research in this paper is to identify the factors that affect schedule (time)
contingency and develop a model that predicts the expected contingency of a
construction project.
LITERATURE REVIEW
There is no standard definition of contingency in which it could mean different
meanings to different estimators, contractors, and owners organizations (Moselhi,
1997). Contingency is probably the most misunderstood, misinterpreted, and
misapplied word in project execution (Patrascu, 1988). It is an amount of money or
time (or other resources) added to the base estimated amount to achieve a specific
confidence level or allow for changes where experience shows obligation (AACE,
2000). It can also be defined as the budget that is set aside to cope with uncertainties
during construction (Touran, 2003) or the amount of money or time needed above the
estimate to reduce the risk of overruns of project objectives to an acceptable level to
the organization (PMI, 2000). Treasury (1993) identified two major categories of
contingency for construction projects:
(i) Design Contingency it addresses the changes during the design process for
factors, such as incomplete scope definition and inaccuracy of estimating methods
and data (Clark & Lorenzoni, 1996).
(ii) Construction Contingency it addresses the changes during the construction
process. Under a traditional procurement arrangement, the contract typically
contains a variation clause(s) to allow for changes and provide a mechanism for
determining and valuing variations (Staugas, 1995).
There are many definitions for contingency in the literature; most of them focused on
cost contingency. Contingency has different meanings to different people. Despite its
importance, estimating time contingency was not thoroughly addressed in the
literature. Prior to reviewing the estimating methods for project contingency, there are
different attributes that affect contingency. Yer and Jha (2006) identified 55 factors
affecting the performance of the project schedule. They observed seven factors that
have the most significant impact on the schedule outcome and divide them into two
main categories. The first include factors that posses the capability to improve
performance level, such as owners competence as well as commitment and conflict
among project members. The second include factors that tend to retain the schedule at
its existing level, such as coordination among project members, lack of knowledge
and skills for the project managers, hostile socioeconomic environment, and
uncertainty of project members. In addition, Touran (2003) indicated that the effect of
change orders increased the original cost and schedule since they modified the
original contract.
There are many factors that impact time contingency. Sukumaran et al. (2006) stated
that it was not only important to identify the factors but evaluate their impact on the
project duration as well. They developed a model in highway work zones that
Downloaded 13 Sep 2011 to 132.205.59.19. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelib
738
Downloaded 13 Sep 2011 to 132.205.59.19. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelib
739
Downloaded 13 Sep 2011 to 132.205.59.19. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelib
740
Environmental Conditions
Management Conditions
Project Conditions
Criteria
Downloaded 13 Sep 2011 to 132.205.59.19. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelib
741
a1
1
a21
a31
a41
a2
a12
1
a32
a42
a11, i =1, j = 1
a3
a13
a23
1
a43
a4
a14
a24
a34
1
1. The diagonal elements are all equal to one because they represent the comparison
of a criterion against itself.
2. The lower triangle values are the reciprocal of the upper triangular values (i.e. aij
= 1/aji).
3. All numbers in the matrix are positive.
4. Square matrix (i.e. number of rows equal to number of columns)
The weight of each factor is determined using Equation (1) as follows:
j= n
ai
(1)
W x = nn j
j=1
ai
i =1
Where, aij represents the matrix elements for i row and j column; n represents the
pair-wise comparison matrix dimension; and Wx represents the weight of factor x.
After determining the weights of each factor in the hierarchy, the time contingency
(CD) is developed using the model shown in Equation (2):
n
CD = Wi * Si * Pi
(2)
i =1
Where, Wi represents the general weight of factor i; Si represents the score of each
factor in a specific project; Pi represents the probability of occurrence of factor I; and
CD is the time contingency.
TIME CONTINGENCY MODEL IMPLEMENTATION
The following are the steps that were used to develop time contingency model using
the collected data.
1- Determine the relative weight of each major category; i.e. project conditions,
management conditions and environmental conditions.
2- Determine the weights (Wi) of the sub factors relative to the weight of its
category.
3- Calculate the factors score (Si) for each of the thirteen factors (using a 1 - 9
scale) in which one represents the most ineffective and nine represents the
most effective to the contingency value.
4- Calculate the Probability of occurrence average (Pi) for each of the thirteen
factors.
5- Multiply the three values Wi * Si * Pi.
6- Sum all the values of multiplication, which constitute the time contingency
value CD.
Downloaded 13 Sep 2011 to 132.205.59.19. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelib
742
After implementing the abovementioned steps to the collected data, Table 3 shows
the weights and relative weights of categories and factors, respectively. In addition, it
shows the time contingency calculation based upon average values of scores and
probabilities. It also shows that time contingency represents 36.78% of project
duration. Therefore, the time estimator has to consider almost 36% increase in project
duration due to the effect of the contingency factors. This value accounts for the
occurrence of all factors; however, the case might be different if only few of them are
expected to occur. In this case, the contingency value might be lower.
Sensitivity Analysis
Sensitivity analysis was performed to determine the most sensitive factors that affect
time contingency rate using @Risk software. The sensitivity analysis was done based
on the change in percentile of distributions 1%, 5%, 25%, 50%, 75%, 95% and 99%.
After the analysis was done, the factors were put in order of their effect on time
contingency as shown in Figure 2. It is clear from the chart that materials availability
factor is the most sensitive factor, followed by project size and 3 resource availability.
Therefore, the developed model proved to be sensitive to all considered factors.
Enviro
nmenta
Management Conditions
Project Conditions
Criteri Weight
a
s
Time
Probabili
Contingenc
ty (Pi)
y (CD)
0.533
0.0258
0.542
0.0237
0.550
0.0367
0.583
0.0383
0.567
0.0297
0.675
0.0260
0.600
0.0217
0.458
0.0224
0.400
0.0109
0.617
0.0272
0.592
0.0247
Downloaded 13 Sep 2011 to 132.205.59.19. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelib
743
Weather conditions
Strike
Site shortage of
resources
0.533
0.0321
0.267
0.0161
0.600
0.0325
CD =
Wi * Si * Pi
0.3678
i =1
Downloaded 13 Sep 2011 to 132.205.59.19. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelib
744
(3)
(4)
i=1
Downloaded 13 Sep 2011 to 132.205.59.19. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelib
745
COBRA (2006). The construction and Building Research, Conference of the Royal
Institution of Chartered Surveyors, University College London, September 7-8.
Clark, F. and Lorenzoni, A. (1996). Applied Cost Engineering, M. Dekker, CRC;
3rd edition, New York, USA.
Dikmen, I., Birgonul, M., and Kiziltas, S. (2005). Prediction of Organizational
Effectiveness in Construction Companies, J. of Construction Engineering and
Management, ASCE, February, 131(2), pp. 252-261.
Illsley, R. (2006). Business Intelligence Pretmaster, Risk Expert, v7.8, Butler
Group Subscription Services, New Jersey, USA.
Interface Consulting International Inc. (2007). Interpreting Force Majeure in the
Wake of Disaster, <www.interface-consulting.com> (Surfed in November 2007)
Iyer, K., and Jha, K. (2006). Critical Factors Affecting Schedule Performance:
Evidence from Indian Construction Projects, J. of Construction Engineering and
Management, ASCE, August, 132(8), pp. 871-881.
Kanoglu, A. (2003). An Integrated System for Duration Estimation in Design/Build
Projects and Organizations, J. of Engineering, Construction and Architecture
Management, Emerald Group Publishing Limited, 10(4), pp. 272-282.
Moselhi, O. (1993). Applied Earned Value for Project Control, CIB W-65
conference Proceedings, Trinidad, WI, USA.
Moselhi, O. (1997). Risk Assessment and Contingency Estimating", Transactions of
the American Association of Cost Engineers, 41, A.06.1.
Park, M., and Pea-Mora, F. (2004). Reliability Buffering for Construction
Projects, J. of Construction Engineering and Management, ASCE,
September/October, 130(5), pp. 626637.
Patrascu, A. (1988). Construction Cost Engineering Handbook, M. Dekker, New
York, USA.
Saaty, T. (1982). Decision Making for Leaders: The Analytic Hierarchy Process for
Decision in a Complex World. Lifetime Learning Publications, Belmont,
California, USA.
Saaty, T. (1991). Decision Making with Dependence and Feedback: The Analytic
Network Process. RWS Publications, Pittsburgh, PA, USA.
Staugus, J, (1995). Variations, Building and Construction Law, 11(3), 156-158.
Sukumaran, P., Bayraktar, M.E., Hong, TH., and Hastak, M. (2006). Model for
Analysis of Factors Affecting Construction Schedule in Highway Work Zones, J.
of Transportation Engineering, ASCE, June, 132(6), pp. 508-517.
PMI (2000). A Guide to the Project Management of Knowledge (PMBOK Guide),
Project Management Institute, PA, USA.
Treasury, H. (1993). CUP Guidance: No.41Managing Risk and Contingency for
Works Projects, Central Unit on Procurement, London, UK.
Zayed, T. and Halpin, D. (2005). Pile Construction Productivity Assessment, J. of
Construction Engineering and Management, ASCE, June, 131(6), pp. 705714.
Downloaded 13 Sep 2011 to 132.205.59.19. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelib